The East Anglia ONE North Offshore Wind Farm Order 2022
- (1) The undertaker may, in connection with the carrying out of the authorised project—
- (a) enter on and take temporary possession of—
- (i) the land specified in column (2) of Schedule 9 (land of which temporary possession may be taken) for the purpose specified in relation to that land in column (3) of that Schedule; and
- (ii) any other Order land in respect of which no notice of entry has been served under section 11 (powers of entry) of the 1965 Act (other than in connection with the acquisition of rights only) and no declaration has been made under section 4 (execution of declaration) of the 1981 Act;
- (b) remove any buildings, agricultural plant and apparatus, drainage, fences, debris and vegetation from that land;
- (c) construct temporary works (including the provision of means of access), haul roads, security fencing, bridges, structures and buildings on that land;
- (d) use the land for the purposes of a working site with access to the working site in connection with the authorised project; and
- (e) construct any works, or use the land, as specified in relation to that land in column 3 of Schedule 9 (land of which temporary possession may be taken), or any mitigation works or operations.
- (2) Not less than 28 days before entering on and taking temporary possession of or using land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.
- (3) The undertaker must not remain in possession of any land under this article for longer than reasonably necessary and in any event must not, without the agreement of the owners of the land, remain in possession of any land under this article—
- (a) in the case of land specified in paragraph 1(a)(i) after the end of the period of one year beginning with the date of completion of the part of the authorised project specified in relation to that land in column (4) of Schedule 9 (land of which temporary possession may be taken); or
- (b) in the case of land specified in paragraph 1(a)(ii) after the end of the period of one year beginning with the date of completion of the part of the authorised project for which temporary possession of the land was taken,
unless the undertaker has, before the end of that period, served a notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act in relation to that land.
- (4) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker is not required to—
- (a) replace a building removed under this article; or
- (b) restore land on which any works have been constructed under paragraph (1)(e).
- (5) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of any power conferred by this article.
- (6) Any dispute as to a person’s entitlement to compensation under paragraph (5), or as to the amount of the compensation, must be determined under Part 1 (determination of disputed compensation) of the 1961 Act.
- (7) Nothing in this article affects any liability to pay compensation under section 152 of the 2008 Act (compensation in case where no right to claim in nuisance) or under any other enactment in respect of loss or damage arising from the carrying out of the authorised project, other than loss or damage for which compensation is payable under paragraph (5).
- (8) The undertaker may not compulsorily acquire under this Order the land referred to in paragraph (1)(a)(i) except that the undertaker is not precluded from—
- (a) acquiring new rights or imposing restrictive covenants over any part of that land under article 20 (compulsory acquisition of rights) to the extent that such land is listed in column (1) of Schedule 7 (land in which only new rights etc. may be acquired); or
- (b) acquiring any part of the subsoil (or rights in the subsoil) of that land under article 24 (acquisition of subsoil or airspace only).
- (9) Where the undertaker takes possession of or uses land under this article, the undertaker is not required to acquire the land or any interest in it.
- (10) Section 13 of the 1965 Act (refusal to give possession to acquiring authority)34 applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).
Temporary use of land for maintaining authorised project
27
- (1) Subject to paragraph (2), at any time during the maintenance period relating to any part of the authorised project, the undertaker may—
- (a) enter on and take temporary possession of any land within the Order limits if such possession is reasonably required for the purpose of maintaining the authorised project; and
- (b) construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.
- (2) Paragraph (1) does not authorise the undertaker to take temporary possession of—
- (a) any house or garden belonging to a house; or
- (b) any building (other than a house) if it is for the time being occupied.
- (3) Not less than 28 days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.
- (4) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised project for which possession of the land was taken.
- (5) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.
- (6) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.
- (7) Any dispute as to a person’s entitlement to compensation under paragraph (6), or as to the amount of the compensation, must be determined under Part 1 of the 1961 Act.
- (8) Nothing in this article affects any liability to pay compensation under section 152 of the 2008 Act (compensation in case where no right to claim in nuisance) or under any other enactment in respect of loss or damage arising from the maintenance of the authorised project, other than loss or damage for which compensation is payable under paragraph (6).
- (9) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.
- (10) Section 13 of the 1965 Act (refusal to give possession to acquiring authority) applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).
- (11) In this article “the maintenance period”, in relation to any part of the authorised project, means—
- (a) the period of five years beginning with the date on which the authorised project first exports electricity to the national electricity transmission network except where the authorised development consists of the maintenance of any tree or shrub for which a 10 year replacement period is specified pursuant to requirement 15 (implementation and maintenance of landscaping), in which case “the maintenance period” means a period of 10 years beginning with the date on which that tree or shrub is first planted; and
- (b) any period falling between the date at which temporary possession is no longer permitted under article 26(3) and the date on which the authorised project first exports electricity to the national electricity transmission network.
Statutory undertakers
28
Subject to the provisions of Schedule 10 (protective provisions) the undertaker may—
- (a) acquire compulsorily, or acquire new rights or impose restrictive covenants over, the land belonging to statutory undertakers shown on the land plans within the Order land and described in the book of reference; and
- (b) extinguish the rights of, remove, relocate the rights of or reposition the apparatus belonging to statutory undertakers over or within the Order land.
Recovery of costs of new connections
29
- (1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article 28 (statutory undertakers) any person who is the owner or occupier of premises to which a supply was given from that apparatus is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.
- (2) Paragraph (1) does not apply in the case of the removal of a public sewer but where such a sewer is removed under article 28, any person who is—
- (a) the owner or occupier of premises the drains of which communicated with that sewer; or
- (b) the owner of a private sewer which communicated with that sewer,
is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.
- (3) This article does not have effect in relation to apparatus to which Part 3 (street works in England and Wales) of the 1991 Act applies.
- (4) In this paragraph—
- “public communications provider” has the same meaning as in section 151(1) of the 2003 Act; and
- “public utility undertaker” means a gas, water, electricity or sewerage undertaker.
PART 6 — Operations
Operation of generating station
30
- (1) The undertaker is hereby authorised to operate the generating station comprised in the authorised project.
- (2) This article does not relieve the undertaker of any requirement to obtain any permit or licence under any other legislation that may be required from time to time to authorise the operation of an electricity generating station.
Deemed marine licences under the 2009 Act
31
The marine licences set out in Schedules 13 (deemed licence under the 2009 Act – generation assets) and 14 (deemed licence under the 2009 Act – offshore transmission assets) are deemed to have been granted to the undertaker under Part 4 (marine licensing) of the 2009 Act for the licensed marine activities set out in Part 1, and subject to the conditions set out in Part 2, of each licence.
PART 7 — Miscellaneous and general
Application of landlord and tenant law
32
- (1) This article applies to—
- (a) any agreement for leasing to any person the whole or any part of the authorised project or the right to operate the same; and
- (b) any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised project, or any part of it,
so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person’s use.
- (2) No enactment or rule of law regulating the rights and obligations of landlords and tenants may prejudice the operation of any agreement to which this article applies.
- (3) Accordingly, no such enactment or rule of law applies in relation to the rights and obligations of the parties to any lease granted by or under any such agreement so as to—
- (a) exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;
- (b) confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or
- (c) restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.
Operational land for purposes of the 1990 Act
33
Development consent granted by this Order is treated as specific planning permission for the purposes of section 264(3)(a) of the 1990 Act (cases in which land is to be treated as not being operational land).
Felling or lopping of trees and removal of hedgerows
34
- (1) Subject to article 35 (trees subject to tree preservation orders), the undertaker may fell or lop any tree or shrub within or overhanging the Order limits, or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub from obstructing or interfering with the construction, maintenance or operation of the authorised project or any apparatus used in connection with the authorised project.
- (2) In carrying out any activity authorised by paragraph (1), the undertaker must do no unnecessary damage to any tree or shrub and must pay compensation to any person for any loss or damage arising from such activity.
- (3) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, must be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
- (4) The undertaker may, for the purposes of the authorised project—
- (a) subject to paragraph (2) above, remove any hedgerows within the Order limits that may be required for the purposes of carrying out the authorised project; and
- (b) remove the important hedgerows as are within the Order limits and specified in Schedule 11 (hedgerows).
- (5) In this article “hedgerow” and “important hedgerow” have the same meaning as in the Hedgerows Regulations 1997.
Trees subject to tree preservation orders
35
- (1) The undertaker may fell or lop any tree described in Schedule 12 (trees subject to tree preservation orders) or any tree within or overhanging land within the Order limits that is subject to a tree preservation order made after 25 June 2019, or cut back its roots if it reasonably believes it to be necessary in order to do so to prevent the tree—
- (a) from obstructing or interfering with the construction, maintenance or operation of the authorised project or any apparatus used in connection with the authorised project; or
- (b) from constituting an unacceptable source of danger (whether to children or to other persons).
- (2) In carrying out any activity authorised by paragraph (1)—
- (a) the undertaker must not cause unnecessary damage to any tree and must pay compensation to any person for any loss or damage arising from such activity; and
- (b) the duty contained in section 206(1) of the 1990 Act (replacement of trees) does not apply.
- (3) The authority given by paragraph (1) constitutes a deemed consent under the relevant tree preservation order.
- (4) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, must be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
Certification of plans etc.
36
- (1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of the documents listed in Schedule 17 (documents to be certified) for certification that they are true copies of the documents referred to in this Order.
- (2) A plan or document so certified is admissible in any proceedings as evidence of the contents of the document of which it is a copy.
- (3) Where a plan or document certified under paragraph (1)—
- (a) refers to a provision of this Order (including any specified requirement) when it was in draft form; and
- (b) identifies that provision by a number, or combination of numbers and letters, which is different from the number, or combination of numbers and letters by which the corresponding provision of this Order is identified in the Order as made
the reference in the plan or document concerned must be construed for the purposes of this Order as referring to the provision (if any) corresponding to that provision in the Order as made.
Arbitration
37
- (1) Subject to article 40 (saving provision for Trinity House), any dispute or difference arising out of or in connection with any provision of this Order, unless otherwise provided for, must be referred to and settled in arbitration in accordance with the rules at Schedule 15 (arbitration rules) to this Order by a single arbitrator to be agreed between the parties, within 14 days of receipt of the notice of arbitration, or if the parties fail to agree within the time period stipulated, to be appointed on the application of either party (after giving notice in writing to the other) by the Secretary of State.
- (2) Any matter for which the consent or approval of the Secretary of State or the Marine Management Organisation is required under any provision of this Order shall not be subject to arbitration.
Requirements, appeals, etc.
38
Schedule 16 (procedure for discharge of requirements) has effect in relation to all consents, agreements or approvals required or contemplated by the requirements within Part 3 of Schedule 1 (requirements) to this Order.
Abatement of works abandoned or decayed
39
Where Work No. 1(a), Work No. 1(b), Work No. 2 or Work No. 3 or any part of those works is abandoned or allowed to fall into decay the Secretary of State may, following consultation with the undertaker, issue a written notice requiring the undertaker at its own expense to repair and restore or remove Work No. 1(a), Work No. 1(b), Work No. 2 or Work No. 3 or any relevant part of those works, without prejudice to any notice served under section 105(2) of the 2004 Act35. The notice may also require the restoration of the site of the relevant part(s) of Work No. 1(a), Work No. 1(b), Work No. 2 or Work No. 3 to a safe and proper condition within an area and to such an extent as may be specified in the notice.
Saving provisions for Trinity House
40
Nothing in this Order prejudices or derogates from any of the rights, duties or privileges of Trinity House.
Crown rights
41
- (1) Nothing in this Order affects prejudicially any estate, right, power, privilege, authority or exemption of the Crown and in particular, nothing in this Order authorises the undertaker or any lessee or licensee to take, use, enter upon or in any manner interfere with any land or rights of any description (including any portion of the shore or bed of the sea or any river, channel, creek, bay or estuary)—
- (a) belonging to Her Majesty in right of the Crown and forming part of The Crown Estate without the consent in writing of the Crown Estate Commissioners;
- (b) belonging to Her Majesty in right of the Crown and not forming part of The Crown Estate without the consent in writing of the government department having the management of that land; or
- (c) belonging to a government department or held in trust for Her Majesty for the purposes of a government department without the consent in writing of that government department.
- (2) A consent under paragraph (1) may be given unconditionally or subject to terms and conditions; and is deemed to have been given in writing where it is sent electronically.
Protective provisions
42
Schedule 10 (protective provisions) has effect.
Funding
43
- (1) The undertaker must not exercise the powers conferred by the provisions referred to in paragraph (2) in relation to any land unless it has first put in place either—
- (a) a guarantee in respect of the liabilities of the undertaker to pay compensation under this Order in respect of the exercise of the relevant power in relation to that land; or
- (b) an alternative form of security for that purpose,
that has been approved by the Secretary of State.
- (2) The provisions are—
- (a) article 18 (compulsory acquisition of land);
- (b) article 20 (compulsory acquisition of rights);
- (c) article 21 (private rights);
- (d) article 24 (acquisition of subsoil or airspace only);
- (e) article 25 (rights under or over streets);
- (f) article 26 (temporary use of land for carrying out the authorised project);
- (g) article 27 (temporary use of land for maintaining the authorised project); and
- (h) article 28 (statutory undertakers).
- (3) A guarantee or alternative form of security given in respect of any liability of the undertaker to pay compensation under this Order is enforceable against the guarantor or person providing the alternative form of security by any person to whom such compensation is payable and must be in such a form as to be capable of enforcement by such a person.
- (4) Nothing in this article requires a guarantee or alternative form of security to be in place for more than 15 years after the date on which the relevant power is exercised.
Offshore ornithology compensation provisions
44
Schedule 18 (offshore ornithology compensation measures) has effect.
Service of notices
45
- (1) A notice or other document required or authorised to be served for the purposes of this Order may be served—
- (a) by post;
- (b) by delivering it to the person on whom it is to be served or to whom it is to be given or supplied; or
- (c) with the consent of the recipient and subject to paragraphs (5) to (8) by electronic transmission.
- (2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.
- (3) For the purposes of section 7 (references to services by post) of the Interpretation Act 197836 as it applies for the purposes of this article, the proper address of any person in relation to the service on that person of a notice or document under paragraph (1) is, if that person has given an address for service, that address, and otherwise—
- (a) in the case of the secretary or clerk of a body corporate, the registered or principal office of that body; and
- (b) in any other case, the last known address of that person at the time of service.
- (4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having any interest in, or as the occupier of, land and the name or address of that person cannot be ascertained after reasonable enquiry, the notice may be served by—
- (a) addressing it to that person by name or by the description of “owner”, or as the case may be “occupier”, of the land (describing it); and
- (b) either leaving it in the hands of a person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.
- (5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement will be taken to be fulfilled only where—
- (a) the recipient of the notice or other document to be transmitted has given consent to the use of electronic transmission in writing or by electronic transmission;
- (b) the notice or document is capable of being accessed by the recipient;
- (c) the notice or document is legible in all material respects; and
- (d) the notice or document is in a form sufficiently permanent to be used for subsequent reference.
- (6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within 7 days of receipt that the recipient requires a paper copy of all or part of that notice or other document the sender will provide such a copy as soon as reasonably practicable.
- (7) Any consent to the use of electronic communication given by a person may be revoked by that person in accordance with paragraph (8).
- (8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—
- (a) that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and
- (b) such revocation will be final and will take effect on a date specified by the person in the notice but that date must not be less than 7 days after the date on which the notice is given.
- (9) This article will not be taken to exclude the employment of any method of service not expressly provided for by it.
- (10) In this article “legible in all material respects” means that the information contained in the notice or document is available to that person to no lesser extent than it would be if served, given or supplied by means of a notice or document in printed form.
SCHEDULE 1 — Authorised project
PART 1 — Authorised development
1
A nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act which is located in the North Sea approximately 31 kilometres from the Suffolk coast, comprising—
Work No. 1aan offshore wind turbine generating station with a gross electrical output capacity of over 100 MW comprising up to 67 wind turbine generators each fixed to the seabed by one of five foundation types (namely monopile, jacket on suction caissons, jacket on piles, suction caisson or gravity base), fitted with rotating blades and situated within the area shown on the works plans and further comprising (b) to (c) below;bup to one meteorological mast fixed to the seabed within the area shown on the works plans by one of five foundation types (namely monopile, jacket on suction caissons, jacket on piles, suction caisson or gravity base); andca network of subsea inter-array cables within the area shown on the works plans between the wind turbine generators and between the wind turbine generators and Work No. 3 including one or more cable crossings,
and associated development within the meaning of section 115(2) (development for which development consent may be granted) of the 2008 Act comprising—
Work No. 2— up to one construction, operation and maintenance platform fixed to the seabed within the area shown on the works plans by one of four foundation types (namely monopile, jacket on suction caissons, jacket on piles or gravity base);
Work No. 3— up to four offshore electrical platforms fixed to the seabed within the area shown on the works plans by one of four foundation types (namely monopile, jacket on suction caissons, jacket on piles or gravity base);
Work No. 4— a network of subsea platform link cables within the area shown on the works plans between the offshore electrical platforms comprising Work No. 3 and between the construction, operation and maintenance platform comprising Work No. 2 and the offshore electrical platforms comprising Work No. 3 for the transmission of electricity and electronic communications including one or more cable crossings;
Work No. 5 — up to two subsea export cables between Work No. 3 and Work No. 6 within the area shown on the works plans including one or more cable crossings;
Work No. 6 — landfall connection works consisting of up to two export cables and up to two separate fibre optic cables laid underground within two cable ducts between Work No. 5 and Work No. 8 within the area shown on the works plans;
Work No. 7 — temporary construction consolidation sites and construction access;
Work No. 8 — the onshore transmission works at the landfall consisting of—
- (a) up to two transition bays;
- (b) up to two export cables and up to two separate fibre optic cables laid underground within two cable ducts from Work No. 6 to the transition bays;
- (c) up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from the transition bays to Work No. 9;
- (d) a temporary horizontal directional drilling compound;
- (e) temporary construction consolidation sites;
- (f) construction of a haul road; and
- (g) access;
Work No. 9 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 8 to Work No. 11 including construction of a haul road and access.
Work No. 10 — formation of a new access from Sizewell Gap including vegetation clearance to the south of Sizewell Gap;
Work No. 11 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 9 to Work No. 12 together with a temporary trenchless technique compound, temporary construction consolidation sites, construction of a haul road and access.
Work No. 12 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 11 to Work No. 13 including construction of a haul road and access.
Work No. 12A — temporary ecological mitigation works in accordance with the ecological management plan and associated access.
Work No. 13 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 12 to Work No. 16 together with a temporary trenchless technique compound, construction of a haul road and access.
Work No. 14 — temporary ecological mitigation works in accordance with the ecological management plan and associated access.
Work No. 15 — formation of a new access at Sizewell Gap including vegetation clearance and construction of an access track to Work No. 13.
Work No. 16 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 13 to Work No. 17 together with temporary construction consolidation sites, construction of a haul road and access.
Work No. 17 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 16 to Work No. 18 and crossing Thorpe Road (B1353) together with the construction of a haul road and access.
Work No. 18 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 17 to Work No. 19 together with temporary construction consolidation sites, construction of a haul road and access.
Work No. 19 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 18 to Work No. 20 and crossing Aldeburgh Road (B1122) together with the construction of a haul road and access and the formation of a new access at Aldeburgh Road including vegetation clearance.
Work No. 20 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 19 to Work No. 21 together with the construction of a haul road and access and the formation of a new access at Aldeburgh Road including vegetation clearance.
Work No. 21 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 20 to Work No. 22 together with the construction of a haul road and access.
Work No. 22 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 21 to Work No. 23 together with temporary construction consolidation sites, construction of a haul road and access.
Work No. 23 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 22 to Work No. 26 together with the construction of a haul road and access and the formation of a new access at Snape Road (B1069) and a lay down area to the east of Snape Road.
Work No. 24 — permanent ecological mitigation works in accordance with the ecological management plan and associated access.
Work No. 25 — construction of bridleway to the west of Snape Road (B1069) connecting to the existing bridleway to the north including drainage works and fencing.
Work No. 26 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 23 to Work No. 31 and crossing Snape Road (B1069) together with the construction of a haul road and access and the formation of a new access at Snape Road (B1069).
Work No. 27 — temporary construction consolidation sites and construction access;
Work No. 28 — ecological mitigation works in accordance with the ecological management plan and associated access.
Work No. 29 — permanent ecological mitigation works in accordance with the ecological management plan and associated access.
Work No. 30 — a new onshore substation at Grove Wood, Friston.
Work No. 31 — up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 26 to Work No. 30 together with temporary construction consolidation sites, construction of a haul road, access and extension of permanent access comprised within Work No. 34.
Work No. 32— a connection consisting of up to six electrical cables, up to two fibre optic cables and up to two distributed temperature sensing cables and up to ten cable ducts laid underground from Work No. 30 to Work No. 41 including a connection above ground and electrical engineering works within the national grid substation comprised within Work No. 41;
Work No. 33 — landscaping works including bunding and planting together with drainage works, sustainable drainage system ponds, surface water management systems, formation of footpaths and access.
Work No. 34 — formation of a new permanent access road from the B1121 north of Kiln Lane to the onshore substation and national grid substation including vegetation clearance on the eastern side of the road. Highway modifications and traffic management measures.
Work No. 35 — highway alterations to the junctions between the A1094 and the B1121 and the A1094 and the B1069 including widening of the highway and vegetation clearance.
Work No. 36 — highway alterations to the junction between the A12 and the A1094 including widening of the highway and vegetation clearance.
Work No. 37 — highway alterations comprising reinforcement of bridge together with temporary construction works area and formation of access from the A12,
and in connection with Work Nos. 1 to 6 and to the extent that they do not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project and which fall within the scope of the work assessed by the environmental statement including—
- (a) scour protection around the foundations of the offshore structures;
- (b) cable protection measures such as rock placement and the placement of concrete mattresses and frond mattresses;
- (c) dredging;
- (d) the removal of material from the seabed required for the construction of Work Nos. 1 to 6 and the disposal of inert material of natural origin and dredged material within the Order limits produced during construction drilling and seabed preparation for the installation of the foundations of the offshore structures or during seabed preparation for cable laying;
and in connection with such Work Nos. 6 to 37 and to the extent that they do not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project and which fall within the scope of the work assessed by the environmental statement, including—
- (a) haul roads, ramps, and other vehicular and pedestrian means of access, including creation of new tracks and footpaths, and widening, upgrades, alterations and improvements of existing roads, tracks and footpaths;
- (b) bunds, embankments, swales, landscaping and boundary treatments;
- (c) habitat creation;
- (d) spoil storage and associated control measures;
- (e) jointing bays, link boxes, cable protection, joint protection, manholes, marker posts, tiles and tape, lighting and other works associated with laying cables and pulling cables through cable ducts;
- (f) water supply works, foul drainage provision, surface water management systems, temporary drainage during installations of cables and culverting;
- (g) works to alter the position of apparatus, including mains, sewers, drains and cables;
- (h) works to alter the course of, or otherwise interfere with, non-navigable rivers, streams or watercourses;
- (i) landscaping and other works to mitigate adverse effects of the construction, maintenance or operation of the authorised project;
- (j) works for the benefit or protection of land affected by the authorised project;
- (k) working sites in connection with the construction of the authorised project, construction lay down areas and compounds and storage compounds;
- (l) works of restoration; and
- (m) fencing or other means of enclosure.
2
A nationally significant infrastructure project as defined in sections 14 and 16 (electric lines) of the 2008 Act comprising—
Work No. 38 — up to three cable sealing end compounds, one of which may include circuit breakers, comprising an electrical compound with electrical equipment and overhead line gantries to allow the connection of Work No. 41 to the overhead lines comprised within Work No. 39 together with cables connecting the national grid substation to the cable sealing ends, extension of the permanent access comprised within Work No. 34 and works to the overhead line pylons.
Work No. 39 — replacement, upgrade and realignment works to the overhead line pylons in the vicinity of Work No. 38 together with up to one new additional overhead line pylon to the north west of the national grid substation comprised within Work No. 41.
Work No. 40 — temporary realignment works to the overhead line pylons in the vicinity of Work No. 38.
and associated development within the meaning of section 115(2) (development for which development consent may be granted) of the 2008 Act comprising—
Work No. 41 — a new national grid substation to the north west of Work No. 30 at Grove Wood, Friston and extension of permanent access comprised within Work No. 34.
Work No. 42 — temporary construction consolidation sites, access and extension of permanent access comprised within Work No. 34.
Work No. 43— temporary working areas for the purposes of constructing Work Nos. 39 and 40 including access.
Work No. 34 — formation of a new permanent access road from the B1121 north of Kiln Lane to the onshore substation and national grid substation including vegetation clearance on the eastern side of the road, highway modifications and traffic management measures.
and in connection with such Work No. 34 and Work Nos. 38 to 43 and to the extent that they do not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project and which fall within the scope of the work assessed by the environmental statement, including—
- (a) haul roads, ramps, and other vehicular and pedestrian means of access, including creation of new tracks and footpaths, and widening, upgrades, alterations and improvements of existing roads, tracks and footpaths;
- (b) bunds, embankments, swales, landscaping and boundary treatments;
- (c) habitat creation;
- (d) spoil storage and associated control measures;
- (e) jointing bays, link boxes, cable protection, joint protection, manholes, marker posts, tiles and tape, lighting and other works associated with laying cables and pulling cables through cable ducts;
- (f) water supply works, foul drainage provision, surface water management systems, temporary drainage during installations of cables and culverting;
- (g) works to alter the position of apparatus, including mains, sewers, drains and cables;
- (h) works to alter the course of, or otherwise interfere with, non-navigable rivers, streams or watercourses;
- (i) landscaping and other works to mitigate adverse effects of the construction, maintenance or operation of the authorised project;
- (j) works for the benefit or protection of land affected by the authorised project;
- (k) working sites in connection with the construction of the authorised project, construction lay down areas and compounds and storage compounds;
- (l) works of restoration; and
- (m) fencing or other means of enclosure.
3
The grid coordinates for that part of the authorised project which is seaward of MHWS are specified below and more particularly shown on the Order limits boundary coordinates plan (offshore)—
| Point | Latitude | Longitude |
|---|---|---|
| 1 | 52° 21 40.240N | 02° 18 57.351E |
| 2 | 52° 22 49.082N | 02° 18 20.131E |
| 3 | 52° 25 41.851N | 02° 18 38.726E |
| 4 | 52° 26 07.817N | 02° 19 55.691E |
| 5 | 52° 25 47.948N | 02° 34 14.117E |
| 6 | 52° 20 33.278N | 02° 34 13.789E |
| 7 | 52° 20 19.052N | 02° 28 56.310E |
| 8 | 52° 18 11.924N | 02° 20 49.771E |
| 9 | 52° 21 07.976N | 02° 19 14.783E |
| 10 | 52° 19 34.060N | 02° 11 21.980E |
| 11 | 52° 19 10.459N | 02° 10 57.491E |
| 12 | 52° 19 10.410N | 02° 08 40.019E |
| 13 | 52° 17 42.613N | 02° 08 31.830E |
| 14 | 52° 18 44.262N | 02° 06 49.319E |
| 15 | 52° 18 39.650N | 01° 57 24.848E |
| 16 | 52° 17 25.858N | 01° 54 09.969E |
| 17 | 52° 17 24.663N | 01° 52 03.374E |
| 18 | 52° 17 24.629N | 01° 52 03.277E |
| 19 | 52° 15 14.373N | 01° 45 57.606E |
| 20 | 52° 14 29.510N | 01° 45 06.050E |
| 21 | 52° 10 51.365N | 01° 42 32.460E |
| 22 | 52° 09 56.713N | 01° 39 52.443E |
| 23 | 52° 09 53.117N | 01° 38 40.253E |
| 24 | 52° 10 06.702N | 01° 37 38.597E |
| 25 | 52° 10 44.466N | 01° 37 04.551E |
| 26 | 52° 11 01.504N | 01° 37 17.750E |
| 27 | 52° 11 02.378N | 01° 37 15.833E |
| 28 | 52° 11 11.451N | 01° 37 20.545E |
| 29 | 52° 11 22.030N | 01° 37 22.233E |
| 30 | 52° 11 30.678N | 01° 37 21.417E |
| 31 | 52° 11 31.210N | 01° 37 24.534E |
| 32 | 52° 11 33.421N | 01° 37 24.505E |
| 33 | 52° 11 53.663N | 01° 37 50.246E |
| 34 | 52° 12 26.106N | 01° 40 17.584E |
| 35 | 52° 13 37.194N | 01° 41 04.014E |
| 36 | 52° 15 54.943N | 01° 45 03.442E |
| 37 | 52° 18 25.193N | 01° 52 05.276E |
| 38 | 52° 20 19.496N | 01° 56 37.327E |
| 39 | 52° 20 25.400N | 02° 08 48.429E |
| 40 | 52° 20 02.196N | 02° 08 47.461E |
| 41 | 52° 20 02.239N | 02° 10 44.070E |
4
Notwithstanding the grid coordinates specified at paragraph 3 and notwithstanding anything to the contrary shown on the work plans referred to in this Part, no part of Work No. 1(a) or Work No. 1(b) may be carried out if it falls within 8 kilometres of the boundary of the Outer Thames Estuary Special Protection Area.
PART 2 — Ancillary works
1
Works within the Order limits which have been subject to an environmental impact assessment recorded in the environmental statement comprising—
- (a) temporary landing places, moorings or other means of accommodating vessels in the construction and/ or maintenance of the authorised development;
- (b) buoys, beacons, fenders and other navigational warning or ship impact protection works; and
- (c) temporary works for the benefit or protection of land or structures affected by the authorised development.
PART 3 — Requirements
Time limits
1
The authorised project must commence no later than the expiration of five years beginning with the date this Order comes into force.
Detailed offshore design parameters
2
- (1) Subject to sub-paragraph (2), wind turbine generators forming part of the authorised project must not—
- (a) exceed a height of 282 metres when measured from LAT to the tip of the vertical blade;
- (b) exceed a height of 175 metres to the height of the centreline of the generator shaft forming part of the hub when measured from LAT;
- (c) exceed a rotor diameter of 250 metres;
- (d) be less than 800 metres from the nearest wind turbine generator in either direction perpendicular to the approximate prevailing wind direction (crosswind) or be less than 1,200 metres from the nearest wind turbine generator in either direction which is in line with the approximate prevailing wind direction (downwind); and
- (e) have an air clearance height of less than 24 metres from MHWS.
- (2) References to the location of a wind turbine generator in sub-paragraph (1) above are references to the centre point of that turbine.
3
- (1) The total number of offshore electrical platforms forming part of the authorised project must not exceed four.
- (2) The total number of construction, operation and maintenance platforms must not exceed one.
- (3) The total number of meteorological masts must not exceed one.
- (4) The dimensions of any offshore electrical platform forming part of the authorised project (excluding towers, helipads, masts and cranes) must not exceed 50 metres in height when measured from LAT, 70 metres in length and 50 metres in width.
- (5) The dimensions of any construction, operation and maintenance platform forming part of the authorised project (excluding towers, helipads, masts and cranes) must not exceed 50 metres in height when measured from LAT, 70 metres in length and 50 metres in width.
- (6) The meteorological mast must not exceed a height of 175 metres above LAT.
4
- (1) The total length of the inter-array cables comprised within Work No. 1(c) must not exceed 200 kilometres.
- (2) The total length of the platform link cables comprised within Work No. 4 must not exceed 75 kilometres.
- (3) The total length of the export cables comprised within Work Nos. 5 and 6 must not exceed 152 kilometres.
5
- (1) In relation to a wind turbine generator, each gravity base foundation must not have a diameter at the level of the seabed which is more than 60 metres.
- (2) In relation to a wind turbine generator, each suction caisson foundation must not have a diameter at the level of the seabed which is more than 35 metres.
- (3) In relation to a wind turbine generator, each jacket foundation must not have—
- (a) a pile diameter which is more than 4.6 metres in the case of pin piles or a suction caisson diameter which is more than 16 metres;
- (b) more than four piles or more than four suction caissons; and
- (c) more than four legs.
- (4) In relation to a wind turbine generator, each monopile foundation must not have a diameter which is more than 15 metres.
6
- (1) In relation to a meteorological mast, each gravity base foundation must not have a footprint at the seabed which is more than 315 m².
- (2) In relation to a meteorological mast, each suction caisson foundation must not have a footprint at the seabed which is more than 177 m².
- (3) In relation to a meteorological mast, each jacket foundation must not have a footprint at the seabed which is more than 651 m².
- (4) In relation to a meteorological mast, each monopile foundation must not have a footprint at the seabed which is more than 51 m².
7
- (1) In relation to each offshore electrical platform, the gravity base foundations must not have a total footprint at the seabed which is more than 4,800 m².
- (2) In relation to each offshore electrical platform, the jacket foundations must not have a total footprint at the seabed which is more than 5,676 m².
- (3) In relation to each offshore electrical platform, the monopile foundations must not have a total footprint at the seabed which is more than 177 m².
8
- (1) In relation to a construction, operation and maintenance platform, the gravity base foundations must not have a total footprint of more than 4,800 m².
- (2) In relation to a construction, operation and maintenance platform, the jacket foundations must not have a total footprint at the seabed which is more than 5,676 m².
- (3) In relation to any construction, operation and maintenance platform, the monopile foundation must not have a total footprint at the seabed which is more than 177 m².
9
The total amount of scour protection for the wind turbine generators, construction, operation and maintenance platform, meteorological mast and offshore electrical platform forming part of the authorised project must not exceed 1,428,854 m².
Offshore decommissioning
10
No offshore works may commence until a written decommissioning programme in compliance with any notice served upon the undertaker by the Secretary of State pursuant to section 105(2) of the 2004 Act37 has been submitted to the Secretary of State for approval.
Stages of authorised development onshore
11
- (1) The transmission works may not be commenced until a written scheme setting out the stages of the transmission works has been submitted to, and approved by, the relevant planning authority.
- (2) The grid connection works may not be commenced until a written scheme setting out the stages of the grid connection works has been submitted to, and approved by, the relevant planning authority.
- (3) Any amendments to the approved written schemes must be submitted to, and approved by, the relevant planning authority.
- (4) The written schemes specified in sub-paragraphs (1) and (2) must be implemented as approved. The approved details shall be taken to include any amendments that may subsequently be approved in accordance with sub-paragraph (3).
Detailed design parameters onshore
12
- (1) No stage of Work No. 30 may commence until details of the layout, scale and external appearance of the onshore substation have been submitted to and approved by the relevant planning authority in consultation with Suffolk County Council. Work No. 30 must be carried out in accordance with the approved details.
- (2) No stage of Work No. 30 may commence until written details of the specification of plant, and any noise mitigation proposed in respect of Work No. 30 together with updated modelling, have been submitted to and approved in writing by the relevant planning authority in consultation with Suffolk County Council. Work No. 30 must thereafter be implemented in accordance with the approved details.
- (3) No stage of the national grid substation comprised within Work No. 41 may commence until details of the layout, scale and external appearance of the national grid substation have been submitted to and approved by the relevant planning authority in consultation with Suffolk County Council. Work No. 41 must be carried out in accordance with the approved details.
- (4) No stage of the cable sealing end compounds comprised within Work No. 38 may commence until details of the layout, scale and external appearance of the cable sealing end compounds have been submitted to and approved by the relevant planning authority in consultation with Suffolk County Council. Work No. 38 must be carried out in accordance with the approved details.
- (5) Any details provided by the undertaker pursuant to sub-paragraphs (1), (2), (3) and (4) must accord with the substations design principles statement and be within the Order limits.
- (6) To the extent comprised within the onshore substation—
- (a) buildings must not exceed a height of 14 metres above finished ground level;
- (b) external electrical equipment, with the exception of lightning protection masts, must not exceed a height of 14 metres above finished ground level;
- (c) lightning protection masts must not exceed a height of 20 metres above finished ground level; and
- (d) the maximum number of lightning protection masts must not exceed six.
- (7) Buildings comprised within the national grid substation must not exceed—
- (a) where AIS substation arrangement is used, a height of 6 metres above finished ground level; and
- (b) where GIS substation arrangement is used, a height of 16 metres above finished ground level.
- (8) External electrical equipment comprised within the national grid substation must not exceed a height of 16 metres above finished ground level.
- (9) To the extent comprised within the cable sealing end compounds comprised within Work No. 38—
- (a) the overhead line gantries must not exceed a height of 16 metres above finished ground level; and
- (b) electrical equipment (excluding the overhead line gantries) must not exceed a height of 14.5 metres above finished ground level.
- (10) For the purposes of sub-paragraphs (6) to (9), ‘finished ground level’ will be defined in accordance with the substations design principles statement .
- (11) The maximum number of new additional overhead line pylons comprised within Work No. 39 must not exceed one and the maximum number of permanently relocated and/or reconstructed overhead line pylons comprised within Work No. 39 must not exceed three.
- (12) The maximum height of any additional, relocated or reconstructed overhead line pylons must not exceed 59.2 metres.
- (13) The width of the new permanent access road comprised within Work No. 34 must not exceed 7 metres.
- (14) The fenced compound area (excluding its accesses) for the onshore substation must not exceed 32,300 m².
- (15) The fenced compound area (excluding its accesses) for the national grid substation must not exceed—
- (a) where AIS substation arrangement is used, 44,950 m²; and
- (b) where GIS substation arrangement is used, 16,800 m².
- (16) The fenced compound area (excluding its accesses) for the cable sealing end compounds comprised within Work No. 38 must not exceed—
- (a) 5,000m² where the cable sealing end compound includes circuit breakers; and
- (b) 2,500m² where the cable sealing end compound does not include circuit breakers.
- (17) The total footprint of the construction consolidation sites comprised within the following works must not exceed the following—
| Work | Total footprint of construction consolidation sites |
|---|---|
| Work Nos. 7 and 8 (combined) | 7,040 m² |
| Work No. 11 | 7,040 m² |
| Work No. 16 | 7,040 m² |
| Work No. 18 | 3,000 m² |
| Work No. 22 | 3,000 m² |
| Work No. 27 | 16,500 m² |
| Work No. 31 | 17,100 m² |
| Work No. 42 | 23,350 m² |
- (18) The working width of the onshore cable route must not exceed 32 metres, save in respect of the following—
- (a) where the cables cross the Sandlings SPA the working width of the onshore cable route must not exceed—
- (i) 16.1 metres, in the event that open cut trenching is used;
- (ii) 90 metres, in the event that a trenchless technique is used;
- (b) where the cables cross the Hundred River the working width of the onshore cable route must not exceed 34 metres for a distance of 40 metres from the banks of the river;
- (c) where the cables cross the woodland to the west of Aldeburgh Road the working width of the onshore cable route must not exceed 16.1 metres;
- (d) where the cables cross an important hedgerow specified in Part 2 of Schedule 11 (important hedgerows that will be crossed using a reduced working width) the working width of the onshore cable route must not exceed 16.1 metres;
- (e) where the cables are within 418 metres of a transition bay forming part of Work No. 8, the working width of the onshore cable route must not exceed 113 metres; and
- (f) where the cables cross the woodland to the east of Aldeburgh Road the working width of the onshore cable route must not exceed 16.1 metres between Aldeburgh Road and the point 40 metres from the western bank of the Hundred River.
- (19) Jointing bays must not be installed within 55 metres of a building used as a dwelling-house.
- (20) Where open cut trenching is used to cross the Sandlings SPA, Work Nos. 11 and 13 must not include trenchless technique compounds.
- (21) The ducts and cables comprised within Work No. 6 must be installed using horizontal directional drilling.
Landfall construction method statement and monitoring plan
13
- (1) No part of Work Nos. 6 or 8 may commence until the following have been submitted to and approved by the relevant planning authority in consultation with the relevant statutory nature conservation body and, in respect of sub-paragraph (a) and to the extent that it relates to works seaward of mean high water springs, the marine management organisation—
- (a) a landfall construction method statement for the construction of that part of Work No. 6 or Work No. 8 (which accords with the outline landfall construction method statement); and
- (b) a landfall monitoring plan (which accords with the outline landfall monitoring plan contained within appendix 2 of the outline landfall construction method statement).
- (2) The landfall construction method statement and the landfall monitoring plan must be implemented as approved.
- (3) In the event that inspections carried out in accordance with the landfall monitoring plan indicate that, as a result of the rate and extent of landfall erosion, Work Nos. 6 or 8 could become exposed during the operation of the authorised project the undertaker must, as soon as practicable, submit proposals in writing for remedial works or mitigation measures to protect Work Nos. 6 or 8 from coastal retreat, together with a timetable for their implementation, to the relevant planning authority for approval in consultation with the relevant statutory nature conservation body and the remedial works or mitigation measures must be implemented as approved.
Provision of landscaping
14
- (1) No stage of the onshore works may commence until for that stage a written landscape management plan and associated work programme (which accords with the outline landscape and ecological management strategy and includes details of the ongoing maintenance and management of the landscaping works) has been submitted to and approved by the relevant planning authority.
- (2) The written landscape management plan(s) and associated work programme(s) must be implemented as approved.
Implementation and maintenance of landscaping
15
- (1) All landscaping works must be carried out and maintained in accordance with the landscape management plan(s) approved under requirement 14 (provision of landscaping), and in accordance with the relevant recommendations of appropriate British Standards.
- (2) Any tree or shrub planted as part of an approved landscape management plan that, within a period of five years (save in relation to Work Nos. 19, 24, 29 and 33, for which the relevant period is ten years) after planting, is removed, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased must be replaced in the first available planting season with a specimen of the same species and size as that originally planted unless alternative timing or a different specimen is otherwise approved by the relevant planning authority.
Highway accesses
16
- (1) Construction of any access must not begin until written details (which accord with the outline access management plan) of the siting, design, layout and any access management measures for any new, permanent or temporary means of access to a highway to be used by vehicular traffic, or any alteration to an existing means of access to a highway used by vehicular traffic, has been submitted to and approved by the relevant highway authority in consultation with the relevant planning authority.
- (2) The highway accesses must be constructed or altered and the works described in sub-paragraph (1) above in relation to access management measures must be carried out, as the case may be, in accordance with the approved details before they are brought into use for the purposes of the authorised project.
Fencing and other means of enclosure
17
- (1) No stage of the onshore works may commence until for that stage written details of all proposed permanent and temporary fences, walls or other means of enclosure of the onshore works have been submitted to and approved by the relevant planning authority.
- (2) All fencing and other means of enclosure of the onshore works must be in accordance with the approved details.
- (3) Any temporary fencing must be removed on completion of the relevant stage of the onshore works unless otherwise approved by the relevant planning authority.
- (4) Any approved permanent fencing in relation to the onshore substation comprised within Work No. 30, the national grid substation comprised within Work No. 41 and the sealing end compounds comprised within Work No. 38 must be completed before the respective substation or sealing end compound is brought into use and must be maintained for the operational lifetime of the work to which it relates.
Contaminated land and groundwater
18
- (1) No stage of the onshore works shall commence until a written scheme applicable to that stage, to mitigate the potential for release of contaminants within the Order limits has, after consultation with the Environment Agency, been submitted to and approved by the relevant planning authority.
- (2) The scheme must include an investigation and assessment report, prepared by a specialist consultant approved by the relevant planning authority, to identify the extent of any contamination within the Order limits comprised in that stage and mitigation measures to be undertaken to limit impacts arising from the potential release of contaminants.
- (3) The written scheme referred to in sub-paragraph (1) must be implemented as approved.
Pre-commencement archaeology execution plan
19
- (1) No intrusive onshore preparation works (including pre-commencement archaeological surveys, archaeological investigations or site preparation works in respect of such surveys or investigations) may be carried out until a pre-commencement archaeology execution plan (which accords with the outline pre-commencement archaeology execution plan and the outline written scheme of investigation (onshore archaeology)) in respect of those works has been submitted to and approved by Suffolk County Council in consultation with the relevant planning authority.
- (2) Intrusive onshore preparation works must be carried out in accordance with the approved plan.
Archaeology
20
- (1) No stage of the onshore works may commence until for that stage a written scheme of archaeological investigation (which accords with the outline written scheme of investigation (onshore archaeology) and is informed by the pre-commencement archaeological surveys) has, after consultation with Historic England, been submitted to and approved by Suffolk County Council in consultation with the relevant planning authority.
- (2) In the event that site investigation is required, the scheme must include details of the following—
- (a) an assessment of significance and research questions;
- (b) the programme and methodology of site investigation and recording;
- (c) the programme for post investigation assessment;
- (d) provision to be made for analysis of the site investigation and recording;
- (e) provision to be made for publication and dissemination of the analysis and records of the site investigation;
- (f) provision to be made for archive deposition of the analysis and records of the site investigation; and
- (g) nomination of a competent person or persons/organisation to undertake the works set out within the written scheme of investigation.
- (3) Any archaeological works or watching brief must be carried out in accordance with the approved written scheme of archaeological investigation for that stage.
- (4) In the event that site investigation is required, the site investigation and post investigation assessment must be completed for that stage in accordance with the programme set out in the written scheme of archaeological investigation and provision made for analysis, publication and dissemination of results and archive deposition secured for that stage.
Ecological management plan
21
- (1) No stage of the onshore works may commence until for that stage a written ecological management plan (which accords with the outline landscape and ecological management strategy) reflecting pre-construction survey results, and the ecological mitigation measures included in the environmental statement and including—
- (a) a breeding bird protection plan;
- (b) an arboricultural method statement;
- (c) an invasive species method statement;
- (d) where appropriate, a special protection area crossing method statement (which accords with the outline SPA crossing method statement); and
- (e) a precautionary method of working for reptiles
has been submitted to and approved by the relevant planning authority in consultation with the relevant statutory nature conservation body.
- (2) Onshore preparation works may not be carried out until a written ecological management plan (which accords with the outline landscape and ecological management strategy) for those works reflecting survey results and the ecological mitigation measures included in the environmental statement has been submitted to and approved by the relevant planning authority in consultation with the relevant statutory nature conservation body.
- (3) The ecological management plan(s) must include an implementation timetable and must be carried out as approved.
Code of construction practice
22
- (1) No stage of the onshore works may commence until for that stage a code of construction practice (which must accord with the outline code of construction practice) has been submitted to and approved by the relevant discharging authority.
- (2) The code of construction practice must include—
- (a) a surface water and drainage management plan;
- (b) a flood management plan;
- (c) a construction phase noise and vibration management plan;
- (d) a site waste management plan;
- (e) a soil management plan including method statements for soil handling;
- (f) an air quality management plan;
- (g) a materials management plan;
- (h) a pollution prevention and response plan including a groundwater protection method statement and construction method statements for the protection of onshore water;
- (i) a stakeholder communications plan;
- (j) an artificial light emissions management plan;
- (k) a watercourse crossing method statement (which accords with the outline watercourse crossing method statement); and
- (l) a Sizewell Gap construction method statement (which accords with the outline Sizewell Gap construction method statement).
- (3) The relevant discharging authority is the relevant planning authority, except in relation to any surface water and drainage management plan prepared under requirements 22(2)(a) or flood management plan prepared under requirement 22(2)(b), where it is the relevant lead local flood authority.
- (4) The code of construction practice approved in relation to the relevant stage of the onshore works must be followed in relation to that stage of the onshore works.
- (5) In approving the code of construction practice the relevant discharging authority must consult with the relevant planning authority in relation to the following plans—
- (a) the surface water and drainage management plan; and
- (b) the flood management plan.
- (6) In approving the code of construction practice the relevant discharging authority must consult with the relevant statutory nature conservation body in relation to the watercourse crossing method statement and in relation to the following plans to the extent that they relate to the Works Nos. specified—
- (a) the surface water and drainage management plan in respect of Work Nos. 7 to 14 and Work No. 19;
- (b) the construction phase noise and vibration management plan in respect of Work Nos. 7 to 14;
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.