The Construction Contracts (England) Exclusion Order 2022

Type Statutory-Instrument
Publication 2022-07-15
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API

Made: 15th July 2022

Coming into force: 1st October 2022

In accordance with section 106A(4)(a) of the Act, a draft of this Order was laid before Parliament and approved by a resolution of each House of Parliament.

Citation, commencement and application

1

Interpretation

2

In this Order, “the Act” means the Housing Grants, Construction and Regeneration Act 1996.

Direct procurement for customers projects

3

Direct procurement for customers project sub-contracts

4

Signed

Callanan — Parliamentary Under Secretary of State — Department for Business, Energy and Industrial Strategy — 15th July 2022

Explanatory note

(This note is not part of the Order)

EXPLANATORY NOTE

Part 2 of the Housing Grants, Construction and Regeneration Act 1996 (“the Act”) makes provision as regards the terms of construction contracts and related matters. The Order excludes from the entirety of Part 2 of the Act infrastructure project contracts where a party to the contract is a sewerage or water undertaker, subject to the following requirements. The contract must relate to a project designated by the Water Services Regulation Authority as a direct procurement for customers project in accordance with the conditions of the relevant undertaker’s appointment. Such contracts must also involve the making of regular payments by reference to actual costs incurred and which become due after one or more parts of the construction operations are completed and are capable of performing a sewerage or water service.

The Order also excludes section 110(1A) of the Act from applying where a party to such a contract enters into a subcontract. Section 110(1A) of the Act provides that the requirement that contracts provide an adequate mechanism for establishing what payments become due and when under the contract is not met if payment is conditional on obligations being performed under another contract.

No regulatory impact assessment has been prepared in relation to this instrument as there is no, or no significant impact, on businesses, charities or the voluntary sector.

Footnotes

[^f00001]: 1996 c. 53; section 106A(1) was inserted by section 138(3) of the Local Democracy, Economic Development and Construction Act 2009 (c. 20).

[^f00002]: 1991 c. 56.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.