The East Northamptonshire Resource Management Facility Order 2023

Type Statutory-Instrument
Publication 2023-01-23
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API

Made: 23rd January 2023

Coming into force: 13th February 2023

The Secretary of State, in exercise of the powers conferred by sections 114, 115 and 120 of the Planning Act 2008, makes the following Order:

PART 1 — PRELIMINARY

Citation and commencement

1

This Order may be cited as the East Northamptonshire Resource Management Facility Order 2023 and comes into force on the 13th February 2023.

Interpretation

2

  • (1) In this Order—
  • the 1961 Act” means the Land Compensation Act 1961[^f00004];
  • the 1965 Act” means the Compulsory Purchase Act 1965[^f00005];
  • the 1980 Act” means the Highways Act 1980[^f00006];
  • the 1990 Act” means the Town and Country Planning Act 1990[^f00007];
  • the 2008 Act” means the Planning Act 2008[^f00008];
  • the 1991 Act” means the New Roads and Street Works Act 1991[^f00009];
  • access plan” means the plan certified as the access plan [Drawing Reference AU/KCW/07-21/22659] by the Secretary of State for the purposes of this Order;
  • address” includes any number or address for the purposes of electronic transmission;
  • “apparatus”, unless otherwise provided for, has the same meaning as in Part 3 of the 1991 Act;
  • authorised development” means the development and associated development[^f00010] described in Schedule 1 (authorised development) and any other development authorised by this Order;
  • building” includes any structure or erection or any part of a building, structure or erection;
  • business days” means Monday to Friday excluding Bank Holidays and other public holidays or days on which general or local elections are held;
  • commence” means the carrying out of a material operation (as defined in section 56(4) of the 1990 Act) excluding any operations relating to ecological enhancement works, planting, soil investigations or works in respect of land contamination, archaeological investigations, site clearance, diversion of services, receipt and erection of construction plant and equipment, the erection of temporary fencing, hoardings and erection of site compound buildings and “commence” and “commenced” must be construed accordingly;
  • DEC” means the document certified as the DCO environmental commitments [Report Reference AU/KCW/LZH/1724/01DECV3] by the Secretary of State for the purposes of this Order;
  • electronic transmission” means a communication transmitted— by means of an electronic communications network; or by other means but while in electronic form;
  • environmental statement” means the document of that name submitted with the application for this Order;
  • hazardous waste” means waste defined as such in regulation 6 of the Hazardous Waste (England and Wales) Regulations 2005[^f00011] and as may be amended from time to time in these or equivalent regulations;
  • hedgerow plan” means the plan certified as the hedgerow removal plan [Drawing Reference AU/KCW/07-21/22661] by the Secretary of State for the purposes of this Order;
  • highway”, “highway authority” and “local highway authority” have the same meaning as in the 1980 Act and “highway” includes part of a highway;
  • land plan” means the plan certified as the land plan [Drawing Reference AU/KCW/08-21/22752] by the Secretary of State for the purposes of this Order;
  • limits of deviation” means the limits of deviation referred to in article 5 (limits of deviation) and shown on the works plan;
  • low level waste” means radioactive waste comprising solid low level radioactive waste typically with a specific activity of up to 200Bq/g;
  • maintain” includes maintain, inspect, repair, remove, clear, refurbish, reconstruct, demolish, replace and improve and “maintenance” must be construed accordingly;
  • the Order limits” means the limits shown on the works plan within which the authorised development may be carried out;
  • original order” means the East Northamptonshire Resource Management Facility Order 2013[^f00012] as amended by the East Northamptonshire Resource Management Facility (Amendment) Order 2018[^f00013];
  • owner”, in relation to land, has the same meaning as in section 7 (interpretation) of the Acquisition of Land Act 1981[^f00014];
  • relevant planning authority” means North Northamptonshire Council or the local planning authority for the area in which the land to which the relevant provision of this Order applies is situated from time to time;
  • Requirements” means the requirements listed in Schedule 2 (Requirements), and any reference to a numbered Requirement is to be construed accordingly;
  • restoration concept scheme” means the scheme certified as the restoration concept scheme [Drawing No. ENORTH 028] by the Secretary of State for the purposes of this Order;
  • restoration profile contour plan” means the plan certified as the restoration profile contour plan [Drawing Reference AU/KCW/07-21/22660revA] by the Secretary of State for the purposes of this Order;
  • the site” means land within the Order limits;
  • statutory undertaker” means any statutory undertaker for the purposes of section 127(8), of the 2008 Act (statutory undertakers’ land) and includes a public communications provider as defined in section 151(1) of the Communications Act 2003[^f00015];
  • street authority”, in relation to a street, has the same meaning as in Part 3 (street works in England and Wales) of the 1991 Act;
  • the undertaker” means Augean South Ltd (Company No. 04636789) or such other person as has the benefit of this Order under section 156(1) of the 2008 Act;
  • watercourse” includes all rivers, streams, ditches, drains, canals, cuts, culverts, dykes, sluices, soakaways, sewers and passages through which water flows except a public sewer or drain;
  • Western Power Distribution” means Western Power Distribution (East Midlands) Plc (company number 02366923), whose registered office is at Avonbank, Feeder Road, Bristol, BS2 0TB
  • work” means a work set out in Schedule 1 and shown on the works plans; and a reference to a work designated by a number or a combination of numbers and letters, is a reference to the work so designated in that Schedule; and
  • the works plan” means the plan certified as the works plan [Drawing Reference AU/KCW/07-21/22655revA] by the Secretary of State for the purposes of this Order.
  • (2) References in this Order to rights over land include references to rights to do or to place and maintain, anything in, on or under land or in the air-space above its surface.
  • (3) All distances, directions and lengths referred to in this Order are approximate.
  • (4) The expression “includes” must be construed without limitation.

PART 2 — PRINCIPAL POWERS

3

Subject to the provisions of this Order and to the Requirements in Schedule 2 (requirements) attached to this Order the undertaker is granted development consent for the authorised development to be carried out within the Order limits.

Effect of this Order on the original order

4

  • (1) The undertaker must not start operational use of Work No. 1A, Work No. 2, or Work No.3 under this Order until notice has been served on the relevant planning authority that the undertaker is ceasing to operate those works under the original order.
  • (2) Upon service of the notice under paragraph (1) construction, operation and maintenance of Work No.1A, Work No.2 and Work No.3 will cease under the original order and from that date the authorised development will be constructed, operated and maintained in accordance with the provisions of this Order and the plans certified under article 18.
  • (3) From the date of the notice served under paragraph (1) the provisions of the original order will not apply in relation to the authorised development.

Limits of deviation

5

In carrying out, maintaining or diverting the authorised development, the undertaker may—

  • (a) construct any such work within the lateral limits of deviation or extents of work shown on the works plans for the relevant work;
  • (b) in relation to Work No. 1 only deviate the works vertically upwards to a limit of 1 metre from the contours shown in grey on the restoration profile contour plan;
  • (c) deviate the works vertically downwards to any extent as may be found necessary to construct the authorised development, subject to approval by the Environment Agency.

Benefit of this Order

6

  • (1) Subject to paragraph (2) and article 7 (consent to transfer benefit of Order), the provisions of this Order have effect solely for the benefit of the undertaker.
  • (2) Paragraph (1) does not apply to the works for which the consent is granted by this Order for the express benefit of owners and occupiers of land, statutory undertakers and other persons affected by the authorised development.

7

  • (1) The undertaker may, with the consent of the Secretary of State—
  • (a) transfer to another person (“the transferee”) any or all of the benefit of the provisions of this Order and such related statutory rights as may be agreed between the undertaker and the transferee; or
  • (b) grant to another person (“the lessee”) for a period agreed between the undertaker and the lessee any or all of the benefit of the provisions of this Order and such related statutory rights as may be so agreed.
  • (2) Where an agreement has been made in accordance with paragraph (1) references in this Order to the undertaker, except in paragraph (3), includes references to the transferee or the lessee.
  • (3) The exercise by a person of any benefits or rights conferred in accordance with any transfer or grant under paragraph (1) is subject to the same restrictions, liabilities and obligations as would apply under this Order if those benefits or rights were exercised by the undertaker.
  • (4) The consent of the Secretary of State is not required under this article where the transfer or grant is made to Western Power Distribution for the purposes of undertaking Work No. 5.

Power to construct and maintain the authorised development

8

The undertaker may at any time construct and maintain the authorised development, except to the extent that this Order or an agreement made under this Order, provides otherwise.

Maintenance of drainage works

9

  • (1) Nothing in this Order, or the construction, maintenance or operation of the authorised development under it, affects any responsibility for the maintenance of any works connected with the drainage of land, whether that responsibility is imposed or allocated by or under any enactment, or otherwise, unless otherwise agreed in writing between the undertaker and the person responsible.
  • (2) In this article “drainage” has the same meaning as in section 72 (interpretation) of the Land Drainage Act 1991[^f00016].

PART 3 — SUPPLEMENTAL POWERS

Access to works

10

  • (1) The undertaker may, for the purposes of the authorised development and subject to paragraph (2), with the consent of the street authority following consultation by the street authority with the relevant planning authority, form and lay out such means of access (permanent or temporary) shown on the access plan or improve existing means of access, within the Order limits as the undertaker reasonably requires for the purposes of the authorised development.
  • (2) The consent of the street authority is not required for the formation, laying out or improvement of a new or existing means of access as shown on the access plan and described in Schedule 1 (authorised development).

Discharge of water

11

  • (1) The undertaker may use any watercourse or any public sewer or drain for the drainage of water in connection with the carrying out or maintenance of the authorised development and for that purpose may lay down, take up and alter pipes and may, on any land within the Order limits, make openings into, and connections with, the watercourse, public sewer or drain.
  • (2) Any dispute arising from the making of connections to or the use of a public sewer or drain by the undertaker pursuant to paragraph (1) is to be determined as if it were a dispute under section 106 of the Water Industry Act 1991[^f00017] (right to communicate with public sewers).
  • (3) The undertaker must not discharge any water into any watercourse, public sewer or drain except with the consent of the person to whom it belongs; and such consent may be given subject to such terms and conditions as that person may reasonably impose, but is not to be unreasonably withheld.
  • (4) The undertaker must not make any opening into any public sewer or drain except—
  • (a) in accordance with plans approved by the person to whom the sewer or drain belongs, but such approval is not to be unreasonably withheld; and
  • (b) where that person has been given the opportunity to supervise the making of the opening.
  • (5) The undertaker must not, in carrying out or maintaining works pursuant to this article, damage or interfere with the bed or banks of any watercourse forming part of a main river.
  • (6) The undertaker must take such steps as are reasonably practicable to secure that any water discharged into a watercourse or public sewer or drain pursuant to this article is as free as may be practicable from gravel, soil or other solid substance, oil or matter in suspension.
  • (7) This article does not authorise the entry into controlled waters of any matter whose entry or discharge into controlled waters is prohibited by Regulation 12 of the Environmental Permitting (England and Wales) Regulations 2016[^f00018].
  • (8) In this article—
  • (a) “public drain” means a drain which belongs to the Homes and Communities Agency, the Environment Agency, an internal drainage board, a joint planning board, a local authority; and
  • (b) other expressions, excluding watercourse, used both in this article and in the Water Resources Act 1991[^f00019] have the same meaning as in that Act.

Authority to survey and investigate the land

12

  • (1) The undertaker may for the purposes of this Order enter on any land shown within the Order limits or which may be affected by the authorised development and—
  • (a) survey or investigate the land;
  • (b) without prejudice to the generality of sub-paragraph (a), make trial holes or bore holes in such positions on the land as the undertaker thinks fit to investigate the nature of the surface layer and subsoil and remove soil samples;
  • (c) without prejudice to the generality of sub-paragraph (a), carry out ecological or archaeological investigations on such land; and
  • (d) place on, leave on and remove from the land apparatus for use in connection with the survey and investigation of land and making of trial holes and bore holes.
  • (2) No land may be entered or equipment placed or left on or removed from the land under paragraph (1) unless at least 14 days’ notice has been served on every owner or occupier of the land.
  • (3) Any person entering land under this article on behalf of the undertaker—
  • (a) must, if so required on entering the land, produce written evidence of their authority to do so; and
  • (b) may take with them such vehicles and equipment as are necessary to carry out the survey or investigation or to make the trial holes or bore holes.
  • (4) No trial holes or bore holes may be made under this article—
  • (a) in land located within the highway boundary without the consent of the highway authority; or
  • (b) in a private street without the consent of the street authority, but such consent must not be unreasonably withheld.
  • (5) The undertaker must compensate the owners and occupiers of the land for any loss or damage arising by reason of the exercise of the authority conferred by this article, such compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
  • (6) If either a highway authority or a street authority which receives an application for consent fails to notify the undertaker of its decision within 28 days of receiving the application for consent—
  • (a) under paragraph (4)(a) in the case of a highway authority; or
  • (b) under paragraph (4)(b) in the case of a street authority; that authority is deemed to have granted consent.
  • (7) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the entry onto, or possession of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

Felling or lopping of trees and removal of hedgerows

13

  • (1) The undertaker may fell or lop or cut back any roots of any tree or shrub near any part of the authorised development, if it reasonably believes it to be necessary to do so to prevent the tree or shrub from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development.
  • (2) In carrying out any activity authorised by paragraph (1), the undertaker must do no unnecessary damage to any tree or shrub and must pay compensation to any person for any loss or damage arising from such activity.
  • (3) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, must be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
  • (4) The undertaker may, for the purposes of carrying out the authorised development —
  • (a) remove the important hedgerows as are within the Order limits and specified in Schedule 5 (removal of important hedgerows); and
  • (b) without limitation on the scope of sub-paragraph (a), and with the consent of the local authority in whose area the hedgerow is located, remove or translocate any hedgerow within the Order limits.
  • (5) The grant of consent of a local authority in terms of paragraph (4)(b) must not be unreasonably withheld.
  • (6) If a local authority fails to notify the undertaker of its decision within 28 days of receiving an application for consent under paragraph (4)(b) the local authority is deemed to have granted consent.
  • (7) In this article “hedgerow” and “important hedgerow” have the same meaning as in the Hedgerow Regulations 1997[^f00020].

PART 4 — MISCELLANEOUS AND GENERAL

Application of landlord and tenant law

14

  • (1) This article applies to—
  • (a) any agreement for leasing to any person the whole or any part of the authorised development or the right to operate the same; and
  • (b) any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised development, or any part of it,

so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person’s use.

  • (2) No enactment or rule of law regulating the rights and obligations of landlords and tenants is to prejudice the operation of any agreement to which this article applies.
  • (3) Accordingly, no such enactment or rule of law is to apply in relation to the rights and obligations of the parties to any lease granted by or under any such agreement so as to—
  • (a) exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;
  • (b) confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or
  • (c) restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.

Procedure for Approvals and Protective Provisions

15

Schedule 3 (procedure for approvals under requirements) and Schedule 6 (protective provisions) of this Order have effect.

Planning permission

16

If planning permission is issued under the 1990 Act for development any part of which is within the Order limits following the publication of this Order that is—

  • (a) not itself a nationally significant infrastructure project under the 2008 Act or part of such a project; and
  • (b) required to complete or enable the construction, use or operation of the development authorised by this Order,

then the carrying out, use or operation of such development under the terms of the planning permission does not constitute a breach of the terms of this Order.

Defence to proceedings in respect of statutory nuisance

17

  • (1) Where proceedings are brought under section 82(1) of the Environmental Protection Act 1990[^f00021] (summary proceedings by person aggrieved by statutory nuisance) in relation to a nuisance falling within paragraphs (a), (c), (d), (e), (g) or (ga) of section 79(1) of that Act no order must be made, and no fine may be imposed, under section 82(2) of that Act if—
  • (a) the defendant shows that the nuisance—
  • (i) relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development and that the nuisance is attributable to the carrying out of the authorised development in accordance with a notice served under section 60 (control of noise on construction site), or a consent given under section 61 (prior consent for work on construction site) or 65 (noise exceeding registered level), of the Control of Pollution Act 1974[^f00022]; or
  • (ii) is a consequence of the construction or maintenance of the authorised development and that it cannot reasonably be avoided; or
  • (b) the defendant shows that the nuisance—
  • (i) relates to premises used by the undertaker for the purposes of or in connection with the use of the authorised development and that the nuisance is attributable to the use of the authorised development which is being used in accordance with Requirement 5; or
  • (ii) is a consequence of the use of the authorised development and that it cannot reasonably be avoided.
  • (2) Section 61(9) (consent for work on construction site to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the Control of Pollution Act 1974 and section 65(8) of that Act (corresponding provision in relation to consent for registered noise level to be exceeded), must not apply where any consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development.

Certification of plans etc

18

  • (1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of the following plans and documents—
  • (a) the access plan;
  • (b) the hedgerow plan;
  • (c) the works plan;
  • (d) the restoration profile contour plan;
  • (e) the restoration concept scheme; and
  • (f) the DEC

for certification that they are true copies of the documents referred to in this Order.

  • (2) A plan or document so certified will be admissible in any proceedings as evidence of the contents of the document of which it is a copy.

Service of Notices

19

  • (1) A notice or other document required or authorised to be served for the purposes of this Order may be served—
  • (a) by post;
  • (b) by delivering it to the person on whom it is to be served or to whom it is to be given or supplied; or
  • (c) with the consent of the recipient and subject to paragraphs (5) to (8) by electronic transmission.
  • (2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.
  • (3) For the purposes of section 7 (references to services by post) of the Interpretation Act 1978[^f00023] as it applies for the purposes of this article, the proper address of any person in relation to the service on that person of a notice or document under paragraph (1) is, if that person has given an address for service, that address, and otherwise—
  • (a) in the case of the secretary or clerk of a body corporate, the registered or principal office of that body; and
  • (b) in any other case, the last known address of that person at the time of service.
  • (4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having any interest in, or as the occupier of, land and the name or address of that person cannot be ascertained after reasonable enquiry, the notice may be served by—
  • (a) addressing it to that person by name or by the description of “owner”, or as the case may be “occupier”, of the land (describing it); and
  • (b) either leaving it in the hands of a person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.
  • (5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the Requirement will be taken to be fulfilled only where—
  • (a) the recipient of the notice or other document to be transmitted has given consent to the use of electronic transmission in writing or by electronic transmission;
  • (b) the notice or document is capable of being accessed by the recipient;
  • (c) the notice or document is legible in all material respects; and
  • (d) the notice or document is in a form sufficiently permanent to be used for subsequent reference.
  • (6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within 7 days of receipt that the recipient requires a paper copy of all or part of that notice or other document the sender will provide such a copy as soon as reasonably practicable.
  • (7) Any consent to the use of electronic communication given by a person may be revoked by that person in accordance with paragraph (8).
  • (8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—
  • (a) that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and
  • (b) such revocation will be final and will take effect on a date specified by the person in the notice but that date must not be less than 7 days after the date on which the notice is given.
  • (9) This article will not be taken to exclude the employment of any method of service not expressly provided for by it.
  • (10) In this article “legible in all material respects” means that the information contained in the notice or document is available to that person to no lesser extent than it would be if served, given or supplied by means of a notice or document in printed form.

Arbitration

20

  • (1) Any difference under any provision of this Order, unless otherwise provided for in this Order, must be referred to and settled in arbitration, by a single arbitrator to be agreed upon by the parties, within 14 days of receipt of the notice of arbitration, or if the parties fail to agree within the time period stipulated, to be appointed on application of either party (after giving written notice to the other) by the Secretary of State.
  • (2) Any matter for which the consent or approval of the Secretary of State is required under any provision of this Order will not be subject to arbitration.

SCHEDULE 1 — Authorised Development

A nationally significant infrastructure project as defined in section 14(1)(p) and 30 of the 2008 Act comprising—

Work No. 1– A hazardous waste landfill facility for the disposal at a direct input rate of up to 150,000 tonnes per annum of predominantly hazardous waste together with small quantities of low level waste on the areas identified on the works plan comprising-

Work No. 1A – the construction and filling of a landfill including -

  • (a) extraction and stockpiling of soil, clay and other suitable materials for engineering and restoration purposes and the exportation of some clay and other suitable materials;
  • (b) all other associated engineering works to construct the landfill phases including a leachate collection system;,
  • (c) a landfill gas pump and gas flare; and
  • (d) surface water management and pumping systems including ponds as needed.

Work No. 1B – the construction and filling of a landfill including -

  • (a) extraction and stockpiling of soil, clay and other suitable materials for engineering and restoration purposes and the exportation of some clay and other suitable materials;
  • (b) all other associated engineering works to construct the landfill phases including a leachate collection system; and
  • (c) surface water management and pumping systems including ponds as needed.

Work No. 2 – A hazardous waste facility, namely the alteration of an existing waste treatment and recovery facility with an increase from the capacity of 200,000tpa in the original order to a capacity of 250,000tpa of predominantly hazardous wastes including -

  • (a) a modular plant located on a concrete pad with associated enclosures or buildings, surface water drainage and collection;
  • (b) stocking areas, stocking bays with concrete walls and storage lagoons;
  • (c) process, reagent, acid waste, water or other liquid storage tanks;
  • (d) storage silos;
  • (e) feed hoppers;
  • (f) screens;
  • (g) conveyors;
  • (h) washing units;
  • (i) separators;
  • (j) mixing vessels;
  • (k) sedimentation units;
  • (l) bioremediation area;
  • (m) a mobile crusher on a campaign basis;
  • (n) open concrete lined settlement tanks;
  • (o) a process control office and staff welfare facilities; and
  • (p) bunded fuel storage tanks and an electricity generator in an insulated container.

Work No. 3 – the site reception area which will include -

  • (a) site access and surfaced access road;
  • (b) storage shed;
  • (c) laboratory;
  • (d) canteen, welfare facilities and offices;
  • (e) car parking area;
  • (f) weighbridge;
  • (g) wheel washing facilities;
  • (h) cess pit, and
  • (i) bunded fuel storage tanks.

Work No.4– the conversion of a culverted drain to an open watercourse with associated ecological works.

Work No. 5– the diversion of an overhead electricity cable.

And for the purposes of or in connection with the construction of Work No.1, Work No. 2 and Work No. 3 further development within the Order limits consisting of—

  • (a) monitoring bore holes;
  • (b) leachate storage tanks;
  • (c) bunded fuel storage tanks;
  • (d) security cameras;
  • (e) lighting;
  • (f) internal site roads; and
  • (g) hardstanding and bunding.

And for the purposes of or in connection with the construction of any of those works mentioned above further development within the Order limits consisting of—

  • (a) boundary fencing;
  • (b) surface water collection ponds;
  • (c) surface and foul water drainage;
  • (d) the restoration of the site including the creation of footpaths and tracks for public access and retention of the car parking area; and aftercare.

And for the purpose of or in connection with the construction of any of the works mentioned in this Schedule within the Order limits, any further development which does not give rise to any materially new or materially different environmental effects to those identified in the environmental statement.

SCHEDULE 2 — Requirements

Interpretation

1

In this Schedule—

  • archaeological mitigation strategy” means the strategy at Appendix DEC A of the DEC;
  • boundary design principles” means the principles set out in Appendix DEC B of the DEC;
  • dust management scheme” means the scheme at Appendix DEC H of the DEC;
  • ecological management, monitoring and aftercare plan” means the plan at Appendix DEC E of the DEC;
  • new works” means Work Nos. 1B, 4 and 5 for which development has not yet commenced at the date this Order takes effect;
  • noise and vibration management plan” means the plan at Appendix DEC L of the DEC;
  • operational site” means Work Nos. 1A, 2 and 3 which are consented under the original order.
  • phase” means the relevant phase referred to in the phasing sequence table;
  • phasing sequence table” means the table in Appendix DEC D of the DEC;
  • relevant parameters” means the parameters set out in Schedule 4 and in Appendix DEC C of the DEC;
  • soil handling and management scheme” means the scheme at Appendix DEC I of the DEC;
  • stockpile management scheme” means the scheme at Appendix DEC J of the DEC;
  • surface water management plan” means the plan at Appendix DEC F of the DEC;
  • traffic management plan” means the plan at Appendix DEC K of the DEC.

Time limits

2

The authorised development must commence within 5 years of the coming into force of this Order.

Detailed design

3

  • (1) The authorised development must be carried out in accordance with the following approved plans and schemes listed in this Requirement (except for minor amendments as approved in writing by the relevant planning authority)—
  • (a) the access plan;
  • (b) the works plan;
  • (c) the boundary design principles; and
  • (d) the surface water management plan.
  • (2) Subject to article 5, the finished ground level contours approved pursuant to Requirement 4(1)(f) must lie between the grey contours and the green contours shown on the restoration profile contour plan and in areas where no green contours are shown, the finished ground level contours must accord with the grey contours shown on the restoration profile contour plan.
  • (3) All parts of the authorised development comprised in Work No.2 and Work No. 3 must be constructed in accordance with the relevant parameters.
  • (4) Work No. 4 must be carried out in accordance with the details set out in the approved phasing, landscaping and restoration scheme submitted pursuant to Requirement 4.
  • (5) Development of the new works must not commence until a detailed drainage design in accordance with the surface water management plan has been submitted to and approved by the relevant planning authority following consultation with the Environment Agency.

Phasing, landscaping and restoration

4

  • (1) The authorised development must be carried out in accordance with the ecological management, monitoring and aftercare plan and the first stage of the phasing sequence table until the phasing, landscaping and restoration scheme is approved pursuant to sub-paragraph (2).
  • (2) Within 24 months of the date of this Order the undertaker must submit a phasing, landscaping and restoration scheme in accordance with the principles set out in the ecological management, monitoring and aftercare plan and the restoration concept scheme to the relevant planning authority for approval in writing following consultation with the Environment Agency.
  • (3) The phasing, landscaping and restoration scheme submitted must include details of phasing timescales and all proposed hard and soft landscaping works, ecological mitigation and enhancement measures including—
  • (a) a programme for the progressive filling, capping and phased restoration of the land including all landscaping, restoration and aftercare works which are in accordance with the phasing sequence table;
  • (b) a programme for review meetings;
  • (c) the location, number, species, size and planting density of any proposed planting;
  • (d) how any invasive species will be managed;
  • (e) soil testing and preparation, cultivation, importing of materials and other operations to maximise plant establishment;
  • (f) details of proposed finished ground level contours in accordance with Requirement 3(2);
  • (g) hard surfacing materials;
  • (h) vehicular and pedestrian access, parking and circulation areas;
  • (i) minor structures, such as furniture, refuse or other storage units, signs and lighting;
  • (j) proposed and existing functional services above and below ground, including drainage, power and communications cables and pipelines, manholes and supports;
  • (k) details of existing trees to be retained, with measures for their protection during the operations; and
  • (l) the location of fuel storage and leachate tanks, extraction and monitoring facilities and any other infrastructure required for the aftercare works.
  • (4) Not later than 24 months from the date the phasing, landscaping and restoration scheme is approved pursuant to sub-paragraph (1) and then again at least every two years from that date the undertaker must submit an updated phasing, landscaping and restoration scheme for approval in writing by the relevant planning authority and if necessary arrange a review meeting with the relevant planning authority to discuss any changes. The works must be undertaken in accordance with the extant phasing, landscaping and restoration scheme.
  • (5) Any tree or shrub planted as part of an approved landscaping and restoration scheme that, within a period of 10 years after planting, is removed, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted, unless otherwise approved in writing by the relevant planning authority.
  • (6) The undertaker must restore the site by 31 December 2046 at the latest and all landscaping, restoration and aftercare works must be carried out for a minimum period of 20 years thereafter in accordance with the extant phasing, landscaping and restoration scheme in place at the time those works are being carried out and to a reasonable standard in accordance with the relevant recommendations of appropriate British Standards or other recognised codes of good practice.
  • (7) The undertaker must provide public access to the authorised development in accordance with the details set out in the phasing, landscaping and restoration scheme.

Noise

5

The authorised development must be carried out, operated and maintained in accordance with the noise and vibration management plan.

Stockpiles and soil

6

  • (1) The stockpiles must be managed in accordance with the details set out in the stockpile management scheme during the operation of the authorised development.
  • (2) The authorised development must be carried out in accordance with the environmental commitments set out in the dust management scheme and soil handling and management scheme, which includes a bird hazard management plan.

Disposal of waste

7

No waste materials may be disposed of at the site other than hazardous wastes and low level waste together with suitable waste materials used for restoration purposes.

Quantities of waste

8

  • (1) The maximum quantities of waste that will be imported to the waste treatment and recovery facility per annum will be 250,000 tonnes and directly to the landfill will be 150,000 tonnes. The combined total amount of waste that can be imported to the site per annum must not exceed 300,000 tonnes.
  • (2) The total quantity of low level waste disposed of at the site in the period up to 31 December 2046 (or its earlier closure) must not exceed 448,000 tonnes in relation to Work No. 1A and 700,000 tonnes in relation to Work No. 1B.

Archaeological mitigation strategy

9

  • (1) The new works must be carried out, operated and maintained in accordance with the archaeological mitigation strategy.
  • (2) Development of the new works must not commence until a written scheme of investigation has been submitted to and approved in writing by the relevant planning authority and the investigation of the new works must be carried out in accordance with the approved written scheme of investigation.

Vehicular access

10

The only vehicular access for the authorised development permitted is by way of the existing access to the site on to the Stamford Road shown on the access plan.

Control of vehicular movements

11

Vehicular traffic associated with this authorised development must comply with the traffic management plan and be controlled as follows—

  • (a) The undertaker must direct that all heavy goods vehicles entering and leaving the site except local collections must travel direct to and from the A47 Trunk Road via Stamford Road north of the access point with no such vehicles travelling along Stamford Road towards King’s Cliffe village south of the site access point.
  • (b) Signs informing vehicle drivers of the Requirements in paragraph (a) above must be maintained in a visible location near to the egress on site.
  • (c) Facilities must be provided for site operatives within the site to observe the direction of vehicle entry to and exit from the site.

Site security

12

The site security measures including the 1.8m palisade fence around the gas compound must be maintained throughout the life of the operations at the site and beyond until the relevant planning authority, in consultation with the Environment Agency, determines and confirms in writing that the site security measures are no longer required and thereafter, any fences must be removed within a period of 3 months.

Wheel cleaning

13

Wheel cleaning facilities must be provided on the site with appropriate drainage and thereafter maintained to the satisfaction of the relevant planning authority. The wheels of all vehicles leaving the site must be cleansed of mud and other debris to prevent mud being carried onto the public highway. All vehicles transporting materials in connection with the authorised development must be adequately sheeted to the satisfaction of the relevant planning authority.

Hours of operation

14

  • (1) Except as may otherwise be approved in writing by the relevant planning authority in temporary limited circumstances, all waste treatment, waste disposal, site preparation, levelling and restoration operations and any associated activities must be restricted to between the hours of 07.00 and 18.00 on Mondays to Fridays and 07.00 and 13.00 on Saturdays, and subject to sub-paragraph (2), no such operations may be carried out on the site on Sundays or public holidays.
  • (2) On a public holiday between the hours of 07.00 and 18.00, the following activities may be carried out—
  • (a) the delivery of up to 20 loads a day of air pollution control residues;
  • (b) the processing in the waste treatment and recovery facility (Work No.2) of those residues; and
  • (c) the stockpiling and management of the processed residues within the waste treatment and recovery facility (Work No.2).
  • (3) For the purposes of this paragraph “public holiday” means Christmas Day, Good Friday or a day which under section 1 of the Banking and Financial Dealings Act 1971[^f00024] is a bank holiday in England.

Gas flare structures

15

Except in respect of minor amendments approved in writing by the relevant planning authority the height of—

  • (a) the gas compound fencing must not exceed 1.8m above existing ground level;
  • (b) any building, plant, machinery, foundation, hardstanding, roadway, bunding, structure or erection in the nature of plant or machinery used in connection with the gas flare and pumping station must not exceed 2m above existing ground level; and
  • (c) any gas flare flue must not exceed 10m above existing ground level.

Floodlighting

16

  • (1) All floodlighting including mobile units must be directed towards the ground to minimise light spillage from the site and except for emergencies will only be operating within the hours of operation specified in Requirement 14.
  • (2) No additional permanent or temporary floodlighting must be installed at the site, until after consultation with the relevant planning authority, and a written scheme for the management and mitigation of artificial light emissions has been submitted to and approved in writing by the relevant planning authority.

Cessation of development

17

The landfilling of waste and the operation of the waste treatment and recovery facility hereby permitted must cease not later than 31 December 2046 by which time the land and the access must be restored or reinstated in accordance with the Requirements of this Order.

Removal of plant and machinery

18

Except to the extent required for aftercare purposes as approved pursuant to the phasing, landscaping and restoration scheme under Requirement 4, any building, plant, machinery, foundation, hardstanding, roadway, structure or erection in the nature of plant or machinery used in connection with the authorised development must be removed from the site when they are respectively no longer required for the purpose for which they were installed and in any case not later than 31 December 2046 upon completion of the aftercare of the site.

Amendments to approved details

19

Where any Requirement requires the authorised development to be carried out in accordance with the details approved by the relevant planning authority, the approved details must be taken to include any amendments that may subsequently be approved in writing by the relevant planning authority.

SCHEDULE 3 — Procedure for approvals under requirements

1

In this Schedule

  • discharging authority” means the relevant planning authority.

Applications made under Requirements

2

This Schedule applies to an application made by the undertaker to a discharging authority for any consent, agreement or approval under a Requirement.

Decision Period

3

  • (1) The discharging authority must give written notice to the undertaker of its decision on the application before the end of the decision period.
  • (2) In sub-paragraph (1), “the decision period” means—
  • (a) where the discharging authority does not give written notice under paragraph 4(1) or 4(2) requiring further information, the period of eight weeks from the later of
  • (i) the day immediately following the day on which the authority receives the application, and
  • (ii) the day on which the authority receives the fee payable under paragraph 5; or
  • (b) where the discharging authority gives written notice under paragraph 4(1) or 4(2) requiring further information, the period of eight weeks from the day immediately following the day on which the undertaker provides the further information; or
  • (c) such longer period as may be agreed in writing by the undertaker and the discharging authority.

Further Information

4

  • (1) If the discharging authority considers that it requires further information to make a decision on the application, it must give written notice to the undertaker specifying the further information required within seven business days from the day on which it receives the application.
  • (2) If the relevant Requirement requires that discharging authority to consult a person (referred to in this Schedule as a “consultee”) in relation to the application—
  • (a) the discharging authority must consult the consultee within five business days from the day on which it receives the application;
  • (b) if the consultee considers that it requires further information to respond to the consultation, it must so notify the discharging authority, specifying what further information is required, within 21 business days from the day on which the discharging authority received the application; and
  • (c) within five business days from the day on which it receives any such notification from the consultee, the discharging authority must give written notice to the undertaker specifying the further information required by the consultee.
  • (3) If the discharging authority, after consultation with any consultee, considers that further information provided by the undertaker in response to a written notice from the discharging authority under sub-paragraph (1) or (2) is not sufficient to allow it to make a decision on the application, it must give written notice to the undertaker specifying what further information is still required, within seven business days from the day on which the undertaker provided the information.
  • (4) If the discharging authority does not give written notice in accordance with sub-paragraph (1), (2) or (3), it is not entitled to request any additional information in relation to the application without the prior agreement in writing of the undertaker.

Fees

5

  • (1) The undertaker must pay the authority a fee of £116, or such greater fee as for the time being is payable to the authority in respect of an application for the discharge of a condition imposed on a grant of planning permission, in respect of each application.
  • (2) The authority must refund the fee paid under sub-paragraph (1) to the undertaker, within the relevant period, if it—
  • (a) rejects the application as being invalidly made;
  • (b) fails to give the written notice required by paragraph 3(1).
  • (3) Sub-paragraph (2) does not apply if, within the relevant period, the undertaker agrees in writing that the authority may retain the fee paid and credit it in respect of a future application.
  • (4) In sub-paragraphs (2) and (3)the relevant period” means the period of eight weeks from, as the case may be—
  • (a) the day on which the authority rejects the application as being invalidly made;
  • (b) the day after the day on which the decision period expires.

Appeal to the Secretary of State (procedure)

6

  • (1) The undertaker may appeal to the Secretary of State against—
  • (a) the discharging authority’s refusal of an application;
  • (b) the discharging authority’s grant subject to conditions of an application;
  • (c) the discharging authority’s failure to give the written notice required by paragraph 3(1);
  • (d) a written notice given by the discharging authority under paragraph 4(1), 4(2) or 4(3).
  • (2) In order to appeal, the undertaker must, within 10 business days from the relevant day, send the Secretary of State the following documents—
  • (a) its grounds of appeal;
  • (b) a copy of the application submitted to the authority;
  • (c) any supporting documentation which it wishes to provide.
  • (3) In sub-paragraph (2), “the relevant day” means—
  • (a) in the case of an appeal under sub-paragraph (1)(a) or (1)(b), the day on which the undertaker is notified by the authority of its decision;
  • (b) in the case of an appeal under sub-paragraph (c), the day after the day on which the decision period expires;
  • (c) in the case of an appeal under sub-paragraph (1)(d), the day on which the undertaker receives the authority’s notice.
  • (4) At the same time as it sends the documents mentioned in sub-paragraph (2) to the Secretary of State, the undertaker must send copies of those documents to the authority and any consultee.
  • (5) As soon as reasonably practicable following receipt of the documents mentioned in sub-paragraph (2), the Secretary of State must—
  • (a) appoint a person (referred to in this Schedule as “the appointed person”) to determine the appeal on his behalf;
  • (b) give written notice to the undertaker, the authority and any consultee of the appointment and of the appointed person’s address for correspondence in relation to the appeal.
  • (6) Within 20 business days from the day on which the Secretary of State gives notice under sub-paragraph (5)(b), the authority and any consultee—
  • (a) may submit written representations in respect of the appeal to the appointed person; and
  • (b) must, at the same time, send a copy of any such representations to the undertaker and (if applicable) to each other.
  • (7) Within 10 business days from the last day on which representations are submitted to the appointed person under sub-paragraph (6), any party—
  • (a) may make further representations to the appointed person in response to the representations of another party; and
  • (b) must, at the same time, send a copy of any such further representations to each other party.

Appeal to the Secretary of State (powers of the appointed person)

7

  • (1) The appointed person may—
  • (a) allow or dismiss the appeal;
  • (b) reverse or vary any part of the authority’s decision, irrespective of whether the appeal relates to that part;
  • (c) make a decision on the application as if it had been made to the appointed person in the first instance.
  • (2) The appointed person—
  • (a) if he considers that he requires further information to make a decision on the appeal, may by written notice require any party to provide such further information to him and to each other party by a specified date;
  • (b) if he gives such a notice, must—
  • (i) at the same time send a copy of it to each other party, and
  • (ii) allow each party to make further representations in relation to any further information provided in response to the notice, within 10 business days from the day on which it is provided.
  • (3) The appointed person may waive or extend any time limit (including after it has expired) for the provision of representations or information in relation to an appeal.

Appeal to the Secretary of State (supplementary)

8

  • (1) The decision of the appointed person on an appeal may not be challenged except by proceedings for judicial review.
  • (2) If the appointed person grants approval of an application, that approval is to be taken as if it were an approval granted by the authority in relation to the application.
  • (3) Subject to sub-paragraph (4), the undertaker must pay the reasonable costs of the appointed person incurred in deciding the appeal.
  • (4) On written application by the authority or the undertaker, the appointed person may make a direction as to the costs of the parties to the appeal and of the appointed person, including imposing an obligation on any party to pay all or part of such costs to the party which incurred them.
  • (5) In considering an application under sub-paragraph (4) the appointed person must have regard to the National Planning Practice Guidance: Advice on planning appeals and the award costs or any circular or guidance which may from time to time replace it.

SCHEDULE 4 — Design parameters

(1) Component (2) Maximum dimensions
Any plant or buildings in Work No. 2 15m high
Any plant in Work No. 3 7.4m high
Any buildings in Work No. 3 (excluding the storage shed) 3.6m high
Work No. 3(b), the storage shed 8m high
Any buildings in Work No. 3 36.5m x 10.5m

SCHEDULE 5 — Removal of important hedgerows

(1) Location of hedgerow (2) Work to be carried out (3) Relevant part of the authorised development
H02 shown on the hedgerow plan Removal Work No. 1B
H03 shown on the hedgerow plan Removal Work No.1B

SCHEDULE 6 — Protective Provisions

PART 1 — For the protection of Anglian Water Services Limited

Application

1

For the protection of Anglian Water the following provisions have effect, unless otherwise agreed in writing between the undertaker and Anglian Water.

Interpretation

2

In this Part of this Schedule—

  • Act” means the Water Industry Act 1991;
  • alternative apparatus” means alternative apparatus adequate to enable Anglian Water to fulfil its statutory functions in a manner no less efficient than previously;
  • Anglian Water” means Anglian Water Services Limited;
  • apparatus” means Anglian Water’s twin water mains running between Stamford Road, King’s Cliffe (at grid references TL0130899796 and TL0131499784 or thereabouts) and A43, Duddington (at grid references SK9888300433 and SK9888000429 or thereabouts, respectively) and includes: any accessories (as defined by section 219 of the Act) forming part of it; any structure in which apparatus is or is to be lodged or which gives or will give access to it; and alternative apparatus;
  • functions” includes powers and duties;
  • “in”, in a context referring to apparatus or alternative apparatus in land, includes a reference to apparatus or alternative apparatus under, over or upon land;
  • plan” includes all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the works to be executed;

Acquisition of land

3

Regardless of any provision in this Order, the undertaker must not acquire any apparatus otherwise than by agreement.

Retained apparatus

4

  • (1) Not less than 28 days before starting the execution of any works in, on or under any land purchased, held, appropriated or used under this Order that are near to, or will or may affect, any apparatus (or any means of access to it) the removal of which has not been required by the undertaker in accordance with section 185 of the Act, the undertaker must submit to Anglian Water a plan of the works to be executed.
  • (2) Those works must be executed only (i) if approved by Anglian Water pursuant to sub-paragraph (3) below, (ii) in accordance with the plan submitted under sub-paragraph (1) and (iii) in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by Anglian Water for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and Anglian Water is entitled to watch and inspect the execution of those works.
  • (3) Any requirements made by Anglian Water under sub-paragraph (2) must be made within a period of 21 days beginning with the date on which a plan under sub-paragraph (1) is submitted to it. The approval that may be given under that sub-paragraph must not be unreasonably withheld (although may be subject to the said requirements) and must be assumed to have been given unless Anglian Water gives written notice to the undertaker that it is being withheld entirely or given subject to the said requirements within the same time period.
  • (4) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan instead of the plan previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.
  • (5) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case must give to Anglian Water notice as soon as is reasonably practicable and a plan of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (3) in so far as is reasonably practicable in the circumstances, using its best endeavours to keep the impact of those emergency works on Anglian Water’s apparatus, on the operation of its water and sewerage network and on end-users of the services Anglian Water provides to a minimum.
  • (6) For the purposes of sub-paragraph (1) and without prejudice to the generality of the principles set out in that sub-paragraph—
  • (a) the establishment of an access way or haul road and underground works are both deemed to be “works” for the purposes of this paragraph; and
  • (b) works are deemed to be in land near Anglian Water’s apparatus if those works fall within 20 metres measured from the medial line of the closer of the two water mains forming such apparatus to the works in question.

Expenses and costs

5

  • (1) Subject to the following provisions of this paragraph, the undertaker must repay to Anglian Water all expenses reasonably incurred by Anglian Water in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to in this Part of this Schedule.
  • (2) There must be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule that value being calculated after removal.
  • (3) If in accordance with the provisions of this Part of this Schedule—
  • (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
  • (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated, and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 20 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to Anglian Water by virtue of sub-paragraph (1) must be reduced by the amount of that excess.
  • (4) For the purposes of sub-paragraph (3)
  • (a) an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
  • (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.

6

  • (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of—
  • (a) the construction of any works of authorised development for which development consent is granted by this Order;
  • (b) any subsidence resulting from such works or development; or
  • (c) any leakage, leachate or radiation resulting from such works or development;

any contamination or damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works), any medium conveyed by such apparatus or any property of Anglian Water, or there is any interruption in any service provided, or in the supply of any goods, by Anglian Water, the undertaker must—

  • (a) bear and pay the cost reasonably incurred by Anglian Water in making good such damage or restoring the supply; and
  • (b) make reasonable compensation to Anglian Water for any other expenses, loss, damages, penalty (whether legal, regulatory or in relation to regulatory funding) or costs incurred by the undertaker;

by reason or in consequence of any such damage or interruption.

  • (2) The fact that any act or thing may have been done by Anglian Water on behalf of the undertaker or in accordance with a plan approved by Anglian Water or in accordance with any requirement of Anglian Water or under its supervision does not, subject to sub-paragraph (3), excuse the undertaker from liability under the provisions of sub-paragraph (1) unless Anglian Water fails to carry out and execute the works properly with due care and attention and in a skilful and professional like manner or in a manner that does not accord with the approved plan.
  • (3) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to:
  • (a) any damage or interruption to the extent that it is attributable to the unlawful or unreasonable act, neglect or default of Anglian Water, its officers, servants, contractors or agents;
  • (b) any part of the authorised development carried out by Anglian Water in the exercise of any functions conferred by this Order pursuant to a transfer of benefit under article 7; or
  • (c) any indirect or consequential loss of any third party (including but not limited to loss of use, revenue, profit, contract, production, increased cost of working) arising from any such damage or interruption, which is not reasonably foreseeable.
  • (4) Anglian Water must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made, without the consent of the undertaker (such consent not to be unreasonably withheld or delayed) who, if withholding such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
  • (5) Anglian Water must act reasonably in relation to any claim or demand served under sub-paragraph (1) and use its reasonable endeavours to mitigate and to minimise any costs, expenses, loss, demands and penalties to which a claim or demand under sub-paragraph (1) applies.

Cooperation

7

  • (1) Where in consequence of the proposed construction of any of the authorised development, Anglian Water makes requirements for the protection or alteration of apparatus under paragraph 4, the undertaker must use all reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of Anglian Water’s undertaking, using existing processes where requested by Anglian Water, provided it is appropriate to do so, and Anglian Water must use all reasonable endeavours to co-operate with the undertaker for that purpose.
  • (2) Where the undertaker identifies any apparatus which may belong to or be maintainable by Anglian Water but which does not appear on any statutory map kept for the purpose by Anglian Water, it must inform Anglian Water of the existence and location of the apparatus as soon as reasonably practicable.
  • (3) Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and Anglian Water in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
  • (4) The undertaker and Anglian Water may by written agreement substitute any period of time for those periods set out in this Part of this Schedule.

Monitoring

8

  • (1) Where in relation to the proposed construction of any of the authorised development, Anglian Water reasonably requires leak detection monitoring and/or monitoring of the water level in the pipe bedding material to be installed (“pipe bedding monitoring”), and gives written notice to the undertaker of that requirement, the following provisions of this paragraph apply—
  • (a) Any leak detection monitoring and pipe bedding monitoring to be installed in land of the undertaker under this Part of this Schedule must be constructed in such manner and in such situation as may be agreed between Anglian Water and the undertaker or in default of agreement settled by arbitration in accordance with article 20 (arbitration).
  • (b) Anglian Water must, after the leak detection monitoring and pipe bedding monitoring to be installed has been agreed or settled by arbitration in accordance with article 20, and after the grant to Anglian Water of any such necessary facilities and rights over the land, proceed without unnecessary delay to construct and bring into operation the agreed leak detection monitoring and pipe bedding monitoring.
  • (c) The undertaker must repay to Anglian Water all expenses reasonably incurred by Anglian Water in, or in connection with, the installation of any leak detection and pipe bedding monitoring apparatus.
  • (d) If Anglian Water gives notice in writing to the undertaker that it desires the undertaker to execute any work, or part of any work in connection with the installation of leak detection or pipe bedding monitoring apparatus or the undertaker and Anglian Water otherwise agree, that work, instead of being executed by Anglian Water, must be executed by the undertaker without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of Anglian Water at the cost of the undertaker.
  • (e) Anglian Water must share all monitoring data arising from the installation of the leak detection monitoring and pipe bedding monitoring with the undertaker on a quarterly basis.

Expert Determination

9

  • (1) Article 20 (arbitration) must apply to any difference as to the legal interpretation of this Schedule and as provided for in paragraph 4(3).
  • (2) Save as provided for in sub–paragraph (1) or sub–paragraph 4(3) any difference under this Part of this Schedule must be referred to and settled by a single independent and suitable person who holds appropriate professional qualifications and is a member of a professional body relevant to the matter in dispute acting as an expert, such person to be agreed by the differing parties or, in the absence of agreement, identified by the President of the Institution of Civil Engineers or the President of the Institution of RICS or the President of the Institution of Engineering and Technology (as relevant and agreed between Anglian Water and the undertaker, both acting reasonably and without delay).
  • (3) All parties involved in settling any difference must use best endeavours to do so within 14 days from the date of a dispute first being notified in writing by one party to the other and in the absence of the difference being settled within that period the expert must be appointed within 21 days of the notification of the dispute.
  • (4) The costs and fees of the expert and the costs of Anglian Water and the undertaker are payable by the parties in such proportions as the expert may determine. In the absence of such determination the costs and fees of the expert are payable equally by the parties who must each bear their own costs.
  • (5) The expert must—
  • (a) invite the parties to make submission to the expert in writing and copied to the other party to be received by the expert within 14 days of the expert’s appointment;
  • (b) permit a party to comment on the submissions made by the other party within 7 days of receipt of the submission;
  • (c) issue a decision within 14 days of receipt of the submissions under sub-paragraph (b); and
  • (d) give reasons for the decision.
  • (6) The expert must consider where relevant—
  • (a) the development outcome sought by the undertaker;
  • (b) the ability of the undertaker to achieve its outcome in a timely and cost-effective manner;
  • (c) the nature of the power sought to be exercised by the undertaker;
  • (d) the effectiveness, cost and reasonableness of proposals for mitigation arising from any party;
  • (e) Anglian Water’s service obligations and licence conditions; and
  • (f) any other important and relevant consideration.
  • (7) Any determination by the expert is final and binding, except in the case of manifest error in which case the difference that has been subject to expert determination may be referred to and settled by arbitration under article 20.

PART 2 — For the protection of Western Power Distribution (East Midlands) Plc

Application

10

For the protection of Western Power Distribution (East Midlands) plc the following provisions, unless otherwise agreed in writing between the undertaker and Western Power Distribution (East Midlands) plc, have effect.

Interpretation

11

In this Part of this Schedule—

  • alternative apparatus” means alternative apparatus adequate to enable WPD to fulfil its statutory functions in a manner not less efficient than previously and where the context requires includes any part of such alternative apparatus;
  • alternative rights” means all and any necessary legal easements, leases, consents, or permissions required by WPD in order to permit or authorise a diversion and to permit or authorise WPD to lay, keep, operate, maintain, adjust, repair, alter, relay, renew, supplement, inspect, examine, test and remove the alternative apparatus;
  • apparatus” means electric lines or electrical plant as defined in the Electricity Act 1989[^f00025], belonging to or maintained by WPD;
  • diversion” means an alteration to the WPD Network in order to enable or facilitate the authorised development;
  • functions” includes powers and duties;
  • “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over or upon land;
  • “plan” or “plans” includes all designs, drawings, specifications, method statements, programmes, calculations, risk assessments and other documents that are reasonably necessary to properly and sufficiently describe and assess the works to be executed;
  • specified work” means so much of any of the authorised development that is carried out within 6 metres of any apparatus;
  • undertaker” means Augean South Ltd (Company No. 04636789) or such other person as has the benefit of this Order;
  • Order land” means any land within the Order limits as defined in Article 2 (1) of this Order;
  • WPD” means Western Power Distribution (East Midlands) plc (company number 02366923) whose registered office is at Avonbank, Feeder Road, Bristol, BS2 0TB;
  • WPD Network” means WPD’s distribution network operated pursuant to its distribution licence issued pursuant to section 6 of the 1989 Act; and other terms have the meaning given in article 2 (interpretation).

Precedence of 1991 Act in respect of apparatus in streets

12

This Part of this Schedule does not apply to apparatus in respect of which the relations between the undertaker and WPD are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act.

No acquisition except by agreement

13

Regardless of any provision in this Order, the undertaker must not acquire any apparatus otherwise than by agreement.

Removal of apparatus

14

  • (1) If, in the exercise of the powers conferred by this Order, the undertaker requires that apparatus is relocated or diverted, that apparatus must not be removed under this Part of this Schedule and any right of WPD to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed, alternative rights acquired or granted for the alternative apparatus and the alternative apparatus is in operation and access to it has been provided if necessary to the reasonable satisfaction of WPD in accordance with sub-paragraphs (2) to (10) or with such alternative or supplementary provisions as the undertaker and WPD may agree between them.
  • (2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to WPD written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed.
  • (3) If as a direct consequence of the exercise of any of the powers conferred by this Order WPD reasonably needs to remove or divert any of its apparatus and the removal of that apparatus has not been required by the undertaker under sub-paragraph (2) then WPD must give to the undertaker written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and this Part has effect as if the removal or diversion of such apparatus had been required by the undertaker under sub-paragraph (2).
  • (4) If as a direct consequence of the removal or diversion of apparatus under sub-paragraph (2) or (3) alternative apparatus is to be constructed in land owned or controlled by the undertaker then the undertaker must afford to WPD the necessary facilities alternative rights and any necessary third party consent or approvals for the construction of alternative apparatus in the other land owned or controlled by the undertaker.
  • (5) If the undertaker or WPD requires to remove or divert any apparatus placed within the Order land and alternative apparatus is to be constructed in land not owned or controlled by the undertaker as a consequence of the removal or diversion of apparatus then WPD must use its reasonable endeavours to obtain alternative rights in the land in which the alternative apparatus is to be constructed.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.