The Boston Alternative Energy Facility Order 2023
- (d) provision requiring the undertaker to take noise measurements as soon as possible following a reasonable request by the relevant planning authority and to submit the measurements to the relevant planning authority as soon as they are available; and
- (e) a definition of the circumstances that constitute an emergency for the purposes of sub-paragraphs (2)(a), (3) and (5).
- (2) The level of noise at each monitoring location must not exceed the maximum permitted level specified for that location in the scheme, except—
- (a) in the case of an emergency (as defined in the noise monitoring scheme);
- (b) with the prior approval of the relevant planning authority; or
- (c) as a result of steam purging or the operation of emergency pressure relief valves or similar equipment of which the undertaker has given notice in accordance with sub–paragraph (3).
- (3) Except in the case of an emergency, the undertaker must give the relevant planning authority 48 hours’ notice of any proposed steam purging or operation of emergency pressure relief valves or similar equipment.
- (4) So far as reasonably practicable, steam purging and the operation of emergency pressure relief valves or similar equipment may only take place—
- (a) between 0900 and 1700 hours on weekdays (excluding bank holidays); and
- (b) between 0900 and 1300 hours on Saturdays (excluding bank holidays).
- (5) Where the level of noise at a monitoring location exceeds the maximum permitted level specified for that location in the approved scheme because of an emergency—
- (a) the undertaker must, as soon as possible and in any event within two business days of the beginning of the emergency, submit to the relevant planning authority a statement detailing—
- (i) the nature of the emergency;
- (ii) why it is necessary for the level of noise to have exceeded the maximum permitted level;
- (b) if the undertaker expects the emergency to last for more than 24 hours, it must inform local residents and businesses affected by the level of noise at that location of—
- (i) the reasons for the emergency; and
- (ii) how long it expects the emergency to last.
Notice of start of commissioning and notice of date of final commissioning
20
- (1) Where practicable, notice of the intended start of commissioning of Work No.1A must be given to the relevant planning authorities prior to such start and in any event within seven days from the date that commissioning is started.
- (2) Within seven days of completing final commissioning of Work No. 1A, the undertaker must provide the relevant planning authorities with notice of the date upon which such commissioning was duly completed.
Combined heat and power
21
- (1) On the date that is 12 months after the date of final commissioning for Work No. 1A, the undertaker must submit to the relevant planning authority for its approval, following consultation with Boston Borough Council, a report (“the CHP review”) updating the combined heat and power assessment.
- (2) The CHP review submitted and approved must—
- (a) consider whether opportunities reasonably exist for the export of heat from numbered Work 1A; and
- (b) include a list of actions (if any) that the undertaker is reasonably required to take (without material additional cost to the undertaker) to increase the potential for the export of heat from Work No. 1A.
- (3) The undertaker must take such actions as are included, within the timescales specified, in the approved CHP review.
- (4) On each date during the operation of Work No. 1A that is five years after the date on which it last submitted the CHP review or a revised CHP review to the relevant planning authority, a revised CHP review must be submitted to and approved by the relevant planning authority, following consultation with Boston Borough Council.
- (5) Sub-paragraphs (2) and (3) apply in relation to a revised CHP review submitted under sub-paragraph (4) in the same way as they apply in relation to the CHP review submitted under sub-paragraph (1).
Decommissioning
22
- (1) Within 24 months of the permanent cessation of the operation of Work Nos. 1 and 2 details of a scheme for the restoration and aftercare of the land for Work Nos. 1. 2, 3, 4 (excluding any parts of Work No. 4 that are covered by the decommissioning scheme approved under the deemed marine licence), 5 and 6 must be submitted to and approved by the relevant planning authority.
- (2) The scheme must include details of structures and buildings to be demolished or retained, details of the means of removal of materials following demolition, phasing of demolition and removal, details of restoration works and phasing thereof.
- (3) The scheme as approved under sub-paragraph (1) must be implemented in accordance with the phasing set out therein.
Amendments to approved details
23
- (1) With respect to the documents certified under article 47 (certification of documents, etc.), the parameters specified in the table in paragraph 5 of this Schedule and any other plans, details or schemes which require approval by the relevant planning authority pursuant to any requirement (together “Approved Documents, Plans, Parameters, Details or Schemes”), the undertaker may submit to the relevant planning authority for approval, following consultation by the undertaker with Lincolnshire County Council, any amendments to the Approved Documents, Plans, Parameters, Details or Schemes and following any such approval by the relevant planning authority the Approved Documents, Plans, Parameters, Details or Schemes are to be taken to include the amendments approved by the relevant planning authority in accordance with this paragraph.
- (2) Approval under sub-paragraph (1) for the amendments to Approved Documents, Plans, Parameters, Details or Schemes must not be given except where it has been demonstrated to the satisfaction of the relevant planning authority that the subject matter of the approval sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
Electricity generation cap
24
- (1) The authorised development must not generate more than 300 megawatts unless otherwise agreed by the relevant planning authority provided that the relevant planning authority is satisfied, following consultation with the relevant statutory nature conservation body to the extent that it relates to matters relevant to its functions, that any increase would not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.
- (2) The undertaker must keep records for the purpose of demonstrating compliance with sub-paragraph (1) and must submit them to the relevant planning authority on an annual basis.
- (3) On receipt of a written request to view the records by the relevant planning authority these records must be made available for inspection within seven days of such a request.
- (4) References in Schedule 1 (authorised development) to 300 megawatts are to be construed as references to any electricity cap approved under sub-paragraph (1).
Tonnage caps
25
- (1) The total amount of—
- (a) waste derived fuel received at Work No. 1A and Work No. 4 must not exceed 1,200,000 tonnes per calendar year;
- (b) bottom ash and boiler ash processed at Work No. 1B must not exceed 200,000 tonnes per calendar year; and
- (c) aggregate to be processed at Work No. 2 and received at Work No. 4 must not exceed 300,000 tonnes per calendar year,
unless otherwise agreed by the relevant planning authority provided that the relevant planning authority is satisfied, following consultation with the relevant statutory nature conservation body to the extent that it relates to matters relevant to its functions, that any increase would not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.
- (2) The undertaker must keep records for the purpose of demonstrating compliance with sub-paragraph (1) and must submit them to the relevant planning authority on an annual basis.
- (3) On receipt of a written request to view the records by the relevant planning authority these records must be made available for inspection within seven days of such a request.
- (4) References in Schedule 1 (authorised development) to any tonnage amount are to be construed as references to any tonnage amount approved under sub-paragraph (1).
PART 2 — PROCEDURE FOR DISCHARGE OF REQUIREMENTS
Applications made under Part 1
26
- (1) Where an application has been made to a relevant planning authority for any consent, agreement or approval required by a requirement (including consent, agreement or approval in respect of part of a requirement) included in this Order, the relevant planning authority must give notice to the undertaker of its decision on the application within a period of eight weeks beginning with—
- (a) the day immediately following that on which the application is received by the relevant planning authority;
- (b) the day immediately following that on which further information has been supplied by the undertaker under paragraph 27 (further information); or
- (c) such longer period as may be agreed between the parties.
- (2) Subject to sub-paragraph (3), in the event that the relevant planning authority does not determine an application within the period set out in sub-paragraph (1), the relevant planning authority is taken to have granted all parts of the application (without any condition or qualification) at the end of that period.
- (3) In determining any application made to the relevant planning authority for any consent, agreement or approval required by a requirement contained in Part 1 of this Schedule, the relevant planning authority may—
- (a) give or refuse its consent, agreement or approval; or
- (b) give its consent, agreement or approval subject to reasonable conditions,
and where consent, agreement or approval is refused or granted subject to conditions the relevant planning authority must provide its reasons for that decision with the notice of its decision.
Further information
27
- (1) In relation to any part of an application made under this Schedule, the relevant planning authority has the right to request such further information from the undertaker as it considers necessary to enable it to consider the application.
- (2) If the relevant planning authority considers that further information is necessary and the requirement concerned contained in Part 2 of this Schedule does not specify that consultation with a consultee is required, the relevant planning authority must, within ten business days of receipt of the application, notify the undertaker in writing specifying the further information required.
- (3) If the requirement concerned contained in Part 1 of this Schedule specifies that consultation with a consultee is required, the relevant planning authority must issue the consultation to the consultee within five business days of receipt of the application, and notify the undertaker in writing specifying any further information requested by the consultee within five business days of receipt of such a request.
- (4) If the relevant planning authority does not give the notification within the period specified in sub-paragraph (2) or (3) it (and the consultee, as the case may be) it is deemed to have sufficient information to consider the application and is not entitled to request further information without the prior agreement of the undertaker.
Fees
28
- (1) Where an application is made to the relevant planning authority for written consent, agreement or approval in respect of a requirement, the fee prescribed under regulation 16(1)(b) of the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 201272 (as may be amended or replaced from time to time A) is to apply and must be paid to the relevant planning authority for each application.
- (2) Any fee paid under this Schedule must be refunded to the undertaker within four weeks of—
- (a) the application being rejected as invalidly made; or
- (b) the relevant planning authority failing to determine the application within the decision period as determined under paragraph 26(1),
unless within that period the undertaker agrees, in writing, that the fee is to be retained by the relevant planning authority and credited in respect of a future application.
Register of requirements
29
- (1) The undertaker must, as soon as practicable following the making of this Order, establish and maintain in an electronic form suitable for inspection by members of the public a register of those requirements contained in Part 1 of this Schedule that provide for further approvals to be given by the relevant planning authority.
- (2) The register must set out in relation to each such requirement the status of the requirement, in terms of whether any approval to be given by the relevant planning authority has been applied for or given, providing an electronic link to any document containing any approved details.
- (3) The register must be maintained by the undertaker for a period of 3 years following completion of the authorised development.
Appeals to the Secretary of State
30
- (1) The undertaker may appeal to the Secretary of State if—
- (a) the relevant planning authority refuses an application for any consent, agreement or approval required by—
- (i) a requirement and any document referred to in any requirement in Part 1 of this Schedule; or
- (ii) any other consent, agreement or approval required under this Order, or grants it subject to conditions to which the undertaker objects;
- (b) the relevant authority does not give notice of its decision to the undertaker within the period specified in paragraph 26(1) or grants it subject to conditions;
- (c) having received a request for further information under paragraph 27(1) the undertaker considers that either the whole or part of the specified information requested by the relevant planning authority is not necessary for consideration of the application;
- (d) having received any further information requested, the relevant authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application; or
- (e) the relevant planning authority issues a notice further to sections 60 or 61 of the Control of Pollution Act 197473.
- (2) The appeal process applicable under sub-paragraph (1) is as follows—
- (a) any appeal by the undertaker must be made within 42 days of the date of the notice of the decision or determination, or (where no determination has been made) the expiry of the decision period as determined under paragraph 26;
- (b) the undertaker must submit to the Secretary of State a copy of the application submitted to the relevant planning authority and any supporting documents which the undertaker may wish to provide (“the appeal documents”);
- (c) the undertaker must on the same day provide copies of the appeal documents to the relevant planning authority and the requirement consultee (if applicable);
- (d) as soon as is practicable after receiving the appeal documentation, the Secretary of State must appoint a person to consider the appeal (“the appointed person”) and must notify the appeal parties of the identity of the appointed person and the address to which all correspondence for their attention should be sent;
- (e) the relevant planning authority and the requirement consultee (if applicable) must submit any written representations in respect of the appeal to the appointed person within 10 business days beginning with the first day immediately following the date on which the appeal parties are notified of the appointment of the appointed person and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;
- (f) the appeal parties must make any counter-submissions to the appointed person within 10 business days beginning with the first day immediately following the date of receipt of written representations pursuant to sub-paragraph (e); and
- (g) the appointed person must make a decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable.
- (3) In the event that the appointed person considers that further information is necessary to enable the appointed person to consider the appeal, the appointed person must as soon as practicable notify the appeal parties in writing specifying the further information required, the appeal party from whom the information is sought, and the date by which the information is to be submitted.
- (4) Any further information required under sub-paragraph (3) must be provided by the party from whom the information is sought to the appointed person and to other appeal parties by the date specified by the appointed person.
- (5) The appeal parties may submit written representations to the appointed person concerning matters contained in the further information.
- (6) Any such representations must be submitted to the appointed person and made available to all appeal parties within 10 business days of the date mentioned in sub-paragraph (3).
- (7) On an appeal under this paragraph, the appointed person may—
- (a) allow or dismiss the appeal; or
- (b) reverse or vary any part of the decision of the relevant planning authority (whether the appeal relates to that part of it or not) and may deal with the application as if it had been made to the appointed person in the first instance.
- (8) The appointed person may proceed to a decision on an appeal taking into account such written representations as have been sent within the relevant time limits and in the sole discretion of the appointed person such written representations as have been sent outside the relevant time limits.
- (9) The appointed person may proceed to a decision even though no written representations have been made within the relevant time limits, if it appears to the appointed person that there is sufficient material to enable a decision to be made on the merits of the case.
- (10) The decision of the appointed person on an appeal is final and binding on the parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review.
- (11) Any consent, agreement or approval given by the appointed person pursuant to this paragraph is deemed to be an approval for the purpose of Part 1 of this Schedule as if it had been given by the relevant planning authority.
- (12) The relevant planning authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) does not affect or invalidate the effect of the appointed person’s determination.
- (13) Except where a direction is given under sub-paragraph (14) requiring some or all of the costs of the appointed person to be paid by the relevant authority, the reasonable costs of the appointed person must be met by the undertaker.
- (14) On application by the relevant authority or undertaker, the appointed person may give directions as to the costs of the appeal and as to the parties by whom such costs are to be paid.
- (15) In considering whether to make any such direction as to the costs of the appeal parties and the terms on which it is to be made, the appointed person must have regard to the relevant Planning Practice Guidance published by the Ministry for Housing, Communities and Local Government or such guidance as may from time to time replace it.
Anticipatory steps towards compliance with any requirement
31
If before the coming into force of this Order the undertaker or any other person has taken any steps that were intended to be steps towards compliance with any provision of Part 1 of this Schedule, those steps may be taken into account for the purpose of determining compliance with that provision if they would have been valid steps for that purpose had they been taken after this Order came into force.
Interpretation of Part 2 of Schedule 2
32
In Part 2 of Schedule 2—
- “the appeal parties” means the relevant planning authority, the requirement consultee and the undertaker;
- “business day” means a day other than a Saturday or Sunday which is not Christmas Day, Good Friday or a bank holiday under section 1 (bank holidays) of the Banking and Financial Dealings Act 197174; and
- “requirement consultee” means any body named in a requirement which is the subject of an appeal as a body to be consulted by the relevant authority in discharging that requirement.
SCHEDULE 3 — STREETS SUBJECT TO STREET WORKS
| (1) Authority | (2) Streets subject to street works |
|---|---|
| Lincolnshire County Council | Nursery Road (private road) |
| Lincolnshire County Council | Callen Road (private road) |
| Lincolnshire County Council | Bittern Way (private road) |
SCHEDULE 4 — STREETS SUBJECT TO ALTERATION OF LAYOUT
PART 1 — PERMANENT ALTERATION OF LAYOUT
| (1) Street subject to alteration of layout | (2) Description of alteration |
|---|---|
| Bittern Way (private road) | Secure site exit for HGV only – left turn only (works forming part of Work No. 5(j)) between points A and B on the access and rights of way plan. |
| New section of public footpath from Boston Public Footpath 14/4 to Boston Public Footpath 14/11 | A new section of footpath (110m approximately) from a point approximately 200 m from the point marked ST1 (OSGR TF3374542872) on the access and rights of way plan which would join BOST/14/11. |
PART 2 — TEMPORARY ALTERATION OF LAYOUT
| (1) Street subject to alteration of layout | (2) Description of alteration |
|---|---|
| Marsh Lane | Works for the provision of temporary accesses (works forming part of Work No. 7) at the point marked Construction Access Point 2 on the access and rights of way plan. |
SCHEDULE 5 — TEMPORARY CLOSURE, ALTERATION, DIVERSION AND RESTRICTION OF THE USE OF STREETS
| (1) Street subject to temporary prohibition or restriction of use | (2) Extent of temporary prohibition or restriction of use of streets |
|---|---|
| Boston Public Footpath 14 | Length of footpath to be temporarily closed between the points marked TC2 (OSGR TF3400742238) to TC3 (OSGR TF3417242188) on the access and rights of way plan to install and facilitate the construction of Work No. 6(d). |
| Boston Public Footpath 14 | Length of footpath to be temporarily closed between the points marked TC1 (OSGR TF3374542872) to TC2 (OSGR TF3400742238) on the access and rights of way plan to install and facilitate the construction of Work No. 6(d). |
SCHEDULE 6 — PERMANENT STOPPING UP OF STREETS AND PUBLIC RIGHTS OF WAY
| (1) Street to be stopped up | (2) Extent of stopping up |
|---|---|
| Boston Public Footpath 14/4 | Footpath to be stopped up between a point approximately 200 m from the point marked ST1 (OSGR TF3374542872) to ST3 (OSGR TF3411942384) on the access and rights of way plan. |
| Boston Public Footpath 14 | Footpath to be stopped up between the points marked ST3 (OSGR TF3411942384) to ST4 (OSGR TF3400742238) on the access and rights of way plan. |
| Boston Public Footpath 14 | Footpath to be stopped up between the points marked ST3 (OSGR TF3411942384) to ST2 (OSGR TF3417242188) on the access and rights of way plan. |
SCHEDULE 7 — LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
| (1) Number of plot shown on land plan and Crown land plan | (2) Purpose for which temporary possession may be taken |
|---|---|
| 3 | Temporary use to facilitate construction for Work No. 7 and other development necessary for the authorised development that takes place within the Order limits. |
SCHEDULE 8 — PROTECTIVE PROVISIONS
PART 1 — FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
1
For the protection of the utility undertakers referred to in this Part of this Schedule the following provisions have effect, unless otherwise agreed in writing between the undertaker and the utility undertaker concerned.
2
In this Part of this Schedule—
- “alternative apparatus” means alternative apparatus adequate to enable the utility undertaker in question to fulfil its statutory functions in a manner no less efficient than previously;
- “apparatus” means— in the case of an electricity undertaker, electric lines or electrical plant (as defined in the Electricity Act 198975), belonging to or maintained by that undertaker; in the case of a gas undertaker, any mains, pipes or other apparatus belonging to or maintained by a gas transporter within the meaning of Part 1 of the Gas Act 198676 for the purposes of gas supply; in the case of a water undertaker, mains, pipes or other apparatus belonging to or maintained by that undertaker for the purposes of water supply; and in the case of a sewerage undertaker— any drain or works vested in the undertaker under the Water Industry Act 199177; and any sewer which is so vested or is the subject of a notice of intention to adopt given under section 102(4)78 (adoption of sewers and disposal works) of that Act or an agreement to adopt made under section 104 (agreement to adopt sewers, drains or sewage disposal works at a future date) of that Act, and includes a sludge main, disposal main (within the meaning of section 219 (general interpretation) of that Act) or sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part of any such sewer, drain or works, and includes any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus;
- “functions” includes powers and duties;
- “in”, in a context referring to apparatus or alternative apparatus in land, includes a reference to apparatus or alternative apparatus under, over or upon land;
- “plan” includes all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the works to be executed;
- “utility undertaker” means— any licence holder within the meaning of Part 1 of the Electricity Act 1989; a gas transporter within the meaning of Part 1 of the Gas Act 1986; a water undertaker within the meaning of the Water Industry Act 1991; and a sewerage undertaker within the meaning of Part 1 of the Water Industry Act 1991, for the area of the authorised development, and in relation to any apparatus, means the utility undertaker to whom it belongs or by whom it is maintained.
On street apparatus
3
This Part of this Schedule does not apply to apparatus in respect of which the relations between the undertaker and the utility undertaker are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act.
Apparatus in stopped up streets
4
- (1) Where any street is stopped up under article 14 (permanent stopping up of streets), any utility undertaker whose apparatus is in the street has the same powers and rights in respect of that apparatus as it enjoyed immediately before the stopping up and the undertaker must grant to the utility undertaker legal easements reasonably satisfactory to the utility undertaker in respect of such apparatus and access to it, but nothing in this paragraph affects any right of the undertaker or of the utility undertaker to require the removal of that apparatus under paragraph 7 or the power of the undertaker to carry out works under paragraph 9.
- (2) Regardless of the temporary stopping up or diversion of any highway under the powers conferred by article 13 (temporary closure, alteration, diversion and restriction of use of streets), a utility undertaker is at liberty at all times to take all necessary access across any such stopped up highway and to execute and do all such works and things in, upon or under any such highway as may be reasonably necessary or desirable to enable it to maintain any apparatus which at the time of the stopping up or diversion was in that highway.
Protective works to buildings
5
The undertaker, in the case of the powers conferred by article 22 (protective work to buildings), must exercise those powers so as not to obstruct or render less convenient the access to any apparatus.
Acquisition of land
6
Regardless of any provision in this Order or anything shown on the land plan and Crown land plan, the undertaker must not acquire any apparatus otherwise than by agreement.
Removal of apparatus
7
- (1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed or requires that the utility undertaker’s apparatus is relocated or diverted, that apparatus must not be removed under this Part of this Schedule, and any right of a utility undertaker to maintain that apparatus in that land must not be extinguished, until alternative apparatus has been constructed and is in operation to the reasonable satisfaction of the utility undertaker in question in accordance with sub-paragraphs (2) to (6).
- (2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, the undertaker must give to the utility undertaker in question 28 days’ written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order a utility undertaker reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to the utility undertaker the necessary facilities and rights for the construction of alternative apparatus in other land of the undertaker and subsequently for the maintenance of that apparatus.
- (3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed the utility undertaker must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible use its best endeavours to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.
- (4) Any alternative apparatus to be constructed in land of the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between the utility undertaker in question and the undertaker or in default of agreement settled by arbitration in accordance with article 49 (arbitration).
- (5) The utility undertaker in question must, after the alternative apparatus to be provided or constructed has been agreed or settled by arbitration in accordance with article 49 (arbitration), and after the grant to the utility undertaker of any such facilities and rights as are referred to in sub-paragraphs (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
- (6) Regardless of anything in sub-paragraph (5), if the undertaker gives notice in writing to the utility undertaker in question that the undertaker desires itself to execute any work, or part of any work in connection with the construction or removal of apparatus in any land of the undertaker, that work, instead of being executed by the utility undertaker, must be executed by the undertaker without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of the utility undertaker.
- (7) If the utility undertaker in question fails either reasonably to approve, or to provide reasons for its failure to approve along with an indication of what would be required to make acceptable, any proposed details relating to required removal works under sub-paragraph (2) within 28 days of receiving a notice of the required works from the undertaker, then such details are deemed to have been approved.
- (8) For the avoidance of doubt, any such “deemed consent” under sub-paragraph (7) does not extend to the actual undertaking of the removal works, which remains the sole responsibility of the utility undertaker or its contractors.
Facilities and rights for alternative apparatus
8
- (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to a utility undertaker facilities and rights for the construction and maintenance in land of the undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities and rights are to be granted upon such terms and conditions as may be agreed between the undertaker and the utility undertaker in question or in default of agreement settled by arbitration in accordance with article 49 (arbitration).
- (2) If the facilities and rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are in the opinion of the arbitrator less favourable on the whole to the utility undertaker in question than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the arbitrator must make such provision for the payment of compensation by the undertaker to that utility undertaker as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
Retained apparatus
9
- (1) Not less than 28 days before starting the execution of any works in, on or under any land purchased, held, appropriated or used under this Order that are near to, or will or may affect, any apparatus the removal of which has not been required by the undertaker under paragraph 7(2), the undertaker must submit to the utility undertaker in question a plan of the works to be executed.
- (2) Those works must be executed only in accordance with the plan submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by the utility undertaker for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and the utility undertaker is entitled to watch and inspect the execution of those works.
- (3) Any requirements made by a utility undertaker under sub-paragraph (2) must be made within a period of 21 days beginning with the date on which a plan under sub-paragraph (1) is submitted to it.
- (4) If a utility undertaker in accordance with sub-paragraph (3) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 1 to 3 and 6 to 8 apply as if the removal of the apparatus had been required by the undertaker under paragraph 7(2).
- (5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan instead of the plan previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.
- (6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case must give to the utility undertaker in question notice as soon as is reasonably practicable and a plan of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (3) in so far as is reasonably practicable in the circumstances.
Expenses and costs
10
- (1) Subject to the following provisions of this paragraph, the undertaker must repay to a utility undertaker all expenses reasonably incurred by that utility undertaker in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to in paragraph 7(2).
- (2) There must be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule that value being calculated after removal.
- (3) If in accordance with the provisions of this Part of this Schedule—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 49 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to the utility undertaker in question by virtue of sub-paragraph (1) must be reduced by the amount of that excess.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
- (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
- (5) An amount which apart from this sub-paragraph would be payable to a utility undertaker in respect of works by virtue of sub-paragraph (1), if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the utility undertaker any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, is to be reduced by the amount which represents that benefit.
11
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works referred to in paragraphs 5 or 7(2), or by reason of any subsidence resulting from such development or works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of a utility undertaker, or there is any interruption in any service provided, or in the supply of any goods, by any utility undertaker, the undertaker must—
- (a) bear and pay the cost reasonably incurred by that utility undertaker in making good such damage or restoring the supply; and
- (b) make reasonable compensation to that utility undertaker for any other expenses, loss, damages, penalty or costs incurred by the undertaker,
- (c) by reason or in consequence of any such damage or interruption.
- (2) The fact that any act or thing may have been done by a utility undertaker on behalf of the undertaker or in accordance with a plan approved by a utility undertaker or in accordance with any requirement of a utility undertaker or under its supervision does not, subject to sub-paragraph (3), excuse the undertaker from liability under the provisions of sub-paragraph (1) unless the utility undertaker fails to carry out and execute the works properly with due care and attention and in a skilful and professional like manner or in a manner that does not accord with the approved plan.
- (3) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of a utility undertaker, its officers, servants, contractors or agents.
- (4) A utility undertaker must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made without the consent of the undertaker who, if withholding such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
Cooperation
12
Where in consequence of the proposed construction of any part of the authorised development, the undertaker or a utility undertaker requires the removal of apparatus under paragraph 7(2) or a utility undertaker makes requirements for the protection or alteration of apparatus under paragraph 9, the undertaker must use best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of the utility undertaker’s undertaking and each utility undertaker must use its best endeavours to co-operate with the undertaker for that purpose.
13
Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and a utility undertaker in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
PART 2 — FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
14
For the protection of any operator, the following provisions have effect, unless otherwise agreed in writing between the undertaker and the operator.
15
In this Part of this Schedule—
- “the 2003 Act” means the Communications Act 200379;
- “electronic communications apparatus” has the same meaning as in the electronic communications code;
- “the electronic communications code” has the same meaning as in Chapter 1 of Part 2 of the 2003 Act80;
- “electronic communications code network” means— so much of an electronic communications network or infrastructure system provided by an electronic communications code operator as is not excluded from the application of the electronic communications code by a direction under section 106 (application of the electronic communications code) of the 2003 Act; and an electronic communications network which the undertaker is providing or proposing to provide;
- “electronic communications code operator” means a person in whose case the electronic communications code is applied by a direction under section 106 of the 2003 Act;
- “infrastructure system” has the same meaning as in the electronic communications code and references to providing an infrastructure system are to be construed in accordance with paragraph 7(2) of that code; and
- “operator” means the operator of an electronic communications code network.
16
The exercise of the powers conferred by article 35 (statutory undertakers) is subject to Part 10 (undertaker’s works affecting electronic communications apparatus) to the electronic communications code.
17
- (1) Subject to sub-paragraphs (2) to (4), if as the result of the authorised development or its construction, or of any subsidence resulting from any of those works—
- (a) any damage is caused to any electronic communications apparatus belonging to an operator (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works), or other property of an operator; or
- (b) there is any interruption in the supply of the service provided by an operator,
the undertaker must bear and pay the cost reasonably incurred by the operator in making good such damage or restoring the supply and make reasonable compensation to that operator for any other reasonable expenses, loss, damages, penalty or costs incurred by it, by reason, or in consequence of, any such damage or interruption.
- (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of an operator, its officers, servants, contractors or agents.
- (3) The operator must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise of the claim or demand is to be made without the consent of the undertaker who, if withholding such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
- (4) Any difference arising between the undertaker and the operator under this Part of this Schedule must be referred to and settled by arbitration under article 49 (arbitration).
- (5) This Part of this Schedule does not apply to—
- (a) any apparatus in respect of which the relations between the undertaker and an operator are regulated by the provisions of Part 3 of the 1991 Act; or
- (b) any damages, or any interruptions, caused by electro-magnetic interference arising from the construction or use of the authorised development.
- (6) Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and an operator in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
PART 3 — FOR THE PROTECTION OF HIGHWAYS AND TRAFFIC UNDERTAKERS
18
- (1) The provisions of this Part of this Schedule have effect unless otherwise agreed in writing between the undertaker and the relevant highway authority.
- (2) In this Part of this Schedule—
- “highway” means any highway of which the relevant highway authority is the highway authority;
- “plans” includes sections, designs, drawings, specifications, soil reports, staging proposals, programmes, calculations, methods of construction, risk assessments and details of the extent, timing and duration of any proposed occupation of any highway and “approved plans” means plans approved or deemed to be approved or settled by arbitration in accordance with the provisions of this Part of this Schedule;
- “property of the relevant highway authority” means any apparatus or street furniture of the relevant highway authority affixed to or placed under any highway; and
- “the relevant highway authority” means the highway authority for the area in which the highway to which the provisions of this Part of this Schedule is situated.
- (3) Wherever in this Part of this Schedule provision is made with respect to the approval or consent of the relevant highway authority, that approval or consent must be in writing and subject to such reasonable terms and conditions as the relevant highway authority may require.
- (4) In exercising the powers conferred by this Order in relation to any highway the undertaker must have regard to the potential disruption of traffic which may be caused and must seek to minimise such disruption so far as is reasonably practicable.
- (5) The undertaker must not, without the consent of the relevant highway authority, construct any part of the works authorised by this Order under and within 50 metres of the surface of any highway which comprises a carriageway except in accordance with plans submitted to, and approved by, the relevant highway authority; and if within 28 days after such plans have been submitted the relevant highway authority has not approved or disapproved them, it is deemed to have approved the plans as submitted.
- (6) In the construction of any part of the said works under a highway no part of it shall, except with the consent of the relevant highway authority, be so constructed as to interfere with the provision of proper means of drainage of the surface of the highway or be nearer than two metres to the surface of the highway.
- (7) The undertaker must not under the powers conferred by or under this Order without the consent of the relevant highway authority, acquire or enter upon, take or use whether temporarily or permanently or acquire any new rights over any part of any highway, including subsoil beneath the surface of any highway.
19
- (1) Before commencing the construction of, or the carrying out of any work which involves interference with a highway, the undertaker must submit to the relevant highway authority for its approval plans, drawings and particulars (in this paragraph referred to as “plans”) relating thereto, and the works must not be carried out except in accordance with the plans submitted to, and approved by, the relevant highway authority.
- (2) If within 28 days after the plans have been submitted the highway authority has not approved or disapproved them, it is deemed to have approved the plans as submitted.
- (3) Any officer of the relevant highway authority duly appointed for the purpose may at all reasonable times, on giving to the undertaker such notice as may in the circumstances be reasonable, enter upon and inspect any part of the works authorised by this Order which—
- (a) is in, over or under any highway, or
- (b) which may affect any highway or any property of the relevant highway authority,
during the carrying out of the work, and the undertaker must give to such officer all reasonable facilities for such inspection and, if the officer is of the opinion that the construction of the work is attended with danger to any highway or to any property of the relevant highway authority on or under any highway, the undertaker must adopt such measures and precautions as may be reasonably practicable for the purpose of preventing any damage or injury to the highway.
20
- (1) The undertaker must not alter, disturb or in any way interfere with any property of the relevant highway authority on or under any highway, or the access thereto, without the consent of the relevant highway authority, and any alteration, diversion, replacement or reconstruction of any such property which may be necessary may be made by the relevant highway authority or the undertaker as the relevant highway authority thinks fit, and the expense reasonably incurred by the relevant highway authority in so doing must be repaid to the relevant highway authority by the undertaker.
- (2) If within 28 days after a request for consent has been submitted the relevant highway authority has not given or refused such consent, it is deemed to have consented to the request as submitted.
21
The undertaker must not remove any soil or material from any highway except so much as must be excavated in the carrying out of the works authorised by this Order.
22
- (1) If the relevant highway authority, after giving to the undertaker not less than 28 days’ notice (or, in case of emergency, such notice as is reasonably practicable) of its intention to do so, incurs any additional expense in the signposting of traffic diversions, in the diversion of footpaths, in the taking of other measures in relation thereto, or in the repair of any highway by reason of the diversion thereto of traffic from a road of a higher standard, in consequence of the construction of the works authorised by this Order, the undertaker must repay to the relevant highway authority the amount of any such expense reasonably so incurred.
- (2) An amount which apart from this sub-paragraph would be payable to the relevant highway authority by virtue of this paragraph in respect of the repair of any highway must, if the highway fell or would have fallen due for repair as part of the maintenance programme of the relevant highway authority at any time within ten years of the repair being carried out by the undertaker, so as to confer on the relevant highway authority financial benefit (whether by securing the completion of overdue maintenance work for which the relevant highway authority is liable or by deferment of the time for such work in the ordinary course), be reduced by the amount which represents that benefit.
23
- (1) The undertaker shall not, except with the consent of the relevant highway authority, deposit any soil or materials, or stand any plant, on or over any highway so as to obstruct or render less safe the use of the highway by any person, or, except with the like consent, deposit any soil or materials on any highway outside a hoarding, but if within 28 days after request for it any such consent is neither given nor refused it is deemed to have been given.
- (2) The expense reasonably incurred by the relevant highway authority in removing any soil or materials deposited on any highway in contravention of this paragraph must be repaid to the relevant highway authority by the undertaker.
24
The undertaker must not, except with the consent of the relevant highway authority, erect or retain on or over a highway to which the public continues to have access any scaffolding or other structure which obstructs the highway.
25
The undertaker must, if reasonably so required by the relevant highway authority, provide and maintain to the reasonable satisfaction of the relevant highway authority, during such time as the undertaker may occupy any part of a highway for the purpose of the construction of any part of the works authorised by this Order, temporary bridges and temporary ramps for vehicular or pedestrian traffic over any part of the works or in such other position as may be necessary to prevent undue interference with the flow of traffic in the highway.
26
- (1) Where any part of any highway has been broken up or disturbed by the undertaker and not permanently stopped up or diverted, the undertaker must make good the subsoil, foundations and surface of that part of the highway to the reasonable satisfaction of the relevant highway authority, and must maintain the same to the reasonable satisfaction of the relevant highway authority for such time as may reasonably be required for the permanent reinstatement of the highway.
- (2) The reinstatement of that part of the highway must be carried out by the undertaker to the reasonable satisfaction of the relevant highway authority in accordance with such requirements as to specification of material and standards of workmanship as may be prescribed for equivalent reinstatement work by regulations made under section 71 of the New Roads and Street Works Act 199181.
27
If any damage to any highway or any property of the relevant highway authority on or under any highway is caused by, or results from, the construction of any work authorised by this Order or any order or omission of the undertaker, its contractors, agents or employees whilst engaged upon such work, the undertaker may, in the case of damage to a highway, make good such damage to the reasonable satisfaction of the relevant highway authority and, where the undertaker does not make good, or in the case of damage to property of the relevant highway authority, the undertaker must make compensation to the relevant highway authority.
28
The fact that any act or thing may have been done in accordance with plans approved by the relevant highway authority does not (if it was not attributable to the act, neglect or default of the relevant highway authority or of any person in its employ or its contractors or agents) exonerate the undertaker from any liability, or affect any claim for damages, under this Part or otherwise.
29
Any difference arising between the undertaker and the relevant highway authority under this Part of this Schedule (other than in difference as to the meaning or construction of this Part of this Schedule) shall be resolved by arbitration under article 49 (arbitration).
PART 4 — FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
30
The following provisions apply for the protection of the Agency unless otherwise agreed in writing between the undertaker and the Agency.
31
In this Part of this Schedule—
- “the Agency” means the Environment Agency;
- “construction” includes execution, placing, altering, replacing, relaying and removal and excavation and “construct” and “constructed” is to be construed accordingly;
- “drainage work” means any main river and includes any land which provides or is expected to provide flood storage capacity for any main river and any bank, wall, embankment or other structure, or any appliance, constructed or used for land drainage, flood defence or tidal monitoring;
- “the fishery” means any waters containing fish and fish in, or migrating to or from, such waters and the spawn, spawning ground, habitat or food of such fish;
- “main river” means all watercourses shown as such on the statutory main river maps held by the Agency and the Department for Environment Food and Rural Affairs including any structure or appliance for controlling or regulating the flow of water in or out of the channel;
- “plans” includes sections, drawings, specifications, calculations and method statements;
- “Roman Bank” means the sea defence known as the Roman Bank as shown on the Roman Bank plan;
- “Roman Bank plan” means the plan titled “Roman Bank within the Order limits” certified by the Secretary of State as the Roman Bank plan for the purposes of this Order under article 47 (certification of documents, etc.);
- “sea defence” means any bank, wall, embankment (and any berm, counterwall or cross-wall connected to any such bank, wall or embankment), barrier, tidal sluice and other defence, whether natural or artificial, against the inundation of land by sea water or tidal water, including natural or artificial high ground which forms part of or makes a contribution to the efficiency of the defences of the Agency’s area against flooding, but excludes any sea defence works which are for the time being maintained by a coast protection authority under the provisions of the Coast Protection Act 194982 or by any local authority or any navigation, harbour or conservancy authority;
- “specified work” means so much of any work or operation authorised by this Order or otherwise as is for the purpose of or in connection with, the construction or maintenance of the authorised development— in, on, under, over or within 16 metres of a drainage work or is otherwise likely to— affect any drainage work or the volumetric rate of flow of water in or flowing to or from any drainage work; affect the flow, purity or quality of water in any watercourse or other surface waters or ground water; cause obstruction to the free passage of fish or damage to any fishery; affect the conservation, distribution or use of water resources; or affect the conservation value of the main river and habitats in its immediate vicinity; in, on, under, over or within 16 metres of the base of a sea defence which is likely to— endanger the stability of, cause damage to or reduce the effectiveness of that defence; or interfere with the Agency’s access to or along that defence; an activity that includes any dredging, raising or taking of any sand, silt, ballast, clay, gravel or other materials from or off the bed or banks of a drainage work (or causing such materials to be dredged, raised or taken), including hydrodynamic dredging or desilting; any quarrying or excavation within 16 metres of a drainage work which is likely to cause damage to or endanger the stability of the banks or structure of that drainage work; and
- “watercourse” includes all rivers, streams, ditches, drains, cuts, culverts, dykes, sluices, basins, sewers and passages through which water flows except a public sewer.
Submission and approval of plans
32
- (1) Before beginning to construct any specified work, the undertaker must submit to the Agency plans of the specified work and such further particulars available to it as the Agency may within 28 days of the receipt of the plans reasonably request.
- (2) Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by the Agency, or determined under paragraph 42.
- (3) Any approval of the Agency required under this paragraph—
- (a) must not be unreasonably withheld or delayed;
- (b) is deemed to have been refused if it is neither given nor refused within 2 months of the submission of the plans or receipt of further particulars if such particulars have been requested by the Agency for approval;
- (c) in the case of a refusal, accompanied by a statement of the grounds of refusal; and
- (d) may be given subject to such reasonable requirements as the Agency may have for the protection of any drainage work or the fishery or for the protection of water resources, or for the prevention of flooding or pollution or in the discharge of its environmental duties.
- (4) The Agency must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (3)(b).
Construction of protective works
33
Without limiting paragraph 32, the requirements which the Agency may have under that paragraph include conditions requiring the undertaker, at its own expense, to construct such protective works, whether temporary or permanent, before or during the construction of the specified works (including the provision of flood banks, walls or embankments or other new works and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably necessary—
- (a) to safeguard any drainage work against damage; or
- (b) to secure that its efficiency for flood defence purposes is not impaired and that the risk of flooding is not otherwise increased,
by reason of any specified work.
Timing of works and service of notices
34
- (1) Subject to sub-paragraph (2), any specified work, and all protective works required by the Agency under paragraph 33, must be constructed—
- (a) without unreasonable delay in accordance with the plans approved under this Part of this Schedule; and
- (b) to the reasonable satisfaction of the Agency,
and the Agency is entitled by its officer to watch and inspect the construction of such works.
- (2) The undertaker must give to the Agency not less than 14 days’ notice in writing of its intention to commence construction of any specified work and notice in writing of its completion not later than 7 days after the date on which it is completed.
- (3) If the Agency reasonably requires, the undertaker must construct all or part of the protective works so that they are in place prior to the construction of the specified work to which the protective works relate.
- (4) If any part of a specified work or any protective work required by the Agency is constructed otherwise than in accordance with the requirements of this Schedule, the Agency may by notice in writing require the undertaker at the undertaker’s own expense to comply with the requirements of this part of this Schedule or (if the undertaker so elects and the Agency in writing consents, such consent not to be unreasonably withheld or delayed) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent and within such limits as the Agency reasonably requires.
- (5) Subject to sub-paragraph (6) and paragraph 39, if, within a reasonable period, being not less than 28 days beginning with the date when a notice under sub-paragraph (4) is served upon the undertaker, the undertaker has failed to begin taking steps to comply with the requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, the Agency may execute the works specified in the notice and any reasonable expenditure incurred by the Agency in so doing is recoverable from the undertaker.
- (6) In the event of any dispute as to whether sub-paragraph (4) is properly applicable to any work in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, the Agency must not, except in the case of an emergency, exercise the powers conferred by sub-paragraph (5) until the dispute has been finally determined in accordance with paragraph 41.
Maintenance of drainage works
35
- (1) Subject to sub-paragraph (5) the undertaker must from the commencement of the construction of the specified works maintain in good repair and condition and free from obstruction any drainage work which is situated within the limits of deviation and on land held by the Applicant for the purposes of or in connection with the specified works, whether or not the drainage work is constructed under the powers conferred by this Order or is already in existence.
- (2) If any such drainage work which the undertaker is liable to maintain is not maintained to the reasonable satisfaction of the Agency, the Agency may by notice in writing require the undertaker to repair the drainage work, or any part of such drainage work, or (if the undertaker so elects and the Agency in writing consents, such consent not to be unreasonably withheld or delayed), to remove the specified work and restore the site to its former condition, to such extent and within such limits as the Agency reasonably requires.
- (3) Subject to sub-paragraph (4) and paragraph 39, if, within a reasonable period, being not less than 28 days beginning with the date on which a notice in respect of any drainage work is served under sub-paragraph (2) on the undertaker, the undertaker has failed to begin taking steps to comply with the reasonable requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, the Agency may do what is reasonably necessary for such compliance and any expenditure reasonably incurred by the Agency in so doing is recoverable from the undertaker.
- (4) In the event of any dispute as to the reasonableness of any requirement of a notice served under sub-paragraph (2), the Agency will not, except in the case of an emergency, exercise the powers conferred by sub-paragraph (3) until the dispute has been finally determined in accordance with paragraph 41.
- (5) This paragraph does not apply to—
- (a) drainage works which are vested in the Agency, or which the Agency or another person is liable to maintain and is not proscribed by the powers of the Order from doing so; and
- (b) any obstruction of a drainage work expressly authorised in the approval of specified works plans and carried out in accordance with the provisions of this Part provided that any obstruction is removed as soon as reasonably practicable.
Impairment of drainage works
36
Subject to paragraph 39, if by reason of the construction of any specified work or of the failure of any such work, the efficiency of any drainage work for flood defence purposes is impaired, or that drainage work is otherwise damaged, such impairment or damage must be made good by the undertaker to the reasonable satisfaction of the Agency and if the undertaker fails to do so, the Agency may make good the impairment or damage and recover any expenditure reasonably incurred by the Agency in so doing from the undertaker.
Agency access
37
If by reason of construction of the specified work the Agency’s access to flood defences or equipment maintained for flood defence purposes is materially obstructed, the undertaker must provide such alternative means of access that will allow the Agency to maintain the flood defence or use the equipment no less effectively than was possible before the obstruction as soon as reasonably practicable and within 24 hours of the undertaker becoming aware of such obstruction unless a longer period of time has been agreed in writing by the Agency.
Free passage of fish
38
- (1) The undertaker must take all such measures as may be reasonably practicable to prevent any interruption of the free passage of fish in the fishery during the construction of any specified work.
- (2) If by reason of—
- (a) the construction of any specified work; or
- (b) the failure of any such work,
damage to the fishery is caused, or the Agency has reason to expect that such damage may be caused, the Agency may serve notice on the undertaker requiring it to take such steps as may be reasonably practicable to make good the damage, or, as the case may be, to protect the fishery against such damage.
- (3) Subject to paragraph 39, if within such time as may be reasonably practicable for that purpose after the receipt of written notice from the Agency of any damage or expected damage to a fishery, the undertaker fails to take such steps as are described in sub-paragraph (2), the Agency may take those steps and any expenditure reasonably incurred by the Agency in so doing is recoverable from the undertaker.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.