The Hornsea Four Offshore Wind Farm Order 2023
Statutory authority to override easements and other rights
24
- (1) The carrying out or use of the authorised development and the doing of anything else authorised by this Order is authorised for the purpose specified in section 158(2) (nuisance: statutory authority) of the 2008 Act, notwithstanding that it involves—
- (a) an interference with an interest or right to which this article applies; or
- (b) a breach of a restriction as to use of land arising by virtue of contract.
- (2) The undertaker must pay compensation to any person whose land is injuriously affected by—
- (a) an interference with an interest or right to which this article applies; or
- (b) a breach of a restriction as to use of land arising by virtue of contract,
authorised by virtue of this Order and the operation of section 158 (nuisance: statutory authority) of the 2008 Act.
- (3) The interests and rights to which this article applies are any easement, liberty, privilege, right or advantage annexed to land and adversely affecting other land, including any natural right to support and any restrictions as to the use of land arising by virtue of a contract.
- (4) Subsection (2) of section 10 (further provision as to compensation for injurious affection) of the 1965 Act applies to paragraph (2) by virtue of section 152(5) of the 2008 Act (compensation in case where no right to claim in nuisance).
- (5) Any rule or principle applied to the construction of section 10 of the 1965 Act must be applied to the construction of paragraph (2) (with any necessary modifications).
Acquisition of subsoil only
25
- (1) The undertaker may acquire compulsorily so much of, or such rights in, the subsoil of the land referred to in paragraph (1) of article 18 (compulsory acquisition of land etc.) or article 21 (compulsory acquisition of rights ...) as may be required for any purpose for which that land may be acquired under that provision instead of acquiring the whole of the land.
- (2) Where the undertaker acquires any part of, or rights in, the subsoil of land under paragraph (1), the undertaker is not required to acquire an interest in any other part of the land.
- (3) The following do not apply in connection with the exercise of the power under paragraph (1) in relation to subsoil only—
- (a) Schedule 2A (counter-notice requiring purchase of land not in notice to treat) to the 1965 Act as modified by Schedule 7 (modification of compensation and compulsory purchase enactments for creation of new rights);
- (b) Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration) to the 1981 Act; and
- (c) Section 153(4A) (blighted land: proposed acquisition of part interest; material detriment test) of the Town and Country Planning Act 1990.
- (4) Paragraphs (2) and (3) do not apply where the undertaker acquires a cellar, vault, arch or other construction forming part of a house, building or factory.
Modification of Part 1 of the 1965 Act
26
- (1) Part 1 (compulsory purchase under Acquisition of Land Act of 1946) of the 1965 Act, as applied to this Order by section 125 (application of compulsory acquisition provisions) of the 2008 Act, is modified as follows.
- (2) In section 4A(1) (extension of time limit during challenge)42—
- (a) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order)” substitute, “section 118 of the 2008 Act (legal challenges relating to applications for orders granting development consent)”; and
- (b) for “the three year period specified in section 4” substitute “the seven year period mentioned in article 20 (time limit for exercise of authority to acquire land compulsorily) of the Hornsea Four Offshore Wind Farm Order 2023”.
- (3) In section 11A (powers of entry: further notices of entry)43—
- (a) in subsection (1)(a), after “land” insert “under that provision”; and
- (b) in subsection (2), after “land” insert “under that provision”.
- (4) In section 22(2) (expiry of time limit for exercise of compulsory purchase power not to affect acquisition of interests omitted from purchase), for “section 4 of this Act” substitute “article 20 (time limit for exercise of authority to acquire land compulsorily) of the Hornsea Four Offshore Wind Farm Order 2023”.
- (5) In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)(c)—
- (a) for paragraphs 1(2) and 14(2) substitute—
(2) But see article 25(3) (acquisition of subsoil only) of the Hornsea Four Offshore Wind Farm Order 2023, which excludes the acquisition of subsoil only from this Schedule.
; and
- (b) at the end insert—
(30) .In this Schedule, references to entering on and taking possession of land do not include doing so under article 16 (protective work to buildings), article 28 (temporary use of land for carrying out the authorised project) or article 29 (temporary use of land for maintaining the authorised project) of the Hornsea Four Offshore Wind Farm Order 2023.
Rights under or over streets
27
- (1) The undertaker may enter on and appropriate so much of the subsoil of or air–space over any street within the Order limits as may be required for the purposes of the authorised project and may use the subsoil or air-space for those purposes or any other purpose ancillary to the authorised project.
- (2) Subject to paragraph (3), the undertaker may exercise any power conferred by paragraph (1) in relation to a street without being required to acquire any part of the street or any easement or right in the street.
- (3) Paragraph (2) does not apply in relation to—
- (a) any subway or underground building; or
- (b) any cellar, vault, arch or other construction in, on or under a street which forms part of a building fronting onto the street.
- (4) Subject to paragraph (5), any person who is an owner or occupier of land appropriated under paragraph (1) without the undertaker acquiring any part of that person’s interest in the land, and who suffers loss as a result, is entitled to compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
- (5) Compensation is not payable under paragraph (4) to any person who is an undertaker to whom section 85 (sharing cost of necessary measures) of the 1991 Act applies in respect of measures of which the allowable costs are to be borne in accordance with that section.
Temporary use of land for carrying out the authorised project
28
- (1) The undertaker may, in connection with the carrying out of the authorised project—
- (a) enter on and take temporary possession of—
- (i) the land specified in columns (1) and (2) of Schedule 8 (land of which temporary possession may be taken) for the purpose specified in relation to that land in column (3) of that Schedule; and
- (ii) any other Order land in respect of which no notice of entry has been served under section 11 (powers of entry) of the 1965 Act (other than in connection with the acquisition of rights only) and no declaration has been made under section 4 (execution of declaration) of the 1981 Act;
- (b) remove any buildings, agricultural plant and apparatus, drainage, fences, debris and vegetation from that land;
- (c) construct temporary works (including the provision of means of access and footpaths), haul roads, security fencing, bridges, services, signage, structures and buildings on that land;
- (d) use the land for the purposes of a working site with access to the working site in connection with the authorised project;
- (e) construct any works, or use the land, as specified in relation to that land in column 3 of Schedule 8 (land of which temporary possession may be taken), or any mitigation works;
- (f) construct such works on that land as are mentioned in Part 1 of Schedule 1 (authorised development); and
- (g) carry out mitigation works required pursuant to the requirements in Part 3 of Schedule 1 (authorised development).
- (2) Not less than 28 days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.
- (3) The undertaker must not remain in possession of any land under this article for longer than reasonably necessary and in any event must not, without the agreement of the owners of the land, remain in possession of any land under this article—
- (a) in the case of land specified in paragraph (1)(a)(i) after the end of the period of one year beginning with the date of completion of the part of the authorised project specified in relation to that land in column (3) of Schedule 8 (land of which temporary possession may be taken); or
- (b) in the case of land specified in paragraph (1)(a)(ii) after the end of the period of one year beginning with the date of completion of the part of the authorised project for which temporary possession of the land was taken unless the undertaker has, before the end of that period, served a notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act in relation to that land.
- (4) Unless the undertaker has served notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act or otherwise acquired the land or rights over land subject to temporary possession or otherwise agreed with the owners of the land, the undertaker must before giving up possession of land of which temporary possession has been taken under this article, remove all works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker is not required to—
- (a) replace any building, structure, drain or electric line removed under this article;
- (b) remove any drainage works installed by the undertaker under this article;
- (c) remove any new road surface or other improvements carried out under this article to any street specified in Schedule 2 (streets subject to street works) or any new footpath surface or other enhancements carried out under this article to any footpath or any improvements carried out under this article to any bridge;
- (d) remove any fencing or boundary treatments installed by the undertaker under this article to replace or enhance existing fencing or boundary treatments; or
- (e) restore the land on which any works have been carried out under paragraph (1)(g) insofar as the works relate to mitigation works identified in the environmental statement or required pursuant to the requirements in Schedule 1.
- (5) The undertaker must pay compensation to the owners and occupiers of land which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of any power conferred by this article.
- (6) Any dispute as to a person’s entitlement to compensation under paragraph (5), or as to the amount of the compensation, must be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
- (7) Nothing in this article affects any liability to pay compensation under section 152 of the 2008 Act (compensation in case where no right to claim in nuisance) or under any other enactment in respect of loss or damage arising from the carrying out of the authorised project, other than loss or damage for which compensation is payable under paragraph (5).
- (8) The undertaker may not compulsorily acquire under this Order the land referred to in paragraph (1)(a)(i) except that the undertaker is not precluded from—
- (a) acquiring new rights or imposing restrictive covenants over any part of that land under article 21 (compulsory acquisition of rights etc.) to the extent that such land is listed in column (1) of Schedule 6; or
- (b) acquiring any part of the subsoil (or rights in the subsoil) of that land under article 25 (acquisition of subsoil only).
- (9) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.
- (10) Section 13 of the 1965 Act (refusal to give possession to acquiring authority) applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).
- (11) Nothing in this article prevents the taking of temporary possession more than once in relation to any land specified in Schedule 8.
- (12) Subject to article 43, so much of the special category land as is required for the purposes of exercising the powers pursuant to this article is temporarily discharged from all rights, trusts and incidents to which it was previously subject, so far as their continuance would be inconsistent with the exercise of those powers, and only for such time as any special category land is being used under this article.
- (13) At any time where the undertaker has taken temporary possession of any part of the Driffield Navigation under this article, on the starting date specified in the notice given under paragraph (15) and for the duration specified in notice given under paragraph (15), the public right of navigation over that part of the Driffield Navigation is suspended and unenforceable against the Driffield Navigation Trust.
- (14) Any person who suffers loss as a result of the suspension of any private right of navigation over the Driffield Navigation under this article is entitled to be paid compensation for such loss by the undertaker, to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
- (15) Not later than 28 days prior to the proposed start of any suspension of the public right of navigation over the Driffield Navigation under this article, the undertaker must give written notice to The Driffield Navigation Trust except in the case of an emergency when the undertaker must give such notice as is reasonably practicable.
- (16) A notice given under paragraph (15) must provide details of the proposed suspension including particulars of the—
- (a) start date;
- (b) duration; and
- (c) affected area.
- (17) Following receipt of a notice given under paragraph (15), The Driffield Navigation Trust must issue a notice to mariners within 14 days, giving the start date and other particulars of the suspension to which the notice relates, and that suspension will take effect on the date specified and as otherwise described in the notice.
Temporary use of land for maintaining the authorised project
29
- (1) Subject to paragraph (2), at any time during the maintenance period relating to any part of the authorised project, the undertaker may—
- (a) enter on and take temporary possession of any of the Order land if such possession is reasonably required for the purpose of maintaining the authorised project;
- (b) enter on any of the Order land for the purpose of gaining such access as is reasonably required for the purpose of maintaining the authorised project; and
- (c) construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.
- (2) Paragraph (1) does not authorise the undertaker to take temporary possession of—
- (a) any house or garden belonging to a house; or
- (b) any building (other than a house) if it is for the time being occupied.
- (3) Not less than 28 days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.
- (4) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised project for which possession of the land was taken.
- (5) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.
- (6) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.
- (7) Any dispute as to a person’s entitlement to compensation under paragraph (6), or as to the amount of the compensation, must be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
- (8) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the maintenance of the authorised project, other than loss or damage for which compensation is payable under paragraph (6).
- (9) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.
- (10) Section 13 of the 1965 Act (refusal to give possession to acquiring authority) applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).
- (11) In this article “the maintenance period” means the period of 5 years beginning with the date on which the authorised project first exports electricity to the national electricity transmission network, unless a different maintenance period is stated in the landscape management plan approved under requirement 8 or in the code of construction practice approved under requirement 18.
- (12) So much of the special category land as is required for the purposes of exercising the powers pursuant to this article is temporarily discharged from all rights, trusts and incidents to which it was previously subject, so far as their continuance would be inconsistent with the exercise of those powers, and only for such time as any special category land is being used under this article.
- (13) At any time where the undertaker has taken temporary possession of any part of the Driffield Navigation under this article, on the starting date specified in the notice given under paragraph (15) and for the duration specified in notice given under paragraph (15), the public right of navigation over that part of the Driffield Navigation is suspended and unenforceable against the Driffield Navigation Trust.
- (14) Any person who suffers loss as a result of the suspension of any private right of navigation over the Driffield Navigation under this article is entitled to be paid compensation for such loss by the undertaker, to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
- (15) Not later than 28 days prior to the proposed start of any suspension of the public right of navigation over the Driffield Navigation under this article, the undertaker must give written notice to the Driffield Navigation Trust except in the case of an emergency when the undertaker must give such notice as is reasonably practicable.
- (16) A notice given under paragraph (15) must provide details of the proposed suspension including particulars of the—
- (a) start date;
- (b) duration; and
- (c) affected area.
- (17) Following receipt of a notice given under paragraph (15), the Driffield Navigation Trust must issue a notice to mariners within 14 days, giving the starting date and other particulars of the suspension to which the notice relates, and that suspension will take effect on the date specified and as otherwise described in the notice.
Statutory undertakers
30
Subject to the provisions of Schedule 9 (protective provisions) the undertaker may—
- (a) acquire compulsorily, or acquire new rights or impose restrictive covenants over, the land belonging to statutory undertakers shown on the land plans within the Order land and described in the book of reference; and
- (b) extinguish or suspend the rights of, or restrictions for the benefit of, or remove, relocate or reposition the apparatus belonging to statutory undertakers over or within the Order land.
Recovery of costs of new connections
31
- (1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article 30 (statutory undertakers) any person who is the owner or occupier of premises to which a supply was given from that apparatus is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.
- (2) Paragraph (1) does not apply in the case of the removal of a public sewer but where such a sewer is removed under article 30 (statutory undertakers), any person who is—
- (a) the owner or occupier of premises the drains of which communicated with that sewer; or
- (b) the owner of a private sewer which communicated with that sewer,
is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.
- (3) This article does not have effect in relation to apparatus to which Part 3 (street works in England and Wales) of the 1991 Act applies.
- (4) In this paragraph—
- “public communications provider” has the same meaning as in section 151(1) of the 2003 Act; and
- “public utility undertaker” means a gas, water, electricity or sewerage undertaker.
PART 6 — OPERATIONS
Operation of generating station
32
- (1) The undertaker is authorised to operate the generating station comprised in the authorised project.
- (2) This article does not relieve the undertaker of any requirement to obtain any permit or licence under any other legislation that may be required from time to time to authorise the operation of an electricity generating station.
Deemed marine licences under the 2009 Act
33
The deemed marine licences set out in Schedules 11 (deemed marine licence under the 2009 Act — generation assets) and 12 (deemed marine licence under the 2009 Act — transmission assets) respectively, are deemed to be granted to the undertaker under Part 4 (marine licences) of the 2009 Act for the licensed marine activities set out in Part 1, and subject to the conditions set out in Part 2 of each of those Schedules.
PART 7 — MISCELLANEOUS AND GENERAL
Application of landlord and tenant law
34
- (1) This article applies to—
- (a) any agreement for leasing to any person the whole or any part of the authorised project or the right to operate the same; and
- (b) any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised project, or any part of it,
so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person’s use.
- (2) No enactment or rule of law regulating the rights and obligations of landlords and tenants prejudices the operation of any agreement to which this article applies.
- (3) Accordingly, no such enactment or rule of law applies in relation to the rights and obligations of the parties to any lease granted by or under any such agreement so as to—
- (a) exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;
- (b) confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or
- (c) restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.
Operational land for purposes of the 1990 Act
35
Development consent granted by this Order is treated as specific planning permission for the purposes of section 264(3)(a) of the 1990 Act (cases in which land is to be treated as not being operational land).
Felling or lopping of trees and removal of hedgerows
36
- (1) Subject to paragraph (3) and article 37 (trees subject to tree preservation orders) the undertaker may fell or lop or cut back the roots of any tree or shrub within or overhanging land within the Order limits or near any part of the authorised project, or cut back its roots, if the undertaker reasonably believes it to be necessary to do so to prevent the tree or shrub from obstructing or interfering with onshore site preparation works, the construction, maintenance or operation of the authorised project or any apparatus used in connection with the authorised project.
- (2) The undertaker may, for the purpose of the authorised project—
- (a) remove any hedgerows within the Order limits and specified in Schedule 10, Part 1 (removal of hedgerows) that may be required for the purposes of carrying out the authorised project; and
- (b) remove the important hedgerows as are within the Order limits and specified in Schedule 10, Part 2 (removal of important hedgerows).
- (3) In carrying out any activity authorised by paragraph (1), the undertaker must not do any unnecessary damage to any tree or shrub and must pay compensation to any person for any loss or damage arising from such activity.
- (4) Any dispute as to a person’s entitlement to compensation under paragraph (3), or as to the amount of compensation, must be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
- (5) In this article “hedgerow” and “important hedgerow” have the same meaning as in the Hedgerows Regulations 199744.
Trees subject to tree preservation orders
37
- (1) The undertaker may fell or lop or cut back the roots of any tree within or overhanging land within the Order limits subject to a tree preservation order as specified on the tree preservation order and hedgerow plan, if it reasonably believes it to be necessary to do so in order to prevent the tree from obstructing or interfering with onshore site preparation works, the construction, maintenance or operation of the authorised project or any apparatus used in connection with the authorised project.
- (2) In carrying out any activity authorised by paragraph (1)—
- (a) the undertaker must do no unnecessary damage to any tree and must pay compensation to any person for any loss or damage arising from such activity; and
- (b) the duty contained in section 206(1) (replacement of trees) of the 1990 Act does not apply.
- (3) The authority given by paragraph (1) constitutes a deemed consent under the relevant tree preservation order.
- (4) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, will be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
Certification of plans and documents, etc.
38
- (1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of the documents listed in Schedule 15 (documents to be certified) for certification that they are true copies of the documents referred to in this Order.
- (2) A plan or document so certified is admissible in any proceedings as evidence of the contents of the document of which it is a copy.
- (3) Where a plan or document certified under paragraph (1)—
- (a) refers to a provision of this Order (including any specified requirement) when it was in draft form; and
- (b) identifies that provision by number, or combination of numbers and letters, which is different from the number, or combination of numbers and letters by which the corresponding provision of this Order is identified in this Order as made;
the reference in the plan or document concerned must be construed for the purposes of this Order as referring to the provision (if any) corresponding to that provision in this Order as made.
Arbitration
39
- (1) Subject to article 42 (saving provisions for Trinity House), any difference under any provision of this Order, unless otherwise provided for, must be referred to and settled in arbitration in accordance with the rules at Schedule 14 (arbitration rules) of this Order, by a single arbitrator to be agreed upon by the parties, within 14 days of receipt of the notice of arbitration, or if the parties fail to agree within the time period stipulated, to be appointed on application of either party (after giving written notice to the other) by the Secretary of State.
- (2) For the avoidance of doubt, any matter for which the consent or approval of the Secretary of State or the Marine Management Organisation is required under any provision of this Order will not be subject to arbitration.
Requirements, appeals, etc.
40
- (1) Where an application is made to, or a request is made of, the relevant planning authority or any other relevant person for any agreement or approval required or contemplated by any of the provisions of this Order, such agreement or approval must, if given, be given in writing and must not be unreasonably withheld or delayed.
- (2) Part 4 of Schedule 1 (procedure for discharge of requirements) has effect in relation to all agreements or approvals granted, refused or withheld in relation to requirements included in Part 3 of that Schedule other than requirement 29.
Abatement of works abandoned or decayed
41
Where any of Work Nos. 1, 2, 3 or 5 or all of them or any part of them, is abandoned or allowed to fall into decay the Secretary of State may, following consultation with the undertaker, issue a written notice requiring the undertaker at its own expense either to repair, make safe and restore one or any of those Works, or any relevant part of them, or to remove them or any relevant part and, without prejudice to any notice served under section 105(2) of the 2004 Act45 restore the site to a safe and proper condition, to such an extent and within such limits as may be specified in the notice.
Saving provisions for Trinity House
42
Nothing in this Order prejudices or derogates from any of the rights, duties or privileges of Trinity House.
Crown rights
43
- (1) Nothing in this Order affects prejudicially any estate, right, power, privilege, authority or exemption of the Crown and in particular, nothing in this Order authorises the undertaker or any lessee or licensee to take, use, enter upon or in any manner interfere with any land or rights of any description (including any portion of the shore or bed of the sea or any river, channel, creek, bay or estuary)—
- (a) belonging to His Majesty in right of the Crown and forming part of The Crown Estate without the consent in writing of the Crown Estate Commissioners;
- (b) belonging to His Majesty in right of the Crown and not forming part of The Crown Estate without the consent in writing of the government department having the management of that land; or
- (c) belonging to a government department or held in trust for His Majesty for the purposes of a government department without the consent in writing of that government department.
- (2) Paragraph (1) does not apply to the exercise of any right under this Order for the compulsory acquisition of an interest in any Crown land (as defined in the 2008 Act) which is for the time being held otherwise than by or on behalf of the Crown.
- (3) A consent under paragraph (1) may be given unconditionally or subject to terms and conditions; and is deemed to have been given in writing where it is sent electronically.
Protective provisions
44
Schedule 9 (protective provisions) has effect.
Funding
45
- (1) The undertaker must not exercise the powers conferred by the provisions referred to in paragraph (2) in relation to any land unless it has first put in place either—
- (a) a guarantee and the amount of that guarantee approved by the Secretary of State in respect of the liabilities of the undertaker to pay compensation under this Order in respect of the exercise of the relevant power in relation to that land; or
- (b) an alternative form of security and the amount of that security for that purpose approved by the Secretary of State in respect of the liabilities of the undertaker to pay compensation under this Order in respect of the exercise of the relevant power in relation to that land.
- (2) The provisions are—
- (a) article 18 (compulsory acquisition of land);
- (b) article 21 (compulsory acquisition of rights etc.);
- (c) article 22 (private rights);
- (d) article 25 (acquisition of subsoil only);
- (e) article 27 (rights under or over streets);
- (f) article 28 (temporary use of land for carrying out the authorised project);
- (g) article 29 (temporary use of land for maintaining the authorised project); and
- (h) article 30 (statutory undertakers).
- (3) A guarantee or alternative form of security given in respect of any liability of the undertaker to pay compensation under this Order is to be treated as enforceable against the guarantor or person providing the alternative form of security by any person to whom such compensation is payable and must be in such a form as to be capable of enforcement by such a person.
- (4) Nothing in this article requires a guarantee or alternative form of security to be in place for more than 15 years after the date on which the relevant power is exercised.
Amendment and modification of statutory provisions
46
The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015 is amended for the purposes of this Order only as set out in Schedule 13 (modifications to and amendments of the Dogger Bank Cryke Beck Offshore Wind Farm Order 2015).
Service of notices
47
- (1) A notice or other document required or authorised to be served for the purposes of this Order may be served—
- (a) by post;
- (b) by delivering it to the person on whom it is to be served or to whom it is to be given or supplied; or
- (c) with the consent of the recipient and subject to paragraphs (6) to (8), by electronic transmission.
- (2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.
- (3) For the purposes of section 7 of the Interpretation Act 197846 (references to service by post) as it applies for the purposes of this article, the proper address of any person in relation to the service on that person of a notice or document under paragraph (1) is, if that person has given an address for service, that address and otherwise—
- (a) in the case of the secretary or clerk of that body corporate, the registered or principal office of that body; and
- (b) in any other case, the last known address of that person at that time of service.
- (4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having an interest in, or as the occupier of, land and the name or address of that person cannot be ascertained after reasonable enquiry, the notice may be served by—
- (a) addressing it to that person by the description of “owner”, or as the case may be “occupier” of the land (describing it); and
- (b) either leaving it in the hands of the person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.
- (5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement is to be taken to be fulfilled only where—
- (a) the recipient of the notice or other document to be transmitted has given consent to the use of electronic transmission in writing or by electronic transmission;
- (b) the notice or document is capable of being accessed by the recipient;
- (c) the notice or document is legible in all material respects; and
- (d) in a form sufficiently permanent to be used for subsequent reference.
- (6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within seven days of receipt that the recipient requires a paper copy of all or any part of that notice or other document the sender must provide such a copy as soon as reasonably practicable.
- (7) Any consent to the use of an electronic transmission by a person may be revoked by that person in accordance with paragraph (8).
- (8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—
- (a) that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and
- (b) such revocation is final and takes effect on a date specified by the person in the notice but that date must not be less than seven days after the date on which the notice is given.
- (9) This article does not exclude the employment of any method of service not expressly provided for by it.
- (10) In this article “legible in all material respects” means that the information contained in the notice or document is available to that person to no lesser extent than it would be if served, given or supplied by means of a notice or document in printed form.
Modification of Section 106 agreements relating to land
48
The undertaker will not be bound by any obligation which would fall on any owner or occupier of land which is bound by any of the section 106 agreements.
Compensation provisions
49
Schedule 16 (compensation to protect the coherence of the national site network) has effect.
SCHEDULE 1 — AUTHORISED PROJECT
PART 1 — AUTHORISED DEVELOPMENT
1
A nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act which is located in the North Sea 69 kilometres due east of Flamborough Head at its closest point, comprising—
Work No. 1—aan offshore wind turbine generating station with a gross electrical output of over 100 megawatts comprising up to 180 wind turbine generators, each fixed to the seabed by one of monopile foundations, mono suction bucket foundations or jacket foundations;bone offshore accommodation platform fixed to the seabed within the area shown on the offshore works plan by one of monopile foundations, mono suction bucket foundations, gravity base structures, box–type gravity base structures or jacket foundations, and which offshore accommodation platform may be connected to one of the offshore substations within Work No. 2 by a bridge link; andca network of cables between the wind turbine generators, and between the wind turbine generators and Work No. 2, including one or more cable crossings;and associated development within the meaning of section 115(2) (development for which development consent may be granted) of the 2008 Act comprising—
Work No. 2—aup to six small offshore transformer substations each fixed to the seabed by one of monopile foundations, mono suction bucket foundations, gravity base structures, box–type gravity base structures or jacket foundations, and which may be connected to each other or the offshore accommodation platform within Work No. 1(b) by a bridge link; orbup to three large offshore transformer substations each fixed to the seabed by one of monopile foundations, mono suction bucket foundations, jacket foundations, box–type gravity base structures, pontoon gravity base type 1 structures, or pontoon gravity base type 2 structures, and which may be connected to each other or the offshore accommodation platform within Work No. 1(b) by a bridge link;cin the event that the mode of transmission is HVDC, either up to three large HVDC converter substations or up to six small HVDC converter substations fixed to the seabed by one of monopile foundations, mono suction bucket foundations, jacket foundations, gravity base structures, box–type gravity base structures, pontoon gravity base type 1 structures, or pontoon gravity base type 2 structures;da network of interconnector cables;eup to six cable circuits between Work No. 2 and Work No. 3, and between Work No. 3 and Work No. 5 consisting of offshore export cables along routes within the Order limits seaward of MLWS including one or more cable crossings; andfup to eight temporary horizontal directional drilling exit pits and associated cofferdams;
Work No. 3— in the event that the mode of transmission is HVAC—aup to three offshore HVAC booster stations fixed to the seabed within the area shown on the offshore works plan by one of monopile foundations, mono suction bucket foundations, jacket foundations, gravity base structures, pontoon gravity base type 1 structures or pontoon gravity base type 2 structures; andbup to six cable circuits between Work No. 2 and Work No. 3, and between Work No. 3 and Work No. 5 consisting of offshore export cables along routes within the Order limits seaward of MHWS including one or more cable crossings;
2
The grid coordinates for that part of the authorised project which is seaward of MHWS are specified below—
| Point ID | Latitude (DMS) | Longitude (DMS) | Point ID | Latitude (DMS) | Longitude (DMS) |
|---|---|---|---|---|---|
| 1 | 54° 2′ 7.166″ N | 0° 12′ 58.381″ W | 68 | 53° 59′ 17.868″ N | 1° 17′ 11.556″ E |
| 2 | 54° 2′ 7.022″ N | 0° 12′ 48.680″ W | 69 | 53° 58′ 55.615″ N | 1° 16′ 14.402″ E |
| 3 | 54° 2′ 28.905″ N | 0° 12′ 23.610″ W | 70 | 53° 58′ 54.680″ N | 1° 16′ 10.907″ E |
| 4 | 54° 3′ 4.330″ N | 0° 9′ 20.564″ W | 71 | 53° 58′ 54.305″ N | 1° 16′ 7.041″ E |
| 5 | 54° 3′ 2.961″ N | 0° 8′ 57.136″ W | 72 | 53° 58′ 48.150″ N | 1° 9′ 3.489″ E |
| 6 | 54° 3′ 46.646″ N | 0° 6′ 22.355″W | 73 | 53° 58′ 49.099″ N | 1° 8′ 56.253″E |
| 7 | 54° 3′ 55.011″ N | 0° 6′ 0.668″ W | 74 | 53° 59′ 33.340″ N | 1° 5′ 22.618″ E |
| 8 | 54° 4′ 5.592″ N | 0° 5′ 7.239″ W | 75 | 53° 59′ 16.728″ N | 1° 0′ 29.597″ E |
| 9 | 54° 4′ 7.120″ N | 0° 4′ 56.079″ W | 76 | 53° 59′ 10.802″ N | 0° 59′ 53.488″ E |
| 10 | 54° 4′ 7.947″ N | 0° 4′ 12.149″ W | 77 | 53° 59′ 0.241″ N | 0° 59′ 7.651″ E |
| 11 | 54° 4′ 7.646″ N | 0° 4′ 2.450″ W | 78 | 53° 58′ 58.446″ N | 0° 58′ 57.385″ E |
| 12 | 54° 3′ 39.131″ N | 0° 1′ 17.603″ E | 79 | 53° 58′ 53.673″ N | 0° 57′ 53.130″ E |
| 13 | 54° 3′ 36.602″ N | 0° 1′ 19.983″ E | 80 | 53° 58′ 53.613″ N | 0° 57′ 45.865″ E |
| 14 | 54° 3′ 36.653″ N | 0° 1′ 27.388″ E | 81 | 53° 58′ 54.420″ N | 0° 57′ 26.213″ E |
| 15 | 54° 3′ 37.742″ N | 0° 1′ 33.117″ E | 82 | 53° 58′ 58.248″ N | 0° 56′ 45.174″ E |
| 16 | 54° 3′ 31.432″ N | 0° 2′ 43.501″ E | 83 | 53° 59′ 56.956″ N | 0° 50′ 1.171″ E |
| 17 | 54° 3′ 21.791″ N | 0° 4′ 54.431″ E | 84 | 54° 0′ 12.504″ N | 0° 48′ 1.381″ E |
| 18 | 54° 3′ 20.107″ N | 0° 5′ 29.470″ E | 85 | 54° 0′ 12.515″ N | 0° 47′ 27.367″ E |
| 19 | 54° 3′ 20.504″ N | 0° 5′ 36.188″ E | 86 | 54° 0′ 13.296″ N | 0° 46′ 40.673″ E |
| 20 | 54° 3′ 29.852″ N | 0° 6′ 6.995″ E | 87 | 54° 0′ 12.634″ N | 0° 46′ 30.459″ E |
| 21 | 54° 4′ 17.513″ N | 0° 8′ 11.780″ E | 88 | 54° 0′ 11.415″ N | 0° 46′ 24.233″ E |
| 22 | 54° 4′ 19.804″ N | 0° 8′ 20.650″ E | 89 | 53° 59′ 39.945″ N | 0° 44′ 55.026″ E |
| 23 | 54° 4′ 29.084″ N | 0° 9′ 5.618″ E | 90 | 53° 59′ 33.773″ N | 0° 44′ 35.130″ E |
| 24 | 54° 4′ 30.902″ N | 0° 9′ 18.035″ E | 91 | 53° 59′ 28.402″ N | 0° 44′ 15.020″ E |
| 25 | 54° 4′ 31.360″ N | 0° 9′ 29.006″ E | 92 | 53° 59′ 26.858″ N | 0° 44′ 5.508″ E |
| 26 | 54° 4′ 30.770″ N | 0° 11′ 14.823″ E | 93 | 53° 59′ 23.738″ N | 0° 43′ 35.842″ E |
| 27 | 54° 4′ 41.436″ N | 0° 13′ 46.313″ E | 94 | 53° 59′ 23.191″ N | 0° 42′ 42.267″ E |
| 28 | 54° 4′ 51.664″ N | 0° 18′ 10.115″ E | 95 | 53° 59′ 23.584″ N | 0° 42′ 32.090″ E |
| 29 | 54° 4′ 49.674″ N | 0° 22′ 20.794″ E | 96 | 53° 59′ 29.653″ N | 0° 41′ 39.599″ E |
| 30 | 54° 4′ 34.602″ N | 0° 25′ 8.241″ E | 97 | 53° 59′ 31.433″ N | 0° 41′ 30.497″ E |
| 31 | 54° 3′ 47.343″ N | 0° 28′ 41.594″ E | 98 | 53° 59′ 34.340″ N | 0° 41′ 20.783″ E |
| 32 | 54° 3′ 29.522″ N | 0° 29′ 45.309″ E | 99 | 54° 1′ 11.539″ N | 0° 37′ 38.060″ E |
| 33 | 54° 3′ 12.983″ N | 0° 30′ 41.496″ E | 100 | 54° 1′ 53.954″ N | 0° 30′ 4.210″ E |
| 34 | 54° 3′ 11.866″ N | 0° 30′ 46.755″ E | 101 | 54° 1′ 55.082″ N | 0° 29′ 58.960″ E |
| 35 | 54° 2′ 29.831″ N | 0° 38′ 16.384″ E | 102 | 54° 2′ 16.836″ N | 0° 28′ 45.068″ E |
| 36 | 54° 2′ 28.252″ N | 0° 38′ 27.328″ E | 103 | 54° 2′ 34.272″ N | 0° 27′ 42.729″ E |
| 37 | 54° 2′ 25.710″ N | 0° 38′ 37.464″ E | 104 | 54° 3′ 14.191″ N | 0° 24′ 52.548″ E |
| 38 | 54° 2′ 22.467″ N | 0° 38′ 46.275″ E | 105 | 54° 3′ 28.906″ N | 0° 22′ 9.330″ E |
| 39 | 54° 0′ 46.742″ N | 0° 42′ 25.062″ E | 106 | 54° 3′ 30.827″ N | 0° 18′ 25.085″ E |
| 40 | 54° 0′ 44.114″ N | 0° 42′ 47.823″ E | 107 | 54° 3′ 25.965″ N | 0° 15′ 11.395″ E |
| 41 | 54° 0′ 44.168″ N | 0° 42′ 53.983″ E | 108 | 54° 3′ 10.152″ N | 0° 11′ 26.334″ E |
| 42 | 54° 0′ 37.964″ N | 0° 43′ 8.166″ E | 109 | 54° 3′ 9.658″ N | 0° 11′ 1.640″ E |
| 43 | 54° 0′ 33.962″ N | 0° 43′ 31.109″ E | 110 | 54° 3′ 10.393″ N | 0° 9′ 39.559″ E |
| 44 | 54° 0′ 51.704″ N | 0° 44′ 6.496″ E | 111 | 54° 3′ 7.676″ N | 0° 9′ 26.386″ E |
| 45 | 54° 0′ 57.175″ N | 0° 44′ 19.901″ E | 112 | 54° 3′ 13.846″ N | 0° 8′ 47.985″ E |
| 46 | 54° 1′ 20.169″ N | 0° 45′ 45.285″ E | 113 | 54° 1′ 59.146″ N | 0° 5′ 34.054″ E |
| 47 | 54° 1′ 22.890″ N | 0° 46′ 0.288″ E | 114 | 54° 1′ 59.193″ N | 0° 5′ 24.927″ E |
| 48 | 54° 1′ 33.372″ N | 0° 47′ 34.265″ E | 115 | 54° 2′ 1.399″ N | 0° 4′ 39.525″ E |
| 49 | 54° 1′ 33.357″ N | 0° 48′ 6.711″ E | 116 | 54° 2′ 14.627″ N | 0° 1′ 34.678″ E |
| 50 | 54° 1′ 32.702″ N | 0° 48′ 19.691″ E | 117 | 54° 2′ 13.616″ N | 0° 1′ 29.370″ E |
| 51 | 54° 1′ 26.938″ N | 0° 49′ 8.341″ E | 118 | 54° 2′ 9.931″ N | 0° 1′ 16.745″ W |
| 52 | 54° 1′ 15.588″ N | 0° 50′ 33.236″ E | 119 | 54° 1′ 43.569″ N | 0° 0′ 7.896″ W |
| 53 | 54° 0′ 17.357″ N | 0° 57′ 13.969″ E | 120 | 54° 1′ 31.663″ N | 0° 0′ 25.766″ W |
| 54 | 54° 0′ 15.266″ N | 0° 57′ 36.824″ E | 121 | 54° 1′ 7.679″ N | 0° 1′ 51.463″ W |
| 55 | 54° 0′ 14.766″ N | 0° 57′ 48.644″ E | 122 | 54° 1′ 0.011″ N | 0° 2′ 21.082″ W |
| 56 | 54° 0′ 17.493″ N | 0° 58′ 26.081″ E | 123 | 54° 1′ 0.055″ N | 0° 4′ 18.699″ W |
| 57 | 54° 0′ 27.621″ N | 0° 59′ 10.323″ E | 124 | 54° 1′ 25.632″ N | 0° 12′ 25.517″ W |
| 58 | 54° 0′ 36.596″ N | 1° 0′ 6.568″ E | 125 | 54° 1′ 41.883″ N | 0° 12′ 50.086″ W |
| 59 | 54° 0′ 53.351″ N | 1° 4′ 59.324″ E | 126 | 54° 1′ 39.112″ N | 0° 12′ 50.078″ W |
| 60 | 54° 2′ 51.236″ N | 1° 8′ 18.052″ E | 127 | 54° 1′ 39.246″ N | 0° 12′ 59.069″ W |
| 61 | 54° 7′ 24.985″ N | 0° 59′ 54.702″ E | 128 | 54° 1′ 39.257″ N | 0° 12′ 59.850″ W |
| 62 | 54° 9′ 13.497″ N | 1° 0′ 43.850″ E | 129 | 54° 1′ 39.742″ N | 0° 12′ 59.821″ W |
| 63 | 54° 10′ 49.480″ N | 0° 58′ 21.782″ E | 130 | 54° 1′ 39.731″ N | 0° 12′ 59.103″ W |
| 64 | 54° 12′ 37.143″ N | 0° 58′ 31.095″ E | 131 | 54° 1′ 43.547″ N | 0° 12′ 59.118″ W |
| 65 | 54° 12′ 17.413″ N | 1° 12′ 18.263″ E | 132 | 54° 1′ 43.811″ N | 0° 12′ 59.860″ W |
| 66 | 54° 4′ 13.012″ N | 1° 30′ 5.270″ E | 133 | 54° 2′ 7.201″ N | 0° 13′ 0.387″ W |
| 67 | 53° 59′ 15.598″ N | 1° 17′ 20.651″ E |
PART 2 — ANCILLARY WORKS
1
Works within the Order limits which have been subject to an environmental impact assessment recorded in the environmental statement comprising—
- (a) temporary landing places, moorings or other means of accommodating or anchoring vessels in the construction and/or maintenance of the authorised development;
- (b) marking buoys, beacons, fenders and other navigational warning or ship impact protection works; and
- (c) temporary works for the benefit or protection of land or structures affected by the authorised development.
PART 3 — REQUIREMENTS
Time limits
1
The authorised project must not be commenced after the expiration of seven years beginning with the date this Order comes into force.
Detailed offshore design parameters
2
- (1) The total number of wind turbine generators comprised in the authorised project must not exceed 180.
- (2) Subject to sub-paragraph (3), each wind turbine generator forming part of the authorised project must not—
- (a) exceed a height of 370 metres when measured from LAT to the tip of the vertical blade;
- (b) exceed a rotor diameter of 305 metres;
- (c) be less than 42.43 metres from LAT to the lowest point of the rotating blade; and
- (d) be less than 810 metres from the nearest wind turbine generator in all directions.
- (3) The minimum distance in sub-paragraph (2)(d) between each wind turbine generator is to be measured from the centre point of the wind turbine generator.
- (4) Wind turbine generator foundation structures forming part of the authorised project must be one of either monopile foundations, mono suction bucket foundations or jacket foundations.
- (5) No wind turbine generator—
- (a) jacket foundations employing pin piles forming part of the authorised project may—
- (i) have a pin pile diameter of greater than four metres; and
- (ii) employ more than 16 pin piles per jacket foundation; and
- (b) monopile foundation forming part of the authorised project may have a diameter greater than 15 metres.
- (6) The total combined seabed footprint area for wind turbine generator foundations must not exceed—
- (a) 302,180 square metres excluding scour protection; and
- (b) 985,240 square metres including scour protection.
- (7) The wind turbine generators comprised in the authorised project must be constructed in accordance with the parameters set out in the pro–rata annex.
3
- (1) The total number of offshore electrical installations and offshore accommodation platforms must not exceed ten, consisting of a combination of no more than—
- (a) six small offshore transformer substations;
- (b) three large offshore transformer substations;
- (c) three offshore HVAC booster stations;
- (d) six small offshore HVDC converter stations;
- (e) three large offshore HVDC converter stations; and
- (f) one offshore accommodation platform.
- (2) The dimensions of any small offshore transformer substation (including auxiliary structures, such as a helipad, crane, lightning protection, but excluding masts, radar and antennae) forming part of the authorised project must not exceed—
- (a) 100 metres in height when measured from LAT;
- (b) 90 metres in length; and
- (c) 90 metres in width.
- (3) The dimensions of any large offshore transformer substation (including auxiliary structures, such as a helipad, crane, lightning protection, but excluding masts, radar and antennae) forming part of the authorised project must not exceed—
- (a) 100 metres in height when measured from LAT;
- (b) 180 metres in length; and
- (c) 90 metres in width.
- (4) The dimensions of any offshore HVAC booster station (including auxiliary structures, such as a helipad, crane, lightning protection, but excluding masts, radar and antennae) forming part of the authorised project must not exceed—
- (a) 100 metres in height when measured from LAT;
- (b) 90 metres in length; and
- (c) 90 metres in width.
- (5) The dimensions of any small offshore HVDC converter substation (including auxiliary structures, such as a helipad, crane, lightning protection, but excluding masts, radar and antennae) forming part of the authorised project must not exceed—
- (a) 90 metres in height when measured from LAT;
- (b) 100 metres in length; and
- (c) 100 metres in width.
- (6) The dimensions of any large offshore HVDC converter substation (including auxiliary structures, such as a helipad, crane, lightning protection, but excluding masts, radar and antennae) forming part of the authorised project must not exceed—
- (a) 100 metres in height when measured from LAT;
- (b) 180 metres in length; and
- (c) 90 metres in width.
- (7) The dimensions of any offshore accommodation platform forming part of the authorised project must not exceed—
- (a) 64 metres in height when measured from LAT;
- (b) 60 metres in length; and
- (c) 60 metres in width.
- (8) Offshore accommodation platform foundation structures forming part of the authorised project must be one of either monopile foundations, mono suction bucket foundations, gravity base structures, jacket foundations or box–type gravity base structures.
- (9) Offshore electrical installation foundation structures forming part of the authorised project must be one of the following foundation options—
- (a) for small offshore transformer substations and offshore HVAC booster stations either monopile foundations, mono suction bucket foundations, jacket foundations, gravity base structures or box–type gravity base structures; and
- (b) for large offshore transformer substations and offshore HVDC converter stations either monopile foundations, mono suction bucket foundations, jacket foundations, box–type gravity base structures, gravity base structures, pontoon gravity base type 1 structures, or pontoon gravity base type 2 structures.
- (10) No offshore electrical installation or offshore accommodation platform—
- (a) jacket foundation employing pin piles forming part of the authorised project may—
- (i) have a pin pile diameter of greater than four metres; and
- (ii) employ more than 16 pin piles per jacket foundation; and
- (b) monopile foundation forming part of the authorised project may have a diameter greater than 15 metres.
- (11) The total seabed footprint area for offshore accommodation platform foundations must not exceed—
- (a) 5,625 square metres excluding scour protection; and
- (b) 30,625 square metres including scour protection.
- (12) The total seabed footprint area for offshore electrical installation foundations must not exceed—
- (a) 101,250 square metres excluding scour protection; and
- (b) 371,250 square metres including scour protection.
- (13) The total number of gravity base structures may not exceed ten for offshore electrical installations and offshore accommodation platforms.
- (14) The offshore electrical installations and offshore accommodation platform comprised in the authorised project must be constructed in accordance with parameters set out in the pro–rata annex.
- (15) A bridge link forming part of the authorised development must be installed at a minimum height of 20 metres when measured from LAT.
4
The total volume of scour protection for wind turbine generators, offshore accommodation platform and offshore electrical installations may not exceed 2,172,040 cubic metres and must be in accordance with the pro–rata annex.
5
- (1) The number of cable circuits must not exceed six.
- (2) The cables comprising Work No. 1(c) must not—
- (a) exceed 600 kilometres in length; and
- (b) be subject to cable protection with an area greater than 624,000 square metres.
- (3) The cables comprising Work No. 2(d) must not—
- (a) exceed 90 kilometres in length; and
- (b) be subject to cable protection with an area greater than 94,000 square metres.
- (4) The cables comprising Work No. 2(e) must not—
- (a) exceed 654 kilometres in length; and
- (b) be subject to cable protection with an area greater than 792,000 square metres.
- (5) The total number of the cable crossings must not exceed—
- (a) 32 within the area of Work Nos. 1 and 2(d); and
- (b) 54 within the area utilised for Work No. 2(e);
unless otherwise agreed with the MMO.
- (6) The total volume of cable protection must not exceed 2,042,000 cubic metres with a maximum footprint of 2,058,000 square metres.
- (7) The cables and cable circuits comprised in the authorised development must be constructed in accordance with the parameters set out in the pro–rata annex.
Biodiversity net gain
6
- (1) No stage of the connection works in Work No. 7 may commence until a net gain strategy (which must accord with the outline net gain strategy) in relation to that stage has been submitted to and approved by the relevant planning authority, in consultation with the relevant SNCBs.
- (2) The net gain strategy must be implemented as approved.
Detailed design approval onshore
7
- (1) Construction of Work No. 7(a) and (b) may not commence until detailed plans and drawings of—
- (a) the layout;
- (b) scale;
- (c) proposed finished ground levels;
- (d) external appearance and materials;
- (e) hard surfacing materials;
- (f) vehicular and pedestrian access, parking and circulation areas;
- (g) minor structures, such as furniture, refuse or other storage units, signs and lighting;
- (h) proposed and existing functional services above and below ground, including drainage, power and communications cables and pipelines, manholes and supports; and
- (i) means to control operational noise from Work No. 7 to a level no greater than 5dB above representative background (LA90,T) at the nearest identified noise sensitive receptors;
relating to that work of the authorised project have been submitted to and approved by the relevant planning authority.
- (2) The details submitted under sub-paragraph (1) must be in accordance with the outline design plan.
- (3) The details submitted under sub-paragraph (1) must be subject to a design review process carried out by an independent design review panel to the satisfaction of the relevant planning authority.
- (4) Work No. 7(a) and (b) must be carried out in accordance with the approved details.
- (5) Work No. 7(a) and (b) may not commence until confirmation of the choice of HVDC or HVAC or a combination of both has been provided to the relevant planning authority, either before, or at the same time as, the details referred to in sub–paragraph (1).
Provision of landscaping
8
- (1) No stage of the connection works may commence until a written landscape management plan and associated work programme (which accords with the outline landscape management plan and outline ecological management plan) for that stage of the connection works has been submitted to and approved by the relevant planning authority in consultation with the relevant SNCBs and Historic England.
- (2) The landscape management plan must include details of—
- (a) surveys, assessments and method statements as guided by BS 5837 and the Hedgerows Regulations 1997;
- (b) location, number, species, size and planting density of any proposed planting;
- (c) cultivation, importing of materials and other operations to ensure plant establishment; and
- (d) implementation timetables for the relevant stage of the landscaping works.
- (3) The landscape management plan must be carried out as approved.
Implementation and maintenance of landscaping
9
- (1) All landscape works must be carried out in accordance with the landscape management plans approved under requirement 8 (provision of landscaping), and in accordance with the relevant recommendations of appropriate British Standards.
- (2) Unless otherwise stated in the approved landscape management plan or enhancement strategy approved under requirement 23, any tree or shrub planted as part of an approved landscape management plan that, within a period of five years after planting, is removed by the undertaker, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased must be replaced in the first available planting season with a specimen of the same species and size as that originally planted unless otherwise approved by the relevant planning authority.
- (3) Unless otherwise stated in the approved landscape management plan or enhancement strategy, within a period of five years after completion of the planting of the approved landscape works comprising Work No. 7(f), a landscape management and maintenance plan for Work No. 7(f) must be submitted to and approved by the relevant planning authority.
- (4) The landscape management and maintenance plan for Work No. 7(f) must include details of the management and maintenance of Work No. 7(f) until the connection works are decommissioned in accordance with the onshore decommissioning plan approved under requirement 25 (onshore decommissioning).
- (5) The landscape management and maintenance plan for Work No. 7(f) must be carried out as approved.
Ecological management plan
10
- (1) No stage of the connection works may commence until a written ecological management plan (which accords with the outline ecological management plan and the relevant recommendations of appropriate British Standards) for that stage of the connection works reflecting the survey results and ecological mitigation has been submitted to and approved by the relevant planning authority in consultation with the relevant SNCBs and (where works have potential to impact wetland habitats) the Environment Agency.
- (2) The ecological management plan must include an implementation timetable for the relevant stage of the connection works and must be carried out as approved.
Highway accesses
11
- (1) Construction of any new permanent or temporary means of access to a highway, or alteration, or use of an existing means of access to a highway, must not commence until an access plan for that access has been submitted to and approved by the relevant highway authority.
- (2) The access plan must include details of the siting, design, layout, visibility splays, access management measures, lighting, signing, safety measures and a maintenance programme relevant to the access it relates to.
- (3) The highway accesses (including visibility splays) must be constructed and maintained in accordance with the approved details.
Fencing and other means of permanent enclosure
12
- (1) No stage of the connection works may commence until details of all proposed permanent fences, walls or other means of enclosure of that stage of the connection works have been submitted to and approved by the relevant planning authority.
- (2) The details submitted under paragraph (1) must be in accordance with the outline design plan.
- (3) Any approved permanent fencing in relation to the connection works in Work No. 7 must be completed before those works are brought into use and must be maintained until the connection works are decommissioned in accordance with the onshore decommissioning plan approved under requirement 25 (onshore decommissioning).
Temporary fencing and other temporary means of enclosure
13
- (1) The details of any temporary fences, walls, or other means of enclosure required for the construction of the connection works must be included in the code of construction practice approved under requirement 18 (which must accord with the outline code of construction practice).
- (2) All construction sites must remain securely enclosed at all times during construction of the connection works in accordance with the details approved under sub-paragraph (1) above.
- (3) The temporary fencing or other temporary means of enclosure must be removed on completion of that stage of the connection works to the satisfaction of the relevant planning authority.
Surface and foul water drainage
14
- (1) No stage of the connection works may commence until written details of the surface and (if any) foul water drainage system (including means of pollution control) (which must accord with the outline onshore infrastructure drainage strategy) for the construction of that stage of the connection works have, after consultation with the relevant sewerage and drainage authorities and the Environment Agency, been submitted to and approved by the lead local flood authority.
- (2) No stage of the connection works may commence operation until written details of the surface and (if any) foul water drainage system (including means of pollution control) for that stage of the connection works have, after consultation with the relevant sewerage and drainage authorities and the Environment Agency, been submitted to and approved by the lead local flood authority.
- (3) The surface and foul water drainage system must be constructed, operated and maintained in accordance with the approved details.
Contaminated land and groundwater scheme
15
- (1) No stage of the connection works or Work No. 5 may commence until a written scheme to deal with the contamination of any land (including groundwater) of that stage of the connection works or Work No. 5 within the Order limits that is likely to cause significant harm to persons or pollution of controlled waters or the environment has been submitted to, and approved by, the relevant planning authority in consultation with the Environment Agency and, to the extent that the plan relates to the intertidal area, the MMO.
- (2) The scheme must include an investigation and assessment report, to identify the extent of any contamination and the remedial measures to be taken for that stage to render the land fit for its intended purpose, together with a management plan which sets out long-term measures with respect to any contaminants remaining on the site.
- (3) Such remediation as may be identified in the approved scheme must be carried out in accordance with the approved scheme.
Surface water
16
- (1) No stage of the connection works in Work No. 7 may commence until, in respect of that installation, a detailed surface water scheme has been prepared in consultation with the relevant sewerage and drainage authorities and the Environment Agency and submitted to and approved by the lead local flood authority.
- (2) The detailed surface water schemes must accord with the outline onshore infrastructure drainage strategy and—
- (a) be based on sustainable drainage principles;
- (b) include an assessment of the hydrological and hydrogeological context of the connection works in Work No. 7; and
- (c) include detailed designs of a surface water drainage scheme.
- (3) Construction of the connection works in Work No. 7 must be carried out in accordance with the approved scheme.
Onshore archaeology
17
- (1) No stage of the connection works or Work No. 5 may commence until a written scheme of archaeological investigation (which must accord with the outline written scheme of investigation for onshore archaeology) for that stage of the connection works or Work No. 5 has been submitted to and approved by the relevant planning authority in consultation with Historic England.
- (2) Archaeological investigations carried out as part of onshore site preparation works must only take place in accordance with a specific written scheme of investigation (which must accord with the outline written scheme of investigation for onshore archaeology) which has been submitted to and approved by the relevant planning authority in consultation with Historic England.
- (3) All archaeological investigations (other than archaeological investigations carried out as part of onshore site preparation works referred to in sub-paragraph (2)) must be carried out in accordance with the written scheme of archaeological investigation approved under sub-paragraph (1).
- (4) The archaeological site investigations and post investigation assessment must be completed in accordance with the programme set out in the written scheme of archaeological investigation and provision made for analysis, publication and dissemination of results and archive deposition.
Code of construction practice
18
- (1) No stage of the connection works, Work No. 2 (f) or Work No. 5 may commence until a code of construction practice (which must accord with the outline code of construction practice but may not include the outline construction traffic management plan in the event that the outline construction traffic management plan has been, or is in the process of being, approved separately pursuant to requirement 19) for that stage of the connection works has been submitted to and approved by the relevant planning authority, in consultation with the Environment Agency, the relevant SNCBs and, if applicable, the MMO.
- (2) All connection works must be undertaken in accordance with the relevant approved code of construction practice.
Construction traffic management plan
19
- (1) No stage of the connection works or Work No. 5 may commence until written details of a construction traffic management plan (which accords with the outline construction traffic management plan) for that stage of the connection works or Work No. 5 has been submitted to and approved by the relevant planning authority in consultation with the relevant highway authorities (and approved by Network Rail in accordance with paragraph 5 of Part 4 of Schedule 9).
- (2) The construction traffic management plan must be implemented as approved.
European protected species onshore
20
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.