The Electricity (Standards of Performance) (Amendment) Regulations 2023

Type Statutory-Instrument
Publication 2023-07-31
State In force
Department King's Printer of Acts of Parliament
articles Not indexed
Reform history JSON API PDF

Made: 31st July 2023

Coming into force in accordance with regulation 1

The Secretary of State has consented to making these Regulations in accordance with sections 39(1) and 39A(1) of the Act.

Citation, commencement and interpretation

1

Amendments to the Principal Regulations

2

(2) For the purposes of calculating and making compensation payments under regulations 5, 6, 7 and 8, where supply is interrupted to a directly connected premises, and the relevant electricity distributor is not a designated electricity distributor, that interruption is deemed to have been caused by the same category of event applicable to the designated electricity distributor in whose distribution services area that relevant electricity distributor operates.

(21A) (1) The prescribed sums for each financial year beginning with 1 April 2024 are calculated by— (a) adjusting the sums specified in columns 3 and 4 of Part 1 of Schedule 2 by the percentage increase or decrease in the CPIH index published for the month of January preceding the financial year for which the adjustment is made in comparison to the CPIH index published for the month of January 2023; and (b) rounding the resulting figure to the nearest £5. (2) In the calculation of prescribed caps for each financial year beginning with 1 April 2024, the sums in column 2 of Part 1A of Schedule 2 are adjusted by— (a) the percentage increase or decrease in the CPIH index published for the month of January preceding the financial year for which the adjustment is made in comparison to the CPIH index published for the month of January 2023; and (b) rounding the resulting figure to the nearest £5. (3) In this regulation, “CPIH index” means the consumer prices index including owner occupiers’ housing costs (all items) published by the Office for National Statistics.

(1) Regulation (2) Prescribed period (3) Prescribed sum domestic customers(£) (4) Prescribed sum non-domestic customers(£)
5(2)(a) 12 hours 90 175
5(2)(b) 12 hours 40 40
6(2)(a) 24 hours 90 175
6(2)(b) 12 hours 40 40
7(4)(a) 24 hours 80 80
7(4)(b) 6 hours 40 40
7(5)(a) 48 hours 80 80
7(5)(b) 6 hours 40 40
8(2) 24 hours 90 175
10(4) a relevant year 90 90
11(3) three hours on a working day, four hours on any other day 35 35
12(4) 2 days 35 70
12(5) 5 days 35 70
12(6) 2 days 35 70
13(2) 7 working days 35 35
13(4)(a) not applicable 35 35
13(4)(b) 5 working days 35 35
17(3)(b) not applicable 35 35
17(4)(b) not applicable 35 35
19(4) 10 working days 35 35
19(5) 10 working days 35 35
(1) Regulation (2) Sum (3) Multiplier (4) Prescribed Cap
6(2)(b) 90 4 £360
7(4)(b) 80 25 £2000
7(5)(b) 80 25 £2000
(1) Designated electricity distributor (2) Eight times the mean daily faults at distribution higher voltage (3) Thirteen times the mean daily faults at distribution higher voltage
ENWL 55 89
NPGN 37 60
NPGY 42 68
WMID 68 111
EMID 54 88
SWALES 43 70
SWEST 71 115
LPN 17 28
SPN 66 107
EPN 94 152
SPD 72 116
SPMW 66 108
SSEH 67 109
SSES 78 127

Amendment to Connection Regulations

3

(17A) (1) The prescribed sums for each financial year beginning with 1 April 2024 are calculated by – (a) adjusting the sums specified in column 3 of Schedule 1 by the percentage increase or decrease in the CPIH index published for the month of January preceding the financial year for which the adjustment is made in comparison to the CPIH index published for the month of January 2023; and (b) rounding the resulting figure to the nearest £5. (2) In this regulation, “CPIH” means the consumer prices index including owner occupiers’ housing costs (all items) published by the Office for National Statistics.

(1) Regulation (2) Prescribed period (3) Prescribed sum (4) Payment Date
4(2) 10 working days £75 the working day on which the budget estimate should have been dispatched
4(3) 20 working days £75 the working day on which the budget estimate should have been dispatched
5(2) 5 working days £20 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched the working day on which the quotation is dispatched
5(3) 15 working days £20 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched the working day on which the quotation is dispatched
6(2) 25 working days £75 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched the working day on which the quotation is dispatched
6(3) 35 working days £160 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched the working day on which the quotation is dispatched
6(4) 65 working days £235 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched the working day on which the quotation is dispatched
7(3) not applicable £395 the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete
7(4) not applicable £785 the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete
8(2) 7 working days £20 for each working day after the end of the prescribed period up to and including the day on which contact occurs the working day on which contact occurs
8(3) the agreed date £40 for each working day after the agreed date up to and including the day on which the works are completed the working day on which the works are completed
9(2) 7 working days £75 for each working day after the end of the prescribed period up to and including the day on which contact occurs the working day on which contact occurs
9(3) 10 working days £160 for each working day after the end of the prescribed period up to and including the day on which contact occurs the working day on which contact occurs
9(4) 15 working days £235 for each working day after the end of the prescribed period up to and including the day on which contact occurs the working day on which contact occurs
9(5) the agreed date £30 for each working day after the agreed date up to and including the day on which the works at the premises are commenced the working day on which the works at the premises are commenced
9(6) the agreed date £160 for each working day after the agreed date up to and including the day on which the works are completed the working day on which the works are completed
9(7) the agreed date £235 for each working day after the agreed date up to and including the day on which the works are completed the working day on which the works are completed
9(8) the agreed date £315 for each working day after the agreed date up to and including the day on which the works are completed the working day on which the works are completed
9(9) the agreed date £160 for each working day after the agreed date up to and including the day on which energisation occurs the working day on which energisation occurs
9(10) the agreed date £235 for each working day after the agreed date up to and including the day on which energisation occurs the working day on which energisation occurs
9(11) the agreed date £315 for each working day after the agreed date up to and including the day on which energisation occurs the working day on which energisation occurs
10(2) 2 hours £75 the working day after the day on which the emergency attendance should have taken place
10(3) 2 calendar days £20 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed the working day on which the fault rectification works are completed
10(4) 10 working days £20 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed the working day on which the fault rectification works are completed
10(5) 20 working days £20 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed the working day on which the fault rectification works are completed
10(6) 25 working days £20 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed the working day on which the fault rectification works are completed
11(2) 25 working days £20 for each working day after the end of the prescribed period up to and including the day the quotation is dispatched the working day on which the quotation is dispatched
12(2) the agreed date £20 for each working day after the agreed date up to and including the day on which the works are completed the working day on which the works are completed
12(3) 35 working days £20 for each working day after the end of the prescribed period up to and including the day on which the works are completed the working day on which the works are completed
14(1) 10 working days £75 not applicable

Signed

The seal of the Gas and Electricity Markets Authority here affixed is authenticated by the signature of

John Crackett — A member of the Gas and Electricity Markets Authority — 13th July 2023

I consent

Graham Stuart — Minister of State — Department for Energy Security and Net Zero — 31st July 2023

Explanatory note

(This note is not part of the Regulations)

EXPLANATORY NOTE

These Regulations amend the Electricity (Standards of Performance) Regulations 2015 (S.I. 2005/699), which prescribe the sums that electricity suppliers and distributors must pay to a customer by way of compensation for failure to meet specified standards of performance in respect of the services to be provided by such suppliers or distributors, subject to certain exemptions.

The main changes are—

These Regulations amend the Electricity (Connection Standards of Performance) Regulations 2015 (S.I. 2015/698), which prescribe the sum that an electricity distributor must pay to a customer or relevant authority as appropriate by way of compensation for failure to meet specified standards of performance in respect of the connection services to be provided by electricity distributor.

The main changes are—

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.