The A38 Derby Junctions Development Consent Order 2023
| (1) | (2) | (3) |
|---|---|---|
| Plot reference number shown on land plans | Purpose for which rights over land may be acquired | Relevant part of the authorised development |
| Land Plans – Sheet 1 | Land Plans – Sheet 1 | Land Plans – Sheet 1 |
| 1/3a | Required for the establishment and maintenance of environmental mitigation and enhancement areas | Work No. 8 |
| 1/3b | Required for the establishment and maintenance of environmental mitigation and enhancement areas and the diversion and maintenance of and access to utilities and the establishment and maintenance of flood storage areas | Work No. 1, 8 and 9 |
| 1/4b | Required for the establishment of environmental mitigation and enhancement and the diversion and maintenance of and access to utilities | Work No. 8 and 9 |
| Land Plans – Sheet 2 | Land Plans – Sheet 2 | Land Plans – Sheet 2 |
| 2/1b | Required for the diversion and maintenance of and access to utilities and the establishment and maintenance of environmental mitigation and enhancement | Work No. 8 and 9 |
| 2/1c | Required for the construction of a diverge slip road and for the establishment of environmental mitigation and enhancement areas and the construction of highway drainage attenuation | Work No. 2 and 8 |
| 2/1f | Required for the construction of a cycle track and the diversion and maintenance of and access to utilities | Work No. 3 and 9 |
| 2/1o | Required for the construction and reconfiguration of the junction between Lyttelton Street and Kingsway Park Close and the diversion and maintenance and access to utilities | Work No. 7 and 9 |
| 2/1p | Required for the construction and reconfiguration of the junction between Lyttelton Street and Kingsway Park Close and the diversion and maintenance and access to utilities | Work No. 7 and 9 |
| 2/7a and 2/8 | Required for the diversion construction and maintenance of a cycle track | Work No. 3 |
| 2/9 | Required for the construction and maintenance of a cycle track and the diversion and maintenance of and access to utilities | Work No. 3 and 9 |
| 2/13a | Required to construct a link road and the diversion and maintenance and access to utilities | Work No. 7 and 9 |
| 2/19a | Required to construct a link road and the diversion and maintenance of and access to utilities and the construction of footways | Work No. 7 and 9 |
| 2/19b | Required to construct a link road and the diversion and maintenance of and access to utilities and the reconfiguration of Lyttelton junction | Work No. 7 and 9 |
| Land Plans – Sheet 3 | Land Plans – Sheet 3 | Land Plans – Sheet 3 |
| 3/1p and 3/1q | Required for the construction of a northbound diverge slip road and the diversion and maintenance of and access to utilities and the stopping up of the Enfield Road entry and exit roads | Work No. 11 and 22 |
| 3/1w and 3/1x | Required for the diversion and maintenance of and access to a utility corridor and construction of a new emergency access | Work No. 16 and 21 |
| 3/5a | Required for the alteration, realignment and grading of highway; the construction, improvement and realignment of cycle track and the diversion and maintenance of and access to utilities | Work No. 10, 15 and 22 |
| 3/9b | Required for alterations to the access to and egress from the filling station and fast-food site and the diversion and maintenance of utilities | Work No. 16 and 22 |
| 3/16a, 3/17 and 3/19 | Required for the construction and alteration of a private means of access | Work No. 16 |
| 3/22b | Required for the construction of a southbound diverge slip and alteration realignment and grading of highway and the construction and maintenance of a noise barrier and alterations to the access to and egress from the A52 to the Royal School for the Deaf | Work No. 13 and 16 |
| Land Plans – Sheet 4 | Land Plans – Sheet 4 | Land Plans – Sheet 4 |
| 4/1b | Required for the diversion and maintenance of and access to a utility corridor and for the demolition of a footbridge and replacement of a footbridge | Work No. 10 and 21 |
| 4/1d | Required for the alteration, realignment and grading of a highway | Work No. 10, 21 and 22 |
| 4/7b | Required for the construction and maintenance of a noise barrier | Work No. 13 |
| Land Plans – Sheet 6 | Land Plans – Sheet 6 | Land Plans – Sheet 6 |
| 6/2 | Required for the construction and maintenance of a flood plain compensation area and the diversion and maintenance of and access to utilities | Work No. 31 |
| Land Plans – Sheet 7 | Land Plans – Sheet 7 | Land Plans – Sheet 7 |
| 7/5 | Required for the construction and maintenance of a flood plain compensation area and the diversion and maintenance of and access to utilities | Work No. 31 |
| Land Plans – Sheet 8 | Land Plans – Sheet 8 | Land Plans – Sheet 8 |
| 8/6 | Required for the access construction and maintenance of a railbridge | Work No. 23 |
| 8/23b, 8/25c and 8/21 | Required for the diversion and maintenance of and access to utilities | Work No. 35 |
| Land Plans – Sheet 9 | Land Plans – Sheet 9 | Land Plans – Sheet 9 |
| 9/6b | Required for the alteration, realignment and grading of northbound and southbound carriageways, the construction of a southbound diverge slip road and the diversion and maintenance of and access to utilities | Work No. 23, 26 and 35 |
SCHEDULE 6 — MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS AND IMPOSITION OF RESTRICTIVE COVENANTS
Compensation enactments
1
The enactments for the time being in force with respect to compensation for the compulsory purchase of land apply, with the necessary modifications as respects compensation, in the case of a compulsory acquisition under this Order of a right by the creation of a new right or imposition of a restrictive covenant as they apply as respects compensation for the compulsory purchase of land and interests in land.
2
- (1) Without limitation on the scope of paragraph 1, the 1961 Act has effect subject to the modification set out in sub-paragraph (2).
- (2) For section 5A(5A) (relevant valuation date) of the 1961 Act substitute—
(5A) If— (a) the acquiring authority enters on land for the purposes of exercising a right in pursuance of a notice of entry under section 11(1) of the 1965 Act (as modified by paragraph 5(5) of Schedule 6 to the A38 Derby Junctions Development Consent Order 2023 (the “A38 Derby Junctions Order”)); (b) the acquiring authority is subsequently required by a determination under paragraph 12 of Schedule 2A to the 1965 Act (as substituted by paragraph 5(8) of Schedule 6 to the A38 Derby Junctions Order) to acquire an interest in the land; and (c) the acquiring authority enter on and take possession of that land, the authority is deemed for the purposes of subsection (3)(a) to have entered on that land when it entered on that land for the purpose of exercising that right.
3
- (1) Without limitation on the scope of paragraph 1, the Land Compensation Act 1973[^f00092] has effect subject to the modifications set out in sub-paragraph (2).
- (2) In section 44(1) (compensation for injurious affection), as it applies to compensation for injurious affection under section 7 (measure of compensation in case of severance) of the 1965 Act as substituted by paragraph 5(3)—
- (a) for “land is acquired or taken from” substitute “a right or restrictive covenant over land is purchased from or imposed on”; and
- (b) for “acquired or taken from him” substitute “over which the right is exercisable or the restrictive covenant enforceable”.
Application of Part 1 of the 1965 Act
4
Part 1 (compulsory purchase under Acquisition of Land Act 1946) of the 1965 Act, as applied by section 125 (application of compulsory acquisition provisions) of the 2008 Act (and modified by article 29 (modification of Part 1 of the 1965 Act)) to the acquisition of land under article 23 (compulsory acquisition of land), applies to the compulsory acquisition of a right by the creation of a new right, or to the imposition of a restrictive covenant under article 26(1) (compulsory acquisition of rights)—
- (a) with the modifications specified in paragraph 5; and
- (b) with such other modifications as may be necessary.
5
- (1) The modifications referred to in paragraph 4(a) are as follows.
- (2) References in the 1965 Act to land are, in the appropriate contexts, to be read (according to the requirements of the particular context) as referring to, or as including references to—
- (a) the right acquired or to be acquired, or the restriction imposed or to be imposed; or
- (b) the land over which the right is or is to be exercisable, or the restriction is or is to be enforceable.
- (3) For section 7 (measure of compensation in case of severance) of the 1965 Act substitute—
(7) In assessing the compensation to be paid by the acquiring authority under this Act, regard must be had not only to the extent (if any) to which the value of the land over which the right is to be acquired or the restrictive covenant is to be imposed is depreciated by the acquisition of the right but also to the damage (if any) to be sustained by the owner of the land by reason of its severance from other land of the owner, or injuriously affecting that other land by the exercise of the powers conferred by this or the special Act.
- (4) The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say—
- (a) section 9(4) (failure by owners to convey);
- (b) paragraph 10(3) of Schedule 1 (owners under incapacity);
- (c) paragraph 2(3) of Schedule 2 (absent and untraced owners); and
- (d) paragraphs 2(3) and 7(2) of Schedule 4 (common land),
are modified so as to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be compulsorily acquired or the restrictive covenant which is to be imposed is vested absolutely in the acquiring authority.
- (5) Section 11[^f00093] (powers of entry) of the 1965 Act is modified so as to secure that, where the acquiring authority has served notice to treat in respect of any right or restrictive covenant, as well as the notice of entry required by subsection (1) of that section (as it applies to a compulsory acquisition under article 23), it has power, exercisable in equivalent circumstances and subject to equivalent conditions, to enter for the purpose of exercising that right or enforcing that restrictive covenant; and sections 11A[^f00094] (powers of entry: further notices of entry), 11B[^f00095] (counter-notice requiring possession to be taken on specified date), 12[^f00096] (unauthorised entry) and 13[^f00097] (refusal to give possession to acquiring authority) of the 1965 Act are modified correspondingly.
- (6) Section 20[^f00098] (tenants at will, etc.) of the 1965 Act applies with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right or the enforcement of the restrictive covenant in question.
- (7) Section 22 (interests omitted from purchase) of the 1965 Act as modified by article 29(4) is also modified so as to enable the acquiring authority in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired, subject to compliance with that section as respects compensation.
- (8) For Schedule 2A of the 1965 Act substitute—
SCHEDULE 2A (1) (1) This Schedule applies where an acquiring authority serves a notice to treat in respect of a right over, or a restrictive covenant affecting, the whole or part of a house, building or factory and have not executed a general vesting declaration under section 4 of the 1981 Act as applied by article 30 (application of the 1981 Act) of the A38 Derby Junctions Development Consent Order 2023 in respect of the land to which the notice to treat relates. (2) But see article 31(3) (acquisition of subsoil or airspace only) of the A38 Derby Junctions Development Consent Order 2023 which excludes the acquisition of subsoil or airspace only from this Schedule. (2) In this Schedule, “house” includes any park or garden belonging to a house. (3) A person who is able to sell the house, building or factory (“the owner”) may serve a counter-notice requiring the acquiring authority to purchase the owner’s interest in the house, building or factory. (4) A counter-notice under paragraph 3 must be served within the period of 28 days beginning with the day on which the notice to treat was served. (5) On receiving a counter-notice, the acquiring authority must decide whether to— (a) withdraw the notice to treat, (b) accept the counter-notice, or (c) refer the counter-notice to the Upper Tribunal. (6) The authority must serve notice of their decision on the owner within the period of 3 months beginning with the day on which the counter-notice is served (“the decision period”). (7) If the authority decide to refer the counter-notice to the Upper Tribunal they must do so within the decision period. (8) If the authority do not serve notice of a decision within the decision period they are to be treated as if they had served notice of a decision to withdraw the notice to treat at the end of that period. (9) If the authority serve notice of a decision to accept the counter-notice, the compulsory purchase order and the notice to treat are to have effect as if they included the owner’s interest in the house, building or factory. (10) On a referral under paragraph 7, the Upper Tribunal must determine whether the acquisition of the right of the imposition of the restrictive covenant would— (a) in the case of a house, building or factory, cause material detriment to the house, building or factory, or (b) in the case of a park or garden, seriously affect the amenity or convenience of the house to which the park or garden belongs. (11) In making the determination, the Upper Tribunal must take into account— (a) the effect of the acquisition of the right or the imposition of the covenant, (b) the use to be made of the right or covenant proposed to be acquired or imposed, and (c) if the right or covenant is proposed to be acquired or imposed for works or other purposes extending to other land, the effect of the whole of the works and the use of the other land. (12) If the Upper Tribunal determines that the acquisition of the right or the imposition of the covenant would have either of the consequences described in paragraph 10, it must determine how much of the house, building or factory the acquiring authority ought to be required to take. (13) If the Upper Tribunal determines that the acquiring authority ought to be required to take some or all of the house, building or factory, the compulsory purchase order and the notice to treat are to have effect as if they included the owner’s interest in that land. (14) (1) If the Upper Tribunal determines that the acquiring authority ought to be required to take some or all of the house, building or factory, the acquiring authority may at any time within the period of 6 weeks beginning with the day on which the Upper Tribunal makes its determination withdraw the notice to treat in relation to that land. (2) If the acquiring authority withdraws the notice to treat under this paragraph it must pay the person on whom the notice was served compensation for any loss or expense caused by the giving and withdrawing of the notice. (15) Any dispute as to the compensation is to be determined by the Upper Tribunal.
SCHEDULE 7 — LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
| (1) | (2) | (3) |
|---|---|---|
| Plot Reference Number shown on land plans | Purpose for which temporary possession may be taken | Relevant part of the authorised development |
| Land Plans – Sheet 1 | Land Plans – Sheet 1 | Land Plans – Sheet 1 |
| 1/3c | Required for the establishment of environmental mitigation and enhancement | Work No. 8 |
| 1/4a | Required for the establishment of environmental mitigation and enhancement | Work No. 8 |
| Land Plans – Sheet 2 | Land Plans – Sheet 2 | Land Plans – Sheet 2 |
| 2/1a | Required for the establishment of environmental mitigation and enhancement | Work No. 8 |
| 2/1d | Required for the construction of a northbound merge slip road and construction and realignment of a cycle track | Work No. 3 |
| 2/1n | Required for the construction of a link road and the construction and maintenance of a noise barrier | Work No. 7 |
| 2/1r | Required for the widening of the Brackensdale Avenue east and west underbridges, the alteration of part of the entry and exit lanes off Brackensdale Avenue which connects to the A38 and the reconfiguration of the existing junction between Lyttelton Street and Kingsway Park Close | Work No. 1 and 7 |
| 2/1s | Required for the alteration of part of the entry and exit lanes off Brackensdale Avenue which connects to the A38 and works to effect the stopping up of part of the entry and exit lanes off Brackensdale Avenue which connect to the A38 | Work No. 1 |
| 2/1t | Required for works to effect the stopping up of part of the entry and exit lanes off Brackensdale Avenue which connect to the A38 | Work No. 1 |
| 2/1u | Required for the alteration, realignment and grading of highway | Work No. 1 |
| 2/3 | Required for the establishment of environmental mitigation and enhancement | Work No. 8 |
| 2/6 | Required for the construction of a cycle track and establishment of environmental mitigation and enhancement | Work No. 3 and 8 |
| 2/13c | Required to construct a link road | Work No. 7 |
| Land Plans – Sheet 3 | Land Plans – Sheet 3 | Land Plans – Sheet 3 |
| 3/1aa | Required for the diversion and construction of a utility corridor | Work No. 21 |
| 3/1b, 3/1c and 3/1d | Required for the alteration, realignment and grading of the A38 | Work No. 10 |
| 3/1g and 3/1h | Required for works to effect the stopping up of the entry and exit lanes of Raleigh Street which connect to the A38; and the improvement and realignment of a cycle track | Work No. 1 and 15 |
| 3/1i | Required for the alteration, realignment and grading of highway and the construction, improvement and realignment of a cycle track | Work No. 10 and 15 |
| 3/1j | Required for the alteration, realignment and grading of the A38 | Work No. 10 |
| 3/1n | Required for the construction of the A38 and the northbound diverge slip road | Work No. 10 and 11 |
| 3/1t and 3/8b | Required for alterations to the access and egress from the filling station and fast-food site | Work No. 16 |
| 3/1v | Required for the construction of a new junction for access to and egress from Markeaton Park including a roundabout and a park & ride bus stop; works to effect the stopping up of the entrance to Markeaton Park; new emergency access from Markeaton Park and relocation of the boundary wall to Markeaton Park | Work No. 16 |
| 3/4 | Required for the alteration, realignment and grading of highway and the construction, improvement and realignment of the existing cycle track and access to undertake utility diversion works | Work No. 10, 15 and 22 |
| 3/5b | Required for the alteration, realignment and grading of highway and the construction of a southbound merge slip road | Work No. 10 and 14 |
| 3/5d | Required for the construction of a temporary construction compound | Work No. 19 |
| 3/8a and 3/9a | Required for amendments to the access to and egress from the filling station and fast-food site | Work No. 11 |
| 3/15a | Required for the construction and alteration of a private means of access | Work No. 16 |
| Land Plans – Sheet 4 | Land Plans – Sheet 4 | Land Plans – Sheet 4 |
| 4/1c | Required for the construction of a southbound merge slip road and access to undertake utility diversion works | Work No. 14 and 21 |
| 4/1f | Required for the establishment of environmental mitigation and enhancement areas | Work No. 20 |
| 4/1h and 4/7d | Required to establish environmental mitigation and enhancement areas | Work No. 20 |
| 4/13b | Required for the establishment of environmental mitigation and enhancement areas | Work No. 20 |
| Land Plans – Sheet 5 | Land Plans – Sheet 5 | Land Plans – Sheet 5 |
| 5/1 and 5/2 | Required to establish environmental mitigation and enhancement areas | Work No. 20 |
| Land Plans – Sheet 7 | Land Plans – Sheet 7 | Land Plans – Sheet 7 |
| 7/1a, 7/1b, 7/2, 7/1d and7/1c | Required for the reconfiguration of highway and a junction | Work No. 34 |
| 7/1f and 7/12 | Required for the realignment of Ford Land and the reconfiguration of the junction with Lambourn Drive and the alteration of Ford Lane Bridge | Work No. 29 and 33 |
| 7/6, 7/7a and 7/7b | Required for the construction of flood compensation area | Work No. 31 |
| 7/17a | Required for the alteration, realignment and grading of carriageway and the construction of a southbound merge slip road and works to effect the stopping up and diversion of a section of a footpath and works to effect the stopping up and diversion of a private means of access | Work No. 23 and 27 |
| 7/14 | Required for the alteration, realignment and grading of the carriageway and the construction of a southbound merge slip road | Work No. 23 and 27 |
| 7/17c | Required for the alteration, realignment and grading of the northbound and southbound lanes of the carriageway and the southbound merge slip road | Work No. 23 and 27 |
| 7/9, 7/8, 7/1e, 7/10 and 7/11 | Required for the realignment of Ford Lane and the reconfiguration of the junction with Lambourn Drive | Work No. 33 |
| 7/1g | Required for the establishment of environmental mitigation areas | Work No. 37 |
| 7/1h and 7/1i | Required for alterations to a bridge on Ford Lane | Work No. 29 |
| 7/1j and 7/13 | Required for works to stop up a highway and carry out works on a bridge | Work No. 28 and 29 |
| Land Plans – Sheet 8 | Land Plans – Sheet 8 | Land Plans – Sheet 8 |
| 8/1 | Required for the erection and accommodation of a temporary works compound | Work No. 32 |
| 8/2, 8/3a and 8/3c | Required for the alteration, realignment and grading of the northbound and southbound carriageways and the construction of a southbound merge slip road | Work No. 23 and 27 |
| 8/5 and 8/8 | Required for the alteration, realignment and grading of the northbound and southbound carriageway and alteration and extension to an existing railway bridge | Work No. 23 |
| 8/18 and 8/19 | Required for the realignment and grading of Ford Lane to connect to the Little Eaton Roundabout | Work No. 30 |
| 8/10b | Required for the alteration, realignment and grading of the northbound and southbound lanes, construction of a southbound merge slip road and the alteration, realignment and grading of carriageway | Work No. 23, 27 and 30 |
| 8/10c and 8/11 | Required for the construction of a southbound diverge slip road and the alteration, realignment and grading of carriageway | Work No. 26 and 30 |
| 8/4h, 8/15, 8/16b, 8/24b and 8/25b | Required for the alteration, realignment and grading of northbound and southbound carriageway, construction of a southbound diverge slip road and the erection and accommodation of a works compound | Work No. 23 and 26 |
| Land Plans – Sheet 9 | Land Plans – Sheet 9 | Land Plans – Sheet 9 |
| 9/1, 9/2, 9/3 and 9/4 | Required for the erection and accommodation of a temporary works compound | Work No. 32 |
SCHEDULE 8 — TREES SUBJECT TO TREE PRESERVATION ORDERS
| (1) | (2) | (3) |
|---|---|---|
| Name of Order/Type of tree | Work to be carried out | Relevant part of the authorised development |
| Land at Royal School for the Deaf, Land at the R.S.D Ashbourne Road, Derby (TPO No. 456) | Tree Removal | Work No. 13 |
| Northern boundary of playing field and adjacent to 32 Queensway, Royal School for the Deaf (160) | Tree Removal | Work No. 13 |
| Land to the north and east of Queensway, Land to the north of Markeaton Street (116) | Tree Removal | Work No. 10 |
| Land at Sturgess Fields (197) | Tree Removal | Work No. 10 |
SCHEDULE 9 — PROTECTIVE PROVISIONS
PART 1 — FOR THE PROTECTION OF ELECTRICITY, WATER AND SEWERAGE UNDERTAKERS
1
For the protection of the utility undertakers referred to in this Part of this Schedule the following provisions have effect, unless otherwise agreed in writing between the undertaker and the utility undertaker concerned.
2
In this Part of this Schedule—
- “alternative apparatus” means alternative apparatus adequate to enable the utility undertaker in question to fulfil its statutory function in a manner no less efficient than previously;
- “apparatus” means— in the case of an electricity undertaker, electric lines or electrical plant (as defined in the Electricity Act 1989[^f00099], belonging to or maintained by that utility undertaker; in the case of a water undertaker, mains, pipes or other apparatus belonging to or maintained by that utility undertaker for the purposes of water supply; and in the case of a sewerage undertaker— any drain or works vested in the utility undertaker under the Water Industry Act 1991[^f00100]; and any sewer which is so vested or is the subject of a notice of intention to adopt given under section 102(4)[^f00101] (adoption of sewers and disposal works) of that Act or an agreement to adopt made under section 104[^f00102] (agreements to adopt sewer, drain or sewage disposal works, at future date) of that Act, and includes a sludge main, disposal main (within the meaning of section 219 (general interpretation) of that Act) or sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part of any such sewer, drain or works, and includes any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus;
- “functions” includes powers and duties;
- “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over or upon land;
- “plan” includes all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the works to be executed; and
- “utility undertaker” means— any licence holder within the meaning of Part 1 of the Electricity Act 1989; a water undertaker within the meaning of the Water Industry Act 1991; and a sewerage undertaker within the meaning of Part 1 of the Water Industry Act 1991, for the area of the authorised development, and in relation to any apparatus, means the utility undertaker to whom it belongs or by whom it is maintained.
On street apparatus
3
This Part of this Schedule does not apply to apparatus in respect of which the relations between the undertaker and the utility undertaker are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act.
Apparatus in stopped up streets
4
- (1) Where any street is stopped up under article 16 (permanent stopping up and restriction of use of streets and private means of access), any utility undertaker whose apparatus is in the street has the same powers and rights in respect of that apparatus as it enjoyed immediately before the stopping up and the undertaker must grant to the utility undertaker legal easements reasonably satisfactory to the utility undertaker in respect of such apparatus and access to it, but nothing in this paragraph affects any right of the undertaker or of the utility undertaker to require the removal of that apparatus under paragraph 7 or the power of the undertaker to carry out works under paragraph 9.
- (2) Regardless of the temporary stopping up or diversion of any highway under the powers conferred by article 15 (temporary stopping up and restriction of use of streets), a utility undertaker is at liberty at all times to take all necessary access across any such stopped up highway and to execute and do all such works and things in, upon or under any such highway as may be reasonably necessary or desirable to enable it to maintain any apparatus which at the time of the stopping up or diversion was in that highway.
Protective works to buildings
5
The undertaker, in the case of the powers conferred by article 21 (protective works to buildings), must exercise those powers so as not to obstruct or render less convenient the access to any apparatus.
Acquisition of land
6
Regardless of any provision in this Order or anything shown on the land plans, the undertaker must not acquire any apparatus otherwise than by agreement.
Removal of apparatus
7
- (1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed or requires that the utility undertaker’s apparatus is relocated or diverted, that apparatus must not be removed under this Part of this Schedule, and any right of a utility undertaker to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed and is in operation to the reasonable satisfaction of the utility undertaker in question in accordance with sub-paragraphs (2) to (7).
- (2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, the undertaker must give to the utility undertaker in question 28 days’ written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order a utility undertaker reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to the utility undertaker the necessary facilities and rights for the construction of alternative apparatus in other land of the undertaker and subsequently for the maintenance of that apparatus.
- (3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed, the utility undertaker in question must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible use its best endeavours to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.
- (4) Any alternative apparatus to be constructed in land of the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between the utility undertaker in question and the undertaker or in default of agreement settled by arbitration in accordance with article 48 (arbitration).
- (5) The utility undertaker in question must, after the alternative apparatus to be provided or constructed has been agreed or settled by arbitration in accordance with article 48 (arbitration), and after the grant to the utility undertaker of any such facilities and rights as are referred to in sub-paragraph (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
- (6) Regardless of anything in sub-paragraph (5), if the undertaker gives notice in writing to the utility undertaker in question that the undertaker desires itself to execute any work, or part of any work in connection with the construction or removal of apparatus in any land of the undertaker, that work, instead of being executed by the utility undertaker, must be executed by the undertaker without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of the utility undertaker.
- (7) Nothing in sub-paragraph (6) authorises the undertaker to execute the placing, installation, bedding, packing, removal, connection or disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is laid in a trench) within 300 millimetres of the apparatus.
Facilities and rights for alternative apparatus
8
- (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to a utility undertaker facilities and rights for the construction and maintenance in land of the undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities and rights are to be granted upon such terms and conditions as may be agreed between the undertaker and the utility undertaker in question or in default of agreement settled by arbitration in accordance with article 48 (arbitration).
- (2) If the facilities and rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are in the opinion of the arbitrator less favourable on the whole to the utility undertaker in question than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the arbitrator must make such provision for the payment of compensation by the undertaker to that utility undertaker as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
Retained apparatus
9
- (1) Not less than 28 days before starting the execution of any works in, on or under any land purchased, held, appropriated or used under this Order that are near to, or will or may affect, any apparatus the removal of which has not been required by the undertaker under paragraph 7(2), the undertaker must submit to the utility undertaker in question a plan of the works to be executed.
- (2) Those works must be executed only in accordance with the plan submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by the utility undertaker for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and the utility undertaker is entitled to watch and inspect the execution of those works.
- (3) Any requirements made by a utility undertaker under sub-paragraph (2) are to be made within a period of 21 days beginning with the date on which a plan under sub-paragraph (1) is submitted to it.
- (4) If a utility undertaker, in accordance with sub-paragraph (3) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 1 to 3 and 6 to 8 apply as if the removal of the apparatus had been required by the undertaker under paragraph 7(2).
- (5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan instead of the plan previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.
- (6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to the utility undertaker in question notice as soon as is reasonably practicable and a plan of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (3) in so far as is reasonably practicable in the circumstances.
- (7) In relation to works which will or may be situated on, over, under or within 10 metres measured in any direction of any electricity apparatus, the plan to be submitted to the utility undertaker under sub-paragraph (1) must be detailed, include a method statement and describe—
- (a) the exact position of the works;
- (b) the level at which they are proposed to be constructed or renewed;
- (c) the manner of their construction or renewal;
- (d) the position of all electricity apparatus; and
- (e) by way of detailed drawings, every alteration proposed to be made to such apparatus.
Expenses and costs
10
- (1) Subject to the following provisions of this paragraph, the undertaker must repay to a utility undertaker all expenses reasonably incurred by that utility undertaker in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to in paragraph 7(2).
- (2) The value of any apparatus removed under the provisions of this Part of this Schedule must be deducted from any sum payable under sub-paragraph (1), that value being calculated after removal.
- (3) If in accordance with the provisions of this Part of this Schedule—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 48 (arbitration) to be necessary then, if such placing involves cost exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to the utility undertaker in question by virtue of sub-paragraph (1) must be reduced by the amount of that excess.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus must not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
- (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole must be treated as if it also had been agreed or had been so determined.
- (5) An amount which apart from this sub-paragraph would be payable to a utility undertaker in respect of works by virtue of sub-paragraph (1), if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the utility undertaker any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, is to be reduced by the amount which represents that benefit.
11
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works referred to in paragraphs 5 or 7(2) any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of a utility undertaker, or there is any interruption in any service provided, or in the supply of any goods, by any utility undertaker, the undertaker must—
- (a) bear and pay the cost reasonably incurred by that utility undertaker in making good such damage or restoring the supply; and
- (b) make reasonable compensation to that utility undertaker for any other expenses, loss, damages, penalty or costs incurred by the utility undertaker,
by reason or in consequence of any such damage or interruption.
- (2) The fact that any act or thing may have been done by a utility undertaker on behalf of the undertaker or in accordance with a plan approved by a utility undertaker or in accordance with any requirement of a utility undertaker or under its supervision does not, subject to sub-paragraph (3), excuse the undertaker from liability under the provisions of sub-paragraph (1).
- (3) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of a utility undertaker, its officers, servants, contractors or agents.
- (4) A utility undertaker must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made without the consent of the undertaker and, if such consent is withheld, the undertaker has the sole conduct of any settlement or compromise of any proceedings necessary to resist the claim or demand.
Co-operation
12
Where in consequence of the proposed construction of any part of the authorised development, the undertaker or a utility undertaker requires the removal of apparatus under paragraph 7(2) or a utility undertaker makes requirements for the protection or alteration of apparatus under paragraph 9, the undertaker must use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of the utility undertaker’s undertaking and each utility undertaker must use its best endeavours to co-operate with the undertaker for that purpose.
13
Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and a utility undertaker in respect of any apparatus in land belonging to the undertaker on the date on which this Order is made.
PART 2 — FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
14
For the protection of any operator, the following provisions have effect, unless otherwise agreed in writing between the undertaker and the operator.
15
In this Part of this Schedule—
- “the 2003 Act” means the Communications Act 2003[^f00103];
- “electronic communications apparatus” has the same meaning as in the electronic communications code;
- “the electronic communications code” has the same meaning as in section 106[^f00104] (application of the electronic communications code) of the 2003 Act;
- “electronic communications code network” means— so much of an electronic communications network or infrastructure system provided by an electronic communications code operator as is not excluded from the application of the electronic communications code by a direction under section 106 of the 2003 Act; and an electronic communications network which the undertaker is providing or proposing to provide;
- “electronic communications code operator” means a person in whose case the electronic communications code is applied by a direction under section 106 of the 2003 Act;
- “infrastructure system” has the same meaning as in the electronic communications code and references to providing an infrastructure system are to be construed in accordance with paragraph 7(2) of that code; and
- “operator” means the operator of an electronic communications code network.
16
The exercise of the powers conferred by article 35 (statutory undertakers) is subject to Part 10 (undertaker’s works affecting electronic communications apparatus) of the electronic communications code.
17
- (1) Subject to sub-paragraphs (2) to (4), if as a result of the authorised development or its construction, or of any subsidence resulting from the authorised development—
- (a) any damage is caused to any electronic communications apparatus belonging to an operator (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised development), or other property of an operator; or
- (b) there is any interruption in the supply of the service provided by an operator,
the undertaker must bear and pay the cost reasonably incurred by the operator in making good such damage or restoring the supply and make reasonable compensation to that operator for any other expenses, loss, damages, penalty or costs incurred by it by reason, or in consequence of, any such damage or interruption.
- (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of an operator, its officers, servants, contractors or agents.
- (3) The operator must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise of the claim or demand is to be made without the consent of the undertaker and, if such consent is withheld, the undertaker has the sole conduct of any settlement or compromise of any proceedings necessary to resist the claim or demand.
- (4) Any difference arising between the undertaker and the operator under this Part of this Schedule must be referred to and settled by arbitration under article 48 (arbitration).
- (5) This Part of this Schedule does not apply to—
- (a) any apparatus in respect of which the relations between the undertaker and an operator are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act; or
- (b) any damages, or any interruptions, caused by electro-magnetic interference arising from the construction or use of the authorised development.
- (6) Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and an operator in respect of any apparatus in land belonging to the undertaker on the date on which this Order is made.
PART 3 — FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
18
- (1) The following provisions apply for the protection of the Agency unless otherwise agreed in writing between the undertaker and the Agency.
- (2) In this Part of this Schedule—
- “the Agency” means the Environment Agency;
- “construction” includes executing, placing, altering, replacing, relaying, removing and excavating and “construct” and “constructed” shall be construed accordingly;
- “drainage work” means any main river and includes any land which provides or is expected to provide flood storage capacity for any main river and any bank, wall, embankment or other structure, or any appliance, constructed or used for land drainage, flood defence or tidal monitoring;
- “fishery” means any waters containing fish and fish in, or migrating to or from, such waters and the spawn, spawning ground, habitat or food of such fish;
- “main river” means all watercourses shown as such on the statutory main river maps held by the Agency and the Department for Environment Food and Rural Affairs including any structure or appliance for controlling or regulating the flow of water in or out of the channel;
- “plans” includes sections, drawings, specifications, calculations and method statements;
- “specified work” means so much of any work or operation authorised by this Order as is in, on, under, over or within 8 metres of a drainage work or is otherwise likely to— affect any drainage work or the volumetric rate of flow of water in or flowing to or from any drainage work; affect the flow, purity or quality of water in any watercourse or other surface waters or ground water; cause obstruction to the free passage of fish or damage to any fishery; affect the conservation, distribution or use of water resources; or affect the conservation value of the main river and habitats in its immediate vicinity;
- “watercourse” includes all rivers, streams, ditches, drains, cuts, culverts, dykes, sluices, basins, sewers and passages through which water flows except a public sewer.
19
- (1) Before beginning to construct any specified work, the undertaker must submit to the Agency plans of the specified work and such further particulars available to it as the Agency may within 28 days of the receipt of the plans reasonably request.
- (2) Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by the Agency, or determined under paragraph 28.
- (3) Any approval of the Agency required under this paragraph—
- (a) must not be unreasonably withheld or delayed;
- (b) in the case of a refusal must be accompanied by a statement of grounds of refusal;
- (c) is deemed to have been refused if it is neither given nor refused within 2 months of the submission of the plans or receipt of further particulars if such particulars have been requested by the Agency for approval; and
- (d) may be given subject to such reasonable requirements as the Agency may have for the protection of any drainage work, fishery or water resources, or for the prevention of flooding or pollution or in the discharge of its environmental duties.
- (4) The Agency must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (3)(c).
20
Without limiting paragraph 19, the requirements which the Agency may have under that paragraph include conditions requiring the undertaker, at its own expense, to construct such protective works, whether temporary or permanent, before or during the construction of the specified works (including the provision of flood banks, walls or embankments or other new works and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably necessary—
- (a) to safeguard any drainage work against damage; or
- (b) to secure that its efficiency for flood defence purposes is not impaired and that the risk of flooding is not otherwise increased,
by reason of any specified work.
21
- (1) Subject to sub-paragraph (2), any specified work, and all protective works required by the Agency under paragraph 20, must be constructed—
- (a) without unreasonable delay in accordance with the plans approved or settled under this Part of this Schedule; and
- (b) to the reasonable satisfaction of the Agency,
and the Agency shall be entitled by its officer to watch and inspect the construction of such works.
- (2) The undertaker must give to the Agency not less than 14 days’ notice in writing of its intention to commence construction of any specified work and notice in writing of its completion not later than 7 days after the date on which it is completed.
- (3) If the Agency reasonably requires, the undertaker must construct all or part of the protective works so that they are in place prior to the construction of the specified work to which the protective works relate.
- (4) If any part of a specified work or any protective work required by the Agency is constructed otherwise than in accordance with the requirements of this Part of this Schedule, the Agency may by notice in writing require the undertaker at the undertaker’s own expense to comply with the requirements of this Part of this Schedule or (if the undertaker so elects and the Agency in writing consents, such consent not to be unreasonably withheld or delayed) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent and within such limits as the Agency reasonably requires.
- (5) Subject to sub-paragraph (6), if within a reasonable period, being not less than 28 days beginning with the date when a notice under sub-paragraph (4) is served upon the undertaker, the undertaker has failed to begin taking steps to comply with the requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, the Agency may execute the works specified in the notice and any reasonable expenditure incurred by the Agency in so doing shall be recoverable from the undertaker.
- (6) In the event of any dispute as to whether sub-paragraph (4) is properly applicable to any work in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, the Agency shall not, except in the case of an emergency, exercise the powers conferred by sub-paragraph (5) until the dispute has been finally determined in accordance with paragraph 28.
22
- (1) Subject to sub-paragraph (7) the undertaker must from the commencement of the construction of the specified works until the date falling 12 months from the date of completion of those works (“the maintenance period”), maintain in good repair and condition and free from obstruction any drainage work which is situated within the limits of deviation and on land held by the undertaker for the purposes of or in connection with the specified works, whether or not the drainage work is constructed under the powers conferred by this Order or is already in existence.
- (2) Upon the expiry of the maintenance period, the drainage work must be maintained by the highway authority of the highway to which the specified work relates.
- (3) If any such drainage work which the undertaker is liable to maintain is not maintained to the reasonable satisfaction of the Agency, the Agency may by notice in writing require the person liable for maintenance to repair and restore the work, or any part of such work, or (if the person liable for maintenance so elects and the Agency in writing consents, such consent not to be unreasonably withheld or delayed), to remove the specified work and restore the site to its former condition, to such extent and within such limits as the Agency reasonably requires.
- (4) Subject to sub-paragraph (6), if, within a reasonable period, being not less than 28 days beginning with the date on which a notice in respect of any drainage work is served under sub-paragraph (3) on the person liable for maintenance, the person has failed to begin taking steps to comply with the reasonable requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, the Agency may do what is reasonably necessary for such compliance and any reasonable expenditure incurred by the Agency in so doing shall be recoverable from that person.
- (5) If there is any failure by the undertaker to obtain consent or comply with conditions imposed by the Agency in accordance with these protective provisions the Agency may serve written notice requiring the undertaker to cease all or part of the specified works and the undertaker must cease the specified works or part thereof until it has obtained the consent or complied with the condition unless the cessation of the specified works or part thereof would cause greater damage than compliance with the written notice.
- (6) In the event of any dispute as to the reasonableness of any requirement of a notice served under sub-paragraph (3), the Agency shall not, except in the case of an emergency, exercise the powers conferred by sub-paragraph (4) until the dispute has been finally determined in accordance with paragraph 28.
- (7) This paragraph does not apply to—
- (a) drainage works which are vested in the Agency, or which the Agency or another person is liable to maintain and is not proscribed by the powers of this Order from doing so; or
- (b) any obstruction of a drainage work for the purpose of a work or operation authorised by this Order and carried out in accordance with the provisions of this Part of this Schedule.
23
If by reason of the construction of any specified work or of the failure of any such work, the efficiency of any drainage work for flood defence purposes is impaired, or that drainage work is otherwise damaged, such impairment or damage must be made good by the undertaker to the reasonable satisfaction of the Agency and if the undertaker fails to do so, the Agency may make good the impairment or damage and recover any expenditure reasonably incurred by the Agency in so doing from the undertaker.
24
If by reason of construction of a specified work the Agency’s access to flood defences or equipment maintained for flood defence purposes is materially obstructed, the undertaker must provide such alternative means of access that will allow the Agency to maintain the flood defence or use the equipment no less effectively than was possible before the obstruction within 24 hours of the undertaker becoming aware of such obstruction.
25
- (1) The undertaker must take all such measures as may be reasonably practicable to prevent any interruption of the free passage of fish in a fishery during the construction of any specified work.
- (2) If by reason of—
- (a) the construction of any specified work; or
- (b) the failure of any such work,
damage to a fishery is caused, or the Agency has reason to expect that such damage may be caused, the Agency may serve notice on the undertaker requiring it to take such steps as may be reasonably practicable to make good the damage, or, as the case may be, to protect the fishery against such damage.
- (3) If within such time as may be reasonably practicable for that purpose after the receipt of written notice from the Agency of any damage or expected damage to a fishery, the undertaker fails to take such steps as are required under sub-paragraph (2), the Agency may take those steps and any expenditure reasonably incurred by the Agency in so doing shall be recoverable from the undertaker.
- (4) In any case where immediate action by the Agency is reasonably required in order to secure that the risk of damage to the fishery is avoided or reduced, the Agency may take such steps as are reasonable for the purpose, and may recover from the undertaker any reasonable expenditure reasonably incurred in so doing provided that notice specifying those steps is served on the undertaker as soon as reasonably practicable after the Agency has taken, or commenced to take, the steps specified in the notice.
26
The undertaker must repay to the Agency all reasonable costs, charges and expenses which the Agency may reasonably incur—
- (a) in the examination or approval of plans under this Part of this Schedule;
- (b) in the inspection of the construction of the specified works or any protective works required by the Agency under this Part of this Schedule; and
- (c) in the carrying out of any surveys or tests by the Agency which are reasonably required in connection with the construction of the specified works.
27
- (1) The undertaker must make reasonable compensation for costs and losses which may be reasonably incurred or suffered by the Agency by reason of—
- (a) the construction of any specified works comprised within the authorised works; or
- (b) any act or omission of the undertaker, its employees, contractors or agents or other whilst engaged upon the construction of the authorised works.
- (2) For the avoidance of doubt, in sub-paragraph (1)—
- “costs” includes— expenses and charges; staff costs and overheads; and legal costs;
- “losses” includes physical damage.
- (3) The undertaker must make reasonable compensation for liabilities, claims and demands arising out of or in connection with the authorised development or otherwise out of the matters referred to in sub-paragraph (1)(a) and (b).
- (4) For the avoidance of doubt, in sub-paragraph (3)—
- “claims” and “demands” include as applicable— costs (within the meaning of sub-paragraph (2)) incurred in connection with any claim or demand; and any interest element of sums claimed or demanded;
- “liabilities” includes— contractual liabilities; tortious liabilities (including liabilities for negligence or nuisance); liabilities to pay statutory compensation or for breach of statutory duty; and liabilities to pay statutory penalties imposed on the basis of strict liability (but does not include liabilities to pay other statutory penalties).
- (5) The Agency must give to the undertaker reasonable written notice of any such claim or demand.
- (6) The undertaker may at its own expense conduct all negotiations for the settlement of the same and any litigation that may arise therefrom.
- (7) The Agency must not compromise or settle any such claim or demand or make any admission which might be prejudicial to the claim or demand without the agreement of the undertaker which agreement must not be unreasonably withheld or delayed.
- (8) The Agency must at all times take reasonable steps to prevent and mitigate any such claims, demands, proceedings, costs, damages, expenses or losses.
- (9) The Agency must, at the request of the undertaker, afford all reasonable assistance for the purpose of contesting any such claim or action, and is entitled to be repaid its reasonable expenses reasonably incurred in so doing.
- (10) The fact that any work or thing has been executed or done by the undertaker in accordance with a plan approved by the Agency, or to its satisfaction, or in accordance with any directions or award of an arbitrator, shall not relieve the undertaker from any liability under the provisions of this Part of this Schedule.
- (11) Nothing in this paragraph imposes any liability on the undertaker with respect to any costs, charges, expenses, damages, claims, demands or losses to the extent they are attributable to the neglect or default of the Agency, its officers, servants, contractors or agents.
28
Any dispute arising between the undertaker and the Agency under this Part of this Schedule will, if the parties agree, be determined by arbitration under article 48 (arbitration), but will otherwise be determined by the Secretary of State for Environment, Food and Rural Affairs or its successor and the Secretary of State for Transport or its successor acting jointly on a reference to them by the undertaker or the Agency, after notice in writing by one to the other.
PART 4 — FOR THE PROTECTION OF NETWORK RAIL
29
The following provisions of this Part of this Schedule have effect, unless otherwise agreed in writing between the undertaker and Network Rail and, in the case of paragraph 43, any other person on whom rights or obligations are conferred by that paragraph.
30
In this Part of this Schedule—
- “construction” includes execution, placing, alteration and reconstruction and “construct” and “constructed” have corresponding meanings;
- “the engineer” means an engineer appointed by Network Rail for the purposes of this Order;
- “network licence” means the network licence, as the same is amended from time to time, granted to Network Rail by the Secretary of State in exercise of their powers under section 8 (licences) of the Railways Act 1993[^f00105];
- “Network Rail” means Network Rail Infrastructure Limited (company number 02904587, whose registered office is at 1 Eversholt Street, London NW1 2DN) and any associated company of Network Rail Infrastructure Limited which holds property for railway purposes, and for the purpose of this definition “associated company” means any company which is (within the meaning of section 1159 (meaning of “subsidiary” etc.) of the Companies Act 2006[^f00106]) the holding company of Network Rail Infrastructure Limited, a subsidiary of Network Rail Infrastructure Limited or another subsidiary of the holding company of Network Rail Infrastructure Limited;
- “plans” includes sections, designs, design data, software, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of railway property;
- “protective works” means any works specified by the engineer under paragraph 33(4);
- “railway operational procedures” means procedures specified under any access agreement (as defined in the Railways Act 1993) or station lease;
- “railway property” means any railway belonging to Network Rail and— any station, land, works, apparatus and equipment belonging to Network Rail or connected with any such railway; and any easement or other property interest held or used by Network Rail for the purposes of such railway or works, apparatus or equipment; and
- “specified work” means so much of any of the authorised development as is or is to be situated upon, across, under, over or within 15 metres of, or may in any way adversely affect, railway property.
31
- (1) Where under this Part of this Schedule Network Rail is required to give its consent, or approval in respect of any matter, that consent, or approval is subject to the condition that Network Rail complies with any relevant railway operational procedures and any obligations under its network licence or under statute.
- (2) In so far as any specified work or the acquisition or use of railway property is or may be subject to railway operational procedures, Network Rail must—
- (a) co-operate with the undertaker with a view to avoiding undue delay and securing conformity as between any plans approved by the engineer and requirements emanating from those procedures; and
- (b) use its reasonable endeavours to avoid any conflict arising between the application of those procedures and the proper implementation of the authorised development pursuant to this Order.
32
- (1) The undertaker must not exercise the powers conferred by—
- (a) article 15 (temporary stopping up and restriction of use of streets);
- (b) article 16 (permanent stopping up and restriction of use of streets and private means of access);
- (c) article 17 (access to works);
- (d) article 20 (discharge of water);
- (e) article 21 (protective works to buildings);
- (f) article 22 (authority to survey and investigate the land);
- (g) article 23 (compulsory acquisition of land);
- (h) article 26 (compulsory acquisition of rights);
- (i) article 28 (private rights over land);
- (j) article 31 (acquisition of subsoil or airspace only);
- (k) article 32 (rights under or over streets);
- (l) article 33 (temporary use of land for carrying out the authorised development);
- (m) article 34 (temporary use of land for maintaining the authorised development);
- (n) article 35 (statutory undertakers);
- (o) article 39 (felling or lopping of trees and removal of hedgerows); and
- (p) article 40 (trees subject to tree preservation orders),
or the powers conferred by section 11(3) (powers of entry) of the 1965 Act or the 1981 Act as applied by this Order, in respect of any railway property unless the exercise of such powers is with the consent of Network Rail.
- (2) The undertaker must not in the exercise of the powers conferred by this Order prevent pedestrian or vehicular access to any railway property, unless preventing such access is with the consent of Network Rail.
- (3) The undertaker must not exercise the powers conferred by sections 271 (extinguishment of rights of statutory undertakers: preliminary notices) or 272 (extinguishment of rights of electronic communications code network operators: preliminary notices) of the 1990 Act or article 35 (statutory undertakers) in relation to any right of access of Network Rail to railway property, but such right of access may be extinguished or diverted with the consent of Network Rail.
- (4) The undertaker must not under the powers of this Order acquire or use or acquire new rights over any railway property except with the consent of Network Rail.
- (5) Where Network Rail is asked to give its consent under this paragraph, such consent must not be unreasonably withheld but may be given subject to reasonable conditions.
33
- (1) The undertaker must before commencing construction of any specified work supply to Network Rail proper and sufficient plans of that work for the reasonable approval of the engineer and the specified work must not be commenced except in accordance with such plans as have been approved in writing by the engineer or settled by arbitration under article 48 (arbitration).
- (2) The approval of the engineer under sub-paragraph (1) must not be unreasonably withheld, and if by the end of the period of 28 days beginning with the date on which such plans have been supplied to Network Rail the engineer has not communicated disapproval of those plans and the grounds of disapproval the undertaker may serve upon the engineer written notice requiring the engineer to communicate approval or disapproval within a further period of 28 days beginning with the date upon which the engineer receives written notice from the undertaker. If by the expiry of the further 28 days the engineer has not communicated approval or disapproval, the engineer is deemed to have approved the plans as submitted.
- (3) If by the end of the period of 28 days beginning with the date on which written notice was served upon the engineer under sub-paragraph (2), Network Rail gives notice to the undertaker that Network Rail desires itself to construct any part of a specified work which in the opinion of the engineer will or may affect the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker desires such part of the specified work to be constructed, Network Rail must construct it without unnecessary delay on behalf of and to the reasonable satisfaction of the undertaker in accordance with the plans approved or deemed to be approved or settled under this paragraph, and under the supervision (where appropriate and if given) of the undertaker.
- (4) When signifying approval of the plans the engineer may specify any protective works (whether temporary or permanent) which in the engineer’s reasonable opinion should be carried out before the commencement of the construction of a specified work to ensure the safety or stability of railway property or the continuation of safe and efficient operation of the railways of Network Rail or the services of operators using the same (including any relocation decommissioning and removal of works, apparatus and equipment necessitated by a specified work and the comfort and safety of passengers who may be affected by the specified works), and such protective works as may be reasonably necessary for those purposes must be constructed by Network Rail or by the undertaker, if Network Rail so desires, and such protective works must be carried out at the expense of the undertaker in either case without unnecessary delay and the undertaker must not commence the construction of the specified works in question until the engineer has notified the undertaker that the protective works have been completed to the engineer’s reasonable satisfaction.
34
- (1) Any specified work and any protective works to be constructed by virtue of paragraph 33(4) must, when commenced, be constructed—
- (a) without unnecessary delay in accordance with the plans approved or deemed to have been approved or settled under paragraph 33;
- (b) under the supervision (where appropriate and if given) and to the reasonable satisfaction of the engineer;
- (c) in such manner as to cause as little damage as is possible to railway property; and
- (d) so far as is reasonably practicable, so as not to interfere with or obstruct the free, uninterrupted and safe use of any railway of Network Rail or the traffic on it and the use by passengers of railway property.
- (2) If any damage to railway property or any such interference or obstruction is caused by the carrying out of, or in consequence of the construction of a specified work or a protective work, the undertaker must, regardless of any such approval, make good such damage and must pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may sustain by reason of any such damage, interference or obstruction.
- (3) Nothing in this Part of this Schedule imposes any liability on the undertaker with respect to any damage, costs, expenses or loss attributable to the negligence of Network Rail or its employees, contractors or agents or any liability on Network Rail with respect to any damage, costs, expenses or loss attributable to the negligence of the undertaker or its employees, contractors or agents.
35
The undertaker must—
- (a) at all times afford reasonable facilities to the engineer for access to a specified work or a protective work during its construction; and
- (b) supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or a protective work or the method of constructing it.
36
Network Rail must at all times afford reasonable facilities to the undertaker and its employees, contractors or agents for access to any works carried out by Network Rail under this Part of this Schedule during their construction and must supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them.
37
- (1) If any permanent or temporary alterations or additions to railway property are reasonably necessary in consequence of the construction of a specified work or a protective work, or during a period of 24 months after the completion of that work in order to ensure the safety of railway property or the continued safe operation of the railway of Network Rail, such alterations or additions may be carried out by Network Rail and if Network Rail gives to the undertaker reasonable notice of its intention to carry out such alterations or additions (which must be specified in the notice), the undertaker must pay to Network Rail the reasonable cost of those alterations or additions including, in respect of any such alterations or additions as are to be permanent, a capitalised sum representing the increase of the costs which are expected to be reasonably incurred by Network Rail in maintaining, working and, when necessary, renewing any such alterations or additions.
- (2) If during the construction of a specified work or a protective work by the undertaker, Network Rail gives notice to the undertaker that Network Rail desires itself to construct that part of the specified work or the protective work which in the opinion of the engineer is endangering the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker decides that part of the specified work or the protective work is to be constructed, Network Rail must assume construction of that part of the specified work or protective work and the undertaker must, regardless of any approval of the specified work or protective work in question under paragraph 33, pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may suffer by reason of the execution by Network Rail of that specified work or protective work.
- (3) The engineer must, in respect of the capitalised sums referred to in this paragraph and paragraph 38(a), provide such details of the formula or method of calculation by which those sums have been calculated as the undertaker may reasonably require.
- (4) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions, a capitalised sum representing such saving must be set off against any sum payable by the undertaker to Network Rail under this paragraph.
38
The undertaker must repay to Network Rail all reasonable fees, costs, charges and expenses reasonably incurred by Network Rail—
- (a) in constructing any part of a specified work on behalf of the undertaker as provided by paragraph 33(3) or in constructing any protective works under the provisions of paragraph 33(4) including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;
- (b) in respect of the approval by the engineer of plans submitted by the undertaker and the supervision by the engineer of the construction of a specified work or a protective work;
- (c) in respect of the employment or procurement of the services of any inspectors, signallers, watchkeepers and other persons whom it is reasonably necessary to appoint for inspecting, signalling, watching and lighting railway property and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of a specified work or a protective work;
- (d) in respect of any special traffic working resulting from any speed restrictions which may in the opinion of the engineer be required to be imposed by reason or in consequence of the construction or failure of a specified work or a protective work or from the substitution or diversion of services which may be reasonably necessary for the same reason; and
- (e) in respect of any additional temporary lighting of railway property in the vicinity of the specified works, being lighting made reasonably necessary by reason or in consequence of the construction or failure of a specified work or a protective work.
39
- (1) In this paragraph—
- “EMI” means, subject to sub-paragraph (2), electromagnetic interference with Network Rail apparatus generated by the operation of the authorised development where such interference is of a level which adversely affects the safe operation of Network Rail’s apparatus; and
- “Network Rail’s apparatus” means any lines, circuits, wires, apparatus or equipment (whether or not modified or installed as part of the authorised development) which are owned or used by Network Rail for the purpose of transmitting or receiving electrical energy or of radio, telegraphic, telephonic, electric, electronic or other like means of signalling or other communications.
- (2) This paragraph applies to EMI only to the extent that such EMI is not attributable to any change to Network Rail’s apparatus carried out after approval of plans under paragraph 33 for the relevant part of the authorised development giving rise to EMI (unless the undertaker has been given notice in writing before the approval of those plans of the intention to make such change).
- (3) Subject to sub-paragraph (5), the undertaker must in the design and construction of the authorised development take all measures necessary to prevent EMI and must establish with Network Rail (both parties acting reasonably) appropriate arrangements to verify their effectiveness.
- (4) In order to facilitate the undertaker’s compliance with sub-paragraph (3)—
- (a) the undertaker must consult with Network Rail as early as reasonably practicable to identify all Network Rail’s apparatus which may be at risk of EMI, and thereafter must continue to consult with Network Rail (both before and after formal submission of plans under paragraph 33) in order to identify all potential causes of EMI and the measures required to eliminate them;
- (b) Network Rail must make available to the undertaker all information in the possession of Network Rail reasonably requested by the undertaker in respect of Network Rail’s apparatus identified pursuant to sub-paragraph (a); and
- (c) Network Rail must allow the undertaker reasonable facilities for the inspection of Network Rail’s apparatus identified under sub-paragraph (a).
- (5) In any case where it is established that EMI can only reasonably be prevented by modifications to Network Rail’s apparatus, Network Rail must not withhold its consent unreasonably to modifications of Network Rail’s apparatus, but the means of prevention and the method of their execution must be selected at the reasonable discretion of Network Rail, and in relation to such modifications paragraph 33 has effect subject to this sub-paragraph.
- (6) If at any time prior to the completion of the authorised development and regardless of any measures adopted under sub-paragraph (3) the testing or commissioning of the authorised development causes EMI, the undertaker must immediately upon receipt of notification by Network Rail of such EMI either in writing or communicated orally (such oral communication to be confirmed in writing as soon as reasonably practicable after it has been issued) cease to use (or procure the cessation of use of) the undertaker’s apparatus causing such EMI until all measures necessary have been taken to remedy such EMI by way of modification to the source of such EMI or (in the circumstances, and subject to the consent specified in sub-paragraph (5)) to Network Rail’s apparatus.
- (7) In the event of EMI having occurred—
- (a) the undertaker must afford reasonable facilities to Network Rail for access to the undertaker’s apparatus in the investigation of such EMI;
- (b) Network Rail must afford reasonable facilities to the undertaker for access to Network Rail’s apparatus in the investigation of such EMI; and
- (c) Network Rail must make available to the undertaker any additional material information in its possession reasonably requested by the undertaker in respect of Network Rail’s apparatus or such EMI.
- (8) Where Network Rail approves modifications to Network Rail’s apparatus pursuant to sub-paragraphs (5) or (6)—
- (a) Network Rail must allow the undertaker reasonable facilities for the inspection of the relevant part of Network Rail’s apparatus; and
- (b) any modifications to Network Rail’s apparatus approved pursuant to those sub-paragraphs must be carried out and completed by the undertaker in accordance with paragraph 34.
- (9) To the extent that it would not otherwise do so, the indemnity in paragraph 43(1) applies to the costs and expenses reasonably incurred or losses suffered by Network Rail through the implementation of the provisions of this paragraph (including costs incurred in connection with the consideration of proposals, approval of plans, supervision and inspection of works and facilitating access to Network Rail’s apparatus) or in consequence of any EMI to which sub-paragraph (6) applies.
- (10) For the purpose of paragraph 38(a) any modifications to Network Rail’s apparatus under this paragraph are deemed to be protective works referred to in that paragraph.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.