The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024
- “Enhanced Operational Controls” means the controls set out in the document of that description listed in Schedule 7 (plans and documents to be certified) and certified by the Secretary of State as the Enhanced Operational Controls for the purposes of this Order;
- “flood risk assessment” means the document of that description in Schedule 7 (plans and documents to be certified) certified by the Secretary of State as the flood risk assessment for the purposes of this Order;
- “impact protection measures” means—part (a) of Work No.3 as defined in Schedule 1 to this Order; orpart (b) of Work No. 3 as defined in Schedule 1 to this Order; orboth parts (a) and (b) of Work No. 3 as defined in Schedule 1 to this Order;
- “IOT” means the Immingham Oil Terminal;
- “IOT Operators” means Associated Petroleum Terminals (Immingham) Ltd and Humber Oil Terminal Trustees Ltd, with “Associated Petroleum Terminals (Immingham) Ltd” meaning Associated Petroleum Terminals (Immingham) Limited, company number (00564394) registered at Queens Road, Immingham, Grimsby, N E Lincolnshire, DN40 2PN, and any successor in title and “Humber Oil Terminal Trustees Ltd” meaning Humber Oil Terminal Trustees Limited, company number (00874993) registered at Queens Road, Immingham, Grimsby, N E Lincolnshire, DN40 2PN, and any successor in title
- “National Highways” means National Highways Limited (company number 09346363) whose registered office is Bridge House, 1 Walnut Tree Close, Guildford, Surrey GU1 4LZ or any such successor or replacement body that may from time to time be primarily responsible for the functions, duties and responsibilities currently exercised by that statutory body;
- “operational freight management plan” means the document of that description listed in Schedule 7 (plans and documents to be certified) and certified by the Secretary of State as the ‘operational freight management plan’ for the purposes of this Order;
- “outline onshore construction environmental management plan” means the document of that description in Schedule 7 (plans and documents to be certified) and certified by the Secretary of State as the outline onshore construction environmental management plan for the purposes of this Order; and
- “travel plan” means the document of that description listed in Schedule 7 (plans and documents to be certified) and certified by the Secretary of State as the ‘travel plan’ for the purposes of this Order.
Time limit for commencement of the authorised development
2
The authorised development must commence within 5 years of the date on which this Order comes into force.
Amendments to approved details
3
With respect to any requirement which requires the authorised development to be carried out in accordance with the details of schemes or plans approved under this Schedule the approved details or schemes or plans are taken to include any amendments that may subsequently be approved in writing by the approving body.
Construction hours – onshore works
4
- (1) Subject to sub-paragraph (2), no construction work for Work Nos. 4 to 13 or any ancillary works associated with them may take place on bank holidays or outside the hours of 07:00 to 19:00 Mondays to Fridays and 07:00 to 13:00 on Saturdays.
- (2) Construction work for Work Nos. 4 to 13 may take place outside the hours mentioned in sub-paragraph (1) provided such works—
- (a) do not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement; and
- (b) do not exceed maximum permitted levels of noise at each agreed monitoring location to be determined with reference to the ABC Assessment Method for the different working time periods, as set out in BS 5228-1:2009+A1:2014, unless otherwise agreed in writing with the Council for specific construction activities; and
- (c) are—
- (i) works that cannot be interrupted; or
- (ii) emergency works; or
- (iii) works that are carried out with the prior approval of the Council.
- (3) Any emergency works carried out under sub-paragraph (2)(c)(ii) must be notified to the Council within 72 hours of their commencement.
- (4) In this requirement, “bank holiday” means a bank holiday in England and Wales under section 1 of the Banking and Financial Dealings Act 197162.
Travel plan
5
- (1) The operation of the authorised development must not be commenced until a final version of the travel plan has been submitted to and approved in writing by the Council.
- (2) The authorised development must be carried out in accordance with the travel plan approved pursuant to sub-paragraph (1).
Piling and marine construction works restrictions
6
- (1) Piling and marine construction works may be undertaken 24 hours a day on Mondays to Sundays provided that such works are undertaken in accordance with paragraph 12 of Part 2 of Schedule 3 (deemed marine licence).
- (2) Any emergency works carried out in accordance with paragraph 12 of Part 2 of Schedule 3 must be notified to the Council within 72 hours of their commencement.
- (3) Works for the capital dredge, which has the same meaning as in paragraph 1(1)(b) of Part 1 of Schedule 3, may be undertaken without restriction as to time or day.
External appearance and height of the authorised development
7
- (1) Construction of—
- (a) the terminal building and the welfare building for HGV drivers and passengers awaiting embarkation and related ancillary buildings as identified as part of Work No. 5(c);
- (b) the proposed administrative and inspection buildings for UK Border Force as identified as Work No. 5(e); and
- (c) the proposed ancillary buildings as identified as part of Work No. 4(f),
must not be commenced until the details of the location, heights relative to the proposed finished ground levels, and external materials to be used in the construction of all new permanent buildings and structures, including the colour, materials and finishes, have been submitted to and approved in writing by the Council.
- (2) The authorised development must be implemented in accordance with the details approved by the Council.
- (3) The authorised development must be carried out in accordance with the general arrangement plans.
- (4) The authorised development will not be in accordance with the general arrangement plans if any departure from the general arrangement plans would give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.
Onshore construction environmental management plan
8
- (1) No part of the authorised development may be commenced until an onshore construction environmental management plan has been submitted to and approved in writing by the Council and National Highways (on matters related to its functions), following consultation with the MMO, Natural England, the Environment Agency, Network Rail, Royal Mail and the Board on matters related to their respective functions.
- (2) The onshore construction environmental management plan submitted and approved under sub-paragraph (1) must be in accordance with the outline onshore construction environmental management plan, including the outline plans and skeleton management plans identified and included in the outline onshore construction environmental management plan.
- (3) The construction of the authorised development must be undertaken in accordance with the approved onshore construction environmental management plan.
Surface water drainage
9
- (1) The authorised development, save for the permitted preliminary works, must not be commenced until a final version of the drainage strategy has been submitted to and approved in writing by the Board. The onshore parts of the authorised development shall be implemented in accordance with the approved drainage strategy.
- (2) The final version of the drainage strategy submitted and approved under sub-paragraph (1) must be in accordance with the drainage strategy.
- (3) In this requirement, “the permitted preliminary works” means—
- (a) works consisting of the removal of existing structures and site clearance works; and
- (b) works consisting of any part of the off-site mitigation works, the installation of wheel cleaning facilities, the installation and diversion of utility services, surveys and the provision of temporary contractors’ facilities.
Noise insulation
10
- (1) Prior to the commencement of the authorised development the undertaker must offer the owner and occupier of each of the residential buildings along Queens Road, Immingham a package of noise insulation mitigation to reduce internal noise levels in sensitive rooms. The noise insulation must be designed to reduce the noise level by at least the maximum predicted increase in road traffic noise (7.4 decibels) due to the operation of the authorised development, taking into consideration the performance of the existing glazing and ventilation.
- (2) If the package of mitigation, or such alternative package as may reasonably be requested by the owner and occupier, offered in accordance with sub-paragraph (1) is agreed in writing by the owner and occupier of the residential building within the period specified in the offer, which must not be less than 30 days starting with the day after the offer has been received by the owner and occupier, then the package of mitigation must be implemented at the undertaker’s cost prior to the commencement of the authorised development.
- (3) Any dispute arising between the undertaker and the owner and occupier of a residential building along Queens Road, Immingham under this requirement is to be determined by arbitration as provided in article 35 (arbitration).
Woodland management
11
The operation of the authorised development must not be commenced until a final version of the WEMP has been submitted to and approved in writing by the Council. The authorised development must be implemented in accordance with the approved WEMP.
East Gate Improvements(Work No. 12)
12
The operation of the authorised development must not be commenced until—
- (a) the undertaker has entered into such agreements with the Council as may be necessary in connection with Work No. 12 ; and
- (b) the agreed works constituting Work No. 12 have been completed and are available for use.
Operational freight management plan
13
- (1) The operation of the authorised development must not be commenced until a final version of the operational freight management plan has been submitted to and approved in writing by the Council and National Highways (on matters related to its functions).
- (2) The authorised development must be carried out in accordance with the operational freight management plan approved pursuant to sub-paragraph (1).
Lighting plan
14
- (1) No part of the authorised development may be brought into operation until a written scheme of the proposed operational lighting to be provided for that part of the authorised development has been submitted to and approved in writing by the Council and Network Rail.
- (2) The written scheme submitted under sub-paragraph (1) must be in general accordance with the lighting plan.
- (3) The authorised development must be operated in accordance with the scheme approved under sub-paragraph (1).
Flood risk assessment
15
The authorised development must be constructed and operated in accordance with the flood risk assessment.
Contaminated land
16
- (1) No part of Work Nos. 4 to 13 inclusive and any ancillary works associated with those onshore works numbers shall be commenced until a written remediation strategy applicable to the relevant part of Work Nos. 4 to 13 inclusive and any ancillary works associated with those onshore works numbers, dealing with any contamination of that land, including groundwater and ground gas, within the Order limits which is likely to cause significant harm to persons or pollution of controlled waters or the environment has, after consultation with the Environment Agency, been submitted to and approved in writing by the Council.
- (2) The remediation strategy submitted for approval must include an investigation and assessment report, prepared by a suitably qualified person, to identify the extent of any contamination and the remedial measures to be taken to render the land fit for its intended purpose, together with a management plan which sets out long-term measures with respect to any contaminants remaining on the site. The remediation strategy submitted for approval must also include a procedure for handling any unexpected contamination encountered during the undertaking of the construction works.
- (3) Any remediation must be carried out in accordance with the approved remediation strategy.
Materials Management Plan
17
- (1) A written materials management plan in compliance with the provisions of the CL:AIRE DoW CoP must be produced and submitted to a Qualified Person for approval and issue of a declaration (made under the CL:AIRE DoW CoP), such declaration to be approved by CL:AIRE and submitted to the Environment Agency and the Council for its records, before any works to which the materials management plan relates commence.
- (2) Any works to which the material management plan relates must be undertaken in accordance with the materials management plan as approved pursuant to sub-paragraph (1).
- (3) In this requirement—
- (a) “CL:AIRE” means the registered charity (No. 1075611) and an environmental body registered with ENTRUST (Entrust No. 119820) also incorporated as a company, limited by guarantee and registered in England and Wales (reg no. 3740059) which provides technical secretariat services for industry wide programmes and is responsible for the registration of Qualified Persons able to issue declarations under the DoW CoP;
- (b) “the DoW CoP” means the CL:AIRE Definition of Waste: Development Industry Code of Practice; and
- (c) “Qualified Person” means a person appearing on the register of Qualified Persons for the CL:AIRE Definition of Waste: Development Industry Code of Practice.
Impact Protection Measures for the IOT trunkway
18
- (1) In the event that the Statutory Conservancy and Navigation Authority or the dock master determine that the impact protection measures comprising Work No. 3(a) are required, upon receiving notification of that determination from the Statutory Conservancy and Navigation Authority or the dock master, the undertaker must construct the impact protection measures.
- (2) Upon receiving notification of the Statutory Conservancy and Navigation Authority’s or dock master’s determination referred to in sub-paragraph (1):
- (a) the undertaker must within 10 business days, notify the IOT Operators and the MMO of that determination; and
- (b) within 30 business days, notify the IOT Operators and the MMO as to the steps it intends to take as a result of the Statutory Conservancy and Navigation Authority’s or dock master’s notification.
- (3) The construction of Work No. 3(a) must not be commenced until the undertaker has consulted the Statutory Conservancy and Navigation Authority, the dock master, the IOT Operators and the MMO as to the detailed design of Work No. 3(a) and has had regard to any consultative representations received by the undertaker.
- (4) No works for the construction of Work No. 3(a) may be commenced until the undertaker has obtained the written consent of the Statutory Conservancy and Navigation Authority to construct Work No. 3(a).
- (5) The detailed design referred to in sub-paragraph (3) must be:
- (a) within the limits of deviation shown on the relevant plans of the works plans;
- (b) in general accordance with the detail shown on the relevant engineering, sections, drawings and plans; and
- (c) in general accordance with the detail shown on the relevant general arrangement plans.
Impact Protection Measures for the IOT finger pier
19
- (1) Prior to the commencement of the commercial operation of Berth 1, using the berth numbering adopted on General Arrangements Plan B2429400-JAC-00-ZZ-DR-ZZ-0202 Revision P05, the undertaker must—
- (a) notify the Statutory Conservancy and Navigation Authority, the dock master, the MMO and IOT Operators of its intention to install the impact protection measures comprising Work No. 3(b);
- (b) agree a programme of works with the parties identified in sub-paragraph (a) above; and
- (c) install the impact protection measures detailed as Work No. 3(b).
Amending the Port of Immingham Marine Operations Manual
20
- (1) The undertaker must not commence marine commercial operations until the dock master has amended the Port of Immingham Marine Operations Manual (the “Manual”) to incorporate the Enhanced Operational Controls prescribing operating procedures for arrival at and departure from the authorised development.
- (2) As soon as reasonably practicable after the amendment mentioned in sub-paragraph (1), the dock master must—
- (a) notify the IOT Operators of its amendments to the Manual insofar as they relate to the operation of the authorised development; and
- (b) publish the amended navigational controls on the Port of Immingham webpage.
- (3) The undertaker must operate the authorised development only in accordance with the Manual referred to in sub–paragraph (1) as may be amended and re-published from time to time.
PART 2 — PROCEDURE FOR DISCHARGE OF REQUIREMENTS
Interpretation
21
In this Part of this Schedule, “discharging authority” means any body responsible for giving any consent, agreement or approval required by a requirement included in Part 1 of this Schedule, or for giving any consent, agreement or approval further to any document referred to in any such requirement.
Applications made under requirements
22
- (1) Subject to sub-paragraph (3), where an application has been made to the discharging authority for any consent, agreement or approval required by a requirement included in this Order, or for any consent, agreement or approval further to any document referred to in any such requirement, the discharging authority must give notice to the undertaker of its decision on the application within a period of 8 weeks beginning with—
- (a) the day immediately following that on which the application is received by the discharging authority; or
- (b) where further information is requested under paragraph 23, the day immediately following that on which the further information has been supplied by the undertaker,
or such longer period as may be agreed in writing by the undertaker and the discharging authority.
- (2) In determining any application made to the discharging authority for any consent, agreement or approval required by a requirement contained in Part 1 of this Schedule, the discharging authority may—
- (a) give or refuse its consent, agreement or approval; or
- (b) give its consent, agreement or approval subject to reasonable conditions,
and where consent, agreement or approval is refused or granted subject to conditions the discharging authority must provide its reasons for that decision with the notice of the decision.
- (3) In the event that the discharging authority does not determine an application in relation to any of Work Nos. 4 to 13 inclusive and any ancillary works associated with those onshore works within the period set out in sub-paragraph (1), the discharging authority is deemed to have granted all parts of the application (without any condition or qualification) at the end of that period unless otherwise agreed in writing.
- (4) An application under sub-paragraph (3) must include a statement informing the discharging authority—
- (a) of the period mentioned in paragraph (1); and
- (b) that if they do not respond before the end of that period, consent will be deemed to have been granted.
Further information regarding requirements
23
- (1) In relation to any application referred to in paragraph 22, the discharging authority may request such further information from the undertaker as it considers necessary to enable it to consider the application.
- (2) If the discharging authority considers that further information is necessary, the discharging authority must, within 24 business days of receipt of the application, notify the undertaker in writing specifying the further information required or must do so within any longer period as may be agreed in writing between the undertaker and the discharging authority.
- (3) If the discharging authority does not give the notification within the period specified in subparagraph (2) it is deemed to have sufficient information to consider the application and is not entitled to request further information without the prior agreement of the undertaker.
Appeals
24
- (1) The undertaker may appeal to the Secretary of State in the event that—
- (a) the discharging authority refuses an application for any consent, agreement or approval required by—
- (i) a requirement in Part 1 of this Schedule; or
- (ii) a document referred to in any requirement contained in Part 1 of this Schedule,
or grants it subject to conditions to which the undertaker objects;
- (b) on receipt of a request for further information pursuant to paragraph 23 of this Part of this Schedule, the undertaker considers that either the whole or part of the specified information requested by the discharging authority is not necessary for consideration of the application; or
- (c) on receipt of any further information requested, the discharging authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application.
- (2) The appeal process is as follows—
- (a) any appeal by the undertaker must be made within 42 days of the date of the notice of the decision or determination, or (where no determination has been made) the expiry of the time period set out in paragraph 22(1), giving rise to the appeal referred to in sub- paragraph (1);
- (b) the undertaker must submit the appeal documentation to the Secretary of State and must on the same day provide copies of the appeal documentation to the discharging authority;
- (c) as soon as is practicable but not later than 21 days after receiving the appeal documentation, the Secretary of State must appoint a person to consider the appeal (“the adjudicator”) and must notify the appeal parties of the identity of the adjudicator and the address to which all correspondence for the attention of the adjudicator must be sent;
- (d) the appointed adjudicator must specify a start date no later than 21 days following the appointment subject to any extension as may be agreed by the parties;
- (e) the discharging authority must submit their written representations together with any other representations to the adjudicator in respect of the appeal within 10 business days of the start date specified by the adjudicator and must ensure that copies of their written representations and any other representations as sent to the adjudicator are sent to the undertaker on the day on which they are submitted to the adjudicator;
- (f) the appeal parties must make any counter-submissions to the adjudicator within 10 business days of receipt of written representations pursuant to sub-paragraph (e) above; and
- (g) the adjudicator must make a decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable but no later than 21 days after the end of the 10 business day period for counter-submissions under sub-paragraph (f).
- (3) The appointment of the adjudicator pursuant to sub-paragraph (2)(c) may be undertaken by a person appointed by the Secretary of State for this purpose instead of by the Secretary of State.
- (4) If the adjudicator considers that further information is necessary to enable the adjudicator to consider the appeal the adjudicator must, as soon as practicable, notify the appeal parties in writing specifying the further information required, the appeal party from whom the information is sought, and the date by which the information is to be submitted.
- (5) Any further information required pursuant to sub-paragraph (4) must be provided by the party from whom the information is sought to the adjudicator and to the other appeal parties by the date specified by the adjudicator. The adjudicator must notify the appeal parties of the revised timetable for the appeal on or before that day. The revised timetable for the appeal must require submission of written representations to the adjudicator within 10 business days of the date specified by the adjudicator but must otherwise be in accordance with the process and time limits set out in sub-paragraphs (2)(c)-(g).
- (6) On an appeal under this paragraph, the adjudicator may—
- (a) allow or dismiss the appeal; or
- (b) reverse or vary any part of the decision of the discharging authority (whether the appeal related to that of it or not),
and may deal with the application as if it had been made to the adjudicator in the first instance.
- (7) The adjudicator may proceed to a decision on an appeal taking into account such written representations as have been sent within the relevant time limits and in the sole discretion of the adjudicator such written representations as have been sent outside of the relevant time limits.
- (8) The adjudicator may proceed to a decision even though no written representations have been made within the relevant time limits, if it appears to the adjudicator that there is sufficient material to enable a decision to be made on the merits of the case.
- (9) The decision of the adjudicator on an appeal is final and binding on the parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for a judicial review.
- (10) If an approval is given by the adjudicator pursuant to this Part of this Schedule, it is deemed to be an approval for the purpose of Part 1 of this Schedule as if it had been given by the discharging authority.
- (11) Save where a direction is given pursuant to sub-paragraph (12) requiring the costs of the adjudicator to be paid by the discharging authority, the reasonable costs of the adjudicator are to be met by the undertaker.
- (12) On application by the discharging authority or the undertaker, the adjudicator may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction and the terms on which it is to be made, the adjudicator must have regard to relevant guidance on the Planning Practice Guidance website or any official circular or guidance which may replace it.
Anticipatory steps towards compliance with any requirement
25
If before this Order came into force the undertaker or any other person took any steps that were intended to be steps towards compliance with any provision of Part 1 of this Schedule, those steps may be taken into account for the purpose of determining compliance with that provision if they would have been valid steps for that purpose had they been taken after this Order came into force.
SCHEDULE 3 — DEEMED MARINE LICENCE
PART 1 — GENERAL
Interpretation
1
- (1) In this Schedule—
- “the 2008 Act” means the Planning Act 2008;
- “the 2009 Act” means the Marine and Coastal Access Act;
- “2021 sediment sampling plan” means—the plan approved by the MMO on 24 September 2021, which details—a detailed dredging methodology;dredge locations;dredge amounts (total and annual, if applicable);dredge depths;duration of dredging activities;whether the dredge is a capital dredging activity or a maintenance dredging activity; andspecific gravity of the material or material type; andany further sediment sampling analyses which may be approved by the MMO in accordance with condition 18(2) prior to the expiry of the 2021 sediment sampling plan;
- “alluvial materials” means dredged unconsolidated material of alluvial origin;
- “the authorised development” means the construction, operation and maintenance of a Roll on Roll off facility on the River Humber as described in Schedule 1 to this Order and has the meaning given in paragraph 3(2);
- “business day” means a day other than a Saturday or Sunday, Good Friday, Christmas Day or a bank holiday in England and Wales under section 1 of the Banking and Financial Dealings Act 1971;
- “business hours” means the period from 09:00 until 17:00 on any business day;
- “capital dredge” means the dredging to a depth not previously dredged, or to a depth not dredged within the last 10 years and is generally undertaken to create or deepen navigational channels, berths or to remove material deemed unsuitable for the foundation of a construction project and “capital dredging” shall be construed accordingly;
- “Chart Datum” means 3.9 m below ordinance datum (Newlyn), corresponding with a depth of 7.6m of the outer sill of the Port of Immingham;
- “cold weather construction restriction strategy” means the strategy of that description referred to in condition 8 of Part 2 of this Schedule 3;
- “commence” means beginning to carry out any part of a licensed activity and “commenced” and “commencement” are to be construed accordingly;
- “condition” means a condition in Part 2 and Part 3 of this licence and references in this licence to numbered conditions are to the conditions with those numbers in Part 2;
- “the environmental statement” means the document of that description certified under article 33 (certification of plans and documents etc.) of the Order, certified by the Secretary of State as the environmental statement for the purposes of the Order;
- “existing marine licence” means licence L/2014/00429 or any subsequent equivalent successor licence as may be granted that permits the disposal of dredged arising from the Port of Immingham;
- “future sediment sampling plan” means—any further sediment sampling plan approved by the MMO in accordance with condition 18(2) which details—a detailed dredging methodology;dredge locations;dredge amounts (total and annual, if applicable);dredge depths;duration of dredging activities;whether the dredge is a capital dredging activity or a maintenance dredging activity; andspecific gravity of the material or material type;
- “glacial clay” means consolidated dredged materials laid down during the last glaciation;
- “high water” means daily high tides in every lunar day;
- “HU056” means the area bounded by co-ordinates (53°39.3000’N, 00°10.4898’W), (53°39.0499’N, 00°10.4700’W), (53°38.8201’N, 00°09.4398’W), (53°39.3000’N, 00°10.4898’W);
- “HU060” means the area bounded by co-ordinates—
- (53°38.7439’N, 00°10.4434’W), (53°38.7499’N, 00°10.4536’W), (53°38.7575’N, 00°10.4677’W), (53°38.7648’N, 00°10.4823’W), (53°38.7718’N, 00°10.4974’W), (53°38.7784’N, 00°10.5128’W), (53°38.7847’N, 00°10.5287’W), (53°38.7906’N, 00°10.5450’W), (53°38.7962’N, 00°10.5617’W), (53°38.8013’N, 00°10.5787’W), (53°38.8061’N, 00°10.5960’W), (53°38.8105’N, 00°10.6136’W), (53°38.8145’N, 00°10.6315’W), (53°38.8181’N, 00°10.6496’W), (53°38.8213’N, 00°10.6679’W), (53°38.8240’N, 00°10.6864’W), (53°38.8264’N, 00°10.7051’W), (53°38.8283’N, 00°10.7239’W), (53°38.8298’N, 00°10.7428’W), (53°38.8309’N, 00°10.7618’W), (53°38.8315’N, 00°10.7809’W), (53°38.8317’N, 00°10.8000’W), (53°38.8315’N, 00°10.8191’W), (53°38.8309’N, 00°10.8382’W), (53°38.8298’N, 00°10.8572’W), (53°38.8283’N, 00°10.8761’W), (53°38.8264’N, 00°10.8949’W), (53°38.8240’N, 00°10.9136’W), (53°38.8213’N, 00°10.9321’W), (53°38.8181’N, 00°10.9504’W), (53°38.8145’N, 00°10.9685’W), (53°38.8105’N, 00°10.9864’W), (53°38.8061’N, 00°11.0040’W), (53°38.8013’N, 00°11.0213’W), (53°38.7962’N, 00°11.0383’W), (53°38.7906’N, 00°11.0550’W), (53°38.7847’N, 00°11.0713’W), (53°38.7784’N, 00°11.0872’W), (53°38.7718’N, 00°11.1026’W), (53°38.7648’N, 00°11.1177’W), (53°38.7575’N, 00°11.1323’W), (53°38.7499’N, 00°11.1464’W), (53°38.7439’N, 00°11.1567’W), (53°38.7438’N, 00°11.1564’W), (53°38.5320’N, 00°10.8000’W), (53°38.7438’N, 00°10.4436’W), (53°38.7439’N, 00°10.4434’W)
- “intertidal mudflat” means exposed mud between mean high water springs and mean low water springs;
- “licensable activity” means an activity licensable under section 66 of the 2009 Act;
- “licensed activity” means any activity authorised in paragraph 3 of this Schedule;
- “local planning authority” means North East Lincolnshire Council;
- “maintenance dredge” means a dredge undertaken to keep channels, berths and other areas at their designed depths, involving removing recently accumulated sediments such as mud, sand and gravel to a level that is not lower than it has been at any time during the past 10 years;
- “marine piles” means piles that will be in a free water condition during construction;
- “marine written scheme of investigation” means the marine archaeological written scheme of investigation contained in appendix 15.3 to the environmental statement;
- “MCMS” means the Marine Case Management System provided by the MMO;
- “mean high water springs” means the average of high water heights occurring at the time of spring tides;
- “mean low water springs” means the average of low water heights occurring at the time of spring tides;
- “the MMO” means the Marine Management Organisation;
- “named vessel” means a vessel whose name and type has been notified to the MMO in writing;
- ...
- “Notice to Mariners” means any notice to mariners which may be issued by the Admiralty, Trinity House, the Statutory Conservancy and Navigation Authority, government departments or harbour and pilotage authorities advising mariners of important matters affecting navigational safety;
- “outline offshore construction environmental management plan” means the document of that description certified under article 33 (certification of plans and documents etc.) of the Order, certified by the Secretary of State as the outline offshore construction environmental management plan for the purposes of the Order;
- “the Order” means the Associated British Ports (Immingham Eastern Ro-Ro Terminal) Order 2024; and
- “percussive piles” means driven piles but excludes the handling, placing and vibro-driving of piles;
- “percussive piling” for the purposes of this licence means the driving of piles by percussive means but does not include the handling, placing or vibro-piling of piles;
- “the Port of Immingham” means the statutory port estate including the Port of Immingham statutory harbour authority area;
- “the River Humber” means the tidal estuary from its mouth at the Spurn Peninsula to its confluence with the rivers Ouse and Trent;
- “sea bed” means the ground under the sea;
- “undertaker” means Associated British Ports (“ABP”) company number ZC000195 registered at 25 Bedford Street, London, WC2E 9ES and any agent, contractor or sub-contractor acting on its behalf; and
- “vessel” means every description of vessel, however propelled or moved and includes a non-displacement craft, a personal watercraft, a seaplane on the surface of the water, a hydrofoil vessel, a hovercraft or any other amphibious vehicle and any other thing constructed or adapted for movement through, in, on or over water and which is at the time in, on or over water.
- (2) Unless otherwise specified, all geographical co-ordinates given in this Schedule are in latitude and longitude degrees and minutes to four decimal places.
- (3) Tonnages of dredged materials are expressed in wet tonnes.
Contacts
2
- (1) Unless otherwise advised in writing by the MMO, the address for postal correspondence with the MMO for the purposes of this licence is the Marine Management Organisation, Marine Licensing Team, Lancaster House, Hampshire Court, Newcastle upon Tyne NE4 7YH, telephone 0300 123 1032 and, unless otherwise advised in writing, where contact to the local MMO office (local office) is required, the following contact details must be used: Marine Management Organisation, The MMO District Office – Crosskill House, Mill Lane, Beverley, HU17 9JB, telephone 0208 720 1344, Email – beverley@marinemanagement.org.uk.
- (2) Unless otherwise advised in writing by the MMO, the address for electronic communication with the MMO for the purposes of this licence is marine.consents@marinemanagement.org.uk or where contact to the local MMO office is required is beverley@marinemanagement.org.uk.
- (3) Unless otherwise advised in writing by the MMO, MCMS must be used for all licence returns or applications to vary this licence. The MCMS address is: https://marinelicensing.marinemanagement.org.uk/mmofox5/fox/live/MMO_LOGIN/login.
- (4) Unless otherwise stated in writing by the MMO, all notifications required by this licence must be sent by the undertaker to the MMO using MCMS.
Licensed marine activities
3
- (1) Subject to the licence conditions in Part 2, this licence authorises the undertaker to carry out licensable marine activities under section 66(1) (licensable marine activities) of the 2009 Act which—
- (a) form part of, or are related to, the authorised development; and
- (b) are not exempt from requiring a marine licence by virtue of any provision made under section 74 (exemption specified by order) of the 2009 Act.
- (2) For the purposes of this licence “the authorised development” means the construction operation and maintenance of a Roll on Roll off facility on the River Humber—
- (a) comprising—
- (i) an open piled approach jetty with abutments carrying on its surface a roadway, a footway, utilities, lighting and environmental screens, rising from ground level to cross over existing landside infrastructure and then extending from the shore in a north easterly direction (Work No.1);
- (ii) a single linkspan bridge carrying on its surface a roadway and footway together with lighting and utilities, extending from the approach jetty to the innermost floating pontoon (Work No.1);
- (iii) two floating pontoons connected by a linkspan, each with lighting, power, cable management system, utilities and a small crew shelter, secured in position by restraint dolphins, each located about a finger pier to accommodate the loading and unloading ramps of berthed ro-ro vessels (Work No.1);
- (iv) two finger piers of open piled construction each with navigation markers, lighting, shore power infrastructure and connections for berthed vessels and water bunkering facilities—
- (aa) the northern finger pier to be constructed with berthing faces on both its northern and southern elevations equipped with mooring infrastructure (Work No.1);
- (bb) the southern finger pier to be constructed with a berthing face only on its northern elevation equipped with mooring infrastructure (Work No.1);
- (v) piling works and construction operations within the River Humber (Work No.1);
- (vi) related capital dredging works within the River Humber for the above and the disposal of any arisings from such dredgings (Work No.2);
- (vii) the construction of—
- (aa) a vessel impact protection barrier formed of a single row of tubular piles with a reinforced concrete capping beam, the outer facing elevation of the beam may be equipped with fendering units and panels (Work No.3(a)); and
- (bb) a piled dolphin structure with a capping slab, with piles installed at each corner of the dolphin structure equipped with donut roller fenders (Work No.3(b)); and
- (viii) the continued use of two existing surface water outfalls;
- (b) activities which will include works to—
- (i) clean, refurbish, re-construct, strengthen or maintain any work or structure; and
- (ii) place and maintain works and structures including jetty furniture, fenders and impact protection; and
- (c) such other incidental works as may be necessary or convenient for the purposes of, or in connection with or in consequence of, the construction, maintenance, operation or use of the authorised development, including works for the accommodation or convenience of vessels (including but not limited to berthing and mooring facilities, ladders, buoys, bollards, dolphins and fenders) and lighting.
Licence to dredge and deposit
4
- (1) Capital dredge – Subject to paragraph 5, the undertaker is permitted to undertake a capital dredge to a depth of -9 metres Chart Datum (with an allowance for the tolerances of the dredging equipment) of the berth pocket the grid coordinates for which are specified in paragraph 5(2) .
- (2) The materials must be dredged in the approximate quantities and deposited at the locations according to the following table—
| Material | Volume (m3) | Specific gravity | Maximum tonnage (wet tonnes) | Disposal site |
|---|---|---|---|---|
| Alluvial materials | 150,000 | 1.35 | 202,500 | HU060 |
| Glacial clay | 40,000 | 2.26 | 90,400 | HU056 |
- (3) Maintenance dredge – the undertaker is permitted to carry out maintenance dredging within the statutory harbour authority area of the Port of Immingham for the purposes of maintaining the authorised development under section 75 of the 2009 Act in accordance with the existing marine licence.
- (4) Deposit of dredged arisings—
- (a) The capital dredge will create arisings of glacial clay and alluvial materials which must be deposited at deposit grounds HU056 and HU060;
- (b) The maintenance dredge will create arisings of alluvial materials which must be deposited at the licenced deposit ground HU060 in accordance with the existing marine licence.
Details of licensed marine activities
5
- (1) The grid coordinates within the UK Marine Area within which the undertaker may carry out a licensed activity (save for the capital dredge and disposal) are specified below—
| Point reference | Latitude | Longitude |
|---|---|---|
| 1 | 53.62711082 | -0.179454009 |
| 2 | 53.62748148 | -0.179008789 |
| 3 | 53.63004695 | -0.178898384 |
| 4 | 53.63198621 | -0.176987837 |
| 5 | 53.62889877 | -0.168536653 |
| 6 | 53.62874293 | -0.168641588 |
| 7 | 53.62841556 | -0.167318049 |
| 8 | 53.62814789 | -0.166235931 |
| 9 | 53.62796289 | -0.166266125 |
| 10 | 53.62773154 | -0.166760098 |
| 11 | 53.62716945 | -0.168370825 |
| 12 | 53.62528877 | -0.1723239 |
| 13 | 53.62449396 | -0.17508587 |
| 14 | 53.62512213 | -0.1750807 |
| 15 | 53.62520845 | -0.175123251 |
| 16 | 53.625269 | -0.175226494 |
- (2) No capital dredging may be carried out by the undertaker other than within the area within the grid coordinates for the area of the River Humber specified below and more particularly identified as the berthing pocket under Work No. 2 on sheets 1 and 2 of the works plans—
| Point of reference | Latitude | Longitude |
|---|---|---|
| 17 | 53.626229 | -0.17082 |
| 18 | 53.629182 | -0.178936 |
| 3 | 53.630047 | -0.178898 |
| 19 | 53.631567 | -0.1774 |
| 20 | 53.628371 | -0.168614 |
PART 2 — CONDITIONS APPLYING TO ALL LICENSABLE ACTIVITIES
Before Licensed Activities
Notifications regarding licensed activities
6
- (1) The undertaker must inform the MMO—
- (a) at least 5 business days prior to the commencement of the first licensed activity; and
- (b) within 5 business days following the completion of the final licensed activity,
of the commencement or the completion (as applicable).
- (2) The undertaker must provide the following information to the MMO—
- (a) the name and function in writing of any agent, contractor or sub-contractor that will carry on any licensed activity on behalf of the undertaker; and
- (b) such notification must be received by the MMO in writing not less than 24 hours before the commencement of the licensed activity.
- (3) The undertaker must ensure that a copy of this licence and any subsequent revisions or amendments has been provided to, read and understood by any agents, contractors, and sub-contractors that will be carrying out any licensed activity on behalf of the undertaker.
- (4) The undertaker must keep a copy of this licence and any subsequent revisions or amendments available for inspection at its registered address and any site office location at or adjacent to a construction site.
- (5) Any changes to details supplied under sub-paragraph (2) must be notified to the MMO in writing no less than 24 hours prior to the agent, contractor or named vessel engaging in the licensed activity in question.
- (6) Only those persons notified to the MMO in accordance with this condition are permitted to carry out a licensed activity.
- (7) Copies of this licence must be available for inspection at the following locations—
- (a) the undertaker’s office at the Port of Immingham; and
- (b) during the construction of the authorised development only, at any site office which is adjacent to or near the River Humber and which has been provided for the purposes of the construction of the authorised development.
- (8) The undertaker must request that the masters responsible for the named vessels that will be carrying out any licensed activity on behalf of the undertaker as notified to the MMO under condition 6(5) make a copy of this licence available for inspection on board such named vessels during the carrying out of any licensed activity.
Agents / contractors / sub-contractors
7
- (1) The undertaker must notify the MMO in writing of any agents, contractors or sub-contractors that will carry on any licensed activity listed in paragraph 3 of this licence on behalf of the undertaker. Such notification must be received by the MMO no less than 24 hours before the commencement of the licensed activity.
- (2) The undertaker must ensure that a copy of this licence and any subsequent revisions or amendments has been provided to, read and understood by any agents, contractors or sub-contractors that will carry on any licensed activity listed in section 3 of this licence on behalf of the undertaker.
Cold weather construction restriction strategy
8
No construction operations for any licensed activity are to commence until a cold weather construction restriction strategy is submitted to and agreed by the MMO in consultation with Natural England. The strategy shall include the following—
- (a) a provision that no construction operations (other than to finish driving any pile that is in the process of being driven at the point that the cold weather restriction comes into force) shall take place following 7 consecutive days of zero or sub zero temperatures (where the temperature does not exceed zero degrees centigrade for more than six hours in any day) or any other formula as may be agreed with the MMO to define short periods of thaw;
- (b) the establishment of three temperature monitoring points within the Humber Estuary; and
- (c) a provision that, if the piling restriction specified in sub-paragraph (a) above comes into effect as a consequence of cold weather conditions, it will be reviewed as follows—
- (i) after 24 hours of above freezing temperatures the restriction will be lifted on a temporary basis provided that the weather forecast relevant for the area including the Port of Immingham, (as agreed with the MMO) indicates that freezing conditions will not return within five days; and
- (ii) after a further 5 clear days of above-freezing temperatures, the restrictions will be lifted entirely.
Marine Noise Registry
9
- (1) Only when impact driven or part-driven pile foundations are proposed to be used as part of the foundation installation the undertaker must provide the following information to the Marine Noise Registry (MNR)—
- (a) prior to the commencement of the licensed activities, information on the expected location, start and end dates of impact pile driving to satisfy the Marine Noise Registry’s Forward Look requirements; and
- (b) within 12 weeks of completion of impact pile driving, information on the exact locations and specific dates of impact pile driving to satisfy the Marine Noise Registry’s Close Out requirements.
- (2) The undertaker must notify the MMO of the successful submission of Forward Look requirements.
Marine written scheme of archaeological investigation
10
- (1) A final version of the marine written scheme of investigation must be submitted to and approved by the MMO in writing before any works to which the final version of the marine written scheme of investigation relate commence.
- (2) The licensed activities must be carried out in accordance with the marine written scheme of investigation approved pursuant to sub-paragraph (1).
During Licensed Activities
Offshore Construction Environmental Management Plan
11
- (1) No licensed activities shall be commenced until an offshore construction environmental management plan in relation to those activities has been submitted to and approved by the MMO following consultation with the local planning authority, the Environment Agency and Natural England on matters related to their respective functions.
- (2) The offshore construction environmental management plan submitted and approved under sub-paragraph (1) must be in accordance with the outline offshore construction environmental management plan, including the outline plans and skeleton management plans included in the outline offshore construction environmental management plan.
- (3) The undertaker must undertake the capital dredge in accordance with the offshore construction environmental management plan approved under sub-paragraph (1).
Piling and marine construction works
12
- (1) Subject to sub-paragraph (2) below, the piling of marine piles in connection with the authorised development shall be subject to the following conditions—
- (a) There shall be at least a 20 minutes “soft start” period prior to the commencement of any piling; and
- (b) The form of soft start shall be submitted to and agreed in writing by the MMO in consultation with Natural England on matters related to its functions prior to the commencement of piling.
- (2) An active and mobile 500 metre marine mammals observation zone, the centre point of which will be the location of the particular marine pile being driven percussively, shall be created, and 30 minutes prior to the commencement of percussive piling a search must be undertaken of the zone, with the purpose of identifying whether any marine mammals enter the zone, and if such mammals are observed within the zone, percussive piling must not be commenced until the mammals have cleared the zone or until 20 minutes after the last visual detection, subject to sub-paragraph (4).
- (3) An active and mobile 500 metre marine mammals observation zone, the centre point of which will be the location of the particular marine pile being driven percussively, shall be maintained during percussive piling with the purpose of identifying whether any marine mammals enter the zone and if such mammals are observed, percussive piling must cease until the mammals have cleared the zone and there is no further detection after 20 minutes.
- (4) Where percussive piling is paused for any reason other than the detection of marine mammals, then recommencement of the percussive piling shall be subject to the provisions be paragraph (2) save for where the active and mobile 500 metre marine mammals observation zone has been observed throughout the period of the pause in operations and no such mammals were observed entering the zone, in which case percussive piling may be recommenced immediately.
- (5) Wherever possible the undertaker will use vibro-piling methodology whilst it is recognised that percussive piling may be required to drive the piles to their ultimately required depth.
- (6) The undertaker must use a noise suppression system consisting of a piling sleeve with noise insulating properties for percussive piling.
- (7) Subject to sub-paragraph (8) below, the undertaker must ensure that no marine construction activity for the approach jetty, linkspan, innermost pontoon and the inner finger pier shall take place between 1 October and 31 March inclusive in any year located within 200 metres of the exposed intertidal mudflat.
- (8) During the restricted period between 1 October and 31 March inclusive in any year, marine construction activity may be undertaken provided that at distances less than 200 metres of exposed intertidal mudflat provided that an acoustic barrier/visual screening is installed on both sides of any semi-completed structure and construction activity will then be undertaken on the approach jetty itself, behind the screens, with no use of large heavy plant.
- (9) During the period between 1 October and 31 March inclusive in any year, the undertaker must ensure that on all floating construction barges an acoustic barrier/screening is placed on the side of the barges closest to the foreshore, and construction activity can only be undertaken from the side of the barge facing away from the foreshore.
- (10) No piling of marine piles within the waterbody is to take place between 1 March and 31 March, 1 June and 30 June and 1 August and 31 October inclusive in any one calendar year after sunset and before sunrise on any day, save for any—
- (a) piling of marine piles undertaken on exposed mudflat outside the water column at periods of low water;
- (b) emergency works; and
- (c) piling operations that have been initiated where an immediate cessation of the activity would form an unsafe working practice.
- (11) The undertaker must ensure that no percussive piling of marine piles within the waterbody shall take place between 1 April and 31 May inclusive in any one calendar year, save for any percussive piling of marine piles undertaken on exposed mudflat outside the water column at periods of low water.
- (12) Percussive piling of marine piles is to be restricted at other times as follows—
- (a) from 1 June to 30 June inclusive in any year, the maximum duration of percussive piling permitted within any four-week period must not exceed—
- (i) 140 hours where a single piling rig is in operation; or
- (ii) 196 hours where two or more rigs are in operation; and
- (b) from 1 August to 31 October inclusive in any year, the maximum duration of percussive piling permitted within any four-week period must not exceed—
- (i) 140 hours where a single piling rig is in operation; or
- (ii) 196 hours where two or more rigs are in operation,
save for any percussive piling of marine piles undertaken on exposed mudflat outside the water column at periods of low water and save for percussive piling operations that have been initiated where an immediate cessation of the activity would form an unsafe working practice.
- (13) The measurement of time during each work-block described in sub-paragraph (12) of this licence must begin at the start of each timeframe, roll throughout it, then cease at the end, where measurement will begin again at the start of the next timeframe, such process to be repeated until the end of piling works.
- (14) Percussive piling must only be carried out in accordance with the cold weather construction restriction strategy.
Percussive piling reporting protocol
13
- (1) The undertaker must submit weekly reports to the MMO of the duration of percussive piling that is undertaken on any given day on which piling takes place during the construction of the authorised development, unless otherwise agreed in writing with the MMO.
- (2) The reports submitted to the MMO pursuant to sub–paragraph (1) must include a log of the number and approximate location of piling rigs which are in operation on any given day, along with the number of piles driven.
- (3) The undertaker will hold fortnightly meetings with the MMO to discuss the weekly reports submitted under sub-paragraph (1) and agree any corrective action if required, unless otherwise agreed in writing with the MMO.
- (4) Subject to sub–paragraph (5), where percussive piling is paused, the recommencement of the percussive piling shall be subject to the provisions of sub–paragraph (1)(a) of paragraph 12 (“the contingency period”).
- (5) The contingency period must not exceed a total of 80 minutes in any given day on which percussive piling takes place.
Concrete and cement
14
Waste concrete, slurry or wash water from concrete or cement activities must not be discharged, intentionally or unintentionally, into the marine environment. Concrete and cement mixing and washing areas must be contained and sited at least 10 metres from any water body or surface water drain.
Coatings and treatment
15
The undertaker must ensure that any coatings or treatments are suitable for use in the marine environment and are used in accordance with guidelines approved by the Health and Safety Executive and the Environment Agency Pollution Prevention Control Guidelines.
Pollution and Spills
16
- (1) Bunding and/or storage facilities must be installed to contain and prevent the release of fuel, oils, and chemicals associated with plant, refuelling and construction equipment, into the marine environment. Secondary containment must be used with a capacity of no less than 110% of the container’s storage capacity.
- (2) Any oil, fuel or chemical spill within the marine environment must be reported to the MMO Marine Pollution Response Team as soon as reasonably practicable, but in any event within 12 hours of being identified in accordance with the following, unless otherwise advised in writing by the MMO—
- (a) within business hours on any business days: 0300 200 2024;
- (b) any other time: 07770 977 825; or
- (c) at all times if other numbers are unavailable: 0845 051 8486 or dispersants@marinemanagement.org.uk.
- (3) All wastes must be stored in designated areas that are isolated from surface water drains, open water and contained to prevent any spillage.
- (4) The undertaker must comply with the existing marine pollution contingency plan in place for the Port of Immingham as detailed in the construction environmental management plan.
Disposal at Sea
17
- (1) The undertaker must inform the MMO of the location and quantities of material deposited each month under the licence. This information must be submitted to the MMO by 15 February each year for the months August to January inclusive and by 15 August each year for the months February to July inclusive.
- (2) The undertaker must ensure that only inert material of natural origin produced during dredging shall be deposited in the disposal sites—
- (a) HU060 (alluvial materials); and
- (b) HU056 (glacial clay),
or any other site approved in writing by the MMO.
Sediment sampling
18
- (1) Any sediment sampling analyses undertaken by a laboratory validated by the MMO and approved by the MMO as part of either the 2021 sediment sampling plan or any future sediment sampling plan is valid for a period of 3 years from the date when those analyses were undertaken.
- (2) Where the validity period for sediment sampling analyses as set out in sub-paragraph (1) above expires, the undertaker must submit a future sediment sampling plan request to the MMO for its approval and any sediment sampling analyses from such future sediment sampling plan must be submitted to the MMO for consultation.
- (3) The undertaker must undertake the capital dredge in accordance with the 2021 sediment sampling plan or the future sediment sampling plan approved under sub-paragraph (2).
19
The material to be disposed of within the disposal sites referred to in paragraph 4(4) must be placed evenly within the boundaries of that site.
20
During the course of disposal at sea, deposited material must be distributed evenly over the disposal site.
Dropped objects
21
- (1) The undertaker must report all dropped objects to the MMO using the dropped object procedure form as soon as reasonably practicable and in any event within 24 hours of becoming aware of an incident.
- (2) On receipt of the dropped object procedure form, the MMO may require, acting reasonably, the undertaker to carry out relevant surveys. The undertaker must carry out surveys in accordance with the MMO’s reasonable requirements and must report the results of such surveys to the MMO.
- (3) On receipt of such survey results, the MMO may, acting reasonably, require the undertaker to remove specific obstructions from the seabed. The undertaker must carry out removals of specific obstructions from the seabed in accordance with the MMO’s reasonable requirements and its own expense.
Notice to Mariners
22
- (1) Local mariners, fishermen’s organisations and the UK Hydrographic Office must be notified of any licensed activity or phase of licensed activity through a local Notice to Mariners.
- (2) A Notice to Mariners must be issued at least 5 days before the commencement of each licensed activity or phase of licensed activity.
- (3) The MMO and Marine Coastguard Agency must be sent a copy of the notification within 24 hours of issue. The Notice to Mariners must include—
- (a) the start and end dates for the works;
- (b) a summary of the works to be undertaken;
- (c) the location of the works area, including coordinated in accordance with World Geodetic System 1984 (WGS84); and
- (d) any markings of the works area that will be put in place.
23
A copy of the notice must be provided to the MMO via MCMS within 24 hours of issue of a notice under sub-paragraph (1).
PART 3 — PROCEDURE FOR THE DISCHARGE OF CONDITIONS
Meaning of “application”
24
In this Part, “application” means a submission by the undertaker for approval by the MMO of any document, strategy, information or plan under conditions 8 (cold weather construction restriction strategy), 9 (marine noise registry), 10 (marine written scheme of investigation), 11 (construction environmental management plan) and 18 (sediment sampling).
Further information regarding application
25
The MMO may request in writing such further information from the undertaker as is necessary to enable the MMO to consider an application.
Determination of application
26
- (1) In determining the application the MMO may have regard to—
- (a) the application and any supporting information or documentation;
- (b) any further information provided by the undertaker; and
- (c) such other matters as the MMO thinks relevant.
- (2) Having considered the application the MMO must—
- (a) grant the application unconditionally;
- (b) grant the application subject to the conditions as the MMO thinks fit; or
- (c) refuse the application.
Notice of determination
27
- (1) Subject to sub-paragraph (2) or (3), the MMO must give notice to the undertaker of the determination of the application as soon as reasonably practicable after the application is received by the MMO.
- (2) Where the MMO has made a request under paragraph 25, the MMO must give notice to the undertaker of the determination of the application as soon as reasonably practicable once the further information is received.
- (3) Where the MMO refuses the application the refusal notice must state the reasons for the refusal.
SCHEDULE 4 — PROTECTIVE PROVISIONS
PART 1 — FOR THE PROTECTION OF THE STATUTORY CONSERVANCY AND NAVIGATION AUTHORITY FOR THE HUMBER
Interpretation
1
In this Part of this Schedule—
- “area of jurisdiction” means the area within the harbour limits, being the area in which the powers of the dock master may be exercised;
- “authorised works” means any work, operation or activity that the undertaker is authorised by this Order to construct or carry out;
- “environmental document” means— the environment statement prepared for the purposes of the application for this Order together with any supplementary environmental information or other document so prepared by way of clarification or amplification of the environmental statement; and any other document containing environmental information provided by the undertaker to the Secretary of State or the Statutory Conservancy and Navigation Authority or Trinity House for the purposes of any tidal works approval under article 37 (provision against danger to navigation), article 38 (lights on tidal works during construction) or article 39 (permanent lights on tidal works);
- “plans” includes sections, drawings, specifications, calculations and method statements;
- “the river” means the River Humber; and
- “the Statutory Conservancy and Navigation Authority” means for the purposes of this Protective Provision Associated British Ports in its capacity as statutory conservancy and navigation authority for the river Humber (as successor to the Conservancy Commissioners established under the Humber Conservancy Act 1868) and including in its role as competent harbour authority and local lighthouse authority for its statutory area.
General
2
- (1) The provisions of this Part of this Schedule, unless otherwise agreed in writing between the undertaker and the Statutory Conservancy and Navigation Authority, have effect until the commencement of the operation of the authorised development for the protection of the Statutory Conservancy and Navigation Authority and the users of the river.
- (2) For the purposes of this Part of this Schedule, the definition of “tidal work” is taken to include—
- (a) any projection over the river outside the area of jurisdiction by booms, cranes and similar plant or machinery, whether or not situated within the area of jurisdiction; and
- (b) any authorised work which affects the river or any functions of the Statutory Conservancy and Navigation Authority , whether or not that authorised work is within the limits of the Statutory Conservancy and Navigation Authority.
Tidal Works: approval of detailed design
3
- (1) Prior to the commencement of the authorised development in the marine environment the undertaker must submit to the Statutory Conservancy and Navigation Authority plans and sections of the tidal works or operation and such further particulars as the Statutory Conservancy and Navigation Authority may, within 28 days from the day on which plans and sections are submitted under this sub-paragraph, reasonably require.
- (2) Any approval of the Statutory Conservancy and Navigation Authority required under this paragraph shall be deemed to have been given if it is neither given nor refused (or is refused but without an indication of the grounds for refusal) within 28 days of the day on which the request for consent is submitted under sub-paragraph (1) must not be unreasonably withheld but may be given subject to such reasonable requirements as the Statutory Conservancy and Navigation Authority may make for the protection of—
- (a) traffic in, or the flow or regime of, the river;
- (b) the use of its operational land or the river for the purposes of performing its functions; or
- (c) the performance of any of its functions connected with environmental protection.
- (3) Requirements made under sub-paragraph (2) may include conditions as to—
- (a) the relocation, provision and maintenance of works, moorings, apparatus and equipment necessitated by the tidal work; and
- (b) the expiry of the approval if the undertaker does not commence construction of the tidal work approved within a prescribed period.
- (4) Before making a decision on any such approval, the Statutory Conservancy and Navigation Authority must take into account any opinion on plans and sections provided to it by the Environment Agency.
- (5) Whenever the undertaker provides the Secretary of State with an environmental document it must at the same time send a copy to the Statutory Conservancy and Navigation Authority.
Commencement of Tidal Works
4
Any operations for the construction of any tidal work approved in accordance with this Order, once commenced, must be carried out by the undertaker without unnecessary delay and to the reasonable satisfaction of the Statutory Conservancy and Navigation Authority so that river traffic, the flow or regime of the river and the exercise of the Statutory Conservancy and Navigation Authority’s functions do not suffer more interference than is reasonably practicable, and an authorised officer of the Statutory Conservancy and Navigation Authority is entitled at all reasonable times, on giving such notice as may be reasonable in the circumstances, to inspect and survey such operations.
Discharges, etc.
5
- (1) The undertaker must not without the Consent of the Statutory Conservancy and Navigation Authority—
- (a) deposit in or allow to fall or be washed into the river any gravel, soil or other material; or
- (b) discharge or allow to escape either directly or indirectly into the river any offensive or injurious matter in suspension or otherwise.
- (2) Any consent of the Statutory Conservancy and Navigation Authority under this paragraph must not be unreasonably withheld but may be given subject to such terms and conditions as the Statutory Conservancy and Navigation Authority may reasonably impose.
- (3) Any such approval is deemed to have been given if it is neither given nor refused (or is refused but without an indication of the grounds for refusal) within 28 days of the day on which the request for consent is submitted under sub-paragraph (1).
- (4) In its application to the discharge of water into the river, article 24 (discharge of water) has effect subject to the terms of any conditions attached to a consent given under this paragraph.
- (5) The undertaker must not, in exercise of the powers conferred by article 24 (discharge of water), damage or interfere with the beds or banks of any watercourse forming part of the river unless such damage or interference is approved as a tidal work under this Order or is otherwise approved in writing by the Statutory Conservancy and Navigation Authority.
Obstruction in river
6
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.