The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024
- (1) Where in consequence of the proposed construction of any part of the authorised works, the undertaker or NGT requires the removal of apparatus under paragraph 87(2) or NGT makes requirements for the protection or alteration of apparatus under paragraph 89, the undertaker shall use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised works and taking into account the need to ensure the safe and efficient operation of NGT’s undertaking and NGT shall use its best endeavours to co-operate with the undertaker for that purpose.
- (2) For the avoidance of doubt whenever NGT’s consent, agreement or approval is required in relation to plans, documents or other information submitted by the undertaker or the taking of action by the undertaker, it must not be unreasonably withheld or delayed.
Access
94
Subject to paragraph 84, if in consequence of the agreement reached in accordance with paragraph 86(1) or the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable NGT to maintain or use the apparatus no less effectively than was possible before such obstruction.
Arbitration
95
Any difference or dispute arising between the undertaker and NGT under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and NGT, be determined by arbitration in accordance with article 52 (arbitration).
Notices
96
Notwithstanding article 49 (Service of Notices), any plans submitted to NGT by the undertaker pursuant to paragraph 89 must be submitted to https://lsbud.co.uk/ or such other address as NGT may from time to time appoint instead for that purpose and notify to the undertaker in writing.
PART 8 — FOR THE PROTECTION OF NORTHERN GAS NETWORK’S APPARATUS
Application
97
For the protection of the statutory undertaker the following provisions shall, unless otherwise agreed in writing between the undertaker and the statutory undertaker, have effect.
Interpretation
98
In this Part—
- “1991 Act” means the New Roads and Street Works Act 1991;
- “alternative apparatus” means appropriate alternative apparatus to the reasonable satisfaction of the Statutory undertaker to enable the Statutory undertaker to fulfil its statutory functions in a manner no less efficient than previously;
- “commence” has the same meaning as in Schedule 3 of the Order;
- “functions” includes powers and duties;
- “in” in a context referring to Works, apparatus or alternative apparatus in land includes a reference to such Works, apparatus or alternative apparatus under, over, across, along or upon such land;
- “maintain” and “maintenance” shall include the ability and right to do any of the following: construct, use, repair, alter, inspect, renew or remove;
- “plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the works to be executed;
- “statutory undertaker” means Northern Gas Networks Limited (Company Number 05167070) whose registered office is at 1100 Century Way, Colton, Leeds, LS15 8TU;
99
Except for paragraphs 100 (apparatus of Statutory undertaker in affected streets), 104 (retained apparatus: protection) and 105 (expenses), this Schedule does not apply to apparatus in respect of which the relations between the undertaker and the statutory undertaker are regulated by the provisions of Part 3 of the 1991 Act.
Apparatus of Statutory undertaker in affected streets
100
Where any street is temporarily closed or diverted under the powers of article 14 (temporary closure of streets, cycle tracks and public rights of way) of this Order, the Statutory undertaker shall be at liberty at all times to take all necessary access across any such closed highway and/or to execute and do all such works and things in, upon or under any such highway as may be reasonably necessary or desirable to enable it to maintain any apparatus which at the time of the closure or diversion was in that highway, subject always to the undertaker’s unimpeded ability to carry out the Works.
Acquisition of land
101
Regardless of any provision in the Order or anything shown on the land plans or contained in the book of reference to the Order, the undertaker shall not acquire any apparatus owned by the Statutory undertaker or override any easement or other interest of the statutory undertaker otherwise than by agreement.
Removal or diversion of apparatus
102
- (1) If the undertaker acquires any interest in land in which the statutory undertaker’s apparatus is placed, that apparatus shall not be removed and any right of a statutory undertaker to maintain that apparatus in that land shall not be extinguished until alternative apparatus has been constructed and is in operation to the reasonable satisfaction of the statutory undertaker provided that the statutory undertaker shall use all reasonable endeavours to construct and install such alternative apparatus as soon as reasonably practicable.
- (2) If, for the purpose of executing any Works, the undertaker requires the removal or diversion of any apparatus, it shall give to the statutory undertaker written notice of that requirement, together with a plan of the Works and the removal or diversion works proposed, the proposed position of the alternative apparatus, and the proposed timeline for the works. The statutory undertaker shall reasonably approve these details within 28 days of receipt of such plan. The undertaker shall afford to the statutory undertaker to their reasonable satisfaction the necessary facilities and rights for—
- (a) the construction of alternative apparatus in other land either within the order land or otherwise; and
- (b) the maintenance of that apparatus
and the statutory undertaker shall complete the works using its reasonable endeavours to meet the undertaker’s proposed timeline, and in any event without undue delay, in accordance with the details provided by the undertaker under this sub-paragraph or as otherwise reasonably agreed by the Undertaker.
- (3) If, in consequence of the Works carried out by the undertaker, the statutory undertaker reasonably needs to remove or divert any of its apparatus, it shall without undue delay give the undertaker written notice of that requirement, together with a plan of the work proposed, the proposed position of the alternative apparatus and the proposed timeline for the works. The undertaker shall reasonably approve these details and shall afford to the statutory undertaker to their reasonable satisfaction the necessary facilities and rights for—
- (a) the construction of alternative apparatus; and
- (b) the maintenance of that apparatus
and the statutory undertaker shall complete the works without undue delay and in accordance with the approved details. If agreement cannot be reached the statutory undertaker reserves the right to terminate the Deed with immediate effect without liability.
- (4) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraphs (2) and (3), the statutory undertaker shall, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances in an endeavour to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed, but this obligation shall not require the statutory undertaker to use its compulsory purchase powers unless it elects to so do.
- (5) Paragraph 105 (Expenses) of this Schedule applies to removal or diversions works under this paragraph 102, but the statutory undertaker must provide to the undertaker a reasonable cost estimate for works that it proposes to carry out for the undertaker’s approval.
Facilities and rights for alternative apparatus
103
- (1) Where, in accordance with the provisions of this Schedule, the undertaker affords to the statutory undertaker facilities and rights for the construction and maintenance in the undertaker’s land of alternative apparatus in substitution for apparatus to be removed, those facilities and rights shall be granted upon such terms and conditions as may be agreed between the undertaker and the statutory undertaker and shall be no less favourable on the whole to the statutory undertaker than the facilities and rights enjoyed by it in respect of the apparatus to be removed, unless otherwise reasonably agreed.
- (2) If the facilities and rights to be afforded by the undertaker in respect of any alternative apparatus in the undertaker’s land are less favourable on the whole to the statutory undertaker than the facilities and rights enjoyed by it in respect of the apparatus to be removed, then the undertaker and the statutory undertaker shall agree appropriate compensation for the extent to which the new facilities and rights render the statutory undertaker less able to effectively carry out its undertaking or require it to do so at greater cost. If the amount of compensation cannot be agreed, then either the undertaker or the statutory undertaker may refer the matter to arbitration as per article 52 (arbitration) of this Order.
Retained apparatus: protection
104
- (1) Not less than 28 days before commencing the execution of any Works that will or may affect any apparatus, the removal or diversion of which has not been required by the undertaker under paragraph 102(2) or otherwise or by the statutory undertaker under paragraph 102(3), the undertaker shall submit to the statutory undertaker in question a plan showing the Works and the apparatus.
- (2) In relation to works which will or may be situated on, over, under or within 15 metres measured in any direction of any apparatus, or (wherever situated) impose any load directly upon any apparatus or involve embankment works within 15 metres of any apparatus, the plan to be submitted to the statutory undertaker under sub-paragraph (1) shall be detailed including a method statement and describing—
- (a) the exact position of the Works;
- (b) the level at which these are proposed to be constructed or renewed;
- (c) the manner of their construction or renewal including details of excavation, positioning of plant etc;
- (d) the position of all apparatus; and
- (e) by way of detailed drawings, every alteration proposed to be made close to (within 15 metres of) any apparatus.
- (3) The undertaker shall not commence the construction or renewal of any works to which sub-paragraphs (1) or (2) apply until the statutory undertaker has given written approval of the plan so submitted.
- (4) Any approval of the statutory undertaker required under sub-paragraph (3)—
- (a) may be given subject to reasonable conditions for any purpose mentioned in sub-paragraph (5) or (7); and
- (b) shall not be unreasonably withheld or delayed.
- (5) In relation to works to which sub-paragraph (2) applies, the statutory undertaker may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its system against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus.
- (6) Works executed under the Order to which this paragraph 104 applies shall be executed only in accordance with the relevant plan, notified under sub-paragraph (1) and approved (with conditions, if applicable) under sub-paragraph (4), as amended from time to time by agreement between the undertaker and the statutory undertaker. The statutory undertaker shall be entitled to watch and inspect the execution of those Works.
- (7) Where the statutory undertaker requires any protective works or subsidence monitoring to be carried out either by itself or by the undertaker (whether of a temporary or permanent nature), the statutory undertaker shall give the undertaker notice of such requirement in its approval under sub-paragraph (3), and—
- (a) such protective works shall be carried out to the statutory undertakers’ reasonable satisfaction prior to the carrying out of the relevant part of the Works;
- (b) ground subsidence monitoring shall be carried out in accordance with a scheme approved by the statutory undertaker (such approval not to be unreasonably withheld or delayed), which shall set out—
- (i) the apparatus which is to be subject to such monitoring;
- (ii) the extent of land to be monitored;
- (iii) the manner in which ground levels are to be monitored;
- (iv) the timescales of any monitoring activities; and
- (v) the extent of ground subsidence which, if exceeded, shall require the undertaker to submit for the statutory undertaker’s approval a ground subsidence mitigation scheme in respect of such subsidence;
- (c) if a subsidence mitigation scheme is required, it shall be carried out as approved by the statutory undertaker (such approval not to be unreasonably withheld or delayed).
- (8) Nothing in this paragraph shall preclude the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of the relevant Works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph shall apply to and in respect of the new plan.
- (9) The undertaker shall not be required to comply with sub-paragraphs (1) or (2) where it needs to carry out emergency works as defined in the 1991 Act, but in that case it shall give to the statutory undertaker notice as soon as is reasonably practicable and a plan of those works shall comply with the other requirements in this paragraph insofar as is reasonably practicable in the circumstances, provided that it always complies with sub-paragraph (10).
- (10) At all times when carrying out any works authorised under the Order that may or will affect the apparatus, the undertaker shall comply with the statutory undertaker’s policies for safe working in proximity to gas apparatus including the “Specification for safe working in the vicinity of Northern Gas Networks, Gas pipelines and associated installation requirements for third parties “NGN/SPSSW22” and the Health and Safety Executive guidance document “HS(G)47 Avoiding Danger from underground services”.
Expenses
105
- (1) Subject to the following provisions of this paragraph, the undertaker shall repay to the statutory undertaker as soon as reasonably practicable all charges, costs and expenses reasonably and properly incurred by the statutory undertaker in, or in connection with, the inspection, removal or diversion, relaying or replacing, alteration or protection of any apparatus or the construction of any new apparatus which may be reasonably required and necessary in consequence of the execution of the Works, including without limitation—
- (a) any costs reasonably incurred or compensation properly paid in connection with the acquisition of rights or the exercise of statutory powers for such apparatus, including without limitation in the event that the statutory undertaker elects to use compulsory purchase powers to acquire any necessary rights under 102(4);
- (b) in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus;
- (c) the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
- (d) the approval of plans;
- (e) the carrying out of protective works;
- (f) the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any works carried out pursuant to this Schedule; and
- (g) any statutory loss of supply payments under the ‘Guaranteed Standards of Service’ regime that the statutory undertaker may incur in consequence of the works, but in the event that such payments are likely to become payable, the statutory undertaker shall give the undertaker notice as soon as reasonably practicable of the payments and the likely amount.
- (2) The statutory undertaker shall use its reasonable endeavours to mitigate in whole or in part, and in any event to minimise, any expenses capable of being claimed under sub-paragraph (1). If requested to do so by the undertaker, the statutory undertaker shall provide an explanation of how the claimed expenses have been minimised. The undertaker shall only be liable to pay expenses that have been reasonably incurred.
- (3) There shall be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Schedule and which is not re-used as part of the alternative apparatus, that value being calculated after removal and not including the costs (if any) of disposing that apparatus.
- (4) If in accordance with the provisions of this part of this Schedule—
- (a) apparatus of greater capacity or of greater dimensions is placed in substitution for existing apparatus; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
then, if this incurs greater expense than would have been incurred by a like-for-like (or as close as practicable to like-for like) replacement at the same depth, the undertaker shall not be liable for this additional expense.
- (5) For the purposes of sub-paragraph (4)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus shall not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus.
Enactments and agreements
106
Nothing in this Schedule shall affect the provisions of any enactment or agreement regulating the relations between the undertaker and the statutory undertaker in respect of any apparatus laid or erected in land belonging to the undertaker.
Co-operation
107
Where in consequence of the proposed construction of any of the Works the undertaker or the statutory undertaker requires the removal of apparatus in accordance with the provisions of these Protective Provisions, each party shall use all reasonable endeavours to co-ordinate the execution of such works in the interests of safety and the efficient and economic execution of such works, taking into account the absolute need to ensure the safe and efficient operation of the statutory undertaker’s undertaking and its apparatus and the safe and efficient operation of the undertaker’s apparatus.
Access
108
If in consequence of the powers granted under the Order, the access to any apparatus is materially obstructed, the undertaker shall provide such alternative means of access to such apparatus as will enable the statutory undertaker to maintain or use the apparatus no less effectively than was possible before such obstruction.
Arbitration
109
Any difference or dispute arising between the undertaker and the statutory undertaker under this Schedule shall, unless otherwise agreed in writing between the undertaker and that statutory undertaker, be determined by arbitration in accordance with the relevant article of the Order.
Works falling outside of development authorised by the Order
110
Nothing in this schedule shall require the undertaker to carry out works, or require the undertaker to enable the statutory undertaker to carry out works, that are not authorised by the Order. The statutory undertaker shall not request any alteration, diversion, protective work or any other work which is not authorised to be carried out under the Order (but for the avoidance of doubt, it may elect to carry out such works itself under any other planning permission, permitted development rights or statutory powers (including those of compulsory acquisition) available to it).
Cathodic protection testing
111
Where in the reasonable opinion of either party—
- (a) the Authorised Development might interfere with the existing cathodic protection forming part of the apparatus; or
- (b) the apparatus might interfere with the proposed or existing cathodic protection forming part of the Authorised Development,
the parties shall co-operate in undertaking the tests which they consider reasonably necessary for ascertaining the nature and extent of such interference and measures for providing or preserving cathodic protection.
SCHEDULE 16 — AMENDMENT OF LOCAL LEGISLATION
PART 1 — LOCAL ENACTMENTS
| Year | Chapter | Title | Section |
|---|---|---|---|
| 1980 | XIV | West Yorkshire Act | 9 and 44 |
PART 2 — BYELAWS
| (1) Title | (2) Byelaw to be disapplied |
|---|---|
| Byelaws for the good rule and government of the City of Leeds and for the prevention of nuisances made by the Council of the City in pursuance of Section 235 of the Local Government Act 1972 | 5, 10, 11 and 17. |
SCHEDULE 17 — HEDGEROWS WHICH MAY BE REMOVED
| (1) Hedgerow | (2) Grid reference | (3) Importance | (4) Sheet number on Figure 8.6(B) (Volume 5, Document 5.4.8(C)) |
|---|---|---|---|
| HE001 | SE 57926 60107 | Important | Sheet 1 |
| HE002 | SE 56766 59769 | Important | Sheet 1 |
| HE003 | SE 56528 59909 | Important | Sheet 1 |
| HE004 | SE 56383 59858 | Important | Sheet 1 |
| HE005 | SE 56375 59877 | Important | Sheet 1 |
| HE006 | SE 56228 59999 | Important | Sheet 1 |
| HE007 | SE 56613 59612 | Important | Sheet 1 |
| HE008 | SE 56395 59455 | Important | Sheet 1 |
| HE009 | SE 56466 59439 | Important | Sheet 1 |
| HE010 | SE 56594 59226 | Important | Sheet 1 |
| HE011 | SE 56592 58923 | Important | Sheet 1 |
| HE012 | SE 56590 58905 | Important | Sheet 1 |
| HE013 | SE 56286 58301 | Important | Sheet 1 |
| HE014 | SE 55984 57930 | Important | Sheet 2 |
| HE015 | SE 55423 57809 | Not Important | Sheet 2 |
| HE016 | SE 55821 57613 | Important | Sheet 2 |
| HE019 | SE 55941 56647 | Not Important | Sheet 2 |
| HE020 | SE 56054 56443 | Not Important | Sheet 3 |
| HE021 | SE 56095 56337 | Not Important | Sheet 3 |
| HE022 | SE 56199 55768 | Not Important | Sheet 3 |
| HE023 | SE 56030 56061 | Not Important | Sheet 3 |
| HE024 | SE 55311 56091 | Important | Sheet 3 |
| HE025 | SE 55430 56997 | Important | Sheet 2 |
| HE026 | SE 55425 57100 | Important | Sheet 2 |
| HE027 | SE 55396 57127 | Important | Sheet 2 |
| HE028 | SE 55402 57199 | Important | Sheet 2 |
| HE029 | SE 55176 57051 | Not Important | Sheet 2 |
| HE030 | SE 54714 56776 | Important | Sheet 2 |
| HE031 | SE 54195 56282 | Important | Sheet 3 |
| HE032 | SE 54062 56250 | Important | Sheet 3 |
| HE033 | SE 53845 55776 | Important | Sheet 3 |
| HE034 | SE 54044 55433 | Important | Sheet 3 |
| HE035 | SE 54105 55306 | Important | Sheet 3 |
| HE036 | SE 54661 54929 | Not Important | Sheet 3 |
| HE037 | SE 54767 54889 | Important | Sheet 3 |
| HE038 | SE 54897 54831 | Important | Sheet 3 |
| HE039 | SE 54915 54811 | Important | Sheet 3 |
| HE040 | SE 52567 56254 | Important | Sheet 4 |
| HE041 | SE 52393 56293 | Important | Sheet 4 |
| HE042 | SE 52378 56407 | Important | Sheet 4 |
| HE043 | SE 52327 56401 | Important | Sheet 4 |
| HE044 | SE 52297 56319 | Important | Sheet 4 |
| HE045 | SE 51974 56589 | Not Important | Sheet 4 |
| HE046 | SE 51492 56433 | Not Important | Sheet 4 |
| HE047 | SE 51418 56409 | Important | Sheet 4 |
| HE048 | SE 51315 56313 | Important | Sheet 4 |
| HE049 | SE 50992 56234 | Important | Sheet 4 |
| HE050 | SE 51002 56207 | Not Important | Sheet 4 |
| HE051 | SE 51192 56053 | Important | Sheet 4 |
| HE052 | SE 51118 55837 | Important | Sheet 4 |
| HE053 | SE 514925 5393 | Important | Sheet 4 |
| HE054 | SE 51147 54638 | Not Important | Sheet 5 |
| HE055 | SE 50777 54702 | Important | Sheet 5 |
| HE056 | SE 51028 54457 | Important | Sheet 5 |
| HE057 | SE 51041 54448 | Important | Sheet 5 |
| HE058 | SE 50672 54388 | Important | Sheet 5 |
| HE059 | SE 50391 53678 | Important | Sheet 5 |
| HE060 | SE 50323 53469 | Not Important | Sheet 5 |
| HE061 | SE 49062 52067 | Important | Sheet 6 |
| HE062 | SE 49050 52058 | Important | Sheet 6 |
| HE063 | SE 48992 52055 | Important | Sheet 6 |
| HE064 | SE 49251 51962 | Important | Sheet 6 |
| HE065 | SE 49224 51921 | Important | Sheet 6 |
| HE066 | SE 49481 51810 | Important | Sheet 6 |
| HR067 | SE 49045 50836 | Important | Sheet 6 |
| HE068 | SE 49062 50805 | Important | Sheet 6 |
| HE069 | SE 48914 50331 | Not Important | Sheet 7 |
| HE070 | SE 48638 48964 | Important | Sheet 7 |
| HE071 | SE 48925 48439 | Important | Sheet 7 |
| HE072 | SE 47954 46665 | Important | Sheet 8 |
| HE073 | SE 48452 46027 | Important | Sheet 8 |
| HE074 | SE 47649 45031 | Important | Sheet 8 |
| HE075 | SE 47612 45002 | Important | Sheet 8 |
| HE076 | SE 47501 44507 | Important | Sheet 8 |
| HE077 | SE 46923 42815 | Important | Sheet 9 |
| HE078 | SE 46856 42552 | Important | Sheet 9 |
| HE079 | SE 46266 42420 | Important | Sheet 9 |
| HE080 | SE 46467 42212 | Important | Sheet 9 |
| HE081 | SE 46287 41936 | Important | Sheet 9 |
| HE082 | SE 46407 41818 | Not Important | Sheet 9 |
| HE083 | SE 46401 41805 | Not Important | Sheet 9 |
| HE084 | SE 45808 41712 | Not Important | Sheet 9 |
| HE085 | SE 45796 41720 | Important | Sheet 9 |
| HE086 | SE 45430 41955 | Important | Sheet 9 |
| HE087 | SE 45627 40876 | Important | Sheet 9 |
| HE088 | SE 46432 38155 | Important | Sheet 10 |
| HE089 | SE 46114 38043 | Important | Sheet 10 |
| HE090 | SE 46154 37942 | Important | Sheet 10 |
| HE091 | SE 46462 37988 | Important | Sheet 10 |
| HE092 | SE 46386 37801 | Important | Sheet 10 |
| HE093 | SE 46733 36981 | Important | Sheet 10 |
| HE094 | SE 46722 36956 | Important | Sheet 10 |
| HE095 | SE 46976 35119 | Important | Sheet 11 |
| HE096 | SE 47840 33184 | Important | Sheet 12 |
| HE097 | SE 47043 32182 | Important | Sheet 12 |
| HE098 | SE 47172 30889 | Important | Sheet 13 |
| HE099 | SE 47219 30876 | Important | Sheet 13 |
| HE100 | SE 47168 30858 | Important | Sheet 13 |
| HE101 | SE 48403 30402 | Important | Sheet 13 |
| HE102 | SE 47535 29902 | Not Important | Sheet 13 |
| HE103 | SE 47553 29662 | Not Important | Sheet 13 |
| HE104 | SE 48421 29425 | Important | Sheet 13 |
| HE105 | SE 48437 29327 | Important | Sheet 13 |
| HE106 | SE 48625 29000 | Important | Sheet 13 |
Signed
Signed by authority of the Secretary of State for Energy Security and Net Zero
Fiona Mettam — Director, Energy Development — Department for Energy Security and Net Zero — 14th March 2024
Explanatory note
(This note is not part of the Order)
EXPLANATORY NOTE
This Order authorises National Grid to undertake works to the national electricity transmission system between the existing substation at Monk Fryston to the existing substation at Osbaldwick. The proposed development is required to provide sufficient transmission capacity to enable the connection of new electricity generation projects in the region, and to carry out all associated works.
The Order also makes provision in connection with the maintenance of the authorised development.
The Order permits National Grid to acquire compulsorily or by agreement, land and rights in land and to use land for this purpose.
A copy of the plans and book of reference referred to in this Order and certified in accordance with article 48 (certification of plans, etc.) of this Order may be inspected free of charge during working hours at the offices of National Grid Electricity Transmission plc, 1-3 Strand, London WC2N 5EH.
Footnotes
[^f00001]: 2008 c. 29. Section 37 was amended by Schedule 13 to the Localism Act 2011 (c. 20).
[^f00002]: S.I. 2009/2264.
[^f00003]: S.I. 2010/103, amended by regulation 5 of S.I. 2012/635.
[^f00004]: Section 74 was amended by the Localism Act 2011 (c. 20) section 240(2), Schedule 13 paragraph 29(2) and Schedule 25 Part 20.
[^f00005]: S.I. 2017/572.
[^f00006]: Section 104 was amended by section 58(5) of the Marine and Coastal Access Act 2009 (c. 23) and by section 240(2) and Schedule 13, paragraph 49(1) to (6) of the Localism Act 2011 (c. 20).
[^f00007]: 1961 c. 33.
[^f00008]: 1965 c. 56.
[^f00009]: 1980 c. 66.
[^f00010]: 1981 c. 66.
[^f00011]: 1984 c. 27.
[^f00012]: 1989 c. 29.
[^f00013]: 1990 c. 8.
[^f00014]: 1991 c. 22.
[^f00015]: 2003 c. 21.
[^f00016]: 2008 c. 29.
[^f00017]: 2016 c. 22.
[^f00018]: S.I. 2016/1154.
[^f00019]: 1971 c. 80.
[^f00020]: “main river” is defined in section 113 of the Water Resources Act 1991 (c. 57), as amended by Water Act 2014 (c. 21), Part 2, section 59(3).
[^f00021]: 1981 c. 67. The definition of “owner” was amended by paragraph 9 of Schedule 15 to, the Planning and Compensation Act 1991 (c. 34). There are other amendments to section 7 which are not relevant to this Order.
[^f00022]: 2004 c. 18.
[^f00023]: 1991 c. 59. Section 23 was amended by the Environment Act 1995 (c. 29), Schedule 22, paragraph 192 and the Flood and Water Management Act 2010 (c. 29), Schedule 2, paragraph 32 and the Natural Resources Body for Wales (Functions) Order 2013/755 Schedule 2(1), paragraph 322(2).
[^f00024]: 1991 c. 56, as amended by S.I. 2009/3104.
[^f00025]: Section 48 was amended by section 124 of the Local Transport Act 2008 (c. 26).
[^f00026]: “street authority” is defined in section 49, which was amended by paragraph 117 of Schedule 1 to the Infrastructure Act 2015 (c. 7).
[^f00027]: S.I. 2010/948.
[^f00028]: 1989 c. 29.
[^f00029]: Section 53 was added by section 45 of the Traffic Management Act 2004.
[^f00030]: Section 56 was amended by sections 40 and 43 of, and Schedule 1 to, the Traffic Management Act 2004.
[^f00031]: Section 56A was inserted by section 44 of the Traffic Management Act 2004.
[^f00032]: Section 58 was amended by sections 40 and 51 of, and Schedule 1 to, the Traffic Management Act 2004.
[^f00033]: Section 58A was inserted by section 52 of the Traffic Management Act 2004.
[^f00034]: Section 73A was inserted by section 55 of the Traffic Management Act 2004.
[^f00035]: Section 73B was inserted by section 55 of the Traffic Management Act 2004.
[^f00036]: Section 73C was inserted by section 55 of the Traffic Management Act 2004.
[^f00037]: Section 78A was inserted by section 57 of the Traffic Management Act 2004.
[^f00038]: Schedule 3A was inserted by section 52(2) of, and Schedule 4 to, the Traffic Management Act 2004.
[^f00039]: Section 54 was amended by section 49(1) of the Traffic Management Act 2004
[^f00040]: Section 55 was amended by sections 49, 51 of, and schedule 1 to, the Traffic Management Act 2004 (c. 18).
[^f00041]: Section 57 was amended by section 52 of, and Schedule 1 to, the Traffic Management Act 2004.
[^f00042]: Section 59 was amended by section 42 of the Traffic Management Act 2004.
[^f00043]: Section 60 was amended by Schedule 1 to the Traffic Management Act 2004.
[^f00044]: Section 68 was amended by Schedule 1 to the Traffic Management Act 2004.
[^f00045]: Section 69 was amended by Schedule 1 to the Traffic Management Act 2004 (c. 18).
[^f00046]: Section 71 was amended by Schedule 1 to the Traffic Management Act 2004.
[^f00047]: 1991 c. 18.
[^f00048]: 1991 c. 18.
[^f00049]: 1991 c. 56. Section 106 was amended by sections 35(1) and (8) and 43(2) of the Competition and Service (Utilities) Act 1992 (c. 43), sections 36(2) and 99 of the Water Act 2003 (c. 37) and section 49 of, and paragraph 16(1) of Schedule 3 to the Flood and Water Management Act 2010 (c. 29).
[^f00050]: 1964 c. 40. Paragraph 9B was inserted into Schedule 2 by the Transport and Works Act 1992 (c. 42), section 63(1) and Schedule 3, paragraph 9(1) and (2), subject to transitional provisions specified in S.I. 1992/1347 article 3.
[^f00051]: 1991 c. 57.
[^f00054]: As amended by Schedule 1, paragraph 293 of S.I. 2009/1307.
[^f00055]: As amended by sections 62(3) and 139(4) to (9) of, paragraphs 27 and 28 of Schedule 13 and Part 3 of Schedule 23 to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).
[^f00056]: As amended by section 190 of, and paragraph 17 of Schedule 16 to, the Housing and Planning Act 2016 (c. 22).
[^f00057]: 1981 c. 67. Words substituted by the Coal Industry Act 1994 (c. 21) Schedule 9 paragraph 27(3).
[^f00058]: Section 125 was amended by section 190 of, and paragraph 17, Schedule 16 of the Housing and Planning Act 2016 (c. 22).
[^f00059]: Section 4A(1) was inserted by Part 7, section 202(1) of the Housing and Planning Act 2016 (c. 22), subject to the transitional provisions specified in S.I. 2016/733 regulation 9.
[^f00060]: Section 118 was amended by paragraphs 1 and 59 of Schedule 13, and Part 20 of Schedule 25 to, the Localism Act 2011 (c. 20) and section 92(4) of the Criminal Justice and Courts Act 2015 (c. 2).
[^f00061]: Section 11A was inserted by section 186(3) of the Housing and Planning Act 2016 (c. 22) subject to the transitional provisions specified in S.I. 2017/75 regulation 3.
[^f00062]: Schedule 2A was inserted by section 216(3) of, and paragraph 3 of Schedule 17 to, the Housing and Planning Act 2016 (c. 22), subject to the transitional provisions specified in S.I. 2017/75 regulation 5.
[^f00063]: Section 5A to the 1981 Act was inserted by section 182(2) of the Housing and Planning Act 2016 (c. 22).
[^f00064]: Section 5B was inserted by section 202(2) of the Housing and Planning Act 2016 (c. 22).
[^f00065]: Section 6 was amended by section 4 of, and paragraph 52(2) of Schedule 2 to the Planning (Consequential Provisions) Act 1990 (c. 11) and paragraph 7 of Schedule 15 to the Housing and Planning Act 2016 (c. 22).
[^f00066]: Section 7(1) was substituted by paragraphs 1 and 3 of Schedule 18 to the Housing and Planning Act 2016 (c. 22).
[^f00067]: Schedule A1 was inserted by paragraphs 1 and 6 of Part 1 of Schedule 18 to the Housing and Planning Act 2016 (c. 22).
[^f00068]: Section 125 was amended by section 216(3) of, and paragraph 17 of Schedule 16 to, the Housing and Planning Act 2016 (c. 22).
[^f00069]: Part 1 was amended by S.I. 1994/2716, 1998 (c. 38), S.I. 1999/481, S.I. 2009/1307, S.I. 2010/490, S.I. 2017/1012 and 2016 (c. 9).
[^f00070]: There are no amendments relevant to section 85 of the act.
[^f00071]: 2017 c. 20.
[^f00072]: 1991 c. 22. Part 3 was amended by 2004 (c. 18) perspective changes to Part 3 are still to come into force, S.I. 2007/1952, S.I. 2008/102 (w. 55) and 2003 (c. 21).
[^f00073]: Section 151 was implemented by Article 1, Section 2 and Schedule 1 of S.I. 2003/1900, Article 3 of S.I. 2003/3142; as amended by Schedule 1 of S.I. 2011/1210. There are other amendments to section 151 which are not relevant to this Order.
[^f00074]: 1990 c. 43. There are amendments to this sub-section which are not relevant to this Order.
[^f00075]: 1974 c. 40. Section 61 was amended by section 162(1) of, and paragraph 15(3) of Schedule 15 to, the Environmental Protection Act 1990 (c. 43). There are other amendments to section 61 but none are relevant to this Order.
[^f00076]: 1991 c. 59, definition substituted by Part V, section 100(2) of the Environment Act 1995 (c. 25).
[^f00077]: 2004 c. 18.
[^f00078]: S.I. 2012/605.
[^f00079]: S.I. 1997/1160.
[^f00080]: 1978 c. 30.
[^f00081]: 1990 c. 43.
[^f00082]: 1973 c. 26.
[^f00083]: Section 58(1) was amended by section 16(3) of, the Compulsory Purchase (Vesting Declarations) Act 1981 (c. 66), section 4 of, and paragraph 29(1) of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11), and Schedule 1 of The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009. S.I. 2009/1307.
[^f00084]: Section 11 was amended by section 34(1) of, and Schedule 4, paragraph 14(3)(a) to, the Acquisition of Land Act 1981 (c. 67), section 3 of, and Part 1 of Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c. 71), section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (No. 1), and section 186 of the Housing and Planning Act 2016 (c. 22). S.I. 2009/1307.
[^f00085]: Section 12, and 12(3) were amended by section 56(2) of, and Part 1 of Schedule 9 to, the Courts Act 1971 (c. 23).
[^f00086]: Section 13 was amended by section 139(4) to (9) and paragraphs 27 and 28 of Schedule 13 and Part 3 of Schedule 23 to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).
[^f00087]: Section 20 was amended by paragraph 4 of Schedule 15(1) to the Planning and Compensation Act 1991 (c. 34) and Schedule 1, paragraph 70. S.I. 2009/1307.
[^f00088]: 1989 c. 29.
[^f00089]: 1991 c. 56.
[^f00090]: 1986 c. 44. A new section 7 was substituted by section 5 of the Gas Act 1995 (c. 45), and was further amended by section 76 of the Utilities Act 2000 (c. 27).
[^f00091]: 2003 c. 21. See section 106.
[^f00092]: 1984 c. 12. Paragraph 23 of Schedule 2 has been repealed by the Digital Economy Act 2017 (c. 30), Part 2 Section 4(1) and subject to the transitional provisions specified in section 4(10) and Schedule 2 and S.I. 2017/1008 regulations 3 and 5.
Editorial notes
[^key-02af880fd43e9b9c4073e8a5f33b73c5]: Sch. 15 para. 51 in force at 5.4.2024, see art. 1
[^key-037405a6c147dcb4444d1383de15e7d0]: Words in Sch. 3 para. 2(3) substituted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-03b9261c561a0993ddf8c34f0e74b377]: Sch. 3 para. 11 in force at 5.4.2024, see art. 1
[^key-03f5bc9ff5a209f0fa6ee577463cf63a]: Sch. 7 Pt. 1 in force at 5.4.2024, see art. 1
[^key-05c43145864dc678cdf1f416f8108c39]: Sch. 15 para. 60 in force at 5.4.2024, see art. 1
[^key-0883176b15b45bead0a89882d64e9caf]: Sch. 10 para. 5 in force at 5.4.2024, see art. 1
[^key-0a03949ea703c4ebd7ead39dd63afd35]: Sch. 15 para. 34 in force at 5.4.2024, see art. 1
[^key-0b8d66a59c8b57d0fb42bf1f158a6326]: Sch. 15 para. 1 in force at 5.4.2024, see art. 1
[^key-0ca839fa359a6e1be193b827e03421ac]: Art. 17 in force at 5.4.2024, see art. 1
[^key-0cd4446b27afb107112ff0982118ad63]: Art. 28 in force at 5.4.2024, see art. 1
[^key-0da43bea48a3443f7c970aef9b0d0c6f]: Sch. 15 para. 50 in force at 5.4.2024, see art. 1
[^key-0da8485fad165ab94e424f0c5fd14556]: Sch. 15 para. 10 in force at 5.4.2024, see art. 1
[^key-0dafd2e0670d625031220a5b8b391d39]: Art. 6 in force at 5.4.2024, see art. 1
[^key-0dc2712c6c4989316d9a62acec7bd1eb]: Sch. 15 para. 104 in force at 5.4.2024, see art. 1
[^key-0e23bbba4bbbcd89b60914e77423616d]: Sch. 15 para. 80 in force at 5.4.2024, see art. 1
[^key-0e54813e8fa423c30c24823eab5a857f]: Sch. 15 para. 62 in force at 5.4.2024, see art. 1
[^key-109df3dfb1abc10d97b6d519848ce4fc]: Sch. 3 para. 6 in force at 5.4.2024, see art. 1
[^key-10fa49fa82c00dd2957b7a850df2d7bc]: Sch. 11 Pt. 1 in force at 5.4.2024, see art. 1
[^key-1196025b61f91f41f9eea6bb979165b3]: Sch. 1 in force at 5.4.2024, see art. 1
[^key-11f26a4f14b2e94da3421520158c9f5f]: Sch. 15 para. 92 in force at 5.4.2024, see art. 1
[^key-1325dbcacfc80e1cc61f8e5c713b45a1]: Sch. 3 para. 4 in force at 5.4.2024, see art. 1
[^key-144a26b205d3660ca168cc3ea00b917e]: Art. 33 in force at 5.4.2024, see art. 1
[^key-14dac07c1ee191614c2ce2b3c6fa55d8]: Sch. 15 para. 18 in force at 5.4.2024, see art. 1
[^key-1548084e327be972e36b331624e4ec35]: Art. 23 in force at 5.4.2024, see art. 1
[^key-15e7178a46e129a641f739706254a840]: Words in art. 2 substituted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-16616bf2d72a5bac824bbbfa4f6ad29b]: Sch. 15 para. 100 in force at 5.4.2024, see art. 1
[^key-17bc107006ce587739d16619a561bc48]: Art. 34 in force at 5.4.2024, see art. 1
[^key-18420e81480e02592e4cacbc4e531bda]: Sch. 15 para. 90 in force at 5.4.2024, see art. 1
[^key-18c7acda50445bb29e41d21ccb2f1fe7]: Sch. 7 Pt. 2 in force at 5.4.2024, see art. 1
[^key-19bfe2698e1924f0a12c5a480cf46627]: Sch. 15 para. 32 in force at 5.4.2024, see art. 1
[^key-1a0a415a7f03a0fca912ab8168874ed3]: Sch. 15 para. 44 in force at 5.4.2024, see art. 1
[^key-1ace4d5efc0d1d9d65ec63cb5b62d422]: Sch. 2 Pt. 1 in force at 5.4.2024, see art. 1
[^key-1b6f3d33a0b5cf0378d73d8aeef93e05]: Sch. 15 para. 77 in force at 5.4.2024, see art. 1
[^key-1e54af1396e8498a16d753992e3e7263]: Sch. 15 para. 78 in force at 5.4.2024, see art. 1
[^key-1f350fcf698c89f235e661426019d1d6]: Sch. 5 para. 7 in force at 5.4.2024, see art. 1
[^key-1f8cec97dd9941c9b48980fdcc403c77]: Art. 9 in force at 5.4.2024, see art. 1
[^key-207e01e611036bfabe6fe6237f8018b7]: Sch. 15 para. 58 in force at 5.4.2024, see art. 1
[^key-213493ec63cdc9c8d01f6177803d0068]: Words in Sch. 3 para. 10(1) inserted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-233ba03bc32d594b1c0d1152ae578a7a]: Sch. 15 para. 25 in force at 5.4.2024, see art. 1
[^key-23dc2a919f316c2650bdea094b777af8]: Sch. 8 Pt. 2 in force at 5.4.2024, see art. 1
[^key-2447801b85269ff26e373740912c4c45]: Sch. 6 in force at 5.4.2024, see art. 1
[^key-252e7b60c1ea4f5e0a228492189dbd30]: Sch. 5 para. 9 in force at 5.4.2024, see art. 1
[^key-259b700945b251ddb076ea0bd06515be]: Sch. 15 para. 13 in force at 5.4.2024, see art. 1
[^key-25dee60d272335d53dbcd17e1cfcb606]: Sch. 10 para. 3 in force at 5.4.2024, see art. 1
[^key-260edcea5fe6809ed1e5c1ab1fe59b35]: Sch. 15 para. 87 in force at 5.4.2024, see art. 1
[^key-268ce762dd74d332ae3e2bf8437c3030]: Sch. 15 para. 111 in force at 5.4.2024, see art. 1
[^key-28b5aef9e1a6648403ff353b6b5805ac]: Art. 2 in force at 5.4.2024, see art. 1
[^key-29b672ad7915352878c03b7fc046f552]: Sch. 15 para. 89 in force at 5.4.2024, see art. 1
[^key-2c2ae56b7094220b36fdece5a8c0f9e5]: Sch. 16 Pt. 1 in force at 5.4.2024, see art. 1
[^key-2c5897e7310714eda798231c1ce6f30e]: Sch. 15 para. 63 in force at 5.4.2024, see art. 1
[^key-2d202964d2767b12f5c27f70a0f1ddde]: Sch. 15 para. 41 in force at 5.4.2024, see art. 1
[^key-2da950a5f31f355ea3e56c16b3b6baa3]: Art. 21 in force at 5.4.2024, see art. 1
[^key-2dc50390ed77d82c417464d7bcd001ce]: Sch. 5 para. 8 in force at 5.4.2024, see art. 1
[^key-2e7cb3dd757256f864c59ec41f22c443]: Sch. 3 para. 3 in force at 5.4.2024, see art. 1
[^key-2f168916c047008cf2e28c8442cba9e3]: Art. 21(1)(a): semicolon omitted (12.6.2024) by virtue of The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-3007389cd9c12ec0bf372b48e6ff3cf0]: Sch. 11 Pt. 2 in force at 5.4.2024, see art. 1
[^key-3029ffeba25de1aec53b36c3ea29ca60]: Sch. 15 para. 47 in force at 5.4.2024, see art. 1
[^key-319cc5718d8dd6f07e4704b15682a831]: Sch. 2 Pt. 8 in force at 5.4.2024, see art. 1
[^key-3220d771c81c79b75d6056cfadb2399a]: Art. 50 in force at 5.4.2024, see art. 1
[^key-323267890455f36088094a263a89af4f]: Sch. 5 para. 3 in force at 5.4.2024, see art. 1
[^key-339d096ef04813ed3bb7597c42424de1]: Sch. 15 para. 79 in force at 5.4.2024, see art. 1
[^key-33bde34b929b473b2535919e2ee4b8c1]: Words in Sch. 15 para. 67(2)(e) substituted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-33f1cd3d1a67404082a03ca2eeee8f10]: Sch. 15 para. 46 in force at 5.4.2024, see art. 1
[^key-344b34fa4ae814c0c6c99e679a5770aa]: Word in art. 48(k) inserted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-369267ccea79c69bd01035330062f2db]: Sch. 10 para. 1 in force at 5.4.2024, see art. 1
[^key-37ac5048e6ff7d282667c23bf3f27ee3]: Art. 13 in force at 5.4.2024, see art. 1
[^key-3a67f2f191c7cda1ee7768226c229be0]: Sch. 15 para. 61 in force at 5.4.2024, see art. 1
[^key-3bb0fb00157eb9f3282407e285aabf83]: Art. 46 in force at 5.4.2024, see art. 1
[^key-3e6b1d8848816e126fb655b887a165bd]: Art. 24 in force at 5.4.2024, see art. 1
[^key-3f07a336bcd9c5a3b499141abe41f764]: Art. 36 in force at 5.4.2024, see art. 1
[^key-40fcdd6fb8da4eb8584519eb9a3dd568]: Sch. 15 para. 55 in force at 5.4.2024, see art. 1
[^key-417f0c826edc6d38339add4c51ceef38]: Sch. 15 para. 35 in force at 5.4.2024, see art. 1
[^key-41a970f9c9d4fa913ac2bf4b8ae6682d]: Sch. 15 para. 91 in force at 5.4.2024, see art. 1
[^key-43efd73c0a66ff4ef1d3de31d98c57c4]: Sch. 2 Pt. 4 in force at 5.4.2024, see art. 1
[^key-44c37a17e00071ec8c7d147dc179490a]: Art. 49 in force at 5.4.2024, see art. 1
[^key-44e762c121b319e286b6f7f660a8c449]: Sch. 15 para. 11 in force at 5.4.2024, see art. 1
[^key-459a12157f9d524e64e9a4292885e65b]: Sch. 15 para. 82 in force at 5.4.2024, see art. 1
[^key-47577e37f65dd22c95ef6c702295378c]: Words in Sch. 15 para. 68(7) substituted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-48ee3113d175afb6bc864abf013386bc]: Sch. 15 para. 109 in force at 5.4.2024, see art. 1
[^key-4a317645059d3d4d554d5982c63a5180]: Art. 16 in force at 5.4.2024, see art. 1
[^key-4b995e39da8d6c42ff27292c38893c68]: Sch. 9 Pt. 2 in force at 5.4.2024, see art. 1
[^key-4c60033ae94db00c3123c366ea0ca797]: Sch. 15 para. 56 in force at 5.4.2024, see art. 1
[^key-4e884a0259675b14e9652617195bc856]: Sch. 15 para. 101 in force at 5.4.2024, see art. 1
[^key-500abe5cfe1b74ce69d96a06a62b4c8f]: Sch. 15 para. 62: semicolon inserted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-5083f48e46f0bf81e4eeabc497068b99]: Sch. 15 para. 40 in force at 5.4.2024, see art. 1
[^key-51baff691600f5fa4929e587c36c0487]: Sch. 15 para. 38 in force at 5.4.2024, see art. 1
[^key-52129d2b7079c887fcc46519f6d7a852]: Sch. 15 para. 75 in force at 5.4.2024, see art. 1
[^key-53169281b115a22c5256992ee796101b]: Sch. 4 para. 4 in force at 5.4.2024, see art. 1
[^key-532c486e6c3a2384d56e9722526772a1]: Words in Sch. 3 para. 18(3) substituted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-538549fab945162ec8f3ddbf01518b09]: Sch. 10 para. 8 in force at 5.4.2024, see art. 1
[^key-543bfeb83a60dd1c97a46a737fcf94f0]: Art. 52 in force at 5.4.2024, see art. 1
[^key-54fc3820a99a59524f77569ab961815d]: Sch. 15 para. 69 in force at 5.4.2024, see art. 1
[^key-5525c04bf42a722842b0f41b5f36c8ea]: Art. 51 in force at 5.4.2024, see art. 1
[^key-56d638335c17912680389f69b58fc61f]: Sch. 15 para. 4 in force at 5.4.2024, see art. 1
[^key-579bf32cf393ec9745f6cfea2bb54b6f]: Sch. 10 para. 4 in force at 5.4.2024, see art. 1
[^key-581abb5b086e1dfd8fd22a4767cb847b]: Sch. 15 para. 39 in force at 5.4.2024, see art. 1
[^key-5a6f8b2ab99a108a0390f8007128cc41]: Sch. 15 para. 68 in force at 5.4.2024, see art. 1
[^key-5b364f98843fa08acf9c81c011d4a023]: Sch. 15 para. 21 in force at 5.4.2024, see art. 1
[^key-5c3a14aef0d555761d527a16264018a2]: Sch. 15 para. 76 in force at 5.4.2024, see art. 1
[^key-5ce3d56f07058c7404c206c727e19f76]: Sch. 4 para. 5 in force at 5.4.2024, see art. 1
[^key-629b319da5eda2ba94bcdc92472e62c3]: Sch. 5 para. 4 in force at 5.4.2024, see art. 1
[^key-6470a0b8c05ad2945d5809cae7398927]: Sch. 15 para. 70 in force at 5.4.2024, see art. 1
[^key-65dd4776415482325a8b299eb060be6d]: Sch. 15 para. 57 in force at 5.4.2024, see art. 1
[^key-687f9cbcaadebfad45bb68074e603232]: Sch. 15 para. 29 in force at 5.4.2024, see art. 1
[^key-69969ec8c00383dccea1c637138365e1]: Sch. 15 para. 59 in force at 5.4.2024, see art. 1
[^key-6a96faf5f4a471c361aecf28d69afbfc]: Sch. 15 para. 12 in force at 5.4.2024, see art. 1
[^key-6ac83ab244279586e2e0e5e4dcc95cc4]: Art. 14 in force at 5.4.2024, see art. 1
[^key-6ccab47a1cdb54f944aa6aeda365b0d1]: Sch. 12 Pt. 1 in force at 5.4.2024, see art. 1
[^key-710012e7cd0f262201bbb810cccb1b09]: Sch. 2 Pt. 3 in force at 5.4.2024, see art. 1
[^key-71c385b7a2ddbfefe80f5cb1023f138a]: Sch. 2 Pt. 5 in force at 5.4.2024, see art. 1
[^key-7495bac44cf75e1c29a9d8dcee79b6b5]: Sch. 3 para. 13 in force at 5.4.2024, see art. 1
[^key-75bd927b92b6c4c7210016aba7233074]: Sch. 2 Pt. 2 in force at 5.4.2024, see art. 1
[^key-77425e536251b07315f160b94172eb61]: Sch. 15 para. 36 in force at 5.4.2024, see art. 1
[^key-77972787579b099cefd84c1f516a0b26]: Sch. 15 para. 8 in force at 5.4.2024, see art. 1
[^key-784bd8998dee2a327cc93a155f531041]: Sch. 15 para. 3 in force at 5.4.2024, see art. 1
[^key-78e09ee52cd2d5f27a6d40bfbd7c0337]: Art. 42 in force at 5.4.2024, see art. 1
[^key-793f5e00d2e1875a4509451c42f2c3a1]: Sch. 15 para. 81 in force at 5.4.2024, see art. 1
[^key-796ff5077cda089bd6d1b5b8140aae78]: Art. 10 in force at 5.4.2024, see art. 1
[^key-7c8d0847f6f1d12c70ccb23336797a7d]: Sch. 15 para. 105 in force at 5.4.2024, see art. 1
[^key-7e4636978e597db45d41213c740442d5]: Sch. 15 para. 66 in force at 5.4.2024, see art. 1
[^key-7ecb0c38422490f376ace7c1578b759c]: Sch. 15 para. 83 in force at 5.4.2024, see art. 1
[^key-7fedcd8845598caa2f4d695358806f6f]: Sch. 3 para. 2 in force at 5.4.2024, see art. 1
[^key-8004311d0f94eb414af97b09924f6f87]: Words in Sch. 3 para. 10(2) inserted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-80304064ff0cf23a832acc33966ea6b3]: Words in Sch. 3 para. 19(4) substituted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-8131b178274f7b2198cf5b20d2fa2cae]: Art. 43 in force at 5.4.2024, see art. 1
[^key-816be88360406c78413f1ac08d534580]: Art. 22 in force at 5.4.2024, see art. 1
[^key-82ca0335e733aa1398a8270161593d97]: Art. 27 in force at 5.4.2024, see art. 1
[^key-830147a5d56835716136a2536ab2135a]: Sch. 3 para. 10 in force at 5.4.2024, see art. 1
[^key-875a26e3409289ce22862da2de7ce241]: Art. 48(k): comma omitted (12.6.2024) by virtue of The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-878a97646ffce659979d50289c491a2f]: Sch. 3 para. 9 in force at 5.4.2024, see art. 1
[^key-87c2981e0d578801ad6ef7c3bea618d6]: Sch. 15 para. 49 in force at 5.4.2024, see art. 1
[^key-87d38a4733a849e2d5b374117f771f95]: Art. 47 in force at 5.4.2024, see art. 1
[^key-889ef0ae056d5af8a66d92dd7635d644]: Words in Sch. 3 para. 19(2) substituted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-88e2873dc8a32d15eb562554ae4b7518]: Sch. 15 para. 93 in force at 5.4.2024, see art. 1
[^key-88f5b0456bec8de541b8ab40b50206e4]: Sch. 3 para. 19(3) substituted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-89cc722646cae8c08a175f6598302439]: Sch. 4 para. 1 in force at 5.4.2024, see art. 1
[^key-8b0d117d3c82751afff73c497854354c]: Art. 35 in force at 5.4.2024, see art. 1
[^key-8b233dd622526c3ae88c82093ef87f08]: Sch. 5 para. 2 in force at 5.4.2024, see art. 1
[^key-8dd9c1f859feb687dd537524e2fa640f]: Art. 48 in force at 5.4.2024, see art. 1
[^key-8e983d4ff03fef63f5361f834cf218b1]: Art. 38 in force at 5.4.2024, see art. 1
[^key-8fe9baaed253f91c8f1071e62ebb9aee]: Sch. 15 para. 9 in force at 5.4.2024, see art. 1
[^key-9016abff8c890a6b8724d84929cfad57]: Sch. 15 para. 37 in force at 5.4.2024, see art. 1
[^key-90c157511c0adceb8f9f1eeb6b8406ce]: Art. 39 in force at 5.4.2024, see art. 1
[^key-930d88f95bf66f9a81557b6756e9d726]: Words in Sch. 3 para. 2(2) substituted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-932c22a790739fcf34e0b72e0de43a98]: Art. 4 in force at 5.4.2024, see art. 1
[^key-93930f93b5f59a3e7b025f2dc181daaf]: Art. 41 in force at 5.4.2024, see art. 1
[^key-94275691f329270168e846926c39a32d]: Art. 7 in force at 5.4.2024, see art. 1
[^key-950fcc4c87cd7458978773182bb462c2]: Sch. 13 Pt. 3 in force at 5.4.2024, see art. 1
[^key-956c44338e1ba18f33d41bb6aafdd98b]: Sch. 15 para. 28 in force at 5.4.2024, see art. 1
[^key-985581010fd8802631d8a34682d57754]: Sch. 10 para. 7 in force at 5.4.2024, see art. 1
[^key-9977702be4638254071bc322d5dd1e2c]: Sch. 13 Pt. 2 in force at 5.4.2024, see art. 1
[^key-9a18d489b482a3f90c793125391a7abb]: Sch. 15 para. 17 in force at 5.4.2024, see art. 1
[^key-9dd3349ab7c7623c4bbdf54001a9aa1b]: Sch. 15 para. 102 in force at 5.4.2024, see art. 1
[^key-9efe86c194601e464d0e16f95ab68d6e]: Art. 18 in force at 5.4.2024, see art. 1
[^key-a0f94c34865129b466343825c1aec9ab]: Sch. 15 para. 16 in force at 5.4.2024, see art. 1
[^key-a1ee350f40767b40f42c0a6c44810658]: Sch. 10 para. 6 in force at 5.4.2024, see art. 1
[^key-a26dac3591a2dd8d7854ea330c072f17]: Sch. 15 para. 23 in force at 5.4.2024, see art. 1
[^key-a387b64e4ed6c4097771d02753baebdf]: Art. 8 in force at 5.4.2024, see art. 1
[^key-a58e747dff3894226b138e96f2155de9]: Sch. 17 in force at 5.4.2024, see art. 1
[^key-a596433742bf9f612a2a427089ba1f8d]: Art. 3 in force at 5.4.2024, see art. 1
[^key-a7553a66f89dcdf5f0dbd7f0039fe9b8]: Sch. 15 para. 24 in force at 5.4.2024, see art. 1
[^key-ac23f78f573cf227ef702e9b4eb12809]: Sch. 3 para. 1 in force at 5.4.2024, see art. 1
[^key-acccdbaad7fdba7ffb1f029d6b900f62]: Sch. 15 para. 52 in force at 5.4.2024, see art. 1
[^key-ad40b6d8b5438577facf40986b453c10]: Sch. 15 para. 7 in force at 5.4.2024, see art. 1
[^key-aea91a7b0affe5d7f595e2668924c75d]: Sch. 15 para. 27 in force at 5.4.2024, see art. 1
[^key-afec39a57aa2d3d258b386bad6562fde]: Sch. 16 Pt. 2 in force at 5.4.2024, see art. 1
[^key-b04df66e0f28aac24e7317df4208389d]: Sch. 15 para. 74 in force at 5.4.2024, see art. 1
[^key-b12dc1587633f60713b01646bf41c116]: Sch. 15 para. 6 in force at 5.4.2024, see art. 1
[^key-b1870e95c81025762f0aabe40662fd46]: Sch. 15 para. 84 in force at 5.4.2024, see art. 1
[^key-b2221d9c362a26e046a839b2885f4aff]: Art. 15 in force at 5.4.2024, see art. 1
[^key-b3dda70791e125771492758c16a25d9f]: Art. 19(10) substituted (12.6.2024) by virtue of The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
[^key-b40837a794a540f6e912e2472114cb63]: Art. 1 in force at 5.4.2024, see art. 1
[^key-b547229cc1e5bf7d99303065bbc67bb1]: Sch. 5 para. 6 in force at 5.4.2024, see art. 1
[^key-b6a3d2a3e7686afd0e597f4c6f429e71]: Sch. 12 Pt. 3 in force at 5.4.2024, see art. 1
[^key-b714d29b88db0f8b7e0add99898f21fe]: Sch. 15 para. 72 in force at 5.4.2024, see art. 1
[^key-b8ba9687a9e58f80d09ab9eaf0da2f30]: Sch. 15 para. 67 in force at 5.4.2024, see art. 1
[^key-ba03072ede83fc7d608b3e395e3ab8d4]: Art. 32 in force at 5.4.2024, see art. 1
[^key-ba1d6c3ed53c3290d2a993e0cf70e38f]: Sch. 15 para. 85 in force at 5.4.2024, see art. 1
[^key-bcd9b6e5203d9262a8bfb38e6c61d213]: Sch. 4 para. 3 in force at 5.4.2024, see art. 1
[^key-bcf710dd8dfe42ddbbd3e93617f6e8a5]: Art. 19 in force at 5.4.2024, see art. 1
[^key-bd5dd985badd8291239c5e176b62f657]: Sch. 15 para. 42 in force at 5.4.2024, see art. 1
[^key-be2900e4ef4fcb2e0b3cce308e60ad65]: Sch. 15 para. 110 in force at 5.4.2024, see art. 1
[^key-c18969d37b392660ddbfbb774d885c76]: Sch. 3 para. 8 in force at 5.4.2024, see art. 1
[^key-c25c614d95d2fa6eb5683fd17efe8cab]: Sch. 15 para. 30 in force at 5.4.2024, see art. 1
[^key-c4a175dfb01f867072fcbf03e4a00a41]: Sch. 15 para. 108 in force at 5.4.2024, see art. 1
[^key-c4dfbab1c00eb7949f303caffbc5712c]: Sch. 15 para. 15 in force at 5.4.2024, see art. 1
[^key-c554286ecb607f4340c542b1ceb0da88]: Sch. 15 para. 71 in force at 5.4.2024, see art. 1
[^key-c5a358b829ab74523d2c6595e9fa90ad]: Sch. 3 para. 14 in force at 5.4.2024, see art. 1
[^key-c5c9de935a7de38d9c824d308c317d17]: Sch. 9 Pt. 3 in force at 5.4.2024, see art. 1
[^key-c618c7355ed05ab81e4ec867d74d4f52]: Sch. 5 para. 1 in force at 5.4.2024, see art. 1
[^key-c703e2063a67dca0e21d27aef807bf6f]: Sch. 15 para. 19 in force at 5.4.2024, see art. 1
[^key-c7211d5482923e0426fd7bfa543bb9c7]: Art. 29 in force at 5.4.2024, see art. 1
[^key-c8e1c7bd07828a575874ea531182ad4f]: Art. 40 in force at 5.4.2024, see art. 1
[^key-cac84fbdf4a239f2ecde9a6d7409e368]: Sch. 15 para. 106 in force at 5.4.2024, see art. 1
[^key-cb584f16ce98abe2b2fe69004d332a9c]: Sch. 15 para. 26 in force at 5.4.2024, see art. 1
[^key-cb5c40b1311cc476c227d679ce76363b]: Sch. 10 para. 9 in force at 5.4.2024, see art. 1
[^key-cb5cdd4077386e278416d668e721e3cd]: Art. 25 in force at 5.4.2024, see art. 1
[^key-cb96c7edfa9d276e8d3843b7d194adfe]: Art. 44 in force at 5.4.2024, see art. 1
[^key-cd01e5b363262052e7b4a7dd3c5ce2d7]: Sch. 15 para. 65 in force at 5.4.2024, see art. 1
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.