The Hornsea Three Offshore Wind Farm (Amendment) Order 2024

Type Statutory-Instrument
Publication 2024-05-09
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API

Made: 9th May 2024

Coming into force: 10th May 2024

Accordingly, the Secretary of State, in exercise of the powers conferred by paragraphs 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order—

Citation and commencement

1

This Order may be cited as the Hornsea Three Offshore Wind Farm (Amendment) Order 2024 and comes into force on 10th May 2024.

Amendment to the Hornsea Three Offshore Wind Farm Order 2020

2

The Hornsea Three Offshore Wind Farm Order 2020 (“the 2020 Order”) is amended in accordance with this Order.

Amendments to Schedule 14 of the 2020 Order

3

In Part 1 of Schedule 14 to the 2020 Order—

(c) an implementation timetable for delivery of four artificial nest structures that ensures all necessary compensation measures are in place to allow three full kittiwake breeding seasons in respect of three artificial nest structures prior to the operation of any turbine forming part of the authorised development, and for the fourth artificial nest structure to be delivered prior to final commissioning of the authorised development.

; and

(4) The undertaker must implement the measures as set out in the KIMP approved by the Secretary of State and no operation of any turbine forming part of the authorised development may be commenced until three full breeding seasons have elapsed from the implementation of three of the artificial nest structures and no final commissioning of the authorised development must take place until the fourth artificial nest structure has been implemented For the purposes of this paragraph each breeding season is assumed to have commenced on 1 March in each year and ended on 30 September.

Signed

Signed by authority of the Secretary of State for Energy Security and Net Zero

John Wheadon — Head of Energy Infrastructure Planning Delivery — Department for Energy Security and Net Zero — 9th May 2024

Explanatory note

(This note is not part of the Order)

EXPLANATORY NOTE

This Order amends the Hornsea Three Offshore Wind Farm Order 2020, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material amendment under paragraph 2 of Schedule 6 to the Planning Act 2008. This Order amends paragraphs 3(c) and 4 of Part 1 of the 2020 Order relating to the kittiwake compensation measures.

Footnotes

[^f00001]: 2008 c. 29. Paragraph 2 was amended by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23), by paragraphs 1 and 72 of Schedule 13 and Schedule 25(2) of the Localism Act 2011 (c. 20), and by section 28 of the Infrastructure Act 2015 (c. 7).

[^f00002]: S.I. 2011/2055. Relevant amendments to this instrument were made by S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/755, S.I. 2015/760, S.I. 2017/314, S.I. 2017/524, S.I. 2018/378, S.I. 2019/734 and S.I. 2020/1534.

[^f00003]: S.I. 2020/1656 as amended by S.I. 2021/599 and S.I. 2023/459.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.