The Gate Burton Energy Park Order 2024

Type Statutory-Instrument
Publication 2024-07-12
Last updated 2024-11-28
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • (e) construct any works on that land as are mentioned in Schedule 1 (authorised development); and
  • (f) carry out mitigation works required under the requirements in Schedule 2 (requirements).
  • (2) Paragraph ‎(1) does not authorise the undertaker to take temporary possession of—
  • (a) any house or garden belonging to a house; or
  • (b) any building (other than a house) if it is for the time being occupied.
  • (3) Not less than 28 days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.
  • (4) The undertaker must not remain in possession of any land under this article for longer than reasonably necessary, and in any event must not, without the agreement of the owners of the land, remain in possession of any land under this article—
  • (a) in the case of the land referred to in paragraph ‎(1)(a)(i) after the end of the period of one year beginning with the date of final commissioning of the part of the authorised development for which temporary possession of the land was taken; or
  • (b) in the case of land referred to in paragraph ‎(1)(a)(ii) after the end of the period of one year beginning with the date of final commissioning of the part of the authorised development for which temporary possession of the land was taken unless the undertaker has, before the end of that period, served a notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act in relation to that land.
  • (5) Unless the undertaker has served notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act or otherwise acquired the land or rights over land subject to temporary possession, the undertaker must before giving up possession of land of which temporary possession has been taken under this article, remove all works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker is not required to—
  • (a) replace any building, structure, debris, drain or electric line removed under this article;
  • (b) remove any drainage works installed by the undertaker under this article;
  • (c) remove any new road surface or other improvements carried out under this article to any street specified in Schedule 4 (streets subject to street works), Schedule 5 (alteration of streets) or Schedule 7 (permanent means of access to works);
  • (d) remove any fencing or boundary treatments installed by the undertaker under this article to replace or enhance existing fencing or boundary treatments; or
  • (e) restore the land on which any works have been carried out under paragraph ‎(1)(f) insofar as the works relate to mitigation works identified in the environmental statement or required pursuant to the requirements in Schedule 2 (requirements).
  • (6) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of any power conferred by this article.
  • (7) Any dispute as to a person’s entitlement to compensation under paragraph ‎(6), or as to the amount of compensation, must be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
  • (8) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the carrying out of the authorised development, other than loss or damage for which compensation is payable under paragraph ‎(6).
  • (9) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.
  • (10) The undertaker must not compulsorily acquire, acquire new rights over or impose restrictive covenants over, the land referred to in paragraph ‎(1)(a)(i) under this Order.
  • (11) Nothing in this article precludes the undertaker from—
  • (a) creating and acquiring new rights or imposing restrictions over any part of the Order land identified in Schedule 9 (land in which only new rights etc. may be acquired); or
  • (b) acquiring any part of the subsoil of (or rights in the subsoil of) that land under article 23 (acquisition of subsoil only) or any part of the subsoil of or airspace over that land under article 26 (rights under or over streets).
  • (12) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.
  • (13) Nothing in this article prevents the taking of temporary possession more than once in relation to any land that the undertaker takes temporary possession of under this article.

Temporary use of land for maintaining the authorised development

28

  • (1) Subject to paragraph ‎(2), at any time during the maintenance period relating to any part of the authorised development, the undertaker may—
  • (a) enter on and take temporary possession of any land within the Order land if such possession is reasonably required for the purpose of maintaining the authorised development;
  • (b) enter on any land within the Order land for the purpose of gaining such access as is reasonably required for the purpose of maintaining the authorised development; and
  • (c) construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.
  • (2) Paragraph ‎(1) does not authorise the undertaker to take temporary possession of—
  • (a) any house or garden belonging to a house; or
  • (b) any building (other than a house) if it is for the time being occupied.
  • (3) Not less than 28 days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.
  • (4) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised development for which possession of the land was taken.
  • (5) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.
  • (6) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.
  • (7) Any dispute as to a person’s entitlement to compensation under paragraph ‎(6), or as to the amount of compensation, must be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
  • (8) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the maintenance of the authorised development, other than loss or damage for which compensation is payable under paragraph ‎(6).
  • (9) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.
  • (10) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.
  • (11) In this article “the maintenance period” means the period of five years beginning with the date of final commissioning of the part of the authorised development for which temporary possession is required under this article except in relation to landscaping where “the maintenance period” means such period as set out in the landscape and ecological management plan which is approved by the relevant planning authority pursuant to requirement 7 beginning with the date on which that part of the landscaping is completed.

Statutory undertakers

29

Subject to the provisions of Schedule 14 (protective provisions) the undertaker may—

  • (a) acquire compulsorily, or acquire new rights or impose restrictive covenants over, the land belonging to statutory undertakers shown on the land plans within the Order land; and
  • (b) extinguish the rights of, remove, relocate the rights of or reposition the apparatus belonging to statutory undertakers over or within the Order land.

Apparatus and rights of statutory undertakers in temporarily closed streets

30

Where a street is altered or diverted or its use is temporarily prohibited or restricted under article ‎8 (street works), article ‎9 (power to alter layout, etc., of streets), article ‎10 (construction and maintenance of altered streets) or article ‎11 (temporary closure of streets and public rights of way) any statutory undertaker whose apparatus is under, in, on, along or across the street has the same powers and rights in respect of that apparatus, subject to Schedule 14 (protective provisions), as if this Order had not been made.

Recovery of costs of new connections

31

  • (1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article ‎29 (statutory undertakers) any person who is the owner or occupier of premises to which a supply was given from that apparatus is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.
  • (2) Sub-paragraph (1) does not apply in the case of the removal of a public sewer but where such a sewer is removed under article ‎29 (statutory undertakers), any person who is—
  • (a) the owner or occupier of premises the drains of which communicated with that sewer; or
  • (b) the owner of a private sewer which communicated with that sewer,

is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.

  • (3) This article does not have effect in relation to apparatus to which Part 3 (street works in England and Wales) of the 1991 Act applies.
  • (4) In this article—
  • “public communications provider” has the same meaning as in section 151(1) (interpretation of Chapter 1) of the Communications Act 200347; and
  • “public utility undertaker” has the same meaning as in the 1980 Act.

PART 6 — MISCELLANEOUS AND GENERAL

Benefit of the Order

32

  • (1) Subject to article ‎33 (consent to transfer the benefit of the Order), the provisions of this Order have effect solely for the benefit of the undertaker.
  • (2) Sub-paragraph ‎(1) does not apply to Work No. 4C in respect of which the provisions of this Order are for the benefit of the undertaker and National Grid.

33

  • (1) Subject to the powers of this Order, the undertaker may—
  • (a) transfer to another person (“the transferee”) any or all of the benefit of the provisions of this Order and such related statutory rights as may be agreed between the undertaker and the transferee; and
  • (b) grant to another person (“the lessee”) for a period agreed between the undertaker and the lessee any or all of the benefit of the provisions of this Order and such related statutory rights as may be so agreed.
  • (2) Where a transfer or grant has been made references in this Order to the undertaker, except in paragraph ‎(8), are to include references to the transferee or lessee.
  • (3) The consent of the Secretary of State is required for the exercise of the powers of paragraph (1) except where—
  • (a) the transferee or lessee is the holder of a licence under section 6 (licences authorising supply etc.) of the 1989 Act; ...
  • (b) the transfer or grant relates to Work No. 4B and the transferee or lessee (as relevant) is the undertaker for the purposes of the proposed Cottam, West Burton or Tillbridge Development Consent Order; or
  • (c) the time limits for claims for compensation in respect of the acquisition of land or effects upon land under this Order have elapsed and—
  • (i) no such claims have been made;
  • (ii) any such claim has been made and has been compromised or withdrawn;
  • (iii) compensation has been paid in full and final settlement of any such claim;
  • (iv) payment of compensation into court has taken place in lieu of settlement of any such claim; or
  • (v) it has been determined by a tribunal or court of competent jurisdiction in respect of any such claim that no compensation is payable.
  • (4) Where the consent of the Secretary of State is not required, the undertaker must notify the Secretary of State in writing before transferring or granting a benefit referred to in paragraph ‎(1).
  • (5) The notification referred to in paragraph ‎(4) must state—
  • (a) the name and contact details of the person to whom the benefit of the powers will be transferred or granted;
  • (b) subject to paragraph ‎(6), the date on which the transfer will take effect;
  • (c) the powers to be transferred or granted;
  • (d) pursuant to paragraph ‎(8), the restrictions, liabilities and obligations that will apply to the person exercising the powers transferred or granted;
  • (e) where relevant, a plan showing the works or areas to which the transfer or grant relates; and
  • (f) a copy of the document effecting the transfer or grant .
  • (6) The date specified under paragraph ‎(5)(b) must not be earlier than the expiry of ten working days from the date of the receipt of the notification.
  • (7) The notification given must be signed by the undertaker and the person to whom the benefit of the powers will be transferred or granted as specified in that notification.
  • (8) Where the undertaker has transferred any benefit, or for the duration of any period during which the undertaker has granted any benefit—
  • (a) the benefit transferred or granted (“the transferred benefit”) must include any rights that are conferred, and any obligations that are imposed, by virtue of the provisions to which the benefit relates;
  • (b) the transferred benefit will reside exclusively with the transferee or, as the case may be, the lessee and the transferred benefit will not be enforceable against the undertaker; and
  • (c) the exercise by a person of any benefits or rights conferred in accordance with any transfer or grant is subject to the same restrictions, liabilities and obligations as would apply under this Order if those benefits or rights were exercised by the undertaker.

Application of landlord and tenant law

34

  • (1) This article applies to—
  • (a) any agreement for leasing to any person the whole or any part of the authorised development or the right to operate the same; and
  • (b) any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised development, or any part of it,

so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person’s use.

  • (2) No enactment or rule of law regulating the rights and obligations of landlords and tenants prejudices the operation of any agreement to which this article applies.
  • (3) Accordingly, no such enactment or rule of law applies in relation to the rights and obligations of the parties to any lease granted by or under any such agreement, so as to—
  • (a) exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;
  • (b) confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or
  • (c) restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.

Operational land for the purposes of the 1990 Act

35

Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3) (cases in which land is to be treated as operational land) of the 1990 Act.

Felling or lopping of trees and removal of hedgerows

36

  • (1) The undertaker may fell or lop any tree or shrub within or overhanging land within the Order limits or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub from—
  • (a) obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development;
  • (b) constituting a danger to persons using the authorised development; or
  • (c) obstructing or interfering with the passage of construction vehicles to the extent necessary for the purposes of construction of the authorised development.
  • (2) In carrying out any activity authorised by paragraph ‎(1) the undertaker must do no unnecessary damage to any tree or shrub and must pay compensation to any person for any loss or damage arising from such activity.
  • (3) Any dispute as to a person’s entitlement to compensation under paragraph ‎(2), or as to the amount of compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
  • (4) The undertaker may, for the purposes of the authorised development and subject to paragraph ‎(2), remove any hedgerows within the Order limits that may be required for the purposes of constructing the authorised development.
  • (5) Without prejudice to the generality of paragraph ‎(4), the undertaker may, for the purposes of the authorised development or in connection with the authorised development and subject to paragraph ‎(2), remove the hedgerows specified in column 2 of the table in Schedule 16 (hedgerows to be removed) as shown on the vegetation removal plan.
  • (6) The undertaker may not pursuant to paragraphs ‎(1) and ‎(4) fell or lop a tree or remove hedgerows within the extent of the publicly maintainable highway without the prior consent of the highway authority.
  • (7) In this article “hedgerow” has the same meaning as in the Hedgerows Regulations 199748.

Trees subject to tree preservation orders

37

  • (1) The undertaker may fell or lop any tree described in Schedule 17 (trees subject to tree preservation orders) or cut back its roots or undertake such other works described in column (2) of that Schedule relating to the relevant part of the authorised development described in column (3) of that Schedule, if it reasonably believes it to be necessary to do so in order to prevent the tree from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development.
  • (2) In carrying out any activity authorised by paragraph ‎(1)—
  • (a) the undertaker must do no unnecessary damage to any tree and must pay compensation to any person for any loss or damage arising from such activity; and
  • (b) the duty contained in section 206(1) (replacement of trees) of the 1990 Act does not apply.
  • (3) The authority given by paragraph ‎(1) constitutes a deemed consent under the relevant tree preservation order.
  • (4) Any dispute as to a person’s entitlement to compensation under paragraph ‎(2), or as to the amount of compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

Certification of plans and documents, etc.

38

  • (1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of all documents and plans listed in the table at Schedule 12 (documents and plans to be certified) for certification that they are true copies of the documents referred to in this Order.
  • (2) A plan or document so certified is admissible in any proceedings as evidence of the contents of the document of which it is a copy.

No double recovery

39

Compensation is not payable in respect of the same matter both under this Order and under any enactment, any contract or any rule of law.

Arbitration

40

  • (1) Any difference under any provision of this Order, unless otherwise provided for, is to be referred to and settled in arbitration in accordance with the rules set out in Schedule 13 (arbitration rules) of this Order, by a single arbitrator to be agreed upon by the parties, within 14 days of receipt of the notice of arbitration, or if the parties fail to agree within the time period stipulated, to be appointed on application of either party (after giving written notice to the other) by the Secretary of State.
  • (2) Any matter for which the consent or approval of the Secretary of State is required under any provision of this Order is not subject to arbitration.

Protective provisions

41

Schedule 14 (protective provisions) has effect.

Service of notices

42

  • (1) A notice or other document required or authorised to be served for the purposes of this Order may be served—
  • (a) by post;
  • (b) by delivering it to the person on whom it is to be served or to whom it is to be given or supplied; or
  • (c) with the consent of the recipient and subject to paragraphs ‎(6) to ‎(8), by electronic transmission.
  • (2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.
  • (3) For the purposes of section 7 (references to service by post) of the Interpretation Act 197849 as it applies for the purposes of this article, the proper address of any person in relation to the service on that person of a notice or document under paragraph ‎(1) is, if that person has given an address for service, that address and otherwise—
  • (a) in the case of the secretary or clerk of a body corporate, the registered or principal office of that body; and
  • (b) in any other case, the last known address of that person at that time of service.
  • (4) Where for the purpose of this Order a notice or other document is required or authorised to be served on a person as having an interest in, or as the occupier of, land and the name or address of that person cannot be ascertained after reasonable enquiry, the notice may be served by—
  • (a) addressing it to that person by the description of “owner”, or as the case may be “occupier” of the land (describing it); and
  • (b) either leaving it in the hands of the person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.
  • (5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement is to be taken to be fulfilled only where—
  • (a) the recipient of the notice or other document to be transmitted has given consent to the use of electronic transmission in writing or by electronic transmission;
  • (b) the notice or document is capable of being accessed by the recipient;
  • (c) the notice or document is legible in all material respects; and
  • (d) the notice or document is in a form sufficiently permanent to be used for subsequent reference.
  • (6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within seven days of receipt that the recipient requires a paper copy of all or any part of that notice or other document the sender must provide such a copy as soon as reasonably practicable.
  • (7) Any consent to the use of an electronic transmission by a person may be revoked by that person in accordance with paragraph ‎(8).
  • (8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—
  • (a) that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and
  • (b) such revocation is final and takes effect on a date specified by the person in the notice but that date must not be less than seven days after the date on which the notice is given.
  • (9) This article does not exclude the employment of any method of service not expressly provided for by it.

Procedure in relation to certain approvals etc.

43

  • (1) Where an application is made to or request is made of, a consenting authority for any consent, agreement or approval required or contemplated by any of the provisions of the Order (not including the requirements), such consent, agreement or approval to be validly given, must be given in writing.
  • (2) Where paragraph ‎(1) applies to any consent, agreement or approval, such consent, agreement or approval must not be unreasonably withheld or delayed.
  • (3) Schedule 15 (procedure for discharge of requirements) has effect in relation to all consents, agreements or approvals required, granted, refused or withheld in relation to the requirements.
  • (4) Save for applications made pursuant to Schedule 15 (procedure for discharge of requirements) and where stated to the contrary if, within ten weeks (or such longer period as may be agreed between the undertaker and the relevant consenting authority in writing) after the application or request has been submitted to a consenting authority it has not notified the undertaker of its disapproval and the grounds of disapproval, it is deemed to have approved the application or request.
  • (5) Where any application is made as described in paragraph ‎(1), the undertaker must include a statement in such application that refers to the timeframe for consideration of the application and the consequences of failure to meet that timeframe as prescribed by paragraph ‎(4).
  • (6) Schedule 15 (procedure for discharge of requirements) does not apply in respect of any consents, agreements or approvals contemplated by the provisions of Schedule 14 (protective provisions) or any dispute under article ‎16(6) (protective work to buildings) to which paragraph ‎(4) applies.
  • (7) In this article “consenting authority” means the relevant planning authority, highway authority, traffic authority, street authority, the owner of a watercourse, sewer or drain or the beneficiary of any of the protective provisions contained in Schedule 14 (protective provisions).

Guarantees in respect of payment of compensation

44

  • (1) The undertaker must not exercise the powers conferred by the provisions referred to in paragraph ‎(2) in relation to any part of the Order land unless it has first put in place either—
  • (a) a guarantee, the form and amount of which has been approved by the Secretary of State in respect of the liabilities of the undertaker to pay compensation pursuant to the provisions referred to in paragraph ‎(2) in respect of the exercise of the relevant provision in relation to that part of the Order land; or
  • (b) an alternative form of security, the form and amount of which has been approved by the Secretary of State in respect of the liabilities of the undertaker to pay compensation pursuant to the provisions referred to in paragraph ‎(2) in respect of the exercise of the relevant provision in relation to that part of the Order land.
  • (2) The provisions are—
  • (a) article ‎18 (compulsory acquisition of land);
  • (b) article ‎20 (compulsory acquisition of rights);
  • (c) article ‎21 (private rights);
  • (d) article ‎26 (rights under or over streets);
  • (e) article ‎27 (temporary use of land for constructing the authorised development);
  • (f) article ‎28 (temporary use of land for maintaining the authorised development); and
  • (g) article ‎29 (statutory undertakers).
  • (3) A guarantee or alternative form of security given in respect of any liability of the undertaker to pay compensation under this Order is to be treated as enforceable against the guarantor or person providing the alternative form of security by any person to whom such compensation is payable and must be in such a form as to be capable of enforcement by such a person.
  • (4) Nothing in this article requires a guarantee or alternative form of security to be in place for more than 15 years after the date on which the relevant power is exercised.

Crown rights

45

  • (1) Nothing in this Order affects prejudicially any estate, right, power, privilege, authority or exemption of the Crown and in particular, nothing in this Order authorises the undertaker or any lessee or licensee to take, use, enter upon or in any manner interfere with any land or rights of any description (including any portion of the shore or bed of the sea or any river, channel, creek, bay or estuary)—
  • (a) belonging to His Majesty in right of the Crown and forming part of The Crown Estate without the consent in writing of the Crown Estate Commissioners;
  • (b) belonging to His Majesty in right of the Crown and not forming part of The Crown Estate without the consent in writing of the government department having the management of that land; or
  • (c) belonging to a government department or held in trust for His Majesty for the purposes of a government department without the consent in writing of that government department.
  • (2) Paragraph ‎(1) does not apply to the exercise of any right under this Order for the compulsory acquisition of an interest in land (as defined in the 2008 Act) which is for the time being held otherwise than by or on behalf of the Crown.
  • (3) A consent under paragraph (1) may be given unconditionally or subject to terms and conditions and is deemed to have been given in writing where it is sent electronically.

SCHEDULE 1 — AUTHORISED DEVELOPMENT

1

In this Schedule—

  • “balance of solar system (BoSS) plant” means inverters, transformers and switch gear and would be either— solar stations being a station comprising centralised inverters, transformers and switch gear with each component for each solar station either— a “solar station” located outside, with a concrete foundation slab or placed on metal skids for each of the inverters and transformers and switch gear; or housed together within a container sitting on a concrete foundation slab or placed on metal skids; or string inverters attached either to mounting structures or a ground mounted frame, switchgear and transformers on a concrete foundation slab or placed on metal skids;
  • “electrical cables” means— cables of differing types and voltages installed for the purposes of conducting electricity, auxiliary cables, cables connecting to direct current (DC) boxes, earthing cables and optical fibre cables; and works associated with cable laying including jointing pits, hardstanding adjoining the jointing pits, combiner boxes, fibre bays, cable ducts, cable protection, joint protection, manholes, kiosks, marker posts, underground cable marker, tiles and tape, send and receive pits for horizontal directional drilling, trenching, lighting, and a pit or container to capture fluids associated with drilling;
  • “energy storage” means equipment used for the storage of electrical energy;
  • “inverter” means electrical equipment required to convert direct current power to alternating current;
  • “mounting structure” means a frame or rack made of galvanised steel, anodised aluminium or other material designed to support the solar panels and mounted on piles driven into the ground, piles rammed into a pre-drilled hole, a pillar attaching to a steel ground screw, or pillars fixed to a concrete foundation;
  • “solar panel” means a solar photovoltaic panel or module designed to convert solar irradiance to electrical energy;
  • “substation” means a substation containing electrical equipment required to switch, transform, convert electricity and provide reactive power compensation;
  • “switch gear” means a combination of electrical disconnect switches, fuses or circuit breakers used to control, protect and isolate electrical equipment; and
  • “transformer” means a structure serving to transform electricity to a higher voltage.

2

In the Districts of West Lindsey and Bassetlaw and in the Counties of Lincolnshire and Nottinghamshire a nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act and associated development under section 115(1)(b) of the 2008 Act.

SCHEDULE 2 — REQUIREMENTS

Interpretation

1

In this Schedule—

  • “relevant planning authority” means— Lincolnshire County Council for the purposes of: requirement 6; requirement 10; requirement 14; requirement 16; requirement 17; and West Lindsey District Council and Bassetlaw District Council for the purposes of: requirement 3; requirement 4; requirement 5; requirement 7; requirement 8; requirement 9; requirement 12; requirement 13; requirement 15; requirement 18; requirement 19; and
  • “relevant planning authorities” means Lincolnshire County Council, West Lindsey District Council and Bassetlaw District Council, as applicable.

Commencement of the authorised development

2

The authorised development must not be commenced after the expiration of five years from the date this Order comes into force.

Approved details and amendments to them

3

  • (1) With respect to the documents certified under Article ‎38 (certification of plans and documents, etc) and any plans, details or schemes which have been approved pursuant to any requirement (together the “Approved Documents, Plans, Details or Schemes”), the undertaker may submit to the relevant planning authority or relevant planning authorities (as applicable) for approval any amendments to any of the Approved Documents, Plans, Details or Schemes and, following approval by the relevant planning authority or relevant planning authorities (as applicable), the relevant Approved Documents, Plans, Details or Schemes is to be taken to include the amendments as so approved pursuant to this paragraph.
  • (2) Approval under sub-paragraph (1) for the amendments to any of the Approved Documents, Plans, Details or Schemes must not be given except where it has been demonstrated to the satisfaction of the relevant planning authority or the relevant planning authorities (as applicable) that the subject matter of the approval sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.

Community liaison group

4

  • (1) Prior to the commencement of the authorised development the undertaker must submit to the relevant planning authorities for approval the terms of reference for a community liaison group whose aim is to facilitate liaison between representatives of people living in the vicinity of the Order limits and other relevant organisations in relation to the construction of the authorised development.
  • (2) The community liaison group must be established prior to commencement of the authorised development and must be administered by the undertaker, and operated, in accordance with the approved terms of reference.
  • (3) The community liaison group is to continue to meet until the date of final commissioning of the final part of the authorised development unless otherwise agreed with the relevant planning authorities.

Detailed design approval

5

  • (1) No part of the authorised development may commence until details of—
  • (a) the layout;
  • (b) scale;
  • (c) proposed finished ground levels;
  • (d) external appearance;
  • (e) hard surfacing materials;
  • (f) vehicular and pedestrian access, parking and circulation areas;
  • (g) refuse or other storage units, signs and lighting;
  • (h) drainage, water, power and communications cables and pipelines;
  • (i) landscaping works, planting works and programme for implementation;
  • (j) fencing;
  • (k) security measures; and
  • (l) any mitigation measures necessary to address noise impacts.

relating to that part have been submitted to and approved in writing by the relevant planning authority for that part or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.

  • (2) The details submitted must accord with—
  • (a) the location, order limits and grid coordinates plan;
  • (b) the works plan; and
  • (c) the outline design principles, or such variation thereof as may be approved by the relevant planning authority pursuant to requirement 3.
  • (3) The authorised development must be carried out in accordance with the approved details.

Battery safety management

6

  • (1) Work No. 2 must not commence until a battery safety management plan has been submitted to and approved by the relevant planning authority.
  • (2) The battery safety management plan must prescribe measures to facilitate safety during the construction, operation and decommissioning of Work No. 2 including the transportation of new, used and replacement battery cells both to and from the authorised development.
  • (3) The battery safety management plan must be substantially in accordance with the outline battery safety management plan.
  • (4) The relevant planning authority must consult with West Lindsey District Council, Lincolnshire Fire and Rescue, Nottinghamshire Fire and Rescue Service and the Environment Agency before determining an application for approval of the battery safety management plan.
  • (5) The battery safety management plan must be implemented as approved and maintained throughout the construction, operation and decommissioning of the authorised development.

Landscape and ecological management plan

7

  • (1) No part of the authorised development may commence until a written landscape and ecological management plan has been submitted to and approved by the relevant planning authority for that part or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities, in consultation with the Environment Agency and Natural England.
  • (2) The landscape and ecological management plan must be substantially in accordance with the outline landscape and ecological management plan.
  • (3) The landscape and ecological management plan must be implemented as approved and maintained throughout the operation of the relevant part of the authorised development to which the plan relates.
  • (4) For the purposes of sub-paragraph ‎(1), “commence” includes part (h) (site clearance (including vegetation removal, demolition of existing buildings and structures)) and part (i) (advanced planting to allow for an early establishment of protective screening) of permitted preliminary works.

Biodiversity net gain

8

  • (1) No part of the authorised development may commence until a biodiversity net gain strategy has been submitted to and approved by the relevant planning authority, in consultation with the relevant statutory nature conservation body.
  • (2) The biodiversity net gain strategy must be substantially in accordance with the outline landscape and ecological management plan and must be implemented as approved and maintained throughout the operation of the relevant part of the authorised development to which the plan relates.

Fencing and other means of enclosure

9

  • (1) No part of the authorised development may commence until written details of all proposed temporary fences, walls or other means of enclosure, including those set out in the construction environmental management plan, for that part have been submitted to and approved by the relevant planning authority or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.
  • (2) No part of the authorised development may commence until written details of all permanent fences, walls or other means of enclosure for that part (which must be substantially in accordance with the relevant outline design principles) have been submitted to and approved by the relevant planning authority or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.
  • (3) For the purposes of sub-paragraph ‎(1), “commence” includes any permitted preliminary works.
  • (4) Any construction site must remain securely fenced in accordance with the approved details under sub-paragraph ‎(1) at all times during construction of the authorised development.
  • (5) Any temporary fencing must be removed on completion of the part of construction of the authorised development for which it was used.
  • (6) Any approved permanent fencing in a part must be completed before the date of final commissioning in respect of such part.

Surface and foul water drainage

10

  • (1) No part of the authorised development may commence until written details of the surface water drainage scheme and (if any) foul water drainage system (which must be substantially in accordance with the outline drainage strategy) have been submitted to and approved by the relevant planning authority for that part or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities, and in each case in consultation with Anglian Water Services Limited or its successor in function as the relevant water undertaker.
  • (2) Any approved scheme must be implemented as approved and maintained throughout the construction and operation of the authorised development.

Archaeology

11

  • (1) The authorised development must be implemented in accordance with the archaeological mitigation strategy.
  • (2) No part of the authorised development may commence until a written scheme of archaeological investigation (which must accord with the archaeological mitigation strategy) for that part has been submitted to and approved by the relevant planning authority.
  • (3) For the purposes of sub-paragraph (1), “commence” includes any permitted preliminary works.
  • (4) Any archaeological works or watching brief must be carried out in accordance with the approved scheme.

Construction environmental management plan

12

  • (1) No part of the authorised development may commence until a construction environmental management plan (which must be substantially in accordance with the framework construction environmental management plan) for that part has been submitted to and approved by the relevant planning authority, or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities, such approval to be in consultation with the relevant highway authority and the Environment Agency.
  • (2) All construction works associated with the authorised development must be carried out in accordance with the approved construction environmental management plan.
  • (3) The details on the amount and type of waste from the authorised development and how it will be reused, recycled or disposed of is to be set out in a Waste Management Plan which is to be included as an appendix to the construction environmental management plan.

Operational environmental management plan

13

  • (1) Prior to the date of final commissioning for any part of the authorised development, an operational environmental management plan for that part must be submitted to and approved by the relevant planning authority for that part, or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities, such approval to be in consultation with Lincolnshire County Council in its capacity as the planning waste authority, the relevant highway authority and the Environment Agency.
  • (2) The operational environmental management plan must be substantially in accordance with the framework operational environmental management plan and must be implemented as approved and maintained throughout the operation of the relevant part of the authorised development to which the plan relates.

Construction traffic management plan

14

  • (1) No part of the authorised development may commence until a construction traffic management plan for that part has been submitted to and approved by the relevant planning authority for that part, or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities, such approval to be in consultation with the relevant highway authority and West Lindsey District Council.
  • (2) The construction traffic management plan must be substantially in accordance with the framework construction traffic management plan.
  • (3) Before approving the construction traffic management plan the relevant planning authority must consult with the relevant highway authority.
  • (4) The construction traffic management plan must be implemented as approved.

Operational noise

15

  • (1) No part of numbered Works No. 1, No. 2 and No. 3 may commence until an operational noise assessment containing details of how the design of that numbered work has incorporated mitigation to ensure the operational noise rating levels as set out in the environmental statement are to be complied with for that part has been submitted to and approved by the relevant planning authority for that part or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.
  • (2) The design as described in the operational noise assessment must be implemented as approved and maintained throughout the operation of the relevant part of the authorised development to which the plan relates.

Public rights of way diversions

16

  • (1) No part of the authorised development may commence until a public rights of way management plan for any sections of public rights of way shown to be temporarily closed on the streets, access and rights of way plans for that part has been submitted to and approved by the relevant planning authority, or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities, such approval to be in consultation with the relevant highway authority.
  • (2) The public rights of way management plan must be substantially in accordance with the outline public rights of way management plan.
  • (3) The public rights of way management plan must be implemented as approved unless otherwise agreed with the relevant planning authority in consultation with the highway authority.

Soils management

17

  • (1) No part of the authorised development may commence until a soil management plan (which must be substantially in accordance with the outline soil management plan as relevant to construction activities) for that part has been submitted to and approved by the relevant planning authority or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.
  • (2) All construction works associated with the authorised development must be carried out in accordance with the soil management plan approved pursuant to sub-paragraph ‎(1).
  • (3) Prior to the date of final commissioning for any part of the authorised development, a soil management plan (which must be substantially in accordance with the outline soil management plan as relevant to operational activities) for that part must be submitted to and approved by the relevant planning authority for that part or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.
  • (4) The operation of the authorised development must be carried out in accordance with the soil management plan approved pursuant to sub-paragraph ‎(3) and maintained throughout the operation of the relevant part of the authorised development to which the plan relates.
  • (5) Prior to the start of any decommissioning works for any part of the authorised development, a soil management plan (which must be substantially in accordance with the outline soil management plan as relevant to decommissioning activities) for that part must be submitted to and approved by the relevant planning authority for that part or, where the part falls within the administrative areas of multiple relevant planning authorities, each of the relevant planning authorities.
  • (6) The decommissioning of the authorised development must be carried out in accordance with the soil management plan approved pursuant to sub-paragraph ‎(5).

Skills, supply chain and employment

18

  • (1) No part of the authorised development may commence until a skills, supply chain and employment plan in relation to that part has been submitted to and approved by the relevant planning authority for that part or, where the part falls within the administrative areas of multiple planning authorities, each of the relevant planning authorities following consultation with Lincolnshire County Council.
  • (2) The skills, supply chain and employment plan must be substantially in accordance with the outline skills, supply chain and employment plan.
  • (3) Any plan under this paragraph must identify opportunities for individuals and businesses to access employment and supply chain opportunities associated with that part of the authorised development and the means for publicising such opportunities.
  • (4) The skills, supply chain and employment plan must be implemented as approved and maintained throughout the operation of the relevant part of the authorised development to which the plan relates.

Decommissioning and restoration

19

  • (1) Decommissioning of the authorised development must commence no later than 60 years following the date of final commissioning of the authorised development.
  • (2) Unless otherwise agreed with the relevant planning authority, no later than 12 months prior to the date the undertaker intends to decommission any part of the authorised development, the undertaker must notify the relevant planning authority of the intended date of decommissioning.
  • (3) Within 12 months of the date notified pursuant to sub-paragraph (2), the undertaker must submit to the relevant planning authority for that part a decommissioning environmental management plan for approval which must include a decommissioning traffic management plan and site waste management plan, in consultation with the Environment Agency.
  • (4) Where the undertaker decides to decommission a part of the authorised development that falls within the administrative areas of multiple planning authorities, the decommissioning environmental management plan must be submitted to each relevant planning authority and the approval of all relevant planning authorities is required for the purposes of this paragraph.
  • (5) The decommissioning environmental management plan must be substantially in accordance with the framework decommissioning environmental management plan.
  • (6) No decommissioning works must be carried out until the relevant planning authority has approved the decommissioning environmental management plan submitted in relation to those works.
  • (7) The decommissioning environmental management plan must be implemented as approved.
  • (8) This requirement is without prejudice to any other consents or permissions that may be required to decommission any part of the authorised development.

SCHEDULE 3 — LEGISLATION TO BE DISAPPLIED

1

The following provisions do not apply in so far as they relate to the construction of any numbered work or the carrying out of any operation required for the purpose of, or in connection with, the construction, operation, maintenance or decommissioning of the authorised development—

  • (a) Great Grimsby and Sheffield Junction Railway Act 184550;
  • (b) Great Northern Railway Act 184651;
  • (c) Sheffield and Lincolnshire Junction Railway Act 184652;
  • (d) Manchester, Sheffield, and Lincolnshire Railways, and Manchester and Lincolnshire Union Railway and Chesterfield and Gainsborough Canal Amalgamation Act 184753;
  • (e) Trent (Burton on Trent and Humber) Navigation Act 188754;
  • (f) Trent Navigation Act 190655;
  • (g) Great Central Railway Act 190756;
  • (h) Lincolnshire Rivers Fisheries Provisional Order Confirmation Act 192857;
  • (i) Trent and Lincolnshire Water Act 197158; and
  • (j) Anglian Water Authority Act 197759.

SCHEDULE 4 — STREETS SUBJECT TO STREET WORKS

Interpretation

1

In this Schedule—

  • “cable works” means works to place, retain and maintain underground electrical and communications apparatus; and
  • “culvert works” means repair, replace, extend or alter and maintain an existing culvert. (1) Area (2) Street (3) Description of the street works District of West LindseyB1241 Kexby LaneCable works and culvert works beneath the width of the street for the length shown in green on sheet 1 of the streets, rights of way and access plans.District of West LindseyGainsborough Road A156 SouthboundCable works beneath the width of the street for the length shown in green on sheet 4 of the streets, rights of way and access plans.District of West LindseyClay LaneCable works beneath the width of the street for the length shown in green on sheet 10 of the streets, rights of way and access plans.District of West LindseyWillingham RoadCable works beneath the width of the street for the length shown in green on sheet 10 of the streets, rights of way and access plans.District of West LindseyA1500 Stow Park RoadCable works and culvert works beneath the width of the street for the length shown in green on sheet 11 of the streets, rights of way and access plans.District of West LindseyA156 High StreetCable works beneath the width of the street for the lengths shown in green on sheet 12 of the streets, rights of way and access plans.District of BassetlawHeadstead BankCable works beneath the width of the street for the length shown in green on sheet 14 of the streets, rights of way and access plans.District of BassetlawCow Pasture LaneCable works beneath the width of the street for the length shown in green on sheet 15 of the streets, rights of way and access plans.District of BassetlawCottam RoadCable works beneath the width of the street for the length shown in green on sheet 15 of the streets, rights of way and access plans.District of BassetlawNightleys RoadCable works beneath the width of the street for the length shown in light blue on sheet 17 of the streets, rights of way and access plans.District of BassetlawShortleys RoadCable works beneath the width of the street for the length shown in light blue on sheet 17 of the streets, rights of way and access plans.District of BassetlawTorksey Ferry RoadCable works beneath the width of the street for the length shown in light blue on sheets 17 and 18 of the streets, rights of way and access plans.

SCHEDULE 5 — ALTERATION OF STREETS

PART 1 — PERMANENT ALTERATION OF LAYOUT

(1)Area (2)Street (3)Description of alteration
District of West Lindsey Field Access Kexby Lane B1241 Westbound Permanent alteration of layout at the point marked 1/01 on sheet 1 of the streets, rights of way and access plans.
District of West Lindsey Field Access Kexby Lane B1241 Eastbound Permanent alteration of layout at the point marked 1/02 on sheet 1 of the streets, rights of way and access plans.
District of West Lindsey Field Access Kexby Lane B1241 Eastbound Permanent alteration of layout at the point marked 1/04 on sheet 1 of the streets, rights of way and access plans.
District of West Lindsey Proposed Access off Kexby Lane B1241 Westbound Permanent alteration of layout at the point marked 1/05 on sheet 1 of the streets, rights of way and access plans.
District of West Lindsey Field Access Gainsborough Road A156 Southbound Permanent alteration of layout at the point marked 4/02 on sheet 4 of the streets, rights of way and access plans.
District of West Lindsey Field Gate Access Willingham Road Eastbound Permanent alteration of layout at the point marked 6/02 on sheet 6 of the streets, rights of way and access plans.
District of West Lindsey Access Track Marton Road Northbound Permanent alteration of layout at the point marked 7/01 on sheet 7 of the streets, rights of way and access plans.
District of West Lindsey Proposed Access off Private Means of Access off Marton Road Northbound Permanent alteration of layout at the point marked 7/02 on sheet 7 of the streets, rights of way and access plans.
District of West Lindsey Proposed Access off Private Means of Access off Marton Road Northbound Permanent alteration of layout at the point marked 7/03 on sheet 7 of the streets, rights of way and access plans.
District of West Lindsey Field Access Marton Road Eastbound Permanent alteration of layout at the point marked 8/02 on sheet 8 of the streets, rights of way and access plans.
District of West Lindsey Field Access Marton Road Eastbound Permanent alteration of layout at the point marked 8/03 on sheet 8 of the streets, rights of way and access plans.
District of West Lindsey Field Access Marton Road Eastbound Permanent alteration of layout at the point marked 8/05 on sheet 8 of the streets, rights of way and access plans.
District of West Lindsey Field Access Marton Road Eastbound Permanent alteration of layout at the point marked 8/07 on sheet 8 of the streets, rights of way and access plans.
District of West Lindsey Field Access Marton Road Eastbound Permanent alteration of layout at the point marked 8/08 on sheet 8 of the streets, rights of way and access plans.
District of West Lindsey Field Access Marton Road Northbound Permanent alteration of layout at the point marked 8/09 on sheet 8 of the streets, rights of way and access plans.
District of West Lindsey Field Access Clay Lane Eastbound Permanent alteration of layout at the point marked 10/08 on sheet 10 of the streets, rights of way and access plans.
District of West Lindsey Proposed access Clay Lane Westbound Permanent alteration of layout at the point marked 10/09 on sheet 10 of the streets, rights of way and access plans.
District of West Lindsey Field Access Clay Lane Westbound Permanent alteration of layout at the point marked 10/10 on sheet 10 of the streets, rights of way and access plans.
District of West Lindsey Proposed access Clay Lane Westbound Permanent alteration of layout at the point marked 10/11 on sheet 10 of the streets, rights of way and access plans.
District of West Lindsey Proposed access Clay Lane Eastbound Permanent alteration of layout at the point marked 10/14 on sheet 10 of the streets, rights of way and access plans.
District of West Lindsey Proposed access off Eastbound carriageway of A1500 Stow Park Road Permanent alteration of layout at the point marked 11/06 on sheet 11 of the streets, rights of way and access plans.
District of West Lindsey Proposed access off Westbound carriageway of A1500 Stow Park Road Permanent alteration of layout at the point marked 11/07 on sheet 11 of the streets, rights of way and access plans.
District of West Lindsey Field Access A156 High Street Northbound Permanent alteration of layout at the point marked 12/08 on sheet 12 of the streets, rights of way and access plans.
District of West Lindsey Access Track A156 High Street Northbound Permanent alteration of layout at the point marked 12/09 on sheet 12 of the streets, rights of way and access plans.
District of West Lindsey Access Track A156 High Street Northbound Permanent alteration of layout at the point marked 12/10 on sheet 12 of the streets, rights of way and access plans.
District of West Lindsey Proposed access off Northbound Carriageway of A156 High Street Permanent alteration of layout at the point marked 12/11 on sheet 12 of the streets, rights of way and access plans.
District of Bassetlaw Field Access off existing access 14/03 Permanent alteration of layout at the point marked 14/02 on sheet 14 of the streets, rights of way and access plans.
District of Bassetlaw Access Track Headstead Bank Southbound Permanent alteration of layout at the point marked 14/03 on sheet 14 of the streets, rights of way and access plans.
District of Bassetlaw Proposed Access off Headstead Bank Northbound Permanent alteration of layout at the point marked 14/20 on sheet 14 of the streets, rights of way and access plans.
District of Bassetlaw Existing access off Cow Pasture Lane Permanent alteration of layout at the point marked 15/09 on sheet 15 of the streets, rights of way and access plans.
District of Bassetlaw Proposed Access off Cottam Road Eastbound Permanent alteration of layout at the point marked 15/10 on sheet 15 of the streets, rights of way and access plans.
District of Bassetlaw Existing Field access off Cottam Road Westbound Permanent alteration of layout at the point marked 15/01 on sheet 15 of the streets, rights of way and access plans.
District of Bassetlaw Proposed Access off Cow Pasture Lane Permanent alteration of layout at the point marked 15/15 on sheet 15 of the streets, rights of way and access plans.
District of Bassetlaw Field Access Torksey Ferry Road Eastbound Permanent alteration of layout at the point marked 17/02 on sheet 17 of the streets, rights of way and access plans.
District of Bassetlaw Field Access Torksey Ferry Road Westbound Permanent alteration of layout at the point marked 17/05 on sheet 17 of the streets, rights of way and access plans.
District of Bassetlaw Field Access Shortleys Lane Northbound Permanent alteration of layout at the point marked 17/18 on sheet 17 of the streets, rights of way and access plans.
District of Bassetlaw Field Access Shortleys Lane Southbound Permanent alteration of layout at the point marked 17/19 on sheet 17 of the streets, rights of way and access plans.

PART 2 — TEMPORARY ALTERATION OF LAYOUT

(1) Area (2) Street (3) Description of alteration
District of West Lindsey Junction of A1500 Stow Park Road and A156 High Street Temporary alteration of layout within the area shaded green on Sheet 11 of the streets, rights of way and access plans.

SCHEDULE 6 — STREETS AND PUBLIC RIGHTS OF WAY

PART 1 — STREETS TO BE TEMPORARILY CLOSED

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.