The Morgan Offshore Wind Project Generation Assets Order 2025

Type Statutory-Instrument
Publication 2025-08-29
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • (a) co-ordinates, depth, current speed, charge utilised and the date and time of each clearance; and
  • (b) whether any mitigation was deployed including feedback on practicalities of deployment of equipment and efficacy of the mitigation where reasonably practicable, or justification if this information is not available.
  • (5) Should there be more than one low order unexploded ordnance clearance activity, the report required under sub-paragraph (4) will be provided at intervals agreed with the MMO.
  • (6) The total number of low order unexploded ordnance clearance as part of the authorised scheme in this licence and the authorised scheme in licence 1 taken together must not exceed 13 (whether undertaken under this licence or licence 1).
  • (7) No high order unexploded ordnance clearance is permitted by this marine licence.

Marine Noise Registry

24

  • (1) In the event that driven or part–driven pile foundations are proposed to be used as part of the foundation installation the undertaker must provide the following information to the Marine Noise Registry—
  • (a) no less than six months prior to the commencement of each stage of construction of the licensed activities, information on the expected location, start and end dates of impact pile driving to satisfy the Marine Noise Registry’s Forward Look requirements,
  • (b) within two weeks after commencement of each stage of construction of the licensed activities, information on the location, start and end dates of impact pile driving to satisfy the Marine Noise Registry’s Forward Look requirements;
  • (c) at six month intervals following the commencement of pile driving, information on the locations and dates of impact pile driving to satisfy the Marine Noise Registry’s Close Out requirements by 7 April for winter season October – March inclusive and 7 October for summer season April – September inclusive or within 12 weeks of completion of impact pile driving whichever is earlier.
  • (2) Within 12 weeks of the completion of pile driving the undertaker must submit information on the locations and dates of those activities to satisfy the Close Out requirements.
  • (3) The undertaker must notify MMO of the successful submission of Forward Look or Close Out information pursuant to sub-paragraphs (1) to (3) above within seven days of the submissions to the Marine Noise Registry.
  • (4) For the purpose of this condition—
  • (a) “Marine Noise Registry” means the database of impulsive noise generating activities in UK seas maintained by Joint Nature Conservation Committee;
  • (b) “Forward Look” and “Close Out” requirements are as set out in the ‘UK Marine Noise Registry: Information Document, Version 1 (May 2016)’ or any updated information document.

Offshore safety management

25

No part of the authorised scheme may commence until the MMO, in consultation with the MCA, has confirmed in writing that the undertaker has taken into account and, so far as is applicable to that stage of the project, adequately addressed all MCA recommendations as appropriate to the authorised scheme contained within MGN654 “Offshore Renewable Energy Installations (OREIs) – Guidance on UK Navigational Practice, Safety and Emergency Response Issues” (or any equivalent guidance that replaces or supersedes it) and its annexes.

Reporting of engaged agents, contractors and vessels

26

  • (1) The undertaker must provide the following information in writing to the MMO, unless otherwise agreed in writing by the MMO—
  • (a) the name, function, company number (if applicable), registered or head office address (as appropriate) of any agent or contractor appointed to engage in the licensed activities within seven days of appointment; and
  • (b) each week during the construction of the authorised scheme a completed Hydrographic Note H102 listing the vessels currently and to be used in relation to the licensed activities.
  • (2) The undertaker must notify the MMO in writing of any vessel being used to carry on any licensed activity listed in this licence on behalf of the undertaker. Such notification must be received by the MMO no less than 24 hours before the commencement of the licensed activity. Notification must include the master’s name, vessel type, vessel IMO number and vessel owner or operating company.
  • (3) Any changes to the supplied details must be notified to the MMO in writing at least 24 hours before the agent, contractor or vessel engages in the licensed activities.

Pre-construction monitoring and surveys

27

  • (1) The undertaker must, in discharging condition 20(1)(c) submit a monitoring plan or plans in accordance with the offshore in principle monitoring plan for written approval by the MMO in consultation with the relevant statutory nature conservation body, which must contain details of proposed monitoring and surveys, including methodologies and timings, and a proposed format and content for a pre-construction baseline report.
  • (2) The survey proposals submitted under sub-paragraph (1) must be in general accordance with the principles set out in the offshore in principle monitoring plan and must specify each survey’s objectives and explain how it will assist in either informing a useful and valid comparison with the post-construction position or will enable the validation or otherwise of key predictions in the environmental statement.
  • (3) The baseline report proposals submitted under sub-paragraph (1) must ensure that the outcome of the agreed surveys, together with existing data and reports, are drawn together to present a valid statement of the pre-construction position, with any limitations, and must make clear what post-construction comparison is intended and the justification for this being required.
  • (4) The pre-construction surveys referred to in sub-paragraph (1) must, unless otherwise agreed with the MMO, have due regard to, but not be limited to, the need to undertake a swath-bathymetry survey to IHO Order 1a standard that meets the requirements of MGN654 and its supporting Hydrographic Guidelines for Offshore Renewable Energy Developers, which includes the requirement for the full density data and reports to be delivered to the MCA and the UKHO for the update of nautical charts and publications and side scan sonar, of the area(s) within the Order limits in which it is proposed to carry out construction works including an appropriate buffer around the location of each work.
  • (5) The undertaker must carry out the surveys specified within the monitoring plan or plans in accordance with that plan or plans, unless otherwise agreed in writing by the MMO in consultation with the relevant statutory nature conservation body.

Construction monitoring

28

  • (1) The undertaker must, in discharging condition 20(1)(c) for each stage of construction, submit details (which accord with the offshore in principle monitoring plan) for approval in writing by the MMO in consultation with the relevant statutory nature conservation bodies of any proposed monitoring, including methodologies and timings, to be carried out during the construction of the authorised scheme. The monitoring proposals must specify each monitoring proposal’s objectives and explain how it will assist in either informing a useful and valid comparison with the pre-construction position and/or will enable the validation or otherwise of key predictions in the environmental statement.
  • (2) The construction monitoring must include—
  • (a) marine traffic monitoring in accordance with the offshore in principle monitoring plan, including the provision of reports on the results of that monitoring at the end of each year of the construction period to the MMO, MCA and Trinity House;
  • (b) in the event that driven or part-driven pile foundations are proposed, measurements of underwater sound generated by the installation of the first four piled foundations of each piled foundation type to be installed collectively under this licence and licence 1 unless the MMO otherwise agrees in writing; and
  • (c) in the event that driven or part-driven pile foundations are proposed, measurements of underwater sound generated by the installation of the first two piled foundations where it is anticipated hammer energies greater than 3,000kJ may be required for installation, unless the MMO otherwise agrees in writing.
  • (3) In the event that piled foundations are proposed to be used, the details submitted in accordance with the marine mammal mitigation protocol must include proposals for monitoring marine mammals.
  • (4) The undertaker must carry out the monitoring approved under sub-paragraph (1), including any further underwater sound monitoring required in writing by the MMO, and provide the agreed reports in the agreed format in accordance with the agreed timetable, unless otherwise agreed in writing with the MMO in consultation with the relevant statutory nature conservation bodies.
  • (5) The results of the initial underwater sound measurements monitored in accordance with sub-paragraph (2)(b) must be provided to the MMO within six weeks of the installation of the first four piled foundations. The assessment of this report by the MMO will determine whether any further underwater sound monitoring is required. If, in the reasonable opinion of the MMO in consultation with the relevant statutory nature conservation body, the assessment shows significantly different underwater sound modelling results to those assessed in the environmental statement or failures in mitigation, all piling activity must cease until an update to the marine mammal mitigation protocol and further monitoring requirements have been agreed.
  • (6) The results of the any underwater sound measurements monitored in accordance with sub-paragraph (2)(c) must be provided to the MMO within six weeks of the installation of the first two piled foundations that exceed 3,000kJ of hammer energy. The assessment of this report by the MMO will determine whether any further underwater sound monitoring is required. If, in the reasonable opinion of the MMO in consultation with the relevant statutory nature conservation body, the assessment shows significantly different underwater sound modelling results to those assessed in the environmental statement or failures in mitigation, any piling activity where the hammer energy is anticipated to exceed 3,000kJ must cease until an update to the marine mammal mitigation protocol and further monitoring requirements have been agreed.
  • (7) The undertaker must carry out the surveys specified in the offshore monitoring plan in accordance with that plan, including any further underwater sound monitoring required in writing by the MMO under sub-paragraph (4), unless otherwise agreed in writing by the MMO in consultation with the relevant statutory nature conservation body.

Post-construction monitoring

29

  • (1) The undertaker must, in discharging condition 20(1)(c) submit details (which accord with the offshore in principle monitoring plan) for approval in writing by the MMO in consultation with relevant statutory nature conservation bodies of proposed post-construction monitoring, including methodologies and timings, and a proposed format, content and timings for providing reports on the results.
  • (2) The monitoring proposals must specify each monitoring proposal’s objectives and explain how it will assist in either informing a useful and valid comparison with the pre-construction position and/or will enable the validation or otherwise of key predictions in the environmental statement.
  • (3) The post-construction monitoring referred to in sub-paragraph (1) must, unless otherwise agreed in writing with the MMO, have due regard to, but not be limited to, the need to—
  • (a) undertake, within 12 months of completion of construction of the authorised scheme, a full sea floor coverage swath-bathymetry survey to IHO Order 1a standard that meets the requirements of MGN 654 and its supporting Hydrographic Guidelines for Offshore Renewable Energy Developers which includes the requirement for the full density data and reports to be delivered to the MCA and the UKHO for the update of nautical charts and publications, and side scan sonar, of the area(s) within the Order limits in which construction works were carried out to assess any changes in bedform topography and such further monitoring or assessment as may be agreed to ensure that cables (including fibre optic cables) have been buried or protected; and
  • (b) undertake post-construction marine traffic monitoring in accordance with the offshore in principle monitoring plan, including the provision of reports on the results of that monitoring to the MMO, MCA and Trinity House.
  • (4) The undertaker must carry out the monitoring agreed under sub-paragraph (1) and provide the agreed reports to the MMO in the agreed format in accordance with the agreed timetable, unless otherwise agreed in writing with the MMO in consultation with the relevant statutory nature conservation bodies.
  • (5) Following the installation of cables, details of cable monitoring required under 20(1)(d)(i) must be updated with the results of the post installation surveys.

Reporting of scour and cable protection

30

  • (1) Not more than four months following completion of the construction of the authorised scheme, the undertaker must provide the MMO and the relevant statutory nature conservation bodies with a report setting out details of the cable protection and scour protection used for the authorised scheme.
  • (2) The report must include the following information—
  • (a) the location of cable protection and scour protection;
  • (b) the volume of cable protection and scour protection; and
  • (c) any other information relating to the cable protection and scour protection as agreed between the MMO and the undertaker.
  • (3) Any cable protection (other than the replenishment or replacement of existing cable protection) authorised under this licence must be deployed within 10 years from the date of completion of construction (as reported in the close-out report under condition 31) unless otherwise agreed by the MMO in writing.

Completion of construction

31

  • (1) The undertaker must submit a close-out report to the MMO, MCA, Trinity House, the UKHO and the relevant statutory nature conservation body within four months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the following details—
  • (a) the final number of installed offshore substation platforms;
  • (b) the installed offshore substation platform parameters;
  • (c) as built plans;
  • (d) latitude and longitude coordinates of the centre point of the location for each offshore substation platform provided as Geographical Information System data referenced to WGS84 datum; and
  • (e) latitude and longitude coordinates of the interconnector cables provided as Geographical Information System data referenced to WGS84 datum.
  • (2) Following completion of construction, no further construction activities can be undertaken under this licence.

Requirement for written approval

32

Where under any of the above conditions the approval or agreement of the MMO is required, that approval or agreement must be given in writing.

SCHEDULE 5 — Documents to be certified

1

The following documents are the list referred to in article 11—

Document Reference Number Examination Library Reference Document Name Version Date
Plans and Drawings Plans and Drawings Plans and Drawings Plans and Drawings Plans and Drawings
B2 APP-081 Order Limits and Grid Coordinates Plan F01 April 2024
B3 APP-082 Works plan F01 April 2024
Environmental Statement Environmental Statement Environmental Statement Environmental Statement Environmental Statement
F1 APP-095 Non-technical summary F01 April 2024
F1.1 APP-008 Volume 1, Chapter 1 Introduction and overarching glossary F01 April 2024
F1.2 APP-009 Volume 1, Chapter 2: Policy and legislative context F01 April 2024
S_D6_15 REP6-024 Volume 1, Chapter 3: Project description F02 February 2025
F1.4 APP-011 Volume 1, Chapter 4: Site selection and consideration of alternatives F01 April 2024
F1.5 APP-012 Volume 1, Chapter 5: Environmental impact assessment methodology F01 April 2024
S_D6_16 REP6-026 Volume 2, Chapter 1: Physical processes F02 February 2025
S_D6_17 REP6-028 Volume 2, Chapter 2: Benthic subtidal ecology F02 February 2025
S_D6_18 REP6-030 Volume 2, Chapter 3: Fish and shellfish ecology F02 February 2025
S_D6_19 REP6-031 Volume 2, Chapter 4: Marine mammals F04 February 2025
S_D6_20 REP6-033 Volume 2, Chapter 5: Offshore ornithology F02 February 2025
F2.6 APP-024 Volume 2, Chapter 6: Commercial fisheries F01 April 2024
S_D6_21 REP6-034 Volume 2, Chapter 7: Shipping and navigation F02 February 2025
F2.8 APP-026 Volume 2, Chapter 8: Marine archaeology and cultural heritage F01 April 2024
S_D6_22 REP6-035 Volume 2, Chapter 9: Other sea users F02 February 2025
S_D6_23 REP6-036 Volume 2, Chapter 10: Seascape, landscape and visual resources F02 February 2025
F2.11 APP-015 Volume 2, Chapter 11: Aviation and radar F01 April 2024
F2.12 APP-016 Volume 2, Chapter 12: Climate change F01 April 2024
S_D6_24 REP6-037 Volume 2, Chapter 13: Socio-economics F02 February 2025
F2.14 APP-018 Volume 2, Chapter 14: Human health assessment F01 April 2024
F2.15 APP-019 Volume 2, Chapter 15: Inter-related effects F01 April 2024
F3.3.1 APP-028 Volume 3 Annex 3.1: Underwater sound technical report F01 April 2024
F3.3.2 APP-029 Volume 3 Annex 3.2: Sulphur hexafluoride report F01 April 2024
F3.3.3 APP-030 Volume 3 Annex 3.3: Scoping opinion F01 April 2024
F3.5.1 APP-031 Volume 3 Annex 5.1: Cumulative effects screening matrix F01 April 2024
F3.5.2 APP-032 Volume 3 Annex 5.2: Transboundary impacts screening F01 April 2024
F4.1.1 APP-033 Volume 4 Annex 1.1: Physical processes technical report F01 April 2024
F4.2.1 APP-050 Volume 4 Annex 2.1: Benthic subtidal ecology technical report F01 April 2024
F4.3.1 APP-051 Volume 4 Annex 3.1: Fish and shellfish ecology technical report F01 April 2024
F4.4.1 APP-052 Volume 4 Annex 4.1: Marine mammals technical report F01 April 2024
S_D1_11 REP1-026 Volume 4 Annex 5.1: Offshore ornithology baseline characterisation F02 October 2024
F4.5.2 APP-054 Volume 4 Annex 5.2: Offshore ornithology displacement technical report F01 April 2024
S_D6_25 REP6-038 Volume 4 Annex 5.3: Offshore ornithology collision risk modelling technical report F02 February 2025
F4.5.4 APP-056 Volume 4 Annex 5.4: Offshore ornithology migratory bird collision risk modelling technical report F01 April 2024
S_D6_26 REP6-039 Volume 4 Annex 5.5: Offshore ornithology apportioning technical report F02 February 2025
F4.5.6 APP-058 Volume 4 Annex 5.6: Offshore ornithology PVA technical report F01 April 2024
S_D6_27 REP6-040 Volume 4 Annex 6.1: Commercial fisheries technical report F02 February 2025
S_D6_28 REP6-041 Volume 4 Annex 7.1: Navigational risk assessment F02 February 2025
F4.8.1 APP-061 Volume 4 Annex 8.1: Marine archaeology technical report F01 April 2024
F4.8.2 APP-062 Volume 4 Annex 8.2: Cultural heritage assessment F01 April 2024
F4.9.1 APP-063 Volume 4 Annex 9.1: Radar early warning systems technical report F01 April 2024
F4.10.1 APP-034 Volume 4 Annex 10.1: Seascape, landscape and visual resources legislation and planning policy context F01 April 2024
F4.10.2 APP-035 Volume 4 Annex 10.2: Seascape and landscape character baseline technical report F01 April 2024
F4.10.3 APP-036 Volume 4 Annex 10.3: Visual baseline technical report F01 April 2024
F4.10.4 APP-037 Volume 4 Annex 10.4: Seascape, landscape and visual resources impact assessment methodology F01 April 2024
F4.10.5 APP-038 Volume 4 Annex 10.5: International and nationally designated landscape study F01 April 2024
F4.10.6 APP-039 Volume 4 Annex 10.6: Seascape visualisations Part 1 (Figures 1.1 – 9.1) F01 April 2024
F4.10.6 APP-040 Volume 4 Annex 10.6: Seascape visualisations Part 2 (Figures 10.1 – 16.3) F01 April 2024
F4.10.6 APP-041 Volume 4 Annex 10.6: Seascape visualisations Part 3 (Figures 16.4 – 25) F01 April 2024
F4.10.6 APP-042 Volume 4 Annex 10.6: Seascape visualisations Part 4 (Figures 26 – 43) F01 April 2024
F4.10.6 APP-043 Volume 4 Annex 10.6: Seascape visualisations Part 5 (Figures 44 – 61) F01 April 2024
F4.10.6 APP-044 Volume 4 Annex 10.6: Seascape visualisations Part 6 (Figures 62 – 74) F01 April 2024
F4.11.1 APP-045 Volume 4, Annex 11.1: Aviation and radar technical report F01 April 2024
F4.12.1 APP-046 Volume 4, Annex 12.1: Technical greenhouse gas assessment F01 April 2024
F4.12.2 APP-047 Volume 4, Annex 11.2: Climate change risk assessment F01 April 2024
F4.13.1 APP-048 Volume 4, Annex 13.1: Socio-economics technical impact report F01 April 2024
F4.14.1 APP-049 Volume 4, Annex 14.1: Airborne construction sound technical report F01 April 2024
S_PD_3.7 PD1-012, PD1-013 and PD1-014 Annex 3.7 to the Applicant’s response to Relevant Representations from Natural England [Seascape, landscape and visual impact assessment] F01 August 2024
S_PD_3.9 PD1-016 Annex 3.9 to the Applicant’s response to Relevant Representations from Natural England [Offshore ornithology] F01 August 2024
S_D1_4.5 REP1-010 Annex 4.5 to Response to Hearing Action Point 15: Offshore Ornithology CEA and In-combination Gap-filling of Historical Projects Note F01 October 2024
S_D1_4.6 REP1-011 Displacement Rates Clarification Note [Offshore ornithology] F01 October 2024
S_D1_4.8 REP1-013 Annex 4.8 to Response to Hearing Action Point 15: Great Orme Head SSSI Clarification Note F01 October 2024
S_D2_13 REP2-021 Treatment of Birds in Flight Data in Abundance Estimation F01 October 2024
S_D2_14 REP2-022 Great black-backed gull regional populations F01 October 2024
S_D2_15 REP2-023 Review of Cumulative Effects Assessment and In-Combination Assessment F01 October 2024
S_D3_4.4 REP3-010 Annex 4.4 to the Applicant’s response to EXQ1: SLVIA Clarification note F01 November 2024
S_D3_9 REP3-018 Inclusion of Awel y Môr in Cumulative Assessments – Clarification note F01 November 2024
S_D3_10 REP3-019 Review of Cumulative Effects Assessment and In-Combination Assessment: Offshore ornithology F01 November 2024
S D4 6.1 REP4-010 Annex 6.1 to the Applicant’s response to Written Representations from MMO at Deadline 3: Cod spawning period [Fish and shellfish] F01 December 2024
S_D4_14 REP4-023 Greenhouse Gas (GHG) Reduction Strategy F01 December 2024
S_D4_15 REP4-024 Review of Cumulative Effects Assessment and In-Combination Assessment: Morgan and Morecambe Offshore Wind Farms: Transmission Assets F01 December 2024
S_D5_15 REP5-031 Additional PVA Modelling for Great Black-Backed Gull Cumulative Assessment [Offshore ornithology] F01 January 2025
S_D5_16.1 REP5-032 Annex 16.1 to Ornithological assessment clarification data English sites F01 January 2025
S_D5a_16.2 AS-013 Annex 16.2 to Ornithological assessment clarification data Welsh sites F02 January 2025
S_D5_16.3 REP5-034 Annex 16.3 to Ornithological assessment clarification data offshore sites F01 January 2025
S_D5_16 REP5-035 Ornithological assessment clarification data F01 January 2025
S_D6_3.3 REP6-007 Helicopter Access Additional Flight Data F01 February 2025
S_D6_3.4 REP6-008 Helicopter Access Additional Meteorological Analysis F01 February 2025
S_D6_29 REP6-042 Review of Cumulative Effects Assessment and In-Combination Assessment at Deadline 6 F01 February 2025
S_D6_37.1 REP6-057 Appendix to Ornithological assessment clarification data (REP5-035) - Explanatory note to support SNCB and Applicant workbooks F01 February 2025
S_D6_37.2 REP6-058 Annex 16.4 to Ornithological assessment clarification data (REP5-035) - Applicant’s parameters (English sites) F01 February 2025
S_D6_37.3 REP6-059 Annex 16.5 to Ornithological assessment clarification data (REP5-035) - Applicant’s parameters (Welsh and offshore sites) F01 February 2025
S_D6_39 REP6-061 Population Viability Analysis for the Regional Population of Guillemot [Offshore ornithology] F01 February 2025
S_D6_40 REP6-062 Project alone and cumulative assessment for the Great Orme’s Head SSSI [Offshore ornithology] F02 February 2025
S_D6_41 REP6-063 Technical Note: Calculation of the Net Effects on Greenhouse Gas Emissions F02 February 2025
S_D7_3.1 REP7-005 Annex 3.1 Warton Aerodrome CNS Safeguarding Assessment Report F01 March 2025
Other Documents Other Documents Other Documents Other Documents Other Documents
S_D4_11 REP4-018 Outline Offshore Environmental Management Plan F01 December 2024
S_D4_22 REP4-032 Outline offshore construction method statement F01 December 2024
S_D5_19 REP5-039 Outline offshore written scheme of investigation for archaeology F02 January 2025
S_D6_30.1 REP6-045 Outline underwater sound management strategy F04 February 2025
S_D5_23 REP5-046 Measures to minimise disturbance to marine mammals and rafting birds from transiting vessels F02 January 2025
S_D6_31 REP6-047 Outline marine mammal mitigation protocol F04 February 2025
S_D6_32 REP6-049 Outline offshore operations and maintenance plan F02 February 2025
S_D6_33 REP6-051 Commitments Register F05 February 2025
S_D6_34 REP6-054 Offshore in-principle monitoring plan F02 February 2025
S_D6_35 REP6-055 Outline vessel traffic management plan F04 February 2025
S_D6_45 REP6-069 Outline fisheries liaison and co-existence plan F06 February 2025

Signed

Signed by the authority of the Secretary of State for Energy Security and Net Zero.

David Wagstaff — Deputy Director for Energy Infrastructure Planning — Department for Energy Security and Net Zero — 29th August 2025

Explanatory note

(This note is not part of the Order)

EXPLANATORY NOTE

This Order grants development consent for, and authorises the construction, operation and maintenance of an offshore wind farm generating station located approximately 36km from the North-West coast of England, together with associated development. This Order imposes requirements in connection with the development.

A copy of the plans referred to in this Order and certified in accordance with article 11 (certification of plans, etc.) may be inspected free of charge at the offices of Lancashire County Council, County Hall, Fishergate, Preston, Lancashire, PR1 8XJ.

Footnotes

[^f00001]: 2008 c. 29. Section 37 was amended by section 128(2) and Schedule 13, Part 1, paragraphs 1 to 5 of the Localism Act 2011 (c. 20).

[^f00002]: S.I. 2010/103. This instrument was amended by S.I. 2012/635.

[^f00003]: S.I. 2017/572.

[^f00004]: 1989 c. 29.

[^f00005]: 2004 c. 20.

[^f00006]: 2009 c. 23.

[^f00007]: 1971 c. 80.

[^f00008]: Section 6 was amended by sections 89, 136, 198, 143 and 145, Part 1 of Schedule 23 and paragraphs 3 and 5 of Schedule 19 to the Energy Act 2004 (c. 20), sections 72 and 121 and Schedule 1 to the Energy Act 2011 (c. 16), sections 166, 186, 334 and 205 to the Energy Act 2023 (c. 52), S.I. 2011/2704. There are other amendments to section 6 which are not relevant to the Order.

[^f00009]: Section 105 was amended by section 69 of the Energy Act 2008 (c. 32).

[^f00010]: 1978 c. 30.

[^f00011]: 1989 c. 29.

[^f00012]: 2004 c. 20.

[^f00013]: 2008 c. 29.

[^f00014]: 2009 c. 23.

[^f00015]: 1971 c. 80.

[^f00016]: 1989 c. 29.

[^f00017]: 2004 c. 20.

[^f00018]: 2008 c. 29.

[^f00019]: 2009 c. 23

[^f00020]: 1971 c. 80.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.