The Cory Decarbonisation Project Order 2025
- (9) Where REPL is to provide or construct the alternative apparatus, and the alternative apparatus is to be provided or constructed on land of the undertaker, the undertaker must grant REPL the necessary rights to provide or construct the alternative apparatus on that land and grant REPL the necessary rights to access and maintain the alternative apparatus on that land.
112
- (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to REPL rights in land of the undertaker for the construction and maintenance of alternative apparatus in substitution for apparatus to be removed, those rights must be granted upon such terms and conditions as may be agreed between the undertaker and REPL or in default of agreement settled by arbitration in accordance with article 49 (arbitration).
- (2) If the rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those rights are to be granted, are in the opinion of the arbitrator materially less favourable on the whole to REPL than the rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those rights are subject, the arbitrator must make such provision for the payment of compensation by the undertaker to REPL as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
113
- (1) Not less than 28 days before starting the execution of any works in, on or under the REPL land that may materially affect the operation of the REPL facility, the undertaker must submit to REPL for approval a plan, section and description of the works to be executed and a timetable for when such works are to be carried out.
- (2) The approval of REPL under sub-paragraph (1) must not be unreasonably withheld or delayed and if by the end of the period of 28 days beginning with the date on which the plan, section, description and timetable have been supplied to REPL, REPL has not intimated disapproval of such plan, section, description and timetable and the grounds of disapproval, REPL is deemed to have approved the said plan, section description and timetable as submitted.
- (3) When giving its approval under sub-paragraph (1), REPL may specify such reasonable requirements which in REPL’s opinion are necessary in the execution of the works.
- (4) The works described in sub-paragraph (1) must be executed only in accordance with the plan, section, description and timetable submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be given in accordance with sub-paragraph (3) by REPL. Where REPL reasonably requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to REPL’s reasonable satisfaction prior to the works described in sub-paragraph (1).
- (5) In the event that REPL issues a disapproval to the plan, section, description and timetable within the 28 day period referred to in sub-paragraph (1), the undertaker may refer the matter to arbitration in accordance with article 49 (arbitration).
- (6) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan, section and description instead of the plan, section and description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section and description.
- (7) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency works (as defined in the 1991 Act) but in that case it must give to REPL notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonably practicable subsequently and must comply with sub-paragraphs (3) and (4) in so far as is reasonably practicable in the circumstances.
114
- (1) Subject to the following provisions of this paragraph, the undertaker must repay to REPL the reasonable expenses incurred by REPL in, or in connection with, the inspection, removal, alteration or protection of any apparatus within the REPL land or the provision or construction of any alternative apparatus which REPL elects to carry out itself as referred to in paragraph 111(8).
- (2) There is to be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule, that value being calculated after removal.
- (3) If in accordance with the provisions of this Part of this Schedule—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated, and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 49 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to REPL by virtue of sub-paragraph (1) will be reduced by the amount of that excess.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus where such extension is required in consequence of the execution of any such works as are referred to in paragraph 111(2); and
- (b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
- (c) an amount which apart from this sub-paragraph would be payable to REPL in respect of works by virtue of sub-paragraph (1) if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on REPL any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, is to be reduced by the amount which represents that benefit.
115
Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and REPL in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
116
Where in consequence of the proposed construction or maintenance of any part of the authorised development, the undertaker or REPL requires the removal of apparatus or REPL makes requirements for the protection or alteration of apparatus, the undertaker shall use its reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution and maintenance of the authorised development and taking into account the need to ensure the safe and efficient operation of REPL’s undertaking and REPL shall use its reasonable endeavours to co-operate with the undertaker for that purpose.
117
If in consequence of any agreement reached or the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable REPL to maintain or use the apparatus no less effectively than was possible before such obstruction.
118
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works authorised by this Part of this Schedule or in consequence of the construction, use, maintenance or failure of any part of the authorised development by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by the undertaker) in the course of carrying out such works, use or maintenance, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised development) or property of REPL, or there is any interruption in any service provided, or in the supply of any goods, by REPL, or REPL becomes liable to pay any amount to any third party, the undertaker will—
- (a) bear and pay on demand the cost reasonably incurred by REPL in making good such damage or restoring the supply; and
- (b) indemnify REPL for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from REPL, by reason or in consequence of any such damage or interruption or REPL becoming liable to any third party as aforesaid other than arising from any default of REPL.
- (2) The fact that any act or thing may have been done by REPL on behalf of the undertaker or in accordance with a plan approved by REPL or in accordance with any requirement of REPL or under its supervision will not (unless sub-paragraph (3) applies), excuse the undertaker from liability under the provisions of this sub-paragraph (1) unless REPL fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan or as otherwise agreed between the undertaker and REPL.
- (3) Nothing in sub-paragraph (1) shall impose any liability on the undertaker in respect of–
- (a) any damage or interruption to the extent that it is attributable to the neglect or default of REPL, its officers, servants, contractors or agents; and
- (b) any part of the authorised development and/or any other works authorised by this Part of this Schedule carried out by REPL, whether pursuant to article 9 (benefit of this Order) or as an assignee, transferee or lessee of a person with the benefit of the Order pursuant to section 156 (benefit of order granting development consent) of the Planning Act 2008 or article 10 (consent to transfer benefit of the Order) subject to the proviso that once such works become apparatus, any part of the authorised development yet to be executed and not falling within this sub-paragraph will be subject to the full terms of this Part of this Schedule including this paragraph.
- (4) REPL must give the undertaker reasonable notice of any such third party claim or demand and no settlement or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and considering their representations.
- (5) REPL must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph applies. If requested to do so by the undertaker, REPL shall provide an explanation of how the claim has been minimised. The undertaker shall only be liable under this paragraph for claims reasonably incurred by REPL.
PART 9 — FOR THE PROTECTION OF EACH RRRL ENTITY
119
For the protection of each RRRL Entity as referred to in this Part of this Schedule the following provisions have effect unless otherwise agreed in writing between the undertaker and the applicable RRRL Entity.
120
In this Part of this Schedule—
- “alternative apparatus” means alternative apparatus adequate to enable each RRRL Entity to fulfil its functions in a manner no less efficient than previously;
- “apparatus” means any electric cables, electrical plant, drains, mains, sewers, pipes, conduits or any other apparatus belonging to or maintained by any RRRL Entity and used for, or for purposes connected with, waste treatment and disposal and the generation, transmission, distribution or supply of electricity and/or heat generated at the RRRL facility and includes any structure in which apparatus is or will be lodged or which gives or will give access to apparatus;
- “authorised development” has the same meaning as in article 2 (interpretation) of this Order;
- “functions” includes powers and duties;
- “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;
- “internal street” means any roads that service the RRRL facility and which are located within the RRRL facility perimeter;
- “plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed;
- “RRRL facility” means the energy from waste facility and associated infrastructure known operated at the date of this Order by RRRL at Norman Road, Belvedere, Bexley, Kent;
- “RRRL facility perimeter” means that part of the Order land identified as plots 1-008, 1-009, 1-019, 1-032, 1-034, 1-035, 1-037, 1-039, 1-040, 1-043, 1-045, 1-048, 1-049, 1-051, 1-052, 1-054, 1-055, 1-056, 1-058, 1-059, 1-060, 1-061, 1-062, 1-063, 1-064, 1-065, 1-066, 1-067, 1-069, 1-071, 1-073, 1-074, 1-075, 1-076, 1-077, 1-078, 1-079, 1-080, 1-084, 1-086, 1-087, 1-091, 1-096, 1-105, 1-109 and 1-112 on the land plans; and
- “RRRL land” means that part of the Order land in the freehold ownership of RRRL which, as at the date upon which this Order comes into force pursuant to article 1 (citation and commencement), are those plots identified as being in the freehold ownership of RRRL in the book of reference.
121
Regardless of any provision in this Order or anything shown on the land plans, the undertaker must not acquire any apparatus within the RRRL land otherwise than by agreement.
122
The undertaker must ensure that each RRRL Entity is at liberty at all times to, except in the case of where to do so would, in the undertaker’s discretion, lead to adverse safety impacts—
- (a) take all necessary access across any street used to access the RRRL facility (including any internal street), including in cases where that street has been temporarily stopped up under article 16 (temporary prohibition or restriction of use of streets, private means of access and public rights of way and authorising vehicular use on public rights of way) or is subject any traffic regulation measure pursuant to article 20 (traffic regulation measures); and
- (b) execute and do all such works and things in, upon or under any such street (including any internal street) used to access the RRRL facility, including in cases where that street has been temporarily stopped up under article 16 (temporary prohibition or restriction of use of streets, private means of access and public rights of way and authorising vehicular use on public rights of way), or is subject any traffic regulation measure pursuant to article 20, as may be reasonably necessary or desirable to enable it to maintain any apparatus which is in that street (including any internal street) used to access the RRRL facility.
123
- (1) If, in the exercise of the powers conferred by this Order, the undertaker—
- (a) acquires any interest in the RRRL land in which any apparatus is placed or over which access to any apparatus is enjoyed; or
- (b) requires that any RRRL Entity’s apparatus within the RRRL land is relocated, diverted or removed, any right of a RRRL Entity to any part of the RRRL land and/or to maintain that apparatus in that land and to gain access to it must not be extinguished, and that apparatus must not be relocated, diverted or removed, until equivalent rights have been granted to each RRRL Entity for alternative apparatus and equivalent alternative apparatus has vested in the applicable RRRL Entity and (in relation to apparatus) has been constructed and is in operation, and access to it has been provided to each RRRL Entity. The location of equivalent alternative apparatus and rights for the equivalent alternative apparatus must in each case be agreed between the undertaker and each RRRL Entity before any step is taken to extinguish, relocate, divert or remove as aforesaid.
- (2) If, for the purpose of executing any works in, on or under the RRRL land, the undertaker requires the relocation, diversion or removal of any apparatus placed in the RRRL land, the undertaker must give to each RRRL Entity for approval written notice of that requirement, a plan and section of the work proposed and of the proposed position of the alternative apparatus together with a timetable for when the alternative apparatus is to be provided or constructed by the undertaker.
- (3) The approval of each RRRL Entity under sub-paragraph (2) must not be unreasonably withheld or delayed and if by the end of the period of 28 days beginning with the date on which the notice, plan, section and timetable have been supplied to each RRRL Entity, a RRRL Entity has not intimated approval or disapproval of such notice, plan, section and timetable and the grounds of disapproval, such RRRL Entity is deemed to have approved the said notice, plan, section and timetable as submitted.
- (4) When giving its approval under sub-paragraph (2), each RRRL Entity may specify such reasonable requirements that are necessary in the provision or construction of the alternative apparatus.
- (5) In the event that any RRRL Entity issues a disapproval to the notice, plan, section and timetable within the 28 day period referred to in sub-paragraph (3), the undertaker may refer the matter to arbitration in accordance with article 49 (arbitration).
- (6) Subject to sub-paragraph (8), any alternative apparatus to be provided or constructed pursuant to this paragraph must be provided or constructed by the undertaker within a timescale, to a standard and in such manner and in such line or situation as is agreed with each RRRL Entity or in default of agreement settled by arbitration in accordance with article 49 (arbitration).
- (7) Where the alternative apparatus is to be provided or constructed on land of the undertaker and once the undertaker has provided or constructed the alternative apparatus, the undertaker must grant each RRRL Entity the necessary rights to access and maintain the alternative apparatus on that land.
- (8) If in the approval to the notice, plan, section and timetable under sub-paragraph (2) or by the end of the period of 28 days beginning with the date on which the arbitrator settles the alternative apparatus to be provided or constructed, a RRRL Entity gives notice to the undertaker that it desires to provide or construct the alternative apparatus and this is agreed to by the undertaker, (acting reasonably) such RRRL Entity, after the grant to such RRRL Entity of the rights as are referred to in sub-paragraph (9), must proceed without unnecessary delay to provide and construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
- (9) Where a RRRL Entity is to provide or construct the alternative apparatus, and the alternative apparatus is to be provided or constructed on land of the undertaker, the undertaker must grant such RRRL Entity the necessary rights to provide or construct the alternative apparatus on that land and grant each RRRL Entity the necessary rights to access and maintain the alternative apparatus on that land.
124
- (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to RRRL rights in land of the undertaker for the construction and maintenance of alternative apparatus in substitution for apparatus to be removed, those rights must be granted upon such terms and conditions as may be agreed between the undertaker and each RRRL Entity or in default of agreement settled by arbitration in accordance with article 49 (arbitration).
- (2) If the rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those rights are to be granted, are in the opinion of the arbitrator materially less favourable on the whole to a RRRL Entity than the rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those rights are subject, the arbitrator must make such provision for the payment of compensation by the undertaker to such RRRL Entity as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
125
- (1) Not less than 28 days before starting the execution of any works in, on or under the RRRL land that may materially affect the operation of the RRRL facility, the undertaker must submit to each RRRL Entity for approval a plan, section and description of the works to be executed and a timetable for when such works are to be carried out.
- (2) The approval of each RRRL Entity under sub-paragraph (1) must not be unreasonably withheld or delayed and if by the end of the period of 28 days beginning with the date on which the plan, section, description and timetable have been supplied to a RRRL Entity, such RRRL Entity has not intimated disapproval of such plan, section, description and timetable and the grounds of disapproval, such RRRL Entity is deemed to have approved the said plan, section description and timetable as submitted.
- (3) When giving its approval under sub-paragraph (1), a RRRL Entity may specify such reasonable requirements which in such RRRL Entity’s opinion are necessary in the execution of the works.
- (4) The works described in sub-paragraph (1) must be executed only in accordance with the plan, section, description and timetable submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be given in accordance with sub-paragraph (3) by the RRRL Entity. Where a RRRL Entity reasonably requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to such RRRL Entity’s reasonable satisfaction prior to the works described in sub-paragraph (1).
- (5) In the event that a RRRL Entity issues a disapproval to the plan, section, description and timetable within the 28 day period referred to in sub-paragraph (1), the undertaker may refer the matter to arbitration in accordance with article 49 (arbitration).
- (6) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan, section and description instead of the plan, section and description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section and description.
- (7) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency works (as defined in the 1991 Act) but in that case it must give to each RRRL Entity notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonably practicable subsequently and must comply with sub-paragraphs (3) and (4) in so far as is reasonably practicable in the circumstances.
126
- (1) Subject to the following provisions of this paragraph, the undertaker must repay to each RRRL Entity the reasonable expenses incurred by such RRRL Entity in, or in connection with, the inspection, removal, alteration or protection of any apparatus within the RRRL land or the provision or construction of any alternative apparatus which such RRRL Entity elects to carry out itself as referred to in paragraph 123(8).
- (2) There is to be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule, that value being calculated after removal.
- (3) If in accordance with the provisions of this Part of this Schedule—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated, and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 49 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to a RRRL Entity by virtue of sub-paragraph (1) will be reduced by the amount of that excess.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus where such extension is required in consequence of the execution of any such works as are referred to in paragraph 123(2); and
- (b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
- (5) An amount which apart from this sub-paragraph would be payable to a RRRL Entity in respect of works by virtue of sub-paragraph (1) if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on a RRRL Entity any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, is to be reduced by the amount which represents that benefit.
127
Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and any RRRL Entity in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
128
Where in consequence of the proposed construction or maintenance of any part of the authorised development, the undertaker or any RRRL Entity requires the removal of apparatus or any RRRL Entity makes requirements for the protection or alteration of apparatus, the undertaker shall use its reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution and maintenance of the authorised development and taking into account the need to ensure the safe and efficient operation of each RRRL Entity’s undertaking and each RRRL Entity shall use its reasonable endeavours to co-operate with the undertaker for that purpose.
129
If in consequence of any agreement reached or the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable each RRRL Entity to maintain or use the apparatus no less effectively than was possible before such obstruction.
130
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works authorised by this Part of this Schedule or in consequence of the construction, use, maintenance or failure of any part of the authorised development by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by the undertaker) in the course of carrying out such works, use or maintenance, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised development) or property of any RRRL Entity, or there is any interruption in any service provided, or in the supply of any goods, by any RRRL Entity, or any RRRL Entity becomes liable to pay any amount to any third party, the undertaker will—
- (a) bear and pay on demand the cost reasonably incurred by such RRRL Entity in making good such damage or restoring the supply; and
- (b) indemnify such RRRL Entity for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from such RRRL Entity, by reason or in consequence of any such damage or interruption or such RRRL Entity becoming liable to any third party as aforesaid other than arising from any default of such RRRL Entity.
- (2) The fact that any act or thing may have been done by a RRRL Entity on behalf of the undertaker or in accordance with a plan approved by such RRRL Entity or in accordance with any requirement of such RRRL Entity or under its supervision will not (unless sub-paragraph (3) applies), excuse the undertaker from liability under the provisions of this sub-paragraph (2) unless such RRRL Entity fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan or as otherwise agreed between the undertaker and such RRRL Entity.
- (3) Nothing in sub-paragraph (1) shall impose any liability on the undertaker in respect of—
- (a) any damage or interruption to the extent that it is attributable to the neglect or default of such RRRL Entity, its officers, servants, contractors or agents; and
- (b) any part of the authorised development and/or any other works authorised by this Part of this Schedule carried out by such RRRL Entity whether pursuant to article 9 (benefit of this Order) or as an assignee, transferee or lessee of a person with the benefit of the Order pursuant to section 156 (benefit of order granting development consent) of the Planning Act 2008 or article 10 (consent to transfer benefit of the Order) subject to the proviso that once such works become apparatus, any part of the authorised development yet to be executed and not falling within this sub-section 130(3)(b) will be subject to the full terms of this Part of this Schedule including this paragraph 130.
- (4) Each RRRL Entity must give the undertaker reasonable notice of any such third party claim or demand and no settlement or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and considering their representations.
- (5) Each RRRL Entity must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph 130 applies. If requested to do so by the undertaker, the applicable RRRL Entity shall provide an explanation of how the claim has been minimised. The undertaker shall only be liable under this paragraph 130 for claims reasonably incurred by a RRRL Entity.
SCHEDULE 13 — DOCUMENTS AND PLANS TO BE CERTIFIED
| (1) Document name | (2) Document reference | (3) Revision number | (4) Date |
|---|---|---|---|
| access and rights of way plan | 2.4 | P03 | September 2024 |
| book of reference | 4.3 | Rev H | May 2025 |
| design principles and design code | 5.7 | Rev E | March 2025 |
| environmental statement | environmental statement 6.1 (excluding chapters 2, 4, 5, 7, 8, 9, 11, 14, 19, 21 and 22) | Rev A | March 2024 |
| environmental statement | environmental statement 6.1 Chapter 2 | Rev B | April 2025 |
| environmental statement | environmental statement 6.1 Chapter 4 | Rev B | April 2025 |
| environmental statement | environmental statement 6.1 Chapter 5 | Rev B | April 2025 |
| environmental statement | environmental statement 6.1 Chapter 7 | Rev B | April 2025 |
| environmental statement | environmental statement 6.1 Chapter 8 | Rev B | April 2025 |
| environmental statement | environmental statement 6.1 Chapter 9 | Rev B | April 2025 |
| environmental statement | environmental statement 6.1 Chapter 11 | Rev B | April 2025 |
| environmental statement | environmental statement 6.1 Chapter 14 | Rev B | April 2025 |
| environmental statement | environmental statement 6.1 Chapter 19 | Rev B | April 2025 |
| environmental statement | environmental statement 6.1 Chapter 21 | Rev B | April 2025 |
| environmental statement | environmental statement 6.1 Chapter 22 | Rev B | April 2025 |
| environmental statement | environmental statement 6.2 (excluding figures 3.3, 7.4, 7.10 and 11.2) | Rev A | March 2024 |
| environmental statement | environmental statement 6.2 (figure 3.3) | Rev B | September 2024 |
| environmental statement | environmental statement 6.2 (figure 7.4) | Rev B | April 2025 |
| environmental statement | environmental statement 6.2 (figure 7.10) | Rev B | April 2025 |
| environmental statement | environmental statement 6.2 (figure 11.2) | Rev B | April 2025 |
| environmental statement | environmental statement 6.3 (excluding appendices 2.1, 4.2, 5.2, 5.3, 5.4, 7.8, 7.9, 10.4, 11.1, 11.2, 11.4 and 19.1) | Rev A | March 2024 |
| environmental statement | environmental statement 6.3 (appendix 2.1) | Rev C | February 2025 |
| environmental statement | environmental statement 6.3 (appendix 4.2) | Rev B | April 2025 |
| environmental statement | environmental statement 6.3 (appendix 5.2) | Rev B | April 2025 |
| environmental statement | environmental statement 6.3 (appendix 5.3) | Rev B | April 2025 |
| environmental statement | environmental statement 6.3 (appendix 5.4) | Rev B | April 2025 |
| environmental statement | environmental statement 6.3 (appendix 7.8) | Rev B | April 2025 |
| environmental statement | environmental statement 6.3 (appendix 7.9) | Rev B | April 2025 |
| environmental statement | environmental statement 6.3 (appendix 11.1) | Rev B | April 2025 |
| environmental statement | environmental statement 6.3 (appendix 11.2) | Rev B | September 2024 |
| environmental statement | environmental statement 6.3 (appendix 11.4) | Rev B | April 2025 |
| environmental statement | environmental statement 6.3 (appendix 19.1) | Rev E | April 2025 |
| environmental statement | environmental statement 6.3 (appendix 10.4) | Rev B | January 2025 |
| extended crossness local nature reserve plan | 2.9 | P04 | January 2025 |
| flood risk assessment | 6.3 Appendix 11.2 | Rev B | September 2024 |
| framework construction traffic management plan | 7.7 | Rev E | March 2025 |
| land plans | 2.2 | P05 | February 2025 |
| mitigation schedule | 7.8 | Rev B | November 2024 |
| outline landscape, biodiversity, access and recreation delivery strategy | 7.9 | Rev H | October 2025 |
| outline code of construction practice | 7.4 | Rev E | March 2025 |
| outline drainage strategy | 7.2 | Rev C | April 2025 |
| outline emergency preparedness and response plan | 7.11 | Rev C | April 2025 |
| outline lighting strategy | 7.3 | Rev B | March 2025 |
| outline site waste management plan | 7.10 | Rev B | April 2025 |
| outline skills and employment plan | 9.15 | Rev A | December 2024 |
| preliminary navigation risk assessment | 6.3 Appendix 19.1 | Rev E | April 2025 |
| traffic regulation measures plan | 2.6 | P03 | September 2024 |
| works plans | 2.3 | P08 | April 2025 |
SCHEDULE 14 — PROCEDURE IN RELATION TO CERTAIN APPROVALS ETC.
Interpretation
1
In this Schedule—
- “the appeal parties” means the relevant authority, the undertaker and any requirement consultees;
- “business day” means a day other than a Saturday or Sunday which is not Christmas Day, Good Friday or a bank holiday under section 1 of the Banking and Financial Dealings Act 1971[^f00084];
- “relevant authority” means the relevant planning authority, relevant highway authority, relevant traffic authority, relevant street authority, or the owner of a watercourse, sewer or drain as may be appropriate to the consent, agreement or approval sought; and
- “requirement consultee” means any body named in a requirement as a body to be consulted by the relevant planning authority in discharging that requirement.
Applications made for consent, agreement or approval
2
- (1) Subject to article 48(2) (procedures in relation to certain approvals etc.), where an application has been made to the relevant authority for any consent, agreement or approval required or contemplated by any provisions of this Order, including—
- (a) consent, agreement or approval in respect of part of a requirement;
- (b) any consent, agreement or approval required by any of the documents listed in Schedule 13 (documents and plans to be certified);
- (c) documents approved pursuant to a requirement; or
- (d) consent sought under section 61 (prior consent for work on construction sites) of the Control of Pollution Act 1974,
the relevant authority must give notice to the undertaker of its decision on the application within a period of nine weeks beginning with—
- (i) the day immediately following that on which the application is received by the relevant authority;
- (ii) the day immediately following that on which further information has been supplied by the undertaker under paragraph 3; or
- (iii) such longer period as may be agreed in writing by the undertaker and the relevant authority.
- (2) Subject to sub-paragraph (4), in the event that the relevant authority does not determine an application within the period set out in sub-paragraph (1), the relevant authority is to be taken to have granted all parts of the application (without any condition or qualification) at the end of that period.
- (3) Where an application is made to the relevant authority for any consent, agreement or approval required by a requirement included in this Order, it must be accompanied by a report which states whether the subject matter of the application will give rise to any materially new or materially different environmental effects to those identified in the environmental statement.
- (4) Where an application has been made to the relevant authority for any consent, agreement or approval required by a requirement included in this Order, and—
- (a) the relevant authority does not determine the application within the period set out in sub-paragraph (1) and such application is accompanied by a report which states that the subject matter of such application is likely to give rise to any materially new or materially different environmental effects to those in the environmental statement; or
- (b) the relevant authority determines during the period set out in sub-paragraph (1) that it considers that the subject matter of such application will give rise to any materially new or materially different environmental effects to those in the environmental statement,
the application is to be taken to have been refused by the relevant authority at the end of that period.
Further information and consultation
3
- (1) In relation to any application to which this Schedule applies, the relevant authority has the right to request such reasonable further information from the undertaker as is necessary to enable it to consider the application.
- (2) In the event that the relevant authority considers such further information to be necessary and the provision of the Order governing or requiring the application does not specify that consultation with a requirement consultee is required, the relevant authority must, within ten business days of receipt of the application, notify the undertaker in writing specifying the further information required.
- (3) If the provision of the Order governing or requiring the application specifies that consultation with a requirement consultee is required, the relevant authority must issue the consultation to the requirement consultee within five business days of receipt of the application, and must notify the undertaker in writing specifying any further information requested by the requirement consultee within five business days of receipt of such a request and in any event within ten business days of receipt of the application.
- (4) In the event that the relevant authority does not give notification as specified in sub-paragraph (2) or (3) it is to be deemed to have sufficient information to consider the application and is not subsequently entitled to request further information without the prior agreement of the undertaker.
Anticipatory steps towards compliance with any requirement
4
If before the coming into force of this Order the undertaker or any other person has taken any steps that were intended to be steps towards compliance with any provision of Schedule 2, those steps may be taken into account for the purpose of determining compliance with that provision if they would have been valid steps for that purpose had they been taken after this Order came into force.
Appeals
5
- (1) The undertaker may appeal in the event that—
- (a) the relevant authority refuses (including a deemed refusal pursuant to paragraph 2(4)) an application for any consent, agreement or approval referred to in paragraph 2 of this Schedule 14 or grants it subject to conditions;
- (b) the relevant authority refuses an application for a permit under a permit scheme, or grants such a permit subject to conditions;
- (c) the relevant authority issues a notice to the undertaker under section 60 (control of noise on construction sites) of the Control of Pollution Act 1974;
- (d) on receipt of a request for further information pursuant to paragraph 3 the undertaker considers that either the whole or part of the specified information requested by the relevant authority is not necessary for consideration of the application; or
- (e) on receipt of any further information requested, the relevant authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application.
- (2) The appeal process is to be as follows—
- (a) any appeal by the undertaker must be made within 42 days of the date of the notice of the decision or determination or request, or (where paragraph 2(4) applies) expiry of the decision period as determined under paragraph 2(1);
- (b) the undertaker must submit the appeal documentation to the Secretary of State and must on the same day provide copies of the appeal documentation to the appeal parties;
- (c) as soon as is practicable following receipt of the appeal documentation, the Secretary of State is to appoint a person to determine the appeal (“the appointed person”) and must notify the appeal parties of the identity of the appointed person and the address to which all correspondence for that person’s attention must be sent, the date of such notification being the “start date” for the purposes of this sub-paragraph (2);
- (d) the relevant authority and any requirement consultee must submit written representations to the appointed person in respect of the appeal within ten business days of the start date and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;
- (e) the appeal parties must make any counter-submissions to the appointed person within ten business days of receipt of written representations pursuant to sub-paragraph (d); and
- (f) the appointed person must decide the appeal and notify the appeal parties of the decision, with reasons, as soon as reasonably practicable and in any event within 30 business days of the deadline for the receipt of counter-submissions pursuant to sub-paragraph (e).
- (3) The appointment of the person pursuant to sub-paragraph (2)(c) may be undertaken by a person appointed by the Secretary of State for this purpose instead of by the Secretary of State.
- (4) If the appointed person considers that further information is necessary to enable consideration of the appeal the appointed person must, within five business days of his appointment, notify the appeal parties in writing specifying the further information required, the appeal part from whom the information is sought, and the date by which the information is to be submitted.
- (5) Any further information required pursuant to sub-paragraph (4) is to be provided by the party from whom the information is sought to the appointed person and to the other appeal parties by the date specified by the appointed person (the “specified date”), and the appointed person must notify the appeal parties of the revised timetable for the appeal on or before that day. The revised timetable for the appeal must require submission of written representations to the appointed person within ten business days of the specified date but otherwise is to be in accordance with the process and time limits set out in sub-paragraphs (2)(d) to (2)(f).
- (6) On an appeal under this paragraph, the appointed person may—
- (a) allow or dismiss the appeal, or
- (b) reverse or vary any part of the decision of the relevant authority (whether the appeal relates to that part of it or not),
and may deal with the application as if it had been made to the appointed person in the first instance.
- (7) The appointed person may proceed to a decision on an appeal taking into account only such written representations as have been sent within the prescribed time limits, or set by the appointed person, under this paragraph.
- (8) The appointed person may proceed to a decision even though no written representations have been made within the prescribed time limits, if it appears to him that there is sufficient material to enable a decision to be made on the merits of the case.
- (9) The decision of the appointed person on an appeal is to be final and binding on the appeal parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review.
- (10) If an approval is given by the appointed person pursuant to this Schedule, it is deemed to be an approval for the purpose of any consent, agreement or approval required under the Order or for the purpose of Schedule 2 (requirements) as if it had been given by the relevant authority. The relevant authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) is not to be taken to affect or invalidate the effect of the appointed person’s determination.
- (11) The appointed person may or may not be a member of the Planning Inspectorate but must be a qualified town planner of at least ten years’ experience.
- (12) Save where a direction is given pursuant to sub-paragraph (13) requiring the costs of the appointed person to be paid by the relevant authority, the reasonable costs of the appointed person must be met by the undertaker.
- (13) On application by the relevant authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction and the terms on which it is to be made, the appointed person must have regard to Planning Practice Guidance: Appeals (March 2014), published by the Ministry of Housing, Communities & Local Government, or any circular or guidance which may from time to time replace it.
Application to protective provisions
6
Nothing in this Schedule applies to any consent, agreement or approval required or contemplated by Schedule 12 (protective provisions) or article 23(6) (protective works to buildings).
SCHEDULE 15 — ARBITRATION RULES
Commencing an arbitration
1
- (1) The primary objective of these arbitration rules is to achieve a fair, impartial, final and binding award on the substantive difference between the parties (save as to costs) within four months from the date the arbitrator is appointed pursuant to article 49 of this Order (arbitration).
- (2) The arbitration is deemed to have commenced when a party (“the claimant”) serves a written notice of arbitration on the other party (“the respondent”).
Time periods
2
- (1) All time periods in these arbitration rules are measured in days and include weekends, but not bank or public holidays.
- (2) Time periods are calculated from the day after the arbitrator is appointed which is either—
- (a) the date the arbitrator notifies the parties in writing of his/her acceptance of an appointment by agreement of the parties; or
- (b) the date the arbitrator is appointed by the Secretary of State.
Timetable
3
- (1) The timetable for the arbitration is that which is set out in sub-paragraphs (2) to (4) below unless amended in accordance with paragraph 5(3).
- (2) Within 14 days of the arbitrator being appointed, the claimant must provide both the respondent and the arbitrator with—
- (a) a written statement of claim which describes the nature of the difference between the parties, the legal and factual issues, the claimant’s contentions as to those issues, the amount of its claim or the remedy it is seeking;
- (b) all statements of evidence and copies of all documents on which it relies, including contractual documentation, correspondence (including electronic documents), legal precedents and expert witness reports.
- (3) Within 14 days of receipt of the claimant’s statements under sub-paragraph (2) by the arbitrator and respondent, the respondent must provide the claimant and the arbitrator with—
- (a) a written statement of defence consisting of a response to the claimant’s statement of claim, its statement in respect of the nature of the difference, the legal and factual issues in the claimant’s claim, its acceptance of any elements of the claimant’s claim and its contentions as to those elements of the claimant’s claim it does not accept;
- (b) all statements of evidence and copies of all documents on which it relies, including contractual documentation, correspondence (including electronic documents), legal precedents and expert witness reports;
- (c) any objection it wishes to make to the claimant’s statements, comments on the claimant’s expert reports (if submitted by the claimant) and explanations of the objections.
- (4) Within seven days of the respondent serving its statements under sub-paragraph (3), the claimant may make a statement of reply by providing both the respondent and the arbitrator with—
- (a) a written statement responding to the respondent’s submissions, including its reply in respect of the nature of the difference, the issues (both factual and legal) and its contentions in relation to the issues;
- (b) all statements of evidence and copies of documents in response to the respondent’s submissions;
- (c) any expert report in response to the respondent’s submissions;
- (d) any objections to the statements of evidence, expert reports or other documents submitted by the respondent; and
- (e) its written submissions in response to the legal and factual issues involved.
Procedure
4
- (1) The parties’ pleadings, witness statements and expert reports (if any) must be concise. A single pleading must not exceed 30 single-sided A4 pages using 10pt Arial font.
- (2) The arbitrator must make an award on the substantive differences based solely on the written material submitted by the parties unless the arbitrator decides that a hearing is necessary to explain or resolve any matters.
- (3) Either party may, within two days of delivery of the last submission, request a hearing giving specific reasons why it considers a hearing is required.
- (4) Within seven days of receiving the last submission, the arbitrator must notify the parties whether a hearing is to be held and the length of that hearing.
- (5) Within ten days of the arbitrator advising the parties that a hearing is to be held, the date and venue for the hearing are to be fixed by agreement with the parties, save that if there is no agreement the arbitrator must direct a date and venue which the arbitrator considers is fair and reasonable in all the circumstances. The date for the hearing must not be less than 35 days from the date of the arbitrator’s direction confirming the date and venue of the hearing.
- (6) A decision must be made by the arbitrator on whether there is any need for expert evidence to be submitted orally at the hearing. If oral expert evidence is required by the arbitrator, then any experts attending the hearing may be asked questions by the arbitrator.
- (7) There is to be no examination or cross-examination of experts, but the arbitrator must invite the parties to ask questions of the experts by way of clarification of any answers given by the experts in response to the arbitrator’s questions. Prior to the hearing in relation to the experts—
- (a) at least 28 days before a hearing, the arbitrator must provide a list of issues to be addressed by the experts;
- (b) if more than one expert is called, they must jointly confer and produce a joint report or reports within 14 days of the issues being provided; and
- (c) the form and content of a joint report must be as directed by the arbitrator and must be provided at least seven days before the hearing.
- (8) Within 14 days of a hearing or a decision by the arbitrator that no hearing is to be held the parties may by way of exchange provide the arbitrator with a final submission in connection with the matters in dispute and any submissions on costs. The arbitrator must take these submissions into account in the award.
- (9) The arbitrator may make other directions or rulings as considered appropriate in order to ensure that the parties comply with the timetable and procedures to achieve an award on the substantive difference within four months of the date on which the arbitrator is appointed, unless both parties otherwise agree to an extension to the date for the award.
- (10) If a party fails to comply with the timetable, procedure or any other direction then the arbitrator may continue in the absence of a party or submission or document, and may make a decision on the information before the arbitrator attaching the appropriate weight to any evidence submitted beyond any timetable or in breach of any procedure or direction.
- (11) The arbitrator’s award must include reasons. The parties must accept that the extent to which reasons are given must be proportionate to the issues in dispute and the time available to the arbitrator to deliver the award.
Arbitrator’s powers
5
- (1) The arbitrator has all the powers of the Arbitration Act 1996[^f00085], save where modified in this Schedule.
- (2) There must be no discovery or disclosure, except that the arbitrator has the power to order the parties to produce such documents as are reasonably requested by another party no later than the statement of reply, or by the arbitrator, where the documents are manifestly relevant, specifically identified and the burden of production is not excessive. Any application and orders are to be made by way of a Redfern Schedule without any hearing.
- (3) Any time limits fixed in accordance with this procedure or by the arbitrator may be varied by agreement between the parties, subject to any such variation being acceptable to and approved by the arbitrator. In the absence of agreement, the arbitrator may vary the timescales or procedure—
- (a) if the arbitrator is satisfied that a variation of any fixed time limit is reasonably necessary to avoid a breach of the rules of natural justice and then;
- (b) only for such a period that is necessary to achieve fairness between the parties.
- (4) On the date the award is made, the arbitrator will notify the parties that the award is completed, signed and dated, and that it is to be issued to the parties on receipt of cleared funds for the arbitrator’s fees and expenses.
Costs
6
- (1) The costs of the arbitration must include the fees and expenses of the arbitrator, the reasonable fees and expenses of any experts and the reasonable legal and other costs incurred by the parties for the arbitration.
- (2) Where the difference involves connected or interrelated issues, the arbitrator must consider the relevant costs collectively.
- (3) The final award must fix the costs of the arbitration and decide which of the parties are to bear them or in what proportion they are to be borne by the parties.
- (4) The arbitrator must award recoverable costs on the general principle that each party should bear its own costs, having regard to all material circumstances, including such matters as exaggerated claims or defences, the degree of success for different elements of the claims, claims that have incurred substantial costs, the conduct of the parties and the degree of success of a party.
Confidentiality
7
- (1) Hearings in this arbitration are to take place in private.
- (2) Materials, documents, awards, expert reports and any matters relating to the arbitration are confidential and must not be disclosed to any third party without prior written consent of the other party, save for any application to the courts or where disclosure is required under any legislative or regulatory requirement.
SCHEDULE 16 — DESIGN PARAMETERS
| (1) Component/Building/Area | (2) Works Area | (3) Maximum Number | (4) Maximum Height (m) of Component/ Building/ Area | (5) Maximum Height (m) | (6) Further Parameters |
|---|---|---|---|---|---|
| Direct Contact Cooler | 1A | 2 | 30 | 33 Above Ordnance Datum | - |
| Absorber Column(s) and Stack(s) | 1B | 2 combined Absorber Columns and Stacks or a maximum of 2 Absorber Columns and 2 Stacks | 110 | 113 Above Ordnance Datum | Minimum vertical distance between top of Absorber Column(s) and top of Stack(s) whether combined or separate – 30m Minimum height of the top of Stack(s) – 100m from development platform as built Where there are 2 Stacks: Maximum internal diameter of Stack associated with Riverside 1: 3.1m Maximum internal diameter of Stack associated with Riverside 2: 2.5m Where there is 1 Stack: Maximum internal diameter of Stack: 4.0m |
| Regenerator | 1A | 2 | 60 | 63 Above Ordnance Datum | - |
| Compression Plant | 1C | 2 | 45 | 48 Above Ordnance Datum | - |
| CO2 Dehydration | 1C | 2 | 25 | 28 Above Ordnance Datum | - |
| CO2 Liquefaction | 1C | 2 | 30 | 33 Above Ordnance Datum | - |
| CO2 Vents | 1C | 2 | 45 | 48 Above Ordnance Datum | - |
| LCO₂ Buffer Storage Area | 1D | 16 | 45 | 48 Above Ordnance Datum | - |
| Hybrid or Dry Cooling Tower | 1E | 2 | 32 | 35 Above Ordnance Datum | - |
| Water Treatment Plant and Wastewater Treatment Plant | 1E | 2 | 20 | 23 Above Ordnance Datum | - |
| Back Pressure Turbine and Generator | 1A | 2 | 35 | 38 Above Ordnance Datum | - |
| Insulated heat pipework and flue gas ducting | 2A(ii) and 2b(i) | - | 30 | 33 Above Ordnance Datum | - |
| Loading platform (not including topside infrastructure and equipment) | 4C | 1 | - | 11.5 Above Chart Datum | Maximum length of 40 metres Maximum width of 50 metres |
| Breasting Dolphins | 4B | 4 | - | 11.5 Above Chart Datum | - |
| Mooring Dolphins | 4B | 6 | - | 11.5 Above Chart Datum | Maximum length of 7 metres Maximum width of 7 metres |
| Access Trestle Start Point (not including topside infrastructure and equipment) | 4B | 1 | - | 20 Above Ordnance Datum | Maximum length of 335 metres Maximum width of 10 metres |
| LCO2 pipelines, piperacks and pipe bridges | 5 | - | 30 | 33 Above Ordnance Datum | - |
Signed
Signed by the authority of the Secretary of State for Energy Security and Net Zero
Vicky Dawe — Director, Energy Development — Department for Energy Security and Net Zero — 5th November 2025
Explanatory note
(This note is not part of the Order)
EXPLANATORY NOTE
This Order authorises Cory Environmental Holdings Limited as notified to the relevant planning authority pursuant to the provisions of this Order (referred to in this Order as the undertaker) to construct, operate, maintain and decommission a carbon capture facility and associated development.
A copy of the Order plans and the book of reference mentioned in this Order and certified in accordance with article 46 of this Order (certification of plans etc.) may be inspected free of charge during working hours at London Borough of Bexley, Civic Offices, 2 Watling Street, Bexleyheath, Kent DA6 7AT.
Footnotes
[^f00001]: 2008 c. 29. The relevant provisions of the 2008 Act are amended by Chapter 6 of Part 6 of, and Schedule 13 to, the Localism Act 2011 (c. 20) and by sections 22 to 27 of the Growth and Infrastructure Act 2013 (c. 27). Transitional provisions are contained in S.I. 2013/1124.
[^f00002]: S.I. 2010/103, amended by S.I. 2012/635.
[^f00003]: 2008 c. 29. Section 83 was amended by paragraphs 35(2) and 35(3) of schedule 13(1) and paragraph 1 of section 25(20) to the Localism Act 2011 (c. 20).
[^f00004]: S.I. 2017/572.
[^f00005]: 2008 c. 29. Section 127 was amended by sections 23(2)(a) to (c) of the Growth and Infrastructure Act 2013 (c. 27) and by paragraphs 64(1) and (2) of Schedule 13(1) and paragraph 1 of Schedule 25 to the Localism Act 2011 (c. 20).
[^f00006]: As amended by paragraph 55 of Part 1 of Schedule 13 to the Localism Act 2011.
[^f00007]: As amended by section 160 of the Housing and Planning Act 2016 (c. 22) and section 43 of the Wales Act 2017 (c. 4).
[^f00008]: As amended by section 140 of, and paragraph 60 of Part 1 of Schedule 13 to, the Localism Act 2011.
[^f00009]: As amended by paragraph 62 of Part 1 of Schedule 13 to the Localism Act 2011.
[^f00011]: Section 149A was inserted by paragraph 4(1) of Part 1 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23).
[^f00012]: 1961 c. 33.
[^f00013]: 1965 c. 56.
[^f00014]: 1968 c. xxxii.
[^f00015]: 1980 c. 66.
[^f00016]: 1981 c. 66.
[^f00017]: 1984 c. 27.
[^f00018]: 1990 c. 8.
[^f00019]: 1991 c. 22.
[^f00020]: 2008 c. 29.
[^f00021]: 2009 c. 23.
[^f00022]: S.I. 2016/1154.
[^f00023]: 2010 c. 29.
[^f00024]: 1981 c. 67. Section 7 was amended by paragraph 9 of Schedule 15(I) to the Planning and Compensation Act 1991 (c. 34). There are other amendments to this section which are not relevant to this Order.
[^f00025]: S.I. 2012/3102.
[^f00026]: 2004 c. 18.
[^f00027]: 1987 c. 21.
[^f00028]: S.I. 2020/419, which was amended by the Riverside Energy Park (Correction) Order 2021 (S.I. 2021/273) and the Riverside Energy Park (Amendment) Order 2023 (S.I. 2023/165).
[^f00029]: 2003 c. 21.
[^f00030]: 1991 c. 59. Section 23 was amended by paragraph 192(2) of Schedule 22 to the Environment Act 1995 (c. 25), paragraphs 25 and 32 of Schedule 2 to the Flood and Water Management Act 2010 (c. 29) and S.I. 2013/755.
[^f00031]: Section 32 was amended by S.I. 2013/755.
[^f00032]: Section 66 was amended by paragraphs 25 and 38 of Schedule 2 to the Flood and Water Management Act 2010 and section 86 of the Water Act 2014 (c. 21).
[^f00033]: 1991 c. 57. Paragraph 5 was amended by section 100 of the Natural Environment and Rural Communities Act 2006 (c. 16), section 84 of, and paragraph 3 of Schedule 11 to, the 2009 Act and S.I. 2013/755. Paragraph 6 was amended by section 105 of, and paragraph 26 of Schedule 15 to, the Environment Act 1995, sections 224, 233 and 321 of, and paragraphs 20 and 24 of Schedule 16 and Part 5(B) of Schedule 22 to, the 2009 Act and S.I. 2013/755. Paragraph 6A was inserted by section 103(3) of the Environment Act 1995.
[^f00034]: S.I. 2016/1154. Regulation 12 was amended by S.I. 2018/110.
[^f00035]: 2017 c. 20.
[^f00036]: 2023 c. 52.
[^f00037]: 1989 c. 29.
[^f00038]: 2023 c. 52.
[^f00039]: 1988 c. 52.
[^f00040]: Section 53 was amended by Schedule 5 to the Countryside and Rights of Way Act 2000 (c. 37) and by section 70(1) of the Natural Environment and Rural Communities Act 2006 (c. 16).
[^f00041]: Section 66 was amended by sections 1, 2 and 7 of, and paragraph 7(6) of Schedule 3 to, the Local Government Act 1985. There are other amendments to this section that are not relevant to this Order.
[^f00042]: S.I. 2016/362.
[^f00043]: S.I. 2016/362.
[^f00044]: S.I. 2011/935.
[^f00045]: 2004 c. 18. There are amendments to this Act not relevant to this Order.
[^f00046]: 1991 c. 56. Section 106 was amended by sections 43(2) and 35(8)(a) of and paragraph 1 of Schedule 2 to, the Competition and Service (Utilities) Act 1992 (c. 43) and sections 99(2), (4), (5)(a), (5)(b), (5)(c) and 36(2) of the Water Act 2003 (c. 37).
[^f00047]: 1964 c. 40.
[^f00048]: 1991 c. 57, as amended by S.I. 2009/3104.
[^f00049]: The functions of the Lands Tribunal under the 1961 Act are transferred to the Upper Tribunal under the Tribunals, Courts and Enforcement Act 2007 (c. 15).
[^f00050]: 1995 c. 21.
[^f00051]: Inserted by section 182(2) of the Housing and Planning Act 2016.
[^f00052]: Inserted by section 202(2) of the Housing and Planning Act 2016.
[^f00053]: Inserted by paragraph 6 of Schedule 18 to the Housing and Planning Act 2016.
[^f00054]: Inserted by section 202(1) of the Housing and Planning Act 2016.
[^f00055]: Inserted by section 186(3) of the Housing and Planning Act 2016.
[^f00056]: Inserted by schedule 17(1) paragraph 3 of the Housing and Planning Act 2016.
[^f00057]: 2003 c. 21. Section 151(1) was amended by paragraphs 90(a)(i), (ii), (iii), 90(b), 90(c) and 90(d) of Schedule 1 to the Electronic Communications and Wireless Telegraphy Regulations 2011 (S.I. 2011/1210).
[^f00058]: S.I. 2011/934.
[^f00059]: 1990 c. 43. Section 82 was amended by section 103 of the Clean Neighbourhoods and Environment Act 2005 (c. 16); section 79 was amended by sections 101 and 102 of the same Act. There are other amendments not relevant to this Order.
[^f00060]: 1974 c. 40.
[^f00061]: 1978 c. 30.
[^f00062]: 1949 c. 97.
[^f00063]: 1967 c. 10. Relevant amendments to section 9 have been made by section 4 of, and Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11).
[^f00064]: 2010 c. 29.
[^f00065]: 1855 c. clxii.
[^f00066]: 1866 c. xlvi.
[^f00067]: 1879 c. cxcviii
[^f00068]: 1881 c. cxlii.
[^f00069]: 1891 c. lxxiv.
[^f00070]: 1901 c. xvii.
[^f00071]: 1957 c. xxxv.
[^f00072]: 1961 c. xliii.
[^f00073]: 1962 c. xlv.
[^f00074]: 1970 c. lxxvi.
[^f00075]: 1972 c. xlv.Section 3(1) and section 25(5)(a) were amended by the Thames Barrier and Flood Prevention Act 1972 (Amendment) Order 1986.
[^f00076]: 1986 c. iv.
[^f00077]: 2013 c. v.
[^f00078]: 1973 c. 26.
[^f00079]: 1971 c. 80.
[^f00080]: 1989 c. 29.
[^f00081]: 1991 c. 56.
[^f00082]: 1986 c. 44. A new section 7 was substituted by section 5 of the Gas Act 1995 (c. 45), and was further amended by section 76 of the Utilities Act 2000 (c. 27).
[^f00083]: 2003 c. 21.
[^f00084]: 1971 c. 80.
[^f00085]: 1996 c. 23.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.