The Helios Renewable Energy Project Order 2025

Type Statutory-Instrument
Publication 2025-12-03
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • (b) all statements of evidence and copies of all documents on which it relies, including contractual documentation, correspondence (including electronic documents), legal precedents and expert witness reports.
  • (3) Within 14 days of receipt of the claimant’s statements under sub-paragraph (2) by the arbitrator and respondent, the respondent will provide the claimant and the arbitrator with—
  • (a) a written statement of defence responding to the claimant’s statement of claim, its statement in respect of the nature of the difference, the legal and factual issues in the claimant’s claim, its acceptance of any element(s) of the claimant’s claim, its contentions as to those elements of the claimant’s claim it does not accept;
  • (b) all statements of evidence and copies of all documents on which it relies, including contractual documentation, correspondence (including electronic documents), legal precedents and expert witness reports;
  • (c) any objections it wishes to make to the claimant’s statements, comments on the claimant’s expert report(s) (if submitted by the claimant) and explanations of the objections.
  • (4) Within 7 days of the respondent serving its statements under sub-paragraph (3), the claimant may make a statement of reply by providing both the respondent and the arbitrator with—
  • (a) a written statement responding to the Respondent’s submissions, including its reply in respect of the nature of the difference, the issues (both factual and legal) and its contentions in relation to the issues;
  • (b) all statements of evidence and copies of documents in response to the Respondent’s submissions;
  • (c) any expert report in response to the Respondent’s submissions;
  • (d) any objections to the statements of evidence, expert reports or other documents submitted by the Respondent;
  • (e) its written submissions in response to the legal and factual issues involved.

Procedure

4

  • (1) The parties’ pleadings, witness statements and expert reports (if any) will be concise. No single pleading will exceed 30 single sided A4 pages using 10pt Arial font.
  • (2) The arbitrator will make an award on the substantive difference(s) based solely on the written material submitted by the parties unless the arbitrator decides that a hearing is necessary to explain or resolve any matters.
  • (3) Either party may, within 2 days of delivery of the last submission, request a hearing giving specific reasons why it considers a hearing is required.
  • (4) Within 7 days of receiving the last submission, the arbitrator will notify the parties whether a hearing is to be held and the length of that hearing.
  • (5) Within 10 days of the arbitrator advising the parties that they will hold a hearing, the date and venue for the hearing will be fixed by agreement with the parties, save that if there is no agreement the arbitrator is to direct a date and venue which they consider is fair and reasonable in all the circumstances. The date for the hearing must not be less than 35 days from the date of the arbitrator’s direction confirming the date and venue of the hearing.
  • (6) A decision will be made by the arbitrator on whether there is any need for expert evidence to be submitted orally at the hearing. If oral expert evidence is required by the arbitrator, then any expert(s) attending the hearing may be asked questions by the arbitrator.
  • (7) There will be no process of examination and cross-examination of experts, but the arbitrator must invite the parties to ask questions of the experts by way of clarification of any answers given by the expert(s) in response to the arbitrator’s questions. Prior to the hearing the procedure for the expert(s) will be that—
  • (a) at least 28 days before a hearing, the arbitrator will provide a list of issues to be addressed by the expert(s);
  • (b) if more than one expert is called, they will jointly confer and produce a joint report or reports within 14 days of the issues being provided; and
  • (c) the form and content of a joint report must be as directed by the arbitrator and must be provided at least 7 days before the hearing.
  • (8) Within 14 days of a hearing or a decision by the arbitrator that no hearing is to be held, the parties may by way of exchange provide the arbitrator with a final submission in connection with the matters in dispute and any submissions on costs. The arbitrator must take these submissions into account in the award.
  • (9) The arbitrator may make other directions or rulings as considered appropriate in order to ensure that the parties comply with the timetable and procedures to achieve an award on the substantive difference within 4 months of the date on which they are appointed, unless both parties otherwise agree to an extension to the date for the award.
  • (10) If a party fails to comply with the timetable, procedure or any other direction then the arbitrator may continue in the absence of a party or submission or document, and may make a decision on the information before him/her attaching the appropriate weight to any evidence submitted beyond any timetable or in breach of any procedure and/or direction.
  • (11) The arbitrator’s award must include reasons. The parties must accept that the extent to which reasons are given must be proportionate to the issues in dispute and the time available to the arbitrator to deliver the award.

Arbitrator’s powers

5

  • (1) The arbitrator has all the powers of the Arbitration Act 199641, including the non-mandatory sections, save where modified by these Rules in this Schedule.
  • (2) There must be no discovery or disclosure, except that the arbitrator is to have the power to order the parties to produce such documents as are reasonably requested by another party no later than the Statement of Reply, or by the arbitrator, where the documents are manifestly relevant, specifically identified and the burden of production is not excessive. Any application and orders should be made by way of a Redfern Schedule without any hearing.
  • (3) Any time limits fixed in accordance with this procedure or by the arbitrator may be varied by agreement between the parties, subject to any such variation being acceptable to and approved by the arbitrator. In the absence of agreement, the arbitrator may vary the timescales and/or procedure—
  • (a) if the arbitrator is satisfied that a variation of any fixed time limit is reasonably necessary to avoid a breach of the rules of natural justice and then;
  • (b) only for such a period that is necessary to achieve fairness between the parties.
  • (4) On the date the award is made, the arbitrator will notify the parties that the award is completed, signed and dated, and that it will be issued to the parties on receipt of cleared funds for the arbitrator’s fees and expenses.

Costs

6

  • (1) The costs of the arbitration must include the fees and expenses of the arbitrator, the reasonable fees and expenses of any experts and the reasonable legal and other costs incurred by the parties for the arbitration.
  • (2) Where the difference involves connected/interrelated issues, the arbitrator will consider the relevant costs collectively.
  • (3) The final award must fix the costs of the arbitration and decide which of the parties are to bear them or in what proportion they are to be borne by the parties.
  • (4) The arbitrator will award recoverable costs on the general principle in paragraph (3) that each party should bear its own costs, having regard to all material circumstances, including such matters as exaggerated claims and/or defences, the degree of success for different elements of the claims, claims that have incurred substantial costs, the conduct of the parties and the degree of success of a party.

Confidentiality

7

  • (1) Subject to sub-paragraphs (2) and (3), any arbitration hearing and documentation is to be open to and accessible by the public.
  • (2) The arbitrator may direct that the whole or part of a hearing is to be private or any documentation to be confidential where it is necessary in order to protect commercially sensitive information.
  • (3) Nothing in this paragraph prevents any disclosure of a document by a party pursuant to an order of a court in England and Wales or where disclosure is required under any enactment.

SCHEDULE 11 — DOCUMENTS TO BE CERTIFIED

(1) Document (2) Application Document Reference (3) Revision (4) Date
Access and rights of way plan 2.4 4 June 2024
Book of reference 4.1 B May 2025
Environmental statement Environmental Statement 6.1 (excluding Chapter 4) 0 June 2024
Environmental statement Environmental Statement 6.1 Chapter 4 1 June 2024
Environmental statement Environmental Statement 6.2 (excluding Figures 7.1-7.12) 0 June 2024
Environmental statement Environmental Statement 6.2 Figures 7.1-7.12 1 June 2024
Environmental statement Environmental Statement 6.3 (excluding Appendices 2.5, 3.1, 5.1, 5.2, 5.3, 5.4, 7.9, 8.8, 8.9, and 14.3) 0 June 2024
Environmental statement Environmental Statement 6.3 Appendix 2.5 8 February 2025
Environmental statement Environmental Statement 6.3 Appendix 8.8 A January 2025
Environmental statement Environmental Statement 6.3 Appendix 8.9 5 April 2025
Environmental statement Environmental Statement 6.3 Appendix 14.3 1 January 2025
Environmental statement Environmental Statement 6.4 1 June 2024
Flood risk assessment 7.5 3.1 April 2025
Land and crown plans 2.2 5 February 2025
Location and order limits plan 2.1 0 June 2024
Outline archaeological mitigation strategy 6.3.6.2 4 June 2024
Outline battery safety management plan 6.3.3.1 5 February 2025
Outline CEMP 6.3.5.1 4 May 2025
Outline CTMP 6.3.5.2 A February 2025
Outline design principles document 9.15 0 April 2025
Outline DEMP 6.3.5.3 2 April 2025
Outline LEMP 6.3.7.9 4 May 2025
Outline OEMP 6.3.5.4 2 April 2025
Outline soil resource management plan 6.3.14.3 1 January 2025
Outline supply chain, employment and skills plan 9.16 0 April 2025
Works plans 2.3 6 June 2024

Signed

Signed by authority of the Secretary of State for Energy Security and Net Zero

David Wagstaff — Deputy Director, Energy Infrastructure Planning — Department for Energy Security and Net Zero — 3rd December 2025

Explanatory note

(This note is not part of the Order)

EXPLANATORY NOTE

This Order grants development consent for, and authorises the construction, operation and maintenance of a solar generating station and battery energy storage facility on land within the Order limits together with associated development. This Order imposes requirements in connection with the development and authorises the compulsory acquisition of rights in land and the right to use land and to override easements and other rights.

A copy of the plans and book of reference referred to in this Order and certified in accordance with article 36 (certification of plans and documents, etc.) may be inspected free of charge during working hours at the undertaker’s registered office at 17th Floor Hylo 103-105 Bunhill Row, London, United Kingdom, EC1Y 8LZ as may be updated from time to time.

Footnotes

1

2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20). Section 37 was amended by sections 128(2) and 137 of, and paragraphs 1 and 5 of Part 1 of Schedule 13 to, the Localism Act 2011 (c. 20).

5

As amended by paragraph 55 of Part 1 of Schedule 13 to the Localism Act 2011.

6

As amended by paragraph 56 of Part 1 of Schedule 13 and Part 20 of Schedule 25 to the Localism Act 2011, section 160 of the Housing and Planning Act 2016 (c. 22) and section 43 of the Wales Act 2017 (c. 4).

7

As amended by section 140 of paragraph 60 of Part 1 of Schedule 13 to, the Localism Act 2011.

8

As amended by paragraph 62 of Part 1 of Schedule 13 to the Localism Act 2011.

9

Ibid.

19

“highway” is defined in section 328(1); for “highway authority” see section 1.

20

“street authority” is defined in section 49, which was amended by paragraph 117 of Schedule 1 to the Infrastructure Act 2015 (c. 7).

21

1990 c. 43. Section 82 was amended by section 103 of the Clean Neighbourhoods and Environment Act 2005 (c. 16); section 79 was amended by sections 101 and 102 of the same Act. There are other amendments not relevant to this Order.

25

Sections 55, 57, 60, 68, and 69 were amended by the Traffic Management Act 2004 (c. 18).

28

1991 c. 56. Section 106 was amended by section 35(8)(a) of the Competition and Service (Utilities) Act 1992 (c. 43) and section 99 of the Water Act 2003 (c. 37). There are other amendments to this section which are not relevant to this Order.

29

Section 5A was inserted by Section 182(2) of the Housing and Planning Act 2016 (c. 22).

30

Section 5B was inserted by Section 202(2) of the Housing and Planning Act 2016 (c. 22).

33

1974 c. 40. Section 61 was amended by Schedule 7 to the Building Act 1984 (c. 55), Schedule 15 to the Environmental Protection Act 1990 (c. 43) and Schedule 24 to the Environment Act 1995 (c. 25).

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.