SCHEDULE 7 — Events Of Re-Run

1

The events in this Schedule are—

SCHEDULE 8 — Events Of Cancellation

1

The events in this paragraph are—

2

The event in this paragraph is a change in circumstances that is likely to result in the interests of existing and future consumers being materially negatively affected if an onshore transmission licence is awarded at the conclusion of the onshore transmission tender exercise.

SCHEDULE 9 — Events Of Disqualification

1

The events in this Schedule in relation to bidder, qualifying bidder, provisional preferred bidder, preferred bidder, reserve bidder or successful bidder, as the case may be, are—

Signed

The seal of the Gas and Electricity Markets Authority here affixed is authenticated by the signature of

Mark McAllister — A member of the Gas and Electricity Markets Authority — 26th March 2025

Signed by authority of the Secretary of State for Energy Security and Net Zero

Michael Shanks — Parliamentary Under Secretary of State — Department of Energy Security and Net Zero — 3rd April 2025

Explanatory note

(This note is not part of the Regulations)

EXPLANATORY NOTE

Sections 6C-6CD of the Electricity Act 1989 (“the Act”) enable the Gas and Electricity Markets Authority (“the Authority”) to make regulations in respect of competitive tenders for a “relevant electricity project” as defined in section 6BA(1) of the Act. Projects competitively tendered under this instrument will be those where the design, construction and delivery of the project is to be tendered.

Tenders must be run by a “delivery body” with some key decision-making by the Authority in the tender process. The Authority is also responsible for conducting the licence application process in respect to the grant of a transmission licence to a “successful bidder” at the end of the tender exercise.

The competitive tender exercise comprises the following stages:

A full Impact Assessment was published alongside the Electricity (Designation of Delivery Bodies) (Transmission) Regulations 2023 (S.I 2023/1228) that covers the impacts of introducing a competitive tender process to the electricity onshore network, as now implemented by these Regulations. The impact assessment is available from the Department for Energy Security and Net Zero at 3-8 Whitehall Place, London, S1A 2EG and is published with the Electricity (Designation of Delivery Bodies) (Transmission) Regulations 2023 onlegislation.gov.uk.

Footnotes

[^f00001]: 1989 c.29. Sections 6C-6CD were substituted for section 6C and 6D by section 203 of, and paragraph 3 of Schedule 15 to, the Energy Act 2023 (c. 52).

[^f00002]: S.I. 2023/1228.

[^f00003]: 2000 c.7.

[^f00004]: 2000 c.36. Definition substituted by section 135(4) of the Energy Act 2004 (c. 20) for the purpose specified in article 2(1) of SI 2004/2184.

[^f00005]: 1989 c.29. Sections.6, 6A and 6B substituted for section 6 by Utilities Act 2000 (c. 27).

[^f00006]: S.I. 2024/168.

[^f00007]: S.I. 2024/168.

[^f00008]: 2010 c.23.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.