The Cambridge Waste Water Treatment Plant Relocation Order 2025

Type Statutory-Instrument
Publication 2025-04-02
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • (9) Nothing in this paragraph 27 precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of the authorised works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph 27 will apply to and in respect of the new plan.
  • (10) The undertaker will not be required to comply with sub-paragraph (1) where it needs to carry out emergency works as defined in the 1991 Act but in that case it must give to Cadent notice as soon as is reasonably practicable and a plan of those works and must comply with—
  • (a) the conditions imposed under sub-paragraph (4)(a) insofar as is reasonably practicable in the circumstances; and
  • (b) sub-paragraph (11) at all times.
  • (11) At all times when carrying out any works authorised under the Order the undertaker must comply with Cadent’s policies for safe working in proximity to gas apparatus “CD/SP/SSW/22 (Cadent’s policies for safe working in the vicinity of Cadent’s Assets” and HSE’s “HS(~G)47 Avoiding Danger from underground services”.
  • (12) As soon as reasonably practicable after any ground subsidence event attributable to the authorised development the undertaker will implement an appropriate ground mitigation scheme save that Cadent retains the right to carry out any further necessary works for the safeguarding of its apparatus and can recover any such costs in line with paragraph 28 of this Part of this Schedule.

Expenses

28

  • (1) Subject to the following provisions of this paragraph 28, the undertaker must pay to Cadent within 28 days of demand all charges, costs and expenses reasonably anticipated or incurred by Cadent in, or in connection with, the inspection, removal, relaying or replacing, alteration or protection of any apparatus or the construction of any new or alternative apparatus which may be required in consequence of the execution of any authorised works as are referred to in this Part of this Schedule including without limitation—
  • (a) any costs reasonably incurred by or compensation properly paid by Cadent in connection with the negotiation or acquisition of rights or the exercise of statutory powers for such apparatus including without limitation all costs (including professional fees) incurred by Cadent as a consequence of Cadent—
  • (i) using its own compulsory purchase powers to acquire any necessary rights under paragraph 25(3); and/or
  • (ii) exercising any compulsory purchase powers in the Order transferred to or benefitting Cadent;
  • (b) in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus;
  • (c) the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
  • (d) the approval of plans;
  • (e) the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works;
  • (f) the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule; and
  • (g) any watching brief pursuant to paragraph 27(6) of this Part of this Schedule.
  • (2) There will be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule and which is not re-used as part of the alternative apparatus, that value being calculated after removal.
  • (3) If in accordance with the provisions of this Part of this Schedule—
  • (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
  • (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with paragraph 33 of this Part of this Schedule to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph (3) would be payable to Cadent by virtue of sub-paragraph (1) will be reduced by the amount of that excess save where it is not possible or appropriate in the circumstances (including due to statutory or regulatory changes) to obtain the existing type of apparatus at the same capacity and dimensions or place at the existing depth in which case full costs will be borne by the undertaker.

  • (4) For the purposes of sub-paragraph (3)—
  • (a) an extension of apparatus to a length greater than the length of existing apparatus will not be treated as a placing of apparatus of greater dimension than those of the existing apparatus; and
  • (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole will be treated as if it also had been agreed or had been so determined.
  • (5) An amount which apart from this sub-paragraph (5) would be payable to Cadent in respect of works by virtue of sub-paragraph (1) will, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on Cadent any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.

Indemnity

29

  • (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works authorised by this Part of this Schedule (including without limitation relocation, diversion, decommissioning, construction and maintenance of apparatus or alternative apparatus) or in consequence of the construction, use, maintenance or failure of any of the authorised works by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by him) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised works) or property of Cadent, or there is any interruption in any service provided, or in the supply of any goods, by Cadent, or Cadent becomes liable to pay any amount to any third party, the undertaker will—
  • (a) bear and pay on demand the cost reasonably incurred by Cadent in making good such damage or restoring the supply; and
  • (b) indemnify Cadent for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from Cadent, by reason or in consequence of any such damage or interruption or Cadent becoming liable to any third party as aforesaid other than arising from any default of Cadent.
  • (2) The fact that any act or thing may have been done by Cadent on behalf of the undertaker or in accordance with a plan approved by Cadent or in accordance with any requirement of Cadent or under its supervision including under any watching brief will not (unless sub-paragraph (3) applies) excuse the undertaker from liability under the provisions of sub-paragraph (1) unless Cadent fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan.
  • (3) Nothing in sub-paragraph (1) imposes any liability on the undertaker in respect of—
  • (a) any damage or interruption to the extent that it is attributable to the neglect or default of Cadent, its officers, servants, contractors or agents; and
  • (b) any authorised works and/or any other works authorised by this Part of this Schedule carried out by Cadent as an assignee, transferee or lessee of the undertaker with the benefit of the Order pursuant to section 156 (benefit of order granting development consent) of the Planning Act 2008 or article 8 (transfer of benefit of Order) subject to the proviso that once such works become apparatus (“new apparatus”), any authorised works yet to be executed and not falling within this sub-paragraph (3)(b) will be subject to the full terms of this Part of this Schedule including this paragraph 29.
  • (4) Cadent must give the undertaker reasonable notice of any such third party claim or demand and no settlement or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and considering the representations.
  • (5) The undertaker must not commence construction (and must not permit the commencement of such construction) of the authorised works on any land owned by Cadent or in respect of which Cadent has an easement or wayleave for its apparatus or any other interest or to carry out any works within 15 metres in any direction of Cadent’s apparatus until the following conditions are satisfied—
  • (a) unless and until Cadent is satisfied acting reasonably (but subject to all necessary regulatory constraints) that the undertaker has first provided the acceptable security (and provided evidence that it will maintain such acceptable security for the construction period of the authorised works from the proposed date of commencement of construction of the authorised works) and Cadent has confirmed the same to the undertaker in writing; and
  • (b) unless and until Cadent is satisfied acting reasonably (but subject to all necessary regulatory constraints) that the undertaker has procured acceptable insurance (and provided evidence to Cadent that it will maintain such acceptable insurance for the construction period of the authorised works from the proposed date of commencement of construction of the authorised works) and Cadent has confirmed the same in writing to the undertaker.
  • (6) In the event that the undertaker fails to comply with sub-paragraph 29(5) of this Part of this Schedule, nothing in this Part of this Schedule will prevent Cadent from seeking injunctive relief (or any other equitable remedy) in any court of competent jurisdiction.

Enactments and agreements

30

Save to the extent provided for to the contrary elsewhere in this Part of this Schedule or by agreement in writing between Cadent and the undertaker, nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and Cadent in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.

Co-operation

31

  • (1) Where in consequence of the proposed construction of any of the authorised works, the undertaker or Cadent requires the removal of apparatus under paragraph 25(2) of this Part of this Schedule or Cadent makes requirements for the protection or alteration of apparatus under paragraph 27 of this Part of this Schedule, the undertaker must use its reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of Cadent’s undertaking and Cadent must use its reasonable endeavours to co-operate with the undertaker for that purpose.
  • (2) For the avoidance of doubt whenever Cadent’s consent, agreement or approval is required in relation to plans, documents or other information submitted by the undertaker or the taking of action by the undertaker, Cadent’s consent must not be unreasonably withheld or delayed.

Access

32

If in consequence of the powers granted under this Order the access to any apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by Cadent in respect of the apparatus) is materially obstructed, the undertaker must provide such alternative rights and means of access to such apparatus as will enable Cadent to maintain or use the apparatus no less effectively than was possible before such obstruction.

Arbitration

33

Save for differences or disputes arising under sub-paragraphs 25(2), 25(4), 26(1), 28(5) and paragraph 27 of this Part of this Schedule any difference or dispute arising between the undertaker and Cadent under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and Cadent, be determined by arbitration in accordance with article 52 (arbitration) and in settling any difference or dispute, the arbitrator must have regard to the requirements of Cadent for ensuring the safety, economic and efficient operation of Cadent’s apparatus.

Notices

34

The plans submitted to Cadent by the undertaker pursuant to sub-paragraph 27(1) must be sent to Cadent Gas Limited Plant Protection by e-mail to plantprotection@cadentgas.com copied by e-mail to landservices@cadentgas.com and sent to the General Counsel Department at Cadent’s registered office or such other address as Cadent may from time to time appoint instead for that purpose and notify to the undertaker.

PART 4 — FOR THE PROTECTION OF RAILWAY INTERESTS

35

The provisions of this Part of this Schedule have effect, unless otherwise agreed in writing between the undertaker and Network Rail and, in the case of paragraph 48 of this Part of this Schedule any other person on whom rights or obligations are conferred by that paragraph.

36

In this Part of this Schedule—

  • asset protection agreement” means an agreement to regulate the construction and maintenance of the specified work in a form agreed between the undertaker and Network Rail which must accord with the form of basic asset protection agreement already agreed between the undertaker and Network Rail as at the date of this Order;
  • construction” includes execution, placing, alteration and reconstruction and “construct” and “constructed” have corresponding meanings;
  • the engineer” means an engineer appointed by Network Rail for the purposes of this Order;
  • network licence” means the network licence, as the same is amended from time to time, granted to Network Rail Infrastructure Limited by the Secretary of State in exercise of their powers under section 8 (licences) of the Railways Act 1993[^f00108];
  • plans” includes sections, designs, design data, software, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of railway property;
  • railway operational procedures” means procedures specified under any access agreement (as defined in the Railways Act 1993) or station lease;
  • railway property” means any railway belonging to Network Rail and— any station, land, works, apparatus and equipment belonging to Network Rail or connected with any such railway; and any easement or other property interest held or used by Network Rail or a tenant or licencee of Network Rail for the purposes of such railway or works, apparatus or equipment;
  • regulatory consents” means any consent or approval required under— the Railways Act 1993; the network licence; and/or any other relevant statutory or regulatory provisions, by either the Office of Rail and Road or the Secretary of State for Transport or any other competent body including change procedures and any other consents, approvals of any access or beneficiary that may be required in relation to the authorised development; and
  • specified work” means so much of any of the authorised development as is situated upon, across, under, over or within 15 metres of, or may in any way adversely affect, railway property and, for the avoidance of doubt, includes the maintenance of such works under the powers conferred by article 5 (maintenance of authorised development) in respect of such works.

37

  • (1) Where under this Part of this Schedule Network Rail is required to give its consent or approval in respect of any matter, that consent or approval is subject to the condition that Network Rail complies with any relevant railway operational procedures and any obligations under its network licence or under statute.
  • (2) In so far as any specified work or the acquisition or use of railway property is or may be subject to railway operational procedures, Network Rail must—
  • (a) co-operate with the undertaker with a view to avoiding undue delay and securing conformity as between any plans approved by the engineer and requirements emanating from those procedures; and
  • (b) use their reasonable endeavours to avoid any conflict arising between the application of those procedures and the proper implementation of the authorised development pursuant to the Order.
  • (3) The undertaker must not under the powers of this Order do anything which would result in railway property being incapable of being used or maintained or which would affect the safe running of trains on the railway.
  • (4) Where Network Rail is asked to give its consent pursuant to this paragraph, such consent must not be unreasonably withheld or delayed (save that it shall never be unreasonable to withhold consent for reasons of operational or railway safety (such matters to be in Network Rail’s absolute discretion)) but may be given subject to reasonable conditions.
  • (5) The undertaker must enter into an asset protection agreement prior to the carrying out of any specified work.

38

  • (1) The undertaker must before commencing construction of any specified work supply to Network Rail proper and sufficient plans of that work for the reasonable approval of the engineer and the specified work must not be commenced except in accordance with such plans as have been approved in writing by the engineer or settled by arbitration in accordance with article 52 (arbitration) of this Order.
  • (2) The approval of the engineer under sub-paragraph (1) must not be unreasonably withheld or delayed (save that it shall never be unreasonable for Network Rail to delay consent where issues of railway and/or public consent are concerned (with such matters being in Network Rail’s absolute discretion)), and if by the end of the period of 28 days beginning with the date on which such plans have been supplied to Network Rail the engineer has not intimated their disapproval of those plans and the grounds of such disapproval the undertaker may serve upon the engineer written notice requiring the engineer to intimate approval or disapproval within a further period of 28 days beginning with the date upon which the engineer receives written notice from the undertaker. If by the expiry of the further 28 days the engineer has not intimated approval or disapproval, the engineer is deemed to have approved the plans as submitted.
  • (3) If by the end of the period of 28 days beginning with the date on which written notice was served upon the engineer under sub-paragraph (2), Network Rail gives notice to the undertaker that Network Rail desires itself to construct any part of a specified work which in the opinion of the engineer will or may affect the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker desires such part of the specified work to be constructed, Network Rail must construct it without unnecessary delay on behalf of and to the reasonable satisfaction of the undertaker in accordance with the plans approved or deemed to be approved or settled under this paragraph 38, and under the supervision (where appropriate and if given) of the undertaker.
  • (4) When signifying their approval of the plans the engineer may specify any protective works (whether temporary or permanent) which in the engineer’s opinion should be carried out before the commencement of the construction of a specified work to ensure the safety or stability of railway property or the continuation of safe and efficient operation of the railways of Network Rail or the services of operators using the same (including any relocation, de-commissioning and removal of works, apparatus and equipment necessitated by a specified work and the comfort and safety of passengers who may be affected by the specified works) and such protective works as may be reasonably necessary for those purposes must be constructed by Network Rail or by the undertaker, if Network Rail so desires, and such protective works must be carried out at the expense of the undertaker in either case without unnecessary delay and the undertaker must not commence the construction of the specified works until the engineer has notified the undertaker that the protective works have been completed to their reasonable satisfaction.

39

  • (1) Any specified work and any protective works to be constructed by virtue of paragraph 38(4) of this Part of this Schedule must, when commenced, be constructed—
  • (a) without unnecessary delay in accordance with the plans approved or deemed to have been approved or settled under paragraph 38 of this Part of this Schedule;
  • (b) under the supervision (where appropriate and if given) and to the reasonable satisfaction of the engineer;
  • (c) in such manner as to cause as little damage as is possible to railway property; and
  • (d) so far as is reasonably practicable, so as not to interfere with or obstruct the free, uninterrupted and safe use of any railway of Network Rail or the traffic thereon and the use by passengers of railway property.
  • (2) If any damage to railway property or any such interference or obstruction is caused by the carrying out of, or in consequence of the construction of a specified work, the undertaker must, notwithstanding any such approval, make good such damage and must pay to Network Rail all reasonable expenses to which Network Rail may be put in accordance with the indemnity provided at paragraph 48(1) of this Part of this Schedule.
  • (3) Nothing in this Part of this Schedule imposes any liability on the undertaker with respect to any damage, costs, expenses or loss attributable to the negligence of Network Rail or its servants, contractors or agents or any liability on Network Rail with respect of any damage, costs, expenses or loss attributable to the negligence of the undertaker or its servants, contractors or agents.

40

The undertaker must—

  • (a) at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and
  • (b) supply the engineer with all such information as they may reasonably require with regard to a specified work or the method of constructing it.

41

Network Rail must at all times afford reasonable facilities to the undertaker and its agents for access to any works carried out by Network Rail under this Part of this Schedule during their construction and must supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them.

42

  • (1) If any permanent or temporary alterations or additions to railway property are reasonably necessary in consequence of the construction or completion of a specified work in order to ensure the safety of railway property or the continued safe operation of the railway of Network Rail, such alterations and additions may be carried out by Network Rail and if Network Rail gives to the undertaker 56 days’ notice (or in the event of an emergency or safety critical issue such notice as is reasonable in the circumstances) of its intention to carry out such alterations or additions (which must be specified in the notice), the undertaker must pay to Network Rail the reasonable cost of the construction of those alterations or additions including, in respect of any such alterations and additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by Network Rail in maintaining, working and, when necessary, renewing any such alterations or additions.
  • (2) If during the construction of a specified work by the undertaker Network Rail gives notice to the undertaker that Network Rail desires itself to construct that part of the specified work which in the opinion of the engineer is endangering the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker decides that part of the specified work is to be constructed, Network Rail must assume construction of that part of the specified work and the undertaker must, notwithstanding any such approval of a specified work under paragraph 38(1) of this Part of this Schedule, pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which Network Rail may suffer by reason of the execution by Network Rail of that specified work.
  • (3) The engineer must, in respect of the capitalised sums referred to in this paragraph 42 and paragraph 43(a) of this Part of this Schedule provide such details of the formula by which those sums have been calculated as the undertaker may reasonably require.
  • (4) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions a capitalised sum representing such saving must be set off against any sum payable by the undertaker to Network Rail under this paragraph 42.

43

The undertaker must repay to Network Rail all reasonable fees, costs, charges and expenses reasonably incurred by Network Rail—

  • (a) in constructing any part of a specified work on behalf of the undertaker as provided by paragraph 38(3) of this Part of this Schedule or in constructing any protective works under the provisions of paragraph 38(4) of this Part of this Schedule including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;
  • (b) in respect of the approval by the engineer of plans submitted by the undertaker and the supervision by the engineer of the construction of a specified work;
  • (c) in respect of the employment or procurement of the services of any inspectors, signallers, watch-persons and other persons whom it shall be reasonably necessary to appoint for inspecting, signalling, watching and lighting railway property and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of a specified work;
  • (d) in respect of any special traffic working resulting from any speed restrictions which may in the opinion of the engineer, require to be imposed by reason or in consequence of the construction or failure of a specified work or from the substitution or diversion of services which may be reasonably necessary for the same reason; and
  • (e) in respect of any additional temporary lighting of railway property in the vicinity of the specified works, being lighting made reasonably necessary by reason or in consequence of the construction or failure of a specified work.

44

  • (1) In this paragraph 44—
  • EMI” means, subject to sub-paragraph (2), electromagnetic interference with Network Rail apparatus generated by the operation of the authorised development where such interference is of a level which adversely affects the safe operation of Network Rail’s apparatus; and
  • Network Rail’s apparatus” means any lines, circuits, wires, apparatus or equipment (whether or not modified or installed as part of the authorised development) which are owned or used by Network Rail for the purpose of transmitting or receiving electrical energy or of radio, telegraphic, telephonic, electric, electronic or other like means of signalling or other communications.
  • (2) This paragraph 44 applies to EMI only to the extent that such EMI is not attributable to any change to Network Rail’s apparatus carried out after approval of plans under paragraph 38(1) of this Part of this Schedule for the relevant part of the authorised development giving rise to EMI (unless the undertaker has been given notice in writing before the approval of those plans of the intention to make such change).
  • (3) Subject to sub-paragraph (5), the undertaker must in the design and construction of the authorised development take all measures necessary to prevent EMI and must establish with Network Rail (both parties acting reasonably) appropriate arrangements to verify their effectiveness.
  • (4) In order to facilitate the undertaker’s compliance with sub-paragraph (3)—
  • (a) the undertaker must consult with Network Rail as early as reasonably practicable to identify all Network Rail’s apparatus which may be at risk of EMI, and thereafter must continue to consult with Network Rail (both before and after formal submission of plans under paragraph 38(1) of this Part of this Schedule) in order to identify all potential causes of EMI and the measures required to eliminate them;
  • (b) Network Rail must make available to the undertaker all information in the possession of Network Rail reasonably requested by the undertaker in respect of Network Rail’s apparatus identified pursuant to sub-paragraph (a); and
  • (c) Network Rail must allow the undertaker reasonable facilities for the inspection of Network Rail’s apparatus identified pursuant to sub-paragraph (a).
  • (5) In any case where it is established that EMI can only reasonably be prevented by modifications to Network Rail’s apparatus, Network Rail must not withhold its consent unreasonably to modifications of Network Rail’s apparatus, but the means of prevention and the method of their execution must be selected in the reasonable discretion of Network Rail, and in relation to such modifications paragraph 38(1) of this Part of this Schedule has effect subject to this sub-paragraph.
  • (6) Prior to the commencement of operation of the authorised development the undertaker shall test the use of the authorised development in a manner that shall first have been agreed with Network Rail and if, notwithstanding any measures adopted pursuant to sub-paragraph (3), the testing of the authorised development causes EMI then the undertaker must immediately upon receipt of notification by Network Rail of such EMI either in writing or communicated orally (such oral communication to be confirmed in writing as soon as reasonably practicable after it has been issued) forthwith cease to use (or procure the cessation of use of) the undertaker’s apparatus causing such EMI until all measures necessary have been taken to remedy such EMI by way of modification to the source of such EMI or (in the circumstances, and subject to the consent, specified in sub-paragraph (5)) to Network Rail’s apparatus.
  • (7) In the event of EMI having occurred—
  • (a) the undertaker must afford reasonable facilities to Network Rail for access to the undertaker’s apparatus in the investigation of such EMI;
  • (b) Network Rail must afford reasonable facilities to the undertaker for access to Network Rail’s apparatus in the investigation of such EMI;
  • (c) Network Rail must make available to the undertaker any additional material information in its possession reasonably requested by the undertaker in respect of Network Rail’s apparatus or such EMI; and
  • (d) the undertaker shall not allow the use or operation of the authorised development in a manner that has caused or will cause EMI until measures have been taken in accordance with this paragraph 44 to prevent EMI occurring.
  • (8) Where Network Rail approves modifications to Network Rail’s apparatus pursuant to sub-paragraphs (5) or (6)—
  • (a) Network Rail must allow the undertaker reasonable facilities for the inspection of the relevant part of Network Rail’s apparatus; and
  • (b) any modifications to Network Rail’s apparatus approved pursuant to those sub-paragraphs must be carried out and completed by the undertaker in accordance with paragraph 39 of this Part of this Schedule.
  • (9) To the extent that it would not otherwise do so, the indemnity in paragraph 48(1) of this Part of this Schedule applies to the costs and expenses reasonably incurred or losses suffered by Network Rail through the implementation of the provisions of this paragraph 44 (including costs incurred in connection with the consideration of proposals, approval of plans, supervision and inspection of works and facilitating access to Network Rail’s apparatus) or in consequence of any EMI to which sub-paragraph (6) applies.
  • (10) For the purpose of paragraph 43(a) of this Part of this Schedule any modifications to Network Rail’s apparatus under this paragraph 44 shall be deemed to be protective works referred to in that paragraph 43(a).
  • (11) In relation to any dispute arising under this paragraph 44 the reference in article 52 (arbitration) to the Institution of Civil Engineers shall be read as a reference to the Institution of Engineering and Technology.

45

If at any time after the completion of a specified work, not being a work vested in Network Rail, Network Rail gives notice to the undertaker informing it that the state of maintenance of any part of the specified work appears to be such as adversely affects the operation of railway property (in the reasonable opinion of the engineer (save that it shall never be unreasonable for Network Rail to delay consent where issues of railway and/or public consent are concerned) (with such matters being in Network Rail’s absolute discretion), the undertaker must, on receipt of such notice, take such steps as may be reasonably necessary to put that specified work in such state of maintenance as not adversely to affect railway property.

46

The undertaker must not provide any illumination or illuminated sign or signal on or in connection with a specified work in the vicinity of any railway belonging to Network Rail unless it has first consulted Network Rail and it must comply with Network Rail’s reasonable requirements for preventing confusion between such illumination or illuminated sign or signal and any railway signal or other light used for controlling, directing or securing the safety of traffic on the railway.

47

Any additional expenses which Network Rail may reasonably incur in altering, reconstructing or maintaining railway property under any powers existing at the making of this Order by reason of the existence of a specified work must, provided that 56 days’ previous notice of the commencement of such alteration, reconstruction or maintenance has been given to the undertaker, be repaid by the undertaker to Network Rail.

48

  • (1) The undertaker must pay to Network Rail all reasonable costs, charges, damages and expenses not otherwise provided for in this Part of this Schedule (subject to article 39 (no double recovery)) which may be reasonably incurred by Network Rail—
  • (a) by reason of the construction, maintenance or operation of a specified work or the failure thereof; or
  • (b) by reason of any act or omission of the undertaker or of any person in its employ or of its contractors or others whilst engaged upon a specified work;
  • (c) by reason of any act or omission of the undertaker or any person in its employ or of its contractors or others whilst accessing to or egressing from a specified work;
  • (d) in respect of any damage caused to or additional maintenance required to, railway property or any such interference or obstruction or delay to the operation of the railway as a result of access to or egress from a specified work by the undertaker or any person in its employ or of its contractors or others;
  • (e) in respect of costs incurred by Network Rail in complying with any railway operational procedures or obtaining any regulatory consents which procedures are required to be followed or consents obtained to facilitate the carrying out or operation of the specified work,

and the undertaker must indemnify and keep indemnified Network Rail from and against all claims and demands arising out of or in connection with a specified work or any such failure, act or omission; and the fact that any act or thing may have been done by Network Rail on behalf of the undertaker or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under the engineer’s supervision will not (if it was done without negligence on the part of Network Rail or of any person in its employ or of its contractors or agents) excuse the undertaker from any liability under the provisions of this sub-paragraph.

  • (2) Network Rail must—
  • (a) give the undertaker reasonable written notice of any such claims or demands;
  • (b) not make any settlement or compromise of such a claim or demand without the prior consent of the undertaker; and
  • (c) take such steps as are within its control and are reasonable in the circumstances to mitigate any liabilities relating to such claims or demands.
  • (3) The sums payable by the undertaker under sub-paragraph (1) will, if relevant, include a sum equivalent to the relevant costs.
  • (4) Subject to the terms of any agreement between Network Rail and a train operator regarding the timing or method of payment of the relevant costs in respect of that train operator, Network Rail must promptly pay to each train operator the amount of any sums which Network Rail receives under sub-paragraph (3) which relates to the relevant costs of that train operator.
  • (5) In no circumstances shall the undertaker be liable to Network Rail under this paragraph 48 for any indirect or consequential loss (including, without limitation, loss of profit) howsoever arising, nor for any direct or indirect loss that may have been caused by a specified work or the carrying out of the authorised development more than six years after any specified work or the relevant part of the authorised development has been completed.
  • (6) The obligation under sub-paragraph (3) to pay Network Rail the relevant costs shall, in the event of default, be enforceable directly by any train operator concerned to the extent that such sums would be payable to that operator pursuant to sub-paragraph (4).
  • (7) In this paragraph 48—
  • the relevant costs” means the costs, losses and expenses (including loss of revenue) reasonably incurred by each train operator as a consequence of any specified work including but not limited to any restriction of the use of Network Rail’s railway network as a result of the construction, maintenance or failure of a specified work or any such act or omission as mentioned in sub-paragraph (1); and
  • train operator” means any person who is authorised to act as the operator of a train by a licence under section 8 of the Railways Act 1993.

49

Network Rail must, on receipt of a request from the undertaker, from time to time provide the undertaker free of charge with written estimates of the costs, charges, expenses and other liabilities for which the undertaker is or will become liable under this Part of this Schedule (including the amount of the relevant costs mentioned in paragraph 48 of this Part of this Schedule) and with such information as may reasonably enable the undertaker to assess the reasonableness of any such estimate or claim made or to be made pursuant to this Part of this Schedule (including any claim relating to those relevant costs).

50

In the assessment of any sums payable to Network Rail under this Part of this Schedule there must not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Network Rail if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by the undertaker under this Part of this Schedule or increasing the sums so payable.

51

The undertaker and Network Rail may, subject in the case of Network Rail to compliance with the terms of its network licence, enter into, and carry into effect, agreements for the transfer to the undertaker of—

  • (a) any railway property shown on the works and land plans and described in the book of reference;
  • (b) any lands, works or other property held in connection with any such railway property; and
  • (c) any rights and obligations (whether or not statutory) of Network Rail relating to any railway property or any lands, works or other property referred to in this paragraph.

52

Nothing in this Order, or in any enactment incorporated with or applied by this Order, prejudices or affects the operation of Part 1 (the provision of railway services) of the Railways Act 1993.

53

The undertaker must give written notice to Network Rail if any application is proposed to be made by the undertaker for the Secretary of State’s consent which includes any railway land, under article 8 (transfer of benefit of Order) of this Order and any such notice must be given no later than 28 days before any such application is made and must describe or give (as appropriate)—

  • (a) the nature of the application to be made;
  • (b) the extent of the geographical area to which the application relates; and
  • (c) the name and address of the person acting for the Secretary of State to whom the application is to be made.

54

The undertaker must no later than 28 days from the date that the plans submitted to and certified by the Secretary of State in accordance with article 51 (certification of plans, etc.) are certified by the Secretary of State, provide a set of those plans to Network Rail via email or by USB.

PART 5 — FOR THE PROTECTION OF NATIONAL HIGHWAYS LIMITED

Application etc.,

55

  • (1) The provisions of this Part of this Schedule apply for the protection of National Highways and have effect unless otherwise agreed in writing between the undertaker and National Highways.
  • (2) Except where expressly amended by this Order the operation of the powers and duties of National Highways or the Secretary of State under the 1980 Act, the 1984 Act, the 1991 Act, the Transport Act 2000[^f00109], or Town and Country Planning (General Permitted Development) (England) Order 2015[^f00110] which shall continue to apply in respect of the exercise of all National Highways’ statutory functions.

Interpretation

56

  • (1) Where the terms defined in article 2 (interpretation) of this Order are inconsistent with sub-paragraph (2), the latter prevail.
  • (2) In this Part of this Schedule—
  • administration fee” means the fee payable pursuant to the provisions of this Part of this Schedule that represent the general internal costs of National Highways in administering the implementation of the specified work and the requirements of this Part of this Schedule and charged as a flat fee based on the final cost of the specified works;
  • as built information” means one electronic copy of the following information— as constructed drawings in both PDF and AutoCAD DWG formats for anything designed by the undertaker, in compliance with Interim Advice Note 184 or any successor document; list of suppliers and materials used, as well as any relevant test results and CCTV surveys (if required to comply with DMRB standards); product data sheets and technical specifications for all materials used; as constructed information for any utilities discovered or moved during the works; method statements for the works carried out; in relation to road lighting, signs, and traffic signals, any information required by Series 1300 and 1400 of the Specification for Highway Works or any replacement or modification of it; organisation and methods manuals for all products used; as constructed programme; test results and records as required by the detailed design information and during construction phase of the project; a stage 3 road safety audit subject to any exceptions to the road safety audit standard as agreed by the undertaker and National Highways; the health and safety file; and such other information as is required by National Highways to be used to update all relevant databases and to ensure compliance with National Highway’s Asset Data Management Manual as is in operation at the relevant time.
  • the bond sum” means the sum equal to 200% of the cost of the carrying out the specified works (to include all costs plus any commuted sum) or such other sum agreed between the undertaker and National Highways;
  • the cash surety” means the sum agreed between the undertaker and National Highways;
  • commuted sum” means such sum calculated as provided for in paragraph 69 of this Part of this Schedule to be used to fund the future cost of maintaining the specified works where such works have resulted in new network equipment or improvements to the SRN which require future maintenance;
  • condition survey” means a survey of the condition of National Highways structures and assets within the Order limits that may be affected by the specified works;
  • contractor” means any contractor or subcontractor appointed by the undertaker to carry out the specified works;
  • defects period” means the period from the date of the provisional certificate to the date of the final certificate which shall be no less than 12 months from the date of the provisional certificate;
  • detailed design information” means such of the following drawings, specifications and calculations as are relevant to the specified works— site clearance details; boundary, environmental and mitigation fencing; road restraints systems and supporting road restraint risk appraisal process assessment; drainage and ducting as required by DMRB CD 535 Drainage asset data and risk management and DMRB CS551 Drainage surveys – standards for Highways; earthworks including supporting geotechnical assessments required by DMRB CD622 Managing geotechnical risk and any required strengthened earthworks appraisal form certification; pavement, pavement foundations, kerbs, footways and paved areas; traffic signs and road markings; traffic signal equipment and associated signal phasing and timing detail; road lighting (including columns and brackets); electrical work for road lighting, traffic signs and signals; motorway communications as required by DMRB; highway structures and any required structural approval in principle; landscaping; proposed departures from DMRB standards; walking, cycling and horse riding assessment and review report; stage 1 and stage 2 road safety audits and exceptions agreed; utilities diversions; topographical survey; maintenance and repair strategy in accordance with DMRB GD304 Designing health and safety into maintenance or any replacement or modification of it; health and safety information including any asbestos survey required by GG105 or any successor document; other such information that may be required by National Highways to be used to inform the detailed design of the specified works; and regime of California Bearing Ratio testing.
  • DBFO contract” means the contract between National Highways and the highway operations and maintenance contractor for the maintenance and operation of parts of the strategic road network which are within the Order Limits or any successor or replacement contract that may be current at the relevant time;
  • DMRB” means the Design Manual for Roads and Bridges or any replacement or modification of it;
  • final certificate” means the certificate relating to those aspects of the specified works that have resulted in any alteration to the strategic road network to be issued by National Highways pursuant to paragraph 67 of this Part of this Schedule;
  • the health and safety file” means the file or other permanent record containing the relevant health and safety information for the authorised development required by the Construction (Design and Management) Regulations 2015[^f00111] (or such updated or revised regulations as may come into force from time to time);
  • highway operations and maintenance contractor” means the contractor appointed by National Highways under the DBFO contract;
  • nominated persons” means the undertaker’s representatives or the contractor’s representatives on site during the carrying out of the specified works as notified to National Highways from time to time;
  • programme of works” means a document setting out the sequence and timetabling of the specified works;
  • provisional certificate” means the certificate of provisional completion relating to those aspects of the specified works that have resulted in any alteration to the strategic road network to be issued by National Highways in accordance with paragraph 63 of this Part of this Schedule when it considers the specified works are substantially complete and may be opened for traffic;
  • road safety audit” means an audit carried out in accordance with the road safety audit standard;
  • road safety audit standard” means DMRB Standard HD GG119 or any replacement or modification of it;
  • road space booking” means road space bookings in accordance with National Highways’ Asset Management Operational Requirements (AMOR) including Network Occupancy Management System (NOMS) used to manage road space bookings and network occupancy;
  • Specification for Highways Works” means the specification for highways works forming part of the manual of contract documents for highway works published by National Highways and setting out the requirements and approvals procedures for work, goods or materials used in the construction, improvement or maintenance of the strategic road network;
  • specified works” means— highway works and signalisation on the strategic road network for which National Highways is the highway authority including any maintenance of such works including the works listed at articles 10 (street works) and 11 (power to alter layout, etc, of streets) of this Order and includes Work No 1; or the installation and maintenance of such parts of the authorised development under or over the strategic road network (including any structure) for which National Highways is the highway authority, authorised by this Order;
  • strategic road network” means any part of the road network including trunk roads, special roads or streets and including any structure on such roads or streets for which National Highways is the highway authority including drainage infrastructure, street furniture, verges and vegetation and all other land, apparatus and rights located in, on, over or under the highway;
  • utilities” means any pipes, wires, cables or equipment belonging to any person or body having power or consent to undertake street works under the 1991 Act; and
  • winter maintenance” means maintenance of the road surface to deal with snow and ice.

General

57

The undertaker acknowledges that parts of the works authorised by this Order affect or may affect parts of the strategic road network in respect of which National Highways have appointed the highway operations and maintenance contractor.

58

References to any standards, manuals, contracts, Regulations and Directives including to specific standards forming part of the DMRB are, for the purposes of this Part of this Schedule, to be construed as a reference to the same as amended, substituted or replaced, and with such modifications as are required in those circumstances.

Works outside the Order limits

59

If the undertaker proposes to carry out works to the strategic road network that are outside of the Order Limits in connection with the authorised development, the undertaker must enter into an agreement with National Highways in respect of the carrying out of those works prior to the commencement of those works. For the avoidance of doubt, the reference to works in this paragraph 59 does not include traffic regulation orders identified on the access and traffic regulation order plans.

Prior approvals and security

60

  • (1) The specified works must not commence until in respect of that part of the specified work, save where an item in (a) to (j) is agreed by National Highways and the undertaker as not being relevant to that part of the specified works—
  • (a) a stage 1 and stage 2 road safety audit has been carried out and all recommendations raised by them or any exceptions are approved by National Highways;
  • (b) the programme of works has been approved by National Highways;
  • (c) the detailed design of the specified works comprising of the following details, insofar as considered relevant by National Highways, has been submitted to and approved by National Highways—
  • (i) the detailed design information, incorporating all recommendations and any exceptions approved by National Highways under sub-paragraph (a);
  • (ii) details of the proposed road space bookings;
  • (iii) the identity and qualification of the contractor and nominated persons;
  • (iv) a process for stakeholder liaison, with key stakeholders to be identified and agreed between National Highways and the undertaker; and
  • (v) information demonstrating that the walking, cycling and horse riding assessment and review process undertaken by the undertaker in relation to the specified works has been adhered to in accordance with DMRB GG142 - Designing for walking, cycling and horse riding.
  • (d) a scheme of traffic management has been submitted by the undertaker and approved by National Highways such scheme to be capable of amendment by agreement between the undertaker and National Highways from time to time;
  • (e) stakeholder liaison has taken place in accordance with the process for such liaison agreed between the undertaker and National Highways under sub-paragraph (c)(iv) above;
  • (f) National Highways has approved the audit brief and CVs for all road safety audits and exceptions to items raised in accordance with the road safety audit standard;
  • (g) the undertaker has agreed the estimate of the commuted sum with National Highways;
  • (h) the scope of all maintenance operations (routine inspections, incident management, reactive and third party damage) to be carried out by the undertaker during the construction of the specified works (which must include winter maintenance) has been agreed in writing by National Highways;
  • (i) the undertaker has procured to National Highways warranties from the contractor and designer of the specified works in favour of National Highways to include covenants requiring the contractor and designer to exercise all reasonable skill, care and diligence in designing and constructing the specified works, including in the selection of materials, goods, equipment and plant; and
  • (j) the condition survey and a reasonable regime of monitoring of any National Highways assets or structures that are the subject of the condition survey has been agreed in writing by National Highways.
  • (2) The undertaker must not exercise—
  • (a) article 5 (maintenance of authorised development);
  • (b) article 12 (temporary stopping up of streets);
  • (c) article 17 (traffic regulation);
  • (d) article 19 (discharge of water);
  • (e) article 20 (protective works to buildings and structures);
  • (f) article 21 (authority to survey and investigate the land);
  • (g) article 23 (felling or lopping trees and removal of hedgerows);
  • (h) article 35 (temporary use of land for carrying out the authorised development); or
  • (i) article 36 (temporary use of land for maintaining the authorised development) of this Order,

over any part of the strategic road network without the consent of National Highways, and National Highways may in connection with any such exercise require the undertaker to provide details of any proposed road space bookings and/or submit a scheme of traffic management for National Highways’ approval.

  • (3) National Highways must prior to the commencement of the specified works or the exercise of any power referenced in sub-paragraph (2) inform the undertaker of the identity of the person who will act as a point of contact on behalf of National Highways for consideration of the information required under sub-paragraphs (1) or (2).
  • (4) Any approval of National Highways required under this paragraph 60—
  • (a) must not be unreasonably withheld;
  • (b) must be given in writing;
  • (c) shall be deemed to have been refused if neither given nor refused within 2 months of the receipt of the information for approval or, where further particulars are requested by National Highways within 2 months of receipt of the information to which the request for further particulars relates; and
  • (d) may be subject to any conditions as National Highways considers necessary.
  • (5) National Highways must provide the undertaker with a list, which is to be agreed between the parties acting reasonably, of all the structures, assets and pavements to be subject to both a condition survey and reasonable regime of monitoring pursuant to sub-paragraph (1)(j) before the first condition survey is conducted and the reasonable regime of monitoring is implemented.

Construction of the specified works

61

  • (1) The undertaker must give National Highways 28 days’ notice in writing of the date on which part of the specified works will start unless otherwise agreed by National Highways.
  • (2) The undertaker must comply with National Highways’ road space booking procedures prior to and during the carrying out of the specified works and no such specified works for which a road space booking is required shall commence without a road space booking having first been secured from National Highways.
  • (3) The specified works must be carried out by the undertaker to the satisfaction of National Highways in accordance with—
  • (a) the relevant detailed design information and programme of works approved pursuant to paragraph 60(1) of this Part of this Schedule or as subsequently varied by agreement between the undertaker and National Highways;
  • (b) the DMRB, the Manual of Contract Documents for Highway Works, including the Specification for Highway Works, together with all other relevant standards as required by National Highways to include, inter alia; all relevant interim advice notes, the Traffic Signs Manual and the Traffic Signs Regulations and General Directions 2016[^f00112] save to the extent that exceptions from those standards apply which have been approved by National Highways; and
  • (c) all aspects of the Construction (Design and Management) Regulations 2015 or any statutory amendment or variation of the same and in particular the undertaker, as client, must ensure that all client duties (as defined in the said regulations) are undertaken to the satisfaction of National Highways.
  • (4) The undertaker must permit and must require the contractor to permit at all reasonable times and upon reasonable notice persons authorised by National Highways (whose identity must have been previously notified to the undertaker by National Highways) to gain access to the specified works for the purposes of inspection and supervision of the specified works.
  • (5) If any part of the specified works is constructed—
  • (a) other than in accordance with the requirements of this Part of this Schedule; or
  • (b) in a way that causes damage to the highway, highway structure or asset or any other land of National Highways,

National Highways may by notice in writing require the undertaker, at the undertaker’s own expense, to comply promptly with the requirements of this Part of this Schedule or remedy any damage notified to the undertaker under this Part of this Schedule, to the satisfaction of National Highways.

  • (6) If within 28 days on which a notice under sub-paragraph (5) is served on the undertaker (or in the event of there being, in the opinion of National Highways, a danger to road users, within such lesser period as National Highways may stipulate), the undertaker has failed to take the steps required by that notice, National Highways may carry out the steps required of the undertaker and may recover any expenditure incurred by National Highways in so doing, such sum to be payable within 30 days of a written demand, including itemised costs.
  • (7) Nothing in this Part of this Schedule prevents National Highways from carrying out any work or taking any such action as it reasonably believes to be necessary as a result of or in connection with or the carrying out or maintenance of the authorised development without prior notice to the undertaker in the event of an emergency or to prevent the occurrence of danger to the public and National Highways may recover any expenditure it reasonably incurs in so doing.
  • (8) In constructing the specified works, the undertaker must at its own expense divert or protect all utilities and all agreed alterations and reinstatement of highway over existing utilities must be constructed to the satisfaction of National Highways.
  • (9) During the construction of the specified works the undertaker must carry out all maintenance (including winter maintenance) in accordance with the scope of maintenance operations agreed by National Highways pursuant to paragraph 60(1)(h) of this Part of this Schedule and the undertaker must carry out such maintenance at its own cost.
  • (10) The undertaker must notify National Highways if it fails to complete the specified works in accordance with the agreed programme pursuant to paragraph 60(1)(b) of this Part of this Schedule or suspends the carrying out of any specified work beyond a reasonable period of time and National Highways reserves the right to withdraw any road space booking granted to the undertaker to ensure compliance with its network occupancy requirements.

Payments

62

  • (1) The undertaker must pay to National Highways a sum equal to the whole of any costs and expenses which National Highways incurs (including costs and expenses for using internal or external staff) in relation to the specified works and in relation to any approvals sought under this Order, or otherwise incurred under this Part of this Schedule, including—
  • (a) the checking and approval of the information required under paragraph 60(1) of this Part of this Schedule;
  • (b) the supervision of the specified works;
  • (c) the checking and approval of the information required to determine approvals under this Order which are not covered by the administration fee;
  • (d) all costs in relation to the transfer of any land or grant of rights which may be required for the specified works;
  • (e) the administration fee;
  • (f) all legal costs incurred which are not already covered by (a) to (e) above; and
  • (g) any value added tax which is payable by National Highways in respect of such costs and expenses in (a) to (f) and for which it cannot obtain reinstatement from HM Revenue and Customs,

together comprising the “NH costs”.

  • (2) The undertaker must pay to National Highways within 30 days of receipt and prior to such costs being incurred the total costs that National Highways believe will be properly and necessarily incurred by National Highways in undertaking any statutory procedure or preparing and bringing into force any traffic regulation order or orders necessary to carry out or for effectively implementing the specified works.
  • (3) National Highways must provide the undertaker with an itemised schedule showing its estimate of the NH costs, including its estimate of the administration fee, prior to the commencement of the specified works and the undertaker must pay to National Highways an amount equal to the estimated sum prior to National Highways incurring any cost and prior to commencing the specified works.
  • (4) If at any time after the payment referred to in sub-paragraph (3) has become payable, National Highways reasonably believes that the NH costs will exceed the estimated NH costs notified pursuant to sub-paragraph (3) it may give written notice to the undertaker of the amount that it believes the NH costs will exceed the estimate (“the excess”) and the undertaker must pay to National Highways within 30 days of the date of the notice a sum equal to the excess.
  • (5) National Highways must give the undertaker an itemised final account of NH costs referred to in sub-paragraph (1) within 91 days of the issue of the provisional certificate issued pursuant to paragraph 63(4) of this Part of this Schedule.
  • (6) Within 30 days of the issue of the final account—
  • (a) if the final account shows a further sum as due to National Highways the undertaker must pay to National Highways the sum shown due to it;
  • (b) if the account shows that the payment or payments previously made by the undertaker have exceeded the costs incurred by National Highways, National Highways must refund the difference to the undertaker.

Provisional Certificate

63

  • (1) Following any closure or partial closure of any part of the strategic road network for the purposes of carrying out the specified works, National Highways will carry out a site inspection to satisfy itself that the part of the strategic road network is, in its opinion, safe for traffic and the undertaker must comply with any requirements of National Highways prior to reopening of that part of the strategic road network.
  • (2) As soon as the undertaker considers that the provisional certificate may be properly issued it must apply to National Highways for the provisional certificate.
  • (3) Following an application for a provisional certificate, National Highways must as soon as reasonably practicable and within 28 days of receipt of the application under sub-paragraph (2) or such other period agreed between the parties, National Highways must—
  • (a) inspect the specified works; and
  • (b) provide the undertaker with a written list of works that are required for the provisional certificate to be issued or confirmation that no further works are required for this purpose.
  • (4) When—
  • (a) a stage 3 road safety audit for the specified works has been carried out (where relevant) and all recommendations raised including remedial works have (subject to any exceptions agreed) been approved by National Highways;
  • (b) the specified works incorporating the approved remedial works under sub-paragraph (4)(a) and any further works notified to the undertaker pursuant to sub-paragraph (3)(b) have been completed to the satisfaction of National Highways;
  • (c) the as built information has been provided to National Highways; and
  • (d) the undertaker has paid the commuted sum to National Highways.

Opening

64

The undertaker must notify National Highways not less than 14 days in advance of the intended date of opening to the public of part (a) of the specified works and the undertaker must notify National Highways of the actual date part (a) of the specified works will be opened to the public within 14 days of that date.

Final condition survey

65

  • (1) The undertaker must, as soon as reasonably practicable after making its application for a provisional certificate pursuant to paragraph 63(2), arrange for the highways structures and assets that were the subject of the condition survey to be re-surveyed and must submit the re-survey to National Highways for its approval. The re-survey will include a renewed geotechnical assessment required by DMRB CD622 or its equivalent if the specified works include any works beneath the strategic road network.
  • (2) If the re-surveys carried out pursuant to sub-paragraph (1) indicate that any damage has been caused to a structure, asset or pavement, the undertaker must submit a scheme for remedial works in writing to National Highways for its approval in writing and the undertaker must carry out the remedial works at its own cost and in accordance with the scheme submitted.
  • (3) If the undertaker fails to carry out the remedial work in accordance with the approved scheme, National Highways may carry out the steps required of the undertaker and may recover any expenditure it reasonably incurs in so doing, such agreed sum to be paid within 30 days of receipt of a written and itemised demand.
  • (4) National Highways may, at its discretion, at the same time as giving its approval to the re-surveys pursuant to sub-paragraph (1) give notice in writing that National Highways will remedy any damage identified in the re-surveys and National Highways may recover any expenditure it reasonably incurs in so doing.
  • (5) The undertaker must make available to National Highways upon request copies of any survey or inspection reports produced pursuant to any inspection or survey of any of the specified work following its completion that the undertaker may from time to time carry out.

Defects Period

66

  • (1) The undertaker must at its own expense remedy any defects in the specified works as are reasonably required by National Highways to be remedied during the defects period. All identified defects must be remedied in accordance with the following timescales—
  • (a) in respect of matters of urgency, within 24 hours of receiving notification for the same (urgency to be determined at the absolute discretion of National Highways);
  • (b) in respect of matters which National Highways considers to be serious defects or faults, within 14 days of receiving notification of the same; and
  • (c) in respect of all other defects notified to the undertaker, within 4 weeks of receiving notification of the same or such other time period as is agreed.
  • (2) On the issue of the provisional certificate National Highways has responsibility for maintenance of the strategic road network save for any soft landscaping works which must be established and which must thereafter be maintained for a period of 3 years by and at the expense of the undertaker.

Final Certificate

67

  • (1) The undertaker must apply to National Highways for the final certificate no sooner than 12 months from the date of the provisional certificate.
  • (2) Following receipt of the application for the final certificate, National Highways must as soon as reasonably practicable and within 28 days of receipt of the application under sub-paragraph (1) National Highways must—
  • (a) inspect the specified works; and
  • (b) provide the undertaker with a written list of any further works required to remedy or make good any defect or damage to the strategic road network or confirmation that no such works are required for this purpose.
  • (3) The undertaker must carry out such works notified to it pursuant to sub-paragraph (2).
  • (4) When National Highways is satisfied that any defects or damage arising from defects during the defects period and any defects notified to the undertaker pursuant to sub-paragraph (2) and any remedial works required as a result of the stage 4 road safety audit have been made good to the satisfaction of National Highways, National Highways must issue the final certificate, such certificate not to be unreasonably withheld or delayed, after which the bond shall be released in full.

Security

68

The specified works must not commence until—

  • (a) the undertaker procures that the specified works are secured by a bond from a bondsman first approved by National Highways in the agreed form between the undertaker and National Highways, to indemnify National Highways against all losses, damages, costs or expenses arising from any breach of any one or more of the obligations of the undertaker in respect of the exercise of the powers under this Order and the specified works under the provisions of this Part of this Schedule provided that the maximum liability of the bond must not exceed the bond sum; and
  • (b) the undertaker has provided the cash surety which may be utilised by National Highways in the event of the undertaker failing to meet its obligations to make payments under paragraph 62 of this Part of this Schedule or to carry out works the need for which arises from a breach of one or more of the obligations of the undertaker under the provisions of this Part of this Schedule.

Commuted sums

69

  • (1) National Highways must provide to the undertaker an estimate of the commuted sum, calculated in accordance with FS Guidance S278 Commuted Lump Sum Calculation Method dated 18 January 2010 or any successor guidance, prior to the commencement of the specified works.
  • (2) The undertaker must pay to National Highways the commuted sum prior to the issue of the provisional certificate.

Insurance

70

Prior to the commencement of the specified works the undertaker must effect public liability insurance with an insurer in the minimum sum of £10,000,000.00 (ten million pounds) in respect of any one claim against any legal liability for damage, loss or injury to any property or any person as a direct result of the execution of the specified works or use of the strategic road network by the undertaker.

Indemnity

71

  • (1) The undertaker must indemnify National Highways from and against all costs, claims, expenses, damages, losses and liabilities directly suffered by National Highways arising from the construction, maintenance or use of the specified works or exercise of or failure to exercise any power under this Order within 30 days of demand provided that—
  • (a) National Highways notifies the undertaker upon receipt of any claim; and
  • (b) National Highways notifies the quantum of the claim to the undertaker in writing.
  • (2) The indemnity provided by this clause shall not apply in respect of any cost, expense, damage, loss and/or liability which may arise out of or be incidental to any negligent or defective act, default or omission on the part of National Highways, its agents, workmen or employees.

Maintenance of the specified works

72

  • (1) The undertaker must, prior to the commencement of any works of maintenance to the specified works, give National Highways 28 days’ notice in writing of the date on which those works will start unless otherwise agreed by National Highways, acting reasonably.
  • (2) If, for the purposes of maintaining the specified works, the undertaker needs to occupy any road space, the undertaker must comply with National Highways’ road space booking requirements and no maintenance of the specified works for which a road space booking is required shall commence without a road space booking having first been secured.
  • (3) The undertaker must comply with any requirements that National Highways may notify to the undertaker, such requirements to be notified to the undertaker not less than 7 days in advance of the planned commencement date of the maintenance works.
  • (4) The provisions of paragraph 64 of this Part of this Schedule shall apply to the opening of any part of the strategic road network following occupation of any road space under this paragraph 72.

Land or rights

73

If the transfer of any land from or to National Highways or the grant of rights in, on, over or under land for the benefit of the undertaker is required in respect of the specified works, National Highways and the undertaker hereby agree to cooperate in the execution of any transfer or deed of grant or easement as may be necessary. National Highways further agrees that the undertaker may exercise any powers under Part 5 of this Order as may be necessary for the acquisition of such rights.

Expert Determination

74

  • (1) Save as set out in sub-paragraph (6), article 52 (arbitration) of the Order does not apply to this Part of this Schedule.
  • (2) Any difference under this Part of this Schedule may be referred to and settled by a single independent and suitable person who holds appropriate professional qualifications and is a member of a professional body relevant to the matter in dispute acting as an expert, such person to be agreed by the differing parties or, in the absence of agreement, identified by the President of the Institution of Civil Engineers.
  • (3) On notification by either party of a dispute, the parties must jointly instruct an expert within 14 days of notification of the dispute.
  • (4) All parties involved in settling any difference must use best endeavours to do so within 21 days from the date that an expert is appointed.
  • (5) The expert must—
  • (a) invite the parties to make submission to the expert in writing and copied to the other party to be received by the expert within 21 days of the expert’s appointment;
  • (b) permit a party to comment on the submissions made by the other party within 21 days of receipt of the submission;
  • (c) issue a decision within 42 days of receipt of the submissions under sub-paragraph (b); and
  • (d) give reasons for the decision.
  • (6) Any determination by the expert is final and binding, except in the case of manifest error in which case the difference that has been subject to expert determination may be referred to and settled by arbitration under article 52.
  • (7) The fees of the expert are payable by the parties in such proportions as the expert may determine or, in the absence of such determination, equally.

PART 6 — FOR THE PROTECTION OF LOCAL HIGHWAY AUTHORITIES

Application etc.

75

The provisions of this Part of this Schedule apply for the protection of the local highway authority and have effect unless otherwise agreed in writing between the undertaker and the local highway authority.

Interpretation

76

  • (1) Where the terms defined in article 2 (interpretation) of this Order are inconsistent with sub-paragraph (2), the latter prevail.
  • (2) In this Part of this Schedule—
  • agreement fee” means a sum equal to eight and a half per cent (8.5%) of the works estimate in respect of the local highway authority’s technical approval, administration and inspection costs for keeping the specified works under observation and inspection during the period of construction from when any specified works begin to when the provisional certificate of completion is issued and undertaking the pre-maintenance inspection pursuant to paragraph 88(1) of this Part of this Schedule and final inspection pursuant to paragraph 90(6) of this Part of this Schedule;
  • approved drawings” means those plans drawings, calculations and diagrams required to demonstrate that the specified works can reasonably be constructed within the local highway which shall be substantially in accordance with the highways plans and approved pursuant to this Part of this Schedule;
  • approved programme and method statement and traffic management proposals” means respectively the detailed programme of works and the method statement and traffic management proposals as approved by the local highway authority as set out in paragraph 81 of this Part of this Schedule and reference to any one of them and the term “the programme” must be construed accordingly;
  • asset management fee” means the sum of £150.00 towards amending the local highway authority’s legal records;
  • asset planning fee” means the sum of £150.00 towards adding and amending the local highway authority’s highway asset inventory;
  • cash deposit” means a sum equivalent to the works sum;
  • CDM Regulations” means The Construction (Design and Management) Regulations 2015;
  • cessation of works notice” means a notice served by the local highway authority on the undertaker requiring the undertaker to forthwith cease carrying out the specified works specified in the notice;
  • commencement notice” means at least twenty (20) working days’ notice to be given by the undertaker to the local highway authority of the undertaker’s intention to commence the specified works on the local highway;
  • commuted sum” means a payment to the local highway authority calculated in accordance with the formulas pursuant to Cambridgeshire County Council’s ‘Highways Commuted Sums’ policy dated 1 April 2023;
  • conditions of contract” means the contract for the specified works which must be let by the undertaker using the New Engineering Contract version 3 2013 (NEC3) or version 4 2017 (NEC4) as amended in 2023 or such other contract as may be approved by the local highway authority;
  • conditions survey” means a survey of the surface features of the existing local highway recording any existing defects, damage or missing elements and the required record shall include photographs and a location measured from the centre line of the proposed works noting the cardinal direction or intermediate directions for the side of the local highway;
  • contractor” means a suitably qualified contractor nominated by the undertaker and approved by the local highway authority (such approval not to be unreasonably withheld or delayed);
  • defects” means any damage or defects to the specified works identified by the local highway authority as part of the pre-maintenance inspection pursuant to paragraph 88(1) of this Part of this Schedule and the final inspection pursuant to 90(6) of this Part of this Schedule;
  • final certificate” means the certificate issued by the local highway authority at the end of the maintenance period and following the stage 3 safety audit (or the stage 4 safety audit, if necessary, as the case may be) signifying the specified works are satisfactory and any defects have been remedied and otherwise made good to the satisfaction of the local highway authority;
  • health and safety file” means the health and safety documentation required under the CDM Regulations prepared by the undertaker and submitted to the local highway authority;
  • “designers response” as described in GG119 of the Design Manual for Roads and Bridges;
  • Housing Estate Road Construction Specification” means the specification within Cambridgeshire County Council’s Development Management – General Principals of Development policy document published by the local highway authority on 7 March 2023;
  • local highway” means any public, vehicular highway, way, route, footpath, cycle route, footway, carriageway, bridleway, byway-open-to-all-traffic which vests or is intended at the completion of specified works to vest in or be otherwise maintainable by the local highway authority at public expense;
  • local highway authority” means the highway authority with responsibility for the relevant local highway pursuant to the 1980 Act;
  • maintenance period” means the period of not less than 12 months from the date of the provisional certificate of completion;
  • overseeing organisation” has the meaning as described in GG119 of the Design Manual for Roads and Bridges;
  • post-construction inventory” means an inventory of new highway assets listing the number and area of each element of the new assets within the specified works as specified by the local highway authority;
  • provisional certificate of completion” means the certificate issued by the local highway authority confirming the specified works have been completed and have been found to be satisfactory to the local highway authority;
  • specification” means the Housing Estate Road Construction Specification and where applicable the ‘Design Manual for Roads and Bridges’ and any other such specifications as reasonably required by the local highway authority and as may be amended from time to time;
  • specified works” means any highway works and any street works carried out within the local highway as part of the authorised development and includes any part of the specified works (as the case may be);
  • stage 2 safety audit” means the audit undertaken of the detailed design of the specified works prior to the commencement of the specified works. The audit shall be undertaken in compliance with the requirements of GG119 of the ‘Design Manual for Roads and Bridges’;
  • stage 3 safety audit” means the audit undertaken following completion of the specified works in compliance with the requirements of GG119 of the ‘Design Manual for Roads and Bridges’;
  • stage 4 safety audit” means the safety audit undertaken in compliance with the requirements of GG119 of the ‘Design Manual for Roads and Bridges’ at the discretion of the local highway authority following expiration of the maintenance period to assess the specified works in order to determine whether any remedial works are required prior to issue of the final certificate;
  • statutory undertaker (highways)” means a statutory undertaker as defined in section 329(1)[^f00113] (further provision as to interpretation) of the 1980 Act and all those bodies deemed to be statutory undertakers for the purposes of the 1980 Act and all those undertakers licensed in accordance with the 1991 Act;
  • street lighting design review” means a review of street lighting comprised in the specified works, such review to include layout design and specification;
  • technical approval” means approval granted to the undertaker by the local highway authority in connection with each of the specified works at a specific specified works location enabling these to progress to on site operations;
  • third party notice information” means— a brief description of the specified works emphasising any changes to the appearance of the streetscape (e.g. removal of grass verges or significant changed in materials used); planned start date; contract period or planned completion date; name and address of contractor carrying out the specified works; details of the person responsible for supervision of the specified works including an address and telephone number to contact should a query arise; details of emergency contact(s) for the specified works which are to be available twenty four hours a day seven days a week for each area of specified works until the final certificate is issued and the contact details must include a telephone number and email address; and where further details of the proposed specified works may be viewed;
  • third party notices” means at least 20 working days’ notice to be given by the undertaker to— the Parish, City or Town Council for the area in which the works are located; and the owner and occupier of every premises adjoining the part of the local highway on which the specified works are to be carried out by letter addressed to “the owner/occupier of [address]” and sent by first class post or delivered to each premises containing the third party notice information;
  • works estimate” means in relation to each part of the specified works the sum specified in the bill of quantities for the relevant part of the specified works in accordance with paragraph 102(5) of this Part of this Schedule;
  • works sum” means a sum equivalent to the works estimate plus 10% (contingency).

77

  • (1) Wherever in this Part of this Schedule provision is made with respect to the approval or consent of the local highway authority, that approval or consent must—
  • (a) not be unreasonably withheld or delayed; and
  • (b) be in writing and subject to such reasonable terms and conditions as the local highway authority may require.

Dispositions

78

  • (1) Until issue (or deemed issue) of the final certificate the undertaker must give the local highway authority written notice of any disposition of any legal interest in the land adjacent to the specified works within 15 working days of completion of such disposals save in the following circumstances—
  • (a) where the disposal is to a—
  • (i) local authority;
  • (ii) statutory body or service supply company of an electricity substation gas governor pumping station, water pumping station or other statutory services which have been or are to be constructed or installed;
  • (iii) local highway authority for the purpose of adoption of the roads and footpaths and cycle ways to be constructed; and/or
  • (iv) a subsidiary of the undertaker;
  • (b) where the disposal comprises or involves—
  • (i) the grant of a legal charge or any security but for the avoidance of doubt not a disposition by a mortgagee in possession or under a power of sale;
  • (ii) a compulsory sale or acquisition (whether permanent or temporary);
  • (iii) the grant of a garage lease with the use restricted to use in association with a dwelling.

Prior approvals and security

79

  • (1) The specified works must not commence until in respect of that part of the specified works—
  • (a) the quantum of the cash deposit and the works estimate have been agreed with the local highway authority;
  • (b) the local highway authority has approved in writing the detailed design of the relevant part(s) of the specified works , the specification and the approved drawings;
  • (c) the local highway authority has agreed the approved programme and method statement and traffic management proposals;
  • (d) the commencement notice and the third party notices have been served by the undertaker on the local highway authority;
  • (e) the undertaker has obtained all necessary consents under the 1991 Act and the Traffic Management Act 2004 (as applicable);
  • (f) All matters relating to the stage 2 safety audit have been fully resolved to the satisfaction of the overseeing organisation;
  • (g) a condition survey of the existing local highway for a distance of not less than 50 metres either side of the centreline of the specified works has been undertaken by the undertaker in the presence of an officer of the local highway authority.
  • (2) If within 40 working days after each and every submission of the details for each and every part of the specified works required to be submitted for approval pursuant to sub-paragraph (1) by the undertaker the local highway authority has not approved or refused them, it is deemed to have approved the details as submitted.
  • (3) If the local highway authority refuses the details submitted to it under this paragraph 79 at any time, it shall provide with such refusal the reasons therefor.
  • (4) The procedure specified in this paragraph 79 shall be repeated until such time as the relevant details are approved (or deemed approved) by the local highway authority.
  • (5) The undertaker must include in any submission made to the local highway authority under this paragraph 79 a statement that the provisions of sub-paragraph (2) apply and if the submission fails to include such statement the provisions of sub-paragraph (2) will not apply.

Construction of the specified works

80

  • (1) The undertaker must carry out the specified works as follows—
  • (a) in a good and workmanlike manner using all professional skill and care and in accordance with good practice for works of the type, size and complexity comprised in the specified works;
  • (b) in accordance with—
  • (i) any reasonable instructions of the local highway authority given in writing or verbally (provided that instruction is confirmed by the local highway authority in writing within 2 working days) to the undertaker;
  • (ii) the specification and approved drawings; and
  • (iii) all relevant consents and approvals;
  • (c) in compliance with—

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk