The Town and Country Planning (Development Management Procedure) (Wales) Order 2012
- (2) The report must relate to the period of 12 months commencing on 1 April in the preceding year (“the report year”).
- (3) The report must contain, in respect of any report year, a statement as to—
- (a) the number of occasions on which the consultee was consulted;
- (b) the number of occasions on which a substantive response was provided;
- (c) when the substantive response was provided; and
- (d) the number of occasions on which the consultee gave a substantive response outside the period prescribed for the purposes of section 54(4) of the 2004 Act or, as the case may be, the period specified in or referred to in article 2E(1) and a summary of the reasons why.
- (4) In this article “substantive response” means either a substantive response to the applicant or local planning authority in accordance with articles 2E or 15A.
Representations by community councils before determination of applications
Notification of mineral applications
Appeal made: Functions of a local planning authority
26A
The additional period prescribed for the purposes of section 78A is four weeks.
SCHEDULE 1A — Minor Commercial Development Uses
Shops
1
Use for all or any of the following purposes—
- (a) for the retail sale of goods other than hot food,
- (b) as a post office,
- (c) for the sale of tickets or as a travel agency,
- (d) for the sale of sandwiches or other cold food for consumption off the premises,
- (e) for hairdressing,
- (f) for the direction of funerals,
- (g) for the display of goods for sale,
- (h) for the hiring out of domestic or personal goods or articles,
- (i) for the washing or cleaning of clothes or fabrics on the premises,
- (j) for the reception of goods to be washed, cleaned or repaired,
where the sale, display or service is to visiting members of the public.
Financial and professional services
2
Use for the provision of—
- (a) financial services,
- (b) professional services (other than health or medical services), or
- (c) any other services (including use as a betting office) which it is appropriate to provide in a shopping area,
where the services are provided principally to visiting members of the public.
Food and drink
3
Use for the sale of food or drink for consumption on the premises or of hot food for consumption off the premises.
PART 1A — Pre-application consultation
Requirement to carry out pre-application consultation
2B
- (1) Major development is specified for the purposes of section 61Z(1) of the 1990 Act (Wales: requirement to carry out pre-application consultation).
- (2) Proposed section 73 applications and applications to be made under section 73A of the 1990 Act (Planning permission for development already carried out) are specified for the purposes of section 61Z(7)(b) of the 1990 Act.
Publicity before applying for planning permission
2C
- (1) The applicant must publicise the proposed application by—
- (a) giving requisite notice—
- (i) by site display in at least one place on or near the land to which the proposed application relates for not less than 28 days; and
- (ii) in writing to any owner or occupier of any land adjoining the land to which the proposed application relates; and
- (b) making the following information available for inspection at a location in the vicinity of the proposed development for not less than 28 days beginning with each day on which each of the notices referred to in sub-paragraph (a) or article 2D(2) are given—
- (i) any documents and particulars or evidence that would be required for a subsequent application, in the same or substantially the same form, to be a valid application except certificates in relation to notices of applications for planning permission required by article 11;
- (ii) a plan which identifies the land to which the proposed application relates;
- (iii) any other plans, drawings and information necessary to describe the development which is the subject of the proposed application;
- (iv) in a case to which article 7 applies, the design and access statement; and
- (v) subject to article 8(2), the particulars or evidence required by the local planning authority under section 62(3) of the 1990 Act.
- (2) Any plans or drawings required to be provided by paragraph (1)(b)(ii) or (iii) must be drawn to an identified scale and, in the case of plans, must show the direction of north.
- (3) The applicant must have complied with paragraph (1) before an application is submitted.
- (4) Where the notice referred to in paragraph (1)(a)(i) is, without any fault or intention of the applicant, removed obscured or defaced before the period of 28 days has elapsed, the applicant will be treated as having complied with the requirements of the relevant paragraph if the applicant has taken reasonable steps to protect the notice and, if need be, replace it.
- (5) In this article “requisite notice” (“hysbysiad gofynnol”) means notice in the form set out in Schedule 1B or in a form substantially to the like effect.
Consultation before applying for planning permission
2D
- (1) The following persons or descriptions of persons are specified for the purposes of section 61Z(4) of the 1990 Act—
- (a) any community consultees; and
- (b) any specialist consultee.
- (2) Where an applicant is required to consult a community consultee, the applicant must give the community consultee requisite notice in writing of the proposed application.
- (3) Where an applicant is required to consult a specialist consultees the applicant must give the specialist consultee requisite notice in writing of the proposed application and enclose each of the documents referred to in article 2C(1)(b) or provide a link to a website on which those documents can be found.
- (4) The applicant must have complied with paragraphs (2) and (3) and have given the specialist consultee time to respond in accordance with article 2E(1) before an application is submitted.
- (5) In this article, “requisite notice” (“hysbysiad gofynnol”) means—
- (a) in relation to a community consultee notice in the form set out in Schedule 1B; and
- (b) in relation to a specialist consultee notice in the form set out in Schedule 1C,
or a form substantially to the like effect.
Duty to respond to pre-application consultation: specialist consultees
2E
- (1) A specialist consultee, consulted in accordance with the provisions of section 61Z(4) of the 1990 Act, must provide a substantive response within 28 days beginning with the day on which the notice referred to in article 2D(3) is given or such other period as may be agreed in writing between the specialist consultee and the applicant.
- (2) For the purposes of this article, a substantive response is one which—
- (a) states that the specialist consultee has no comment to make;
- (b) states that the specialist consultee has no objection to the proposed development and refers the applicant to current standing advice by the specialist consultee on the subject of the consultation;
- (c) advises the applicant of any concerns identified in relation to the proposed development and how those concerns can be addressed; or
- (d) advises the applicant that the specialist consultee has concerns and that it would object to an application for planning permission made in the same or substantially the same terms and sets out the reasons for those objections.
Pre-application consultation reports
2F
- (1) Where an applicant has been required to carry out pre-application consultation in accordance with the provisions of section 61Z of the 1990 Act and articles 2C and 2D and submits an application for planning permission, that application must be accompanied by a pre-application consultation report which gives particulars of—
- (a) how the applicant complied with section 61Z of the 1990 Act;
- (b) any response to the consultation received from any person consulted under section 61Z(3) or (4) of the 1990 Act; and
- (c) the account taken of those responses.
- (2) The pre-application consultation report must include—
- (a) a copy of the notice referred to in article 2C(1)(a)(i);
- (b) a declaration that the notice referred to in article 2C(1)(a)(i) was displayed in accordance with the requirements of that article;
- (c) a list of the addresses of persons who were given notice of the proposed application in accordance with article 2C(1)(a)(ii) and a copy of the notice given to such persons;
- (d) copies of all notices given to community consultees and specialist consultees in accordance with articles 2D(2) and 2D(3);
- (e) a summary of all issues raised by any person notified of the proposed application in accordance with section 61Z(3) of the 1990 Act and articles 2C and 2D(2), including confirmation of whether the issues raised have been addressed, and, if so, how; and
- (f) copies of all responses received from specialist consultees with an explanation of the account taken of each response.
Consultations before the grant of section 73 applications
15ZA
- (1) This article applies in relation to a section 73 application other than a section 73 application which is an EIA application.
- (2) Before granting planning permission on an application in relation to which this article applies, the local planning authority may consult authorities or persons falling within a category set out in the Table in Schedule 4.
- (3) Where, by or under this article, a local planning authority consult any authority or person (“the consultee”) before granting planning permission—
- (a) they must, unless an applicant has served a copy of an application for planning permission on the consultee, give notice of the application to the consultee; and
- (b) they must not determine the application until at least 21 days after the date on which notice is given under sub-paragraph (a) or, if earlier, 21days after the date of service of a copy of the application on the consultee by the applicant.
- (4) The local planning authority must in determining the application take into account any representations received from a consultee.
Duty to respond to consultation
Duty to respond to consultation: annual reports
Consultation in respect of certain applications relating to planning permission; time periods
15C
The period specified for the purposes of section 100A(3)(a) of the 1990 Act is the period of 21 days , or 30 days in the case of an EIA application, in either case beginning with the day on which —
- (a) the document on which the views of the consultees are sought; or
- (b) where there is more than one document and they are sent on different days, the last of those documents, is received by the consultee.
Information to be provided by local planning authority
15D
The local planning authority must provide the following information to a statutory consultee for the purposes of or in connection with the consultation—
- (a) a copy of the application form relating to a relevant application;
- (b) the reference number allocated by the local planning authority to the original application;
- (c) any drawings in connection with the relevant application; and
- (d) any report in connection with the relevant application which is issued to the local planning authority.
Substantive response to consultation
15E
A substantive response for the purposes of section 100A(2) of the 1990 Act is a response which —
- (a) states that the consultee has no comment to make;
- (b) states that the consultee has no objection to the matters which are the subject of the consultation and refers the person consulting to current standing advice by the consultee on the subject of the consultation;
- (c) advises the person consulting of any concerns identified in relation to the matters which are the subject of the consultation and how those concerns can be addressed by the applicant; or
- (d) advises that the consultee objects to the matters which are the subject of the consultation and sets out the reasons for the objection.
Annual reports – compliance with consultation requirements
15F
- (1) Each statutory consultee who is consulted about a relevant application must give to the Welsh Ministers, not later than 1 July in each calendar year beginning with 1 July 2017, a report as to that consultee’s compliance with sections 100A(2) and (3) of the 1990 Act and article 15C.
- (2) The report must relate to the period of 12 months commencing on 1 April in the preceding calendar year (“the report year”).
- (3) The report must contain, in respect of the report year in question, a statement as to—
- (a) the number of occasions on which the consultee was consulted;
- (b) the number of occasions on which a substantive response was provided;
- (c) the number of occasions on which the consultee gave a substantive response outside the period prescribed for the purposes of section 100A(3) of the 1990 Act and a summary of the reasons why.
Representations by community councils before determination of applications
Notification of mineral applications
Revised notice of decision to grant planning permission
24A
- (1) Applicants are specified for the purposes of section 71ZA(5) of the 1990 Act.
- (2) For the purposes of section 71ZA(6) the details to be included in the revised version of the notice of a decision to grant planning permission are—
- (a) the reference number;
- (b) the date and effect of the decision;
- (c) the name of the body that made the decision; and
- (d) the revision number.
Notification of initiation of development and display of notice
24B
- (1) Planning permission for major development is specified for the purposes of section 71ZB(6) of the 1990 Act.
- (2) The notice to be given to a local planning authority before beginning any development to which a relevant planning permission relates, in accordance with section 71ZB(1) of the 1990 Act, must be in the form set out in Schedule 5A or in a form substantially to the like effect.
- (3) The notice to be displayed at all times when development to which a relevant planning permission relates is being carried out, in accordance with section 71ZB(2) of the 1990 Act, must—
- (a) be in the form set out in Schedule 5B or in a form substantially to the like effect;
- (b) be firmly affixed and displayed in a prominent place at or near the place where the development is being carried out;
- (c) be legible and easily visible to the public without having to enter the site; and
- (d) be printed on durable material.
- (4) Where the notice to be displayed is, without any fault or intention of the person carrying out development, removed, obscured or defaced, the person will be treated as having complied with the requirements of sub-paragraphs (b) and (c) of paragraph (3) if they have taken reasonable steps to protect the notice and, if need be, replace it.
Appeals against notice of non-validation
24C
- (1) An applicant who wishes to appeal to the Welsh Ministers under section 62ZB of the 1990 Act must give notice of appeal to the Welsh Ministers by—
- (a) serving on the Welsh Ministers, within the time limit specified in paragraph (2), a form obtained from the Welsh Ministers together with the documents referred to in paragraph (3); and
- (b) serving on the local planning authority, as soon as reasonably practicable, a copy of the form and the documents that are served on the Welsh Ministers.
- (2) The time limit mentioned in paragraph (1)(a) is two weeks from the date of the service of the notice pursuant to article 8(3A) or 23(5) stating that the application is invalid or such longer period as the Welsh Ministers may at any time allow.
- (3) For the purposes of paragraph (1)(a) the documents are—
- (a) in the case of an application for planning permission—
- (i) a copy of the notice served pursuant to article 8(3A) stating that the application is invalid;
- (ii) a copy of the application made to the local planning authority which has occasioned the appeal; and
- (iii) a copy of the forms, documents, plans, drawings, statements, declarations, certificates, particulars or evidence mentioned in articles 5 and 8(1) which were given to the authority in connection with the application before the date of the notice served pursuant to article 8(3A) stating that the application is invalid.
- (b) in the case of an application made under article 23—
- (i) a copy of the notice served pursuant to article 23(5) stating that the application is invalid;
- (ii) a copy of the application made to the local planning authority which has occasioned the appeal;
- (iii) a copy of the notice of the decision to grant planning permission, if any, pursuant to which the application is made; and
- (iv) a copy of the forms, documents, plans, drawings, statements, declarations, certificates, particulars or evidence (including such of them that are mentioned in article 4(1) where applicable) which were given to the authority in connection with the application before the date of the notice served pursuant to article 23(5) stating that the application is invalid.
- (c) Where sub-paragraph (b)(iii) applies and a revised version of the notice of the decision has been issued by the authority in accordance with section 71ZA(5) of the 1990 Act and article 24A, sub-paragraph (b)(iii) is to be read as referring to the revised version of the notice.
- (4) The Welsh Ministers may refuse to accept a notice of appeal from an applicant if the form and documents required under paragraph (1)(a) are not served on the Welsh Ministers within the time limit specified in paragraph (2).
- (5) The Welsh Ministers may provide, or arrange for the provision of, a website for use for such purposes as the Welsh Ministers think fit which—
- (a) relate to appeals under section 62ZB of the 1990 Act and this article, and
- (b) are capable of being carried out electronically.
- (6) Where a person gives notice of appeal to the Welsh Ministers using electronic communications, the provisions of article 32 apply.
Notice of appeal under section 78 of the 1990 Act
Appeals under section 78 of the 1990 Act
Appeal made under section 78 of the 1990 Act: Functions of a local planning authority
SCHEDULE 1B — PUBLICITY AND CONSULTATION BEFORE APPLYING FOR PLANNING PERMISSION
SCHEDULE 1C — CONSULTATION BEFORE APPLYING FOR PLANNING PERMISSION
Interpretation of Table
SCHEDULE 5A
SCHEDULE 5B
Reference of applications to the Welsh Ministers
Appeals under section 195 of the 1990 Act
26B
- (1) An applicant who wishes to appeal to the Welsh Ministers under section 195 of the 1990 Act (appeals against refusal or failure to give decision on application for a certificate of lawfulness of existing or proposed use or development) must give notice of appeal to the Welsh Ministers by—
- (a) serving on the Welsh Ministers a form obtained from the Welsh Ministers, together with—
- (i) such of the documents specified in paragraph (2) as are relevant to the appeal; and
- (ii) a full statement of case;
- (b) serving on the local planning authority a copy of the form mentioned in sub-paragraph (a), as soon as reasonably practicable, together with a copy of any relevant documents mentioned in paragraph (2)(d) and a copy of the full statement of case.
- (2) The documents mentioned in paragraph (1)(a)(i) are—
- (a) the application made to the local planning authority which occasioned the appeal;
- (b) all plans, drawings and documents sent to the authority in connection with the application;
- (c) all correspondence with the authority relating to the application;
- (d) any other plans, documents or drawings relating to the application which were not sent to the authority;
- (e) the notice of the decision or determination, if any.
- (3) For the purposes of section 195(1B) of the1990 Act the prescribed time within which an appeal must be made under section 195(1)(a) of that Act is 6 months from the date of the notice of the decision or determination giving rise to the appeal.
- (4) The Welsh Ministers may refuse to accept a notice of appeal—
- (a) under section 195(1)(a) of the 1990 Act if the documents required under paragraphs (1) and (2) are not served on the Welsh Ministers within the time prescribed in paragraph (3);
- (b) under section 195(1)(b) of the 1990 Act if the documents required under paragraphs (1) and (2) are not served on the Welsh Ministers.
- (5) The Welsh Ministers may provide, or arrange for the provision of, a website for use for such purposes as the Welsh Ministers think fit which—
- (a) relate to appeals under section 195 of the 1990 Act and this article, and
- (b) are capable of being carried out electronically.
- (6) Where a person gives notice of appeal to the Welsh Ministers using electronic communications, the provisions of article 32 apply.
Variation of applications after notice of appeal
26C
- (1) For the purposes of sections 78(4BA) and 195(1DA) of the 1990 Act the prescribed circumstance is the application to which the appeal relates contains a correctable error.
- (2) An application which is varied in the circumstance prescribed in paragraph (1) is subject to such further consultation as the Welsh Ministers consider appropriate.
- (3) In this article “correctable error” (“gwall cywiradwy”) means an error which—
- (a) is corrected in order to ensure consistency in the information contained in the application and the accompanying documents; and
- (b) does not alter the substance of the application.
Coronavirus: temporary modifications of this Part
2G
- (1) This Part applies with the modifications set out in this article where—
- (a) each of the notices that articles 2C(1)(a) and 2D(2) require an applicant to give in relation to a proposed application is given after the start of the emergency period, and
- (b) at least one of those notices is given before the end of the emergency period.
- (2) In this article, “the emergency period” means the period—
- (a) beginning with 19 May 2020, and
- (b) ending with 8 October 2021.
- (3) Article 2C(1) has effect as if—
- (a) in sub-paragraph (b), for “making the following information available for inspection at a location in the vicinity of the proposed development” there were substituted “making the following information available on a website”;
- (b) after sub-paragraph (b) there were inserted—
and (c) sending hard copies of the documents referred to in sub-paragraph (b) to any person who requests them, where the request is made within the period of 28 days mentioned in that sub-paragraph.
- (4) Article 2C has effect as if after paragraph (3) there were inserted—
(3A) If hard copies of any documents have been requested as mentioned in paragraph (1)(c), an application must not be submitted before the end of the period of 14 days beginning with the day on which the last document is sent in accordance with that paragraph.
- (5) Article 2C(5) has effect in relation to each notice given by the applicant under article 2C(1)(a) as if the reference to Schedule 1B were to Schedule 1D.
- (6) Article 2D(5)(a) has effect in relation to each notice given by the applicant under article 2D(2) as if the reference to Schedule 1B were to Schedule 1D.
- (7) Article 2F(2) has effect as if after sub-paragraph (c) there were inserted—
(ca) a declaration that the information referred to in sub-paragraph (b) of article 2C(1) was made available in accordance with that sub-paragraph; (cb) a statement setting out whether hard copies of any documents were requested as mentioned in sub-paragraph (c) of article 2C(1) and, if so, a declaration that the hard copies were sent in accordance with that sub-paragraph;
SCHEDULE 1D — PUBLICITY AND CONSULTATION BEFORE APPLYING FOR PLANNING PERMISSION: NOTICE TO BE GIVEN DURING EMERGENCY PERIOD
Enwi, cychwyn a chymhwyso
Dehongli
Ceisiadau am ganiatâd cynllunio amlinellol
Ceisiadau am gymeradwyo materion a gadwyd yn ôl
Ceisiadau am ganiatâd cynllunio
Ceisiadau mewn perthynas â thir y Goron
Datganiadau dylunio a mynediad
Darpariaethau cyffredinol ynglŷn â cheisiadau
Datganiad sydd i'w gyflwyno ynghyd â chais i awdurdod cynllunio lleol am ganiatâd cynllunio ar gyfer datblygiad cyfathrebiadau electronig penodol
Hysbysiadau o geisiadau am ganiatâd cynllunio
Tystysgrifau mewn perthynas â hysbysiadau o geisiadau am ganiatâd cynllunio
Cyhoeddusrwydd i geisiadau am ganiatâd cynllunio
Hysbysiad o atgyfeirio ceisiadau at Weinidogion Cymru
Ymgyngoriadau cyn rhoi caniatâd
Ymgyngoriadau cyn rhoi caniatâd cynllunio: datblygiad brys y Goron
Sylwadau gan gynghorau cymuned cyn penderfynu ceisiadau
Hysbysu ynghylch ceisiadau mwynau
Cyfarwyddiadau gan Weinidogion Cymru
Datblygiad sy'n effeithio ar briffyrdd presennol ac arfaethedig penodol
Datblygiad nad yw'n cydweddu â'r cynllun datblygu
Sylwadau sydd i'w cymryd i ystyriaeth
Cyfnodau amser ar gyfer penderfyniadau
Ceisiadau a wneir o dan amod cynllunio
Hysbysiad ysgrifenedig o benderfyniad neu ddyfarniad mewn perthynas â chais cynllunio
Hysbysiad o apêl
Apelau
Gorchmynion datblygu lleol
Tystysgrif cyfreithlondeb defnydd neu ddatblygiad
Cofrestr o geisiadau a gorchmynion datblygu lleol
Cofrestr o hysbysiadau gorfodi ac atal
Cyfarwyddiadau
Defnyddio cyfathrebiadau electronig
Dirymiadau, darpariaethau trosiannol ac arbedion
| Paragraff | Disgrifiad o’r Datblygiad | Ymgynghorai |
|---|---|---|
| (a) | Datblygiad sy’n debygol o effeithio ar dir yn ardal awdurdod cynllunio lleol arall | Yr awdurdod cynllunio lleol perthnasol |
| (b) | Datblygiad y gwnaed cais am ganiatâd cynllunio mewn perthynas ag ef i Weinidogion Cymru o dan adran 293A o Ddeddf 1990 (datblygiad brys y Goron: gwneud cais), pan fo’r datblygiad hwnnw’n debygol o effeithio ar dir yn ardal cyngor cymuned | Y cyngor cymuned |
| (c) | Datblygiad o fewn ardal yr hysbyswyd yr awdurdod cynllunio lleol yn ei chylch gan yr Awdurdod Gweithredol Iechyd a Diogelwch at ddibenion y ddarpariaeth hon oherwydd bod sylweddau gwenwynig, tra adweithiol, ffrwydrol neu fflamadwy yn bresennol yn y cyffiniau (ac eithrio ar safle niwclear perthnasol), a’r datblygiad yn cynnwys darparu—(i) llety preswyl;(ii) mwy na 250metr sgwâro arwynebedd llawr manwerthu;(iii) mwy na 500 metr sgwâro arwynebedd llawr swyddfa; neu(iv) mwy na 750 metr sgwâro arwynebedd llawr sydd i’w ddefnyddio ar gyfer proses ddiwydiannol,neu rywfodd arall yn debygol o achosi cynnydd sylweddol yn nifer y personau sy’n gweithio o fewn yr ardal yr hysbyswyd yn ei chylch, neu sy’n ymweld â’r ardal honno. | Yr Awdurdod Gweithredol Iechyd a Diogelwch |
| (d) | Datblygiad o fewn ardal yr hysbyswyd yr awdurdod cynllunio lleol yn ei chylch gan y Swyddfa Rheoleiddio Niwclear at ddibenion y ddarpariaeth hon oherwydd bod sylweddau gwenwynig, tra adweithiol, ffrwydrol neu fflamadwy yn bresennol yn y cyffiniau ar safle niwclear perthnasol, a’r datblygiad yn cynnwys darparu—(i) llety preswyl;(ii) mwy na 250 metr sgwâro arwynebedd llawr manwerthu;(iii) mwy na 500 metr sgwâro arwynebedd llawr swyddfa; neu(iv) mwy na 750 metr sgwâro arwynebedd llawr sydd i’w ddefnyddio ar gyfer proses ddiwydiannol,neu rywfodd arall yn debygol o achosi cynnydd sylweddol yn nifer y personau sy’n gweithio o fewn yr ardal yr hysbyswyd yn ei chylch, neu sy’n ymweld â’r ardal honno. | Y Swyddfa Rheoleiddio Niwclear |
| (e) | Datblygiad sy’n debygol o achosi cynnydd sylweddol ym maint y traffig, neu newid sylweddol yng nghymeriad y traffig— | |
| (i) sy’n ymuno neu’n ymadael â chefnffordd; neu | Gweinidogion Cymru | |
| (ii) yn defnyddio croesfan dros reilffordd | Gweithredwr y rhwydwaith sy’n cynnwys y rheilffordd o dan sylw, a Gweinidogion Cymru | |
| (f) | Datblygiad sy’n debygol o achosi cynnydd sylweddol ym maint y traffig, neu newid sylweddol yng nghymeriad y traffig sy’n ymuno neu’n ymadael â ffordd ddosbarthiadol neu briffordd arfaethedig | Yr awdurdod priffyrdd lleol perthnasol |
| (g) | Datblygiad sy’n debygol o amharu ar wella neu adeiladu ffordd ddosbarthiadol neu briffordd arfaethedig | Yr awdurdod priffyrdd lleol perthnasol |
| (h) | Datblygiad sy’n ymwneud â— | |
| (i) ffurfio, gosod neu addasu unrhyw fynedfa i briffordd (ac eithrio cefnffordd); neu | Yr awdurdod priffyrdd lleol perthnasol | |
| (ii) adeiladu priffordd neu fynedfa breifat i fangre, sy’n darparu mynediad i ffordd sydd â gorchymyn tollau mewn grym arni. | Yr awdurdod priffyrdd lleol perthnasol, ac yn achos ffordd sy’n ddarostyngedig i gonsesiwn, y consesiynydd | |
| (i) | Datblygiad sydd at y diben o osod neu adeiladu stryd newydd neu sy’n cynnwys gwaith o’r fath | Yr awdurdod priffyrdd lleol |
| (j) | Datblygiad, ac eithrio datblygiad gan ddeiliad tŷ, o fewn ardal yr hysbyswyd yr awdurdod cynllunio lleol yn ei chylch gan yr Awdurdod Glo at ddiben y ddarpariaeth hon, oherwydd y risg o ansefydlogrwydd a achosir gan fwyngloddio. | Yr Awdurdod Glo |
| (k) | Datblygiad sy’n ymwneud â, neu’n cynnwys, gweithrediadau mwyngloddio | Corff Adnoddau Naturiol Cymru |
| (l) | (i) Datblygiad sy’n cael effaith ffisegol uniongyrchol ar heneb gofrestredig.(ii) Datblygiad sy’n debygol o fod yn weladwy o heneb gofrestredig ac sy’n bodloni un o’r criteria canlynol—a) bod o fewn pellter o 0.5 cilometr o unrhyw bwynt ar berimedr heneb gofrestredig;b) bod o fewn pellter o 1 cilometr o berimedr heneb gofrestredig ac yn 15 metr o uchder neu’n uwch, neu gydag arwynebedd o 0.2 hectar neu fwy;c) bod o fewn pellter o 2 cilometr o berimedr heneb gofrestredig ac yn 50 metr o uchder neu’n uwch, neu gydag arwynebedd o 0.5 hectar neu fwy;d) bod o fewn pellter o 3 cilometr o berimedr heneb gofrestredig ac yn 75 metr o uchder neu’n uwch, neu gydag arwynebedd o 1 hectar neu fwy; neue) bod o fewn pellter o 5 cilometr o berimedr heneb gofrestredig ac yn 100 metr o uchder neu’n uwch, neu gydag arwynebedd o 1 hectar neu fwy.(iii) Datblygiad sy’n debygol o effeithio ar barc hanesyddol cofrestredig neu ardd hanesyddol gofrestredig neu leoliad parc neu ardd o’r fath;(iv) Datblygiad o fewn tirwedd hanesyddol gofrestredig pan fo Asesiad Effaith Amgylcheddol yn ofynnol; neu(v) Datblygiad sy’n debygol o effeithio ar werth cyffredinol eithriadol Safle Treftadaeth y Byd. | Gweinidogion Cymru |
| (m) | Datblygiad sy’n ymwneud â chyflawni gwaith neu weithrediadau ar wely neu ar lannau afon neu ffrwd | Corff Adnoddau Naturiol Cymru |
| (n) | Datblygiad at y diben o buro neu storio olewau mwynol a’u deilliadau | Corff Adnoddau Naturiol Cymru |
| (o) | Datblygiad sy’n ymwneud â chadw, trin neu waredu carthion, gwastraff masnachol, slyri neu slwtsh (ac eithrio gosod carthffosydd, adeiladu tai pwmpio mewn llinell o garthffosydd, adeiladu tanciau carthion neu garthbyllau sy’n gwasanaethu tai annedd sengl neu garafanau sengl neu adeiladau sengl lle na fydd mwy na deg o bobl fel arfer yn preswylio, gweithio neu ymgynnull, a gwaith sy’n ategol i hynny) | Corff Adnoddau Naturiol Cymru |
| (p) | Datblygiad sy’n ymwneud â defnyddio tir fel mynwent | Corff Adnoddau Naturiol CymruYr ymgymerwr dŵr a charthffosiaeth perthnasol |
| (q) | Datblygiad sydd—(i) mewn neu’n debygol o effeithio ar safle o ddiddordeb gwyddonol arbennig; neu(ii) mewn ardal yr hysbyswyd yr awdurdod cynllunio lleol yn ei chylch gan Gorff Adnoddau Naturiol Cymru ac sydd o fewn dau gilometr i safle o ddiddordeb gwyddonol arbennig y rhoddwyd hysbysiad ohoni, neu sy’n cael effaith fel pe bai hysbysiad ohoni wedi ei roi i’r awdurdod cynllunio lleol gan Gorff Adnoddau Naturiol Cymru, yn unol ag adran 28 o Ddeddf Bywyd Gwyllt a Chefn Gwlad 1981 (safleoedd o ddiddordeb gwyddonol arbennig) fel y’i cymhwysir yng Nghymru gan adran 27AA o’r Ddeddf honno | Corff Adnoddau Naturiol Cymru |
| (r) | Datblygiad sy’n ymwneud ag—(i) unrhyw dir sydd â theatr arno;(ii) datblygiad preswyl (ac eithrio datblygiad gan ddeiliad tŷ) o fewn 50 metr i theatr (nad yw’n dod o fewn paragraff (i)); neu(iii) theatr arfaethedig. | Yr Ymddiriedolaeth Theatrau |
| (s) | Datblygiad nad yw at ddibenion amaethyddol, nad yw’n unol â darpariaethau cynllun datblygu, ac sy’n golygu—(i) colli dim llai nag 20 hectar o dir amaethyddol graddau 1, 2 neu 3a a ddefnyddir ar y pryd (neu a ddefnyddiwyd ddiwethaf) at ddibenion amaethyddol; neu(ii) colli llai nag 20 hectar o dir amaethyddol graddau 1, 2 neu 3a a ddefnyddir ar y pryd (neu a ddefnyddiwyd ddiwethaf) at ddibenion amaethyddol, mewn amgylchiadau pan fo’r datblygiad yn debygol o arwain at golled bellach o dir amaethyddol a fyddai’n peri bod y golled gronnus o dir amaethyddol yn 20 hectar neu’n fwy. | Gweinidogion Cymru |
| (t) | Datblygiad sydd o fewn 250 metr i dir—(i) a ddefnyddir, neu sydd wedi ei ddefnyddio ar unrhyw adeg yn ystod y cyfnod o 30 mlynedd cyn y cais perthnasol, ar gyfer dyddodi sbwriel neu wastraff ; a(ii) yr hysbyswyd Gweinidogion Cymru yn ei gylch gan Gorff Adnoddau Naturiol Cymru at ddibenion y ddarpariaeth hon | Corff Adnoddau Naturiol Cymru |
| (u) | Datblygiad—(i) sy’n debygol o amharu ar ddefnyddio tir, neu arwain at golli’r defnydd o dir, a ddefnyddir fel maes chwarae; neu(ii) sydd ar dir—(aa) a ddefnyddiwyd fel maes chwarae ar unrhyw adeg yn ystod y 5 mlynedd cyn gwneud y cais perthnasol ac sy’n parhau heb ei ddatblygu; neu(bb) a ddyrannwyd ar gyfer ei ddefnyddio fel maes chwarae mewn cynllun datblygu neu mewn cynigion ar gyfer cynllun o’r fath neu ar gyfer ei addasu neu ei amnewid; neu(iii) sy’n golygu gosod arwyneb artiffisial, arwyneb o wneuthuriad dynol neu arwyneb cyfansawdd ar lain chwarae yn lle arwyneb o laswellt | Cyngor Chwaraeon Cymru |
| (v) | Datblygiad sy’n debygol o effeithio ar—(i) unrhyw ddyfrffordd fewndirol (boed naturiol neu artiffisial) neu gronfa ddŵr sy’n eiddo i’r Canal and River Trust neu a reolir ganddi; neu(ii) unrhyw sianel gyflenwi, cwrs dŵr, dihangfa dŵr neu gwlfert ar gyfer camlas, sydd o fewn ardal yr hysbyswyd yr awdurdod cynllunio lleol yn ei chylch at ddibenion y ddarpariaeth hon gan y Canal and River Trust. | The Canal and River Trust |
| (w) | Datblygiad—(i) sy’n ymwneud â lleoli sefydliadau newydd;(ii) sydd at y diben o addasu sefydliadau presennol sydd o fewn cwmpas Erthygl 11 o Gyfarwyddeb 2012/18/EU; neu(iii) sydd yn newydd, gan gynnwys llwybrau trafnidiaeth, lleoliadau a ddefnyddir gan y cyhoedd ac ardaloedd preswyl yng nghyffiniau sefydliadau presennol, lle y gallai lleoli neu ddatblygu achosi neu gynyddu’r risg o ddamwain fawr, neu ychwanegu at ganlyniadau damwain fawr. | Yr awdurdod cymwys rheoli peryglon damweiniau mawr, ac mewn perthynas â datblygiad sy’n dod o fewn paragraff (iii), unrhyw berson sydd â rheolaeth o’r tir y lleolir arno unrhyw sefydliad presennol o dan sylw, yn ôl y gofrestr a gedwir gan yr awdurdod sylweddau peryglus o dan reoliad 22 o Reoliadau Cynllunio (Sylweddau Peryglus) (Cymru) 2015 |
| (x) | Datblygiad—(i) ar dir a ddynodwyd yn Barth Llifogydd C2;(ii) sy’n ymwneud â, neu sy’n cynnwys, datblygiad gwasanaethau brys neu ddatblygiad a all fod mewn perygl mawr, ar dir a ddynodwyd yn Barth Llifogydd C1 neu ar dir yr hysbyswyd yr awdurdod cynllunio lleol yn ei gylch gan Gorff Adnoddau Naturiol Cymru at ddiben y ddarpariaeth hon. | Corff Adnoddau Naturiol Cymru |
| (y) | Datblygiad—(i) sy’n ymwneud â datblygiad preswyl newydd (gan gynnwys unedau sengl); a(ii) sy’n ddatblygiad mawr nad yw’n dod o fewn paragraff (i). | Yr ymgymerwr dŵr a charthffosiaeth perthnasol |
Dehongli’r Tabl
Apelau i Weinidogion Cymru
Hysbysiadau Prynu
Ceisiadau am newidiadau amherthnasol i ganiatâd cynllunio
Datblygiad i gynnwys gweithrediadau mewnol penodol
Dyletswydd i ymateb i ymgynghoriad
Dyletswydd i ymateb i ymgynghoriad: adroddiadau blynyddol
Sylwadau gan gynghorau cymuned cyn penderfynu ceisiadau
Hysbysu ynghylch ceisiadau mwynau
Apêl a wnaed: Swyddogaethau awdurdod cynllunio lleol
Siopau
Gwasanaethau ariannol a phroffesiynol
Bwyd a diod
Gofyniad i gynnal ymgynghoriad cyn-ymgeisio
Cyhoeddusrwydd cyn gwneud cais am ganiatâd cynllunio
Ymgynghori cyn gwneud cais am ganiatâd cynllunio
Dyletswydd i ymateb i ymgynghoriad cyn-ymgeisio: ymgyngoreion arbenigol
Adroddiadau ar ymgynghoriad cyn-ymgeisio
Ymgyngoriadau cyn caniatáu ceisiadau adran 73
Dyletswydd i ymateb i ymgynghoriad
Dyletswydd i ymateb i ymgynghoriad: adroddiadau blynyddol
Ymgynghori mewn cysylltiad â cheisiadau penodol yn ymwneud â chaniatâd cynllunio: cyfnodau amser
Gwybodaeth sydd i’w darparu gan awdurdod cynllunio lleol
Ymateb o sylwedd i ymgynghoriad
Adroddiadau blynyddol – cydymffurfiaeth â gofynion ymgynghori
Sylwadau gan gynghorau cymuned cyn penderfynu ceisiadau
Hysbysu ynghylch ceisiadau mwynau
Hysbysiad diwygiedig o benderfyniad i roi caniatâd cynllunio
Hysbysu ynghylch cychwyn datblygiad ac arddangos hysbysiad
Apelau yn erbyn hysbysiad o farnu’n annilys
Hysbysiad o apêl o dan adran 78 o Ddeddf 1990
Apelau o dan adran 78 o Ddeddf 1990
Apêl a wnaed o dan adran 78 o Ddeddf 1990: Swyddogaethau awdurdod cynllunio lleol
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.