§ 2348. Project acceleration
§ 2348. Project acceleration
(a) Definitions In this section:
(1) Environmental impact statement The term “environmental impact statement” means the detailed statement of environmental impacts of a project required to be prepared pursuant to the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).
(2) Environmental review process
(A) In general The term “environmental review process” means the process of preparing an environmental impact statement, environmental assessment, categorical exclusion, or other document under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) for a project study.
(B) Inclusions The term “environmental review process” includes the process for and completion of any environmental permit, approval, review, or study required for a project study under any Federal law other than the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).
(3) Federal jurisdictional agency The term “Federal jurisdictional agency” means a Federal agency with jurisdiction delegated by law, regulation, order, or otherwise over a review, analysis, opinion, statement, permit, license, or other approval or decision required for a project study under applicable Federal laws (including regulations).
(4) Federal lead agency The term “Federal lead agency” means the Corps of Engineers.
(5) Project The term “project” means a water resources development project to be carried out by the Secretary.
(6) Project sponsor The term “project sponsor” has the meaning given the term “non-Federal interest” in section 1962d–5b(b) of title 42.
(7) Project study The term “project study” means a feasibility study for a project carried out pursuant to section 2282 of this title.
(b) Applicability
(1) In general This section—
(A) shall apply to each project study that is initiated after June 10, 2014, and for which an environmental impact statement is prepared under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); and
(B) may be applied, to the extent determined appropriate by the Secretary, to other project studies initiated after June 10, 2014, and for which an environmental review process document is prepared under that Act.
(2) Flexibility Any authority granted under this section may be exercised, and any requirement established under this section may be satisfied, for the conduct of an environmental review process for a project study, a class of project studies, or a program of project studies.
(3) List of project studies
(A) In general The Secretary shall annually prepare, and make publicly available, a separate list of each study that the Secretary has determined—
(i) meets the standards described in paragraph (1); and
(ii) does not have adequate funding to make substantial progress toward the completion of the project study.
(B) Inclusions The Secretary shall include for each project study on the list under subparagraph (A) a description of the estimated amounts necessary to make substantial progress on the project study.
(c) Project review process
(1) In general The Secretary shall develop and implement a coordinated environmental review process for the development of project studies.
(2) Coordinated review The coordinated environmental review process described in paragraph (1) shall require that any review, analysis, opinion, statement, permit, license, or other approval or decision issued or made by a Federal, State, or local governmental agency or an Indian tribe for a project study described in subsection (b) be conducted, to the maximum extent practicable, concurrently with any other applicable governmental agency or Indian tribe.
(3) Timing The coordinated environmental review process under this subsection shall be completed not later than the date on which the Secretary, in consultation and concurrence with the agencies identified under subsection (e), establishes with respect to the project study.
(d) Lead agencies
(1) Joint lead agencies
(A) In general At the discretion of the Secretary and subject to the requirements of the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) and the requirements of section 1506.8 of title 40, Code of Federal Regulations (or successor regulations), including the concurrence of the proposed joint lead agency, a project sponsor may serve as the joint lead agency.
(B) Project sponsor as joint lead agency A project sponsor that is a State or local governmental entity may—
(i) with the concurrence of the Secretary, serve as a joint lead agency with the Federal lead agency for purposes of preparing any environmental document under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); and
(ii) prepare any environmental review process document under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) required in support of any action or approval by the Secretary if—
(I) the Secretary provides guidance in the preparation process and independently evaluates that document;
(II) the project sponsor complies with all requirements applicable to the Secretary under—
(aa) the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.);
(bb) any regulation implementing that Act; and
(cc) any other applicable Federal law; and
(III) the Secretary approves and adopts the document before the Secretary takes any subsequent action or makes any approval based on that document, regardless of whether the action or approval of the Secretary results in Federal funding.
(2) Duties The Secretary shall ensure that—
(A) the project sponsor complies with all design and mitigation commitments made jointly by the Secretary and the project sponsor in any environmental document prepared by the project sponsor in accordance with this subsection; and
(B) any environmental document prepared by the project sponsor is appropriately supplemented to address any changes to the project the Secretary determines are necessary.
(3) Adoption and use of documents Any environmental document prepared in accordance with this subsection shall be adopted and used by any Federal agency making any determination related to the project study to the same extent that the Federal agency could adopt or use a document prepared by another Federal agency under—
(A) the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); and
(B) parts 1500 through 1508 of title 40, Code of Federal Regulations (or successor regulations).
(4) Roles and responsibility of lead agency With respect to the environmental review process for any project study, the Federal lead agency shall have authority and responsibility—
(A) to take such actions as are necessary and proper and within the authority of the Federal lead agency to facilitate the expeditious resolution of the environmental review process for the project study; and
(B) to prepare or ensure that any required environmental impact statement or other environmental review document for a project study required to be completed under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) is completed in accordance with this section and applicable Federal law.
(e) Participating and cooperating agencies
(1) Identification of jurisdictional agencies With respect to carrying out the environmental review process for a project study, the Secretary shall identify, as early as practicable in the environmental review process, all Federal, State, and local government agencies and Indian tribes that may—
(A) have jurisdiction over the project;
(B) be required by law to conduct or issue a review, analysis, opinion, or statement for the project study; or
(C) be required to make a determination on issuing a permit, license, or other approval or decision for the project study.
(2) State authority If the environmental review process is being implemented by the Secretary for a project study within the boundaries of a State, the State, consistent with State law, may choose to participate in the process and to make subject to the process all State agencies that—
(A) have jurisdiction over the project;
(B) are required to conduct or issue a review, analysis, opinion, or statement for the project study; or
(C) are required to make a determination on issuing a permit, license, or other approval or decision for the project study.
(3) Invitation
(A) In general The Federal lead agency shall invite, as early as practicable in the environmental review process, any agency identified under paragraph (1) to become a participating or cooperating agency, as applicable, in the environmental review process for the project study.
(B) Deadline An invitation to participate issued under subparagraph (A) shall set a deadline by which a response to the invitation shall be submitted, which may be extended by the Federal lead agency for good cause.
(4) Procedures Section 1501.6 of title 40, Code of Federal Regulations (as in effect on June 10, 2014) shall govern the identification and the participation of a cooperating agency.
(5) Federal cooperating agencies Any Federal agency that is invited by the Federal lead agency to participate in the environmental review process for a project study shall be designated as a cooperating agency by the Federal lead agency unless the invited agency informs the Federal lead agency, in writing, by the deadline specified in the invitation that the invited agency—
(A)
(i)
(I) has no jurisdiction or authority with respect to the project;
(II) has no expertise or information relevant to the project; or
(III) does not have adequate funds to participate in the project; and
(ii) does not intend to submit comments on the project; or
(B) does not intend to submit comments on the project.
(6) Administration A participating or cooperating agency shall comply with this section and any schedule established under this section.
(7) Effect of designation Designation as a participating or cooperating agency under this subsection shall not imply that the participating or cooperating agency—
(A) supports a proposed project; or
(B) has any jurisdiction over, or special expertise with respect to evaluation of, the project.
(8) Concurrent reviews Each participating or cooperating agency shall—
(A) carry out the obligations of that agency under other applicable law concurrently and in conjunction with the required environmental review process, unless doing so would prevent the participating or cooperating agency from conducting needed analysis or otherwise carrying out those obligations; and
(B) formulate and implement administrative, policy, and procedural mechanisms to enable the agency to ensure completion of the environmental review process in a timely, coordinated, and environmentally responsible manner.
(f) Programmatic compliance
(1) In general The Secretary shall issue guidance regarding the use of programmatic approaches to carry out the environmental review process that—
(A) eliminates repetitive discussions of the same issues;
(B) focuses on the actual issues ripe for analyses at each level of review;
(C) establishes a formal process for coordinating with participating and cooperating agencies, including the creation of a list of all data that is needed to carry out an environmental review process; and
(D) complies with—
(i) the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); and
(ii) all other applicable laws.
(2) Requirements In carrying out paragraph (1), the Secretary shall—
(A) as the first step in drafting guidance under that paragraph, consult with relevant Federal, State, and local governmental agencies, Indian tribes, and the public on the appropriate use and scope of the programmatic approaches;
(B) emphasize the importance of collaboration among relevant Federal, State, and local governmental agencies, and Indian tribes in undertaking programmatic reviews, especially with respect to including reviews with a broad geographical scope;
(C) ensure that the programmatic reviews—
(i) promote transparency, including of the analyses and data used in the environmental review process, the treatment of any deferred issues raised by Federal, State, and local governmental agencies, Indian tribes, or the public, and the temporal and special scales to be used to analyze those issues;
(ii) use accurate and timely information in the environmental review process, including—
(I) criteria for determining the general duration of the usefulness of the review; and
(II) the timeline for updating any out-of-date review;
(iii) describe—
(I) the relationship between programmatic analysis and future tiered analysis; and
(II) the role of the public in the creation of future tiered analysis; and
(iv) are available to other relevant Federal, State, and local governmental agencies, Indian tribes, and the public;
(D) allow not fewer than 60 days of public notice and comment on any proposed guidance; and
(E) address any comments received under subparagraph (D).
(g) Coordinated reviews
(1) Coordination plan
(A) Establishment
(i) In general The Federal lead agency shall, after consultation with and with the concurrence of each participating and cooperating agency and the project sponsor or joint lead agency, as applicable, establish a plan for coordinating public and agency participation in, and comment on, the environmental review process for a project study or a category of project studies.
(ii) Incorporation The plan established under clause (i) shall be incorporated into the project schedule milestones set under section 2282(g)(2) of this title.
(B) Schedule
(i) In general As soon as practicable but not later than 45 days after the close of the public comment period on a draft environmental impact statement, the Federal lead agency, after consultation with and the concurrence of each participating and cooperating agency and the project sponsor or joint lead agency, as applicable, shall establish, as part of the coordination plan established in subparagraph (A), a schedule for completion of the environmental review process for the project study.
(ii) Factors for consideration In establishing a schedule, the Secretary shall consider factors such as—
(I) the responsibilities of participating and cooperating agencies under applicable laws;
(II) the resources available to the project sponsor, joint lead agency, and other relevant Federal and State agencies, as applicable;
(III) the overall size and complexity of the project;
(IV) the overall schedule for and cost of the project; and
(V) the sensitivity of the natural and historical resources that could be affected by the project.
(iii) Modifications The Secretary may—
(I) lengthen a schedule established under clause (i) for good cause; and
(II) shorten a schedule only with concurrence of the affected participating and cooperating agencies and the project sponsor or joint lead agency, as applicable.
(iv) Dissemination A copy of a schedule established under clause (i) shall be—
(I) provided to each participating and cooperating agency and the project sponsor or joint lead agency, as applicable; and
(II) made available to the public.
(2) Comment deadlines The Federal lead agency shall establish the following deadlines for comment during the environmental review process for a project study:
(A) Draft environmental impact statements For comments by Federal and States 11 So in original. Probably should be “State”. agencies and the public on a draft environmental impact statement, a period of not more than 60 days after publication in the Federal Register of notice of the date of public availability of the draft environmental impact statement, unless—
(i) a different deadline is established by agreement of the Federal lead agency, the project sponsor or joint lead agency, as applicable, and all participating and cooperating agencies; or
(ii) the deadline is extended by the Federal lead agency for good cause.
(B) Other environmental review processes For all other comment periods established by the Federal lead agency for agency or public comments in the environmental review process, a period of not more than 30 days after the date on which the materials on which comment is requested are made available, unless—
(i) a different deadline is established by agreement of the Federal lead agency, the project sponsor, or joint lead agency, as applicable, and all participating and cooperating agencies; or
(ii) the deadline is extended by the Federal lead agency for good cause.
(3) Deadlines for decisions under other laws In any case in which a decision under any Federal law relating to a project study, including the issuance or denial of a permit or license, is required to be made by the date described in subsection (h)(5)(B)(ii), the Secretary shall submit to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives—
(A) as soon as practicable after the 180-day period described in subsection (h)(5)(B)(ii), an initial notice of the failure of the Federal agency to make the decision; and
(B) every 60 days thereafter until such date as all decisions of the Federal agency relating to the project study have been made by the Federal agency, an additional notice that describes the number of decisions of the Federal agency that remain outstanding as of the date of the additional notice.
(4) Involvement of the public Nothing in this subsection reduces any time period provided for public comment in the environmental review process under applicable Federal law (including regulations).
(5) Transparency reporting
(A) Reporting requirements Not later than 1 year after June 10, 2014, the Secretary shall establish and maintain an electronic database and, in coordination with other Federal and State agencies, issue reporting requirements to make publicly available the status and progress with respect to compliance with applicable requirements of the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et. seq.) and any other Federal, State, or local approval or action required for a project study for which this section is applicable.
This document does not substitute reading the official United States Code published by the Office of the Law Revision Counsel. We assume no responsibility for any inaccuracies resulting from the conversion to this format.