Commission Regulation (EU) No 651/2014 of 17 June 2014 declaring certain categories of aid compatible with the internal market in application of Articles 107 and 108 of the Treaty Text with EEA relevance

Type Regulation
Publication 2014-06-26
Last updated 2023-07-01
State In force
Department European Commission
Source EUR-Lex
articles 90
Reform history JSON API
  • (124) ‘energy efficient district heating and cooling’ means efficient district heating and cooling as defined in Article 2, point (41), of Directive 2012/27/EU;
  • (124a) ‘district heating’ and ‘district cooling’ means district heating or district cooling as defined in Article 2, point (19), of Directive 2010/31/EU;
  • (124b) ‘district heating and cooling systems’, means heating and/or cooling generation facilities, thermal storage and distribution network, comprising both primary – transmission – and secondary network of pipelines, to supply heating or cooling to consumers. Reference to district heating is to be interpreted as district heating and/or cooling systems, depending on whether the networks supply heat or cooling jointly or separately;
  • (125) ‘polluter’ means someone who directly or indirectly damages the environment or who creates conditions leading to such damage.
  • (126) ‘re-use’ means re-use as defined in Article 3, point (13), of Directive 2008/98/EC of the European Parliament and of the Council ([^E0035]);
  • (127) ‘preparing for re-use’ means preparing for re-use as defined in Article 3, point (16), of Directive 2008/98/EC;
  • (128) ‘recycling’ means recycling as defined in Article 3, point (17), of Directive 2008/98/EC;
  • (128a) ‘resource efficiency’ means reducing the quantity of inputs needed to produce a unit of output or substituting primary inputs with secondary inputs;
  • (128b) ‘waste’ means waste as defined in Article 3, point (1), of Directive 2008/98/EC;
  • (128c) ‘waste heat’ means waste heat as defined in Article 2, point (9), of Directive (EU) 2018/2001;
  • (128d) ‘treatment’ means treatment as defined in Article 3, point (14), of Directive 2008/98/EC as well as treatment of other products, materials, or substances;
  • (128e) ‘recovery’ means recovery as defined in Article 3, point (15), of Directive 2008/98/EC as well as recovery of other products, materials or substances;
  • (128f) ‘disposal’ means disposal as defined in Article 3, point (19), of Directive 2008/98/EC;
  • (128g) ‘other products, materials or substances’ means materials, products and substances other than waste, including by-products referred to in Article 5 of Directive 2008/98/EC, agricultural and forestry residues, waste water, rain water and runoff water, minerals, nutrients, residual gases from production processes, and redundant products, parts and materials;
  • (128h) ‘redundant products, parts and materials’ means products, parts or materials that are no longer needed by or useful for its holder but are suitable for re-use;
  • (128i) ‘separate collection’ means separate collection as defined in Article 3, point (11), of Directive 2008/98/EC;
  • (130) ‘energy infrastructure’ means any physical equipment or facility which is located within the Union or linking the Union to one or more third countries and falling under the following categories:
  • (a) electricity:
  • (i) transmission and distribution systems, where ‘transmission’ means the transport of electricity onshore as well as offshore on the extra high-voltage and high-voltage interconnected system with a view to its delivery to final customers or to distributors, but does not include supply and ‘distribution’ means the transport of electricity onshore as well as offshore on high-voltage, medium-voltage and low-voltage distribution systems with a view to its delivery to customers, but does not include supply;
  • (ii) any equipment or installation essential for the systems referred to in point (i) to operate safely, securely and efficiently, including protection, monitoring and control systems at all voltage levels and substations;
  • (iii) fully integrated network components, as defined in Article 2, point (51), of Directive (EU) 2019/944 of the European Parliament and of the Council ([^E0036]);
  • (iv) smart electricity grids, which means systems and components integrating information and communications technology, through operational digital platforms, control systems and sensor technologies both at transmission and distribution level, aiming at a more secure, efficient and intelligent electricity transmission and distribution network, increased capacity to integrate new forms of generation, storage and consumption and facilitating new business models and market structures;
  • (v) off-shore electricity grids, which means any equipment or installation of electricity transmission or distribution infrastructure as defined in point (i), which has dual functionality: interconnection and transmission or distribution of offshore renewable electricity from the offshore generation sites to two or more countries. This also includes smart grids as well as any offshore adjacent equipment or installation essential to operate safely, securely and efficiently, including protection, monitoring and control systems, and necessary substations if they also ensure technology interoperability and among other interface compatibility between different technologies;
  • (b) gas (natural gas, biogas- including biomethane – and/or renewable gas of non-biological origin):
  • (i) transmission and distribution pipelines for the transport of gas that form part of a network, excluding high-pressure pipelines used for upstream distribution of natural gas;
  • (ii) underground storage facilities connected to the high-pressure gas pipelines referred to in point (i);
  • (iii) reception, storage and regasification or decompression facilities for liquefied or compressed gas;
  • (iv) any equipment or installation essential for the system to operate safely, securely and efficiently or to enable bi-directional capacity, including compressor stations;
  • (v) smart gas grids, which means any of the following equipment or installation aiming at enabling and facilitating the integration of renewable and low-carbon gases (including hydrogen or gases of non-biological origin) into the network: digital systems and components integrating information and communication technologies, control systems and sensor technologies to enable the interactive and intelligent monitoring, metering, quality control and management of gas production, transmission, distribution and consumption within a gas network. Furthermore, smart grids may also include equipment to enable reverse flows from the distribution to the transmission level and related necessary upgrades to the existing network;
  • (c) hydrogen:
  • (i) transmission pipelines, for the high-pressure transport of hydrogen, as well as distribution pipelines for the local distribution of hydrogen, giving access to multiple network users on a transparent and non-discriminatory basis;
  • (ii) storage facilities, which means facilities used for the stocking of hydrogen of a high grade of purity, including the part of a hydrogen terminal used for storage but excluding the portion used for production operations, and including facilities reserved exclusively for hydrogen network operators in carrying out their functions. Hydrogen storage facilities include underground storage facilities connected to the high-pressure hydrogen pipelines referred to in point (i);
  • (iii) dispatch, reception, storage and regasification or decompression facilities for hydrogen or hydrogen embedded in other chemical substances with the objective of injecting the hydrogen into the grid either for gas or dedicated to hydrogen;
  • (iv) terminals, which means installations used for the transformation of liquid hydrogen into gaseous hydrogen for injection into the hydrogen network. Terminals include ancillary equipment and temporary storage necessary for the transformation process and subsequent injection into the hydrogen network, but does not include any part of the hydrogen terminal used for storage;
  • (v) interconnectors, which means a hydrogen network (or part thereof) which crosses or spans a border between Member States, or between a Member State and a third country up to the territory of the Member States or the territorial sea of that Member State;
  • (vi) any equipment or installation essential for the hydrogen system to operate safely, securely and efficiently or to enable bi-directional capacity, including compressor stations; Any of the assets listed under points (i) to (vi) may be newly constructed assets or assets converted from natural gas to hydrogen, or a combination of the two. Assets listed under points (i) to (vi), which are subject to third party access shall qualify as energy infrastructure;
  • (d) carbon dioxide:
  • (i) pipelines, other than upstream pipeline network, used to transport carbon dioxide from more than one source, this is to say, industrial installations (including power plants) that produce carbon dioxide gas from combustion or other chemical reactions involving fossil or non-fossil carbon-containing compounds, for the purpose of permanent geological storage of carbon dioxide pursuant to Article 3 of Directive 2009/31/EC of the European Parliament and of the Council ([^E0037]) or for the purpose of use of carbon dioxide as feedstock or to enhance the yields of biological processes;
  • (ii) facilities for liquefaction and buffer storage of carbon dioxide in view of its transport or storage. This does not include infrastructure within a geological formation used for the permanent geological storage of carbon dioxide pursuant to Article 3 of Directive 2009/31/EC and associated surface and injection facilities;
  • (iii) any equipment or installation essential for the system in question to operate properly, securely and efficiently, including protection, monitoring and control systems. This may include dedicated mobile assets for the transport and storage of carbon dioxide, provided that such mobile assets fulfil the definition of a clean vehicle; Assets listed under points (i), (ii) and (iii) which are subject to third party access shall qualify as energy infrastructure;
  • (e) infrastructure used for transmission or distribution of thermal energy in the form of steam, hot water or chilled liquids from multiple producers or users, based on use of renewable energy or waste heat from industrial applications;
  • (f) Projects of Common Interest, as defined in Article 2, point (4), of Regulation (EU) No 347/2013 of the European Parliament and of the Council ([^E0038]) and project of mutual interest referred to in Article 171 of the Treaty;
  • (g) other infrastructure categories that enable physical or wireless connection of renewable or carbon-free energy between producers and users from multiple access and exit points and which are open to access by third parties not belonging to the infrastructure owner or manager undertakings; Assets listed under points (a) to (g) which are built for one or a small group of ex ante identified users and tailored to their needs (‘dedicated infrastructure’) shall not qualify as energy infrastructure.
  • (130a) ‘distribution system operator’ (DSO) means a distribution system operator as defined in Article 2, point (29), of Directive (EU) 2019/944;
  • (130b) ‘transmission system operator’ (TSO) means a transmission system operator as defined in Article 2, point (35), of Directive (EU) 2019/944;
  • (130c) ‘electricity storage’ means deferring the final use of electricity to a moment later than when it was generated, or the conversion of electrical energy into a form of energy which can be stored, the storing of such energy, and the subsequent reconversion of such energy into electrical energy;
  • (130d) ‘thermal storage’ means deferring the final use of thermal energy to a moment later than when it was generated, or the conversion of electrical or thermal energy into a form of energy which can be stored, the storing of such energy, and, where appropriate, the subsequent conversion or reconversion of such energy into thermal energy for final use (i.e., heating or cooling);
  • (131) ‘internal energy market legislation’ means Directive (EU) 2019/944, Directive 2009/73/EC of the European Parliament and of the Council ([^E0039]), Regulation (EU) 2019/943 and Regulation (EC) No 715/2009 of the European Parliament and of the Council ([^E0040]);
  • (131a) ‘carbon capture and storage’ or ‘CCS’ means a set of technologies that make it possible to capture the CO2 emitted from industrial plants, including process-inherent emissions, or to capture it directly from ambient air, to transport it to a storage site and inject it in suitable underground geological formations for the purpose of permanent storage;
  • (131b) ‘carbon capture and use’ or ‘CCU’ means a set of technologies that make it possible to capture the CO2 emitted from industrial plants, including process-inherent emissions, or to capture it directly from ambient air, and to transport it to a CO2-consumption or utilisation site for full usage of that CO2;

Definitions applying to social aid for transport for residents of remote regions

  • (132) ‘normal residence’ means the place where a natural person lives for at least 185 days, in each calendar year, because of personal and occupational ties; in the case of a person whose occupational ties are in a different place from his/her personal ties and who lives in two or more Member States, the place of normal residence is regarded as the place of his/her personal ties provided that he/she returns there regularly; where a person is living in a Member State in order to carry out a task of a set duration, the place of residence is still regarded as being the place of his/her personal ties, irrespective of whether he/she returns there during the course of this activity; attendance at a university or school in another Member State does not constitute a transfer of normal residence; alternatively, ‘normal residence’ shall have the meaning attributed to it in Member States' national law.

Definitions for aid for broadband infrastructures

  • (135) ‘ducts’ means underground pipes or conduits used to house (fibre, copper or coax) cables of a broadband network.
  • (136) ‘physical unbundling’ grants access to the end-consumer access line and allows competitors' own transmission systems to directly transmit over it.
  • (137) ‘broadband infrastructure’ means a broadband network without any active component and comprises the physical infrastructure, including ducts, poles, masts, towers, dark fibre, cabinets and cables (including dark fibre and copper cables);
  • (137a) ‘backhaul network’ means the part of a broadband network that connects the access network to the backbone network and which does not provide direct access to end-users. It is the part of the network where the traffic of end users is aggregated;
  • (137b) ‘backbone network’ means the core network that interconnects backhaul networks from different areas or regions;
  • (137c) ‘access network’ means the segment of a broadband network that connects the backhaul network with the end users’ premises or devices;
  • (139) ‘wholesale access’ means access which enables an operator to utilise the facilities of another operator. The wholesale access shall include, on the basis of the current technological developments, at least the following access products: (i) for FTTx networks: access to the broadband infrastructure, unbundling and bitstream access; (ii) for cable networks: access to the broadband infrastructure and access to active services; (iii) for fixed wireless networks: access to the broadband infrastructure and access to active services; (iv) for mobile networks: access to the broadband infrastructure and access to active services (at least roaming); (v) for satellite platforms: access to active services; (vi) for backhaul networks: access to the broadband infrastructure and access to active services;
  • (139a) ‘premises passed’ means end-user premises to which, upon request from end-users and within 4 weeks from the date of request, a provider can provide broadband services (regardless of whether these premises are already connected or not connected to the network). The price charged for the provision of broadband services at the end users’ premises in this case must not exceed normal connection fees, meaning it must not include any additional or exceptional cost as compared to the standard commercial practice and, in any case, must not exceed the usual price in the Member State concerned. That price must be determined by the competent national authority;
  • (139b) ‘socioeconomic drivers’ means entities which by their mission, nature or location can directly or indirectly generate important socioeconomic benefits to citizens, business and local communities located in their surrounding territory or in their area of influence, including among others public authorities, public or private entities entrusted with the operation of services of general interest or of services of general economic interest as set out in Article 106(2) of the Treaty and digitally intensive enterprises;
  • (139c) ‘5G corridor’ means a transport path, road, railway or inland waterway, fully covered with digital connectivity infrastructure, in particular 5G systems, and enabling the uninterrupted provision of synergy digital services as defined in Regulation (EU) 2021/1153 of the European Parliament and of the Council ([^E0041]), such as connected and automated mobility, similar smart mobility services for railways or digital connectivity on inland waterways;
  • (139d) ‘peak-time’ means the time of the day with a typical duration of one hour where the network load is usually at its maximum;
  • (139e) ‘peak-time conditions’ means the conditions under which the network is expected to operate at ‘peak-time’;
  • (139f) ‘relevant time horizon’ means a time horizon used for verifying planned private investments and corresponds to the time frame that the Member State estimates for deploying the planned State funded network, starting from the moment of publication of the public consultation on the planned State intervention until the entry into operation of the network (i.e. start of the provision of wholesale and/or retail services on the State funded network). The relevant time horizon cannot be shorter than 2 years;

Definitions for aid for culture and heritage conservation

  • (140) ‘difficult audiovisual works’: means the works identified as such by Member States on the basis of pre-defined criteria when setting up schemes or granting the aid and may include films whose sole original version is in a language of a Member State with a limited territory, population or language area, short films, films by first-time and second-time directors, documentaries, or low budget or otherwise commercially difficult works.
  • (141) Development Assistance Committee (DAC) List of the OECD: means all countries and territories that are eligible to receive official development assistance and included in the list compiled by the Organisation for Economic Cooperation and Development (OECD);
  • (142) ‘reasonable profit’ shall be determined with respect to the typical profit for the sector concerned. In any event, a rate of return on capital that does not exceed the relevant swap rate plus a premium of 100 basis points will be considered to be reasonable.

Definitions for aid for sport and multifunctional recreational infrastructures

  • (143) ‘professional sport’ means the practice of sport in the nature of gainful employment or remunerated service, irrespective of whether or not a formal labour contract has been established between the professional sportsperson and the relevant sport organisation, where the compensation exceeds the cost of participation and constitutes a significant part of the income for the sportsperson. Travel and accommodation expenses to participate to the sport event shall not be considered as compensation for the purposes of this Regulation.

Definitions for Aid for regional airports

  • (144) ‘airport infrastructure’ means infrastructure and equipment for the provision of airport services by the airport to airlines and the various service providers, including runways, terminals, aprons, taxiways, centralised ground handling infrastructure and any other facilities that directly support the airport services, excluding infrastructure and equipment which is primarily necessary for pursuing non-aeronautical activities;
  • (145) ‘airline’ means any airline with a valid operating licence issued by a Member State or a Member of the Common European Aviation Area pursuant to Regulation (EC) No 1008/2008 of the European Parliament and of the Council ([^E0042]);
  • (146) ‘airport’ means an entity or group of entities performing the economic activity of providing airport services to airlines;
  • (147) ‘airport services’ means services provided to airlines by an airport or any of its subsidiaries, to ensure the handling of aircraft, from landing to take-off, and of passengers and freight, so as to enable airlines to provide air transport services, including the provision of ground handling services and the provision of centralised ground handling infrastructure;
  • (148) ‘average annual passenger traffic’ means a figure determined on the basis of the inbound and outbound passenger traffic during the two financial years preceding that in which the aid is granted;
  • (149) ‘centralised ground handling infrastructure’ means infrastructure which is normally operated by the airport manager and put at the disposal of the various providers of ground handling services active at the airport in exchange for remuneration, excluding equipment owned or operated by the providers of ground handling services;
  • (150) ‘high-speed train’ means a train capable of reaching speeds of over 200 km/h;
  • (151) ‘ground handling services’ means services provided to airport users at airports as described in the Annex to Council Directive 96/67/EC ([^E0043]);
  • (152) ‘non-aeronautical activities’ means commercial services to airlines or other users of the airport, including ancillary services to passengers, freight forwarders or other service providers, renting out of offices and shops, car parking and hotels;
  • (153) ‘regional airport’ means an airport with average annual passenger traffic of up to 3 million passengers;

Definitions for Aid for ports

  • (154) ‘port’ means an area of land and water made up of such infrastructure and equipment, so as to permit the reception of waterborne vessels, their loading and unloading, the storage of goods, the receipt and delivery of those goods and the embarkation and disembarkation of passengers, crew and other persons and any other infrastructure necessary for transport operators in the port;
  • (155) ‘maritime port’ means a port for, principally, the reception of sea-going vessels;
  • (156) ‘inland port’ means a port other than a maritime port, for the reception of inland waterway vessels;
  • (157) ‘port infrastructure’ means infrastructure and facilities for the provision of transport related port services, for example berths used for the mooring of ships, quay walls, jetties and floating pontoon ramps in tidal areas, internal basins, backfills and land reclamation, infrastructure for the collection of ship-generated waste and cargo residues and recharging and refuelling infrastructure in ports supplying vehicles, mobile terminal equipment and mobile groundhandling equipment with electricity, hydrogen, ammonia and methanol;
  • (158) ‘port superstructure’ means surface arrangements (such as for storage), fixed equipment (such as warehouses and terminal buildings) as well as mobile equipment (such as cranes) located in a port for the provision of transport related port services;
  • (159) ‘access infrastructure’ means any type of infrastructure necessary to ensure access and entry from land or sea and river by users to a port, or in a port, such as roads, rail tracks, channels and locks;
  • (160) ‘dredging’ means the removal of sediments from the bottom of the waterway access to a port, or in a port;
  • (162) ‘vessels’ mean floating structures, whether self-propelled or not, with one or more surface displacement hulls;
  • (163) ‘sea-going vessels’ mean vessels other than those which navigate solely or mainly in inland waterways or in waters within, or closely adjacent to, sheltered waters;
  • (164) ‘inland waterway vessels’ mean vessels intended solely or mainly for navigation on inland waterways or in waters within, or closely adjacent to, sheltered waters;
  • (165) ‘infrastructure for the collection of ship-generated waste and cargo residues’ means fixed, floating or mobile port facilities capable of receiving ship-generated waste or cargo residues as defined in Directive 2000/59/EC of the European Parliament and of the Council ([^E0044]).

Definitions for aid involved in financial products supported by the InvestEU Fund (terms defined under other headings of this Article shall have the same meaning as laid down therein also for aid involved in financial products supported by the InvestEU Fund)

  • (166) ‘InvestEU Fund’, ‘EU guarantee’, ‘financial product’, ‘national promotional banks or institutions’ and ‘implementing partner’ have the meaning set out in Article 2 of Regulation (EU) 2021/523;
  • (167) ‘financial intermediary’ for the purposes of Section 16 means a financial intermediary within the meaning of point (34), with the exception of implementing partners;
  • (168) ‘commercial financial intermediary’ means a financial intermediary which operates on a for profit basis and at full own risk, without a public guarantee, national promotional banks or institutions are not considered to be commercial financial intermediaries;
  • (169) ‘TEN-T urban node’ has the meaning set out in Article 3, point (p), of Regulation (EU) No 1315/2013 of the European Parliament and of the Council ([^E0045]);
  • (170) ‘new entrant’ means a railway undertaking within the meaning of Article 3(1) of Directive 2012/34/EU of the European Parliament and of the Council ([^E0046]), which fulfils the following conditions:
  • (a) it received a licence pursuant to Article 17(3) of Directive 2012/34/EU for the relevant market segment less than 20 years before the aid is granted;
  • (b) it is not linked within the meaning of Article 3(3) of Annex I to this Regulation to a railway undertaking that received a license within the meaning of Article 3(14) of Directive 2012/34/EU prior to 1 January 2010;
  • (171) ‘urban transport’ means transport within a city or an agglomeration and its commuting zones;
  • (172) ‘ecosystem’, ‘biodiversity’ and ‘the good condition of an ecosystem’ have the meaning set out in Article 2 of Regulation (EU) 2020/852 of the European Parliament and of the Council ([^E0047]).
Article 3
Conditions for exemption

Aid schemes, individual aid granted under aid schemes and ad hoc aid shall be compatible with the internal market within the meaning of Article 107(2) or (3) of the Treaty and shall be exempted from the notification requirement of Article 108(3) of the Treaty provided that such aid fulfils all the conditions laid down in Chapter I of this Regulation, as well as the specific conditions for the relevant category of aid laid down in Chapter III of this Regulation.

Article 4
Notification thresholds
1.

This Regulation shall not apply to aid which exceeds the following thresholds:

  • (a) for regional investment aid: for an investment with eligible costs of EUR 110 million or more, the aid amounts per undertaking per investment projects as set out below:
  • — in cases of maximum regional aid intensity of 10 %: EUR 8.25 million;
  • — in cases of maximum regional aid intensity of 15 %: EUR 12.38 million;
  • — in cases of maximum regional aid intensity of 20 %: EUR 16.5 million;
  • — in cases of maximum regional aid intensity of 25 %: EUR 20.63 million;
  • — in cases of maximum regional aid intensity of 30 %: EUR 24.75 million;
  • — in cases of maximum regional aid intensity of 35 %: EUR 28.88 million;
  • — in cases of maximum regional aid intensity of 40 %: EUR 33 million;
  • — in cases of maximum regional aid intensity of 50 %: EUR 41.25 million;
  • — in cases of maximum regional aid intensity of 60 %: EUR 49.5 million;
  • — in cases of maximum regional aid intensity of 70 %: EUR 57.75 million;
  • (b) for regional urban development aid, EUR 22 million as laid down in Article 16(3);
  • (c) for investment aid to SMEs: EUR 8.25 million per undertaking per investment project;
  • (d) for aid for consultancy in favour of SMEs: EUR 2.2 million per undertaking, per project;
  • (e) for aid to SMEs for participation in fairs: EUR 2.2 million per undertaking, per year;
  • (ea) for aid to microenterprises in the form of public interventions concerning the supply of electricity, gas or heat referred to in Article 19c: EUR 200 000 per beneficiary per calendar year. For microenterprises active in the primary production of agricultural products, this limit shall be EUR 25 000 per beneficiary per calendar year, and for microenterprises active in the fishery and aquaculture sectors, EUR 30 000 per beneficiary per calendar year;
  • (eb) for aid to SMEs in the form of temporary public interventions concerning the supply of electricity, gas or heat produced from natural gas or electricity to mitigate the impact of price increases following Russia’s war of aggression against Ukraine referred to in Article 19d: EUR 2 million per beneficiary per calendar year. For SMEs active in the primary production of agricultural products, this limit shall be EUR 250 000 per beneficiary per calendar year, and for SMEs active in the fishery and aquaculture sectors, EUR 300 000 per beneficiary per calendar year. Aid granted to undertakings active in the processing and marketing of agricultural products shall be conditional on not being partly or entirely passed on to primary producers;
  • (f) for aid for undertakings participating in European Territorial Cooperation projects: for aid under Article 20, EUR 2.2 million per undertaking, per project; for aid under Article 20a, the amounts laid down in Article 20a(2) per undertaking, per project;
  • (g) for risk finance aid: EUR 16.5 million per eligible undertaking as laid down in Article 21(8) and Article 21a(2);
  • (h) for aid for start-ups: the amounts laid down per undertaking in Article 22(3), (4), (5) and (7);
  • (i) for aid for research and development:
  • (i) if the project is predominantly fundamental research: EUR 55 million per undertaking, per project; that is the case where more than half of the eligible costs of the project are incurred through activities which fall within the category of fundamental research;
  • (ii) if the project is predominantly industrial research: EUR 35 million per undertaking, per project; that is the case where more than half of the eligible costs of the project are incurred through activities which fall within the category of industrial research or within the categories of industrial research and fundamental research taken together;
  • (iii) if the project is predominantly experimental development: EUR 25 million per undertaking, per project; that is the case where more than half of the eligible costs of the project are incurred through activities which fall within the category of experimental development;
  • (iv) if the project is a Eureka project, is implemented by a Joint Undertaking established on the basis of Article 185 or of Article 187 of the Treaty, or complies with the conditions set out in Article 25(6), point (d), the amounts referred to in points (i) to (iii) are doubled;
  • (v) if the aid for research and development projects is granted in the form of repayable advances which, in the absence of an accepted methodology to calculate their gross grant equivalent, are expressed as a percentage of the eligible costs and the measure provides that in case of a successful outcome of the project, as defined on the basis of a reasonable and prudent hypothesis, the advances will be repaid with an interest rate at least equal to the discount rate applicable at the time of grant, the amounts referred to in points (i) to (iv) are increased by 50 %;
  • (vi) aid for feasibility studies in preparation for research activities: EUR 8.25 million per study;
  • (vii) for aid for SMEs for research and development projects awarded a Seal of Excellence quality label and implemented under Article 25a, the amount referred to in Article 25a;
  • (viii) for aid Marie Skłodowska-Curie actions and ERC Proof of Concept actions implemented under Article 25b, the amounts referred to in Article 25b;
  • (ix) for aid involved in co-funded research and development projects implemented under Article 25c, the amounts referred to in Article 25c;
  • (x) for aid for Teaming actions, the amounts referred to in Article 25d;
  • (xi) for aid involved in the co-funding of projects supported by the European Defence Fund or the European Defence Industrial Development Programme under Article 25e: EUR 80 million per undertaking, per project;
  • (j) for investment aid for research infrastructures: EUR 35 million per infrastructure;
  • (ja) for investment aid for testing and experimentation infrastructures: EUR 25 million per infrastructure;
  • (k) for aid for innovation clusters: EUR 10 million per cluster;
  • (l) Innovation aid for SMEs: EUR 10 million per undertaking, per project;
  • (m) for aid for process and organisational innovation: EUR 12.5 million per undertaking, per project;
  • (n) for training aid: EUR 3 million per training project;
  • (o) for aid for the recruitment of disadvantaged workers: EUR 5.5 million per undertaking, per year;
  • (p) for aid for the employment of workers with disabilities in the form of wage subsidies: EUR 11 million per undertaking, per year;
  • (q) for aid for compensating the additional costs of employing workers with disabilities: EUR 11 million per undertaking, per year;
  • (r) for aid for compensating the costs of assistance provided to disadvantaged workers: EUR 5.5 million per undertaking, per year;
  • (s) for investment aid for environmental protection, unless otherwise specified: EUR 30 million per undertaking per investment project;
  • (sa) for aid for dedicated infrastructure and storage referred to in Article 36(4): EUR 25 million per project;
  • (sb) for investment aid for recharging or refuelling infrastructure referred to in Article 36a(1) and (2): EUR 30 million per undertaking per project and, in the case of schemes, an average annual budget of EUR 300 million;
  • (sc) for investment aid for the combined improvements of the energy and environmental performance of buildings referred to in Articles 38a(7) and 39(2a): EUR 30 million per undertaking per project;
  • (sd) for aid for the facilitation of energy performance contracting referred to in Article 38b: EUR 30 million of total nominal outstanding financing per beneficiary;
  • (se) for investment aid for energy efficiency projects in buildings in the form of financial instruments: the amounts set out in Article 39(5);
  • (sf) for aid in form of reduction of environmental taxes or levies referred to in Article 44a: EUR 50 million per scheme per year;
  • (v) for operating aid for the promotion of electricity from renewable sources, as referred to in Article 42, and operating aid for the promotion of energy from renewable sources and renewable hydrogen in small projects and renewable energy communities, as referred to in Article 43: EUR 30 million per undertaking per project; the sum of the budgets of all the schemes falling under Article 42 and the sum of the budgets of all the schemes falling under Article 43 should respectively not exceed EUR 300 million per year;
  • (w) for aid for district heating and/or cooling systems, as referred to in Article 46: EUR 50 million per undertaking per project;
  • (x) for aid for energy infrastructure, as referred to in Article 48: EUR 70 million per undertaking per project;
  • (y) for aid for the deployment of fixed broadband networks awarded in the form of a grant: EUR 100 million total costs per project; for aid for fixed broadband networks awarded in the form of a financial instrument the nominal amount of total financing provided to any final beneficiary per project must not exceed EUR 150 million;
  • (ya) for aid for the deployment of 4G or 5G mobile networks awarded in the form of a grant: EUR 100 million total costs per project; for aid for 4G or 5G mobile networks awarded in the form of a financial instrument the nominal amount of total financing provided to any final beneficiary per project must not exceed EUR 150 million;
  • (yb) for aid for certain projects of common interest in the area of trans-European digital connectivity infrastructures financed under Regulation (EU) 2021/1153 or awarded a Seal of Excellence quality label under that Regulation awarded in the form of a grant: EUR 100 million total costs per project; for aid for certain projects of common interest in the area of trans-European digital connectivity infrastructures awarded in the form of a financial instrument the nominal amount of total financing provided to any final beneficiary per project must not exceed EUR 150 million;
  • (yc) for aid in the form of connectivity vouchers schemes: the total State aid budget over 24 months for all connectivity voucher schemes in a Member State must not exceed EUR 50 million (total amount including national and regional or local voucher schemes);
  • (yd) for aid for the deployment of backhaul networks awarded in the form of a grant: EUR 100 million total costs per project; for aid for the deployment of backhaul networks awarded in the form of a financial instrument the nominal amount of total financing provided to any final beneficiary per project must not exceed EUR 150 million;
  • (z) for investment aid for culture and heritage conservation: EUR 165 million per project; operating aid for culture and heritage conservation: EUR 82.5 million per undertaking per year;
  • (aa) for aid schemes for audiovisual works: EUR 55 million per scheme per year;
  • (bb) for investment aid for sport and multifunctional recreational infrastructures: EUR 33 million or the total costs exceeding EUR 110 million per project; operating aid for sport infrastructure: EUR 2.2 million per infrastructure per year;
  • (cc) for investment aid for local infrastructures: EUR 11 million or the total costs exceeding EUR 22 million for the same infrastructure;
  • (dd) for aid for regional airports: the aid intensities and aid amounts laid down in Article 56a;
  • (ee) for aid for maritime ports: eligible costs of EUR 143 million per project (or EUR 165 million per project in a maritime port included in the work plan of a Core Network Corridor as referred to in Article 47 of Regulation (EU) No 1315/2013 of the European Parliament and of the Council ([^E0048])); as regards dredging a project is defined as all dredging carried out within 1 calendar year;
  • (ff) for aid for inland ports: eligible costs of EUR 44 million per project (or EUR 55 million per project in an inland port included in the work plan of a Core Network Corridor as referred to in Article 47 of Regulation (EU) No 1315/2013); as regards dredging a project is defined as all dredging carried out within 1 calendar year;
  • (gg) for aid involved in financial products supported by the InvestEU Fund: the amounts laid down in Section 16 of Chapter III; and
  • (hh) for aid to SMEs for costs incurred by participating in community-led local development (‘CLLD’) projects: for aid under Article 19a, EUR 2 million per undertaking, per project; for aid under Article 19b, the amounts laid down in Article 19b(2) per project.
2.

The thresholds set out or referred to in paragraph 1 shall not be circumvented by artificially splitting up the aid schemes or aid projects.

Article 5
Transparency of aid
1.

This Regulation shall apply only to aid in respect of which it is possible to calculate precisely the gross grant equivalent of the aid ex ante without any need to undertake a risk assessment (‘transparent aid’).

2.

The following categories of aid shall be considered to be transparent:

  • (a) aid comprised in grants and interest rate subsidies;
  • (b) aid comprised in loans, where the gross grant equivalent has been calculated on the basis of the reference rate prevailing at the time of the grant;
  • (c) aid comprised in guarantees:
  • (i) where the gross grant equivalent has been calculated on the basis of safe-harbour premiums laid down in a Commission notice; or
  • (ii) where before the implementation of the measure, the methodology to calculate the gross grant equivalent of the guarantee has been accepted on the basis of the Commission Notice on the application of Articles 87 and 88 of the EC Treaty to State aid in the form of guarantees ([^E0049]), or any successor notice, following notification of that methodology to the Commission under any regulation adopted by the Commission in the State aid area applicable at the time, and the approved methodology explicitly addresses the type of guarantee and the type of underlying transaction at stake in the context of the application of this Regulation;
  • (d) aid in the form of tax advantages, where the measure provides for a cap ensuring that the applicable threshold is not exceeded;
  • (e) aid for regional urban development if the conditions laid down in Article 16 are fulfilled;
  • (ea) aid to undertakings for their participation in European Territorial Cooperation projects under Article 20a, where it provides for a cap ensuring that the applicable threshold laid down in Article 20a is not exceeded;
  • (f) aid comprised in risk finance measures if the conditions laid down in Articles 21 and 21a are fulfilled;
  • (g) aid for start-ups if the conditions laid down in Article 22 are fulfilled;
  • (ga) aid for SMEs in the form of reduced access fees or free access to innovation advisory services and innovation support services, as defined in Article 2, points (94) and (95) respectively, offered for example by research and knowledge dissemination organisations, research infrastructures, testing and experimentation infrastructures or innovation clusters based on an aid scheme provided that the following conditions are met:
  • (i) the advantage consisting in reduced fees or free access acquired is quantifiable and demonstrable;
  • (ii) the full or partial price discounts for services and the rules in accordance with which SMEs may apply for and be selected and granted discounts are made publicly available (through web sites or other suitable means) before the service provider starts offering the discounts;
  • (iii) the service provider shall keep records of the amounts of aid granted to each SME in the form of price discounts to make sure that the ceilings set out in Article 28(3) and (4) are complied with. Such records shall be kept for 10 years from the date on which the last aid was granted by the service provider;
  • (h) aid for energy efficiency projects if the conditions laid down in Article 39 are fulfilled;
  • (i) aid in the form of premiums in addition to the market price if the conditions laid down in Article 42 are fulfilled;
  • (j) aid in the form of repayable advances, if the total nominal amount of the repayable advance does not exceed the thresholds applicable under this Regulation or if, before implementation of the measure, the methodology to calculate the gross grant equivalent of the repayable advance has been accepted following its notification to the Commission;
  • (k) aid in the form of the sale or the lease of tangible assets below market rates where the value is established either by an independent expert evaluation prior to the transaction or by reference to a publicly available, regularly updated and generally accepted benchmark;
  • (l) aid involved in financial products supported by the InvestEU Fund, if the conditions laid down in Chapter III, Section 16, are fulfilled;
  • (m) aid to microenterprises in the form of public interventions concerning the supply of electricity, gas or heat, if the conditions set out in Articles 19c are fulfilled;
  • (n) aid to SMEs in the form of temporary public interventions concerning the supply of electricity, gas or heat produced from natural gas or electricity to mitigate the impact of price increases following Russia’s war of aggression against Ukraine, if the conditions set out in Article 19d are fulfilled.
Article 6
Incentive effect
1.

This Regulation shall apply only to aid which has an incentive effect.

2.

Aid shall be considered to have an incentive effect if the beneficiary has submitted a written application for the aid to the Member State concerned before work on the project or activity starts. The application for the aid shall contain at least the following information:

  • (a) undertaking's name and size;
  • (b) description of the project, including its start and end dates;
  • (c) location of the project;
  • (d) list of project costs;
  • (e) type of aid (grant, loan, guarantee, repayable advance, equity injection or other) and amount of public funding needed for the project;
3.

Ad hoc aid granted to large enterprises shall be considered to have an incentive effect if, in addition to ensuring that the condition laid down in paragraph 2 is fulfilled, the Member State has verified, before granting the aid concerned, that documentation prepared by the beneficiary establishes that the aid will result in one or more of the following:

  • (a) in the case of regional investment aid: that a project is carried out, which would not have been carried out in the area concerned or would not have been sufficiently profitable for the beneficiary in the area concerned in the absence of the aid.
  • (b) in all other cases, that there is:
  • — a material increase in the scope of the project/activity due to the aid, or
  • — a material increase in the total amount spent by the beneficiary on the project/activity due to the aid, or
  • — a material increase in the speed of completion of the project/activity concerned;
4.

By way of derogation from paragraphs 2 and 3, measures in the form of tax advantages shall be deemed to have an incentive effect if the following conditions are fulfilled:

  • (a) the measure establishes a right to aid in accordance with objective criteria and without further exercise of discretion by the Member State; and
  • (b) the measure has been adopted and is in force before work on the aided project or activity has started, except in the case of fiscal successor schemes, where the activity was already covered by the previous schemes in the form of tax advantages.
5.

By way of derogation from paragraphs 2, 3 and 4, the following categories of aid are not required to have or shall be deemed to have an incentive effect:

  • (a) regional operating aid and regional urban development aid, where the relevant conditions laid down in Articles 15 and 16 are fulfilled;
  • (b) aid for access to finance for SMEs, if the relevant conditions laid down in Articles 21, 21a and 22 are fulfilled;
  • (c) aid for the recruitment of disadvantaged workers in the form of wage subsidies and aid for the employment of workers with disabilities in the form of wage subsidies, if the relevant conditions laid down in Articles 32 and 33 respectively are fulfilled;
  • (d) aid compensating for the additional costs of employing workers with disabilities and aid for compensating the costs of assistance provided to disadvantaged workers, where the relevant conditions laid down in Articles 34 and 35 are fulfilled;
  • (e) aid in the form of reductions in environmental taxes under Directive 2003/96/EC, if the conditions laid down in Article 44 of this Regulation are fulfilled;
  • (f) aid to make good the damage caused by certain natural disasters, if the conditions laid down in Article 50 are fulfilled;
  • (g) social aid for transport for residents of remote regions, if the conditions laid down in Article 51 are fulfilled;
  • (h) aid for culture and heritage conservation, if the conditions laid down in Article 53 are fulfilled;
  • (i) aid for undertakings participating in European Territorial Cooperation projects, if the relevant conditions in Article 20 or Article 20a are fulfilled;
  • (j) aid for research and development projects awarded a Seal of Excellence quality label, Marie Skłodowska-Curie actions and ERC Proof of Concept actions awarded a Seal of Excellence quality label, aid involved in co-funded projects and in co-funded Teaming actions, if the relevant conditions laid down in Article 25a, Article 25b, Article 25c or Article 25d are fulfilled;
  • (k) aid involved in financial products supported by the InvestEU Fund, if the conditions laid down in Section 16 of Chapter III are fulfilled;
  • (l) aid for SMEs participating in or benefitting from community-led local development (‘CLLD’) projects, if the relevant conditions in Article 19a or 19b are fulfilled;
  • (m) aid for the remediation of environmental damage and the rehabilitation of natural habitats and ecosystems where the remediation or rehabilitation costs exceed the increase in value of the land or property and the conditions laid down in Article 45 are fulfilled;
  • (n) aid for the protection of biodiversity and the implementation of nature-based solutions for climate change adaptation and mitigation where the conditions laid down in Article 45 are fulfilled;
  • (o) aid for the promotion of energy from renewable energy sources under Article 41, 42 and 43 when the aid is granted automatically in accordance with objective and non-discriminatory criteria and without further exercise of discretion by the Member State and the measure has been adopted and is in force before work on the aided project or activity has started;
  • (p) aid to microenterprises in the form of public interventions concerning the supply of electricity, gas or heat, subject to the conditions set out in Article 19c;
  • (q) aid to SMEs in the form of temporary public interventions concerning the supply of electricity, gas or heat produced from natural gas or electricity to mitigate the impact of price increases following Russia’s war of aggression against Ukraine, subject to the conditions set out in Article 19d.
Article 7
Aid intensity and eligible costs
1.

For the purposes of calculating aid intensity and eligible costs, all figures used shall be taken before any deduction of tax or other charge. Value added tax charged on eligible costs or expenses that is refundable under the applicable national tax law shall, however, not be taken into account for calculating aid intensity and eligible costs. The eligible costs shall be supported by documentary evidence which shall be clear, specific and contemporary. The amounts of eligible costs may be calculated in accordance with simplified cost options, provided that an operation is at least partly financed through a Union fund that allows the use of simplified cost options and that the category of costs is eligible according to the relevant exemption provision. In such case, the simplified cost options provided in the relevant rules governing the Union fund are applicable. In addition, for projects implemented in line with Recovery and Resilience Plans as approved by the Council under Regulation (EU) 2021/241 of the European Parliament and of the Council ([^E0050]), the amounts of eligible costs may also be calculated in accordance with simplified cost options, provided that the simplified cost options set out in Regulation (EU) No 1303/2013 or Regulation (EU) 2021/1060 are used. In addition, for aid under Articles 25a and 25b, indirect costs can be calculated in accordance with the rules laid down in the respective paragraph 3 of Articles 25a and 25b.

2.

Where aid is granted in a form other than a grant, the aid amount shall be the gross grant equivalent of the aid.

3.

Aid payable in the future, including aid payable in several instalments, shall be discounted to its value at the moment it is granted. The eligible costs shall be discounted to their value at the moment the aid is granted. The interest rate to be used for discounting purposes shall be the discount rate applicable at the moment the aid is granted.

5.

Where aid is granted in the form of repayable advances which, in the absence of an accepted methodology to calculate their gross grant equivalent, are expressed as a percentage of the eligible costs and the measure provides that in case of a successful outcome of the project, as defined on the basis of a reasonable and prudent hypothesis, the advances will be repaid with an interest rate at least equal to the discount rate applicable at the moment the aid is granted, the maximum aid intensities laid down in Chapter III may be increased by 10 percentage points.

6.

Where regional aid is granted in the form of repayable advances, the maximum aid intensities established in a regional aid map in force at the moment the aid is granted may not be increased.

Article 8
Cumulation
1.

In determining whether the notification thresholds in Article 4 and the maximum aid intensities in Chapter III are respected, the total amount of State aid for the aided activity or project or undertaking shall be taken into account.

2.

Where Union funding centrally managed by the institutions, agencies, joint undertakings or other bodies of the Union that is not directly or indirectly under the control of the Member State is combined with State aid, only the latter shall be considered for determining whether notification thresholds and maximum aid intensities or maximum aid amounts are respected, provided that the total amount of public funding granted in relation to the same eligible costs does not exceed the most favourable funding rate laid down in the applicable rules of Union law. By way of derogation, the total public funding for projects supported by the European Defence Fund may reach up to the total eligible costs of the project, irrespective of the maximum funding rate applicable under this fund, provided that the notification thresholds and maximum aid intensities or maximum aid amounts under this Regulation are respected.

3.

Aid with identifiable eligible costs exempted by this Regulation may be cumulated with:

  • (a) any other State aid, as long as those measures concern different identifiable eligible costs,
  • (b) any other State aid, in relation to the same eligible costs, partly or fully overlapping, only if such cumulation does not result in exceeding the highest aid intensity or aid amount applicable to this aid under this Regulation. Financing provided to the final beneficiaries with support from the InvestEU Fund covered by Section 16 of Chapter III and the cost covered by this financing shall not be considered for determining compliance with the cumulation provisions laid down in the first sentence of this point. Instead, the amount relevant for determining compliance with the cumulation provisions of the first sentence of this point shall be calculated as follows. First, the nominal amount of the financing supported by the InvestEU Fund shall be deducted from the total eligible project costs, obtaining the total remaining eligible costs; second, the maximum aid shall be calculated by applying the relevant highest aid intensity or aid amount only to the total remaining eligible costs. In cases of Articles for which the notification threshold is expressed as a maximum aid amount, the nominal amount of financing provided to the final beneficiaries with the support from the InvestEU Fund shall also not be considered for determining whether the notification thresholds in Article 4 are respected. Alternatively, for senior loans or guarantees on senior loans supported by the InvestEU Fund under Section 16 of Chapter III, the gross grant equivalent of the aid entailed in such loans or guarantees provided to the final beneficiaries may be calculated in accordance with Article 5(2), point (b) or (c), as appropriate. This gross grant equivalent of the aid can be used for ensuring, in line with the first sentence of this point, that cumulation with any other aid for the same identifiable eligible costs does not result in exceeding the highest aid intensity or aid amount applicable to the aid under this Regulation or the relevant notification threshold under this Regulation.
4.

Aid without identifiable eligible costs exempted under Articles 19b, 20a, 21, 21a, 22 or 23, Article 56e(5), point (a)(ii), (iii) or (iv), Article 56e(10) and Article 56f may be cumulated with any other State aid with identifiable eligible costs. Aid without identifiable eligible costs may be cumulated with any other State aid without identifiable eligible costs, up to the highest relevant total financing threshold fixed in the specific circumstances of each case by this or another block exemption regulation or decision adopted by the Commission. Aid without identifiable eligible costs exempted under this Regulation may be cumulated with other aid without identifiable eligible costs granted to remedy a serious disturbance in the economy of a Member State under Article 107(3), point (b), of the Treaty approved in a decision adopted by the Commission. Aid without identifiable eligible costs exempted under Article 56e(5), point (a)(ii), (iii) or (iv), Article 56e(10) and Article 56f may be cumulated with other aid without identifiable eligible costs exempted under those Articles.

5.

State aid exempted under this Regulation shall not be cumulated with any de minimis aid in respect of the same eligible costs if such cumulation would result in an aid intensity exceeding those laid down in Chapter III of this Regulation.

6.

By way of derogation from paragraph 3(b), aid in favour of workers with disabilities, as provided for in Articles 33 and 34 may be cumulated with other aid exempted under this Regulation in relation to the same eligible costs above the highest applicable threshold under this Regulation, provided that such cumulation does not result in an aid intensity exceeding 100 % of the relevant costs over any period for which the workers concerned are employed.

7.

By way of derogation from paragraphs 1 to 6, in determining whether the ceilings for regional operating aid in outermost regions, as set out in Article 15(4), are respected, only regional operating aid in outermost regions implemented under this Regulation shall be taken into account.

Article 9
Publication and information
1.

The Member State concerned shall ensure the publication, in the Commission’s transparency award module ([^E0051]) or on a comprehensive State aid website, at national or regional level, of:

  • (a) the summary information referred to in Article 11 in the standardised format laid down in Annex II or a link providing access to it;
  • (b) the full text of each aid measure, as referred to in Article 11 or a link providing access to the full text;
  • (c) the information referred to in Annex III on each individual aid award exceeding EUR 100 000 , or for aid involved in financial products supported by the InvestEU fund under Section 16 on each individual aid award exceeding EUR 500 000 , or for beneficiaries active in primary agricultural production or in the fishery and aquaculture sector, other than those to which Section 2a applies, on each individual aid award exceeding EUR 10 000 .

As regards aid granted to European Territorial Cooperation projects as referred to in Article 20, the information referred to in this paragraph shall be placed on the website of the Member State in which the managing authority concerned, as defined in Article 21 of Regulation (EU) No 1299/2013 of the European Parliament and of the Council ([^E0052]), or Article 45 of Regulation (EU) 2021/1059 of the European Parliament and of the Council ([^E0053]), whichever is applicable, is located. Alternatively, the participating Member States may decide that each of them shall provide the information relating to the aid measures within their territory on the respective websites.

The publication obligations laid down in the first subparagraph shall not apply to aid granted to European Territorial Cooperation projects referred to in Article 20a, as well as community-led local development (‘CLLD’) projects under Article 19b.

2.

For schemes in the form of tax advantages, and for schemes covered by Articles 16, 21a and 22 ([^E0054]) the conditions set out in paragraph 1, first subparagraph, point (c), of this Article shall be considered fulfilled if Member States publish the required information on individual aid amounts in the following ranges (in EUR million):

0.01-0.1 (only for fishery and aquaculture as well as primary agricultural production);

0.1-0.5;

0.5-1;

1-2;

2-5;

5-10;

10-30; and

30 and more.

3.

For schemes under Article 51 of this Regulation, the publication obligations laid down in this article shall not apply to final consumers.

3a. If a financial product has been implemented by a Member State under the InvestEU Member State compartment or by a national promotional bank acting as an implementing partner or acting as a financial intermediary under InvestEU, the Member State remains under the obligation to ensure the publication of information as laid down in paragraph 1, first subparagraph, point (c). However, this obligation is deemed to be fulfilled if the implementing partner provides to the Commission the information as laid down in paragraph 1, first subparagraph, point (c), no later than 30 June of the year following the financial year in which the aid was granted and if the guarantee agreement signed between the Commission and the implementing partner stipulates the requirement to provide to the Commission the information as laid down in paragraph 1, first subparagraph, point (c).

4.

The information referred to in paragraph 1, point (c), shall be organised and accessible in a standardised manner, as described in Annex III, and shall allow for effective search and download functions. It shall be published within 6 months from the date the aid was granted, or for aid in the form of tax advantages, within 1 year from the date the tax declaration is due, and shall be available for at least 10 years from the date on which the aid was granted. For aid in the form of tax advantages, if there is no formal requirement for an annual declaration, 31 December of the year for which the aid was granted will be considered as the granting date for the purposes of this paragraph.

5.

The Commission shall publish on its website:

  • (a) the links to the State aid websites referred to in paragraph 1 of this Article;
  • (b) the summary information referred to in Article 11.
6.

Member States shall comply with the provisions of this Article at the latest within two years after the entry into force of this Regulation.

CHAPTER II MONITORING

Article 10
Withdrawal of the benefit of the block exemption

Where a Member State grants aid allegedly exempted from the notification requirement under this Regulation without fulfilling the conditions set out in Chapters I to III, the Commission may, after having provided the Member State concerned with the possibility to make its views known, adopt a decision stating that all or some of the future aid measures adopted by the Member State concerned which would otherwise fulfil the requirements of this Regulation, are to be notified to the Commission in accordance with Article 108(3) of the Treaty. The measures to be notified may be limited to the measures granting certain types of aid or in favour of certain beneficiaries or aid measures adopted by certain authorities of the Member State concerned.

Article 11
Reporting
1.

Member States, or in the case of aid granted to European Territorial Cooperation projects under Article 20, alternatively the Member State in which the Managing Authority, as defined in Article 21 of Regulation (EU) No 1299/2013, or Article 45 of Regulation (EU) 2021/1059, whichever is applicable, is located, shall transmit to the Commission:

  • (a) via the Commission’s electronic notification system, the summary information about each aid measure exempted under this Regulation in the standardised format laid down in Annex II, together with a link providing access to the full text of the aid measure, including its amendments, within 20 working days following its entry into force; and
  • (b) an annual report, as referred to in Commission Regulation (EC) No 794/2004 ([^E0055]) in electronic form, on the application of this Regulation, containing the information indicated in that Regulation, in respect of each whole year or each part of the year during which this Regulation applies. For financial products implemented by a Member State under the InvestEU Member State compartment or by a national promotional bank acting as an implementing partner or acting as a financial intermediary under InvestEU, this obligation of the Member State is deemed to be fulfilled if the implementing partner provides the annual reports to the Commission, in accordance with the relevant reporting requirements laid down in the guarantee agreement signed between the Commission and the implementing partner.

The first subparagraph shall not apply in respect of aid granted to European Territorial Cooperation projects referred to in Article 20a, as well as to community-led local development (‘CLLD’) projects as referred to in Article 19b.

2.

Where, as a consequence of the extension of the application period of this Regulation until 31 December 2023 by Commission Regulation (EU) 2020/972 ([^E0056]), a Member State plans to extend measures in respect of which the summary information was submitted to the Commission in accordance with paragraph 1 of this Article, that Member State shall update that summary information regarding the extension of those measures and communicate that update to the Commission within 20 working days following the entry into force of the act which extends the respective measure by the Member State.

Article 12
Monitoring
1.

In order to enable the Commission to monitor the aid exempted from notification by this Regulation, Member States, or alternatively, in the case of aid granted to European Territorial Cooperation projects referred to in Article 20, the Member State in which the Managing Authority is located, shall maintain detailed records with the information and supporting documentation necessary to establish that all the conditions laid down in this Regulation are fulfilled. Such records shall be kept for 10 years from the date on which the ad hoc aid was granted or the last aid was granted under the scheme.

The first subparagraph shall not apply in respect of aid granted to European Territorial Cooperation projects referred to in Article 20a, as well as to European Innovation Partnership for agricultural productivity and sustainability Operational Group projects and to community-led local development (‘CLLD’) projects as referred to Article 19b.

2.

In the case of schemes under which fiscal aid is granted automatically, such as those based on tax declarations of the beneficiaries, and where there is no ex ante verification that all compatibility conditions are met for each beneficiary, Member States shall regularly verify, at least ex post and on a sample basis, that all compatibility conditions are met, and draw the necessary conclusions. Member States shall maintain detailed records of the verifications for at least 10 years from the date of the controls.

3.

The Commission may request, from each Member State, all the information and supporting documentation which the Commission considers necessary to monitor the application of this Regulation, including the information mentioned in paragraphs 1 and 2. The Member State concerned shall provide the Commission with the requested information and supporting documents within a period of 20 working days from receipt of the request or such longer period as may be fixed in the request.

CHAPTER III SPECIFIC PROVISIONS FOR DIFFERENT CATEGORIES OF AID

SECTION 1 Regional aid

Subsection A Regional investment and operating aid

Article 13
Scope of regional aid

This Section shall not apply to:

  • (a) aid in the steel sector, the lignite sector and the coal sector;
  • (b) aid to the transport sector as well as the related infrastructure; aid for energy generation, storage, transmission, distribution and infrastructure, except for regional investment aid in outermost regions and regional operating aid schemes; and aid in the broadband sector except for regional operating aid schemes;
  • (c) regional aid in the form of schemes which are targeted at a limited number of specific sectors of economic activity; schemes aimed at tourism activities or processing and marketing of agricultural products are not considered to be targeted at specific sectors of economic activity;
  • (d) regional operating aid granted to undertakings whose principal activities fall under Section K ‘Financial and insurance activities’ of the NACE Rev. 2 or to undertakings that perform intra-group activities whose principal activities fall under classes 70.10 ‘Activities of head offices’ or 70.22 ‘Business and other management consultancy activities’ of NACE Rev. 2.
Article 14
Regional investment aid
1.

Regional investment aid measures shall be compatible with the internal market within the meaning of Article 107(3) of the Treaty and shall be exempted from the notification requirement of Article 108(3) of the Treaty, provided that the conditions laid down in this Article and in Chapter I are fulfilled.

2.

The aid shall be granted in assisted areas.

3.

In assisted areas fulfilling the conditions of Article 107(3), point (a), of the Treaty, the aid may be granted for any form of initial investment regardless of the size of the beneficiary. In assisted areas fulfilling the conditions of Article 107(3), point (c), of the Treaty, the aid may be granted to SMEs for any form of initial investment and to large enterprises only for an initial investment that creates a new economic activity in the area concerned.

4.

The eligible costs shall be one or several of the following:

Reading this document does not replace reading the official text published in the Official Journal of the European Union. We assume no responsibility for any inaccuracies arising from the conversion of the original to this format.

This text is published under EUR-Lex's own terms of reuse, not a Legalize or public-domain licence. EUR-Lex
Creative Commons Attribution 4.0 International (CC BY 4.0)
© European Union, https://eur-lex.europa.eu — Source: EUR-Lex (Publications Office of the European Union). Reused under the Creative Commons Attribution 4.0 International (CC BY 4.0) licence. Only EU legislation published in the printed Official Journal of the European Union is deemed authentic; consolidated texts are reproduced here for documentation purposes and have been reformatted to Markdown.