Regulation (EU, Euratom) 2018/1046 of the European Parliament and of the Council of 18 July 2018 on the financial rules applicable to the general budget of the Union, amending Regulations (EU) No 1296/2013, (EU) No 1301/2013, (EU) No 1303/2013, (EU) No 1304/2013, (EU) No 1309/2013, (EU) No 1316/2013, (EU) No 223/2014, (EU) No 283/2014, and Decision No 541/2014/EU and repealing Regulation (EU, Euratom) No 966/2012
- 1.1.The duration of a framework contract shall not exceed four years, save in exceptional cases duly justified in particular by the subject matter of the framework contract.
- Specific contracts based on framework contracts shall be awarded in accordance with the terms of the framework contract.
- When concluding specific contracts, the parties shall not substantially deviate from the framework contract.
- 1.2.Where a framework contract is concluded with a single economic operator, the specific contracts shall be awarded within the limits of the terms laid down in the framework contract.
- In such circumstances and where duly justified, contracting authorities may request the contractor in writing to supplement its tender if necessary.
- 1.3.Where a framework contract is to be concluded with several economic operators (‘multiple framework contract’), it may take the form of separate contracts signed in identical terms with each contractor.
- Specific contracts based on multiple framework contracts shall be implemented in one of the following ways:
- (a) in accordance with the terms of the framework contract: without reopening of competition, where it sets out all the terms governing the provision of the works, supplies or services concerned and the objective conditions for determining which of the contractors shall perform them;
- (b) where not all the terms governing the provision of the works, supplies or services concerned are laid down in the framework contract: through reopening of competition among the contractors, in accordance with point 1.4 and on the basis of any of the following:
- (i) the same terms, where necessary more precisely formulated;
- (ii) where appropriate, on the basis of other terms referred to in the procurement documents relating to the framework contract.
- (c) partly without reopening of competition in accordance with point (a) and partly with reopening of competition amongst the contractors in accordance with point (b), where that possibility has been stipulated by the contracting authority in the procurement documents relating to the framework contract.
- The procurement documents referred to in point (c) of the second subparagraph shall also specify which terms may be subject to reopening of competition.
- 1.4.A multiple framework contract with reopening of competition shall be concluded with at least three economic operators, provided that there is a sufficient number of admissible tenders as referred to in point 29.3.
- When awarding a specific contract through reopening of competition among the contractors, the contracting authority shall consult them in writing and fix a time limit which is sufficiently long to allow specific tenders to be submitted. Specific tenders shall be submitted in writing. The contracting authority shall award each specific contract to the tenderer who has submitted the most economically advantageous specific tender on the basis of the award criteria set out in the procurement documents relating to the framework contract.
- 1.5.In sectors subject to a rapid price and technological evolution, framework contracts without reopening of competition shall contain a clause either on a mid-term review or on a benchmarking system. After the mid-term review, if the conditions initially laid down are no longer adapted to the price or technological evolution, the contracting authority shall not use the framework contract concerned and shall take appropriate measures to terminate it.
- 1.6.Specific contracts based on framework contracts shall be preceded by a budgetary commitment.
-
- Advertising of procedures for contracts with a value equal to or greater than the thresholds referred to in Article 175(1) of this Regulation or for contracts falling within the scope of Directive 2014/24/EU
- 2.1.The notices for publication in the Official Journal of the European Union shall include all the information set out in the relevant standard forms referred to in Directive 2014/24/EU to ensure transparency of the procedure.
- 2.2.The contracting authority may make known its intentions of planned procurement for the financial year through the publication of a prior information notice. It shall cover a period equal to or less than 12 months from the date on which the notice is sent to the Publications Office of the European Union (the Publications Office).
- The contracting authority may publish the prior information notice either in the Official Journal of the European Union or on its buyer profile. In the latter case, a notice of publication on the buyer profile shall be published in the Official Journal of the European Union.
- 2.3.The contracting authority shall send to the Publications Office an award notice on the results of the procedure no later than 30 days after the signature of a contract or framework contract with a value equal to or greater than the thresholds referred to in Article 175(1).
- Notwithstanding the first subparagraph, award notices relating to contracts based on a dynamic purchasing system may be grouped together on a quarterly basis. In such cases, the contracting authority shall send the award notice no later than 30 days after the end of each quarter.
- Award notices shall not be published for specific contracts based on a framework contract.
- 2.4.The contracting authority shall publish an award notice:
- (a) before concluding a contract or a framework contract with a value equal to or greater than the thresholds referred to in Article 175(1) and awarded in accordance with point (b) of the second subparagraph of point 11.1;
- (b) after concluding a contract or a framework contract with a value equal to or greater than the thresholds referred to in Article 175(1), including contracts awarded in accordance with point (a) and points (c) to (f) of the second subparagraph of point 11.1.
- 2.5.The contracting authority shall publish in the Official Journal of the European Union a notice of modification of contract during its duration in the cases set out in points (a) and (b) of the first subparagraph of Article 172(3) where the value of the modification is equal to or greater than the thresholds referred to in Article 175(1) or is equal to or greater than the thresholds set out in Article 178(1) for procedures in the field of external actions.
- 2.6.For an interinstitutional procedure, the contracting authority responsible for the procedure shall be in charge of the applicable publicity measures.
-
- Advertising of procedures for contracts with a value below the thresholds referred to in Article 175(1) of this Regulation or for contracts outside the scope of Directive 2014/24/EU
- 3.1.Procedures with an estimated contract value below the thresholds referred to in Article 175(1) shall be advertised by appropriate means. Such advertising shall involve appropriate ex ante publicity on the internet or a contract notice or, for contracts awarded in accordance with the procedure set out in point 13, the publication of a notice for a call for expression of interest in the Official Journal of the European Union. That obligation shall not apply to the procedure set out in point 11 and the negotiated procedure for very low value contracts set out in point 14.4.
- 3.2.For contracts awarded in accordance with points (g) and (i) of the second subparagraph of point 11.1, the contracting authority shall send a list of contracts to the European Parliament and Council no later than 30 June of the following financial year. Where the contracting authority is the Commission, that list shall be annexed to the summary of the annual activity report referred to in Article 74(9).
- 3.3.Contract award information shall contain the name of the contractor, the amount legally committed and the subject matter of the contract and, in the case of direct contracts and specific contracts, it shall comply with Article 38(3).
- The contracting authority shall publish a list of contracts on its website no later than 30 June of the following financial year for:
- (a) contracts below the thresholds referred to in Article 175(1);
- (b) contracts awarded in accordance with point (h) and points (j) to (m) of the second subparagraph of point 11.1;
- (c) modifications of contracts as set out in point (c) of the first subparagraph of Article 172(3);
- (d) modifications of contracts as set out in points (a) and (b) of the first subparagraph of Article 172(3) where the value of the modification is below the thresholds referred to in Article 175(1);
- (e) specific contracts under a framework contract.
- For the purposes of point (e) of the second subparagraph, the published information may be aggregated per contractor for specific contracts under the same framework contract.
- 3.4.For interinstitutional framework contracts, each contracting authority shall be responsible for advertising its specific contracts and their modifications in accordance with point 3.3.
-
- Publication of notices
- 4.1.The contracting authority shall draw up and transmit the notices referred to in points 2 and 3 by electronic means to the Publications Office.
- 4.2.The Publications Office shall publish the notices referred to in points 2 and 3 in the Official Journal of the European Union no later than:
- (a) seven days after their dispatch if the contracting authority uses the electronic system for filling out the standard forms referred to in point 2.1 and limits free text to 500 words;
- (b) 12 days after their dispatch in all other cases.
- 4.3.The contracting authority shall be able to provide evidence of the date of dispatch.
-
- Other forms of advertising
In addition to the advertising provided for in points 2 and 3 procurement procedures may be advertised in any other way, in particular in electronic form. Any such advertising shall refer to the notice published in the Official Journal of the European Union, if the notice has been published, and shall not precede the publication of that notice, which alone is authentic.
Such advertising shall not introduce any discrimination between candidates or tenderers nor contain details other than those contained in the contract notice, if the notice has been published.
SECTION 2
Procurement procedures
6. Minimum number of candidates and arrangements for negotiation
- 6.1.In a restricted procedure and in the procedures referred to in points (a) and (b) of point 13.1 and for contracts awarded in accordance with point 14.2, the minimum number of candidates shall be five.
- 6.2.In a competitive procedure with negotiation, a competitive dialogue, an innovation partnership, a prospection of the local market in accordance with point (g) of the second subparagraph of point 11.1 and a negotiated procedure for low value contracts in accordance with point 14.3, the minimum number of candidates shall be three.
- 6.3.Points 6.1 and 6.2 shall not apply in the following cases:
- (a) negotiated procedures for very low value contracts in accordance with point 14.4;
- (b) negotiated procedures without prior publication in accordance with point 11, except for design contests in accordance with point (d) of the second subparagraph of point 11.1 and prospections of the local market in accordance with point (g) of the second subparagraph of point 11.1.
- 6.4.Where the number of candidates meeting the selection criteria is below the minimum number specified in points 6.1 and 6.2, the contracting authority may continue the procedure by inviting the candidates with the required capacities. The contracting authority shall not include other economic operators that did not initially request to participate or that it did not initially invite.
- 6.5.During a negotiation, the contracting authority shall ensure equal treatment for all tenderers.
- A negotiation may take place in successive stages in order to reduce the number of tenders to be negotiated by applying the award criteria specified in the procurement documents. The contracting authority shall indicate whether it will use that option in the procurement documents.
- 6.6.For contracts awarded in accordance with points (d) and (g) of the second subparagraph of point 11.1 and points 14.2 and 14.3, the contracting authority shall invite at least all economic operators who have expressed interest following ex ante publicity as set out in point 3.1 or prospection of the local market or a design contest.
7. Innovation partnership
- 7.1.An innovation partnership shall aim at the development of an innovative product, service or innovative works and the subsequent purchase of the resulting works, supplies or services, provided that they correspond to the performance levels and maximum costs agreed between the contracting authorities and the partners.
- The innovation partnership shall be structured in successive phases following the sequence of steps in the research and innovation process, which may include the completion of the works, the manufacturing of the products or the provision of the services. The innovation partnership shall set intermediate targets to be attained by the partners.
- Based on those intermediate targets, the contracting authority may decide after each phase to terminate the innovation partnership or, in the case of an innovation partnership with several partners, to reduce the number of partners by terminating individual contracts, provided that the contracting authority has indicated those possibilities and the conditions for their use in the procurement documents.
- 7.2.Before launching an innovation partnership, the contracting authority shall consult the market as provided for in point 15 in order to ascertain that the work, supply or service does not exist on the market or as near-to-market development activity.
- The arrangements on negotiation set out in Article 164(4) and in point 6.5 shall be complied with.
- In the procurement documents, the contracting authority shall describe the need for innovative works, supplies or services that cannot be met by purchasing works, supplies or services already available on the market. It shall indicate which elements of that description define the minimum requirements. The information provided shall be sufficiently precise to enable economic operators to identify the nature and scope of the required solution and decide whether to request to participate in the procedure.
- The contracting authority may decide to set up the innovation partnership with one partner or with several partners conducting separate research and development activities.
- The contracts shall be awarded on the sole basis of the best price-quality ratio as set out in Article 167(4).
- 7.3.In the procurement documents, the contracting authority shall specify the arrangements applicable to intellectual property rights.
- In the framework of the innovation partnership, the contracting authority shall not reveal to the other partners solutions proposed or other confidential information communicated by a partner without its agreement.
- The contracting authority shall ensure that the structure of the partnership and, in particular, the duration and value of the different phases reflect the degree of innovation of the proposed solution and the sequence of the research and innovation activities required for the development of an innovative solution not yet available on the market. The estimated value of works, supplies or services shall be proportionate in relation to the investment required for their development.
8. Design contests
- 8.1.Design contests shall be subject to the rules on advertising set out in point 2 and may include the award of prizes.
- Where design contests are restricted to a limited number of candidates, the contracting authority shall lay down clear and non-discriminatory selection criteria.
- The number of candidates invited to participate shall be sufficient to ensure genuine competition.
- 8.2.The jury shall be appointed by the authorising officer responsible. It shall be composed exclusively of natural persons who are independent of candidates in the contest. Where a particular professional qualification is required from candidates in a contest, at least one third of the members of the jury shall have the same or an equivalent qualification.
- The jury shall be autonomous in its opinions. Its opinions shall be adopted on the basis of projects submitted to it anonymously by the candidates and solely in the light of the criteria set out in the contest notice.
- 8.3.The proposals of the jury, based on the merits of each project, and its ranking and remarks, shall be recorded in a report signed by its members.
- Candidates shall remain anonymous until the jury has given its opinion.
- Candidates may be asked by the jury to answer the questions recorded in the report in order to clarify a project. A full report of the resulting dialogue shall be drawn up.
- 8.4.The contracting authority shall take an award decision that includes the name and address of the candidate selected and the reasons for the choice by reference to the criteria announced in the contest notice, especially if the choice departs from the proposals made in the jury’s opinion.
9. Dynamic purchasing system
- 9.1.A dynamic purchasing system may be divided into categories of works, supplies or services that are objectively defined on the basis of characteristics of the procurement to be undertaken in the category concerned. In that case, selection criteria shall be defined for each category.
- 9.2.The contracting authority shall indicate in the procurement documents the nature and estimated quantity of the purchases envisaged and all the necessary information concerning the purchasing system, the electronic equipment used and the technical connection arrangements and specifications.
- 9.3.The contracting authority shall give any economic operator, throughout the period of validity of the dynamic purchasing system, the possibility of requesting to participate in the system. It shall complete its evaluation of such requests within 10 working days of their receipt. That deadline may be prolonged to 15 working days where justified. However, the contracting authority may extend the evaluation period provided that no invitation to tender is issued in the meantime.
- The contracting authority shall inform the candidate as soon as possible of whether or not it has been admitted to the dynamic purchasing system.
- 9.4.The contracting authority shall invite all candidates admitted to the system in the relevant category to submit a tender within a reasonable time. The contracting authority shall award the contract to the tenderer who has submitted the most economically advantageous tender on the basis of the award criteria set out in the contract notice. Those criteria may, if appropriate, be formulated more precisely in the invitation to tender.
- 9.5.The contracting authority shall indicate the period of validity of the dynamic purchasing system in the contract notice.
- A dynamic purchasing system shall not last for more than four years, except in duly justified exceptional cases.
- The contracting authority shall not resort to such a system to prevent, restrict or distort competition.
10. Competitive dialogue
- 10.1.The contracting authority shall specify its needs and requirements, the award criteria and an indicative timeframe in the contract notice or in a descriptive document.
- It shall award the contract to the tender offering the best price-quality ratio.
- 10.2.The contracting authority shall open a dialogue with the candidates satisfying the selection criteria in order to identify and define the means best suited to satisfying its needs. It may discuss all aspects of the procurement with the selected candidates during that dialogue but it cannot alter its needs and requirements and award criteria as provided for in point 10.1.
- During the course of the dialogue, the contracting authority shall ensure equality of treatment among all tenderers and shall not reveal the solutions proposed or other confidential information communicated by a tenderer without its agreement to waive that confidentiality.
- The competitive dialogue may take place in successive stages in order to reduce the number of solutions to be discussed by applying the announced award criteria if provision is made for that possibility in the contract notice or the descriptive document.
- 10.3.The contracting authority shall continue the dialogue until it can identify the solution or solutions which are capable of meeting its needs.
- After informing the remaining tenderers that the dialogue is concluded, the contracting authority shall ask each of them to submit their final tenders on the basis of the solution or solutions presented and specified during the dialogue. Those tenders shall contain all the elements required and necessary for the performance of the project.
- At the request of the contracting authority, those final tenders may be clarified, specified and optimised provided this does not involve substantial changes to the tender or to the procurement documents.
- The contracting authority may negotiate with the tenderer having submitted the tender offering the best price-quality ratio to confirm commitments contained in the tender provided this does not have the effect of modifying substantial aspects of the tender and does not risk distorting competition or causing discrimination.
- 10.4.The contracting authority may specify the payments to be made to the selected candidates taking part in the dialogue.
11. Use of a negotiated procedure without prior publication of a contract notice
- 11.1.Where the contracting authority uses the negotiated procedure without prior publication of a contract notice, it shall comply with the arrangements on negotiation set out in Article 164(4) and in point 6.5.
- The contracting authority may use the negotiated procedure without prior publication of a contract notice, regardless of the estimated value of the contract, in the following cases:
- (a) where no tenders, or no suitable tender, or no request to participate or no suitable request to participate as provided for in point 11.2 have been submitted in response to an open procedure or restricted procedure after that procedure has been completed, provided that the original procurement documents are not substantially altered;
- (b) where the works, supplies or services can only be provided by a single economic operator under the conditions set out in point 11.3 and for any of the following reasons:
- (i) the aim of the procurement is the creation or acquisition of a unique work of art or an artistic performance;
- (ii) competition is absent for technical reasons;
- (iii) the protection of exclusive rights, including intellectual property rights, must be ensured;
- (c) in so far as is strictly necessary where, for reasons of extreme urgency brought about by unforeseeable events, it is impossible to comply with the time limits laid down in points 24, 26 and 41 and where the justification of such extreme urgency is not attributable to the contracting authority;
- (d) where a service contract follows a design contest and is to be awarded to the winner or to one of the winners; in the latter case, all winners shall be invited to participate in the negotiations;
- (e) for new services or works consisting in the repetition of similar services or works entrusted to the economic operator to which the same contracting authority awarded an original contract, provided that those services or works are in conformity with a basic project for which the original contract was awarded after publication of a contract notice, subject to the conditions set out in point 11.4;
- (f) for supply contracts:
- (i) for additional deliveries which are intended either as a partial replacement of supplies or installations or as the extension of existing supplies or installations, where a change of supplier would oblige the contracting authority to acquire supplies having different technical characteristics which would result in incompatibility or disproportionate technical difficulties in operation and maintenance; when Union institutions award contracts on their own account, the duration of such contracts shall not exceed three years;
- (ii) where the products are manufactured purely for the purpose of research, experimentation, study or development; however, such contracts shall not include quantity production to establish commercial viability or to recover research and development costs;
- (iii) for supplies quoted and purchased on a commodity market;
- (iv) for purchases of supplies on particularly advantageous terms, from either an economic operator which is definitively winding up its business activities, or the liquidators in an insolvency procedure, an arrangement with creditors, or a similar procedure under national law;
- (g) for building contracts, after prospecting the local market;
- (h) for contracts for any of the following:
- (i) legal representation by a lawyer within the meaning of Article 1 of Council Directive 77/249/EEC (38) in arbitration or conciliation or judicial proceedings;
- (ii) legal advice given in the preparation of the proceedings referred to in point (i), or where there is tangible indication and high probability that the matter to which the advice relates will become the subject of such proceedings, provided that the advice is given by a lawyer within the meaning of Article 1 of Directive 77/249/EEC;
- (iii) arbitration and conciliation services;
- (iv) document certification and authentication services which must be provided by notaries;
- (i) for contracts declared to be secret or for contracts whose performance must be accompanied by special security measures, in accordance with the administrative provisions in force or when the protection of the essential interests of the Union so requires, provided the essential interests concerned cannot be guaranteed by other measures; such measures may consist of requirements to protect the confidential nature of information which the contracting authority makes available in the procurement procedure;
- (j) for financial services in connection with the issue, sale, purchase or transfer of securities or other financial instruments within the meaning of Directive 2014/65/EU of the European Parliament and of the Council (39), central bank services and operations conducted with the European Financial Stability Facility and the European Stability Mechanism;
- (k) loans, whether or not in connection with the issue, sale, purchase or transfer of securities or other financial instruments within the meaning of Directive 2014/65/EU;
- (l) for the purchase of public communication networks and electronic communications services within the meaning of Directive 2002/21/EC of the European Parliament and of the Council (40);
- (m) services provided by an international organisation where it cannot participate in competitive procedures according to its statute or act of establishment.
- 11.2.A tender shall be considered unsuitable where it does not relate to the subject matter of the contract and a request to participate shall be considered unsuitable where the economic operator is in an exclusion situation referred to in Article 136(1) or does not meet the selection criteria.
- 11.3.The exceptions set out in points (b)(ii) and (iii) of the second subparagraph of point 11.1 shall only apply when no reasonable alternative or substitute exists and the absence of competition is not the result of an artificial narrowing down of the parameters when defining the procurement.
- 11.4.In the cases referred to in point (e) of the second subparagraph of point 11.1, the basic project shall indicate the extent of possible new services or works and the conditions under which they will be awarded. As soon as the basic project is put up for tender, the possible use of the negotiated procedure shall be disclosed, and the total estimated amount for the subsequent services or works shall be taken into consideration in applying the thresholds referred to in Article 175(1), or in Article 178(1) in the field of external actions. When Union institutions award contracts on their own account, that procedure shall only be used during the performance of the original contract and at the latest during the three years following its conclusion.
12. Use of a competitive procedure with negotiation or competitive dialogue
- 12.1.When the contracting authority uses the competitive procedure with negotiation or the competitive dialogue, it shall follow the arrangements on negotiation set out in Article 164(4) and in point 6.5. The contracting authority may use those procedures, regardless of the estimated value of the contract, in the following cases:
- (a) where only irregular or unacceptable tenders as specified in points 12.2 and 12.3 have been submitted in response to an open or restricted procedure after that procedure has been completed provided that the original procurement documents are not substantially altered;
- (b) with regard to works, supplies or services fulfilling one or more of the following criteria:
- (i) where the needs of the contracting authority cannot be met without the adaptation of a readily available solution;
- (ii) the works, supplies or services include design or innovative solutions;
- (iii) the contract cannot be awarded without prior negotiations because of specific circumstances related to the nature, complexity or the legal and financial make-up of the contract or the risks attached to the subject matter of the contract;
- (iv) the technical specifications cannot be established with sufficient precision by the contracting authority with reference to a standard, as set out in point 17.3;
- (c) for concession contracts;
- (d) for the service contracts referred to in Annex XIV to Directive 2014/24/EU;
- (e) for research and development services other than those covered by CPV codes 73000000-2 to 73120000-9, 73300000-5, 73420000-2 and 73430000-5 as set out in Regulation (EC) No 2195/2002 unless the benefits accrue exclusively to the contracting authority for its use in the conduct of its own affairs, or unless the service provided is wholly remunerated by the contracting authority;
- (f) for service contracts for the acquisition, development, production or co-production of programme material intended for audiovisual media services as defined in Directive 2010/13/EU of the European Parliament and of the Council (41) or radio media services or contracts for broadcasting time or programme provision.
- 12.2.A tender shall be considered irregular in any of the following cases:
- (a) when it does not comply with the minimum requirements specified in the procurement documents;
- (b) when it does not comply with the requirements for submission set out in Article 168(3);
- (c) when the tenderer is rejected under point (b) or (c) of the first subparagraph of Article 141(1);
- (d) when the contracting authority has declared the tender to be abnormally low.
- 12.3.A tender shall be considered unacceptable in any of the following cases:
- (a) when the price of the tender exceeds the contracting authority’s maximum budget as determined and documented prior to the launching of the procurement procedure;
- (b) when the tender fails to meet the minimum quality levels for award criteria.
- 12.4.In the cases referred to in point (a) of point 12.1, the contracting authority shall not be required to publish a contract notice if it includes in the competitive procedure with negotiation all those tenderers who satisfied the exclusion and selection criteria except those who submitted a tender declared to be abnormally low.
13. Procedure involving a call for expression of interest
- 13.1.For contracts with a value below the thresholds referred to in Article 175(1) or in Article 178(1), and without prejudice to points 11 and 12, the contracting authority may use a call for expression of interest to do either of the following:
- (a) to pre-select candidates to be invited to submit tenders in response to future restricted invitations to tender;
- (b) to collect a list of vendors to be invited to submit requests to participate or tenders.
- 13.2.The list drawn up following a call for expression of interest shall be valid for not more than four years from the date on which the notice referred to in point 3.1 is published.
- The list referred to in the first subparagraph may include sub-lists.
- Any interested economic operator may express interest at any time during the period of validity of the list, with the exception of the last three months of that period.
- 13.3.Where a contract is to be awarded, the contracting authority shall invite all candidates or vendors entered on the relevant list or sub-list to do either of the following:
- (a) to submit a tender in the case referred to in point (a) of point 13.1;
- (b) to submit, in case referred to in point (b) of point 13.1, either of the following:
- (i) tenders including documents relating to exclusion and selection criteria;
- (ii) documents relating to exclusion and selection criteria and, as a second step, tenders, for those fulfilling those criteria.
14. Middle, low and very low value contracts
- 14.1.Middle, low and very low value contracts may be awarded by negotiated procedure in accordance with the arrangements on negotiation set out in Article 164(4) and in point 6.5. Only candidates invited simultaneously and in writing by the contracting authority shall submit an initial tender.
- 14.2.A contract of a value exceeding EUR 60 000 and below the thresholds referred to in Article 175(1) shall be deemed of middle value. Points 3.1, 6.1 and 6.4 shall apply to such contracts.
- 14.3.A contract of a value not exceeding EUR 60 000 , but exceeding the threshold set out in point 14.4, shall be deemed of low value. Points 3.1, 6.2 and 6.4 shall apply to such contracts.
- 14.4.A contract of a value not exceeding EUR 15 000 shall be deemed of very low value. Point 6.3 shall apply to such contracts.
- 14.5.Payments of amounts not exceeding EUR 1 000 in respect of items of expenditure may be carried out simply as payment against invoices, without prior acceptance of a tender.
15. Preliminary market consultation
- 15.1.For preliminary market consultation, the contracting authority may seek or accept advice from independent experts or authorities or from economic operators. That advice may be used in the planning and conduct of the procurement procedure, provided that such advice does not have the effect of distorting competition and does not result in a violation of the principles of non-discrimination and transparency.
- 15.2.Where an economic operator has advised the contracting authority or has otherwise been involved in the preparation of the procurement procedure, the contracting authority shall take appropriate measures as set out in Article 141 to ensure that competition is not distorted by the participation of that economic operator in the award procedure.
16. Procurement documents
- 16.1.The procurement documents shall include the following:
- (a) if applicable, the contract notice or other advertising measure as provided for in points 2 to 5;
- (b) the invitation to tender;
- (c) the tender specifications or the descriptive documents in the case of a competitive dialogue, including the technical specifications and the relevant criteria;
- (d) the draft contract based on the model contract.
- Point (d) of the first subparagraph shall not apply to cases where, due to exceptional and duly justified circumstances, the model contract cannot be used.
- 16.2.The invitation to tender shall:
- (a) specify the rules governing the submission of tenders, including in particular the conditions to maintain them confidential until opening, the closing date and time for receipt and the address to which they are to be sent or delivered or the internet address in case of electronic submission;
- (b) state that submission of a tender implies acceptance of the terms and conditions set out in the procurement documents and that such submission binds the contractor to whom the contract is awarded during performance of the contract;
- (c) specify the period during which a tender will remain valid and shall not be modified in any respect;
- (d) forbid any contact between the contracting authority and the tenderer during the procedure, save, exceptionally, under the conditions laid down in Article 169, and, where provision is made for an on-the-spot visit, specify the arrangements for such a visit;
- (e) specify the means of proof for compliance with the time limit for receipt of tenders;
- (f) state that submission of a tender implies acceptance of receiving notification of the outcome of the procedure by electronic means.
- 16.3.The tender specifications shall contain the following:
- (a) the exclusion and selection criteria;
- (b) the award criteria and their relative weighting or, where weighting is not possible for objective reasons, their decreasing order of importance, which shall also apply to variants if they are authorised in the contract notice;
- (c) the technical specifications referred to in point 17;
- (d) if variants are authorised, the minimum requirements which they must meet;
- (e) information whether the Protocol No 7 on the privileges and immunities of the European Union, annexed to the TEU and the TFEU, or, where appropriate, the Vienna Convention on Diplomatic Relations or the Vienna Convention on Consular Relations applies;
- (f) the evidence of access to procurement;
- (g) the requirement to indicate in which country the tenderers are established and to present the supporting evidence normally acceptable under the law of that country;
- (h) in the case of a dynamic purchasing system or electronic catalogues, information on the electronic equipment used and the technical connection arrangements and specifications needed.
- 16.4.The draft contract shall:
- (a) specify the liquidated damages for failure to comply with its clauses;
- (b) specify the details which must be contained in invoices and in the relevant supporting documents in accordance with Article 111;
- (c) state that, when Union institutions award contracts on their own account, the law which applies to the contract is Union law complemented, where necessary, by a national law or, if necessary for building contracts, exclusively national law;
- (d) specify the competent court for hearing disputes;
- (e) specify that the contractor shall comply with applicable obligations in the fields of environmental, social and labour law established by Union law, national law, collective agreements or by the international social and environmental conventions listed in Annex X to Directive 2014/24/EU;
- (f) specify whether the transfer of intellectual property rights will be required;
- (g) state that the price quoted in the tender is firm and non-revisable, or lay down the conditions or formulas for revision of prices during the lifetime of the contract.
- For the purposes of point (g) of the first subparagraph, if a revision of prices is set out in the contract, the contracting authority shall take particular account of:
- (a) the subject matter of the procurement and the economic situation in which it is taking place;
- (b) the type of contract and tasks and its duration;
- (c) the financial interests of the contracting authority.
- Points (c) and (d) of the first subparagraph of this point may be waived for contracts signed in accordance with point (m) of the second subparagraph of point 11.1.
17. Technical specifications
- 17.1.Technical specifications shall allow equal access of economic operators to the procurement procedures and not have the effect of creating unjustified obstacles to the opening up of procurement to competition.
- Technical specifications shall include the characteristics required for works, supplies or services, including minimum requirements, so that they fulfil the use for which they are intended by the contracting authority.
- 17.2.The characteristics referred to in point 17.1 may include as appropriate:
- (a) the quality levels;
- (b) environmental performance and climate performance;
- (c) for purchases intended for use by natural persons, the accessibility criteria for people with disabilities or the design for all users, except in duly justified cases;
- (d) the levels and procedures of conformity assessment;
- (e) performance or use of the supply;
- (f) safety or dimensions, including, for supplies, the sales name and user instructions, and, for all contracts, terminology, symbols, testing and test methods, packaging, marking and labelling, production processes and methods;
- (g) for works contracts, the procedures relating to quality assurance and the rules relating to design and costing, the test, inspection and acceptance conditions for works and methods or techniques of construction and all the other technical conditions which the contracting authority is in a position to prescribe under general or specific regulations in relation to the finished works and to the materials or parts which they involve.
- 17.3.The technical specifications shall be formulated in any of the following ways:
- (a) in order of preference, by reference to European standards, European technical assessments, common technical specifications, international standards, other technical reference systems established by European standardisation bodies or, failing this, their national equivalents; every reference shall be accompanied by the words ‘or equivalent’;
- (b) in terms of performance or of functional requirements, including environmental characteristics, provided that the parameters are sufficiently precise to allow tenderers to determine the subject matter of the contract and to allow the contracting authority to award the contract;
- (c) by a combination of the methods set out in points (a) and (b).
- 17.4.Where the contracting authority uses the option of referring to the specifications provided for in point (a) of point 17.3, it shall not reject a tender on the grounds that it does not comply with those specifications once the tenderer proves, by any appropriate means, that the solution proposed satisfies, in an equivalent manner, the requirements defined in the technical specifications.
- 17.5.Where the contracting authority uses the option provided for in point (b) of point 17.3 to formulate technical specifications in terms of performance or of functional requirements, it shall not reject a tender which complies with a national standard transposing a European standard, a European technical approval, a common technical specifications, an international standard or technical reference systems established by a European standardisation body, if those specifications address the performance or functional requirements which it has laid down.
- The tenderer shall prove by any appropriate means that the work, supply or service in compliance with the standard meets the performance or functional requirements set out by the contracting authority.
- 17.6.Where a contracting authority intends to purchase works, supplies or services with specific environmental, social or other characteristics, it may require a specific label or specific requirements from a label, provided that all of the following conditions are satisfied:
- (a) the label requirements only concern criteria which are linked to the subject matter of the contract and are appropriate to define the characteristics of the purchase;
- (b) the label requirements are based on objectively verifiable and non-discriminatory criteria;
- (c) the labels are established in an open and transparent procedure in which all the relevant stakeholders may participate;
- (d) the labels are accessible to all interested parties;
- (e) the label requirements are set by a third party over which the economic operator applying for the label cannot exercise a decisive influence.
- The contracting authority may require that economic operators provide a test report or a certificate as means of proof of conformity with the procurement documents from a conformity assessment body accredited in accordance with Regulation (EC) No 765/2008 of the European Parliament and of the Council (42) or an equivalent conformity assessment body.
- 17.7.The contracting authority shall accept any other appropriate means of proof than those referred to in point 17.6, such as a technical dossier from the manufacturer, where the economic operator had no access to the certificates or test reports, or no possibility of obtaining them or obtaining a specific label within the relevant time limits, for reasons that are not attributable to that economic operator and provided that the economic operator concerned proves that the works, supplies or services to be provided fulfil the requirements of the specific label or the specific requirements indicated by the contracting authority.
- 17.8.Unless justified by the subject matter of the contract, technical specifications shall not refer to a specific make or source, or a particular process which characterises the products or services provided by a specific economic operator, or to trade marks, patents, types or a specific origin or production with the effect of favouring or eliminating certain products or economic operators.
- Such reference shall be permitted on an exceptional basis where a sufficiently detailed and intelligible description of the subject matter of the contract is not possible. Such reference shall be accompanied by the words ‘or equivalent’.
18. Exclusion and selection criteria
- 18.1.For the purpose of Article 137, the contracting authority shall accept the European Single Procurement Document (ESPD) referred to in Directive 2014/24/EU, or, failing that, a declaration on honour signed and dated.
- An economic operator may reuse an ESPD which has already been used in a previous procedure, provided that the economic operator confirms that the information contained therein continues to be correct.
- 18.2.The contracting authority shall indicate in the procurement documents the selection criteria, the minimum levels of capacity and the evidence required to prove that capacity. All requirements shall be related and proportionate to the subject matter of the contract.
- The contracting authority shall specify in the procurement documents how groups of economic operators are to meet the selection criteria taking into account point 18.6.
- Where a contract is divided into lots, the contracting authority may set minimum levels of capacity for each lot. It may set additional minimum levels of capacity in the event that several lots are awarded to the same contractor.
- 18.3.With regard to capacity to pursue the professional activity, the contracting authority may require an economic operator to fulfil at least one of the following conditions:
- (a) be enrolled in a relevant professional or trade register, except when the economic operator is an international organisation;
- (b) for service contracts, hold a particular authorisation proving that it is authorised to perform the contract in its country of establishment or be a member of a specific professional organisation.
- 18.4.When receiving requests to participate or tenders, the contracting authority shall accept the ESPD or, failing that, a declaration on honour stating that the candidate or tenderer fulfils the selection criteria. The requirement to submit an ESPD or a declaration on honour may be waived for very low value contracts.
- The contracting authority may ask tenderers and candidates at any moment during the procedure to submit an updated declaration or all or part of the supporting documents where this is necessary to ensure the proper conduct of the procedure.
- The contracting authority shall require the candidates or successful tenderers to submit up-to-date supporting documents except where it has already received them for the purpose of another procedure and provided that the documents are still up-to-date or it can access them in a national database free of charge.
- 18.5.The contracting authority may, depending on its assessment of risks, decide not to require evidence of the legal, regulatory, financial, economic, technical and professional capacity of economic operators in the following cases:
- (a) procedures for contracts awarded by Union institutions on their own account, with a value not exceeding the thresholds referred to in Article 175(1);
- (b) procedures for contracts awarded in the field of external actions, with a value not exceeding the thresholds referred to in Article 178(1);
- (c) procedures for contracts awarded in accordance with points (b), (e), (f)(i) and (iv), (h) and (m) of the second subparagraph of point 11.1.
- Where the contracting authority decides not to require evidence of the legal, regulatory, financial, economic, technical and professional capacity of economic operators, no pre-financing shall be made except in duly justified cases.
- 18.6.An economic operator may, where appropriate and for a particular contract, rely on the capacities of other entities, regardless of the legal nature of the links which it has with them. It shall in that case prove to the contracting authority that it will have at its disposal the resources necessary for the performance of the contract by producing a commitment by those entities to that effect.
- With regard to technical and professional criteria, an economic operator shall only rely on the capacities of other entities where the latter will perform the works or services for which those capacities are required.
- Where an economic operator relies on the capacities of other entities with regard to criteria relating to economic and financial capacity, the contracting authority may require that the economic operator and those entities be jointly liable for the performance of the contract.
- The contracting authority may request information from the tenderer on any part of the contract that the tenderer intends to subcontract and on the identity of any subcontractors.
- For works or services provided at a facility directly under the oversight of the contracting authority, the contracting authority shall require the contractor to indicate the names, contacts and authorised representatives of all subcontractors involved in the performance of the contract, including any changes of subcontractors.
- 18.7.The contracting authority shall verify whether the entities on whose capacity the economic operator intends to rely and the envisaged subcontractors, when subcontracting represents a significant part of the contract, fulfil the relevant selection criteria.
- The contracting authority shall require that the economic operator replaces an entity or subcontractor which does not meet a relevant selection criterion.
- 18.8.In the case of works contracts, service contracts and siting or installation operations in the context of a supply contract, the contracting authority may require that certain critical tasks be performed directly by the tenderer itself or, where the tender is submitted by a group of economic operators, a participant in the group.
- 18.9.The contracting authority shall not demand that a group of economic operators have a given legal form in order to submit a tender or request to participate, but the selected group may be required to adopt a given legal form after it has been awarded the contract if such change is necessary for the proper performance of the contract.
19. Economic and financial capacity
- 19.1.To ensure that economic operators possess the necessary economic and financial capacity to perform the contract, the contracting authority may require in particular that:
- (a) economic operators have a certain minimum yearly turnover, including a certain minimum turnover in the area covered by the contract;
- (b) economic operators provide information on their annual accounts showing ratios between assets and liability;
- (c) economic operators provide an appropriate level of professional risk indemnity insurance.
- For the purposes of point (a) of the first subparagraph, the minimum yearly turnover shall not exceed two times the estimated annual contract value, except in duly justified cases linked to the nature of the purchase, which the contracting authority shall explain in the procurement documents.
- For the purposes of point (b) of the first subparagraph, the contracting authority shall explain the methods and criteria for such ratios in the procurement documents.
- 19.2.In the case of dynamic purchasing systems, the maximum yearly turnover shall be calculated on the basis of the expected maximum size of specific contracts to be awarded under that system.
- 19.3.The contracting authority shall define in the procurement documents the evidence to be provided by an economic operator to demonstrate its economic and financial capacity. It may request in particular one or more of the following documents:
- (a) appropriate statements from banks or, where appropriate, evidence of relevant professional risk indemnity insurance;
- (b) financial statements or their extracts for a period equal to or less than the last three financial years for which accounts have been closed;
- (c) a statement of the economic operator’s overall turnover and, where appropriate, turnover in the area covered by the contract for a maximum of the last three financial years available.
- If, for any valid reason, the economic operator is unable to provide the references requested by the contracting authority, it may prove its economic and financial capacity by any other document which the contracting authority considers appropriate.
20. Technical and professional capacity
- 20.1.The contracting authority shall verify that candidates or tenderers fulfil the minimum selection criteria concerning technical and professional capacity in accordance with points 20.2 to 20.5.
- 20.2.The contracting authority shall define in the procurement documents the evidence to be provided by an economic operator to demonstrate its technical and professional capacity. It may request one or more of the following documents:
- (a) for works, supplies requiring siting or installation operations or services, information on the educational and professional qualifications, skills, experience and expertise of the persons responsible for performance;
- (b) a list of the following:
- (i) the principal services provided and supplies delivered in the past three years, with the sums, dates and clients, public or private accompanied upon request by statements issued by the clients;
- (ii) the works carried out in the last five years, accompanied by certificates of satisfactory execution for the most important works;
- (c) a statement of the technical equipment, tools or the plant available to the economic operator for performing a service or works contract;
- (d) a description of the technical facilities and means available to the economic operator for ensuring quality, and a description of available study and research facilities;
- (e) a reference to the technicians or technical bodies available to the economic operator, whether or not belonging directly to it, especially those responsible for quality control;
- (f) in respect of supplies: samples, descriptions or authentic photographs or certificates drawn up by official quality control institutes or agencies of recognised competence attesting the conformity of the products clearly identified by references to technical specifications or standards;
- (g) for works or services, a statement of the average annual manpower and the number of managerial staff of the economic operator for the last three years;
- (h) an indication of the supply chain management and tracking systems that the economic operator will be able to apply when performing the contract;
- (i) an indication of the environmental management measures that the economic operator will be able to apply when performing the contract.
- For the purposes of point (b)(i) of the first subparagraph, where necessary in order to ensure an adequate level of competition, the contracting authority may indicate that evidence of relevant supplies or services delivered or performed more than three years before will be taken into account.
- For the purposes of point (b)(ii) of the first subparagraph, where necessary in order to ensure an adequate level of competition, the contracting authority may indicate that evidence of relevant works delivered or performed more than five years before will be taken into account.
- 20.3.Where the supplies or services are complex or, exceptionally, are required for a special purpose, evidence of technical and professional capacity may be secured by means of a check carried out by the contracting authority or on its behalf by a competent official body of the country in which the economic operator is established, subject to that body’s agreement. Such checks shall concern the supplier’s technical capacity and production capacity and, if necessary, its study and research facilities and quality control measures.
- 20.4.Where the contracting authority requires the provision of certificates drawn up by independent bodies attesting the compliance of the economic operator with certain quality assurance standards, including on accessibility for disabled persons, it shall refer to quality assurance systems based on the relevant European standards series certified by accredited bodies. The contracting authority shall also accept other evidence of equivalent quality assurance measures from an economic operator that has demonstrably no access to such certificates or has no possibility of obtaining such certificates within the relevant time limits, for reasons that are not attributable to that economic operator and provided that the economic operator proves that the proposed quality assurance measures comply with the required quality assurance standards.
- 20.5.Where the contracting authority requires the provision of certificates drawn up by independent bodies attesting that the economic operator complies with certain environmental management systems or standards, it shall refer to the European Union Eco-Management and Audit Scheme or to other environmental management systems as recognised in accordance with Article 45 of Regulation (EC) No 1221/2009 of the European Parliament and of the Council (43) or other environmental management standards based on the relevant European or international standards by accredited bodies. Where an economic operator had demonstrably no access to such certificates, or no possibility of obtaining them within the relevant time limits for reasons that are not attributable to that economic operator, the contracting authority shall also accept other evidence of environmental management measures, provided that the economic operator proves that those measures are equivalent to those required under the applicable environmental management system or standard.
- 20.6.A contracting authority may conclude that an economic operator does not possess the required professional capacity to perform the contract to an appropriate quality standard where the contracting authority has established that the economic operator has conflicting interests which may negatively affect its performance.
21. Award criteria
- 21.1.Quality criteria may include elements such as technical merit, aesthetic and functional characteristics, accessibility, design for all users, social, environmental and innovative characteristics, production, provision and trading process and any other specific process at any stage of the life cycle of the works, supplies or services, organisation of the staff assigned to performing the contract, after-sales service, technical assistance or delivery conditions such as delivery date, delivery process and delivery period or period of completion.
- 21.2.The contracting authority shall specify in the procurement documents the relative weighting which it gives to each of the criteria chosen to determine the most economically advantageous tender except when using the lowest price method. Those weightings may be expressed as a range with an appropriate maximum spread.
- The weighting applied to price or cost in relation to the other criteria shall not result in the neutralisation of price or cost.
- If weighting is not possible for objective reasons, the contracting authority shall indicate the criteria in decreasing order of importance.
- 21.3.The contracting authority may lay down minimum levels of quality. Tenders below those levels of quality shall be rejected.
- 21.4.Life-cycle costing shall cover parts or all of the following costs, to the extent relevant, over the life cycle of works, supplies or services:
- (a) costs, borne by the contracting authority or other users, such as:
- (i) costs relating to acquisition;
- (ii) costs of use, such as consumption of energy and other resources;
- (iii) maintenance costs;
- (iv) end-of-life costs, such as collection and recycling costs;
- (b) costs attributed to environmental externalities linked to the works, supplies or services during their life cycle, provided their monetary value can be determined and verified.
- 21.5.Where the contracting authority assesses the costs using a life-cycle costing approach, it shall indicate in the procurement documents the data to be provided by the tenderers and the method which it will use to determine the life-cycle costs on the basis of those data.
- The method used for the assessment of costs attributed to environmental externalities shall fulfil the following conditions:
- (a) it is based on objectively verifiable and non-discriminatory criteria;
- (b) it is accessible to all interested parties;
- (c) economic operators can provide the required data with reasonable effort.
- Where applicable, the contracting authority shall use the mandatory common methods for the calculation of life-cycle costs provided for in Union legal acts listed in Annex XIII to Directive 2014/24/EU.
22. Use of electronic auctions
- 22.1.The contracting authority may use electronic auctions, in which new prices, revised downwards, or new values concerning certain elements of tenders are presented.
- The contracting authority shall structure the electronic auction as a repetitive electronic process, which occurs after an initial full evaluation of the tenders, enabling them to be ranked using automatic evaluation methods.
- 22.2.In open, restricted or competitive procedures with negotiation, the contracting authority may decide that the award of a public contract is preceded by an electronic auction when the procurement documents can be established with precision.
- An electronic auction may be held on the reopening of competition among the parties to a framework contract as referred to in point (b) of the second subparagraph of point 1.3 and on the opening for competition of contracts to be awarded under the dynamic purchasing system referred to in point 9.
- The electronic auction shall be based on one of the award methods set out in Article 167(4).
- 22.3.The contracting authority which decides to hold an electronic auction shall state that fact in the contract notice.
- The procurement documents shall include the following details:
- (a) the values of the features which will be the subject of an electronic auction, provided that those features are quantifiable and can be expressed in figures or percentages;
- (b) any limits on the values which may be submitted, as they result from the specifications relating to the subject matter of the contract;
- (c) the information which will be made available to tenderers in the course of the electronic auction and, where appropriate, when it will be made available to them;
- (d) the relevant information concerning the electronic auction process including whether it includes phases and how it will be closed, as set out in point 22.7;
- (e) the conditions under which the tenderers will be able to tender and, in particular, the minimum differences which will, where appropriate, be required when submitting the tender;
- (f) the relevant information concerning the electronic equipment used and the arrangements and technical specifications for connection.
- 22.4.All tenderers who have submitted admissible tenders shall be invited simultaneously by electronic means to participate in the electronic auction using the connections in accordance with the instructions. The invitation shall specify the date and time of the start of the electronic auction.
- The electronic auction may take place in a number of successive phases. The electronic auction shall not start sooner than two working days after the date on which invitations are sent out.
- 22.5.The invitation shall be accompanied by the outcome of a full evaluation of the relevant tender.
- The invitation shall also state the mathematical formula to be used in the electronic auction to determine automatic re-rankings on the basis of the new prices and/or new values submitted. That formula shall incorporate the weighting of all the criteria fixed to determine the most economically advantageous tender, as indicated in the procurement documents. For that purpose, any ranges shall, however, be reduced beforehand to a specified value.
- Where variants are authorised, a separate formula shall be provided for each variant.
- 22.6.Throughout each phase of an electronic auction the contracting authority shall instantaneously communicate to all tenderers at least sufficient information to enable them to ascertain their relative rankings at any moment. It may also, where this has been previously indicated, communicate other information concerning other prices or values submitted as well as announce the number of tenderers in any specific phase of the auction. It shall not however disclose the identities of the tenderers during any phase of an electronic auction.
- 22.7.The contracting authority shall close an electronic auction in one or more of the following ways:
- (a) at the previously indicated date and time;
- (b) when it receives no more new prices or new values which meet the requirements concerning minimum differences, provided that it has previously stated the time which it will allow to elapse after receiving the last submission before it closes the electronic auction;
- (c) when the previously indicated number of phases in the auction has been completed.
- 22.8.After closing an electronic auction, the contracting authority shall award the contract on the basis of the results of the electronic auction.
23. Abnormally low tenders
- 23.1.If, for a given contract, the price or costs proposed in a tender appears to be abnormally low, the contracting authority shall request in writing details of the constituent elements of the price or costs which it considers relevant and shall give the tenderer the opportunity to present its observations.
- The contracting authority may, in particular, take into consideration observations relating to:
- (a) the economics of the manufacturing process, of the provision of services or of the construction method;
- (b) the technical solutions chosen or the exceptionally favourable conditions available to the tenderer;
- (c) the originality of the tender;
- (d) compliance of the tenderer with applicable obligations in the fields of environmental, social and labour law;
- (e) compliance of subcontractors with applicable obligations in the fields of environmental, social and labour law;
- (f) the possibility of the tenderer obtaining State aid in compliance with applicable rules.
- 23.2.The contracting authority shall only reject the tender where the evidence supplied does not satisfactorily account for the low price or costs proposed.
- The contracting authority shall reject the tender where it has established that the tender is abnormally low because it does not comply with applicable obligations in the fields of environmental, social and labour law.
- 23.3.Where the contracting authority establishes that a tender is abnormally low because the tenderer has obtained State aid, it may reject the tender on that sole ground only if the tenderer is unable to prove, within a sufficient time limit fixed by the contracting authority, that the aid in question was compatible with the internal market within the meaning of Article 107 TFEU.
24. Time limits for receipt of tenders and requests to participate
- 24.1.The time limits shall be longer than the minimum time limits set out in this point where tenders can only be drawn up after a visit to the site or after an on-the-spot consultation of the documents supporting the procurement documents.
- The time limits shall be prolonged by five days in any of the following cases:
- (a) the contracting authority does not offer direct access free of charge by electronic means to the procurement documents;
- (b) the contract notice is published in accordance with point (b) of point 4.2.
- 24.2.In open procedures, the time limit for receipt of tenders shall be no less than 37 days from the day following dispatch of the contract notice.
- 24.3.In restricted procedures, in competitive dialogue, in competitive procedures with negotiation, in dynamic purchasing systems and in innovation partnerships, the time limit for receipt of requests to participate shall be no less than 32 days from the day following dispatch of the contract notice.
- 24.4.In restricted procedures and in competitive procedures with negotiation, the time limit for receipt of tenders shall be no less than 30 days from the day following dispatch of the invitation to tender.
- 24.5.In a dynamic purchasing system, the time limit for receipt of tenders shall be no less than 10 days from the day following dispatch of the invitation to tender.
Reading this document does not replace reading the official text published in the Official Journal of the European Union. We assume no responsibility for any inaccuracies arising from the conversion of the original to this format.
This text is published under EUR-Lex's own terms of reuse, not a Legalize or public-domain licence.
EUR-Lex
Creative Commons Attribution 4.0 International (CC BY 4.0)
© European Union, https://eur-lex.europa.eu — Source: EUR-Lex (Publications Office of the European Union). Reused under the Creative Commons Attribution 4.0 International (CC BY 4.0) licence. Only EU legislation published in the printed Official Journal of the European Union is deemed authentic; consolidated texts are reproduced here for documentation purposes and have been reformatted to Markdown.