Lietuvos Respublikos įstatymas dėl koncesijos suteikimo ir Lietuvos Respublikos esminių turtinių įsipareigojimų prisiėmimo Visagino branduolinės (atominės) elektrinės projekte

Tipas Įstatymas
Publikavimas 2012-06-21
Būsena Galiojantis
Ministerija Lietuvos Respublikos Seimas
Šaltinis TAR
straipsniai 5
Pakeitimų istorija JSON API

102.2       Each segment of the corridor shall be evaluated to verify viability and determine the necessary improvements to meet the criteria specified herein. Each evaluation shall include a condition assessment that determines the load carrying characteristics, geometric parameters, physical barriers and constraints to be altered. The evaluations shall include data collection and gathering design input consisting of, but not limited to, the following:

a.         Perform geotechnical investigation to determine existing soil strength and soil quality values that will be used for determining existing and for designing new pavements and structures.

b.         Perform structural evaluation and assessment of bridges and culverts to determine integrity and load rating.

c.         Perform topographic surveying and mapping to accurately document existing surface features and overhead obstructions, and to verify property limits and ownership, where warranted.

d.         Perform subsurface utility surveying and mapping to identify and document utility crossings along the heavy haul corridor and within road/structure improvement areas.

d1.       Evaluate and record environmental conditions where required as part of the permitting process.

e.         The existing road and infrastructure conditions along the corridor vary significantly, and include asphalt paved highways, municipal streets, and unsurfaced trails as identified in Articles 116.1.b, c, d and j. The full extent of overall design work will be confirmed after the condition assessment and improvement evaluation phases, however based on initial reconnaissance information the work shall include the following Design Activities:

e1.       Design road structural section upgrades and improvements to increase the load carrying capacity and stability as necessary to meet the minimum criteria specified herein.

e2.       Design road intersection modifications, and improve horizontal and vertical alignment along the corridor to provide sufficient width, grade, and curvature to satisfy the combined heavy haul transporter vehicle and equipment dimensions (as defined in transportation schemes), turning movements, and operating requirements.

e3.       Design permanent modifications and improvements for existing bridge and culvert crossings to stabilize, stiffen, and reinforce superstructure and substructure elements to withstand design heavy haul loads and to satisfy transporter dimensions and operating requirements.

e4.       Design new bridges, culverts, and buried utility protection systems where existing bridges, culverts and utilities are not capable of supporting design heavy haul loads.

e5.       Design relocations and/or alterations for overhead obstructions, including traffic sign trusses and utility crossing bridges, truss mounted traffic signals, and low voltage electric cables (4kV and 10kV).

e6.       Identify relocation and/or alteration requirements for overhead obstructions and traffic control appurtenances that will be relocated, including high voltage electric transmission lines (35kV, 110kV, and 330kV), light poles and/or lighting mast arms, post mounted traffic signals, and post-mounted traffic control signs.

e7.       Develop stopping areas along the heavy haul transporter corridor to be used for fueling and vehicle maintenance (maintenance performed by the heavy haul transporter vehicle personnel).

e8.       Develop overtaking zones or traffic bypass plans along the heavy haul transport corridor to be used to minimize traffic congestion.

e9.       The Design Consultant shall prepare deliverables consisting of technical specifications and design drawings to identify the material quality and installation requirements for the Design Activities specified above to be used for construction, permitting, scheduling, and cost estimating. The deliverables shall meet both local, state, and national codes, standards, and regulations within Lithuania and Lithuanian road bounding parameters defined in Article 103 and the combined heavy haul transporter vehicle and equipment requirements defined in Article 104.

e10.     The Owner may prepare a pre-haul test plan for portions of the heavy haul corridor to be performed after construction improvements are completed to verify that the as-constructed heavy haul road is able to withstand anticipated live loads from the heavy haul transporter.

102.3       To support the required design and engineering, this Functional Technical Specification has been prepared to define the overall objective of the project, and to identify the minimum requirements and criteria that shall be used by a qualified Design Consultant to design the heavy haul road.

102.4       This Specification may not be all inclusive, and the expectation is that the knowledge and experience of the Design Consultant will supplement the requirements defined in this Specification. This Specification is intended for the evaluation of existing facilities and the design of upgrades, modifications, and alterations for the heavy haul road construction upgrades: this Specification is not intended to meet the long term design criteria of the haul road after completion of the project, nor to meet the long term design criteria of the local and national governing agencies; however, at a minimum the existing functional classification of each road segment that is modified in any way shall continue to meet current functionality with regard to traffic use and safety, utility easement and ownership, and storm water drainage and conveyance.

102.5       This Specification covers the requirements and criteria for performing a detailed corridor investigation and roadway/bridge design. The scope shall include verification of design inputs, environmental impact assessment, preparing preliminary and final documents for review, permitting support, developing cost estimates, and preparing a detailed schedule covering design, permitting, and construction.

102.6       Design Consultant Requirements and Qualifications:

a.         Design Consultant will be selected by the RoL, and shall demonstrate competency by having previous experience in projects with similar magnitude and character involving infrastructure assessment, design of highways and bridges, buried and overhead utility relocations, and associated permitting, construction, cost estimating, and scheduling.

b.         Design Consultant shall posses experience in roadway design, including horizontal and vertical geometric alignment, structural thickness design, safety, and traffic control.

c.         Design Consultant shall possess experience in bridge design of multiple span structures and segmental bridges, and in bridge assessment and modification.

d.         Design Consultant shall possess experience in geotechnical design and analysis for road pavements, bridges, and structural foundations.

e.         Design Consultant shall possess experience in hydrology and hydraulic analysis relating to bridges, including flood evaluation and routing, scour analysis, water surface modeling, and storm water management regulations.

102.7       The Work shall conform to the requirements of this Specification and shall be performed and supervised by personnel who are experienced and knowledgeable in the type of work to be performed. The Work shall be performed exclusively by the Design Consultant’s trained and competent personnel or, where authorized, that of its subcontractors.

102.8       The Design Consultant, at the Owner’s request, shall provide the Owner with any and all information pertaining to the Work including design documents, construction documents, schedule information, etc.

103.

LITHUANIAN ROAD BOUNDING PARAMETERS

103.1       Maximum road width in straight road sections identified in Article 116.1. k 9.5 m:

a.         6.5 meters asphalt paved with 0.25 meter compacted gravel shoulders

b.         1.25 compacted road side

c.         There shall be no gap between asphalt covered and compacted road side areas.

103.2       Maximum road ground bearing pressure for 103.1 a.. as identified in Article 116.1. k:

a.         4.4 metric tons load per square meter

b.         10 metric tons load per axle

103.3       Maximum ground bearing pressure as identified in Article 116.1. h:

a.         1.800 ton, being the sum of combined heavy haul transporter vehicle and equipment

104.

HEAVY HAUL TRANSPORTER VEHICLE AND EQUIPMENT PAYLOAD DATA

104.1       The heavy haul transport vehicle will be a modular, multi-axle rubber tire vehicle designed specifically for transporting the equipment. The heavy haul transporter arrangement will vary based on the type of equipment being transported, however the largest, bounding arrangement for RPV will consist of two coupled self-propelled trailers, each with a turntable supporting the equipment load, pulled by two prime movers, and pushed by two additional prime movers. The following information shall be considered the largest-maximum bounding dimensional data as identified in Article 116.1. e, h, i, l and n, with supplemental information on bounding obstacle parameters provided in Article 116.1. m:

a.         Overall transport vehicle length: 115.6 m (two trailers and four prime movers)

b.         Maximum Trailer length: 33 m (each). 69 m for two (2) transporters including connector

c.         Maximum Trailer width: 6.300 m

d.         Maximum Trailer bed height: 1.19 m

e.         Minimum ground clearance: 0.94 m

f.         Number of axles: 88 per platform, per each trailer

g.         Number of axle lines: 22 axles at 1.5 meters per platform, per each trailer

h.         Number of tires per axle: 16

i.          Axle spacing: 1.5 m

j.          RPV width path: 10 m, 5 m on each side of the center of the road, measured 7.7 m from grade RPV height path: 13 m,

k.         RPV pedestal No.3 height path: 17 m

l.          Trailer width path (no obstacles): 8 m

104.2       RPV Equipment Payload: the number described below through a. to b. subject to change due to design progress.

a.         Maximum payload weight: approximately 1004 metric tons

b.         Maximum rigging/support frame weight: approximately 136 metric tons

c.         Maximum payload width: 9.2 meters, measured 7.707 meters from grade

d.         Maximum payload height: 12.207 meters from grade

104.3       Gross Operating Weight of Heavy Haul Transporter:

a.         The gross operating weight of the combined heavy haul transporter vehicle and equipment: no more than 1800 metric tons

b.         Ground bearing pressure: 4.4 metric tons per square meter

104.4       The heavy haul transporter has the following operational characteristics:

a.         Operating speed: 10 – 25 kilometers per hour (for reference purposes)

b.         RPV Minimum inner turning radius: 13.5 meters

c.         RPV Minimum outer turning radius: 33.5 meters

104.5       Heavy Haul Road Geometric Requirements for straight road sections and corners:

a.         Maximum slope: less than 8 percent, on dry pavement

b.         RPV Minimum curvature radius for vertical slope: greater than 340.5 m

c.         RPV Minimum length of relaxation slops: greater than 27.3 m

d.         Traversal inclines:

d1. Minimum traversal incline for straight-line is 2.5 %; Maximum traversal incline for straight-line is 4.0 %

d2. Minimum traversal incline for curve-line is 2.5 %; Maximum traversal incline for curve-line is 4.0 %;

d3. Minimum traversal incline for crossroad is 2.5 %; Maximum traversal incline for crossroad is 4.0 %.

104.6       Temporary Support Vehicle Information:

a.         The movement of the heavy haul transporter will be accompanied en-route by support vehicles to ensure safety of the crew and public, provide security, perform routine maintenance, and to manage emergencies as they arise. The type of support vehicles anticipated will be determined by the heavy haul transport company.

105.

HEAVY HAUL TRIP DATA

105.1       The following information shall be used in establishing the load repetitions for pavement and bridge design with appropriate margin:

a.         The preliminary total number of heavy haul transporter trips anticipated as described in Article 116.1.a.

b.         The Owner will provide the Design Consultant with a final list upon receipt from EPC Contractor.

106.

ROADWAY DESIGN CRITERIA

106.1       All road segments shall be inspected and evaluated to determine the condition and serviceability to support the transporter loads for the term of the transporter moves. All deficiencies shall be documented in a report with recommendations for repairs or demolition and rebuilding.

106.2       Road structural layers shall be determined through a geotechnical investigation by obtaining pavement cores and soil borings, or by other acceptable methods, to determine thickness, type, and condition of layers present in the structural section that may include asphalt, concrete, aggregate base, and to determine the soil subgrade properties.

106.3       Road pavement shall be analyzed and upgraded or reconstructed, as necessary, to withstand the heavy haul transporter loads and loading repetitions in accordance with the Functional Technical Specifications defined in this document and meet the requirements of European Union norms and Lithuanian laws.

106.4       Road alignment geometric parameters shall be modified as necessary to meet the requirements described in Article 103 and 104 in order to provide sufficient passage for combined heavy haul transporter vehicle and equipment, and also meet Lithuanian road safety requirements.

107.

BRIDGE DESIGN CRITERIA

107.1       All bridges shall be inspected and evaluated to determine their condition and serviceability load rating capacity to support the combined heavy haul transporter vehicle and equipment for the term of the transporter moves. All deficiencies shall be documented in a report with recommendations for repairs or demolition and rebuilding.

107.2       Bridges and culverts shall be designed in accordance with the Functional Technical Specifications defined in this document and meet the requirements of European Union norms and Lithuanian laws.

a.         Concrete and steel decks shall meet the requirements of all local and government regulations.

b.         Parapets and guard rails shall be designed to meet the Functional Technical Specifications defined in Articles 103 and 104.

108.

STANDARDS AND CODES REFERENCES

108.1       The following design standards and codes as applicable to the work to be performed, from the Lithuanian Road Administration, Lithuanian Association of Surveyors, the Lithuanian Standards Board, and from other jurisdictional authorities.

109.

SURVEY INFORMATION

109.1       The Design Consultant shall prepare a topographic survey of the heavy haul transporter corridor where required to obtain accurate locations and elevations of existing features (pavement limits and grade, trees, signs, culverts, etc.) that require modification or alteration of the corridor. The survey shall be of sufficient detail and limits as necessary to meet the intended design purpose.

110.

STOPPING AREA AND OVERTAKING ZONE REQUIREMENTS

110.1       Stopping areas are required for periodic heavy haul transporter vehicles stops that will be used for vehicle maintenance and refueling, provide a safe location to allow for inclement weather to pass, and for operator rest. The following criteria shall be used for the layout and design of the stopping areas along the heavy haul transporter corridor.

a.         The stopping area shall be located directly adjacent to the heavy haul road, and provide sufficient space for support vehicles and smaller heavy haul transporters: large transporters will stop and remain on the heavy haul road and not utilize the stopping area.

b.         The location, size, and exact number of stopping areas shall be coordinated with the Owner during the detailed design phase.

c.         The stopping areas shall be compacted to meet the combined heavy haul transport vehicle and equipment load requirements.

d.         Trees surrounding the stopping areas shall be preserved to the fullest extent possible.

110.2       Overtaking zones or traffic bypasses shall be appropriately identified and/or located, with Owner’s acceptance, to allow passage of vehicles around the heavy haul transporter vehicle to limit traffic congestion to the greatest extent practical.

111.

SUBMITTALS

111.1       Submittals required with proposal:

a.         Key Personnel: Name and resume of Project Manager and Project Lead Engineer identified to work on this project, having at least five years of supervisory experience with highway and road projects of similar size and/or scope.

b.         Project Experience: Description of the company’s recent work history over the last five years for projects of similar magnitude and scope. For each project, include a brief description of work scope.

c.         References: Name and current phone number of professional references, from recent projects that include condition assessment, evaluation, design, and permitting for road and bridge related projects.

112.

GEOTECHNICAL INFORMATION

112.1       A subsurface investigation program shall be performed along the heavy haul transporter corridor where it is necessary to obtain subsurface information in accordance with Lithuanian laws.

112.2       The following are the minimum requirements for road sections that consist of asphalt pavement:

a.         Soil borings shall be obtained in sufficient depth, quantity, and frequency to obtain reasonable pavement and subgrade soil information that allows accurate assessment of the pavement loading capacity and design of modified or new pavement structural layers in accordance with Lithuanian laws.

112.3       The following are the minimum requirements where new bridges are to be constructed or existing bridges need to be upgraded:

a.         Soil borings shall be obtained in sufficient depth, quantity, and frequency to obtain required subsoil parameters to design bridge modifications or design new bridges in accordance with Lithuanian laws.

113.

SERVICES AND INFORMATION PROVIDED BY OTHERS

113.1       The initial selection of the heavy haul corridor has been investigated and evaluated by the Owner, as identified in Articles 116.1.b, c, d and j, and shall be used as the primary input for establishing the corridor of the heavy haul transporter.

113.2       The heavy haul transporter arrangement (length, number of axles, etc.) for each piece of equipment to be hauled as identified in Article 116.1.a will be prepared by EPC Contractor and will not exceed the bounding road parameters specified in Article 103.1.

113.3       Heavy haul transporter maintenance, repair, and fueling will be performed by the Heavy Haul Transporter Company.

113.4       Relocation and/or alteration, and restoration of roadside obstructions that include electric transmission lines (35 kV, 110 kV, and 330 kV), light poles and/or lighting mast arms, post mounted traffic signals, post-mounted traffic control signs, etc., shall be considered in the haul road improvements and shall be performed if necessary..

113.5       The Scope of Work covered by this Functional Technical Specification is limited to the heavy haul road between Klaipeda port pier and the boundary of the VNPP construction site, and improvements beyond these limits, if necessary, will be provided by Others.

114.

DEFINITIONS

114.1       Whenever the following terms appear in the Contract Documents, they shall mean the following:

a.         Design Consultant - means the firm, company, organization retained by Owner to perform the Work covered by this Specification

b.         Work - means documentation preparation and submittal, procurement, labor, services, equipment, material, construction and maintenance work as set forth in the Contract Documents

c.         Contract Documents - means all Drawings, Data, Specifications, Addenda and Revisions thereto; Purchase Orders and Supplements to the Purchase Order; Design Consultant’s Drawings as accepted by Owner; and all documents which are a part of the Contract

d.         Heavy Haul Transport Company - means the entity responsible for providing heavy haul transporter equipment, supervision, and labor to transport the equipment along the heavy haul corridor defined herein

e.         Others - means any firm exclusive of the Design Consultant

f.         Indicated - means as shown, noted, called for, or specified on the Drawings and Data

g.         Provide - means furnish, perform and install and when applicable place in successful operation

115.

CORRESPONDENCE

115.1       Address and submit correspondence, reports and related documents to the following:

a.         Owner contact: VAE

Technical Contact: To be determined

Contractual Contact: To be determined

116.

DRAWINGS AND DATA

116.1       The following Drawings and Data prepared and/or supplied by the Owner, Owner’s Engineer, or Hitachi-GE Nuclear Energy/ Hitachi Transport Systems, unless otherwise indicated, form a part hereof:

a.         Major Component Packing List for VPN, CNJ-LT-G001_R2_Major Component Packing List 20111228, Hitachi-GE Nuclear Energy, Ltd (this information must be used only for reference purposes, and is subject to revision).

b.         Route Survey of the Lithuanian Road Network, Summary Report, prepared by Visagino Atomine Elektrine (VAE), 2011.

c.         Survey Results and Recommendations Report, prepared by Hitachi Transport Systems, Ltd., 2011 (this information must be used only for reference purposes, and is subject to revision).

d.         Difficult Turns Report, prepared by Hitachi Transport Systems, Ltd., 2011 (this information must be used only for reference purposes, and is subject to revision).

e.         Transport Arrangement RPV, 0010053120-NL03-D-T1, Sheet 1, Revision 0, (this information must be used only for reference purposes, and is subject to revision).

f.         General Arrangement Platform Trailers RPV, 0010053120-NL03-D-G01, Sheet 1, Revision 0, (this information must be used only for reference purposes, and is subject to revision).

g.         General Arrangement Discharge at Klaipeda Port RPV, 0010053120-NL03-D-G02, Sheet 1, Revision 0, (this information must be used only for reference purposes, and is subject to revision).

h.         Functional Requirements for the Access Road, Hitachi-GE Nuclear Energy, Ltd., April 25, 2012.

i.          Hitachi-GE Nuclear Energy Letter XE-LT-0156, Rev.0, February 24, 2012.

j.          VAE Detailed road survey maps (Difficult turns VH-12022701, February 27, 2012 and Straight part of route VH-12030501, March 5, 2012).

k.         Republic of Lithuania bounding road parameters VH-12031401, March 14, 2012.

l.          Hitachi-GE Nuclear Energy Letter XE-LT-0161, Rev.0, February 27, 2012.

m.        Bounding obstacles parameters VH-12031402, March 14, 2012.

n.         Transport Arrangement RPV pedestal No. 3, 0010053120-D-T03, Sheet 1, Revision 0, (this information must be used only for reference purposes, and is subject to revision).

o.         Hitachi-GE Nuclear Energy Letter XL-LT-0029, Rev.0, March 29, 2012.

SCHEDULE 3

INITIAL SHAREHOLDERS' DETAILS AND SHAREHOLDING

Shareholder

Potential shareholding

Lithuanian Investor

38 %

Strategic Investor

20 %

Latvenergo AS

20 %

Eesti Energia AS

22 %

SCHEDULE

NATIONAL SECURITY CRITERIA

1.

None of the transferee or any of its Associated Companies, either individually or collectively:

1.1       controls, directly or indirectly, whether by virtue of a State-granted right or as a matter of fact, the importation from any Non-NATO State or Non-EEA State into the Republic of Lithuania of one third or more of the total volume of any type of fossil fuel imported into the Republic of Lithuania;

1.2       effectively controls fossil fuel supply infrastructure in any Non-NATO State or Non-EEA State, which effective control enables the transferee or any of its Associated Companies (either individually or collectively) as the case may be to reduce the supply of any type of fossil fuel imported into the Republic of Lithuania by 33 per cent. or more of the total imported volume;

1.3       controls, directly or indirectly, whether by virtue of a State-granted right or as a matter of fact, the importation into the Republic of Lithuania from any Non-NATO State or Non-EEA State of one third or more of the total of electricity imported into the Republic of Lithuania; or

1.4       controls electricity transmission infrastructure in any Non-NATO State or Non-EEA State, which control enables the transferee or any of its Associated Companies (either individually or collectively) as the case may be to reduce the supply of electricity imported into the Republic of Lithuania by 33 per cent. or more of the total imported volume,

and the proportions referred to in this Paragraph 1 shall be calculated by reference to the 12-month period preceding the date on which the relevant Transfer Notice is issued by the Transferring Shareholder.

2.

None of the transferee or any of its Associated Companies has been convicted as part of a properly convened process as a result of its direct or indirect relationship with organised criminal groups, special services or groups of foreign states which have connections to international terrorist organisations.

SCHEDULE 5

SITE

1.

Subject to Paragraph 2 of this Schedule 5 (Site), the "Site" shall be the eastern site (including the infrastructure on the site) as more specifically described in Part I of this Schedule 5 (Site).

2.

If, following the Concession Date, the site described in Part I of this Schedule 5 (Site) is considered by the PCO (acting reasonably) to be unsuitable for the Project, the PCO shall notify the RoL as soon as practicable, and in any event no later than eighteen (18) Months after the Investment Date, that the "Site" shall instead be the western site (including the infrastructure on the western site) as more specifically described in Part II of this Schedule 5 (Site).

PART I

EASTERN SITE

No.

Unique/Cadastral No.

Area (ha)

Purpose/Type of Use

1.

4400-2110-7279 4535/0003:7 Karlu k.v.

212.4183

Other, territories for industry and storage objects (for construction of industry and storage companies)

2.

4400-2110-7380 4535/0002:19 Karlu k.v.

28.9150

3.

4400-2110-7024 4535/0002:17 Karlu k.v.

11.9552

Other, territories for engineering infrastructure (for corridors of communication and infrastructure networks)

4.

4400-2110-7446 4535/0002:20 Karlu k.v.

34.4229

The infrastructure on the eastern site comprises the Cooling Water Facilities located on the land plot unique No. 4400-2110-7446, cadastral No. 4535/0002:20 Karlu k.v.

PART II

WESTERN SITE

No.

Unique/Cadastral No.

Area (ha)

Purpose/Type of Use

1.

4400-2110-8854 4535/0002:22 Karlu k.v.

63.6512

Other, territories for industry and storage objects (for construction of industry and storage companies)

2.

4400-2110-7598 4535/0002:21 Karlu k.v.

29.7316

Other, type of use not specified

3.

4400-2103-1594 4535/0002:16 Karlu k.v.

10.6823

Other, territories for industry and storage objects (for construction of industry and storage companies)

4.

4400-2110-9138 4535/0002:23 Karlu k.v.

9.4718

Other, territories for engineering infrastructure (for corridors of communication and infrastructure networks)

5.

4400-2110-7446 4535/0002:20 Karlu k.v.

34.4229

The infrastructure on the western site comprises the Cooling Water Facilities located on the land plot unique No. 4400-2110-7446, cadastral No. 4535/0002:20 Karlu k.v., the land plot unique No. 4400-2110-9138, cadastral No. 4535/0002:23 Karlu k.v. (which can serve for connection to the Cooling Water Facilities) and transmission lines.

SCHEDULE 6

DECOMMISSIONING AND WASTE FUNDING PRINCIPLES

(1)       The decommissioning and radioactive waste management and disposal for the Visaginas New Nuclear Power Plant (NNPP) shall be based on a “polluter pays” principle and established in accordance with the principles and procedures set out herein.

(2)       RoL shall ensure that any Laws applicable to the decommissioning of the NNPP and/or the management or disposal of radioactive waste originating from the NNPP are consistent with the Decommissioning and Waste Management Principles (as defined below) and the other provisions of this Schedule 6.

Decommissioning and Waste Management Arrangements

(3)       The detailed procedures, methods and outcomes for the decommissioning of the NNPP and management and disposal of radioactive waste during the period from first criticality of the NNPP until the completion of all decommissioning works together with the method for estimating and revising the costs of decommissioning and planning for expenditure shall be set out in detailed decommissioning and waste management provisions (the “Decommissioning and Waste Management Arrangements”) in accordance with this Schedule 6.

(4)       The PCO shall be responsible for the preparation of the Decommissioning and Waste Management Arrangements in a manner which is consistent with the Decommissioning and Waste Management Principles (as defined below).

(5)       The Decommissioning and Waste Management Arrangements shall be submitted by the PCO to the Supervising Authority (as defined below) for review. The Supervising Authority shall be established, resourced and staffed and will conduct its activities in a manner consistent with the Commission Recommendation of 24 October 2006 on the management of financial resources for the decommissioning of nuclear installations, spent fuel and radioactive waste (2006/851/Euratom) and the Guide to the Commission Recommendation on the management of financial resources for the decommissioning of nuclear installations, spent fuel and radioactive waste (2006/851/Euratom) (both together - the "Commission Requirements") and the principles set out herein.

(6)       The arrangements for the funding of decommissioning of the NNPP and the funding of management and disposal of radioactive waste shall be carried out in accordance with the Decommissioning and Waste Management Arrangements (as revised from time to time in accordance with this Schedule 6).

(7)       No Law will provide for any project participant or direct or indirect investor in the PCO to have any liability to any person in connection with the matters referred to in paragraph 6.

(8)       The PCO shall maintain and update the Decommissioning and Waste Management Arrangements to ensure continuing compliance with the Decommissioning and Waste Management Principles (as defined below).

(9)       The Decommissioning and Waste Management Arrangements and the cost estimates contained therein shall be updated every five years and whenever information becomes available to the PCO which will result in a material change to the Decommissioning and Waste Management Arrangements or the estimated costs of decommissioning the NNPP. The adequacy of the fund's assets shall be assessed annually.

Decommissioning and Waste Management Principles

(10)     The principles for the decommissioning of the NNPP and the management and disposal of radioactive waste shall include the following matters:

• a sufficiently high certainty basis for estimating the cost and a method for its determination;

• clear division of rights, responsibilities and liabilities in relation to fund management;

• regular contributions to the Fund by the PCO, subject to paragraph 7, as the PCO is the only private sector party which will be required by applicable law to make contributions to the Fund or for the implementation of decommissioning and waste management arrangements;

• a mechanism for a conservative estimation and independent verification of growth assumptions of the Fund;

• a mechanism and a sufficient prudent timescale for correction of any underfunding or overfunding of the Fund;

• regular updates of the Decommissioning and Waste Management Arrangements, the cost estimates of the respective arrangements; fund performance, its financial assumptions, adequacy and contribution levels;

• a price firming process for the calculation of costs for management and final disposal of waste from the Ignalina NPP and Visaginas NNPP (subject to an agreement between the parties in accordance with paragraph 15 of this Schedule 6)

(11)     Decommissioning and waste management and disposal methods and procedures shall be based on the most up-to-date available knowledge of the state of the plant and up-to-date and proven technologies and methods at each of the reviews referred to in paragraph 9.

(12)     The costs of decommissioning, waste management and disposal shall be estimated on a transparent basis and the methods and procedures used for estimating costs shall ensure a sufficiently high certainty as to the projected future costs of decommissioning at all stages throughout the expected operating life of the NNPP.

(13)     There shall be a clear division of rights, responsibilities and liabilities between the RoL and the PCO with respect to decommissioning, waste management and disposal based on the principles set out herein.

(14)     Without limiting the operation of paragraph 15, the PCO may elect at its option (to the extent in accordance with applicable Law and regulation) that the final disposal of spent nuclear fuel and other high level waste shall be achieved by one of:

• construction and operation of a national geological disposal facility in Lithuania;

• to the extent permitted by Law and to the extent feasible, disposal of spent nuclear fuel and other high level waste into a geological disposal facility developed on a regional (international) level;

• reprocessing of spent nuclear fuel and consequent disposal of reprocessed waste or by-products of reprocessing in a national or regional (international) geological disposal facility; or

• a combination of any or all of the above.

(15)     The parties acknowledge that if RoL intends to construct and operate a geological disposal facility in Lithuania for the final disposal of spent nuclear fuel and other high level waste originating from the Ignalina NPP (the “Shared Facility”), then the PCO may elect, at its option, to explore options with the RoL to utilise the Shared Facility for the final disposal of spent nuclear fuel and other high level waste originating from the Visaginas New Nuclear Power Plant. If the PCO and RoL agree, acting reasonably, to use the Shared Facility for the final disposal of spent nuclear fuel and other high level waste originating from the Visaginas New Nuclear Power Plant, then RoL and the PCO shall share the costs associated with the development and use of that Shared Facility on an equitable basis and shall have regard to any cost savings derived from the synergies between the final disposal of spent nuclear fuel and other high level waste originating from the Ignalina NPP and the Visaginas New Nuclear Power Plant. The PCO’s contribution with respect to such cost sharing as described in this paragraph 15 shall be pro rata to the quantity and nature of spent fuel and other high level waste to be deposited and storage space to be used in connection with the final disposal of spent nuclear fuel and other high level waste originating from the Visaginas New Nuclear Power Plant.

(16)     The PCO may at its option enter into a contract with the body appointed by the Lithuanian State to manage and/or dispose the waste and/or construct appropriate facilities for the purpose of waste management and disposal on its own.

(17)     The waste management and/or disposal fees of the body appointed by the Lithuanian State to manage and/or dispose radioactive waste originating from the NNPP (the Radioactive Waste Manager) shall be cost based reflecting research and development, design, construction, operational, closure and surveillance costs of the management and/or disposal facility. Cost will be defined in the respective contract with the body appointed by the Lithuanian State to exclude profits (but to include indirect costs and overheads to the extent attributable to the relevant action) and shall not provide for any double recovery in respect of the use of generic and/or previously-developed research and development or design costs.

(18)     The final estimate for decommissioning and final waste disposal of the NNPP shall be prepared by the PCO in accordance with the Decommissioning and Waste Management Arrangements 12 months prior to the end of estimated operating life of the NNPP (being 60 years unless extended) at the latest and shall be submitted to the Supervising Authority for review. The PCO shall, by no later than the last day of the operating life of the NNPP, be obliged to make a sufficient contribution to ensure that the Fund meets the final estimate in full discounted on a basis to be agreed taking into account the planned scheduling of the decommissioning works and the fund growth expected over the period of the decommissioning.

(19)     The PCO shall be entitled in its absolute discretion, within one month after the estimate of the final costs of decommissioning has been produced in accordance with paragraph 18, to elect whether to perform (or procure the performance by third party contractor(s)) or not to perform the works in connection with the decommissioning of the NNPP.

(20)     If the PCO elects to perform, or procure the performance, of the works in connection with the decommissioning and waste management and disposal of the NNPP the PCO shall be entitled to have access to all amounts standing to the credit of the Fund subject to prudent verification by Supervising Authority of the use of the Fund strictly for its intended purpose, but shall bear the risk of any funding shortfall provided that any overfunding shall be returned to the PCO.

(21)     If the PCO does not make an election within the time required by paragraph 19, above, it shall be deemed to have elected not to perform the works connected with the decommissioning of the NNPP.

(22)     If, in accordance with this Schedule 6, the PCO elects, or is deemed to have elected, not to perform the works connected with the decommissioning and waste management and disposal of the NNPP, RoL shall be solely responsible for implementing the Decommissioning and Waste Management Arrangements until all decommissioning works have been completed and paragraph 32 of this Schedule 6 shall apply to the costs of decommissioning (and, subject to the compliance of the PCO with paragraph 18, the PCO shall have no liability howsoever arising in respect of the costs of the decommissioning of the NNPP or waste management arrangements).

Supervising Authority

(23)     The Supervising Authority shall be an independent body established by RoL and shall have the roles and responsibilities as described in Commission Requirements. When exercising the powers and carrying out the tasks and duties the Supervising Authority shall not seek or take instructions from the Government, its institutions or other body. The Government, its institutions and other bodies shall undertake to respect this principle and not to seek to influence the Supervising Authority in the performance of the tasks of the Supervising Authority and to provide sufficient funding for the Supervising Authority to carry out its role.

(24)     The Supervising Authority shall be responsible for:

• review the scope of Decommissioning and Waste Management Arrangements, any cost estimates and projections contained therein;

• review the adequacy of the fixed processes and timescales for determination of adjustments to decommissioning and waste management arrangements, cost estimates and correction of underfunding or overfunding (if necessary); and

• other functions as set out in the Commission Requirements.

The Fund

(25)     A Fund shall be maintained and operated by the Board of the Fund and funded by the PCO in accordance with this Schedule 6. It will be independent of the RoL, the PCO, its Shareholders and the Custodian Bank referred to in paragraph 26 below and insolvency remote from the PCO, its Shareholders, the RoL and the Custodian Bank.

(26)     The Fund shall be held as a segregated account at an international commercial bank (Custodian Bank). The PCO is eligible to propose candidacies of the Custodian Bank for the approval by the Board of the Fund.

(27)     The Fund shall monitor compliance with the Decommissioning and Waste Management Arrangements and the funds for the future decommissioning of the NNPP and invest them in accordance with the investment strategy proposed by the PCO and approved by the Board of the Fund.

(28)     Funding for the costs of waste management and disposal as established pursuant to the Decommissioning and Waste Management Arrangements shall be contributed by the PCO on the earlier of (a) the date that nuclear fuel is loaded into the NNPP or (b) otherwise as radioactive waste is generated. The PCO shall be obliged to make sufficient contribution to cover the estimated cost discounted on a basis to be agreed taking into account the planned scheduling of the waste management and disposal activities and the fund growth expected over the period of the waste management and disposal activities.

(29)     The PCO shall be obliged to make an annual contribution to the Fund in respect of decommissioning to cover the annual proportion of the total outstanding discounted decommissioning costs estimated by the PCO under the Decommissioning and Waste Management Arrangements prepared in accordance with this Schedule 6 and discounted on a basis to be agreed taking into account the planned scheduling of the decommissioning works and the fund growth expected over the period of the decommissioning. The PCO is liable to make contributions into the Fund until the Fund meets the final estimate.

(30)     From first criticality, in order to meet the obligations to make contributions to the Fund on a discounted basis during operations and to meet the obligations to fund to the final cost estimate, the PCO shall ensure that appropriate arrangements are in place so that the PCO can meet its obligations in relation to the funding of decommissioning and waste management and disposal costs. From first criticality there shall also be a requirement for the PCO to provide sufficient funding (pursuant to paragraph 7) to put the plant into safe store in case of early shut down on the basis set out in this paragraph 30, and the funding of waste costs for first fuel load on the basis set out in paragraph 28. The amounts for safe store shall be calculated by the PCO and shall cover the costs of the shutdown of the nuclear reactor, removal of the nuclear fuel from the nuclear reactor and placing it into a spent nuclear fuel pools, storage of radioactive waste, including spent nuclear fuel, until the sufficient amount of the resources for full decommissioning shall be accumulated. Funding for the undiscounted safe store costs shall be made in cash contribution on an overnight cost basis.

(31)     In the event of early shutdown of the plant the final estimate of decommissioning and waste management cost in money values of the day shall be prepared by the PCO within 1 year after early shutdown. This final estimate of cost shall be subject to the review of the Supervising Authority in accordance with its role as set out in the Commission Requirements. Any increased costs of early decommissioning and any other shortfalls in the fund as of the date of the early shutdown, discounted on a basis to be agreed taking into account the planned scheduling of the decommissioning and waste management and disposal activities and the fund growth expected over the period of the decommissioning and waste management and disposal activities, must be funded by the PCO unless the early shutdown was politically procured by the Lithuanian State against the will of the PCO.

(32)     Decommissioning costs shall be funded from amounts standing to the credit of the Fund and, except where paragraph 20 of this Schedule 6 applies, the RoL shall bear the sole responsibility, without recourse to the PCO or any other person, for any decommissioning costs which are in excess of the amounts standing to the credit of the Fund provided that any overfunding shall be returned to the RoL.

Management of Fund

(33)     The Fund shall have a Board of the Fund (Board) the members of which shall be nominated by the RoL. The RoL shall not have a right to reject candidate proposed for nomination by the PCO. The Chairman of the Board shall be nominated by the Lithuanian Government. The members of the Board shall be adequately qualified and free from any conflicts of interest.

(34)     The Board shall deal with funds standing to the credit of the Fund in accordance with arrangements set out in this Schedule 6 and the Decommissioning and Waste Management Arrangements and shall otherwise act transparently, independently and fairly and in the best interests of the Fund.

(35)     The Board shall commission and publish to the RoL, the PCO and each Shareholder of the PCO an annual report in accordance with international accounting standards which shall include a balance sheet of the Fund and description on the annual returns of the Fund holdings.

(36)     The Board shall include representatives from Lithuanian Ministry of Energy, Lithuanian Nuclear Regulatory Institution, Lithuanian Financial Regulatory Institution and the PCO. RoL shall have a voting majority in the Board.

(37)     The Fund shall have an auditor, the candidacy of which shall be proposed by the PCO (being an internationally recognised accountancy firm).

(38)     The costs of discharging the Fund's administrative/management duties and functions shall, subject to an efficiency and performance protection for the PCO, be met from the assets of the Fund.

(39)     In order to avoid conflicting use of financial recourses of the Fund, to reach the highest level of the Fund independence from the RoL, the PCO, its Shareholders and the Custodian Bank referred to in paragraph 26 above and to minimise correlation between the Fund performance and the financial status of the RoL, the PCO, its Shareholders and the Custodian Bank referred to in paragraph 26 above, the investments in related parties (mother and/or other group companies) shall not be allowed. This rule shall apply to all classes of securities including direct lending, acquisitions of bonds or stocks and other financial instruments.

(40)     The Fund assets shall be invested in the credible financial assets and the investment strategy shall be conservative to ensure prudent risk exposure and diversification of investment.

Dispute Resolution

(41)     The final determination in respect of appeals against decisions of the Supervising Authority and/or the Board shall be made where possible by an arbitral tribunal to be agreed or otherwise, as required under Lithuanian law.

(42)     All references to waste management and disposal relate to activities and costs relating to waste management and disposal which are not part of operational waste management.

SCHEDULE 7

LIV IP

No.

Object

Date

Agreement

Parties

1.

Description of Physical Protection Requirements and Feasibility, Phase 1 Report No (9.17-3)-P17-4/G_2009-176. (LT, EN)

30 January 2009

Agreement on Order of Author’s Work No S_113-2009-3 dated 15 January 2009

VAE Vaidas Brasiūnas (Service Provider)

2.

Description of Physical Protection Requirements and Feasibility, Phase 2 Report No G_2009-224 (5.2) (LT, EN)

24 March 2009

3.

Description of Physical Protection Requirements and Feasibility, Phase 3 Report No G_2009-317 (LT, EN)

19 April 2009

4.

Possible Means of Equipment of Physical Protection System for Visaginas Power Plant No (9.17.2)-P17-12 (LT)

13 July 2009

5.

Environmental Impact Assessment Report New Nuclear Power Plant in Lithuania (LT, EN, RU)

27 March 2009

Agreement No 87-08 dated 4 February 2008

AB “Lietuvos energija” Consortium of Poyry Energy Oy and Lietuvos energetikos institutas (Lithuanian Energy Institute) (Service Provider)

6.

Agreement on Transfer of Consultancy Services Agreement No 951-08 dated 19 November 2008

VAE AB “Lietuvos energija” Poyry Energy Oy and Lietuvos energetikos institutas (Lithuanian Energy Institute) (Service Provider)

7.

Pro-Forma Business Model and Financing Plan (Project White Knight) (EN)

October 2009

Agreement on Provision of Services No S_113-2009-33 dated 19 June 2009

VAE N M Rothschild & Sons Limited (Service Provider) However, the Project White Knight: Baltic Power Market Report has been prepared by NERA Economic Consulting and the Project White Knight Technical Analysis Report – by FICHTNER

8.

Project White Knight: Baltic Power Market Report (EN)

21 August 2009

9.

Project White Knight Technical Analysis Report No 6757P02/FICHT-5172339-v3 (EN)

July 2009

10.

Project of “New Nuclear Power Plant Oversized and Super Heavy Load Transportation Route Research” Feasibility Study No 01-02-625

2009

Agreement on Provision of Services No S_113-2009-11 dated 24 March 2009

VAE UAB “Hidroprojektas” (Service Provider)

11.

Selection of Design Solutions of Visaginas Nuclear Power Plant Oversized, Super Heavy and Other Load Transportation Route and their Economic Evaluation: Researches of Lithuanian Road Transport Network, Part 1, No MIS-2010-24-PP-B (LT)

2010

Agreement on Provision of Services No MIS-2010-24 dated 1 April 2010

VAE VĮ Transporto ir kelių tyrimo institutas (Service Provider) UAB “Kelprojektas” (Service Provider)

12.

Selection of Design Solutions of Visaginas Nuclear Power Plant Oversized, Super Heavy and Other Load Transportation Route and their Economic Evaluation: Researches of Lithuanian Road Transport Network, Part 2, No MIS-2011-29-PP-T (LT)

2011

Agreement on Provision of Services No MIS-2011-29 dated 23 May 2011

VAE (VĮ Transporto ir kelių tyrimo institutas (Service Provider)

13.

Special Communication Plan No 10076 (LT)

10 October 2011

Agreement on Preparation of the Special Communication Plan and Provision of Services Related to it No MIS-2010-47-1 dated 30 August 2010

VAE UAB “Sweco Lietuva” (Service Provider)

14.

Safety Audit of Solutions of Special Plan Related to the Roads of State Importance (LT)

November 2010

Agreement on Provision of Audit Services No MIS-2010-48 dated 2 September 2010

VAE UAB “Strateginio transportavimo sprendimai” (Service Provider)

15.

Selection of Design Solutions of Visaginas Nuclear Power Plant Oversized, Super Heavy and Other Load Transportation Route and their Economic Evaluation: Researches of Inland Water Transport Network in Lithuania (LT)

2011

Agreement on Provision of Services No MIS-2011-05 dated 8 February 2011

VAE UAB “Vilniaus hidroprojektas” (Service Provider)

16.

Renewal and Supplement of Assessment of Potential New Nuclear Power Plant Construction Sites in Respect of External Events No S/17-1219.10.12-G4-V:01 (LT)

20 December 2010

Agreement on Provision of Services No MIS-2010-58 dated 15 October 2010

VAE Lietuvos energetikos institutas (Service Provider)

17.

Investigation of Deep Geological Setting of Potential Construction Sites of Visaginas NPP by Using 2D/3D Seismic Survey (EN)

15 November 2010

Agreement on Provision of Services No 8-50/MIS-2010-31 dated 1 June 2010

VAE Ministry of Energy of the Republic of Lithuania AB Lietuvos elektrinė Lietuvos ir Danijos UAB “Minijos nafta” (Service Provider)

18.

Constructional Remains and Subsurface Geologic Setting Survey of Potential Visaginas NPP Sites Using Electrical Tomography Method (LT, EN)

2009

Service Agreement No. S_113-2009-17 dated 17 April 2009. The agreement was terminated by the agreement of the parties dated 12 June 2009.

VAE UAB “Geobaltic” (Service Provider)

19.

Geotechnical, Geological and Seismological (GG&S) Data Inventory for the Visaginas Sites (EN)

2012

Service Agreement No. MIS-2009-1 dated 31 July 2009

VAE UAB “Eldra” (Service Provider)

20.

Report on Investigations of Contamination with Radionuclides of Potential Plots for a New Nuclear Power Plant (LT, EN)

23 June 2009

Service Agreement No. S_113-2009-13/2009/PES-64 dated 3 April 2009

VAE Radiacinės saugos centras (Service Provider)

21.

Preliminary Ecogeological Survey of Construction Site of New Visaginas NPP (I Var) in Drūkšiniai vil. Visaginas TN No 2031-2009 (LT, EN)

2009

Service Agreement No. S_113-2009-18 dated 28 April 2009

VAE UAB “Geotestus” (Service Provider)

22.

Preparation of Connection of New Nuclear Power Plant to the Transmission Network Infrastructure. Stages for Connection of New Nuclear Power Plant to the Transmission Network (Design Proposals) No 729 – PP – T1 (LT)

2009

Service Agreement No. S_113/17-70-2009-29 dated 19 May 2009

VAE UAB “Energetikos pajėgos” (Service Provider)

23.

Fuel Strategy Report (EN)

August 2009

Agreement No. S_116-2009-15 dated 8 April 2009

VAE TVO Nuclear Services Oy (Service Provider)

24.

Proposal for Radioactive Waste Management Strategy (EN)

September 2009

25.

Feasibility and Capabilities of the Regional Supply Chain to Support the Visaginas NPP Construction Project (EN)

16 August 2010

Service Agreement No MIS-2010-21 dated 29 March 2010

VAE UAB “Deloitte Lietuva” (Service Provider)

26.

Design Proposals for Removal of Construction Waste from the Construction Site of Visaginas NPP No 7964 (LT, EN)

2010

Service Agreement No 038-09/MIS-2009-16 dated 8 October 2009

VAE AB “Pramprojektas” (Service Provider)

27.

Evaluation of Geological and Seismological Conditions at Potential VAE Sites Using Seismic Exploration Data (Volume 1, Volume 2)

June 2009

Service Agreement No S_113-2009-14 dated 10 April 2009

VAE AB “Geonafta” (Service Provider)

28.

Investigations of Engineering Geological and Geotechnical Conditions of the Potential Construction Sites of Visaginas NPP (Verification Stage and Confirmation Stage)

September 2010

Service Agreement No MIS-2010-1 dated 12 January 2010

VAE UAB “Geotestus” (Service Provider)

29.

Feasibility Study of Use of the Near-Surface Repositories of Short-Lived Radioactive Waste of Very Low, Low and Intermediate Activity (Intended for Radioactive Waste from the Ignalina Nuclear Power Plant) for the Disposal of Radioactive Waste from the Visaginas Nuclear Power Plant (LT, EN)

18 September 2009

N/A

Developed by VAE

30.

Visaginas Nuclear Power Plant Site Evaluation Report (EN)

2 December 2011

N/A

Developed by VAE

31.

Taking Over of the INPP Industrial Area Existing Infrastructure Project P022 (Project First Stage Report) (EN)

2009

N/A

Developed by VAE

32.

Determining Possibilities to Connect to the Engineering Networks No P023-4 (LT)

7 August 2009

N/A

Developed by VAE

33.

Pre-Design Solutions on Supply of Electricity Power to VAE Construction Sites No P037 (LT)

2011

N/A

Developed by VAE

34.

Legal and Regulatory Environment for the New Nuclear Power Plant in Lithuania No (9.13.3)-P13-8 (LT)

10 April 2009

N/A

Developed by VAE

35.

The Lithuanian New Nuclear Power Plant Build Programme (Lithuanian Human Resources Capability and Ability to Participate in the NPP Project) (EN)

2009

N/A

Developed by VAE

SCHEDULE 8

FUNDAMENTAL CHANGE

1.

Pre-FID Fundamental Changes

Subject to Paragraph 2, the following are "Pre-FID Fundamental Changes" and each a "Pre-FID Fundamental Change":

2.5       Changes to laws implemented for the Project

Repeal of or material amendments to the following laws which have come into force and effect within the Republic of Lithuania:

2.5.1      the Law on Assuming the Essential Property Obligations of the Republic of Lithuania in the Visaginas Nuclear Power Plant Project; and

2.5.2      the Law on the Nuclear Power Plant,

provided that the net effect of the repeal and/or material amendments (when taken into account with any other applicable Laws and/or circumstances, including any amendments to and/or repeal or enactment of any other applicable Laws), excluding the effect of any increase in costs which is not a Significant Increase in Costs, has or will have a very serious adverse effect on the implementation of the Project, or on the operation of the NNPP, or rights of the NNPP to sell electricity generated by the NNPP, or the Shareholders to offtake and/or export electricity generated by the NNPP, when compared to the circumstances in effect as at the Concession Date and the RoL has not remedied such repeal or material amendment or the net fundamental adverse effect of such repeal or material amendment by the earlier of (i) 3 Months following service of a notice on the RoL by the PCO that the Shareholders are prepared to take FID and (ii) 30 June 2015.

For the purposes of this paragraph 1.1, a "Significant Increase in Costs" shall mean an increase in the costs of the Project which is, in and of itself (and not only in the context of any incremental change in the costs of the Project), a very significant increase.

2.6       Withdrawal or denouncement from specified nuclear treaties

Withdrawal by the RoL from, denouncement by the RoL of, or the material amendment (adversely affecting the implementation), repeal or invalidity of any Law in the Republic of Lithuania implementing or giving effect to, any of the following instruments:

2.6.1      the Non Proliferation Treaty;

2.6.2      the Vienna Convention 1963;

2.6.3      the Vienna Protocol (only from such date as the Vienna Protocol is in force and applicable in, or in respect of, the Republic of Lithuania);

2.6.4      the Convention on Supplementary Compensation (only from such date as the Convention on Supplementary Compensation is in force and applicable in, or in respect of, the Republic of Lithuania);

2.6.5      the Joint Protocol;

2.6.6      the IAEA Statute;

2.6.7      the IAEA Agreement; and/or

2.6.8      any Nuclear Safety Treaty,

where, subject to the provisions below, such withdrawal, denouncement, repeal, material amendment or invalidity shall be a Pre-FID Fundamental Change from the earlier of the date on which the relevant international instrument ceases to be binding and enforceable in the Republic of Lithuania or the date on which the repeal, material amendment or invalidity occurred:

(A)      provided that such withdrawal, denouncement, repeal, material amendment or invalidity by the RoL is of its own accord and not:

(1)       as a result of the termination or lapse of or amendment to the relevant international instrument listed; or

(2)       as a result of a decision or communication of the European Commission or a ruling by the Court of Justice of the European Union requiring or recommending that the RoL (specifically) or (more generally) the European Union Member States withdraw from the relevant international instrument or otherwise ruling that its existence is not in accordance with European Union principles;

(B)       and except where another international instrument or applicable Law applies or is brought into effect in the Republic of Lithuania (prior to, at the same time as, or not later than a reasonable period following, such withdrawal or denouncement and in any event not later than the earlier of (i) three (3) Months following service of a notice on the RoL by the PCO that the Shareholders are prepared to take FID and (ii) 30 June 2015) and:

(1)       where such international instrument or applicable Law can reasonably be considered to fulfil a substantially similar purpose as the relevant international instrument which the RoL has denounced or from which it has withdrawn or which otherwise is considered by the parties to the replacement international instrument to replace or supersede the replaced international instrument; or

(2)       if such international instrument or applicable Law fulfils more than one purpose, contains provisions which can reasonably be considered together to fulfil a substantially similar purpose as the relevant international instrument which the RoL has denounced or from which it has withdrawn,

(and such replacing international instrument or applicable Law, in the case of both 1.2.8(B)(1) and 1.2.8(B)(2), shall be a "Specified Nuclear Treaty Replacement" and "Specified Nuclear Treaty Replacements" shall be construed accordingly).

2.7       Withdrawal from or denouncement of the Energy Charter Treaty

Withdrawal by the RoL from or denouncement by the RoL of the Energy Charter Treaty:

2.7.1      provided that such withdrawal or denouncement by the RoL is of its own accord and not:

(A)      as a result of the termination or lapse of the Energy Charter Treaty; or

(B)       as a result of a decision or communication of the European Commission or a ruling by the Court of Justice of the European Union requiring or recommending that the RoL (specifically) or (more generally) the European Union Member States withdraw from the Energy Charter Treaty or otherwise ruling that its existence is not in accordance with European Union principles;

2.7.2      and except where another international instrument or applicable Law applies or is brought into effect in the Republic of Lithuania (before, at the same time as, or not later than a reasonable period following withdrawal from or denouncement of the Energy Charter Treaty and in any event not later than the earlier of (i) three (3) Months following service of a notice on the RoL by the PCO that the Shareholders are prepared to take FID and (ii) 30 June 2015) and:

(A)      where such international instrument or applicable Law can reasonably be considered to fulfil a similar purpose as the Energy Charter Treaty; or

(B)       if such international instrument or applicable Law fulfils more than one purpose, where it contains provisions which can reasonably be considered together to fulfil a similar purpose as the Energy Charter Treaty or which otherwise is considered by the parties to the replacement international instrument to replace or supersede the Energy Charter Treaty,

(and such international instrument or applicable Law, in the case of either (i) or (ii), shall be a "Energy Charter Treaty Replacement").

2.8       Withdrawal or denouncement from the New York Convention

Withdrawal by the RoL from, denouncement by the RoL of, or the material amendment (adversely affecting the implementation) of, repeal or invalidity of, any Law in the Republic of Lithuania implementing or giving effect to, the New York Convention:

2.8.1      provided that such withdrawal, denouncement, repeal, material amendment and/or invalidity by the RoL is of its own accord and not:

(A)      as a result of the termination or lapse of the New York Convention; or

(B)       as a result of a decision of the European Commission or a ruling by the Court of Justice of the European Union requiring that the RoL (specifically) or (more generally) the European Union Member States withdraw from the New York Convention or otherwise ruling that its existence is not in accordance with European Union principles;

2.8.2      and except where another international instrument or applicable Law applies or is brought into effect in the Republic of Lithuania (before, at the same time as or not later than a reasonable period following, withdrawal from or denouncement of the New York Convention and in any event not later than the earlier of (i) three (3) Months following service of a notice on the RoL by the PCO that the Shareholders are prepared to take FID and (ii) 30 June 2015) and:

(A)      where such international instrument or applicable Law can reasonably be considered to fulfil a substantially similar purpose as the New York Convention; or

(B)       if such treaty, protocol, agreement, convention or applicable Law fulfils more than one purpose, it contains provisions which can reasonably be considered together to fulfil a substantially similar purpose as the New York Convention or which otherwise is considered by the parties to the replacement international instrument to replace or supersede the New York Convention,

(and such international instrument or applicable Law, in the case of either 1.4.2(A) or 1.4.2(B), shall be a "New York Convention Replacement"),

and where such withdrawal, denouncement, material amendment, repeal or invalidity shall be a Pre-FID Fundamental Change from the earlier of the date on which the New York Convention ceases to be applicable in, or in respect of, the Republic of Lithuania or the date on which the repeal, material amendment or invalidity occurred.

2.9       Negative Decision on Nuclear Power

A negative decision on nuclear power, being:

2.9.1      a declaration by the RoL of a moratorium on nuclear power, where "moratorium on nuclear power" means where the RoL declares a moratorium on the generation of nuclear power which relates to the Visaginas NNPP and which is directly and primarily as a result of a decision of the Parliament of the Republic of Lithuania and provided that:

(A)      such moratorium did not relate, to nor was as a result of:

(1)       any negligent act or omission, default or breach of the PCO of any of its obligations under this Concession Agreement and/or any applicable Law (as applicable); or

(2)       a European or international decision to close nuclear power stations of the advanced boiling water reactor type; and/or

(B)       no Regulator has rejected the PCO's nuclear safety case prior to the relevant decision being taken.

2.9.2      the result of any referendum held in the Republic of Lithuania that:

(A)      is to any extent in relation to civilian nuclear power;

(B)       is to any extent in relation to the storage and disposal of nuclear waste (including spent nuclear fuel);

(C)       refers to or affects the Visaginas Nuclear Power Plant, the Project or the Concession;

(D)      refers to Hitachi, Ltd. or any of its Associated Companies, any Shareholder, VATESI or the ABWR; or

(E)       refers to or affects any of the laws or treaties referred to in Paragraph 1.1. or 1.2 of this Schedule 8,

and would or could reasonably be expected to have (if the President or Parliament were to act or not act in accordance with the outcome of the referendum) a material and adverse effect on the Project, the timely performance of the Concession, and/or the likelihood of a positive FID occurring.

3.

Exclusions from Pre-FID FUndamental Changes

3.1       Notwithstanding Paragraph 1 of this Schedule 8 (Fundamental Change), any of the changes in circumstance referred to in Paragraph 1 above (other than Paragraph 1.5) shall not be a Pre-FID Fundamental Change:

3.1.1      if the change requires the same or equivalent action as a change in applicable Law or technical, security or safety requirements in another nuclear installation state that affects the generic reactor design to be used in the Project, taking into account the siting of the Project;

3.1.2      where any such change transposes or implements into Law in the Republic of Lithuania or otherwise brings or is a consequence of bringing into force and effect (i) the agreed principles in relation to waste and decommissioning in Schedule 6 (Decommissioning and Waste Funding Principles); (ii) the Vienna Protocol; (iii) the Convention on Supplementary Compensation; and/or (iv) any change associated with the design, construction or maintenance of the Access Road and/or with national sources of project financing;

3.1.3      where any such change, the draft of which, seven (7) Calendar Days or more prior to the Concession Date, is published on the website of any of the Parliament of the Republic of Lithuania, the Government of the Republic of Lithuania, any Ministry, or any Regulator and such change is transposed or implemented into Law in substantially the same way as published;

3.1.4      any change which transposes or implements into national law, or otherwise gives effect to:

(A)      any laws, directives, regulations, decisions, standards or requirements which are required under relevant European Union law or required or recommended under international law ("Transnational Laws"); or

(B)       any requirements, principles, standards or guidelines produced and/or published by the IAEA, WENRA, ENSREG or EURATOM or any other institution which can reasonably be considered to have replaced the IAEA, WENRA, ENSREG or EURATOM ("Principles, Standards or Guidelines"),

where such change, together with any other applicable Law, can reasonably be regarded as reflecting all or part of the purpose of the relevant Transnational Laws and/or Principles, Standards or Guidelines;

3.1.5      any change which transposes or implements into national law, or otherwise gives effect to any laws, directives, regulations, decisions, standards or requirements which are recommended by any European Union institution ("Recommended Measure(s)"):

(A)      where such change can reasonably be considered to reflect all, or part of, the purpose of the Recommended Measure(s) and is reasonably proportionate to, or not substantially more onerous than, the Recommended Measure(s) having regard to:

(1)       the Project, including the status, technology and siting of the Project; and

(2)       generally applicable standards in the European Union; and/or

(B)       where such change can reasonably be considered to reflect all, or part of, the purpose of the Recommended Measure(s) and the manner in which any such Recommended Measure has been implemented in respect of any other European Union nuclear installation and/or implemented or transposed into, or otherwise brought into effect under, the law of any other Member State; or

3.1.6      if and to the extent that the change arises out of a breach by the PCO of any of its obligations under this Concession Agreement, applicable Law or a breach by the PCO or the EPC Contractor of any of their obligations under any relevant Ancillary Contract or applicable Law or any other act or omission of the PCO or the EPC Contractor.

3.2       Notwithstanding Paragraph 1.1 of this Schedule 8 (Fundamental Change), Paragraph 1.1 shall not apply to any articles of the Laws referred to at Paragraphs 1.1.1 or 1.1.2 that have not come into force and effect within the Republic of Lithuania unless and until any such article has come into force and effect within the Republic of Lithuania.

4.

Effect of Replacement Specified Nuclear Treaty, Replacement Energy Charter Treaty or REplacement New York Convention

If a Specified Nuclear Treaty Replacement, Energy Charter Treaty Replacement and/or New York Convention Replacement is in force in or with respect to the RoL (each a "Replacement Measure"), Paragraphs 1.2 (Withdrawal or denouncement from specified nuclear treaties), 1.3 (Withdrawal or denouncement from the Energy Charter Treaty) or 1.4 (Withdrawal or denouncement from the New York Convention) of this Schedule 8 (Fundamental Change), as applicable, shall be deemed to refer, mutatis mutandis, to the relevant Replacement Measure to the extent that such Replacement Measure, or any provisions together therein, can reasonably be considered to fulfil a substantially similar purpose to the international instrument replaced and the relevant Paragraph shall be deemed no longer to refer to the international instrument replaced by the Replacement Measure.

SCHEDULE 9

INVESTED CAPITAL STATEMENT

To be completed by the PCO in respect of each Exiting Shareholder under Clause 26 and delivered to the RoL. The boxes in Sections 1-3 below are to be expanded as necessary to account for every Tranche of Invested Capital.

As at


(Calculation Date)

Invested Capital (x) of


= €EURAI __

Name of Exiting Shareholder

SECTION 1 – SUBSCRIPTION PAYMENTS

Complete a line entry for each Tranche of Subscription Payment made by the Exiting Shareholder

Date of Subscription Payment

Number of Calendar Days between Subscription Payment and the Calculation Date (c)

Amount of Subscription Payment (€EURAI) (a)

TOTAL

SECTION 2 – PRINCIPAL AMOUNTS

Complete a line entry for each Tranche of Principal Amount drawn down from the Exiting Shareholder

Date of draw down of Principal Amount

Number of Calendar Days between draw down of Principal Amount and the Calculation Date (c)

Amount of Principal Amount (€EURAI) (a)

TOTAL

SECTION 3 – CREDIT PAYMENTS

Complete a line entry for each Tranche of payment made under Exiting Shareholder credit support for PCO obligations

Date of Credit Payment

Number of Calendar Days between Credit Payment and the Calculation Date (c)

Amount of Credit Payment (€EURAI) (a)

TOTAL

SECTION 4 – INTEREST PAID

State the total amount of interest paid to the Exiting Shareholder under Shareholder Loans

Aggregate amount of interest paid (€EURAI) (d)

____                                                       ________

signed for and on behalf of                                                                                                 (Date)

the PCO


DATA [•]

LIETUVOS RESPUBLIKA

ir

[„HITACHI, LTD.“ SPĮ]

ir

[PB]

KONCESIJOS SUTARTIS SU STRATEGINIU INVESTUOTOJU IR PROJEKTO BENDROVE DĖL VISAGINO NAUJOS ATOMINĖS ELEKTRINĖS PROJEKTO

TURINYS

1 DALIS: ĮŽANGINĖS NUOSTATOS IR TERMINAS..................................................... 117

1......... SĄVOKOS IR JŲ AIŠKINIMAS............................................................................. 117

2......... KONCESIJOS SUTEIKIMAS IR TERMINAS....................................................... 118

3......... KONCESIJOS APIMTIS.......................................................................................... 119

4......... SANTYKIAI: Bendradarbiavimo PRINCIPAI.......................................... 120

5......... STRATEGINIO INVESTUOTOJO ĮSIPAREIGOJIMAI....................................... 122

6......... PB ĮSIPAREIGOJIMAI............................................................................................ 122

7......... LR ĮSIPAREIGOJIMAI............................................................................................ 124

8......... AKCININKŲ SUTARTIES PAKEITIMAI............................................................. 125

2 DALIS: PB AKCIJŲ DALYS............................................................................................ 126

9......... PB AKCIJŲ DALYS................................................................................................. 126

3 DALIS: BENDRIEJI ĮSIPAREIGOJIMAI....................................................................... 127

10....... UŽSAKOMIEJI DARBAI IR SUBRANGA........................................................... 127

4 DALIS: PROJEKTO VALDYMAS................................................................................... 128

11....... ATASKAITOS IR STEBĖSENA.............................................................................. 128

12....... REGULIAVIMO SISTEMA..................................................................................... 130

5 DALIS: KONFIDENCIALUMAS IR VIEŠUMAS......................................................... 131

13....... KONFIDENCIALUMAS.......................................................................................... 131

14....... VIEŠUMAS............................................................................................................... 136

6 DALIS: BRANDUOLINĖ ATSAKOMYBĖ IR DRAUDIMAS..................................... 137

15....... BRANDUOLINĖS ŽALOS ATLYGINIMAS........................................................ 137

16....... ATSAKOMYBĖ........................................................................................................ 137

17....... NUOSTOLIŲ ATLYGINIMAS YRA NEPAKANKAMA KOMPENSACIJA IR TURI BŪTI TAIKOMOS TEISIŲ GYNIMO PRIEMONĖS PAGAL teisingumą............. 143

18....... DRAUDIMAS........................................................................................................... 143

7 DALIS: NUTRAUKIMAS................................................................................................. 144

19....... 19–26 PUNKTŲ TAIKYMAS: NUTRAUKIMAS.................................................. 144

20....... LR ĮVYKIS................................................................................................................ 146

21....... PB ĮSIPAREIGOJIMŲ NEVYKDYMAS............................................................... 148

22....... STRATEGINIO INVESTUOTOJO ĮSIPAREIGOJIMŲ NEVYKDYMAS.......... 149

23....... SUTARTIES NUTRAUKIMAS NE DĖL ĮSIPAREIGOJIMŲ NEVYKDYMO.. 151

24....... SU SUTARTIES NUTRAUKIMU SUSIJUSIŲ NUOSTOLIŲ ATLYGINIMAS 152

25....... AKCININKŲ SUTARTYJE NUMATOMOS LR TREČIOJO ASMENS TEISĖS 153

26....... LR ĮVYKIS. PRIVALOMASIS AKCIJŲ PERLEIDIMAS................................... 154

8 DALIS: BENDROSIOS NUOSTATOS............................................................................ 158

27....... TOLESNIS GALIOJIMAS, TEISĖS IR ĮSIPAREIGOJIMAI................................ 158

28....... garantijos........................................................................................................... 159

29....... NENUGALIMA JĖGA............................................................................................. 161

30....... TEISIŲ PERLEIDIMAS........................................................................................... 162

31....... AKCIJŲ PERLEIDIMO IR KONTROLĖS PASIKEITIMO APRIBOJIMAI....... 163

32....... AKCININKŲ PASIRINKIMO PARDUOTI SANDORIS..................................... 165

33....... PRANEŠIMAI........................................................................................................... 166

34....... VISA APIMANTI SUTARTIS................................................................................. 168

35....... pakeitimai ir teisių atsisakymas........................................................... 168

36....... Egzempliorių skaičius.................................................................................. 169

37....... Atskiriamumas.................................................................................................. 169

38....... SĄNAUDOS IR IŠLAIDOS..................................................................................... 169

39....... ĮSIPAREIGOJIMŲ NEVYKDYMO ATVEJU MOKAMI DELSPINIGIAI........ 169

40....... sutarčių (trečiųjų šalių teisių) įstatymas...................................... 169

41....... partnerystės / tarpininkavimo nebuvimas..................................... 170

42....... bendradarbiavimas, susijęS su ENERGIJOS UŽ SAVIKAINĄ STRUKTŪRA           170

43....... KALBA...................................................................................................................... 170

44....... TAIKOMA TEISĖ..................................................................................................... 171

45....... GINČŲ SPRENDIMO TVARKA IR ARBITRAŽAS............................................ 171

46....... Teisių į IMUNITETą ATSISAKYMAS............................................................... 174

1 PRIEDĖLIS Sąvokos.......................................................................................................... 176

2 PRIEDĖLIS Privažiavimo kelio darbai............................................................................... 194

3 PRIEDĖLIS Informacija apie pradinius akcininkus ir akcijų dalys..................................... 207

4 PRIEDĖLIS Nacionalinio saugumo kriterijai...................................................................... 207

5 PRIEDĖLIS Statybvietė..................................................................................................... 207

6 PRIEDĖLIS Eksploatavimo nutraukimo ir atliekų tvarkymo finansavimo principai.......... 209

7 PRIEDĖLIS LIV intelektinė nuosavybė............................................................................. 215

8 PRIEDĖLIS Esminiai pakeitimai........................................................................................ 219

9 PRIEDĖLIS Investuotojo kapitalo ataskaita....................................................................... 225

ŠIĄ SUTARTĮ ........... m. ................... ............... d.

SUDARĖ

(1)       LIETUVOS RESPUBLIKA, atstovaujama Lietuvos Respublikos energetikos ministerijos (toliau – LR);

(1)       [„HITACHI, LTD.“ SPĮ], [•] įsteigta ir registruota bendrovė [[įmonės kodas], kurios adresas yra [•¶ (toliau – Strateginis investuotojas); ir

(2)       [PB], Lietuvos Respublikoje įsteigta ir registruota bendrovė [[įmonės kodas], kurios adresas yra [•¶ (toliau – PB),

toliau atskirai vadinamos „Šalimi“ arba kartu – „Šalimis“.

PREAMBULĖ

(A)      2007 m. sausio 18 d. Lietuvos nacionalinėje energetikos strategijoje LR dar kartą patvirtino ilgalaikį Lietuvos Respublikos įsipareigojimą plėtoti branduolinės energijos gamybą. Vienas iš strateginių Lietuvos Respublikos tikslų yra naujos atominės elektrinės statyba ir komercinės eksploatacijos pradžia.

(A)      Vadovaudamasi Lietuvos Respublikos koncesijų įstatymu, EM LR vardu surengė atvirą konkursą, siekdama atrinkti strateginį investuotoją į naujosios atominės elektrinės projektą įgyvendinančią bendrovę, kuri vystys, statys, eksploatuos naująją atominę elektrinę ir nutrauks jos eksploatavimą. 2009 m. gruodžio 10 d. ES Oficialiajame leidinyje buvo paskelbtas pranešimas apie konkursą (Nr. 2009/S 236-338047). Konkursas baigėsi 2011 m. sausio 3 d., kai ūkio subjektas, įvardytas kaip potencialus konkurso laimėtojas, pasitraukė iš konkurso, o daugiau tinkamų pasiūlymų pateikta nebuvo. EM, veikdama LR vardu (kaip Koncesiją suteikiančioji institucija) ir vadovaudamasi Koncesijų įstatymu, priėmė sprendimą (įsigaliojusį 2011 m. sausio 14 d.) pradėti tiesiogines derybas su potencialiais strateginiais investuotojais.

(B)       Vykdant tiesiogines derybas buvo surengta atvira konkurencinė procedūra taikant tuos pačius kvalifikacinius ir vertinimo reikalavimus kaip ir ankstesniame konkurse. Įvertinus pasiūlymus, pateiktus vykdant tiesiogines derybas, Strateginio investuotojo vardu „Hitachi, Ltd.“ pateiktas pasiūlymas buvo pripažintas ekonomiškai naudingiausiu, todėl „Hitachi, Ltd.“ ir Lietuvos Respublika, atstovaujama EM, sudarė išimtinį susitarimą, pagal kurį „Hitachi, Ltd.“ buvo suteikta išimtinė teisė derėtis dėl sąlygų, kuriomis Strateginis investuotojas dalyvautų ir investuotų į koncesininkę, kuri yra projektą įgyvendinanti bendrovė (PB). LR ir Strateginis investuotojas dėl šios Koncesijos sutarties derėjosi pagal minėto išimtinio susitarimo sąlygas. Buvo susitarta, kad, vadovaujantis šios Koncesijos sutarties sąlygomis, Strateginiam investuotojui arba vienai ar kelioms su juo Susijusioms bendrovėms, kurias paskirs Strateginis investuotojas, bus suteikta teisė: 1) su PB sudaryti EPC rangos sutartį dėl 1350 MW (bendrasis) klasės pažangiojo verdančio vandens reaktoriaus vystymo ir statybos laikantis ir nepažeidžiant EPC rangos sutarties sąlygų („Visagino nauja atominė elektrinė“ arba „NAE“); ir, 2) jeigu pagal šios Koncesijos sutarties sąlygas to paprašys PB (ir tai bus įmanoma pagal O&M pagalbinių paslaugų sąlygas), pagal O&M pagalbinių paslaugų sutartį teikti NAE eksploatacijos ir priežiūros paslaugas ir (arba), jeigu pagal šios Koncesijos sutarties sąlygas to paprašys PB (ir tai bus įmanoma pagal Branduolinio kurio tiekimo sąlygas), pagal Kuro tiekimo sutartį tiekti NAE branduolinį kurą ir teikti susijusias paslaugas.

(C)       LR, Strateginis investuotojas ir PB dėl šios Koncesijos sutarties susitarė vykdydamos tiesiogines derybas, o LR suteikia Koncesiją PB vadovaudamasi šios Koncesijos sutarties sąlygomis tikėdamasi, kad toks suteikimas padės Lietuvos Respublikai integruoti jos elektros energijos perdavimo sistemas į kontinentinės Europos perdavimo tinklą bei padidins Lietuvos Respublikos pagrindinių energijos išteklių įvairovę, pagerins Lietuvos Respublikos energijos tiekimo saugumą, prisidės ir didins pagrindinių energijos išteklių įvairovę visame Baltijos regione (kaip nurodoma bendrame Lietuvos, Latvijos, Estijos ir Lenkijos ministrų pranešime, pasirašytame 2010 m. gegužės 31 d., dalyvaujant Europos Komisijai).

(D)      Vadovaudamasi Koncesijų įstatymu ir šios Koncesijos sutarties sąlygomis, LR suteikia teisę PB, o PB įsipareigoja, kiekvienu atveju laikantis šioje Koncesijos sutartyje nustatytų sąlygų, projektuoti, finansuoti, vystyti, statyti, testuoti, pradėti eksploataciją, eksploatuoti, prižiūrėti Visagino naują atominę elektrinę ir nutraukti jos eksploataciją Statybvietėje (įskaitant darbus ir paslaugas pagal Papildomas sutartis ar kitas sutartis) („Koncesija“).

(E)       Pagal Koncesijų įstatymą PB visais atžvilgiais laikytina koncesininke.

Šis dokumentas nepakeičia oficialaus paskelbimo Teisės aktų registre. Neprisiimame atsakomybės už galimus netikslumus, atsiradusius perkeliant originalą į šį formatą.

Šis tekstas skelbiamas pagal paties šaltinio TAR pakartotinio naudojimo sąlygas, o ne pagal Legalize ar viešosios srities licenciją. TAR
Creative Commons Priskyrimas 4.0 tarptautinė (CC BY 4.0)
Duomenų šaltinis: Teisės aktų registras (TAR), Lietuvos atvirų duomenų portalas (data.gov.lt). Licencija: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/deed.lt). Duomenys gali būti pakeisti (konvertuoti į Markdown formatą).