Crossrail Act 2008

Type Public General Act
Publication 2008-07-22
Last updated 2024-10-30
State In force
Department Statute Law Database
articles Not indexed
Reform history JSON API
  • (1) Any specified work, and all protective works required by the Agency under paragraph 2, shall be constructed to the reasonable satisfaction of the Agency and the Agency shall be entitled by its officer at all reasonable times, on giving such notice as may be reasonable in the circumstances, to inspect the construction of such works.
  • (2) The nominated undertaker shall give to the Agency not less than 14 days' notice in writing of its intention to commence construction of any specified work and notice in writing of its completion not later than 7 days after the date on which it is brought into use.
  • (3) If any part of the works comprising a structure in, over or under a watercourse is constructed otherwise than in accordance with the requirements of this Part, the Agency may by notice in writing require the nominated undertaker at the nominated undertaker's own expense to comply with the requirements of this Part or (if the nominated undertaker so elects and the Agency in writing consents, such consent not to be unreasonably withheld) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent and within such limits as the Agency reasonably requires.
  • (4) Subject to sub-paragraph (5), if within a reasonable period, being not less than 28 days from the date when a notice under sub-paragraph (3) is served upon the nominated undertaker, it has failed to begin taking steps to comply with the requirements of the notice and thereafter to make reasonably expeditious progress towards their implementation, the Agency may execute the works specified in the notice and any expenditure reasonably incurred by it in so doing shall be recoverable from the nominated undertaker.
  • (5) In the event of any dispute as to whether sub-paragraph (3) is properly applicable to any work in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, the Agency shall not, except in an emergency, exercise the powers conferred by sub-paragraph (4) until the dispute has been finally determined.
5
  • (1) Any work constructed under this Act for the purpose of providing a flood defence shall be maintained to the reasonable satisfaction of the Agency by the person who has control of the work.
  • (2) If any such work is not maintained to the reasonable satisfaction of the Agency, the Agency may by notice in writing require that person to repair and restore the work, or any part of it, or (if the person having control of the work so elects and the Agency in writing consents, such consent not to be unreasonably withheld), to remove the work and restore the site (including any sea defences) to its former condition, to such extent and within such limits as the Agency reasonably requires.
  • (3) If, within a reasonable period being not less than 28 days beginning with the date on which a notice in respect of any work is served under sub-paragraph (2) on the person who has control of that work, that person has failed to begin taking steps to comply with the reasonable requirements of the notice and has not thereafter made reasonably expeditious progress towards their implementation, the Agency may do what is necessary for such compliance and may recover any expenditure reasonably incurred by it in so doing from that person.
  • (4) In the event of any dispute as to the reasonableness of any requirement of a notice served under sub-paragraph (2), the Agency shall not except in a case of immediate foreseeable need exercise the powers of sub-paragraph (3) until the dispute has been finally determined.
6
  • (1) If by reason of the construction of any specified work or of the failure of any such work the efficiency of any drainage work for flood defence purposes is impaired, or that work is otherwise damaged, so as to require remedial action, such impairment or damage shall be made good by the nominated undertaker to the reasonable satisfaction of the Agency.
  • (2) If such impaired or damaged drainage work for flood defence purposes is not made good to the reasonable satisfaction of the Agency, the Agency may by notice in writing require the nominated undertaker to restore it to its former standard of efficiency or where necessary to construct some other work in substitution for it.
  • (3) If, within a reasonable period being not less than 28 days beginning with the date on which a notice in respect of impaired or damaged drainage work for flood defence purposes is served under sub-paragraph (2) on the nominated undertaker, the nominated undertaker has failed to begin taking steps to comply with the requirements of the notice and has not thereafter made reasonably expeditious progress towards its implementation, the Agency may do what is necessary for such compliance and may recover any expenditure reasonably incurred by it in so doing from the nominated undertaker.
  • (4) In the event of any dispute as to the reasonableness of any requirement of a notice served under sub-paragraph (2), the Agency shall not except in a case of immediate foreseeable need exercise the powers conferred by sub-paragraph (3) until the dispute has been finally determined.
7
  • (1) The nominated undertaker shall take all such measures as may be reasonably practicable to prevent any interruption of the free passage of fish in any fishery during the construction of any specified work.
  • (2) If by reason of—
  • (a) the construction of any specified work, or
  • (b) the failure of any such work,

damage to a fishery is caused, or the Agency has reason to expect that such damage may be caused, the Agency may serve notice on the nominated undertaker requiring it to take such steps as may be reasonably practicable to make good the damage or, as the case may be, to protect the fishery against such damage.

  • (3) If, within such time as may be reasonably practicable for that purpose after the receipt of written notice from the Agency of any damage or expected damage to a fishery, the nominated undertaker fails to take such steps as are described in sub-paragraph (2), the Agency may take those steps and may recover from the nominated undertaker the expense reasonably incurred by it in doing so.
  • (4) In any case where immediate action by the Agency is reasonably required in order to secure that the risk of damage to a fishery is avoided or reduced, the Agency may take such steps as are reasonable for the purpose, and may recover from the nominated undertaker the reasonable cost of so doing provided that notice specifying those steps is served on the nominated undertaker as soon as reasonably practicable after the Agency has taken, or commenced to take, the steps specified in the notice.
8
  • (1) The nominated undertaker shall indemnify the Agency from all claims, demands, proceedings or damages, which may be made or taken against, or recovered from the Agency by reason of—
  • (a) any damage to any drainage work so as to impair its efficiency for flood defence purposes,
  • (b) any damage to a fishery,
  • (c) any raising or lowering of the water table in land adjoining the works authorised by this Act or any sewers, drains and watercourses, or
  • (d) any flooding or increased flooding of any such lands,

which is caused by, or results from, the construction of any specified work or any act or omission of the nominated undertaker, its contractors, agents or employees whilst engaged upon the work.

  • (2) The Agency shall give to the nominated undertaker reasonable notice of any such claim or demand and no settlement or compromise of any such claim or demand shall be made without the consent of the nominated undertaker which, if it withholds such consent, shall have the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
9

Nothing in paragraph 8 shall require the nominated undertaker to indemnify the Agency in respect of any claim, demand, proceedings or damages which the Agency could reasonably make, take against or recover from any other person.

10

The fact that any work or thing has been executed or done in accordance with a plan approved or deemed to be approved by the Agency, or to its satisfaction, or in accordance with any determination under paragraph 12, shall not (in the absence of negligence on the part of the Agency, its officers, contractors or agents) relieve the nominated undertaker from any liability under the provisions of this Part.

11

For the purposes of section 5 of the Metropolis Management (Thames River Prevention of Floods) Amendment Act 1879 (c. cxcviii) and Chapter 2 of Part 2 of the Water Resources Act 1991 (c. 57) (abstraction and impounding of water) and section 109 of that Act (as to structures in, over or under watercourses) as applying to the construction of any specified work, any consent or approval given or deemed to be given by the Agency under this Part with respect to such construction shall be deemed also to constitute an impounding licence under that Chapter or, as the case may be, a consent or approval under those sections, and the nominated undertaker shall not be obliged to serve any notice which would otherwise be required by section 30 of the said Act of 1991 (which relates to the construction of boreholes and similar works in respect of which a licence is not required).

12
  • (1) Any dispute arising between the nominated undertaker and the Agency under this Part shall be determined by arbitration if—
  • (a) the parties agree, or
  • (b) the dispute relates to the amount of any sum payable under this Part,

but shall otherwise by determined by a person appointed by the appropriate Ministers.

  • (2) Any person appointed by the appropriate Ministers under sub-paragraph (1) shall, in determining any dispute arising under this Part, have regard to such matters as may be specified by the appropriate Ministers on making the appointment.
  • (3) In this paragraph the reference to the appropriate Ministers is to the Secretary of State for Transport and the Secretary of State for Environment, Food and Rural Affairs acting jointly.

Part 4 — Protection of electronic communications code networks

1
  • (1) The following provisions of this Part shall, unless otherwise agreed in writing between the nominated undertaker and an operator of an electronic communications code network, have effect.
  • (2) In this Part—
  • the authorised works” means the works authorised by this Act;
  • construction” includes installation and “construct” shall be construed accordingly;
  • electronic communications code” means the code set out in Schedule 3A to the Communications Act 2003; and
  • operator”, “electronic communications apparatus”, and “electronic communications code network” have the meanings given by paragraph 17(1) of Schedule 17 to the Communications Act 2003 (c. 21).
2
  • (1) Subject to sub-paragraph (2), Part 10 of the electronic communications code shall apply for the purposes of the authorised works.
  • (2) Parts 6 and 10 of the electronic communications code shall not apply for the purposes of the authorised works,
  • (a) insofar as such works are regulated by the New Roads and Street Works Act 1991 (c. 22) or any regulation made under that Act;
  • (b) where the nominated undertaker exercises a right under subsection (4)(b) of section 272 of the Town and Country Planning Act 1990 (c. 8) or under an order made under that section to remove electronic communications apparatus; or
  • (c) in respect of any matter regulated by sub-paragraphs (3) to (8) of paragraph 4.
3

The temporary stopping up or diversion of any highway under paragraph 5 of Schedule 3 shall not affect any right of an operator under Part 8 of the electronic communications code in respect of any apparatus which at the time of the stopping up or diversion is in the highway.

4
  • (1) Where a highway is stopped up under paragraph 1 or 2 of Schedule 3, any operator of an electronic communications code network whose electronic communications apparatus is under, over, in, on, along or across that highway may exercise the same rights of access in order to inspect, maintain, adjust, repair or alter that apparatus as if this Act had not been passed, but nothing in this sub-paragraph shall affect any right of the nominated undertaker or the operator to require removal of that apparatus under this Part or the power of the nominated undertaker to alter apparatus in accordance with Part 10 of the electronic communications code.
  • (2) The nominated undertaker shall give not less than 28 days' notice in writing of its intention to stop up any highway under paragraph 1 or 2 of Schedule 3 to any operator of an electronic communications code network whose apparatus is under, over, in, on, along or across the highway.
  • (3) Where a notice under sub-paragraph (2) has been given, the operator, if it reasonably considers that it is necessary for the safe and efficient operation and maintenance of the apparatus, may, and if reasonably requested so to do by the nominated undertaker in the notice, shall, as soon as reasonably practicable after the service of the notice—
  • (a) remove the apparatus and place it or other apparatus provided in substitution for it in such other position as the operator may reasonably determine and have power to place it, or
  • (b) provide other apparatus in substitution for the existing apparatus and place it in such other position as aforesaid.
  • (4) Subject to the following provisions of this paragraph the nominated undertaker shall pay to any operator of an electronic communications code network an amount equal to the cost reasonably incurred by the operator in or in connection with—
  • (a) the execution of relocation works required in consequence of the stopping up of the highway, and
  • (b) the doing of any other work or thing rendered necessary by the execution of relocation works.
  • (5) If in the course of the execution of relocation works under sub-paragraph (3)—
  • (a) apparatus of better type, greater capacity or greater dimensions is placed in substitution for existing apparatus of worse type, smaller capacity or smaller dimensions, except where this has been solely due to using the nearest currently available type, capacity or dimension, or
  • (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which existing apparatus was,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the nominated undertaker, or, in default of agreement, is not determined to be necessary in consequence of the construction of the authorised works in order to ensure the continued efficient operation of the electronic communications code network of the operator then, if it involves cost in the execution of the relocation works exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this paragraph would be payable to the operator by virtue of sub-paragraph (4) shall be reduced by the amount of that excess.

  • (6) For the purposes of sub-paragraph (5)—
  • (a) an extension of apparatus to a length greater than the length of existing apparatus shall not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus except in a case where the apparatus as so extended provides more than an equivalent service, and
  • (b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole (in either case of such type, capacity and dimensions as shall reasonably be appropriate) shall be treated as if it also had been agreed or had been so determined.
  • (7) The amount which apart from this sub-paragraph would be payable to an operator in respect of works by virtue of sub-paragraph (4) (and having regard, where relevant, to sub-paragraph (5)) shall, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7½ years earlier so as to confer on the operator any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
  • (8) Sub-paragraphs (4) to (7) shall not apply where the authorised works constitute major transport works or major highway works for the purpose of Part 3 of the New Roads and Street Works Act 1991 (c. 22) (including that provision as applied by paragraph 8 of Schedule 3 to this Act), but instead—
  • (a) the allowable costs of any relocation works shall be determined in accordance with section 85 of that Act (sharing of costs of necessary measures) and any regulations for the time being having effect under that section, and
  • (b) the allowable costs shall be borne by the nominated undertaker and the operator in such proportions as may be prescribed by any such regulations.
5
  • (1) Subject to sub-paragraphs (2) to (4), if by reason of the construction of the authorised works or any subsidence resulting from any of those works, any damage is caused to any electronic communications apparatus, other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works, or property of the operator of an electronic communications code network, or there is any interruption in the supply of the service provided by the operator, the nominated undertaker shall bear and pay the cost reasonably incurred by the operator in making good such damage or restoring the supply and shall—
  • (a) make reasonable compensation to the operator for loss sustained by it, and
  • (b) indemnify the operator against all claims, demands, proceedings, or damages which may be made or taken against, or recovered from, the operator, by reason of any such damage or interruption.
  • (2) Sub-paragraph (1) shall not apply to any apparatus in respect of which the relations between the nominated undertaker and the operator are regulated by the provisions of Part 3 of the New Roads and Street Works Act 1991.
  • (3) Nothing in sub-paragraph (1) shall impose any liability on the nominated undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of the operator, its officers, servants, contractors or agents.
  • (4) The operator shall give the nominated undertaker reasonable notice of any such claim or demand and no settlement or compromise of any such claim or demand shall be made without the consent of the nominated undertaker which, if it withholds such consent, shall have the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
6
  • (1) Any dispute arising between the nominated undertaker and an operator under this Part shall be determined by arbitration if—
  • (a) the parties agree, or
  • (b) the dispute relates to the amount of any sum payable under this Part,

but shall otherwise by determined by a person appointed by the appropriate Ministers.

  • (2) Any person appointed by the appropriate Ministers under sub-paragraph (1) shall, in determining any dispute arising under this Part, have regard to such matters as may be specified by the appropriate Ministers on making the appointment.
  • (3) In this paragraph the reference to the appropriate Ministers is a reference to the Secretary of State for Transport and the Secretary of State for Science, Innovation and Technology acting jointly.

Part 5 — Protection of Canal & River Trust

1
  • (1) The following provisions of this Part shall, unless otherwise agreed in writing between the nominated undertaker, or the Secretary of State as the case may be, and Canal & River Trust, have effect.
  • (2) In this Part—
  • ...
  • the canal” means any canal or waterway owned or managed by Canal & River Trust, and includes any works connected therewith for the maintenance of which Canal & River Trust is responsible and any lands held or used by Canal & River Trust for the purposes of the canal;
  • construction” includes execution, placing, altering, replacing and relaying and includes removal;
  • plans” includes sections, drawings, specifications and method statements;
  • specified work” means so much of any permanent or temporary work authorised by this Act as is in, across, under, or within 15 metres of, or may in any way affect, the canal.
2

The Secretary of State shall not under the powers of section 6 acquire compulsorily any land of Canal & River Trust or any easement or other right over such land other than such land, or easements or other rights thereover, as is reasonably necessary for, or in connection with, the construction, maintenance or operation of works authorised by this Act.

3
  • (1) Before beginning to construct any specified work, the nominated undertaker shall submit to Canal & River Trust plans of the work and such further particulars available to it as Canal & River Trust may within 14 days of the submission of the plans reasonably require.
  • (2) Any specified work shall not be constructed except in accordance with such plans as may be approved in writing by Canal & River Trust or determined under paragraph 11.
  • (3) Any approval of Canal & River Trust required under this paragraph shall not be unreasonably withheld and—
  • (a) shall be deemed to have been given if it is neither given nor refused (with an indication of the grounds for refusal) within 28 days of the submission of the plans for approval or where further particulars are submitted under paragraph 3(1), within 28 days of the submission of those particulars; and
  • (b) may be given subject to such reasonable requirements as Canal & River Trust may make for the purpose of ensuring the safety or stability of the canal, including requirements as to the construction of protective works.
4
  • (1) Any specified work, and any protective works required by Canal & River Trust under paragraph 3(3)(b), shall be constructed with all reasonable despatch to the reasonable satisfaction of Canal & River Trust, and in such manner as to cause as little damage to the canal as may be reasonably practicable and as little interference as may be reasonably practicable with the passage of vessels using the canal, and Canal & River Trust shall be entitled by its officer at all reasonable times, on giving such notice as may be reasonable in the circumstances, to inspect the construction of such work or works.
  • (2) The nominated undertaker shall give to Canal & River Trust not less than 28 days' notice in writing of its intention to commence construction of any specified work or any protective works and also, except in emergency (when the nominated undertaker shall give such notice as may be reasonably practicable), of its intention to carry out any works for the repair or maintenance of any specified work insofar as such works of repair or maintenance affect or interfere with the canal.
5
  • (1) The nominated undertaker shall not deposit any polluting material on, in or over the canal and shall not without the consent of Canal & River Trust—
  • (a) deposit any other materials on, in or over the canal (other than materials comprised in a specified work); or
  • (b) notwithstanding anything in this Act, discharge any water directly or indirectly into the canal.
  • (2) Any consent of Canal & River Trust required under this paragraph shall not be unreasonably withheld and—
  • (a) shall be deemed to have been given if it is neither given nor refused within 28 days of the submission of the request for it; and
  • (b) may be given subject to such reasonable requirements as Canal & River Trust may make—
  • (i) in the case of a deposit, so as to ensure that the use of the canal is not obstructed or rendered less safe, and
  • (ii) in the case of a discharge, concerning the reimbursement by the nominated undertaker of expenses incurred by Canal & River Trust in disposing of the water so discharged, being expenses which Canal & River Trust would not have incurred but for the discharge.
6

In its application to the discharge of water into the canal, paragraph 8(5) of Schedule 2 shall have effect subject to the terms of any conditions attached to the consent under paragraph 5(2) above and, where such discharge includes a deposit to which consent has been given under paragraph 5(1) above, to any conditions attached to that consent.

7
  • (1) If as a result of the construction of any specified work any part of the towing path or access way beside the canal, or any public right of way giving access thereto, is temporarily closed to pedestrians or cyclists and there is no way which provides a reasonable alternative, the nominated undertaker shall, so far as reasonably practicable and to the extent that it is consistent with safety, provide a substitute path or paths for such time as the closure continues.
  • (2) This paragraph is without prejudice to the requirements of paragraph 5(2) or (5) of Schedule 3.
8
  • (1) If any canal work is abandoned, Canal & River Trust may by notice in writing require the nominated undertaker to take such reasonable steps as may be specified in the notice to remove the work and (to such extent as Canal & River Trust reasonably requires) to restore the site to its former condition.
  • (2) If any canal work is in such condition that it is, or is likely to become, a danger to or to interfere with navigation, Canal & River Trust may by notice in writing require the nominated undertaker to take such reasonable steps as may be specified in the notice—
  • (a) to repair and restore the work or part of it, or
  • (b) if the nominated undertaker so elects, to remove the work and (to such extent as Canal & River Trust reasonably requires) to restore the site to its former condition.
  • (3) If—
  • (a) a work which consists of a canal work and a non-canal work is abandoned or falls into decay; and
  • (b) the non-canal work is in such a condition as to interfere with the right of navigation in the relevant canal or as to interfere with the rights of access or use of land adjacent to the relevant canal;

Canal & River Trust may include the non-canal work, or any part of it, in any notice under this paragraph.

  • (4) If after such reasonable period as may be specified in a notice under this paragraph the nominated undertaker has failed to begin taking steps to comply with the requirements of the notice or after beginning has failed to make reasonably expeditious progress towards their implementation, Canal & River Trust may carry out the works specified in the notice and any expenditure reasonably incurred by it in so doing shall be recoverable from the nominated undertaker.
  • (5) In this paragraph “canal work” means so much of any specified work or any other work of which the nominated undertaker is in possession under the powers of this Act as is in or over a canal owned or managed by Canal & River Trust and “non-canal work” means so much of any such work as is not in or over a canal.
9
  • (1) The nominated undertaker shall indemnify Canal & River Trust from all claims, demands, proceedings or damages, which may be made or given against, or recovered from Canal & River Trust by reason of any damage to the canal which is caused by the construction of any specified work or protective work or any act or omission of the nominated undertaker, its contractors, agents or employees whilst engaged upon the work and from any costs reasonably incurred in making good such damage.
  • (2) Canal & River Trust shall give to the nominated undertaker reasonable notice of any such claim or demand and no settlement or compromise of any such claim or demand shall be made without the consent of the nominated undertaker which, if it notifies Canal & River Trust that it desires to do so, shall have the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
10

Nothing in paragraph 9 shall impose any liability on the nominated undertaker with respect to any damage to the extent that it is attributable to the act, neglect or default of Canal & River Trust, its officers, servants, contractors or agents but the fact that any work or thing has been executed or done in accordance with a plan approved or deemed to be approved by Canal & River Trust, or to its satisfaction, or in accordance with a determination under paragraph 11, shall not (in the absence of negligence on the part of Canal & River Trust, its officers, servants, contractors or agents) relieve the nominated undertaker from any liability under the provisions of this Part.

11
  • (1) Any dispute arising between the nominated undertaker and Canal & River Trust under this Part of this Schedule shall be determined by arbitration if—
  • (a) the parties agree, or
  • (b) the dispute relates to the amount of any sum payable under this Part,

but shall otherwise by determined by a person appointed by the appropriate Ministers.

  • (2) Any person appointed by the appropriate Ministers under sub-paragraph (1) shall, in determining any dispute arising under this Part, have regard to such matters as may be specified by the appropriate Ministers on making the appointment.
  • (3) In this paragraph, the reference to the appropriate Ministers is to the Secretary of State for Transport and the Secretary of State for Environment, Food and Rural Affairs acting jointly.

Part 6 — Protection of Port of London Authority

1
  • (1) The following provisions of this Part shall, unless otherwise agreed in writing between the nominated undertaker and the Port Authority, have effect for the protection of the Port Authority and the users of the river.
  • (2) In this Part—
  • the 1968 Act” means the Port of London Act 1968 (c.xxxii);
  • construction” includes execution, placing, altering, replacing, relaying and removal and, in its application to works which include or comprise any operation, means the carrying out of that operation;
  • operations” includes temporary works and operations authorised by paragraph 10 of Schedule 2;
  • plans” includes sections, drawings, specifications and method statements;
  • the Port Authority” means the Port of London Authority;
  • the river” means the waters within the limits of the port of London as described in Schedule 1 to the 1968 Act;
  • specified work” means so much of any permanent or temporary work authorised by this Act (which includes, for the avoidance of doubt, any removal of gravel or other material, any dredging or similar work and any geotechnical investigations that may be undertaken) as is on, in, under or over—the surface of land below the level of mean high water springs forming part of the river; orany other land owned, occupied or used by the Port Authority for operational purposes.
2
  • (1) Before beginning any operations for the construction of any specified work, the nominated undertaker shall submit to the Port Authority plans of the work and such further particulars available to it as the Port Authority may within 14 days of the submission of the plans reasonably require.
  • (2) Any specified work shall not be constructed except in accordance with such plans as may be approved in writing by the Port Authority or determined under paragraph 13.
  • (3) Any approval of the Port Authority required under this paragraph shall not be unreasonably withheld and—
  • (a) shall be deemed to be given if it is neither given nor refused (with an indication of the grounds for refusal) within 28 days of the submission of the plans or where further particulars are submitted under paragraph 2(1), within 28 days of the submission of those particulars; and
  • (b) may be given subject to such reasonable requirements as the Port Authority may make for the protection of—
  • (i) navigation in, or the flow or regime of, the river; or
  • (ii) the use of its land for the purposes of performing its statutory functions.
  • (4) The requirement for approval under this paragraph does not constitute any specified work a work subject to any of the controls in Part 5 of the 1968 Act.
3

The nominated undertaker shall carry out all operations for the construction of any specified work with all reasonable despatch to the reasonable satisfaction of the Port Authority so that navigation in, or the flow or regime of, the river and the exercise of the Port Authority's statutory functions shall not suffer more interference than is reasonably practicable and the Port Authority shall be entitled by its officer at all reasonable times, on giving such notice as may be reasonable in the circumstances, to inspect and survey such operations.

4
  • (1) The nominated undertaker shall not, without the consent of the Port Authority—
  • (a) deposit in, or allow to fall or be washed into, the river any gravel, soil or other material in suspension or otherwise;
  • (b) discharge or allow to escape into the river any offensive or injurious matter in suspension or otherwise, or oil; or
  • (c) notwithstanding anything in paragraph 8 of Schedule 2, discharge any water directly or indirectly into the river.
  • (2) Any consent of the Port Authority under this paragraph shall not be unreasonably withheld and—
  • (a) shall be deemed to have been given if it is neither given nor refused within 28 days of the submission of the request for it; and
  • (b) may be given subject to such reasonable requirements as the Port Authority may make for the protection of navigation in, or the flow or regime of, the river.
  • (3) In its application to the discharge of water into the river, paragraph 8(5) of Schedule 2 shall have effect subject to the terms of any conditions attached to a consent given under this paragraph.
  • (4) Nothing in this paragraph authorises the doing of anything prohibited by section 85(1), (2) or (3) of the Water Resources Act 1991 (c. 57) (offences of polluting controlled waters).
5
  • (1) If any pile, stump or other object becomes exposed in the course of constructing any specified work (other than a pile, stump or other object on the site of any permanent work), such that it has or is likely to have any adverse effect on navigation in, or flow or regime of, the river, the nominated undertaker shall notify the Port Authority and as soon as reasonably practicable after the receipt of notice in writing from the Port Authority requiring such action, remove it from the river or, if it is not reasonably practicable to remove it, cut it off at such level below the bed of the river as the Port Authority may reasonably direct.
  • (2) If the nominated undertaker fails to remove from the river or cut off any such pile, stump or other object within 28 days after receipt of written notice from the Port Authority requiring the removal or cutting off, the Port Authority may carry out the removal or cutting off and recover their costs from the nominated undertaker.
6

If—

  • (a) by reason of the construction of any specified work it is reasonably necessary for the Port Authority to incur costs in altering, removing, resiting or reinstating existing moorings, or laying down and removing substituted moorings, or carrying out dredging operations for any such purpose, not being costs which it would have incurred for any other reason; and
  • (b) the Port Authority gives to the nominated undertaker not less than 28 days' notice of its intention to incur such costs, and takes into account any representations which the nominated undertaker may make in response to the notice within 14 days of the receipt of the notice;

the nominated undertaker shall pay the costs reasonably so incurred by the Port Authority.

7

The nominated undertaker shall, at or near every specified work, and any other work of which the nominated undertaker is in possession in exercise of any of the powers of this Act, being in either case a work which is below the level of mean high water springs, exhibit such lights, lay down such buoys and take such other steps for preventing danger to navigation as the Port Authority may from time to time reasonably require.

8
  • (1) If any tidal work is abandoned, the Port Authority may by notice in writing require the nominated undertaker to take such reasonable steps as may be specified in the notice to remove the work and (to such extent as the Port Authority reasonably requires) to restore the site to its former condition.
  • (2) If any tidal work is in such condition that it is, or is likely to become, a danger to or to interfere with navigation in or the regime of, the river, the Port Authority may by notice in writing require the nominated undertaker to take such reasonable steps as may be specified in the notice—
  • (a) to repair and restore the work or part of it, or
  • (b) if the nominated undertaker so elects, to remove the work and (to such extent as the Port Authority reasonably requires) to restore the site to its former condition.
  • (3) If—
  • (a) a work which consists of a tidal work and a non-tidal work is abandoned or falls into decay; and
  • (b) the non-tidal work is in such a condition as to interfere with the right of navigation in the river;

the Port Authority may include the non-tidal work, or any part of it, in any notice under this paragraph.

  • (4) In this paragraph “tidal work” means so much of any specified work or any other work of which the nominated undertaker is in possession under the powers of this Act as is below the level of mean high water springs and “non-tidal work” means so much of any such work as is above that level.
  • (5) If after such reasonable period as may be specified in a notice under this paragraph the nominated undertaker has failed to begin taking steps to comply with the requirements of the notice or after beginning has failed to make reasonably expeditious progress towards their implementation, the Port Authority may carry out the works specified in the notice and any expenditure reasonably incurred by it in so doing shall be recoverable from the nominated undertaker.
9

Paragraph 8(4) of Schedule 2 shall apply to any discharge of water under paragraph 8(1) of that Schedule in connection with the construction or maintenance of a specified work notwithstanding that the part of the river affected by the discharge is not a main river.

10

The exercise of the powers of this Act to navigate or moor barges, or other vessels or craft within the river shall be subject to such directions as the harbour master of the Port Authority may make from time to time under section 112 of the 1968 Act.

11
  • (1) The nominated undertaker shall indemnify the Port Authority from all claims, demands, proceedings or damages, which may be made or given against, or recovered from the Port Authority by reason of any damage to the bed or banks of the river which is caused by the construction of any specified work or protective work or any act or omission of the nominated undertaker, its contractors, agents or employees whilst engaged upon the work and from any costs reasonably incurred in making good such damage.
  • (2) The Port Authority shall give to the nominated undertaker reasonable notice of any such claim or demand and no settlement or compromise of any such claim or demand shall be made without the consent of the nominated undertaker which, if it notifies the Port Authority that it desires to do so, shall have the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
12

Nothing in paragraph 11 shall impose any liability on the nominated undertaker with respect to any damage to the extent that it is attributable to the act, neglect or default of the Port Authority, its officers, servants, contractors or agents but the fact that any work or thing has been executed or done in accordance with a plan approved or deemed to be approved by the Port Authority, or to its satisfaction, or in accordance with a determination under paragraph 13, shall not (in the absence of negligence on the part of the Port Authority, its officers, servants, contractors or agents) relieve the nominated undertaker from any liability under the provisions of this Part.

13
  • (1) Any dispute arising between the nominated undertaker and the Port Authority under this Part shall be determined by arbitration if—
  • (a) the parties agree, or
  • (b) the dispute relates to the amount of any sum payable under this Part,

but shall otherwise be determined by a person appointed by the Secretary of State.

  • (2) Any person appointed by the Secretary of State under sub-paragraph (1) shall, in determining any dispute arising under this Part, have regard to such matters as may be specified by the Secretary of State on making the appointment.

Construction and maintenance of scheduled works

Planning: general

Permitted development: time limit

Fees for planning applications

EIA regulations: replacement development

Extension of permitted development rights

Control of construction sites: appeals

Proceedings in respect of statutory nuisance: defence

Objective of Office of Rail and Road in relation to Crossrail

Duty of Office of Rail and Road to publish reports

Closures

Prohibitions or restrictions on land use imposed for Crossrail purposes

Reinstatement of discontinued facilities

Description of works

The works which the nominated undertaker is authorised by section 1 to make and maintain are the following–

In the City of Westminster, London Boroughs of Camden, Islington and Tower Hamlets and City of London–

In the London Boroughs of Tower Hamlets and Newham–

In the London Borough of Newham–

In the London Boroughs of Newham and Greenwich–

In the London Borough of Greenwich—

In the London Boroughs of Greenwich and Bexley–

In the City of Westminster and Royal Borough of Kensington & Chelsea–

In the City of Westminster–

In the City of Westminster and London Borough of Camden–

In the London Borough of Camden–

In the City of London–

In the City of London and London Borough of Islington–

In the City of London–

In the London Borough of Tower Hamlets–

In the London Borough of Newham–

In the London Boroughs of Greenwich and Bexley–

In the London Borough of Greenwich–

In the London Borough of Bexley–

In the London Boroughs of Greenwich and Bexley–

In the London Borough of Bexley–

In the London Boroughs of Tower Hamlets and Newham–

In the London Borough of Newham–

In the London Borough of Tower Hamlets—

In the London Borough of Newham–

In the London Boroughs of Redbridge and Newham–

In the London Borough of Newham–

In the London Boroughs of Redbridge and Barking & Dagenham–

In the London Boroughs of Barking & Dagenham and Havering–

In the London Borough of Havering–

In the County of Essex, Borough of Brentwood–

In the County of Essex, District of Basildon–

In the London Borough of Redbridge—

In the London Borough of Newham—

In the County of Berkshire, Royal Borough of Windsor & Maidenhead–

In the County of Berkshire, Borough of Slough–

In the County of Berkshire, Borough of Slough and County of Buckinghamshire, District of South Bucks, Parish of Iver–

In the County of Berkshire, Borough of Slough—

In the County of Buckinghamshire, District of South Bucks, Parish of Iver–

In the London Borough of Hillingdon–

In the London Borough of Ealing–

In the London Borough of Hammersmith & Fulham–

In the London Borough of Hammersmith & Fulham and the Royal Borough of Kensington & Chelsea—

In the London Borough of Hammersmith & Fulham—

In the London Borough of Hammersmith & Fulham and the Royal Borough of Kensington & Chelsea—

In the London Borough of Hammersmith & Fulham and the Royal Borough of Kensington & Chelsea—

In the Royal Borough of Kensington & Chelsea—

Additional works

Highway accesses

Overhead line diversions

Mitigation and protection works

Support of buildings

Discharge of water

Entry for preparatory purposes

Temporary interference with waterways

Stopping-up

Permanent obstruction

Temporary interference

Working sites in highways

Street works

Construction

Maintenance

Bridges carrying highways

Agreements with highway authorities etc.

Use of subsoil

Scope of Schedule

Publicity

Consultation

Interpretation

Occupation and use for construction of works

Occupation and use for maintenance of works

Suspension of private rights of way

Enforcement

Lands Clauses Consolidation Act 1845

Compulsory Purchase Act 1965

Compulsory Purchase (Vesting Declarations) Act 1981

Acquisition of new rights

Limitation of power of acquisition to rights only

Limitation of power of acquisition to land of specified description

Acquisition of subsoil

Limitation of power of acquisition in relation to land not more than 9 metres below the surface

Extension of power to acquire new rights

Acquisition of part only of certain properties

Minerals

Power to require acquisition where time limit extended

Compensation

Specification

Transition

Introductory

Planning regimes

Conditions: non-qualifying authority

Conditions: qualifying authority

Conditions: general

Introductory

Planning regimes: district councils

District conditions: non-qualifying authority

District conditions: qualifying authority

District conditions: general

County conditions: qualifying authority

Programming of requests for planning approvals

Consultation

Intervention by the Secretary of State

Appeals

Modification of Schedule

Interpretation

Conditions of permitted development

Controls in relation to proposed development

Notices

Interpretation

Listed buildings and conservation areas

Ancient monuments etc.

Highway (Railway Crossings) Act 1839 (c. 45)

Railway Regulation Act 1842 (c. 55)

Railways Clauses Consolidation Act 1845 (c. 20)

Railways Clauses Act 1863 (c. 92)

Railway Companies (Accounts and Returns) Act 1911 (c. 34)

British Transport Commission Act 1949 (c. xxix)

Miscellaneous

Scheme for grant of lease

Property, rights and liabilities that may be transferred

Creation by a scheme of interests, rights and liabilities

Identifying what is transferred or created by a scheme

Scheme may provide for contraventions etc. to be treated as not occurring

Transfer of shares in subsidiary of transferor

Scheme may modify interests, rights and liabilities of third parties

Scheme may impose obligations to enter into agreements or execute instruments

Supplementary provisions of schemes

Effect of scheme

Modification of scheme by agreement

Transfer of employees and continuity of employment

Provision of information to person making scheme

Agreements relating to schemes

Interpretation

Meaning of “public body”

Meaning of “taxable public body” and “exempt public body”

Interpretation: supplementary

Meaning of “relevant transfer” in Part 2 of Schedule

Computation of profits and losses in respect of transfer of trade

Transfers of trading stock

Capital allowances: transfer of whole trade

Capital allowances: transfer of part of a trade

Capital allowances: transfer of plant or machinery

Capital allowances: transfers not to be sales

Chargeable gains: assets to be treated as disposed of without a gain or a loss

Chargeable gains: roll-over relief

Continuity in relation to transfer of intangible assets

Continuity in relation to loan relationships

Continuity in relation to derivative contracts

Leased assets

Meaning of “relevant transfer” in Part 3 of Schedule

Transfers of trading stock

Capital allowances: determination of disposal value of plant or machinery

Capital allowances: determination of disposal value of fixtures

Capital allowances: determination of capital value of industrial buildings etc.

Chargeable gains: assets to be treated as disposed of without a gain or a loss

Neutral effect of transfer of intangible assets

Neutral effect of transfer for loan relationships and derivative contracts

Leased assets

Meaning of “relevant transfer” in Part 4 of Schedule

Capital allowances: transfer of plant or machinery

Capital allowances: determination of capital value of industrial buildings etc.

Meaning of “relevant transfer” in Part 5 of Schedule

Trading losses: change in ownership

Chargeable gains: degrouping charges

Stamp duty

Meaning of “relevant transfer” in Part 6 of Schedule

Transfers of trading stock

Capital allowances: determination of disposal value of plant or machinery

Capital allowances: determination of disposal value of fixtures

Capital allowances: section 265 of CAA 2001 not to apply in relation to transferee

Capital allowances: determination of capital value of industrial buildings etc.

Chargeable gains: disposals not to be treated as made at market value

Loan relationships

Chargeable gains: value shifting

Group relief

Modification of transfer schemes and determinations under paragraph 9(1)(d) or 27(1)(c): companies

Modification of transfer schemes: other persons and partnerships

Power to make further provision in relation to transfer schemes

Consequential amendment

Ecclesiastical law

Overground wires

London Squares Preservation Act 1931

London Building Acts (Amendment) Act 1939

Coast works

Port of London Act 1968

Highways, etc.

Building regulations

Deposits in the sea

London lorries: general

London lorries: emergency permit

Works under streets in Greater London

New Roads and Street Works Act 1991

Water abstraction

Communication with public sewers in London

Party Wall etc. Act 1996

Notice of removal

Removal of remains

Removal of monuments

Records

Supplementary

Power to reinstate

Planning conditions

Editorial notes

[^key-b83faab4316c6711a9118d24657afd29]: S. 4(5)(b) transfer of functions (5.3.2009) by Secretary of State for Energy and Climate Change Order 2009 (S.I. 2009/229), arts. 1(2), 4, Sch. 1(i)

[^key-d035a90e852ddef089e99da1cf02ae2c]: Sch. 4 para. 12 transfer of functions (5.3.2009) by Secretary of State for Energy and Climate Change Order 2009 (S.I. 2009/229), arts. 1(2), 4, Sch. 1(j)

[^key-54ff98084853bf6cb2b840d4c62b7c3b]: Sch. 17 Pt. 2 para. 13(3) transfer of functions (5.3.2009) by Secretary of State for Energy and Climate Change Order 2009 (S.I. 2009/229), arts. 1(2), 4, Sch. 1(k)

[^M_C_5e0fc8e1-2d8d-4154-9693-ab2906b04d40]: Sch. 17 Pt. 2 para. 2(4) transfer of functions (5.3.2009) by Secretary of State for Energy and Climate Change Order 2009 (S.I. 2009/229), arts. 1(2), 4, Sch. 1(k)

[^key-563584f8c8baaa1fbc0532e903674bd4]: Definition in Sch. 13 para. 3(1) inserted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(2) (with Sch. 2 Pts. 1, 2)

[^key-f223703d4602db57718827ed9ed030d2]: Words in Sch. 13 para. 5(5) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(3) (with Sch. 2 Pt. 1, 2)

[^key-f14a86739cc7172a1b7360797835ba73]: Words in Sch. 13 para. 6(5) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(4) (with Sch. 2 Pts. 1, 2)

[^key-cb1425fa32e1e4304976193c74102f37]: Words in Sch. 13 para. 13(1) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(5)(a) (with Sch. 2 Pts. 1, 2)

[^key-50aed92a456a700f588c71cd3f7fc499]: Word in Sch. 13 para. 13(2) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(5)(b) (with Sch. 2 Pts. 1, 2)

[^key-434d4ab954fb82f99b28512e1d0ae384]: Words in Sch. 13 para. 14(1) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(6)(a) (with Sch. 2 Pts. 1, 2)

[^key-4d6f3c15c698f977d904e664d95a0e1d]: Words in Sch. 13 para. 14(2) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(6)(b) (with Sch. 2 Pts. 1, 2)

[^key-1daab7b9e3ce73be70086c7e293c1867]: Words in Sch. 13 para. 15(1) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(7)(a) (with Sch. 2 Pts. 1, 2)

[^key-b1e2ce155faf8a1d8721c423d55bc690]: Words in Sch. 13 para. 15(2) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(7)(b) (with Sch. 2 Pts. 1, 2)

[^key-1f3c38316174f567eb85bcb293ae827f]: Words in Sch. 13 para. 18(6) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(8) (with Sch. 2 Pts. 1, 2)

[^key-42c6080cf4536a1bc5c729b2c06c8875]: Words in Sch. 13 para. 23(1) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(9)(a) (with Sch. 2 Pts. 1, 2)

[^key-c67f542e58c9b7312df29b40ececbe37]: Word in Sch. 13 para. 23(2) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(9)(b) (with Sch. 2 Pts. 1, 2)

[^key-ccf3828d5fe0e2953ae74f669eeeba12]: Words in Sch. 13 para. 24(b) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(10)(b) (with Sch. 2 Pts. 1, 2)

[^key-1613cebfbf183ede20638f9d19570bdb]: Words in Sch. 13 para. 24(a) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(10)(a) (with Sch. 2 Pts. 1, 2)

[^key-f7267be75c5b246c1f7a754b6a33f21e]: Words in Sch. 13 para. 34(6) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(11) (with Sch. 2 Pts. 1, 2)

[^key-50cbe8946c04474a4bf49410fa967e39]: Words in Sch. 13 para. 40(1) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(12)(a) (with Sch. 2 Pts. 1, 2)

[^key-a8bb65e126d619b8725fbee79c0a50e2]: Words in Sch. 13 para. 40(2) substituted (with effect in accordance with s. 1329(1) of the commencing Act) by Corporation Tax Act 2009 (c. 4), s. 1329(1), Sch. 1 para. 739(12)(b) (with Sch. 2 Pts. 1, 2)

[^key-38bd6849cabf8dc1c07bbbe2f4e92ec3]: Words in Sch. 6 para. 7(3) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 290(2)(a)(i) (with Sch. 5)

[^key-c33f82a0d506b9f681d677a884d89ec6]: Words in Sch. 6 para. 7(3) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 290(2)(a)(ii)(aa) (with Sch. 5)

[^key-4d2b412a1dd8698a53e096a19dd45c95]: Words in Sch. 6 para. 7(3) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 290(2)(a)(ii)(bb) (with Sch. 5)

[^key-40e3bd2a09a7931687ec95622f584518]: Words in Sch. 6 para. 7(3) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 290(2)(b) (with Sch. 5)

[^key-7e2860bd916dbc0e497a4be4a2953f46]: Words in Sch. 6 para. 7(3) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 290(2)(c) (with Sch. 5)

[^key-45006df2fde8f589c6e24605aa024912]: Words in Sch. 6 para. 7(3) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 290(2)(d)(i) (with Sch. 5)

[^key-543e412d51c40120792a4bdbac8ba85a]: Words in Sch. 6 para. 7(3) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 290(2)(d)(ii) (with Sch. 5)

[^key-56d70bfa4602cc8fe69a48d0dbe06c49]: Words in Sch. 6 para. 7(10) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 290(3) (with Sch. 5)

[^key-978fe8b34a34f192a9f31d316b5be21f]: Words in Sch. 6 para. 14(5) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 290(4) (with Sch. 5)

[^key-a20473e6e5186f27da8bcf245cac1048]: Words in Sch. 6 para. 15(1)-(6) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 290(5) (with Sch. 5)

[^key-fbe7676b354f7f20a0ac76fc0d9cd272]: Words in Sch. 6 para. 16(1) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 290(6) (with Sch. 5)

[^key-aaef8fb7c2c22c2e524769251cdd2d49]: Words in Sch. 6 para. 16(2) substituted (1.6.2009) by The Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307), art. 1, Sch. 1 para. 290(6) (with Sch. 5)

[^key-4646012fd276c352ad338a325e87d399]: S. 48(A1) inserted (1.3.2010) by Planning Act 2008 (c. 29), s. 241(8), Sch. 2 para. 66(2) (with s. 226); S.I. 2010/101, art. 2 (with art. 6)

[^key-2fdbd76c353f5e39ef379db36581dfce]: Words in s. 48(1) substituted (1.3.2010) by Planning Act 2008 (c. 29), s. 241(8), Sch. 2 para. 66(3) (with s. 226); S.I. 2010/101, art. 2 (with art. 6)

[^key-1dfd1b9f497c5d406e59a4ed5646e0f1]: Word in s. 48(2) substituted (1.3.2010) by Planning Act 2008 (c. 29), s. 241(8), Sch. 2 para. 66(4) (with s. 226); S.I. 2010/101, art. 2 (with art. 6)

[^key-c94b741bc0f84776512777907125836b]: Word in s. 48(5) substituted (1.3.2010) by Planning Act 2008 (c. 29), s. 241(8), Sch. 2 para. 66(5) (with s. 226); S.I. 2010/101, art. 2 (with art. 6)

[^key-c5c219410a567b2f6ac6ef2c292fb6ff]: Definition in Sch. 13 para. 3(1) inserted (with effect in accordance with s. 1184(1) of the commencing Act) by Corporation Tax Act 2010 (c. 4), s. 1184(1), Sch. 1 para. 584(2) (with Sch. 2)

[^key-04327d2472bc52bc90878d9a7cedb220]: Words in Sch. 13 para. 18(7) substituted (with effect in accordance with s. 1184(1) of the commencing Act) by Corporation Tax Act 2010 (c. 4), s. 1184(1), Sch. 1 para. 584(3) (with Sch. 2)

[^key-9dcbde041b0eaa42895a2d4a4b82dd97]: Words in Sch. 13 para. 30(2) substituted (with effect in accordance with s. 1184(1) of the commencing Act) by Corporation Tax Act 2010 (c. 4), s. 1184(1), Sch. 1 para. 584(4) (with Sch. 2)

[^key-485e0c695ef377dd3d78a272311bd967]: Words in Sch. 13 para. 34(7) substituted (with effect in accordance with s. 1184(1) of the commencing Act) by Corporation Tax Act 2010 (c. 4), s. 1184(1), Sch. 1 para. 584(5) (with Sch. 2)

[^key-bb44c2c9979034fb4c43d3b2b79742bd]: Words in Sch. 13 para. 42(a) substituted (with effect in accordance with s. 1184(1) of the commencing Act) by Corporation Tax Act 2010 (c. 4), s. 1184(1), Sch. 1 para. 584(6)(a) (with Sch. 2)

[^key-50ef5df5ddb41f1acf30bccbd41806f1]: Words in Sch. 13 para. 42(b) substituted (with effect in accordance with s. 1184(1) of the commencing Act) by Corporation Tax Act 2010 (c. 4), s. 1184(1), Sch. 1 para. 584(6)(b) (with Sch. 2)

[^key-f1347d5d667f59a4d8e581bbdc9c2a21]: S. 6(1) modified (21.4.2010) by The Crossrail (Devolution of Functions) Order 2010 (S.I. 2010/988), arts. 1, 3 (with art. 13)

[^key-4a1f44abf5cbee564364faf346561b95]: S. 7(1)(2) modified (21.4.2010) by The Crossrail (Devolution of Functions) Order 2010 (S.I. 2010/988), arts. 1, 3 (with art. 13)

[^key-c8bb540845f85fdc5e6e906a591735ee]: S. 8(1) modified (21.4.2010) by The Crossrail (Devolution of Functions) Order 2010 (S.I. 2010/988), arts. 1, 3 (with art. 13)

[^key-381c8fddf5afb926dad635724c877dc1]: S. 8(3) modified (21.4.2010) by The Crossrail (Devolution of Functions) Order 2010 (S.I. 2010/988), arts. 1, 3 (with art. 13)

[^key-588abda3dcbc02b2b1090b4f1384b61e]: S. 8(4) modified (21.4.2010) by The Crossrail (Devolution of Functions) Order 2010 (S.I. 2010/988), arts. 1, 3 (with arts. 12, 13)

[^key-96854e971c95e1a7dd62230255d019c3]: S. 47(1) modified (21.4.2010) by The Crossrail (Devolution of Functions) Order 2010 (S.I. 2010/988), arts. 1, 3 (with arts. 12, 13)

[^key-41b8e2deaff15fe97c5b4308d7d5405e]: S. 47(7) modified (21.4.2010) by The Crossrail (Devolution of Functions) Order 2010 (S.I. 2010/988), arts. 1, 3 (with arts. 12, 13)

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.