The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014

Type Statutory-Instrument
Publication 2014-09-03
Last updated 2014-09-24
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
Title Ref Text
CoCP Part B CREWD1 Until completion of construction the authorised development shall be carried out in accordance with the CoCP Part A subject to the site specific variations set out in CoCP Part B for this site, unless otherwise agreed with the relevant planning authority in consultation with other relevant stakeholders.
Detailed design approval for permanent above-ground structures CREWD2 (1) Construction of any permanent above-ground structure shall not commence until details of the design (including size, external appearances and samples of materials), which shall accord with the indicative features on the Proposed site features plan (Drawing No. DCO-PP-11X-CREWD-130008 – rev 1) and the design principles for this site, are submitted to and approved by the relevant planning authority. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority.
Detailed design approval for signature ventilation columns CREWD3 (1) Construction of the signature ventilation columns shall not commence until details of the height, dimensions, external appearance and materials, which shall accord with the Ventilation column type B (Drawing No. DCO-PP-900-ZZZZZ-290002 – rev 2), are submitted to and approved by the relevant planning authority. (2) The ventilation columns at this site shall not exceed 6 metres in height. (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority.
Details of works to listed buildings and structures CREWD4 (1) The following works to Lots Road Pumping Station shall not commence until details of those works, which shall accord with the design principles for this site and the maximum permanent extent of loss of the listed buildings/structures, shown on the Listed structure interface – Lots Road Pumping Station plan (Drawing No. DCO-PP-11X-CREWD-130012 – rev 1), are submitted to and approved by the relevant planning authority in consultation with the HBMCE— works to amend or replace the existing ventilation duct on the southeastern corner of the building works to install new equipment in the building works to protect the listed fabric during construction (2) The details provided shall include the following— detailed drawings showing all fixings to Lots Road Pumping Station detailed elevations construction method statement, including engineer’s drawings samples of materials. (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE.
Restoration works to listed buildings CREWD5 (1) Works to Lots Road Pumping Station shall not commence until details of works to restore the listed fabric including materials are submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE.
Contaminated land CREWD6 Site-specific remediation strategy (1) No works shall be carried out at this site (except for works in the highway including site access, works to trees and installation of monitoring equipment), unless otherwise agreed, until the following are submitted to and approved by the relevant planning authority in consultation with the Environment Agency— a preliminary risk assessment and site investigation scheme which identifies— all previous uses potential contaminants associated with those uses a conceptual model of the site indicating sources, pathways and receptors a qualitative risk assessment of any potentially unacceptable risks arising from contamination at the site a proposed site investigation scheme (based on the preliminary risk assessment) providing information for a detailed quantitative assessment of the risk to all receptors that may be affected, including those off-site. a remediation strategy which includes— the results of the site investigation a detailed quantitative risk assessment an options appraisal giving full details of the remediation measures required and how they shall be carried out a verification plan providing details of the data to be collected in order to demonstrate that the works set out in the remediation strategy are complete and identifying any requirements for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action a programme for the submission of elements detailed in (3) and (4) below. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Verification report (3) Prior to completion of the works, a verification report demonstrating completion of the works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The report shall include results of sampling and monitoring carried out in accordance with the approved details to demonstrate that the site remediation criteria were met. It shall also include a plan for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action as identified in the verification plan. (4) The long-term monitoring and maintenance plan shall be implemented in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Unexpected contamination (5) If, in carrying out any works on this site, contamination not previously identified is found to be present, then unless otherwise agreed by the relevant planning authority, no further development or works shall be carried out in the part of the site in which the contamination is identified until a remediation strategy is submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority.
Archaeology CREWD7 (1) No excavation shall be carried out until a SSAWSI (which shall accord with the OAWSI) is submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The authorised development shall be carried out in accordance with the approved details by a suitably qualified person or body.
Cremorne Wharf site restoration CREWD8 (1) Use of the authorised development shall not commence until a site restoration scheme for Cremorne Wharf (the area designated by the secretary of state as a Safeguarded Wharf), which shall accord with the design principles for this site, the Site works parameter plan and maintain the viability of the safeguarded wharf for cargo handling in accordance with the London Plan, is submitted to and approved by the Mayor of London, in consultation with the Port of London Authority and the relevant planning authority. (2) The site restoration scheme in paragraph (1) above shall include the following details— a. proposed finished ground levels b. hard-surfacing materials and load bearing capacities c. minor structures such as furniture, access ladders, hand rails, refuse or other storage units, signs and lighting d. permanent fences or other means of enclosure. (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the Mayor of London in consultation with the Port of London Authority and the relevant planning authority.
Construction traffic management plan CREWD9 (1) Work No. 11a shall not commence until a traffic management plan (which shall accord with the CoCP) is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with TfL.
Travel plan CREWD10 (1) Work No. 11a shall not commence until a site-specific construction workforce travel plan, which shall accord with the Draft Project Framework Travel Plan, is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The approved travel plan(s) shall be implemented from commencement of Work No. 11a and remain in place for the duration of the construction works, unless otherwise approved by the relevant planning authority in consultation with TfL.
Specification of accesses (construction and operational) CREWD11 (1) No alterations shall be made to any existing access or any new access provided until details of the design, which shall accord with the Access plan (Drawing No. DCO-PP-11X-CREWD-130003) and the design principles for this site, are submitted to and approved by the local highway authority in consultation with the Mayor of London. Any such works shall be completed prior to their use. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the highway authority in consultation with the Mayor of London.
Surface water drainage CREWD12 (1) Construction of the permanent above-ground structures or site restoration scheme shall not commence until details of the surface water drainage system for this site (including means of pollution control, an assessment of the hydrological and hydrogeological context and how the scheme shall be maintained and managed following completion), which shall accord with the design principles for this site, are submitted to and approved by the relevant planning authority in consultation with the Environment Agency. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the Environment Agency, and completed prior to use of the authorised development.
Lighting (operational phase) CREWD13 (1) Use of the authorised development at this site shall not commence until details of the operational lighting, which shall accord with the design principles for this site, are submitted to and approved by the relevant planning authority in consultation with the Port of London Authority. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the Port of London Authority.
Heritage interpretation CREWD14 (1) Prior to completion of the works (save for commissioning) any relevant details applicable to this site from the project wide heritage strategy required by PW11 shall be submitted to and approved by the relevant planning authority. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority.

Chelsea Embankment Foreshore

12

The table below sets out the specific requirements for the Chelsea Embankment Foreshore site—

Title Ref Text
CoCP Part B CHEEF1 Until completion of construction the authorised development shall be carried out in accordance with the CoCP Part A subject to the site specific variations set out in CoCP Part B for this site, unless otherwise agreed with the relevant planning authority in consultation with other relevant stakeholders.
Location of permanent works CHEEF2 (1) The inter-tidal terracing, which includes the permanent river wall, shall not extend beyond the alignment shown on the Site works parameter plan. (2) Should the alignment be less than the maximum extent shown on the Site works parameter plan, details of the amended alignment, which shall accord with the design principles for this site, shall be submitted and approved by the relevant planning authority in consultation with the HBMCE, Port of London Authority and the Environment Agency and thereafter be carried out in accordance with the approved details.
Detailed design approval for river wall and foreshore structure CHEEF3 (1) Construction of the new river wall and terraces shall not commence until details of the design (including external appearance and samples of materials), which shall accord with the design principles for this site and the Site works parameter plan, are submitted to and approved by the relevant planning authority in consultation with the HBMCE and the Environment Agency in respect of land based access to flood defences and potential for ecological enhancements. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE and the Environment Agency.
Detailed design approval for permanent above-ground structures CHEEF4 (1) Construction of any permanent above-ground structure shall not commence until details of the design (including size, external appearances and samples of materials), which shall accord with the design principles for this site and the Site works parameter plan, are submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE.
Protective works to heritage assets CHEEF5 (1) Works to the embankment wall or boundary to Ranelagh Gardens (as relevant) shall not commence until the following details are submitted to and approved by the relevant planning authority in consultation with the HBMCE— works to protect the embankment wall and boundary treatment to Ranelagh Gardens works to remove, store and re-use the parapet, lamp standards and facing materials for the embankment wall and the bricks and railings from the Ranelagh Garden boundary (2) Materials of heritage significance in b above shall be re-used in accordance with the principles set out in Section 3.6 of the Heritage Statement. (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE.
Restoration works to heritage assets CHEEF6 (1) The temporary works platform shall not be removed until details of the works to restore the fabric of the embankment wall including materials are submitted to and approved by the relevant planning authority. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE.
Detailed design approval for signature ventilation columns CHEEF7 (1) Construction of the signature ventilation columns shall not commence until details of the height, dimensions, external appearance and materials, which shall accord with Ventilation column type B (Drawing No. DCO-PP-900-ZZZZZ-290002 – rev 2), are submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The ventilation columns at this site shall not exceed 6 metres in height. (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE.
Landscaping works CHEEF8 (1) Construction of the permanent above-ground structures shall not commence until details of the landscaping works, which shall accord with the indicative features on the Proposed landscape plan (Drawing No. DCO-PP-12X-CHEEF-140010 – rev 1 and DCO-PP-12X-CHEEF-140011 – rev 1), the design principles for this site and the Site works parameter plan, are submitted to and approved by the relevant planning authority in consultation with the HBMCE, TfL (in respect of street trees) and the Environment Agency (in respect of the inter-tidal terraces). (2) Unless otherwise agreed by the relevant planning authority, the landscaping information required in paragraph (1) above shall comprise details of all hard and soft landscaping works including: a. location, quantity, species, size and density of any proposed planting b. cultivation, importation of materials and other operations to ensure plant establishment c. monitoring and maintenance (including any maintenance or restoration of landscaping required after tunnel commissioning) d. proposed finished ground levels e. hard-surfacing materials f. minor structures such as furniture, refuse or other storage units, signs and lighting g. retained historic landscape features and proposals for restoration, where relevant h. a programme for implementation of all landscaping works i. details of fencing/enclosures j. vehicular and pedestrian access, parking and circulation areas, (including details of areas of public access) k. proposed and existing functional services above and below ground, including drainage, power and communications cables and pipelines, manholes and supports l. details of existing trees to be retained (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority, in consultation with the Environment Agency in respect of the inter-tidal terraces. (4) The approved landscaping works shall be carried out by suitably trained or qualified personnel to a reasonable standard in accordance with the relevant recommendations of appropriate British Standards or other recognised codes of good practice. Replacement trees and shrubs (5) If, within a period of five years from the date of the planting of any tree or shrub, that tree or shrub (or any tree or shrub planted to replace it) is uprooted or destroyed or dies, another tree or shrub of the same species and size as that originally planted shall be planted in the same place, unless the relevant planning authority approves any variation.
Temporary works platform CHEEF9 (1) The temporary works platform shall not extend beyond the alignment shown on the Site works parameter plan. (2) Should the alignment be less than the maximum extent shown on the Site works parameter plan, construction of the temporary works platform shall not commence until details of the proposed structure(s) (including additional lengths of cofferdam, temporary decking areas and pontoons) are submitted to and approved by the Port of London Authority in consultation with the Environment Agency.
Contaminated land CHEEF10 Site-specific remediation strategy (1) No works shall be carried out at this site (except for works in the highway including site access, works to trees and installation of monitoring equipment), unless otherwise agreed, until the following are submitted to and approved by the relevant planning authority in consultation with the Environment Agency— a. a preliminary risk assessment and site investigation scheme which identifies— all previous uses potential contaminants associated with those uses a conceptual model of the site indicating sources, pathways and receptors a qualitative risk assessment of any potentially unacceptable risks arising from contamination at the site a proposed site investigation scheme (based on the preliminary risk assessment) providing information for a detailed quantitative assessment of the risk to all receptors that may be affected, including those off-site. b. a remediation strategy which includes— the results of the site investigation a detailed quantitative risk assessment an options appraisal giving full details of the remediation measures required and how they shall be carried out a verification plan providing details of the data to be collected in order to demonstrate that the works set out in the remediation strategy are complete and identifying any requirements for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action a programme for the submission of elements detailed in (3) and (4) below. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Verification report (3) Prior to completion of the works, a verification report demonstrating completion of the works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The report shall include results of sampling and monitoring carried out in accordance with the approved details to demonstrate that the site remediation criteria were met. It shall also include a plan for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action as identified in the verification plan. (4) The long-term monitoring and maintenance plan shall be implemented in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Unexpected contamination (5) If, in carrying out any works on this site, contamination not previously identified is found to be present, then unless otherwise agreed by the relevant planning authority, no further development or works shall be carried out in the part of the site in which the contamination is identified until a remediation strategy is submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority.
Archaeology CHEEF11 (1) No excavation shall be carried out until a SSAWSI (which shall accord with the OAWSI) is submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The authorised development shall be carried out in accordance with the approved details by a suitably qualified person or body.
Construction traffic management plan CHEEF12 (1) Work No. 12a shall not commence until a traffic management plan (which shall accord with the CoCP) is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with TfL.
Travel plan CHEEF13 (1) Work No. 12a shall not commence until a site-specific construction workforce travel plan, which shall accord with the Draft Project Framework Travel Plan, is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The approved travel plan(s) shall be implemented from commencement of Work No. 12a and remain in place for the duration of the construction works, unless otherwise approved by the relevant planning authority in consultation with TfL.
Specification of accesses (construction and operational) CHEEF14 (1) No alterations shall be made to any existing access or any new access provided until details of the design, which shall accord with the design principles for this site, are submitted to and approved by the local highway authority. Any such works shall be completed prior to their use. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the highway authority.
Highway works CHEEF15 (1) Authorised development consisting of construction in or alteration of Chelsea Embankment or the construction or alteration of any highway structures which form part of Chelsea Embankment shall not commence until details of the design are submitted to and approved by the local highway authority. (2) The information required in paragraph (1) above shall include details of any permanent works for a new or altered surface and foul water drainage system for Chelsea Embankment and any permanent works for a new or modified highway lighting scheme for Chelsea Embankment. (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the local highway authority.
Surface water drainage CHEEF16 (1) Construction of the permanent above-ground structures or landscaping shall not commence until details of the surface water drainage system for this site (including means of pollution control, an assessment of the hydrological and hydrogeological context and how the scheme shall be maintained and managed following completion), which shall accord with the design principles for this site, are submitted to and approved by the relevant planning authority in consultation with the Environment Agency. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the Environment Agency, and completed prior to use of the authorised development.
Lighting (operational phase) CHEEF17 (1) Use of the authorised development shall not commence until details of the operational lighting, which shall accord with the design principles for this site, are submitted to and approved by the relevant planning authority in consultation with the HBMCE and the Port of London Authority. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE and the Port of London Authority.
Commissioning works CHEEF18 (1) On or before the completion of the landscaping works approved further to requirement CHEEF8 (landscaping), the undertaker shall give notice to the relevant planning authority. (2) (Save for works carried out in accordance with (5) below) within 1 month of the notice under (1) the undertaker shall: a. remove all hoarding or other temporary enclosure from the site; and b. make the site publically accessible in accordance with the approved landscape scheme. (3) The undertaker shall provide a ‘commissioning notice’ to the relevant planning authority at least 2 months before undertaking any commissioning works. The notice shall include: a. a programme for the commissioning works; and b. a location plan for any fencing or hoarding associated with those works (including identifying areas to be accessible to the public). (4) The undertaker shall provide a ‘commissioning confirmation notice’ 21 days prior to starting the commissioning works, confirming the date of commencement of commissioning. (5) The commissioning works shall be undertaken in accordance with the programme in the commissioning notice and the location plan unless otherwise agreed with the relevant planning authority.

Kirtling Street

13

The table below sets out the specific requirements for the Kirtling Street site—

Title Ref Text
CoCP Part B KRTST1 Until completion of construction the authorised development shall be carried out in accordance with the CoCP Part A subject to the site specific variations set out in CoCP Part B for this site, unless otherwise agreed with the relevant planning authority in consultation with other relevant stakeholders.
Contaminated land KRTST2 Site-specific remediation strategy (1) No works shall be carried out at this site (except for demolition of existing buildings, works in the highway including site access, works to trees and installation of monitoring equipment), unless otherwise agreed, until the following are submitted to and approved by the relevant planning authority in consultation with the Environment Agency— a. a preliminary risk assessment and site investigation scheme which identifies— all previous uses potential contaminants associated with those uses a conceptual model of the site indicating sources, pathways and receptors a qualitative risk assessment of any potentially unacceptable risks arising from contamination at the site a proposed site investigation scheme providing information for a detailed quantitative assessment of the risk to all receptors that may be affected, including those off-site. b. a remediation strategy which includes— a detailed quantitative risk assessment an options appraisal giving full details of the remediation measures required and how they shall be carried out a verification plan providing details of the data to be collected in order to demonstrate that the works set out in the remediation strategy are complete and identifying any requirements for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action a programme for the submission of elements detailed in (3) and (4) below. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Verification report (3) Prior to completion of the works, a verification report demonstrating completion of the works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The report shall include results of sampling and monitoring carried out in accordance with the approved details to demonstrate that the site remediation criteria were met. It shall also include a plan for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action as identified in the verification plan. (4) The long-term monitoring and maintenance plan shall be implemented in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Unexpected contamination (5) If, in carrying out any works on this site, contamination not previously identified is found to be present, then unless otherwise agreed by the relevant planning authority, no further development or works shall be carried out in the part of the site in which the contamination is identified until a remediation strategy is submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority.
Archaeology KRTST3 (1) No excavation shall be carried out until a SSAWSI (which shall accord with the OAWSI) is submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The authorised development shall be carried out in accordance with the approved details by a suitably qualified person or body.
Site restoration (excluding the designated Safeguarded wharf) KRTST4 (1) Construction of the permanent above-ground structures (save for work no. 13b(ii)) shall not commence until details of the landscaping works, which shall accord with the indicative Proposed landscape plan (Drawing No. DCO-PP-13X-KRTST-150008) and the design principles for this site, are submitted to and approved by the relevant planning authority in consultation with the Mayor of London. (2) Unless otherwise agreed by the relevant planning authority, the landscaping information required in paragraph (1) above shall comprise details of all hard and soft landscaping works including: a. location, quantity, species, size and density of any proposed planting b. cultivation, importation of materials and other operations to ensure plant establishment c. monitoring and maintenance (including any maintenance or restoration of landscaping required after tunnel commissioning) d. proposed finished ground levels e. hard-surfacing materials f. minor structures such as furniture, refuse or other storage units, signs and lighting g. retained historic landscape features and proposals for restoration, where relevant h. a programme for implementation of all landscaping works i. details of fencing/enclosures j. vehicular and pedestrian access, parking and circulation areas, (including details of areas of public access) k. proposed and existing functional services above and below ground, including drainage, power and communications cables and pipelines, manholes and supports l. details of existing trees to be retained (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. (4) The approved landscaping works shall be carried out by suitably trained or qualified personnel to a reasonable standard in accordance with the relevant recommendations of appropriate British Standards or other recognised codes of good practice. Replacement trees and shrubs (5) If, within a period of five years from the date of the planting of any tree or shrub, that tree or shrub (or any tree or shrub planted to replace it) is uprooted or destroyed or dies, another tree or shrub of the same species and size as that originally planted shall be planted in the same place, unless the relevant planning authority approves any variation.
Concrete batching plant KRTST5 (1) Construction of Work No. 13b shall not commence until details of the relocated concrete batching plant (Work No. 13b (ii)) relating to scale, layout, materials and lighting are submitted to and approved by the relevant planning authority. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise agreed with the relevant planning authority.
Concrete batching plant KRTST6 (1) Construction of the batching plant shall not commence until a Noise Management Plan, an Air Quality Management Plan, a Dust and Particulates Management Plan and a Delivery Servicing Plan are submitted to and approved by the relevant planning authority in consultation with the Mayor of London. (2) The authorised development shall be constructed and operated in accordance with these approved details, unless otherwise agreed with the relevant planning authority in consultation with the Mayor of London.
Concrete batching plant, Noise Management Plan KRTST7 The Noise Management Plan (submitted further to requirement KRTST6) shall ensure that the concrete batching plant (Work No. 13b (ii)) adopt best practicable means to manage noise and shall include details of hours of working and measures to ensure that while barge off-loading is occurring during night time (between 23—00 and 07—00) the following activities would not occur— aggregate load out from storage bins; use of the cement blowing shed on the jetty, and the operation of the loading shovel. The noise mitigation measures shall include, but not be limited to, that the loading shovel and mixer lorries based at the site should be fitted with “smart” reversing alarm systems which have an audible white noise alarm rather than a standard tonal alarm (and are set at an appropriate agreed level); and the new concrete batching plant and aggregate processing facilities adopt best practices.
Concrete batching plant, Air Quality Management Plan KRTST8 The Air Quality Management Plan for the concrete batching plant (Work No. 13b (ii)) shall include details of all air quality mitigation measures, including details of dust suppression measures and a method of air quality monitoring for fine particles. The air quality mitigation measures shall be retained throughout the operation of the plant.
Concrete batching plant, Dust and Particulates Management Plan KRTST9 The Dust and Particulates Management Plan for the concrete batching plant (Work No. 13b (ii)) shall include details of the prevention of material being tracked out on to the highway; the use of dust suppressants; the full enclosure of all aggregate feed conveyors; the installation of a dust suppression system in the vicinity of the exit from the site; and the use of a road sweeper to clean the local roads.
Concrete batching plant, Delivery Servicing Plan KRTST10 The Delivery Servicing Plan (submitted further to requirement KRTST6) for the concrete batching plant (Work No. 13b (ii)) shall include an emphasis on the increased use of the river to import aggregates and cement; the volumes and types of materials imported and exported; and the capping of the annual HGV movements for the concrete batching plant at 50,000. Details of the annual HGV movements for each calendar year shall be provided to the Council to allow the Council to monitor the number of movements per annum.
Concrete batching plant, Energy Statement KRTST11 1) Work No. 13b (ii)) shall not commence until an Energy Statement for the concrete batching plant is submitted to and approved by the relevant planning authority. The statement shall include details of the measures to reduce carbon emissions from the site. 2) The development shall be implemented and operated in accordance with the approved sustainability and energy measures.
Concrete batching plant, parking scheme KRTST12 1) Work No. 13b (ii)) shall not commence until details of a parking scheme for the concrete batching plant for the provision of three active and one passive electric vehicle charging points, and the provision of two spaces for people with disabilities, is submitted to and approved by the relevant planning authority. 2) The parking scheme shall be implemented in accordance with the approved details.
Concrete batching plant, piling methods KRTST13 Piling or any other foundation designs using penetrative methods relating to construction of the concrete batching plant (Work No. 13b (ii)) shall not be permitted other than with the express written consent of the local planning authority, which may be given for those parts of the site where it has been demonstrated that there is no resultant unacceptable risk to groundwater.
Concrete batching plant, drainage KRTST14 Work No. 13b (ii)) shall not commence until details of foul water drainage have been submitted to and approved by, the relevant planning authority in consultation with the sewerage undertaker. No discharge of foul water from the site shall be accepted into the public system until these drainage works have been completed.
Concrete batching plant, landscape treatment KRTST15 Work No. 13b (ii)) shall not commence until details of the treatment of those parts of the site not covered by plant and buildings, including any parking areas, access ways, landscaping and surface treatment (including the provision of a hard surface across the site that is capable of being kept clean), are submitted to and approved by the relevant planning authority. The development shall be implemented in accordance with the approved details.
Concrete batching plant, visual impact KRTST16 Work No. 13b (ii)) shall not commence until details of measures to mitigate the visual impact of the plant are submitted to and approved by the relevant planning authority. The details should include the potential use of green walls to clad the aggregate storage bins, and the finish to all the on site plant. The development shall be implemented and operated in accordance with the approved details.
Construction traffic management plan KRTST17 (1) Work No. 13a shall not commence until a traffic management plan (which shall accord with the CoCP) is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with TfL.
Travel plan KRTST18 (1) Work No. 13a shall not commence until a site-specific construction workforce travel plan, which shall accord with the Draft Project Framework Travel Plan, is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The approved travel plan(s) shall be implemented from commencement of Work No. 13a and remain in place for the duration of the construction works, unless otherwise approved by the relevant planning authority in consultation with TfL.
Highway works KRTST19 (1) Authorised development consisting of construction in or alteration of Nine Elms Lane (A3205) or the construction or alteration of any highway structures which form part of Nine Elms Lane shall not commence until details of the design are submitted to and approved by the local highway authority. (2) The information required in paragraph 1 above shall include details of any permanent works for a new or altered surface and foul water drainage system for Nine Elms Lane (A3205) and any permanent works for a new or modified highway lighting scheme for Nine Elms Lane. (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the local highway authority.
Specification of accesses (construction and operational) KRTST20 (1) No alterations shall be made to any existing access or any new access provided until details of the design, which shall accord with the design principles for this site, are submitted to and approved by the local highway authority in consultation with the Mayor of London. Any such works shall be completed before use. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the highway authority in consultation with the Mayor of London.
Surface water drainage KRTST21 (1) Construction of the permanent above-ground structures or landscaping (save for work no. 13b(ii)) shall not commence until details of the surface water drainage system for this site (including means of pollution control, an assessment of the hydrological and hydrogeological context and how the scheme shall be maintained and managed following completion), which shall accord with the design principles for this site, are submitted to and approved by the relevant planning authority in consultation with the Environment Agency. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the Environment Agency, and completed prior to use of the authorised development.
Detailed design approval for permanent above-ground structures KRTST22 (1) Construction of any permanent above-ground structure (save for work no. 13b(ii)) shall not commence until details of the design (including size, external appearances and samples of materials), which shall accord with the design principles for this site and the Site works parameter plan, are submitted to and approved by the relevant planning authority in consultation with the Mayor of London. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the Mayor of London.
Kirtling Wharf, Site restoration KRTST23 (1) Use of the authorised development shall not commence until a site restoration scheme for Kirtling Wharf (the area designated by the secretary of state as a Safeguarded Wharf), which shall accord with the design principles for this site, the Site works parameter plan and maintain the viability of the safeguarded wharf for cargo handling in accordance with the London Plan, is submitted to and approved by the Mayor of London, in consultation with the Port of London Authority and the relevant planning authority. (2) The site restoration scheme in paragraph (1) above shall include the following details— a. proposed finished ground levels b. hard-surfacing materials and load bearing capacities c. minor structures such as furniture, access ladders, hand rails, refuse or other storage units, signs and lighting d. permanent fences or other means of enclosure. e. details of a riverside walk (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the Mayor of London in consultation with the Port of London Authority and the relevant planning authority.
Location of above ground structures KRTST24 (1) Construction of any permanent above-ground structures (save for work no. 13b(ii)) shall not commence until the location of the above ground structure which shall accord with the design principles for this site, the Site works parameter plan and maintain the viability of the safeguarded wharf for cargo handling in accordance with the London Plan, is submitted to and approved by the Mayor of London, in consultation with the Port of London Authority and the relevant planning authority. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the Mayor of London, in consultation with the Port of London Authority and the relevant planning authority.

Heathwall Pumping Station

14

The table below sets out the specific requirements for the Heathwall Pumping Station site—

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.