The North Wales Wind Farms Connection Order 2016
- (4) The new trees planted pursuant to this Requirement must be planted and maintained in accordance with the reinstatement planting plan as approved under this Requirement.
Felling
8
- (1) All felling must be undertaken in accordance with the relevant guidance specified in paragraph (2) and NRW best practice (as amended from time to time).
- (2) The relevant guidance is—
- (a) The UK Forestry Standard (“UKFS”);
- (b) UKFS Guidelines – Forests and Water (2011);
- (c) UKFS Guidelines – Forests and Soil (2011);
- (d) UKFS Guidelines – Forests and Biodiversity (2011); and
- (e) UKFS Guidelines – Forests and Historic Environment (2011).
Highway works
9
- (1) No work to construct or alter any permanent or temporary means of access to a highway to be used by vehicular traffic must commence until, following consultation with the relevant highway authority, written details of the design and layout of that means of access has been submitted to and approved by the relevant highway authority.
- (2) The highway accesses must be constructed in accordance with the details approved under sub-paragraph (1).
Construction Hours
10
- (1) Subject to sub-paragraphs (2) and (3), construction work must not take place other than during the core working hours.
- (2) The following operations must only take place between 0900 and 1700 hours Monday to Friday and excluding bank or public holidays—
- (a) piling;
- (b) excavator and hydraulic jack hammer operations; and
- (c) HGV deliveries to and from Broadleys compound.
- (3) The following operations may take place outside the core working hours referred to in sub-paragraph (1)—
- (a) the installation and removal of protective netting across highways or watercourses;
- (b) only at Broadleys compound, the completion of operations commenced during the core working hours which cannot safely be stopped; and
- (c) only at Broadleys compound, start up and close down activities up to one hour either side of core working hours.
- (4) No artificial lighting is to be used in carrying out the construction of the authorised development other than at Broadleys compound.
Contaminated land and groundwater
11
- (1) In the event that contamination is found at any time when carrying out the authorised development, it must be reported in writing immediately to the relevant planning authority and the carrying out of that part of the authorised development affected by such contamination must cease immediately. An investigation and risk assessment must be completed in accordance with a scheme to assess the nature and extent of any contamination within the Order limits and whether or not it originates within the Order limits, such scheme to be submitted to and approved by the relevant planning authority, after consulting with NRW. The investigation and risk assessment must be undertaken by competent persons and a written report of the findings must be produced and submitted to and approved by the relevant planning authority, after consulting with NRW.
- (2) Where remediation is required pursuant to the approved investigation and risk assessment, a detailed remediation scheme to bring the relevant land to a condition suitable for the intended use must be prepared, and submitted for the written approval of the relevant planning authority.
- (3) The approved remediation scheme must be carried out in accordance with its terms.
- (4) Following completion of measures identified in the approved remediation scheme, a verification report that demonstrates the effectiveness of the remediation carried out must be produced, and approved in writing by the relevant planning authority.
- (5) Where the carrying out of any part of the authorised development has ceased pursuant to sub-paragraph (1) the undertaker may only recommence the carrying out of that part of the authorised development following—
- (a) where remediation is required pursuant to the approved investigation and risk assessment for contamination affecting that part, the completion of measures pursuant to sub-paragraph (4); or
- (b) in all other cases the approval of the investigation and risk assessment pursuant to sub-paragraph (2).
Archaeology
12
- (1) No stage of the authorised development is to commence until, following consultation with the Clwyd-Powys Archaeological Trust and the relevant planning authority, for that stage, a written scheme setting out the methodology for a watching brief over areas of archaeological interest has been submitted to and approved by the relevant planning authority.
- (2) The scheme must identify areas where a watching brief is required, and the measures to be taken to protect, record or preserve any significant archaeological remains that may be found.
- (3) Any watching brief carried out under the scheme must be by a suitably qualified person or body approved by the relevant planning authority.
- (4) Any watching brief must be carried out in accordance with the approved scheme.
Construction Environmental Management Plan
13
- (1) No stage of the authorised development is to commence until, following consultation with NRW, the highways authority and the relevant planning authority, a construction environmental management plan for that stage, which is substantially in accordance with the outline construction environmental management plan, has been submitted to and approved by the relevant planning authority, after consulting with NRW. The construction environmental management plan must include measures to minimise impacts of construction works and must include but not be limited to the following plans—
- (a) an ecological management plan including but not limited to method statements for sensitive habitats and species;
- (b) hedgerow management plan including but not limited to principles to be followed for hedgerow removal and reinstatement;
- (c) a traffic management plan including but not limited to the following—
- (i) details of haulage routes for HGVs to use to deliver materials to the authorised development;
- (ii) communication of the routes to drivers of HGVs;
- (iii) details of timing for deliveries;
- (iv) proposals for assessing the existing condition of affected highways; and
- (v) details for making good any incidental damage to highways by construction traffic associated with the authorised development.
- (2) The authorised development must be carried out in accordance with the construction environmental management plan as approved under this Requirement.
Piling
14
- (1) No stage of the authorised development which requires piling activities must commence until a piling method statement for that stage of the authorised development has been submitted to and approved by the relevant planning authority.
- (2) Piling must be carried out in accordance with the approved piling method statement.
Restoration of land used temporarily for construction
15
- (1) No land within the Order limits that is to be used temporarily for construction is to be used until a photographic condition survey has been carried out and submitted to and approved by the relevant planning authority.
- (2) Any land within the Order limits which is used temporarily for construction must be reinstated to its former condition as identified on the photographic condition survey, or such condition as the relevant planning authority may approve, within six months of the date of final commissioning of the authorised development (or such other period as may be agreed with the owner of the land) and the relevant planning authority shall be notified in writing upon reinstatement.
Requirement for written approval
16
Where under any of the above Requirements, the approval or agreement of the relevant planning authority or another person is required, that approval or agreement must be given in writing.
Decommissioning
17
- (1) Not less than 12 months before the date set out in Requirement 19 (expiry of development consent), a decommissioning and site restoration scheme must be submitted to the relevant planning authority for its approval.
- (2) The decommissioning and site restoration scheme must include provision for—
- (a) a timetable for the implementation and completion of the decommissioning and site restoration scheme;
- (b) removal of works 1A and 1B;
- (c) the restoration of the Order land;
- (d) a methodology for the ecological management of sensitive habitats during the decommissioning and restoration works;
- (e) a methodology for the management of traffic during the decommissioning and restoration works; and
- (f) a decommissioning environmental management plan, which is, where relevant to the proposed works, substantially in accordance with the construction environmental management plan approved in accordance with Requirement 13.
- (3) Decommissioning and restoration must be completed in accordance with the approved decommissioning and site restoration scheme within the period set out in the approved scheme.
Decommissioning Environmental Management Plan
18
- (1) No stage of the authorised development is to be decommissioned until, following consultation with NRW, the highways authority and the relevant planning authority, a decommissioning environmental management plan for that stage has been submitted to and approved by the relevant planning authority, after consultating with NRW. The decommissioning environmental management plan must include measures to minimise impacts of decommissining works and must include but not be limited to the following plans—
- (a) an ecological management plan including but not limited to method statements for sensitive habitats and species;
- (b) hedgerow management plan including but not limited to principles to be followed for hedgerow reinstatement;
- (c) a traffic management plan including but not limited to the following—
- (i) details of haulage routes for HGVs to use to deliver materials to or remove materials from the authorised development;
- (ii) communication of the routes to drivers of HGVs;
- (iii) details of timing for deliveries or removals;
- (iv) proposals for assessing the existing condition of affected highways; and
- (v) details for making good any incidental damage to highways by construction traffic associated with decommissioning the authorised development.
- (2) The decommissioning of the authorised development must be carried out in accordance with the decommissioning environmental management plan as approved under this Requirement.
Expiry of development consent
19
The development consent granted by this Order expires 30 years after the date of this Order.
Requirements for written approval, etc.
20
- (1) Where under any of the above Requirements the approval or agreement of the relevant planning authority or any other party is required, that approval or agreement must be provided in writing.
- (2) Where under any of the above Requirements a written scheme is required it shall be accompanied by such illustrations as are necessary and appropriate in the circumstances.
Approved plans and amendments to approved plans.
21
- (1) Where a Requirement requires the authorised development to be carried out in accordance with a plan, scheme, statement, strategy or details (the “plan”) approved by the relevant planning authority, the approved plan must be taken to include any amendments that may be approved subsequently by the relevant planning authority (after consulting every person required to be consulted before approval of the original plan).
- (2) The relevant planning authority must not approve the plan or an amendment to the plan unless it is satisfied that the plan or the amendment is unlikely to give rise to any new or materially different environmental effects from those assessed in the environmental statement.
SCHEDULE 3 — STREETS SUBJECT TO PERMANENT AND TEMPORARY ALTERATION OF LAYOUT
PART 1 — PERMANENT ALTERATION OF LAYOUT
| (1) Area | (2) Street subject to alteration of layout | (3) Description of alteration |
|---|---|---|
| Denbighshire | Access track from Leger Bach | Modify the existing tarmacked track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) between points AZ1/AZ2 and BA to provide temporary access to numbered work 1A during construction. |
| Conwy | Access track from Leger Bach | Modify the existing tarmacked track comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) between points BA to BB to provide temporary access to numbered work 1B during construction. |
| Denbighshire | Lon Llewelyn (A453) | Extend existing access comprising part of numbered work 4 and shown on the access and rights of way plans (sheet 7) between points AQ1 and AQ2 to provide temporary access to numbered work 4 during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Access track from A543 to Broadleys Farm | Modify the existing track comprising part of numbered works 4 and shown on the access and rights of way plans (sheet 7) between points AQ1/2 and AR to provide temporary access to numbered work 4 during construction. |
| Conwy | Henllan to Llannefydd Road | Upgrade existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BY1 and BY2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Access track from Henllan to Llannefydd Road | Modify the existing stoned track comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BY1/2 and BZ to provide temporary access to numbered work 1B during construction. |
| Conwy | Bontnewydd Road | Extend existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CJ1 and CJ2 to provide temporary access to numbered work 1B during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Access track from Bontnewydd Road | Modify the existing stoned track comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CJ1/2 and CK to provide temporary access to numbered work 1B during construction. |
| Conwy | Henllan to Llannefydd Road | Upgrade existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 12) between points CN1 and CN2 to provide temporary access to numbered work 1B during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Access track from Henllan to Llannefydd Road | Modify the existing stoned track comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 12) between points CN1/2 and CQ to provide temporary access to numbered work 1B during construction. |
PART 2 — TEMPORARY ALTERATION OF LAYOUT
| (1) Area | (2) Street subject to alteration of layout | (3) Description of alteration |
|---|---|---|
| Denbighshire | Hafodty Ddu Road | Creation of new southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points A and B to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Hafodty Ddu Road | Creation of new northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points A and B to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Hafodty Ddu Road | Extend existing western access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points C1 and C2 to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Hafodty Ddu Road | Extend existing eastern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points C2 and C3 to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Access track from Hafodty Ddu Road | Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points C1/C2 and D to provide temporary access to numbered work 1A during construction. |
| Denbighshire | Access track from Hafodty Ddu Road | Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points C2/C3 and E to provide temporary access to numbered work 1A during construction. |
| Denbighshire | Hafodty Ddu Road | Creation of new western access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points J and K to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Hafodty Ddu Road | Creation of new eastern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) between points J and K to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Hafodty Ddu Road | Creation of new access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 2) between points L1 and L2 to provide temporary access to numbered work 1A during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Access track from Hafodty Ddu Road | Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 2) between points L1/L2 and M to provide temporary access to numbered work 1A during construction. |
| Denbighshire | Nantglyn to Saron Road (B5435) | Creation of new southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 2) between points P and Q to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Nantglyn to Saron Road (B5435) | Creation of new northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 2) between points P and Q to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Bwlch Road | Extend existing southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 3) between points T2 and U1 to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Bwlch Road | Upgrade existing northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 3) between points T2 and U1 to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Prion Road | Extend existing access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 3) between points X1 and X2 to provide temporary access to numbered work 1A during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Access track off Prion Road | Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 3) between pointsX1/X2 and Y to provide temporary access to numbered work 1A during construction. |
| Denbighshire | Denbigh to Cerrigydrudion Road (B4501) | Extend existing southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 4) between points AB1 and AB2 to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Denbigh to Cerrigydrudion Road (B4501) | Extend existing northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 4) between points AD1 and AD2 to provide temporary access to numbered work 1A during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Access track off Denbigh to Cerrigydrudion Road (B4501) | Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 4) between pointsAD1/AD2 and AE to provide temporary access to numbered work 1A during construction. |
| Denbighshire | Denbigh to Nantglyn Road | Creation of new access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 5) between points AH1 and AH2 to provide temporary access to numbered work 1A during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Access track off Denbigh to Nantglyn Road | Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 5) between points AH1/AH2 and AI to provide temporary access to numbered work 1A during construction. |
| Denbighshire | Denbigh to Nantglyn Road | Creation of new access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 5) between points AJ and AK to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Ffordd Gwaenynog (Bodeiliog Road) | Extend existing eastern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) between points AO and AP to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Ffordd Gwaenynog (Bodeiliog Road) | Upgrade existing western access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) between points AO and AP to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Lon Llewelyn (A543) | Extend existing southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) between points AU2 and AV to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Lon Llewelyn (A543) | Extend existing southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) between points AV and AW to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Lon Llewelyn (A543) | Creation of new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) between points AU2 and AV to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Lon Llewelyn (A543) | Creation of new northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) between points AV and AW to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Access track from Lon Llewelyn (A543) | Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) between points AX1/AX2 and AY to provide temporary access to numbered work 1A during construction. |
| Denbighshire | Access track from Leger Bach | Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) between points BC and BB to provide temporary access to numbered work 1A during construction. |
| Conwy | Access track from Leger Bach | Creation of temporary stoned track comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) between points BB and BD to provide temporary access to numbered work 1B during construction. |
| Denbighshire | Access track from Leger Bach | Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) between points BD and BE to provide temporary access to numbered work 1A during construction. |
| Conwy | Henllan to Groes Road (B5428) | Creation of new southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 8) between points BH and BI2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Henllan to Groes Road (B5428) | Creation of new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 8) between points BH and BI2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Eriviat Bach Road | Creation of new southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 8) between points BJ and BK2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Eriviat Bach Road | Creation of new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 8) between points BJ and BK2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Henllan to Llansannan Road (B5382) | Creation of new southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 9) between points BN2 and BO to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Henllan to Llansannan Road (B5382) | Extend existing northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 9) between points BN2 and BO to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Henllan to Cefn Berain Road | Extend existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BR1 and BR2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Access track from Henllan to Cefn Berain Road | Creation of temporary stoned track comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BR1/BR2 and BS to provide temporary access to numbered work 1B during construction. |
| Conwy | Henllan to Cefn Berain Road | Extend existing southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BT2 and BU to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Henllan to Cefn Berain Road | Extend existing northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BT2 and BU to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Cefn Berain to Bontnewydd Road | Extend existing southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BV and BW2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Cefn Berain to Bontnewydd Road | Creation of new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points BV and BW2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Henllan to Llannefydd Road | Creation of new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) between points CD1 and CD2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Henllan to Llannefydd Road | Upgrade existing eastern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CB2 and CE1 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Henllan to Llannefydd Road | Extend existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CB1 and CA1 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Bontnewydd Road | Upgrade existing southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CF and CG to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Bontnewydd Road | Upgrade existing northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CF and CG to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Conwy | Bontnewydd Road | Extend existing northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) between points CH and CI2 to provide temporary access to numbered work 1B during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Groesffordd Marli to Cefn Meiriadog Road | Creation of new southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 13) between points CR and CS to provide temporary access to numbered work 1A during construction. |
| Denbighshire | Groesffordd Marli to Cefn Meiriadog Road | Extend existing northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 13) between points CR and CS to provide temporary access to numbered work 1A during construction. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Groesffordd Marli to Glascoed Road | Extend existing access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 13) between points CT1 and CT2 to provide temporary access to numbered work 1A during construction and for maintenance. Comprising, where required, of the installation of new or improved street surface, white lining, removal of vegetation including hedgerows and replacement of vegetation including hedgerows. |
| Denbighshire | Access track from Groesffordd Marli to Glascoed Road | Creation of temporary stoned track comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 13) between points CT1/CT2 and CU to provide temporary access to numbered work 1A during construction. |
SCHEDULE 4 — STREETS SUBJECT TO STREET WORKS
| (1) Area | (2) Street subject to street works |
|---|---|
| Denbighshire | Hafodty Ddu Road |
| Denbighshire | Access tracks off Hafodty Ddu Road |
| Denbighshire | Nantglyn to Saron Road (B5435) |
| Denbighshire | Bwlch Road |
| Denbighshire | Prion Road |
| Denbighshire | Access track off Prion Road |
| Denbighshire | Denbigh to Cerrigydrudion Road (B4501) |
| Denbighshire | Access track off Denbigh to Cerrigydrudion Road (B4501) |
| Denbighshire | Denbigh to Nantglyn Road |
| Denbighshire | Access track off Denbigh to Nantglyn Road |
| Conwy | Ffordd Gwaenynog (Bodeiliog Road) |
| Conwy | Lon Llewelyn (A543) |
| Denbighshire | Lon Llewelyn (A543) |
| Conwy | Access tracks off Lon Llewelyn (A543) |
| Denbighshire | Access tracks off Lon Llewelyn (A543) |
| Denbighshire | Access track off Lon Llewelyn (A543) to Broadleys Farm |
| Conwy | Henllan to Groes Road (B5428) |
| Conwy | Eriviat Bach Road |
| Conwy | Henllan to Llansannan Road (B5382) |
| Conwy | Henllan to Cefn Berain Road |
| Conwy | Access track off Henllan to Cefn Berain Road |
| Conwy | Cefn Berain to Bontnewydd Road |
| Conwy | Henllan to Llannefydd Road |
| Conwy | Access track off Henllan to Cefn Berain Road |
| Conwy | Bontnewydd Road |
| Conwy | Access track off Henllan to Llannefydd Road |
| Denbighshire | Groesffordd Marli to Cefn Meiriadog Road |
| Denbighshire | Groesffordd Marli to Glascoed Road |
| Denbighshire | Access track off Groesffordd Marli to Glascoed Road |
SCHEDULE 5 — ACCESS
PART 1 — THOSE PARTS OF ACCESSES TO BE MAINTAINED AT THE EXPENSE OF THE UNDERTAKER
| (1) Area | (2) Street | (3) Description of relevant part of access |
|---|---|---|
| Denbighshire | Hafodty Ddu Road | The new southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) hatched green between points A and B. |
| Denbighshire | Hafodty Ddu Road | The new northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) hatched green between points A and B. |
| Denbighshire | Hafodty Ddu Road | The extension of the existing western access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) hatched green between points C1 and C2. |
| Denbighshire | Hafodty Ddu Road | The extension of the existing eastern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) hatched green between points C2 and C3. |
| Denbighshire | Hafodty Ddu Road | The new western access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) hatched green between points J and K. |
| Denbighshire | Hafodty Ddu Road | The new eastern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 1) hatched green between points J and K. |
| Denbighshire | Hafodty Ddu Road | The new access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 2) hatched green between points L1 and L2. |
| Denbighshire | Nantglyn to Saron Road (B5435) | The new southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 2) hatched green between points P and Q. |
| Denbighshire | Nantglyn to Saron Road (B5435) | The new northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 2) hatched green between points P and Q. |
| Denbighshire | Bwlch Road | The extension of existing southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 3) hatched green between points T2 and U1. |
| Denbighshire | Bwlch Road | The upgrade of existing northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 3) hatched green between points T2 and U1. |
| Denbighshire | Prion Road | The extension of an existing access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 3) hatched green between points X1 and X2. |
| Denbighshire | Denbigh to Cerrigydrudion Road (B4501) | The extension of the existing southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 4) hatched green between points AB1 and AB2. |
| Denbighshire | Denbigh to Cerrigydrudion Road (B4501) | The extension of the existing northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 4) hatched green between points AD1 and AD2. |
| Denbighshire | Denbigh to Nantglyn Road | The new access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 5) hatched green between points AH1 and AH2. |
| Denbighshire | Denbigh to Nantglyn Road | The new access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 5) hatched green between points AJ and AK. |
| Conwy | Ffordd Gwaenynog (Bodeiliog Road) | The extension of the existing eastern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) hatched blue between points AO and AP. |
| Conwy | Ffordd Gwaenynog (Bodeiliog Road) | The upgrade of the existing western access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) hatched blue between points AO and AP. |
| Conwy | Lon Llewelyn (A543) | The extension of the existing southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) hatched blue between points AU2 and AV. |
| Conwy | Lon Llewelyn (A543) | The new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 6) hatched blue between points AU2 and AV. |
| Denbighshire | Lon Llewelyn (A543) | The extension of the existing southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) hatched green between points AV and AW. |
| Denbighshire | Lon Llewelyn (A543) | The new northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 6) hatched green between points AV and AW. |
| Denbighshire | Lon Llewelyn (A543) | The extension of the existing access comprising part of numbered works 4 and shown on the access and rights of way plans (sheet 7) hatched green between points AQ1 and AQ2. |
| Conwy | Henllan to Groes Road (B5428) | The new southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 8) hatched blue between points BH and BI2. |
| Conwy | Henllan to Groes Road (B5428) | The new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 8) hatched blue between points BH and BI2. |
| Conwy | Eriviat Bach Road | The new southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 8) hatched blue between points BJ and BK2. |
| Conwy | Eriviat Bach Road | The new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 8) hatched blue between points BJ and BK2. |
| Conwy | Henllan to Llansannan Road (B5382) | The new southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 9) hatched blue between points BN2 and BO. |
| Conwy | Henllan to Llansannan Road (B5382) | The extension of the existing northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 9) hatched blue between points BN2 and BO. |
| Conwy | Henllan to Cefn Berain Road | The extension of the existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) hatched blue between points BR1 and BR2. |
| Conwy | Henllan to Cefn Berain Road | The extension of the existing southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) hatched blue between points BT2 and BU. |
| Conwy | Henllan to Cefn Berain Road | The extension of the existing northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) hatched blue between points BT2 and BU. |
| Conwy | Cefn Berain to Bontnewydd Road | The extension of the existing southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) hatched blue between points BV and BW2. |
| Conwy | Cefn Berain to Bontnewydd Road | The new northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) hatched blue between points BV and BW2. |
| Conwy | Henllan to Llannefydd Road | The upgrade to existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) hatched blue between points BY1 and BY2. |
| Conwy | Henllan to Llannefydd Road | The new access north comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 10) hatched blue between points CD1 and CD2. |
| Conwy | Henllan to Llannefydd Road | The upgrade to existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) hatched blue between points CB2 and CE1. |
| Conwy | Henllan to Llannefydd Road | The extension of the existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) hatched blue between points CB1 and CA1. |
| Conwy | Bontnewydd Road | The upgrade to existing southern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) hatched blue between points CF and CG. |
| Conwy | Bontnewydd Road | The upgrade to existing northern access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) hatched blue between points CF and CG. |
| Conwy | Bontnewydd Road | The extension of the existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) hatched blue between points CH and CI2. |
| Conwy | Bontnewydd Road | The extension of the existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 11) hatched blue between points CJ1 and CJ2. |
| Conwy | Henllan to Llannefydd Road | The upgrade to existing access comprising part of numbered works 2B and shown on the access and rights of way plans (sheet 12) hatched blue between points CN1 and CN2. |
| Denbighshire | Groesffordd Marli to Cefn Meiriadog Road | The new southern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 13) hatched green between points CR and CS. |
| Denbighshire | Groesffordd Marli to Cefn Meiriadog Road | The extension of the existing northern access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 13) hatched green between points CR and CS. |
| Denbighshire | Groesffordd Marli to Glascoed Road | The extension of the existing access comprising part of numbered works 2A and shown on the access and rights of way plans (sheet 13) hatched green between points CT1 and CT2. |
PART 2 — THOSE WORKS TO RESTORE TEMPORARY ACCESSES WHICH WILL BE MAINTAINED AT THE PUBLIC EXPENSE
| (1) Location | (2) Street | (3) Description of relevant part of access |
|---|---|---|
| Denbighshire | Hafodty Ddu Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 1) hatched green between points A and B following the completion and installation of numbered work 1A. |
| Denbighshire | Hafodty Ddu Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 1) hatched green between points A and B following the completion and installation of numbered work 1A. |
| Denbighshire | Hafodty Ddu Road | The restoration works restoring the western access shown on the access and rights of way plans (sheet 1) hatched green between points C1 and C2 following the completion and installation of numbered work 1A. |
| Denbighshire | Hafodty Ddu Road | The restoration works restoring the eastern access shown on the access and rights of way plans (sheet 1) hatched green between points C2 and C3 following the completion and installation of numbered work 1A. |
| Denbighshire | Hafodty Ddu Road | The restoration works restoring the western access shown on the access and rights of way plans (sheet 1) hatched green between points J and K following the completion and installation of numbered work 1A. |
| Denbighshire | Hafodty Ddu Road | The restoration works restoring the eastern access shown on the access and rights of way plans (sheet 1) hatched green between points J and K following the completion and installation of numbered work 1A. |
| Denbighshire | Hafodty Ddu Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 2) hatched green between points L1 and L2 following the completion and installation of numbered work 1A. |
| Denbighshire | Nantglyn to Saron Road (B5435) | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 2) hatched green between points P and Q following the completion and installation of numbered work 1A. |
| Denbighshire | Nantglyn to Saron Road (B5435) | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 2) hatched green between points P and Q following the completion and installation of numbered work 1A. |
| Denbighshire | Bwlch Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 3) hatched green between points T2 and U1 following the completion and installation of numbered work 1A. |
| Denbighshire | Bwlch Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 3) hatched green between points T2 and U1 following the completion and installation of numbered work 1A. |
| Denbighshire | Prion Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 3) hatched green between points X1 and X2 following the completion and installation of numbered work 1A. |
| Denbighshire | Denbigh to Cerrigydrudion Road (B4501) | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 4) hatched green between points AB1 and AB2 following the completion and installation of numbered work 1A. |
| Denbighshire | Denbigh to Cerrigydrudion Road (B4501) | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 4) hatched green between points AD1 and AD2 following the completion and installation of numbered work 1A. |
| Denbighshire | Denbigh to Nantglyn Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 5) hatched green between points AH1 and AH2 following the completion and installation of numbered work 1A. |
| Denbighshire | Denbigh to Nantglyn Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 5) hatched green between points AJ and AK following the completion and installation of numbered work 1A. |
| Conwy | Ffordd Gwaenynog (Bodeiliog Road) | The restoration works restoring the eastern access shown on the access and rights of way plans (sheet 6) hatched blue between points AO and AP following the completion and installation of numbered work 1B. |
| Conwy | Ffordd Gwaenynog (Bodeiliog Road) | The restoration works restoring the western access shown on the access and rights of way plans (sheet 6) hatched blue between points AO and AP following the completion and installation of numbered work 1B. |
| Conwy | Lon Llewelyn (A543) | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 6) hatched blue between points AU2 and AV following the completion and installation of numbered work 1B. |
| Conwy | Lon Llewelyn (A543) | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 6) hatched blue between points AU2 and AV following the completion and installation of numbered work 1B. |
| Denbighshire | Lon Llewelyn (A543) | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 6) hatched green between points AV and AW following the completion and installation of numbered work 1A. |
| Denbighshire | Lon Llewelyn (A543) | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 6) hatched green between points AV and AW following the completion and installation of numbered work 1A. |
| Conwy | Henllan to Groes Road (B5428) | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 8) hatched blue between points BH and BI2 following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Groes Road (B5428) | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 8) hatched blue between points BH and BI2 following the completion and installation of numbered work 1B. |
| Conwy | Eriviat Bach Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 8) hatched blue between points BJ and BK2 following the completion and installation of numbered work 1B. |
| Conwy | Eriviat Bach Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 8) hatched blue between points BJ and BK2 following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Llansannan Road (B5382) | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 9) hatched blue between points BN2 and BO following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Llansannan Road (B5382) | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 9) hatched blue between points BN2 and BO following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Cefn Berain Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 10) hatched blue between points BR1 and BR2 following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Cefn Berain Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 10) hatched blue between points BT2 and BU following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Cefn Berain Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 10) hatched blue between points BT2 and BU following the completion and installation of numbered work 1B. |
| Conwy | Cefn Berain to Bontnewydd Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 10) hatched blue between points BV and BW2 following the completion and installation of numbered work 1B. |
| Conwy | Cefn Berain to Bontnewydd Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 10) hatched blue between points BV and BW2 following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Llannefydd Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 10) hatched blue between points CD1 and CD2 following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Llannefydd Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 11) hatched blue between points CB2 and CE1 following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Llannefydd Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 11) hatched blue between points CB1 and CA1 following the completion and installation of numbered work 1B. |
| Conwy | Bontnewydd Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 11) hatched blue between points CF and CG following the completion and installation of numbered work 1B. |
| Conwy | Bontnewydd Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 11) hatched blue between points CF and CG following the completion and installation of numbered work 1B. |
| Conwy | Bontnewydd Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 11) hatched blue between points CH and CI2 following the completion and installation of numbered work 1B. |
| Denbighshire | Groesffordd Marli to Cefn Meiriadog Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 13) hatched green between points CR and CS following the completion and installation of numbered work 1A. |
| Denbighshire | Groesffordd Marli to Cefn Meiriadog Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 13) hatched green between points CR and CS following the completion and installation of numbered work 1A. |
| Denbighshire | Groesffordd Marli to Glascoed Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 13) hatched green between points CT1 and CT2 following the completion and installation of numbered work 1A. |
PART 3 — THOSE WORKS TO RESTORE TEMPORARY ACCESSES WHICH WILL BE MAINTAINED BY THE STREET AUTHORITY
| (1) Area | (2) Street | (3) Description of the relevant part of access |
|---|---|---|
| Denbighshire | Hafodty Ddu Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 1) hatched red between points A and B following the completion and installation of numbered work 1A. |
| Denbighshire | Hafodty Ddu Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 1) hatched red between points A and B following the completion and installation of numbered work 1A. |
| Denbighshire | Access track from Hafodty Ddu Road | The restoration works restoring the western access shown on the access and rights of way plans (sheet 1) hatched red between points C1/C2 and D following the completion and installation of numbered work 1A. |
| Denbighshire | Access track from Hafodty Ddu Road | The restoration works restoring the eastern access shown on the access and rights of way plans (sheet 1) hatched red between points C2/C3 and E following the completion and installation of numbered work 1A. |
| Denbighshire | Hafodty Ddu Road | The restoration works restoring the western access shown on the access and rights of way plans (sheet 2) hatched red between points J and K following the completion and installation of numbered work 1A. |
| Denbighshire | Hafodty Ddu Road | The restoration works restoring the eastern access shown on the access and rights of way plans (sheet 2) hatched red between points J and K following the completion and installation of numbered work 1A. |
| Denbighshire | Access track from Hafodty Ddu Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 2) hatched red between points L1/L2 and M following the completion and installation of numbered work 1A. |
| Denbighshire | Nantglyn to Saron Road (B5435) | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 2) hatched red between points P and Q following the completion and installation of numbered work 1A. |
| Denbighshire | Nantglyn to Saron Road (B5435) | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 2) hatched red between points P and Q following the completion and installation of numbered work 1A. |
| Denbighshire | Bwlch Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 3) hatched red between points T2 and U1 following the completion and installation of numbered work 1A. |
| Denbighshire | Bwlch Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 3) hatched red between points T2 and U1 following the completion and installation of numbered work 1A. |
| Denbighshire | Access track from Hafodty Ddu Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 3) hatched red between points X1/X2 and Y following the completion and installation of numbered work 1A. |
| Denbighshire | Denbigh to Cerrigydrudion Road (B4501) | The restoration works restoring the access shown on the access and rights of way plans (sheet 4) hatched red between points AB1 and AB2 following the completion and installation of numbered work 1A. |
| Denbighshire | Access track from Denbigh to Cerrigydrudion Road (B4501) | The restoration works restoring the access shown on the access and rights of way plans (sheet 4) hatched red between points AD1/AD2 and AE following the completion and installation of numbered work 1A. |
| Denbighshire | Access track from Denbigh to Nantglyn Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 5) hatched red between points AH1/AH2 and AI following the completion and installation of numbered work 1A. |
| Denbighshire | Denbigh to Nantglyn Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 5) hatched red between points AJ and AK following the completion and installation of numbered work 1A. |
| Conwy | Ffordd Gwaenynog (Bodeiliog Road) | The restoration works restoring the eastern access shown on the access and rights of way plans (sheet 6) hatched pink between points AO and AP following the completion and installation of numbered work 1B. |
| Conwy | Ffordd Gwaenynog (Bodeiliog Road) | The restoration works restoring the western access shown on the access and rights of way plans (sheet 6) hatched pink between points AO and AP following the completion and installation of numbered work 1B. |
| Denbighshire | Lon Llewelyn (A543) | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 6) hatched red between points AU2 and AW following the completion and installation of numbered work 1A. |
| Denbighshire | Lon Llewelyn (A543) | The restoration works restoring the access shown on the access and rights of way plans (sheet 6) hatched red between points AV and AW following the completion and installation of numbered work 1A. |
| Conwy | Lon Llewelyn (A543) | The restoration works restoring the access shown on the access and rights of way plans (sheet 6) hatched pink between points AU2 and AV following the completion and installation of numbered work 1B. |
| Denbighshire | Access track from Lon Llewelyn (A543) | The restoration works restoring the access shown on the access and rights of way plans (sheet 6) hatched red between points AX1/AX2 and AY following the completion and installation of numbered work 1A. |
| Denbighshire | Access track from Leger Bach | The restoration works restoring the access shown on the access and rights of way plans (sheet 6) hatched red between points BC and BB following the completion and installation of numbered work 1A. |
| Conwy | Access track from Leger Bach | The restoration works restoring the access shown on the access and rights of way plans (sheet 6) hatched pink between points BB and BD following the completion and installation of numbered work 1B. |
| Denbighshire | Access track from Leger Bach | The restoration works restoring the access shown on the access and rights of way plans (sheet 6) hatched red between points BD and BE following the completion and installation of numbered work 1A. |
| Conwy | Henllan to Groes Road (B5428) | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 8) hatched pink between points BH and BI2 following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Groes Road (B5428) | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 8) hatched pink between points BH and BI2 following the completion and installation of numbered work 1B. |
| Conwy | Eriviat Bach Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 8) hatched pink between points BJ and BK2 following the completion and installation of numbered work 1B. |
| Conwy | Eriviat Bach Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 8) hatched pink between points BJ and BK2 following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Llansannan Road (B5382) | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 9) hatched pink between points BN2 and BO following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Llansannan Road (B5382) | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 9) hatched pink between points BN2 and BO following the completion and installation of numbered work 1B. |
| Conwy | Access track from Henllan to Cefn Berain Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 10) hatched pink between points BR1/BR2 and BS following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Cefn Berain Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 10) hatched pink between points BT2 and BU following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Cefn Berain Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 10) hatched pink between points BT2 and BU following the completion and installation of numbered work 1B. |
| Conwy | Cefn Berain to Bontnewydd Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 10) hatched pink between points BV and BW2 following the completion and installation of numbered work 1B. |
| Conwy | Cefn Berain to Bontnewydd Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 10) hatched pink between points BV and BW2 following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Llannefydd Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 10) hatched pink between points CD1 and CD2 following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Llannefydd Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 11) hatched pink between points CB2 and CE1 following the completion and installation of numbered work 1B. |
| Conwy | Henllan to Llannefydd Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 11) hatched pink between points CB1 and CA1 following the completion and installation of numbered work 1B. |
| Conwy | Bontnewydd Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 11) hatched pink between points CF and CG following the completion and installation of numbered work 1B. |
| Conwy | Bontnewydd Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 11) hatched pink between points CF and CG following the completion and installation of numbered work 1B. |
| Conwy | Bontnewydd Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 11) hatched pink between points CH and CI2 following the completion and installation of numbered work 1B. |
| Denbighshire | Groesffordd Marli to Cefn Meiriadog Road | The restoration works restoring the southern access shown on the access and rights of way plans (sheet 13) hatched red between points CR and CS following the completion and installation of numbered work 1A. |
| Denbighshire | Groesffordd Marli to Cefn Meiriadog Road | The restoration works restoring the northern access shown on the access and rights of way plans (sheet 13) hatched red between points CR and CS following the completion and installation of numbered work 1A. |
| Denbighshire | Access track from Groesffordd Marli to Cefn Meiriadog Road | The restoration works restoring the access shown on the access and rights of way plans (sheet 13) hatched red between points CT1/CT2 to CU following the completion and installation of numbered work 1A. |
PART 4 — THOSE PARTS OF ACCESSES TO BE MAINTAINED BY THE STREET AUTHORITY
| (1) Area | (2) Street | (3) Description of the relevant part of access |
|---|---|---|
| Denbighshire | Access track from Leger Bach | The modified existing tarmacked track shown on the access and rights of way plans (sheet 6) hatched red between points AZ1/AZ2 to BA following the cessation of its use for the construction of numbered work 1A. |
| Conwy | Access track from Leger Bach | The modified existing tarmacked track shown on the access and rights of way plans (sheet 6) hatched pink between points BA to BB following the cessation of its use for the construction of numbered work 1B. |
| Denbighshire | Access track from A543 to Broadleys Farm | The modified existing track shown on the access and rights of way plans (sheet 7) hatched red between points AQ1/AQ2 to AR following the cessation of its use for the construction of numbered work 1A. |
| Conwy | Access track from Henllan to Llannefydd Road | The modified existing stoned track shown on the access and rights of way plans (sheet 10) hatched pink between points BY1/BY2 and BZ following the cessation of its use for the construction of numbered work 1B. |
| Conwy | Access track from Bontnewydd Road | The modified existing stoned track shown on the access and rights of way plans (sheet 11) hatched pink between points CJ1/CJ2 and CK following the cessation of its use for the construction of numbered work 1B. |
| Conwy | Access track from Henllan to Llannefydd Road | The modified existing stoned track shown on the access and rights of way plans (sheet 12) hatched pink between points CN1/CN2 and CQ following the cessation of its use for the construction of numbered work 1B. |
SCHEDULE 6 — TEMPORARY PROHIBITION OR RESTRICTION OF THE USE OF STREETS OR PUBLIC RIGHTS OF WAY
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.