The Triton Knoll Electrical System Order 2016
Work No. 19 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 17 in a generally south westerly direction for a distance of 2.3 kilometres to Work No. 21 including accesses for construction from the public highway and temporary haul roads;
Work No. 20 – a temporary construction compound to the south side of Station Road including access from the public highway;
Work No. 21 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 19 in a generally south westerly direction for a distance of 2.5 kilometres to Work No. 22 including accesses for construction from the public highway and temporary haul roads;
Work No. 22 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 21 in a generally south westerly direction for a distance of 4.4 kilometres to Work No. 24 including accesses for construction from the public highway and temporary haul roads;
Work No. 23 – a temporary construction compound to the east side of Hobhole Bank including access from the public highway;
Work No. 24 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 22 in a generally south westerly direction for a distance of 1.3 kilometres to Work No. 26 including accesses for construction from the public highway and temporary haul roads;
Work No. 25 – a temporary construction compound to the north side of Fodder Dike including access from the public highway;
Work No. 26 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 24 in a generally south-south westerly direction for a distance of 4.3 kilometres to Work No. 29 including accesses for construction from the public highway and temporary haul roads;
Work No. 27 – a temporary construction compound to the east side of the A16 highway including access from the public highway;
Work No. 28 – a temporary construction compound to the west side of the A16 highway including access from the public highway;
Work No. 29 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 26 in a generally south westerly direction for a distance of 3.6 kilometres to Work No. 31 including accesses for construction from the public highway and temporary haul roads;
Work No. 30 – a temporary construction compound to the west side of Staunt Road including access from the public highway;
Work No. 31 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 29 in a generally south westerly direction for a distance of 1 kilometre to Work No. 33 including accesses for construction from the public highway and temporary haul roads;
Work No. 32 – a temporary construction compound to the east side of Carrington Road including access from the public highway;
Work No. 33 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 31 in a generally south-south westerly direction for a distance of 5 kilometres to Work No. 37 including accesses for construction from the public highway and temporary haul roads;
Work No. 34 – a temporary construction compound to the north side of Leagate Road including access from the public highway;
Work No. 35 – a temporary construction compound to the north side of Mere Booth Road including access from the public highway;
Work No. 36 – a temporary construction compound to the south side of Mere Booth Road including access from the public highway;
In the County of Lincolnshire, Borough of Boston
Work No. 37 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 33 in a generally south westerly direction for a distance of 2.3 kilometres to Work No. 39 including accesses for construction from the public highway and temporary haul roads;
PART 2 — Ancillary works
Works and operations within the Order limits and which fall within the scope of the work assessed by the environmental statement comprising—
- (a) temporary landing places, moorings or other means of accommodating vessels in the construction or maintenance of the authorised development;
- (b) temporary or permanent buoys, beacons, fenders and other navigational warning or ship impact protection works;
- (c) temporary works for the protection of land or structures affected by the authorised development;
- (d) cable route preparation works including grapnel runs and pre-lay jetting; and
- (e) the removal, reconstruction or alteration of the position of subsea cables.
PART 3 — Requirements
Interpretation
1
In this Part—
- “above-ground infrastructure” means the buildings, busbars, capacitors, reactors, reactive power compensation equipment, filters, cooling equipment, control and welfare buildings, lightning rods, security fencing and other associated equipment, structures and buildings including noise-attenuation panels required for the intermediate electrical compound and the substation compound (Work No. 50A);
- “AIS” means air-insulated switchgear;
- “AOD” means above ordnance datum;
- “GIS” means gas-insulated switchgear;
- “stage” means one of the following 28 stages of the onshore works— the IEC enabling works (using the temporary construction compound at Work No. 10); the substation enabling works (using the temporary construction compound at Work No. 51); Work Nos. 3 and 4 including Work Nos. 3A and 3B (using the temporary construction compound at Work No. 3B); Work No. 5 (using the temporary construction compound at Work No. 6); Work No. 8 (using the temporary construction compound at Work No. 7); Work No. 9 excluding the IEC enabling works and Work No. 9A (using the temporary construction compound at Work No. 10); Work No. 9A (using the temporary construction compound at Work No. 10); Work No. 11 (using the temporary construction compound at Work No. 12); Work No. 14 (using the temporary construction compounds at Work Nos. 13 and 15); Work No. 17 (using the access at Work No. 16); Work No. 19 (using the temporary construction compound at Work No. 18); Work No. 21 (using the temporary construction compound at Work No. 20); Work No. 22 (using the temporary construction compound at Work No. 23); Work No. 24 (using the temporary construction compound at Work No. 25); Work No. 26 (using the temporary construction compounds at Work Nos. 27 and 28); Work No. 29 (using the temporary construction compound at Work No. 30); Work No. 31 (using the temporary construction compound at Work No. 32); Work No. 33 (using the temporary construction compounds at Work Nos. 34, 35 and 36); Work No. 37 (using the temporary construction compound at Work No. 38); Work No. 39 (using the temporary construction compounds at Work Nos. 40 and 41); Work No. 42 (using the temporary construction compound at Work No. 43); Work No. 44 (using the temporary construction compound at Work No. 45); Work No. 46 (using the temporary construction compound at Work No. 47A or 51 and access at Work No. 48); Work Nos. 48 and 49 (using the temporary construction compound at Work No. 47A); Work No. 50 excluding the substation enabling works and Work No. 50A (using the temporary construction compound at Work No. 51); Work No. 50A (using the temporary construction compound at Work No. 51); Work No. 52 (using the temporary construction compound at Work No. 53); Work No. 55 (using the temporary construction compound at Work No. 53),
or such other stage of the onshore works agreed in writing with the relevant planning authority.
Time limit for commencing authorised development
2
The authorised development must be commenced on or before 26th September 2021.
Detailed offshore design parameters
3
- (1) The total number of cables comprising Work No. 1 must not exceed 6.
- (2) The total length of the cables comprising Work No. 1 must not exceed 396 kilometres.
- (3) The total amount of cable protection for the cables comprising Work No. 1 must not exceed 367,200 square metres and 320,760 cubic metres.
- (4) The finished height of any cable protection must not exceed 10% of the navigable water depth existing before works commence unless otherwise agreed in writing in advance with the MMO and the MCA.
Offshore decommissioning
4
No part of the development seaward of MHWS may be commenced until a written decommissioning programme in compliance with any notice served on the undertaker by the Secretary of State under section 105(2) of the Energy Act 2004[^f00039] has been submitted to the Secretary of State for approval.
Detailed design onshore
5
- (1) The IEC enabling works and the substation enabling works must not be commenced until details of the ground-raising and stoned site platform have been submitted to and approved by the relevant planning authority.
- (2) No part of Work No. 9A may be commenced until details of the layout, scale and external appearance of the above-ground infrastructure including permanent fencing relating to Work No. 9A have been submitted to and approved by the relevant planning authority.
- (3) No part of Work No. 50A may be commenced until—
- (a) details of the layout, scale and external appearance of the above-ground infrastructure including permanent fencing relating to Work No. 50A have been submitted to and approved by the relevant planning authority; and
- (b) the undertaker has notified the relevant planning authority whether AIS or GIS is to be installed for Work No. 50A.
- (4) Any details provided by the undertaker under paragraphs (2) and (3) must, where relevant to that stage, be in accordance with the design principles document.
- (5) Finished floor levels for Work Nos. 9A and 50A must, after consultation with the Environment Agency, be based on the results of topographic surveys.
- (6) In relation to Work No. 3A—
- (a) the total area in which the landfall transition joint bays may be contained must not exceed 20,288 square metres;
- (b) the total area of land raising must not exceed 5,000 square metres; and
- (c) the total number of landfall transition joint bays must not exceed 6.
- (7) In relation to Work No. 9A—
- (a) the highest part of any building must not exceed 16.54 metres AOD;
- (b) the highest part of any external electrical equipment, excluding lightning rods, must not exceed 14.04 metres AOD;
- (c) the total number of lightning rods within the fenced compound must not exceed 4 and the height of any lightning rod must not exceed 21.54 metres AOD;
- (d) the total area of the fenced compound (excluding its accesses) must not exceed 17,000 square metres; and
- (e) any GIS building may be located only within the dotted area shown within Work No. 9A on the works plans.
- (8) In relation to Work No. 50A—
- (a) if AIS is installed—
- (i) the highest part of any building must not exceed 10 metres AOD;
- (ii) the highest part of any external electrical equipment, excluding lightning rods, must not exceed 15 metres AOD; and
- (iii) the total area of the fenced compound (excluding its accesses) must not exceed 86,000 square metres;
- (b) if GIS is installed—
- (i) the highest part of any building must not exceed 16 metres AOD;
- (ii) the highest part of any external electrical equipment, excluding lightning rods, must not exceed 13.5 metres AOD; and
- (iii) the total area of the fenced compound (excluding its accesses) must not exceed 69,000 square metres; and
- (c) the total number of lightning rods within the fenced compound must not exceed 22 and the height of any lightning rod must not exceed 21 metres AOD.
- (9) In relation to Work No. 54—
- (a) the total number of connection bays must not exceed 2;
- (b) the connection bays may be located only within the hatched areas shown within Work Nos. 54A and 54B on the works plans; and
- (c) if 2 connection bays are accommodated within Work No. 54A, Work Nos. 54B and 55 must not be constructed.
- (10) Unless otherwise agreed by the relevant planning authority, after consultation with the relevant drainage boards, the Environment Agency and the highways authority, where identified in the crossings schedule for the purpose of passing under a relevant obstruction, trenchless techniques must be used to install the cable ducts and electrical circuits within Work Nos. 2, 3, 5, 8, 11, 14, 17, 19, 21, 22, 24, 26, 29, 31, 33, 37, 39, 42, 44 and 46.
- (11) The undertaker must—
- (a) at least 3 months before the commencement of the onshore cable works—
- (i) submit to the relevant planning authority a cable route sequencing plan including details of the indicative sequencing of the onshore cable works; and
- (ii) notify the public and owners of land of the sequencing of the onshore cable works in accordance with the communications plan approved as part of the code of construction practice;
- (b) before construction of any stage of the onshore cable works, submit to the relevant planning authority a copy of the cable installation plans provided to owners in accordance with the soil management plan approved as part of the code of construction practice; and
- (c) within 3 months of the completion of the installation of the cable circuits for any stage of the onshore cable works, submit to the relevant planning authority as built plans for that stage showing the alignment of the cable circuits.
- (12) Any plans submitted in accordance with paragraph (11)(a) and (b) may be updated from time to time and must be submitted to the relevant planning authority and communicated to owners and the public in accordance with the code of construction practice.
- (13) In this Requirement, “onshore cable works” means Work Nos. 3, 5, 8, 11, 14, 17, 19, 21, 22, 24, 26, 29, 31, 33, 37, 39, 42, 44, 46 and 52.
Provision of landscaping
6
- (1) Work Nos. 9A and 50A must not be commenced until a written landscaping scheme and associated work programme (in accordance with the outline landscape strategy and ecological management plan) for the relevant work has been submitted to and approved by the relevant planning authority.
- (2) The written landscaping scheme must include details of all proposed hard and soft landscaping works including—
- (a) location, number, species, size and planting density of any proposed planting including any trees; and
- (b) implementation timetables for all landscaping works.
- (3) If Work No. 55 is constructed before the completion of the unlicensed works, a written landscaping scheme and associated work programme (in accordance with the outline landscape strategy and ecological management plan) must be submitted to and approved by the relevant planning authority after consultation with National Grid Electricity Transmission plc (company number 02366977).
Implementation and maintenance of landscaping
7
- (1) All landscaping works must, where relevant, be carried out in accordance with the landscaping scheme approved under Requirement 6.
- (2) Any tree or shrub planted as part of an approved landscaping scheme that, within 10 years after planting, is removed, dies or becomes, in the reasonable opinion of the relevant planning authority, seriously damaged or diseased must be replaced in the first available planting season with a specimen of the same species and size as that originally planted.
Highway accesses and improvements
8
- (1) No stage of the onshore works may be commenced until for that stage written details (which accord with the outline access management plan) of the siting, design, layout, sequencing and timing and any access management measures for any new permanent or temporary means of access to a highway to be used by vehicular traffic, or any alteration to an existing means of access to a highway, have, after consultation with the highway authority, been submitted to and approved by the relevant planning authority.
- (2) The highway accesses for that stage must be constructed or altered, and the works described in paragraph (1) in relation to access management measures carried out, in accordance with the approved details before the relevant highway accesses are brought into use for the purposes of the authorised development.
- (3) No stage of the onshore works may be commenced until for that stage a scheme of temporary highways alterations within the highway boundary has, after consultation with the highway authority, been submitted to and approved by the relevant planning authority.
- (4) The temporary highways alterations for that stage must be constructed in accordance with the approved scheme before they are brought into use for the purposes of the authorised development.
Fencing and other means of enclosure
9
- (1) No stage of the onshore works may be commenced until for that stage written details of all proposed fences, walls or other means of enclosure have been submitted to and approved by the relevant planning authority.
- (2) All temporary construction compounds must remain securely fenced in accordance with the approved details at all times during construction of the onshore works.
- (3) Temporary fencing, except temporary fencing for the beach works, must be removed on completion of the relevant stage of the onshore works.
- (4) Temporary fencing for the beach works must be removed on completion of construction of those works excluding testing.
- (5) Any approved permanent fencing in relation to Work Nos. 9A and 50A must be completed before the relevant Work is brought into use and maintained for the operational lifetime of Work Nos. 9A and 50A.
- (6) In this Requirement, “beach works” means Work No. 2 and works related to the installation of cable ducts and cable circuits within Work No. 3 but excluding Work Nos. 3A and 3B.
Requirement for surface water drainage scheme
10
- (1) Work Nos. 9, 50, 54A and 54B must not be commenced until a surface water drainage scheme for the Work, or part of the Work, in question has, after consultation with Lincolnshire County Council and the relevant drainage boards, been submitted to and approved by the relevant planning authority.
- (2) The surface water drainage scheme submitted under paragraph (1) must be based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the authorised development and must be in accordance with the surface water drainage strategy submitted as part of the flood risk assessment included within the environmental statement.
- (3) Where relevant to the Work, or part of the Work, in question, the scheme must include—
- (a) provision for limiting the surface water run-off generated by all rainfall events up to the 1 in 100 year plus 20% (for climate change) critical rain storm so that it will not exceed the run-off from the undeveloped site and not increase the risk of flooding off-site;
- (b) provision of surface water run-off attenuation storage to accommodate the difference between the allowable discharge rates and all rainfall events up to the 1 in 100 year plus 20% (for climate change) critical rain storm;
- (c) detailed design (plans, cross-sections and calculations) in support of any surface water drainage scheme including details of any attenuation system and the outfall arrangements;
- (d) details of how the scheme is to be maintained and managed after completion; and
- (e) details of percolation testing (carried out in accordance with Building Research Establishment Digest 365 or Construction Industry Research and Information Association guidance R156) to demonstrate that the use of infiltration techniques are suitable.
- (4) The surface water drainage scheme must be implemented as approved.
- (5) In this Requirement, “relevant drainage boards” means the drainage boards within the meaning of section 25 of the Land Drainage Act 1991[^f00040] for the area in which the Work is situated.
Requirement for foul water drainage scheme
11
- (1) Work Nos. 9 and 50 must not be commenced until a detailed foul water drainage scheme (including means of pollution control) for the Work, or part of the Work, in question has, after consultation with Anglian Water Services Limited (company number 02366656) and the Environment Agency, been submitted to and approved by the relevant planning authority.
- (2) The foul water drainage scheme must be implemented as approved.
Archaeology
12
- (1) No stage of the onshore works may be commenced until for that stage a written scheme of investigation in accordance with the outline onshore written scheme of investigation has been submitted to and approved by the relevant planning authority.
- (2) The approved scheme must—
- (a) identify areas where archaeological work is required; and
- (b) the measures to be taken to protect, record or preserve any significant archaeological remains (as defined in the outline onshore written scheme of investigation) that may be found.
- (3) Pre-construction archaeological investigations and pre-commencement material operations which involve intrusive ground works may take place only in accordance with a specific written scheme of investigation which—
- (a) is in accordance with the details set out in the outline onshore written scheme of investigation; and
- (b) has been submitted to and approved by the relevant planning authority.
- (4) Any archaeological works must be carried out by a suitably qualified and competent person or body previously notified to the relevant planning authority.
- (5) The written scheme of investigation must be implemented as approved.
Ecological management plan and removal of hedgerows
13
- (1) No stage of the onshore works may be commenced until for that stage a written ecological management plan (which accords with the outline landscape strategy and ecological management plan) reflecting the survey results and ecological mitigation and enhancement measures included in the environmental statement has after consultation with the appropriate statutory nature conservation body been submitted to and approved by the relevant planning authority.
- (2) The ecological management plan must include an implementation timetable and measures to be taken to reinstate hedgerows on completion of the relevant stage of the onshore works.
- (3) The ecological management plan must be implemented as approved.
- (4) Any hedgerow removal or replacement undertaken before approval of the written ecological management plan under paragraph (1) must be carried out in accordance with the details set out in the outline landscape strategy and ecological management plan.
Code of construction practice
14
- (1) No stage of the onshore works may be commenced until for that stage a code of construction practice in accordance with the outline code of construction practice (onshore) has, after consultation with the Environment Agency, been submitted to and approved by the relevant planning authority.
- (2) The code of construction practice must, where relevant to that stage, cover all the matters set out in the outline code of construction practice (onshore).
- (3) The code of construction practice must include—
- (a) a construction method statement including details of the management of public rights of way and methods (including trenchless and non-trenchless techniques) for the crossing of watercourses (main river crossings to be undertaken using trenchless techniques only);
- (b) a health and safety plan;
- (c) a noise and vibration management plan;
- (d) an air quality management plan;
- (e) a soil management plan;
- (f) an artificial light emissions plan;
- (g) a site waste management plan;
- (h) a pollution prevention and emergency incident response plan;
- (i) a construction environment management plan; and
- (j) a communications plan.
- (4) The soil management plan (which forms part of the code of construction practice) must, where relevant to a stage, secure that any link box located in a place where agricultural machinery may pass over it has a cover that is—
- (a) capable of bearing agricultural machinery loads; and
- (b) designed so as to allow the wheels or tracks of agricultural machinery to pass over the link box without damaging the wheels or tracks of the machinery or the link box.
- (5) The code of construction practice must be implemented as approved.
Unexpected contamination
15
- (1) If, during any stage of the authorised development, contamination not identified or addressed within the relevant code of construction practice is found to be present within the Order limits, no further development in the vicinity of the contamination may be carried out until a written scheme to deal with the associated risks has been submitted to and approved by the relevant planning authority after consultation with the Environment Agency.
- (2) The scheme must include an investigation and assessment report, prepared by a specialist consultant notified in advance to the relevant planning authority, the purpose of which is to identify the extent of any contamination and the remedial measures to be taken to render the land fit for its intended purpose, together with a management plan which sets out long-term measures with respect to any contaminants remaining on site.
- (3) No remedial work identified in accordance with paragraph (2) may be carried out until the scheme has been approved.
- (4) The scheme and management plan must be implemented as approved.
Control of operational artificial light emissions
16
- (1) Work Nos. 9A and 50A must not be brought into operation until a written scheme for the management and mitigation of artificial light emissions for the relevant Work has been submitted to and approved by the relevant planning authority.
- (2) The approved schemes for the management and mitigation of artificial light emissions must be implemented and maintained during the lifetime of Work Nos. 9A and 50A.
Construction hours
17
- (1) Except as otherwise agreed in the code of construction practice and subject to paragraphs (2) to (4), construction of the onshore works and construction-related traffic movements to or from the site of the relevant Work may take place only between 7 a.m. and 7 p.m. from Monday to Saturday, with no activity on Sundays or bank holidays.
- (2) If agreed in advance with the relevant planning authority, construction of the onshore works and construction-related traffic movements to or from the site of the relevant Work may take place outside the hours specified in paragraph (1) for certain identified works including—
- (a) where continuous periods of construction are required, for works such as concrete pouring and finishing, electrical circuit pulling and jointing and testing;
- (b) for the delivery and unloading of abnormal loads;
- (c) for the landfall works; and
- (d) for any other time-critical element of the onshore works.
- (3) Except as provided in paragraph (4), all construction works which are to be undertaken outside the hours specified in paragraph (1) must be agreed in advance with the relevant planning authority.
- (4) In respect of trenchless techniques—
- (a) where continuous 24-hour working is required, the undertaker must notify the relevant planning authority in advance of such works;
- (b) where a trenchless technique is to take place within 100 metres of an occupied dwelling, the works must take place within the hours specified in paragraph (1) unless otherwise agreed in advance with the resident of that dwelling and notified to the relevant planning authority.
Control of noise during operational phase
18
- (1) The rating level of the overall operational noise immissions from Work No. 9A or 50A must not exceed 35 dB LAeq (5 min.) free-field (as defined in and measured in accordance with BS4142:2014 including any relevant penalties for tonal or impulsive character) at any residential property that lawfully exists on the date on which this Order is made.
- (2) In the event of a complaint to the relevant planning authority relating to noise immissions from the operation of Work No. 9A or 50A which may reasonably be expected to result in levels above those allowed by paragraph (1)—
- (a) the undertaker must submit a proposed measurement and assessment procedure, based on the guidance and assessment methodology outlined in BS4142:2014, including a proposed measurement methodology and monitoring locations to the relevant planning authority for approval;
- (b) measurements must be undertaken in accordance with the approved procedure by an independent consultant appointed by the undertaker in order to determine compliance or otherwise with paragraph (1).
Construction traffic
19
- (1) No stage of the onshore works may be commenced until for that stage, after consultation with the highway authority, a construction traffic management plan in accordance with the outline traffic management plan including a contractor travel plan has been submitted to and approved by the relevant planning authority.
- (2) Construction and contractor traffic related to the authorised development must use only Work No. 48 or 49 to access Work Nos. 50 to 55.
- (3) The timings for the construction of Work Nos. 48 and 49 must be included within the construction method statement approved as part of the relevant code of construction practice.
- (4) The construction traffic management plan and contractor travel plan must be implemented as approved.
European protected species
20
- (1) No stage of the onshore works may be commenced until for that stage final pre-construction survey work has been carried out to establish whether a European protected species is present on any of the land affected, or likely to be affected, by that stage of the onshore works or in any of the trees to be lopped or felled as part of that stage of the onshore works.
- (2) Where a European protected species is shown to be present, the relevant stage of the onshore works may not be commenced until, after consultation with the statutory nature conservation body and the relevant planning authority, a scheme of protection and mitigation measures has been submitted to and approved by the relevant planning authority.
- (3) The relevant stage of the onshore works must be carried out in accordance with the approved scheme.
- (4) In this Requirement, “European protected species” means a European protected species of animal or plant within the meaning of Part 3 of the Conservation of Habitats and Species Regulations 2017.
Restoration of land used temporarily for construction
21
- (1) Any land landward of MHWS which is used temporarily for construction of the onshore works and not ultimately incorporated in permanent works or approved landscaping must be reinstated within 6 months of completion of the relevant stage of the onshore works in accordance with details approved by the relevant planning authority.
- (2) Any hedgerow reinstatement must be carried out on accordance with Requirement 13(3).
Onshore decommissioning
22
Within 6 months of the cessation of commercial operation of the onshore works, and after consultation with owners in relation to their landholding, an onshore decommissioning plan must be submitted to the relevant planning authority for approval.
Local employment
23
- (1) No stage of the onshore works within a relevant planning authority’s area may be commenced until, after consultation with the relevant planning authority and the Greater Lincolnshire Local Enterprise Partnership, a plan detailing arrangements to promote local employment and skills development opportunities related to the onshore works has been notified to the relevant planning authority.
- (2) The plan must include proposals for working with the Greater Lincolnshire Local Enterprise Partnership and the relevant planning authority to promote such opportunities.
- (3) The employment and skills plan must be implemented and maintained for the duration of the construction of the onshore works.
Approval, etc. to be in writing
24
Where the approval or agreement of the Secretary of State or the relevant planning authority is required under a Requirement, that approval or agreement must be given in writing.
Amendments to approved plans, etc.
25
- (1) Where a Requirement requires the authorised development to be carried out in accordance with a plan, scheme, statement, strategy or details (the “plan”) approved by the relevant planning authority, the plan must be carried out as approved unless an amendment is previously agreed in writing by the relevant planning authority in accordance with paragraph (2).
- (2) Any amendment to the approved plan must be in accordance with the principles and assessments set out in the environmental statement and the other documents set out in article 35; and the agreement of the relevant planning authority to an amendment may be given only where it has been demonstrated to the satisfaction of the relevant planning authority that the amendment is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
- (3) The approved plan must be taken to include any amendment that may subsequently be approved in writing by the relevant planning authority.
SCHEDULE 2 — Streets subject to street works
| (1) District | (2) Street subject to street works (see access to works and streets plans) | (3) Grid co-ordinates | (3) Grid co-ordinates |
|---|---|---|---|
| (1) District | (2) Street subject to street works (see access to works and streets plans) | Easting | Northing |
| East Lindsey | Hutt/10/4/footpath | 554608 | 376836 |
| East Lindsey | 554503 | 376813 | |
| East Lindsey | Ande/17/2/footpath | 554237 | 376293 |
| East Lindsey | Ande/25/1/footpath | 553749 | 375398 |
| East Lindsey | Sea Road | 553747 | 375899 |
| East Lindsey | Roman Bank | 554325 | 376452 |
| East Lindsey | Roman Bank | 554192 | 376734 |
| East Lindsey | Hutt/10/4/footpath | 554197 | 376740 |
| East Lindsey | Ande/22/4/footpath | 553722 | 375727 |
| East Lindsey | Ande/23/1/footpath | 553722 | 375727 |
| East Lindsey | Ande/22/3/footpath | 553722 | 375727 |
| East Lindsey | Mumb/26/1/footpath | 553404 | 375064 |
| East Lindsey | Mumb/59/8/footpath | 553278 | 374481 |
| East Lindsey | Mumb/61/1/footpath | 553076 | 374192 |
| East Lindsey | Langham Road | 552852 | 373850 |
| East Lindsey | 552745 | 372633 | |
| East Lindsey | Sloothby High Lane | 552768 | 371237 |
| East Lindsey | Listoft Lane | 552737 | 371863 |
| East Lindsey | Hogs/58/2/footpath | 552716 | 373428 |
| East Lindsey | Marsh Lane | 552235 | 367778 |
| East Lindsey | Ingoldmells Road | 551927 | 366133 |
| East Lindsey | Chalk Lane | 551979 | 366293 |
| East Lindsey | Younger’s Lane | 551854 | 365781 |
| East Lindsey | BurM/265/1/footpath | 551849 | 365045 |
| East Lindsey | Skegness Road | 551884 | 364653 |
| East Lindsey | Skegness Road | 551677 | 364700 |
| East Lindsey | BurM/261/2/footpath | 551210 | 364293 |
| East Lindsey | Low Lane | 549737 | 363928 |
| East Lindsey | Billgate Lane | 550874 | 364061 |
| East Lindsey | High Lane | 549541 | 363837 |
| East Lindsey | Lymn Bank | 547595 | 361881 |
| East Lindsey | Spilsby Road | 547576 | 361869 |
| East Lindsey | Tip Lane | 547187 | 361492 |
| East Lindsey | Tip Lane | 546959 | 361475 |
| East Lindsey | Lymn Bank | 546707 | 361686 |
| East Lindsey | Harrison’s Lane | 545951 | 360772 |
| East Lindsey | 546451 | 360602 | |
| East Lindsey | Fendike Bank | 545225 | 360887 |
| East Lindsey | 544335 | 360672 | |
| East Lindsey | 544406 | 360646 | |
| East Lindsey | Spilsby Road | 540547 | 358398 |
| East Lindsey | 538464 | 357361 | |
| East Lindsey | Fodder Dike Bank | 537270 | 356983 |
| East Lindsey | Black Drove | 536854 | 356970 |
| East Lindsey | 535854 | 355477 | |
| East Lindsey | Main Road | 535171 | 354456 |
| East Lindsey | Thorndales Lane | 535143 | 354569 |
| East Lindsey | Main Road | 535164 | 354554 |
| East Lindsey | Westhouses | 534385 | 353879 |
| East Lindsey | Staunt Road | 532754 | 352939 |
| East Lindsey | 532759 | 352950 | |
| East Lindsey | 532704 | 352947 | |
| East Lindsey | Carrington Road | 531478 | 351306 |
| East Lindsey | Westville Road | 531252 | 350893 |
| East Lindsey | Canister Lane | 530901 | 350507 |
| East Lindsey | Peacock’s Road | 530071 | 349321 |
| East Lindsey | Leagate Road | 529247 | 348560 |
| East Lindsey | Mere Booth Road | 528535 | 348075 |
| Boston (B) | Langrick Road | 526770 | 347276 |
| Boston and South Holland | Brot/2/1/footpath | 526284 | 347004 |
| Boston (B) | Kirton Drove | 525143 | 346217 |
| Boston (B) | North Forty Foot Bank | 525615 | 346514 |
| Boston (B) | Sutterton Drove | 524323 | 345745 |
| Boston (B) | Claydike Bank | 523493 | 345383 |
| Boston (B) | Claydike Bank | 523450 | 345437 |
| Boston (B) | 521383 | 343290 | |
| Boston (B) | Station Road | 521732 | 342951 |
| Boston (B) | 521729 | 342991 | |
| Boston (B) | 521273 | 343376 | |
| Boston (B) | Station Road | 522154 | 342298 |
| Boston (B) | Doubletwelves Drove | 519105 | 340112 |
| Boston (B) | Bicker Drove | 519871 | 339207 |
| Boston (B) | 519930 | 338732 | |
| East Lindsey | 546596 | 367333 | |
| East Lindsey | 546845 | 367295 | |
| East Lindsey | Sausthorpe Road | 540505 | 367977 |
| East Lindsey | 537720 | 363658 | |
| Boston (B) | Boardsides | 530280 | 343449 |
| Boston (B) | Sleaford Road | 530692 | 343547 |
| Boston (B) | John Adams Way | 532582 | 343678 |
| Boston (B) | Liquorpond Street | 532517 | 343690 |
| Boston (B) | South End | 532834 | 343751 |
| Boston (B) | John Adams Way | 532884 | 343787 |
| Boston (B) | John Adams Way | 532805 | 343750 |
SCHEDULE 3 — Streets to be temporarily stopped up
| (1) Dist-rict | (2) Streets to be temporarily stopped up (see access to works and streets plans) | (3) Grid co-ordinates (start) | (3) Grid co-ordinates (start) | (3) Grid co-ordinates (start) | (4) Ident-ifier | (5) Grid co-ordinates (end) | (5) Grid co-ordinates (end) | (5) Grid co-ordinates (end) | (6) Ident-ifier | (7) Extent of stop-ping up |
|---|---|---|---|---|---|---|---|---|---|---|
| Easting | Easting | Northing | Easting | Easting | Northing | |||||
| East Lindsey | East Lindsey | East Lindsey | East Lindsey | East Lindsey | East Lindsey | East Lindsey | East Lindsey | East Lindsey | East Lindsey | East Lindsey |
| Hutt/10/4/ footpath | 554608 | 554608 | 376836 | Cx | 554704 | 554704 | 376859 | Cy | ||
| Ande/17/2/ footpath | 554226 | 554226 | 376295 | Dx | 554130 | 554130 | 376277 | Dy | ||
| Roman Bank | 554191 | 554191 | 376754 | AC | 554194 | 554194 | 376713 | AD | 41 | |
| Roman Bank | 554311 | 554311 | 376482 | AE | 554338 | 554338 | 376422 | AF | 66 | |
| 554197 | 554197 | 376754 | AA | 554809 | 554809 | 376886 | AB | 629 | ||
| Hutt/10/4/ footpath | 554197 | 554197 | 376740 | Ca | 554815 | 554815 | 376888 | Cb | ||
| Sea Road | 553723 | 553723 | 375923 | AG | 553771 | 553771 | 375876 | AH | 67 | |
| Langham Road | 552820 | 552820 | 373849 | AI | 552884 | 552884 | 373848 | AJ | 64 | |
| 552692 | 552692 | 372642 | AK | 552797 | 552797 | 372624 | AL | 107 | ||
| Ande/25/1/ footpath | 553583 | 553583 | 375327 | Ha | 553564 | 553564 | 375283 | Hb | ||
| Ande/25/1/ footpath | 553535 | 553535 | 375216 | Hx | 553462 | 553462 | 375199 | Hy | ||
| Ande/22/4/ footpath | 553722 | 553722 | 375727 | Ex | 553728 | 553728 | 375729 | Ey | ||
| Ande/23/1/ footpath | 553722 | 553722 | 375727 | Fx | 553725 | 553725 | 375719 | Fy | ||
| Ande/22/3/ footpath | 553722 | 553722 | 375727 | Gx | 553652 | 553652 | 375683 | Gy | ||
| Mumb/26/1/ footpath | 553404 | 553404 | 375064 | Ix | 553450 | 553450 | 375020 | Iy | ||
| Mumb/59/8/ footpath | 553278 | 553278 | 374481 | Jx | 553337 | 553337 | 374466 | Jy | ||
| Mumb/61/1/ footpath | 553076 | 553076 | 374192 | Kx | 553089 | 553089 | 374117 | Ky | ||
| Listoft Lane | 552705 | 552705 | 371875 | AM | 552768 | 552768 | 371875 | AN | 67 | |
| Sloothby High Lane | 552738 | 552738 | 371225 | AO | 552798 | 552798 | 371248 | AP | 64 | |
| Marsh Lane | 552225 | 552225 | 367773 | AQ | 552415 | 552415 | 367878 | AR | 217 | |
| Hogs/58/2/ footpath | 552716 | 552716 | 373428 | Lx | 552773 | 552773 | 373332 | Ly | ||
| Chalk Lane | 551931 | 551931 | 366283 | AS | 552026 | 552026 | 366303 | AT | 97 | |
| Ingoldmells Road | 551883 | 551883 | 366094 | AU | 551971 | 551971 | 366172 | AV | 117 | |
| Younger’s Lane | 551817 | 551817 | 365777 | AW | 551891 | 551891 | 365785 | AX | 74 | |
| BurM/265/1/ footpath | 551849 | 551849 | 365045 | Mx | 551917 | 551917 | 365039 | My | ||
| Skegness Road | 551624 | 551624 | 364712 | AY | 551730 | 551730 | 364688 | AZ | 108 | |
| Skegness Road | 551798 | 551798 | 364673 | BA | 551970 | 551970 | 364634 | BB | 176 | |
| Billgate Lane | 550834 | 550834 | 364072 | BC | 550915 | 550915 | 364050 | BD | 84 | |
| BurM/261/2/ footpath | 551210 | 551210 | 364293 | Nx | 551249 | 551249 | 364246 | Ny | ||
| Low Lane | 549721 | 549721 | 363954 | BE | 549753 | 549753 | 363902 | BF | 61 | |
| High Lane | 549526 | 549526 | 363863 | BG | 549555 | 549555 | 363810 | BH | 60 | |
| Lymn Bank | 547579 | 547579 | 361892 | BI | 547611 | 547611 | 361870 | BJ | 38 | |
| Spilsby Road | 547579 | 547579 | 361892 | BK | 547574 | 547574 | 361845 | BL | 47 | |
| Tip Lane | 547140 | 547140 | 361487 | BM | 547235 | 547235 | 361497 | BN | 95 | |
| Tip Lane | 546955 | 546955 | 361488 | BO | 546973 | 546973 | 361469 | BP | 26 | |
| Lymn Bank | 546690 | 546690 | 361682 | BQ | 546722 | 546722 | 361691 | BR | 33 | |
| 546434 | 546434 | 360599 | BS | 546468 | 546468 | 360605 | BT | 34 | ||
| Harrison’s Lane | 545940 | 545940 | 360803 | BU | 545962 | 545962 | 360742 | BV | 65 | |
| Fendike Bank | 545231 | 545231 | 360917 | BW | 545222 | 545222 | 360857 | BX | 60 | |
| 544301 | 544301 | 360685 | BY | 544369 | 544369 | 360660 | BZ | 72 | ||
| 544390 | 544390 | 360652 | CA | 544421 | 544421 | 360641 | CB | 33 | ||
| 541839 | 541839 | 359030 | CC | 541939 | 541939 | 359060 | CD | 104 | ||
| Spilsby Road | 540555 | 540555 | 358432 | CE | 540539 | 540539 | 358364 | CF | 70 | |
| 538472 | 538472 | 357404 | CG | 538456 | 538456 | 357318 | CH | 87 | ||
| Black Drove | 536858 | 536858 | 356990 | CI | 536850 | 536850 | 356951 | CJ | 40 | |
| Fodder Dike Bank | 537235 | 537235 | 356981 | CK | 537305 | 537305 | 356982 | CL | 70 | |
| 535819 | 535819 | 355479 | CM | 535888 | 535888 | 355475 | CN | 69 | ||
| Main Road | 535152 | 535152 | 354586 | CO | 535159 | 535159 | 354575 | CP | 13 | |
| Thorndales Lane | 535127 | 535127 | 354562 | CQ | 535159 | 535159 | 354519 | CR | 60 | |
| Main Road | 535169 | 535169 | 354510 | CS | 535166 | 535166 | 354401 | CT | 109 | |
| Westhouses | 534374 | 534374 | 353911 | CU | 534396 | 534396 | 353847 | CV | 68 | |
| Staunt Road | 532754 | 532754 | 353010 | CW | 532754 | 532754 | 352868 | CX | 141 | |
| 532688 | 532688 | 352946 | CY | 532720 | 532720 | 352948 | CZ | 33 | ||
| 532725 | 532725 | 352948 | DA | 532793 | 532793 | 352953 | DB | 69 | ||
| Carrington Road | 531475 | 531475 | 351340 | DC | 531482 | 531482 | 351272 | DD | 68 | |
| Westville Road | 531225 | 531225 | 350908 | DE | 531278 | 531278 | 350879 | DF | 60 | |
| Canister Lane | 530869 | 530869 | 350498 | DG | 530934 | 530934 | 350516 | DH | 67 | |
| Peacock’s Road | 530060 | 530060 | 349349 | DI | 530083 | 530083 | 349293 | DJ | 60 | |
| Leagate Road | 529222 | 529222 | 348584 | DK | 529273 | 529273 | 348538 | DL | 69 | |
| Mere Booth Road | 528507 | 528507 | 348090 | DM | 528563 | 528563 | 348060 | DN | 63 | |
| Boston (B) | Boston (B) | Boston (B) | Boston (B) | Boston (B) | Boston (B) | Boston (B) | Boston (B) | Boston (B) | Boston (B) | Boston (B) |
| Langrick Road | 526754 | 347301 | 347301 | DO | 526786 | 347250 | 347250 | DP | 60 | |
| North Forty Foot Bank | 525586 | 346544 | 346544 | DQ | 525643 | 346485 | 346485 | DR | 81 | |
| Kirton Drove | 525126 | 346235 | 346235 | DS | 525160 | 346198 | 346198 | DT | 50 | |
| Sutterton Drove | 524304 | 345769 | 345769 | DU | 524342 | 345722 | 345722 | DV | 60 | |
| Claydike Bank | 523441 | 345449 | 345449 | DW | 523459 | 345426 | 345426 | DX | 30 | |
| Claydike Bank | 523474 | 345407 | 345407 | DY | 523512 | 345360 | 345360 | DZ | 61 | |
| 521246 | 343393 | 343393 | EA | 521301 | 343358 | 343358 | EB | 66 | ||
| 521341 | 343325 | 343325 | EC | 521424 | 343255 | 343255 | ED | 109 | ||
| Station Road | 522137 | 342325 | 342325 | EE | 522171 | 342271 | 342271 | EF | 63 | |
| Doubletwelves Drove | 519277 | 340463 | 340463 | EG | 518939 | 339758 | 339758 | EH | 782 | |
| Bicker Drove | 519836 | 339223 | 339223 | EI | 519906 | 339192 | 339192 | EJ | 77 | |
| 519942 | 338749 | 338749 | EK | 519922 | 338712 | 338712 | EL | 42 | ||
| Boston and South Holland | Boston and South Holland | Boston and South Holland | Boston and South Holland | Boston and South Holland | Boston and South Holland | Boston and South Holland | Boston and South Holland | Boston and South Holland | Boston and South Holland | Boston and South Holland |
| Brot/2/1/ footpath | 526284 | 526284 | 347004 | Px | 526244 | 526244 | 346908 | Py |
SCHEDULE 4 — Access to works
| (1) District | (2) Grid reference points | (2) Grid reference points | (3) Description of access (see access to works and streets plans) |
|---|---|---|---|
| Easting | Northing | ||
| East Lindsey | 554197 | 376740 | AC1 |
| East Lindsey | 554327 | 376455 | AC2 |
| East Lindsey | 554323 | 376451 | AC3 |
| East Lindsey | 553747 | 375901 | AC4 |
| East Lindsey | 553746 | 375896 | AC5 |
| East Lindsey | 552855 | 373852 | AC6 |
| East Lindsey | 552853 | 373849 | AC7 |
| East Lindsey | 552742 | 372636 | AC8 |
| East Lindsey | 552742 | 372631 | AC9 |
| East Lindsey | 552737 | 371866 | AC10 |
| East Lindsey | 552738 | 371858 | AC11 |
| East Lindsey | 552766 | 371242 | AC12 |
| East Lindsey | 552767 | 371236 | AC13 |
| East Lindsey | 552239 | 367778 | AC14 |
| East Lindsey | 551981 | 366294 | AC15 |
| East Lindsey | 551977 | 366291 | AC16 |
| East Lindsey | 551927 | 366135 | AC17 |
| East Lindsey | 551926 | 366129 | AC18 |
| East Lindsey | 551855 | 365783 | AC19 |
| East Lindsey | 551854 | 365778 | AC20 |
| East Lindsey | 551675 | 364696 | AC22 |
| East Lindsey | 551915 | 364651 | AC21 |
| East Lindsey | 550882 | 364063 | AC23 |
| East Lindsey | 550880 | 364061 | AC24 |
| East Lindsey | 549739 | 363926 | AC25 |
| East Lindsey | 549736 | 363924 | AC26 |
| East Lindsey | 549545 | 363842 | AC27 |
| East Lindsey | 549540 | 363839 | AC28 |
| East Lindsey | 547600 | 361883 | AC29 |
| East Lindsey | 547572 | 361865 | AC30 |
| East Lindsey | 547193 | 361494 | AC31 |
| East Lindsey | 547190 | 361490 | AC32 |
| East Lindsey | 546955 | 361473 | AC33 |
| East Lindsey | 546708 | 361684 | AC34 |
| East Lindsey | 546450 | 360601 | AC35 |
| East Lindsey | 545954 | 360773 | AC36 |
| East Lindsey | 545950 | 360773 | AC37 |
| East Lindsey | 545226 | 360888 | AC38 |
| East Lindsey | 545223 | 360888 | AC39 |
| East Lindsey | 544407 | 360643 | AC40 |
| East Lindsey | 541886 | 359040 | AC41 |
| East Lindsey | 541883 | 359034 | AC42 |
| East Lindsey | 540547 | 358397 | AC43 |
| East Lindsey | 540541 | 358395 | AC44 |
| East Lindsey | 538462 | 357336 | AC45 |
| East Lindsey | 536854 | 356969 | AC46 |
| East Lindsey | 535857 | 355480 | AC47 |
| East Lindsey | 535854 | 355477 | AC48 |
| East Lindsey | 535175 | 354463 | AC49 |
| East Lindsey | 535169 | 354463 | AC50 |
| East Lindsey | 534385 | 353879 | AC51 |
| East Lindsey | 532759 | 352955 | AC52 |
| East Lindsey | 532705 | 352945 | AC53 |
| East Lindsey | 531481 | 351305 | AC54 |
| East Lindsey | 531475 | 351300 | AC55 |
| East Lindsey | 531252 | 350895 | AC56 |
| East Lindsey | 530903 | 350511 | AC57 |
| East Lindsey | 530902 | 350505 | AC58 |
| East Lindsey | 530072 | 349323 | AC59 |
| East Lindsey | 530069 | 349322 | AC60 |
| East Lindsey | 529245 | 348564 | AC61 |
| East Lindsey | 529240 | 348562 | AC62 |
| East Lindsey | 528537 | 348077 | AC63 |
| East Lindsey | 528534 | 348074 | AC64 |
| Boston (B) | 526773 | 347277 | AC65 |
| Boston (B) | 526767 | 347274 | AC66 |
| Boston (B) | 525599 | 346533 | AC67 |
| Boston (B) | 525146 | 346219 | AC68 |
| Boston (B) | 525143 | 346216 | AC69 |
| Boston (B) | 524325 | 345746 | AC70 |
| Boston (B) | 524321 | 345743 | AC71 |
| Boston (B) | 523499 | 345381 | AC72 |
| Boston (B) | 523449 | 345438 | AC73 |
| Boston (B) | 521386 | 343293 | AC74 |
| Boston (B) | 521381 | 343287 | AC75 |
| Boston (B) | 522152 | 342298 | AC76 |
| Boston (B) | 519870 | 339210 | AC77 |
| Boston (B) | 519871 | 339206 | AC78 |
| Boston (B) | 519909 | 338733 | AC79 |
SCHEDULE 5 — Land in which only new rights, etc. may be acquired
East Lindsey District
| (1) Number of plot shown on land plans | (2) Purpose for which rights may be acquired |
|---|---|
| 01/01, 01/02, 01/06, 01/08, 02/01, 02/03, 02/05, 02/06, 02/07, 02/10, 02/12, 02/14, 02/15, 02/17, 02/18, 03/01, 03/03, 03/04, 04/01, 04/05, 04/09, 04/10, 04/11, 04/13, 04/16, 04/17, 04/18, 05/01, 05/03, 05/06, 05/08, 05/09, 05/10, 05/16, 05/21, 05/30, 05/33, 06/01, 06/02, 06/03, 06/05, 06/07, 06/08, 06/10, 06/11, 06/12, 06/13, 06/14, 07/01, 07/02, 07/05, 07/06, 07/08, 07/11, 07/12, 07/13, 07/14, 07/18, 08/01, 08/03, 08/05, 09/01, 09/02, 09/04, 09/05, 10/01, 10/04, 10/11, 10/12, 10/13, 11/01, 11/02, 11/03, 11/04, 11/06, 11/07, 11/10, 11/12, 11/13, 11/15, 11/16, 12/01, 12/03, 12/04, 12/06, 12/07, 12/08, 12/09, 12/10, 12/11, 12/16, 12/17, 12/21, 12/22, 12/24, 12/26, 13/01, 13/07, 13/11, 13/13, 13/14, 13/15, 13/16, 13/17, 13/21, 13/22, 13/23, 13/24, 15/01, 15/02, 15/04, 15/06, 15/07, 15/11, 15/15, 15/16, 15/17, 15/18, 15/19, 16/01, 16/02, 16/03, 16/05, 16/07, 16/09, 16/11, 16/12, 16/14, 16/15, 16/16, 16/17, 16/20, 16/21, 16/22, 16/23, 16/25, 17/01, 17/02, 17/03, 17/06, 17/07, 17/10, 17/11, 17/12, 17/14, 17/16, 17/17, 17/19, 17/20, 18/01, 18/03, 18/05, 18/07, 18/08, 18/13, 18/14, 18/16, 18/17, 18/18, 18/19, 19/01, 19/04, 19/05, 19/06, 19/08, 19/09, 20/01, 20/02, 20/04, 20/05, 20/06, 20/07, 20/08, 20/10, 20/15, 20/16, 20/17, 21/01, 21/07, 21/09, 22/01, 22/02, 22/05, 22/10, 22/14, 22/15, 22/18, 22/20, 22/21, 22/22, 22/25, 24/01, 24/02, 24/03, 24/05, 24/08, 24/09, 24/10, 24/11, 24/12, 24/13, 25/01, 25/02, 25/03, 25/05, 25/06, 25/07, 25/10, 25/11, 25/12, 25/13, 25/14, 25/15, 25/16, 25/17, 25/18, 25/19, 25/20, 25/22, 25/23, 25/24, 26/01, 26/03, 26/06, 26/07, 26/09, 27/01, 27/06, 27/07, 27/09, 27/11, 27/13, 28/01, 28/02, 28/04, 28/05, 28/08, 28/11, 29/03, 29/04, 29/05, 29/06, 29/07, 29/08, 29/09, 29/12, 29/17, 29/18, 29/19, 29/21, 29/22, 29/23, 30/01, 30/02, 30/07, 30/08, 30/09, 30/10, 30/13, 30/14, 30/15, 30/17, 30/18, 31/01, 31/03, 31/04, 31/05, 31/06, 31/07, 31/08, 31/09, 31/10, 31/11, 31/13, 32/01, 32/03, 32/08, 32/09, 32/10, 32/11, 32/14, 33/01, 33/02, 33/04, 33/05, 33/10, 33/12, 33/13, 33/15, 33/16, 34/01, 34/03, 34/04, 34/07, 34/08, 34/09, 34/12, 34/13, 34/15, 34/16, 35/01, 35/02, 35/03, 35/06, 35/07, 35/08, 36/01, 36/06, 36/07, 36/09, 37/01, 37/06, 37/11, 37/13, 37/17, 37/18, 37/19, 37/20 | A restrictive covenant over the land for the benefit of the remainder of the Order land to— a prevent anything being done in or on the land or any part thereof for the purpose of— i the erection of any buildings; or ii the construction, erection or works of any kind requiring foundations, footings or other supporting structures, without the consent in writing of the undertaker (such consent not to be unreasonably withheld or delayed if the proposed building, erection, construction or works would not cause damage to the relevant part of the authorised project nor make it materially more difficult to access or maintain the authorised project); b prevent anything to be done by way of hard surfacing of the land with concrete of any kind or with any other material or surface whatsoever without the consent in writing of the undertaker (such consent not to be unreasonably withheld or delayed if the proposed surfacing would not cause damage to the relevant part of the authorised project nor make it materially more difficult to access or maintain the authorised project) provided that the undertaker acknowledges that— i the laying of new hard core access tracks does not require the consent of the undertaker where no manhole, access chamber or other access point serving the authorised project is located on the surface of the land; and ii the maintenance or repair of pre-existing hard surfacing, hard core surfaces or tracks with the same or equivalent surface or material does not require the consent of the undertaker where no manhole, access chamber or other access point serving the authorised project is located on the surface of the land; c prevent— i mole draining; ii anything to be done by way of excavation of any kind or agricultural practices exceeding 0.6 metres in depth from— aa the surface of the land; or bb the hard bed level of the open drain, ditch, watercourse or river; or iii any activities which increase or decrease ground cover or soil levels or change the composition of the land in any manner whatsoever, without the consent in writing of the undertaker (such consent not to be unreasonably withheld or delayed, with consent for mole requests to be determined within 24 hours not including weekend or bank holiday hours, if the proposed activity would not cause damage to the relevant part of the authorised project nor make it materially more difficult to access or maintain the authorised project, with such consent being subject to such reasonable conditions as the undertaker may require) provided that— iv acts of cultivation including soil preparation, ploughing and sub-soiling not exceeding 0.6 metres in depth from the surface of the land do not require the consent of the undertaker; and v flushing of land drainage systems, maintenance of outfalls and culverts of land drainage systems, clearance of vegetation (by use of machinery or by hand) and the operation of existing land drainage systems do not require the consent of the undertaker; d prevent the planting or growing within the land of any trees, shrubs or underwood without the consent in writing of the undertaker (such consent not to be unreasonably withheld or delayed provided that the proposed trees, shrubs or underwood would not cause damage to the relevant part of the authorised project nor make it materially more difficult to maintain or to access the relevant part of the authorised project) provided that the growing within the land of any pre-existing trees, shrubs or underwood do not require the consent of the undertaker; and e prevent anything being done in or on the land or any part thereof which will, or which the owner can reasonably foresee may, interfere with the exercise of the other rights set out in this Schedule or the use of the authorised project or in any way render the authorised project or any part thereof in breach of any statute or regulation for the time being in force and applicable thereto, provided that nothing in the preceding restrictions in paragraphs (a) to (e) restricts National Grid Electricity Transmission plc, the Environment Agency or any other body from exercising their respective statutory functions, statutory powers, statutory rights, statutory duties, statutory responsibilities or statutory obligations. |
| 01/01, 01/02, 01/06, 01/08, 02/01, 02/03, 02/05, 02/06, 02/07, 02/10, 02/12, 02/14, 02/15, 02/17, 02/18, 03/01, 03/03, 03/04, 04/01, 04/05, 04/09, 04/10, 04/11, 04/13, 04/16, 04/17, 04/18, 05/01, 05/03, 05/06, 05/08, 05/09, 05/10, 05/16, 05/21, 05/30, 05/33, 06/01, 06/02, 06/03, 06/05, 06/07, 06/08, 06/10, 06/11, 06/12, 06/13, 06/14, 07/01, 07/02, 07/05, 07/06, 07/08, 07/11, 07/12, 07/13, 07/14, 07/18, 08/01, 08/03, 08/05, 09/01, 09/02, 09/04, 09/05, 10/01, 10/04, 10/11, 10/12, 10/13, 11/01, 11/02, 11/03, 11/04, 11/06, 11/07, 11/10, 11/12, 11/13, 11/15, 11/16, 12/01, 12/03, 12/04, 12/06, 12/07, 12/08, 12/09, 12/10, 12/11, 12/16, 12/17, 12/21, 12/22, 12/24, 12/26, 13/01, 13/07, 13/11, 13/13, 13/14, 13/15, 13/16, 13/17, 13/21, 13/22, 13/23, 13/24, 15/01, 15/02, 15/04, 15/06, 15/07, 15/11, 15/15, 15/16, 15/17, 15/18, 15/19, 16/01, 16/02, 16/03, 16/05, 16/07, 16/09, 16/11, 16/12, 16/14, 16/15, 16/16, 16/17, 16/20, 16/21, 16/22, 16/23, 16/25, 17/01, 17/02, 17/03, 17/06, 17/07, 17/10, 17/11, 17/12, 17/14, 17/16, 17/17, 17/19, 17/20, 18/01, 18/03, 18/05, 18/07, 18/08, 18/13, 18/14, 18/16, 18/17, 18/18, 18/19, 19/01, 19/04, 19/05, 19/06, 19/08, 19/09, 20/01, 20/02, 20/04, 20/05, 20/06, 20/07, 20/08, 20/10, 20/15, 20/16, 20/17, 21/01, 21/07, 21/09, 22/01, 22/02, 22/05, 22/10, 22/14, 22/15, 22/18, 22/20, 22/21, 22/22, 22/25, 24/01, 24/02, 24/03, 24/05, 24/08, 24/09, 24/10, 24/11, 24/12, 24/13, 25/01, 25/02, 25/03, 25/05, 25/06, 25/07, 25/10, 25/11, 25/12, 25/13, 25/14, 25/15, 25/16, 25/17, 25/18, 25/19, 25/20, 25/22, 25/23, 25/24, 26/01, 26/03, 26/06, 26/07, 26/09, 27/01, 27/06, 27/07, 27/09, 27/11, 27/13, 28/01, 28/02, 28/04, 28/05, 28/08, 28/11, 29/03, 29/04, 29/05, 29/06, 29/07, 29/08, 29/09, 29/12, 29/17, 29/18, 29/19, 29/21, 29/22, 29/23, 30/01, 30/02, 30/07, 30/08, 30/09, 30/10, 30/13, 30/14, 30/15, 30/17, 30/18, 31/01, 31/03, 31/04, 31/05, 31/06, 31/07, 31/08, 31/09, 31/10, 31/11, 31/13, 32/01, 32/03, 32/08, 32/09, 32/10, 32/11, 32/14, 33/01, 33/02, 33/04, 33/05, 33/10, 33/12, 33/13, 33/15, 33/16, 34/01, 34/03, 34/04, 34/07, 34/08, 34/09, 34/12, 34/13, 34/15, 34/16, 35/01, 35/02, 35/03, 35/06, 35/07, 35/08, 36/01, 36/06, 36/07, 36/09, 37/01, 37/06, 37/11, 37/13, 37/17, 37/18, 37/19, 37/20. | Rights for the purposes of the construction, installation, operation, maintenance and decommissioning of the authorised project to— a lay down, install, adjust, alter, construct, operate, erect, use, maintain, repair, renew, upgrade, inspect, remove and replace the electricity cables (including the removal of materials including spoil) in, under, over and/or on the land, together with such telemetry and fibre-optic lines, ducting, jointing bays and other apparatus, protection measures and other equipment which is ancillary to the purposes of transmitting electricity along such electricity cables (collectively referred to as the “cables”); b enter, be on, and break up the surface of, the land and remain with or without plant, vehicles, machinery, apparatus and equipment which is ancillary to the purposes of transmitting electricity along the cables; c retain and use or permit the cables to transmit and distribute any matters or thing the transmission of which is for the time being not prohibited by law through, to and from the land; d pass and re-pass with or without vehicles, plant, machinery, apparatus, equipment and materials for the purposes of laying down, installing, adjusting, altering, constructing, using, maintaining, repairing, renewing, inspecting, removing and replacing the cables; e construct and install and thereafter use the land for all necessary purposes for the commissioning, construction, repair, testing and maintenance of the cables and any electric cables in, on or under other land including (but not limited to) the following— i facilities and activities in connection with the cables or other work carried out in accordance with the rights; ii portakabins/portaloos; iii storage of plant and equipment; and iv additional service lines or cables (in emergency only); f place and use plant, machinery, structures and temporary structures within the land for the purposes of the installation, construction, maintenance, repairing, renewing, upgrading, inspecting, removal and replacing of the cables; g erect fencing and create secure works compounds; h construct, lay down, use and remove temporary access roads including any necessary temporary bridging, culverting or diversion of water courses and drains during any period during which construction, maintenance, repair or renewal is being carried out; i effect access to the highway; j make such investigations in or on the land as required; k install and maintain cable marker posts to identify the location of the cables (subject to an obligation to minimise interference with future use and operations within the land); l fell, lop or cut, coppice wood, uproot trees or hedges or shrubs which now or hereafter may be standing on the land or other land which would if not felled, lopped, cut or removed obstruct or interfere with the working of the cables; m install, use, inspect, maintain, adjust, alter, renew, repair, test or cleanse pre- and post-development drainage schemes on the land or reinstate the existing drainage scheme on the land and thereafter cleanse and maintain, alter, adjust, replace, improve or extend culverts; n install, alter, re-lay, maintain, protect, adjust or remove pipes, cables or conduits or apparatus (including the pipes, cables or conduits or apparatus of statutory undertakers); o remove fences within the land during any period during which construction, maintenance, repair or renewal is being carried out (subject to erection of any temporary stock-proof fencing as is reasonably required and the re-instating of the original fences following the exercise of the rights); p store and stockpile materials (including excavated material); q use or resort to trenchless construction techniques including (but not limited to) directional drilling; r lay out temporary paths for public use; s carry out environmental or ecological mitigation or enhancement works; t locate, install and inspect chambers or manholes within or on the land; u carry out such works (together with associated fencing) required by a planning permission and/or consent now or to be granted over the land in accordance with any necessary licences relating to protected species and/or wildlife (which for the avoidance of doubt includes newts); and v (in an emergency only when the cables are temporarily unusable) lay down, install, use maintain and inspect underground cables, telephone signalling and fibre-optic cables and ancillary equipment, associated works and other conducting media together with conduits or pipes for containing the same in and under the land. |
| 02/02, 02/04, 02/08, 02/09, 02/11, 02/13, 02/16, 02/19, 03/02, 03/05, 03/06, 03/08, 04/02, 04/03, 04/04, 04/06, 04/07, 04/08, 04/12, 04/14, 04/15, 05/02, 05/04, 05/05, 05/07, 05/11, 05/12, 05/13, 05/14, 05/15, 05/27, 05/31, 05/32, 06/04, 06/06, 06/09, 07/03, 07/04, 07/09, 07/10, 07/15, 07/16, 07/17, 07/19, 08/02, 08/04, 08/06, 09/03, 09/06, 09/07, 10/02, 10/03, 10/05, 11/05, 11/08, 11/09, 11/11, 12/02, 12/05, 12/12, 12/13, 12/14, 12/15, 12/18, 12/20, 12/25, 13/02, 13/04, 13/09, 13/12, 13/18, 13/19, 13/20, 13/25, 13/26, 14/01, 14/02, 14/03, 14/04, 15/03, 15/05, 15/08, 15/09, 15/10, 15/12, 15/13, 16/04, 16/06, 16/08, 16/10, 16/13, 16/18, 16/19, 16/24, 17/04, 17/05, 17/08, 17/09, 17/13, 17/15, 17/18, 18/02, 18/04, 18/09, 18/12, 18/15, 19/02, 19/07, 20/03, 20/09, 20/12, 20/18, 20/19, 21/02, 21/03, 21/04, 21/05, 21/06, 21/08, 22/03, 22/04, 22/06, 22/07, 22/08, 22/09, 22/11, 22/12, 22/13, 22/16, 22/17, 22/19, 22/23, 22/24, 23/01, 24/04, 24/06, 24/07, 25/04, 25/08, 25/09, 25/21, 26/02, 26/10, 27/03, 27/04, 27/08, 27/10, 27/12, 27/14, 28/03, 28/06, 28/07, 28/09, 28/10, 28/12, 29/01, 29/02, 29/11, 29/14, 29/20, 30/03, 30/04, 30/05, 30/06, 30/11, 30/12, 30/16, 31/02, 32/02, 32/04, 32/05, 32/06, 32/07, 32/12, 32/13, 33/06, 33/07, 33/11, 33/14, 34/02, 34/05, 34/06, 34/10, 34/11, 34/14, 35/04, 35/05, 36/04, 36/05, 36/08, 36/10, 37/02, 37/04, 37/05, 37/08, 37/09, 37/12, 37/14, 37/15, 37/16. | Rights for the purposes of the construction, installation, operation, maintenance and decommissioning of the authorised project to— a pass and re-pass with or without vehicles, plant, machinery, apparatus, equipment and materials for the purposes of the unlicensed works and the drainage works, the inspection, testing, maintenance, renewal, upgrading, replacement and removal of the cables and connection into any adjacent cables and associated works, plant and equipment on adjoining land and make such investigations in or on the land which is ancillary for the purposes of exercise of the rights; b lay down, use, repair, alter and remove steel plates for the purpose of access to adjoining land; c erect temporary bridges and supporting or protective structures for the purposes of access to adjoining land; d fell, lop, cut, coppice, uproot trees or hedges or shrubs which now or hereafter may be present on the land for the purpose of enabling the right to pass and re-pass to adjoining land; and e erect and remove temporary fencing. |
| 01/05, 01/06, 01/07 | Rights for the purposes of the construction, installation, operation, maintenance and decommissioning of the authorised project to— a pass and re-pass with or without vehicles, plant, machinery, apparatus, equipment and materials for the inspection, testing, maintenance, renewal, upgrading, replacement and removal of the cables and connection into any adjacent cables and associated works, plant and equipment on adjoining land and make such investigations in or on the land which is ancillary for the purposes of exercise of the rights; b upgrade, surface, resurface, use and repair the land for the purposes of enabling the right to pass and re-pass to adjoining land; c erect temporary bridges and supporting or protective structures for the purposes of access to adjoining land; d fell, lop, cut, coppice, uproot trees or hedges or shrubs which now or hereafter may be present on the land for the purpose of enabling the right to pass and re-pass to adjoining land; and e erect and remove temporary fencing. |
| 10/08, 10/09 | Rights for the purposes of the construction, installation, operation, maintenance and decommissioning of the authorised project to— a lay down, install, adjust, alter, construct, create, use, maintain, repair, renew, upgrade, inspect, remove and replace a drainage scheme on the land (the “drainage works”); b inspect, use mechanical excavation (including directional drilling and/or digging), reinstate, remove, move or alter such part or parts of the drainage system on the land for the purposes of the drainage works (including connecting the drainage works to any land drain as at the date of the drainage works); c enter and be on the land and remain with or without plant, vehicles, machinery, apparatus and equipment, for the purposes of the drainage works; d pass and re-pass with or without vehicles, plant, machinery, apparatus, equipment and materials for the purposes of the drainage works; e place and use machinery, structures and temporary structures within the land for the purposes of the drainage works; f erect, create and remove fencing and secure works compounds including temporary drilling and tunnelling compounds and working areas for the purposes of the drainage works; g make such investigations in or on the land as required for the purposes of the drainage works; h use or resort to trenchless construction techniques including (but not limited to) directional drilling in connection with the drainage works; i install, alter, re-lay, maintain, protect, adjust or remove pipes, cables or conduits or apparatus (including the pipes, cables or conduits or apparatus of statutory undertakers) for the purposes of the drainage works; and j construct, use and remove any necessary temporary access roads including any necessary temporary bridging, culverting or diversion of water courses and drains during any period during which construction, maintenance, repair or renewal is being carried out. |
| 01/01, 01/02,01/05, 01/06, 01/07, 01/08, 02/01,02/03, 02/05, 02/06, 02/07, 02/10, 02/12, 02/14, 02/15, 02/17, 02/18, 03/01, 03/03, 03/04, 04/01, 04/05, 04/09, 04/10, 04/11, 04/13, 04/16, 04/17, 04/18, 05/01, 05/03, 05/06, 05/08, 05/09, 05/10, 05/16, 05/21, 05/30, 05/33, 06/01, 06/02, 06/03, 06/05, 06/07, 06/08, 06/10, 06/11, 06/12, 06/13, 06/14, 07/01, 07/02, 07/05, 07/06, 07/08, 07/11, 07/12, 07/13, 07/14, 07/18, 08/01, 08/03, 08/05, 09/01, 09/02, 09/04, 09/05, 10/01, 10/04, 10/11, 10/12, 10/13, 11/01, 11/02, 11/03, 11/04, 11/06, 11/07, 11/10, 11/12, 11/13, 11/15, 11/16, 12/01, 12/03, 12/04, 12/06, 12/07, 12/08, 12/09, 12/10, 12/11, 12/16, 12/17, 12/21, 12/22, 12/24, 12/26, 13/01, 13/07, 13/11, 13/13, 13/14, 13/15, 13/16, 13/17, 13/21, 13/22, 13/23, 13/24, 15/01, 15/02, 15/04, 15/06, 15/07, 15/11, 15/15, 15/16, 15/17, 15/18, 15/19, 16/01, 16/02, 16/03, 16/05, 16/07, 16/09, 16/11, 16/12, 16/14, 16/15, 16/16, 16/17, 16/20, 16/21, 16/22, 16/23, 16/25, 17/01, 17/02, 17/03, 17/06, 17/07, 17/10, 17/11, 17/12, 17/14, 17/16, 17/17, 17/19, 17/20, 18/01, 18/03, 18/05, 18/07, 18/08, 18/13, 18/14, 18/16, 18/17, 18/18, 18/19, 19/01, 19/04, 19/05, 19/06, 19/08, 19/09, 20/01, 20/02, 20/04, 20/05, 20/06, 20/07, 20/08, 20/10, 20/15, 20/16, 20/17, 21/01, 21/07, 21/09, 22/01, 22/02, 22/05, 22/10, 22/14, 22/15, 22/18, 22/20, 22/21, 22/22, 22/25, 24/01, 24/02, 24/03, 24/05, 24/08, 24/09, 24/10, 24/11, 24/12, 24/13, 25/01, 25/02, 25/03, 25/05, 25/06, 25/07, 25/10, 25/11, 25/12, 25/13, 25/14, 25/15, 25/16, 25/18, 25/19, 25/20, 25/22, 25/23, 25/24, 26/01, 26/03, 26/06, 26/07, 26/09, 27/01, 27/06, 27/07, 27/09, 27/11, 27/13, 28/01, 28/02, 28/04, 28/05, 28/08, 28/11, 29/03, 29/04, 29/05, 29/06, 29/07, 29/08, 29/09, 29/12, 29/17, 29/18, 29/19, 29/21, 29/22, 29/23, 30/01, 30/02, 30/07, 30/08, 30/09, 30/10, 30/13, 30/14, 30/15, 30/17, 30/18, 31/01, 31/03, 31/04, 31/05, 31/06, 31/07, 31/08, 31/09, 31/10, 31/11, 31/13, 32/01, 32/03, 32/08, 32/09, 32/10, 32/11, 32/14, 33/01, 33/02, 33/04, 33/05, 33/10, 33/12, 33/13, 33/15, 33/16, 34/01, 34/03, 34/04, 34/07, 34/08, 34/09, 34/12, 34/13, 34/15, 34/16, 35/01, 35/02, 35/03, 35/06, 35/07, 35/08, 36/01, 36/06, 36/07, 36/09, 37/01, 37/06, 37/11, 37/13, 37/17, 37/18, 37/19, 37/20. | Rights for the purposes of the construction, installation, operation, maintenance and decommissioning of the authorised project to— a lay down, install, adjust, alter, construct, create, use, maintain, repair, renew, upgrade, inspect, remove and replace ramps, means of access and footpaths, bunds, embankments, swales, landscaping and boundary treatments, habitat, jointing bays, manholes and link boxes; b install, use, inspect, maintain, adjust, alter, renew, repair, test or cleanse pre- and post-development water supply, surface water management and drainage schemes on the land or reinstate the existing scheme on the land and thereafter cleanse and maintain, alter, adjust, replace, improve or extend culverts; c create boreholes; d erect, create and remove fencing and secure works compounds including temporary drilling and tunnelling compounds and working areas; e store and stockpile materials (including excavated material); f use or resort to trenchless construction techniques including (but not limited to) directional drilling beneath sea defences, watercourses, roads and railways; g remove, reconstruct, or alter the position of apparatus including mains, sewers, drains, cables and pipelines of statutory undertakers; h enter and be on the land and remain with or without plant, vehicles, machinery, apparatus and equipment, and break up the surface of the land; i pass and re-pass with or without vehicles, plant, machinery, apparatus, equipment and materials; j place, construct, use and remove plant, machinery and temporary structures in, on or over the land including any necessary temporary bridging of water courses including bailey bridges; k remove fences within the land during any period during which construction, maintenance, repair or renewal is being carried out (subject to erection of any temporary stock-proof fencing as is reasonably required and the re-instating of the original fences following the exercise of the rights); and l carry out such works (together with associated fencing) required by a planning permission and/or consent now or to be granted over the land in accordance with any necessary licences relating to protected species and/or wildlife (which for the avoidance of doubt includes newts). |
Boston Borough
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.