The Triton Knoll Electrical System Order 2016

Type Statutory-Instrument
Publication 2016-09-05
Last updated 2017-11-30
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • (6) Any dispute as to a person’s entitlement to compensation under paragraph (4), or as to the amount of compensation, must be determined under Part 1 of the 1961 Act.

Certification of plans, etc.

35

  • (1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of—
  • (a) the works plans (rev. C);
  • (b) the Order limits plans (rev. C);
  • (c) the land plans (rev. C);
  • (d) the book of reference (rev. D, dated 8th August 2016);
  • (e) the environmental statement (rev. A);
  • (f) the access to works and streets plans (rev. C);
  • (g) the hedgerow plans (rev. C);
  • (h) the public rights of way plans (rev. C);
  • (i) the crossings schedule (rev. 4.0);
  • (j) the design principles document (rev. A);
  • (k) the outline code of construction practice (onshore) (rev. C) comprising—
  • (i) the outline construction method statement (rev. E);
  • (ii) the outline health and safety plan;
  • (iii) the outline noise and vibration management plan (rev. B);
  • (iv) the outline air quality management plan;
  • (v) the outline soil management plan (rev. E);
  • (vi) the outline artificial light emissions plan;
  • (vii) the outline site waste management plan;
  • (viii) the outline pollution prevention and emergency incident response plan (rev. C);
  • (ix) the outline construction environment management plan (rev. B);
  • (x) the outline communications plan (rev. B);
  • (l) the outline landscape strategy and ecological management plan (rev. D);
  • (m) the outline traffic management plan (rev. B);
  • (n) the outline onshore written scheme of investigation (rev. B);
  • (o) the outline offshore written scheme of investigation (rev. A);
  • (p) the outline access management plan (rev. B);
  • (q) the outline offshore operations and maintenance plan (rev. A),

for certification that they are true copies of the documents referred to in this Order.

  • (2) A plan or document so certified is admissible in proceedings as evidence of the contents of the document of which it is a copy.

Arbitration

36

Any difference under any provision of this Order, unless otherwise provided for, must be referred to and settled by a single arbitrator to be agreed between the parties, or failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the Secretary of State.

Guarantees in respect of payment of compensation

37

  • (1) The undertaker must not exercise the powers conferred by the provisions referred to in paragraph (2) in relation to any land unless it has first put in place—
  • (a) a guarantee approved by the Secretary of State in respect of the liabilities of the undertaker to pay compensation under this Order in respect of the exercise of the relevant power in relation to that land; or
  • (b) an alternative form of security for that purpose approved by the Secretary of State.
  • (2) The provisions are—
  • (a) article 15 (compulsory acquisition of land);
  • (b) article 16 (compulsory acquisition of land: minerals);
  • (c) article 18 (compulsory acquisition of rights);
  • (d) article 19 (private rights);
  • (e) article 21 (acquisition of subsoil only);
  • (f) article 22 (rights under or over streets);
  • (g) article 24 (temporary use of land for carrying out authorised project);
  • (h) article 25 (temporary use of land for maintaining authorised project); and
  • (i) article 27 (statutory undertakers).
  • (3) A guarantee or alternative form of security given in respect of any liability of the undertaker to pay compensation under this Order must be treated as enforceable against the guarantor or person providing the alternative form of security by any person to whom such compensation is payable and must be in such a form as to be capable of enforcement by such a person.
  • (4) Nothing in this article requires a guarantee or alternative form of security to be in place for more than 15 years after the date on which the relevant power is exercised.

Procedure regarding certain approvals, etc.

38

  • (1) Where an application is made to, or a request is made of, the relevant planning authority, a highway authority, a street authority or the owner of a watercourse, sewer or drain for any consent, agreement or approval required or contemplated by any of the provisions of this Order, the consent, agreement or approval must, if given, be given in writing and is not to be unreasonably withheld or delayed.
  • (2) Schedule 11 (procedure for discharge of Requirements) has effect in relation to all consents, agreements or approvals granted, refused or withheld in relation to the Requirements unless otherwise agreed in writing between the undertaker and the relevant planning authority.

Saving provisions for Trinity House

39

Nothing in this Order prejudices or derogates from any of the rights, duties or privileges of Trinity House.

Crown rights

40

  • (1) Nothing in this Order affects prejudicially any estate, right, power, privilege, authority or exemption of the Crown and, in particular, nothing in this Order authorises the undertaker or any licensee to take, use, enter on or in any manner interfere with any land or rights of any description (including any portion of the shore or bed of the sea or any river, channel, creek, bay or estuary)—
  • (a) belonging to Her Majesty in right of the Crown and forming part of the Crown Estate without the consent in writing of the Crown Estate Commissioners;
  • (b) belonging to Her Majesty in right of the Crown and not forming part of the Crown Estate without the consent in writing of the government department having the management of that land; or
  • (c) belonging to a government department or held in trust for Her Majesty for the purposes of a government department without the consent in writing of that government department.
  • (2) Paragraph (1) does not apply to the exercise of any right under this Order for the compulsory acquisition of an interest in any Crown land (as defined in the 2008 Act) which is for the time being held otherwise than by or on behalf of the Crown.
  • (3) A consent under paragraph (1)—
  • (a) may be given unconditionally or subject to terms and conditions;
  • (b) is deemed to have been given in writing where it is sent electronically.

SCHEDULE 1 — Authorised project

PART 1 — Authorised development

1

Development which, in accordance with a direction made by the Secretary of State under section 35 of the 2008 Act on 14th November 2013, is development for which development consent is required on the bed of the North Sea from the coast to approximately 33 kilometres off the coast of Lincolnshire and 46 kilometres off the coast of Norfolk within the Renewable Energy Zone and within the County of Lincolnshire and the District of East Lindsey and Borough of Boston, comprising—

Offshore

Work No. 1 – up to 6 cables for the transmission of high voltage alternating current electricity laid on or beneath the seabed between the collector substations and Work No. 2 including pipeline crossings and cable protection;

In the County of Lincolnshire, District of East Lindsey

Work No. 2 – up to 6 cables for the transmission of high voltage alternating current electricity laid on or beneath the seabed and/or underground in cable ducts from mean low water connecting Work No. 1 and Work No. 3;

Work No. 38 – a temporary construction compound to the north side of North Forty Foot Bank including access from the public highway;

Work No. 39 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 37 in a generally south-south westerly direction for a distance of 3.9 kilometres to Work No. 42 including accesses for construction from the public highway and temporary haul roads;

Work No. 40 – a temporary construction compound to the north side of Sutterton Drove including access from the public highway;

Work No. 41 – a temporary construction compound to the west side of Claydike Bank including access from the public highway;

Work No. 42 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 39 in a generally south-south westerly direction for a distance of 1.8 kilometres to Work No. 44 including accesses for construction from the public highway and temporary haul roads;

Work No. 43 – a temporary construction compound to the north side of the A17 highway including access from the public highway;

Work No. 44 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 42 in a generally south-south westerly direction for a distance of 0.6 kilometres to Work No. 46 including accesses for construction from the public highway and temporary haul roads;

Work No. 45 – a temporary construction compound to the south side of the A17 highway including access from the public highway;

Work No. 46 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 44 in a generally south westerly direction for a distance of 3.4 kilometres to Work No. 50 including accesses for construction from the public highway and temporary haul roads;

Work No. 47A – a temporary construction compound to the west side of the A17 highway and to the north of Work No. 49 including access from the public highway;

Work No. 48 – a permanent access from the A17 to Work No. 50 including security gates;

Work No. 49 – a temporary access from the A17 to Work No. 50 including security fencing and access from the public highway;

Work No. 50 –

  • (a) the substation enabling works;
  • (b) Work No. 50A – a compound for the connection of the electrical circuits to the transmission network (the “substation compound”) containing (but not limited to) switchgear and electrical equipment including power transformers, reactive compensation equipment, filters, cooling equipment, control and welfare buildings, lightning rods, internal roads, security fencing and other associated equipment, structures and buildings including noise-attenuation works;
  • (c) landscaping and drainage, utilities connections, temporary and permanent access roads, a security gate, cabling and ducting to the north west of the existing National Grid substation at Bicker Fen;

Work No. 51 – the temporary construction compound for Work No. 50;

Work No. 52 – up to 4 electrical circuits for the transmission of high voltage alternating current electricity including earthing connections between Work Nos. 50 and 55 laid underground in cable ducts from Work No. 50 in a generally south easterly direction for a distance of 1.3 kilometres to the connection point at the National Grid substation at Bicker Fen including earthing connections between Work Nos. 50 and 54, accesses for construction, operations and maintenance;

Work No. 53 – a temporary construction compound to the north side of the National Grid substation at Bicker Fen.

2 Associated development comprising the following— Work No. 54 – a unlicensed works at the National Grid substation at Bicker Fen including cable ducts and cabling; b Work No. 54A – connecting bays at the northern part of the National Grid substation at Bicker Fen housing circuit breakers, cable sealing ends, dis-connectors, surge arrestors, transformers, busbars and busbar clamps, measuring equipment and relay/marshalling rooms; c Work No. 54B – a connection bay at the southern part of the National Grid substation at Bicker Fen housing circuit breakers, cable sealing ends, dis-connectors, surge arrestors, transformers, busbars and busbar clamps, measuring equipment and relay/marshalling rooms; d electrical earthing works; Work No. 55 – up to 2 electrical circuits for the transmission of high voltage alternating current electricity including earthing connections between Work Nos. 52 and 54 laid underground in cable ducts from Work No. 52 in a generally southerly direction for a distance of 0.3 kilometres to Work No. 54B including landscaping; Work No. 56 – temporary highways alterations.

3 In connection with Work Nos. 2 to 56, further associated development shown on the plans referred to in, or approved under, the Requirements including— a ramps, means of access and footpaths; b bunds, embankments, swales, landscaping and boundary treatments; c habitat creation; d boreholes; e jointing bays, manholes, link boxes, marker posts and other works associated with the installation of cable ducts and electrical circuits including trenchless techniques, tunnelling works beneath sea defences, watercourses and roads and trenchless techniques launch and receptor pits; f water supply works, foul drainage provision and surface water management systems; g temporary structures including those needed to facilitate the crossing of watercourses including bailey bridges; h temporary construction laydown areas and compounds including accesses and their restoration; i temporary drilling and tunnelling compounds and working areas and their restoration; j works to remove, reconstruct or alter the position of apparatus including mains, sewers, drains, cables and pipelines; and k such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project, which fall within the scope of the works assessed by the environmental statement.

4 The grid co-ordinates for the part of the authorised project which is seaward of MHWS are specified below and more particularly shown on the Order limits plans— Co-ordinates for Order limits seaward of MHWS PointLatitude (DMS)Longitude (DMS)PointLatitude (DMS)Longitude (DMS) AI53° 32′ 16.234″ N0° 51′ 40.692″ EG53° 17′ 0.671″ N0° 23′ 40.084″ EAJ53° 24′ 31.248″ N0° 59′ 39.385″ EH53° 17′ 20.885″ N0° 24′ 5.700″ EAS53° 22′ 56.159″ N0° 46′ 8.201″ EI53° 17′ 25.462″ N0° 24′ 16.736″ EAT53° 22′ 35.877″ N0° 45′ 39.771″ EJ53° 19′ 9.809″ N0° 25′ 20.599″ EAU53° 20′ 58.870″ N0° 45′ 30.470″ EK53° 19′ 38.094″ N0° 25′ 44.472″ EAV53° 20′ 18.829″ N0° 44′ 23.598″ EL53° 20′ 27.460″ N0° 26′ 42.541″ EAW53° 20′ 2.612″ N0° 43′ 18.260″ EM53° 20′ 43.520″ N0° 27′ 29.635″ EAX53° 20′ 1.822″ N0° 41′ 58.661″ EN53° 20′ 46.705″ N0° 28′ 38.086″ EAY53° 20′ 4.107″ N0° 41′ 22.273″ EO53° 20′ 39.043″ N0° 34′ 13.401″ EAZ53° 20′ 1.898″ N0° 40′ 30.850″ EP53° 20′ 31.962″ N0° 35′ 58.445″ EBA53° 19′ 58.395″ N0° 39′ 51.749″ EQ53° 20′ 32.022″ N0° 36′ 28.081″ EBB53° 19′ 59.805″ N0° 37′ 16.544″ ER53° 20′ 35.314″ N0° 37′ 11.880″ EBC53° 19′ 56.528″ N0° 36′ 32.931″ ES53° 20′ 33.895″ N0° 39′ 46.605″ EBD53° 19′ 56.382″ N0° 35′ 55.878″ ET53° 20′ 37.303″ N0° 40′ 24.656″ EBE53° 20′ 3.584″ N0° 34′ 8.235″ EU53° 20′ 39.751″ N0° 41′ 23.781″ EBF53° 20′ 11.127″ N0° 28′ 36.545″ EV53° 20′ 37.410″ N0° 42′ 1.047″ EBG53° 20′ 7.964″ N0° 27′ 43.904″ EW53° 20′ 37.931″ N0° 43′ 9.122″ EBH53° 20′ 1.938″ N0° 27′ 23.706″ EX53° 20′ 47.002″ N0° 43′ 46.826″ EBI53° 19′ 17.721″ N0° 26′ 33.517″ EY53° 21′ 11.473″ N0° 44′ 32.598″ EBJ53° 18′ 55.345″ N0° 26′ 14.927″ EZ53° 22′ 14.571″ N0° 44′ 36.340″ EBK53° 17′ 2.447″ N0° 25′ 4.201″ EAA53° 22′ 50.453″ N0° 44′ 45.224″ EBL53° 16′ 54.685″ N0° 24′ 46.623″ EAB53° 23′ 37.771″ N0° 45′ 8.186″ EBM53° 16′ 37.940″ N0° 24′ 25.834″ EAC53° 24′ 10.968″ N0° 45′ 42.526″ EBN53° 16′ 4.626″ N0° 23′ 15.114″ EAD53° 25′ 2.619″ N0° 44′ 32.111″ EBO53° 15′ 55.271″ N0° 21′ 40.714″ EAE53° 28′ 4.193″ N0° 44′ 10.434″ EBP53° 15′ 52.991″ N0° 20′ 45.646″ EAF53° 28′ 19.752″ N0° 44′ 13.790″ EBQ53° 15′ 51.994″ N0° 20′ 34.705″ EAG53° 29′ 12.732″ N0° 41′ 28.840″ EBR53° 15′ 51.249″ N0° 19′ 42.683″ EAH53° 31′ 42.626″ N0° 42′ 58.368″ EBS53° 15′ 58.542″ N0° 19′ 24.827″ EAR53° 24′ 6.378″ N0° 48′ 43.578″ EBT53° 16′ 0.730″ N0° 19′ 19.467″ EAQ53° 24′ 46.233″ N0° 49′ 44.994″ EA53° 16′ 6.688″ N0° 19′ 15.877″ EAP53° 25′ 38.625″ N0° 52′ 49.002″ EB53° 16′ 23.419″ N0° 19′ 35.327″ EAO53° 25′ 38.029″ N0° 53′ 0.402″ EC53° 16′ 27.466″ N0° 20′ 29.534″ EAN53° 25′ 21.824″ N0° 53′ 25.522″ ED53° 16′ 28.433″ N0° 20′ 40.181″ EAM53° 24′ 38.801″ N0° 55′ 38.414″ EE53° 16′ 30.664″ N0° 21′ 34.324″ EAL53° 24′ 39.002″ N0° 56′ 17.146″ EF53° 16′ 38.211″ N0° 22′ 53.464″ EAK53° 24′ 31.246″ N0° 56′ 45.454″ E

Work No. 19 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 17 in a generally south westerly direction for a distance of 2.3 kilometres to Work No. 21 including accesses for construction from the public highway and temporary haul roads;

Work No. 20 – a temporary construction compound to the south side of Station Road including access from the public highway;

Work No. 21 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 19 in a generally south westerly direction for a distance of 2.5 kilometres to Work No. 22 including accesses for construction from the public highway and temporary haul roads;

Work No. 22 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 21 in a generally south westerly direction for a distance of 4.4 kilometres to Work No. 24 including accesses for construction from the public highway and temporary haul roads;

Work No. 23 – a temporary construction compound to the east side of Hobhole Bank including access from the public highway;

Work No. 24 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 22 in a generally south westerly direction for a distance of 1.3 kilometres to Work No. 26 including accesses for construction from the public highway and temporary haul roads;

Work No. 25 – a temporary construction compound to the north side of Fodder Dike including access from the public highway;

Work No. 26 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 24 in a generally south-south westerly direction for a distance of 4.3 kilometres to Work No. 29 including accesses for construction from the public highway and temporary haul roads;

Work No. 27 – a temporary construction compound to the east side of the A16 highway including access from the public highway;

Work No. 28 – a temporary construction compound to the west side of the A16 highway including access from the public highway;

Work No. 29 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 26 in a generally south westerly direction for a distance of 3.6 kilometres to Work No. 31 including accesses for construction from the public highway and temporary haul roads;

Work No. 30 – a temporary construction compound to the west side of Staunt Road including access from the public highway;

Work No. 31 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 29 in a generally south westerly direction for a distance of 1 kilometre to Work No. 33 including accesses for construction from the public highway and temporary haul roads;

Work No. 32 – a temporary construction compound to the east side of Carrington Road including access from the public highway;

Work No. 33 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 31 in a generally south-south westerly direction for a distance of 5 kilometres to Work No. 37 including accesses for construction from the public highway and temporary haul roads;

Work No. 34 – a temporary construction compound to the north side of Leagate Road including access from the public highway;

Work No. 35 – a temporary construction compound to the north side of Mere Booth Road including access from the public highway;

Work No. 36 – a temporary construction compound to the south side of Mere Booth Road including access from the public highway;

In the County of Lincolnshire, Borough of Boston

Work No. 37 – up to 6 electrical circuits for the transmission of high voltage alternating current electricity laid underground in cable ducts from Work No. 33 in a generally south westerly direction for a distance of 2.3 kilometres to Work No. 39 including accesses for construction from the public highway and temporary haul roads;

PART 2 — Ancillary works

Works and operations within the Order limits and which fall within the scope of the work assessed by the environmental statement comprising—

  • (a) temporary landing places, moorings or other means of accommodating vessels in the construction or maintenance of the authorised development;
  • (b) temporary or permanent buoys, beacons, fenders and other navigational warning or ship impact protection works;
  • (c) temporary works for the protection of land or structures affected by the authorised development;
  • (d) cable route preparation works including grapnel runs and pre-lay jetting; and
  • (e) the removal, reconstruction or alteration of the position of subsea cables.

PART 3 — Requirements

Interpretation

1

In this Part—

  • “above-ground infrastructure” means the buildings, busbars, capacitors, reactors, reactive power compensation equipment, filters, cooling equipment, control and welfare buildings, lightning rods, security fencing and other associated equipment, structures and buildings including noise-attenuation panels required for the intermediate electrical compound and the substation compound (Work No. 50A);
  • “AIS” means air-insulated switchgear;
  • “AOD” means above ordnance datum;
  • “GIS” means gas-insulated switchgear;
  • “stage” means one of the following 28 stages of the onshore works— the IEC enabling works (using the temporary construction compound at Work No. 10); the substation enabling works (using the temporary construction compound at Work No. 51); Work Nos. 3 and 4 including Work Nos. 3A and 3B (using the temporary construction compound at Work No. 3B); Work No. 5 (using the temporary construction compound at Work No. 6); Work No. 8 (using the temporary construction compound at Work No. 7); Work No. 9 excluding the IEC enabling works and Work No. 9A (using the temporary construction compound at Work No. 10); Work No. 9A (using the temporary construction compound at Work No. 10); Work No. 11 (using the temporary construction compound at Work No. 12); Work No. 14 (using the temporary construction compounds at Work Nos. 13 and 15); Work No. 17 (using the access at Work No. 16); Work No. 19 (using the temporary construction compound at Work No. 18); Work No. 21 (using the temporary construction compound at Work No. 20); Work No. 22 (using the temporary construction compound at Work No. 23); Work No. 24 (using the temporary construction compound at Work No. 25); Work No. 26 (using the temporary construction compounds at Work Nos. 27 and 28); Work No. 29 (using the temporary construction compound at Work No. 30); Work No. 31 (using the temporary construction compound at Work No. 32); Work No. 33 (using the temporary construction compounds at Work Nos. 34, 35 and 36); Work No. 37 (using the temporary construction compound at Work No. 38); Work No. 39 (using the temporary construction compounds at Work Nos. 40 and 41); Work No. 42 (using the temporary construction compound at Work No. 43); Work No. 44 (using the temporary construction compound at Work No. 45); Work No. 46 (using the temporary construction compound at Work No. 47A or 51 and access at Work No. 48); Work Nos. 48 and 49 (using the temporary construction compound at Work No. 47A); Work No. 50 excluding the substation enabling works and Work No. 50A (using the temporary construction compound at Work No. 51); Work No. 50A (using the temporary construction compound at Work No. 51); Work No. 52 (using the temporary construction compound at Work No. 53); Work No. 55 (using the temporary construction compound at Work No. 53),

or such other stage of the onshore works agreed in writing with the relevant planning authority.

Time limit for commencing authorised development

2

The authorised development must be commenced on or before 26th September 2021.

Detailed offshore design parameters

3

  • (1) The total number of cables comprising Work No. 1 must not exceed 6.
  • (2) The total length of the cables comprising Work No. 1 must not exceed 396 kilometres.
  • (3) The total amount of cable protection for the cables comprising Work No. 1 must not exceed 367,200 square metres and 320,760 cubic metres.
  • (4) The finished height of any cable protection must not exceed 10% of the navigable water depth existing before works commence unless otherwise agreed in writing in advance with the MMO and the MCA.

Offshore decommissioning

4

No part of the development seaward of MHWS may be commenced until a written decommissioning programme in compliance with any notice served on the undertaker by the Secretary of State under section 105(2) of the Energy Act 200438 has been submitted to the Secretary of State for approval.

Detailed design onshore

5

  • (1) The IEC enabling works and the substation enabling works must not be commenced until details of the ground-raising and stoned site platform have been submitted to and approved by the relevant planning authority.
  • (2) No part of Work No. 9A may be commenced until details of the layout, scale and external appearance of the above-ground infrastructure including permanent fencing relating to Work No. 9A have been submitted to and approved by the relevant planning authority.
  • (3) No part of Work No. 50A may be commenced until—
  • (a) details of the layout, scale and external appearance of the above-ground infrastructure including permanent fencing relating to Work No. 50A have been submitted to and approved by the relevant planning authority; and
  • (b) the undertaker has notified the relevant planning authority whether AIS or GIS is to be installed for Work No. 50A.
  • (4) Any details provided by the undertaker under paragraphs (2) and (3) must, where relevant to that stage, be in accordance with the design principles document.
  • (5) Finished floor levels for Work Nos. 9A and 50A must, after consultation with the Environment Agency, be based on the results of topographic surveys.
  • (6) In relation to Work No. 3A—
  • (a) the total area in which the landfall transition joint bays may be contained must not exceed 20,288 square metres;
  • (b) the total area of land raising must not exceed 5,000 square metres; and
  • (c) the total number of landfall transition joint bays must not exceed 6.
  • (7) In relation to Work No. 9A—
  • (a) the highest part of any building must not exceed 16.54 metres AOD;
  • (b) the highest part of any external electrical equipment, excluding lightning rods, must not exceed 14.04 metres AOD;
  • (c) the total number of lightning rods within the fenced compound must not exceed 4 and the height of any lightning rod must not exceed 21.54 metres AOD;
  • (d) the total area of the fenced compound (excluding its accesses) must not exceed 17,000 square metres; and
  • (e) any GIS building may be located only within the dotted area shown within Work No. 9A on the works plans.
  • (8) In relation to Work No. 50A—
  • (a) if AIS is installed—
  • (i) the highest part of any building must not exceed 10 metres AOD;
  • (ii) the highest part of any external electrical equipment, excluding lightning rods, must not exceed 15 metres AOD; and
  • (iii) the total area of the fenced compound (excluding its accesses) must not exceed 86,000 square metres;
  • (b) if GIS is installed—
  • (i) the highest part of any building must not exceed 16 metres AOD;
  • (ii) the highest part of any external electrical equipment, excluding lightning rods, must not exceed 13.5 metres AOD; and
  • (iii) the total area of the fenced compound (excluding its accesses) must not exceed 69,000 square metres; and
  • (c) the total number of lightning rods within the fenced compound must not exceed 22 and the height of any lightning rod must not exceed 21 metres AOD.
  • (9) In relation to Work No. 54—
  • (a) the total number of connection bays must not exceed 2;
  • (b) the connection bays may be located only within the hatched areas shown within Work Nos. 54A and 54B on the works plans; and
  • (c) if 2 connection bays are accommodated within Work No. 54A, Work Nos. 54B and 55 must not be constructed.
  • (10) Unless otherwise agreed by the relevant planning authority, after consultation with the relevant drainage boards, the Environment Agency and the highways authority, where identified in the crossings schedule for the purpose of passing under a relevant obstruction, trenchless techniques must be used to install the cable ducts and electrical circuits within Work Nos. 2, 3, 5, 8, 11, 14, 17, 19, 21, 22, 24, 26, 29, 31, 33, 37, 39, 42, 44 and 46.
  • (11) The undertaker must—
  • (a) at least 3 months before the commencement of the onshore cable works—
  • (i) submit to the relevant planning authority a cable route sequencing plan including details of the indicative sequencing of the onshore cable works; and
  • (ii) notify the public and owners of land of the sequencing of the onshore cable works in accordance with the communications plan approved as part of the code of construction practice;
  • (b) before construction of any stage of the onshore cable works, submit to the relevant planning authority a copy of the cable installation plans provided to owners in accordance with the soil management plan approved as part of the code of construction practice; and
  • (c) within 3 months of the completion of the installation of the cable circuits for any stage of the onshore cable works, submit to the relevant planning authority as built plans for that stage showing the alignment of the cable circuits.
  • (12) Any plans submitted in accordance with paragraph (11)(a) and (b) may be updated from time to time and must be submitted to the relevant planning authority and communicated to owners and the public in accordance with the code of construction practice.
  • (13) In this Requirement, “onshore cable works” means Work Nos. 3, 5, 8, 11, 14, 17, 19, 21, 22, 24, 26, 29, 31, 33, 37, 39, 42, 44, 46 and 52.

Provision of landscaping

6

  • (1) Work Nos. 9A and 50A must not be commenced until a written landscaping scheme and associated work programme (in accordance with the outline landscape strategy and ecological management plan) for the relevant work has been submitted to and approved by the relevant planning authority.
  • (2) The written landscaping scheme must include details of all proposed hard and soft landscaping works including—
  • (a) location, number, species, size and planting density of any proposed planting including any trees; and
  • (b) implementation timetables for all landscaping works.
  • (3) If Work No. 55 is constructed before the completion of the unlicensed works, a written landscaping scheme and associated work programme (in accordance with the outline landscape strategy and ecological management plan) must be submitted to and approved by the relevant planning authority after consultation with National Grid Electricity Transmission plc (company number 02366977).

Implementation and maintenance of landscaping

7

  • (1) All landscaping works must, where relevant, be carried out in accordance with the landscaping scheme approved under Requirement 6.
  • (2) Any tree or shrub planted as part of an approved landscaping scheme that, within 10 years after planting, is removed, dies or becomes, in the reasonable opinion of the relevant planning authority, seriously damaged or diseased must be replaced in the first available planting season with a specimen of the same species and size as that originally planted.

Highway accesses and improvements

8

  • (1) No stage of the onshore works may be commenced until for that stage written details (which accord with the outline access management plan) of the siting, design, layout, sequencing and timing and any access management measures for any new permanent or temporary means of access to a highway to be used by vehicular traffic, or any alteration to an existing means of access to a highway, have, after consultation with the highway authority, been submitted to and approved by the relevant planning authority.
  • (2) The highway accesses for that stage must be constructed or altered, and the works described in paragraph (1) in relation to access management measures carried out, in accordance with the approved details before the relevant highway accesses are brought into use for the purposes of the authorised development.
  • (3) No stage of the onshore works may be commenced until for that stage a scheme of temporary highways alterations within the highway boundary has, after consultation with the highway authority, been submitted to and approved by the relevant planning authority.
  • (4) The temporary highways alterations for that stage must be constructed in accordance with the approved scheme before they are brought into use for the purposes of the authorised development.

Fencing and other means of enclosure

9

  • (1) No stage of the onshore works may be commenced until for that stage written details of all proposed fences, walls or other means of enclosure have been submitted to and approved by the relevant planning authority.
  • (2) All temporary construction compounds must remain securely fenced in accordance with the approved details at all times during construction of the onshore works.
  • (3) Temporary fencing, except temporary fencing for the beach works, must be removed on completion of the relevant stage of the onshore works.
  • (4) Temporary fencing for the beach works must be removed on completion of construction of those works excluding testing.
  • (5) Any approved permanent fencing in relation to Work Nos. 9A and 50A must be completed before the relevant Work is brought into use and maintained for the operational lifetime of Work Nos. 9A and 50A.
  • (6) In this Requirement, “beach works” means Work No. 2 and works related to the installation of cable ducts and cable circuits within Work No. 3 but excluding Work Nos. 3A and 3B.

Requirement for surface water drainage scheme

10

  • (1) Work Nos. 9, 50, 54A and 54B must not be commenced until a surface water drainage scheme for the Work, or part of the Work, in question has, after consultation with Lincolnshire County Council and the relevant drainage boards, been submitted to and approved by the relevant planning authority.
  • (2) The surface water drainage scheme submitted under paragraph (1) must be based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the authorised development and must be in accordance with the surface water drainage strategy submitted as part of the flood risk assessment included within the environmental statement.
  • (3) Where relevant to the Work, or part of the Work, in question, the scheme must include—
  • (a) provision for limiting the surface water run-off generated by all rainfall events up to the 1 in 100 year plus 20% (for climate change) critical rain storm so that it will not exceed the run-off from the undeveloped site and not increase the risk of flooding off-site;
  • (b) provision of surface water run-off attenuation storage to accommodate the difference between the allowable discharge rates and all rainfall events up to the 1 in 100 year plus 20% (for climate change) critical rain storm;
  • (c) detailed design (plans, cross-sections and calculations) in support of any surface water drainage scheme including details of any attenuation system and the outfall arrangements;
  • (d) details of how the scheme is to be maintained and managed after completion; and
  • (e) details of percolation testing (carried out in accordance with Building Research Establishment Digest 365 or Construction Industry Research and Information Association guidance R156) to demonstrate that the use of infiltration techniques are suitable.
  • (4) The surface water drainage scheme must be implemented as approved.
  • (5) In this Requirement, “relevant drainage boards” means the drainage boards within the meaning of section 25 of the Land Drainage Act 199139 for the area in which the Work is situated.

Requirement for foul water drainage scheme

11

  • (1) Work Nos. 9 and 50 must not be commenced until a detailed foul water drainage scheme (including means of pollution control) for the Work, or part of the Work, in question has, after consultation with Anglian Water Services Limited (company number 02366656) and the Environment Agency, been submitted to and approved by the relevant planning authority.
  • (2) The foul water drainage scheme must be implemented as approved.

Archaeology

12

  • (1) No stage of the onshore works may be commenced until for that stage a written scheme of investigation in accordance with the outline onshore written scheme of investigation has been submitted to and approved by the relevant planning authority.
  • (2) The approved scheme must—
  • (a) identify areas where archaeological work is required; and
  • (b) the measures to be taken to protect, record or preserve any significant archaeological remains (as defined in the outline onshore written scheme of investigation) that may be found.
  • (3) Pre-construction archaeological investigations and pre-commencement material operations which involve intrusive ground works may take place only in accordance with a specific written scheme of investigation which—
  • (a) is in accordance with the details set out in the outline onshore written scheme of investigation; and
  • (b) has been submitted to and approved by the relevant planning authority.
  • (4) Any archaeological works must be carried out by a suitably qualified and competent person or body previously notified to the relevant planning authority.
  • (5) The written scheme of investigation must be implemented as approved.

Ecological management plan and removal of hedgerows

13

  • (1) No stage of the onshore works may be commenced until for that stage a written ecological management plan (which accords with the outline landscape strategy and ecological management plan) reflecting the survey results and ecological mitigation and enhancement measures included in the environmental statement has after consultation with the appropriate statutory nature conservation body been submitted to and approved by the relevant planning authority.
  • (2) The ecological management plan must include an implementation timetable and measures to be taken to reinstate hedgerows on completion of the relevant stage of the onshore works.
  • (3) The ecological management plan must be implemented as approved.
  • (4) Any hedgerow removal or replacement undertaken before approval of the written ecological management plan under paragraph (1) must be carried out in accordance with the details set out in the outline landscape strategy and ecological management plan.

Code of construction practice

14

  • (1) No stage of the onshore works may be commenced until for that stage a code of construction practice in accordance with the outline code of construction practice (onshore) has, after consultation with the Environment Agency, been submitted to and approved by the relevant planning authority.
  • (2) The code of construction practice must, where relevant to that stage, cover all the matters set out in the outline code of construction practice (onshore).
  • (3) The code of construction practice must include—
  • (a) a construction method statement including details of the management of public rights of way and methods (including trenchless and non-trenchless techniques) for the crossing of watercourses (main river crossings to be undertaken using trenchless techniques only);
  • (b) a health and safety plan;
  • (c) a noise and vibration management plan;
  • (d) an air quality management plan;
  • (e) a soil management plan;
  • (f) an artificial light emissions plan;
  • (g) a site waste management plan;
  • (h) a pollution prevention and emergency incident response plan;
  • (i) a construction environment management plan; and
  • (j) a communications plan.
  • (4) The soil management plan (which forms part of the code of construction practice) must, where relevant to a stage, secure that any link box located in a place where agricultural machinery may pass over it has a cover that is—
  • (a) capable of bearing agricultural machinery loads; and
  • (b) designed so as to allow the wheels or tracks of agricultural machinery to pass over the link box without damaging the wheels or tracks of the machinery or the link box.
  • (5) The code of construction practice must be implemented as approved.

Unexpected contamination

15

  • (1) If, during any stage of the authorised development, contamination not identified or addressed within the relevant code of construction practice is found to be present within the Order limits, no further development in the vicinity of the contamination may be carried out until a written scheme to deal with the associated risks has been submitted to and approved by the relevant planning authority after consultation with the Environment Agency.
  • (2) The scheme must include an investigation and assessment report, prepared by a specialist consultant notified in advance to the relevant planning authority, the purpose of which is to identify the extent of any contamination and the remedial measures to be taken to render the land fit for its intended purpose, together with a management plan which sets out long-term measures with respect to any contaminants remaining on site.
  • (3) No remedial work identified in accordance with paragraph (2) may be carried out until the scheme has been approved.
  • (4) The scheme and management plan must be implemented as approved.

Control of operational artificial light emissions

16

  • (1) Work Nos. 9A and 50A must not be brought into operation until a written scheme for the management and mitigation of artificial light emissions for the relevant Work has been submitted to and approved by the relevant planning authority.
  • (2) The approved schemes for the management and mitigation of artificial light emissions must be implemented and maintained during the lifetime of Work Nos. 9A and 50A.

Construction hours

17

  • (1) Except as otherwise agreed in the code of construction practice and subject to paragraphs (2) to (4), construction of the onshore works and construction-related traffic movements to or from the site of the relevant Work may take place only between 7 a.m. and 7 p.m. from Monday to Saturday, with no activity on Sundays or bank holidays.
  • (2) If agreed in advance with the relevant planning authority, construction of the onshore works and construction-related traffic movements to or from the site of the relevant Work may take place outside the hours specified in paragraph (1) for certain identified works including—
  • (a) where continuous periods of construction are required, for works such as concrete pouring and finishing, electrical circuit pulling and jointing and testing;
  • (b) for the delivery and unloading of abnormal loads;
  • (c) for the landfall works; and
  • (d) for any other time-critical element of the onshore works.
  • (3) Except as provided in paragraph (4), all construction works which are to be undertaken outside the hours specified in paragraph (1) must be agreed in advance with the relevant planning authority.
  • (4) In respect of trenchless techniques—
  • (a) where continuous 24-hour working is required, the undertaker must notify the relevant planning authority in advance of such works;
  • (b) where a trenchless technique is to take place within 100 metres of an occupied dwelling, the works must take place within the hours specified in paragraph (1) unless otherwise agreed in advance with the resident of that dwelling and notified to the relevant planning authority.

Control of noise during operational phase

18

  • (1) The rating level of the overall operational noise immissions from Work No. 9A or 50A must not exceed 35 dB LAeq (5 min.) free-field (as defined in and measured in accordance with BS4142:2014 including any relevant penalties for tonal or impulsive character) at any residential property that lawfully exists on the date on which this Order is made.
  • (2) In the event of a complaint to the relevant planning authority relating to noise immissions from the operation of Work No. 9A or 50A which may reasonably be expected to result in levels above those allowed by paragraph (1)—
  • (a) the undertaker must submit a proposed measurement and assessment procedure, based on the guidance and assessment methodology outlined in BS4142:2014, including a proposed measurement methodology and monitoring locations to the relevant planning authority for approval;
  • (b) measurements must be undertaken in accordance with the approved procedure by an independent consultant appointed by the undertaker in order to determine compliance or otherwise with paragraph (1).

Construction traffic

19

  • (1) No stage of the onshore works may be commenced until for that stage, after consultation with the highway authority, a construction traffic management plan in accordance with the outline traffic management plan including a contractor travel plan has been submitted to and approved by the relevant planning authority.
  • (2) Construction and contractor traffic related to the authorised development must use only Work No. 48 or 49 to access Work Nos. 50 to 55.
  • (3) The timings for the construction of Work Nos. 48 and 49 must be included within the construction method statement approved as part of the relevant code of construction practice.
  • (4) The construction traffic management plan and contractor travel plan must be implemented as approved.

European protected species

20

  • (1) No stage of the onshore works may be commenced until for that stage final pre-construction survey work has been carried out to establish whether a European protected species is present on any of the land affected, or likely to be affected, by that stage of the onshore works or in any of the trees to be lopped or felled as part of that stage of the onshore works.
  • (2) Where a European protected species is shown to be present, the relevant stage of the onshore works may not be commenced until, after consultation with the statutory nature conservation body and the relevant planning authority, a scheme of protection and mitigation measures has been submitted to and approved by the relevant planning authority.
  • (3) The relevant stage of the onshore works must be carried out in accordance with the approved scheme.
  • (4) In this Requirement, “European protected species” means a European protected species of animal or plant within the meaning of Part 3 of the Conservation of Habitats and Species Regulations 2017.

Restoration of land used temporarily for construction

21

  • (1) Any land landward of MHWS which is used temporarily for construction of the onshore works and not ultimately incorporated in permanent works or approved landscaping must be reinstated within 6 months of completion of the relevant stage of the onshore works in accordance with details approved by the relevant planning authority.
  • (2) Any hedgerow reinstatement must be carried out on accordance with Requirement 13(3).

Onshore decommissioning

22

Within 6 months of the cessation of commercial operation of the onshore works, and after consultation with owners in relation to their landholding, an onshore decommissioning plan must be submitted to the relevant planning authority for approval.

Local employment

23

  • (1) No stage of the onshore works within a relevant planning authority’s area may be commenced until, after consultation with the relevant planning authority and the Greater Lincolnshire Local Enterprise Partnership, a plan detailing arrangements to promote local employment and skills development opportunities related to the onshore works has been notified to the relevant planning authority.
  • (2) The plan must include proposals for working with the Greater Lincolnshire Local Enterprise Partnership and the relevant planning authority to promote such opportunities.
  • (3) The employment and skills plan must be implemented and maintained for the duration of the construction of the onshore works.

Approval, etc. to be in writing

24

Where the approval or agreement of the Secretary of State or the relevant planning authority is required under a Requirement, that approval or agreement must be given in writing.

Amendments to approved plans, etc.

25

  • (1) Where a Requirement requires the authorised development to be carried out in accordance with a plan, scheme, statement, strategy or details (the “plan”) approved by the relevant planning authority, the plan must be carried out as approved unless an amendment is previously agreed in writing by the relevant planning authority in accordance with paragraph (2).
  • (2) Any amendment to the approved plan must be in accordance with the principles and assessments set out in the environmental statement and the other documents set out in article 35; and the agreement of the relevant planning authority to an amendment may be given only where it has been demonstrated to the satisfaction of the relevant planning authority that the amendment is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
  • (3) The approved plan must be taken to include any amendment that may subsequently be approved in writing by the relevant planning authority.

SCHEDULE 2 — Streets subject to street works

(1) District (2) Street subject to street works (see access to works and streets plans) (3) Grid co-ordinates (3) Grid co-ordinates
(1) District (2) Street subject to street works (see access to works and streets plans) Easting Northing
East Lindsey Hutt/10/4/footpath 554608 376836
East Lindsey 554503 376813
East Lindsey Ande/17/2/footpath 554237 376293
East Lindsey Ande/25/1/footpath 553749 375398
East Lindsey Sea Road 553747 375899
East Lindsey Roman Bank 554325 376452
East Lindsey Roman Bank 554192 376734
East Lindsey Hutt/10/4/footpath 554197 376740
East Lindsey Ande/22/4/footpath 553722 375727
East Lindsey Ande/23/1/footpath 553722 375727
East Lindsey Ande/22/3/footpath 553722 375727
East Lindsey Mumb/26/1/footpath 553404 375064
East Lindsey Mumb/59/8/footpath 553278 374481
East Lindsey Mumb/61/1/footpath 553076 374192
East Lindsey Langham Road 552852 373850
East Lindsey 552745 372633
East Lindsey Sloothby High Lane 552768 371237
East Lindsey Listoft Lane 552737 371863
East Lindsey Hogs/58/2/footpath 552716 373428
East Lindsey Marsh Lane 552235 367778
East Lindsey Ingoldmells Road 551927 366133
East Lindsey Chalk Lane 551979 366293
East Lindsey Younger’s Lane 551854 365781
East Lindsey BurM/265/1/footpath 551849 365045
East Lindsey Skegness Road 551884 364653
East Lindsey Skegness Road 551677 364700
East Lindsey BurM/261/2/footpath 551210 364293
East Lindsey Low Lane 549737 363928
East Lindsey Billgate Lane 550874 364061
East Lindsey High Lane 549541 363837
East Lindsey Lymn Bank 547595 361881
East Lindsey Spilsby Road 547576 361869
East Lindsey Tip Lane 547187 361492
East Lindsey Tip Lane 546959 361475
East Lindsey Lymn Bank 546707 361686
East Lindsey Harrison’s Lane 545951 360772
East Lindsey 546451 360602
East Lindsey Fendike Bank 545225 360887
East Lindsey 544335 360672
East Lindsey 544406 360646
East Lindsey Spilsby Road 540547 358398
East Lindsey 538464 357361
East Lindsey Fodder Dike Bank 537270 356983
East Lindsey Black Drove 536854 356970
East Lindsey 535854 355477
East Lindsey Main Road 535171 354456
East Lindsey Thorndales Lane 535143 354569
East Lindsey Main Road 535164 354554
East Lindsey Westhouses 534385 353879
East Lindsey Staunt Road 532754 352939
East Lindsey 532759 352950
East Lindsey 532704 352947
East Lindsey Carrington Road 531478 351306
East Lindsey Westville Road 531252 350893
East Lindsey Canister Lane 530901 350507
East Lindsey Peacock’s Road 530071 349321
East Lindsey Leagate Road 529247 348560
East Lindsey Mere Booth Road 528535 348075
Boston (B) Langrick Road 526770 347276
Boston and South Holland Brot/2/1/footpath 526284 347004
Boston (B) Kirton Drove 525143 346217
Boston (B) North Forty Foot Bank 525615 346514
Boston (B) Sutterton Drove 524323 345745
Boston (B) Claydike Bank 523493 345383
Boston (B) Claydike Bank 523450 345437
Boston (B) 521383 343290
Boston (B) Station Road 521732 342951
Boston (B) 521729 342991
Boston (B) 521273 343376
Boston (B) Station Road 522154 342298
Boston (B) Doubletwelves Drove 519105 340112
Boston (B) Bicker Drove 519871 339207
Boston (B) 519930 338732
East Lindsey 546596 367333
East Lindsey 546845 367295
East Lindsey Sausthorpe Road 540505 367977
East Lindsey 537720 363658
Boston (B) Boardsides 530280 343449
Boston (B) Sleaford Road 530692 343547
Boston (B) John Adams Way 532582 343678
Boston (B) Liquorpond Street 532517 343690
Boston (B) South End 532834 343751
Boston (B) John Adams Way 532884 343787
Boston (B) John Adams Way 532805 343750

SCHEDULE 3 — Streets to be temporarily stopped up

(1) Dist-rict (2) Streets to be temporarily stopped up (see access to works and streets plans) (3) Grid co-ordinates (start) (3) Grid co-ordinates (start) (3) Grid co-ordinates (start) (4) Ident-ifier (5) Grid co-ordinates (end) (5) Grid co-ordinates (end) (5) Grid co-ordinates (end) (6) Ident-ifier (7) Extent of stop-ping up
Easting Easting Northing Easting Easting Northing
East Lindsey East Lindsey East Lindsey East Lindsey East Lindsey East Lindsey East Lindsey East Lindsey East Lindsey East Lindsey East Lindsey
Hutt/10/4/ footpath 554608 554608 376836 Cx 554704 554704 376859 Cy
Ande/17/2/ footpath 554226 554226 376295 Dx 554130 554130 376277 Dy
Roman Bank 554191 554191 376754 AC 554194 554194 376713 AD 41
Roman Bank 554311 554311 376482 AE 554338 554338 376422 AF 66
554197 554197 376754 AA 554809 554809 376886 AB 629
Hutt/10/4/ footpath 554197 554197 376740 Ca 554815 554815 376888 Cb
Sea Road 553723 553723 375923 AG 553771 553771 375876 AH 67
Langham Road 552820 552820 373849 AI 552884 552884 373848 AJ 64
552692 552692 372642 AK 552797 552797 372624 AL 107
Ande/25/1/ footpath 553583 553583 375327 Ha 553564 553564 375283 Hb
Ande/25/1/ footpath 553535 553535 375216 Hx 553462 553462 375199 Hy
Ande/22/4/ footpath 553722 553722 375727 Ex 553728 553728 375729 Ey
Ande/23/1/ footpath 553722 553722 375727 Fx 553725 553725 375719 Fy
Ande/22/3/ footpath 553722 553722 375727 Gx 553652 553652 375683 Gy
Mumb/26/1/ footpath 553404 553404 375064 Ix 553450 553450 375020 Iy
Mumb/59/8/ footpath 553278 553278 374481 Jx 553337 553337 374466 Jy
Mumb/61/1/ footpath 553076 553076 374192 Kx 553089 553089 374117 Ky
Listoft Lane 552705 552705 371875 AM 552768 552768 371875 AN 67
Sloothby High Lane 552738 552738 371225 AO 552798 552798 371248 AP 64
Marsh Lane 552225 552225 367773 AQ 552415 552415 367878 AR 217
Hogs/58/2/ footpath 552716 552716 373428 Lx 552773 552773 373332 Ly
Chalk Lane 551931 551931 366283 AS 552026 552026 366303 AT 97
Ingoldmells Road 551883 551883 366094 AU 551971 551971 366172 AV 117
Younger’s Lane 551817 551817 365777 AW 551891 551891 365785 AX 74
BurM/265/1/ footpath 551849 551849 365045 Mx 551917 551917 365039 My
Skegness Road 551624 551624 364712 AY 551730 551730 364688 AZ 108
Skegness Road 551798 551798 364673 BA 551970 551970 364634 BB 176
Billgate Lane 550834 550834 364072 BC 550915 550915 364050 BD 84
BurM/261/2/ footpath 551210 551210 364293 Nx 551249 551249 364246 Ny
Low Lane 549721 549721 363954 BE 549753 549753 363902 BF 61
High Lane 549526 549526 363863 BG 549555 549555 363810 BH 60
Lymn Bank 547579 547579 361892 BI 547611 547611 361870 BJ 38
Spilsby Road 547579 547579 361892 BK 547574 547574 361845 BL 47
Tip Lane 547140 547140 361487 BM 547235 547235 361497 BN 95
Tip Lane 546955 546955 361488 BO 546973 546973 361469 BP 26
Lymn Bank 546690 546690 361682 BQ 546722 546722 361691 BR 33
546434 546434 360599 BS 546468 546468 360605 BT 34
Harrison’s Lane 545940 545940 360803 BU 545962 545962 360742 BV 65
Fendike Bank 545231 545231 360917 BW 545222 545222 360857 BX 60
544301 544301 360685 BY 544369 544369 360660 BZ 72
544390 544390 360652 CA 544421 544421 360641 CB 33
541839 541839 359030 CC 541939 541939 359060 CD 104
Spilsby Road 540555 540555 358432 CE 540539 540539 358364 CF 70
538472 538472 357404 CG 538456 538456 357318 CH 87
Black Drove 536858 536858 356990 CI 536850 536850 356951 CJ 40
Fodder Dike Bank 537235 537235 356981 CK 537305 537305 356982 CL 70
535819 535819 355479 CM 535888 535888 355475 CN 69
Main Road 535152 535152 354586 CO 535159 535159 354575 CP 13
Thorndales Lane 535127 535127 354562 CQ 535159 535159 354519 CR 60
Main Road 535169 535169 354510 CS 535166 535166 354401 CT 109
Westhouses 534374 534374 353911 CU 534396 534396 353847 CV 68
Staunt Road 532754 532754 353010 CW 532754 532754 352868 CX 141
532688 532688 352946 CY 532720 532720 352948 CZ 33
532725 532725 352948 DA 532793 532793 352953 DB 69
Carrington Road 531475 531475 351340 DC 531482 531482 351272 DD 68
Westville Road 531225 531225 350908 DE 531278 531278 350879 DF 60
Canister Lane 530869 530869 350498 DG 530934 530934 350516 DH 67
Peacock’s Road 530060 530060 349349 DI 530083 530083 349293 DJ 60
Leagate Road 529222 529222 348584 DK 529273 529273 348538 DL 69
Mere Booth Road 528507 528507 348090 DM 528563 528563 348060 DN 63
Boston (B) Boston (B) Boston (B) Boston (B) Boston (B) Boston (B) Boston (B) Boston (B) Boston (B) Boston (B) Boston (B)
Langrick Road 526754 347301 347301 DO 526786 347250 347250 DP 60
North Forty Foot Bank 525586 346544 346544 DQ 525643 346485 346485 DR 81
Kirton Drove 525126 346235 346235 DS 525160 346198 346198 DT 50
Sutterton Drove 524304 345769 345769 DU 524342 345722 345722 DV 60
Claydike Bank 523441 345449 345449 DW 523459 345426 345426 DX 30
Claydike Bank 523474 345407 345407 DY 523512 345360 345360 DZ 61
521246 343393 343393 EA 521301 343358 343358 EB 66
521341 343325 343325 EC 521424 343255 343255 ED 109
Station Road 522137 342325 342325 EE 522171 342271 342271 EF 63
Doubletwelves Drove 519277 340463 340463 EG 518939 339758 339758 EH 782
Bicker Drove 519836 339223 339223 EI 519906 339192 339192 EJ 77
519942 338749 338749 EK 519922 338712 338712 EL 42
Boston and South Holland Boston and South Holland Boston and South Holland Boston and South Holland Boston and South Holland Boston and South Holland Boston and South Holland Boston and South Holland Boston and South Holland Boston and South Holland Boston and South Holland
Brot/2/1/ footpath 526284 526284 347004 Px 526244 526244 346908 Py

SCHEDULE 4 — Access to works

(1) District (2) Grid reference points (2) Grid reference points (3) Description of access (see access to works and streets plans)
Easting Northing
East Lindsey 554197 376740 AC1
East Lindsey 554327 376455 AC2
East Lindsey 554323 376451 AC3
East Lindsey 553747 375901 AC4
East Lindsey 553746 375896 AC5
East Lindsey 552855 373852 AC6
East Lindsey 552853 373849 AC7
East Lindsey 552742 372636 AC8
East Lindsey 552742 372631 AC9
East Lindsey 552737 371866 AC10
East Lindsey 552738 371858 AC11
East Lindsey 552766 371242 AC12
East Lindsey 552767 371236 AC13
East Lindsey 552239 367778 AC14
East Lindsey 551981 366294 AC15
East Lindsey 551977 366291 AC16
East Lindsey 551927 366135 AC17
East Lindsey 551926 366129 AC18
East Lindsey 551855 365783 AC19
East Lindsey 551854 365778 AC20
East Lindsey 551675 364696 AC22
East Lindsey 551915 364651 AC21
East Lindsey 550882 364063 AC23
East Lindsey 550880 364061 AC24
East Lindsey 549739 363926 AC25
East Lindsey 549736 363924 AC26
East Lindsey 549545 363842 AC27
East Lindsey 549540 363839 AC28
East Lindsey 547600 361883 AC29
East Lindsey 547572 361865 AC30
East Lindsey 547193 361494 AC31
East Lindsey 547190 361490 AC32
East Lindsey 546955 361473 AC33
East Lindsey 546708 361684 AC34
East Lindsey 546450 360601 AC35
East Lindsey 545954 360773 AC36
East Lindsey 545950 360773 AC37
East Lindsey 545226 360888 AC38
East Lindsey 545223 360888 AC39
East Lindsey 544407 360643 AC40
East Lindsey 541886 359040 AC41
East Lindsey 541883 359034 AC42
East Lindsey 540547 358397 AC43
East Lindsey 540541 358395 AC44
East Lindsey 538462 357336 AC45
East Lindsey 536854 356969 AC46
East Lindsey 535857 355480 AC47
East Lindsey 535854 355477 AC48
East Lindsey 535175 354463 AC49
East Lindsey 535169 354463 AC50
East Lindsey 534385 353879 AC51
East Lindsey 532759 352955 AC52
East Lindsey 532705 352945 AC53
East Lindsey 531481 351305 AC54
East Lindsey 531475 351300 AC55
East Lindsey 531252 350895 AC56
East Lindsey 530903 350511 AC57
East Lindsey 530902 350505 AC58
East Lindsey 530072 349323 AC59
East Lindsey 530069 349322 AC60
East Lindsey 529245 348564 AC61
East Lindsey 529240 348562 AC62
East Lindsey 528537 348077 AC63
East Lindsey 528534 348074 AC64
Boston (B) 526773 347277 AC65
Boston (B) 526767 347274 AC66
Boston (B) 525599 346533 AC67
Boston (B) 525146 346219 AC68
Boston (B) 525143 346216 AC69
Boston (B) 524325 345746 AC70
Boston (B) 524321 345743 AC71
Boston (B) 523499 345381 AC72
Boston (B) 523449 345438 AC73
Boston (B) 521386 343293 AC74
Boston (B) 521381 343287 AC75
Boston (B) 522152 342298 AC76
Boston (B) 519870 339210 AC77
Boston (B) 519871 339206 AC78
Boston (B) 519909 338733 AC79

SCHEDULE 5 — Land in which only new rights, etc. may be acquired

East Lindsey District

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.