The Southampton to London Pipeline Development Consent Order 2020

Type Statutory-Instrument
Publication 2020-10-07
State In force
Department Queen's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API

and in section 240(1) (provisions supplemental to ss.238 and 239) of the 1990 Act reference to “regulations made for the purposes of sections 238(3) and (4) and 239(2)” means, so far as applicable to land or a right over land acquired under this Order, paragraphs (2) to (15) of this article and in section 240(3) of the 1990 Act reference to a “statutory undertaker” includes the undertaker and reference to “any other enactment” includes this Order.

  • (18) The Town and Country Planning (Churches, Places of Worship and Burial Ground) Regulations 1950[^f00064] do not apply to the authorised development.

Application of landlord and tenant law

38
  • (1) This article applies to—
  • (a) any agreement for leasing to any person the whole or any part of the authorised development or the right to operate the same; and
  • (b) any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised development, or any part of it,

so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person’s use.

  • (2) No enactment or rule of law regulating the rights and obligations of landlords and tenants prejudices the operation of any agreement to which this article applies.
  • (3) No enactment or rule of law to which paragraph (2) applies is to apply in relation to the rights and obligations of the parties to any lease granted by or under any such agreement so as to—
  • (a) exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;
  • (b) confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or
  • (c) restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.

Operational land for purposes of the Town and Country Planning Act 1990

39

Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3)(a) of the 1990 Act (cases in which land is to be treated as not being operational land).

Planning permission

40

If planning permission is issued under the 1990 Act for development any part of which is within the Order limits following the publication of this Order that is—

  • (a) not itself a nationally significant infrastructure project under the 2008 Act or part of such a project; and
  • (b) required to complete or enable the construction, use or operation of the development authorised by this Order,

then the carrying out, use or operation of such development under the terms of the planning permission does not constitute a breach of the terms of this Order.

Defence to proceedings in respect of statutory nuisance

41
  • (1) Where proceedings are brought under section 82(1) of the Environmental Protection Act 1990[^f00065] (summary proceedings by person aggrieved by statutory nuisance) in relation to a nuisance falling within paragraph (g) (noise emitted from premises so as to be prejudicial to health or a nuisance) of section 79(1) of that Act no order is to be made, and no fine may be imposed, under section 82(2) of that Act if—
  • (a) the defendant shows that the nuisance—
  • (i) relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development and that the nuisance is attributable to the carrying out of the authorised development in accordance with a notice served under section 60 (control of noise on construction site), or a consent given under section 61 (prior consent for work on construction sites) of the Control of Pollution Act 1974[^f00066]; or
  • (ii) relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development and that the nuisance is attributable to the carrying out of the authorised development in accordance with the controls and measures relating to noise as described in the code of construction practice or the construction environment management plan approved under Schedule 2 (Requirements) or in accordance with the noise levels set out in an environmental permit relating to the operation of the authorised development;
  • (iii) is a consequence of the construction or maintenance of the authorised development and that it cannot reasonably be avoided; or
  • (iv) is a consequence of complying with a requirement of this Order and that it cannot reasonably be avoided; or
  • (b) the defendant shows that the nuisance is a consequence of the use of the authorised development and that it cannot be reasonably avoided.
  • (2) For the purposes of paragraph (1) above, compliance with the controls and measures relating to noise described in the code of construction practice and the CEMP will be sufficient, but not necessary, to show that an alleged nuisance could not reasonably be avoided.
  • (3) Where a relevant planning authority is acting in accordance with section 60(4) and section 61(4) of the Control of Pollution Act 1974 in relation to the construction of the authorised development then the local authority must also have regard to the controls and measures relating to noise referred to in the code of construction practice or the CEMP approved under Schedule 2 (Requirements).
  • (4) Section 61(9) (consent for work on construction site to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the Control of Pollution Act 1974 does not apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development.
  • (5) In this article “premises” has the same meaning as in section 79 of the Environmental Protection Act 1990[^f00067].

Felling or lopping

42
  • (1) The undertaker may fell, lop, prune, coppice, pollard or reduce in height or width, any tree or shrub within or overhanging land within the Order limits, or may cut back the roots of a tree or shrub which extend into the Order land if it reasonably believes it to be necessary to do so to prevent the tree, shrub or roots from—
  • (a) obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development; or
  • (b) constituting a danger to persons using the authorised development.
  • (2) In carrying out any activity authorised by paragraph (1) or (3), the undertaker must not cause unnecessary damage to any tree, shrub or hedgerow and must pay compensation to any person who sustains any loss or damage arising from such activity for that loss or damage.
  • (3) The undertaker may, for the purpose of the authorised development—
  • (a) subject to paragraph (2), remove any hedgerows within the Order limits that may be required for the purposes of carrying out the authorised development; and
  • (b) only remove important hedgerows identified in Schedule 10 (Removal of important hedgerows) to the extent shown on the plans identified in Schedule 10.
  • (4) The power conferred by paragraph (3) removes any obligation upon the undertaker to secure any consent under the Hedgerows Regulations 1997[^f00068] in undertaking works pursuant to paragraph 3(a) or (b).
  • (5) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, must be determined under Part 1 of the 1961 Act (determination of questions of disputed compensation).
  • (6) In this article “hedgerow” and “important hedgerow” have the meaning given in the Hedgerow Regulations 1997.

Trees subject to Tree Preservation Orders

43
  • (1) The undertaker may fell, lop or prune any part of any tree which is within, over or under land within the Order limits and which is described in Schedule 8 (trees subject to Tree Preservation Orders) and identified on the general arrangement plans, or cut back its roots, if it reasonably believes it to be necessary in order to prevent the tree—
  • (a) from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development; or
  • (b) from constituting a danger to persons using the authorised development.
  • (2) In carrying out any activity authorised by paragraph (1)—
  • (a) the undertaker must do no unnecessary damage to any tree or shrub and must pay compensation to any person for any damage arising from such activity; and
  • (b) the duty in section 206(1) of the 1990 Act (replacement of trees) must not apply.
  • (3) The authority given by paragraph (1) constitutes a deemed consent under the relevant tree preservation order.
  • (4) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, must be determined under Part 1 of the 1961 Act.

Protection of interests

44

Schedule 9 (protective provisions) to the Order has effect.

Certification of documents, etc.

45
  • (1) As soon as practicable after the making of this Order, the undertaker must submit copies of each of the plans and documents set out in Schedule 11 (documents to be certified) to the Secretary of State for certification as true copies of those plans and documents.
  • (2) Where any plan or document set out in Schedule 11 requires to be amended to reflect the terms of the Secretary of State’s decision to make the Order, that plan or document in the form amended to the Secretary of State’s satisfaction is the version of the plan or document required to be certified under paragraph (1).
  • (3) A plan or document so certified will be admissible in any proceedings as evidence of the contents of the document of which it is a copy.

Service of notices

46
  • (1) A notice or other document required or authorised to be served for the purposes of this Order may be served—
  • (a) by post;
  • (b) by delivering it to the person on whom it is to be served or to whom it is to be given or supplied; or
  • (c) with the consent of the recipient and subject to paragraphs (5) to (8) by electronic transmission.
  • (2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.
  • (3) For the purposes of section 7 (references to services by post) of the Interpretation Act 1978[^f00069] as it applies for the purposes of this article, the proper address of any person in relation to the service on that person of a notice or document under paragraph (1) is, if that person has given an address for service, that address, and otherwise—
  • (a) in the case of the secretary or clerk of a body corporate, the registered or principal office of that body; and
  • (b) in any other case, the last known address of that person at the time of service.
  • (4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having any interest in, or as the occupier of, land and the name or address of that person cannot be ascertained after reasonable enquiry, the notice may be served by—
  • (a) addressing it to that person by name or by the description of “owner”, or as the case may be “occupier”, of the land (describing it); and
  • (b) either leaving it in the hands of a person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.
  • (5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement will be taken to be fulfilled only where—
  • (a) the recipient of the notice or other document to be transmitted has given consent to the use of electronic transmission in writing or by electronic transmission;
  • (b) the notice or document is capable of being accessed by the recipient;
  • (c) the notice or document is legible in all material respects; and
  • (d) the notice or document is in a form sufficiently permanent to be used for subsequent reference.
  • (6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within 7 days of receipt that the recipient requires a paper copy of all or part of that notice or other document the sender will provide such a copy as soon as reasonably practicable.
  • (7) Any consent to the use of electronic communication given by a person may be revoked by that person in accordance with paragraph (8).
  • (8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—
  • (a) that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and
  • (b) such revocation will be final and will take effect on a date specified by the person in the notice but that date must not be less than 7 days after the date on which the notice is given.
  • (9) This article will not be taken to exclude the employment of any method of service not expressly provided for by it.
  • (10) In this article “legible in all material respects” means that the information contained in the notice or document is available to that person to no lesser extent than it would be if served, given or supplied by means of a notice or document in printed form.

No double recovery

47

Compensation must not be payable in respect of the same matter both under this Order and under any other enactment, any contract or deed or any rule of law, or under two or more different provisions of this Order.

Arbitration

48

Except where otherwise expressly provided for in this Order and unless otherwise agreed in writing between the parties, any difference under any provision of this Order (other than a difference which falls to be determined by the Lands Chamber of the Upper Tribunal) must be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the Secretary of State.

SCHEDULE 1 — AUTHORISED DEVELOPMENT

A nationally significant infrastructure project as defined in sections 14 and 21 of the 2008 Act, and associated development as defined in section 115 of the 2008 Act, comprising:

In the County of Hampshire

Work No.1A — Works to construct a high-pressure aviation fuel pipeline approximately 20 kilometres in length and with a nominal external diameter of 330 millimetres (subject to engineering tolerance), starting at the indicative point shown on Sheet 1 of the Works Plans and ending at the indicative start point of Work No. 1B shown on Sheets 11/12 of the Works Plans and comprising—

  • (a) construction and installation of the pipeline by trenched and trenchless methods which may include the installation of concrete-lined sleeve tunnels, reception shaft, launch shaft and backfilling of permanent structures; and
  • (b) installation of pipeline marker posts and cathodic protection test posts along the pipeline route,

as shown on Sheets 1 to 12 (inclusive) of the Works Plans.

Work No.1B — Works to construct a high-pressure aviation fuel pipeline approximately 15 kilometres in length and with a nominal external diameter of 330 millimetres (subject to engineering tolerance), starting at the indicative end point of Work No. 1A shown on Sheets 11/12 of the Works Plans and ending at the indicative start point of Work No. 1C shown on Sheet 20 of the Works Plans and comprising—

  • (a) construction and installation of the pipeline by trenched and trenchless methods which may include the installation of concrete-lined sleeve tunnels, reception shaft, launch shaft and backfilling of permanent structures; and
  • (b) installation of pipeline marker posts and cathodic protection test posts along the pipeline route,

as shown on Sheets 11 to 20 (inclusive) of the Works Plans

Work No.1C — Works to construct a high-pressure aviation fuel pipeline approximately 15 kilometres in length and with a nominal external diameter of 330 millimetres (subject to engineering tolerance), starting at the indicative end point of Work No. 1B shown on Sheet 20 of the Works Plans and ending at the indicative start point of Work No. 1D shown on Sheet 28 of the Works Plans and comprising—

  • (a) construction and installation of the pipeline by trenched and trenchless methods which may include the installation of concrete-lined sleeve tunnels, reception shaft, launch shaft and backfilling of permanent structures; and
  • (b) installation of pipeline marker posts and cathodic protection test posts along the pipeline route,

as shown on Sheets 20 to 28 (inclusive) of the Works Plans.

Work No. 1D —Works to construct a high-pressure aviation fuel pipeline approximately 9 kilometres in length and with a nominal external diameter of 330 millimetres (subject to engineering tolerance), starting at the indicative end point of Work No. 1C shown on Sheet 28 of the Works Plans and ending at the indicative start point of Work No. 1E shown on Sheet 33 of the Works Plans and comprising—

  • (a) construction and installation of the pipeline by trenched and trenchless methods which may include the installation of concrete-lined sleeve tunnels, reception shaft, launch shaft and backfilling of permanent structures; and
  • (b) installation of pipeline marker posts and cathodic protection test posts along the pipeline route,

as shown on Sheets 28 to 33 (inclusive) of the Works Plans.

In the Counties of Hampshire and Surrey

Work No. 1Ei —Works to construct a high-pressure aviation fuel pipeline approximately 6 kilometres in length and with a nominal external diameter of 330 millimetres (subject to engineering tolerance), starting at the indicative end point of Work No. 1D shown on Sheet 33 of the Works Plans and ending at the indicative start point of Work No. 1Eii shown on Sheet 35 of the Works Plans and comprising—

  • (a) construction and installation of the pipeline by trenched and trenchless methods which may include the installation of concrete-lined sleeve tunnels, reception shaft, launch shaft and backfilling of permanent structures; and
  • (b) installation of pipeline marker posts and cathodic protection test posts along the pipeline route,

as shown on Sheets 33 to 35 (inclusive) of the Works Plans.

Work No. 1Eii —Works to construct a high-pressure aviation fuel pipeline approximately 0.6 kilometres in length and with a nominal external diameter of 330 millimetres (subject to engineering tolerance), starting at the indicative end point of Work No. 1Ei shown on Sheet 35 of the Works Plans and ending at the indicative start point of Work No. 1Eiii shown on Sheet 35 of the Works Plans and comprising—

  • (a) construction and installation of the pipeline by trenched and trenchless methods which may include the installation of concrete-lined sleeve tunnels, reception shaft, launch shaft and backfilling of permanent structures; and
  • (b) installation of pipeline marker posts and cathodic protection test posts along the pipeline route,

as shown on Sheet 35 of the Works Plans.

Work No. 1Eiii —Works to construct a high-pressure aviation fuel pipeline approximately 2.4 kilometres in length and with a nominal external diameter of 330 millimetres (subject to engineering tolerance), starting at the indicative end point of Work No. 1Eii shown on Sheet 35 of the Works Plans and ending at the indicative start point of Work No. 1F shown on Sheet 38 of the Works Plans and comprising—

  • (a) construction and installation of the pipeline by trenched and trenchless methods which may include the installation of concrete-lined sleeve tunnels, reception shaft, launch shaft and backfilling of permanent structures; and
  • (b) installation of pipeline marker posts and cathodic protection test posts along the pipeline route,

as shown on Sheets 35 to 38 (inclusive) of the Works Plans.

In the County of Surrey

Work No. 1F —Works to construct a high-pressure aviation fuel pipeline approximately 17 kilometres in length and with a nominal external diameter of 330 millimetres (subject to engineering tolerance), starting at the indicative end point of Work No. 1E shown on Sheet 38 of the Works Plans and ending at the indicative start point of Work No. 1G shown on Sheet 47 of the Works Plans and comprising—

  • (a) construction and installation of the pipeline by trenched and trenchless methods which may include the installation of concrete-lined sleeve tunnels, reception shaft, launch shaft and backfilling of permanent structures; and
  • (b) installation of pipeline marker posts and cathodic protection test posts along the pipeline route,

as shown on Sheets 38 to 47 (inclusive) of the Works Plans.

Work No. 1G —Works to construct a high-pressure aviation fuel pipeline approximately 4 kilometres in length and with a nominal external diameter of 330 millimetres (subject to engineering tolerance), starting at the indicative end point of Work No. 1F shown on Sheet 47 of the Works Plans and ending at the indicative start of point of Work No. 1H shown on Sheet 49 of the Works Plans and comprising—

  • (a) construction and installation of the pipeline by trenched and trenchless methods which may include the installation of concrete-lined sleeve tunnels, reception shaft, launch shaft and backfilling of permanent structures; and
  • (b) installation of pipeline marker posts and cathodic protection test posts along the pipeline route,

as shown on Sheets 47 to 49 (inclusive) of the Works Plans.

In the County of Surrey and the London Borough of Hounslow

Work No. 1H —Works to construct a high-pressure aviation fuel pipeline approximately 8 kilometres in length and with a nominal external diameter of 330 millimetres (subject to engineering tolerance), starting at the indicative end point of Work No. 1G shown on Sheet 49 of the Works Plans and ending at the indicative point shown on Sheet 53 of the Works Plans and comprising—

  • (a) construction and installation of the pipeline by trenched and trenchless methods which may include the installation of concrete-lined sleeve tunnels, reception shaft, launch shaft and backfilling of permanent structures; and
  • (b) installation of pipeline marker posts and cathodic protection test posts along the pipeline route,

as shown on Sheets 49 to 53 (inclusive) of the Works Plans.

In the County of Hampshire

Work No. 2A — Works to construct an above ground valve within Work No. 3A, together with associated works, comprising an area of up to 3 metres by 2 metres, at the indicative point shown on Sheet 2 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above.

Work No. 2B —Works to construct a partially buried concrete chamber containing a valve, together with associated works, comprising an area of up to 5 metres by 7 metres, at the indicative point shown on Sheet 4 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above,

subject to the chamber, valve and associated works not exceeding approximately 2 metres in height in any case.

Work No. 2C —Works to construct a partially buried concrete chamber containing a valve, together with associated works, comprising an area of up to 5 metres by 7 metres, at the indicative point shown on Sheet 7 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above,

subject to the chamber, valve and associated works not exceeding approximately 2 metres in height in any case.

Work No. 2D —Works to construct a partially buried concrete chamber containing a valve, together with associated works, comprising an area of up to 5 metres by 7 metres, at the indicative point shown on Sheet 12 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above,

subject to the chamber, valve and associated works not exceeding approximately 2 metres in height in any case.

Work No. 2E —Works to construct a partially buried concrete chamber containing a valve, together with associated works, comprising an area of up to 5 metres by 7 metres, at the indicative point shown on Sheet 16 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above,

subject to the chamber, valve and associated works not exceeding approximately 2 metres in height in any case.

Work No. 2F —Works to construct a partially buried pressure transducer, together with associated works, comprising an area of up to 5 metres by 7 metres, at the indicative point shown on Sheet 17 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above,

subject to the pressure transducer and associated works not exceeding approximately 2 metres in height in any case.

Work No. 2G —Works to construct a partially buried concrete chamber containing a valve, together with associated works, comprising an area of up to 5 metres by 7 metres, at the indicative point shown on Sheet 20 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above,

subject to the chamber, valve and associated works not exceeding approximately 2 metres in height in any case.

Work No. 2H —Works to construct an above ground valve within Work No. 3B, together with associated works, comprising an area of up to 3 metres by 2 metres, at the indicative point shown on Sheet 23 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above.

Work No. 2I —Works to construct a partially buried concrete chamber containing a valve, together with associated works, comprising an area of up to 5 metres by 7 metres, at the indicative point shown on Sheets 31 and 102 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above,

subject to the chamber, valve and associated works not exceeding approximately 2 metres in height in any case.

Work No. 2J —Works to construct a partially buried concrete chamber containing a valve, together with associated works, comprising an area of up to 5 metres by 7 metres, at the indicative point shown on Sheets 33 and 103 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above,

subject to the chamber, valve and associated works not exceeding approximately 2 metres in height in any case.

In the County of Surrey

Work No. 2K —Works to construct a partially buried concrete chamber containing a valve, together with associated works, comprising an area of up to 5 metres by 7 metres, at the indicative point shown on Sheets 36 and 112 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above,

subject to the chamber, valve and associated works not exceeding approximately 2 metres in height in any case.

Work No. 2L —Works to construct a partially buried concrete chamber containing a valve, together with associated works, comprising an area of up to 5 metres by 7 metres, at the indicative point shown on Sheet 41 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above,

subject to the chamber, valve and associated works not exceeding approximately 2 metres in height in any case.

Work No. 2M —Works to construct a partially buried concrete chamber containing a valve, together with associated works, comprising an area of up to 5 metres by 7 metres, at the indicative point shown on Sheet 43 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above,

subject to the chamber, valve and associated works not exceeding approximately 2 metres in height in any case.

Work No. 2N —Works to construct a partially buried concrete chamber containing a valve, together with associated works, comprising an area of up to 5 metres by 7 metres, at the indicative point shown on Sheet 47 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above,

subject to the chamber, valve and associated works not exceeding approximately 2 metres in height in any case.

Work No. 2O —Works to construct a partially buried concrete chamber containing a valve, together with associated works, comprising an area of up to 5 metres by 7 metres, at the indicative point shown on Sheets 51 and 124 of the Works Plans, such associated works to include—

  • (a) fencing;
  • (b) up to two personnel gates;
  • (c) below ground pipework;
  • (d) above ground control boxes and below ground cable ducts; and
  • (e) any other equipment as may be necessary or expedient in connection with the above,

subject to the chamber, valve and associated works not exceeding approximately 2 metres in height in any case.

In the County of Hampshire

Work No. 3A — Works to construct an Above Ground Installation at Boorley Green (“the Boorley Green AGI”), being a secure compound with an approximate area of 23 metres by 30 metres and a maximum height of 3 metres, comprising equipment for the reception and launching of pipeline inspection gauges in connection with pipeline inspection, cleansing and monitoring, at the indicative point shown on Sheet 2 of the Works Plans, to include—

  • (a) fencing (to an approximate height of 3 metres);
  • (b) a double entrance gate;
  • (c) up to two personnel gates;
  • (d) below ground pipework;
  • (e) above ground pipework, vessels, valves and instrumentation;
  • (f) above ground control boxes and below ground cable ducts;
  • (g) an internal access road;
  • (h) changes to ground levels as may be necessary, including the provision of drainage works and the laying of hard standing; and
  • (i) permanent widening of an access track off Netherhill Lane, and an extension of the access track to join the Boorley Green AGI.

Work No. 3B —Works to construct pipework, valves, pumps and any associated equipment, at the existing Alton Pumping Station, at the indicative point shown on Sheet 23 of the Works Plans.

In the London Borough of Hounslow

Work No. 3C — Works to construct pipework, valves, vessels and equipment for the reception and launching of pipeline inspection gauges in connection with pipeline inspection, cleansing and monitoring, together with any associated equipment, at the existing West London Terminal Above Ground Installation, at the indicative point shown on Sheets 53 and 123 of the Works Plans.

In the County of Hampshire

Work No. 4A — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 42 metres by 51 metres, at the indicative point shown on Sheet 1 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4B — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 60 metres by 62 metres, at the indicative point shown on Sheet 2 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) a plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4C — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 75 metres by 32 metres, at the indicative point shown on Sheet 2 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4D — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 69 metres by 44 metres, at the indicative point shown on Sheet 4 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4E — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 49 metres by 56 metres, at the indicative point shown on Sheet 4 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4F — Work No. not used.

Work No. 4G — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 50 metres by 48 metres, at the indicative point shown on Sheet 9 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4H — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 42 metres by 53 metres, at the indicative point shown on Sheet 9 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4I — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 43 metres by 52 metres, at the indicative point shown on Sheet 11 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4J — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 53 metres by 43 metres, at the indicative point shown on Sheet 11 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4K — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 53 metres by 42 metres, at the indicative point shown on Sheet 12 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4L — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 50 metres by 40 metres, at the indicative point shown on Sheet 15 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4M — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 32 metres by 42 metres, at the indicative point shown on Sheet 16 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4N — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 37 metres by 56 metres, at the indicative point shown on Sheet 19 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4O — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 66 metres by 52 metres, at the indicative point shown on Sheet 20 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4P— Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 40 metres by 53 metres, at the indicative point shown on Sheet 21 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4Q — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 51 metres by 38 metres, at the indicative point shown on Sheet 23 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4R — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 107 metres by 80 metres, at the indicative point shown on Sheet 23 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4S — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 34 metres by 52 metres, at the indicative point shown on Sheet 24 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4T — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 66 metres by 52 metres, at the indicative point shown on Sheet 25 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4U — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 53 metres by 41 metres, at the indicative point shown on Sheet 28 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4V — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 68 metres by 50 metres, at the indicative point shown on Sheet 29 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4W— Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 68 metres by 39 metres, at the indicative point shown on Sheet 29 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4X — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 60 metres by 42 metres, at the indicative point shown on Sheet 30 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4Y — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 67 metres by 48 metres, at the indicative point shown on Sheet 30 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4Z — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 42 metres by 59 metres, at the indicative point shown on Sheets 31 and 102 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4AA — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 39 metres by 25 metres, at the indicative point shown on Sheet 32 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4AB — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 52 metres by 24 metres, at the indicative point shown on Sheet 33 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4AC — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 32 metres by 52 metres, at the indicative point shown on Sheet 33 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4AD — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 29 metres by 62 metres, at the indicative point shown on Sheets 34 and 104 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 4AE — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 25 metres by 25 metres, at the indicative point shown on Sheets 34 and 105 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

In the County of Surrey

Work No. 5A — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 43 metres by 43 metres, at the indicative point shown on Sheets 36 and 112 of the Works Plans, and including―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas;
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5B — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 72 metres by 22 metres, at the indicative point shown on Sheets 36 and 112 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5C— Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 55 metres by 40 metres, at the indicative point shown on Sheets 36 and 113 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5D — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 95 metres by 10 metres, at the indicative point shown on Sheet 38 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5E — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 64 metres by 45 metres, at the indicative point shown on Sheet 41 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5F — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 59 metres by 42 metres, at the indicative point shown on Sheet 42 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5G — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 73 metres by 32 metres, at the indicative point shown on Sheet 43 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management area; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5H — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 40 metres by 20 metres, at the indicative points shown on Sheet 43 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5I — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 80 metres by 40 metres, at the indicative points shown on Sheet 44 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5J — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 75 metres by 42 metres, at the indicative point shown on Sheet 45 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5K — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 30 metres by 24 metre, at the indicative point shown on Sheet 46 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5L — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 47 metres by 45 metres, at the indicative point shown on Sheet 47 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5M — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 51 metres by 31 metres, at the indicative point shown on Sheet 47 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5N — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 53 metres by 45 metres, at the indicative point shown on Sheet 49 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5O — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 47 metres by 50 metres, at the indicative point shown on Sheet 50 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5P — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 48 metres by 50 metres, at the indicative point shown on Sheet 50 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5Q — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 93 metres by 113 metres, at the indicative point shown on Sheets 52 and 121 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5R — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 57 metres by 30 metres, at the indicative point shown on Sheets 53 and 123 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5S — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 47 metres by 35 metres, at the indicative point shown on Sheets 53 and 123 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5T — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 53 metres by 33 metres, at the indicative point shown on Sheets 53 and 123 of the Works Plans, to include―

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

Work No. 5U — Works to construct a temporary compound for use during the construction of the authorised development, comprising an area of up to 149 metres by 19 metres, at the indicative point shown on Sheet 37 of the Works Plans, to include—

  • (a) office, welfare and security facilities;
  • (b) a parking area for staff;
  • (c) power supplies and temporary lighting;
  • (d) pipe equipment and fittings storage;
  • (e) plant storage;
  • (f) a fabrication area;
  • (g) a plant wheel wash area;
  • (h) waste processing and management areas; and
  • (i) fencing and gating (to an approximate height of 2.4 metres).

In the County of Hampshire

Work No. 6A — Work No. not used.

Work No. 6B — Works to construct a temporary logistics and construction materials storage hub for use during the construction of the authorised development , comprising an area approximately 200 metres by 100 metres, at the indicative point shown on Sheet 59 of the Works Plans, to include—

  • (a) office, welfare and security facilities;
  • (b) lighting situated on lighting columns (at an approximate height of 4 metres);
  • (c) close circuit television cameras situated on columns (at an approximate maximum height of 4 metres);
  • (d) security monitoring systems;
  • (e) a parking area for staff;
  • (f) power supplies;
  • (g) pipeline equipment and fittings storage;
  • (h) construction equipment for trenchless crossings;
  • (i) plant and material storage;
  • (j) a fabrication area;
  • (k) a plant wheel wash area;
  • (l) waste processing and management areas;
  • (m) installation of drainage, drainage attenuation and land drainage, including outfalls; and
  • (n) fencing and gating (to an approximate height of 3 metres).

Work No. 6C — Works to construct a temporary logistics and construction materials storage hub for use during the construction of the authorised development, comprising an area approximately 150 metres by 150 metres, at the indicative point shown on Sheet 56 of the Works Plans, to include—

  • (a) office, welfare and security facilities;
  • (b) lighting situated on lighting columns (at an approximate maximum height of 4 metres);
  • (c) close circuit television cameras situated on columns (at an approximate height of 4 metres);
  • (d) security monitoring systems;
  • (e) a parking area for staff;
  • (f) power supplies;
  • (g) pipeline equipment and fittings storage;
  • (h) construction equipment for trenchless crossings;
  • (i) plant and material storage;
  • (j) a fabrication area;
  • (k) a plant wheel wash area;
  • (l) waste processing and management areas;
  • (m) installation of drainage, drainage attenuation and land drainage, including outfalls; and
  • (n) fencing and gating (to an approximate height of 3 metres).

In the County of Surrey

Work No. 7A — Work No. not used.

Work No. 7B — Work No. not used.

Work No. 7C — Work No. not used.

In the County of Hampshire

Work No. 8A — Works to construct a temporary construction access to the south of Maddoxford Lane, in the indicative location shown on Sheet 1 of the Works Plans.

Work No. 8B — Works to construct a temporary construction access to the north of Maddoxford Lane, in the indicative location shown on Sheet 1 of the Works Plans.

Work No. 8C — Works to construct a temporary construction access to the west of Netherhill Lane, in the indicative location shown on Sheet 1 of the Works Plans.

Work No. 8D — Works to construct a temporary construction access to the south of Gregory Lane, in the indicative location shown on Sheet 2 of the Works Plans.

Work No. 8E — Works to construct a temporary construction access to the north of Gregory Lane, in the indicative location shown on Sheet 2 of the Works Plans.

Work No. 8F — Works to construct a temporary construction access to the west of Mincingfield Lane, in the indicative location shown on Sheet 3 of the Works Plans.

Work No. 8G — Works to construct a temporary construction access to the east of Mincingfield Lane, in the indicative location shown on Sheet 3 of the Works Plans.

Work No. 8H — Works to construct a temporary construction access to the south of Wintershill, in the indicative location shown on Sheet 4 of the Works Plans.

Work No. 8I — Works to construct a temporary construction access to the north of Wintershill, in the indicative location shown on Sheet 4 of the Works Plans.

Work No. 8J — Works to construct a temporary construction access to the south of the B2177 Winchester Road, in the indicative location shown on Sheet 4 of the Works Plans.

Work No. 8K — Works to construct a temporary construction access to the north of the B2177 Winchester Road, in the indicative location shown on Sheet 4 of the Works Plans.

Work No. 8L — Works to construct a temporary construction access to the south of Bigpath Lane, in the indicative location shown on Sheet 6 of the Works Plans.

Work No. 8M — Works to construct a temporary construction access to the north of Bigpath Lane, in the indicative location shown on Sheet 6 of the Works Plans.

Work No. 8N — Works to construct a temporary construction access to the north of Bigpath Lane and west of Belmore, in the indicative location shown on Sheet 6 of the Works Plans.

Work No. 8O — Works to construct a temporary construction access to the east of Belmore and to the north of Bigpath Lane, in the indicative location shown on Sheet 6 of the Works Plans.

Work No. 8P — Works to construct a temporary construction access to the west of Stake’s Lane, in the indicative location shown on Sheet 6 of the Works Plans.

Work No. 8Q — Works to construct a temporary construction access to the east of Stake’s Lane, in the indicative location shown on Sheet 6 of the Works Plans.

Work No. 8R — Works to construct a temporary construction access to the south of Wheely Down Farm Road, in the indicative location shown on Sheet 9 of the Works Plans.

Work No. 8S — Works to construct a temporary construction access to the north of Wheely Down Farm Road, in the indicative location shown on Sheet 9 of the Works Plans.

Work No. 8T — Works to construct a temporary construction access to the south of Kilmeston Road, in the indicative location shown on Sheet 9 of the Works Plans.

Work No. 8U — Works to construct a temporary construction access to the north of Kilmeston Road, in the indicative location shown on Sheet 9 of the Works Plans.

Work No. 8V — Work No. not used.

Work No. 8W — Work No. not used.

Work No. 8X — Work No. not used.

Work No. 8Y — Works to construct a temporary construction access to the south of the A272, in the indicative location shown on Sheet 11 of the Works Plans.

Work No. 8Z — Works to construct a temporary construction access to the north of the A272/Tithelands Lane, in the indicative location shown on Sheet 12 of the Works Plans.

Work No. 8AA — Works to construct a temporary construction access to the west of Tithelands Lane, in the indicative location shown on Sheet 12 of the Works Plans.

Work No. 8AB — Works to construct a temporary construction access to the east of Tithelands Lane, in the indicative location shown on Sheet 12 of the Works Plans.

Work No. 8AC — Works to construct a temporary construction access to the west of Stapley Lane, in the indicative location shown on Sheet 14 of the Works Plans.

Work No. 8AD — Works to construct a temporary construction access to the east of Stapley Lane, in the indicative location shown on Sheet 14 of the Works Plans.

Work No. 8AE — Works to construct a temporary construction access to the south of Smugglers Lane, in the indicative location shown on Sheet 15 of the Works Plans.

Work No. 8AF — Works to construct a temporary construction access to the north of Smugglers Lane, in the indicative location shown on Sheet 15 of the Works Plans.

Work No. 8AG — Works to construct a temporary construction access to the south of Petersfield Road, in the indicative location shown on Sheet 15 of the Works Plans.

Work No. 8AH — Works to construct a temporary construction access to the north of Petersfield Road, in the indicative location shown on Sheet 15 of the Works Plans.

Work No. 8AI — Works to construct a temporary construction access to the south of Kitwood Lane, in the indicative location shown on Sheet 16 of the Works Plans.

Work No. 8AJ — Works to construct a temporary construction access to the north of Kitwood Lane, in the indicative location shown on Sheet 16 of the Works Plans.

Work No. 8AK — Works to construct a temporary construction access to the south of Hawthorn Road, in the indicative location shown on Sheet 16 of the Works Plans.

Work No. 8AL — Works to construct a temporary construction access to the north of Hawthorn Road, in the indicative location shown on Sheet 16 of the Works Plans.

Work No. 8AM — Works to construct a temporary construction access to the west of Headmore Lane, in the indicative location shown on Sheet 17 of the Works Plans.

Work No. 8AN — Works to construct a temporary construction access to the east of Headmore Lane, in the indicative location shown on Sheet 17 of the Works Plans.

Work No. 8AO — Works to construct a temporary construction access to the south of Brightstone Lane, in the indicative location shown on Sheet 17 of the Works Plans.

Work No. 8AP — Works to construct a temporary construction access to the north of Brightstone Lane, in the indicative location shown on Sheet 17 of the Works Plans.

Work No. 8AQ — Works to construct a temporary construction access to the south of Woodside Lane, in the indicative location shown on Sheet 18 of the Works Plans.

Work No. 8AR — Works to construct a temporary construction access to the north of Woodside Lane, in the indicative location shown on Sheet 18 of the Works Plans.

Work No. 8AS — Works to construct a temporary construction access to the west of the A32, in the indicative location shown on Sheet 19 of the Works Plans.

Work No. 8AT — Works to construct a temporary construction access to the east of the A32, opposite Woodside Lane, in the indicative location shown on Sheet 19 of the Works Plans.

Work No. 8AU — Works to construct a temporary construction access to the south of the B3006 Selbourne Road, in the indicative location shown on Sheet 20 of the Works Plans.

Work No. 8AV — Works to construct a temporary construction access to the north of the B3006 Selbourne Road, in the indicative location shown on Sheet 20 of the Works Plans.

Work No. 8AW — Works to construct a temporary construction access to the south of the B3004 Cakers Lane, in the indicative location shown on Sheet 21 of the Works Plans.

Work No. 8AX — Works to construct a temporary construction access to the north of the B3004 Cakers Lane, in the indicative location shown on Sheet 21 of the Works Plans.

Work No. 8AY — Works to construct a temporary construction access to the south of Binsted Road, in the indicative location shown on Sheet 23 of the Works Plans.

Work No. 8AZ — Works to construct a temporary construction access to the north of Binsted Road, in the indicative location shown on Sheet 23 of the Works Plans.

Work No. 8BA — Works to construct a temporary construction access in proximity to the A31 south bound slip road, in the indicative location shown on Sheet 23 of the Works Plans.

Work No. 8BB — Works to construct a temporary construction access to the west of the unnamed road leading from the A31 to Ryebridge Road, in the indicative location shown on Sheet 24 of the Works Plans.

Work No. 8BC — Works to construct a temporary construction access to the east of the unnamed road leading from the A31 to Ryebridge Road, in the indicative location shown on Sheet 24 of the Works Plans.

Work No. 8BD — Works to construct a temporary construction access to the south of Gid Lane, in the indicative location shown on Sheet 24 of the Works Plans.

Work No. 8BE — Works to construct a temporary construction access to the north of Gid Lane, in the indicative location shown on Sheet 24 of the Works Plans.

Work No. 8BF — Works to construct a temporary construction access to the west of Froyle Road, in the indicative location shown on Sheet 25 of the Works Plans.

Work No. 8BG — Works to construct a temporary construction access to the east of Froyle Road, in the indicative location shown on Sheet 25 of the Works Plans.

Work No. 8BH— Works to construct a temporary construction access to the west of Hole Lane, in the indicative location shown on Sheet 26 of the Works Plans.

Work No. 8BI — Works to construct a temporary construction access to the east of Hole Lane, in the indicative location shown on Sheet 26 of the Works Plans.

Work No. 8BJ — Works to construct a temporary construction access to the south of Dippenhall Road, in the indicative location shown on Sheet 27 of the Works Plans.

Work No. 8BK — Works to construct a temporary construction access to the north of Dippenhall Road, in the indicative location shown on Sheet 27 of the Works Plans.

Work No. 8BL — Works to construct a temporary construction access to the west of Dippenhall Street, in the indicative location shown on Sheet 28 of the Works Plans.

Work No. 8BM — Works to construct a temporary construction access to the east of Dippenhall Street, in the indicative location shown on Sheet 28 of the Works Plans.

Work No. 8BN — Works to construct a temporary construction access to the south of Heath Lane, in the indicative location shown on Sheet 29 of the Works Plans.

Work No. 8BO — Works to construct a temporary construction access to the north of Heath Lane, in the indicative location shown on Sheet 29 of the Works Plans.

Work No. 8BP — Works to construct a temporary construction access to the south of Redlands Lane, in the indicative location shown on Sheet 29 of the Works Plans.

Work No. 8BQ — Works to construct a temporary construction access to the north of Redlands Lane, in the indicative location shown on Sheet 29 of the Works Plans.

Work No. 8BR — Works to construct a temporary construction access to the south of the A287 Ewshot Hill, in the indicative location shown on Sheet 29 of the Works Plans.

Work No. 8BS — Works to construct a temporary construction access to the north of the A287 Ewshot Hill, in the indicative location shown on Sheet 29 of the Works Plans.

Work No. 8BT — Works to construct a temporary construction access to the north of the A287 Ewshot Hill, in the indicative location shown on Sheet 29 of the Works Plans.

Work No. 8BU — Works to construct a temporary construction access to the south of Ewshot Lane, in the indicative location shown on Sheet 30 of the Works Plans.

Work No. 8BV — Works to construct a temporary construction access to the north of Ewshot Lane, in the indicative location shown on Sheet 30 of the Works Plans.

Work No. 8BW — Works to construct a temporary construction access to the west of Naishes Lane, in the indicative location shown on Sheet 30 of the Works Plans.

Work No. 8BX — Works to construct a temporary construction access to the east of Naishes Lane, in the indicative location shown on Sheet 30 of the Works Plans.

Work No. 8BY — Works to construct a temporary construction access to the east of Naishes Lane, south of Jubilee Drive, in the indicative location shown on Sheets 30 and 101 of the Works Plans.

Work No. 8BZ — Works to construct a temporary construction access to the east of Naishes Lane, west of Wakefords Copse, in the indicative location shown on Sheets 30 and 101 of the Works Plans.

Work No. 8CA — Works to construct a temporary construction access to the west of the B3013 Beacon Hill Road, south of Sandy Lane, in the indicative location shown on Sheets 30 and 102 of the Works Plans.

Work No. 8CB — Works to construct a temporary construction access to the east of the B3013 Beacon Hill Road, south of Bourley Road, in the indicative location shown on Sheets 31 and 102 of the Works Plans.

Work No. 8CC — Works to construct a temporary construction access to the south of Bourley Road, in the indicative location shown on Sheets 31 and 102 of the Works Plans.

Work No. 8CD — Works to construct a temporary construction access to the north of Bourley Road, in the indicative location shown on Sheets 31 and 102 of the Works Plans.

Work No. 8CE — Works to construct a temporary construction access to the south of Aldershot Road, in the indicative location shown on Sheet 31 of the Works Plans.

Work No. 8CF — Works to construct a temporary construction access to the north of Aldershot Road, in the indicative location shown on Sheet 31 of the Works Plans.

Work No. 8CG — Works to construct a temporary construction access to the east of Concorde Road, in the indicative location shown on Sheets 33 and 103 of the Works Plans.

Work No. 8CH — Works to construct a temporary construction access to the south of Ively Road, in the indicative location shown on Sheet 33 of the Works Plans.

Work No. 8CI — Works to construct a temporary construction access to the north of Ively Road, in the indicative location shown on Sheet 33 of the Works Plans.

Work No. 8CJ — Works to construct a temporary construction access to the west of the A327 Ively Road, in the indicative location shown on Sheet 33 of the Works Plans.

Work No. 8CK — Works to construct a temporary construction access to the east of the A327 Ively Road, in the indicative location shown on Sheet 33 of the Works Plans.

Work No. 8CL — Works to construct a temporary construction access to the east end of Grasmere Road, in the indicative location shown on Sheets 34 and 104 of the Works Plans.

Work No. 8CM — Works to construct a temporary construction access to the south of the B3014 Cove Road, in the indicative location shown on Sheets 34 and 104 of the Works Plans.

Work No. 8CN — Works to construct a temporary construction access to the west side of Cove Brook and to the south of West Heath Road, in the indicative location shown on Sheets 34 and 104 of the Works Plans.

Work No. 8CO — Works to construct a temporary construction access to the west side of Cove Brook and to the north of West Heath Road, in the indicative location shown on Sheets 34 and 104 of the Works Plans.

Work No. 8CP — Works to construct a temporary construction access to the east end of Cabrol Road, in the indicative location shown on Sheets 34 and 105 of the Works Plans.

Work No. 8CQ — Works to construct a temporary construction access to the east side of the A325 Farnborough Road, in the indicative location shown on Sheets 35 and 106 of the Works Plans.

Work No. 8CR — Works to construct a temporary construction access to the east side of Ship Lane, in the indicative location shown on Sheets 35, 107 and 108 of the Works Plans.

Work No. 8CS — Works to construct a temporary construction access to the east side of Farnborough Street, in the indicative location shown on Sheets 35 and 107 of the Works Plans.

Work No. 8CT — Works to construct a temporary construction access to the east of the A331 Frimley Bypass, in the indicative location shown on Sheets 35 and 108 of the Works Plans.

Work No. 8CU —Work No. not used.

Work No. 8CV — Works to construct a temporary construction access to the west of the A331 and to the north of Chapel Street, in the indicative location shown on Sheets 35 and 107 of the Works Plans.

Work No. 8CW — Work No. not used.

Work No. 8CX — Works to construct a temporary construction access to the east of Northfield Lane, in the indicative location shown on Sheet59 of the Works Plans.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.