The Southampton to London Pipeline Development Consent Order 2020
Work No. 8CY — Works to construct a temporary construction access to the east of Bramshot Road, in the indicative location shown on Sheets 32 and 56 of the Works Plans.
Work No. 8CZ — Works to construct a temporary construction access to the west of the A325 Farnborough Road, in the indicative location shown on Sheet 35 of the Works Plans.
In the County of Surrey
Work No. 9A — Works to construct a temporary construction access to the east of the A331 and to the north of The Hatches, in the indicative location shown on Sheets 35 and 110 of the Works Plans.
Work No. 9B — Works to construct a temporary construction access to the west of the B3411 Frimley Green Road and to the south of the SC Johnson Factory, in the indicative location shown on Sheets 36 and 112 of the Works Plans.
Work No. 9C — Works to construct a temporary construction access to the west of the B3411 Frimley Green Road and to the north of the SC Johnson Factory, in the indicative location shown on Sheets 36 and 109 of the Works Plans.
Work No. 9D — Works to construct a temporary construction access to the east of St Catherines Road, in the indicative location shown on Sheets 36 and 113 of the Works Plans.
Work No. 9E — Works to construct a temporary construction access in proximity to Frith Hill Road off the B3015 Deepcut Bridge Road, in the indicative location shown on Sheet 37 of the Works Plans.
Work No. 9F — Work No. not used.
Work No. 9G — Works to construct a temporary construction access to the west of the B3015 Deepcut Bridge Road, to the south of Old Bisley Road, in the indicative location shown on Sheet 38 of the Works Plans.
Work No. 9H — Works to construct a temporary construction access to the east of the B3015 Deepcut Bridge Road, south of Old Bisley Road, in the indicative location shown on Sheet 38 of the Works Plans.
Work No. 9I — Works to construct a temporary construction access to the south of the B311 Red Road, west of Briar Avenue, in the indicative location shown on Sheet 40 of the Works Plans.
Work No. 9J — Works to construct a temporary construction access to the north of the B311 Red Road, west of Lightwater Road, in the indicative location shown on Sheet 40 of the Works Plans.
Work No. 9K — Works to construct a temporary construction access to the west of Guildford Road, south of Blackstroud Lane West, in the indicative location shown on Sheet 41 of the Works Plans.
Work No. 9L — Works to construct a temporary construction access to the east of Guildford Road, south of Blackstroud Lane West, in the indicative location shown on Sheet 41 of the Works Plans.
Work No. 9M — Works to construct a temporary construction access to the south of Blackstroud Lane East, in the indicative location shown on Sheet 41 of the Works Plans.
Work No. 9N — Works to construct a temporary construction access to the north of Blackstroud Lane East, in the indicative location shown on Sheet 41 of the Works Plans.
Work No. 9O — Works to construct a temporary construction access to the west of Halebourne Lane, in the indicative location shown on Sheet 42 of the Works Plans.
Work No. 9P — Works to construct a temporary construction access to the east of Halebourne Lane, in the indicative location shown on Sheet 42 of the Works Plans.
Work No. 9Q — Works to construct a temporary construction access to the south of Windlesham Road, opposite Woodcock Drive, in the indicative location shown on Sheets 42 and 114 of the Works Plans.
Work No. 9R — Works to construct a temporary construction access to the north of Windlesham Road, east of Woodcock Drive, in the indicative location shown on Sheets 42 and 114 of the Works Plans.
Work No. 9S — Works to construct a temporary construction access to the south of Steep Hill, in the indicative location shown on Sheet 43 of the Works Plans.
Work No. 9T — Works to construct a temporary construction access to the north of Steep Hill, in the indicative location shown on Sheet 43 of the Works Plans.
Work No. 9U — Works to construct a temporary construction access to the west of the B383 Windsor Road, south of Staple Hill, in the indicative location shown on Sheet 43 of the Works Plans.
Work No. 9V — Works to construct a temporary construction access to the east of the B383 Windsor Road, south of Staple Hill, in the indicative location shown on Sheet 43 of the Works Plans.
Work No. 9W — Works to construct a temporary construction access to the west of Accommodation Road, in the indicative location shown on Sheet 45 of the Works Plans.
Work No. 9X — Works to construct a temporary construction access to the east of Accommodation Road, in the indicative location shown on Sheet 45 of the Works Plans.
Work No. 9Y — Works to construct a temporary construction access to the south of the B386 Longcross Road, east of Accommodation Road, in the indicative location shown on Sheet 45 of the Works Plans.
Work No. 9Z — Works to construct a temporary construction access to the south of the B386 Longcross Road, west of Lyne Lane, in the indicative location shown on Sheet 46 of the Works Plans.
Work No. 9AA — Works to construct a temporary construction access to the north of the B386 Longcross Road, east of Lyne Lane, in the indicative location shown on Sheets 46 and 115 of the Works Plans.
Work No. 9AB — Works to construct a temporary construction access to the west of Hardwick Lane, in the indicative location shown on Sheet 58 of the Works Plans.
Work No. 9AC — Works to construct a temporary construction access to the west of the A320 Guildford Road, in the indicative location shown on Sheet 47 of the Works Plans.
Work No. 9AD — Works to construct a temporary construction access to the east of the A320 Guildford Road, using the entrance to Salesian School, in the indicative location shown on Sheet 47 of the Works Plans.
Work No. 9AE — Works to construct a temporary construction access in proximity to The Knoll/Hanworth Lane, in the indicative location shown on Sheet 47 of the Works Plans.
Work No. 9AF — Works to construct a temporary construction access in proximity to Green Lane and the Abbey Moor Golf Club, in the indicative location shown on Sheet 47 of the Works Plans.
Work No. 9AG — Works to construct a temporary construction access to the east of the A317 Chertsey Road, in proximity to Chertsey High School, in the indicative location shown on Sheets 48 and 116 of the Works Plans.
Work No. 9AH — Works to construct a temporary construction access to the south of Mead Lane, in the indicative location shown on Sheets 48 and 49 of the Works Plans.
Work No. 9AI — Works to construct a temporary construction access to the west of Old Littleton Lane, in the indicative location shown on Sheets 49 and 117 of the Works Plans.
Work No. 9AJ — Works to construct a temporary construction access to the west of Littleton Lane, using the entrance to the Brett Aggregates Industrial Estate, in the indicative location shown on Sheets 49 and 118 of the Works Plans.
Work No. 9AK — Works to construct a temporary construction access to the south of the B276 Shepperton Road, in the indicative location shown on Sheet 50 of the Works Plans.
Work No. 9AL — Works to construct a temporary construction access to the north of the B276 Shepperton Road, in the indicative location shown on Sheet 50 of the Works Plans.
Work No. 9AM — Works to construct a temporary construction access to the east of the B377 The Broadway, south of the Queen Mary Intake Channel, in the indicative location shown on Sheet 51 of the Works Plans.
Work No. 9AN — Works to construct a temporary construction access to the west of the B377 Ashford Road, at the junction of Kingston Road and Ashford Road, in the indicative location shown on Sheets 51 and 120 of the Works Plans.
Work No. 9AO — Works to construct a temporary construction access to the north of the B377 Ashford Road, east of Kingston Road, in the indicative location shown on Sheets 51 and 120 of the Works Plans.
Work No. 9AP — Works to construct a temporary construction access to the north end of Celia Crescent, in the indicative location shown on Sheets 52 and 120 of the Works Plans.
Work No. 9AQ — Works to construct a temporary construction access to the south of Ferndale Road, in the indicative location shown on Sheets 52 and 120 of the Works Plans.
Work No. 9AR — Works to construct a temporary construction access to the north of Village Way, using the entrance to Clarendon School, in the indicative location shown on Sheets 52 and 122 of the Works Plans.
Work No. 9AS — Works to construct a temporary construction access to the north of the B378 Stanwell Road, using the entrance to St James School, in the indicative location shown on Sheets 52, 121 and 122 of the Works Plans.
Work No. 9AT — Works to construct a temporary construction access to the west of Short Lane, in the indicative location shown on Sheets 53 and 123 of the Works Plans.
Work No. 9AU — Works to construct a temporary construction access to the east of Short Lane, in the indicative location shown on Sheets 53 and 123 of the Works Plans.
Work No. 9AV — Work No. not used.
In the County of Hampshire
Work No. 10A —Works to construct a permanent access to Work No. 2A, together with provision for vehicular parking, off the unnamed road in proximity to Netherhill Lane, in the indicative location shown on Sheet 2 of the Works Plans.
Work No. 10B —Works to construct a permanent access to Work No. 2B, together with provision for vehicular parking, off Cross Lane, in the indicative location shown on Sheet 4 of the Works Plans.
Work No. 10C —Works to construct a permanent access to Work No. 2C, together with provision for vehicular parking, off Lower Preshaw Lane and the private means of access to Betty Mundy’s Cottage, in the indicative location shown on Sheet 7 of the Works Plans.
Work No. 10D —Works to construct a permanent access to Work No. 2D, together with provision for vehicular parking, off Uncle Bill’s Lane, in the indicative location shown on Sheet 12 of the Works Plans.
Work No. 10E —Works to construct a permanent access to Work No. 2E, together with provision for vehicular parking, off Kitwood Lane, in the indicative location shown on Sheet 16 of the Works Plans.
Work No. 10F —Works to construct a permanent access to Work No. 2F, together with provision for vehicular parking, off Headmore Lane, in the indicative location shown on Sheet 17 of the Works Plans.
Work No. 10G — Works to construct a permanent access to Work No. 2G, together with provision for vehicular parking, off the B3006 Selbourne Road, in the indicative location shown on Sheet 20 of the Works Plans.
Work No. 10H —Works to construct a permanent access to Work No. 2H, off the access road to Alton Pumping Station, in the indicative location shown on Sheet 23 of the Works Plans.
Work No. 10I —Works to construct a permanent access to Work No. 2I, off Bourley Road (at Tweseldown Racecourse) in the indicative location shown on Sheets 31 and 102 of the Works Plans.
Work No. 10J —Works to construct a permanent access to Work No. 2J, off Concord Road/Whittle Roundabout, in the indicative location shown on Sheets 33 and 103 of the Works Plans.
In the County of Surrey
Work No. 11A —Works to construct a permanent access to Work No. 2K, together with provision for vehicular parking, along the access road to the SC Johnson Factory, off Frimley Green Road, in the indicative location shown on Sheets 36 and 112 of the Works Plans.
Work No. 11B — Works to construct a permanent access to Work No. 2L, off Guildford Road, in the indicative location shown on Sheet 41 of the Works Plans.
Work No. 11C — Works to construct a permanent access to Work No. 2M, together with provision for vehicular parking, off Steep Hill Lane, in the indicative location shown on Sheet 43 of the Works Plans.
Work No. 11D —Works to construct a permanent access to Work No. 2N, together with provision for vehicular parking, off The Knoll/Hanworth Lane, in the indicative location shown on Sheet 47 of the Works Plans.
Work No. 11E —Works to construct a permanent access to Work No. 2O, together with provision for vehicular parking off the B377 Ashford Road, in the indicative location shown on Sheets 51 and 124 of the Works Plans.
In connection with the construction of any of those works, further development within the Order limits which does not give rise to any materially new or materially different environmental effects to those assessed in the environmental statement consisting of—
- (a) site preparation works, site clearance (including fencing, vegetation removal, demolition of existing structures and the creation of alternative footpaths); earthworks (including soil stripping and storage and site levelling) and pre-construction drainage works;
- (b) installation of wires, cables, conductors, pipes and ducts;
- (c) establishment of winching points and installation of temporary scaffolding;
- (d) in relation to Works Nos. 1A to 1H (inclusive), 2A to 2O (inclusive) and 3A to 3C (inclusive), construction works including—
- (i) surveying and setting out;
- (ii) works to enable power supplies and temporary lighting;
- (iii) establishment of temporary working areas;
- (iv) installation of demarcation fencing/stockproof fencing/heras fencing or similar;
- (v) trenchless works, drive and reception pits, hydraulic rams, rollers and brackets, pipe thrusters and winch;
- (vi) topsoil and subsoil stripping and storage;
- (vii) archaeological surveys/investigations and watching brief;
- (viii) pipeline installation including pipe stringing, pipe bending, end preparation, front end welding, back end welding, fabrication welding, pipeline coating, pipeline trench excavation, dewatering activities, lower and lay, sand padding, backfilling, pipeline tie-ins, re-grading of soil, post construction drainage, cross-ripping and reinstatement of top-soil;
- (ix) filling, testing and dewatering test sections;
- (x) aerial markers, cathodic protection test posts, cathodic protection rectifier cabinets, sacrificial anodes and field boundary markers;
- (xi) reinstating test locations;
- (xii) removing demarcation fencing;
- (xiii) reinstating boundary walls, hedges and fencing;
- (xiv) final gauge plate and calliper surveys;
- (xv) drying and commissioning pipelines; and
- (xvi) demobilisation from site;
- (e) the carrying out of works to alter the layout of streets pursuant to article 10 (power to alter layout, etc. of streets) and of works to streets pursuant to article 11 (street works), as well as kerbing and paving, the provision of signals, road markings, traffic management measures and temporary roads;
- (f) works required for the strengthening, improvement, maintenance, or reconstruction of any street;
- (g) works to place, alter, remove or maintain street furniture;
- (h) the construction of ramps, means of access, non-motorised links, footpaths, footways, bridleways, cycle tracks and crossing facilities;
- (i) the construction of embankments, abutments, shafts, foundations, retaining walls, drainage, outfalls, ditches, pollution control devices, highway lighting, fencing and culverts;
- (j) works to place, alter, divert, relocate, remove or maintain the position of apparatus, services, plant and other equipment in a street, or in other land, including mains, sewers, drains, pipes, lights and cables;
- (k) works to alter the course of, or otherwise interfere with a watercourse, drainage works, attenuation ponds and temporary culverts;
- (l) works to rebuild recreational playground facilities, garden sheds, fences and other buildings and structures;
- (m) landscaping, noise barriers, works associated with the provision of ecological mitigation and other works to mitigate any adverse effects of the construction, maintenance or operation of the authorised development;
- (n) works for the benefit or protection of land, structures, apparatus or equipment affected by the authorised development;
- (o) the felling, planting and maintenance of trees and hedgerows;
- (p) establishment of site construction compounds, storage areas, temporary vehicle parking, construction fencing, perimeter enclosure, security fencing, construction related buildings, welfare facilities, construction lighting, haulage roads and other machinery, apparatus, works and conveniences; and
- (q) such other works, including scaffolding, working sites storage areas, works of demolition or works of whatever nature, as may be necessary or expedient for the purposes of, or for purposes associated with or ancillary to, the construction, operation or maintenance of the authorised development.
SCHEDULE 2 — REQUIREMENTS
PART 1 — REQUIREMENTS
Interpretation
1
In this Part—
- “archaeological mitigation strategy” means the strategy of that description set out in Schedule 11 (documents to be certified) and certified as the archaeological mitigation strategy by the Secretary of State for the purposes of this Order;
- “CEP” means the community engagement plan to be prepared and approved under Requirement 15 (community engagement plan);
- “contamination” means contamination of any land (including groundwater) within the Order limits which has not been previously identified in the environmental statement which is in the reasonable opinion of the undertaker likely to affect the construction of the authorised development and/or cause significant harm to persons or pollution of controlled waters or the environment;
- “CTMP” means the construction traffic management plan to be prepared and approved under Requirement 7 (construction traffic management plan);
- “European protected species” has the same meaning as in regulations 42 (European protected species of animals) and 46 (European protected species of plants) of the Conservation of Habitats and Species Regulations 2017[^f00070];
- “existing fuel pipeline” means so much of the existing Jetline pipeline from the undertaker’s Fawley refinery in Hampshire to the undertaker’s West London Terminal storage facility in the London Borough of Hounslow as is to be replaced by the pipeline works;
- “Habitats Regulations Assessment” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the Habitats Regulations Assessment by the Secretary of State for the purposes of this Order;
- “HRA Commitments Schedule” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the HRA Commitments Schedule by the Secretary of State for the purposes of this Order;
- “indicative layout drawings” means the drawings of that description set out in Schedule 11 (documents to be certified) and certified as the indicative layout drawings by the Secretary of State for the purposes of this Order;
- “Lead Local Flood Authority” means Hampshire County Council or Surrey County Council, as the case may be;
- “LEMP” means the landscape and ecological management plan to be prepared and approved under Requirement 12 (landscape and ecological management plan);
- “nationally protected species” means any species protected under the Wildlife and Countryside Act 1981[^f00071];
- “outline CEP” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the outline CEP by the Secretary of State for the purposes of this Order;
- “outline CEMP” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the outline CEMP by the Secretary of State for the purposes of this Order;
- “outline CTMP” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the outline CTMP by the Secretary of State for the purposes of this Order;
- “outline LEMP” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the outline LEMP by the Secretary of State for the purposes of this Order;
- “outline SFWDP” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the outline SFWDP by the Secretary of State for the purposes of this Order;
- “protected species” means European protected species or nationally protected species;
- “relevant authority” means the body responsible for giving a consent, agreement or approval under this Schedule;
- “SDNP Schedule” means the document of that description set out in Schedule 11 (documents to be certified) and certified as the SDNP Schedule by the Secretary of State for the purposes of this Order;
- “Site Specific Plans” means the plans of that description set out in Schedule 11 (documents to be certified) and certified as the site specific plans by the Secretary of State for the purposes of this Order;
- “SSSI working plans” means the plans of that description showing the method of working in sites of special scientific interest as set out in Appendix B of the Habitats Regulations Assessment; and
- “stage” means a defined spatial section or part of the authorised development, the extent of which is shown in a scheme submitted to the relevant planning authority pursuant to Requirement 3 (stages of authorised development).
Time limits
2
The authorised development must be commenced within five years of the date that this Order comes into force.
Stages of authorised development
3
The authorised development may not commence until a written scheme setting out all stages of the authorised development including a phasing plan indicating when each stage will be constructed has been submitted to each relevant planning authority.
Scheme design
4
- (1) Works Nos. 2B to 2G (inclusive), 2I to 2O (inclusive), 3A, 4A to 4AE (inclusive), 5A to 5U (inclusive), 6B and 6C must be carried out in general accordance with the indicative layout drawings.
- (2) The authorised development will not be in general accordance with the indicative layout drawings if any departure from the indicative layout drawings would give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
Code of construction practice
5
The authorised development must be undertaken in accordance with the code of construction practice, or with such changes to that document as agreed by the relevant planning authority, provided that any such changes must—
- (a) be in accordance with the principles set out in the code of construction practice;
- (b) be necessary or desirable to reflect a change or update in legislation, guidance or good practice or confined to a specific location along the route of the authorised development,
- (c) not give rise to any materially new or materially different environmental effects to those assessed in the environmental statement; and
- (d) not result in a variation to the measures set out in the HRA Commitments Schedule.
Construction environmental management plan
6
- (1) No stage of the authorised development must commence until a CEMP for that stage, in accordance with the outline CEMP, has been submitted to and approved by the relevant planning authority following consultation with the Lead Local Flood Authority and/or the Environment Agency as regards any water mitigation and management measures relevant to that stage.
- (2) The construction of each stage of the authorised development must be carried out in accordance with the approved CEMP for that stage.
- (3) The CEMP submitted for approval under paragraph (1) must include the mitigation measures to be secured by the CEMP as set out in the HRA Commitments Schedule.
Construction traffic
7
- (1) Save in respect of matters approved in accordance with article 13 (temporary closure, alteration, diversion or restriction of streets and public rights of way) no stage of the authorised development must commence until a CTMP for that stage, in accordance with the outline CTMP, has been submitted to and approved by the relevant planning authority following consultation with the relevant highway authority.
- (2) The CTMP for each stage must be implemented as approved.
Vegetation
8
- (1) For any stage of the authorised development that would affect any vegetation—
- (a) the retention and removal of all vegetation must be undertaken in accordance with—
- (i) a written vegetation retention and removal plan which has been submitted to the relevant planning authority prior to the commencement of that stage of the authorised development and which implements the requirements of the LEMP; or
- (ii) where applicable, the Site Specific Plans or such changes to those plans as may be requested by the undertaker and agreed by the relevant planning authority in accordance with Requirement 17 (site specific plans);
- (b) any written vegetation retention and removal plan submitted under sub-paragraph 8(1)(a)(i) in respect of the area of the South Downs National Park must also be in accordance with the SDNP Schedule or such changes to that Schedule as may be agreed by the South Downs National Park Authority as the relevant planning authority; and
- (c) the reinstatement of all vegetation must be undertaken in accordance with a written plan of reinstatement to be prepared by the undertaker in accordance with paragraph (2).
- (2) The written plan of reinstatement referred to in sub-paragraph (1)(c) must form part of the LEMP approved in accordance with Requirement 12 (landscape and ecological management plan).
- (3) Any vegetation which is part of an approved reinstatement plan that, within a period of five years beginning with the date of planting, is removed, uprooted, destroyed, dies or (in the reasonable opinion of the relevant planning authority) becomes seriously damaged or defective, must be replaced with planting material of the same specification as that originally planted unless otherwise approved by the relevant planning authority and the landowner concerned.
Surface and foul water drainage
9
- (1) No stage of the authorised development must commence until, for that stage, a surface and foul water drainage plan for permanent works relevant to that stage, in accordance with the outline SFWDP, has been submitted to and approved by the sewerage and/or drainage authority or, where applicable, the Environment Agency and/or the Lead Local Flood Authority.
- (2) The surface water drainage system for each stage must be constructed in accordance with the approved details.
- (3) No discharge of water under article 18 (discharge of water) must be made until details of the location and rate of discharge have been submitted to and approved in writing by the relevant sewerage and/or drainage authority or, where applicable, the Environment Agency and/or the Lead Local Flood Authority.
Contaminated land and groundwater
10
- (1) In the event that contamination is found at any time when carrying out the authorised development it must be reported in writing to the relevant planning authority.
- (2) Where contamination has been reported to the relevant planning authority in accordance with sub-paragraph (1), an investigation and risk assessment must be completed in accordance with a scheme to assess the nature and extent of any contamination on the part of the Order limits within which works are being carried out, whether or not that contamination originates on that part of the Order limits; and—
- (a) the contents of that scheme are subject to the approval of the relevant planning authority; and
- (b) that investigation and risk assessment must be undertaken in accordance with the approved scheme and a written report of the findings must be submitted to the relevant planning authority.
- (3) Where remediation is required to control or prevent the release or potential release of contamination as a result of the works, a detailed remediation scheme must be prepared and submitted for the approval of the relevant planning authority.
- (4) The approved remediation scheme must be carried out in accordance with its terms.
Archaeology
11
- (1) The authorised development must be undertaken in accordance with the archeological mitigation strategy.
- (2) No stage of the authorised development must commence until a written scheme for the investigation of areas of archaeological interest relevant to that stage (if any) as identified in the archaeological mitigation strategy has been submitted to and approved by the relevant planning authority.
- (3) The written scheme must reflect the measures set out in the archeological mitigation strategy.
- (4) The written scheme must identify areas where archaeological works are required and the measures to be taken to protect, record or preserve any significant archaeological remains that may be found and must include an implementation timetable.
- (5) Any archaeological works carried out under the scheme must be carried out by a suitably qualified and registered person or body and approved by the relevant planning authority.
- (6) Any archaeological works must be carried out in accordance with the approved scheme.
Landscape and ecological management plan
12
- (1) Subject to sub-paragraph (3), no stage of the authorised development must commence until a LEMP, for that stage, in accordance with the outline LEMP and the SSSI working plans, has been submitted to and approved by the relevant planning authority.
- (2) The LEMP must include an implementation timetable and must be carried out as approved.
- (3) Sub-paragraph (1) only applies to those stages of the authorised development in respect of which any landscape and ecological management measures are to be implemented by the undertaker, as identified in the outline LEMP.
- (4) The LEMP submitted for approval under sub-paragraph (1) must include the mitigation measures to be secured by the LEMP as set out in the HRA Commitments Schedule.
Protected species
13
- (1) In the event that any protected species which were not previously identified in the environmental statement are found at any time when carrying out the authorised development the undertaker must cease construction works and report it immediately to the Environmental Clerk of Works.
- (2) The undertaker must prepare a written scheme for the protection and mitigation measures for any protected species that were not previously identified in the environmental statement.
- (3) The undertaker must implement the written scheme prepared under sub-paragraph (2) immediately and construction in the area specified in the written scheme must not recommence until any necessary licences are obtained to enable mitigation measures to be implemented.
Construction hours
14
- (1) Subject to sub-paragraphs (2), (3) and (4), construction works must only take place between 0800 and 1800 on weekdays (except Public and Bank Holidays) and Saturdays, except in the event of an emergency.
- (2) In the event of an emergency, notification of that emergency must be given to the relevant planning authority and the relevant highway authority as soon as reasonably practicable.
- (3) The following operations may where necessary continue or take place on an exceptional basis outside the working hours referred to in sub-paragraph (1)—
- (a) trenchless construction techniques which cannot be interrupted;
- (b) filling, testing, dewatering and drying;
- (c) works required to mitigate delays to the construction of the authorised development due to extreme weather conditions; and
- (d) commissioning of the pipeline works.
- (4) Nothing in sub-paragraph (1) precludes—
- (a) the receipt of oversize deliveries to site and the undertaking of non-intrusive activities;
- (b) start-up and shut-down activities up to an hour either side of the core working hours and undertaken in compliance with the CEMP; and
- (c) works on a traffic sensitive street where so directed by the relevant highway authority pursuant to a permit granted under the permit schemes and following consultation by the relevant highway authority with the relevant planning authority under the terms of such scheme.
- (5) In this Requirement—
- (a) “emergency” means a situation where, if the relevant action is not taken, there will be adverse health, safety, security or environmental consequences that in the reasonable opinion of the undertaker would outweigh the adverse effects to the public (whether individuals, classes or generally as the case may be) of taking that action; and
- (b) “non-intrusive activities” means activities which would not create any discernible light, noise or vibration outside the Order limits.
Community engagement plan
15
- (1) No stage of the authorised development must commence until a CEP for that stage, in accordance with the outline CEP, has been submitted to and approved by the relevant planning authority.
- (2) The CEP for each stage must be implemented as approved.
Commercial operation of the existing fuel pipeline
16
The undertaker must ensure that the existing fuel pipeline is no longer capable of commercial operation once the pipeline works have been commissioned.
Site specific plans
17
The authorised development must be undertaken in accordance with the Site Specific Plans, or with such changes to those plans as agreed by the relevant planning authority provided that any such changes must be—
- (a) necessary or desirable to reflect a change or update in legislation, guidance or good practice; and
- (b) must not give rise to any materially new or materially different environmental effects to those assessed in the environmental statement and must not result in a variation to the measures set out in the HRA Commitments Schedule.
Removal of above-ground infrastructure
18
- (1) The undertaker must as soon as reasonably practicable following the abandonment of the authorised development, and in any event within six months of that date, remove any above-ground infrastructure, including for the avoidance of doubt, any aerial markers, cathodic protection test posts, cathodic protection rectifier cabinets and field boundary markers, to ground level.
- (2) In this Requirement—
- (a) “abandonment” means a final determination by the undertaker to permanently cease operating the authorised development; and
- (b) “above-ground infrastructure” means any part of the authorised development located above the surface of the ground which is not required for the operation of any other infrastructure owned or operated by the undertaker.
Written approval
19
Where under any of the Requirements the approval or agreement of the relevant planning authority or another person or authority is required, that approval or agreement must be given in writing.
Amendments to approved details
20
- (1) With respect to any Requirement which requires the authorised development to be carried out in accordance with the details approved by the relevant planning authority or another approval authority, the approved details must be carried out as approved unless an application for an amendment or variation is previously agreed, by the relevant planning authority or that other approval authority as specified in the relevant Requirement, in accordance with sub-paragraph (2) and in consultation with any body specified in the relevant Requirement.
- (2) No amendments to or variations from the approved details may be approved if their likely significant effects on the environment are not assessed in the environmental statement, or have not been subject to such further assessment as the relevant planning authority or that other approval authority may require; provided that such approval must not be given except where it has been demonstrated that the subject-matter of the approval sought is unlikely to give rise to any materially new or materially different environmental effects in comparison with the authorised development as approved (as identified in the environmental statement).
- (3) The approved details must be taken to include any amendments that may subsequently be approved by the relevant planning authority or that other approval authority.
- (4) Subject to sub-paragraph (2), if a relevant planning authority which receives an application for approval of any amendments to approved details under sub-paragraph (1) fails to notify the undertaker of its decision before the end of the period of 42 days beginning with the date on which the application was made, it is deemed to have granted consent.
Anticipatory steps towards compliance with any requirement
21
If, before the coming into force of this Order, the undertaker or any other person has taken any steps towards compliance with any provision of Part 1 of this Schedule, those steps may be taken into account for the purpose of determining compliance with that provision if they would have been valid steps for that purpose had they been taken after this Order came into force.
Register of requirements
22
- (1) The undertaker must, prior to the formal submission of any application for approval under Part 2 of this Schedule, establish and maintain in a form suitable for inspection by members of the public an online register of requirements contained in this Part of this Schedule that provide for approvals to be given by a relevant authority.
- (2) The register must set out in relation to each requirement the status of the requirement for each stage of the authorised development, in terms of whether any approval to be given by a relevant authority has been applied for or given in relation to that stage, providing an electronic link to any document containing any approved details.
- (3) The register must be maintained by the undertaker for a period of 3 years following completion of the authorised development.
PART 2 — PROCEDURE FOR DISCHARGE OF REQUIREMENTS
Applications made under Requirements
23
- (1) Where an application has been made to a relevant authority for any consent, agreement or approval under a Requirement, the relevant authority must give notice to the undertaker of its decision on the application within a period of 42 days beginning with—
- (a) where no further information is requested under Requirement 25, the day immediately following that on which the application is received by the authority;
- (b) where further information is requested under Requirement 25, the day immediately following that on which further information has been supplied by the undertaker; or
- (c) such longer period as may be agreed in writing by the undertaker and the relevant authority.
- (2) In the event that the relevant authority does not determine an application within the period set out in sub-paragraph (1), the relevant authority is taken to have granted all parts of the application (without any condition or qualification) at the end of that period unless otherwise agreed in writing.
Applications involving multiple relevant authorities under Requirements
24
Where an application is required to be made to more than one relevant authority for any single consent, agreement or approval under a Requirement, the undertaker may submit a request for comments in respect of its proposed application to each relevant authority and, where it does so, each relevant authority must provide its comments in writing on the proposed application within a period of 20 days beginning with the day immediately following that on which the request is received by the authority, so as to enable the undertaker to prepare a consolidated application to each relevant authority in respect of the consent, agreement or approval required by the Requirement.
Further information
25
- (1) Where an application has been made under Requirement 23 the relevant authority may, subject to complying with the requirements of this paragraph, request such reasonable further information from the undertaker as it considers is necessary to enable it to consider the application.
- (2) If the relevant authority considers further information is necessary and the Requirement does not specify that consultation with a requirement consultee is required, the relevant authority must, within five business days of receipt of the application, notify the undertaker in writing specifying the further information required.
- (3) If the Requirement specifies that consultation with a requirement consultee is required, the relevant authority must issue the consultation to the requirement consultee within five business days of receipt of the application and must notify the undertaker in writing specifying any further information requested by the requirement consultee within five business days of receipt of such a request and in any event within 21 days of receipt of the application.
- (4) If the relevant authority does not give the notification mentioned in sub-paragraphs (2) or (3) or otherwise fails to request any further information within the timescales provided for in this paragraph, it is deemed to have sufficient information to consider the application and is not thereafter entitled to request further information without the prior agreement of the undertaker.
Fees
26
- (1) Where an application or a request for comments is made to a relevant planning authority for any consent, agreement or approval required by a Requirement, a fee must be paid to the relevant planning authority as follows—
- (a) such fee as may be prescribed (under sections 303 and 333(2A) of the 1990 Act for the discharge of conditions attached to a planning permission); or
- (b) a fee of £97 per application or request.
- (2) Any fee paid under this Schedule must be refunded to the undertaker within 35 days of—
- (a) the application or request being rejected as invalidly made; or
- (b) the relevant planning authority failing to determine the application or to provide written comments within 42 days from the date on which the application is received, unless within that period the undertaker agrees in writing that the fee may be retained by the relevant planning authority and credited in respect of a future application or a future request for comments.
Appeals
27
- (1) The undertaker may appeal if—
- (a) the relevant authority refuses an application for–
- (i) any consent, agreement or approval required by a Requirement or any document referred to in any Requirement; or
- (ii) any other consent, agreement or approval required under this Order,
or grants it subject to conditions to which the undertaker objects;
- (b) having received a request for further information under Requirement 25 the undertaker considers that either the whole or part of the specified information requested by the relevant authority is not necessary for consideration of the application; or
- (c) having received any further information requested, the relevant authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application.
- (2) The procedure for appeals is as follows—
- (a) the undertaker must submit to the Secretary of State a copy of the application submitted to the relevant authority and any supporting documents which the undertaker may wish to provide (“the appeal documents”);
- (b) the undertaker must on the same day provide copies of the appeal documents to the relevant authority and the requirement consultee (if applicable);
- (c) within 28 days of receiving the appeals documents the Secretary of State must appoint a person to determine the appeal (“the appointed person”) and notify the appeal parties of the identity of the appointed person and the address to which all correspondence for the appointed person must be sent;
- (d) the relevant authority and the requirement consultee (if applicable) may submit any written representations in respect of the appeal to the appointed person within 10 business days beginning with the first day immediately following the date on which the appeal parties are notified of the appointment of the appointed person and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;
- (e) the appeal parties may make any counter-submissions to the appointed person within 10 business days beginning with the first day immediately following the date of receipt of written representations pursuant to sub-paragraph (d) above; and
- (f) the appointed person must make a decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable.
- (3) If the appointed person considers that further information is necessary to consider the appeal, the appointed person must as soon as practicable notify the appeal parties in writing specifying the further information required, the appeal party from whom the information is sought, and the date by which the information must be submitted.
- (4) Any further information required pursuant to sub-paragraph (3) must be provided by the party from whom the information is sought to the appointed person and to the other appeal parties by the date specified by the appointed person.
- (5) The appeal parties may submit written representations to the appointed person concerning matters contained in the further information.
- (6) Any such representations must be submitted to the appointed person and made available to all appeal parties within 10 business days of the date mentioned in sub-paragraph (3).
Outcome of appeals
28
- (1) On an appeal under Requirement 27, the appointed person may—
- (a) allow or dismiss the appeal; or
- (b) reverse or vary any part of the decision of the relevant authority (whether the appeal relates to that part of it or not),
and may deal with the application as if it had been made to the appointed person in the first instance.
- (2) The appointed person may proceed to a decision on an appeal taking into account only such written representations as have been sent within the time limits prescribed, or set by the appointed person under Requirement 27.
- (3) The appointed person may proceed to a decision even though no written representations have been made within those time limits if it appears to the appointed person that there is sufficient material to enable a decision to be made on the merits of the case.
- (4) The decision of the appointed person on an appeal is final and binding on the parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review within 6 weeks of the date of the appointed person’s decision.
- (5) Any consent, agreement or approval given by the appointed person pursuant to this Schedule is deemed to be an approval for the purpose of Part 1 of Schedule 2 (Requirements) as if it had been given by the relevant authority.
- (6) The relevant authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) does not affect or invalidate the effect of the appointed person’s determination.
- (7) Except where a direction is given pursuant to sub-paragraph (8) requiring the costs of the appointed person to be paid by the relevant authority, the reasonable costs of the appointed person must be met by the undertaker.
- (8) On application by the relevant authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction as to the costs of the appeal parties and the terms on which it is made, the appointed person must have regard to the Planning Practice Guidance: Appeals (March 2014) or any circular or guidance which may from time to time replace it.
29
In this Part—
- “the appeal parties” means the relevant authority, the requirement consultee and the undertaker;
- “relevant authority” means the body responsible for giving a consent, agreement or approval under this schedule; and
- “requirement consultee” means any body named in a Requirement which is the subject of an appeal as a body to be consulted by the relevant authority in discharging that Requirement.
SCHEDULE 3 — STREETS SUBJECT TO TEMPORARY ALTERATION OF LAYOUT
| (1) Street subject to alteration of layout | (2) Description of alteration of layout |
|---|---|
| Station Road – Ashford | Suspension of parking bays, single way working (one direction only) and alterations to entrance from Woodthorpe Road, as shown on Sheet No.52 of the Access & Rights of Way Plan |
SCHEDULE 4 — STREETS SUBJECT TO STREET WORKS
| (1) Street subject to street works | (2) Access & Rights of Way Plan Reference Number |
|---|---|
| In the County of Hampshire | In the County of Hampshire |
| Maddoxford Lane | Access & Rights of Way Plan Sheet No.1 |
| Unnamed Road between Heathen Street and Netherhill Lane | Access & Rights of Way Plan Sheet No.2 |
| Gregory Lane | Access & Rights of Way Plan Sheet No.2 |
| Mincingfield Lane | Access & Rights of Way Plan Sheet No.3 |
| Wintershill | Access & Rights of Way Plan Sheet No.4 |
| B2177 – Winchester Road | Access & Rights of Way Plan Sheet No.4 |
| Cross Lane | Access & Rights of Way Plan Sheet No.4 |
| Peak Lane | Access & Rights of Way Plan Sheet No.5 |
| Bigpath Lane | Access & Rights of Way Plan Sheet No.6 |
| Belmore | Access & Rights of Way Plan Sheet No.6 |
| Lower Preshaw Lane | Access & Rights of Way Plan Sheet No.6 |
| Wheely Down Farm Lane | Access & Rights of Way Plan Sheet No.9 |
| Kilmeston Road | Access & Rights of Way Plan Sheet No.9 |
| Joan’s Acre Lane | Access & Rights of Way Plan Sheet No.11 |
| Tithelands Lane | Access & Rights of Way Plan Sheet No.12 |
| Uncle Bill’s Lane | Access & Rights of Way Plan Sheet No.12 |
| Stapley Lane | Access & Rights of Way Plan Sheet No.14 |
| Soames Lane | Access & Rights of Way Plan Sheet No.14 |
| Smugglers Lane | Access & Rights of Way Plan Sheet No.15 |
| Lyeway Lane | Access & Rights of Way Plan Sheet No.15 |
| Kitwood Lane | Access & Rights of Way Plan Sheet No.16 |
| Hawthorn Road | Access & Rights of Way Plan Sheet No.16 |
| Headmore Lane | Access & Rights of Way Plan Sheet No.17 |
| Brightstone Lane | Access & Rights of Way Plan Sheet No.17 |
| Woodside Lane | Access & Rights of Way Plan Sheet No.18 |
| B3006 – Selborne Road | Access & Rights of Way Plan Sheet No.20 |
| Binsted Road | Access & Rights of Way Plan Sheet No.23 |
| West End | Access & Rights of Way Plan Sheet No.23 |
| Unnamed Road between A31 and Ryebridge Lane | Access & Rights of Way Plan Sheet No.24 |
| Gid Lane | Access & Rights of Way Plan Sheet No.24 |
| Froyle Road | Access & Rights of Way Plan Sheet No.25 |
| Isnage Farm Lane | Access & Rights of Way Plan Sheet No.26 |
| Hole Lane | Access & Rights of Way Plan Sheet No.26 |
| Dippenhall Road | Access & Rights of Way Plan Sheet No.27 |
| Dippenhall Street (Crondall) leading to Clare Park Road | Access & Rights of Way Plan Sheet No.28 |
| Heath Lane | Access & Rights of Way Plan Sheet No.29 |
| Redlands Lane | Access & Rights of Way Plan Sheet No.29 |
| Ewshot Lane | Access & Rights of Way Plan Sheet No.30 |
| Naishes Lane (1 of 3) | Access & Rights of Way Plan Sheet Nos. 30 and 101 |
| Naishes Lane (2 of 3) | Access & Rights of Way Plan Sheet Nos. 30 and 101 |
| Quetta Park | Access & Rights of Way Plan Sheet Nos. 30 and 101 |
| Jubilee Drive | Access & Rights of Way Plan Sheet Nos. 30 and 101 |
| Naishes Lane (3 of 3) | Access & Rights of Way Plan Sheet Nos. 30 and 101 |
| B3013 - Beacon Hill Road | Access & Rights of Way Plan Sheet Nos. 30 and 102 |
| Bourley Road | Access & Rights of Way Plan Sheet Nos. 31 and 102 |
| Aldershot Road | Access & Rights of Way Plan Sheet No.31 |
| Old Ively Road | Access & Rights of Way Plan Sheet Nos. 32 and 103 |
| Buccaneer Way | Access & Rights of Way Plan Sheet Nos. 32 and 103 |
| Comet Road | Access & Rights of Way Plan Sheet Nos. 32, 33 and 103 |
| Victor Way (West of Whittle Roundabout) | Access & Right of Way Plan Sheet Nos. 33 and 103 |
| Concorde Road | Access & Rights of Way Plan Sheet Nos. 33 and 103 |
| A327 – Ively Road | Access & Rights of Way Plan Sheet Nos. 33 and 103 |
| B3014 – Cove Road | Access & Rights of Way Plan Sheet Nos. 34 and 104 |
| Nash Close | Access & Rights of Way Plan Sheet Nos. 34 and 104 |
| Stake Lane Garages | Access & Rights of Way Plan Sheet Nos. 34 and 105 |
| Farnborough Road | Access & Rights of Way Plan Sheet Nos. 35 and 106 |
| Ship Lane | Access & Rights of Way Plan Sheet Nos. 35 and 108 |
| Ringwood Road | Access & Rights of Way Plan Sheet Nos. 35 and 108 |
| In the County of Surrey | In the County of Surrey |
| B4311 – Frimley Green Road | Access & Rights of Way Plan Sheet Nos. 36 and 113 |
| Balmoral Drive | Access & Rights of Way Plan Sheet Nos. 36, 112 and 113 |
| St Catherines Road | Access & Rights of Way Plan Sheet Nos. 36 and 113 |
| Rhododendron Road | Access & Rights of Way Plan Sheet Nos. 36 and 113 |
| Deepcut Bridge Road | Access & Rights of Way Plan Sheet No.38 |
| B3015 The Maultway | Access & Rights of Way Plan Sheet Nos. 38 and 39 |
| B311 Red Road | Access & Rights of Way Plan Sheet No.40 |
| Guildford Road | Access & Rights of Way Plan Sheet No.41 |
| Blackstroud Lane East | Access & Rights of Way Plan Sheet No.41 |
| Halebourne Lane | Access & Rights of Way Plan Sheet No.42 |
| Steep Hill | Access & Rights of Way Plan Sheet No.43 |
| B383 – Windsor Road | Access & Rights of Way Plan Sheet No.43 |
| Canford Drive (1 of 2) | Access & Rights of Way Plan Sheet Nos .48 and 116 |
| Canford Drive (2 of 2) | Access & Rights of Way Plan Sheet Nos .48 and 116 |
| Roakes Avenue | Access & Rights of Way Plan Sheet Nos. 48 and 116 |
| Mead Lane | Access & Rights of Way Plan Sheet Nos. 49 and 117 |
| Ashford Road | Access & Rights of Way Plan Sheet Nos. 51, 119 and 124 |
| Buxton Road | Access & Rights of Way Plan Sheet Nos. 52 and 120 |
| Prison entrance from Woodthorpe Road | Access & Rights of Way Plan Sheet Nos. 52 and 121 |
| Woodthorpe Road | Access & Rights of Way Plan Sheet Nos. 52, 121 and 122 |
| Station Approach | Access & Right of Way Plan Sheet Nos.52 & 122 |
| Station Road – Ashford | Access & Rights of Way Plan Sheet Nos. 52 and 122 |
| Short Lane | Access & Rights of Way Plan Sheet Nos. 53 and 123 |
SCHEDULE 5 — STREETS OR PUBLIC RIGHTS OF WAY TO BE TEMPORARILY CLOSED, ALTERED, DIVERTED OR RESTRICTED
PART 1 — STREETS OR PUBLIC RIGHTS OF WAY TO BE TEMPORARILY CLOSED, ALTERED, DIVERTED OR RESTRICTED FOR WHICH A DIVERSION IS TO BE PROVIDED
| (1) Street or Public Right of Way to be temporarily closed, altered, diverted or restricted | (2) Extent of temporary closure, alteration, diversion or restriction | (3) Temporary diversion |
|---|---|---|
| In the County of Hampshire | In the County of Hampshire | In the County of Hampshire |
| Durley Fp No.1 | Approximately 48 metres shown at point PRoW1 on Sheet No.1 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW1 on Sheet No.1 of the Access & Rights of Way Plan |
| Durley Fp No.1 | Approximately 68 metres shown at point PRoW2 on Sheet No.1 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW2 on Sheet No. 1 of the Access & Rights of Way Plan |
| Durley Fp No.1 | Approximately 125 metres shown at point PRoW3 on Sheet No.2 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW3 on Sheet No.2 of the Access & Rights of Way Plan |
| Durley Fp No.1 | Approximately 125 metres shown at point PRoW4 on Sheet No.2 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW4 on Sheet No.2 of the Access & Rights of Way Plan |
| Durley Fp No.3 | Approximately 49 metres shown at point PRoW5 on Sheet No.2 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW5 on Sheet No.2 of the Access & Rights of Way Plan |
| Durley Fp No.9 | Approximately 74 metres shown at point PRoW6 on Sheet No.2 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW6 on Sheet No.2 of the Access & Rights of Way Plan |
| Durley Fp No.26 | Approximately 64 metres shown at point PRoW7 on Sheet No.3 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW7 on Sheet No.3 of the Access & Rights of Way Plan |
| Durley Fp No.27 | Approximately 55 metres shown at point PRoW8 on Sheet No.3 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW8 on Sheet No.3 of the Access & Rights of Way Plan |
| Bishop Waltham Fp No.42a | Approximately 55 metres shown at point PRoW9 on Sheet No.4 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW9 on Sheet No.4 of the Access & Rights of Way Plan |
| Bishop Waltham Fp No.42a | Approximately 50 metres shown at point PRoW10 on Sheet No.4 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW10 on Sheet No.4 of the Access & Rights of Way Plan |
| Bishop Waltham Fp No.39 | Approximately 51 metres shown at point PRoW11 on Sheet No.4 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW11 on Sheet No.4 of the Access & Rights of Way Plan |
| Bishop Waltham Fp No.34 | Approximately 55 metres shown at point PRoW12 on Sheet No.4 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW12 on Sheet No.4 of the Access & Rights of Way Plan |
| Bishop Waltham Fp No.23 | Approximately 55 metres shown at point PRoW13 on Sheet No.5 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW13 on Sheet No.5 of the Access & Rights of Way Plan |
| Upham Fp No.4 | Approximately 52 metres shown at point PRoW14 on Sheet No.6 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW14 on Sheet No.6 of the Access & Rights of Way Plan |
| Exton Fp No.9a | Approximately 50 metres shown at point PRoW16 on Sheet No.7 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW16 on Sheet No.7 of the Access & Rights of Way Plan |
| Exton Br No.12b | Approximately 61 metres shown at point PRoW17 on Sheet No.8 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW17 on Sheet No.8 of the Access & Rights of Way Plan |
| Kilmiston Fp No.7 | Approximately 55 metres shown at point PRoW19 on Sheet No.9 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW19 on Sheet No.9 of the Access & Rights of Way Plan |
| Warnford Fp No.8 | Approximately 44 metres shown at point PRoW20 on Sheet No.10 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW20 on Sheet No.10 of the Access & Rights of Way Plan |
| Bramdean and Hinton Ampner Fp No.15b | Approximately 52 metres shown at point PRoW23 on Sheet No.11 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW23 on Sheet No.11 of the Access & Rights of Way Plan |
| Bramdean and Hinton Ampner Fp No.17 | Approximately 69 metres shown at point PRoW25 on Sheet No.11 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW25 on Sheet No.11 of the Access & Rights of Way Plan |
| Bramdean and Hinton Ampner Fp No.20a | Approximately 52 metres shown at point PRoW26 on Sheet No.12 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW26 on Sheet No.12 of the Access & Rights of Way Plan |
| Bramdean and Hinton Ampner Fp No.30 | Approximately 108 metres shown at point PRoW27 on Sheet No.12 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW27 on Sheet No.12 of the Access & Rights of Way Plan |
| Bramdean and Hinton Ampner Fp No.30 | Approximately 30 metres shown at point PRoW28 on Sheet No.12 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW28 on Sheet No.12 of the Access & Rights of Way Plan |
| West Tisted Br No.4 | Approximately 53 metres shown at point PRoW29 on Sheet No.13 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW29 on Sheet No.13 of the Access & Rights of Way Plan |
| West Tisted By No.27 | Approximately 65 metres shown at point PRoW30 on Sheet No.13 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW30 on Sheet No.13 of the Access & Rights of Way Plan |
| West Tisted By No.26 | Approximately 65 metres shown at point PRoW31 on Sheet No.13 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW31 on Sheet No.13 of the Access & Rights of Way Plan |
| West Tisted Fp No.7b | Approximately 48 metres shown at point PRoW32 on Sheet No.14 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW32 on Sheet No.14 of the Access & Rights of Way Plan |
| West Tisted Br No.6 | Approximately 40 metres shown at point PRoW33 on Sheet No.14 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW33 on Sheet No.14 of the Access & Rights of Way Plan |
| Ropley Fp No.34 | Approximately 48 metres shown at point PRoW34 on Sheet No.14 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW34 on Sheet No.14 of the Access & Rights of Way Plan |
| Ropley Fp No.31 | Approximately 43 metres shown at point PRoW35 on Sheet No.15 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW35 on Sheet No.15 of the Access & Rights of Way Plan |
| Ropley Fp No.32 | Approximately 46 metres shown at point PRoW36 on Sheet No.15 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW36 on Sheet No.15 of the Access & Rights of Way Plan |
| Ropley Fp No.32 | Approximately 44 metres shown at point PRoW37 on Sheet No.15 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW37 on Sheet No.15 of the Access & Rights of Way Plan |
| Four Marks By No.23 | Approximately 59 metres shown at point PRoW38 on Sheet No.16 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW38 on Sheet No.16 of the Access & Rights of Way Plan |
| Four Marks Fp No.8 | Approximately 44 metres shown at point PRoW39 on Sheet No.17 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW39 on Sheet No.17 of the Access & Rights of Way Plan |
| Four Marks Fp No.13 | Approximately 112 metres shown at point PRoW40 on Sheet No.17 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW40 on Sheet No.17 of the Access & Rights of Way Plan |
| Farringdon By No.22 | Approximately 45 metres shown at point PRoW41 on Sheet No.17 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW41 on Sheet No.17 of the Access & Rights of Way Plan |
| Farringdon Fp No.4 | Approximately 50 metres shown at point PRoW42 on Sheet No.17 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW42 on Sheet No.17 of the Access & Rights of Way Plan |
| Farringdon By No.24 | Approximately 35 metres shown at point PRoW43 on Sheet No.17 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW43 on Sheet No.17 of the Access & Rights of Way Plan |
| Farringdon Fp No.9 | Approximately 52 metres shown at point PRoW44 on Sheet No.17 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW44 on Sheet No.17 of the Access & Rights of Way Plan |
| Farringdon Fp No.1 | Approximately 40 metres shown at point PRoW45 on Sheet No.18 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW45 on Sheet No.18 of the Access & Rights of Way Plan |
| Farringdon Fp No.6 | Approximately 38 metres shown at point PRoW46 on Sheet No.18 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW46 on Sheet No.18 of the Access & Rights of Way Plan |
| Farringdon Fp No.18 | Approximately 39 metres shown at point PRoW49 on Sheet No.19 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW49 on Sheet No.19 of the Access & Rights of Way Plan |
| Chawton Fp No.7 | Approximately 60 metres shown at point PRoW50 on Sheet No.20 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW50 on Sheet No.20 of the Access & Rights of Way Plan |
| Alton Cp No.66 | Approximately 100 metres shown at point PRoW51 on Sheet No.20 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW51 on Sheet No.20 of the Access & Rights of Way Plan |
| Worldham Fp No.5 | Approximately 50 metres shown at point PRoW52 on Sheet No.20 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW52 on Sheet No.20 of the Access & Rights of Way Plan |
| Worldham Fp No.20 | Approximately 43 metres shown at point PRoW53 on Sheet No.20 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW53 on Sheet No.20 of the Access & Rights of Way Plan |
| Worldham By No.40 | Approximately 54 metres shown at point PRoW54 on Sheet No.21 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW54 on Sheet No.21 of the Access & Rights of Way Plan |
| Worldham Fp No.43 | Approximately 44 metres shown at point PRoW55 on Sheet No.21 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW55 on Sheet No.21 of the Access & Rights of Way Plan |
| Worldham Fp No.21 | Approximately 39 metres shown at point PRoW56 on Sheet No.21 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW56 on Sheet No.21 of the Access & Rights of Way Plan |
| Worldham Fp No.31 | Approximately 44 metres shown at point PRoW57 on Sheet No.21 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW57 on Sheet No.21 of the Access & Rights of Way Plan |
| Worldham Fp No.32 | Approximately 91 metres shown at point PRoW58 on Sheet No.22 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW58 on Sheet No.22 of the Access & Rights of Way Plan |
| Binsted Fp No.1 | Approximately 91 metres shown at point PRoW59 on Sheet No.22 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW59 on Sheet No.22 of the Access & Rights of Way Plan |
| Binsted Fp No.3 | Approximately 56 metres shown at point PRoW60 on Sheet No.22 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW60 on Sheet No.22 of the Access & Rights of Way Plan |
| Binsted Fp No.4 | Approximately 52 metres shown at point PRoW61 on Sheet No.22 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW61 on the Access & Rights of Way Plan Sheet No.22 |
| Binsted Fp No.57 | Approximately 38 metres shown at point PRoW62 on Sheet No.23 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW62 on Sheet No.23 of the Access & Rights of Way Plan |
| Froyle Fp No. 18 | Approximately 83 metres shown at point PRoW63 on Sheet No.24 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW63 on Sheet No.24 of the Access & Rights of Way Plan |
| Froyle Fp No.12 | Approximately 86 metres shown at point PRoW64 on Sheet No.24 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW64 on Sheet No.24 of the Access & Rights of Way Plan |
| Froyle Fp No.9 | Approximately 55 metres shown at point PRoW67 on Sheet No.24 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW67 on Sheet No.24 of the Access & Rights of Way Plan |
| Froyle Fp No.7 | Approximately 43 metres shown at point PRoW68 on Sheet No.25 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW68 on Sheet No.25 of the Access & Rights of Way Plan |
| Bentley Fp No.4 | Approximately 91 metres shown at point PRoW69 on Sheet No.25 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW69 on Sheet No.25 of the Access & Rights of Way Plan |
| Bentley Fp No.8 | Approximately 48 metres shown at point PRoW70 on Sheet No.26 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW70 on Sheet No.26 of the Access & Rights of Way Plan |
| Crondall Fp No.504 | Approximately 63 metres shown at point PRoW71 on Sheet No.28 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW71 on Sheet No.28 of the Access & Rights of Way Plan |
| Crondall Fp No.1 | Approximately 51 metres shown at point PRoW72 on Sheet No.28 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW72 on Sheet No.28 of the Access & Rights of Way Plan |
| Crondall Fp No.2 | Approximately 51 metres shown at point PRoW73 on Sheet No.28 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW73 on Sheet No.28 of the Access & Rights of Way Plan |
| Eweshot Fp No.741 | Approximately 132 metres shown at point PRoW74 on Sheet Nos. 30 and 101 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW74 on Sheet Nos. 30 and 101 of the Access & Rights of Way Plan |
| Eweshot Fp No.743 | Approximately 67 metres shown at point PRoW75 on Sheet Nos. 30 and 101 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW75 on Sheet Nos. 30 and 101 of the Access & Rights of Way Plan |
| Church Crookham Fp No.741 | Approximately 143 metres shown at point PRoW76 on Sheet Nos. 30 and 101 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW76 on Sheet Nos. 30 and 101 of the Access & Rights of Way Plan |
| Church Crookham Fp No.741 | Approximately 77 metres shown at point PRoW77 on Sheet Nos. 30 and 101 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW77 on Sheet Nos. 30 and 101 of the Access & Rights of Way Plan |
| Fleet CP Br No.725 | Approximately 81 metres shown at point PRoW78 on Sheet No.32 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW78 on Sheet No.32 of the Access & Rights of Way Plan |
| Rushmoor Fp No.10 | Approximately 59 metres shown at point PRoW79 on Sheet Nos. 33 and 103 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW79 on Sheet Nos. 33 and 103 of the Access & Rights of Way Plan |
| Rushmoor Fp No.20b | Approximately 71 metres shown at point PRoW80 on Sheet Nos.35 and 108 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW80 on Sheet Nos. 35 and 108 of the Access & Rights of Way Plan |
| In the County of Surrey | In the County of Surrey | In the County of Surrey |
| St Catherines Road | Approximately 130 metres between points E and F as shown on Sheet No.36 of the Access & Rights of Way Plan | Diversions via Public Highways Regent Way, Alphington Avenue, Tomlins Avenue, the B331 Chobham Road, Old Bisley Road, the B3015 Deepcut Bridge Road and Lake Road as shown on Sheet Nos. 60 and 61 of the Access & Rights of Way Plan |
| Camberley 7 Frimley CP Br No.13 | Approximately 92 metres shown at point PRoW82 on Sheet Nos. 36 and 113 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW82 on Sheet Nos. 36 and 113 of the Access & Rights of Way Plan |
| Camberley & Frimley CP Br No.14 | Approximately 92 metres shown at point PRoW83 on Sheet Nos. 36 and 113 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW83 on Sheet Nos. 36 and 113 of the Access & Rights of Way Plan |
| Camberley & Frimley CP Fp No.16 | Approximately 475 metres shown at point PRoW84 on Sheet No.37 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW84 on Sheet No.37 of the Access & Rights of Way Plan |
| Camberley & Frimley CP Br No.15 | Approximately 77 metres shown at point PRoW85 on Sheet No.37 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW85 on Sheet No.37 of the Access & Rights of Way Plan |
| Camberley & Frimley CP Fp No.126a | Approximately 189 metres shown at point PRoW87 on Sheet No.38 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW87 on Sheet No.38 of the Access & Rights of Way Plan |
| Camberley & Frimley CP Fp No.193 | Approximately 67 metres shown at point PRoW88 on Sheet No.39 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW88 on Sheet No.39 of the Access & Rights of Way Plan |
| West End CP Br No.129 | Approximately 18 metres shown at point PRoW91 on Sheet No.41 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW91 on Sheet No.41 of the Access & Rights of Way Plan |
| West End CP Fp No.157 | Approximately 74 metres shown at point PRoW93 on Sheet No.41 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW93 on Sheet No.41 of the Access & Rights of Way Plan |
| West End CP Fp No.40 | Approximately 65 metres shown at point PRoW94 on Sheet No.41 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW94 on Sheet No.41 of the Access & Rights of Way Plan |
| West End CP Br No.41 | Approximately 46 metres shown at point PRoW95 on Sheet No.41 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW95 on Sheet No.41 of the Access & Rights of Way Plan |
| West End CP Fp No.122 | Approximately 70 metres shown at point PRoW96 on Sheet No.42 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW96 on Sheet No.42 of the Access & Rights of Way Plan |
| Chobham CP Fp No.122 | Approximately 31 metres shown at point PRoW97 on Sheet No.42 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW97 on Sheet No.42 of the Access & Rights of Way Plan |
| Chobham CP Fp No.42 | Approximately 31 metres shown at point PRoW98 on Sheet No.42 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW98 on Sheet No.42 of the Access & Rights of Way Plan |
| Chobham CP Fp No.58 | Approximately 50 metres shown at point PRoW100 on Sheet No.42 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW100 on Sheet No.42 of the Access & Rights of Way Plan |
| Chobham CP Br No.87 | Approximately 45 metres shown at point PRoW101 on Sheet No.43 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW101 on Sheet No.43 of the Access & Rights of Way Plan |
| Chobham CP Br No.202 | Approximately 46 metres shown at point PRoW102 on Sheet No.43 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW102 on Sheet No.43 of the Access & Rights of Way Plan |
| Chobham CP Fp No.86 | Approximately 47 metres shown at point PRoW103 on Sheet No.43 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW103 on Sheet No.43 of the Access & Rights of Way Plan |
| Chobham CP Fp No.91 | Approximately 44 metres shown at point PRoW104 on Sheet No.43 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW104 on Sheet No.43 of the Access & Rights of Way Plan |
| Chobham CP Br No.90 | Approximately 49 metres shown at point PRoW105 on Sheet No.43 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW105 on Sheet No.43 of the Access & Rights of Way Plan |
| Chobham CP Fp No.55 | Approximately 43 metres shown at point PRoW106 on Sheet No.43 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW106 on Sheet No.43 of the Access & Rights of Way Plan |
| Chobham CP Fp No.97 | Approximately 45 metres shown at point PRoW107 on Sheet No.44 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW107 on Sheet No.44 of the Access & Rights of Way Plan |
| Chobham CP Br No.187 | Approximately 64 metres shown at point PRoW108 on Sheet No.44 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW108 on Sheet No.44 of the Access & Rights of Way Plan |
| Chertsey CP Fp No.46 | Approximately 67 metres shown at point PRoW110 on Sheet No.44 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW110 on Sheet No.44 of the Access & Rights of Way Plan |
| Chertsey CP Fp No.36 | Approximately 43 metres shown at point PRoW111 on Sheet No.47 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW111 on Sheet No.47 of the Access & Rights of Way Plan |
| Chertsey CP Fp No.36 | Approximately 76 metres shown at point PRoW112 on Sheet No.47 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW112 on Sheet No.47 of the Access & Rights of Way Plan |
| Chertsey CP Fp No.35 | Approximately 52 metres shown at point PRoW113 on Sheet Nos. 48 and 116 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW113 on Sheet Nos. 48 and 116 of the Access & Rights of Way Plan |
| Chertsey CP Fp No.8 | Approximately 49 metres shown at point PRoW114 on Sheet Nos. 48, 49 and 116 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW114 on Sheet Nos. 48, 49 and 116 of the Access & Rights of Way Plan |
| Chertsey CP Fp No.70 | Approximately 49 metres shown at point PRoW115 on Sheet Nos. 48, 49 and 116 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW115 on Sheet Nos. 48, 49 and 116 of the Access & Rights of Way Plan |
| Chertsey CP Fp No.8 | Approximately 26 metres shown at point PRoW116 on Sheet Nos. 48, 49 and 116 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW116 on Sheet Nos. 48, 49 and 116 of the Access & Rights of Way Plan |
| Chertsey CP Fp No.9 | Approximately 42 metres shown at point PRoW117 on Sheet Nos. 48, 49 and 116 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW117 on Sheet Nos. 48, 49 and 116 of the Access & Rights of Way Plan |
| Chertsey CP Fp No.9 | Approximately 11 metres shown at point PRoW118 on Sheet Nos. 48, 49 and 116 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW118 on Sheet Nos. 48, 49 and 116 of the Access & Rights of Way Plan |
| Staines CP Fp No.26 | Approximately 16 metres shown at point PRoW122 on Sheet Nos. 52 and 122 of the Access & Rights of Way Plan | Within Order limits and shown as DPRoW122 on Sheet Nos. 52 and 122 of the Access & Rights of Way Plan |
PART 2 — STREETS OR PUBLIC RIGHTS OF WAY TO BE TEMPORARILY CLOSED, ALTERED, DIVERTED OR RESTRICTED FOR WHICH NO DIVERSION IS TO BE PROVIDED
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.