The West Midlands Rail Freight Interchange Order 2020
- (a) in constructing any part of a specified work on behalf of the undertaker or in constructing any protective works including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;
- (b) in respect of the approval by the Trust of plans submitted by the undertaker and the supervision by it of the construction of a specified work or any protective works;
- (c) in respect of the employment or procurement of the services of any persons whom it must be reasonably necessary to appoint for inspecting, signalling, watching and lighting the waterway and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or incident arising from the construction or failure of a specified work or any protective works;
- (d) in respect of any additional temporary lighting of the waterway in the vicinity of the specified works or any protective works, being lighting made reasonably necessary by reason or in consequence of the construction or failure of a specified work or protective work;
- (e) in bringing the specified works or any protective works to the notice of users of the Trust’s network; and
- (f) in constructing and/or carrying out any measures relating to the authorised development which are reasonably required by the Trust to ensure the safe navigation of the waterway save that nothing shall require the Trust to construct and/or carry out such measures.
20
- (1) If any permanent or temporary alterations or additions to the waterway are reasonably necessary in consequence of the construction of a specified work, or during a period of 24 months after the completion of that work in order to ensure the safety of the waterway, the continued safe operation of the waterway or the prevention of a detriment such alterations and additions may be carried out by the Trust upon the giving of reasonable notice to the undertaker and the undertaker must pay to the Trust the reasonable cost of those alterations or additions including, in respect of any such alterations and additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by the Trust in maintaining, working and, when necessary, renewing any such alternations or additions.
- (2) If during the construction of a specified work by the undertaker, the Trust gives notice to the undertaker that the Trust desires itself to construct that part of the specified work which in the opinion of the Trust is endangering the stability of the waterway or the safe operation of any waterway then, if the undertaker decided that part of the specified work is to be constructed, the Trust shall assume construction of that part of the specified work under paragraph 4(3) of this Part of this Schedule and the undertaker must pay to the Trust all reasonable expenses to which the Trust may be put and compensation for any loss which it may suffer by reason of the execution by the Trust of that specified work.
- (3) The Trust must, in respect of the capitalised sums referred to in this paragraph and the other provisions of this Part of this Schedule, provide such details of the formula by which those sums have been calculated as the undertaker may reasonably request in writing within 14 days of Trust notifying the undertaker of the amount of the capitalised sums.
- (4) If the cost of maintaining, working or renewing the waterway is reduced in consequence of any such alterations or additions, a capitalised sum representing such saving is to be set off against any sum payable by the undertaker to the Trust under this paragraph.
Costs of alterations
21
Any additional expenses which the Trust may reasonably incur in altering, reconstructing or maintaining the waterway under any powers existing at the date when this Order was made by reason of the existence of a specified work must, provided that 56 days’ previous notice of the commencement of such alteration, reconstruction or maintenance has been given to the undertaker, be paid by the undertaker to the Trust.
22
- (1) The fact that any act or thing may have been done by the Trust on behalf of the undertaker or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under the engineer's supervision or in accordance with any directions or awards of an arbitrator does not (if it was done without negligence on the part of the Trust or of any person in its employ or of its contractors or agents) excuse the undertaker from any liability under the provisions of this paragraph.
- (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the neglect or wilful default of the Trust, its officers, servants, contractors or agents.
Fencing
23
Where so reasonably required by the engineer the undertaker must to the reasonable satisfaction of the engineer fence off a specified work or protective works or take such other steps as the engineer may require to be taken for the purpose of separating a specified work or protective works from the waterway, whether on a temporary or permanent basis or both.
Capitalised sums
24
Any capitalised sum which is required to be paid under this Part of this Schedule must be calculated by multiplying the cost of the maintenance or renewal works to the waterway necessitated as a result of the operation of the authorised development by the number of times that the maintenance or renewal works will be required during the operation of the authorised development.
Expert determination
25
- (1) Article 47 (arbitration) does not apply to this Part of this Schedule except in respect of sub-paragraph (7).
- (2) Any difference under this Part of this Schedule must be referred to and settled by a single independent and suitable person who holds appropriate professional qualifications and is a member of a professional body relevant to the matter in dispute acting as an expert, such person to be agreed by the undertaker and the Trust or, in the absence of agreement, identified by the President of the Institution of Civil Engineers.
- (3) All parties involved in settling any difference must use best endeavours to do so within 21 days from the date of a dispute first being notified in writing by one party to the other and in the absence of the difference being settled within that period the expert must be appointed within 28 days of the notification of the dispute.
- (4) The fees of the expert are payable by the parties in such proportions as the expert may determine or, in the absence of such determination, equally.
- (5) The expert must—
- (a) invite the parties to make submissions to the expert in writing and copied to the other party to be received by the expert within 21 days of the expert's appointment;
- (b) permit a party to comment on the submissions made by the other party within 21 days of receipt of the submission;
- (c) issue a decision within 42 days of receipt of the submissions under paragraph (b); and
- (d) give reasons for the decision.
- (6) The expert must consider where relevant—
- (a) the development outcome sought by the undertaker;
- (b) the ability of the undertaker to achieve its outcome in a timely and cost-effective manner;
- (c) the status of the Trust as a registered charity;
- (d) the requirement for the Trust to comply with its statutory duties and responsibilities;
- (e) the nature of the power sought to be exercised by the undertaker;
- (f) the effectiveness, cost and reasonableness of proposals for mitigation arising from any party; and
- (g) any other important and relevant consideration.
- (7) Any determination by the expert is final and binding, except in the case of manifest error in which case the difference that has been subject to expert determination may be referred to and settled by arbitration under article 47.
PART 8 — FOR THE PROTECTION OF CADENT GAS LIMITED AS GAS UNDERTAKER
Application
1
The provisions of this Part of this Schedule have effect unless otherwise agreed in writing between the undertaker and Cadent.
Interpretation
2
In this Part of this Schedule—
- “alternative apparatus” means appropriate alternative apparatus to the satisfaction of Cadent to enable it to fulfil its statutory functions in a manner no less efficient than previously;
- “apparatus” means any gas mains, pipes, pressure governors, ventilators, cathodic protection, cables or other apparatus belonging to or maintained by Cadent for the purpose of gas supply together with any replacement apparatus and such other apparatus constructed pursuant to the Order that becomes operational apparatus of Cadent for the purposes of transmission, distribution and/or supply and includes any structure in which apparatus is or will be lodged or which gives or will give access to the apparatus;
- “authorised works” has the same meaning as is given to the term “authorised development” in article 2 (interpretation) of this Order and includes any associated development authorised by the Order and for the purposes of this Part of this Schedule includes the use and maintenance of the authorised works and construction of any works authorised by this Part of this Schedule;
- “Cadent” means Cadent Gas Limited (Company Number 10080864) whose registered office is situated at Ashbrook Court, Prologis Park, Central Boulevard, Coventry, CV7 8EP and any successor in title or assignee including any successor to their license as a gas transporter under Part 1 of the Gas Act 1986[^f00089];
- “deed of consent” means a deed of consent, crossing agreement, deed of variation or new deed of grant agreed between the parties acting reasonably in order to vary and/or replace existing easements, agreements, enactments and other such interests so as to secure land rights and interests as are necessary to carry out, maintain, operate and use the apparatus in a manner consistent with the terms of this Part of this Schedule;
- “functions” includes powers and duties;
- “ground mitigation scheme” means a scheme approved by the undertaker (such approval not to be unreasonably withheld or delayed) setting out the necessary measures (if any) for a ground subsidence event;
- “ground monitoring scheme” means a scheme for monitoring ground subsidence which sets out the apparatus which is to be subject to such monitoring, the extent of land to be monitored, the manner in which ground levels are to be monitored, the timescales of any monitoring activities and the extent of ground subsidence which, if exceeded, will require the undertaker to submit for Cadent’s approval a ground mitigation scheme;
- “ground subsidence event” means any ground subsidence identified by the monitoring activities set out in the ground monitoring scheme that has exceeded the level described in the ground monitoring scheme as requiring a ground mitigation scheme;
- “in”, in a context referring to apparatus or alternative apparatus in land, includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;
- “maintain” and “maintenance” includes the ability and right to do any of the following in relation to any apparatus or alternative apparatus of Cadent including construct, use, repair, alter, inspect, renew or remove the apparatus;
- “plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed; and
- “specified works” means any of the authorised works or activities undertaken in association with the authorised works which— will or may be situated over, or within 15 metres measured in any direction of any apparatus the removal of which has not been required by the undertaker under paragraph 6(2) of this Part of this Schedule or otherwise; or include any of the activities that are referred to in paragraph 8 of T/SP/SSW/22 Cadent policies for safe working in proximity to gas apparatus “Specification for safe working in the vicinity of National Grid, High pressure Gas pipelines and associated installation requirements for third parties T/SP/SSW/22”.
On Street Apparatus
3
- (1) Except for paragraphs 4 (apparatus of Cadent in stopped up streets), 6 (removal of apparatus) and 7 (facilities and rights for alternative apparatus) (in so far as sub-paragraph (2) applies), 8 (retained apparatus: protection), 9 (expenses) and 10 (indemnity) of this Part of this Schedule which will apply in respect of the exercise of all or any powers under the Order affecting the rights and apparatus of the undertaker, and subject to sub-paragraph (2), the other provisions of this Part of this Schedule do not apply to apparatus in respect of which the relations between the undertaker and Cadent are regulated by the provisions of Part 3 of the 1991 Act.
- (2) Notwithstanding sub-paragraph (1), paragraphs 6 and 7 of this Part of this Schedule apply to diversions even where carried out under the 1991 Act, in circumstances where any apparatus is diverted from an alignment within the existing adopted public highway but not wholly replaced within existing adopted public highway.
- (3) Notwithstanding article 33(5) (rights under or over streets) and article 35(7) (temporary use of land for maintaining the authorised development) or any other powers in the Order generally, section 85 (sharing cost of necessary measures) of the 1991 Act, and the regulations made thereunder, do not apply in relation to any diversion of apparatus of Cadent under the 1991 Act.
Apparatus of Cadent in stopped up streets
4
- (1) Without prejudice to the generality of any other protection afforded to Cadent elsewhere in the Order, where any street is stopped up under article 10 (permanent stopping up of streets), if Cadent has any apparatus in the street or accessed via that street Cadent will be entitled to the same rights in respect of such apparatus as it enjoyed immediately before the stopping up and the undertaker will grant to Cadent, or will procure the granting to Cadent, legal easements reasonably satisfactory to Cadent in respect of such apparatus and access to it prior to the stopping up of any such street but nothing is this paragraph affects any right of the undertaker or Cadent to require removal of the apparatus under paragraph 6 of this Part of this Schedule.
- (2) Notwithstanding the temporary stopping up or diversion of any street under the powers of article 11 (temporary stopping up of streets), Cadent will be at liberty at all times to take all necessary access across any such stopped up street and/or to execute and do all such works and things in, upon or under any such street as may be reasonably necessary or desirable to enable it to maintain any apparatus which at the time of the stopping up or diversion was in that street.
- (3) The protective provisions in this Part of this Schedule apply and take precedence over article 36(2) to (7) (apparatus and rights of statutory undertakers in stopped up streets) of the Order which do not apply to Cadent.
Acquisition of land
5
- (1) Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference, the undertaker may not acquire any land interest or apparatus or acquire, extinguish, interfere with or otherwise override any easement and/or other interest or right of Cadent otherwise than by agreement.
- (2) As a condition of agreement between the parties in sub-paragraph (1), prior to the carrying out of any part of the authorised works (or in such other timeframe as may be agreed between Cadent and the undertaker) that are subject to the requirements of this Part of this Schedule that will cause any conflict with or breach the terms of any easement or other legal or land interest of Cadent or affects the provisions of any enactment or agreement regulating the relations between Cadent and the undertaker in respect of any apparatus laid or erected in land belonging to or secured by the undertaker, the undertaker must as Cadent reasonably requires enter into such deeds of consent upon such terms and conditions as may be agreed between Cadent and the undertaker acting reasonably and which must be no less favourable on the whole to Cadent unless otherwise agreed by Cadent, and it will be the responsibility of the undertaker to procure or secure the consent and entering into of such deeds and variations by all other third parties with an interest in the land at that time who are affected by such authorised works.
- (3) Where there is any inconsistency or duplication between the provisions set out in this Part of this Schedule relating to the relocation or removal of apparatus (including the payment of costs and expenses relating to such relocation or removal of apparatus) and the provisions of any existing easement, rights, agreements and licences granted, used, enjoyed or exercised by Cadent or other enactments relied upon by Cadent as of right or other use in relation to the apparatus, then the provisions in this Part of this Schedule prevail.
- (4) Any agreement or consent granted by Cadent under paragraph 8, or any other paragraph, of this Part of this Schedule, is not be taken to constitute agreement under sub-paragraph (1).
Removal of apparatus
6
- (1) If, in the exercise of the agreement reached in accordance with paragraph 5 of this Part of this Schedule or in any other authorised manner, the undertaker acquires any interest in any land in which any apparatus is placed, that apparatus must not be removed under this Part of this Schedule and any right of Cadent to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed, and is in operation to the reasonable satisfaction of Cadent in accordance with sub-paragraphs (2) to (5).
- (2) If, for the purpose of executing any works in, on, under or over any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to Cadent advance written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order Cadent reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to Cadent to its satisfaction (taking into account paragraph 8(1) of this Part of this Schedule) the necessary facilities and rights—
- (a) for the construction of alternative apparatus in other land of or land secured by the undertaker; and
- (b) subsequently for the maintenance of that apparatus.
- (3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of or land secured by the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, Cadent must, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances in an endeavour to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed, with the undertaker’s assistance if required by Cadent, save that this obligation does not extend to the requirement for Cadent to use its compulsory purchase powers to this end unless it elects to so do.
- (4) Any alternative apparatus to be constructed in land of or land secured by the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between Cadent and the undertaker.
- (5) Cadent must, after the alternative apparatus to be provided or constructed has been agreed, and subject to the prior grant to Cadent of any such facilities and rights as are referred to in sub-paragraph (2) or (3), then proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
Facilities and rights for alternative apparatus
7
- (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to or secures for Cadent facilities and rights in land for the construction, use, maintenance and protection of alternative apparatus in substitution for apparatus to be removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between the undertaker and Cadent and must be no less favourable on the whole to Cadent than the facilities and rights enjoyed by it in respect of the apparatus to be removed unless otherwise agreed by Cadent.
- (2) If the facilities and rights to be afforded by the undertaker and agreed with Cadent under sub-paragraph (1) in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are less favourable on the whole to Cadent than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject in the matter will be referred to arbitration in accordance with paragraph 14 of this Part of this Schedule and the arbitrator is to make such provision for the payment of compensation by the undertaker to Cadent as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
Retained apparatus: protection
8
- (1) Not less than 56 days before the commencement of any specified works the undertaker must submit to Cadent a plan and, if reasonably required by Cadent, a ground monitoring scheme in respect of those works.
- (2) The plan to be submitted to the undertaker under sub-paragraph (1) must include a method statement and describe—
- (a) the exact position of the works;
- (b) the level at which these are proposed to be constructed or renewed;
- (c) the manner of their construction or renewal including details of excavation, positioning of plant etc.;
- (d) the position of all apparatus;
- (e) by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus; and
- (f) any intended maintenance regimes.
- (3) The undertaker must not commence any works to which sub-paragraph (1) applies until Cadent has given written approval of the plan so submitted.
- (4) Any approval of Cadent required under sub-paragraph (3)—
- (a) may be given subject to reasonable conditions for any purpose mentioned in sub-paragraphs (5) or (7); and,
- (b) must not be unreasonably withheld or delayed.
- (5) In relation to any work to which sub-paragraph (1) applies, Cadent may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its apparatus against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus.
- (6) Works to which this paragraph applies must only be executed in accordance with the plan, submitted under sub-paragraph (1) or as relevant sub-paragraph (5), as approved or as amended from time to time by agreement between the undertaker and Cadent and in accordance with such reasonable requirements as may be made in accordance with sub-paragraphs (5) or (7) by Cadent for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and Cadent will be entitled to watch and inspect the execution of those works.
- (7) Where Cadent requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to Cadent’s satisfaction prior to the commencement of any authorised works (or any relevant part thereof) for which protective works are required and the Cadent must give 56 days’ notice of such works from the date of submission of a plan pursuant to this paragraph (except in an emergency).
- (8) If Cadent in accordance with sub-paragraphs (5) or (7) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, sub-paragraphs (1) to (3) and (6) to (8) apply as if the removal of the apparatus had been required by the undertaker under paragraph 6(2) of this Part of this Schedule.
- (9) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of the authorised works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph will apply to and in respect of the new plan.
- (10) The undertaker will not be required to comply with sub-paragraph (1) where it needs to carry out emergency works as defined in the 1991 Act but in that case it must give to Cadent notice as soon as is reasonably practicable and a plan of those works and must—
- (a) comply with sub-paragraphs (5), (6) and (7) insofar as is reasonably practicable in the circumstances; and
- (b) comply with sub-paragraph (11) at all times.
- (11) At all times when carrying out any works authorised under the Order the undertaker must comply with the Cadent policies for safe working in proximity to gas apparatus “Specification for safe working in the vicinity of National Grid, High pressure Gas pipelines and associated installation requirements for third parties T/SP/SSW22” and HSE’s “HS(~G)47 Avoiding Danger from underground services”.
- (12) As soon as reasonably practicable after any ground subsidence event attributable to the authorised development the undertaker must implement an appropriate ground mitigation scheme save that Cadent retains the right to carry out any further necessary protective works for the safeguarding of its apparatus and can recover any such costs in line with paragraph 9 of this Part of this Schedule.
Expenses
9
- (1) Subject to the following provisions of this paragraph, the undertaker must pay to Cadent on demand all charges, costs and expenses reasonably anticipated or incurred by Cadent in, or in connection with, the inspection, removal, relaying or replacing, alteration or protection of any apparatus or the construction of any new or alternative apparatus which may be required in consequence of the execution of any authorised works as are referred to in this Part of this Schedule including without limitation—
- (a) any costs reasonably incurred by or compensation properly paid in connection with the acquisition of rights or the exercise of statutory powers for such apparatus including without limitation all costs incurred by Cadent as a consequence of Cadent—
- (i) using its own compulsory purchase powers to acquire any necessary rights under paragraph 6(3); or
- (ii) exercising any compulsory purchase powers in the Order transferred to or benefitting Cadent
- (b) in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus;
- (c) the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
- (d) the approval of plans;
- (e) the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works;
- (f) the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule.
- (2) There will be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule and which is not re-used as part of the alternative apparatus, that value being calculated after removal.
- (3) If in accordance with the provisions of this Part of this Schedule—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 47 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to Cadent by virtue of sub-paragraph (1) will be reduced by the amount of that excess save where it is not possible in the circumstances to obtain the existing type of apparatus at the same capacity and dimensions or place at the existing depth in which case full costs will be borne by the undertaker.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus will not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
- (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole will be treated as if it also had been agreed or had been so determined.
- (5) An amount which apart from this sub-paragraph would be payable to Cadent in respect of works by virtue of sub-paragraph (1) will, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on Cadent any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
Indemnity
10
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works authorised by this Part of this Schedule or in consequence of the construction, use, maintenance or failure of any of the authorised works by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by him) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised works) or property of Cadent, or there is any interruption in any service provided, or in the supply of any goods, by Cadent, or Cadent becomes liable to pay any amount to any third party, the undertaker will—
- (a) bear and pay on demand the cost reasonably incurred by Cadent in making good such damage or restoring the supply; and
- (b) indemnify Cadent for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from Cadent, by reason or in consequence of any such damage or interruption or Cadent becoming liable to any third party as aforesaid other than arising from any default of Cadent.
- (2) The fact that any act or thing may have been done by Cadent on behalf of the undertaker or in accordance with a plan approved by Cadent or in accordance with any requirement of Cadent or under its supervision will not (unless sub-paragraph (3) applies), excuse the undertaker from liability under the provisions of sub-paragraph (1) unless Cadent fails to carry out and execute the works properly with due care and attention and in a skilful and workmanlike manner or in a manner that does not accord with the approved plan.
- (3) Nothing in sub-paragraph (1) imposes any liability on the undertaker in respect of—
- (a) any damage or interruption to the extent that it is attributable to the neglect or default of Cadent, its officers, servants, contractors or agents; and
- (b) any authorised works and/or any other works authorised by this Part of this Schedule carried out by Cadent as an assignee, transferee or lessee of the undertaker with the benefit of the Order pursuant to section 156 (benefit of order granting development consent ) of the 2008 Act subject to the proviso that once such works become apparatus (“new apparatus”), any authorised works yet to be executed and not falling within this paragraph (b) will be subject to the full terms of this Part of this Schedule including this paragraph 10.
- (4) Cadent must give the undertaker reasonable notice of any such third-party claim or demand and no settlement or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and considering their representations.
Enactments and agreements
11
Save to the extent provided for to the contrary elsewhere in this Part of this Schedule or by agreement in writing between Cadent and the undertaker, nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between Cadent and the undertaker in respect of any apparatus laid or erected in land belonging to Cadent on the date on which this Order is made.
Co-operation
12
- (1) Where in consequence of the proposed construction of any of the authorised works, the undertaker or Cadent requires the removal of apparatus under paragraph 6(2) of this part of this Schedule Cadent makes requirements for the protection or alteration of apparatus under paragraph 8 of this Part of this Schedule, the undertaker must use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of Cadent’s undertaking and Cadent must use its best endeavours to co-operate with the undertaker for that purpose.
- (2) Whenever Cadent’s consent, agreement or approval is required in relation to plans, documents or other information submitted by the undertaker or the taking of action by the undertaker, it must not be unreasonably withheld or delayed.
Access
13
If in consequence of the agreement reached in accordance with paragraph 5(1) of this Part of this Schedule or the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable Cadent to maintain or use the apparatus no less effectively than was possible before such obstruction.
Arbitration
14
Any difference or dispute arising between the undertaker and Cadent under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and Cadent, be determined by arbitration in accordance with article 47 (arbitration).
Notices
15
The plan and scheme submitted to the undertaker by Cadent pursuant to paragraph 8(1) of this Part of this Schedule must be sent to Cadent Gas Limited Plant Protection at plantprotection@cadentgas.com or such other address as the undertaker may from time to time appoint instead for that purpose and notify to the undertaker.
PART 9 — FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
1
The provisions of this Part of this Schedule have effect unless otherwise agreed in writing between the undertaker and the operator.
2
In this Part of this Schedule—
- “the 2003 Act” means the Communications Act 2003[^f00090];
- “electronic communications apparatus” has the same meaning as in the electronic communications code[^f00091];
- “the electronic communications code” has the same meaning as in section 106(1)[^f00092] (application of the electronic communications code) of the 2003 Act;
- “electronic communications code network” means— so much of an electronic communications network or infrastructure system provided by an electronic communications code operator as is not excluded from the application of the electronic communications code by a direction under section 106 of the 2003 Act; and an electronic communications network which the undertaker is providing or proposing to provide;
- “electronic communications code operator” means a person in whose case the electronic communications code is applied by a direction under section 106 of the 2003 Act;
- “infrastructure system” has the same meaning as in the electronic communications code and references to providing an infrastructure system are to be construed in accordance with paragraph 7(2) of that code; and
- “operator” means the operator of an electronic communications code network.
3
The exercise of the powers conferred by article 32 (statutory undertakers and operators of the electronic communications code network) is subject to Part 10 of the electronic communications code.
4
- (1) Subject to sub-paragraphs (2) to (4), if as the result of the authorised development or its construction, or of any subsidence resulting from any of those works—
- (a) any damage is caused to any electronic communications apparatus belonging to an operator (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works), or other property of an operator; or
- (b) there is any interruption in the supply of the service provided by an operator,
the undertaker must bear and pay the cost reasonably incurred by the operator in making good such damage or restoring the supply and make reasonable compensation to that operator for any other expenses, loss, damages, penalty or costs incurred by it, by reason, or in consequence of, any such damage or interruption.
- (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of an operator, its officers, servants, contractors or agents.
- (3) The operator must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise of the claim or demand is to be made without the consent of the undertaker who, if withholding such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
- (4) Any difference arising between the undertaker and the operator under this Part of this Schedule must be referred to and settled by arbitration under article 47 (arbitration).
- (5) This Part of this Schedule does not apply to—
- (a) any apparatus in respect of which the relations between the undertaker and an operator are regulated by the provisions of Part 3 of the 1991 Act; or
- (b) any damages, or any interruptions, caused by electro-magnetic interference arising from the construction or use of the authorised development.
- (6) Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and an operator in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
PART 10 — FOR THE PROTECTION OF WATER AND SEWERAGE UNDERTAKERS
1
The provisions of this Part of this Schedule have effect unless otherwise agreed in writing between the undertaker and the utility undertaker concerned.
2
In this Part of this Schedule—
- “alternative apparatus” means any temporary or permanent alternative apparatus adequate to enable the utility undertaker in question to fulfil its statutory functions in a manner no less efficient than previously;
- “apparatus” means— in the case of a water undertaker, mains, pipes or other apparatus belonging to or maintained by that undertaker for the purposes of water supply; and in the case of a sewerage undertaker— any drain or works vested in that undertaker under the Water Industry Act 1991[^f00093]; and any sewer which is so vested or is the subject of a notice of intention to adopt given under section 102(4)[^f00094] (adoption of sewers and disposal works) of that Act or an agreement to adopt made under section 104[^f00095] (agreements to adopt sewer, drain or sewage disposal works, at future date) of that Act, and includes a sludge main, disposal main (within the meaning of section 219 (general interpretation) of that Act) or sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part of any such sewer, drain or works, and includes any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus;
- “functions” includes powers and duties;
- “in”, in a context referring to apparatus or alternative apparatus in land, includes a reference to apparatus or alternative apparatus under, over or upon land;
- “plan” includes all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the works to be executed;
- “utility undertaker” means— a water undertaker within the meaning of the Water Industry Act 1991; and a sewerage undertaker within the meaning of Part 1 of the Water Industry Act 1991, for the area of the authorised development, and in relation to any apparatus, means the undertaker to whom it belongs or by whom it is maintained.
On street apparatus
3
This Part of this Schedule does not apply to apparatus in respect of which the relations between the undertaker and the utility undertaker are regulated by the provisions of Part 3 of the 1991 Act.
Apparatus in stopped up streets
4
- (1) Where any street is stopped up under article 10 (permanent stopping up of streets), any utility undertaker whose apparatus is in the street has the same powers and rights in respect of that apparatus as it enjoyed immediately before the stopping up and the undertaker must grant to the utility undertaker legal easements reasonably satisfactory to the utility undertaker in respect of such apparatus and access to it, but nothing in this paragraph affects any right of the undertaker or of the utility undertaker to require the removal of that apparatus under paragraph 6 of this Part of this Schedule or the power of the undertaker to carry out works under paragraph 8 of this Part of this Schedule.
- (2) Regardless of the temporary stopping up or diversion of any street under the powers conferred by article 11 (temporary stopping up of streets), a utility undertaker is at liberty at all times to take all necessary access across any such stopped up street and to execute and do all such works and things in, upon or under any such street as may be reasonably necessary or desirable to enable it to maintain any apparatus which at the time of the stopping up or diversion was in that street.
Acquisition of land
5
Regardless of any provision in this Order or anything shown on the land plans, the undertaker must not acquire any apparatus otherwise than by agreement.
Removal of apparatus
6
- (1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed or requires that the utility undertaker’s apparatus is relocated or diverted, that apparatus must not be removed, diverted or otherwise altered under this Part of this Schedule, and/or any right of a utility undertaker to maintain apparatus in that land must not be extinguished, or made incapable of being exercised unless—
- (a) it is in the reasonable opinion of the undertaker necessary for the purpose of carrying out the authorised development;
- (b) any alternative, diverted or relocated apparatus required by the utility undertaker (acting reasonably) has been constructed and is in operation to the reasonable satisfaction of the utility undertaker in question in accordance with sub-paragraphs (2) to (6);
- (c) any rights required by the utility undertaker (acting reasonably) including to install, access, retain, replace, divert, relocate and maintain any apparatus or alternative apparatus have been granted to the reasonable satisfaction of the utility undertaker; and
- (d) any of the apparatus or alternative apparatus referred to in paragraph (b) or rights required and referred to in paragraph (c) do not in the reasonable opinion of the utility undertaker cause a material increase in the time, resources of and costs to the utility undertaker in using, operating or maintaining its apparatus unless agreed otherwise by the utility undertaker.
- (2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, the undertaker requires the removal, diversion or alteration of any apparatus placed in that land, the undertaker must give to the utility undertaker in question 28 days’ written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order an undertaker reasonably needs to remove any apparatus) the undertaker must, subject to sub-paragraph (3), afford to the utility undertaker the necessary facilities and rights for the construction of alternative apparatus in other land of the undertaker and subsequently for the maintenance of that apparatus, and the utility undertaker may elect to leave in situ any apparatus that the undertaker requires to be removed provided that it permits the undertaker to remove the apparatus and at its own cost in place of the utility undertaker.
- (3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed the utility undertaker must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible use its best endeavours to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.
- (4) Any alternative apparatus to be constructed in land of the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between the utility undertaker in question and the undertaker or in default of agreement settled by arbitration in accordance with article 47 (arbitration).
- (5) The utility undertaker in question must, after the alternative apparatus to be provided or constructed has been agreed or settled by arbitration in accordance with article 47, and after the grant to the utility undertaker of any such facilities and rights as are referred to in sub-paragraphs (2) or (3), and in accordance with a timetable to be agreed with the undertaker (both parties acting reasonably) such timetable to have due and proper regard to the utility undertaker’s statutory obligations with regard to its apparatus and undertaking including its obligation to maintain the supply of clean water at all times, proceed without unnecessary delay to construct and bring into operation the alternative apparatus and, subject to the provisions of sub-paragraph (2) of this paragraph, subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
- (6) Regardless of anything in sub-paragraph (5), if the undertaker gives notice in writing to the utility undertaker in question that the undertaker desires itself to execute any work, or part of any work in connection with the construction or removal of apparatus in any land of the undertaker, that work, instead of being executed by the utility undertaker, must be executed by the undertaker without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of the utility undertaker.
- (7) Nothing in sub-paragraph (6) authorises the undertaker to execute the placing, installation, bedding, packing, removal, connection of disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is lain in a trench) within 300 millimetres of apparatus which is not being removed, diverted or altered without the consent of the utility undertaker (such consent not to be unreasonably withheld or delayed).
Facilities and rights for alternative apparatus
7
- (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to a utility undertaker facilities and rights for the construction and maintenance in land of the undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities and rights are to be granted upon such terms and conditions as may be agreed between the undertaker and the utility undertaker in question or in default of agreement settled by arbitration in accordance with article 47 (arbitration).
- (2) If the facilities and rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are in the opinion of the arbitrator less favourable on the whole to the utility undertaker in question than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the arbitrator must make such provision for the payment of compensation by the undertaker to that utility undertaker as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
Retained apparatus
8
- (1) Not less than 28 days before starting the execution of any works in, on or under any land purchased, held, appropriated or used under this Order that are near to, or will or may affect, any apparatus the removal, diversion or alteration of which has not been required by the undertaker under paragraph 6(2) of this Part of this Schedule, the undertaker must submit to the utility undertaker in question for approval (such approval not to be unreasonably withheld or delayed and in any event within 17 working days) a plan, section and description of the works to be executed including (where appropriate) the proposed details of and location of alternative apparatus.
- (2) Those works must be executed only in accordance with the plan approved under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by the utility undertaker for the alteration or otherwise of the works necessary for the protection of apparatus, or for securing access to it, and the utility undertaker is entitled to watch and inspect the execution of those works.
- (3) Any requirements made by a utility undertaker under sub-paragraph (2) must be made within a period of 17 working days beginning with the date on which a plan, section and/or description of the works under sub-paragraph (1) is submitted to it.
- (4) If a utility undertaker in accordance with sub-paragraph (3) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 1 to 3 and 6 to 8 of this Part of this Schedule apply as if the removal of the apparatus had been required by the undertaker under paragraph 6(2).
- (5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan section and description for approval of the utility undertaker (such approval not to be unreasonably withheld or delayed and in any event within 17 working days) instead of the plan, section or description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section and description.
- (6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case must give to the utility undertaker in question notice as soon as is reasonably practicable and a plan of those works as soon as reasonably practicable subsequently and it must comply with sub-paragraph (3) in so far as is reasonably practicable in the circumstances and it must not under any circumstances interfere with the apparatus of the utility undertaker or do anything that would interfere with or prevent the use of that apparatus without the express permission of the utility undertaker.
- (7) The utility undertaker must acknowledge any notice received from the undertaker pursuant to sub-paragraph (6) without delay and within not more than 24 hours of receipt of such notice and it must agree with the undertaker as soon as reasonably possible exercising all reasonable endeavours a scheme of works necessary to address the emergency and which works may at the utility undertaker’s absolute discretion be carried out by the undertaker, and the utility undertaker must without delay co-operate with the undertaker to address the emergency in so far as it may interfere with the apparatus of the utility undertaker or do anything that would interfere with or prevent the use of that apparatus.
Expenses and costs
9
- (1) Subject to the sub-paragraph (2), the undertaker must repay to a utility undertaker all expenses reasonably incurred by that utility undertaker in, or in connection with, the approval of plans, specification, descriptions, inspection, installation, removal, diversion, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to in paragraph 8(2) of this Part of this Schedule and the reasonable costs of securing any rights which the utility undertaker requires (acting reasonably).
- (2) There must be deducted from any sum payable under sub-paragraph (1) a sum, equivalent to 7.5% of the costs of any of those matters referred to in sub-paragraph (1) occasioned by the creation of new traffic islands at—
- (a) the A5 between Gailey Bridge (on the Staffordshire and Worcestershire Canal) and Calf Heath Reservoir; and
- (b) Junction of the A449 Stafford Road with Crateford Lane and Gravelly Lane.
10
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the exercise of any rights or powers under this Order, or construction of any such works referred to in paragraphs 6 or 8(2) of this Part of this Schedule, or by reason of any subsidence resulting from such development or works, any damage is caused to any apparatus (whether unaltered, diverted or relocated) or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of a utility undertaker, or there is any interruption in any service provided, or in the supply of any goods, by any utility undertaker, or there is an increase in the cost to the utility undertaker of carrying out its statutory obligations or providing services or goods or operating or maintaining its apparatus or any omission by the undertaker or its agents causes any such matter the undertaker must—
- (a) bear and pay the cost reasonably incurred by that utility undertaker in making good such damage or restoring the supply; and
- (b) indemnify that utility undertaker for any other expenses, loss, proceedings, damages, claims, penalty or costs incurred by the utility undertaker, by reason or in consequence of any such damage or interruption or increase in costs or the utility undertaker becoming liable to any third party as aforesaid other than arising from any default of the utility undertaker.
- (2) The fact that any act or thing may have been done by a utility undertaker on behalf of the undertaker or in accordance with a plan, specification or description approved by a utility undertaker or in accordance with any requirement of a utility undertaker or under its supervision does not, subject to sub-paragraph (3), excuse the undertaker from liability under the provisions of sub-paragraph (1).
- (3) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of a utility undertaker, its officers, servants, contractors or agents.
- (4) A utility undertaker must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made without the consent of the undertaker who, if withholding such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
Cooperation
11
Where in consequence of the proposed construction of any of the authorised development, the undertaker or a utility undertaker requires the removal, diversion or alteration of apparatus under paragraph 6(2) of this Part of this Schedule or a utility undertaker makes requirements for the protection or alteration of apparatus under paragraph 8 of this Part of this Schedule, the undertaker must use best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of the utility undertaker’s undertaking and each utility undertaker must use its best endeavours to co-operate with the undertaker for that purpose.
12
Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and a utility undertaker in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
SCHEDULE 14 — MISCELLANEOUS CONTROLS
Public general legislation
Introduction
1
This Schedule applies, modifies and excludes statutory provisions which relate to matters for which provision may be made in this Order.
Highways Act 1980
2
- (1) Section 141 (restriction on planting trees etc. in or near carriageway) of the 1980 Act does not apply to any tree or shrub planted in the course of the authorised development before completion of construction.
- (2) Section 167 (powers relating to retaining walls near streets) of the 1980 Act does not apply in relation to—
- (a) the erection of a wall in the course of the authorised development before completion of construction; or
- (b) a wall on land on which works are being carried out, or are to be carried out, in pursuance of the authorised development before completion of construction.
New Roads and Street Works Act 1991
3
- (1) The powers conferred by section 56(1) and (1A) (powers to give directions as to the timing of proposed and subsisting street works) of the 1991 Act do not apply in relation to the authorised development.
- (2) Section 56A (power to give directions as to placing of apparatus) of the 1991 Act does not apply in relation to the placing of apparatus in the course of the authorised development.
- (3) No restriction under section 58(1) (power to impose restriction on execution of street works in the twelve months following completion of substantial road works) of the 1991 Act has effect in relation to the authorised development.
- (4) Section 61(1) (under which the consent of the street authority is required for the placing of apparatus in a protected street) of the 1991 Act does not apply to the placing of apparatus in the course of the authorised development.
- (5) Section 62(2) (power following designation of a protected street to require removal or repositioning of apparatus already placed in the street) of the 1991 Act does not apply in relation to apparatus placed in the course of the authorised development.
- (6) Section 62(4) (power when designation as a protected street commences or ceases to give directions with respect to works in progress) of the 1991 Act does not apply in relation to the authorised development.
- (7) Section 63(1) (under which Schedule 4 to that Act has effect for requiring the settlement of a plan and section of street works to be executed in a street designated by the street authority as having special engineering difficulties) of the 1991 Act does not apply in relation to the authorised development.
- (8) The powers conferred by section 73A(1) and 78A(1) (requirements for undertaker to re-surface street) of the 1991 Act are not be exercised in relation to the authorised development.
- (9) Sections 74 and 74A (charge for occupation of the highway and charge determined by reference to duration of works) of the 1991 Act do not apply in relation to the authorised development.
- (10) Schedule 3A (restriction on works following substantial street works) to the 1991 Act does not apply where a notice under section 54 (advance notice of certain works) or 55 (notice of starting date of works) of that Act is given in respect of the authorised development.
- (11) No notice under paragraph 2(1)(d) of Schedule 3A to the 1991 Act has effect to require the notification of works proposed to be carried out in the course of the authorised development.
- (12) No directions under paragraph 3 of Schedule 3A to the 1991 Act are to be issued to the undertaker.
- (13) Paragraph 3(4) of Schedule 3A to the 1991 Act does not apply in relation to the execution of works in the course of the authorised development.
- (14) Paragraph 5(1) of Schedule 3A to the 1991 Act does not apply in relation to the execution of works in the course of the authorised development.
Local Government (Miscellaneous Provisions) Act 1976
4
Section 42 (certain future local Acts, etc., to be subject to the planning enactments, etc., except as otherwise provided) of the Local Government (Miscellaneous Provisions) Act 1976 does not apply to the extent that it would make provisions of this Order authorising the authorised development subject to other provisions.
Town and Country Planning Act 1990
5
No order, notice or regulation under the 1990 Act in relation to the preservation of trees, has effect in relation to the authorised development.
Environment Act 1995
6
No order, notice or regulation under the Environment Act 1995 in relation to the preservation of hedgerows, has effect in relation to the authorised development.
SCHEDULE 15 — CERTIFICATION DOCUMENTS
1
Documents for certification that they are true copies of the documents referred to in this Order
Signed
Signed by authority of the Secretary of State
Susan Anderson — Head of the Transport and Works Act Unit — 2020-05-04
Explanatory note
(This note is not part of the Order)
Footnotes
[^f00001]: 2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20).
[^f00002]: S.I. 2009/2264, amended by S.I. 2010/439, S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/755, S.I. 2014/469, S.I. 2014/2381, S.I. 2015/377, S.I. 2015/1682, S.I. 2017/524, S.I. 2017/572, S.I. 2018/378 and S.I. 2019/734.
[^f00003]: S.I. 2010/103, amended by S.I. 2012/635.
[^f00004]: 1961 c. 33.
[^f00005]: 1965 c. 56.
[^f00006]: 1973 c. 26.
[^f00007]: 1980 c. 66.
[^f00008]: 1981 c. 66.
[^f00009]: 1984 c. 27.
[^f00010]: 1990 c. 8.
[^f00011]: 1991 c. 22.
[^f00012]: S.I. 2007/783, amended by S.I. 2011/2057, S.I. 2011/3058, S.I. 2012/2372, S.I. 2013/2114, S.I. 2015/377, S.I. 2017/1011 and S.I. 2019/907.
[^f00013]: 2008 c. 29.
[^f00014]: S.I. 2010/948, amended by S.I. 2011/987, S.I. 2012/635, S.I. 2012/666, S.I. 2012/702, S.I. 2012/2975, S.I. 2013/982, S.I. 2014/385, S.I. 2015/377, S.I. 2015/644, S.I. 2015/836, S.I. 2018/172, S.I. 2019/966 and S.I. 2019/1103.
[^f00015]: S.I. 2017/572, amended by S.I. 2017/1012, S.I. 2018/695, S.I. 2018/834 and S.I. 2018/1232.
[^f00016]: S.I. 2016/362. There are amendments to the Regulations which are not relevant to this Order.
[^f00017]: The definition of “cycle track” was amended by section 1 of the Cycle Tracks Act 1984 (c. 38) and paragraph 21(2) of Schedule 3 to the Road Traffic (Consequential Provisions) Act 1988 (c. 54).
[^f00018]: 2003 c. 21. Section 106 was amended by section 4 of the Digital Economy Act 2017 (c. 30).
[^f00019]: S.I. 1997/1160. There are amendments to the Regulations which are not relevant to this Order.
[^f00020]: S.I. 2015/376.
[^f00021]: 1981 c. 67. Section 7 was amended by section 70 of, and paragraph 9 of Schedule 15 to, the Planning and Compensation Act 1991 (c. 34). There are other amendments to the 1981 Act which are not relevant to this Order.
[^f00022]: 2006 c. 46.
[^f00023]: There are amendments to section 127 which are not relevant to this Order.
[^f00024]: There are amendments to section 151 which are not relevant to this Order.
[^f00025]: Section 48(3A) was inserted by section 124 of the Local Transport Act 2008 (c. 26).
[^f00026]: Section 121A was inserted by section 168(1) of, and paragraph 70 of Part 2 of Schedule 8 to, the New Roads and Street Works Act 1991 (c. 22), and subsequently amended by section 1(b) of, and paragraphs 70 and 95(1) and (3) of Part 2 of Schedule 1 to, the Infrastructure Act 2015 (c. 7) and S.I. 2001/1400. There are other amendments to section 121A which are not relevant to this Order.
[^f00027]: 2004 c. 18.
[^f00028]: Section 10 was amended by section 22(2)(a), (b) and (cc) of the New Roads and Street Works Act 1991 (c. 22), section 36 of, and paragraphs 21 and 22 of Schedule 2 to, the Planning Act 2008 (c. 29) and section 1(6) of, and paragraphs 1, 10(1) to (4) of Part 1 of Schedule 1 to, the Infrastructure Act 2015 (c. 7). Section 19(1) was amended by section 1(6) of, and paragraphs 1 and 15 of Part 1 of Schedule 1 to, the Infrastructure Act 2015 (c. 7).
[^f00029]: 1981 c. 69. Section 53 was amended by paragraph 1 of Part 1 of Schedule 5 to the Countryside and Rights of Way Act 2000 (c. 37), section 70(1) of the Natural Environment and Rural Communities Act 2006 (c. 16) and section 26(1) and (2) of, and paragraphs 1, 2, 9 and 10 of Schedule 7 to, the Deregulation Act 2015 (c. 20).
[^f00030]: S.I. 2011/935.
[^f00031]: Section 32 was amended by section 102 of, and Schedule 17 to, the Local Government Act 1985 (c. 51). There are other amendments to section 32 which are not relevant to this Order.
[^f00032]: Schedule 3A was inserted by section 4(2) of, and Schedule 1 to, the Digital Economy Act 2017 (c. 30).
[^f00033]: 1991 c. 56.
[^f00034]: 2000 c. 26.
[^f00035]: 1991 c. 56. Section 106 was amended by section 35(1) and (8) and section 43(2) of, and Schedule 2 to, the Competition and Service (Utilities) Act 1992 (c. 43), sections 36(2) and 99 of the Water Act 2003 (c. 37) (subject to the transitional provisions contained in article 6 of, and Schedule 3 to, S.I. 2004/641) and paragraph 16(1) of Schedule 3 to the Flood and Water Management Act 2010 (c. 29).
[^f00036]: S.I. 2016/1154, amended by S.I. 2017/1012, S.I. 2017/1075, S.I. 2018/110, S.I. 2018/428, S.I. 2018/575, S.I. 2018/721, S.I. 2018/1216 and S.I. 2018/1227.
[^f00037]: 1991 c. 57.
[^f00038]: Section 134 was amended by section 142(1) to (4) and section 237 of, and Part 21 of Schedule 25 to, the Localism Act 2011 (c. 20) and S.I. 2017/16.
[^f00039]: Section 8 was amended by paragraphs 1 and 2 of Part 1 of Schedule 17 to the Housing and Planning Act 2016 (c. 22) and S.I. 2009/1307.
[^f00040]: Schedule 2A was inserted by paragraphs 1 and 3 of Schedule 17 to the Housing and Planning Act 2016 (c. 22).
[^f00041]: Section 11(1) was amended by section 186(1) and (2), section 187(1) and (2) and section 188 of the Housing and Planning Act 2016 (c. 22) and section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (2006 No 1).
[^f00042]: Section 152 was amended by S.I. 2009/1307.
[^f00043]: Section 138 was amended by section 23(4) of the Growth and Industry Act 2013 (c. 27) and S.I. 2017/1285.
[^f00044]: Section 10 was amended by S.I. 2009/1307.
[^f00045]: 1981 c. 67.
[^f00046]: Section 4 was amended by sections 184, 185 and 199(2) of, and paragraphs 1 and 2 of Part 1 of Schedule 13 to, the Housing and Planning Act 2016 (c. 22).
[^f00047]: Section 4A(1) was inserted by section 202(1) of the Housing and Planning Act 2016 (c. 22).
[^f00048]: S.I. 2020/511.
[^f00049]: Section 5 was amended by section 183 of, and Schedule 15 to, the Housing and Planning Act 2016 (c. 22).
[^f00050]: Section 5A was inserted by section 182(2) of the Housing and Planning Act 2016 (c. 22).
[^f00051]: Section 5B(1) was inserted by section 202(2) of the Housing and Planning Act 2016 (c. 22).
[^f00052]: Section 6 was amended by section 183 of, and paragraphs 4 and 7 of Schedule 15 to, the Housing and Planning Act 2016 (c. 22) and section 4 of, and paragraph 52(2) of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11).
[^f00053]: Section 7 was amended by section 199(2) of, and paragraphs 1 and 3 of Part 1 of Schedule 18 to, the Housing and Planning Act 2016 (c. 22).
[^f00054]: Schedule A1 was inserted by paragraph 6 of Part 1 of Schedule 18 to the Housing and Planning Act 2016 (c. 22).
[^f00055]: Section 11 was amended by section 186(1) and (2), section 187(1) and (2) and section 188 of, and paragraphs 1 and 2 of Schedule 16 to, and paragraph 6 of Schedule 14 to, the Housing and Planning Act 2016 (c. 22), section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous provisions) Measure 2006 (2006 No 1) and S.I. 2009/1307.
[^f00056]: Section 125 was amended by paragraph 17 of Schedule 16 to the Housing and Planning Act 2016 (c. 22).
[^f00057]: 1965 c. 56. Section 13 was amended by section 139(4) to (9) and section 62(3) of, paragraphs 27 and 28(1) to (3) of Schedule 13 to, and Part 13 of Schedule 23 to, the Tribunal, Courts and Enforcement Act 2007 (c. 15).
[^f00058]: 1991 c. 57. Paragraph 5 was amended by section 106 of the Natural Environmental and Rural Communities Act 2006, section 31 of, and paragraphs 40 and 49 of Schedule 2 to the Flood and Water Management Act 2010 (c. 29), and sections 84 and 146(1) of, and paragraph 3 of Schedule 11 to, the Marine and Coastal Access Act 2009 (c. 23). Paragraph 6 was amended by section 105 of, and paragraph 6 of Schedule 15 to, the Environment Act 1995 (c. 25), sections 233(1), 224 and 321 of, and paragraphs 20 and 24 of Schedule 16 and Part 5(b) of Schedule 22 to, the Marine and Coastal Access Act 2009 (c. 23). Paragraph 6A was inserted by section 103(3) of the Environment Act 1995 (c. 25).
[^f00059]: 1991 c. 59. Section 23 was amended by section 31 of, and paragraphs 25 and 32 of Schedule 2 to, the Flood and Water Management Act 2010 (c. 29).
[^f00060]: Section 32 was amended by S.I. 2013/755.
[^f00061]: Section 66 was amended by section 31 of, and paragraphs 25 and 38 of Schedule 2 to, the Flood and Water Management Act 2010 (c. 29) and section 86(1) and (3) of the Water Act 2014 (c. 21).
[^f00062]: 1981 c. 69. Section 28E was amended by section 105(1) of, and paragraphs 79 and 80 of Part 1 of Schedule 11 to, the Natural Environment and Rural Communities Act 2006 (c. 16).
[^f00063]: 2017 c. 20.
[^f00064]: Sections 160 and 161 were amended by S.I. 2015/664. Section 161 was also amended by section 112(2) of, and paragraph 4 of Part 1 of Schedule 8 to, the Marine and Coastal Access Act 2009 (c. 23).
[^f00065]: 1978 c. 30.
[^f00066]: Section 115(2) was amended by section 160(1) and (3) of the Housing and Planning Act 2016 (s. 22) and section 43(1) and (2) of the Wales Act 2017 (c. 4).
[^f00067]: 1971 c. 80.
[^f00068]: 2010 c. 29.
[^f00069]: 1971 c. 80.
[^f00070]: The appointment is made at the discretion of the Secretary of State, and such appointment may be made by the Planning Inspectorate on behalf of the Secretary of State.
[^f00071]: The costs of the appointed person are calculated based on the applicable day rate for a Single Inspector as if he or she were appointed under s78/ s79 of the PA2008. See the National Infrastructure Planning website for more information: https://infrastructure.planninginspectorate.gov.uk/application-process/application-fees/
[^f00072]: S.I. 2012/2920, amended by S.I. 2013/2153, S.I. 2014/357, S.I. 2014/2026, S.I. 2015/643, S.I. 2017/1314 and S.I. 2019/1154.
[^f00073]: S.I. 2020/511.
[^f00074]: 1973 c. 26.
[^f00075]: Section 11 was amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67), sections 186(2), 187(2) and 188 of, and paragraph 6 of Schedule 14 and paragraph 3 of Schedule 16 to, the Housing and Planning Act 2016 (c. 22), section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (No. 1) and S.I. 2009/1307.
[^f00076]: Section 11A was inserted by section 186(3) of the Housing and Planning Act 2016 (c. 22).
[^f00077]: Section 11B was inserted by section 187(3) of the Housing and Planning Act 2016 (c.22).
[^f00078]: Section 12 was amended by section 56(2) of, and Part 1 of Schedule 9 to, the Courts Act 1971 (c. 23).
[^f00079]: Section 13 was amended by sections 62(3), 139(4) to (9) and 146 of, and paragraphs 27 and 28 of Schedule 13 and Part 3 of Schedule 23 to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).
[^f00080]: Section 20 was amended by paragraph 4 of Schedule 15 to the Planning and Compensation Act 1991 (c. 34) and S.I. 2009/1307.
[^f00081]: 1993 c. 43. Section 8 was amended by section 216 of, and paragraphs 1 and 4 of Schedule 17 and Part 4 of Schedule 31 to, the Transport Act 2000 (c. 38), paragraphs 1 and 5 of Schedule 2 to the Railways and Transport Safety Act 2003 (c. 20), paragraph 3 of Schedule 1, and Part 1 of Schedule 13, to the Railways Act 2005 (c. 14) and S.I. 2015/1682.
[^f00082]: 2006 c. 46.
[^f00083]: Section 272 was amended by paragraph 103(1) and (2) of Schedule 17 to the Communications Act 2003 (c. 21).
[^f00084]: S.I. 2016/362.
[^f00085]: S.I. 2015/51.
[^f00086]: Section 272 was amended by paragraph 103(1) and (2) of Schedule 17 to the Communications Act 2003 (c. 21).
[^f00087]: 1995 c. i.
[^f00088]: 1968 c. 73. Section 105 was amended by S.I. 2012/1659.
[^f00089]: 1986 c. 44.
[^f00090]: 2003 c. 21.
[^f00091]: See paragraph 5 of Schedule 3A (the electronic communications code) to the Communications Act 2003 (c. 21). Schedule 3A was inserted by Schedule 1 to the Digital Economy Act 2017 (c. 30).
[^f00092]: Section 106 was amended by section 4(3) to (9) of the Digital Economy Act 2017 (c. 30).
[^f00093]: 1991 c. 56.
[^f00094]: Section 102(4) was amended by sections 56 and 96(1)(c) to (e) of, and paragraphs 2 and 90 of Schedule 7 to, the Water Act 2014 (c. 21).
[^f00095]: Section 104 was amended by sections 96(4) and 101(2) of, and Part 3 of Schedule 9 to, the Water Act 2003 (c.37), section 42(3) of the Flood and Water Management Act 2010 (c. 29) and sections 11 and 56 of, and paragraphs 2 and 91 of Schedule 7 to, the Water Act 2014 (c. 21).
[^f00096]: 1980 c. 66. Section 141 was amended by sections 37 and 46 of the Criminal Justice Act 1982 (c. 48).
[^f00097]: 1980 c. 66. Section 167 was amended by sections 37, 38 and 46 of the Criminal Justice Act 1982 (c. 48).
[^f00098]: 1991 c. 22. Section 56(1) and (1A) were amended by section 43 of the Traffic Management Act 2004 (c. 18).
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.