The West Midlands Rail Freight Interchange Order 2020

Type Statutory-Instrument
Publication 2020-05-04
Last updated 2025-04-11
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • “programme of works” means a document setting out the sequence and timetabling of the phase of the trunk road works in question;
  • “Road Safety Audit” means an audit carried out in accordance with the Road Safety Audit Standard, and the approved audit team will include a member of Highways England West Midlands Asset Delivery Road Safety Team;
  • “Road Safety Audit Standard” means the Design Manual for Roads and Bridges Standard HD 19/15 or any successor document;
  • “trunk road works” means that part of Works Nos. 4 or 7 shown coloured green and blue on the future highway maintenance plans, the general arrangement of which is shown on the relevant highway general arrangement plans and any ancillary works thereto;
  • “utilities” means any pipes, wires, cables or equipment belonging to any person or body having power or consent to undertake street works under the 1991 Act; and
  • “winter maintenance” means maintenance of the road surface to deal with snow and ice.
3
  • (1) No work must commence on any phase of the trunk road works until the detailed design information and a programme of works in respect of that phase has been submitted to and approved by Highways England.
  • (2) Highways England must nominate a person who will be a single point of contact on behalf of Highways England for consideration of the detailed design information and who will co-ordinate the Highways England response to the details submitted.
  • (3) No works must commence on any phase of the trunk road works other than by a contractor employed by the undertaker for that phase but first approved by Highways England.
  • (4) No work must commence on any phase of the trunk road works until Highways England has agreed the bond sum for that phase and the undertaker has provided security for the carrying out of those works as provided for in paragraph 9 of this Part of this Schedule or some other form of security acceptable to Highways England.
  • (5) No work must commence on any phase of the trunk road works until Stage 1 and Stage 2 Road Safety Audits have been carried out in respect of that phase and all recommendations raised incorporated into an amended design approved by Highways England or secured by agreement with Highways England pursuant to article 20 (agreements with highway authorities) or any relevant exceptions approved by Highways England.
  • (6) No work must commence on any phase of the trunk road works until the undertaker demonstrates to the satisfaction of Highways England that the walking, cycling and horse riding assessment and review process for that phase has been adhered to in accordance with the Design Manual for Roads and Bridges Standard HD 42/17 or any successor document.
  • (7) No work must commence on any phase of the trunk road works until a scheme of traffic management has been submitted by the undertaker and approved by Highways England for that phase, such scheme to be capable of amendment by agreement between the undertaker and Highways England from time to time.
  • (8) No work must commence on any phase of the trunk road works until stakeholder liaison has taken place for that phase in accordance with a scheme for such liaison agreed between the undertaker and Highways England.
  • (9) No work must commence on any phase of the trunk road works until Highways England has approved the audit brief and CVs for all road safety audits and exceptions to items raised if appropriate for that phase in accordance with the Road Safety Audit Standard.
  • (10) No work must commence on any phase of the trunk road works until the undertaker has agreed the commuted sum for that phase with Highways England to be calculated in accordance with paragraph 10 of this Part of this Schedule.
  • (11) No work must commence on any phase of the trunk road works until a dilapidation survey for that phase has been carried out by the undertaker and has been submitted to and approved in writing by Highways England.
  • (12) No work must commence on any phase of the trunk road works until the scope of all routine maintenance to be carried out by the undertaker during the construction of the phase concerned has been agreed in writing by Highways England, such maintenance only to include winter maintenance of the phase concerned when—
  • (a) access to carry out such maintenance by Highways England is not available by virtue of the works being carried out at that phase; and
  • (b) any winter maintenance is needed immediately prior to the opening of any carriageway to traffic when that carriageway had been closed for the purposes of the carrying out of the phase concerned.
4
  • (1) The undertaker must prior to commencement of each phase of the trunk road works give Highways England 28 days' notice in writing of the date on which that phase will start unless otherwise agreed by Highways England.
  • (2) The undertaker must comply with Highways England's usual road space booking procedures prior to and during the carrying out of each phase of the trunk road works and no trunk road works for which a road space booking is required is to commence without a road space booking having first been secured such road space booking not to be unreasonably withheld or delayed.
  • (3) Each phase of the trunk road works must be carried out to the satisfaction of Highways England in accordance with—
  • (a) the relevant detailed design information and a programme of works approved pursuant to paragraph 3(1) of this Part of this Schedule or as subsequently varied by agreement between the undertaker and Highways England;
  • (b) the Design Manual for Roads and Bridges, the Specification for Highway Works (contained within the Manual of Contract Documents for Highways Works), all relevant interim advice notes, the Traffic Signs Manual and Traffic Signs Regulations and General Directions 2016 and any amendment to or replacement thereof for the time being in force save to the extent that they are inconsistent with the general arrangement of the trunk road works as shown on the highways general arrangement plans or a departure from such standards has been approved by Highways England;
  • (c) such approvals or requirements of Highways England that are required by the provisions of paragraph 3 of this Part of this Schedule to be in place prior to the relevant phase of the trunk road works being undertaken; and
  • (d) all aspects of the Construction (Design and Management) Regulations 2015 and in particular the undertaker, as client, must ensure that all client duties (as defined in those regulations) are undertaken to the satisfaction of Highways England.
  • (4) The undertaker must permit and require the contractor to permit at all reasonable times persons authorised by Highways England (whose identity must be previously notified to the undertaker by Highways England) to gain access to the trunk road works and county highway works for the purposes of inspection and supervision and the undertaker must provide to Highways England contact details of the nominated persons with whom Highways England should liaise during the carrying out of the trunk road works.
  • (5) At any time during the carrying out of the trunk road works the nominated persons must act upon any reasonable request made by Highways England in relation to the carrying out of the trunk road works as soon as practicable following such request being made to the nominated persons save to the extent that the contents of such request are inconsistent with or fall outside the contractor's obligations under its contract with the undertaker or the undertaker's obligations in this Order.
  • (6) If at any time the undertaker does not comply with any of the terms of this Part of this Schedule in respect of any phase of the trunk road works having been given notice of an alleged breach and an adequate opportunity to remedy it by Highways England then Highways England on giving the undertaker 14 days' notice in writing to that effect be entitled to—
  • (a) (carry out and complete that phase of the trunk road works and any maintenance works which the undertaker would have been responsible for on the undertaker's behalf; or
  • (b) carry out such necessary works of reinstatement of the highway and other land and premises of Highways England,

and in either case the undertaker must within 28 days of receipt of the itemised costs pay to Highways England the costs so incurred by Highways England.

  • (7) If at any time the undertaker in carrying out the authorised development causes any damage or disruption to the strategic road network not hereby authorised then Highways England is to give notice of such damage or disruption and allow the undertaker 14 days to remedy the problem. Should the undertaker fail to adequately remedy the problem to the satisfaction of Highways England. Highways England, on giving to the undertaker 7 days' notice in writing to that effect, is entitled to carry out such necessary works as Highways England acting reasonably deem appropriate to remedy the damage or disruption, and the undertaker must within 28 days of receipt of the itemised costs pay to Highways England the costs so incurred by Highways England.
  • (8) Nothing in this Part of this Schedule prevents Highways England from carrying out any work or taking such action as deemed appropriate, without prior notice to the undertaker, in the event of an emergency or danger to the public. The cost to Highways England of such work or action being chargeable to and recoverable from the undertaker if the need for such action arises from the carrying out of the authorised development. This provision applies to all areas of the authorised development including any area of traffic management deployed under the traffic management plan approved pursuant to paragraph 3(7) of this Part of this Schedule to facilitate delivery of the authorised development.
  • (9) The undertaker in carrying out each phase of the trunk road works must at its own expense divert or protect all utilities as may be necessary to enable the trunk road works to be properly carried out and all agreed alterations to existing services must be carried out to the reasonable satisfaction of Highways England.
  • (10) During the construction of each phase of the trunk road works the undertaker is responsible for all routine maintenance at its cost within that phase (including winter maintenance when required to be undertaken by the undertaker in accordance with paragraph 3(12) of this Part of this Schedule). All routine maintenance must be carried out in accordance with the scope of routine maintenance operations agreed by Highways England in accordance with paragraph 3(12).
5
  • (1) The undertaker must fund the whole of the cost of the trunk road works and all costs incidental to the trunk road works and must also pay to Highways England in respect of each phase of the trunk road works a sum equal to the whole of any costs and expenses which Highways England incur including costs and expenses for using external staff and resources as well as costs and expenses of using in-house staff and resources in relation to the trunk road works and arising out of them and their implementation, including—
  • (a) the checking and approval of all design work carried out by or on behalf of the undertaker for that phase;
  • (b) costs in relation to agreeing the programme of works for that phase;
  • (c) the carrying out of supervision of that phase; and
  • (d) all administrative costs in relation to paragraphs (a) and (b),

together comprising “the estimated costs”.

  • (2) The sums referred to in sub-paragraph (1) do not include any sums payable from the undertaker to the contractor but do include any value added tax which is payable by Highways England in respect of such costs and expenses and for which it cannot obtain reinstatement from HM Revenue and Customs.
  • (3) The undertaker must pay to Highways England upon demand and prior to such costs being incurred the total costs that Highways England believe will be properly and necessarily incurred by Highways England in undertaking any statutory procedure or preparing and bringing into force any traffic regulation order or orders necessary to carry out or for effectively implementing the trunk road works provided that this paragraph does not apply to the making of any orders which duplicate orders contained in this Order.
  • (4) The undertaker must make the payments of the estimated costs as follows—
  • (a) the undertaker must pay a sum equal to the anticipated cost of the tasks referred to in sub-paragraph (1)(a), (b) and (d) to Highways England prior to Highways England undertaking those tasks;
  • (b) the undertaker must pay a sum equal to the anticipated cost of the tasks referred to in sub-paragraph (1)(c) prior to commencing that phase;
  • (c) if at any time after the payment in respect of a phase referred to in sub-paragraph (4)(a) and (b) has become payable and Highways England reasonably estimates that the costs in respect of that phase referred to in sub-paragraph (1) will exceed the estimated costs for that phase it may give notice to the undertaker of the amount by which it then reasonably estimates those costs will exceed the estimated costs (“the excess”) and the undertaker must pay to Highways England within 28 days of the date of that notice a sum equal to the excess.
  • (5) Within 91 days of the issue of the handover certificate for each phase of the trunk road works in accordance with paragraph 7 of this Part of this Schedule, Highways England must give the undertaker a final account of the costs referred to in sub-paragraph (1) and within 28 days from the expiry of the 91-day period—
  • (a) if the account shows a further sum as due to Highways England the undertaker must pay to Highways England the sum shown due to it in that final account; and
  • (b) if the account shows that the payment or payments previously made have exceeded those costs Highways England must refund the difference to the undertaker.
  • (6) If any payment due under any of the provisions of this Part of this Schedule is not made on or before the date on which it falls due the party from whom it was due must at the same time as making the payment pay to the other party interest at 1% above the rate payable in respect of compensation under section 32 (rate of interest after entry on land) of the 1961 Act for the period starting on the date upon which the payment fell due and ending with the date of payment of the sum on which interest is payable together with that interest.
6
  • (1) As soon as—
  • (a) each phase of the trunk road works has been completed; and
  • (b) a Stage 3 Road Safety Audit for that phase has been carried out and any resulting recommendations complied with Highways England and any exceptions agreed,

Highways England must issue a provisional certificate of completion in respect of that phase, such certificate not to be unreasonably withheld or delayed.

7
  • (1) As soon as, in respect of a phase—
  • (a) the undertaker has carried out a dilapidation survey in accordance with paragraph 3(11) of this Part of this Schedule and completed any remedial works necessary to bring that area into as good a condition as when it was originally surveyed, such works to be first agreed with Highways England;
  • (b) the undertaker has provided a plan clearly identifying the extent of any land which is to become highway maintainable at public expense together with any ancillary equipment that will become the responsibility of Highways England; and
  • (c) the as built information has been provided to Highways England,

Highways England must forthwith issue a handover certificate in respect of that phase such certificate not to be unreasonably withheld or delayed.

  • (2) The undertaker must at its own expense remedy any defects in any phase of the trunk road works as are reasonably required to be remedied by Highways England during a period of 12 months from the date of the handover certificate in respect of that phase. All identified defects are to be remedied in accordance with the following timescales—
  • (a) in respect of matters of urgency, within 24 hours of receiving notification (urgency to be determined at the absolute discretion of Highways England);
  • (b) in respect of matters which Highways England consider to be serious defects or faults, within 14 days of receiving notification or, if a road space booking is required at the time when the road space is available, whichever is the later; and
  • (c) in respect of all other defects notified to the undertaker, within 4 weeks of receiving notification or, if a road space booking is required, at the time when the road space is available, whichever is the later.
  • (3) Following the issue of the handover certificate in respect of a phase, Highways England is to be responsible for the trunk road works within that phase which will thereafter be maintained by and at the expense of Highways England.
  • (4) The undertaker must submit Stage 4 Road Safety Audits for each phase as required by and in line with the timescales stipulated in the Road Safety Audit Standard. The undertaker must comply with the findings of the Stage 4 Road Safety Audits and be responsible for all costs of and incidental to such.
8

Highways England must issue the final certificate in respect of each phase at the expiration of the 12-month period in respect of that phase referred to in paragraph 7(2) of this Part of this Schedule or if later on the date on which any defects or damage arising from defects during that period have been made good to the reasonable satisfaction of Highways England such certificate not to be unreasonably withheld or delayed.

9
  • (1) Subject to paragraph 3(4) of this Part of this Schedule the undertaker must provide security for the carrying out of the trunk road works as follows—
  • (a) prior to the commencement of each phase, the trunk road works within that phase must be secured by a bond from a bondsman first approved by Highways England drafted substantially as detailed in Form 1 contained in paragraph 17 of this Part of this Schedule, or such other form that may be agreed between the undertaker and Highways England, to indemnify Highways England against all losses, damages, costs or expenses arising from any breach of any one or more of the obligations of the undertaker in respect of that phase under the provisions of this Part of this Schedule provided that the maximum liability of the bond does not exceed the bond sum relating to that phase; and
  • (b) prior to the commencement of the trunk road works the undertaker must provide the cash surety which may be utilised by Highways England in the event of the undertaker failing to meet its obligations to make payments under paragraph 5 of this Part of this Schedule or to carry out works the need for which arises from a breach of one or more of the obligations of the undertaker (which will be a single cash surety for the entirety of the trunk road works).
  • (2) Each bond sum and the cash surety (the latter in respect of the final phase only) must be progressively reduced as follows—
  • (a) on receipt of written confirmation (including receipt of receipted invoices evidencing payments made by the undertaker to the contractors) from the undertaker of the payments made from time to time to the contractor Highways England must in writing authorise the reduction of the bond sum by such proportion of the bond sum as amounts to 80% of those payments provided that an evaluation of the trunk road works completed and remaining has been carried out by the undertaker and audited and agreed by Highways England to ensure that the stage of completion of the works is relative to the payments made by the undertaker to the contractors. Highways England will only be required to provide the said authorisation if it is satisfied that the monies remaining secured by the bond sum will be sufficient to cover all remaining costs and liabilities anticipated to be incurred in completing the trunk road works plus an additional 20%;
  • (b) within 20 working days of completion of each phase of the trunk road works (as evidenced by the issuing of the provisional certificate in respect of that phase in accordance with paragraph 6(1) of this Part of this Schedule) Highways England must in writing release the bond provider from its obligations in respect of 80% of the bond sum relating to that phase (“the revised bond sum”) save insofar as any claim or claims have been made against the bond and/or liability on its part has arisen prior to that date in which case Highways England will retain a sufficient sum to meet all necessary costs; and
  • (c) within 20 working days of the issue of the final certificate for each phase of the trunk road works referred to in paragraph 8 of this part of this Schedule, Highways England must in writing release the bond provider from its obligations in respect of the revised bond sum relating to that phase and (in respect of the final phase) release the remainder of the cash surety to the undertaker save insofar as any claim or claims have been made against the bond or liability on its part has arisen prior to that date in which case Highways England will retain a sufficient sum to meet all necessary costs.
10

The undertaker must pay to Highways England the commuted sum for the relevant phase calculated in accordance with FS Guidance S278 Commuted Lump Sum Calculation dated 18th January 2010 within 28 days of the date of that phase of the trunk road works becomes maintainable by Highways England in accordance with paragraph 7(3) of this Part of this Schedule.

11

The undertaker must prior to commencement of the trunk road works effect public liability insurance with an insurer in the minimum sum of £10,000,000.00 (ten million pounds) against any legal liability for damage loss or injury to any property or any person as a direct result of the execution of the trunk road works or any part thereof by the undertaker.

12
  • (1) The undertaker must in relation to the carrying out of the trunk road works take such precautions for the protection of the public and private interest as would be incumbent upon it if it were the highway authority and must indemnify Highways England from and against all costs expenses damages losses and liabilities arising from or in connection with or ancillary to any claim demand action or proceedings resulting from the design and carrying out of the trunk road works provided that—
  • (a) the foregoing indemnity does not extend to any costs, expenses, liabilities and damages caused by or arising out of the neglect or default of Highways England or its officers, servants, agents or contractors or any person or body for whom it is responsible;
  • (b) Highways England must notify the undertaker immediately upon receipt of any claim; and
  • (c) Highways England must, following the acceptance of any claim, notify the quantum to the undertaker in writing and the undertaker must within 14 days of the receipt of such notification pay to Highways England the amount specified as the quantum of such claim.
  • (2) The undertaker must notify Highways England of the intended date of opening of each phase to public traffic not less than 14 days in advance of the intended date and the undertaker must notify Highways England of the actual date that each phase is open to public traffic on each occasion within 14 days of that occurrence.
13

The undertaker must procure warranties from the contractor and designer of each phase to the effect that all reasonable skill care and due diligence will be exercised in designing and constructing that phase including the selection of materials, goods, equipment and plant such warranties to be provided to Highways England before that phase commences.

14
  • (1) Following the issuing of the final certificates for all the trunk road works Highways England may serve notice on the undertaker that it wishes to take a freehold transfer of land within the then extent of highway land which is not in the ownership of Highways England but has been acquired by the undertaker for the purposes of carrying out the trunk road works.
  • (2) If the undertaker receives a notice under sub-paragraph (1), the undertaker must co-operate in a freehold transfer of the land which is the subject of the notice and complete such transfer as soon as reasonably practicable at no cost to Highways England which includes the undertaker being responsible for the reasonable legal costs incurred by Highways England in connection with such transfer.
15
  • (1) Any approvals, certificates, consents or agreements required of or sought from or with Highways England in accordance with the provisions of this Part of this Schedule must not be unreasonably withheld or delayed and must be given in writing.
  • (2) If Highways England fail to notify the undertaker of its decision in respect of any approval, consent or agreement in accordance with the provisions of this Part of this Schedule within 28 days of the specified day, the undertaker may serve upon Highways England written notice requiring Highways England to give their decision within a further 28 days beginning on the date upon which Highways England received written notice from the undertaker. Subject to sub-paragraph (3), if by the expiry of the further 28 days Highways England has failed to notify the undertaker of its decision, Highways England is deemed to have given the relevant approval, consent or agreement.
  • (3) Any further notice given by the undertaker to Highways England under sub-paragraph (2) must include a written statement that the provisions of sub-paragraph (2) apply to the relevant approval, consent or agreement.
  • (4) In this paragraph “specified day” means—
  • (a) the day on which particulars of the matter are submitted to Highways England under the provisions of this Part of this Schedule; or
  • (b) the day on which the undertaker provides Highways England with any further particulars of the matter that have been reasonably requested by Highways England within 14 days of the date in sub-paragraph (2)(a),

whichever is the later.

16
  • (1) Article 47 (arbitration) does not apply to this Part of this Schedule except in respect of sub-paragraph (5).
  • (2) Any difference under this Part of this Schedule may be referred to and settled by a single independent and suitable person who holds appropriate professional qualifications and is a member of a professional body relevant to the matter in dispute acting as an expert, such person to be agreed by the differing parties or, in the absence of agreement, identified by the President of the Institution of Civil Engineers.
  • (3) All parties involved in settling any difference must use best endeavours to do so within 21 days from the date of a dispute first being notified in writing by one party to the other and in the absence of the difference being settled within that period the expert must be appointed within 21 days of the notification of the dispute.
  • (4) The expert must—
  • (a) invite the parties to make submissions to the expert in writing and copied to the other party to be received by the expert within 21 days of the expert's appointment;
  • (b) permit a party to comment on the submissions made by the other party within 21 days of receipt of the submission;
  • (c) issue a decision within 42 days of receipt of the submissions under paragraph (b); and
  • (d) give reasons for the decision.
  • (5) Any determination by the expert is final and binding, except in the case of manifest error in which case the difference that has been subject to expert determination may be referred to and settled by arbitration under article 47.
  • (6) The fees of the expert are payable by the parties in such proportions as the expert may determine or, in the absence of such determination, equally.
17

Form 1 as referred to in paragraph 9—

1

The provisions of this Part of this Schedule have effect, and apply to the county highway works, unless otherwise agreed in writing between the undertaker and the local highway authority.

2
  • (1) The terms used in this Schedule are as defined in article 2 (interpretation) of this Order save where inconsistent with sub-paragraph (2) which will prevail.
  • (2) In this Schedule—
  • “approval in principle” means the document, which records the agreed basis and criteria for the detailed design or assessment of a highway structure.
  • “as built information” means one electronic copy of the following information where applicable to the phase in question—as constructed drawings in both PDF AutoCAD DWG, MX and GIS formats for anything designed by the undertaker;list of suppliers and materials, test results and CCTV surveys;product data sheets, technical specifications for all materials used;as constructed information for any utilities discovered or moved during the worksmethod statements for works carried out;in relation to road lighting, signs and traffic signals any information required by Series 1400 of the Specification for Highway Works;organisation and methods manuals for all products used;as constructed programme;health and safety file under the Construction (Design and Management) Regulations 2015;test results and records; andother such information as is readily available to the undertaker and may be reasonably required by the local highway authority to be used to update any relevant databases;
  • “bond” means a bond from a surety approved by the local highway authority for the bond sum drafted substantially as detailed in Form 2 contained in paragraph 15 of this Part of this Schedule;
  • “the bond sum” means the sum equal to 120% of the estimated costs of the carrying out of the phase of the county highway works concerned or such other sum agreed between the undertaker and the local highway authority;
  • “commuted sum” means such sum as calculated by the local highway authority in accordance with paragraph 7(2)(c) of this Part of this Schedule for any structure within each phase to be used to fund the future cost of maintaining such structures;
  • “contractor” means any contractor or sub-contractor appointed by the undertaker to carry out the county highway works or any phase of the county highway works and approved by the local highway authority in accordance with paragraph 3(2) of this Part of this Schedule;
  • “county highway works” means those parts of Works Nos. 4 and 7 coloured pink and yellow on the future highway maintenance plans the general arrangement of which is shown on the highway general arrangement plans and any ancillary works;
  • “defects period” means a period of twelve months from the date of the provisional certificate or longer period if agreed between the undertaker and the local highway authority in which all defects arising from the county highway works must be rectified by the undertaker;
  • “detailed design information” means the following drawings, specifications and other information which must be in accordance with the general arrangements shown on the highway general arrangements plans unless otherwise agreed between the local highway authority and the undertaker—site clearance details;boundary environmental and mitigation fencing;road restraint systems (vehicle and pedestrian) and supporting Road Restraint Risk Assessment Process assessment (RRRAP);drainage and ducting;earthworks including supporting geotechnical assessments required by HD22/08 and any required Strengthened Earthworks Appraisal Form certification;kerbs, footways and paved areas;traffic signs, signals and road markings;road lighting (including columns, brackets and bat hop-overs);electrical work for road lighting and traffic signs;highway structures and any required certification in accordance with BD2/12;agreed departures from Standard;landscaping;utilities diversions; andwildlife crossings,where relevant to the phase concerned;
  • “estimated costs” means the estimated costs in respect of each phase agreed in accordance with paragraph 5(1) of this Part of this Schedule;
  • “the excess” means the amount by which the county highway authority estimates that the costs referred to in paragraph 5(1) of this Part of this Schedule will exceed the estimated costs in accordance with paragraph 5(5)(b) of this Part of this Schedule;
  • “final certificate” means the certificate issued by the local highway authority to the undertaker for each phase to certify that the defects period has been completed to the satisfaction of the local highway authority;
  • “nominated persons” means the undertaker's representatives or the contractors' representatives on site during the carrying out of the county highway works;
  • “phase” means a phase of the county highway works which are to be carried out in separate phases such phases to be agreed with the local highway authority;
  • “programme of works” means a document setting out the sequence and timetabling of works for the phase in question;
  • “provisional certificate” means the certificate issued by the local highway authority to the undertaker for each phase of the county highway works to certify that in the opinion of the local highway authority the county highway works perform the function for which they were intended and are complete except for minor items not affecting safety;
  • “Road Safety Audit” means an audit carried out in accordance with the Road Safety Audit Standard;
  • “Road Safety Audit Standard” means the Design Manual for Roads and Bridges Standard GG119 or any successor document;
  • “satisfaction of the local highway authority” means the normal standards of the local highway authority in approving the design construction and/or rectification of defects of equivalent highway works applied elsewhere within their administrative area; and
  • “technical approval authority” means the organisation responsible for agreeing the approval in principle and subsequently accepting the relevant certificates for all highway structures; and
  • “utilities” means any pipes wires cables or equipment belonging to any person or body having power or consent to undertake street works under the 1991 Act.
3
  • (1) The local highway authority is the technical approval authority in respect of all highway structures included in the county highway works, including the bridge which will carry the A5/A449 link road over the railway and canal, and the approval in principle for all such highway structures must be submitted to the local highway authority prior to any work commencing on the detailed design for any such highway structure.
  • (2) No work must commence on any phase until the detailed design information and a programme of works in respect of that phase has been submitted to and approved by the local highway authority.
  • (3) No works must commence on any phase other than by a contractor employed by the undertaker but first approved by the local highway authority.
  • (4) No work must commence on any phase until the undertaker has provided security for the carrying out of those works as provided for in paragraph 9 of this Part of this Schedule or some other form of security acceptable to the local highway authority.
  • (5) No work must commence on any phase until a Stage 2 Road Safety Audit has been carried out in respect of that phase and as necessary all issues raised incorporated into an amended design approved by the local highway authority or any relevant exceptions approved by the local highway authority.
  • (6) No work must commence on any phase until traffic management provisions have been agreed with the local highway authority.
  • (7) No work must commence on any phase until any land within that phase not within the public highway which will become public highway as a result of the authorised works is in the ownership of the undertaker.
4
  • (1) The undertaker must prior to commencement of each phase give the local highway authority 14 days' notice in writing of the proposed date on which that phase will start.
  • (2) The undertaker must give the local highway authority 14 days' notice of the road space required for the carrying out of each phase.
  • (3) Each phase must be carried out to the satisfaction of the local highway authority in accordance with—
  • (a) the relevant detailed design information and a programme of works approved pursuant to paragraph 3(1) of this Part of this Schedule or as subsequently varied by agreement between the undertaker and the local highway authority;
  • (b) the Design Manual for Roads and Bridges, the Specification for Highway Works (contained within the Manual of Contract Documents for Highways Works) and any amendment to or replacement thereof for the time being in force save to the extent that they are inconsistent with the Highway General Arrangement Plans (Documents 2.9A – 2.9K) or a departure from such standards has been approved by the local highway authority or such approvals or requirements of the local highway authority in paragraph 3 of this Part of this Schedule that need to be in place prior to the works being undertaken; and
  • (c) all aspects of the Construction (Design and Management) Regulations 2015 and in particular the undertaker must ensure that all client duties (as defined in those regulations) are satisfied.
  • (4) The undertaker must permit and require the contractor to permit at all reasonable times persons authorised by the local highway authority (whose identity must have been previously notified to the undertaker by the local highway authority) to gain access to the county highway works for the purposes of inspection and supervision and the undertaker must provide to the local highway authority contact details of the nominated persons with whom the local highway authority should liaise during the carrying out of the county highway works.
  • (5) The undertaker must permit attendance by representatives of the local highway authority at all pre-contract and progress meetings held in relation to each phase.
  • (6) The undertaker must provide shared working facilities including access to welfare and office facilities for the local highway authority for the duration of each phase including the defects period unless otherwise agreed.
  • (7) The undertaker must during the period in which the county highway works are carried out maintain the flow of traffic and safeguard the passage of pedestrians along any street on which the county highway works are being carried out and maintain, or provide temporary alternative for all accesses (including, for the avoidance of doubt, private accesses) affected thereby or in the vicinity thereof.
  • (8) At any time during the carrying out of the county highway works the nominated persons must act upon any reasonable request made by the local highway authority in relation to the carrying out of the county highway works as soon as practicable following such request being made to the nominated persons save to the extent that the contents of such request are inconsistent with or fall outside the contractor's obligations under its contract with the undertaker or the undertakers' obligations in this Order.
  • (9) If at any time the undertaker does not comply with any of the terms of this Part of this Schedule in respect of any phase having been given one month's notice of an alleged breach by the local highway authority, then the undertaker must within 14 days of receipt of a demand by the local highway authority pay to the county highway authority the sum of the local highway authority's proper estimate of completing that phase and any maintenance works which the undertaker would have been responsible for, and if the undertaker fails to pay the demand from the local highway authority within 14 days, the local highway authority is entitled to use the bond to meet the cost of completing the county highway works on behalf of the undertaker.
  • (10) Nothing in this Part of this Schedule prevents the local highway authority from carrying out any work or taking such action as deemed appropriate, without prior notice to the undertaker, in the event of an emergency or danger to the public. The cost to the local highway authority of such work or action being chargeable to and recoverable from the undertaker if the need for such action arises from the carrying out of the county highway works, and the local highway authority is entitled to utilise the bond should the undertaker fail to pay any costs arising from this sub-paragraph within 14 days of a demand for such costs being made by the local highway authority.
  • (11) The undertaker in carrying out each phase must at its own expense divert or protect all utilities as may be necessary to enable the local highway works to be properly carried out and all agreed alterations to existing services must be carried out to the satisfaction of the local highway authority acting reasonably.
5
  • (1) The undertaker must fund the whole of the cost of the county highway works and all costs incidental to the county highway works and must also pay to the local highway authority in respect of each phase in accordance with sub-paragraph (4) a sum equal to the whole of any costs and expenses which the local highway authority incur, including costs and expenses for using external staff and resources as well as costs and expenses of using in-house staff and resources in relation to the county highway works and arising out of them and their implementation including—
  • (a) the checking and approval of all design work carried out by or on behalf of the undertaker for that phase;
  • (b) costs in relation to agreeing the programme of works for that phase;
  • (c) the carrying out of supervision of that phase; and
  • (d) all legal and administrative costs in relation to paragraphs (a) and (b),

together comprising “the estimated costs”.

  • (2) The undertaker must pay to the local highway authority upon demand the total costs properly and necessarily incurred by the local highway authority in undertaking any statutory procedure or preparing and bringing into force any traffic regulation order or orders necessary to carry out or for effectively implementing the county highway works provided that this paragraph does not apply to the making of any orders which duplicate orders contained in this Order.
  • (3) The undertaker and the local highway authority must agree a schedule of the estimated costs to be incurred pursuant to sub-paragraph (1) in respect of each phase prior to the commencement of that phase.
  • (4) The undertaker must make the payments referred to in sub-paragraph (1) as follows—
  • (a) the undertaker must pay a sum equal to the agreed estimated costs in respect of a phase prior to commencing that phase; and
  • (b) if at any time or times after the payment in respect of a phase referred to in sub-paragraph (4)(a) has become payable the local highway authority reasonably estimates that the costs in respect of that phase referred to in sub-paragraph (1) will exceed the estimated costs for that phase it may give notice to the undertaker of the amount by which it then reasonably estimates those costs will exceed the estimated costs (“the excess”) and the undertaker must pay to the local highway authority within 28 days of the date of that notice a sum equal to the excess.
  • (5) If the local highway authority has received the as built information within 91 days of the issue of the final certificate for the final phase of the A5/A449 link road pursuant to paragraph 7 of this Part of this Schedule, or for each phase pursuant to paragraph 8 of this Part of this Schedule, as the case may be, the local highway authority must give the undertaker a final account of the costs referred to in sub-paragraph (1) and within 28 days from the expiry of the 91-day period—
  • (a) if the account shows a further sum as due to the local highway authority the undertaker must pay to the local highway authority the sum shown due to it in that final account; and
  • (b) if the account shows that the payment or payments previously made have exceeded those costs the local highway authority must refund the difference to the undertaker.
  • (6) If any payment due under any of the provisions of this Part of this Schedule is not made on or before the date on which it falls due the party from whom it was due must at the same time as making the payment pay to the other party interest at 1% above the Base Rate of Lloyds Bank Plc for the period starting on the date upon which the payment fell due and ending with the date of payment of the sum on which interest is payable together with that interest.
6
  • (1) As soon as each phase has been completed and a Stage 3 Road Safety Audit for that phase has been carried out and any resulting recommendations complied with to the satisfaction of the local highway authority, the local highway authority must immediately issue a provisional certificate of completion in respect of that phase, such certificate not to be unreasonably withheld or delayed.
  • (2) The undertaker must at its own expense remedy any defects in that phase identified by the local highway authority to the satisfaction of the local highway authority acting reasonably during the defects period in respect of that phase.
  • (3) The undertaker must submit Stage 4(a) (12 months after completion of each phase) and Stage 4(b) (36 months after completion of each phase) Road Safety Audits as required by and in line with the timescales stipulated in the Road Safety Audit Standard. The undertaker must at its own expense comply with the findings of the Stage 4(a) and 4(b) Road Safety Audits to the satisfaction of the local highway authority acting reasonably.
  • (4) The local highway authority must approve the audit brief and CVs for all Road Safety Audits and exceptions to items raised if appropriate in accordance with the Road Safety Audit Standard.
7
  • (1) The provisions of this paragraph apply to all the county highway works with the exception of the A5/A449 link road.
  • (2) The undertaker must apply to the local highway authority for the issue of the final certificate in respect of each phase of the works to which this paragraph applies at the expiration of the defects period in respect of that phase) or if later on the date on which any defects or damage arising from defects during the defects period have been made good to the satisfaction of the local highway authority acting reasonably, and when making such application the undertaker must submit to the local highway authority—
  • (a) as built information of the relevant phase; and
  • (b) a plan, for approval, clearly identifying the extent of any land which is to be highway maintainable at public expense by the local highway authority which must be in accordance with the detailed design information but reflecting the as built outcome.
  • (3) If the provisions of paragraph 7(2) of this Part of this Schedule are complied with to the satisfaction of the local highway authority, the local highway authority must immediately issue a final certificate for the phase concerned, such certificate not to be unreasonably withheld or delayed.
8
  • (1) The provisions of this paragraph apply only to the A5/A449 link road.
  • (2) The undertaker must apply to the local highway authority for the issue of the final certificate in respect of the entirety of the A5/A449 link road at the expiration of the defects period of the last phase of the A5/A449 link road to be constructed or if later on the date on which any defects or damage arising from defects during the defects period of the last phase of the A5/A449 link road to be constructed have been made good to the satisfaction of the local highway authority acting reasonably, and when making such application the undertaker must—
  • (a) submit to the local highway authority as built information of the relevant phase;
  • (b) submit to the local highway authority a plan clearly identifying the extent of any land which is to be highway maintainable at public expense by the county highway authority which must be in accordance with the detailed design information but reflecting the as built outcome; and
  • (c) pay to the local highway authority the commuted sum calculated in accordance with the versions of the ADEPT Commuted Sums Calculator and the ADEPT Bridge Sums Guidance in force at the date on which the commuted sum is calculated.
  • (3) If the provisions of paragraph 9(2) of this Part of this Schedule are complied with to the satisfaction of the local highway authority, the local highway authority must immediately issue a final certificate for the entirety of the A5/A449 link road, such certificate not to be unreasonably withheld or delayed.
9
  • (1) Prior to the commencement of each phase the county highway works within that phase must be secured by a bond or such other form of bond or other security that may be agreed between the undertaker and the local highway authority to indemnify the local highway authority against all losses, damages, costs or expenses arising from any breach of any one or more of the obligations of the undertaker in respect of that phase under the provisions of this Part of this Schedule provided that the maximum liability of the bond or other form of security does not exceed the bond sum relating to that phase.
  • (2) In respect of all the county highway works, with the exception of the A5/A449 link road, each bond sum must be automatically reduced as follows—
  • (a) on the issue of the provisional certificate for each phase the bond sum must automatically reduce by 80% of the bond sum relating to that phase save insofar as any claim or claims have been made against the bond or other form of security and/or liability on its part has arisen prior to that date; and
  • (b) on the issue of the final certificate for each phase the bond/security provider must automatically be released from all its obligations in respect of the bond or other form of security relating to that phase save insofar as any claim or claims have been made against the Bond or other form of security or liability on its part has arisen prior to that date.
  • (3) In respect of the A5/A449 link road the bond sum for each phase of the A5/A449 link road must be reduced as follows—
  • (a) in respect of any phase which includes any part of the new bridge to be provided over the railway and canal on the issue of the provisional certificate for that phase the bond sum must be reduced by such percentage as the undertaker and the local highway authority agree save insofar as any claim or claims have been made against the bond or other form of security and/or liability on its part has arisen prior to that date;
  • (b) in respect of all phases of the A5/A449 link road to which paragraph (a) does not apply, on the issue of the provisional certificate for that phase the bond sum must be reduced by such percentage as the undertaker and the local highway authority agree subject to a minimum reduction to 50% of the bond sum save insofar as any claim or claims have been made against the bond or other form of security and/or liability on its part has arisen prior to that date; and
  • (c) on the issue of the final certificate for the A5/A449 link road in accordance with paragraph 8 of this Part of this Schedule the bond/security provider must automatically be released from all its obligations in respect of all bonds or other form of security relating to the A5/A449 link road save insofar as any claim or claims have been made against the bond or other form of security or liability on its part has arisen prior to that date.
10

The undertaker must prior to commencement of the county highway works effect public liability insurance with an insurer in the minimum sum of £10,000,000.00 (ten million pounds) against any legal liability for damage loss or injury to any property or any person as a direct result of the execution of the county highway works or any part thereof by the undertaker.

11
  • (1) The undertaker must in relation to the carrying out of the county highway works take such precautions for the protection of the public and private interest as would be incumbent upon it if it were the highway authority and must indemnify the local highway authority from and against all costs, expenses, damages, losses and liabilities arising from or in connection with or ancillary to any claim, demand, action or proceedings resulting from the design and carrying out of the county highway works prior to the issue of each defects certificate provided that the foregoing indemnity does not extend to any costs, expenses, liabilities and damages caused by or arising out of the neglect or default of the local highway authority or its officers, servants, agents or contractors or any person or body for whom it is responsible.
  • (2) The undertaker must pay to the local highway authority each sum (if any) that is due to the local highway authority and certified as correct by the local highway authority arising from paragraph 12 of this Part of this Schedule within 28 days of receiving written notice from the local highway authority to do so and where payment is overdue interest will be payable calculated on a daily basis at a rate of 1% above the Base Rate of Lloyds Bank Plc.
  • (3) The undertaker must notify the local highway authority of the intended date of opening of each phase to public traffic not less than 14 days in advance of the intended date.
  • (4) The undertaker must notify the local highway authority of the actual date that each phase is open to public traffic on each occasion within 14 days of that occurrence.
12

The undertaker must procure warranties from the contractor and designer of each phase to the effect that all reasonable skill, care and due diligence will be exercised in designing and constructing that phase including the selection of materials, goods, equipment and plant, such warranties to be provided to the local highway authority before that phase commences.

13
  • (1) Any approvals, certificates, consents or agreements required of, or sought from or with the local highway authority pursuant to the provisions of this Schedule must not be unreasonably withheld or delayed and must be given in writing save that any such approval, certificate, consent or agreement is deemed to have been given if it is neither given nor refused within 42 days of the specified day.
  • (2) In this paragraph “specified day” means—
  • (a) the day on which particulars of the matter are submitted to the local highway authority under the provisions of this Part of this Schedule; or
  • (b) the day on which the undertaker provides the local highway authority with any further particulars of the matter that have been reasonably requested by the local highway authority within 28 days of the date in paragraph (a),

whichever is the later.

14
  • (1) Article 47 (arbitration) does not apply to this Part of this Schedule except in respect of sub-paragraph (7).
  • (2) Any difference under this Part of this Schedule must be referred to and settled by a single independent and suitable person who holds appropriate professional qualifications and is a member of a professional body relevant to the matter in dispute acting as an expert, such person to be agreed by the differing parties or, in the absence of agreement, identified by the President of the Institution of Civil Engineers.
  • (3) All parties involved in settling any difference must use best endeavours to do so within 21 days from the date of a dispute first being notified in writing by one party to the other and in the absence of the difference being settled within that period the expert must be appointed within 28 days of the notification of the dispute.
  • (4) The fees of the expert are payable by the parties in such proportions as the expert may determine or, in the absence of such determination, equally.
  • (5) The expert must—
  • (a) invite the parties to make submissions to the expert in writing and copied to the other party to be received by the expert within 21 days of the expert's appointment;
  • (b) permit a party to comment on the submissions made by the other party within 21 days of receipt of the submission;
  • (c) issue a decision within 42 days of receipt of the submissions under paragraph (b); and
  • (d) give reasons for the decision.
  • (6) The expert must consider where relevant—
  • (a) the development outcome sought by the undertaker;
  • (b) the ability of the undertaker to achieve its outcome in a timely and cost-effective manner;
  • (c) the nature of the power sought to be exercised by the undertaker;
  • (d) the effectiveness, cost and reasonableness of proposals for mitigation arising from any party;
  • (e) in respect of decisions on the level of the reductions of the bond sums pursuant to paragraph 9(3)(a) and (b) of this Part of this Schedule the need to ensure that the financial risk to the local highway authority is no greater than that which would ordinarily be accepted in relation to highway improvements required to facilitate private developments in which the local highway authority is carrying out its statutory duty as local highway authority, but having regard to any specific circumstances relating to the A5/A449 link road; and
  • (f) any other important and relevant consideration.
  • (7) Any determination by the expert is final and binding, except in the case of manifest error in which case the difference that has been subject to expert determination may be referred to and settled by arbitration under article 47.
15

Form 2 as referred to in paragraph 2—

1

The provisions of this Part of this Schedule have effect, unless otherwise agreed in writing between the undertaker and WPD.

2

In this Part of this Schedule—

  • “alternative apparatus” means alternative apparatus adequate to enable WPD to fulfil its statutory functions in a manner not less efficient than previously;
  • “alternative rights” means all necessary legal easements, consents or permissions required by WPD to permit a diversion of apparatus or to authorise the construction of alternative apparatus;
  • “apparatus” means any conduit overhead electric lines cables ducts pipes or other apparatus or equipment belonging to or maintained by WPD for the purposes of electricity transmission and its distribution, and includes any structure in which apparatus is or will be lodged or which gives or will give access to apparatus;
  • “functions” includes powers and duties;
  • “in”, in a context referring to apparatus or alternative apparatus in land, includes a reference to apparatus or alternative apparatus under, over or upon land;
  • “plan” or “plans” includes all designs, drawings, specifications, method statements, programmes, calculations, risk assessments and other documents that are reasonably necessary to properly and sufficiently describe and assess the works to be executed;
  • “specified work” means so much of any of the authorised development that is carried out within 6 metres of any apparatus; and
  • “WPD” means Western Power Distribution Limited (West Midlands) Plc (Company Registration Number 03600574) whose registered office is at Avonbank, Feeder Road, Bristol, BS2 0TB.
3

This Part of this Schedule does not apply to apparatus in respect of which the relations between the undertaker and WPD are regulated by the provisions of Part 3 of the 1991 Act.

4

Regardless of any provision in this Order or anything shown on the land plans, the undertaker may not acquire any apparatus otherwise than by agreement.

5
  • (1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed or over which access to any apparatus is enjoyed or requires that WPD's apparatus is relocated or diverted, that apparatus must not be removed under this Part of this Schedule and any right of WPD to maintain that apparatus in that land or gain access to it must not be extinguished without the prior consent of WPD until alternative apparatus has been constructed and is in operation and access to it has been provided if necessary all to the reasonable satisfaction of WPD.
  • (2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to WPD written notice of that requirement, together with a plan and section of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order WPD reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (6), afford to WPD the necessary facilities and rights for the construction of alternative apparatus in other land owned or controlled by the undertaker and subsequently for the maintenance of that apparatus.
  • (3) If, for the purpose of executing any works, the undertaker requires to remove or divert any apparatus placed within the Order land, and alternative apparatus or any part of such alternative apparatus is to be constructed in land other than the Order land as a consequence of the removal or diversion of apparatus, then the undertaker must use reasonable endeavours to obtain alternative facilities and rights in other land in which the alternative apparatus is to be constructed.
  • (4) Should the undertaker not be able to obtain the alternative rights required under sub-paragraph (3) then the undertaker and WPD must use reasonable endeavours to agree a reasonably practicable and mutually agreeable alternative engineering solution which does not require alternative apparatus to be constructed in land other than Order land and does not require alternative rights.
  • (5) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker and the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (3) and an alternative engineering solution cannot be agreed in accordance with sub-paragraph (4), WPD must on receipt of written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed save that this obligation does not extend to a requirement on WPD to use its compulsory purchase powers to this end unless WPD elects to do so.
  • (6) Any alternative apparatus required pursuant to sub-paragraphs (2) or (3) must be constructed in such manner and in such line or situation as may be agreed between WPD and the undertaker or in default of agreement settled in accordance with paragraph 10 of this Part of this Schedule.
  • (7) WPD must, after the alternative apparatus to be provided or constructed has been agreed or settled pursuant to paragraph 10 of this Part of this Schedule, and after the grant to WPD of any such facilities and rights as are referred to in sub-paragraphs (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
  • (8) Regardless of anything in sub-paragraph (7), if the undertaker gives notice in writing to WPD that it desires itself to execute any work, or part of any work in connection with the construction or removal of apparatus in any land of the undertaker, that work, instead of being executed by WPD, must be executed by the undertaker without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of WPD.
  • (9) Nothing in sub-paragraph (8) authorises the undertaker to execute the placing, installation, bedding, packing, removal, connection or disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is laid in a trench) within 600 millimetres of the apparatus.
6
  • (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to WPD facilities and rights for the construction and maintenance in land of the undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between the undertaker and WPD or in default of agreement settled in accordance with paragraph 10 of this Part of this Schedule.
  • (2) In settling those terms and conditions in respect of alternative apparatus to be constructed in the land of the undertaker, the expert must—
  • (a) give effect to all reasonable requirements of the undertaker for ensuring the safety and efficient operation of the authorised development and for securing any subsequent alterations or adaptations of the alternative apparatus which may be required to prevent interference with any proposed works of the undertaker; and
  • (b) so far as it may be reasonable and practicable to do so in the circumstances of the particular case, give effect to the terms and conditions, if any, applicable to the apparatus constructed in the land for which the alternative apparatus is to be substituted.
  • (3) If the facilities and rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are in the opinion of the expert less favourable on the whole to WPD than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the expert must make provision for the payment of compensation by the undertaker to WPD as appears to the expert to be reasonable having regard to all the circumstances of the particular case.
7
  • (1) Not less than 60 days before the undertaker intends to start the execution of any specified work, the undertaker must submit to WPD a plan, section and description of the works to be executed. Any submission must note the time limits imposed on WPD under sub-paragraph (3).
  • (2) Subject to sub-paragraph (3) the undertaker must not commence any works to which sub-paragraph (1) applies until WPD has given written approval of the submitted plan, and identified any reasonable requirements it has in relation to the carrying out of the works, such approval not to be unreasonably withheld or delayed.
  • (3) If by the expiry of 60 days beginning with the date on which a plan, section and description under sub-paragraph (1) are submitted WPD has not advised the undertaker in writing of its approval or disapproval of the plans and any reasonable requirements for the alteration or otherwise for the protection of the apparatus, or for securing access to it, it is deemed to have approved the plans, sections or descriptions as submitted.
  • (4) The works referred to in sub-paragraph (1) must be executed in accordance with the plan, section and description approved under sub-paragraph (3) and in accordance with any reasonable requirements as may be notified in accordance with sub-paragraph (2) by WPD, and WPD is entitled to watch and inspect the execution of those works.
  • (5) At all times when carrying out any works authorised under the Order the undertaker must comply with WPD's “Avoidance of Danger from Electricity Overhead Lines and Underground Cables” (2014), the Energy Network Association's “A Guide to the Safe Use of Mechanical Plant in the Vicinity of Electricity Overhead Lines” (undated), the Health and Safety Executive's GS6 “Avoiding Danger from Overhead Power Lines” and the Health and Safety Executive's “HSG47 Avoiding Danger from Underground Services” (3rd edition, 2014) as the same may be replaced from time to time.
  • (6) If in consequence of the works proposed by the undertaker, WPD reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement in accordance with sub-paragraph (2), the provisions of this paragraphs apply as if the removal of the apparatus had been required by the undertaker under paragraph 5(2) of this Part of this Schedule.
  • (7) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 60 days before commencing the execution of any works, a new plan, section and description instead of the plan, section and description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section and description.
  • (8) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to WPD notice as soon as is reasonably practicable, submit a plan, section and description of those works to WPD as soon as reasonably practicable subsequently and comply with sub-paragraph (4) in so far as is reasonably practicable in the circumstances.
8

The undertaker must repay to WPD the reasonable expenses incurred by WPD in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new connection arising as a result of the powers conferred upon the undertaker pursuant to this Order.

9
  • (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any specified work, any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of WPD, or there is any interruption in any service provided, or in the supply of any goods by, WPD, the undertaker is to—
  • (a) bear and pay the cost reasonably incurred by WPD in making good such damage or restoring the supply; and

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.