The Medworth Energy from Waste Combined Heat and Power Facility Order 2024
- (i) so much of the land specified in columns (1) and (2) of Schedule 10 (land of which temporary possession may be taken) for the purpose specified in relation to that land in column (3) of that Schedule;
- (ii) any other Order land in respect of which no notice of entry has been served under section 11 (powers of entry) of the 1965 Act (other than in connection with the acquisition of rights only) and no declaration has been made under section 4 (execution of declaration) of the 1981 Act;
- (b) remove any buildings, fences, drainage, debris and vegetation from that land;
- (c) construct temporary works (including the provision of means of access), security fencing, bridges, services, signage and buildings on that land;
- (d) construct any works (including mitigation works), or use the land, for the purposes specified in Schedule 10 (land of which temporary possession may be taken) in relation to that land;
- (e) construct any works on that land as are mentioned in Schedule 1 (authorised development); and
- (f) carry out any mitigation works required pursuant to the requirements in Schedule 2 (requirements).
- (2) Not less than 14 days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.
- (3) The undertaker must not remain in possession of any land under this article for longer than reasonably necessary and in any event may not, without the agreement of the owners of the land, remain in possession of any land under this article—
- (a) in the case of land specified in paragraph (1)(a)(i) after the end of the period of one year beginning with the date of final commissioning of the authorised development; or
- (b) in the case of land referred to in paragraph (1)(a)(ii) after the end of the period of one year beginning with the date of final commissioning of the authorised development unless the undertaker has, before the end of that period, served notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act or has otherwise acquired the land subject to temporary possession.
- (4) Unless the undertaker has served notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act or has otherwise acquired the land subject to temporary possession, the undertaker must, before giving up possession of land of which temporary possession has been taken under this article, remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker is not required to—
- (a) replace a building, drain or any debris removed under this article;
- (b) remove any drainage works installed by the undertaker under this article;
- (c) remove any new road surface or other improvements carried out under this article to any street specified in Schedule 3 (streets subject to street works), Schedule 4 (streets subject to permanent alteration of layout), Schedule 5 (streets subject to temporary alteration of layout), or land that is subject to an agreement with the local highway authority for it to be dedicated as highway;
- (d) remove any fencing or boundary treatments installed by the undertaker under this article to replace or enhance existing fencing or boundary treatments; or
- (e) restore the land on which any works have been carried out under paragraph (1)(f) insofar as the works relate to mitigation works identified in the environmental statement or required pursuant to the requirements in Schedule 2 (requirements).
- (5) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.
- (6) Any dispute as to a person’s entitlement to compensation under paragraph (5), or as to the amount of compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
- (7) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the carrying out of the authorised development, other than loss or damage for which compensation is payable under paragraph (5).
- (8) The undertaker may not compulsorily acquire under this Order the land referred to in paragraph (1)(a)(i).
- (9) Nothing in this article precludes the undertaker from—
- (a) creating and acquiring new rights over any part of the Order land identified in Schedule 8 under article 25 (compulsory acquisition of rights and imposition of restrictive covenants); or
- (b) acquiring any right in the subsoil of any part of the Order land under article 26 (acquisition of subsoil only) or article 31 (rights under or over streets).
- (10) Where the undertaker takes possession of land under this article, the undertaker is not to be required to acquire the land or any interest in it.
- (11) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.
- (12) Nothing in this article prevents the taking of temporary possession more than once in relation to any land specified in Schedule 10.
Temporary use of land for maintaining the authorised development
33
- (1) Subject to paragraph (2), at any time during the maintenance period (as defined in paragraph (11)) relating to any part of the authorised development, the undertaker may—
- (a) enter on and take temporary possession of any land within the Order land if possession is reasonably required for the purpose of maintaining the authorised development;
- (b) enter on any land within the Order land for the purpose of gaining such access as is reasonably required for the purpose of maintaining the authorised development; and
- (c) construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.
- (2) Paragraph (1) does not authorise the undertaker to take temporary possession of—
- (a) any house or garden belonging to a house; or
- (b) any building (other than a house) if it is for the time being occupied.
- (3) Not less than 28 days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.
- (4) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised development for which possession of the land was taken.
- (5) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.
- (6) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.
- (7) Any dispute as to a person’s entitlement to compensation under paragraph (6), or as to the amount of the compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
- (8) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the maintenance of the authorised development, other than loss or damage for which compensation is payable under paragraph (6).
- (9) Where the undertaker takes possession of land under this article, the undertaker is not to be required to acquire the land or any interest in it.
- (10) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.
- (11) In this article “the maintenance period” means the period of five years beginning with the date of final commissioning unless a different maintenance period is stated in the landscape and ecology management plan approved under requirement 5 in Schedule 2 (requirements).
Statutory undertakers
34
Subject to the provisions of Schedule 11 (protective provisions), the undertaker may—
- (a) acquire compulsorily, or acquire new rights or impose restrictive covenants over, any land belonging to statutory undertakers within the Order land;
- (b) extinguish or suspend the rights of or restrictive covenants for the benefit of, and remove or reposition the apparatus belonging to, statutory undertakers on, under, over or within the Order land.
Apparatus and rights of statutory undertakers in altered or closed streets
35
Where a street is altered or diverted or its use is temporarily prohibited or restricted under article 10 (street works), article 11 (power to alter layout, etc., of streets), article 12 (construction and maintenance of new or altered means of access) or article 13 (temporary prohibition or restriction of use of streets and public rights of way) any statutory undertaker whose apparatus is under, in, on, along or across the street has the same powers and rights in respect of that apparatus, subject to Schedule 11 (protective provisions), as if this Order had not been made.
Recovery of costs of new connections
36
- (1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article 34 (statutory undertakers) any person who is the owner or occupier of premises to which a supply was given from that apparatus is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.
- (2) Paragraph (1) does not apply in the case of the removal of a public sewer but where such a sewer is removed under article 34 (statutory undertakers) any person who is—
- (a) the owner or occupier of premises the drains of which communicated with the sewer; or
- (b) the owner of a private sewer which communicated with that sewer,
is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.
- (3) This article does not have effect in relation to apparatus to which article 35 (apparatus and rights of statutory undertakers in altered or closed streets) or Part 3 (street works in England and Wales) of the 1991 Act applies.
- (4) In this article—
- “public communications provider” has the same meaning as in section 151(1) of the Communications Act 2003[^f00031]; and
- “public utility undertaker” has the same meaning as in the 1980 Act.
PART 6 — MISCELLANEOUS AND GENERAL
Electronic communications
37
- (1) In this Order—
- (a) references to documents, plans, drawings, certificates, or to copies, include references to them in electronic form; and
- (b) references to a form of communication being “in writing” include references to an electronic communication that satisfies the conditions in paragraph (3) and references to “written” and cognate expressions are to be construed accordingly.
- (2) If an electronic communication is received outside the recipient’s business hours, it is to be taken to have been received on the next working day.
- (3) The conditions are that the communication is—
- (a) capable of being accessed by the recipient;
- (b) legible in all material respects; and
- (c) sufficiently permanent to be used for subsequent reference.
- (4) For the purposes of paragraph (3)(b), a communication is legible in all material respects if the information contained in it is available to the recipient to no lesser extent than it would be if transmitted by means of a document in printed form.
- (5) In this article “electronic communication” has the meaning given in section 15(1) of the Electronic Communications Act 2000[^f00032].
Application of landlord and tenant law
38
- (1) This article applies to—
- (a) any agreement for leasing to any person the whole or any part of the authorised development or the right to operate the same; and
- (b) any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised development, or any part of it,
so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person’s use.
- (2) No enactment or rule of law regulating the rights and obligations of landlords and tenants prejudices the operation of any agreement to which this article applies.
- (3) Accordingly, no such enactment or rule of law applies in relation to the rights and obligations of the parties to any lease granted by or under any such agreement so as to—
- (a) exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;
- (b) confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or
- (c) restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.
Operational land for the purposes of the 1990 Act
39
Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3)(a) (cases in which land is to be treated as not being operational land) of the 1990 Act.
Defence to proceedings in respect of statutory nuisance
40
- (1) Where proceedings are brought under section 82(1) (summary proceedings by persons aggrieved by statutory nuisances) of the Environmental Protection Act 1990[^f00033] in relation to a nuisance falling within sub-paragraph (g) of section 79(1) (statutory nuisances and inspections therefor) of that Act no order is to be made, and no fine may be imposed, under section 82(2) of that Act if—
- (a) the defendant shows that the nuisance—
- (i) relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance or decommissioning of the authorised development and that the nuisance is attributable to the carrying out of the authorised development in accordance with a notice served under section 60 (control of noise on construction sites), or a consent given under section 61 (prior consent for work on construction sites), of the Control of Pollution Act 1974[^f00034]; or
- (ii) is a consequence of the construction or maintenance or decommissioning of the authorised development and that it cannot reasonably be avoided; or
- (b) the defendant shows that the nuisance—
- (i) relates to premises used by the undertaker for the purposes of or in connection with the use of the authorised development and that the nuisance is attributable to the use of the authorised development which is being used in compliance with requirement 19 of Schedule 2 (requirements); or
- (ii) is a consequence of the use of the authorised development and that it cannot reasonably be avoided.
- (2) Section 61(9) of the Control of Pollution Act 1974 does not to apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance or decommissioning of the authorised development.
Protective provisions
41
Schedule 11 (protective provisions) has effect.
Certification of plans etc.
42
- (1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of all documents and plans listed in Table 10 of Schedule 13 (documents and plans to be certified) to this Order for certification that they are true copies of those documents.
- (2) A plan or document so certified is to be admissible in any proceedings as evidence of the contents of the document of which it is a copy.
- (3) Where a plan or document certified under paragraph (1)—
- (a) refers to a provision of this Order (including any specified requirement) when it was in draft form; and
- (b) identifies that provision by number, or combination of numbers and letters, which is different from the number, or combination of numbers and letters by which the corresponding provision of this Order is identified in this Order as made;
the reference in the plan or document concerned must be construed for the purposes of this Order as referring to the provision (if any) corresponding to that provision in this Order as made.
Service of notices
43
- (1) A notice or other document required or authorised to be served for the purposes of this Order may be served—
- (a) by post;
- (b) by delivering it to the person on whom it is to be served or to whom it is to be given or supplied; or
- (c) with the consent of the recipient and subject to paragraphs (6) to (8), by electronic transmission.
- (2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.
- (3) For the purposes of section 7 (references to service by post) of the Interpretation Act 1978[^f00035] as it applies for the purposes of this article, the proper address of any person in relation to the service on that person of a notice or document under paragraph (1) is, if that person has given an address for service, that address and otherwise—
- (a) in the case of the secretary or clerk of a body corporate, the registered or principal office of that body; and
- (b) in any other case, the last known address of that person at that time of service.
- (4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having an interest in, or as the occupier of, land and the name or address of that person cannot be ascertained after reasonable enquiry, the notice may be served by—
- (a) addressing it to that person by the description of “owner”, or as the case may be “occupier” of the land (describing it); and
- (b) either leaving it in the hands of the person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.
- (5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement is to be taken to be fulfilled only where—
- (a) the recipient of the notice or other document to be transmitted has given consent to the use of electronic transmission in writing or by electronic transmission;
- (b) the notice or document is capable of being accessed by the recipient;
- (c) the notice or document is legible in all material respects; and
- (d) in a form sufficiently permanent to be used for subsequent reference.
- (6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within seven days of receipt that the recipient requires a paper copy of all or any part of that notice or other document the sender must provide such a copy as soon as reasonably practicable.
- (7) Any consent to the use of an electronic transmission by a person may be revoked by that person in accordance with paragraph (8).
- (8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—
- (a) that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and
- (b) such revocation is final and takes effect on a date specified by the person in the notice but that date must not be less than seven days after the date on which the notice is given.
- (9) This article does not exclude the employment of any method of service not expressly provided for by it.
Procedure in relation to certain approvals etc.
44
- (1) Where an application is made to or request is made of the relevant planning authority, a highway authority, a traffic authority, a street authority, or the owner of a watercourse, sewer or drain or the beneficiary of any of the protective provisions contained in Part 1 or Part 2 of Schedule 11 (protective provisions) for any consent, agreement or approval required or contemplated by any of the provisions of the Order (not including the requirements), such consent, agreement or approval to be validly given, must be given in writing and must not be unreasonably withheld or delayed.
- (2) Save for applications made pursuant to Schedule 12 (procedure for the discharge of requirements), if, within eight weeks after the application or request has been submitted to an authority, beneficiary of protective provisions or an owner as referred to in paragraph (1) of this article (or such longer period as may be agreed with the undertaker in writing) it has not notified the undertaker of its decision (and if it is a disapproval the grounds of the disapproval), it is deemed to have approved the application or request.
- (3) Schedule 12 is to have effect in relation to all consents, agreements or approvals required from the relevant planning authority in respect of discharge of requirements listed in Schedule 2.
No double recovery
45
Compensation is not payable in respect of the same matter both under this Order and under any enactment, any contract or any rule of law.
Arbitration
46
Any difference or dispute arising under any provision of this Order shall, unless otherwise agreed in writing between the undertaker and the party in question, be referred to and settled in arbitration in accordance with the rules at Schedule 15 (arbitration rules) of this Order, by a single arbitrator to be agreed upon by the parties within 14 days of receipt of the notice of arbitration, or if the parties fail to agree within the time period stipulated, to be appointed on application of either party (after giving written notice to the other) by the Secretary of State.
Incorporation of the mineral code
47
Parts 2 and 3 of Schedule 2 (minerals) to the Acquisition of Land Act 1981[^f00036] are incorporated in this order subject to the following modifications—
- (a) for “the acquiring authority” substitute “the undertaker”; and
- (b) for the “undertaking” substitute “authorised development”.
Modification of the section 106 agreement relating to land
48
- (1) The section 106 agreement is modified so that the section 106 agreement no longer applies to and can no longer be enforced in respect of any land within the Order limits.
- (2) The modification set out in sub–section (1) will only have effect if—
- (a) Work No. 4A has commenced;
- (b) the highway authority serves a notice pursuant to section 228(1) of the 1980 Act in respect of any land within the Order limits that is bound by the section 106 agreement; and
- (c) the period of one month from the day on which the notice was first displayed pursuant to section 228(1) of the 1980 Act has expired.
- (3) This article does not affect the terms of, any rights or liabilities under or the ability of any person to enforce the section 106 agreement in respect of any other land bound by the section 106 agreement that is outside of the Order limits.
SCHEDULE 1 — AUTHORISED DEVELOPMENT
Authorised Development
1
In the County of Cambridgeshire and the County of Norfolk a nationally significant infrastructure project as defined in section 14(1)(a) (nationally significant infrastructure projects: general) and section 15 (generating stations) of the 2008 Act and associated development within the meaning of section 115(2) (development for which development consent may be granted) of the 2008 Act comprising all or part of—
SCHEDULE 2 — REQUIREMENTS
Time limits
1
The authorised development must not commence after the expiration of five years beginning with the date on which this Order comes into force.
Detailed design approval
2
- (1) No part of Work Nos. 1, 1A, 1B, 2A, 2B, 3, 6A, 6B, 7, 8, 9 or 10 may commence until details of the layout, scale and , in respect of above ground development, external appearance for that Work No. have been submitted to and approved by the relevant planning authority.
- (2) The details submitted for approval under sub-paragraph (1) must be substantially in accordance with the design principles applicable to that work order as set out in Appendix A of the design and access statement.
- (3) Where a requirement requires the authorised development to be constructed in accordance with details approved by the relevant planning authority, the approved details are taken to include any amendments subsequently approved by the relevant planning authority.
- (4) The authorised development must be carried out in accordance with the approved details.
Parameters of authorised development
3
The elements of the authorised development listed in column (1) of Table 11 in Schedule 14 (maximum and minimum design parameters) must not exceed the maximum and minimum dimensions and levels set out in relation to that element in columns (3) to (6) of that table.
Biodiversity and landscape mitigation
4
- (1) No part of the authorised development may commence until a written landscape and ecology strategy for that part has been submitted to and approved by the relevant planning authority. The landscape and ecology strategy must be substantially in accordance with the outline landscape and ecology strategy.
- (2) The landscape and ecology strategy must be implemented as approved under sub-paragraph (1).
Landscape and ecology management plan
5
- (1) Prior to the date of final commissioning a landscape and ecology management plan for Work No. 1, 1A, 1B, 2A, 2B and 9 must be submitted to and approved by the relevant planning authority for the operation of that part of the authorised development. The landscape and ecology management plan must be substantially in accordance with the outline landscape and ecology management plan.
- (2) The landscape and ecology management plan must be implemented as approved under sub‑paragraph (1).
Biodiversity net gain
6
- (1) No part of the authorised development may commence until a biodiversity net gain strategy has been submitted to and approved by the relevant planning authority, in consultation with the relevant statutory nature conservation body.
- (2) The biodiversity net gain strategy must include details of how the strategy will secure a minimum of 10% biodiversity net gain, calculated using the biodiversity metric 3.0 published by Natural England in July 2021 or such other biodiversity metric approved by the relevant planning authority in consultation with the relevant statutory nature conservation body, during the operation of the authorised development including onsite and offsite measures and be substantially in accordance with the outline biodiversity net gain strategy.
- (3) The biodiversity net gain strategy must be implemented as approved under sub-paragraph (1).
Highway works
7
- (1) Construction of any new permanent or temporary means of access to a highway, or alteration of an existing means of access to a highway, or other works to alter the layout of a highway, must not commence until a plan for that access or other work has been submitted to and approved by the relevant highway authority.
- (2) No part of Work No. 4A may commence until written details for that Work No. have been submitted to and approved by the relevant highway authority.
- (3) No part of Work No. 4B may commence until written details for that Work No. have been submitted to and approved by the relevant planning authority in consultation with the relevant highway authority.
- (4) Any new permanent or temporary means of access to a highway, or alteration of an existing means of access to a highway, or other works to alter the layout of a highway must be constructed or altered in accordance with the details approved pursuant to sub-paragraph (1).
- (5) Work No. 4A must be constructed in accordance with the details approved pursuant to sub‑paragraph (2).
- (6) Work No. 4B must be constructed in accordance with the details approved pursuant to sub‑paragraph (3).
Drainage strategy
8
- (1) No part of Work No. 1, 1A, 1B, 2A, 2B, 4A, 4B, 6A, 6B and 9 may commence until written details of the drainage strategy for that Work No. has been submitted to and approved by the relevant planning authority.
- (2) The written details submitted for approval must be substantially in accordance with the outline drainage strategy.
- (3) The relevant planning authority must consult with Anglian Water in respect of any discharge to a public sewer before approving any drainage strategy submitted under sub-paragraph (1).
- (4) The relevant planning authority must consult with the Environment Agency before approving any drainage strategy submitted under sub-paragraph (1).
- (5) The drainage strategy must be implemented as approved under sub-paragraph (1).
Contamination and groundwater
9
- (1) No part of the authorised development may commence until a scheme (which may be included in the construction environmental management plan to be submitted under requirement 10) to deal with the contamination of any land (including groundwater) for that part which is likely to cause significant harm to persons or significant pollution of controlled waters or the environment has been submitted to and approved in writing by the relevant planning authority.
- (2) The scheme must include an investigation and assessment report, prepared by a specialist consultant, to identify the extent of any contamination and any remedial measures to be taken to render the land fit for its intended purpose, together with a management plan which sets out long-term measures with respect to any contaminants remaining on the site.
- (3) The relevant planning authority must consult with the Environment Agency before approving a scheme under sub-paragraph (1).
- (4) Any remedial measures must be carried out in accordance with the approved scheme.
Construction environmental management plan
10
- (1) No part of the authorised development may commence until a construction environmental management plan for that part has been submitted to and approved by the relevant planning authority.
- (2) The construction environmental management plan submitted for approval must be substantially in accordance with the outline construction environmental management plan.
- (3) The relevant planning authority must consult with the Environment Agency before approving the construction environmental management plan.
- (4) All construction works associated with the authorised development must be undertaken in accordance with the approved construction environmental management plan unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency.
Construction traffic management plan
11
- (1) No stage of the authorised development may commence until a construction traffic management plan for that stage has been submitted to and approved by the relevant planning authority in consultation with the highway authority. The construction traffic management plan must be substantially in accordance with the outline construction traffic management plan.
- (2) The construction traffic management plan must be implemented as approved throughout the construction of the authorised development unless otherwise agreed by the relevant planning authority in consultation with the highway authority.
Operational traffic management plan
12
- (1) Prior to the date of final commissioning, an operational traffic management plan must be submitted to the relevant planning authority for approval in consultation with the highway authority. The operational traffic management plan must be substantially in accordance with the outline operational traffic management plan.
- (2) The operational traffic management plan must be implemented as approved throughout the operation of the authorised development unless otherwise agreed by the relevant planning authority in consultation with the highway authority.
Flood emergency management plan
13
- (1) Prior to the date of final commissioning, a flood emergency management plan for Work Nos. 1, 1A, 1B, 2A, 2B and 9 must be submitted to the relevant planning authority for approval.
- (2) The flood emergency management plan submitted for approval must be substantially in accordance with the outline flood emergency management plan.
- (3) The relevant planning authority must consult with the Environment Agency and lead local flood authority before approving any flood emergency management plan submitted under sub-paragraph (1).
- (4) The flood emergency management plan submitted and approved under sub-paragraph (1) must be implemented as approved and remain in place throughout the operation of the authorised development unless otherwise agreed by the relevant planning authority in consultation with the Environment Agency and lead local flood authority.
Waste hierarchy scheme
14
- (1) Prior to the date of final commissioning, the undertaker must submit to the relevant planning authority for approval a scheme, which sets out arrangements for maintenance of the waste hierarchy and which aims to minimise recyclable and reusable waste received at the authorised development during the commissioning and operational period of the authorised development (the “waste hierarchy scheme”).
- (2) The waste hierarchy scheme must include details of—
- (a) operational procedures that seek to ensure that waste suitable for recycling and reuse is not received at the authorised development. These procedures are to be annually reviewed and, where practicable, improved;
- (b) a record of the tonnages of any waste identified by the undertaker prior to tipping into the waste bunker at the authorised development and rejected as it was identified as being suitable for recycling, reuse or both;
- (c) a record of tonnages of waste considered suitable for recycling, reuse or both that has been diverted further up the waste hierarchy by persons who also send waste to be processed at the authorised development, as far as practicable;
- (d) a record to be kept of how these procedures have been regularly reviewed (on an annual basis at a minimum), what changes were made, and how these have reduced the amount of waste potentially suitable for recycling and reuse being processed at the authorised development;
- (e) how waste transfer notes and weighbridge data detailing the sources of the residual waste will be collected and retained;
- (f) the types of waste and permitted EWC codes to be accepted at the authorised development as specified by the environmental permit;
- (g) how waste delivered to the authorised development will be checked to ensure compliance with the permitted EWC codes;
- (h) arrangements for ensuring that commercial suppliers deliver only those EWC codes which are permitted; and
- (i) records which are to be kept for the purposes of demonstrating compliance with the waste hierarchy scheme and for allowing inspection of such records by the relevant planning authority.
- (3) The relevant planning authority must consult with the Environment Agency before approving any scheme submitted under sub-paragraph (1).
- (4) The waste hierarchy scheme must be implemented as approved under sub-paragraph (1).
Operational travel plan
15
- (1) Prior to the date of final commissioning, an operational travel plan must be submitted to and approved by the relevant planning authority. The operational travel plan must set out measures to encourage staff working at Work No. 1, 1A, 1B, 2A and 2B to use sustainable modes of transport and must be substantially in accordance with the outline operational travel plan.
- (2) The operational travel plan must be implemented as approved under sub-paragraph (1).
Odour management plan
16
- (1) Prior to completion of commissioning of any part of Work No. 1, an odour management plan must be submitted to the relevant planning authority for approval. The odour management plan submitted for approval must be substantially in accordance with the outline odour management plan.
- (2) The relevant planning authority must consult with the Environment Agency before approving the odour management plan.
- (3) The odour management plan must be implemented as approved under sub-paragraph (1).
Fire prevention plan
17
- (1) Prior to the completion of commissioning of any part of Work No. 1, a fire prevention plan must be submitted to and approved by the relevant planning authority. The fire prevention plan submitted for approval must be substantially in accordance with the outline fire prevention plan.
- (2) The fire prevention plan must be implemented as approved under sub-paragraph (1).
Lighting strategy
18
- (1) Prior to the installation of any permanent lighting for the authorised development, a written scheme for the management and mitigation of artificial light emissions for that part of the authorised development must be submitted to and approved by the relevant planning authority. The lighting strategy submitted for approval must be substantially in accordance with the outline lighting strategy.
- (2) The written scheme for the management and mitigation of artificial light emissions must be implemented as approved under sub-paragraph (1).
Noise management
19
- (1) No part of Work No. 4A may commence until the residential use at plot numbers 11/4a and 11/4b shown on the land plans and described in the book of reference has ceased unless otherwise agreed by the relevant planning authority.
- (2) Plot numbers 11/4a and 11/4b shown on the land plans and described in the book of reference must not be used for residential purposes until the authorised development has been decommissioned in accordance with requirement 28 unless otherwise agreed by the relevant planning authority.
- (3) No part of Work No. 4A may commence until Work No. 10 has been constructed. Work No. 10 must be maintained until the authorised development has been decommissioned in accordance with requirement 28 unless otherwise agreed by the relevant planning authority.
- (4) Prior to the date of completion of commissioning of any part of Work No. 1, 1A, 2A, 2B and 9(a), an operational noise management plan for that part must be submitted to and approved by the relevant planning authority.
- (5) The operational noise management plan submitted for approval must be substantially in accordance with the outline operational noise management plan.
- (6) The relevant planning authority must consult with the Environment Agency before approving the operational noise management plan.
- (7) The operational noise management plan must be implemented as approved under sub‑paragraph (4).
Notice of start of commissioning and notice of date of final commissioning
20
- (1) Notice of the commencement of commissioning of Work No. 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is commenced.
- (2) Notice of the completion of commissioning of Work No. 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is completed.
Employment and skills strategy
21
- (1) No part of the authorised development may commence until an employment and skills strategy has been submitted to the relevant planning authority for approval. The employment and skills strategy submitted for approval must be substantially in accordance with the outline employment and skills strategy.
- (2) The employment and skills strategy must be implemented as approved under sub-paragraph (1).
Carbon capture and export readiness reserve space
22
- (1) Prior to the date of final commissioning, the undertaker must demonstrate to the relevant planning authority that it has constructed Work No. 1 in accordance with the carbon capture and export embedded design measures.
- (2) Following commencement of the authorised development and until such time as the authorised development is decommissioned, the undertaker must not, without the consent of the Secretary of State—
- (a) dispose of any interest in the carbon capture and export readiness reserve space; or
- (b) do anything, or allow anything to be done or to occur which may reasonably be expected to diminish the undertaker’s ability to prepare the carbon capture and export readiness reserve space for the installation and operation of carbon capture and export equipment within two years of such action or occurrence.
- (3) In this paragraph “export” means the removal of carbon from the authorised development and transporting it to a place of usage or sequestration to avoid its release to the atmosphere.
Carbon capture readiness monitoring report
23
- (1) The undertaker must make a report (“carbon capture and export readiness monitoring report”) to the Secretary of State—
- (a) on or before the date which is three months after the date of completion of commissioning of Work No. 1A; and
- (b) within one month of the second anniversary, and each subsequent even-numbered anniversary, of that date.
- (2) Each carbon capture and export readiness monitoring report must provide evidence that the undertaker has complied with Requirement 22—
- (a) in the case of the first carbon capture and export readiness monitoring report, since commencement of the authorised development; and
- (b) in the case of any subsequent report, since the making of the previous carbon capture and export readiness monitoring report,
and explain how the undertaker expects to continue to comply with Requirement 22 over the next two years.
- (3) Each carbon capture and export readiness monitoring report must state whether the undertaker considers the retrofit of carbon capture and export technology is feasible explaining the reasons for any such conclusion and whether any impediments could be overcome.
- (4) Each carbon capture and export readiness monitoring report must state, with reasons, whether the undertaker has decided to seek any additional regulatory clearances, or to modify any existing regulatory clearances, in respect of any carbon capture and export readiness proposals.
- (5) In this paragraph “export” means the removal of carbon from the authorised development and transporting it to a place of usage or sequestration to avoid its release to the atmosphere.
Community liaison manager
24
Prior to the date of final commissioning, the undertaker must notify the relevant planning authority of the name of the community liaison manager appointed and thereafter must keep the relevant planning authority up to date on any changes.
Combined heat and power
25
- (1) Prior to the date of final commissioning, the undertaker must demonstrate to the relevant planning authority that it has constructed Work No. 1 and Work No. 2 in accordance with the combined heat and power embedded design measures.
- (2) No later than the date that is 18 months after the date of final commissioning, the undertaker must submit to the relevant planning authority for its approval a report (“the CHP review”) updating the combined heat and power assessment.
- (3) The CHP review submitted must—
- (a) consider the opportunities that reasonably exist for the export of heat from Work No. 3, 3A and 3B at the time of submission of the CHP review; and
- (b) include a list of actions (if any) that the undertaker is reasonably and practicably able to take (without material additional cost to the undertaker) to increase the potential for the export of heat from Work No. 3, 3A and 3B.
- (4) The undertaker must take such actions as are included, within the timescales specified, in the approved CHP review.
- (5) The relevant planning authority must consult with the Environment Agency before approving any CHP review.
- (6) On each date (or the first date thereafter which is a working day) during the operation of Work No. 1 that is five years after the date on which it last submitted the CHP review or a revised CHP review to the relevant planning authority, the undertaker must submit to the relevant planning authority for its approval a revised CHP review.
- (7) Sub-paragraphs (3) to (5) apply in relation to a revised CHP review submitted under sub‑paragraph (6) in the same way as they apply in relation to the CHP review submitted under sub‑paragraph (7).
Air safety
26
- (1) The information specified in sub-paragraph (2), that is required by the Defence Geographic Centre of the Ministry of Defence to chart the authorised development for aviation purposes, must be submitted to the relevant planning authority and the Ministry of Defence before any part of the authorised development is commenced.
- (2) The information submitted to and approved under sub-paragraph (1) must include—
- (a) location of the authorised development;
- (b) date of commencement of construction;
- (c) anticipated date of completion of construction of tall structures including the chimneys;
- (d) height above ground level of tall structures including the chimneys;
- (e) maximum extension height of any construction equipment; and
- (f) details of aviation warning lighting to be fitted to the tall structures, which must include fitting the chimneys with an infra–red light fitted at the highest practicable point of the structure.
- (3) The aviation warning lighting details submitted under sub-paragraph (2)(f) must be implemented in full before the construction of the chimneys is complete unless otherwise agreed by the relevant planning authority in consultation with the Ministry of Defence.
- (4) At the earliest opportunity prior to the date of completion of the construction of the chimneys, the anticipated date of construction completion must be submitted to the relevant planning authority and provided in copy to the Ministry of Defence.
- (5) All details submitted to and approved under this requirement must be implemented as approved and maintained throughout (to the extent relevant) the construction of the authorised development and the operation of the authorised development unless otherwise agreed by the relevant planning authority in consultation with the Ministry of Defence.
Local air quality monitoring strategy
27
- (1) Prior to the commencement of the authorised development, a local air quality monitoring strategy must be submitted to the relevant planning authority for approval. The local air quality monitoring strategy submitted for approval must be substantially in accordance with the outline local air quality monitoring strategy.
- (2) The local air quality monitoring strategy must be implemented as approved under sub‑paragraph (1).
Decommissioning
28
- (1) Within 24 months of the permanent cessation of the commercial operation of the authorised development, the undertaker must submit to the relevant planning authority for its approval a decommissioning plan for the authorised development, including a timetable for its implementation.
- (2) The decommissioning plan submitted for approval must be substantially in accordance with the outline decommissioning plan.
- (3) The plan submitted to and approved under sub-paragraph (1) must be implemented as approved unless otherwise agreed with the relevant planning authority.
Origin of waste
29
- (1) Not less than 17.5% of the waste processed at the authorised development per operational year must originate from within Waste Area 1 unless otherwise agreed by the relevant planning authority. Waste originating outside of Waste Area 1 and then transported to a waste loading point located in Waste Area 1 is not considered to have originated in Waste Area 1.
- (2) Not less than 80% of the waste processed at the authorised development per operational year must originate from Waste Area 1 and Waste Area 2 unless otherwise agreed by the relevant planning authority. Subject to sub-paragraph (1), waste transported into Waste Area 2 to a waste loading point is considered to have originated in Waste Area 2.
- (3) No more than 20% of the waste processed at the authorised development per operational year must originate from outside of Waste Area 1 and Waste Area 2 unless otherwise agreed by the relevant planning authority. Waste sent direct to the authorised development from a location that is not located in either Waste Area 1 or Waste Area 2 will be deemed to originate from outside of Waste Area 2.
- (4) The maximum tonnage of waste received from any one waste planning authority’s administrative area within Waste Area 2 must not exceed 312,800 tonnes in any operational year unless otherwise agreed by the relevant planning authority.
- (5) From the date of final commissioning of the authorised development until the authorised development has been decommissioned in accordance with requirement 28 (unless otherwise agreed by the relevant planning authority), the undertaker must maintain a written record, retained at the authorised development, of the quantities and origin of the waste treated by the authorised development for each operational year.
- (6) From the date of final commissioning until the authorised development has been decommissioned in accordance with requirement 28 (unless otherwise agreed by the relevant planning authority), on or prior to 1 February each year, the undertaker must provide to the relevant planning authority a report for the preceding operational year (the “Waste Catchment Report”). The Waste Catchment Report must identify—
- (a) the waste throughput of the authorised development including the total tonnage of waste processed at the authorised development for the operational year;
- (b) waste catchment including as far as it is reasonably practicable to audit, the waste area for each waste loading point for waste processed at the authorised development for the operational year, separately totalling tonnages received from waste area 1, waste area 2 and outside of waste area 2; and
- (c) the total annual tonnage processed at the authorised development from each waste planning authority for the operational year.
- (7) The relevant planning authority can request an interim Waste Catchment Report at any time for the preceding 12 month period. The undertaker must submit an interim Waste Catchment Report to the relevant planning authority within 6 weeks of receiving the request. The interim Waste Catchment Report must cover the 12 month period ending on the last day of the month the written request was made by the relevant planning authority to the undertaker unless otherwise agreed by the relevant planning authority.
- (8) In this paragraph—
- “operational year” means the period from 1 January to 31 December, inclusive;
- “throughput” means the tonnage of waste received at the authorised development;
- “waste area 1” means a 75 kilometre radius from the point that has grid reference N307892.6931 and E545496.9373 and shown on the waste area plan;
- “waste area 2” means the area shown on the waste area plan; and
- “waste loading point” means the location where the waste is loaded onto a vehicle prior to being sent directly to the authorised development.
- (9) In sub-paragraph (6)(b) “waste area” means the areas or locations for each waste loading point, disaggregated to the smallest administrative area practicable, including but not limited to county, unitary, district, borough or postcode area.
Amendments to approved details
30
- (1) With respect to the documents certified under article 42 (certification of plans etc.), the parameters specified in Table 11 of Schedule 14 (maximum and minimum design parameters) and any other plans, details or schemes which require approval by the relevant planning authority pursuant to any requirement (together “Approved Documents, Plans, Parameters, Details or Schemes”), the undertaker may submit to the relevant planning authority for approval any amendments to the Approved Documents, Plans, Parameters, Details or Schemes and following any such approval by the relevant planning authority the Approved Documents, Plans, Parameters, Details or Schemes are to be taken to include the amendments approved by the relevant planning authority pursuant to this paragraph.
- (2) Approval under sub-paragraph (1) for the amendments to Approved Documents, Plans, Parameters, Details or Schemes must not be given except where it has been demonstrated to the satisfaction of the relevant planning authority that the subject matter of the approval sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
SCHEDULE 3 — STREETS SUBJECT TO STREET WORKS
| (1)Area | (2)Streets subject to street works | (3)Description of the street works |
|---|---|---|
| In the County of Cambridgeshire and the County of Norfolk | A47 (public highway) | Street works to the extent of the A47 coloured light purple on the access and public rights of way plan |
| In the County of Cambridgeshire | Algores Way (private street) | Street works to the extent of Algores Way coloured yellow on the access and public rights of way plan |
| In the County of Norfolk | Broadend Road (public highway) | Street works to the extent of Broadend Road coloured light green on the access and public rights of way plan |
| In the County of Cambridgeshire | Cromwell Road (public highway) | Street works to the extent of Cromwell Road coloured pink on the access and public rights of way plan |
| In the County of Cambridgeshire | Cromwell Road (private street) | Street works to the extent of Cromwell Road coloured pink on the access and public rights of way plan |
| In the County of Norfolk | Elm High Road (public highway) | Street works to the extent of Elm High Road coloured turquoise on the access and public rights of way plan |
| In the County of Cambridgeshire | New Drove (public highway) | Street works to the extent of New Drove coloured dark green on the access and public rights of way plan |
| In the County of Cambridgeshire | New Bridge Lane (public highway) | Street works to the extent of New Bridge Lane coloured blue on the access and public rights of way plan |
| In the County of Cambridgeshire | New Bridge Lane (private street) | Street works to the extent of New Bridge Lane coloured blue on the access and public rights of way plan |
| In the County of Cambridgeshire | Salters Way (public highway) | Street works to the extent of Salters Way coloured dark purple on the access and public rights of way plan |
| In the County of Cambridgeshire | Weasenham Lane (public highway) | Street works to the extent of Weasenham Lane coloured red on the access and public rights of way plan |
SCHEDULE 4 — STREETS SUBJECT TO PERMANENT ALTERATION OF LAYOUT
| (1)Area | (2)Streets subject to alteration of layout | (3)Description of alteration |
|---|---|---|
| In the County of Cambridgeshire | Algores Way (private street) | Permanent alteration of layout to the extent of Algores Way shown as Work No. 4B on the works plan and located within that area coloured yellow on the access and public rights of way plan including carriageway and footway widening and highway alteration works |
| In the County of Cambridgeshire | Cromwell Road (public highway) | Permanent alteration of layout to the extent of Cromwell Road coloured pink on the access and public rights of way plan including carriageway and footway widening and highway alteration works |
| In the County of Cambridgeshire | Cromwell Road (private street) | Permanent alteration of layout to the extent of Cromwell Road coloured pink on the access and public rights of way plan including carriageway and footway widening and highway alteration works |
| In the County of Cambridgeshire | New Bridge Lane (public highway) | Permanent alteration of layout to the extent of New Bridge Lane coloured blue on the access and public rights of way plan including carriageway and footway widening and highway alteration works |
| In the County of Cambridgeshire | New Bridge Lane (private street) | Permanent alteration of layout to the extent of New Bridge Lane coloured blue on the access and public rights of way plan including carriageway and footway widening and highway alteration works |
| In the County of Cambridgeshire | Salters Way (public highway) | Permanent alteration of layout to the extent of Salters Way coloured dark purple on the access and public rights of way plan including carriageway and footway widening and highway alteration works |
SCHEDULE 5 — STREETS SUBJECT TO TEMPORARY ALTERATION OF LAYOUT
| (1)Area | (2)Street subject to alteration of layout | (3)Description of alteration |
|---|---|---|
| In the County of Cambridgeshire and the County of Norfolk | A47 (public highway) | Temporary alteration of layout to the extent of the A47 coloured light purple on the access and public rights of way plan |
| In the County of Norfolk | Broadend Road (public highway) | Temporary alteration of layout to the extent of Broadend Road coloured light green on the access and public rights of way plan |
| In the County of Norfolk | Elm High Road (public highway) | Temporary alteration of layout to the extent of Elm High Road coloured turquoise on the access and public rights of way plan |
| In the County of Cambridgeshire | New Bridge Lane (public highway) | Temporary alteration of layout to the extent of New Bridge Lane coloured blue on the access and public rights of way plan |
| In the County of Cambridgeshire | New Drove (public highway) | Temporary alteration of layout to the extent of New Drove coloured dark green on the access and public rights of way plan |
| In the County of Cambridgeshire | Weasenham Lane (public highway) | Temporary alteration of the layout to the extent of Weasenham Lane coloured red on the access and public rights of way plan |
SCHEDULE 6 — ACCESS
PART 1 — THOSE PARTS OF THE ACCESS TO BE MAINTAINED AT THE PUBLIC EXPENSE
| (1)Location | (2)Street | (3)Description of relevant part of access |
|---|---|---|
| In the County of Cambridgeshire | Weasenham Lane (public highway) | Access to the area shown coloured orange and marked A1 on sheet 2 of the access and public rights of way plan to the extent that such access is or will be located within the public highway |
| In the County of Cambridgeshire | Weasenham Lane (public highway) | Access to the area shown coloured orange and marked A2 on sheet 2 of the access and public rights of way plan to the extent that such access is or will be located within the public highway |
| In the County of Cambridgeshire | New Bridge Lane (public highway) | Access to the area shown coloured orange and marked A8 on sheet 1 of the access and public rights of way plan to the extent that such access is or will be located within the public highway |
| In the County of Cambridgeshire | New Bridge Lane (public highway) | Access to the area shown coloured orange and marked A6 on sheet 1 of the access and public rights of way plan to the extent that such access is or will be located within the public highway. |
| In the County of Cambridgeshire | New Bridge Lane (public highway) | Access to the area shown coloured orange and marked A7 on sheet 1 of the access and public rights of way plan to the extent that such access is or will be located within the public highway |
| In the County of Cambridgeshire | New Drove (public highway) | Access to the area shown coloured orange and marked A10 on sheet 1 of the access and public rights of way plan to the extent that such access is or will be located within the public highway |
| In the County of Cambridgeshire | New Bridge Lane (public highway) | Access to the area shown coloured orange and marked A11 on sheet 1 of the access and public rights of way plan to the extent that such access is or will be located within the public highway |
| In the County of Cambridgeshire | Broadend Road (public highway) | Access to the area shown coloured orange and marked A12 on sheet 4 of the access and public rights of way plan to the extent that such access is or will be located within the public highway |
PART 2 — THOSE PARTS OF THE ACCESS TO BE MAINTAINED BY THE STREET AUTHORITY
| (1)Location | (2)Street | (3)Description of relevant part of access |
|---|---|---|
| In the County of Cambridgeshire | Algores Way (private street) | Access to the area shown coloured yellow between the area shown coloured orange and marked A3 and the area shown coloured orange and marked A5 on sheet 1 of the access and public rights of way plan to the extent that such access is or will be located outside the public highway |
| In the County of Cambridgeshire | Algores Way (private street) | Access to the area shown coloured orange and marked A4 on sheet 1 of the access and public rights of way plan |
| In the County of Cambridgeshire | New Bridge Lane (public highway) | Access to the area shown coloured orange and marked A6 on sheet 1 of the access and public rights of way plan to the extent that such access is or will be located outside of the public highway |
| In the County of Cambridgeshire | New Bridge Lane (public highway) | Access to the area shown coloured orange and marked A7 on sheet 1 of the access and public rights of way plan to the extent that such access is or will be located outside of the public highway |
| In the County of Cambridgeshire | New Bridge Lane (public highway) | Access to the area shown coloured orange and marked A8 on sheet 1 of the access and public rights of way plan to the extent that such access is or will be located outside of the public highway |
PART 3 — THOSE WORKS TO RESTORE THE TEMPORARY ACCESSES WHICH WILL BE MAINTAINED BY THE STREET AUTHORITY
| (1)Location | (2)Street | (3)Description of relevant part of access |
|---|---|---|
| In the County of Cambridgeshire | Weasenham Lane (public highway) | Access to the area shown coloured orange and marked A1 on sheet 2 of the access and public rights of way plan to the extent that such access is or will be located outside of the public highway |
| In the County of Cambridgeshire | Weasenham Lane (public highway) | Access to the area shown coloured orange and marked A2 on sheet 2 of the access and public rights of way plan to the extent that such access is or will be located outside of the public highway |
| In the County of Cambridgeshire | New Bridge Lane (public highway) | Access to the area shown coloured orange and marked A9 on sheet 1 of the access and public rights of way plan to the extent that such access is or will be located outside of the public highway |
| In the County of Cambridgeshire | New Drove (public highway) | Access to the area shown coloured orange and marked A10 on sheet 1 of the access and public rights of way plan to the extent that such access is or will be located outside of the public highway |
| In the County of Cambridgeshire | New Bridge Lane (public highway) | Access to the area shown coloured orange and marked A11 on sheet 1 of the access and public rights of way plan to the extent that such access is or will be located outside of the public highway |
| In the County of Norfolk | Broadend Road (public highway) | Access to the area shown coloured orange and marked A12 on sheet 4 of the access and public rights of way plan to the extent that such access is or will be located outside of the public highway |
SCHEDULE 7 — TEMPORARY PROHIBITION OR RESTRICTION OF THE USE OF STREETS OR PUBLIC RIGHTS OF WAY
| (1)Area | (2)Street subject to temporary prohibition or restriction of use | (3)Extent of temporary prohibition or restriction of use of streets |
|---|---|---|
| In the County of Cambridgeshire and the County of Norfolk | A47 (public highway) | Temporary stopping up of the extent of the A47 shown coloured light purple and hatched blue on the access and public rights of way plan |
| In the County of Cambridgeshire | Algores Way (private street) | Temporary stopping up of the extent of Algores Way shown coloured yellow and hatched blue on the access and public rights of way plan |
| In the County of Norfolk | Broadend Road (public highway) | Temporary stopping up of the extent of Broadend Road shown coloured light green and hatched blue on the access and public rights of way plan |
| In the County of Cambridgeshire | Cromwell Road (public highway) | Temporary stopping up of the extent of Cromwell Road shown coloured pink and hatched blue on the access and public rights of way plan |
| In the County of Cambridgeshire | Cromwell Road (private street) | Temporary stopping up of the extent of Cromwell Road shown coloured pink and hatched blue on the access and public rights of way plan |
| In the County of Norfolk | Elm High Road (public highway) | Temporary stopping up of the extent of Elm High Road shown coloured turquoise and hatched blue on the access and public rights of way plan |
| In the County of Cambridgeshire | New Drove (public highway) | Temporary stopping up of the extent of New Drove shown coloured dark green and hatched blue on the access and public rights of way plan |
| In the County of Cambridgeshire | New Bridge Lane (public highway) | Temporary stopping up of the extent of New Bridge Lane shown coloured blue and hatched blue on the access and public rights of way plan |
| In the County of Cambridgeshire | New Bridge Lane (private street) | Temporary stopping up of the extent of New Bridge Lane shown coloured blue and hatched blue on the access and public rights of way plan |
| In the County of Cambridgeshire | Salters Way (public highway) | Temporary stopping up of the extent of Salters way shown coloured dark purple and hatched blue on the access and public rights of way plan |
| In the County of Cambridgeshire | Weasenham Lane (public highway) | Temporary stopping up of the extent of Weasenham Lane shown coloured red and hatched blue on the access and public rights of way plan |
SCHEDULE 8 — LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.