The Medworth Energy from Waste Combined Heat and Power Facility Order 2024
- (5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan instead of the plan previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.
- (6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case must give to Anglian Water notice as soon as is reasonably practicable and a plan of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances, using its reasonable endeavours to keep the impact of those emergency works on Anglian Water’s apparatus, on the operation of its water and sewerage network and on end-users of the services Anglian Water provides to a minimum.
- (7) For the purposes of sub-paragraph (1) and without prejudice to the generality of the principles set out in that sub-paragraph, works are deemed to be in land near Anglian Water’s apparatus (where it is a pipe) if those works fall within the following distances measured from the medial line of such apparatus—
- (a) 4 metres where the diameter of the pipe is less than 250 millimetres;
- (b) 5 metres where the diameter of the pipe is between 250 and 400 millimetres, and
- (c) a distance to be agreed on a case by case basis and before the submission of the plan under sub-paragraph (1) is submitted where the diameter of the pipe exceeds 400 millimetres.
Expenses and costs
86
- (1) Subject to the following provisions of this paragraph, the undertaker must repay to Anglian Water all expenses reasonably incurred by Anglian Water in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to in this Part of this Schedule.
- (2) There must be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule and which is not re-used as part of the alternative apparatus that value being calculated after removal.
- (3) If in accordance with the provisions of this Part of this Schedule—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 46 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to Anglian Water by virtue of sub‑paragraph (1) must be reduced by the amount of that excess.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
- (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
87
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works referred to in paragraphs 81 or 83(2), or by reason of any subsidence resulting from such development or works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of Anglian Water, or there is any interruption in any service provided, or in the supply of any goods, by Anglian Water, the undertaker must—
- (a) bear and pay the cost reasonably incurred by Anglian Water in making good such damage or restoring the supply; and
- (b) make reasonable compensation to Anglian Water for any other expenses, loss, damages, penalty or costs incurred by Anglian Water,
by reason or in consequence of any such damage or interruption.
- (2) The fact that any act or thing may have been done by Anglian Water on behalf of the undertaker or in accordance with a plan approved by Anglian Water or in accordance with any requirement of Anglian Water or under its supervision does not, subject to sub-paragraph (3), excuse the undertaker from liability under the provisions of sub-paragraph (1) unless Anglian Water fails to carry out and execute the works properly with due care and attention and in a skilful and professional like manner or in a manner that does not accord with the approved plan.
- (3) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the unlawful or unreasonable act, neglect or default of Anglian Water, its officers, servants, contractors or agents.
- (4) Anglian Water must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made, without the consent of the undertaker (such consent not to be unreasonably withheld or delayed) who, if withholding such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
Cooperation
88
Where in consequence of the proposed construction of any of the authorised development, the undertaker or Anglian Water requires the removal of apparatus under paragraph 83(2) or Anglian Water makes requirements for the protection or alteration of apparatus under paragraph 85, the undertaker must use all reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of Anglian Water’s undertaking, using existing processes where requested by Anglian Water, provided it is appropriate to do so, and Anglian Water must use all reasonable endeavours to co-operate with the undertaker for that purpose.
89
Where the undertaker identifies any apparatus which may belong to or be maintainable by Anglian Water but which does not appear on any statutory map kept for the purpose by Anglian Water, it shall inform Anglian Water of the existence and location of the apparatus as soon as reasonably practicable.
90
Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and Anglian Water in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
91
The undertaker and Anglian Water may by written agreement substitute any period of time for those periods set out in this Part of this Schedule.
PART 8 — FOR THE PROTECTION OF RAILWAY INTERESTS
92
The provisions of this Part of this Schedule have effect, unless otherwise agreed in writing between the undertaker and Network Rail and, in the case of paragraph 106 of this Part of this Schedule any other person on whom rights or obligations are conferred by that paragraph.
93
In this Part of this Schedule—
- “asset protection agreement” means an agreement to regulate the construction and maintenance of the specified work in a form prescribed from time to time by Network Rail;
- “construction” includes execution, placing, alteration and reconstruction and “construct” and “constructed” have corresponding meanings;
- “the engineer” means an engineer appointed by Network Rail for the purposes of this Order;
- “network licence” means the network licence, as the same is amended from time to time, granted to Network Rail Infrastructure Limited by the Secretary of State in exercise of their powers under section 8 (licences) of the Railways Act 1993;
- “Network Rail” means Network Rail Infrastructure Limited (company number 02904587, whose registered office is at Waterloo General Office, London, SE1 8SW) and any associated company of Network Rail Infrastructure Limited which holds property for railway purposes, and for the purpose of this definition “associated company” means any company which is (within the meaning of section 1159 of the Companies Act 2006) the holding company of Network Rail Infrastructure Limited, a subsidiary of Network Rail Infrastructure Limited or another subsidiary of the holding company of Network Rail Infrastructure Limited and any successor to Network Rail Infrastructure Limited’s railway undertaking;
- “plans” includes sections, designs, design data, software, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of railway property;
- “railway operational procedures” means procedures specified under any access agreement (as defined in the Railways Act 1993) or station lease;
- “railway property” means any railway belonging to Network Rail and—any station, land, works, apparatus and equipment belonging to Network Rail or connected with any such railway; andany easement or other property interest held or used by Network Rail or a tenant or licencee of Network Rail for the purposes of such railway or works, apparatus or equipment;
- “regulatory consents” means any consent or approval required under—the Railways Act 1993;the network licence; and/orany other relevant statutory or regulatory provisions;by either the Office of Rail and Road or the Secretary of State for Transport or any other competent body including change procedures and any other consents, approvals of any access or beneficiary that may be required in relation to the authorised development;
- “specified work” means so much of any of the authorised development as is situated upon, across, under, over or within 15 metres of, or may in any way adversely affect, railway property and, for the avoidance of doubt, includes the maintenance of such works under the powers conferred by article 4 (maintenance of authorised development) in respect of such works.
94
- (1) Where under this Part of this Schedule Network Rail is required to give its consent or approval in respect of any matter, that consent or approval is subject to the condition that Network Rail complies with any relevant railway operational procedures and any obligations under its network licence or under statute.
- (2) In so far as any specified work or the acquisition or use of railway property is or may be subject to railway operational procedures, Network Rail must—
- (a) co-operate with the undertaker with a view to avoiding undue delay and securing conformity as between any plans approved by the engineer and requirements emanating from those procedures; and
- (b) use its reasonable endeavours to avoid any conflict arising between the application of those procedures and the proper implementation of the authorised development pursuant to this Order.
95
- (1) The undertaker must not exercise the powers conferred by—
- (a) article 3 (development consent granted by the Order);
- (b) article 4 (maintenance of authorised development);
- (c) article 18 (discharge of water);
- (d) article 19 (authority to survey and investigate the land);
- (e) article 21 (felling or lopping of trees);
- (f) article 23 (compulsory acquisition of land);
- (g) article 25 (compulsory acquisition of rights and imposition of restrictive covenants);
- (h) article 26 (acquisition of subsoil only);
- (i) article 27 (private rights);
- (j) article 28 (power to override easements and other rights);
- (k) article 32 (temporary use of land for the construction of the authorised development);
- (l) article 33 (temporary use of land for maintaining the authorised development);
- (m) article 34 (statutory undertakers);
- (n) the powers conferred by section 11(3) (power of entry) of the 1965 Act;
- (o) the powers conferred by section 203 (power to override easements and rights) of the Housing and Planning Act 2016;
- (p) the powers conferred by section 172 (right to enter and survey land) of the Housing and Planning Act 2016;
- (q) any powers under in respect of the temporary possession of land under the Neighbourhood Planning Act 2017;
in respect of any railway property unless the exercise of such powers is with the consent of Network Rail.
- (2) The undertaker must not in the exercise of the powers conferred by this Order prevent pedestrian or vehicular access to any railway property, unless preventing such access is with the consent of Network Rail.
- (3) The undertaker must not exercise the powers conferred by sections 271 or 272 of the 1990 Act, article 34 (statutory undertakers), article 28 (power to override easements and other rights) or article 27 (private rights), in relation to any right of access of Network Rail to railway property, but such right of access may be diverted with the consent of Network Rail.
- (4) The undertaker must not under the powers of this Order acquire or use or acquire new rights over, or seek to impose any restrictive covenants over, any railway property, or extinguish any existing rights of Network Rail in respect of any third party property, except with the consent of Network Rail.
- (5) The undertaker must not under the powers of this Order do anything which would result in railway property being incapable of being used or maintained or which would affect the safe running of trains on the railway.
- (6) Where Network Rail is asked to give its consent pursuant to this paragraph, such consent must not be unreasonably withheld but may be given subject to reasonable conditions but it shall never be unreasonable to withhold consent for reasons of operational or railway safety (such matters to be in Network Rail’s absolute discretion).
- (7) The undertaker must enter into an asset protection agreement prior to the carrying out of any specified work.
96
- (1) The undertaker must before commencing construction of any specified work supply to Network Rail proper and sufficient plans of that work for the reasonable approval of the engineer and the specified work must not be commenced except in accordance with such plans as have been approved in writing by the engineer or settled by arbitration.
- (2) The approval of the engineer under sub-paragraph (1) must not be unreasonably withheld, and if by the end of the period of 28 days beginning with the date on which such plans have been supplied to Network Rail the engineer has not intimated their disapproval of those plans and the grounds of such disapproval the undertaker may serve upon the engineer written notice requiring the engineer to intimate approval or disapproval within a further period of 28 days beginning with the date upon which the engineer receives written notice from the undertaker. If by the expiry of the further 28 days the engineer has not intimated approval or disapproval, the engineer shall be deemed to have approved the plans as submitted.
- (3) If by the end of the period of 28 days beginning with the date on which written notice was served upon the engineer under sub-paragraph (2), Network Rail gives notice to the undertaker that Network Rail desires itself to construct any part of a specified work which in the opinion of the engineer will or may affect the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker desires such part of the specified work to be constructed, Network Rail must construct it without unnecessary delay on behalf of and to the reasonable satisfaction of the undertaker in accordance with the plans approved or deemed to be approved or settled under this paragraph, and under the supervision (where appropriate and if given) of the undertaker.
- (4) When signifying their approval of the plans the engineer may specify any protective works (whether temporary or permanent) which in the engineer’s opinion should be carried out before the commencement of the construction of a specified work to ensure the safety or stability of railway property or the continuation of safe and efficient operation of the railways of Network Rail or the services of operators using the same (including any relocation de-commissioning and removal of works, apparatus and equipment necessitated by a specified work and the comfort and safety of passengers who may be affected by the specified works), and such protective works as may be reasonably necessary for those purposes must be constructed by Network Rail or by the undertaker, if Network Rail so desires, and such protective works must be carried out at the expense of the undertaker in either case without unnecessary delay and the undertaker must not commence the construction of the specified works until the engineer has notified the undertaker that the protective works have been completed to their reasonable satisfaction.
97
- (1) Any specified work and any protective works to be constructed by virtue of paragraph 96(4) must, when commenced, be constructed—
- (a) without unnecessary delay in accordance with the plans approved or deemed to have been approved or settled under paragraph 96;
- (b) under the supervision (where appropriate and if given) and to the reasonable satisfaction of the engineer;
- (c) in such manner as to cause as little damage as is possible to railway property; and
- (d) so far as is reasonably practicable, so as not to interfere with or obstruct the free, uninterrupted and safe use of any railway of Network Rail or the traffic thereon and the use by passengers of railway property.
- (2) If any damage to railway property or any such interference or obstruction shall be caused by the carrying out of, or in consequence of the construction of a specified work, the undertaker must, notwithstanding any such approval, make good such damage and must pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may sustain by reason of any such damage, interference or obstruction.
- (3) Nothing in this Part of this Schedule imposes any liability on the undertaker with respect to any damage, costs, expenses or loss attributable to the negligence of Network Rail or its servants, contractors or agents or any liability on Network Rail with respect of any damage, costs, expenses or loss attributable to the negligence of the undertaker or its servants, contractors or agents.
98
The undertaker must—
- (a) at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and
- (b) supply the engineer with all such information as they may reasonably require with regard to a specified work or the method of constructing it.
99
Network Rail must at all times afford reasonable facilities to the undertaker and its agents for access to any works carried out by Network Rail under this Part of this Schedule during their construction and must supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them.
100
- (1) If any permanent or temporary alterations or additions to railway property are reasonably necessary in consequence of the construction or completion of a specified work in order to ensure the safety of railway property or the continued safe operation of the railway of Network Rail, such alterations and additions may be carried out by Network Rail and if Network Rail gives to the undertaker 56 days’ notice (or in the event of an emergency or safety critical issue such notice as is reasonable in the circumstances) of its intention to carry out such alterations or additions (which must be specified in the notice), the undertaker must pay to Network Rail the reasonable cost of those alterations or additions including, in respect of any such alterations and additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by Network Rail in maintaining, working and, when necessary, renewing any such alterations or additions.
- (2) If during the construction of a specified work by the undertaker, Network Rail gives notice to the undertaker that Network Rail desires itself to construct that part of the specified work which in the opinion of the engineer is endangering the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker decides that part of the specified work is to be constructed, Network Rail must assume construction of that part of the specified work and the undertaker must, notwithstanding any such approval of a specified work under paragraph 96(3), pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may suffer by reason of the execution by Network Rail of that specified work.
- (3) The engineer must, in respect of the capitalised sums referred to in this paragraph and paragraph 101(a) provide such details of the formula by which those sums have been calculated as the undertaker may reasonably require.
- (4) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions a capitalised sum representing such saving must be set off against any sum payable by the undertaker to Network Rail under this paragraph.
101
The undertaker must repay to Network Rail all reasonable fees, costs, charges and expenses reasonably incurred by Network Rail—
- (a) in constructing any part of a specified work on behalf of the undertaker as provided by paragraph 96(3) or in constructing any protective works under the provisions of paragraph 96(4) including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;
- (b) in respect of the approval by the engineer of plans submitted by the undertaker and the supervision by the engineer of the construction of a specified work;
- (c) in respect of the employment or procurement of the services of any inspectors, signallers, watch-persons and other persons whom it shall be reasonably necessary to appoint for inspecting, signalling, watching and lighting railway property and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of a specified work;
- (d) in respect of any special traffic working resulting from any speed restrictions which may in the opinion of the engineer, require to be imposed by reason or in consequence of the construction or failure of a specified work or from the substitution or diversion of services which may be reasonably necessary for the same reason; and
- (e) in respect of any additional temporary lighting of railway property in the vicinity of the specified works, being lighting made reasonably necessary by reason or in consequence of the construction or failure of a specified work.
102
- (1) In this paragraph—
- “EMI” means, subject to sub-paragraph (2), electromagnetic interference with Network Rail apparatus generated by the operation of the authorised development where such interference is of a level which adversely affects the safe operation of Network Rail’s apparatus; and
- “Network Rail’s apparatus” means any lines, circuits, wires, apparatus or equipment (whether or not modified or installed as part of the authorised development) which are owned or used by Network Rail for the purpose of transmitting or receiving electrical energy or of radio, telegraphic, telephonic, electric, electronic or other like means of signalling or other communications.
- (2) This paragraph applies to EMI only to the extent that such EMI is not attributable to any change to Network Rail’s apparatus carried out after approval of plans under paragraph 96(1) for the relevant part of the authorised development giving rise to EMI (unless the undertaker has been given notice in writing before the approval of those plans of the intention to make such change).
- (3) Subject to sub-paragraph (5), the undertaker must in the design and construction of the authorised development take all measures necessary to prevent EMI and must establish with Network Rail (both parties acting reasonably) appropriate arrangements to verify their effectiveness.
- (4) In order to facilitate the undertaker’s compliance with sub-paragraph (3)—
- (a) the undertaker must consult with Network Rail as early as reasonably practicable to identify all Network Rail’s apparatus which may be at risk of EMI, and thereafter must continue to consult with Network Rail (both before and after formal submission of plans under paragraph 96(1)) in order to identify all potential causes of EMI and the measures required to eliminate them;
- (b) Network Rail must make available to the undertaker all information in the possession of Network Rail reasonably requested by the undertaker in respect of Network Rail’s apparatus identified pursuant to paragraph (a); and
- (c) Network Rail must allow the undertaker reasonable facilities for the inspection of Network Rail’s apparatus identified pursuant to paragraph (a).
- (5) In any case where it is established that EMI can only reasonably be prevented by modifications to Network Rail’s apparatus, Network Rail must not withhold its consent unreasonably to modifications of Network Rail’s apparatus, but the means of prevention and the method of their execution must be selected in the reasonable discretion of Network Rail, and in relation to such modifications paragraph 96(1) has effect subject to the sub-paragraph.
- (6) Prior to the commencement of operation of the authorised development the undertaker shall test the use of the authorised development in a manner that shall first have been agreed with Network Rail and if, notwithstanding any measures adopted pursuant to sub-paragraph (3), the testing of the authorised development causes EMI then the undertaker must immediately upon receipt of notification by Network Rail of such EMI either in writing or communicated orally (such oral communication to be confirmed in writing as soon as reasonably practicable after it has been issued) forthwith cease to use (or procure the cessation of use of) the undertaker’s apparatus causing such EMI until all measures necessary have been taken to remedy such EMI by way of modification to the source of such EMI or (in the circumstances, and subject to the consent, specified in sub-paragraph (5)) to Network Rail’s apparatus.
- (7) In the event of EMI having occurred—
- (a) the undertaker must afford reasonable facilities to Network Rail for access to the undertaker’s apparatus in the investigation of such EMI;
- (b) Network Rail must afford reasonable facilities to the undertaker for access to Network Rail’s apparatus in the investigation of such EMI;
- (c) Network Rail must make available to the undertaker any additional material information in its possession reasonably requested by the undertaker in respect of Network Rail’s apparatus or such EMI; and
- (d) the undertaker shall not allow the use or operation of the authorised development in a manner that has caused or will cause EMI until measures have been taken in accordance with this paragraph to prevent EMI occurring.
- (8) Where Network Rail approves modifications to Network Rail’s apparatus pursuant to sub-paragraphs (5) or (6)—
- (a) Network Rail must allow the undertaker reasonable facilities for the inspection of the relevant part of Network Rail’s apparatus;
- (b) any modifications to Network Rail’s apparatus approved pursuant to those sub-paragraphs must be carried out and completed by the undertaker in accordance with paragraph 97.
- (9) To the extent that it would not otherwise do so, the indemnity in paragraph 106(1) applies to the costs and expenses reasonably incurred or losses suffered by Network Rail through the implementation of the provisions of this paragraph (including costs incurred in connection with the consideration of proposals, approval of plans, supervision and inspection of works and facilitating access to Network Rail’s apparatus) or in consequence of any EMI to which sub-paragraph 97 applies.
- (10) For the purpose of paragraph 101(a) any modifications to Network Rail’s apparatus under this paragraph shall be deemed to be protective works referred to in that paragraph.
- (11) In relation to any dispute arising under this paragraph the reference in article 46 (arbitration) to the Institution of Civil Engineers shall be read as a reference to the Institution of Engineering and Technology.
103
If at any time after the completion of a specified work, not being a work vested in Network Rail, Network Rail gives notice to the undertaker informing it that the state of maintenance of any part of the specified work appears to be such as adversely affects the operation of railway property, the undertaker must, on receipt of such notice, take such steps as may be reasonably necessary to put that specified work in such state of maintenance as not adversely to affect railway property.
104
The undertaker must not provide any illumination or illuminated sign or signal on or in connection with a specified work in the vicinity of any railway belonging to Network Rail unless it has first consulted Network Rail and it must comply with Network Rail’s reasonable requirements for preventing confusion between such illumination or illuminated sign or signal and any railway signal or other light used for controlling, directing or securing the safety of traffic on the railway.
105
Any additional expenses which Network Rail may reasonably incur in altering, reconstructing or maintaining railway property under any powers existing at the making of this Order by reason of the existence of a specified work must, provided that 56 days’ previous notice of the commencement of such alteration, reconstruction or maintenance has been given to the undertaker, be repaid by the undertaker to Network Rail.
106
- (1) The undertaker must pay to Network Rail all reasonable costs, charges, damages and expenses not otherwise provided for in this Part of this Schedule (subject to article 45 (no double recovery)) which may be occasioned to or reasonably incurred by Network Rail—
- (a) by reason of the construction, maintenance or operation of a specified work or the failure thereof; or
- (b) by reason of any act or omission of the undertaker or of any person in its employ or of its contractors or others whilst engaged upon a specified work;
- (c) by reason of any act or omission of the undertaker or any person in its employ or of its contractors or others whilst accessing to or egressing from the authorised development;
- (d) in respect of any damage caused to or additional maintenance required to, railway property or any such interference or obstruction or delay to the operation of the railway as a result of access to or egress from the authorised development by the undertaker or any person in its employ or of its contractors or others;
- (e) in respect of costs incurred by Network Rail in complying with any railway operational procedures or obtaining any regulatory consents which procedures are required to be followed or consents obtained to facilitate the carrying out or operation of the authorised development;
and the undertaker must indemnify and keep indemnified Network Rail from and against all claims and demands arising out of or in connection with a specified work or any such failure, act or omission: and the fact that any act or thing may have been done by Network Rail on behalf of the undertaker or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under the engineer’s supervision shall not (if it was done without negligence on the part of Network Rail or of any person in its employ or of its contractors or agents) excuse the undertaker from any liability under the provisions of this sub-paragraph.
- (2) Network Rail must—
- (a) give the undertaker reasonable written notice of any such claims or demands;
- (b) not make any settlement or compromise of such a claim or demand without the prior consent of the undertaker; and
- (c) take such steps as are within its control and are reasonable in the circumstances to mitigate any liabilities relating to such claims or demands.
- (3) The sums payable by the undertaker under sub-paragraph (1) shall if relevant include a sum equivalent to the relevant costs.
- (4) Subject to the terms of any agreement between Network Rail and a train operator regarding the timing or method of payment of the relevant costs in respect of that train operator, Network Rail must promptly pay to each train operator the amount of any sums which Network Rail receives under sub-paragraph (3) which relates to the relevant costs of that train operator.
- (5) The obligation under sub-paragraph (3) to pay Network Rail the relevant costs shall, in the event of default, be enforceable directly by any train operator concerned to the extent that such sums would be payable to that operator pursuant to sub-paragraph (4).
- (6) In this paragraph—
- “the relevant costs” means the costs, losses and expenses (including loss of revenue) reasonably incurred by each train operator as a consequence of any specified work including but not limited to any restriction of the use of Network Rail’s railway network as a result of the construction, maintenance or failure of a specified work or any such act or omission as mentioned in sub-paragraph (1); and
- “train operator” means any person who is authorised to act as the operator of a train by a licence under section 8 of the Railways Act 1993.
107
Network Rail must, on receipt of a request from the undertaker, from time to time provide the undertaker free of charge with written estimates of the costs, charges, expenses and other liabilities for which the undertaker is or will become liable under this Part of this Schedule (including the amount of the relevant costs mentioned in paragraph 106) and with such information as may reasonably enable the undertaker to assess the reasonableness of any such estimate or claim made or to be made pursuant to this Part of this Schedule (including any claim relating to those relevant costs).
108
In the assessment of any sums payable to Network Rail under this Part of this Schedule there must not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Network Rail if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by the undertaker under this Part of this Schedule or increasing the sums so payable.
109
The undertaker and Network Rail may, subject in the case of Network Rail to compliance with the terms of its network licence, enter into, and carry into effect, agreements for the transfer to the undertaker of—
- (a) any railway property shown on the works and land plans and described in the book of reference;
- (b) any lands, works or other property held in connection with any such railway property; and
- (c) any rights and obligations (whether or not statutory) of Network Rail relating to any railway property or any lands, works or other property referred to in this paragraph.
110
Nothing in this Order, or in any enactment incorporated with or applied by this Order, prejudices or affects the operation of Part I of the Railways Act 1993.
111
The undertaker must give written notice to Network Rail if any application is proposed to be made by the undertaker for the Secretary of State’s consent, under article 8 (consent to transfer benefit of the Order) of this Order and any such notice must be given no later than 28 days before any such application is made and must describe or give (as appropriate)—
- (a) the nature of the application to be made;
- (b) the extent of the geographical area to which the application relates; and
- (c) the name and address of the person acting for the Secretary of State to whom the application is to be made.
112
The undertaker must no later than 28 days from the date that the plans submitted to and certified by the Secretary of State in accordance with article 42 (certification of plans etc.) are certified by the Secretary of State, provide a set of those plans to Network Rail in a format specified by Network Rail.
113
In relation to any dispute arising under this part of this Part of this Schedule (except for those disputes referred to in paragraph 102) the provisions of article 46 (arbitration) shall not apply and any such dispute, unless otherwise provided for, must be referred to and settled by a single arbitrator in accordance with the rules at Schedule 15 to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) to the President of the Institution of Civil Engineers.
PART 9 — FOR THE PROTECTION OF CAMBRIDGESHIRE COUNTY COUNCIL AS HIGHWAY AUTHORITY
114
- (1) The following provisions of this Part of this Schedule, unless otherwise agreed in writing between the undertaker and Cambridgeshire County Council, have effect.
- (2) In this Part of this Schedule—
- “highway” means any highway of which Cambridgeshire County Council is the highway authority;
- “plans” includes sections, designs, drawings, specifications, soil reports, staging proposals, programmes, calculations, methods of construction, risk assessments and details of the extent, timing and duration of any proposed occupation of any highway and “approved plans” means plans approved or deemed to be approved or settled by arbitration in accordance with the provisions of this Part of this Schedule; and
- “property of Cambridgeshire County Council” means any apparatus or street furniture of the highway authority affixed to or placed under any highway.
- “works” means so much of any part of the authorised development as forms part of or is intended to become a highway, or part of any such highway, or any work which could introduce water onto the highway or any work which is underneath or over the highway.
- (3) Wherever in this Part of this Schedule provision is made with respect to the approval or consent of Cambridgeshire County Council, that approval or consent must be in writing and subject to such reasonable terms and conditions as Cambridgeshire County Council may require.
- (4) In exercising the powers conferred by this Order in relation to any highway the undertaker must have regard to the potential disruption of traffic which may be caused and must seek to minimise such disruption so far as is reasonably practicable.
115
- (1) Before commencing the construction of, or the carrying out of any work which involves interference with a highway, the undertaker must submit to Cambridgeshire County Council for its approval plans relating thereto, and the works must not be carried out except in accordance with the plans submitted to, and approved by, Cambridgeshire County Council.
- (2) If within 28 days after the plans have been submitted Cambridgeshire County Council has not approved or disapproved them, it is deemed to have approved the plans as submitted provided that this sub-paragraph does not apply to any plans submitted for approval pursuant to requirement 5 of Schedule 2 where the time periods set out in Schedule 12 apply.
- (3) In the event of any disapproval of plans by Cambridgeshire County Council under sub‑paragraph (2), the undertaker shall re-submit the plans with modifications and, in that event, if Cambridgeshire County Council has not intimated its disapproval and the grounds of disapproval within 28 days of the plans being re-submitted, it is deemed to have approved them.
- (4) The undertaker must include in any submission made to Cambridgeshire County Council under sub-paragraph (1) or any re-submission under sub-paragraph (3), a statement that the deemed approval provisions of sub-paragraph (2) or sub-paragraph (3) apply, as the case may be, and if the submission fails to do so, the deemed approval provision is null and void.
- (5) Any officer of Cambridgeshire County Council duly appointed for the purpose of inspecting the works may at all reasonable times during the carrying out of work and following completion of the works, on giving to the undertaker such notice as may in the circumstances be reasonable, enter upon and inspect any part of the works authorised by this Order (and such inspection may include works to be uncovered as reasonably required by the officer at the cost of the undertaker) which—
- (a) is in, over or under any highway; or
- (b) which may affect any highway or any property of Cambridgeshire County Council,
during the carrying out of the work, and the undertaker must give to such officer all reasonable facilities for such inspection and shall ensure that the officer is accompanied by one of its contractors, agents or employees familiar with the works, if the officer is of the opinion that the construction of the work is attended with danger to any highway or to any property of Cambridgeshire County Council on or under any highway, the undertaker must adopt such measures and precautions as may be reasonably practicable for the purpose of preventing any damage or injury to the highway.
- (6) In the construction of any part of the said works under a highway no part of it shall, except with the consent of Cambridgeshire County Council, be so constructed as to interfere with the provision of proper means of drainage of the surface of the highway.
116
- (1) The undertaker must not alter, disturb or in any way interfere with any property of Cambridgeshire County Council on or under any highway, or the access thereto, without the consent of the Cambridgeshire County Council, and any alteration, diversion, replacement or reconstruction of any such property which may be necessary may be made by Cambridgeshire County Council or the undertaker as the Cambridgeshire County Council thinks fit, and the expense reasonably incurred by Cambridgeshire County Council in so doing must be repaid to Cambridgeshire County Council by the undertaker.
- (2) The undertaker must not under the powers conferred by or under this Order without the consent of Cambridgeshire County Council, acquire or enter upon, take or use whether temporarily or permanently or acquire any new rights over any part of any highway, including subsoil beneath the surface of any highway.
- (3) If within 28 days after a request for consent has been submitted Cambridgeshire County Council has not given or refused such consent, it is deemed to have consented to the request as submitted provided that the undertaker includes in any such request for consent a statement confirming that the deemed consent provisions this paragraph apply to such request and if such request fails to do so, the deemed consent provision of this paragraph is null and void.
117
- (1) Where any part of any highway has been broken up or disturbed by the undertaker, the undertaker must make good the subsoil, foundations and surface of that part of the highway to the reasonable satisfaction of Cambridgeshire County Council and must maintain the same to the reasonable satisfaction of Cambridgeshire County Council for such time as may reasonably be required for the permanent reinstatement of the highway.
- (2) The reinstatement of that part of the highway must be carried out by the undertaker to the reasonable satisfaction of Cambridgeshire County Council in accordance with such requirements as to specification of material and standards of workmanship as may be prescribed for equivalent reinstatement work by regulations made under section 71 of the 1991 Act.
118
If any damage to any highway or any property of Cambridgeshire County Council on or under any highway is caused by, or results from, the construction of any work authorised by this Order or any act or omission of the undertaker, its contractors, agents or employees whilst engaged upon such work, the undertaker must, in the case of damage to a highway, make good such damage to the reasonable satisfaction of Cambridgeshire County Council and, where the undertaker does not make good, or in the case of damage to property of Cambridgeshire County Council, the undertaker must pay reasonable compensation to Cambridgeshire County Council for such damage.
119
The fact that any act or thing may have been done in accordance with plans approved by Cambridgeshire County Council does not (if it was not attributable to the act, neglect or default of Cambridgeshire County Council or of any person in its employment or its contractors or agents) exonerate the undertaker from any liability, or affect any claim for damages, under this Part or otherwise.
120
Cambridgeshire County Council must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which paragraph 118 applies. If requested to do so by the undertaker, Cambridgeshire County Council must provide an explanation of how the claim has been minimised. The undertaker is only liable under paragraph 118 for claims reasonably incurred by Cambridgeshire County Council.
121
On completion of the works the undertaker must seek written certification from Cambridgeshire County Council that the works are acceptable and relevant drawings and new highway asset information shall be provided to Cambridgeshire County Council as part of the undertaker’s request for certification. Cambridgeshire County Council shall only resume its maintenance responsibilities for the affected highways once certification under this paragraph has been issued.
122
- (1) Cambridgeshire County Council must not unreasonably withhold or delay the issue of a written certification under paragraph 121. Subject to sub-paragraphs (2) and (3), if Cambridgeshire County Council has not given or refused such written certification within 28 days, it is deemed to have issued a written certification provided that the undertaker includes in any such request for certification a statement confirming that the deemed certification provisions this paragraph apply to such request and if such request fails to do so, the deemed certification provision of this paragraph is null and void.
- (2) Any officer of Cambridgeshire County Council duly appointed for the purpose of issuing a written certification under sub-paragraph (1) may at all reasonable times and on reasonable notice during the 28 day period enter upon and inspect any part of the completed works.
- (3) If further information is requested by Cambridgeshire County Council, the 28 day period to issue a written certificate in accordance with sub-paragraph (1) will recommence starting on the date that such further information has been submitted by the undertaker to Cambridgeshire County Council.
123
On receipt of certification that completed works are acceptable under paragraph 121 above unlocking devices for the new bollards on New Bridge Lane shall be provided by the undertaker to Cambridgeshire County Council.
124
Any difference arising between the undertaker and the Cambridgeshire County Council under this part of this Schedule (other than in difference as to the meaning or construction of this Part of this Schedule) shall be resolved by arbitration under article 46 (arbitration).
125
- (1) Subject to sub-paragraphs (2) and (3), the undertaker must indemnify Cambridgeshire County Council from and against all costs, expenses, damages, losses and liabilities suffered by Cambridgeshire County Council arising from or in connection with any claim, demand, action or proceedings resulting from damage caused by the construction, maintenance or use of the specified works.
- (2) Sub-paragraph (1) does not apply if the costs, expenses, liabilities and damages were caused by or arose out of the neglect or default of Cambridgeshire County Council or its officers, servants, agents or contractors or any person or body for whom it is responsible.
- (3) If any person makes a claim or notifies an intention to make a claim against Cambridgeshire County Council which may reasonably be considered likely to give rise to a liability under this paragraph then Cambridgeshire County Council must—
- (a) as soon as reasonably practicable give the undertaker reasonable notice of any such third party claim or demand, specifying the nature of the indemnity liability in reasonable detail; and
- (b) not make any admission of liability, agreement or compromise in relation to the indemnity liability without first consulting the undertaker and considering their representations.
- (4) The undertaker acknowledges that Cambridgeshire County Council may receive statutory compensation claims and that Cambridgeshire County Council may not be able to comply with sub-paragraph (3) in respect of such claims.
- (5) Where Cambridgeshire County Council considers that sub-paragraph (4) applies to any claim or demand it must give notice of that view as part of the relevant notice provided pursuant to sub-paragraph (3)(a).
- (6) Cambridgeshire County Council must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands and penalties to which the indemnity under this paragraph applies where it is within Cambridgeshire County Council’s reasonable gift and control to do so and which expressly excludes any obligation to mitigate liability arising from third parties which is outside of Cambridgeshire County Council’s control. If reasonably requested to do so by the undertaker, Cambridgeshire County Council must provide an explanation of how any claim has been mitigated or minimised or where mitigation or minimisation is not possible an explanation as to why.
126
All reasonable costs incurred by Cambridgeshire County Council under this part of this Schedule shall be paid in full by the undertaker on written demand by Cambridgeshire County Council.
SCHEDULE 12 — PROCEDURE FOR THE DISCHARGE OF REQUIREMENTS
Interpretation
1
In this Schedule—
- “relevant authority” means the relevant planning authority, Ministry of Defence, relevant highway authority, traffic authority, street authority, or the owner of a watercourse, sewer or drain as may be appropriate to the consent, agreement or approval sought; and
- “requirement consultee” means any body named in a requirement as a body required to be consulted by the relevant authority in discharging that requirement.
Applications made under requirements
2
- (1) Where an application has been made to the relevant authority for any consent, agreement or approval required by a requirement (including consent, agreement or approval in respect of part of a requirement) the relevant authority must give notice to the undertaker of their decision on the application within a period of 12 weeks beginning with—
- (a) the day immediately following that on which the application is received by the authority;
- (b) the day immediately following that on which further information has been supplied by the undertaker under sub-paragraph (2); or
- (c) such longer period as may be agreed in writing by the undertaker and the relevant authority,
whichever is the latest.
- (2) Subject to sub-paragraph (4), in the event that the relevant authority does not determine an application within the period set out in sub-paragraph (1), the relevant authority is to be taken to have granted all parts of the application (without any condition or qualification) at the end of that period.
- (3) Any application made to the relevant authority pursuant to sub-paragraph (1) must—
- (a) include a statement to confirm whether it is likely that the subject matter of the application will give rise to any materially new or materially different environmental effects compared to those in the environmental statement and if it will then it must be accompanied by information setting out what those effects are; and
- (b) include confirmation that the application has been notified and provided to the requirement consultees in accordance with sub-paragraph (5), if the provision governing or requiring the application specifies that consultation with a requirement consultee is required. Such confirmation to include contact details for the requirement consultees.
- (4) Where an application has been made to the relevant authority for any consent, agreement or approval required by a requirement included in this Order, and—
- (a) the relevant authority does not determine the application within the period set out in sub‑paragraph (1) and such application is accompanied by a report pursuant to sub-paragraph (3) which states that the subject matter of such application is likely to give rise to any materially new or materially different environmental effects compared to those in the environmental statement; or
- (b) the relevant authority determines during the period set out in sub-paragraph (1) that it considers that the subject matter of such application will give rise to any materially new or materially different environmental effects compared to those in the environmental statement,
then the application is to be taken to have been refused by the relevant authority at the end of that period.
- (5) At the same time as submitting an application to the relevant authority for any consent, agreement or approval required by a requirement, the undertaker must also give notice of such application, and provide a copy of the application, to any requirement consultee, if the provision governing or requiring the application specifies that consultation with a requirement consultee is required. As part of the notification to any requirement consultee, the undertaker must include a statement that refers to—
- (a) the timeframes in which the requirement consultee can request any further information from the undertaker (via the relevant authority) as prescribed in paragraph 3(6)(a) and the consequences of the failure to meet those timescales as prescribed in paragraph 3(6)(b); and
- (b) the timeframes in which the requirement consultee must give notice to the relevant authority of its comments on the application as prescribed in paragraph 3(6)(d) and the consequences of the failure to meet those timescales as prescribed in paragraph 3(6)(e).
Further information and consultation
3
- (1) In relation to any application to which this Schedule applies, the relevant authority may request such reasonable further information from the undertaker as is necessary to enable it to consider the application.
- (2) In the event that the relevant authority considers such further information to be necessary and the provision governing or requiring the application does not specify that consultation with a requirement consultee is required the relevant authority must, within 14 working days of receipt of the application, notify the undertaker in writing specifying the further information required.
- (3) If the provision governing or requiring the application specifies that consultation with a requirement consultee is required, the relevant authority must notify the undertaker in writing specifying any further information requested by the requirement consultee within 15 working days of receipt of such a request and in any event within 35 working days of receipt of the application or such longer period as may be agreed in writing by the undertaker and the relevant authority.
- (4) In the event that the relevant authority does not give notification as specified in sub‑paragraph (2) or (3) it is to be deemed to have sufficient information to consider the application and is not thereafter entitled to request further information without the prior agreement of the undertaker.
- (5) Where further information is requested under this paragraph 3 in relation to part only of an application, that part is to be treated as separate from the remainder of the application for the purposes of calculating time periods in paragraph 2(1)(b), paragraph 2(4) and paragraph 3.
- (6) If the provision governing or requiring the application specifies that consultation with a requirement consultee is required—
- (a) A requirement consultee is required to notify the relevant authority in writing specifying any further information it considers necessary in order to comment on the application within 10 working days of receipt of the application pursuant to paragraph 2(5);
- (b) If a requirement consultee does not give notification as specified in paragraph (a) it is deemed to have sufficient information to comment on the application and is not thereafter entitled to request further information without the prior agreement of the undertaker and relevant authority;
- (c) At the same time as providing any further information to the relevant authority pursuant to a request under sub-paragraph (2), if the undertaker has been notified of further information requested by a requirement consultee, the undertaker must also give any further information to the requirement consultee;
- (d) A requirement consultee is required to notify the relevant authority in writing of any comments on the application within 15 working days of receipt of the application from the undertaker pursuant to paragraph 2(5), or the receipt of any further information pursuant to paragraph (c) (where further information has been requested); and
- (e) If a requirement consultee does not give notification as specified in paragraph (d) it is deemed to have no comments on the application.
Appeals
4
- (1) The undertaker may appeal in the event that—
- (a) the relevant authority refuses (including a deemed refusal pursuant to paragraph 2(4)) an application for any consent, agreement or approval required by an article or requirement included in this Order or grants it subject to conditions;
- (b) on receipt of a request for further information pursuant to paragraph 3 the undertaker considers that either the whole or part of the specified information requested by the relevant authority is not necessary for consideration of the application; or
- (c) on receipt of any further information requested, the relevant authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application.
- (2) The appeal process is to be as follows—
- (a) the undertaker must submit the appeal documentation to the Secretary of State and must on the same day provide copies of the appeal documentation to the relevant authority and any requirement consultee required to be consulted pursuant to the article or requirement which is the subject of the appeal (together with the undertaker, these are the “appeal parties”);
- (b) the Secretary of State is to appoint a person within 20 working days of receiving the appeal documentation and must forthwith notify the appeal parties of the identity of the appointed person and the address to which all correspondence for his attention should be sent, the date of such notification being the “start date” for the purposes of this sub‑paragraph (2);
- (c) the relevant authority and any consultee required to be consulted pursuant to the article or requirement which is the subject of the appeal must submit written representations to the appointed person in respect of the appeal within 10 working days of the start date and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;
- (d) the appeal parties must make any counter-submissions to the appointed person within 10 working days of receipt of written representations pursuant to paragraph (c) above;
- (e) the appointed person must make his decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable and in any event within 30 working days of the deadline for the receipt of counter-submissions pursuant to paragraph (d); and
- (f) the appointment of the person pursuant to paragraph (b) may be undertaken by a person appointed by the Secretary of State for this purpose instead of by the Secretary of State.
- (3) In the event that the appointed person considers that further information is necessary to enable him to consider the appeal he must, within five working days of his appointment, notify the appeal parties in writing specifying the further information required.
- (4) Any further information required pursuant to sub-paragraph (3) must be provided by the undertaker to the appointed person, the relevant authority and any consultee required to be consulted pursuant to the article or requirement the subject of the appeal on the date specified by the appointed person (the “specified date”), and the appointed person must notify the appeal parties of the revised timetable for the appeal on or before that day. The revised timetable for the appeal must require submission of written representations to the appointed person within 10 working days of the specified date but otherwise is to be in accordance with the process and time limits set out in paragraphs (2)(c) to (2)(e).
- (5) On an appeal under this paragraph, the appointed person may—
- (a) allow or dismiss the appeal; or
- (b) reverse or vary any part of the decision of the relevant authority (whether the appeal relates to that part of it or not),
and may deal with the application as if it had been made to him in the first instance.
- (6) The appointed person may proceed to a decision on an appeal taking into account only such written representations as have been sent within the relevant time limits.
- (7) The appointed person may proceed to a decision even though no written representations have been made within the relevant time limits, if it appears to him that there is sufficient material to enable a decision to be made on the merits of the case.
- (8) The decision of the appointed person on an appeal is to be final and binding on the parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review.
- (9) If an approval is given by the appointed person pursuant to this Schedule, it is to be deemed to be an approval for the purpose of Schedule 2 (requirements) as if it had been given by the relevant authority. The relevant authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) is not to be taken to affect or invalidate the effect of the appointed person’s determination.
- (10) Save where a direction is given pursuant to sub-paragraph (11) requiring the costs of the appointed person to be paid by the relevant authority, the reasonable costs of the appointed person must be met by the undertaker.
- (11) On application by the relevant authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction and the terms on which it is to be made, the appointed person must have regard to Planning Practice Guidance: Appeals (March 2014) or any circular or guidance which may from time to time replace it.
SCHEDULE 13 — DOCUMENTS AND PLANS TO BE CERTIFIED
| (1)Document name | (2)Document reference | (3)Revision number | (4)Date |
|---|---|---|---|
| access and public rights of way plans | 2.4 | 7 | August 2023 |
| book of reference | 4.1 | 6 | August 2023 |
| carbon capture and export embedded design measures | 14.7 (Appendix B) | 1 | June 2023 |
| carbon capture and export readiness reserve space plan | 10.7 | 1 | March 2023 |
| combined heat and power embedded design measures | 14.7 (Appendix A) | 1 | June 2023 |
| combined heat and power assessment | 7.6 | 1 | June 2022 |
| design and access statement | 7.5 | 1 | June 2022 |
| environmental statement | 6.1, 6.2 | 2 | June 2023 |
| environmental statement figures | 6.3 | 2 | May 2023 |
| environmental statement appendices | 6.4 | 2 | March 2023 |
| flood risk assessment | 6.4 (ES Appendix 12A) | 1 | June 2022 |
| land plans | 2.2 | 5 | August 2023 |
| outline biodiversity net gain strategy | 6.4 (ES Appendix 11M) | 5 | July 2023 |
| outline construction environmental management plan | 7.12 | 6 | July 2023 |
| outline construction traffic management plan | 6.4 (ES Appendix 6A) | 7 | August 2023 |
| outline decommissioning plan | 12.4 | 1 | May 2023 |
| outline drainage strategy | 6.4 (ES Appendix 12F) | 4 | August 2023 |
| outline employment and skills strategy | 7.8 | 1 | June 2022 |
| outline fire prevention plan | 7.10 | 3 | August 2023 |
| outline flood emergency management plan | 7.9 | 2 | March 2023 |
| outline landscape and ecology strategy | 6.3 (ES Figure 3.14) | 2 | March 2023 |
| outline landscape and ecology management plan | 7.7 | 2 | April 2023 |
| outline lighting strategy | 6.4 (ES Appendix 3B) | 3 | June 2023 |
| outline local air quality monitoring strategy | 9.21 | 3 | May 2023 |
| outline odour management plan | 7.11 | 3 | August 2023 |
| outline operational noise management plan | 6.4 (ES Appendix 7D) | 4 | June 2023 |
| outline operational traffic management plan | 7.15 | 4 | July 2023 |
| outline operational travel plan | 6.4 (ES Appendix 6C) | 1 | June 2022 |
| waste area plan | 15.9 | 1 | July 2023 |
| works plans | 2.3 | 4 | August 2023 |
SCHEDULE 14 — MAXIMUM AND MINIMUM DESIGN PARAMETERS
| (1)Element of authorised development | (2)Work No. | (3)Maximum length (metres) | (4)Maximum width (metres) | (5)Maximum height (metres) (above finished floor level of 3.0m AOD) | (6)Minimum height (metres) (above finished floor level of 3.0m AOD) |
|---|---|---|---|---|---|
| Gatehouse / weighbridge | 2A | 9.5 | 2.4 | 3 | |
| Tipping hall | 1 | 58.5 | 38 | 18.5 | |
| Fire water tank | 2A | 16 | 10 | ||
| Fire water pump building | 2A | 12.5 | 9.5 | 5.5 | |
| Waste bunker building | 1 | 102 | 37 | 38.5 | |
| Tipping bunker | 1 | – | – | -14 | |
| Main waste bunker | 1 | – | – | -14 | |
| Boiler house building | 1 | 55 | 47.6 | 52 | |
| Loading area (a) | 1 | 12.2 | 12.2 | 12 | |
| APCr silos | 1 | 33.3 | 12.2 | 37 | |
| Loading area (b) | 1 | 12.2 | 12.2 | 12 | |
| Air pollution control building | 1 | 33.2 | 28.6 | 37 | |
| Induced draft fans building | 1 | 10 | 10 | 12 | |
| Chimneys | 1A | – | 3.2 | 90 | 84 |
| CEMS platform | 1A | – | – | 18 | |
| Switchgear building north | 1 | 35.2 | 10 | 35 | |
| Switchgear building south | 1 | 12.4 | 10 | 18 | |
| IBA enclosure east | 1 | 14 | 11 | 12 | |
| IBA enclosure west | 1 | 11 | 6 | 12 | |
| Diesel tanks and urea tanks building | 1 | 25.9 | 9.1 | 35 | |
| Compressed air station | 1 | 13 | 8 | 10 | |
| Main transformer | 2A | 11 | 6 | 12 | |
| Emergency diesel generator | 1 | 13.5 | 5.5 | 12 | |
| Air cooled condenser | 1 | 37 | 37 | 30 | |
| Turbine hall | 1 | 47 | 34 | 27 | |
| Water treatment plant | 1 | 30 | 22 | 18 | |
| Workshop and stores | 2A | 34 | 15 | 18 | |
| Administration building | 1B | 34 | 12 | 15 | |
| 132kV switching compound | 2A | 23 | 13 | 6.5 | |
| Private wire transformer | 2A | 11 | 5 | 12 | |
| Private wire switchgear compound | 2A | 7 | 6 | 12 | |
| Water re–cooling system | 1 | 18.5 | 7.5 | 27 | |
| Steam and condensate pipelines | 3 | – | – | 23 |
SCHEDULE 15 — ARBITRATION RULES
Primary objective
1
- (1) The primary objective of these Arbitration Rules is to achieve a fair, impartial, final and binding award on the substantive difference between the parties (save as to costs) within 4 months from the date the arbitrator is appointed pursuant to article 46.
- (2) The parties will first use their reasonable endeavours to settle a dispute amicably through negotiations undertaken in good faith by the senior management of the parties. Any dispute which is not resolved amicably by the senior management of the parties within twenty (20) working days of the dispute arising, or such longer period as agreed in writing by the parties, will be subject to arbitration in accordance with the terms of this Schedule.
- (3) The Arbitration will be deemed to have commenced when a party (“the Claimant”) serves a written notice of arbitration on the other party (“the Respondent”).
Time periods
2
- (1) All time periods in these Arbitration Rules will be measured in working days and this will exclude weekends, bank and public holidays.
- (2) Time periods will be calculated from the day after the arbitrator is appointed which will be either—
- (a) the date the arbitrator notifies the parties in writing of his/her acceptance of an appointment by agreement of the parties; or
- (b) the date the arbitrator is appointed by the Secretary of State.
Timetable
3
- (1) The timetable for the arbitration will be that set out in sub-paragraphs (2) to (4) below unless amended in accordance with paragraph 5(3).
- (2) Within 15 days of the arbitrator being appointed, the Claimant will provide both the Respondent and the arbitrator with—
- (a) a written Statement of Claim which describes the nature of the difference between the parties, the legal and factual issues, the Claimant’s contentions as to those issues, and the remedy it is seeking; and
- (b) all statements of evidence and copies of all documents on which it relies, including contractual documentation, correspondence (including electronic documents), legal precedents and expert witness reports.
- (3) Within 15 days of receipt of the Claimant’s statements under sub-paragraph (2) by the arbitrator and Respondent, the Respondent will provide the Claimant and the arbitrator with—
- (a) a written Statement of Defence responding to the Claimant’s Statement of Claim, its statement in respect of the nature of the difference, the legal and factual issues in the Claimant’s claim, its acceptance of any element(s) of the Claimant’s claim, its contentions as to those elements of the Claimant’s claim it does not accept;
- (b) all statements of evidence and copies of all documents on which it relies, including contractual documentation, correspondence (including electronic documents), legal precedents and expert witness reports; and
- (c) any objections it wishes to make to the Claimant’s statements, comments on the Claimant’s expert report(s) (if submitted by the Claimant) and explanations for the objections.
- (4) Within 5 days of the Respondent serving its statements pursuant to sub-paragraph (3), the Claimant may make a Statement of Reply by providing both the Respondent and the arbitrator with—
- (a) a written statement responding to the Respondent’s submissions, including its reply in respect of the nature of the difference, the issues (both factual and legal) and its contentions in relation to the issues;
- (b) all statements of evidence and copies of documents in response to the Respondent’s submissions;
- (c) any expert report in response to the Respondent’s submissions;
- (d) any objections to the statements of evidence, expert reports or other documents submitted by the Respondent; and
- (e) its written submissions in response to the legal and factual issues involved.
Procedure
4
- (1) The arbitrator will make an award on the substantive difference(s) based solely on the written material submitted by the parties unless the arbitrator decides that a hearing is necessary to explain or resolve any matters.
- (2) Either party may, within 2 days of delivery of the last submission, request a hearing giving specific reasons why it considers a hearing is required.
- (3) Within 5 days of receiving the last submission, the arbitrator will notify the parties whether a hearing is to be held and the length of that hearing.
- (4) Within 10 days of the arbitrator advising the parties that he will hold a hearing, the date and venue for the hearing will be fixed by agreement with the parties, save that if there is no agreement the arbitrator will direct a date and venue which he considers is fair and reasonable in all the circumstances. The date for the hearing will not be less than 35 days from the date of the arbitrator’s direction confirming the date and venue of the hearing.
- (5) A decision will be made by the arbitrator on whether there is any need for expert evidence to be submitted orally at the hearing. If oral expert evidence is required by the arbitrator, then any expert(s) attending the hearing may be asked questions by the arbitrator.
- (6) There will be no process of examination and cross–examination of experts, but the arbitrator will invite the parties to ask questions of the experts by way of clarification of any answers given by the expert(s) in response to the arbitrator’s questions. Prior to the hearing the procedure for the expert(s) will be that—
- (a) at least 20 days before a hearing, the arbitrator will provide a list of issues to be addressed by the expert(s);
- (b) if more than one expert is called, they will jointly confer and produce a joint report or reports within 10 days of the issues being provided; and
- (c) the form and content of a joint report will be as directed by the arbitrator and must be provided at least 5 days before the hearing.
- (7) Within 10 days of a hearing or a decision by the arbitrator that no hearing is to be held the parties may by way of exchange provide the arbitrator with a final submission in connection with the matters in dispute and any submissions on costs. The arbitrator will take these submissions into account in the award.
- (8) The arbitrator may make other directions or rulings as considered appropriate in order to ensure that the parties comply with the timetable and procedures to achieve an award on the substantive difference within 4 months of the date on which they are appointed, unless both parties otherwise agree to an extension to the date for the award.
- (9) If a party fails to comply with the timetable, procedure or any other direction then the arbitrator may continue in the absence of a party or submission or document, and may make a decision on the information before them attaching the appropriate weight to any evidence submitted beyond any timetable or in breach of any procedure or direction or both.
- (10) The arbitrator’s award will include reasons. The parties will accept that the extent to which reasons are given will be proportionate to the issues in dispute and the time available to the arbitrator to deliver the award.
Arbitrator’s powers
5
- (1) The arbitrator has all the powers of the Arbitration Act 1996[^f00046], including the non–mandatory sections, save where modified by these Rules.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.