The HyNet Carbon Dioxide Pipeline Order 2024
- (3) Any requirements made by Wales and West Utilities under sub-paragraph (2) must be made within a period of 42 days beginning with the date on which a plan, section drawing, description, and risk assessment method statement under sub-paragraph (1) is submitted to it.
- (4) If Wales and West Utilities, in accordance with sub-paragraph (3) and in consequence of the works proposed by the undertaker, reasonably requires the removal or decommissioning of any apparatus or any reasonably necessary protective works and gives written notice to the undertaker of that requirement, the provisions of this Part apply as if the removal or decommissioning of the apparatus or the protective works had been required by the undertaker under paragraph 123(2).
- (5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 42 days before commencing the execution of any works, a new plan instead of the plan, section drawing, description and risk assessment method statement previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section drawing, description and risk assessment method statement.
- (6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to Wales and West Utilities notice as soon as is reasonably practicable and a plan, section drawing, description and risk assessment method statement of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances.
- (7) Where the specified works only include ground investigation or PAS128 Cat A surveys, all timeframes in this paragraph shall be reduced to 14 days.
Expenses and costs
126
- (1) Subject to the following provisions of this paragraph, the undertaker must repay to Wales and West Utilities within 30 days of a request by Wales and West Utilities the reasonable expenses agreed with the undertaker in advance and reasonably incurred by Wales and West Utilities in the inspection, removal, relaying or replacing, alteration or protection of any apparatus or security infrastructure of the construction of any new apparatus or security infrastructure which may be required in direct consequence of the execution of any such works as are referred to in paragraph 123(2) or any specified work, but always provided that the undertaker shall not be liable under any circumstances for any consequential loss or indirect loss suffered by Wales and West Utilities.
- (2) The value of any apparatus removed under the provisions of this Part must be deducted from any sum payable under sub-paragraph (1), that value being calculated after removal.
- (3) If in accordance with the provisions of this Part—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 47 (arbitration) to be necessary then, if such placing involves cost in the construction of works under this Part exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to the utility undertaker in question by virtue of sub-paragraph (1) must be reduced by the amount of that excess.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus must not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
- (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole must be treated as if it also had been agreed or had been so determined.
- (5) An amount which apart from this sub-paragraph would be payable to Wales and West Utilities in respect of works by virtue of sub-paragraph (1) must, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on Wales and West Utilities any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, is to be reduced by the amount which represents that benefit.
127
- (1) Subject to sub-paragraph (2), if by reason or in consequence of the construction of any such works referred to in paragraph 6(2) or any specified work any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of Wales and West Utilities, or there is any interruption in any service provided, or in the supply of any goods, by Wales and West Utilities, the undertaker must—
- (a) bear and pay the cost reasonably incurred by Wales and West Utilities in making good such damage or restoring the supply; and
- (b) make reasonable compensation to Wales and West Utilities for any other expenses, loss, damages, penalty or costs incurred by Wales and West Utilities,
as a direct result of any such damage or interruption and always provided that the undertaker shall not be liable under any circumstances for any consequential loss or indirect loss suffered by Wales and West Utilities.
- (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of Wales and West Utilities, its officers, servants, contractors or agents.
- (3) Wales and West Utilities must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made without the consent of the undertaker unless payment is required and the level specified in accordance with a statutory compensation scheme and, if such consent is withheld, the undertaker has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand provided that the undertaker consults Wales and West Utilities and takes any representations it makes into account.
Enactments and agreements
128
Nothing in this Part affects the provisions of any enactment or agreement regulating the relations between the undertaker and Wales and West Utilities in respect of any apparatus in land belonging to the undertaker on the date on which this Order is made.
PART 11 — Protection for Welsh Water
129
The provisions of this Part have effect unless otherwise agreed in writing between the undertaker and Welsh Water.
130
In this Part—
- “alternative apparatus” means alternative apparatus adequate to enable the utility undertaker in question to fulfil its statutory functions in a manner no less efficient than previously;
- “apparatus” means—mains, pipes or other apparatus belonging to or maintained by that water undertaker for the purposes of water supply; andany drain or works vested in the sewerage undertaker under the Water Industry Act 1991; andany sewer which is so vested or is the subject of a notice of intention to adopt given under section 102(4) (adoption of sewers and disposal works) of that Act or an agreement to adopt made under section 104 (agreements to adopt sewer, drain or sewerage disposal works, at future date) of that Act;and includes a sludge main, disposal main (within the meaning of section 219 (general interpretation) of that Act) or sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part of any such sewer, drain or works,
and includes any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus;
- “functions” includes powers and duties;
- “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over or upon land;
- “plan” includes all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the works to be executed; and
- “utility undertaker” means—a water undertaker within the meaning of the Water Industry Act 1991; anda sewerage undertaker within the meaning of Part 1 of the Water Industry Act 1991,and in relation to any apparatus, means the utility undertaker to whom it belongs or by whom it is maintained.
On street apparatus
131
This Part does not apply to apparatus in respect of which the relations between the undertaker and the utility undertaker are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act.
Acquisition of land
132
Regardless of any provision of this Order or anything shown on the land plans, the undertaker must not acquire any apparatus otherwise than by agreement.
Removal of apparatus
133
- (1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed or requires that the utility undertaker’s apparatus is relocated or diverted, that apparatus must not be removed under this Part, and any right of a utility undertaker to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed and is in operation to the reasonable satisfaction of the utility undertaker in question.
- (2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, the undertaker must give to the utility undertaker in question 28 days’ written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed; and in that case (or if in consequence of the exercise of any of the powers conferred by this Order a utility undertaker reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to the utility undertaker the necessary facilities and rights for the construction of alternative apparatus in other land of the undertaker and subsequently for the maintenance of that apparatus.
- (3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed, the utility undertaker in question must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible use reasonable endeavours to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.
- (4) Any alternative apparatus to be constructed in land of the undertaker under this Part must be constructed in such manner and in such line or situation as may be agreed between the utility undertaker in question and the undertaker or in default of agreement settled by arbitration in accordance with article 47 (arbitration).
- (5) The utility undertaker in question must, after the alternative apparatus to be provided or constructed has been agreed or settled by arbitration in accordance with article 49 (arbitration), and after the grant to the utility undertaker of any such facilities and rights as are referred to in sub-paragraph (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part.
- (6) Regardless of anything in sub-paragraph (5), if the undertaker gives notice in writing to the utility undertaker in question that the undertaker desires itself to execute any work, or part of any work, in connection with the construction or removal of apparatus in any land of the undertaker, that work, instead of being executed by the utility undertaker, must be executed by the undertaker without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of the utility undertaker.
- (7) Nothing in sub-paragraph (6) authorises the undertaker to execute the placing, installation, bedding, packing, removal, connection or disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is laid in a trench) within 300 millimetres of the apparatus.
Facilities and rights for alternative apparatus
134
- (1) Where, in accordance with the provisions of this Part, the undertaker affords to a utility undertaker facilities and rights for the construction and maintenance in land of the undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between the undertaker and the utility undertaker in question or in default of agreement settled by arbitration in accordance with article 49 (arbitration).
- (2) In settling those terms and conditions in respect of alternative apparatus to be constructed in or along the authorised development, the arbitrator must—
- (a) give effect to all reasonable requirements of the undertaker for ensuring the safety and efficient operation of the authorised development and for securing any subsequent alterations or adaptations of the alternative apparatus that may be required to prevent interference with any proposed works of the undertaker; and
- (b) so far as it may be reasonable and practicable to do so in the circumstances of the particular case, give effect to the terms and conditions, if any, applicable to the apparatus constructed in or along the authorised project for which the alternative apparatus is to be substituted.
- (3) If the facilities and rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are in the opinion of the arbitrator less favourable on the whole to the utility undertaker in question than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the arbitrator must make such provision for the payment of compensation by the undertaker to that utility undertaker as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
Retained apparatus
135
- (1) Not less than 28 days before starting the execution of any works in, on or under any land purchased, held, appropriated or used under this Order that are near to, or will or may affect, any apparatus the removal of which has not been required by the undertaker under paragraph 133(2), the undertaker must submit to the utility undertaker in question a plan of the works to be executed.
- (2) Those works must be executed only in accordance with the plan submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by the utility undertaker for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and the utility undertaker is entitled to watch and inspect the execution of those works.
- (3) Any requirements made by a utility undertaker under sub-paragraph (2) must be made within a period of 21 days beginning with the date on which a plan under sub-paragraph (is submitted to it.
- (4) If a utility undertaker, in accordance with sub-paragraph (3) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, the provisions of this Part apply as if the removal of the apparatus had been required by the undertaker under paragraph 133(2).
- (5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan instead of the plan previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.
- (6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to the utility undertaker in question notice as soon as is reasonably practicable and a plan of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances.
Expenses and costs
136
- (1) Subject to the following provisions of this paragraph, the undertaker must repay to a utility undertaker the reasonable expenses agreed with the undertaker in advance and reasonably incurred by that utility undertaker in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to in paragraph 133(2).
- (2) The value of any apparatus removed under the provisions of this Part must be deducted from any sum payable under sub-paragraph (1), that value being calculated after removal.
- (3) If in accordance with the provisions of this Part—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 47 (arbitration) to be necessary then, if such placing involves cost in the construction of works under this Part exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to the utility undertaker in question by virtue of sub-paragraph (1) must be reduced by the amount of that excess.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus must not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
- (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole must be treated as if it also had been agreed or had been so determined.
- (5) An amount which apart from this sub-paragraph would be payable to a utility undertaker in respect of works by virtue of sub-paragraph (1) must, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the utility undertaker any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, is to be reduced by the amount which represents that benefit.
137
- (1) Subject to sub-paragraph (2), if by reason or in consequence of the construction of any such works referred to in paragraph 133(2) any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of a utility undertaker, or there is any interruption in any service provided, or in the supply of any goods, by any utility undertaker, the undertaker must—
- (a) bear and pay the cost reasonably incurred by that utility undertaker in making good such damage or restoring the supply; and
- (b) make reasonable compensation to that utility undertaker for any other expenses, loss, damages, penalty or costs incurred by the utility undertaker,
by reason or in consequence of any such damage or interruption.
- (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of a utility undertaker, its officers, servants, contractors or agents.
- (3) A utility undertaker must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made without the consent of the undertaker and, if such consent is withheld, the undertaker has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
Miscellaneous
138
Nothing in this Part affects the provisions of any enactment or agreement regulating the relations between the undertaker and a utility undertaker in respect of any apparatus in land belonging to the undertaker on the date on which this Order is made.
PART 12 — For the protection of United Utilities Water Limited (UU Water)
Application
139
For the protection of UU Water the following provisions, unless otherwise agreed in writing between the undertaker and UU Water, have effect.
Interpretation
140
In this Part of this Schedule—
- “alternative apparatus” means appropriate alternative apparatus to the reasonable satisfaction of UU Water to enable UU Water to fulfil its statutory functions in a manner no less efficient than previously;
- “apparatus” means any treatment works, reservoirs, pumping stations, water mains, sewers, drains, sludge mains, disposal mains, pipes or any accessories (including those within the meaning of section 219 of the Water Industry Act 1991) vested in UU Water under the Water Industry Act 1991 and any preceding legislation or other apparatus belonging to or maintained by UU Water for the purposes of UU Water’s undertaking together with any replacement apparatus and such other apparatus constructed pursuant to this Order that becomes operational apparatus of UU Water for the purposes of UU Water’s undertaking and includes any structure in which apparatus is or will be lodged or which gives or will give access to apparatus;
- “authorised works” has the same meaning as is given to the term “authorised development” in article 2 of the Order and for the purposes of this Part of this Schedule includes the use and maintenance of the authorised works and construction of any works authorised by this Schedule;
- “deed of consent” means a deed of consent, crossing agreement, deed of variation or new deed of grant agreed between the parties acting reasonably in order to vary or replace existing easements, agreements, enactments and other such interests so as to secure land rights and interests as are necessary to carry out, maintain, operate and use the apparatus in a manner consistent with the terms of this Part of this Schedule;
- “Estimate” means a reasonable estimate of the total reasonable and proper costs that UU Water expects to incur in respect of staff and orders or instructions that need to be given to UU Water’s vendors in its supply chain or to third party organisations to obtain their consent in respect of the specified works.
- “facilities and rights” for construction and for maintenance include any appropriate working areas required to reasonably and safely undertake that construction or maintenance activity, and any necessary rights of access;
- “functions” includes powers and duties;
- “ground mitigation scheme” means a scheme approved by UU Water (such approval not to be unreasonably withheld or delayed) setting out the necessary measures (if any) for a ground subsidence event;
- “ground monitoring scheme” means a scheme for monitoring ground conditions and vibration which sets out the apparatus which is to be subject to such monitoring, the extent of land to be monitored, the manner in which ground levels and water supplies are to be monitored (including turbidity), the timescales of any monitoring activities and the extent of ground subsidence, dewatering and / or vibration which, if exceeded, shall require the undertaker to submit for UU Water’s approval a ground mitigation scheme;
- “ground subsidence event” means any ground subsidence, ground dewatering or vibration identified by the monitoring activities set out in the ground monitoring scheme that has exceeded or reasonably has the potential to exceed the level described in the ground monitoring scheme as requiring a ground mitigation scheme;
- “in” (in a context referring to apparatus or alternative apparatus in land) includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;
- “maintain” and “maintenance” have effect as if the term maintain includes protect and use;
- “plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary to properly and sufficiently describe and assess the works to be executed;
- “protective works” means any works that are reasonably necessary to protect UU Water’s services to its customers and its apparatus from damage that may be caused by the carrying out, maintenance or use of the authorised development;
- “rights” includes restrictive covenants and, in relation to decommissioned apparatus, the surrender of rights, release of liabilities and transfer of decommissioned apparatus;
- “specified works” means any of the authorised works or activities (including maintenance) undertaken in association with the authorised development (including maintenance and notwithstanding the definition of “commence” in Article 2 of this Order) including but not limited to any intrusive site preparation works, intrusive remediation works, intrusive surveys and investigations (including archaeological, utility or soil surveys), erection of temporary fencing requiring intrusive supports, intrusive marking out of site boundaries, diversion or laying of services or intrusive environmental mitigation measures and any such temporary access by HGVs or LGVs that may be required in association with these, and which— when involving a pipe up to and including 300mm in diameter, will or may be situated over, or within 3000mm measured in any direction of any apparatus, the removal of which has not been required by the undertaker under sub-paragraph 144(2) or otherwise; when involving a pipe exceeding 300mm in diameter, will or may be situated over, or within 5000mm measured in any direction of any apparatus the removal of which has not been required by the undertaker under sub-paragraph 144(2) or otherwise; or may in any way adversely affect any apparatus the removal of which has not been required by the undertaker under sub-paragraph 144(2) or otherwise;
- “UU Water” means United Utilities Water Limited (company number 02366678), registered office at Haweswater House, Lingley Mere Business Park, Lingley Green Avenue, Great Sankey, Warrington, WA5 3LP and includes its successors in title or any successor as a water and sewerage undertaker within the meaning of the Water Industry Act 1991; and
- “UU Water’s undertaking” means the rights, duties and obligations of United Utilities Water Limited as a water and sewerage undertaker under the Water Industry Act 1991.
Apparatus of UU Water stopped up in street
141
Notwithstanding the temporary alteration, diversion or restriction of use of any street under the powers of article 15 (temporary restriction of use of streets) UU Water will be at liberty at all times to take all necessary access across any such street and to execute and do all such works and things in, upon or under any such street as it would have been entitled to do immediately before such temporary alteration, diversion or restriction in respect of any apparatus which at the time of the stopping up or diversion was in that street.
Discharge of Water, foul and surface water
142
- (1) If the undertaker proposes to connect foul water to a public sewer operated by UU Water, the undertaker shall give to UU Water notice of the proposal, and within 42 days of the receipt by them of the notice, UU Water may refuse permission for the connection but only if it has reasonable grounds for doing so, or it may grant permission for the connection or alteration, subject to such reasonable conditions as it thinks fit acting reasonably. Any such permission may in particular specify the mode and point of connection.
- (2) If the undertaker proposes to connect surface water to a public sewer operated by UU Water, the undertaker shall give to UU Water notice of the proposal, and within 42 days of the receipt by them of the notice, UU Water may refuse permission for the connection, but only if it has reasonable grounds for doing so, or it may grant permission for the connection or alteration, subject to such reasonable conditions as it thinks fit acting reasonably. Any such permission may in particular specify the mode, the point of connection, the rate of discharge and the size of any attenuation necessary. UU Water shall be entitled to refuse any connection where the sustainable drainage system hierarchy for managing surface water has not been reasonably investigated and / or sustainable drainage has not been incorporated within the proposed surface water drainage to the satisfaction of UU Water.
- (3) Where there are separate public sewers for foul water and surface water, UU Water may prohibit the discharge of foul water into the public sewer reserved for surface water, and prohibit the discharge of surface water into the public sewer reserved for foul water.
- (4) Where UU Water has not granted or refused permission under this paragraph within 42 days from the receipt of notice of a proposal the permission shall be deemed to be granted
- (5) Nothing in this section entitles the undertaker to:
- (a) discharge in to a public sewer (directly or indirectly), highway drainage, groundwater, trade effluent or any liquid or other matter, the discharge of which in to a public sewer is prohibited by or under any enactment; or
- (b) have drains or sewers that communicate directly with a storm water overflow.
Protective works to buildings
143
The undertaker must exercise the powers conferred by article 22 (protective work to buildings) so as not to obstruct or render less convenient the access to any apparatus without the written consent of UU Water (such consent not to be unreasonably withheld or delayed) and if by reason of the exercise of those powers any damage to any apparatus (other than apparatus the repair of which is not reasonably necessary in the view of its intended removal or abandonment) or property of UU Water or any interruption in the supply of water and the provision of sewerage services by UU Water, as the case may be, is caused, the undertaker must bear and pay on demand the cost reasonably incurred and documented by UU Water in making good such damage or restoring the supply; and, shall pay compensation to UU Water for any loss sustained by reason of any such damage or interruption.
Removal of apparatus
144
- (1) If, in the exercise of the powers conferred by this Order, including pursuant to any agreement reached in accordance with paragraph 143, the undertaker acquires any interest in any land in which any apparatus is placed, that apparatus must not be decommissioned or removed and any right of UU Water to maintain that apparatus in that land must not be extinguished or interfered with until alternative apparatus has been constructed, is in operation, and the facilities and rights referred to in sub-paragraph (2) have been provided, to the reasonable satisfaction of UU Water and in accordance with sub-paragraphs (2) to (5) inclusive.
- (2) If, for the purpose of executing any works in, on, under or over any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to UU Water advance written notice of not less than 70 days of that requirement, together with a plan and section of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order UU Water reasonably needs to move or remove any of its apparatus) the undertaker must afford to UU Water to its reasonable satisfaction the necessary facilities and rights—
- (a) for the construction of alternative apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by UU Water in respect of the apparatus);
- (b) subsequently for the maintenance of that apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by UU Water in respect of the apparatus); and
- (c) to allow access to that apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by UU Water in respect of the apparatus).
- (3) If the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, UU Water must, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances in an endeavour to assist the undertaker in obtaining the necessary facilities and rights in the land in which the alternative apparatus is to be constructed save that this obligation will not extend to the requirement for UU Water to use its compulsory purchase powers to this end unless it (in its absolute discretion) elects to so do.
- (4) Any alternative apparatus to be constructed in land of or land secured by the undertaker under this Part of this Schedule must be constructed in such manner and in such position as may be agreed between UU Water and the undertaker, each acting reasonably.
- (5) UU Water must, after the alternative apparatus to be provided or constructed has been agreed, and subject to the prior grant to UU Water of such facilities and rights as are referred to in sub-paragraph (2) or (3), then proceed without unnecessary delay to construct and bring in to operation the alternative apparatus and subsequently to decommission or remove any apparatus required by the undertaker to be decommissioned or removed under the provisions of this Part of this Schedule.
Facilities and rights for alternative apparatus
145
- (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to or secures for UU Water facilities and rights in land for the access to, construction and maintenance of alternative apparatus in substitution for apparatus to be decommissioned or removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between the undertaker and UU Water, each acting reasonably, and must be no less favourable on the whole to UU Water than the facilities and rights enjoyed by it in respect of the apparatus to be decommissioned or removed unless otherwise agreed by UU Water.
- (2) If the facilities and rights to be afforded by the undertaker and agreed with UU Water under sub- paragraph (1) in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are less favourable on the whole to UU Water than the facilities and rights enjoyed by it in respect of the apparatus to be decommissioned or removed, then the terms and conditions to which those facilities and rights are subject may be referred to arbitration in accordance with paragraph 149 of this Part of this Schedule and the arbitrator must make such provision for the payment of reasonable compensation by the undertaker to UU Water as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
Retained apparatus: protection of UU Water
146
- (1) Not less than 56 days before the commencement of any specified works the undertaker must submit to UU Water a plan and, if reasonably required by UU Water, a ground monitoring scheme in respect of those works.
- (2) The plan to be submitted to UU Water under sub-paragraph (1) must include a method statement and describe—
- (a) the exact position of the works;
- (b) the level at which these are proposed to be constructed or renewed;
- (c) the manner of their construction or renewal including details of
- (d) excavation, positioning of plant etc.;
- (e) the position of all apparatus, identified if necessary by survey or investigation works carried out with the prior agreement and to the reasonable satisfaction of UU Water;
- (f) by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus; and
- (g) any intended maintenance regimes.
- (3) the undertaker must not commence any specified works until UU Water has given written approval of the plan so submitted (and the ground monitoring scheme if required).
- (4) Any approval of UU Water given under sub-paragraph (3)—
- (a) may be given subject to reasonable conditions for any purpose mentioned in sub-paragraph (5); and
- (b) must not be unreasonably withheld or delayed and UU Water and any approval or refusal must be provided to the undertaker within 56 days of the date of submission of the plan under sub-paragraph (1).
- (5) UU Water may require protective works or such modifications to be made to the plan as may be reasonably necessary for the purpose of maintaining services to its customers, or securing its apparatus against interference or risk of damage, or for the purpose of providing or securing proper and convenient means of access to any apparatus.
- (6) Specified works must only be executed in accordance with—
- (a) the plan submitted under sub-paragraph (1) (and ground monitoring scheme if required), as approved or as amended from time to time by agreement between the undertaker and UU Water; and
- (b) all conditions imposed under sub-paragraph (4)(a), and UU Water will be entitled to watch and inspect the execution of those works.
- (7) Where UU Water reasonably requires any protective works or such modifications to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works or modifications, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to UU Water’s reasonable satisfaction prior to the commencement of any specified works (or any relevant part thereof) for which such protective works or modifications are required prior to commencement.
- (8) If UU Water, in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 139 to 141 and 143 to 145 apply as if the removal of the apparatus had been required by the undertaker under paragraph 144(2).
- (9) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of the specified works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph will apply to and in respect of the new plan.
- (10) As soon as is reasonably practicable after any ground subsidence event attributable to the authorised works (including such an event attributable to its maintenance)—
- (a) the undertaker must implement an appropriate ground mitigation scheme; and
- (b) UU Water retains the right to carry out any further necessary protective works for the safeguarding of its apparatus and can recover any such reasonable and documented costs in line with paragraph 147.
- (11) The undertaker is not required to comply with sub-paragraph (1) where it needs to carry out emergency works but in that case it must give to UU Water notice as soon as is reasonably practicable and a plan of those works and must comply with the conditions imposed under sub-paragraph (4)(a) insofar as is reasonably practicable in the circumstances.
- (12) In this paragraph, “emergency works” means works whose execution at the time when they are executed is required in order to put an end to, or to prevent the occurrence of, circumstances then existing or imminent (or which the person responsible for the works believes on reasonable grounds to be existing or imminent) which are likely to cause danger to life or property or the environment, and to any interruption of a supply of water provided to any premises and to any interruption of the provision of sewerage services to any premises.
Expenses
147
- (1) At the same time as any written notice is provided by UU Water in accordance with paragraph 146(8), UU Water shall also submit an Estimate to the undertaker.
- (2) If the undertaker elects that it will proceed with the specified works it shall make an advance payment of the Estimate to UU Water no later than 28 days prior to the planned commencement of the specified works. The undertaker shall not commence the specified works until a minimum of 28 days of receipt by UU Water of the advance payment.
- (3) If at any point UU Water’s Estimate is forecast to be exceeded, UU Water shall submit an early warning notification and then a change request documenting all costs already incurred and forecast to be reasonably incurred and submit an updated Estimate to the undertaker no less than 28 days prior to the Estimate being reasonably expected to be exceeded. The undertaker shall make such additional payment required by the updated Estimate as soon as reasonably possible and in any event no later than 56 days after receipt of the updated Estimate.
- (4) Where the undertaker fails to make such additional payment required under sub-paragraph (3) within 56 days of receipt of the updated Estimate, UU Water will be entitled to require the undertaker to suspend works from the point at which the charges, costs and expenses reach or exceed the Estimate. In addition any reasonable abortive/demobilisation costs resulting from this would be recoverable by UU Water from the undertaker.
- (5) In the event of any dispute as to the reasonableness of costs included in an updated Estimate submitted under sub-paragraph (3), UU Water must not exercise the powers of sub-paragraph (4) until the dispute has been finally determined.
- (6) Subject to the following provisions of this paragraph, UU Water’ will retain an account of all its direct charges, costs and expenses reasonably incurred and documented by UU Water in the design, planning, inspection, removal, relaying or replacing, alteration or protection of any apparatus or the construction of any new or alternative apparatus required as a direct result of the execution of any authorised works including without limitation—
- (a) any costs reasonably incurred by or compensation properly paid by UU Water in connection with the acquisition of rights or the exercise of statutory powers for such apparatus including reasonable costs (including professional fees) incurred by UU Water as a consequence of UU Water;
- (i) using its own compulsory purchase powers to acquire any necessary rights under paragraph 5(3) if it elects to do so; or
- (ii) exercising any compulsory purchase powers under this Order transferred to or benefitting UU Water;
- (b) in connection with the cost of the carrying out of any necessary diversion work or the provision of any alternative apparatus;
- (c) the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
- (d) the approval of plans;
- (e) the carrying out of protective works;
- (f) the survey of any land, apparatus or works, the inspection and monitoring of works, the provision of network contingency measures or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule;
- (g) any watching brief pursuant to sub-paragraph 145(6);
- (h) in connection with an assessment of flood risk from UU Water apparatus (note above comment about whether this apparatus includes a reservoir);
- (i) in connection with an assessment of the impact on a UU Water outfall;
- (j) any relevant charges in accordance with the charges scheme under the Water Industry Act 1991.
- (7) UU Water shall give the undertaker regular actual and forecast cost updates at intervals to be agreed between UU Water and the undertaker, each acting reasonably.
- (8) Within 90 days of completion of the specified works, UU Water shall reconcile its accounts with its supply chain and collate its internal costs and advise the undertaker of the final account position. Within 28 days of this final account, UU shall reimburse the undertaker of all remaining monies that were received as part of any advance payment arrangements. If the final account is above the Estimate, the undertaker will be required to pay UU Water within 28 days of submission of the final account.
- (9) UU Water may in carrying out works, elect to place—
- (a) alternative apparatus of a better type, or greater capacity or of greater dimensions in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions save where this has been solely due to using the nearest currently available type (or where it is more economical overall or there is no practical alternative to the relevant course of action, including where the same is mandated by UU Water’s Standards); or
- (b) existing or alternative apparatus at a depth greater than the depth at which the existing apparatus was situated save for where the requirement for a greater depth cannot reasonably be avoided, (a “Betterment”).
- (10) The twinning of assets crossing the authorised works or similar initiatives to provide resilience to UU Water’s network in accordance with the prevailing business and engineering requirements may be necessary, in circumstances in which the proposed authorised works will compromise the future access or present an unacceptable operational or business risk to the relevant asset (without interference with the authorised work), and such twinning or similar arrangement is not Betterment. Where UU Water can demonstrate on a case by case basis that the particular asset is critical (for example, it is critical to the provision of water or wastewater services, or the authorised works cannot accommodate a like for like asset replacement, or there is no alternative means of maintaining services to customers by bypassing the asset under the authorised works), the twinning of assets crossing the authorised works or similar arrangement is not Betterment.
- (11) Where UU Water has elected to place apparatus which is assessed and agreed by UU Water as Betterment, the undertaker shall not be required to cover any additional cost associated with that Betterment. Any such assessment and decision by UU Water on whether such apparatus is Betterment or not shall always be made by UU Water acting reasonably.
Indemnity
148
- (1) If by reason of the authorised works any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of UU Water, or there is any material interruption in any service provided, or in the supply of any goods by UU Water, or UU Water has to take action to protect the services to its customers, or UU Water elects to use its statutory powers, the undertaker must—
- (a) bear and pay the cost reasonably incurred by UU in making good such damage or restoring the supply or use of the UU Water’s statutory powers; and
- (b) make reasonable compensation to UU Water for any other expenses, loss, damages, penalty or costs suffered or incurred and documented by UU Water, by reason of any such damage or interruption or use of UU Water’s statutory powers,
provided always that UU Water makes all reasonable endeavours to mitigate any such expenses, losses, damages, penalties or costs.
- (2) The fact that any act or thing may have been done by UU Water on behalf of the undertaker or in accordance with a plan approved by UU Water or in accordance with any requirement of UU Water or under its supervision does not, excuse the undertaker from liability under the provisions.
- (3) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of UU Water, its officers, servants, contractors or agents.
- (4) Notwithstanding any paragraph or sub-paragraph of this Part of the Schedule, the undertaker shall under no circumstances be liable for any consequential loss or indirect loss suffered by UU Water.
Enactments and agreements
149
Except where this Part of this Schedule provides otherwise, nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and UU Water in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
Co-operation
150
- (1) Where in consequence of the proposed construction of any part of the authorised works, the undertaker or UU Water requires the removal of apparatus under paragraph 144(2) or UU Water makes requirements for the protection or alteration of apparatus under paragraph 146, the undertaker must use all reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised works and taking into account the need to ensure the safe and efficient operation of UU Water’s undertaking, using existing processes where requested by UU Water, provided it is appropriate to do so, and UU Water must use its reasonable endeavours to co-operate with the undertaker for that purpose.
- (2) For the avoidance of doubt whenever UU Water’s consent, agreement or approval is required in relation to plans, documents or other information submitted by UU Water or the taking of action by UU Water, it must not be unreasonably withheld or delayed.
- (3) Where the undertaker identifies any apparatus which may belong to or be maintainable by UU Water but which does not appear on any statutory map kept for the purpose by UU Water, it shall inform UU Water of the existence and location of the apparatus as soon as is reasonably practicable.
- (4) Where UU Water identifies any apparatus which may belong to others but which does not appear on any statutory map kept for the purpose by UU Water, it shall inform the undertaker of the existence and location of the apparatus as soon as is reasonably practicable.
- (5) The undertaker shall notify UU Water of any hazardous material/contamination encountered in land involving UU apparatus or where sub-paragraphs (a), (b) and/or (c) of the definition of Specified Works applies. UU Water shall likewise notify the undertaker where it believes there is a risk that the undertaker may encounter hazardous material/contamination in such land.
Access
151
If in consequence of any agreement reached in accordance with paragraph 139(1) or the powers conferred by this Order the access to any apparatus is materially obstructed, the undertaker shall seek to provide such alternative rights and means of access to such apparatus, to the extent that provision of such rights and means of access is within the ability of the undertaker to grant, as will enable UU Water to maintain or use the apparatus no less effectively than was possible before such obstruction.
Arbitration
152
Save for differences or disputes arising under paragraph 141(4) any difference or dispute arising between the undertaker and UU Water under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and UU Water, be determined by arbitration in accordance with article 47 (arbitration).
Notices
153
Notwithstanding article 45 (service of notices) any plans submitted to UU Water by the undertaker must be sent via email to UU Water s and sent to the General Counsel Department at UU Water’s registered office or such other address as UU Water may from time to time appoint instead for that purpose and notify to the undertaker in writing.
PART 13 — For the protection of United Kingdom Oil Pipelines Limited
154
For the protection of United Kingdom Oil Pipelines Limited
Application
155
The provisions of this Part have effect unless otherwise agreed in writing between the undertaker and UKOP.
Interpretation
156
In this Part—
- “1991 Act” means the New Roads and Street Works Act 1991;
- “alternative apparatus” means alternative apparatus adequate to enable UKOP to fulfil its functions as a private commercial fuel pipeline operator/transporter in a manner no less efficient than previously;
- “apparatus” means the whole or any part of any pipeline cable or other apparatus owned or operated by UKOP (or its authorised agents) used in connection with the transmission of hydrocarbon fuel together with any other plant and equipment ancillary thereto (which includes any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus);
- “authorised works” has the same meaning as is given to the term “authorised development” in article 2(1) of this Order and for the purposes of this Part of this Schedule includes the use and maintenance of the authorised works and construction of any works authorised by this Schedule;
- “commence” and “commencement” in this Part of this Schedule shall include any below ground surveys, monitoring, ground work operations or the receipt and erection of construction plant and equipment;
- “deed(s) of consent” means any deed of consent, crossing agreement, deed of variation or new deed agreed between the parties acting reasonably in order to vary or replace existing easements, leases, agreements, enactments and other such interests so as to secure land rights and interests as are necessary to carry out, maintain, operate and use the apparatus in a manner consistent with the terms of this Part of this Schedule;
- “ground mitigation scheme” means a scheme approved by UKOP (such approval not to be unreasonably withheld or delayed) setting out the necessary measures (if any) for a ground subsidence event;
- “ground monitoring scheme” means a scheme for monitoring ground subsidence which sets out the apparatus which is to be subject to such monitoring, the extent of land to be monitored, the manner in which ground levels are to be monitored, the timescales of any monitoring activities and the extent of ground subsidence which, if exceeded, shall require the undertaker to submit for UKOP’s approval a ground mitigation scheme;
- “ground subsidence event” means any ground subsidence identified by the monitoring activities set out in the ground monitoring scheme that has exceeded the level described in the ground monitoring scheme as requiring a ground mitigation scheme;
- “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over across along or upon land;
- “maintain” and “maintenance” shall include the ability and right to do any of the following in relation to any apparatus or alternative apparatus of UKOP including construct, use, repair, alter, inspect, renew or remove the apparatus;
- “plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed;
- “specified works” means any of the authorised works or activities undertaken in association with the authorised works which will or may be situated over, or within 15 metres measured in any direction of any apparatus the removal of which has not been required by the undertaker under paragraph 157(2) or otherwise; and/or may in any way adversely affect any apparatus the removal of which has not been required by the undertaker under paragraph 157(2) or otherwise;
- “UKOP” means United Kingdom Oil Pipelines Limited (Co. No.00746709) whose registered office is at 5-7 Alexandra Road, Hemel Hempstead, Hertfordshire, HP2 5BS; and
- “undertaker” means the undertaker as defined in article 2(1) of this Order.
On Street Apparatus
157
Except for paragraph 161 (retained apparatus) and 162 (expenses and costs) of this Part of this Schedule which will apply in respect of the exercise of all or any powers under the Order affecting the rights and apparatus of UKOP, the other provisions of this Schedule do not apply to apparatus in respect of which the relations between the undertaker and UKOP are regulated by the provisions of Part 3 of the 1991 Act.
Acquisition or possession of land
158
- (1) Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference to the Order, the undertaker may not (a) appropriate or acquire or take temporary possession of any apparatus or (b) appropriate, acquire, extinguish, interfere with or override any easement, other interest or right and/or apparatus of UKOP otherwise than by agreement (all such agreement(s) not to be unreasonably withheld or delayed) and unless it grants replacement rights to UKOP in a form agreed between the parties in accordance with the provisions of paragraph 159 (Removal of apparatus) or paragraph 160 (UKOP Replacement facilities and rights).
- (2) As a condition of any agreement between the parties in sub-paragraph (1), prior to the carrying out of any part of the authorised works (or in such other timeframe as may be agreed between UKOP and the undertaker) that is subject to the requirements of this Part of this Schedule that will cause any conflict with or breach the terms of any easement or other legal or land interest of UKOP or affect the provisions of any enactment or agreement regulating the relations between UKOP and the undertaker in respect of any apparatus laid or erected in land belonging to or secured by the undertaker, the undertaker must as UKOP reasonably requires enter into such deeds of consent upon such terms and conditions as may be agreed between UKOP and the undertaker, both acting reasonably, and which must be no less favourable on the whole to UKOP unless otherwise agreed by UKOP, and it will be the responsibility of the undertaker to procure and/or secure the consent and entering into of such deeds and variations by all other third parties with an interest in the land at that time who are affected by such authorised works.
- (3) The undertaker and UKOP agree that where there is any inconsistency or duplication between the provisions set out in this Part of this Schedule relating to the relocation and/or removal of apparatus/including but not limited to the payment of costs and expenses relating to such relocation and/or removal of apparatus) and the provisions of any existing easement, rights, agreements and licences granted, used, enjoyed or exercised by UKOP and/or other enactments relied upon by UKOP as of right or other use in relation to the apparatus, then the provisions in this Schedule shall prevail.
- (4) Any agreement or consent granted by UKOP under paragraph 161 or any other paragraph of this Part of this Schedule, shall not be taken to constitute agreement under sub-paragraph (1).
Removal of apparatus
159
- (1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed or requires that UKOP’s apparatus is relocated or diverted, that apparatus must not be removed under this Part, and any right of UKOP to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed and is in operation to the reasonable satisfaction of UKOP in accordance with sub-paragraphs (2) to (5).
- (2) If, for the purpose of executing any works in, on, under or over any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to UKOP advance written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order UKOP reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), secure any necessary consents for the alternative apparatus and afford to UKOP to its reasonable satisfaction (taking into account paragraph 160(1) below) the necessary facilities and rights
- (a) for the construction of alternative apparatus in other land of or land secured by the undertaker; and
- (b) subsequently for the maintenance of that apparatus.
- (3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of or land secured by the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed, UKOP must, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances in an endeavour to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed save that this obligation shall not extend to the requirement for UKOP to use its compulsory purchase powers to this end.
- (4) Any alternative apparatus to be constructed in land of or land secured by the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between UKOP and the undertaker.
- (5) UKOP must, after the alternative apparatus to be provided or constructed has been agreed, and subject to a written diversion agreement having been entered into between the parties and the grant to UKOP of any such facilities and rights as are referred to in sub-paragraphs (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule
UKOP replacement facilities and rights
160
- (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker is to afford to or secure for UKOP facilities and rights in land for the construction, use, maintenance and protection of apparatus either in substitution for apparatus to be removed (or where existing rights are being sterilized), deeds of consent must be granted upon such terms and conditions as may be agreed between the undertaker and UKOP both acting reasonably and must be no less favourable on the whole to UKOP than the facilities and rights enjoyed by it previously in respect of the apparatus unless otherwise agreed by UKOP and it will be the responsibility of the undertaker to procure and/or secure the consent and entering into of such deeds and variations by all other third parties with an interest in the land at that time who are affected by such authorised works.
- (2) If the facilities and rights to be afforded by the undertaker pursuant to sub-paragraph (1) above, and the terms and conditions subject to which those facilities and rights are to be granted, are less favourable on the whole to UKOP than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the matter may be referred to arbitration in accordance with paragraph 166 (Arbitration) of this Part of this Schedule the arbitrator must make such provision for the payment of compensation by the undertaker to UKOP as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
Retained apparatus
161
- (1) Not less than 56 days before the commencement of any specified works the undertaker must submit to UKOP a plan and, if reasonably required by UKOP, a ground monitoring scheme in respect of those works taking place within 20 metres of the apparatus.
- (2) The plan to be submitted to UKOP under sub-paragraph (1) must include a method statement and describe—
- (a) the exact position of the works and details of any infrastructure machinery or vehicles to be used in connection therewith;
- (b) the level at which these are proposed to be constructed or renewed;
- (c) the manner of their construction or renewal including details of all excavation, positioning of plant etc and any works’ compounds;
- (d) the position of all apparatus and fencelines;
- (e) by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus; and
- (f) any intended maintenance regimes.
- (3) In relation to any works which will or may be situated within 6.1 metres measured in any direction of any apparatus (the removal of which has not been required by the undertaker under paragraph 157(2) or otherwise), the plan to be submitted under sub-paragraph (1) must also describe—
- (a) details of any trench design including route, dimensions and clearance to the apparatus;
- (b) demonstration that the apparatus will not be affected prior to, during and post construction; and
- (c) details of load bearing capacities of trenches.
- (4) The undertaker must not commence any works to which sub-paragraphs (1), (2) or (3) apply until UKOP has given written approval of the plan so submitted.
- (5) UKOP may within 10 working days of initial receipt of the plan submitted under sub-paragraph (1) raise any additional questions or comments or request further information and/or clarification in relation to the plan.
- (6) Any approval of UKOP required under sub-paragraph (4):
- (a) may be given subject to reasonable conditions for any purpose mentioned in sub-paragraphs (8) or (10); and
- (b) must not be unreasonably withheld or delayed.
- (7) UKOP is deemed to have approved the plan as submitted under sub-paragraph (1) if UKOP has not intimated its approval or disapproval of the plan, and the grounds of that disapproval, within 30 working days after the plan or the responses to any additional questions, comments, further information or clarification raised or requested under sub-paragraph (5) has been received by UKOP.
- (8) In relation to any work to which sub-paragraphs (1), (2) and/or (3) apply, UKOP may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its apparatus against interference or risk of damage for the provision of protective works or for the purpose of providing or securing proper and convenient means of access to any apparatus.
- (9) Works executed under sub-paragraphs (1) or (2) must be executed in accordance with the plan, submitted under sub-paragraph (1) or as relevant sub-paragraph (6), as approved or as amended from time to time by agreement between the undertaker and UKOP and in accordance with such reasonable requirements as may be made in accordance with sub-paragraphs (8) or (10) by UKOP for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and UKOP will be entitled to watch and inspect the execution of those works.
- (10) Where UKOP reasonably requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to UKOP’s satisfaction, acting reasonably, prior to the commencement of any specified works for which protective works are required and UKOP give notice of its requirement for such works within 42 days of the date of submission of a plan pursuant to this paragraph (except in an emergency).
- (11) If UKOP in accordance with sub-paragraphs (8) or (10) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, sub-paragraphs (1) to (4) and (8) to (10) apply as if the removal of the apparatus had been required by the undertaker under paragraph 159(2).
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.