The Associated British Ports (Immingham Green Energy Terminal) Order 2025
- (3) The landscape and ecology measures approved under sub-paragraph (1) must be carried out, established and maintained in accordance with the details approved under sub-paragraph (1).
- (4) Where any tree or shrub planted pursuant to this paragraph that, within a period of five years after planting, is removed, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased, that tree or shrub must be replaced by the undertaker in the first available planting season with a specimen of the same species and size as that originally planted, unless otherwise approved by the relevant planning authority.
Woodland compensation plan
11
The woodland compensation plan must be complied with, unless otherwise approved by the relevant planning authority.
Surface water drainage
12
- (1) No part of Work No. 1 outside of the UK marine area, Work Nos. 2, 3, 5 or 7 (except the clearance of trees or other vegetation from Long Strip) may be commenced until the drainage strategy for that part has been submitted to and approved by the relevant planning authority, following consultation with the Environment Agency and the Board on matters related to their respective functions.
- (2) Any drainage strategy submitted and approved under sub-paragraph (1) must be substantially in accordance with the outline drainage strategy contained in appendix 18.B of the environmental statement.
- (3) Each part of Work No. 1 outside of the UK marine area, Work Nos. 2, 3, 5 and 7 must be carried out in accordance with the drainage strategy approved under sub-paragraph (1) for that part, unless otherwise approved by the relevant planning authority.
Flood risk assessment
13
The authorised project outside of the UK marine area must be carried out and operated in accordance with the approved flood risk assessment contained in appendix 18A of the environment statement, unless otherwise approved by the relevant planning authority.
Queens Road residential properties
14
- (1) No part of Work No. 7 may be brought into operational use until, in respect of the Queens Road residential properties—
- (a) the undertaker has entered on and taken possession of all of the Queens Road residential properties following either compulsory acquisition pursuant to article 22 (compulsory acquisition of land) of this Order or acquisition of it by agreement by the Company or Air Products (whether before or after the date of this Order);
- (b) the use of all of the Queens Road residential properties for residential purposes has ceased; and
- (c) notice confirming such possession and cessation of use has been served on the relevant planning authority.
- (2) From the date of the notice served on the relevant planning authority pursuant to sub-paragraph (1), no part of the Queens Road residential properties may be used for residential purposes for so long as any part of Work No. 7 is in operational use.
- (3) In this article—
- (a) “Queens Road residential properties” means the land comprised in plots 5/3, 5/4, 7/15, 7/16, 7/17, 7/18, 7/20, 7/21, 7/22 or 7/23 shown on the land plans and described in the book of reference; and
- (b) “residential purposes” means any use falling within a class set out in Part C of Schedule 1 to the Town and Country Planning (Use Classes) Order 1987 (as in force at the date of this Order) or any other use for residential purposes.
Contaminated land
15
- (1) No part of Work No. 1 outside of the UK marine area, Work Nos. 2 to 7 (except the clearance of trees or other vegetation from Long Strip) may be commenced until a written remediation strategy applicable to that part to deal with any contamination of that applicable land which is likely to cause significant harm to persons or pollution of controlled waters or the environment has been submitted to and approved by the relevant planning authority, following consultation with the Environment Agency on matters related to its function.
- (2) In the event that any unexpected contamination is discovered during the construction of any part of Work No. 1 outside of the UK marine area, Work Nos. 2 to 7, the part of the works to which the contamination relates must cease until a site investigation and assessment report applicable to that part and, if necessary, a remediation strategy to deal with any contamination which is likely to cause significant harm to persons or pollution of controlled waters or the environment has been submitted to and approved by the relevant planning authority, following consultation with the Environment Agency on matters related to its function.
- (3) Any remediation strategy submitted under sub-paragraphs (1) or (2) must be substantially in accordance with the outline remediation strategy contained in appendix 21.C of the environmental statement.
- (4) Any remediation required pursuant to sub-paragraphs (1) or (2) must be carried out in accordance with the remediation strategy approved pursuant to sub-paragraphs (1) or (2) (as the case may be) unless otherwise approved by the relevant planning authority.
- (5) Any verification report required by a remediation strategy approved pursuant to sub-paragraphs (1) or (2) must be submitted to the relevant planning authority in accordance with that remediation strategy.
External lighting
16
- (1) No part of the authorised project within Work No. 1 outside of the UK marine area, pr Work Nos. 2, 3, 5 and 7 may be brought into operational use until a written scheme of the proposed operational external lighting relating to that part has been submitted to and approved by the relevant planning authority.
- (2) Any scheme submitted and approved under sub-paragraph (1) must be substantially in accordance with the lighting assessment report contained in appendix 2.B of the environmental statement.
- (3) Each part of Work No. 1 outside of the UK marine area, Work Nos. 2, 3, 5 and 7 must be operated in accordance with the scheme approved under sub-paragraph (1) for that part, unless otherwise approved by the relevant planning authority.
Control of noise during operational use
17
- (1) No part of the authorised project comprised in Work Nos. 3, 5 or 7 may be brought into operational use until a scheme for noise management (addressing any parts of Work Nos. 3, 5 and 7 to which the application relates together with any parts in respect of which a scheme has previously been approved) has been submitted to and approved by the relevant planning authority.
- (2) Any scheme submitted and approved under sub-paragraph (1) must demonstrate that the effects of noise on the noise sensitive receptors identified in chapter 7 of the environmental statement are no worse than the residual effects identified in that chapter.
- (3) Each part of Work Nos. 3, 5 and 7 must be operated in accordance with the scheme approved under sub-paragraph (1) for that part, unless otherwise approved by the relevant planning authority.
Decommissioning environmental management plan
18
- (1) Prior to the decommissioning of (in each case) the entirety of Work Nos. 2 (except the jetty access road), 3, 4, 5, 6 or 7, a decommissioning environmental management plan for that part of the authorised project must be submitted to and approved by the relevant planning authority, following consultation with the Environment Agency on matters related to its function.
- (2) Any decommissioning environmental management plan submitted and approved under sub-paragraph (1) must be substantially in accordance with the outline decommissioning environmental management plan.
- (3) The decommissioning of (in each case) the entirety of Work Nos. 2 (except the jetty access road), 3, 4, 5, 6 or 7 must be carried out in accordance with the approved decommissioning environmental management plan for that part of the authorised project unless otherwise approved by the relevant planning authority.
Operational travel plan
19
- (1) No part of the authorised project comprised in Work Nos. 3, 5 or 7 may be brought into operational use until an operational travel plan relating to that part of the authorised project has been submitted to and approved by the relevant planning authority.
- (2) Any operational travel plan submitted and approved under sub-paragraph (1) must be substantially in accordance with the outline operational travel plan.
- (3) Each part of Work Nos. 3, 5 and 7 must be operated in accordance with the approved operational travel plan for that part, unless otherwise approved by the relevant planning authority.
Operational phase flood emergency response plans
20
- (1) No part of Work No. 1 outside of the UK marine area, Work Nos. 2, 3, 5 or 7 may be brought into operational use until a flood emergency response plan to apply during operation of that part has been submitted to and approved by the relevant planning authority, following consultation with North East Lincolnshire Council in its capacity as lead local flood authority (within the meaning of section 6 (other definitions) of the Flood and Water Management Act 2010107) and the Environment Agency on matters related to their respective functions.
- (2) Any flood emergency response plan submitted and approved under sub paragraph (1) must be substantially in accordance with the flood risk assessment contained in appendix 18.A of the environmental statement.
- (3) Each part of Work No. 1 outside of the UK marine area, Work Nos. 2, 3, 5 and 7 must be operated in accordance with the plan approved under sub-paragraph (1) for that part, unless otherwise approved by the relevant planning authority.
Flood Defence Agreement
21
No part of the authorised project shall be commenced until a Flood Defence Agreement between the Applicant and the Environment Agency regarding the reconstruction, future ownership, operation and maintenance of the flood defence that will be impacted by the authorised project, has been submitted to and approved by the Local Planning Authority. The authorised project must be carried out in accordance with the approved agreement.
SCHEDULE 3 — DEEMED MARINE LICENCE
PART 1 — GENERAL
Interpretation
1
In this Schedule—
- “the 2008 Act” means the Planning Act 2008;
- “the 2009 Act” means the Marine and Coastal Access Act 2009108;
- “the 2017 Regulations” means the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017;
- “2023 sediment sampling plan” means— the document of that name identified in the table at Schedule 15 (documents and plans to be certified) of the Order and which has been certified by the Secretary of State as the 2023 sediment sampling plan for the purposes of the Order, which sets out— a detailed dredging methodology; dredge locations; dredge amounts (total and annual, if applicable); dredge depths; duration of dredging activities; whether the dredge is a capital dredging activity or a maintenance dredging activity; and specific gravity of the material or material type; and any sediment sampling analyses submitted to the MMO related to the plan to which sub-paragraph (a) refers prior to its expiry;
- “the authorised development” has the meaning given in paragraph 3(2);
- “business day” means a day other than a Saturday or Sunday, Good Friday, Christmas Day or a bank holiday in England and Wales under section 1 of the banking and Financial Dealings Act 1971;
- “business hours” means the period from 09:00 until 17:00 on any business day;
- “capital dredge” means dredging to a depth not previously dredged, or to a depth not dredged within the last 10 years and is generally undertaken to create or deepen navigational channels, berths or to remove material deemed unsuitable for the foundation of a construction project and “capital dredging” is to be construed accordingly;
- “Chart Datum” means 3.9 m below ordinance datum (Newlyn), corresponding with a depth of 7.6m of the outer sill of the Port of Immingham;
- “cold weather construction restriction strategy” means the strategy of that description referred to in paragraph 11 of this Schedule;
- “commence” means beginning to carry out any part of a licensed activity and “commenced” and “commencement” are to be construed accordingly;
- “condition” means a condition in Part 2 and Part 3 of this licence and references in this licence to numbered conditions are to the conditions with those numbers in Part 2;
- “consolidated dredged materials” mean materials including glacial clay with a diameter of less than 31.25 micrometres and gravel with a diameter of at least 2 and less than 64 millimetres;
- “environmental statement” means the document of that name identified in the table at Schedule 15 (documents and plans to be certified) of the Order and which has been certified by the Secretary of State as the environmental statement for the purposes of the Order;
- “existing marine licence” means licence L/2014/00429 and any variation to it or any subsequent equivalent successor licence as may be granted that permits the disposal of dredged arisings from the Port of Immingham;
- “flood risk assessment” means the flood risk assessment contained in appendix 18A of the environmental statement;
- “further sediment sampling plan” means— any further sediment sampling plan approved by the MMO in accordance with paragraph 9(2) of this Schedule which sets out— a detailed dredging methodology; dredge locations; dredge amounts (total and annual, if applicable); dredge depths; duration of dredging activities; whether the dredge is a capital dredging activity or a maintenance dredging activity; and specific gravity of the material or material type; and any sediment sampling analyses submitted by the MMO related to the plan to which sub-paragraph (a) refers prior to its expiry;
- “high water” means daily high tides in every lunar day;
- “HU056” means the area bounded by co-ordinates (53°39.3000’N, 00°10.4898’W), (53°39.0499’N, 00°10.4700’W), (53°38.8201’N, 00°09.4398’W), (53°39.3000’N, 00°10.4898’W);
- “HU060” means the area bounded by co-ordinates (53°39.3000’N, 00°10.4898’W) (53°38.7499’N, 00°10.4536W); (53°38.7575’N, 00°10.4677’W), (53°38.7648’N, 00°10.4823’W), (53°38.7718’N, 00°10.4974’W), (53°38.7784’N, 00°10.5128’W), (53°38.7847’N, 00°10.5287’W), (53°38.7906’N, 00°10.5450’W), (53°38.7962’N, 00°10.5617’W), (53°38.8013’N, 00°10.5787’W), (53°38.8061’N, 00°10.5960’W), (53°38.8105’N, 00°10.6136’W), (53°38.8145’N, 00°10.6315’W), (53°38.8181’N, 00°10.6496’W), (53°38.8213’N, 00°10.6679’W), (53°38.8240’N, 00°10.6864’W), (53°38.8264’N, 00°10.7051’W), (53°38.8283’N, 00°10.7239’W), (53°38.8298’N, 00°10.7428’W), (53°38.8309’N, 00°10.7618’W), (53°38.8315’N, 00°10.7809’W), (53°38.8317’N, 00°10.8000’W), (53°38.8315’N, 00°10.8191’W), (53°38.8309’N, 00°10.8382’W), (53°38.8298’N, 00°10.8572’W), (53°38.8283’N, 00°10.8761’W), (53°38.8264’N, 00°10.8949’W), (53°38.8240’N, 00°10.9136’W), (53°38.8213’N, 00°10.9321’W), (53°38.8181’N, 00°10.9504’W), (53°38.8145’N, 00°10.9685’W), (53°38.8105’N, 00°10.9864’W), (53°38.8061’N, 00°11.0040’W), (53°38.8013’N, 00°11.0213’W), (53°38.7962’N, 00°11.0383’W), (53°38.7906’N, 00°11.0550’W), (53°38.7847’N, 00°11.0713’W), (53°38.7784’N, 00°11.0872’W), (53°38.7718’N, 00°11.1026’W), (53°38.7648’N, 00°11.1177’W), (53°38.7575’N, 00°11.1323’W), (53°38.7499’N, 00°11.1464’W), (53°38.7439’N, 00°11.1567’W), (53°38.7438’N, 00°11.1564’W), (53°38.5320’N, 00°10.8000’W), (53°38.7438’N, 00°10.4436’W) and (53°38.7439’N, 00°10.4434’W);
- “licensable activity” means an activity licensable under section 66 of the 2009 Act;
- “licensed activity” means any activity authorised in paragraph 3 of this Schedule;
- “maintenance dredge” means a dredge undertaken to keep channels, berths and other areas at their designed depths, involving removing recently accumulated sediments such as mud, sand and gravel to a level that is not lower than it has been at any time during the past 10 years and “maintenance dredging” is to be construed accordingly;
- “marine piles” means piles that will be in a free water condition during construction;
- “MCMS” means the Marine Case Management System provided by the MMO;
- “mean high water springs” means the average of high water heights occurring at the time of spring tides;
- “mean low water springs” means the average of low water heights occurring at the time of spring tides;
- “the MMO” means the Marine Management Organisation;
- “outline marine written scheme of investigation” means the outline marine archaeological written scheme of investigation contained in appendix 15B to the environmental statement;
- “Notice to Mariners” means any notice to mariners which may be issued by the Admiralty, Trinity House, the King’s harbour masters, government departments or harbour and pilotage authorities advising mariners of important matters affecting navigational safety;
- “the Order” means the Associated British Ports (Immingham Green Energy Terminal) Order 2025;
- “outline construction environmental management plan” means the document of that name identified in the table at Schedule 15 (documents and plans to be certified) of the Order and which has been certified by the Secretary of State as the outline construction environmental management plan for the purposes of the Order;
- “percussive piles” means driven piles but excludes the handling, placing and vibro-driving of piles;
- “percussive piling” for the purposes of this licence means the driving of piles by percussive means but does not include the handling, placing or vibro-driving of piles and a “marine pile” means a pile which will, during construction, be in a free-water state;
- “the Port of Immingham” has the meaning given in the Order;
- “relevant planning authority” has the meaning given in the Order;
- “the River Humber” means the tidal estuary from its mouth at the Spurn Peninsula to its confluence with the rivers Ouse and Trent;
- “subtidal” means areas of the bed of the estuary permanently submerged throughout the tidal cycle;
- “unconsolidated dredged materials” mean materials including alluvial sand with a diameter of at least 62.5 micrometres and less than two millimetres, alluvial silt with a diameter of at least 31.25 and less than 62.5 micrometres and gravel with a diameter of at least 2 and less than 64 millimetres;
- “undertaker” has the meaning given to “undertaker” in article 2 (interpretation) of the Order;
- “vessels” means every description of vessel, however propelled or moved, and includes a displacement and non-displacement craft, a personal watercraft, a seaplane on the surface of the water, a hydrofoil vessel, a hovercraft or any other amphibious vehicle and any other thing constructed or adapted for movement through, in, on or over in water and which is at the time in, on, or over water; and
- “the works plans” means the plans of that name identified in the table at Schedule 15 (documents and plans to be certified) and which is certified by the Secretary of State as the works plans for the purposes of the Order.
- (2) Unless otherwise specified, all geographical co-ordinates given in this Schedule are in latitude and longitude degrees and minutes to four decimal places.
- (3) Tonnages of dredged materials are expressed in wet tonnes.
- (4) References to sunset and sunrise are, unless otherwise agreed with the MMO, to be in accordance with the relevant daily set and rise times for the British Isles provided by HM Nautical Almanac Office.
Contacts
2
- (1) Unless otherwise advised in writing by the MMO, the address for postal correspondence with the MMO for the purposes of this licence is the Marine Management Organisation, Marine Licensing Team, Lancaster House, Hampshire Court, Newcastle upon Tyne NE4 7YH, telephone 0300 123 1032 and, unless otherwise advised in writing, where contact to the local MMO office (local office) is required, the following contact details must be used: Marine Management Organisation, The MMO District Office - Crosskill House, Mill Lane, Beverley, HU17 9JB, telephone 0208 720 1344, email – beverley@marinemanagement.org.uk.
- (2) Unless otherwise advised in writing by the MMO, the address for electronic communication with the MMO for the purposes of this licence is marine.consents@marinemanagement.org.uk or where contact to the local MMO office is required is beverley@marinemanagement.org.uk.
- (3) Unless otherwise advised in writing by the MMO, MCMS must be used for all licence returns or applications to vary this licence. The MCMS address is: https://marinelicensing.marinemanagement.org.uk/mmofox5/fox/live/MMO_LOGIN/login.
- (4) Unless otherwise stated in writing by the MMO, all notifications required by this licence must be sent by the undertaker to the MMO using MCMS.
Licensed marine activities
3
- (1) Subject to the licence conditions in Part 2, this licence authorises the undertaker to carry out licensable marine activities under section 66(1) (licensable marine activities) of the 2009 Act which—
- (a) form part of, or are related to, the authorised development; and
- (b) are not exempt from requiring a marine licence by virtue of any provision made under section 74 (exemption specified by order) of the 2009 Act.
- (2) For the purposes of this licence “the authorised development” means the construction, operation and maintenance of a liquid bulk facility on the River Humber comprising—
- (a) within the area shown as Work No.1a on the works plans—
- (i) an open piled approach jetty carrying on its surface a roadway, a footway, pipes, pipework and utilities and lighting, rising from ground level to cross over existing flood defence infrastructure and then extending from the shore in a north easterly direction connecting to a jetty head;
- (ii) a jetty head comprising structures including loading and unloading platforms with mechanical loading arms, two breasting dolphins with fenders, each with a gangway tower and eight mooring dolphins linked by walkways;
- (iii) four monopiles located in front of the jetty head or loading platform to provide fendering for smaller vessels;
- (iv) a jetty head building, a separate refuge building with attached office, water closet and external safety shower, an electrical building, shelters, pump housing and pump canister;
- (v) a jetty operations building located near the landside end of the jetty to house control room functions including switch room, operations room and welfare facilities;
- (vi) topside infrastructure installed on the jetty to load and unload vessels including marine loading arms, gangways, pipes, piping, valves and other process equipment, maintenance access roadways and access ramps;
- (vii) lighting infrastructure, utilities and electrical systems including firewater systems, communication systems and security systems;
- (viii) piling works and construction operations within the River Humber;
- (b) within the area shown as Work No.1 on sheets 1, 2, 3 and 4 of the works plans, capital dredging works within the River Humber related to the works to which paragraph 3(2)(a) refers and the disposal of any arisings from such dredging;
- (c) activities including works to—
- (i) alter, clean, modify, dismantle, refurbish, reconstruct, carry out excavations and clearance (excluding clearance or detonation of ordnance), deepen, scour and cleanse;
- (ii) temporarily remove, alter, strengthen, interfere with, occupy and use the banks, bed, foreshore and waters of the River Humber;
- (iii) remove, relocate or replace any work or structure;
- (iv) construct, place and maintain works and structures including piled fenders; and
- (v) alter the course or otherwise interfere with navigable or non-navigable watercourses;
- (d) such other works as may be necessary or convenient for the purposes of, or in connection with or in consequence of, the construction, maintenance, operation or use of the authorised development, including works for the accommodation or convenience of vessels (including but not limited to berthing and mooring facilities, ladders, buoys, bollards, dolphins, fenders and pontoons) and lighting.
Licence to dredge and deposit
4
- (1) Subject to paragraph 5, the undertaker is permitted to undertake a capital dredge to a depth of 14.5 metres below chart datum (with an allowance for the tolerances of the dredging equipment) of the berth pocket, the grid coordinates for which are specified in paragraph 5(2).
- (2) The materials dredged may not exceed the approximate quantities and must be deposited at the locations set out in the following table—
| Material | Volume (m3) | Specific gravity | Maximum tonnage (wet tonnes) | Disposal site |
|---|---|---|---|---|
| Unconsolidated | 3,900 | 1.35 | 5,265 | HU060 |
| Consolidated | 100 | 2.26 | 226 | HU056 |
- (3) It is acknowledged that pursuant to section 75 of the 2009 Act the undertaker does not need a marine licence to carry out maintenance dredging within the statutory harbour authority area of the Port of Immingham and that the disposal of dredged arisings for such maintenance dredging is permitted in accordance with the existing marine licence.
- (4) Arisings of consolidated and unconsolidated materials from the capital dredge must be deposited at HU056 or HU060.
- (5) It is noted that arisings of unconsolidated materials from maintenance dredging must be deposited at HU060 in accordance with the existing marine licence.
Details of licensed marine activities
5
- (1) The grid coordinates within the UK marine area within which the undertaker may carry out a licensed activity (save for the capital dredge and disposal of any arisings from such dredge to which paragraph 3(2)(b) refers) are specified below—
| Point reference | Latitude | Longitude |
|---|---|---|
| 1 | 53.622880 | -0.169136 |
| 2 | 53.623860 | -0.167200 |
| 3 | 53.627714 | -0.157052 |
| 4 | 53.630360 | -0.155051 |
| 5 | 53.628116 | -0.145503 |
| 6 | 53.624711 | -0.147881 |
| 7 | 53.624489 | -0.153444 |
| 8 | 53.621258 | -0.164738 |
- (2) No capital dredging may be carried out by the undertaker other than within the area of the River Humber bounded by the grid coordinates specified below and identified as Work No. 1 on sheets 1, 2, 3 and 4 of the works plans—
| Point reference | Latitude | Longitude |
|---|---|---|
| 1 | 53.627888 | -0.155204 |
| 2 | 53.628925 | -0.154488 |
| 3 | 53.627495 | -0.148612 |
| 4 | 53.626455 | -0.149329 |
PART 2 — CONDITIONS APPLYING TO ALL LICENSABLE ACTIVITIES
General
6
- (1) With respect to any provision of this Schedule which requires the licensed activities to be carried out in accordance with documents, strategies, information, plans, protocols or statements approved by the MMO prior to or under this licence, the documents, strategies, information, plans, protocols or statements so approved are taken to include amendments approved in writing by the MMO subsequent to the first approval of those documents, strategies, information, plans, protocols or statements provided it has been demonstrated to the satisfaction of the MMO that the subject matter of the relevant amendments does not give rise to any materially new or materially different environmental effects to those assessed in the environmental statement or in any environmental information supplied under the 2017 Regulations.
- (2) When any approval or agreement is required of, or with, the MMO pursuant to this Schedule such approval or agreement must not be given if it would give rise to any materially new or materially different significant effects on the environment that have not been assessed in the environmental statement or in any environmental information supplied under the 2017 Regulations.
Before licensed activities
Notifications regarding licensed activities
7
- (1) The undertaker must inform the MMO—
- (a) at least five business days prior to the commencement of the first licensed activity; and
- (b) within five business days following the completion of the final licensed activity,
of the commencement or the completion (as applicable).
- (2) The undertaker must provide the following information to the MMO—
- (a) the name and function in writing of any agent or contractor or sub-contractor that will carry on any licensed activity on behalf of the undertaker; and
- (b) such notification must be received by the MMO in writing not less than 24 hours before the commencement of the licensed activity.
- (3) The undertaker must ensure that a copy of this licence and any subsequent revisions or amendments has been provided to, read and understood by any agents, contractors, and sub-contractors that will be carrying out any licensed activity on behalf of the undertaker.
- (4) The undertaker must keep a copy of this license and any subsequent revisions or amendments available for inspection at its registered address and any site office location at or adjacent to a construction site.
- (5) Any changes to details supplied under sub-paragraph (2) must be notified to the MMO in writing no less than 24 hours prior to the agent, contractor or vessel engaging in the licensed activity in question.
- (6) Only those persons notified to the MMO in accordance with this condition are permitted to carry out a licensed activity.
- (7) Copies of this licence must be available for inspection at the following locations—
- (a) the undertaker’s office at the Port of Immingham; and
- (b) during the construction of the authorised development only, at any site office which is adjacent to or near the River Humber and which has been provided for the purposes of the construction of the authorised development.
- (8) The undertaker must request that the masters responsible for the vessels that will be carrying out any licensed activity on behalf of the undertaker as notified to the MMO under sub-paragraph (6) make a copy of this licence available for inspection on board such vessels during the carrying out of any licensed activity.
Construction environmental management plan
8
- (1) No licensed activities may be commenced until a construction environmental management plan for them has been submitted to and approved by the MMO following consultation with the relevant planning authority, the Environment Agency and Natural England on matters related to their function; and the submitted construction environmental management plan must be in accordance with the outline construction environmental management plan, unless otherwise approved in writing by the MMO.
- (2) Any construction environmental management plan submitted pursuant to sub-paragraph (1) and any construction environmental management plan submitted pursuant to paragraph 6(1) of Schedule 2 (requirements) of the Order may be comprised in the same document or separate documents.
Sediment sampling
9
- (1) Any sediment sampling analyses undertaken by a laboratory validated by the MMO and approved by the MMO as part of either the 2023 sediment sampling plan or any further sediment sampling plan are valid for a period of 3 years from the date when those analyses were undertaken.
- (2) Where the validity period for sediment sampling analyses set out in sub-paragraph (1) above expires, the undertaker must submit a further sediment sampling plan request to the MMO for its approval and any sediment sampling analyses from such further sediment sampling plan must be submitted to the MMO.
Agents, contractors and sub-contractors
10
- (1) The undertaker must notify the MMO in writing of any agents, contractors or sub- contractors that will carry on any licensed activity listed in paragraph 3 of this licence on behalf of the undertaker. Such notification must be received by the MMO no less than 24 hours before the commencement of the licensed activity.
- (2) The undertaker must ensure that a copy of this licence and any subsequent revisions or amendments has been provided to, read and understood by any agents, contractors or sub-contractors that will carry on any licensed activity listed in section 3 of this licence on behalf of the undertaker.
Cold weather construction restriction strategy
11
- (1) No construction operations for any licensed activity are to commence until a cold weather construction restriction strategy is submitted to and agreed by the MMO in consultation with Natural England. The strategy must include the following—
- (a) A provision that no construction operations (other than to finish driving any pile that is in the process of being driven at the point that the cold weather restriction comes into force) within 200 metres of exposed mudflat and at least 200 metres seaward of mean low water springs may take place following seven consecutive days of zero or sub zero temperatures (where the temperature does not exceed zero degrees centigrade for more than six hours in any day or any other formula as may be agreed with the MMO to define short periods of thaw);
- (b) The establishment of three temperature monitoring points within the Humber Estuary;
- (c) A provision that if the construction restriction comes into effect as a consequence of cold weather conditions, it will be reviewed as follows—
- (i) after 24 hours of above freezing temperatures the restriction will be lifted on a temporary basis provided that the weather forecast relevant for the area including the Port of Immingham, (as agreed with the MMO) indicates that freezing conditions will not return within five days; and
- (ii) after a further five clear days of above-freezing temperatures, the restrictions will be lifted entirely.
- (2) All licensed activities must be carried out in accordance with the cold weather construction restriction strategy approved pursuant to sub-paragraph (1), unless otherwise approved by the MMO.
Marine Noise Registry
12
- (1) Only when impact driven or part-driven pile foundations or detonation of explosives are proposed to be used as part of the foundation installation the undertaker must provide the following information to the Marine Noise Registry—
- (a) prior to the commencement of the licensed activities, information on the expected location, start and end dates of impact pile driving or detonation of explosives to satisfy the Marine Noise Registry’s Forward Look requirements; and
- (b) within 12 weeks of completion of impact pile driving or detonation of explosives, information on the exact locations and specific dates of impact pile driving or detonation of explosives to satisfy the Marine Noise Registry’s Close Out requirements.
- (2) The undertaker must notify the MMO of the successful provision to the Marine Noise Registry of Forward Look and Close-out requirements within 7 days of the submission.
Marine written scheme of archaeological investigation
13
Archaeological method statements, together with a written report on any consultation carried out with Historic England and the relevant planning authority on matters related to their respective functions in their preparation, must be submitted to and approved by the MMO in writing in accordance with the provisions of the outline marine written scheme of investigation and a subsequent update must be provided to the MMO six weeks before commencement of any licensed activity to which the method statement relates.
During licensed activities
Flood risk assessment
14
- (1) All licensed activities must be carried out in accordance with the flood risk assessment, unless otherwise approved by the MMO.
- (2) No part of the licensed activities may be brought into operational use until a flood emergency response plan to apply during operation of that part has been submitted to and approved by the MMO, following consultation with the Environment Agency on matters related to its functions.
- (3) Any a flood emergency response plan submitted and approved under sub-paragraph (2) must (so far as applicable) be substantially in accordance with the flood risk assessment.
- (4) Each part of the licensed activities must be operated in accordance with the plan approved under sub-paragraph (2) for that part, unless otherwise approved by the MMO.
Construction environmental management plan
15
All licensed activities must be carried out in accordance with the construction environmental management plan for those activities approved pursuant to paragraph 8 of this Schedule where applicable, unless otherwise approved by the MMO.
Piling and marine construction works
16
- (1) Subject to sub-paragraph (2) below, the piling of marine piles in connection with the authorised development must be subject to the following conditions—
- (a) there must be at least a 20 minutes “soft start” period at the commencement of any piling; and
- (b) The form of soft start must be agreed with the MMO following consultation with Natural England on matters related to its functions prior to the commencement of piling.
- (2) An active and mobile 500 metre marine mammals observation zone, the centre point of which will be the location of the particular marine pile being driven percussively, must be created, and 30 minutes prior to the commencement of percussive piling a search should be undertaken of the zone, with the purpose of identifying whether any marine mammals enter the zone, and if such mammals are observed within the zone, percussive piling should not be commenced until the mammals have cleared the zone or until 20 minutes after the last visual detection, subject to sub-paragraph (4).
- (3) An active and mobile 500 metre marine mammals observation zone, the centre point of which will be the location of the particular marine pile being driven percussively, must be maintained during percussive piling with the purpose of identifying whether any marine mammals enter the zone and if such mammals are observed, percussive piling will cease until the mammals have cleared the zone and there is no further detection after 20 minutes.
- (4) Where during operations percussive piling is paused for any reason other than the detection of marine mammals, then recommencing of the percussive piling must be subject to the provisions of sub-paragraph (2) save for where the active and mobile 500 metre marine mammals observation zone has been observed throughout the period of the pause in operations and no such mammals were observed entering the zone, in which case percussive piling may be recommenced immediately.
- (5) Wherever possible the undertaker will use vibro-piling methodology whilst it is recognised that percussive piling may be required to drive the piles to their ultimately required depth.
- (6) Subject to sub-paragraph (7) below, the undertaker must ensure that no construction activity for the approach jetty or decommissioning of topsides located within 200 metres of mean low water springs takes place between 1 October and 31 March inclusive in any year.
- (7) During the restricted period between 1 October and 31 March inclusive in any year, marine construction activity or decommissioning of topsides may be undertaken at distances less than 200 metres of mean low water springs provided that—
- (a) an acoustic barrier or visual screening is installed on both sides of any semi-completed structure;
- (b) construction activity is then undertaken on the approach jetty itself, behind the screening; and
- (c) noise levels are less than 70 dB(A) on exposed intertidal foreshore.
- (8) No piling of marine piles within the waterbody may take place between 1 April and 31 May (inclusive) in any one calendar year, except for any percussive piling of marine piles undertaken on exposed mudflat outside the water column at periods of low water.
- (9) Subject to sub-paragraph (10), no piling of marine piles within the waterbody is to take place between the hours of 7pm and 7am from 1 March to 31 March (inclusive) and from 1 September to 31 October (inclusive) or between the hours of sunset and sunrise from 1 June to 30 June (inclusive) and from 1 August to 31 August (inclusive) in any one calendar year.
- (10) Sub-paragraph (9) does not apply in relation to any—
- (a) percussive piling of marine piles undertaken on exposed mudflat outside the water column at periods of low water;
- (b) emergency works; and
- (c) percussive piling operations that have been initiated where an immediate cessation of the activity would form an unsafe working practice.
- (11) Percussive piling of marine piles is to be restricted at other times—
- (a) subject to sub-paragraph (18), from 1 June to 30 June (inclusive) in any one calendar year the maximum amount of percussive piling permitted within any 24 hour period must not exceed 270 minutes;
- (b) subject to sub-paragraph (18), from 1 August to 31 October (inclusive) in any one calendar year, the maximum amount of percussive piling permitted within any 24 hour period must not exceed 270 minutes,
except (in each case) for any percussive piling of marine piles undertaken on exposed mudflat outside the water column at periods of low water and save for percussive piling operations that have been initiated where an immediate cessation of the activity would form an unsafe working practice.
- (12) The measurement of time during each work-block described in sub-paragraph (11) of this Schedule must begin at the start of each timeframe, roll throughout it, then cease at the end, where measurement will begin again at the start of the next timeframe, such process to be repeated until the end of piling works.
- (13) Percussive piling must only be carried out in accordance with the cold weather piling restriction strategy.
- (14) A noise suppression system consisting of a piling sleeve with noise insulating properties must be employed for percussive piling on the approach jetty comprised in the authorised development.
- (15) The undertaker must submit weekly reports to the MMO of the duration of percussive piling that is undertaken on any given day on which piling takes place during the construction of the authorised development, unless otherwise agreed in writing with the MMO.
- (16) The reports submitted to the MMO pursuant to sub-paragraph (15) must include a log of the number and approximate location of piling rigs which are in operation on any given day, along with the number of piles driven.
- (17) The undertaker must hold fortnightly meetings with the MMO to discuss the weekly reports submitted pursuant to sub-paragraph (15) and agree any corrective action if required, unless otherwise agreed in writing with the MMO.
- (18) Where percussive piling is paused the recommencement of such percussive piling may take place for a contingency period of up to a total of 60 minutes within any 24 hour period in addition to the otherwise maximum amount of percussive piling permitted within any 24 hour period specified in sub–paragraph (11).
Marine written scheme of archaeological investigation
17
All licensed activities must be carried out in accordance with the marine written scheme of investigation.
Concrete and cement
18
Waste concrete, slurry or wash water from concrete or cement activities must not be discharged, intentionally or unintentionally, into the marine environment. Concrete and cement mixing and washing areas must be contained and sited at least 10 metres from any water body or surface water drain.
Coatings and treatment
19
The undertaker must ensure that any coatings and any treatments are suitable for use in the marine environment and are used in accordance with relevant guidelines approved by the Health and Safety Executive and the Environment Agency.
Pollution and spills
20
- (1) Bunding and storage facilities must be installed to contain and prevent the release of fuel, oils and chemicals associated with plant, refuelling and construction equipment into the marine environment. Secondary containment must be used with a capacity of no less than 110% of the container’s storage capacity.
- (2) Any oil, fuel or chemical spill within the marine environment must be reported to the MMO Marine Pollution Response Team as soon as reasonably practicable, but in any event within 12 hours of being identified in accordance with the following, unless otherwise advised in writing by the MMO—
- (a) within business hours on any business days: 0300 200 2024;
- (b) any other time: 07770 977 825; or
- (c) at all times if other numbers are unavailable: 0845 051 8486 or dispersants@marinemanagement.org.uk.
- (3) All wastes must be stored in designated areas that are isolated from surface water drains, open water and contained to prevent any spillage.
- (4) The undertaker must comply with the existing marine pollution contingency plan in place for the Port of Immingham as detailed in the construction environmental management plan.
Disposal at sea
21
- (1) The undertaker must inform the MMO of the location and quantities of material deposited each month under the licence. This information must be submitted to the MMO by 15 February each year for the months August to January inclusive and by 15 August each year for the months February to July inclusive.
- (2) The undertaker must ensure that only inert material of natural origin produced during dredging must be deposited in the disposal sites—
- (a) HU060 (unconsolidated); and
- (b) HU056 (consolidated),
or any other site approved in writing by the MMO.
- (3) The material to be disposed of within the disposal sites referred to in sub-paragraph (2) must be placed evenly within the relevant site’s boundaries.
- (4) During the course of disposal at sea, deposited material must be distributed evenly over the disposal site.
Dropped objects
22
- (1) The undertaker must report all dropped objects to the MMO using the Dropped Object Procedure Form as soon as reasonably practicable and in any event within 24 hours of becoming aware of an incident.
- (2) On receipt of the Dropped Object Procedure Form, the MMO may require, acting reasonably, the undertaker to carry out relevant surveys. The undertaker must carry out surveys in accordance with the MMO’s reasonable requirements and must report the results of such surveys to the MMO.
- (3) On receipt of such survey results the MMO may, acting reasonably, require the undertaker to remove specific obstructions from the seabed. The undertaker must carry out removals of the specific obstructions form the seabed in accordance with the MMO’s reasonable requirements and its own expense.
Notice to Mariners
23
- (1) Local mariners, fishermen’s organisations and the UK Hydrographic Office must be notified of any licensed activity or phase of licensed activity through a local Notice to Mariners.
- (2) A Notice to Mariners must be issued at least 5 days before the commencement of each licensed activity or phase of licensed activity.
- (3) The MMO and Maritime and Coastguard Agency must be sent a copy of the notification within 24 hours of issue. The Notice to Mariners must include—
- (a) the start and end dates of the work;
- (b) a summary of the works to be undertaken;
- (c) the location of the works area, including coordinated in accordance with WGS84; and
- (d) any markings of the works area that will be put in place.
- (4) A copy of the notice must be provided to the MMO via MCMS within 24 hours of issue of a notice under sub-paragraph (1).
PART 3 — PROCEDURE FOR THE DISCHARGE OF CONDITIONS
Approvals and appeals
24
Schedule 17 (procedure regarding certain approvals, etc.) of the Order has effect in relation to any submission by the undertaker for approval by or agreement of the MMO in respect of any document, strategy, information, plan, protocol or statement under this Schedule.
SCHEDULE 4 — STREETS SUBJECT TO STREET WORKS
| (1) Area | (2) Street | (3) Description of the street works |
|---|---|---|
| North East Lincolnshire | Unnamed access road | Works set out in article 7(1) for the placing and connecting of apparatus and associated works in the area between the point marked B on sheet 4 of the street works and accesses plan and the point marked C on sheets 4 and 5 of that plan. |
| North East Lincolnshire | Laporte Road | Works set out in article 7(1) for the placing and connecting of apparatus and associated works in the area between the point marked E on inset 1 of the street works and accesses plan and the point marked D on sheets 4 and 5 of that plan. |
| North East Lincolnshire | Unnamed private road to water treatment works | Works set out in article 7(1) for the placing and connecting of apparatus and associated works in the area between the point marked F on sheets 4 and 5 of the street works and accesses plan and the point marked G on sheet 4 of that plan. |
| North East Lincolnshire | Queens Road | Works set out in article 7(1) for the placing and connecting of apparatus and associated works in the area marked Con sheets 4 and 5 of the street works and accesses plan and the point marked I on sheets 5 and 6 of that plan. |
| North East Lincolnshire | Kings Road | Works set out in article 7(1) for the placing and connecting of apparatus and associated works in each of the area between the point marked V on sheets 6 and 7 of the street works and accesses plan and the point marked W on sheet 7 of that plan, the area between the point marked AI on sheets 6 and 7 of the street works and accesses plan and the points marked AH and AJ on sheet 7 of that plan, the area between the points marked AK and AL on sheet 7 of the street works and accesses plan, the area between the points marked AM and AN on sheet 7 of the street works and accesses plan and the area between the points marked AO, AP and AQ on sheet 7 of the street works and accesses plan. |
SCHEDULE 5 — ALTERATION OF STREETS
PART 1 — PERMANENT ALTERATION OF LAYOUT
| (1) Area | (2) Street | (3) Description of alteration, etc. |
|---|---|---|
| North East Lincolnshire | Unnamed access road | Works for the provision of a permanent means of access, altered layout and revised signage and markings within the area edged purple and marked A on sheets 4 and 5 of the street works and accesses plan. |
| North East Lincolnshire | Laporte Road | Works for the provision of a permanent means of access, altered layout and revised signage and markings within each of the areas edged purple and marked respectively J, K and L on sheet 4 of the street works and accesses plan. |
| North East Lincolnshire | Unnamed private road to water treatment works | Works for the provision of a permanent means of access, altered layout and revised signage and markings within the area edged purple and marked M on sheets 4 and 5 of the street works and accesses plan. |
| North East Lincolnshire | Laporte Road | Works for the provision of an altered layout and revised signage and markings in relation to the provision of the permanent speed limit change to which Part 1 (permanent speed limits) of Schedule 10 (traffic regulation measures) refers within the area shaded blue between the points marked D on sheets 4 and 5 and BC on sheet 4 of the street works and accesses plan and the area shaded yellow between the points marked BC on sheet 4 of the street works and accesses plan and point E on inset 1 of that plan. |
| North East Lincolnshire | A1173 | Works for the provision of a permanent means of access, altered layout and revised signage and markings within the area edged purple and marked AB on sheet 6 of the street works and accesses plan. |
| North East Lincolnshire | Kings Road | Works for the provision of a permanent means of access, altered layout and revised signage and markings within each of the areas edged purple and marked respectively Z and AA on sheets 6 and 7 of the street works and accesses plan. |
PART 2 — TEMPORARY ALTERATION OF LAYOUT
| (1) Area | (2) Street subject to alteration of layout | (3) Description of alteration |
|---|---|---|
| North East Lincolnshire | Laporte Road | Works for the provision of a temporary means of access, altered layout and revised signage and markings within each of the areas shaded orange and marked respectively N and P on sheet 4 of the street works and accesses plan and the area shaded orange and marked O on sheet 4 of that plan. |
| North East Lincolnshire | Unnamed private road to water treatment works | Works for the provision of a temporary means of access, altered layout and revised signage and markings within the area shaded orange and marked M on sheets 4 and 5 of the street works and accesses plan. |
| North East Lincolnshire | Queens Road | Works for the provision of a temporary means of access, altered layout and revised signage and markings within the area shaded orange and marked U on sheets 5 and 6 of the street works and accesses plan. |
| North East Lincolnshire | A1173 | Works for the provision of a temporary means of access, altered layout and revised signage and markings within the areas shaded orange and marked AB and AC on sheet 6 of the street works and accesses plan. |
| North East Lincolnshire | Kings Road | Works to enable the passage of abnormal indivisible loads including the removal of signage and street furniture within the area shaded red and marked AI, AD, AH and AJ on sheet 7 of the street works and accesses plan and within the area shaded red and marked AE, AQ, AO and AP on sheet 7 of that plan. |
| North East Lincolnshire | Kings Road | Works to enable the temporary modification of existing overhead cables and lines within the area shaded purple and marked AG, AM and AN on sheet 7 of the street works and accesses plan and within the area shaded purple and marked AF, AL and AK on that plan. |
| North East Lincolnshire | Kings Road | Works for the provision of a temporary means of access, altered layout and revised signage and markings within the area shaded orange and marked AA on sheets 6 and 7 of the street works and accesses plan. |
SCHEDULE 6 — PERMANENT STOPPING UP OF HIGHWAYS
| (1) Area | (2) Street to be stopped up Public right of way | (3) Extent of stopping up |
|---|---|---|
| North East Lincolnshire | Unnamed highway adjacent to Laporte Road | All of each of the areas hatched pink (including any areas shaded green which underlie the areas hatched pink) marked respectively AT and AW on sheets 4 and 5 of the stopping up and restriction of use of streets and public rights of way plan. |
| North East Lincolnshire | Kings Road | All of the area hatched pink (including any area shaded green which underlies the area hatched pink) marked AX on sheets 6 and 7 of the stopping up and restriction of use of streets and public rights of way plan. |
SCHEDULE 7 — PUBLIC RIGHTS OF WAY TO BE PERMANENTLY STOPPED UP
| (1) Area | (2) Public right of way | (3) Extent of stopping up |
|---|---|---|
| North East Lincolnshire | The area including the sea wall north west along the coast from but excluding Bridleway Number 36 hatched pink and marked AR on sheets 3 and 4 of the stopping up and restriction of use of streets and public rights of way plan | All of the area hatched pink and marked AR on sheets 3 and 4 of the stopping up and restriction of use of streets and public rights of way plan. |
SCHEDULE 8 — TEMPORARY RESTRICTION OR ALTERATION, ETC. OF THE USE OF STREETS OR PUBLIC RIGHTS OF WAY
PART 1 — TEMPORARY PROHIBITION OR RESTRICTION OF THE USE OR DIVERSION OF STREETS OR PUBLIC RIGHTS OF WAY
| (1) Area | (2) Street or public right of way | (3) Measure |
|---|---|---|
| North East Lincolnshire | Bridleway Number 36 | Temporary closure of that part of Bridleway Number 36 to the extent shown by the dashed green line between the points marked BA and BB on sheet 4 of the stopping up and restriction of use of streets and public rights of way plan (with a length of that part of Bridleway Number 36 being shown dashed green on sheet 3 of that plan) and the temporary diversion of Bridleway Number 36 along any alignment within Work No. 9 between those marked points. |
| North East Lincolnshire | Unnamed area shaded green and marked AY on sheets 4 and 5 of the stopping up and restriction of use of streets and public rights of way plan | Temporary closure of the area shaded green and marked AY on sheets 4 and 5 of the stopping up and restriction of use of streets and public rights of way plan. |
| North East Lincolnshire | Unnamed access road | Temporary closure of the area shaded green and marked A on sheets 4 and 5 of the stopping up and restriction of use of streets and public rights of way plan. |
| North East Lincolnshire | Laporte Road | Temporary closure of each of the areas within Laporte Road shaded green and marked respectively J, K, L, N, O and P on sheet 4 of the stopping up and restriction of use of streets and public rights of way plan. |
| North East Lincolnshire | Unnamed private road to water treatment works | Temporary closure of the area shaded green and marked M on sheets 4 and 5 of the stopping up and restriction of use of streets and public rights of way plan. |
| North East Lincolnshire | Laporte Road | Temporary closure to all traffic save for traffic under the direction of the undertaker of the area shaded green between the point marked S on sheets 4 and 5 of the stopping up and restriction of use of streets and public rights of way plan and the point marked T on sheet 4 of that plan. |
| North East Lincolnshire | Queens Road | Temporary closure of the area shaded green and marked U on sheets 5 and 6 of the stopping up and restriction of use of streets and public rights of way plan. |
| North East Lincolnshire | A1173 | Temporary closure of the areas within the A1173 shaded green and marked AB and AC on sheet 6 of the stopping up and restriction of use of streets and public rights of way plan. |
| North East Lincolnshire | Kings Road | Temporary closure of the area shaded green and marked Z on sheets 6 and 7 of the stopping up and restriction of use of streets and public rights of way plan. |
PART 2 — TEMPORARY USE OF MOTOR VEHICLES ON PUBLIC RIGHTS OF WAY
| (1) Area | (2) Public right of way | (3) Measure |
|---|---|---|
| North East Lincolnshire | Bridleway Number 36 | Motor vehicles under the direction of the undertaker may temporarily use and cross that part of Bridleway Number 36 shown dashed green between the points marked BA and BB on sheet 4 of the stopping up and restriction of use of streets and public rights of way plan (with a length of that part of Bridleway Number 36 being shown dashed green on sheet 3 of that plan). |
SCHEDULE 9 — ACCESS TO WORKS
PART 1 — PERMANENT MEANS OF ACCESS TO WORKS
| (1) Area | (2) Street | (3) Means of access |
|---|---|---|
| North East Lincolnshire | Laporte Road | Permanent means of access within each of the areas edged purple and marked respectively J, K and L on sheet 4 of the street works and accesses plan. |
| North East Lincolnshire | Unnamed private road to water treatment works | Permanent means of access within the area edged purple and marked M on sheets 4 and 5 of the street works and accesses plan. |
| North East Lincolnshire | Unnamed private access road | Permanent means of access within the area edged purple and marked A on sheets 4 and 5 of the street works and accesses plan. |
| North East Lincolnshire | A1173 | Permanent means of access within the area edged purple and marked AB on sheet 6 of the street works and accesses plan. |
| North East Lincolnshire | Kings Road | Permanent means of access within each of the areas edged purple and marked respectively Z and AA on sheets 6 and 7 of the street works and accesses plan. |
PART 2 — TEMPORARY MEANS OF ACCESS TO WORKS
| (1) Area | (2) Street | (3) Means of access |
|---|---|---|
| North East Lincolnshire | Laporte Road | Temporary means of access within each of the areas shaded orange and marked respectively N and P on sheet 4 of the street works and accesses plan and shaded orange and marked O on sheets 4 and 5 of that plan. |
| North East Lincolnshire | Unnamed private road to water treatment works | Temporary means of access within the area shaded orange and marked M on sheets 4 and 5 of the street works and accesses plan. |
| North East Lincolnshire | Queens Road | Temporary means of access within the area shaded orange and marked U on sheets 5 and 6 of the street works and accesses plan. |
| North East Lincolnshire | A1173 | Temporary means of access within each of the areas shaded orange and marked respectively AB and AC on sheet 6 of the street works and accesses plan. |
| North East Lincolnshire | Kings Road | The provision of a temporary means of access within the area shaded orange and marked AA on sheets 6 and 7 of the street works and accesses plan. |
SCHEDULE 10 — TRAFFIC REGULATION MEASURES
PART 1 — PERMANENT SPEED LIMITS
| (1) Area | (2) Road name and length | (3) Permanent speed limit |
|---|---|---|
| North East Lincolnshire | That part of Laporte Road shaded blue and between the point marked D on sheets 4 and 5 of the traffic regulation measures plan and the point marked BC on sheet 4 of that plan, a distance of approximately 365 metres. | 30 miles per hour |
| North East Lincolnshire | That part of Laporte Road shaded yellow and between the point marked BC on sheet 4 of the traffic regulation measures plan and the point marked E on inset 1 of that plan, a distance of approximately 545 metres | 40 miles per hour |
PART 2 — TEMPORARY PROHIBITION OF PARKING
| (1) Area | (2) Road name and length | (3) Measure |
|---|---|---|
| North East Lincolnshire | That part of Laporte Road, Queens Road and Kings Road hatched dark blue between the point marked BC on sheet 4 of the traffic regulation measures plan and the point marked BD on sheet 8 of that plan (with the remainder of that part of those roads shown on sheets 5, 6 and 7 of that plan), a distance of approximately 2,890 metres. | Temporary parking suspension |
PART 3 — TEMPORARY ROAD CLOSURES
| (1) Area | (2) Road name and length | (3) Measure |
|---|---|---|
| North East Lincolnshire | That part of Laporte Road, Queens Road and Kings Road hatched dark blue between the point marked BC on sheet 4 of the traffic regulation measures plan and the point marked BD on sheet 8 of that plan (with the remainder of that part of those roads shown on sheets 5, 6 and 7 of that plan), a distance of approximately 2,890 metres. | Temporary road closure between the hours of 11pm and 6am to all traffic save for traffic under the direction of the undertaker. |
PART 4 — PRIORITY OF VEHICULAR TRAFFIC
| (1) Area | (2) Road name and length | (3) Measure |
|---|---|---|
| North East Lincolnshire | That part of Laporte Road edged green between the point marked BE on sheets 4 and 5 of the traffic regulation measures plan and the point marked BF on sheet 4 of that plan. | Priority of vehicular traffic to be regulated by temporary traffic lights at the direction of the undertaker. |
SCHEDULE 11 — MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR THE CREATION OF NEW RIGHTS AND IMPOSITION OF NEW RESTRICTIVE COVENANTS
Compensation enactments
1
The enactments for the time being in force with respect to compensation for the compulsory purchase of land apply, with the necessary modifications as respects compensation, in the case of a compulsory acquisition under this Order of a right, by the creation of a new right or imposition of a restrictive covenant as they apply in respect of compensation on the compulsory purchase of land and interests in land.
2
- (1) Without limitation on the scope of paragraph 1, the Land Compensation Act 1973109 has effect subject to the modifications set out in sub-paragraph (2).
- (2) In section 44(1) (compensation for injurious affection), as it applies to compensation for injurious affection under section 7 of the 1965 Act as substituted by paragraph 4(5))—
- (a) for “land is acquired or taken from” substitute “a right or restrictive covenant over land is purchased from or imposed on”; and
- (b) for “acquired or taken from him” substitute “over which the right is exercisable or the restrictive covenant enforceable”.
3
- (1) Without limitation on the scope of paragraph 1, the 1961 Act has effect subject to the modification set out in sub-paragraph 2(2).
- (2) For Section 5A(5A) (relevant valuation date) of the 1961 Act, omit the words after “If” and substitute—
(a) the acquiring authority enters on land for the purpose of exercising a right in pursuance of a notice of entry under section 11(1) of the 1965 Act (as modified by paragraph 4(7) of Schedule 11 to the Associated British Ports (Immingham Green Energy Terminal) Order 2025); (b) the acquiring authority is subsequently required by a determination under paragraph 13 of Schedule 2A to the 1965 Act (as substituted by paragraph 4(10) of Schedule 11 to the Associated British Ports (Immingham Green Energy Terminal) Order 2025 to acquire an interest in the land; and (c) the acquiring authority enters on and takes possession of that land, the authority is deemed for the purposes of subsection (3)(a) to have entered on that land when it entered on that land for the purpose of exercising that right.
Application of the 1965 Act
4
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.