The Associated British Ports (Immingham Green Energy Terminal) Order 2025

Type Statutory-Instrument
Publication 2025-02-06
Last updated 2025-02-27
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • (4) Subject to the terms of any agreement between Network Rail and a train operator regarding the timing or method of payment of the relevant costs in respect of that train operator, Network Rail must promptly pay to each train operator the amount of any sums which Network Rail receives under sub-paragraph (3) which relates to the relevant costs of that train operator.
  • (5) The obligation under sub-paragraph (3) to pay Network Rail the relevant costs is, in the event of default, enforceable directly by any train operator concerned to the extent that such sums would be payable to that operator pursuant to sub-paragraph (4).
  • (6) In this paragraph—
  • “the relevant costs” means the costs, direct losses and expenses (including loss of revenue) reasonably incurred by each train operator as a consequence of any specified work, including but not limited to any restriction of the use of Network Rail’s railway network as a result of the construction, maintenance or failure of a specified work or any such act or omission as mentioned in sub-paragraph (1); and
  • “train operator” means any person who is authorised to act as the operator of a train by a licence under section 8 of the Railways Act 1993.
73

Network Rail must, on receipt of a request from the undertaker, from time to time provide the undertaker free of charge with written estimates of the costs, charges, expenses and other liabilities for which the undertaker is or will become liable pursuant to this Part of this Schedule (including the amount of the relevant costs mentioned in paragraph 72(5) and with such information as may reasonably enable the undertaker to assess the reasonableness of any such estimate made or to be made pursuant to this Part of this Schedule (including any claim relating to those relevant costs).

74

In the assessment of any sums payable to Network Rail under this Part of this Schedule there must not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Network Rail if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by the undertaker under this Part of this Schedule or increasing the sums so payable.

75

The undertaker and Network Rail may, subject in the case of Network Rail to compliance with the terms of its network licence, enter into, and carry into effect, agreements for the transfer to the undertaker of—

  • (a) any railway property shown on the works and land plans and described in the book of reference;
  • (b) any lands, works or other property held in connection with any such railway property; and
  • (c) any rights and obligations (whether or not statutory) of Network Rail relating to any railway property or any lands, works or other property referred to in this paragraph.
76

Nothing in this Order, or in any enactment incorporated with or applied by this Order, prejudices or affects the operation of Part 1 of the Railways Act 1993.

77

The undertaker must give written notice to Network Rail where any application is proposed to be made by the undertaker for the Secretary of State’s consent under article 46 (benefit of Order), except in respect of the deemed marine licence, and any such notice must be given no later than 28 days before any such application is made and must describe or give (as appropriate)—

  • (a) the nature of the application to be made;
  • (b) the extent of the geographical area to which the application relates; and
  • (c) the name and address of the person acting for the Secretary of State to whom the application is to be made.
78

The undertaker must no later than 28 days from the date that the plans and documents referred to in article 63 (certification of documents, public register, etc.) are certified by the Secretary of State provide a set of those plans and documents to Network Rail.

PART 6 — FOR THE PROTECTION OF NORTH EAST LINCOLNSHIRE COUNCIL (AS LEAD LOCAL FLOOD AUTHORITY)

Application

79

The provisions of this Part of this Schedule apply whilst any part of the authorised project is being constructed for the protection of the authority unless otherwise agreed between the undertaker and the authority.

Interpretation

80

In this Part of this Schedule—

  • “authority” means North East Lincolnshire Council (as lead local flood authority within the meaning of the Flood and Water Management Act 2010);
  • “authorised officer” means an officer authorised by the authority;
  • “construction” includes execution, placing, altering, replacing, relaying and removal and “construct” and “constructed” are construed accordingly;
  • “drainage work” means any ordinary watercourse and includes any land which is expected to provide flood storage capacity for an ordinary watercourse and any bank, wall, embankment or other structure, or any appliance, constructed or used for land drainage or flood defence in connection with an ordinary watercourse;
  • “ordinary watercourse” has the meaning as given in section 72 (interpretation) of the Land Drainage Act 1991;
  • “plans” includes sections, drawings, specifications and method statements; and
  • “specified work” means any works carried out in relation to or which may affect any ordinary watercourse, drain or culvert in a manner that would be likely to affect the flow of the watercourse, drain or culvert.
81
  • (1) Before beginning to construct any specified work, the undertaker must submit to the authority plans of the specified work and such further particulars available to it as the authority may within 28 days of the receipt of the plans reasonably require.
  • (2) Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by the authority, or determined under sub-paragraph (3).
  • (3) Any approval of the authority required under sub-paragraph (2)—
  • (a) must not be unreasonably withheld or delayed;
  • (b) is deemed to have been given if it is neither given nor refused within 28 days of the receipt of the plans for approval or where further particulars are submitted under sub-paragraph (1) within 28 days of the submission of those particulars, and, in the case of a refusal, accompanied by a statement of the grounds of refusal; and
  • (c) may be given subject to such reasonable requirements as it may make for the protection of any drainage work or for the prevention of flooding; and
  • (d) the authority must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (b).
82
  • (1) Without limitation on the scope of paragraph 81, the requirements which the authority may make include conditions requiring the undertaker at its own expense to construct such protective works, whether temporary or permanent, before or during the construction of the specified works (including any new works as well as alterations to existing works) as are reasonably necessary—
  • (a) to safeguard any drainage work against damage, or
  • (b) to secure that the efficiency of any ordinary watercourse for flood defence or land drainage purposes is not impaired and that the risk of flooding is not otherwise increased,

by reason of the specified work.

83
  • (1) Subject to sub-paragraph (3), any specified work, and all protective works required by the authority under paragraph 82 must be constructed—
  • (a) without unreasonable delay in accordance with the plans approved or settled under this Part of this Schedule; and
  • (b) to the reasonable satisfaction of the authority,

and an authorised officer of the authority is entitled to watch and inspect the construction of such works.

  • (2) The undertaker must give to the authority not less than 14 days’ notice in writing of its intention to commence construction of any specified work and notice in writing of its completion not later than 7 days after the date on which it is completed.
  • (3) If any part of a specified work or any protective work required by the authority over or under any ordinary watercourse is constructed otherwise than in accordance with the requirements of this Part of Schedule, the authority may by notice in writing require the undertaker at the undertaker’s own expense to comply with the requirements of this Part of this Schedule or (if the undertaker so elects and the authority in writing consents, such consent not to be unreasonably withheld or delayed) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent and within such limits as the authority reasonably requires.
  • (4) Subject to sub-paragraph (5) and paragraph 81, if within a reasonable period, being not less than 28 days from the date when a notice under sub-paragraph (3) is served upon the undertaker, it has failed to begin taking steps to comply with the requirements of the notice and subsequently to make reasonably expeditious progress towards their implementation, the authority may execute the works specified in the notice and any reasonable expenditure incurred by it in so doing is recoverable from the undertaker.
  • (5) In the event of any dispute as to whether sub-paragraph (3) is applicable to any work in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, the authority must not except in an emergency exercise the powers conferred by sub-paragraph (4) until the dispute has been finally determined.
84
  • (1) Subject to sub-paragraph (2) the undertaker must from the commencement of the construction of the specified works maintain in good repair and condition and free from obstruction any drainage work which is situated on land held by the undertaker for the purposes of or in connection with the specified works within the Order limits, whether or not the drainage work is constructed under the powers conferred by this Order or is already in existence.
  • (2) If any such drainage work which the undertaker is liable to maintain is not maintained to the reasonable satisfaction of the authority it may by notice in writing require the undertaker to repair and restore the work, or any part of such work, or (if the undertaker so elects and the authority in writing consents, such consent not to be unreasonably withheld or delayed), to remove the work and restore the site to its former condition, to such extent and within such limits as the authority reasonably requires.
  • (3) Subject to sub-paragraph (4) and paragraph 81, if, within a reasonable period being not less than 28 days beginning with the date on which a notice in respect of any drainage work is served under sub-paragraph (2) on the undertaker, the undertaker has failed to begin taking steps to comply with the reasonable requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, the authority may do what is necessary for such compliance and may recover any expenditure reasonably incurred by it in so doing from the undertaker.
  • (4) In the event of any dispute as to the reasonableness of any requirement of a notice served under sub-paragraph (2), the authority must not, except in a case of an emergency, exercise the powers conferred by sub-paragraph (3) until the dispute has been finally determined.
  • (5) This paragraph does not apply to—
  • (a) drainage works which are vested in the authority, or which the authority or another person is liable to maintain and is not precluded by the powers of the Order from doing so; and
  • (b) any obstruction of a drainage work for the purpose of a work or operation authorised by this Order and carried out in accordance with the provisions of this Part of this Schedule.
85

Subject to paragraph 84, if by reason of the construction of any specified work or of the failure of any such work the efficiency of any ordinary watercourse for flood defence or land drainage purposes is impaired, or that watercourse is otherwise damaged, so as to require remedial action, such impairment or damage must be made good by the undertaker to the reasonable satisfaction of the authority and if the undertaker fails to do so, the authority may make good the same and recover from the undertaker the proper and reasonable expense reasonably incurred by it in so doing.

86
  • (1) The undertaker must repay the authority all proper and reasonable costs, charges and expenses which the authority may reasonably incur or have to pay or which it may sustain—
  • (a) in the examination or approval of plans under this Part of this Schedule; and
  • (b) in the inspection of the construction of the specified work in respect of an ordinary watercourse or any protective works required by the authority under this Part of this Schedule.
  • (2) The maximum amount payable to the authority under sub-paragraph (1)(a) or (1)(b) is to be the same as would have been payable to the authority in accordance with the scale of charges for pre-application advice and land drainage consent applications published by the authority from time to time.
87
  • (1) Without affecting the other provisions of this Part of this Schedule, the undertaker must indemnify the authority from all claims, demands, proceedings, costs, charges, penalties, damages, expenses and losses, which may be made or taken against, recovered from, or incurred by, the authority by reason of—
  • (a) any damage to any drainage work so as to impair its efficiency for flood defence or land drainage purposes;
  • (b) any raising or lowering of the water table in land adjoining or affected by a specified work or adjoining any sewers, drains and watercourses; or
  • (c) any flooding, increased flooding or impaired drainage of any such lands as are mentioned in paragraph 85,
  • (d) any claim in respect of pollution under the Control of Pollution Act 1974;
  • (e) damage to property including property owned by third parties; or
  • (f) injury to or death of any person,

which is caused by the construction of any of the specified works or any act or omission of the undertaker, its contractors, agents or employees whilst engaged upon the work.

  • (2) The authority must give to the undertaker reasonable notice of any such claim or demand and no settlement or compromise may be made without the agreement of the undertaker which agreement must not be unreasonably withheld or delayed.
  • (3) The authority must at all times take reasonable steps to prevent and mitigate any such claims demands proceedings costs charges penalties damages expenses and losses.
88

The fact that any work or thing has been executed or done by the undertaker in accordance with plans approved by the authority, or to its satisfaction, or in accordance with any directions or award of an arbitrator, does not (in the absence of negligence on the part of the authority, its officers, contractors or agents) relieve the undertaker from any liability under the provisions of this Part of this Schedule.

89

Any dispute arising between the undertaker and the authority under this Part of this Schedule is to be determined by arbitration in accordance with article 61 (arbitration).

PART 7 — FOR THE PROTECTION OF CADENT GAS LIMITED AS GAS UNDERTAKER

Application

90

For the protection of Cadent the following provisions will, unless otherwise agreed in writing between the undertaker and Cadent, have effect during the construction of the authorised works (as defined in this Part of this Schedule) and for a further period of 18 months from completion of the authorised works (as defined in this Part of this Schedule).

Interpretation

91

In this Part of this Schedule—

  • “alternative apparatus” means appropriate alternative apparatus to the satisfaction of Cadent to enable Cadent to fulfil its statutory functions in a manner no less efficient than previously;
  • “apparatus” means any gas mains, pipes, pressure governors, ventilators, cathodic protections, cables or other apparatus (including transformed rectifiers and any associated groundbeds or cables) belonging to or maintained by Cadent for the purposes of gas supply together with any replacement apparatus and such other apparatus constructed pursuant to the Order that becomes operational apparatus of Cadent for the purposes of transmission, distribution or supply and includes any structure in which apparatus is or will be lodged or which gives or will give access to apparatus;
  • “authorised works” has the same meaning as is given to the term “authorised development” in article 2 (interpretation) of this Order and includes any associated development authorised by this Order;
  • “Cadent” means Cadent Gas Limited and includes its successors in title or any successor as a gas transporter within the meaning of Part 1 of the Gas Act 1986;
  • “commence” has the same meaning as in Schedule 2 (requirements) of this Order and “commencement” is to be construed to have the same meaning save that for the purposes of this Part of this Schedule the terms “commence” and “commencement” include any below ground surveys, monitoring, work operations, remedial work in respect of any contamination or other adverse ground condition, the receipt and erection of construction plant and equipment, and non-intrusive investigations for the purpose of assessing ground operations for the purposes of archaeological or ecological investigations and investigations of the existing condition of the ground or of structures and the diversion, laying and construction of services;
  • “deed of consent” means a deed of consent, crossing agreement, deed of variation or new deed of grant agreed between the parties acting reasonably in order to vary or replace existing easements, agreements, enactments and other such interests so as to secure land rights and interests as are necessary to carry out, maintain, operate and use the apparatus in a manner consistent with the terms of this Part of this Schedule;
  • “functions” includes powers and duties;
  • “ground mitigation scheme” means a scheme approved by Cadent (such approval not to be unreasonably withheld or delayed and setting out the necessary measures (if any) for a ground subsidence event);
  • “ground monitoring scheme” means a scheme for monitoring ground subsidence which sets out the apparatus which is to be subject to such monitoring, the extent of land to be monitored, the manner in which ground levels are to be monitored, the timescales of any monitoring activities and the extent of ground subsidence which, if exceeded, will require the undertaker to submit for Cadent′s approval a ground mitigation scheme;
  • “ground subsidence event” means any ground subsidence identified by the monitoring activities set out in the ground monitoring scheme that has exceeded the level described in the ground monitoring scheme as requiring a ground mitigation scheme;
  • “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;
  • “maintain” and “maintenance” includes the ability and right to do any of the following in relation to any apparatus or alternative apparatus of Cadent including retain, lay, construct, inspect, maintain, protect, use, access, enlarge, replace, renew, remove, decommission or render unusable or remove the apparatus;
  • “plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed;
  • “rights” includes rights and restrictive covenants, and in relation to decommissioned apparatus the surrender of rights, release of liabilities and transfer of decommissioned apparatus; and
  • “specified works” means any of the authorised works or activities undertaken in association with the authorised works which— will or may be situated over, or within 15 metres measured in any direction of any apparatus the removal of which has not been required by the undertaker under sub-paragraph 96(2) or otherwise; may in any way adversely affect any apparatus the removal of which has not been required by the undertaker under sub-paragraph 96(2) or otherwise; or include any of the activities that are referred to in CD/SP/SSW/22 (Cadent′s policies for safe working in the vicinity of Cadent′s Assets).

On street apparatus

92
  • (1) Except for paragraphs 93 (apparatus of Cadent in stopped up streets), 96 (removal of apparatus) in so far as sub-paragraph 96(2) applies, 97 (facilities and rights for alternative apparatus) in so far as its sub-paragraph 97(1) applies, 98 (retained apparatus: protection of Cadent), 99 (expenses) and 100 (indemnity) which will apply in respect of the exercise of all or any powers under this Order affecting the rights and apparatus of Cadent, the other provisions of this Part of this Schedule do not apply to apparatus in respect of which the relations between the undertaker and Cadent are regulated by the provisions of Part 3 of the 1991 Act.
  • (2) Paragraphs 96 and 97 of this Agreement will apply to diversions even where carried out under the 1991 Act, in circumstances where any apparatus is diverted from an alignment within the existing adopted public highway but not wholly replaced within existing adopted public highway.
  • (3) Notwithstanding article 8 (application of the 1991 Act) or any other powers in the Order generally, section 85 of the 1991 Act in relation to cost sharing and the regulations made under it will not apply in relation to any diversion of apparatus of Cadent under the 1991 Act.

Apparatus of Cadent in stopped up streets

93
  • (1) Without prejudice to the generality of any other protection afforded to Cadent elsewhere in this Order, where any street is stopped up under article 11 (permanent stopping up of streets), if Cadent has any apparatus in the street or accessed via that street Cadent will be entitled to the same rights in respect of such apparatus as it enjoyed immediately before the stopping up and the undertaker will grant to Cadent, or will procure the granting to Cadent of, legal easements reasonably satisfactory to Cadent in respect of such apparatus and access to it prior to the stopping up of any such street or highway but nothing in this paragraph affects any right of the undertaker or of Cadent to require the removal of that apparatus under paragraph 96.
  • (2) Notwithstanding the temporary stopping up or diversion of any highway under the powers of article 13 (temporary stopping up and prohibition or restriction of use of streets and public rights of way), Cadent will be at liberty at all times to take all necessary access across any such stopped up highway or to execute and do all such works and things in, upon or under any such highway as it would have been entitled to do immediately before such temporary stopping up or diversion in respect of any apparatus which at the time of the stopping up or diversion was in that highway.

Protective works to buildings

94
  • (1) The undertaker, in the case of the powers conferred by article 20 (protective works), must exercise those powers so as not to obstruct or render less convenient the access to any apparatus without the written consent of Cadent and, if by reason of the exercise of those powers any damage to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal or abandonment) or property of Cadent or any interruption in the supply of gas by Cadent, as the case may be, is caused, the undertaker must bear and pay on demand the cost reasonably incurred by Cadent in making good such damage or restoring the supply; and, subject to sub-paragraph (2), must—
  • (a) pay compensation to Cadent for any loss sustained by it; and
  • (b) indemnify Cadent against all claims, demands, proceedings, costs, damages and expenses which may be made or taken against or recovered from or incurred by Cadent, by reason of any such damage or interruption.
  • (2) Nothing in this paragraph imposes any liability on the undertaker with respect to any damage or interruption to the extent that such damage or interruption is attributable to the act, neglect or default of Cadent or its contractors or workmen; and Cadent must give to the undertaker reasonable notice of any claim or demand as aforesaid and no settlement or compromise of it must be made by Cadent, save in respect of any payment required under a statutory compensation scheme, without first consulting the undertaker and giving the undertaker an opportunity to make representations as to the claim or demand.

Acquisition of land

95
  • (1) Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference to the Order, the undertaker may not appropriate or acquire any land interest or appropriate, acquire, extinguish, interfere with or override any easement, other interest or right or apparatus of Cadent otherwise than by agreement (such agreement not to be unreasonably withheld or delayed).
  • (2) As a condition of agreement between the parties in sub-paragraph (1), prior to the carrying out of any part of the authorised works (or in such other timeframe as may be agreed between Cadent and the undertaker) that are subject to the requirements of this Part of this Schedule that will cause any conflict with or breach the terms of any easement or other legal or land interest of Cadent or affects the provisions of any enactment or agreement regulating the relations between Cadent and the undertaker in respect of any apparatus laid or erected in land belonging to or secured by the undertaker, the undertaker must as Cadent reasonably requires enter into such deeds of consent and variations upon such terms and conditions as may be agreed between Cadent and the undertaker acting reasonably and which must be no less favourable on the whole to Cadent unless otherwise agreed by Cadent, and it will be the responsibility of the undertaker to procure or secure the consent and entering into of such deeds and variations by all other third parties with an interest in the land at that time who are affected by such authorised works.
  • (3) The undertaker and Cadent agree that where there is any inconsistency or duplication between the provisions set out in this Part of this Schedule relating to the relocation or removal of apparatus, including but not limited to the payment of costs and expenses relating to such relocation or removal of apparatus, and the provisions of any existing easement, rights, agreements and licences granted, used, enjoyed or exercised by Cadent or other enactments relied upon by Cadent as of right or other use in relation to the apparatus, then the provisions in this Schedule prevail.
  • (4) Any agreement or consent granted by Cadent under paragraph 98 (retained apparatus: protection of Cadent) or any other paragraph of this Part of this Schedule, must not be taken to constitute agreement under sub-paragraph (1).
  • (5) As a condition of an agreement between the parties in sub-paragraph (1) that involves decommissioned apparatus being left in situ the undertaker must accept a surrender of any existing easement and any other interest of Cadent in such decommissioned apparatus and consequently acquire title to such decommissioned apparatus and release Cadent from all liabilities in respect of such de-commissioned apparatus from the date of such surrender.
  • (6) Where an undertaker acquires land which is subject to any Cadent right or interest (including, without limitation, easements and agreements relating to rights or other interests) and the provisions of paragraph 96 (removal of apparatus) do not apply, the undertaker must—
  • (a) retain any notice of Cadent’s easement, right or other interest on the title to the relevant land when registering the undertaker’s title to such acquired land; and
  • (b) (where no such notice of Cadent’s easement, right or other interest exists in relation to such acquired land or any such notice is registered only on the Land Charges Register) include (with its application to register title to the undertaker’s interest in such acquired land at the Land Registry) a notice of Cadent’s easement, right or other interest in relation to such acquired land.

Removal of apparatus

96
  • (1) If, in the exercise of the agreement reached in accordance with paragraph 95 (acquisition of land) or in any other authorised manner, the undertaker acquires any interest in any land in which any apparatus is placed, that apparatus must not be decommissioned or removed under this Part of this Schedule and any right of Cadent to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed, is in operation, and the rights and facilities referred to in sub-paragraph (2) have been provided, to the satisfaction of Cadent and in accordance with sub-paragraphs (2) to (5) inclusive.
  • (2) If, for the purpose of executing any works in, on, under or over any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to Cadent advance written notice of that requirement, together with a plan and section of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order Cadent reasonably needs to move or remove any of its apparatus) the undertaker must afford to Cadent to its satisfaction (taking into account sub-paragraph 97(1) (facilities and rights for alternative apparatus)) the necessary facilities and rights—
  • (a) for the construction of alternative apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by Cadent in respect of the apparatus);
  • (b) subsequently for the maintenance of that apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by Cadent in respect of the apparatus); and
  • (c) to allow access to that apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by Cadent in respect of the apparatus).
  • (3) If the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed, Cadent may, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances in an endeavour to assist the undertaker in obtaining the necessary facilities and rights in the land in which the alternative apparatus is to be constructed save that this obligation does not extend to the requirement for Cadent to use its compulsory purchase powers to this end unless it (in its absolute discretion) elects to so do.
  • (4) Any alternative apparatus to be constructed in land of or land secured by the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between Cadent and the undertaker.
  • (5) Cadent must, after the alternative apparatus to be provided or constructed has been agreed, and subject to the prior grant to Cadent of such facilities and rights as are referred to in sub-paragraphs (2) or (3) have been afforded to Cadent to its satisfaction, then proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to decommission or remove any apparatus required by the undertaker to be decommissioned or removed under the provisions of this Part of this Schedule.

Facilities and rights for alternative apparatus

97
  • (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to or secures for Cadent facilities and rights in land for the access to, construction and maintenance of alternative apparatus in substitution for apparatus to be decommissioned or removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between the undertaker and Cadent and must be no less favourable on the whole to Cadent than the facilities and rights enjoyed by it in respect of the apparatus to be decommissioned or removed unless otherwise agreed by Cadent.
  • (2) If the facilities and rights to be afforded by the undertaker and agreed with Cadent under paragraph 96(2) above in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are less favourable on the whole to Cadent than the facilities and rights enjoyed by it in respect of the apparatus to be decommissioned or removed (in Cadent’s reasonable opinion) then the terms and conditions to which those facilities and rights are subject in the matter will be referred to arbitration in accordance with paragraph 105 (arbitration) of this Part of this Schedule and the arbitrator must make such provision for the payment of compensation by the undertaker to Cadent as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.

Retained apparatus: protection of Cadent

98
  • (1) Not less than 56 days before the commencement of any specified works the undertaker must submit to Cadent a plan and, if reasonably required by Cadent, a ground monitoring scheme in respect of those works.
  • (2) The plan to be submitted to Cadent under sub-paragraph (1) must include a method statement and describe—
  • (a) the exact position of the works;
  • (b) the level at which these are proposed to be constructed or renewed;
  • (c) the manner of their construction or renewal including details of excavation, positioning of plant, etc.;
  • (d) the position of all apparatus;
  • (e) by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus; and
  • (f) any intended maintenance regimes.
  • (3) The undertaker must not commence any works to which sub-paragraphs (1) and (2) apply until Cadent has given written approval of the plan so submitted.
  • (4) Any approval of Cadent required under sub-paragraph (3)—
  • (a) may be given subject to reasonable conditions for any purpose mentioned in sub-paragraphs (5) or (7); and
  • (b) must not be unreasonably withheld.
  • (5) In relation to any work to which sub-paragraphs (1) or (2) apply, Cadent may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing apparatus against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus.
  • (6) Works to which this paragraph applies must only be executed in accordance with the plan, submitted under sub-paragraphs (1) and (2) or as relevant sub-paragraph (5), as approved or as amended from time to time by agreement between the undertaker and Cadent and in accordance with all conditions imposed under sub-paragraph (4)(a), and Cadent will be entitled to watch and inspect the execution of those works.
  • (7) Where Cadent requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to Cadent’s reasonable satisfaction prior to the commencement of any specified works (or any relevant part of them) for which protective works are required prior to commencement.
  • (8) If Cadent, in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 96 (removal of apparatus), 97 (facilities and rights for alternative apparatus), 99 (expenses), 100 (indemnity) and 102 (co-operation) apply as if the removal of the apparatus had been required by the undertaker under sub-paragraph 96(2) (removal of apparatus).
  • (9) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of the specified works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph will apply to and in respect of the new plan.
  • (10) The undertaker will not be required to comply with sub-paragraph (1) where it needs to carry out emergency works as defined in the 1991 Act but in that case it must give to Cadent notice as soon as is reasonably practicable and a plan of those works must comply with—
  • (a) the conditions imposed under sub-paragraph (4)(a) insofar as is reasonably practicable in the circumstances; and
  • (b) sub-paragraph (11) at all times.
  • (11) At all times when carrying out any works authorised under the Order the undertaker must comply with Cadent′s policies for safe working in proximity to gas apparatus ″CD/SP/SSW/22 (Cadent′s policies for safe working in the vicinity of Cadent′s Assets″ and HSE’s ″HS(~G)47 Avoiding Danger from underground services″.
  • (12) As soon as reasonably practicable after any ground subsidence event attributable to the authorised development the undertaker must implement an appropriate ground mitigation scheme save that Cadent retains the right to carry out any further necessary protective works for the safeguarding of its apparatus and can recover any such costs in accordance with paragraph 99. (expenses).

Expenses

99
  • (1) Subject to the following provisions of this paragraph, the undertaker must pay to Cadent on demand all charges, costs and expenses reasonably incurred by Cadent in, or in connection with, the inspection, removal, relaying or replacing, alteration or protection of any apparatus or the construction of any new or alternative apparatus which may be required in consequence of the execution of any authorised works as are referred to in this Part of this Schedule including without limitation—
  • (a) any costs reasonably incurred by or compensation properly paid by Cadent in connection with the negotiation or acquisition of rights or the exercise of statutory powers for such apparatus including without limitation all costs (including professional fees) incurred by Cadent as a consequence of Cadent—
  • (i) using its own compulsory purchase powers to acquire any necessary rights under paragraph 96(3) (removal of apparatus) if it elects to do so; or
  • (ii) exercising any compulsory purchase powers in the Order transferred to or benefitting Cadent;
  • (b) in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus;
  • (c) the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
  • (d) the approval of plans;
  • (e) the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works;
  • (f) the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule; and
  • (g) any watching brief pursuant to paragraph 98(6) (retained apparatus).
  • (2) Nothing in sub-paragraph (1) requires the undertaker to repay any charge, cost or expense for which Cadent is liable to a third party or the undertaker as a consequence of any default, negligence or omission by Cadent, its officers, employees, servants, contractors or agents except insofar as such default or omission is caused by a breach of this Part of this Schedule by the undertaker or is in consequence of the construction, use, maintenance or failure of any of the authorised works by or on behalf of the undertaker.
  • (3) There will be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule and which is not re-used as part of the alternative apparatus, that value being calculated after removal.
  • (4) If in accordance with the provisions of this Part of this Schedule—
  • (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
  • (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 61 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to Cadent by virtue of sub-paragraph will be reduced by the amount of that excess save where it is not possible or appropriate in the circumstances (including due to statutory or regulatory changes) to obtain the existing type of apparatus at the same capacity and dimensions or place at the existing depth in which case full costs will be borne by the undertaker.

  • (5) For the purposes of sub-paragraph (4)—
  • (a) an extension of apparatus to a length greater than the length of existing apparatus will not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
  • (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole will be treated as if it also had been agreed or had been so determined.
  • (6) An amount which apart from this sub-paragraph would be payable to Cadent in respect of works by virtue of sub-paragraph (1) will, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on Cadent any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.

Indemnity

100
  • (1) Subject to sub-paragraphs (2) to (4) if by reason or in consequence of the construction of any such works authorised by this Part of this Schedule (including without limitation relocation, diversion, decommissioning, construction and maintenance of apparatus or alternative apparatus) or in consequence of the construction, use, maintenance or failure of any of the authorised works by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by him) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised works) or property of Cadent, or there is any interruption in any service provided, or in the supply of any goods, by Cadent, or Cadent becomes liable to pay any amount to any third party, the undertaker will—
  • (a) bear and pay on demand the cost reasonably incurred by Cadent in making good such damage or restoring the supply; and
  • (b) indemnify Cadent for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from Cadent, by reason or in consequence of any such damage or interruption or Cadent becoming liable to any third party as aforesaid other than arising from any default of Cadent.
  • (2) The fact that any act or thing may have been done by Cadent on behalf of the undertaker or in accordance with a plan approved by Cadent or in accordance with any requirement of Cadent or under its supervision including under any watching brief will not (unless sub-paragraph (3) applies) excuse the undertaker from liability under the provisions of this sub-paragraph (1) unless Cadent fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan.
  • (3) Nothing in sub-paragraph (1) imposes any liability on the undertaker in respect of—
  • (a) any damage or interruption to the extent that it is attributable to the neglect or default of Cadent, its officers, servants, contractors or agents;
  • (b) any authorised works or any other works authorised by this Part of this Schedule carried out by Cadent with the benefit of this Order pursuant to section 156 of the Planning Act 2008 or article 52 (benefit of Order) subject to the proviso that once such works become apparatus (“new apparatus”), any authorised works yet to be executed and not falling within this paragraph (b) will be subject to the full terms of this Part of this Schedule including this paragraph 100; and
  • (c) any indirect or consequential loss of any third party (including but not limited to loss of use revenue profit contract production increased cost of working or business interruption arising from any such damage or interruption, which is not reasonably foreseeable at the commencement of the relevant works referred to in sub-paragraph (1)).
  • (4) Cadent must give the undertaker reasonable notice of any such third party claim or demand and no settlement or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the promoter and considering their representations.

Enactments and agreements

101

Save to the extent provided for to the contrary elsewhere in this Part of this Schedule or by agreement in writing between Cadent and the undertaker, nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and Cadent in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made; except that in the event of an inconsistency between a term of this Part of this Schedule and a term of—

  • (a) the deed of easement between (1) Mr G.M.V. Winn and others (2) and The British Gas Corporation dated 25 April 1975; and
  • (b) the deed of easement between (1) Mr G.M.V. Winn and others (2) and The British Gas Corporation dated 6 May 1980,

the term of this Part of this Schedule applies.

Co-operation

102

Where in consequence of the proposed construction of any of the authorised works, the undertaker or Cadent requires the removal of apparatus under paragraph 96(2) (removal of apparatus) or Cadent makes requirements for the protection or alteration of apparatus under paragraph 98 (retained apparatus), the undertaker must use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of Cadent’s undertaking and Cadent must use its best endeavours to co-operate with the undertaker for that purpose.

103

For the avoidance of doubt whenever Cadent’s consent, agreement or approval is required in relation to plans, documents or other information submitted by Cadent or the taking of action by Cadent, it must not be unreasonably withheld or delayed.

Access

104

If in consequence of the agreement reached in accordance with paragraph 95(1) (acquisition of land) or the powers granted under this Order the access to any apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by Cadent in respect of the apparatus) is materially obstructed, the undertaker must provide such alternative rights and means of access to such apparatus as will enable Cadent to maintain or use the apparatus no less effectively than was possible before such obstruction.

Arbitration

105

Any difference or dispute arising between the undertaker and Cadent under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and Cadent, be determined by arbitration in accordance with article 61 (arbitration) and in settling any difference or dispute, the arbitrator must have regard to the reasonable requirements of Cadent for ensuring the safety and economic and efficient operation of Cadent’s apparatus and of the authorised development.

Notices

106

The plans submitted to Cadent by the undertaker pursuant to sub-paragraph 98(1) (retained apparatus) must be sent to Cadent Gas Limited Plant Protection by e-mail to plantprotection@cadentgas.com copied by e-mail to landservices@cadentgas.com and sent to the General Counsel Department at Cadent’s registered office or such other address as Cadent may from time to time appoint instead for that purpose and notify to the undertaker.

PART 8 — FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS

Application

107

For the protection of any operator, referred to in this Part of this Schedule, the following provisions have effect, unless otherwise agreed in writing between the undertaker and the operator.

Interpretation

108

In this Part of this Schedule—

  • “the code rights” has the same meaning as in the Paragraph 3 of the electronic communications code;
  • “electronic communications apparatus” has the same meaning as in electronic communications code;
  • “electronic communications code operator” means a person in whose case the electronic communications code is applied by a direction under section 106 of the 2003 Act;
  • “infrastructure system” has the same meaning as in the electronic communications code and references to providing an infrastructure system are to be construed in accordance with paragraph 7(2) of that code; and
  • “operator” means the operator of an electronic communications code network.
109

The exercise of the powers of article 33 (statutory undertakers) is subject to Part 10 (undertaker’s works affecting electronic communications apparatus) of the electronic communications code.

110
  • (1) Subject to paragraphs 111 and 112, if as the result of the authorised development or its construction, or of any subsidence resulting from any of the authorise development—
  • (a) any damage is caused to any electronic communications apparatus belonging to an operator (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised development), or other property of an operator; or
  • (b) there is any interruption in the supply of the service provided by an operator the undertaker must bear and pay the cost reasonably incurred by the operator in making good such damage or restoring the supply and make reasonable compensation to that operator for any other expenses, loss, damages, penalty or costs incurred by it, by reason, or in consequence of, any such damage or interruption.
  • (2) Nothing in this Part of this Schedule imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of an operator, its officers, servants, contractors or agents.
  • (3) The operator must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise of the claim or demand is to be made without the consent of the undertaker and if such consent, is withheld, the undertaker has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
  • (4) Any difference arising between the undertaker and the operator under this Part of this Schedule must be referred to and settled by arbitration under article 61 (arbitration).
111

This Part of this Schedule does not apply to—

  • (a) any apparatus in respect of which the relations between the undertaker and an operator are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act; or
  • (b) any damage, or any interruption, caused by electro-magnetic interference arising from the construction or use of the authorised development.
112

Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and an operator in respect of any apparatus in land belonging to the undertaker on the date on which this Order is made; except that in the event of an inconsistency between a term of this Part of this Schedule and a term of the wayleave between (1) The London and North Eastern Railway Company and (2) Her Majesty’s Postmaster General dated 24 May 1933, the term of this Part of this Schedule applies.

PART 9 — FOR THE PROTECTION OF THE NORTH EAST LINDSEY DRAINAGE BOARD

Application

113

The provisions of this Part of this Schedule have effect for the protection of the Board unless otherwise agreed in writing between the undertaker and the Board.

Interpretation

114

In this part of this Schedule—

  • “construction” includes execution, placing, altering, replacing, relaying and removal; and “construct” and “constructed” must be construed accordingly;
  • “drainage work” means any ordinary watercourse and includes any land that provides or is expected to provide flood storage capacity for any ordinary watercourse and any bank, wall, embankment or other structure, or any appliance, constructed or used for land drainage or flood defence in connection with an ordinary watercourse;
  • “ordinary watercourse” has the meaning given in section 72 (Interpretation) of the Land Drainage Act 1991119;
  • “plans” includes sections, drawings, specifications and method statements;
  • “specified works” means— the making of any opening into or connections with any watercourse or drain in connection with the authorised development; and/or so much of any work or operation of the authorised development as is in, on, under, over or within 9 metres of a drainage work for which the Board has responsibility or is otherwise likely to— affect any such drainage work; affect the total volume or volumetric rate of flow of water in or flowing to or from any such drainage work; affect the flow of water in any such drainage work; or affect the conservation, distribution or use of water resources.
115
  • (1) The undertaker must not make any opening into or connections with any watercourse or drain in connection with the authorised development or carry out any specified work except—
  • (a) in accordance with plans approved by the Board in accordance with this Part of this Schedule or determined under paragraph 122; and
  • (b) where the Board has been given the opportunity to supervise the making of the opening or connection,

and no discharge of water under article 18 (discharge of water) shall be made until details of the location and maximum rate of discharge have been submitted to and approved in writing by the Board (unless such location or maximum rate of discharge is in accordance with a drainage strategy approved under paragraph 12(1) of Schedule 2 (requirements)).

  • (2) Before beginning to construct any specified work, the undertaker must submit to the Board plans of the specified work, and any such further particulars available to it as the Board may within 28 days of the submission of the plans reasonably require.
  • (3) Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by the Board or determined under paragraph 122.
  • (4) Any approval of the Board required under this paragraph—
  • (a) must not be unreasonably withheld or delayed;
  • (b) is deemed to have been given if it is neither given nor refused within 2 months of the submission of the plans for approval (or the submission of further particulars if applicable) or, in the case of a refusal, if it is not accompanied by a statement of the grounds of refusal; and
  • (c) may be given subject to such reasonable requirements and conditions as the Board may consider appropriate.
  • (5) The Board must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (4)(b).
  • (6) Where under this Part of this Schedule the Board is required to give its consent or approval in respect of any matter, that consent or approval is subject to the condition that the Board complies with its obligations to consult other appropriate agencies, to have regard to any guidance issued by any appropriate supervisory body and has regard to its obligations under statute.
116

Without limiting paragraph 115, the requirements which the Board may make under that paragraph include conditions requiring the undertaker at its own expense to construct such protective works, whether temporary or permanent, during the construction of the specified work (including the provision of flood banks, walls or embankments or other new works and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably necessary—

  • (a) to safeguard any drainage work against damage; or
  • (b) to secure that its efficiency for flood defence purposes is not impaired and that the risk of flooding is not otherwise increased, by reason of any specified work.
117
  • (1) Subject to sub-paragraph (2), any specified work, and all protective works required by the Board under paragraph 116 , must be constructed—
  • (a) without unreasonable delay in accordance with the plans approved or deemed to have been approved or settled under this Part; and
  • (b) to the reasonable satisfaction of the Board, and an officer of the Board is entitled to give such notice as may be reasonably required in the circumstances to watch and inspect the construction of such works.
  • (2) The undertaker must give to the Board—
  • (a) not less than 14 days’ notice in writing of its intention to commence construction of any specified work; and
  • (b) notice in writing of its completion not later than 7 days after the date on which it is brought into use.
  • (3) If the Board reasonably requires, the undertaker must construct all or part of the protective works so that they are in place before the construction of the specified work to which the protective works relate.
  • (4) If any part of a specified work or any protective work required by the Board is constructed otherwise than in accordance with the requirements of this Part of this Schedule, the Board may by notice in writing require the undertaker at the undertaker’s expense to comply with the requirements of this Part of this Schedule or (if the undertaker so elects and the Board in writing consents, such consent not to be unreasonably withheld or delayed) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent and within such limits as the Board reasonably requires.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.