The North Lincolnshire Green Energy Park Order 2025

Type Statutory-Instrument
Publication 2025-03-13
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • (3) The scheme approved under sub-paragraph (1) must be implemented as approved prior to the coming into operation of the authorised development and maintained throughout the operation of the authorised development.
  • (4) Prior to the energy park works coming into operation, the undertaker will construct the northern spur.
  • (5) No later than the date that is 18 months after the date of the energy park works coming into operation, the undertaker must submit to the relevant planning authority for its approval a report (“the CHP review”) updating the combined heat and power assessment.
  • (6) The CHP review submitted must—
  • (a) consider the opportunities that reasonably exist for the export of heat from Work No. 11 at the time of submission of the CHP review; and
  • (b) include a list of actions (if any) that the undertaker is reasonably and practicably able to take (without material additional cost to the undertaker) to increase the potential for the export of heat from Work No. 11.
  • (7) The undertaker must take such actions as are included, within the timescales specified, in the approved CHP review.
  • (8) The relevant planning authority must consult with the Environment Agency before approving any CHP review.

Commissioning

19
  • (1) Notice of the intended completion of commissioning of Work Nos. 1 (ERF), 1B (CCUS) and 2(b) (CBMF) must be given to the relevant planning authority where practicable prior to such completion.
  • (2) Work No. 1B (CCUS) must be constructed and commissioned within 6 months of the commissioning of Work No. 1 (ERF) and Work No. 2(b) (CBMF) must be constructed and commissioned within 12 months of the commissioning of Work No. 1B except that these timescales may be amended where it has been demonstrated to the satisfaction of the relevant planning authority that the alternative timescales sought are unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.

Carbon Capture

20
  • (1) Once commissioned, Work No. 1B (CCUS) must capture a minimum quantity of CO2 which equates to the lesser of 54,387 tonnes per annum or 8.37% of the weight of the ERF waste throughput per annum from the date that the CCUS is commissioned until the energy park works are decommissioned.
  • (2) Within 28 days of the date which is one calendar year from the date Work No. 1B comes into operation, the undertaker must submit a report to the relevant planning authority confirming the amount of CO2 captured during the previous year of operation and must continue to submit such reports annually until the energy park works are decommissioned.

Rail

21
  • (1) The undertaker must use reasonable endeavours to complete all necessary works forming part of Work No.3 to such an extent as to facilitate the use of the railway by rail freight importing or exporting waste or other materials within 12 months of construction of the new access road (Work No. 5) to base course level as per requirement 15 and in any event must complete Work No. 3 prior to commissioning of Work No. 1
  • (2) Following completion of Work No. 3 the undertaker must retain, manage and keep the railway forming part of the authorised development available for use throughout the construction and operation of the authorised development.

Local employment and skills

22
  • (1) No part of the authorised development, save for the preliminary works, may commence until a detailed employment and skills plan (which must be in accordance with the outline employment and skills policy) has been submitted to and approved by the relevant planning authority.
  • (2) The employment and skills plan shall identify opportunities for individuals and businesses based in the region of Greater Lincolnshire to access employment opportunities associated with the construction, operation and maintenance of the authorised development.
  • (3) The employment and skills plan approved under sub-paragraph (1) must be implemented as approved.

Noise

23

The rating level (LAr) of noise from the operation of the authorised development shall not exceed: 45 dB LAr for any fifteen-minute period between 23:00 and 07:00; and 50 dB LAeq for any one-hour period between 07:00 and 23:00, determined one metre free-field external to any window or door of any existing permanent residential premises using the definitions and methods described in ‘Methods for rating and assessing industrial and commercial sound’ British Standards Institution BS4142 2014+A1:2019.

PRF

24
  • (1) Notice of the intended completion of commissioning of the plastic recycling facility (Work No. 6) must be given to the relevant planning authority where practicable prior to such completion. Approved details and amendments to them.
  • (2) Prior to the coming into operation of Work No. 1 (ERF) the plastic recycling Facility (Work No. 6) must have been constructed and commissioned.
  • (3) The plastic recycling facility (Work No. 6) shall only treat plastic waste received from suppliers who are also supplying the undertaker with refuse derived fuel used to fuel the combustion system in Work No. 1 (b).
25

Where a requirement requires the authorised development to be constructed in accordance with details approved by the relevant planning authority, the approved details are taken to include any amendments subsequently approved by the relevant planning authority.

Amendments agreed by the relevant planning authority

26
  • (1) Where the words “unless otherwise agreed by the relevant planning authority” appear in the requirements—
  • (a) whenever the undertaker requests that the relevant planning authority provides its agreement in accordance with those words, the undertaker must provide the relevant planning authority with information on compliance with any document listed in the relevant requirement and any other relevant certified document; and
  • (b) any such approval or agreement may only be given in relation to non-material amendments and where it has been demonstrated to the satisfaction of that authority that the subject matter of the approval or agreement sought will not give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
  • (2) In cases where the requirement or the relevant sub-paragraph requires consultation with specified persons, any such approval or agreement must not be given without the relevant planning authority having first consulted with those persons.

Requirement for written approval

27

Where under any of the requirements the approval or agreement of the relevant planning authority or another person is required, that approval or agreement must be provided in writing.

Anticipatory steps towards compliance with any requirement

28
  • (1) If before this Order came into force the undertaker or any other person took any steps that were intended to be steps towards compliance with any provision of this Schedule, those steps must be taken into account for the purpose of determining compliance with that provision if they would have been valid steps for that purpose had they been taken after this Order came into force.
  • (2) Any document submitted to the relevant planning authority which the undertaker considers may constitute a step referred to at sub-paragraph (1) must include a statement that it is likely to engage sub-paragraph (1).

PART 2 — PROCEDURE FOR DISCHARGE OF REQUIREMENTS

Applications made under requirements

29
  • (1) Where an application has been made to the discharging authority for any consent, agreement or approval required by a requirement (including consent, agreement or approval in respect of part of a requirement) included in this Order—
  • (a) the undertaker must give the discharging authority sufficient information to identify the requirement(s) to which the application relates;
  • (b) the undertaker must provide such particulars, and the request be accompanied by such plans and drawings as are reasonably considered necessary to deal with the application.
  • (2) The discharging authority must give notice to the undertaker of the decision on the application before the end of the decision period.
  • (3) For the purposes of sub-paragraph (2), the decision period is—
  • (a) where no information is requested under paragraph 31 (further information), 8 weeks from the day immediately following that on which the application is received by the discharging authority;
  • (b) where further information is requested under paragraph 31 (further information), 8 weeks from the day immediately following that on which further information has been supplied by the undertaker under paragraph 31; or
  • (c) such longer period as may be agreed between the undertaker and the discharging authority in writing before the end of the period in sub-paragraph (a) or (b).
  • (4) In determining any application made under sub-paragraph (1), the discharging authority may—
  • (a) give or refuse its consent, agreement or approval; or
  • (b) give its consent, agreement or approval subject to reasonable conditions,

and where consent, agreement or approval is refused or granted subject to conditions the discharging authority must provide its reasons for that decision with the notice of the decision pursuant to sub-paragraph (2).

Fees

30
  • (1) Where an application is made to the discharging authority for consent, agreement or approval in respect of a requirement, a fee prescribed under regulation 16(1)(b) of the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 201237 (as may be amended or replaced from time to time) is to be paid to that authority.
  • (2) Any fee paid under this Schedule must be refunded to the undertaker within 42 days of—
  • (a) the application being rejected as invalidly made; or
  • (b) the discharging authority failing to determine the application within the decision period as determined under paragraph 29(3),

unless within that period the undertaker agrees, in writing, that the fee is to be retained by the discharging authority and credited in respect of a future application.

Further information

31
  • (1) In relation to any part of an application made under this Schedule, the discharging authority has the right to request such further information from the undertaker as is necessary to enable it to consider the application.
  • (2) In the event that the discharging authority considers such further information to be necessary the discharging authority must, as soon as reasonably practicable and within 20 business days of receipt of the application, notify the undertaker in writing specifying the further information required and (if applicable) to which part of the application it relates.
  • (3) In the event that the discharging authority does not give such notification within that 20 business day period it is deemed to have sufficient information to consider the application and is not subsequently entitled to request further information without the prior agreement of the undertaker.
  • (4) Where further information is requested under this paragraph in relation to part only of an application, that part is to be treated as separate from the remainder of the application for the purposes of calculating the time periods referred to in paragraph 29 (applications made under requirements) and in this paragraph.

Appeals

32
  • (1) The undertaker may appeal to the Secretary of State in the event that—
  • (a) the discharging authority refuses an application for any agreement or approval required by a requirement included in this Order;
  • (b) the discharging authority does not give notice of its decision to the undertaker within the decision period as determined in paragraph 29;
  • (c) on receipt of a request for further information pursuant to paragraph 31 (further information) the undertaker considers that either the whole or part of the specified information requested by the discharging authority is not reasonably necessary for consideration of the application; or
  • (d) on receipt of any further information requested, the discharging authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not reasonably necessary for consideration of the application.
  • (2) The appeal process is as follows—
  • (a) the undertaker must submit the appeal documentation to the Secretary of State, a copy of the application submitted to the discharging authority and any supporting documentation which the undertaker may wish to provide (“the appeal documentation”);
  • (b) the undertaker must on the same day provide copies of the appeal documentation to the discharging authority and any requirement consultee (if applicable) required to be consulted pursuant to the article or requirement which is the subject of the appeal;
  • (c) as soon as is practicable after receiving the appeal documentation, but in any event within 20 business days of receiving the appeal documentation, the Secretary of State must appoint a person and forthwith notify the appeal parties of the identity of the appointed person and the address to which all correspondence for that person’s attention should be sent;
  • (d) the discharging authority and any requirement consultee (if applicable) must submit written representations to the appointed person in respect of the appeal within 20 business days of the date on which the appeal parties are notified of the appointment of a person under paragraph (c) and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person; and
  • (e) the appeal parties must make any counter-submissions to the appointed person within 20 business days of receipt of written representations pursuant to paragraph (d) above.
  • (3) The appointed person must make their decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable. If the appointed person considers that further information is necessary to consider the appeal, the appointed person must, as soon as practicable, notify the appeal parties in writing specifying the further information required, the appeal party from whom the information is sought, and the date by which the information is to be submitted.
  • (4) Any further information required pursuant to sub-paragraph (3) must be provided by the appeal party from whom the information is sought to the appointed person and to other appeal parties by the date specified by the appointed person. Any written representations concerning matters contained in the further information must be submitted to the appointed person, and made available to all appeal parties, within 20 business days of that date.
  • (5) On an appeal under this paragraph, the appointed person may—
  • (a) allow or dismiss the appeal; or
  • (b) reverse or vary any part of the decision of the discharging authority (whether the appeal relates to that part of it or not),

and may deal with the application as if it had been made to the appointed person in the first instance.

  • (6) The appointed person may proceed to a decision on an appeal taking into account only such written representations as have been sent within the time limits prescribed, or set by the appointed person, under this paragraph.
  • (7) The appointed person may proceed to a decision even though no written representations have been made within those time limits, if it appears to the appointed person that there is sufficient material to enable a decision to be made on the merits of the case.
  • (8) The decision of the appointed person on an appeal is final and binding on the parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review.
  • (9) If an approval is given by the appointed person pursuant to this Schedule, it is deemed to be an approval for the purpose of Part 1 of this Schedule (requirements) as if it had been given by the discharging authority. The discharging authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) may not be taken to affect or invalidate the effect of the appointed person’s determination.
  • (10) Save where a direction is given pursuant to sub-paragraph (11) requiring the costs of the appointed person to be paid by the discharging authority, the reasonable costs of the appointed person must be met by the undertaker.
  • (11) On application by the discharging authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction and the terms on which it is to be made, the appointed person must have regard to the Planning Practice Guidance: Appeals (March 2014) on the award of costs, or any guidance which may from time to time replace it.

Interpretation

33

In this Schedule—

  • “the appeal parties” means the discharging authority, the requirement consultee and the undertaker;
  • “business day” means a day other than Saturday or Sunday, which is not Christmas Day, Good Friday or a bank holiday under section 1 (bank holidays) of the Banking and Financial Dealings Act 197138;
  • “discharging authority” means that person or body responsible for approving details pursuant to the requirements in Part 1 of this Schedule.

SCHEDULE 3 — STREETS SUBJECT TO STREET WORKS

(1) Area (2) Streets subject to street works (3) Description of street works
The rights of way and access plans – Sheet 1 The rights of way and access plans – Sheet 1 The rights of way and access plans – Sheet 1
In the Borough of North Lincolnshire Brumby Common Lane and verge, Scunthorpe between points SW1 and SW2 Installation of the DHPWN (Work Nos. 10 and 11).
The rights of way and access plans – Sheet 2 The rights of way and access plans – Sheet 2 The rights of way and access plans – Sheet 2
In the Borough of North Lincolnshire West of M181 between points SW3 and SW4 Installation of the DHPWN (Work Nos. 10 and 11).
The rights of way and access plans – Sheet 3 The rights of way and access plans – Sheet 3 The rights of way and access plans – Sheet 3
In the Borough of North Lincolnshire A18 Doncaster Road between points SW5 and SW6 Installation of the DHPWN (Work Nos. 10 and 11).
The rights of way and access plans – Sheet 4 The rights of way and access plans – Sheet 4 The rights of way and access plans – Sheet 4
In the Borough of North Lincolnshire Flixborough Parish Council B1216 Ferry Road West between points SW7 and SW8 The creation of a new roundabout at the junction with the new spine road. Installation of the DHPWN (Work Nos. 10 and 11).
In the Borough of North Lincolnshire Flixborough Parish Council B1216 Ferry Road West between points SW8 and SW9 Installation of the DHPWN (Work Nos. 10 and 11).
In the Borough of North Lincolnshire Flixborough Parish Council A1077 Phoenix Parkway between points SW10 and SW11 including the eastern and western junctions with Ferry Road West The creation of a new staggered toucan crossing, extension of the existing exit lane towards Ferry Road West with the associated road marking, re-shape of the existing traffic islands, realignment of the kerb line located at the north of the crossing and the creation of a new shared footway that connects to the junction with Ferry Road West and Main Avenue. Installation of the DHPWN (Work Nos. 10 and 11).
In the Borough of North Lincolnshire Flixborough Parish Council A1077 Phoenix Parkway between points SW11 and SW12 Installation of the DHPWN (Work Nos. 10 and 11).
In the Borough of North Lincolnshire Flixborough Parish Council Holyrood Drive between points SW13 and SW14 Installation of the DHPWN (Work Nos. 10 and 11).
The rights of way and access plans – Sheet 5 The rights of way and access plans – Sheet 5 The rights of way and access plans – Sheet 5
In the Borough of North Lincolnshire Flixborough Parish Council First Avenue between points SW16 and SW17 Improvements including the creation of a segregated cycle track, the realignment of the southern kerbline and new road marking. Installation of the DHPWN (Work Nos. 10 and 11) and other utilities.
In the Borough of North Lincolnshire Flixborough Parish Council Bellwin Drive between points SW17 and SW18 Installation of the DHPWN (Work Nos. 10 and 11) and other utilities.
In the Borough of North Lincolnshire Flixborough Parish Council The junction of Bellwin Drive and Stather Road between points SW18 and SW19 Improvements and widening including the creation of a segregated cycle track, realignment of Stather Road and Bellwin Drive with associated road marking, creation of a new junction with a ghost island arranged to the new spine road and new junction to the proposed employee parking area for the ERF. Installation of the DHPWN (Work Nos. 10 and 11) and other utilities.
In the Borough of North Lincolnshire Flixborough Parish Council North of Stather Road between points SW19 and SW20 Installation of the DHPWN (Work Nos. 10 and 11) and other utilities.
In the Borough of North Lincolnshire Flixborough Parish Council First Avenue between points SW20 and SW17 Installation of the DHPWN (Work Nos. 10 and 11) and other utilities.
In the Borough of North Lincolnshire Flixborough Parish Council First Avenue between points SW20 and SW21 Installation of the DHPWN (Work Nos. 10 and 11) and other utilities.
The rights of way and access plans – Sheet 9 The rights of way and access plans – Sheet 9 The rights of way and access plans – Sheet 9
In the Borough of North Lincolnshire A1077 Phoenix Parkway between points SW15 (also on Sheet 4) and SW22 Installation of the DHPWN (Work Nos. 11 and 12).
In the Borough of North Lincolnshire A1077 Phoenix Avenue and Clayfield Road roundabout between points SW22 and SW23 Installation of the DHPWN (Work Nos. 10 and 11).
The rights of way and access plans – Sheet 10 The rights of way and access plans – Sheet 10 The rights of way and access plans – Sheet 10
In the Borough of North Lincolnshire A1077 Phoenix Parkway between points SW23 (Sheet 9) and SW24 Installation of the DHPWN (Work Nos. 10 and 11).
In the Borough of North Lincolnshire A1077 Phoenix Parkway and Normanby Road roundabout between points SW24 and SW25 Installation of the DHPWN (Work Nos. 10 and 11).
In the Borough of North Lincolnshire Normanby Road, Warren Road, Bessemer Way and Mannaberg Way between points SW25 and SW26 Installation of the DHPWN (Work Nos. 10 and 11).

SCHEDULE 4 — STREETS TO BE PERMANENTLY STOPPED UP FOR WHICH A SUBSTITUTE IS TO BE PROVIDED

(1) Area (2) Street to be stopped up (3) Extent of stopping up (4) New street to be substituted
The rights of way and access plans – Sheets 4 and 5 The rights of way and access plans – Sheets 4 and 5 The rights of way and access plans – Sheets 4 and 5 The rights of way and access plans – Sheets 4 and 5
In the Borough of North Lincolnshire Flixborough Parish Council Reference A1 to A2 Part of Stather Road Reference A1 to A2 from point A1 located 40 metres north of Neap House to point A2 located at the junction between Stather Road and Bellwin Drive, a distance of 1020 metres Reference B1 to B2 To be substituted by a new highway from point B1 located on the B1216 Ferry Road West running in a northern direction to a point B2 located 146 metres east of Bellwin Drive, a distance of 1410 metres

SCHEDULE 5 — PUBLIC RIGHTS OF WAY

PART 1 — PUBLIC RIGHTS OF WAY TO BE TEMPORARILY SUSPENDED

(1) Area (2) Footpath to be temporarily suspended or diverted (3) Extent of temporary suspension (4) Diversion to be provided
The rights of way and access plans – Sheet 6 The rights of way and access plans – Sheet 6 The rights of way and access plans – Sheet 6 The rights of way and access plans – Sheet 6
In the Borough of North Lincolnshire Flixborough Parish Council Public footpath FLIX175 from its junction with Stather Road to the railway crossing point Between points E1 and E2, a distance of 116 metres No
In the Borough of North Lincolnshire Flixborough Parish Council Public footpath FLIX178 in the vicinity of the railway crossing point Between points E3 and E4, a distance of 47.5 metres No
The rights of way and access plans – Sheet 9 The rights of way and access plans – Sheet 9 The rights of way and access plans – Sheet 9 The rights of way and access plans – Sheet 9
In the Borough of North Lincolnshire Public footpath SCUN 175 at the crossing with the A1077 Phoenix Parkway Between points E5 and E6, a distance of 21 metres Yes
In the Borough of North Lincolnshire Cycle track NCN 169 at the crossing with the A1077 Phoenix Parkway Between points E5 and E6, a distance of 21 metres Yes

PART 2 — NEW PUBLIC RIGHTS OF WAY TO BE CREATED

(1) Area (2) Length of footpath/pedestrian-cycle path
The rights of way and access plans – Sheet 4 The rights of way and access plans – Sheet 4
In the Borough of North Lincolnshire Flixborough Parish Council Reference CCF1 to CCF2 A cycle track in the verge on the northern side of the B1216 Ferry Road West from point CCF1 in a south eastern direction to point CCF2, a distance of 501 metres
In the Borough of North Lincolnshire Flixborough Parish Council Reference CCF3 to CCF5 (Sheet 5) A cycle track in the verge on the northern side of Ferry Road West from point CCF3 (east of the A1077 Phoenix Parkway) in a north western direction to point CCF2 on the new spine road and then in a northern direction to Point CCF4 on Stather Road and then in a western direction to point CCF5 at the junction with Bellwin Drive, a distance of 2090 metres
In the Borough of North Lincolnshire Flixborough Parish Council Reference CCF6 to CCF7 A cycle track from point CCF6 on the new spine road in a western direction to point CCF7 on Stather Road, a distance of 330 metres
In the Borough of North Lincolnshire Flixborough Parish Council Reference FP1 to FP2 A footpath from point FP1 on the new spine road in an eastern direction along Lysaght’s drain to point FP2, a distance of 921 metres
The rights of way and access plans – Sheet 5 The rights of way and access plans – Sheet 5
In the Borough of North Lincolnshire Flixborough Parish Council Reference CCF8 to CCF9 A cycle track in the verge on the south side of First Avenue from point CCF8 in a north eastern direction to point CCF9, a distance of 150 metres
In the Borough of North Lincolnshire Flixborough Parish Council Reference FP3 to FP4 A footpath from point FP3 on Stather Road in a north western direction to point FP4 on existing public right of way FLIX 304, a distance of 412 metres
The rights of way and access plans – Sheet 6 The rights of way and access plans – Sheet 6
In the Borough of North Lincolnshire Flixborough Parish Council Reference FP6 to FP5 A footpath from point FP6 on existing public right of way FLIX 178 in a south western direction to point FP5, a distance of 97 metres

SCHEDULE 6

PART 1 — PRIVATE MEANS OF ACCESS TO BE CLOSED FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED

(1) Area (2) Private means of access
The rights of way and access plans – Sheet 4 The rights of way and access plans – Sheet 4
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as C1
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as C2
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as C10
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as C11
The rights of way and access plans – Sheet 5 The rights of way and access plans – Sheet 5
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as C3
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as C4
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as C5
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as C6
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as C7
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as C8
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as C9
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as C12

PART 2 — NEW PRIVATE MEANS OF ACCESS CREATED

(1) Area (2) Private means of access
The rights of way and access plans - Sheet 4 The rights of way and access plans - Sheet 4
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as D1
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as D2
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as D3
The rights of way and access plans - Sheet 5 The rights of way and access plans - Sheet 5
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as D4
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as D5
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as D6
In the Borough of North Lincolnshire Flixborough Parish Council The private means of access shown as D7

SCHEDULE 7 — CLEARWAYS

(1) Area (2) Road name and length (3) Measures
The TRO drawings – Sheet 4 The TRO drawings – Sheet 4 The TRO drawings – Sheet 4
In the Borough of North Lincolnshire Flixborough Parish Council Reference B and C The B1216 Ferry Road West including the new roundabout between B and C. Clearway (including verges and hardshoulders)
The TRO drawings – Sheets 4 and 5 The TRO drawings – Sheets 4 and 5 The TRO drawings – Sheets 4 and 5
In the Borough of North Lincolnshire Flixborough Parish Council Reference A and D A new road between B1216 Ferry Road West northwards to Stather Road between A and D. Clearway (including verges and hardshoulders)
The TRO drawings – Sheet 5 The TRO drawings – Sheet 5 The TRO drawings – Sheet 5
In the Borough of North Lincolnshire Flixborough Parish Council Reference E and F First Avenue between E and F. Proposed waiting time restriction

SCHEDULE 8 — CLASSIFICATION OF HIGHWAYS

(1) Area (2) Extent of highway (3) Classification
The rights of way and access plans – Sheets 4 and 5 The rights of way and access plans – Sheets 4 and 5 The rights of way and access plans – Sheets 4 and 5
In the Borough of North Lincolnshire Flixborough Parish Council A new road from the B1216 Ferry Road West northwards to Stather Road in the approximate position between B1 to B2 Classified C Road

SCHEDULE 9 — SPEED LIMITS

(1) Area (2) Extent of highway (3) Speed limit
The TRO drawings – Sheets 4 and 5 The TRO drawings – Sheets 4 and 5 The TRO drawings – Sheets 4 and 5
In the Borough of North Lincolnshire Flixborough Parish Council Reference A and D A new road from the B1216 Ferry Road West northwards to Stather Road between A and D. 50 miles per hour

SCHEDULE 10 — LAND IN WHICH ONLY NEW RIGHTS ETC., MAY BE ACQUIRED

PART 1 — OPTION A – LAND IN WHICH ONLY NEW RIGHTS ETC., MAY BE ACQUIRED

(1) Number of land shown on land plan (2) Purpose for which rights may be acquired
Access tracks Plots 1-1, 1-2, 1-3, 1-11, 1-12, 1-13, 1-14, 2-12, 2-13, 2-15, 2-16, 2-17, 2-18, 3-3, 3-4, 3-5, 3-6, 3-7, 3-8, 3-17, 3-18, 3-22, 3-25, 4-33, 4-81, 6-2, 8-4, 8-5, 8-6, 8-7, 8-8 1 The right to enter onto and remain on the land for the purposes of construction, installation, operation, maintenance and decommissioning of the authorised development and to— a pass and repass with or without vehicles, plant, equipment, materials and machinery to access adjoining land and highway for the purposes of laying, installing, adjusting, altering, constructing, using, maintaining, repairing, renewing, upgrading, inspecting, removing and replacing authorised works; b retain and maintain existing hardstandings and lay down, use, repair, alter and remove hardstandings for the purposes of access to adjoining land and highway; c retain, maintain and use temporary supporting or protective structures and erect temporary supporting or protective structures (including the bridging over or protection of the apparatus of the statutory undertakers) for the purposes of access to adjoining land and highway; d alter, lop, uproot and replant trees, shrubs and hedges and other vegetation for the purposes of enabling the right to pass and repass to and from adjoining land; e retain and maintain existing temporary permissive paths and lay out temporary permissive paths for public use (if applicable); f effect access and egress to and from the highway; g retain, maintain, straighten, widen, repair, alter, upgrade and use existing access routes for the purposes of accessing adjoining land and highway; h remove fences, hedges or other barriers during any period in which construction, maintenance, upgrading, improvement, renewal or removal works are being carried out and for the exercise of the power to access the cables (subject to the prior erection of any temporary stock proof fencing as is reasonably required and the replacement or re-instatement of the fences, hedges or other barriers following the end of each period of the exercise of the rights); and i construct, install, use, retain, maintain, inspect, modify, improve, adjust, repair, replace, extend, test, cleanse and remove temporary or permanent drainage and manage waterflows in any drains, watercourses and culverts. “adjoining land” for the purposes of this paragraph 1 means such other parts of the land within the Order limits required for the authorised development.
Access tracks (public rights of way) Plots 5-66, 5-67 2 The right to enter onto and remain on the land for the purposes of construction, installation, operation, maintenance and decommissioning of the authorised development and to— a pass and repass with or without vehicles, plant, equipment, materials and machinery to access adjoining land and highway for the purposes of laying, installing, adjusting, altering, constructing, using, maintaining, repairing, renewing, upgrading, inspecting, removing and replacing authorised works; b retain and maintain existing hardstandings for the purposes of access to adjoining land and highway; c retain, maintain and use temporary supporting or protective structures and erect temporary supporting or protective structures (including the bridging over or protection of the apparatus of the statutory undertakers) for the purposes of access to adjoining land and highway; d alter, lop, uproot and replant trees, shrubs and hedges and other vegetation for the purposes of enabling the right to pass and repass to and from adjoining land; e effect access and egress to and from the highway; f retain, maintain, straighten, widen, repair, alter, upgrade and use existing access routes for the purposes of accessing adjoining land and highway; g remove fences, hedges or other barriers during any period in which construction, maintenance, upgrading, improvement, renewal or removal works are being carried out (subject to the prior erection of any temporary stock proof fencing as is reasonably required and the replacement or re-instatement of the fences, hedges or other barriers following the end of each period of the exercise of the rights); and h construct, install, use, retain, maintain, inspect, modify, improve, adjust, repair, replace, extend, test, cleanse and remove temporary or permanent drainage and manage waterflows in any drains, watercourses and culverts. “adjoining land” for the purposes of this paragraph 1 means such other parts of the land within the Order limits required for the authorised development.
Full cable rights Plots 1-4, 1-5, 1-9, 1-10, 2-1, 2-2, 2-4, 2-9, 2-14, 3-3, 3-9, 3-11, 3-12, 3-13, 3-14, 3-19, 3-20, 3-21, 3-26, 4-1, 4-18, 4-21, 4-22, 4-23, 4-106, 5-26, 5-28, 5-31, 5-57, 5-58, 9-1, 9-4, 9-8, 9-11, 9-12, 9-14, 9-19, 9-20, 9-22, 9-23, 9-24, 9-25, 9-27, 9-28, 9-32, 9-35, 9-37, 10-35, 10-53, 10-56, 10-57, 10-60, 10-62 3 The right to enter onto and remain on the land for the purposes of construction, installation, operation, maintenance and decommissioning of the authorised development and to— a construct, lay and install, adjust, alter, use, maintain, repair, replace, renew, upgrade, inspect and remove the cables and pipes by way of drilling and/or trenching; b construct, install, use, retain, maintain, inspect, modify, improve, adjust, repair, extend, test, cleanse, and remove temporary or permanent drainage and manage waterflows in any drains, watercourse and culverts; c pass and repass, with or without vehicles, plant, equipment, materials and machinery for the purposes of constructing, laying, installing, adjusting, altering, using, maintaining, repairing, replacing, renewing, upgrading, inspecting and removing the pipes, cables, cable ducts and jointing works; d retain and maintain existing hardstandings and lay down, use, repair, alter and remove hardstandings for the purposes of constructing, laying, installing, adjusting, altering, using maintaining, repairing, replacing, renewing, upgrading, inspecting and removing the pipes, cables, cable ducts and jointing works; e enter and be upon the land and remain with or without plant, vehicles, machinery, apparatus and equipment which is ancillary to the purposes of transmitting electricity along the cables and steam along the pipes, or use of the cable ducts and jointing works; f retain and use the pipes and cables for the purposes of the transmission of steam, communications, gas and electricity; g place and use plant, machinery and temporary structures within the land for the installation, construction, maintenance, repairing, renewing, upgrading, inspecting, removal and replacing of the pipes, cables, cable ducts and jointing works; h install and maintain cable marker posts to identify the location of the cables, cable ducts and jointing works as required for routine integrity testing; i remove, store and stockpile materials (including excavated material) within the Order land; j remove fences, hedges or other barriers during any period in which construction, maintenance, upgrading, improvement, renewal or removal are being carried out and for the exercise of the power to access the pipes and cables (subject to the prior erection of any temporary stock proof fencing as is reasonably required and the replacement or re-instatement of the fences, hedges or other barriers following the end of each period of the exercise of the rights); k install, alter, re-lay, maintain, protect, adjust or remove pipes, cables, conduits or apparatus (including the pipes, cables, conduits or apparatus of statutory undertakers); l carry out works to lop, fell, cut or coppice trees or remove roots of trees or hedges or shrubs; m retain and maintain existing temporary permissive paths or lay out temporary permissive paths for public use (if applicable); n remove archaeological artefacts where they would prevent or cause it to be materially more difficult or expensive to construct, lay, install, adjust, alter, use, maintain, repair, replace, renew, upgrade, inspect or remove the pipes, cables, cable ducts and jointing works; o carry out environmental mitigation, remediation and enhancement works; p install, construct, use and remove temporary welfare facilities during any periods of construction, maintenance, repair, replacement, renewal, upgrade and removal of the pipes, cables, cable ducts and jointing works; q when the pipes and cables are temporarily unusable, to lay down, install, use, maintain and inspect on the surface of the land steam pipes, electric lines, ancillary equipment and associated works and other conducting media together with conduits or pipes for containing the same in and under the land; and r place temporarily and use plant, machinery and structures on the land in connection with the lighting of the land and the authorised development. 4 The right to enter and remain on the land for the purposes of the construction, installation, operation, maintenance and decommissioning of the authorised development, and to— a enter upon the land and to create temporary secure areas; b place equipment on the land, including portakabins and welfare equipment; c store plant, materials and equipment; d create car parking sites, site offices, site areas for temporary security and welfare facilities; e effect access and egress to and from the highway; f create fuel storage and bunded facilities for the storage of materials ancillary to the implementation of the authorised development; and g access the underground pipes, cables, cable ducts and jointing works and any other land used or to be used in connection with the installation and use of the underground steam pipes,, cables, cable ducts and jointing works, over the temporary secure area within the land, for purposes in connection with the installation and use of the underground steam pipes and cables. 5 The right to enter onto and remain on the land for the purposes of construction, installation, operation, maintenance and decommissioning of the authorised development and to— a pass and repass with or without vehicles, plant, equipment, materials and machinery to access adjoining land and highway for the purposes of laying, installing, adjusting, altering, constructing, using, maintaining, repairing, renewing, upgrading, inspecting, removing and replacing the pipes, cables, cable ducts and jointing works; b retain and maintain existing hardstandings and lay down, use, repair, alter and remove hardstandings for the purposes of access to adjoining land and highway; c erect temporary supporting or protective structures (including the bridging over or protection of the apparatus of the statutory undertakers) for the purposes of access to adjoining land and highway; d alter, lop, uproot and replant trees, shrubs and hedges and other vegetation for the purposes of enabling the right to pass and repass to and from adjoining land; e retain and maintain existing temporary permissive paths or lay out temporary permissive paths for public use (if applicable); f effect access and egress to and from the highway; g retain, maintain, straighten, widen, repair, alter, upgrade and use existing access routes for the purposes of accessing adjoining land and highway; h remove fences, hedges or other barriers during any period in which construction, maintenance, upgrading, improvement, renewal or removal are being carried out and for the exercise of the power to access the pipes and cables (subject to the prior erection of any temporary stock proof fencing as is reasonably required and the replacement or re-instatement of the fences, hedges or other barriers following the exercise of the rights); and i construct, retain, maintain, install, use, inspect, modify, improve, maintain, adjust, repair, replace, extend, test, cleanse and remove temporary or permanent drainage and manage waterflows in any drains, watercourses and culverts. “adjoining land” for the purposes of this paragraph 3 means such other parts of the land within the Order limits required for the authorised development. 6 A restrictive covenant over the land for the benefit of the remainder of the Order land to— a prevent anything to be done in or upon the Order land or any part thereof for the purpose of the erection of any buildings or construction or erection of works of any kind (including the foundations, footings or other supportive structures thereto); b prevent anything to be done by way of hard surfacing of the Order land with concrete of any kind or with any other material or surface whatsoever without the consent in writing of the undertaker (such consent not to be unreasonably withheld or delayed if the proposed surfacing would not cause damage to relevant part of the authorised development nor make it materially more difficult or expensive to maintain the authorised development); c prevent mole draining or anything to be done by way of excavation of any kind in the Order land nor any activities which increase or decrease ground cover or soil levels in any manner whatsoever without the consent in writing of the undertaker save as are reasonably required for agricultural activities; d prevent the planting or growing within the Order land of any trees, shrubs or underwood without the consent in writing of the undertaker (such consent not to be unreasonably withheld or delayed provided that the proposed trees, shrubs or underwood would not cause damage to the relevant part of the authorised development nor make it materially more difficult or expensive to access the relevant part of the authorised development) provided that the growing within the land of any pre-existing trees, shrubs or underwood do not require the consent of the undertaker; and e prevent anything to be done in or upon the Order land or any part thereof which shall or which it is reasonably foreseeable may interfere with the exercise of the other rights set out in this Schedule or the use of the authorised development or in any way render the authorised development or any part thereof in breach of any statute or regulation for the time being in force and applicable thereto.
Cable rights in highways Plots 1-7, 1-8, 2-3, 4-2, 4-3, 4-6, 4-7, 4-13, 4-14, 4-16, 4-17, 4-19, 4-25, 4-27, 4-38, 4-39, 4-107, 4-108, 5-23, 5-24, 5-25, 5-27, 5-29, 5-30, 5-32, 5-33, 5-59, 5-60, 5-61, 5-62, 5-89, 9-5, 9-18, 9-26, 9-29, 9-31, 10-1, 10-2, 10-3, 10-4, 10-5, 10-6, 10-7, 10-10, 10-12, 10-13, 10-18, 10-37, 10-38, 10-50, 10-54, 10-61, 10-64, 10-73, 10-75, 10-76, 10-79, 10-80 7 The right to enter onto and remain on the land for the purposes of construction, installation, operation, maintenance and decommissioning of the authorised development and to— a construct, lay and install, adjust, alter, use, maintain, repair, replace, renew, upgrade, inspect and remove the cables and pipes by way of drilling and/or trenching; b construct, retain, maintain, install, use, inspect, modify, improve, maintain, adjust, repair, extend, test, cleanse, and remove temporary or permanent drainage and manage waterflows in any drains, watercourse and culverts; c pass and repass, with or without vehicles, plant, equipment, materials and machinery for the purposes of constructing, laying, installing, adjusting, altering, using, maintaining, repairing, replacing, renewing, upgrading, inspecting and removing the pipes, cables and cable ducts; d retain and maintain existing hardstandings and lay down, use, repair, alter and remove hardstandings for the purposes of constructing, laying, installing, adjusting, altering, using maintaining, repairing, replacing, renewing, upgrading, inspecting and removing the pipes, cables and cable ducts; e enter and be upon the land and remain with or without plant, vehicles, machinery, apparatus and equipment which is ancillary to the purposes of transmitting electricity and telecommunications along the pipes, cables and cable ducts; f retain and use the cables for the purposes of the transmission of steam, telecommunications and electricity; g place and use plant, machinery and temporary structures within the land for the installation, construction, maintenance, repairing, renewing, upgrading, inspecting, removal and replacing of the pipes, cables and cable ducts; h install and maintain cable marker posts to identify the location of the pipes, cables and cable ducts as required for routine integrity testing; i remove store and stockpile materials (including excavated material) within the Order land; j remove fences, hedges or other barriers during any period in which construction, maintenance, upgrading, improvement, renewal or removal are being carried out and for the exercise of the power to access the cables (subject to the prior erection of any temporary stock proof fencing as is reasonably required and the replacement or re-instatement of the fences, hedges or other barriers following the end of each period of the exercise of the rights); k install, alter, re-lay, maintain, protect, adjust or remove pipes, cables, conduits or apparatus (including the pipes, cables, conduits or apparatus of statutory undertakers); l carry out works to lop, fell, cut or coppice trees or remove roots of trees or hedges or shrubs; m retain and maintain existing temporary permissive paths or lay out temporary permissive paths for public use (if applicable); n remove archaeological artefacts where they would prevent or cause it to be materially more difficult or expensive to construct, lay, install, adjust, alter, use, maintain, repair, replace, renew, upgrade, inspect or remove the pipes, cables and cable ducts; o carry out environmental mitigation, remediation and enhancement works; p install, construct, use and remove temporary welfare facilities during any periods of maintenance, repair, replacement, renewal, upgrade and removal of the pipes, cables and cable ducts; q when the pipes or cables are temporarily unusable, to lay down, install, use, maintain and inspect on the surface of the land steam pipes, electric lines, telecommunications, ancillary equipment and associated works and other conducting media together with conduits or pipes for containing the same in and under the land; and r place temporarily and use plant, machinery and structures on the land in connection with the lighting of the land and the authorised development.
Major crossings (railway, highways) Plots 2-6, 2-7, 3-23, 3-24 8 The right to enter onto and remain on the land for the purposes of construction, installation, operation, maintenance and decommissioning of the authorised development and to— a construct, lay and install, adjust, alter, use, maintain, repair, replace, renew, upgrade, inspect and remove the pipes, pipe sleeves and cables by way of horizontal drilling or other trenchless techniques; b construct, retain, maintain, install, use, inspect, modify, improve, maintain, adjust, repair, extend, test, cleanse, and remove temporary or permanent drainage and manage waterflows in any drains, watercourse and culverts; c enter the land with or without machinery, apparatus and equipment which is ancillary to the purposes of transmitting steam along the pipes and electricity along the cables and cable ducts; d retain and use the pipes and cables for the purposes of the transmission of steam and electricity; and e install, alter, re-lay, maintain, protect, adjust or remove pipes, cables, conduits or apparatus (including the pipes, cables, conduits or apparatus of statutory undertakers).
Highway works Plots 4-2, 4-3, 4-4, 4-5, 4-6, 4-7, 4-8, 4-13, 4-21, 4-22, 4-23, 4-25, 4-27, 4-98, 4-105, 4-106, 4-107, 4-108, 5-23, 5-24, 5-25, 5-26, 5-27, 5-28, 5-29, 5-30, 5-36, 5-37, 5-55, 5-62 9 The right to enter onto and remain on the land for the purposes of construction, installation, operation, maintenance and decommissioning of the authorised development and to— a construct, adjust, alter, use, maintain, repair, replace, renew, upgrade, inspect and remove road works and associated infrastructure and street furniture; b construct, retain, maintain, install, use, inspect, modify, improve, maintain, adjust, repair, extend, test, cleanse, and remove temporary or permanent drainage and manage waterflows in any drains, watercourse and culverts; c enter the land with or without machinery, apparatus and equipment which is ancillary to the purposes of road works; d install, alter, re-lay, maintain, protect, adjust or remove pipes, cables, conduits or apparatus of statutory undertakers.
Utility works Plots 4-2, 4-3, 4-6, 4-7, 4-13, 4-14, 4-16, 4-17, 4-18, 4-19, 4-21, 4-22, 4-23, 4-25, 4-26, 4-27, 4-38, 4-39, 4-106, 4-107, 4-180, 5-23, 5-24, 5-25, 5-26, 5-27, 5-28, 5-29, 5-30, 5-31, 5-32, 5-33, 5-36, 5-37, 5-55, 5-56, 5-57, 5-58, 5-59, 5-60, 5-61, 5-62, 5-64, 5-65, 5-68, 5-69, 5-82 10 The right to enter onto and remain on the land for the purposes of construction, installation, operation, maintenance and decommissioning of the authorised development and to— a divert install, underground, retain, use, monitor and maintain pipes, cables, conduits or apparatus of statutory undertakers; b pass and repass with or without vehicles, plant, equipment, materials and machinery to access adjoining land and highway for the purposes of laying, installing, adjusting, altering, constructing, using, maintaining, repairing, renewing, upgrading, inspecting, removing and replacing the pipes, cables, conduits or apparatus; c enter the land with or without machinery, apparatus and equipment which is ancillary to the purposes of utility works. “adjoining land” for the purposes of this paragraph 1 means such other parts of the land within the Order limits required for the authorised development. 11 A restrictive covenant over the land to protect the apparatus from excavation.
Drainage rights Plots 4-34, 4-41, 4-42, 4-43, 4-44, 4-76, 4-81, 4-82, 4-87, 4-88, 4-95, 5-7, 5-8, 5-19, 5-90, 6-1, 6-2, 6-3, 6-5, 6-11, 6-12, 6-13, 6-83 12 The right to enter onto and remain on the land for the purposes of construction, installation, operation, maintenance and decommissioning of the authorised development and to construct, retain, maintain, install, use, inspect, modify, improve, adjust, repair, extend, test, cleanse, and remove temporary or permanent drainage and manage waterflows in any drains, watercourse and culverts.
13 The right to drain on, in and/or through the land to and from adjoining land. “adjoining land” for the purposes of this paragraph 2 means such other parts of the land within the Order limits required for the authorised development. 14 A restrictive covenant over the land for the benefit of the remainder of the Order land to prevent anything to be done in or upon the land or any part thereof which shall or which it is reasonably foreseeable may interfere with the right to drain.
Landscaping access Plots 5-76, 5-89, 6-34 15 The right to enter onto and remain on the land for the purposes of construction, installation, operation, maintenance and decommissioning of the authorised development and to enter the land with or without machinery, apparatus and equipment which is ancillary to the purposes of landscaping works.
16 A restrictive covenant over the land for the benefit of the remainder of the Order land to— a prevent anything to be done in or upon the land or any part thereof which shall or which it is reasonably foreseeable may interfere with access to the landscaping works; b prevent anything to be done in or upon the land or any part thereof which shall or which it is reasonably foreseeable may render the authorised development or any part thereof in breach of any statute or regulation for the time being in force and applicable thereto.
Railway works Plots 8-1, 8-2, 8-3, 8-5, 8-9 17 The right to enter onto and remain on the land for the purposes of construction, installation, operation, maintenance and decommissioning of the authorised development and to— a construct, adjust, alter, use, maintain, repair, replace, renew, upgrade, inspect and remove railway works and associated infrastructure; b construct, retain, maintain, install, use, inspect, modify, improve, maintain, adjust, repair, extend, test, cleanse, and remove temporary or permanent drainage and manage waterflows in any drains, watercourse and culverts; c enter the land with or without machinery, apparatus and equipment which is ancillary to the purposes of railway works.

PART 2 — OPTION B - LAND IN WHICH ONLY NEW RIGHTS ETC., MAY BE ACQUIRED

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.