The Viking CCS Carbon Dioxide Pipeline Order 2025

Type Statutory-Instrument
Publication 2025-04-09
Last updated 2025-08-20
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • “road space booking” means road space bookings in accordance with National Highways’ Asset Management Operational Requirements (AMOR) including Network Occupancy Management System (NOMS) used to manage road space bookings and network occupancy;
  • “specified works” means so much of any work, including highway works, authorised by this Order including any maintenance of that work, as is undertaken on, in, under or over the strategic road network for which National Highways is the highway authority;
  • “Specification for Highways Works” means the specification for highways works forming part of the manual of contract documents for highway works published by National Highways and setting out the requirements and approvals procedures for work, goods or materials used in the construction, improvement or maintenance of the strategic road network;
  • “strategic road network” means any part of the road network including trunk roads, special roads or streets for which National Highways is the highway authority including drainage infrastructure, street furniture, verges and vegetation and all other land, apparatus and rights located in, on, over or under the highway for which National Highways is the highway authority; and
  • “utilities” means any pipes wires cables or equipment belonging to any person or body having power or consent to undertake street works under the New Roads and Street Works Act 1991.

General

116

  • (1) References to any standards, manuals, contracts, regulations and directives including to specific standards forming part of the DMRB are, for the purposes of this Part of this Schedule, to be construed as a reference to the same as amended, substituted or replaced, and with such modifications as are required in those circumstances.
  • (2) No works in carrying out, maintaining or diverting the authorised development may be carried out under the strategic road network at a distance within 4 metres of the lowest point of any services and/or drainage under the highway.
  • (3) All works associated with the construction and installation of the pipeline pursuant to Work No.03 and Work No.08 shall, in so far as those works cross the strategic road network, be carried out by trenchless methods unless otherwise agreed by National Highways.

Prior approvals

117

  • (1) The specified works must not commence until—
  • (a) a stage 1 and stage 2 road safety audit has been carried out and all recommendations raised by them or any exceptions are approved by National Highways;
  • (b) the programme of works has been approved by National Highways;
  • (c) the detailed design of the specified works comprising of the following details, insofar as considered relevant by National Highways, has been submitted to and approved by National Highways—
  • (i) the detailed design information, incorporating all recommendations and any exceptions approved by National Highways under sub-paragraph (a);
  • (ii) details of the proposed road space bookings;
  • (iii) the identity and suitability of the contractor and nominated persons;
  • (iv) a process for stakeholder liaison, with key stakeholders to be identified and agreed between National Highways and the undertaker; and
  • (v) information demonstrating that the walking, cycling and horse-riding assessment and review process undertaken by the undertaker in relation to the specified works has been adhered to in accordance with DMRB GG142 – Designing for walking, cycling and horse riding;
  • (d) a scheme of traffic management has been submitted by the undertaker and approved by National Highways such scheme to be capable of amendment by agreement between the undertaker and National Highways from time to time;
  • (e) stakeholder liaison has taken place in accordance with the process for such liaison agreed between the undertaker and National Highways under sub-paragraph (c)(iv) above; and
  • (f) a condition survey and regime of monitoring of any National Highways assets or structures that National Highways considers will be affected by the specified works, has been agreed in writing by National Highways.
  • (2) Except where an approval has otherwise been provided under this Part, the undertaker must not exercise—
  • (a) article 5 (power to maintain the authorised development);
  • (b) article 9 (street works);
  • (c) article 10 (power to alter layout, etc. of streets)
  • (d) article 12 (temporary restriction of public rights of way);
  • (e) article 13 (temporary restriction of use of streets);
  • (f) article 14 (access to works);
  • (g) article 17 (traffic regulation);
  • (h) article 18 (discharge of water);
  • (i) article 20 (authority to survey and investigate land);
  • (j) article 21 (protective works to buildings);
  • (k) article 22 (compulsory acquisition of land);
  • (l) article 24 (compulsory acquisition of rights and restrictive covenants);
  • (m) article 31 (rights under or over streets);
  • (n) article 32 (temporary use of land for carrying out the authorised development);
  • (o) article 33 (temporary use of land for maintaining the authorised development); or
  • (p) article 39 (felling or lopping of trees and removal of hedgerows) of this Order,

over any part of the strategic road network.

  • (3) National Highways must prior to the commencement of the specified works or the exercise of any power referenced in sub-paragraph (2) inform the undertaker of the identity of the person who will act as a point of contact on behalf of National Highways for consideration of the information required under sub-paragraphs (1) or (2).
  • (4) National Highways must within 56 days of the undertaker requesting National Highways’ approval pursuant to sub-paragraphs (1) and (2)—
  • (a) intimate their approval;
  • (b) intimate their refusal together with reasons for refusal; or
  • (c) request more time to intimate approval or refusal pursuant to sub-paragraphs (a) or (b).
  • (5) In the event National Highways requests more time pursuant to sub-paragraph (4)(c), the undertaker may—
  • (a) approve that request; or
  • (b) require that the person identified to the undertaker pursuant to sub-paragraph (3) meets with the undertaker’s project director to discuss the request for approval.
  • (6) Any approval of National Highways required under this paragraph ‎117—
  • (a) must be given in writing; and
  • (b) may be subject to any conditions as National Highways considers reasonably necessary.
  • (7) Any change to the identity of the contractor and/or designer of the specified works will be notified to National Highways as soon as reasonably practicable and in any event within 7 days and details of their suitability to deliver the specified works will be provided on request.
  • (8) Any change to the detailed design of the specified works must be approved by National Highways in accordance with sub-paragraph (4).

Construction of the specified works

118

  • (1) The undertaker must give National Highways 28 days’ notice in writing of the date on which the specified works will start unless otherwise agreed by National Highways.
  • (2) The undertaker must comply with National Highways’ road space booking procedures prior to and during the carrying out the specified works and no specified works for which a road space booking is required shall commence without a road space booking having first been secured from National Highways.
  • (3) The specified works must be carried out by the undertaker to the satisfaction of National Highways in accordance with—
  • (a) the relevant detailed design information and programme of works approved pursuant to paragraph ‎117(1) above or as subsequently varied by agreement between the undertaker and National Highways;
  • (b) in so far as it may be applicable, the DMRB, the Manual of Contract Documents for Highway Works, including the Specification for Highway Works, together with all other relevant standards as may reasonably be required by National Highways to include, inter alia; all relevant interim advice notes, the Traffic Signs Manual, and the Traffic Signs Regulations and General Directions 2016, save to the extent that exceptions from those standards apply which have been approved by National Highways; and
  • (c) all aspects of the Construction (Design and Management) Regulations 2015 or any statutory amendment or variation of the same and in particular the undertaker, as client, must ensure that all client duties (as defined in the said regulations) are undertaken to the satisfaction of National Highways.
  • (4) The undertaker must permit and must require the contractor to permit at all reasonable times persons authorised by National Highways (whose identity must have been previously notified to the undertaker by National Highways) to gain access to the specified works for the purposes of inspection and supervision of the specified works.
  • (5) If any part of the specified works is constructed—
  • (a) other than in accordance with the requirements of this Part of this Schedule; or
  • (b) in a way that causes damage to the highway, highway structure or asset or any other land of National Highways, National Highways may by notice in writing require the undertaker, at the undertaker’s own expense, to comply promptly with the requirements of this Part of this Schedule or remedy any damage notified to the undertaker under this Part of this Schedule, to the satisfaction of National Highways acting reasonably.
  • (6) If during the carrying out of the authorised development the undertaker or its appointed contractors or agents causes damage to the strategic road network then National Highways may carry out steps required to remedy the damage and may recover any expenditure reasonably incurred by National Highways in so doing, such sum to be payable within 30 days of demand.
  • (7) Nothing in this Part of this Schedule prevents National Highways from carrying out any work or taking any such action as it reasonably believes to be necessary as a result of or in connection with the carrying out or maintenance of the authorised development without prior notice to the undertaker in the event of an emergency or to prevent the occurrence of danger to the public and National Highways may recover any expenditure it reasonably incurs in so doing. Notwithstanding the foregoing, National Highways will inform the undertaker of any such works or action as soon as reasonably practicable.
  • (8) In constructing the specified works, the undertaker must at its own expense divert or protect all utilities (where required to prevent unreasonable interference or damage) and all agreed alterations and reinstatement of highway over existing utilities must be constructed to the satisfaction of National Highways acting reasonably.
  • (9) The undertaker must notify National Highways if it fails to complete the specified works in accordance with the agreed programme pursuant to paragraph ‎117(1)(b) of this Part or suspends the carrying out of any specified work beyond a reasonable period of time and National Highways reserves the right to withdraw any road space booking granted to the undertaker to ensure compliance with its network occupancy requirements.
  • (10) Powers granted to National Highways to undertake any works under this paragraph include works to make safe an area but do not include powers to undertake any works to, the pipeline or any works which could conflict with the duties and obligations of the undertaker under the Pipeline Safety Regulations 1996, any direction issued by the Health and Safety Executive under those Regulations or any other health and safety legislation relating to the operation and maintenance of the pipeline.

Payments

119

  • (1) The undertaker must pay to National Highways a sum equal to the whole of any costs and expenses which National Highways reasonably incurs (including costs and expenses for using internal or external staff and costs relating to any work which becomes abortive) in relation to the specified works, including—
  • (a) the checking and approval of the information required under this Part;
  • (b) the supervision of the specified works;
  • (c) all legal and administrative costs and disbursements incurred by National Highways in connection with the specified works and sub-paragraphs (a) and (b); and
  • (d) any value added tax which is payable by National Highways in respect of such costs and expenses and for which it cannot obtain reinstatement from HM Revenue and Customs,

together comprising “the NH costs”.

  • (2) National Highways must within 14 days of receipt of the information pursuant to sub-paragraph ‎117(1) provide the undertaker with a schedule showing its estimate of the NH costs.
  • (3) The undertaker must within 30 days of receipt of the notice pursuant to sub-paragraph (2) pay to National Highways the estimate of the NH costs.
  • (4) If at any time after the payment referred to in sub-paragraph (3) has become payable, National Highways reasonably believes that the NH costs will exceed the estimated NH costs notified pursuant to sub-paragraph (2) it may give notice to the undertaker of the amount that it believes the NH costs will exceed the estimate (the “excess”).
  • (5) The undertaker must within 30 days of receipt of the notification pursuant to sub-paragraph (4) pay to National Highways an amount equal to the excess.
  • (6) National Highways must give the undertaker a final account of the NH costs referred to in sub-paragraph (1) above as a fully itemised invoice within 30 days of the undertaker notifying to National Highways that a specified work has been completed.
  • (7) Within 30 days of the issue of the final account—
  • (a) if the final account shows a further sum as due to National Highways the undertaker must pay to National Highways the sum shown due to it; and
  • (b) if the account shows that the payment or payments previously made by the undertaker have exceeded the costs incurred by National Highways, National Highways must refund the difference to the undertaker.
  • (8) The undertaker must pay to National Highways within 30 days of receipt and prior to such costs being incurred the total costs that National Highways believe will be properly and necessarily incurred by National Highways in undertaking any statutory procedure or preparing and bringing into force any traffic regulation order or orders necessary to carry out or for effectively implementing the specified works.

Completion of a specified work

120

  • (1) The undertaker must within 28 days of completion of a specified work arrange for the highways structures and assets that were the subject of the condition survey to be re-surveyed including a renewed geotechnical assessment required by DMRB CD622 and must submit the re-survey to National Highways for its approval.
  • (2) If the re-surveys carried out pursuant to sub-paragraph (1) indicates that any damage has been caused to a structure or asset, the undertaker must submit a scheme for remedial works in writing to National Highways for its approval in writing, which must not be unreasonably withheld or delayed, and the undertaker must carry out the remedial works at its own cost and in accordance with the scheme submitted.
  • (3) If the undertaker fails to carry out the remedial work in accordance with the approved scheme, National Highways may carry out the steps required of the undertaker and may recover any expenditure it reasonably incurs in so doing.
  • (4) National Highways may, at its discretion, at the same time as giving its approval to the re-surveys pursuant to sub-paragraph (1) give notice in writing that National Highways will remedy any damage identified in the re-surveys and National Highways may recover any expenditure it reasonably incurs in so doing.
  • (5) The undertaker must make available to National Highways upon request copies of any survey or inspection reports produced pursuant to any inspection or survey of any specified work following its completion that the undertaker may from time to time carry out.
  • (6) The undertaker must within 28 days of completion of any specified works submit to National Highways the as built information in relation to those works.
  • (7) A defects period shall commence following completion of a specified work during which time the undertaker must, at its own expense, remedy any defects in the SRN as are reasonably required by National Highways. All identified defects must be remedied in accordance with the following timescales—
  • (a) in respect of matters of urgency, within 24 hours of receiving notification for the same (urgency to be determined at the absolute discretion of National Highways);
  • (b) in respect of matters which National Highways considers to be serious defects or faults, within 14 days of receiving notification of the same; and
  • (c) in respect of all other defects notified to the undertaker, within 4 weeks of receiving notification of the same.

Security

121

No specified work shall commence until the undertaker has first provided the acceptable security in favour of National Highways, and provided evidence (to the reasonable satisfaction of National Highways) that it shall maintain such acceptable security for the construction period of the specified works from the proposed date of commencement of the specified works until no earlier than the end of the defects period.

Insurance

122

Prior to the commencement of the specified works the undertaker must effect public liability insurance with an insurer in the minimum sum of £10,000,000 (ten million pounds) in respect of any one claim against any legal liability for damage loss or injury to any property or any person as a direct result of the execution of the specified works.

Indemnity

123

  • (1) The undertaker fully indemnifies National Highways from and against all costs, claims, expenses, damages, losses and liabilities suffered by National Highways arising from the construction, maintenance or use of the specified works or exercise of or failure to exercise any power under this Order within 30 days of demand.
  • (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to—
  • (a) any loss arising out of or in consequence of any negligent act or default of National Highways or its officers servants agents or contractors or any person or body for which it is responsible; or
  • (b) any indirect or consequential loss of National Highways or any third party (including but not limited to loss of use, revenue, profit, contract, production, increased cost of working or business interruption).

Maintenance of the specified works

124

  • (1) The undertaker must, prior to the commencement of any works of maintenance to the specified works, give National Highways 28 days’ notice in writing of the date on which those works will start unless otherwise agreed by National Highways, acting reasonably.
  • (2) If, for the purposes of maintaining the specified works, the undertaker needs to occupy any road space, the undertaker must comply with National Highways’ road space booking requirements and no maintenance of the specified works for which a road space booking is required shall commence without a road space booking having first been secured.
  • (3) The undertaker must comply with any reasonable requirements that National Highways may notify to the undertaker, such requirements to be notified to the undertaker not less than 7 days in advance of the planned commencement date of the maintenance works.

Land

125

The undertaker must not under the powers of this Order—

  • (a) acquire or use land forming part of;
  • (b) acquire new or existing rights over; or
  • (c) seek to impose or extinguish any restrictive covenants over,

any of the strategic road network, or extinguish any existing rights of National Highways in respect of any third-party property, except with the consent of National Highways such not to be unreasonably withheld or delayed by written request to legalservicesteam@nationalhighways.co.uk.

Expert Determination

126

  • (1) Subject to the provisions of this paragraph, article 48 (arbitration) of the Order does not apply to this Part of this Schedule.
  • (2) Any difference under this Part of this Schedule may be referred to and settled by a single independent and suitable person who holds appropriate professional qualifications and is a member of a professional body relevant to the matter in dispute acting as an expert, such person to be agreed by the differing parties or, in the absence of agreement, identified by the President of the Institution of Civil Engineers.
  • (3) On notification by either party of a dispute, the parties must jointly instruct an expert within 14 days of notification of the dispute.
  • (4) All parties involved in settling any difference must use best endeavours to do so within 21 days from the date that an expert is appointed.
  • (5) The expert must—
  • (a) invite the parties to make submission to the expert in writing and copied to the other party to be received by the expert within 7 days of the expert’s appointment;
  • (b) permit a party to comment on the submissions made by the other party within 7 days of receipt of the submission;
  • (c) issue a decision within 7 days of receipt of the submissions under sub-paragraph (b); and
  • (d) give reasons for the decision.
  • (6) Any determination by the expert is final and binding, except in the case of manifest error in which case the difference that has been subject to expert determination may be referred to and settled by arbitration under article 48 (arbitration).
  • (7) The fees of the expert are payable by the parties in such proportions as the expert may determine or, in the absence of such determination, equally.

Co-operation

127

  • (1) Where in consequence of the proposed construction of any part of the authorised development, National Highways makes requirements for the protection of the SRN under paragraph ‎119, the undertaker must use its best endeavours to co-ordinate the execution of the works in the interests of safety of the authorised development and taking into account the need to ensure the safety of National Highways’ undertaking and National Highways must use its best endeavours to co-operate with the undertaker for that purpose.
  • (2) For the avoidance of doubt whenever National Highways’ consent, agreement or approval is required in relation to plans, documents or other information submitted by the undertaker or the taking of action by the undertaker, it must not be unreasonably withheld or delayed.

PART 10 — For the protection of Anglian Water

Application

128

For the protection of Anglian Water the following provisions have effect, unless otherwise agreed in writing between the undertaker and Anglian Water.

Interpretation

129

In this Part of this Schedule—

  • “alternative apparatus” means alternative apparatus adequate to enable Anglian Water to fulfil its statutory functions in a manner no less efficient than previously;
  • “Anglian Water” means Anglian Water Services Limited;
  • “apparatus” means:any works, mains, pipes or other apparatus belonging to or maintained by Anglian Water for the purposes of water supply and sewerage;any drain or works vested in Anglian Water under the Water Industry Act 1991;any sewer which is so vested or is the subject of a notice of intention to adopt given under section 102(4) of that Act or an agreement to adopt made under section 104 of that Act;any drainage system constructed for the purpose of reducing the volume of surface water entering any public sewer belonging to Anglian Water; andincludes a sludge main, disposal main or sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part of any such sewer, drain or works, and includes any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus,and for the purpose of this definition, where words are defined by section 219 of that Act, they shall be taken to have the same meaning;
  • “functions” includes powers and duties;
  • “in”, in a context referring to apparatus or alternative apparatus in land, includes a reference to apparatus or alternative apparatus under, over or upon land;
  • “plan” includes all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the works to be executed.

On street apparatus

130

This Part of this Schedule does not apply to apparatus in respect of which the relations between the undertaker and Anglian Water are regulated by the provisions of Part 3 of the 1991 Act.

Apparatus in stopped up streets

131

Regardless of the temporary stopping up or diversion of any highway under the powers conferred by articles 12 (temporary restriction of public rights of way) and 13 (temporary restriction of use of streets), Anglian Water is at liberty at all times to take all necessary access across any such stopped up highway and to execute and do all such works and things in, upon or under any such highway as may be reasonably necessary or desirable to enable it to maintain any apparatus which at the time of the stopping up or diversion was in that highway.

Protective works to buildings

132

The undertaker, in the case of the powers conferred by article 21 (protective work to buildings), must exercise those powers so as not to obstruct or render less convenient the access to any apparatus.

Acquisition of land

133

Regardless of any provision in this Order or anything shown on the land plans, the undertaker must not acquire any apparatus otherwise than by agreement.

Removal of apparatus

134

  • (1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed or requires that Anglian Water’s apparatus is relocated or diverted, that apparatus must not be removed under this Part of this Schedule, and any right of Anglian Water to maintain that apparatus in that land must not be extinguished, until—
  • (a) alternative apparatus has been constructed and is in operation to the reasonable satisfaction of Anglian Water in accordance with sub-paragraphs (2) to (8); and
  • (b) facilities and rights have been secured for that alternative apparatus in accordance with paragraph 135.
  • (2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, the undertaker must give to Anglian Water 28 days’ written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order an undertaker reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to Anglian Water the necessary facilities and rights for the construction of alternative apparatus in other land of the undertaker and subsequently for the maintenance of that apparatus.
  • (3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed Anglian Water must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible use its best endeavours to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.
  • (4) Any alternative apparatus to be constructed in land of the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between Anglian Water and the undertaker or in default of agreement settled by arbitration in accordance with article 48 (arbitration).
  • (5) Anglian Water must, after the alternative apparatus to be provided or constructed has been agreed or settled by arbitration in accordance with article 48 (arbitration), and after the grant to Anglian Water of any such facilities and rights as are referred to in sub-paragraphs (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
  • (6) Regardless of anything in sub-paragraph (5), if Anglian Water gives notice in writing to the undertaker that it desires the undertaker to execute any work, or part of any work in connection with the construction or removal of apparatus in any land of the undertaker or to the extent that Anglian Water fails to proceed with that work in accordance with sub-paragraph (5) or the undertaker and Anglian Water otherwise agree, that work, instead of being executed by Anglian Water, must be executed by the undertaker without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of Anglian Water.
  • (7) If Anglian Water fails either to approve, or to provide reasons for its failure to approve along with an indication of what would be required to make acceptable, any proposed details relating to required removal works under sub-paragraph (2) within 28 days of receiving a notice of the required works from the undertaker, then such details are deemed to have been approved. For the avoidance of doubt, any such “deemed consent” does not extend to the actual undertaking of the removal works, which shall remain the sole responsibility of Anglian Water or its contractors.
  • (8) Whenever alternative apparatus is to be or is being substituted for existing apparatus, the undertaker shall, before taking or requiring any further step in such substitution works, use best endeavours to comply with Anglian Water’s reasonable requests for a reasonable period of time to enable Anglian Water to—
  • (a) make network contingency arrangements; or
  • (b) bring such matters as it may consider reasonably necessary to the attention of end users of the utility in question.

Facilities and rights for alternative apparatus

135

  • (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to Anglian Water facilities and rights for the construction and maintenance in land of the undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities and rights are to be granted upon such terms and conditions as may be agreed between the undertaker and Anglian Water or in default of agreement settled by arbitration in accordance with article 48 (arbitration).
  • (2) If the facilities and rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are in the opinion of the arbitrator less favourable on the whole to Anglian Water than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the arbitrator must make such provision for the payment of compensation by the undertaker to Anglian Water as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
  • (3) Such facilities and rights as are set out in this paragraph are deemed to include any statutory permits granted to the undertaker in respect of the apparatus in question, whether under the Environmental Permitting Regulations (England and Wales) 2016 or other legislation.

Retained apparatus

136

  • (1) Not less than 28 days before starting the execution of any works in, on or under any land purchased, held, appropriated or used under this Order that are near to, or will or may affect, any apparatus (or any means of access to it) the removal of which has not been required by the undertaker under paragraph 134(2), the undertaker must submit to Anglian Water a plan of the works to be executed.
  • (2) Those works must be executed only in accordance with the plan submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by Anglian Water for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and Anglian Water is entitled to watch and inspect the execution of those works.
  • (3) Any requirements made by Anglian Water under sub-paragraph (2) must be made within a period of 21 days beginning with the date on which a plan under sub-paragraph (1) is submitted to it.
  • (4) If Anglian Water in accordance with sub-paragraph (3) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 128 to 130 and 166 to 136 apply as if the removal of the apparatus had been required by the undertaker under paragraph 134(2).
  • (5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan instead of the plan previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.
  • (6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case must give to Anglian Water notice as soon as is reasonably practicable and a plan of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (3) in so far as is reasonably practicable in the circumstances, using its best endeavours to keep the impact of those emergency works on Anglian Water’s apparatus, on the operation of its water and sewerage network and on end-users of the services Anglian Water provides to a minimum.
  • (7) For the purposes of sub-paragraph (1) and without prejudice to the generality of the principles set out in that sub-paragraph, works are deemed to be in land near Anglian Water’s apparatus (where it is a pipe) if those works fall within the following distances measured from the medial line of such apparatus—
  • (a) 4 metres where the diameter of the pipe is less than 250 millimetres;
  • (b) 5 metres where the diameter of the pipe is between 250 and 400 millimetres; and
  • (c) a distance to be agreed on a case by case basis and before the submission of the plan submitted under sub-paragraph (1) (but which distance, for the avoidance of doubt, shall not exceed 7 metres) where the diameter of the pipe exceeds 400 millimetres.

Expenses and costs

137

  • (1) Subject to the following provisions of this paragraph, the undertaker must repay to Anglian Water all expenses reasonably incurred by Anglian Water in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to in this Part of this Schedule.
  • (2) There must be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule that value being calculated after removal.
  • (3) If in accordance with the provisions of this Part of this Schedule—
  • (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
  • (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated, and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 48 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to Anglian Water by virtue of subparagraph (1) must be reduced by the amount of that excess.
  • (4) For the purposes of sub-paragraph (3)—
  • (a) an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
  • (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
  • (5) An amount which apart from this sub-paragraph would be payable to Anglian Water in respect of works by virtue of sub-paragraph (1), if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on Anglian Water any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, is to be reduced by the amount which represents that benefit.

Indemnity

138

  • (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works referred to in paragraphs 129 or 131(2), or by reason of any subsidence resulting from such development or works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of Anglian Water, or there is any interruption in any service provided, or in the supply of any goods, by Anglian Water, the undertaker must—
  • (a) bear and pay the cost reasonably incurred by Anglian Water in making good such damage or restoring the supply; and
  • (b) make reasonable compensation to Anglian Water for any other expenses, loss, damages, penalty or costs incurred by the undertaker,

by reason or in consequence of any such damage or interruption.

  • (2) The fact that any act or thing may have been done by Anglian Water on behalf of the undertaker or in accordance with a plan approved by Anglian Water or in accordance with any requirement of Anglian Water or under its supervision does not, subject to sub-paragraph (4), excuse the undertaker from liability under the provisions of sub-paragraph (1) unless Anglian Water fails to carry out and execute the works properly with due care and attention and in a skilful and professional like manner or in a manner that does not accord with the approved plan.
  • (3) Anglian Water must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, penalties and costs to which the provisions of this Part of this Schedule apply. If requested to do so by the undertaker, Anglian Water must provide an explanation of how any claim has been minimised. The undertaker shall not be liable under this paragraph for claims unreasonably incurred by Anglian Water.
  • (4) Nothing in this paragraph imposes any liability on the undertaker with respect to:
  • (a) any damage or interruption to the extent that it is attributable to the act, neglect or default of Anglian Water, its officer, servants, contractors or agents; or
  • (b) any indirect or consequential loss of Anglian Water or any third party (including but not limited to loss of use, revenue, profit, contract, production, increased cost of working or business interruption) arising from any such damage or interruption.
  • (5) Anglian Water must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made, without the consent of the undertaker (such consent not to be unreasonably withheld or delayed) who, if withholding such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.

Cooperation

139

Where in consequence of the proposed construction of any of the authorised development, the undertaker or Anglian Water requires the removal of apparatus under paragraph 134(2) or Anglian Water makes requirements for the protection or alteration of apparatus under paragraph 136, the undertaker must use all reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of Anglian Water’s undertaking, using existing processes where requested by Anglian Water, provided it is appropriate to do so, and Anglian Water must use all reasonable endeavours to co-operate with the undertaker for that purpose.

140

Where the undertaker identifies any apparatus which may belong to or be maintainable by Anglian Water but which does not appear on any statutory map kept for the purpose by Anglian Water, it shall inform Anglian Water of the existence and location of the apparatus as soon as reasonably practicable.

141

Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and Anglian Water in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.

PART 11 — For the protection of Phillips 66 Limited

Application

142

For the protection of P66 (as referred to in this Part of this Schedule) the following provisions have effect, unless otherwise agreed in writing between the undertaker and P66.

Interpretation

143

In this Part of this Schedule—

  • “affected assets” means apparatus owned or operated by P66 on or above ground which in the reasonable opinion of P66 would have the potential to be physically affected by the relevant works;
  • “apparatus” means any part of the pipelines and includes—any structure existing at the time when a particular action is to be taken under this Part of this Schedule in which apparatus is or is to be lodged or which will give access to apparatus;any cathodic protection, coating or special wrapping of the apparatus; andall ancillary apparatus properly appurtenant to the pipelines, that would be treated as being associated with a pipe or systems of pipes under section 65(2) of the Pipe-Lines Act 1962, as if the pipelines were a “pipe-line” in section 65(1) of that Act;
  • “damage” includes all damage including in relation to a pipeline leakage and the weakening of the mechanical strength of a pipeline;
  • “engineer” means an engineer appointed by P66 for the purposes of this Order;
  • “HOR” means the Humber Oil Refinery which at the date of this Order is owned and operated by P66;
  • “P66” means Phillips 66 Limited (company number 00529086) and any subsequent owner of the pipelines or HOR;
  • “P66 address” means the postal address details to be provided pursuant to paragraph ‎161;
  • “P66 email” means the email address details to be provided pursuant to paragraph ‎161;
  • “pipelines” means the pipelines owned and operated by P66 located within the multi-pipeline rack on the north side of A1173 Manby Road and all ancillary apparatus including such works and apparatus properly appurtenant to the pipelines as are specified by section 65(2) of the Pipe-lines Act 1962;
  • “protected land” means such parts of the Order land as is within 30 metres of the pipelines;
  • “relevant work” means a work which may have an effect on the operation, maintenance, abandonment of or access to any of the pipelines; and
  • “works details” means the following—a description of the proposed works together with plans and sections of the proposed works where such plans and sections are reasonably required to describe the works concerned or their location;details of the undertaker and their principal contractors management of change procedures;details of the traffic management plan, which plan must include details of vehicle access routes for construction and operational traffic and which must assess the risk from vehicle movements and include safeguards to address identified risks;details of the electrical design of the authorised works in sufficient detail to allow an independent specialist to assess whether AC interference from the authorised development may cause damage to any of the pipelines;details of the means by which the pipelines can be properly inspected and if necessary repaired during the construction and operation of the authorised development;details of the assessment and monitoring work to be undertaken both prior to the construction of the authorised development and during the operation of the authorised development to ascertain any change or damage to any pipeline cathodic protection system and the proposed remedial works;any further particulars provided in accordance with paragraph 144(3).

Authorisation of works details affecting pipelines or protected crossings

144

  • (1) Before commencing any part of a relevant work the undertaker must submit the works details to P66 in accordance with paragraph ‎145.
  • (2) The works details submitted under sub-paragraph (1) will be treated as having been received by P66 on the date—
  • (a) that the undertaker obtains written acknowledgement of receipt from P66; or
  • (b) two clear working days following the date that the work details were submitted under sub-paragraph (1),

whichever is earliest.

  • (3) The undertaker must as soon as reasonably practicable provide such further particulars as P66 may, within 30 days from the receipt of the works details under sub-paragraph (2), reasonably require.

145

No part of a relevant work is to be commenced until one of the following conditions has been satisfied-

  • (a) the works details supplied in respect of that relevant work under paragraph ‎144 have been authorised by P66; or
  • (b) the works details supplied in respect of that relevant work under paragraph ‎144 have been authorised by an expert under paragraph ‎147(2).

146

  • (1) Any authorisation by P66 required under paragraph ‎145(a) must not be unreasonably withheld but may be given subject to such reasonable conditions as P66 may require to be made for—
  • (a) the continuing safety and operation or viability of the affected asset; and
  • (b) the requirement for P66 to have–
  • (i) uninterrupted and unimpeded emergency access with or without vehicles to the affected asset at all times; and
  • (ii) reasonable access with or without vehicles to inspect, repair, replace and maintain and ensure the continuing safety and operation or viability of the affected asset.
  • (2) Where P66 can reasonably demonstrate that the authorised development will significantly adversely affect the safety of the pipelines it is entitled to withhold its authorisation until the undertaker can demonstrate to the reasonable satisfaction of P66 that the authorised development will not significantly adversely affect the safety of the pipelines.
  • (3) The authorised development must be carried out in accordance with the works details authorised under paragraph ‎145 and any conditions imposed on the authorisation under sub-paragraph (1).
  • (4) Where there has been a reference to an expert in accordance with paragraph ‎147 and the expert gives authorisation, the authorised development must be carried out in accordance with the authorisation and conditions contained in the award of the expert under paragraph ‎147(2).

147

  • (1) In the event that-
  • (a) the undertaker considers that P66 has unreasonably withheld its authorisation under paragraph ‎146(1); or
  • (b) the undertaker considers that P66 has given its authorisation under paragraph ‎146(1) subject to unreasonable conditions,

the undertaker may refer the matter to an expert for determination under paragraph ‎160.

  • (2) Where the matter is referred to an expert under paragraph 160(2) the expert is to determine whether or not authorisation should be given and, if so, the conditions which should reasonably be attached to the authorisation under sub-paragraphs (a) and (b) of paragraph ‎146(1).
  • (3) Where the undertaker considers that P66 has unreasonably withheld its authorisation under paragraph ‎146(2) then the matter may be referred to an expert on the application of either party (after giving notice in writing to each other) appointed by the secretary of the United Kingdom Onshore Pipeline Association for determination under paragraph ‎160.

Notice of works

148

The undertaker must provide to P66 a minimum of 28 days’ notice prior to commencing any relevant work in order that an engineer can be made available to observe the relevant works and, when required, advise on the necessary safety precautions.

Further provisions about works

149

  • (1) Before carrying out a relevant work the undertaker must—
  • (a) provide P66 with baseline data for any existing cathodic protection of the affected asset; and
  • (b) carry out a pipeline settlement and stress analysis to demonstrate any potential pipeline movement will not present an integrity risk to the affected asset.
  • (2) A minimum clearance of 1500 millimetres must be maintained between any part of the authorised development and any affected asset unless otherwise agreed with P66.

Monitoring for damage to pipelines

150

  • (1) When carrying out the relevant work the undertaker must monitor the relevant affected assets to establish whether damage has occurred.
  • (2) Where any damage occurs to an affected asset as a result of the relevant work, the undertaker must immediately cease all work in the vicinity of the damage and must notify P66 to enable repairs to be carried out to the reasonable satisfaction of P66.
  • (3) If damage has occurred to an affected asset as a result of relevant work the undertaker will, at the request and election of P66—
  • (a) afford P66 all reasonable facilities to enable it to fully and properly repair and test the affected asset and pay to P66 its costs incurred in doing so including the costs of testing the effectiveness of the repairs and cathodic protection and any further works or testing shown by that testing to be reasonably necessary; or
  • (b) fully and properly repair the affected asset as soon as reasonably practicable, in which case the repairs must be properly tested by the undertaker and be shown to the satisfaction of P66 to have effectively repaired the affected asset before any backfilling takes place.
  • (4) If in the course of carrying out repairs under sub-paragraph (3)(a) or (3)(b) apparatus of a better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus; or apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which existing apparatus was, and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker, or, in default of agreement is not determined by arbitration to be necessary, then, if it involves cost in the execution of the repairs exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which would be payable to P66 under sub-paragraph (3)(a), or incurred by the undertaker under sub-paragraph (3)(b), by virtue of paragraph (3) will be reduced by the amount of that excess.
  • (5) Where testing has taken place under sub-paragraph (3)(b), the undertaker must (except where P66 agrees otherwise in writing) provide it with a copy of the results of such testing prior to any backfilling.
  • (6) Following the completion of a relevant work if damage is found to have occurred to an affected asset as a result of the relevant work, sub-paragraphs (2) to (4) of this paragraph apply to that damage.
  • (7) In relation to the approved assessment and monitoring work to be undertaken both prior to the construction of the authorised development and during the operation of the authorised development to ascertain any change or damage to any pipeline cathodic protection system, the undertaker must undertake any necessary remedial work.
  • (8) In the event that the undertaker does not carry out necessary remedial work in a timely manner then P66 is entitled, but not obliged, to undertake the necessary remedial work and recover the cost of doing so from the undertaker.

151

  • (1) If any damage occurs to a pipeline causing a leakage or escape from a pipeline, all work in the vicinity must cease and P66 must be notified immediately.
  • (2) Where there is leakage or escape of gas, the undertaker must immediately—
  • (a) remove all personnel from the immediate vicinity of the leak;
  • (b) inform P66;
  • (c) prevent any approach by the public, extinguish all naked flames and other sources of ignition for at least 350 metres from the leakage; and
  • (d) assist emergency services as may be requested.

Compliance with requirements etc applying to the protected land

152

  • (1) Subject to sub-paragraph (2), in undertaking any works in relation to the protected land or exercising any rights relating to or affecting owners of the protected land, the undertaker must comply with such conditions, requirements or regulations relating to health, safety, security and welfare as are operated in relation to access to or activities in the relevant land including without limitation Appendix K - Code of Practice for Safe Working in the vicinity or crossing of Phillips 66 Ltd’s Pipelines and associated installations.
  • (2) The undertaker is not bound by any condition, requirement or regulation that is—
  • (a) introduced after the date on which notice of the works was given under paragraph ‎144; or
  • (b) determined by the expert following a determination under paragraph ‎160 to unreasonably—
  • (i) create significant engineering, technical or programming difficulties; or
  • (ii) materially increase the cost of carrying out the works.
  • (3) Sub-paragraph (2) does not apply if the condition, requirement or regulation was introduced by way of legislation, direction or policy of the government, a relevant government agency, a local authority (exercising its public functions) or the police.

Restriction on exercising powers

153

The undertaker must in the exercise of the powers conferred by this Order at all times act so as to minimise, as far as reasonably practicable, any detrimental effects on P66, including any disruption to access and supplies of utilities and other services that are required by P66 in order to carry out its operations.

Insurance

154

  • (1) Before carrying out any part of the authorised development on the protected land, the undertaker must put in place a policy of insurance with a reputable insurer against its liabilities under paragraph ‎156 subject to a minimum level of £200,000,000.00 (two hundred million pounds) per occurrence or series of occurrences arising out of one event, and evidence of that insurance must be provided on request to P66.
  • (2) The undertaker must maintain insurance in relation to the authorised development affecting P66 during the construction, operation, maintenance, repair and decommissioning of the authorised development.

Costs

155

The undertaker must repay to P66 all reasonable fees, costs, charges and expenses reasonably incurred by them in relation to these protective provisions in respect of—

  • (a) authorisation of works details submitted by the undertaker under paragraph ‎144 and the imposition of conditions under paragraph ‎145;
  • (b) the engagement of an engineer and their observation of the authorised works affecting the pipelines and the provision of safety advice under paragraph ‎148; and
  • (c) the repair and testing of a pipeline or protected crossing under paragraph ‎150;
  • (d) including the reasonable costs incurred by P66 in engaging and retaining such external experts, consultants and contractors as may be reasonably necessary to P66 to carry out its functions under these protective provisions.

Indemnity

156

  • (1) The undertaker must indemnify and keep P66 indemnified against all reasonable costs, charges, damages and expenses—
  • (a) by reason of the construction, operation, maintenance, repair and decommissioning of the authorised development or the failure of it; or
  • (b) by reason of any act or omission of the undertaker or of any person in its employ or of its contractors or others whilst engaged upon the construction, operation, maintenance, repair and decommissioning of the authorised development.
  • (2) The fact that any act or thing may have been done by P66 on behalf of the undertaker or in accordance with a plan approved by P66 or in accordance with any requirement of P66 or under its supervision will not (unless sub-paragraph (3) applies), excuse the undertaker from liability under the provisions of sub-paragraph (1) unless P66 fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan.
  • (3) Nothing in sub-paragraph (1) shall impose any liability on the undertaker in respect of—
  • (a) any damage or interruption to the extent that it is attributable to the neglect or default of P66, its officers, servants, contractors or agents; and/or
  • (b) any indirect or consequential loss of P66 or any third party (including but not limited to loss of use, revenue, profit, contract, production, increased cost of working or business interruption) arising from any such damage or interruption.
  • (4) P66 must give the undertaker reasonable notice of any claim or demand under sub-paragraph (1) and no settlement or compromise of such a claim or demand is to be made without the prior consent of the undertaker.
  • (5) P66 must, in respect of any matter covered by the indemnity given by the undertaker in this paragraph, at all times act reasonably and in the same manner as it would as if settling third party claims on its own behalf from its own funds.
  • (6) P66 must use its reasonable endeavours to mitigate and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph applies where it is within P66’s reasonable ability and control to do so and which expressly excludes any obligation to mitigate liability arising from third parties which is outside of P66’s control and if reasonably requested to do so by the undertaker P66 must provide an explanation of how the claim has been minimised, where relevant.
  • (7) P66 must, on receipt of a request from the undertaker, from time to time provide the undertaker free of charge with written estimates of the costs, charges, expenses and other liabilities for which the undertaker is or will become liable under this Part of this Schedule and with such information as may reasonably enable the undertaker to assess the reasonableness of any such estimate or claim made or to be made under this Part of this Schedule.

Further protection in relation to the exercise of powers under the Order

157

The undertaker must give written notice to P66 if any application is proposed to be made by the undertaker for the Secretary of State’s consent under article 7 (benefit of the Order), and any such notice must be given no later than 28 days before any such application is made and must describe or give (as appropriate)—

  • (a) the nature of the application to be made;
  • (b) the extent of the geographical area to which the application relates; and
  • (c) the name and address of the person acting for the Secretary of State to whom the application is to be made.

158

The undertaker must, when requested to do so by P66, provide it with a complete set of the documents submitted to and certified by the Secretary of State in accordance with article 44 (certification of plans, etc.) in the form of a computer disc with read only memory or such other format as may be agreed between the relevant parties.

159

Prior to the commencement of the authorised development the undertaker must prepare an emergency response plan following consultation with the local emergency services and provide a copy of that plan to P66.

Expert Determination

160

  • (1) Except as provided in sub-paragraph (7), article 48 (arbitration) does not apply to this Part of this Schedule.
  • (2) Any difference under this Part of this Schedule must be referred to and settled by a single independent and suitable person who holds appropriate professional qualifications and is a member of a professional body relevant to the matter in dispute acting as an expert, such person to be agreed by the differing parties or, in the absence of agreement, identified by the President of the Institution of Civil Engineers.
  • (3) All parties involved in settling any difference must use best endeavours to do so within 21 days from the date of a dispute first being notified in writing by one party to the other and in the absence of the difference being settled within that period the expert must be appointed within 28 days of the notification of the dispute.
  • (4) The fees of the expert are payable by the parties in such proportions as the expert may determine or, in the absence of such determination, equally.
  • (5) The expert must—
  • (a) invite the parties to make submission to the expert in writing and copied to the other party to be received by the expert within 21 days of the experts appointment;
  • (b) permit a party to comment on the submissions made by the other party within 21 days of receipt of the submission;
  • (c) issue a decision within 42 days of receipt of the submissions under paragraph (b); and
  • (d) give reasons for the decision.
  • (6) The expert must consider where relevant—
  • (a) the development outcome sought by the undertaker;
  • (b) the ability of the undertaker to achieve its outcome in a timely and cost-effective manner;
  • (c) the nature of the power sought to be exercised by the undertaker;
  • (d) the nature of any operation or development undertaken or proposed to be undertaken by any party other than the undertaker;
  • (e) the ability of any party other than the undertaker to undertake a relevant operation or development in a timely and cost-effective manner, while giving consideration to any restriction or limitation which might be caused to the ability of any party to carry out their statutory or regulatory duties, requirements or obligations;
  • (f) the effects of the undertaker’s proposals on any party other than the undertaker and the effects of any operation or development undertaken by any party other than the undertaker;
  • (g) whether this Order provides any alternative powers by which the undertaker could reasonably achieve the development outcome sought in a manner that would reduce or eliminate adverse effects on any party other than the undertaker;
  • (h) the effectiveness, cost and reasonableness of proposals for mitigation arising from any party; and
  • (i) any other important and relevant consideration.
  • (7) Any determination by the expert is final and binding, except in the case of manifest error in which case the difference that has been subject to expert determination may be referred to and settled by arbitration under article 48.

Notices

161

  • (1) P66 must as soon as reasonably practicable following a written request from the undertaker provide details of the P66 address and P66 email.
  • (2) A notice or other document required or authorised to be served on P66 under this Part of the Schedule must be served—
  • (a) by post to the P66 address; and
  • (b) by electronic transmission to the P66 email,

or to such other postal or electronic mail address which P66 may from time to time notify to the undertaker.

  • (3) In the event that P66 does not provide the P66 address and P66 email within 14 days of the undertaker’s request pursuant to sub-paragraph (1) then sub-paragraph (2) does not apply and the undertaker must—
  • (a) serve any notice or document on P66 at its registered office; and
  • (b) send a copy of such notice or document to the HOR marked for the attention of the refinery manager.

PART 12 — For the protection of Immingham Oil Terminal operators

Application

162

For the protection of the IOT Operators as referred to in this Part of this Schedule the following provisions have effect, unless otherwise agreed in writing between the undertaker and IOT Operators.

Interpretation

163

In this Part of this Schedule—

  • “affected assets” means apparatus owned or operated by the IOT Operators on or above ground which in the reasonable opinion of the IOT Operators would have the potential to be physically affected by a relevant work;
  • “alternative apparatus” means alternative apparatus adequate to enable the IOT Operators to fulfil its functions in a manner not less efficient than previously;
  • “alternative rights” means rights for the construction and for access to and for the use, protection, inspection, maintenance, repair and renewal of alternative apparatus including any restrictions on the landowner and occupiers for the protection of the alternative apparatus and to allow the IOT Operators to perform its functions;
  • “apparatus” means any part of the pipelines and includes—any structure existing at the time when a particular action is to be taken under this Part of this Schedule in which apparatus is or is to be lodged or which will give access to apparatus;any cathodic protection, coating or special wrapping of the apparatus; andall ancillary apparatus properly appurtenant to the pipelines, that would be treated as being associated with a pipe or systems of pipes under section 65(2) of the Pipe-Lines Act 1962, as if the pipelines were a “pipe-line” in section 65(1) of that Act;such legal interest, and benefit of property rights and covenants as are vested in respect of these items;
  • “APT” means Associated Petroleum Terminals (Immingham) Limited (company number 00564394), whose registered office is at Queens Road, Immingham, Grimsby, North East Lincolnshire, DN40 2PN, and in all cases any successor in title;
  • “authorised development” has the same meaning as that given in article 2 (interpretation) and for the purposes of this Part of this Schedule;
  • “commence” has the same meaning as that given in article 2 (interpretation) of the Order (and “commencing” must be construed accordingly);
  • “damage” includes all and any damage including in relation to a pipeline leakage and the weakening of the mechanical strength of a pipeline;
  • “deed(s) of consent” means any deed of consent, crossing agreement, deed of variation or new deed agreed between the parties acting reasonably in order to vary or replace existing easements, leases, agreements, enactments and other such interests so as to secure land rights and interests as are necessary to carry out, maintain and operate and use the apparatus in a manner consistent with the terms of this Part of this Schedule;
  • “engineer” means an engineer appointed by the IOT Operators for the purposes of this Part of this Schedule;
  • “functions” includes powers and duties and commercial undertaking;
  • “HOTT” means Humber Oil Terminals Trustee Limited (company number 00874993), whose registered office is at Queens Road, Immingham, Grimsby, North East Lincolnshire, DN40 2PN, and in all cases any successor in title;
  • “IOT” means the pipe-line and storage system associated with the Immingham Oil Terminal;
  • “IOT Operators” means APT and HOTT, acting in their capacity as operators and owners of the IOT, and any subsequent owner(s) and operator(s) of the pipelines or IOT;
  • “IOT Operators address” means the postal address details to be provided pursuant to paragraph ‎179;
  • “IOT Operators email” means the email address details to be provided pursuant to paragraph ‎179;
  • “party” means the undertaker and the IOT Operators and “party” is to be construed accordingly;
  • “pipelines” means the whole or any part of the pipelines belonging to or maintained or operated by the IOT Operators located within the multi-pipeline rack on the north side of A1173 Manby Road and all ancillary apparatus including such works and apparatus properly appurtenant to the pipelines as are specified by section 65(2) of the Pipe-Lines Act 1962;
  • “plans” includes all designs, drawings, sections, specifications, method statement, soil reports, programmes, calculations, risks assessment and other documents that are reasonably necessary to allow the IOT Operators to assess the relevant works to be executed properly and sufficiently and in particular must describe—the exact position of the works;the level at which the works are proposed to be constructed or renewed;the manner of the works’ construction or renewal including details of excavation, position of plant etc;the position of the affected apparatus and/or premises and any other apparatus belonging to another undertaker;by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus;any intended maintenance regime;details of the proposed method of working and timing of execution of works; anddetails of vehicle access routes for construction and operational traffic;

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.