The National Grid (Hinkley Point C Connection Project) Order 2016
(8) (1) Where in consequence of the service on a person under section 5 of this Act of a notice to treat in respect of a right over land consisting of a house, building or manufactory or of a park or garden belonging to a house (“the relevant land”)— (a) a question of disputed compensation in respect of the purchase of the right or the imposition of the restrictive covenant would apart from this section fall to be determined by the Tribunal; and (b) before the Tribunal has determined that question the Tribunal is satisfied that the person has an interest in the whole of the relevant land and is able and willing to sell that land and— (i) where that land consists of a house, building or manufactory, that the right cannot be purchased or the restrictive covenant imposed without material detriment to that land; or (ii) where that land consists of such a park or garden, that the right cannot be purchased or the restrictive covenant imposed without seriously affecting the amenity or convenience of the house to which that land belongs, the National Grid (Hinkley Point C Connection Project) Order2016 (“the Order”) ceases, in relation to that person, to authorise the purchase of the right or imposition of a restriction and is deemed to authorise the purchase of that person’s interest in the whole of the relevant land including, where the land consists of such a park or garden, the house to which it belongs, and the notice is deemed to have been served in respect of that interest on such date as the Tribunal directs. (2) Any question as to the extent of the land in which the Order is deemed to authorise the purchase of an interest by virtue of subsection (1) of this section must be determined by the Tribunal. (3) Where in consequence of a determination of the Tribunal that it is satisfied as mentioned in subsection (1) the Order is deemed by virtue of that subsection to authorise the purchase of an interest in land, the acquiring authority may, at any time within the period of 6 weeks beginning with the date of the determination, withdraw the notice to treat in consequence of which the determination was made; but nothing in this subsection prejudices any other power of the authority to withdraw the notice.
6
The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say—
- (a) section 9(4) (failure by owners to convey);
- (b) paragraph 10(3) of Schedule 1 (owners under incapacity);
- (c) paragraph 2(3) of Schedule 2 (absent and untraced owners); and
- (d) paragraphs 2(3) and 7(2) of Schedule 4 (common land),
are modified to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be compulsorily acquired or the restrictive covenant which is to be imposed is vested absolutely in the acquiring authority.
7
Section 11[^f00031] of the 1965 Act (powers of entry) is modified to secure that, as from the date on which the acquiring authority has served notice to treat in respect of any right or restriction, it has power, exercisable in equivalent circumstances and subject to equivalent conditions, to enter for the purpose of exercising that right or enforcing that restrictive covenant (which is deemed for this purpose to have been created on the date of service of the notice); and sections 12[^f00032] (penalty for unauthorised entry) and 13[^f00033] (entry on warrant in the event of obstruction) of the 1965 Act are modified correspondingly.
8
Section 20[^f00034] of the 1965 Act (protection for interests of tenants at will, etc.) applies with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right or the enforcement of the restrictive covenant in question.
9
Section 22 of the 1965 Act (protection of acquiring authority’s possession where by inadvertence an estate, right or interest has not been got in) is modified as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired or to enforce the restriction imposed, subject to compliance with that section as respects compensation.
SCHEDULE 11 — LAND WHICH MAY BE COMPULSORILY ACQUIRED
| (1)Area | (2)Plot number of land shown on Land Plans |
|---|---|
| Sedgemoor District Council – Section A | 162 & 175 |
| Sedgemoor District Council – Section B | 637 & 645 |
| North Somerset Council – Section D | 29, 30, 74.1, 74.2, 74.3, 74.4, 74.5, 75, 118 & 119 |
| Bristol City Council – Section G | 599 & 600 |
SCHEDULE 12 — LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
PART 1 — NATIONAL GRID
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
|---|---|---|---|
| 1, 3, 4, 6, 7, 8, 9, 14, 15, 19, 29, 34, 35, 36, 41, 50, 56, 60, 61, 63, 64, 65, 70, 71, 74, 81, 82, 88, 91 & 94 | Dismantling of redundant infrastructure | Work No. 4B | |
| 2, 5, 10, 16, 23, 28, 33, 40, 47, 53, 54, 62, 75, 78, 83, 84, 89, 90 & 93 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| 11, 12, 13, 17, 18, 20, 21, 22, 24, 25, 26, 27, 30, 31, 32, 37, 38, 39, 42, 43, 44, 45, 46, 48, 49, 51, 52, 55, 57, 58, 59, 66, 67, 68, 69, 72, 73, 76, 77, 79, 80, 85, 86, 87, 92, 97, 98, 101, 157 & 158 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| 95, 96, 99, 100, 102, 103, 104, 107, 109, 112, 122, 124, 127, 129, 130, 153, 156 & 160 | Construction of authorised development | Work No. 1B | |
| 111, 118, 119, 137, 138, 146, 147, 148, 150, 151, 152 & 155 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 1B | |
| 165, 167, 168, 171, 173 & 176 | Construction of authorised development | Works Nos. 1A and 2A | |
| 163, 164 & 166 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 1A and 2A | |
| 177, 178, 179 & 180 | Construction of authorised development | Work No. 1A | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 2, 3, 7, 25, 26, 27, 28, 30, 31, 48, 49, 50, 57 & 72 | Construction of authorised development | Work No. 1B | |
| 4, 14, 36, 38, 39, 120, 125, 127, 131, 142, 159, 167, 171, 172, 174, 177.2, 178, 186, 187, 190, 193, 194, 251, 273, 274, 278, 279, 281, 286, 392, 394, 399, 400, 401, 402, 403, 404, 407, 411, 412, 417, 420, 421, 422, 423, 425, 434, 462, 463, 465, 470, 471, 472, 481, 485, 491, 495, 499, 500, 513, 531, 532, 533, 538, 543, 546, 547, 603.2, 603.3, 619, 625, 631, 660, 677 & 678 | Dismantling of redundant infrastructure | Work No. 4B | |
| 5, 12, 15, 37, 76, 119, 140, 151, 170, 177.1, 179, 185, 188, 191, 266, 269, 271, 272, 277, 280, 285, 288, 393, 397, 406, 408, 413, 419, 424, 426, 454, 461, 477, 482, 492, 501, 510, 527, 537, 591, 603.1, 620, 627, 641, 654 & 676 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| 11, 16, 17, 40, 121, 122, 138, 139, 165, 166, 168, 169, 173, 175, 176, 180, 181, 182, 183, 184, 189, 192, 255, 267, 268, 270, 275, 276, 282, 283, 284, 287, 395, 396, 398, 405, 409, 410, 414, 415, 416, 418, 427, 459, 460, 464, 466, 478, 483, 484, 486, 496, 508, 509, 512, 621, 642, 653, 675 & 679 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| 13, 18, 22, 23, 24, 45 & 46 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 1B and 4B | |
| 44 & 47 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 1B | |
| 58, 59, 60, 69, 70 & 71 | Construction of authorised development | Works Nos. 1B and 1C | |
| 65, 66, 67, 68, 74, 75, 77, 87, 90, 93, 98, 103 & 104 | Construction of authorised development | Work No. 1C | |
| 73, 82 & 83 | Construction of authorised development | Works Nos. 1B, 1C and 4B | |
| 78, 79, 80, & 84 | Construction of authorised development | Works Nos. 1C and 4B | |
| 81 & 86 | Construction of authorised development | Works Nos. 1C and 4B | Removal of pylon foundations only to a depth of 1 metre |
| 85, 88, 89, 91, 92, 94, 95, 99 & 100 | Construction of authorised development | Works Nos. 1C and 1D | |
| 102, 108, 109, 111, 112, 113, 117, 199, 201, 202, 203, 206, 207, 210, 213, 214, 297, 298, 299, 302, 303, 306, 308, 309, 313, 316, 317, 318, 319, 321, 326, 330, 337, 339, 340, 342, 343, 344, 348, 350, 351, 354, 355, 356, 357, 374, 376, 436, 438, 440, 441, 442, 443, 446, 448, 451, 452, 517, 519, 521, 522, 523, 575, 577, 583, 590, 592, 594.1, 594.2, 601,1, 601.2, 605.1, 605.2, 605.3, 606.1, 606.2, 608.1, 608.2, 610, 613, 635 & 639 | Construction of authorised development | Work No. 1D | |
| 118, 154, 156, 488, 489, 518 & 520 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 1D and 4B | |
| 148, 149, 152, 197, 198, 200, 204, 205, 222, 223, 231, 245, 292, 294, 295, 311, 312, 314, 322, 324, 362, 363, 364 & 447 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 1D | |
| 153 | Dismantling of redundant infrastructure | Works Nos. 1D and 4B | |
| 155, 157, 158, 163, 164, 502, 503, 507, 516, 582, 618 & 640 | Construction of authorised development | Works Nos. 1D and 4B | |
| 593, 595 & 596 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 1D, 2B, 2C and 4B | |
| 597 | Construction of authorised development | Works Nos. 1D, 2B, 2C and 4B | |
| 599 | Construction of authorised development | Works Nos. 1D, 2B, 2D and 4B | |
| 611 & 612 | Construction of authorised development | Works Nos. 2B, 2D and 4B | Removal of pylon foundations only to a depth of 1 metre |
| 614, 615 & 616 | Construction of authorised development | Works Nos. 1D, 2B and 4B | |
| 643, 652, 665, 681 & 682 | Construction of authorised development | Works Nos. 2B and 4B | |
| 636, 646, 651, 655, 661, 669.1, 669.2, 671, 673, 674, 680, 683, 685, 688 & 689 | Construction of authorised development | Work No. 2B | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 664 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 1 & 2 | Dismantling of redundant infrastructure | Work No. 4B | |
| 3, 4, 5, 7, 10, 11, 12, 16 & 17 | Construction of authorised development | Work No. 2B | |
| 18 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 19 & 27 | Construction of authorised development | Work No. 2B | |
| 29 & 30 | Dismantling of redundant infrastructure | Work No. 4B | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 28, 31, 32, 36, 38, 39, 40, 42, 45, 46, 48, 49, 52, 57, 60, 63, 67, 69, 70, 79, 80, 81, 82, 87, 90, 92, 95, 97, 100, 104, 105, 107, 109, 110, 113, 114, 117, 118, 120, 121, 124, 126, 127, 130, 131, 133, 135, 138, 144, 146, 148, 149, 150, 155, 163, 164, 168, 170, 173, 175, 177, 178, 192, 194, 195, 197, 198, 200, 201, 203, 204, 218, 219, 220, 221, 223, 224, 226, 229, 230, 232, 237, 239, 241, 243, 246, 250, 254, 255, 266, 269, 270, 273, 275 & 278 | Construction of authorised development | Work No. 2B | |
| 41, 51, 58, 59, 62, 83, 84, 85, 86, 88, 89, 93, 94, 98, 108, 111, 136, 137, 187, 188, 189, 190, 191, 207, 212, 213, 214, 215, 216, 227, 228, 231, 252, 253, 271, 282, 283, 284 & 285 | Dismantling of redundant infrastructure | Work No. 4B | |
| 43, 233 & 256 | Construction of authorised development | Works Nos. 2B and 4B | |
| 50, 68, 112, 116, 147, 158, 159, 169, 205, 206, 209, 217, 240, 242, 247, 251 & 272 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| 181, 184, 185, 186, 208, 210 & 211 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 1, 2, 5, 6, 14, 16, 18, 58, 59.1, 59.2, 60 & 64 | Construction of authorised development | Work No. 2B | |
| 7, 8, 9, 11, 12, 13, 112.1, 112.2, 112.3, 115, 117, 188, 189, 197, 203, 205, 210, 211, 213, 229, 248, 249, 253, 254, 278, 279, 283, 284, 285, 289, 290, 296, 304, 306, 318.1, 318.2, 319, 321, 329, 341, 349, 351, 367, 372, 492, 529, 544.1, 544.2, 548, 557, 558, 559, 561, 566, 567, 571, 572, 575, 591, 594, 595, 602, 604, 605, 611, 612, 615, 616, 620, 621, 623, 672, 674, 675, 677, 678, 828, 900, 901, 902, 904, 961, 962, 963, 964, 965, 966, 967, 968, 969 & 970 | Dismantling of redundant infrastructure | Work No. 4B | |
| 10, 76, 106, 187, 194, 198, 212, 232, 252, 288, 297, 308, 339, 345, 361, 371, 522, 530, 545, 573, 596, 606, 617, 622, 673, 827, 832 & 903 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| 19 | Construction of authorised development | Works Nos. 4B and 4C | Removal of pylon foundations only to a depth of 1 metre |
| 20 | Construction of authorised development | Works Nos. 4B and 4C | |
| 21, 23, 24, 27, 28, 31, 33.1, 33.2 , 34, 35, 40, 41, 42, 43, 44, 45, 46 & 48 | Construction of authorised development | Work No. 4C | |
| 22, 38 & 39 | Dismantling of redundant infrastructure | Work No. 4C | |
| 25 & 47 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4C | |
| 26 & 32 | Construction of authorised development | Work No. 4C | Removal of pylon foundations only to a depth of 1 metre |
| 50 & 51 | Construction of authorised development | Works Nos. 2B, 3A and 3B | |
| 52, 63, 70 & 73 | Construction of authorised development | Works Nos. 2B and 3A | |
| 53 & 61 | Construction of authorised development | Works Nos. 2B, 3A and 4B | |
| 62 | Construction of authorised development | Works Nos. 2B, 3A and 4B | Removal of pylon foundations only to a depth of 1 metre |
| 77, 78, 79, 80, 102, 120 & 121 | Construction of authorised development | Work No. 3A | |
| 84, 85, 90, 92, 95, 214, 307, 309, 310, 334.1, 334.2, 335, 368, 377, 378, 380, 381, 382, 406, 540, 541, 580, 581, 680, 681, 682, 684, 687, 698, 758, 759 & 761 | Construction of authorised development | Work No. 1E | |
| 86, 208, 218, 226, 303, 317, 320, 322, 323, 324, 325, 344, 358, 362, 365, 366, 546, 547, 562, 564, 576, 597, 598, 599, 600, 601, 603, 618, 619, 676 & 826 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| 91, 256, 259, 266, 273, 275, 276, 316, 330, 374, 375, 403, 404, 405, 412, 470.1, 470.2, 471.1, 471.2, 475, 476, 480, 488, 489, 493, 495, 549, 551 & 552 | Construction of authorised development | Works Nos. 1E and 4B | |
| 94, 96.1 & 96.2 | Construction of authorised development | Works Nos. 1E and 4A | |
| 104, 105.1, 105.2, 105.3, 110, 111.1, 111.2, 122, 123, 126, 127, 129, 130, 133, 153, 156, 159, 160, 161, 162, 165, 169, 172, 175 & 176 | Construction of authorised development | Work No. 4A | |
| 131, 140, 141, 148, 163, 166, 167, 170, 181, 182 & 184 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4A | |
| 173, 178, 179, 180, 185, 186 & 193 | Dismantling of redundant infrastructure | Work No. 4A | |
| 177 | Construction of authorised development | Work No. 4A | Removal of pylon foundations only to a depth of 1 metre |
| 183 | Dismantling of redundant infrastructure | Work No. 4A | Removal of pylon foundations only to a depth of 1 metre |
| 233, 235, 538, 588, 589, 607, 608, 685, 696, 700, 706, 710, 712, 713, 821, 823, 824, 974, 975 & 977 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 1E | |
| 246, 263, 264, 268, 269.1, 269.2 , 270.1, 270.2, 271, 272, 299.1, 299.2, 301.1, 301.2, 302, 332.1, 332.2, 333, 337, 338, 369, 370, 373, 384, 386, 398, 399, 402, 407, 408.1, 408.2, 411, 436, 441, 447, 459, 460, 461, 462, 469, 472, 474, 477, 478, 531, 550, 555 & 556 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 1E and 4B | |
| 326, 327, 328, 331, 563 & 565 | Construction of authorised development | Work No. 4B | |
| 624, 783, 784, 785 & 833 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4B and 4D | |
| 625, 628, 629, 630, 636, 660.1, 660.2, 660.3, 660.4, 660.5, 661, 662, 663.1, 663.2, 664, 665, 666, 667, 668, 669, 768, 786, 787, 788, 789, 790, 791, 792, 793, 794, 795, 796, 797, 798, 799, 800, 801, 802, 803, 804, 805, 806, 807, 808, 809, 810, 811, 812, 813, 814, 836, 837, 838, 839, 840, 841, 842, 843, 844, 845, 846, 847, 848, 849, 850, 851, 852, 853, 854, 855, 856, 857, 858, 859, 860, 861, 862, 863, 864, 865, 866, 867, 868, 869, 870, 871, 872, 874, 875, 876, 877, 878, 879, 880, 881, 882, 884, 885, 886, 906, 908, 909, 910, 911, 912, 913, 914, 915, 916, 917, 918, 919, 920, 921, 922, 923, 924, 925, 926, 927, 928, 929, 930, 931, 932, 933, 934, 935, 936, 937, 938, 939, 943, 944, 949, 950, 951, 952, 953, 954, 955, 956, 957, 958 & 959 | Dismantling of redundant infrastructure | Work No. 4D | |
| 626.1, 626.2, 627, 634, 635, 637, 643, 648, 649, 658, 659, 723, 729, 731, 737, 739, 740, 741, 742, 743, 744, 745, 748, 750, 752, 753, 754, 829, 831, 834, 887, 888, 889, 945, 946, 948, 978, 979 & 980 | Construction of authorised development | Work No. 4D | |
| 631, 633, 670, 769, 835, 873 & 907 | Dismantling of redundant infrastructure | Work No. 4D | Removal of pylon foundations only to a depth of 1 metre |
| 632, 639, 640, 641, 642, 650, 651, 671, 905 & 960 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4D | |
| 703, 704, 816, 976.1 & 976.2 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 1E, 4B and 4D | |
| 770, 777, 780 & 781.2 | Dismantling of redundant infrastructure | Works Nos. 4B and 4D | |
| 781.1 & 815 | Dismantling of redundant infrastructure | Works Nos. 4B and 4D | Removal of pylon foundations only to a depth of 1 metre |
| 818 | Construction of authorised development | Works Nos. 1E and 4D | |
| 981, 982, 987, 988, 989, 990, 991, 992, 993, 994, 1002, 1004, 1008, 1009, 1011, 1012, 1013, 1015, 1016, 1017, 1019 & 1020 | Construction of authorised development | Work No. 4F | |
| 995 & 996 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4F | |
| 999 & 1000 | Dismantling of redundant infrastructure | Work No. 4F | |
| 1001 | Construction of authorised development | Work No. 4F | Removal of pylon foundations only to a depth of 1 metre |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 1, 4, 6, 7, 163, 222, 232, 238 & 239 | Construction of authorised development | Work No. 4D | |
| 10, 34 & 46 | Construction of authorised development | Works Nos. 4B and 4D | |
| 11 | Dismantling of redundant infrastructure | Works Nos. 4B and 4D | |
| 13, 68, 70, 79, 135, 168, 169, 170, 174 & 175 | Dismantling of redundant infrastructure | Work No. 4B | |
| 22, 109 & 111 | Construction of authorised development | Work No. 1E | |
| 23, 30, 45, 54 & 66 | Dismantling of redundant infrastructure | Works Nos. 4B and 4D | Removal of pylon foundations only to a depth of 1 metre |
| 37, 40, 49, 60, 63, 132, 133, 138, 149, 162, 191 & 194 | Construction of authorised development | Works Nos. 1E and 4D | |
| 53, 112, 113, 154, 167 & 176 | Construction of authorised development | Works Nos. 1E, 4B and 4D | |
| 96, 116 & 120 | Dismantling of redundant infrastructure | Work No. 4D | Removal of pylon foundations only to a depth of 1 metre |
| 97, 98, 99.1, 99.2, 100.1, 100.2, 101, 115, 119, 207 & 208 | Dismantling of redundant infrastructure | Work No. 4D | |
| 117, 118, 121, 122, 123, 134 & 144 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4D | |
| 142, 143, 155 & 171 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| 172 & 173 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 1, 2, 3, 4, 18, 19, 21, 22, 23, 29, 30, 34, 35, 36 & 202 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| 5, 6, 7, 8, 10, 11, 12, 13, 14, 15, 16, 17, 24, 25, 26, 27, 31, 32, 33, 138, 140, 141, 142, 143, 144, 145, 146, 149, 156, 158, 219.1, 222, 224, 225, 228 & 229 | Dismantling of redundant infrastructure | Work No. 4B | |
| 9, 20, 28, 37, 157, 201 & 219.2 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| 43, 95, 98, 192, 194 & 213 | Construction of authorised development | Work No. 4D | |
| 45, 94.3, 137, 147, 164, 165, & 262 | Construction of authorised development | Work No. 1F | |
| 46, 48, 57, 72, 76, 88, 89, 90, 150, 151, 152, 153, 154, 155, 166, 214.1, 214.2 & 223 | Dismantling of redundant infrastructure | Work No. 4D | |
| 64, 79, 200, 218 & 249 | Dismantling of redundant infrastructure | Work No. 4D | Removal of pylon foundations only to a depth of 1 metre |
| 87 | Construction of authorised development | Works Nos. 1E and 1F | |
| 148, 163 & 203 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4B and 4D | |
| 160 & 161 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 1F and 4D | |
| 176, 177, 178, 179, 186, 188, 196 & 217 | Construction of authorised development | Works Nos. 1F and 4D | |
| 226, 230, 231, 233, 247 & 248 | Construction of authorised development | Work No. 4E | |
| 227 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4B, 4D, 4E, 4G and 4P | |
| 232, 278 & 298 | Dismantling of redundant infrastructure | Work No. 4G | Removal of pylon foundations only to a depth of 1 metre |
| 234, 235, 240, 243, 276, 282 & 293 | Dismantling of redundant infrastructure | Work No. 4G | |
| 253 & 255 | Dismantling of redundant infrastructure | Work No. 4P | |
| 258 | Dismantling of redundant infrastructure | Work No. 4P | Removal of pylon foundations only to a depth of 1 metre |
| 260 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4P | |
| 266 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 1F | |
| 269, 279, 280, 281, 294, 296, 300, 307, 312, 314, 316, 317 & 322 | Construction of authorised development | Work No. 4P | |
| 284 | Construction of authorised development | Work No. 4P | Removal of pylon foundations only to a depth of 1 metre |
| 325 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 1F, 4G and 4P | |
| 326, 327, 328, 329 & 330 | Construction of authorised development | Works Nos. 1F and 4P | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 23.1, 23.2, 24.1, 24.2, 25, 112 & 113 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4G | |
| 35, 70, 71, 72, 73, 74, 75, 76, 77, 78, 79, 80, 81 & 86 | Construction of authorised development | Work No. 1F | |
| 39.1, 39.2, 42 & 43 | Dismantling of redundant infrastructure | Work No. 4G | |
| 82 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 1F and 4G | |
| 111 & 138 | Dismantling of redundant infrastructure | Work No. 4G | Removal of pylon foundations only to a depth of 1 metre |
| 120, 122, 124, 125, 127 & 130 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 1G and 4G | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 139 | Dismantling of redundant infrastructure | Work No. 4G | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 143, 144, 145, 146, 148, 248, 249, 250, 251, 252.1, 252.2, 253, 254, 255, 256, 257, 258, 259, 262, 263, 264, 265, 266, 267, 268, 270, 271, 272, 273, 274.1, 274.2, 275, 276, 277, 278, 279, 280, 281, 282, 283, 284, 285, 286, 287, 288, 289, 290, 291, 292, 293, 294, 295, 296, 297, 298, 299, 300, 301, 303, 304, 305, 306, 307, 308, 309, 310, 311, 312, 313, 315, 316, 317, 318, 322, 323, 324, 325, 326, 327, 329, 330, 331, 332, 333 & 334 | Dismantling of redundant infrastructure | Work No. 4G | |
| 147.1, 147.2, 260, 269, 302, 314 & 328 | Dismantling of redundant infrastructure | Work No. 4G | Removal of pylon foundations only to a depth of 1 metre |
| 171, 172, 173, 176, 177, 229, 369, 370, 494, 495, 510, 533, 535, 538, 540, 544, 546, 548 & 549 | Construction of authorised development | Work No. 1G | |
| 236, 241, 242, 243, 244, 245, 361, 365, 366, 507, 508 & 509 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 1G | |
| 261, 319, 320 & 321 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4G | |
| 335 | Dismantling of redundant infrastructure | Works Nos. 4G and 4H | Removal of pylon foundations only to a depth of 1 metre |
| 336 | Construction of authorised development | Work No. 4K | |
| 337 | Construction of authorised development | Works Nos. 4I and 4K | |
| 338, 339, 340, 341, 342, 343, 344, 345, 346, 347, 359, 437, 438, 439, 474, 475, 476, 477, 478, 479, 480, 481, 482.1, 482.2 , 498.1, 498.2 , 504, 517, 518 & 519 | Dismantling of redundant infrastructure | Work No. 4H | |
| 351, 352.1, 352.2, 353.1, 353.2, 355, 383, 384, 399, 400, 401, 402, 403, 404, 406, 407, 408 & 441 | Construction of authorised development | Works Nos. 1G and 4I | |
| 380 | Construction of authorised development | Work No. 4I | |
| 397 & 409 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4H | |
| 398, 405, 440 & 502 | Dismantling of redundant infrastructure | Work No. 4H | Removal of pylon foundations only to a depth of 1 metre |
| 562 & 564 | Construction of authorised development | Works Nos. 4M and 4N | |
| 565 | Dismantling of redundant infrastructure | Work No. 4N | |
| 572 & 575 | Construction of authorised development | Works Nos. 1G, 4L, 4M and 4N | |
| 593.1, 593.2, 594, 596 & 597 | Construction of authorised development | Work No. 5 | |
| 604, 605, 606, 607, 609 & 610 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4L, 4M, 4N, 4O and 5 | |
| 608 & 611 | Construction of authorised development | Works Nos. 4L, 4M, 4N, 4O and 5 | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 558 & 559 | Construction of authorised development | Works Nos. 4M and 4N | |
| 560 | Construction of authorised development | Works Nos. 1G, 4L, 4M and 4N | |
| 573 | Construction of authorised development | Work No. 4L | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 561 | Construction of authorised development | Works Nos. 4M and 4N | |
| 574 | Construction of authorised development | Work No. 4L | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 6, 9, 11, 24, 25, 81.1 & 81.2 | Construction of authorised development | Work No. 6E | |
| 29 & 30 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 6B, 6D and 6E | |
| 32 | Construction of authorised development | Works Nos. 6B, 6D and 6E | |
| 33, 34, 60 & 64 | Construction of authorised development | Works Nos. 6A, 6C and 6E | |
| 35, 37 & 65 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 6A, 6C and 6E | |
| 36 & 94 | Construction of authorised development | Works Nos. 6A and 6C | |
| 43, 44 & 45 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 6A and 6C | |
| 53 | Construction of authorised development | Works Nos. 6C and 6E | |
| 61 & 63 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 6A, 6B, 6C, 6D and 6E | |
| 82, 86 & 87 | Dismantling of redundant infrastructure | Works Nos. 6B and 6D | Removal of pylon foundations only to a depth of 1 metre |
| 83, 84 & 85 | Dismantling of redundant infrastructure | Works Nos. 6B and 6D | |
| 88 | Dismantling of redundant infrastructure | Work No. 6B | |
| 89, 90, 91 & 92 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 6B and 6D | |
| 111 | Construction of authorised development | Work No. 6A | |
| 114 & 117 | Construction of authorised development | Works Nos. 6C and 6D | |
| 115 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 6C |
PART 2 — WESTERN POWER DISTRIBUTION
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
|---|---|---|---|
| 1, 3, 4, 6, 7, 8, 9, 14, 15, 19, 29, 34, 35, 36, 41, 50, 56, 60, 61, 63, 64, 65, 70, 71, 74, 81, 82, 88, 91 & 94 | Dismantling of redundant infrastructure | Work No. 4B | |
| 2, 5, 10, 16, 23, 28, 33, 40, 47, 53, 54, 62, 75, 78, 83, 84, 89, 90 & 93 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| 11, 12, 13, 17, 18, 20, 21, 22, 24, 25, 26, 27, 30, 31, 32, 37, 38, 39, 42, 43, 44, 45, 46, 48, 49, 51, 52, 55, 57, 58, 59, 66, 67, 68, 69, 72, 73, 76, 77, 79, 80, 85, 86, 87, 92, 97, 98, 101, 157 & 158 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 4, 8, 9, 14, 36, 38, 39, 78, 84, 120, 125, 126, 127, 131, 132, 133, 134, 142, 153, 159, 160, 167, 171, 172, 174, 177.2, 178, 186, 187, 190, 193, 194, 251, 252, 253, 254, 273, 274, 278, 279, 281, 286, 371, 378, 380, 383, 385, 392, 394, 399, 400, 401, 402, 403, 404, 407, 411, 412, 417, 420, 421, 422, 423, 425, 434, 455, 462, 463, 465, 470, 471, 472, 476, 481, 485, 491, 494, 495, 498, 499, 500, 513, 514, 528, 530, 531, 532, 533, 534, 538, 540, 542, 543, 546, 547, 548, 551, 560, 572, 579, 587, 588, 589, 602, 603.2, 603.3, 604.2, 615, 619, 625, 626, 630, 631, 660, 666, 677 & 678 | Dismantling of redundant infrastructure | Work No. 4B | |
| 5, 12, 15, 37, 76, 81, 86, 119, 135, 140, 151, 170, 177.1, 179, 185, 188, 191, 266, 269, 271, 272, 277, 280, 285, 288, 370, 386, 393, 397, 406, 408, 413, 419, 424, 426, 454, 461, 477, 482, 492, 501, 510, 527, 535, 537, 545, 558, 568, 578, 591, 603.1, 604.1, 611, 612, 620, 627, 641, 654, 659 & 676 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| 10, 11, 13, 16, 17, 18, 19, 20, 22, 23, 24, 34, 40, 42, 45, 46, 73, 79, 80, 82, 83, 115, 118, 121, 122, 129, 130, 138, 139, 154, 156, 165, 166, 168, 169, 173, 175, 176, 180, 181, 182, 183, 184, 189, 192, 255, 256, 257, 258, 259, 260, 261, 262, 263, 264, 265, 267, 268, 270, 275, 276, 282, 283, 284, 287, 359, 368, 373, 381, 384, 388, 391, 395, 396, 398, 405, 409, 410, 414, 415, 416, 418, 427, 428, 429, 433, 435, 437, 439, 450, 459, 460, 464, 466, 469, 478, 479, 480, 483, 484, 486, 488, 489, 490, 496, 502, 503, 504, 506, 507, 508, 509, 511, 512, 515, 516, 518, 520, 525, 526, 536.1, 536.2, 539, 541, 544, 549, 550, 556, 559, 562, 569, 581, 582, 584, 586, 593, 595, 596, 597, 599, 609.1, 609.2, 609.3, 609.4, 614, 616, 617, 618, 621, 622, 623, 624, 632, 633, 634, 640, 642, 643, 644, 649, 650.1, 650.2 , 652, 653, 665, 675, 679, 681 & 682 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 664 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 1 & 2 | Dismantling of redundant infrastructure | Work No. 4B | |
| 6, 13, 15 & 19 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| 14 & 18 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 25 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| 29 & 30 | Dismantling of redundant infrastructure | Work No. 4B | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 33, 34, 37, 42, 43, 44, 47, 53, 56, 61, 64, 65, 66, 67, 71, 76, 77, 78, 91, 96, 99, 106, 107, 114, 115, 117, 119, 122, 123, 125, 128, 129, 132, 134, 139, 145, 146, 154, 160, 161, 162, 167, 168, 171, 172, 176, 181, 182, 183, 184, 185, 186, 196, 202.1, 202.2, 204, 208, 210, 211, 219, 220, 221, 225, 233, 234, 249, 255, 256, 257, 267, 268, 273, 274, 277, 280 & 281 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| 41, 51, 58, 59, 62, 83, 84, 85, 86, 88, 89, 93, 94, 98, 108, 111, 136, 137, 152, 153, 156, 157, 166, 180, 187, 188, 189, 190, 191, 207, 212, 213, 214, 215, 216, 227, 228, 231, 252, 253, 271, 276, 282, 283, 284 & 285 | Dismantling of redundant infrastructure | Work No. 4B | |
| 50, 68, 112, 116, 147, 158, 159, 169, 205, 206, 209, 217, 240, 242, 244, 247, 248, 251 & 272 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 3, 15 & 57 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4B and 4C | |
| 4 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4A and 4B | |
| 7, 8, 9, 11, 12, 13, 17, 52, 53, 54, 55, 56, 61, 66, 68, 75, 88, 89, 112.1, 112.2, 112.3, 115, 117, 118, 188, 189, 190, 196, 197, 203, 204, 205, 210, 211, 213, 229, 231, 237.1, 237.2, 240, 243, 248, 249, 251, 253, 254, 255, 278, 279, 283, 284, 285, 286, 289, 290, 296, 304, 306, 318.1, 318.2, 319, 321, 329, 341, 348, 349, 351, 352, 367, 372, 394, 416, 419, 422, 424, 434, 452, 453, 467, 484, 485, 492, 504, 506, 514, 517, 529, 544.1, 544.2, 548, 557, 558, 559, 560, 561, 566, 567, 571, 572, 574, 575, 591, 592, 593, 594, 595, 602, 604, 605, 611, 612, 613, 615, 616, 620, 621, 623, 672, 674, 675, 677, 678, 775, 776, 828, 900, 901, 902, 904, 961, 962, 963, 964, 965, 966, 967, 968, 969 & 970 | Dismantling of redundant infrastructure | Work No. 4B | |
| 10, 62, 76, 106, 187, 194, 198, 199, 212, 232, 236, 247, 252, 288, 297, 308, 339, 345, 361, 371, 391, 413, 430, 438, 455, 464, 494, 511, 521, 522, 530, 545, 573, 596, 606, 617, 622, 673, 827, 832 & 903 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| 18 & 20 | Construction of authorised development | Works Nos. 4B and 4C | |
| 19 | Construction of authorised development | Works Nos. 4B and 4C | Removal of pylon foundations only to a depth of 1 metre |
| 21, 23, 24, 27, 28, 29, 31, 33.1, 33.2 , 34, 35, 40, 41, 42, 43, 44, 45, 46 & 48 | Construction of authorised development | Work No. 4C | |
| 22, 30, 38 & 39 | Dismantling of redundant infrastructure | Work No. 4C | |
| 25 & 47 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4C | |
| 26 & 32 | Construction of authorised development | Work No. 4C | Removal of pylon foundations only to a depth of 1 metre |
| 63, 67, 69, 74.1, 74.2, 74.3, 74.4, 74.5 77, 83, 86, 87, 102, 200, 208, 217, 218, 219, 220.1, 220.2, 221, 223, 224, 225, 226, 227, 228, 233, 234, 235, 241, 242, 244, 245, 246, 250, 257, 258.1, 258.2 , 262, 263, 264, 265, 267, 268, 269.1, 269.2 , 270.1, 270.2, 271, 272, 274, 277, 280, 282, 287, 291, 292, 293, 294, 295, 299.1, 299.2, 301.1, 301.2, 302, 303, 305.1, 305.2, 307, 311, 315.1, 315.2, 316, 317, 320, 322, 323, 324, 325, 332.1, 332.2, 333, 336, 337, 338, 340, 343, 344, 346, 350, 354, 355, 356, 357.1, 357.2, 358, 359, 362, 363, 364, 365, 366, 369, 370, 373, 376, 377, 378, 383, 384, 385, 386, 387, 388, 390, 392, 393, 395, 396, 397, 398, 399, 400.1, 400.2 , 402, 407, 408.1, 408.2, 409, 410, 411, 414, 417, 418, 420, 425, 427, 428, 429, 431, 432, 436, 437, 439, 440, 441, 442, 445, 446, 447, 448, 449, 450, 451, 454, 456, 457, 458, 459, 460, 461, 462, 466, 468.1, 468.2, 469, 472, 473, 474, 477, 478, 479, 481, 482, 483, 486, 490, 491, 500, 502, 503, 505, 507, 510, 512, 513, 515, 516, 518, 523, 531, 532, 546, 547, 550, 555, 556, 562, 564, 568, 569, 570, 576, 585, 587, 588, 589, 590, 597, 598, 599, 600, 601, 603, 607, 608, 609, 618, 619, 676, 680, 685, 686, 687 & 826 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| 65 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4A, 4B and 4C | |
| 104, 105.1, 105.2, 105.3, 110, 111.1, 111.2, 120, 121, 122, 123, 126, 127, 129, 130, 133, 153, 156, 159, 160, 161, 162, 165, 169, 172, 175, 176 & 177 | Construction of authorised development | Work No. 4A | |
| 131, 140, 141, 148, 163, 166, 167, 170, 181, 182 & 184 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4A | |
| 173, 178, 179, 180, 185, 186, 192 & 193 | Dismantling of redundant infrastructure | Work No. 4A | |
| 183 | Dismantling of redundant infrastructure | Work No. 4A | Removal of pylon foundations only to a depth of 1 metre |
| 256, 266, 273, 275, 276, 326, 327, 328, 330, 331, 470.1, 470.2, 471.1, 471.2, 475, 476, 480, 488, 489, 493, 495, 549, 551, 552, 563 & 565 | Construction of authorised development | Work No. 4B | |
| 624, 702, 703, 704, 707, 759, 760, 762, 772, 782.1, 782.2, 783, 784, 785, 816, 817, 833, 976.1 & 976.2 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4B and 4D | |
| 625, 628, 629, 630, 636, 660.1, 660.2, 660.3, 660.4, 660.5, 661, 662, 663.1, 663.2, 664, 665, 666, 667, 668, 669, 768, 786, 787, 788, 789, 790, 791, 792, 793, 794, 795, 796, 797, 798, 799, 800, 801, 802, 803, 804, 805, 806, 807, 808, 809, 810, 811, 812, 813, 814, 836, 837, 838, 839, 840, 841, 842, 843, 844, 845, 846, 847, 848, 849, 850, 851, 852, 853, 854, 855, 856, 857, 858, 859, 860, 861, 862, 863, 864, 865, 866, 867, 868, 869, 870, 871, 872, 874, 875, 876, 877, 878, 879, 880, 881, 882, 884, 885, 886, 906, 908, 909, 910, 911, 912, 913, 914, 915, 916, 917, 918, 919, 920, 921, 922, 923, 924, 925, 926, 927, 928, 929, 930, 931, 932, 933, 934, 935, 936, 937, 938, 939, 943, 944, 949, 950, 951, 952, 953, 954, 955, 956, 957, 958 & 959 | Dismantling of redundant infrastructure | Work No. 4D | |
| 626.1, 626.2, 627, 634, 635, 637, 643, 648, 649, 658, 659, 723, 729, 731, 737, 739, 740, 741, 742, 743, 744, 745, 748, 750, 752, 753, 754, 818, 829, 831, 834, 887, 888, 889, 945, 946, 948, 978, 979 & 980 | Construction of authorised development | Work No. 4D | |
| 631, 633, 670, 769, 835, 873 & 907 | Dismantling of redundant infrastructure | Work No. 4D | Removal of pylon foundations only to a depth of 1 metre |
| 632, 639, 640, 641, 642, 650, 651, 671, 905 & 960 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4D | |
| 758 | Construction of authorised development | Works Nos. 4B and 4D | |
| 764, 765, 770, 777, 780 & 781.2 | Dismantling of redundant infrastructure | Works Nos. 4B and 4D | |
| 771, 781.1 & 815 | Dismantling of redundant infrastructure | Works Nos. 4B and 4D | Removal of pylon foundations only to a depth of 1 metre |
| 981, 982, 987, 988, 989, 990, 991, 992, 993, 994, 1002, 1004, 1008, 1009, 1011, 1012, 1013, 1015, 1016, 1017, 1019 & 1020 | Construction of authorised development | Work No. 4F | |
| 995 & 996 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4F | |
| 999 & 1000 | Dismantling of redundant infrastructure | Work No. 4F | |
| 1001 | Construction of authorised development | Work No. 4F | Removal of pylon foundations only to a depth of 1 metre |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 1, 4, 6, 7, 33, 37, 40, 49, 50, 59, 60, 63, 132, 133, 138, 146, 149, 162, 163, 191, 194, 222, 232, 238 & 239 | Construction of authorised development | Work No. 4D | |
| 10, 34, 43, 46, 53, 94, 103, 104, 109, 110, 112, 113, 154, 167 & 176 | Construction of authorised development | Works Nos. 4B and 4D | |
| 11, 16, 19, 29 & 93 | Dismantling of redundant infrastructure | Works Nos. 4B and 4D | |
| 13, 14, 68, 70, 77, 79, 105, 127, 128, 135, 136, 145, 159, 168, 169, 170, 174 & 175 | Dismantling of redundant infrastructure | Work No. 4B | |
| 23, 30, 45, 54 & 66 | Dismantling of redundant infrastructure | Works Nos. 4B and 4D | Removal of pylon foundations only to a depth of 1 metre |
| 44, 57, 65, 96, 116 & 120 | Dismantling of redundant infrastructure | Work No. 4D | Removal of pylon foundations only to a depth of 1 metre |
| 78, 126, 142, 143, 155 & 171 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| 95.1, 95.2, 97, 98, 99.1, 99.2, 100.1, 100.2, 101, 115, 119, 207, 208, 209 & 210 | Dismantling of redundant infrastructure | Work No. 4D | |
| 117, 118, 121, 122, 123, 134 & 144 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4D | |
| 160 | Construction of authorised development | Works Nos. 4B and 4D | |
| 131, 137, 172 & 173 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 1, 2, 3, 4, 18, 19, 21, 22, 23, 29, 30, 34, 35, 36 & 202 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4B | |
| 5, 6, 7, 8, 10, 11, 12, 13, 14, 15, 16, 17, 24, 25, 26, 27, 31, 32, 33, 138, 139, 140, 141, 142, 143, 144, 145, 146, 149 156, 158, 159, 219.1, 222, 224, 225, 228 & 229 | Dismantling of redundant infrastructure | Work No. 4B | |
| 9, 20, 28, 37, 157, 201 & 219.2 | Dismantling of redundant infrastructure | Work No. 4B | Removal of pylon foundations only to a depth of 1 metre |
| 38, 40, 41, 45, 60, 160, 161, 162 & 165 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4D | |
| 39, 64, 79, 81, 200, 218 & 249 | Dismantling of redundant infrastructure | Work No. 4D | Removal of pylon foundations only to a depth of 1 metre |
| 43, 67, 95, 98, 137, 176, 177, 178, 179, 186, 188, 192, 194, 196, 213 & 217 | Construction of authorised development | Work No. 4D | |
| 46, 47, 48, 57, 58, 59, 69, 72, 74, 76, 78, 82, 83, 84, 88, 89, 90, 91, 150, 151, 152, 153, 154, 155, 166, 167, 168, 169, 170, 172, 199, 214.1, 214.2 & 223 | Dismantling of redundant infrastructure | Work No. 4D | |
| 148, 163, 203 & 204 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4B and 4D | |
| 226, 230, 231, 233, 247 & 248 | Construction of authorised development | Work No. 4E | |
| 227 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4B, 4D, 4E, 4G and 4P | |
| 232, 278, 298 & 320 | Dismantling of redundant infrastructure | Work No. 4G | Removal of pylon foundations only to a depth of 1 metre |
| 234, 235, 240, 243, 276, 282, 293, 302 & 304 | Dismantling of redundant infrastructure | Work No. 4G | |
| 253, 255 & 285 | Dismantling of redundant infrastructure | Work No. 4P | |
| 258 | Dismantling of redundant infrastructure | Work No. 4P | Removal of pylon foundations only to a depth of 1 metre |
| 260 & 264 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4P | |
| 267, 269, 279, 280, 281, 288, 294, 296, 300, 307, 312, 314, 316, 317, 322, 326, 327, 328, 329 & 330 | Construction of authorised development | Work No. 4P | |
| 284 | Construction of authorised development | Work No. 4P | Removal of pylon foundations only to a depth of 1 metre |
| 303, 313 & 325 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4G and 4P | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 38, 39.1, 39.2, 42, 43, 45, 46, 47.1, 47.2, 48, 52,57, 58.1, 58.2, 59, 64, 69, 84, 107, 118, 134 & 137 | Dismantling of redundant infrastructure | Work No. 4G | |
| 53, 61, 65, 108, 111, 116 & 138 | Dismantling of redundant infrastructure | Work No. 4G | Removal of pylon foundations only to a depth of 1 metre |
| 23.1, 23.2, 24.1, 24.2, 25, 82, 112, 113, 119, 120, 121, 122, 124, 125, 127, 128 & 130 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4G | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 139 | Dismantling of redundant infrastructure | Work No. 4G | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 143, 144, 145, 146, 148, 151, 248, 249, 250, 251, 252.1, 252.2, 253, 254, 255, 256, 257, 258, 259, 262, 263, 264, 265, 266, 267, 268, 270, 271, 272, 273, 274.1, 274.2, 275, 276, 277, 278, 279, 280, 281, 282, 283, 284, 285, 286, 287, 288, 289, 290, 291, 292, 293, 294, 295, 296, 297, 298, 299, 300, 301, 303, 304, 305, 306, 307, 308, 309, 310, 311, 312, 313, 315, 316, 317, 318, 322, 323, 324, 325, 326, 327, 329, 330, 331, 332, 333 & 334 | Dismantling of redundant infrastructure | Work No. 4G | |
| 147.1, 147.2, 260, 269, 302, 314 & 328 | Dismantling of redundant infrastructure | Work No. 4G | Removal of pylon foundations only to a depth of 1 metre |
| 261, 319, 320 & 321 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4G | |
| 335 | Dismantling of redundant infrastructure | Works Nos. 4G and 4H | Removal of pylon foundations only to a depth of 1 metre |
| 336 | Construction of authorised development | Work No. 4K | |
| 337 | Construction of authorised development | Works Nos. 4I and 4K | |
| 338, 339, 340, 341, 342, 343, 344, 345, 346, 347, 359, 378, 437, 438, 439, 474, 475, 476, 477, 478, 479, 480, 481, 482.1, 482.2 , 498.1, 498.2 , 499, 500, 501, 503, 504, 514, 515, 517, 518 & 519 | Dismantling of redundant infrastructure | Work No. 4H | |
| 351, 352.1, 352.2, 353.1, 353.2, 355, 380, 383, 384, 399, 400, 401, 402, 403, 404, 406, 407, 408 & 441 | Construction of authorised development | Work No. 4I | |
| 397 & 409 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Work No. 4H | |
| 398, 405, 440 & 502 | Dismantling of redundant infrastructure | Work No. 4H | Removal of pylon foundations only to a depth of 1 metre |
| 562 & 564 | Construction of authorised development | Works Nos. 4M and 4N | |
| 563, 570, 571, 572 & 575 | Construction of authorised development | Works Nos. 4L, 4M and 4N | |
| 565 | Dismantling of redundant infrastructure | Work No. 4N | |
| 572 | Construction of authorised development | Works Nos. 4L, 4M and 4N | |
| 599 | Dismantling of redundant infrastructure | Work No. 4L | Removal of pylon foundations only to a depth of 1 metre |
| 604, 605, 606, 607, 609 & 610 | Access to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access | Works Nos. 4L, 4M, 4N and 4O | |
| 608 & 611 | Construction of authorised development | Works Nos. 4L, 4M, 4N and 4O | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 558 & 559 | Construction of authorised development | Works Nos. 4M and 4N | |
| 560 | Construction of authorised development | Works Nos. 4L, 4M and 4N | |
| 573 | Construction of authorised development | Work No. 4L | |
| (1)Plot number of land shown on Land Plan | (2)Purpose for which temporary possession may be taken | (3)Relevant part of the authorised development | (4)Element of Work in respect of which land is not required to be re-instated |
| --- | --- | --- | --- |
| 561 | Construction of authorised development | Works Nos. 4M and 4N | |
| 574 | Construction of authorised development | Work No. 4L |
SCHEDULE 13 — TRAFFIC REGULATION
PART 1 — TEMPORARY PROHIBITION OF VEHICULAR ACCESS AND NO WAITING AND SPEED RESTRICTION
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.