Construction hours for the transmission works

23

  • (1) Construction work for the transmission works must only take place between 0700 hours and 1900 hours Monday to Friday and 0700 hours and 1300 hours on Saturdays, with no activity on Sundays or bank holidays, except as specified in sub-paragraph (2).
  • (2) Outside the hours specified in sub-paragraph (1), construction work may be undertaken for essential activities including but not limited to—
  • (a) continuous periods of operation that are required as assessed in the environmental statement, such as concrete pouring, dewatering, cable pulling, cable jointing and drilling during the operation of a trenchless technique;
  • (b) internal fitting out works associated with the onshore substation;
  • (c) delivery to the transmission works of abnormal loads that may cause congestion on the local road network;
  • (d) the testing or commissioning of any electrical plant or cables installed as part of the authorised development; and
  • (e) activity necessary in the instance of an emergency where there is a risk to persons, delivery of electricity or property.
  • (3) With the exception of activities undertaken in accordance with sub-paragraph (2)(e), the timing and duration of construction work undertaken in accordance with sub-paragraph (2) and, where works do not fall within sub-paragraphs (2)(a) to (2)(e), whether such works are essential, must be approved by the relevant planning authority in writing in advance, and must be carried out within the approved time.

Construction hours for the grid connection works

24

  • (1) Construction work for the grid connection works must only take place between 0700 hours and 1900 hours Monday to Friday and 0700 hours and 1300 hours on Saturdays, with no activity on Sundays or bank holidays, except as specified in sub-paragraph (2).
  • (2) Outside the hours specified in sub-paragraph (1), construction work may be undertaken for essential activities including but not limited to—
  • (a) continuous periods of operation that are required as assessed in the environmental statement, such as concrete pouring and the installation and removal of conductors, pilot wires and associated protective netting across highways or public footpaths;
  • (b) internal fitting out works associated with the national grid substation;
  • (c) the completion of construction activities commenced during the approved working hours which cannot safely be stopped;
  • (d) the testing or commissioning of any electrical plant installed as part of the authorised development; and
  • (e) activity necessary in the instance of an emergency where there is a risk to persons or property.
  • (3) With the exception of activities undertaken in accordance with sub-paragraph (2)(e), the timing and duration of construction work undertaken in accordance with sub-paragraph (2) and, where works do not fall within sub-paragraphs (2)(a) to (2)(e), whether such works are essential, must be approved by the relevant planning authority in writing in advance, and must be carried out within the approved time.

Control of artificial light emissions during operational phase

25

  • (1) Work No. 30 must not begin operation until an operational artificial light emissions management plan providing details of artificial light emissions during the operation of Work No. 30, including measures to minimise lighting pollution and the hours of lighting, has been submitted to and approved by the relevant planning authority.
  • (2) The approved operational artificial light emissions management plan must be implemented upon, and maintained during, the operation of Work No. 30.
  • (3) Work No. 41 must not begin operation until an operational artificial light emissions management plan providing details of artificial light emissions during the operation of Work No. 41, including measures to minimise lighting pollution and the hours of lighting, has been submitted to and approved by the relevant planning authority.
  • (4) The approved operational artificial light emissions management plan must be implemented upon, and maintained during, the operation of Work No. 41.
  • (5) Work No. 38 must not begin operation until an operational artificial light emissions management plan providing details of artificial light emissions during the operation of Work No. 38, including measures to minimise lighting pollution and the hours of lighting, has been submitted to and approved by the relevant planning authority.
  • (6) The approved operational artificial light emissions management plan must be implemented upon, and maintained during, the operation of Work No. 38.

Onshore preparation works management plan

26

  • (1) Prior to carrying out specified onshore preparation works, an onshore preparation works management plan in respect of those works (which accords with appendix 1 of the outline code of construction practice) must be submitted to and approved by the relevant planning authority in consultation with Suffolk County Council.
  • (2) The specified onshore preparation works must be carried out in accordance with the approved onshore preparation works management plan.
  • (3) For the purposes of this requirement, “specified onshore preparation works” means operations consisting of site clearance, demolition work, early planting of landscaping works, intrusive ecological mitigation, investigations for the purpose of assessing ground conditions, remedial work in respect of any contamination or other adverse ground conditions, diversion and laying of services, erection of temporary means of enclosure, creation of site accesses, footpath creation and erection of welfare facilities.

Control of noise during operational phase

27

  • (1) The combined noise rating level for the standard operation of Work No. 30 cumulatively with the standard operation of the new national grid substation and the East Anglia ONE North onshore substation must not exceed—
  • (a) 32dB LAeq (15 min) at any time at a free field location immediately adjacent to the following noise sensitive locations—
  • (i) 1 Woodside Cottages, Grove Road (641837, 261172);
  • (ii) Woodside Barn Cottages, Church Road (641237, 260645);
  • (b) 31dB LAeq (15 min) at any time at a free field location immediately adjacent to the noise sensitive location—
  • Little Moor Farm, Knodishall (641228, 261676).
  • (2) Work No. 30 must not operate at the same time as the new national grid substation or the East Anglia ONE North onshore substation until a scheme for monitoring compliance with the noise rating levels set out in sub-paragraph (1) above has been submitted to and approved by the relevant planning authority. The scheme must be based on principles set out in BS 4142:2014+A1:2019. The reference method set out in Annex D to BS 4142:2014+A1:2019 shall be used in the assessment of whether tonal penalties apply. The scheme must identify—
  • (a) the required meteorological and other conditions under which the measurements will be taken, acknowledging that data obtained during emergency operation or testing of certain plant and equipment is not to be taken in to account;
  • (b) suitable monitoring locations (and alternative surrogate locations if appropriate); and
  • (c) times when the monitoring is to take place

to demonstrate that the noise levels have been achieved after—

  • (d) initial commencement of—
  • (i) Work No. 30, the new national grid substation and the East Anglia ONE North onshore substation all operating at the same time; and
  • (ii) where Work No. 30 begins operation before the East Anglia ONE North onshore substation, Work No. 30 and the new national grid substation operating at the same time; and
  • (e) six months after—
  • (i) Work No. 30, the new national grid substation and the East Anglia ONE North onshore substation have all been operating cumulatively at full capacity; and
  • (ii) where Work No. 30 begins operation at least six months before the East Anglia ONE North onshore substation, both Work No. 30 and the new national grid substation have been operating cumulatively at full capacity.
  • (3) The monitoring scheme must be implemented as approved.
  • (4) For the purposes of this requirement—
  • (a) “East Anglia ONE North onshore substation” means the onshore substation comprised within Work No. 30 of the East Anglia ONE North Order;
  • (b) “new national grid substation” means the national grid substation comprised within Work No. 41 of this Order and Work No. 41 of the East Anglia ONE North Order; and
  • (c) “standard operation” means the ordinary operation of the substations excluding emergency operation and the testing of plant and equipment associated with emergency operation.

Traffic

28

  • (1) No stage of the onshore works may commence until for that stage the following have been submitted to and approved by the relevant highway authority in consultation with the relevant planning authority—
  • (a) a construction traffic management plan which must be in accordance with the outline construction traffic management plan; and
  • (b) a travel plan which must be in accordance with the outline travel plan.
  • (2) The plans approved under sub-paragraph (1) must be implemented upon commencement of the relevant stage of the onshore works.

Restoration of land used temporarily for construction

29

Any land landward of mean low water springs within the Order limits which is used temporarily for construction of the onshore works and not ultimately incorporated in permanent works or approved landscaping must be reinstated, in accordance with such details as the relevant planning authority in consultation with the relevant highway authority may approve, within twelve months of completion of the relevant stage of the onshore works or such other period as the relevant planning authority may approve.

Onshore decommissioning

30

  • (1) The undertaker must notify the relevant planning authority of the permanent cessation of commercial operation of the transmission works within 14 days following the date of permanent cessation.
  • (2) Within six months following the permanent cessation of commercial operation of the transmission works an onshore decommissioning plan in respect of the transmission works must be submitted to and approved by the relevant planning authority in consultation with the relevant highway authority and the relevant statutory nature conservation body.
  • (3) The undertaker must notify the relevant planning authority of the permanent cessation of commercial operation of the grid connection works within 14 days following the date of permanent cessation.
  • (4) Within six months following the permanent cessation of commercial operation of the grid connection works an onshore decommissioning plan in respect of the grid connection works must be submitted to and approved by the relevant planning authority in consultation with the relevant highway authority and the relevant statutory nature conservation body.
  • (5) The decommissioning plans must be implemented as approved.

Aviation Lighting

31

  • (1) The undertaker must exhibit such lights, with such shape, colour and character as are required in writing by Air Navigation Order 201637 and determined necessary for aviation safety in consultation with the Defence Infrastructure Organisation Safeguarding and as directed by the Civil Aviation Authority.
  • (2) Such lights will be operated at the lowest permissible lighting intensity level.

Public rights of way

32

  • (1) No stage of the authorised development or onshore preparation works that would affect a public right of way specified in Schedule 3 (public rights of way to be temporarily stopped up) or Schedule 4 (footpaths to be stopped up) is to be undertaken until a public rights of way strategy in respect of that stage and in accordance with the outline public rights of way strategy, including the specification for the making up of an alternative right of way (where appropriate) has been submitted to and approved by the relevant highway authority in consultation with the relevant planning authority.
  • (2) Any alternative public rights of way must be implemented in accordance with the approved public rights of way strategy.

Emergency planning arrangements

33

  • (1) No part of the relevant works shall commence until the Suffolk Resilience Forum Radiation Emergency Plan has been reviewed to account for the relevant works or part thereof and reissued in accordance with the relevant Radiation Emergency Preparedness Regulations.
  • (2) Emergency planning arrangements specified within the Suffolk Resilience Forum Radiation Emergency Plan in respect of the relevant works shall be implemented in relation to the relevant part of the relevant works, unless otherwise agreed with Suffolk County Council after consultation with the Sizewell Emergency Planning Consultative Committee or Suffolk Resilience Forum as appropriate.
  • (3) For the purposes of this requirement—
  • (a) “the relevant works” means—
  • (i) the onshore preparation works;
  • (ii) the onshore works; and
  • (iii) to the extent that they are within the Sizewell B Detailed Emergency Planning Zone, the offshore works.
  • (b) “the relevant Radiation Emergency Preparedness Regulations” means the Radiation (Emergency Preparedness and Public Information) Regulations 201938 as amended from time to time; and
  • (c) “the relevant Sizewell B Detailed Emergency Planning Zone” means the Sizewell Detailed Emergency Planning Zone detailed within the Suffolk Resilience Forum Radiation Emergency Plan.

Ministry of Defence surveillance operations

34

  • (1) No wind turbine generator forming part of the authorised development is permitted to rotate its rotor blades on its horizontal axis until the Secretary of State, having consulted with the Ministry of Defence, confirms satisfaction in writing that appropriate mitigation will be implemented and maintained for the life of the authorised development and that arrangements have been put in place with the Ministry of Defence to ensure that the approved mitigation is implemented.
  • (2) For the purposes of this requirement—
  • (a) “appropriate mitigation” means measures to prevent or remove any adverse effects which the authorised development will have on the air defence radar at Remote Radar Head Trimingham and the Ministry of Defence’s air surveillance and control operations;
  • (b) “approved mitigation” means the detailed Radar Mitigation Scheme that will set out the appropriate measures and timescales for implementation as agreed with the Ministry of Defence at the time the Secretary of State confirms satisfaction in writing in accordance with sub-paragraph (1);
  • (c) “Ministry of Defence” means the Ministry of Defence as represented by Defence Infrastructure Organisation – Safeguarding, Kingston Road, Sutton Coldfield, B75 7RL or any successor body.
  • (3) The undertaker must thereafter comply with all other obligations contained within the approved mitigation for the life of the authorised development.

Cromer Primary Surveillance Radar

35

  • (1) No erection of any wind turbine generator forming part of the authorised development may commence until the Secretary of State, having consulted with NATS, has confirmed satisfaction in writing that appropriate mitigation will be implemented and maintained for the required period and that arrangements have been put in place with NATS to ensure that the approved mitigation is implemented and in operation prior to erection of the wind turbine generators.
  • (2) The undertaker must thereafter comply with the obligations contained within the approved mitigation for the required period.
  • (3) For the purposes of this requirement—
  • (a) “appropriate mitigation” means measures to mitigate any adverse effects which the operation of the authorised development will have on the primary surveillance radar at Cromer and NATS’ associated air traffic (surveillance and control) services/operations during the required period;
  • (b) “approved mitigation” means the detailed Primary Radar Mitigation Scheme setting out the appropriate mitigation approved by the Secretary of State and confirmed in writing in accordance with sub-paragraph (1);
  • (c) “NATS” means NATS (En-Route) Plc (company number 04129273) or any successor body;
  • (d) “the required period” means the shorter of—
  • (i) the operational life of the authorised development; and
  • (ii) the period ending on the date notified to the Secretary of State by the undertaker and confirmed in writing by NATS being the date on which NATS no longer requires the appropriate mitigation to be in place.

Port traffic

36

  • (1) No part of Work No. 1 may commence until—
  • (a) a port construction traffic management plan (which accords with the outline port construction traffic management and travel plan) for the onshore port-related traffic to and from the construction port or ports and relating to that part of the authorised development, has been submitted to and approved by the relevant highway authority in consultation with the relevant planning authority; or
  • (b) the relevant highway authority has confirmed, after consultation with the relevant planning authority, that no port construction traffic management plan is required for that part of the authorised development.
  • (2) No part of Work No. 1 may begin operating until—
  • (a) a port travel plan (which accords with the outline port construction traffic management and travel plan) for the onshore port-related traffic to and from the operation port or ports and relating to that part of the authorised development, has been submitted to and approved by the relevant highway authority in consultation with the relevant planning authority; or
  • (b) the relevant highway authority has confirmed, after consultation with the relevant planning authority, that no port travel plan is required for that part of the authorised development.
  • (3) The port construction traffic management plan must be implemented as approved at all times specified within the port construction traffic management plan during the construction of the authorised project.
  • (4) The port travel plan must be implemented as approved at all times specified within the port travel plan during the operation of the authorised project.
  • (5) For the purposes of this requirement—
  • “relevant planning authority” and “relevant highway authority” mean—in respect of sub-paragraph (1), the planning or highway authority or authorities in whose area the relevant construction port is located; andin respect of sub-paragraph (2), the planning or highway authority or authorities in whose area the relevant operation port is located;
  • “construction port” or “ports” means a port or ports situated in England and/or Wales and used for construction of the authorised project; and
  • “operation port” or “ports” means a port or ports situated in England and/or Wales and used by management personnel for the ongoing operational management of the authorised project.

Decommissioning of relevant landfall works

37

  • (1) After a period of 24 years but before the expiration of a period of 25 years following completion of construction of the relevant landfall works, the undertaker must submit a report to the relevant planning authority detailing the following—
  • (a) the extent of coastal retreat experienced following completion of construction;
  • (b) whether any remedial works or mitigation measures to protect the relevant landfall works from coastal retreat have been required during this period, what these works comprised and an assessment of their impacts on coastal processes;
  • (c) the length of the anticipated remaining operational lifespan of the authorised project;
  • (d) the extent of the likely coastal retreat during the timeframe of the anticipated remaining operational lifespan of the authorised project and the likely need for, and nature of, any proposed remedial works or mitigation measures to protect the relevant landfall works from coastal retreat and an analysis of their predicted impact on coastal processes; and
  • (e) any proposed remedial works or mitigation measures identified under sub-paragraph (d).
  • (2) If it cannot be demonstrated to the reasonable satisfaction of the relevant planning authority that, taking into account any proposals for such remedial works or mitigation measures, the relevant landfall works will not have a significant impact on coastal processes then the relevant landfall works must be decommissioned in accordance with Requirement 30 (onshore decommissioning).
  • (3) For the purposes of this requirement—
  • “the relevant landfall works” means Work No. 6, to the extent that the works are landward of mean low water springs, and Work No. 8.

Restriction on carrying out grid connection works where consented in another order

38

  • (1) Where any part of the grid connection works are being or have been constructed under another development consent order, that part of the grid connection works must not be constructed under this Order.
  • (2) Work No. 34 must not—
  • (a) be constructed more than once under this Order;
  • (b) be constructed under this Order if it is being or has been constructed under another development consent order.

Requirement for written approval

39

Where under any of the above requirements the approval or agreement of the Secretary of State, the relevant planning authority or another person is required, that approval or agreement must be given in writing.

Amendments to approved details

40

  • (1) With respect to any requirement which requires the authorised project to be carried out in accordance with the details approved by the relevant planning authority or another person, the approved details must be carried out as approved unless an amendment or variation is previously approved in writing by the relevant planning authority or that other person in accordance with sub-paragraph (2).
  • (2) Any amendments to or variations from the approved details must be in accordance with the principles and assessments set out in the environmental statement. Such agreement may only be given in relation to immaterial changes where it has been demonstrated to the satisfaction of the relevant planning authority or that other person that the subject matter of the agreement sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
  • (3) The approved details must be taken to include any amendments that may subsequently be approved in writing by the relevant planning authority or that other person.

Operational drainage management plan

41

  • (1) No part of Work Nos. 30, 34, 38 or 41 may commence until an operational drainage management plan in respect of that part (which accords with the outline operational drainage management plan) and includes provision for the maintenance of any measures identified, has been submitted to and approved by the relevant lead local flood authority, in consultation with the relevant planning authority and the Environment Agency.
  • (2) The operational drainage management plan must be implemented as approved.

Installation of cable ducts

42

  • (1) In the event that the cables comprised within the East Anglia ONE North cable works are installed prior to the cables comprised within the East Anglia TWO cable works, the East Anglia TWO cable works may not subsequently be installed unless the cable ducts forming part of the East Anglia TWO cable works have been installed concurrently with the installation of the cables comprised within the East Anglia ONE North cable works.
  • (2) For the purposes of this requirement—
  • (a) “the East Anglia ONE North cable works” mean Work Nos. 6, 8, 9, 11, 12, 13, 16 to 23 and 26 of the East Anglia ONE North Order; and
  • (b) “the East Anglia TWO cable works” mean Work Nos. 6, 8, 9, 11, 12, 13, 16 to 23 and 26 of this Order.

Restriction on carrying out grid connection works

43

No part of the grid connection works may commence under this Order until either—

  • (a) the offshore works have commenced; or
  • (b) the undertaker has provided appropriate evidence to the Secretary of State demonstrating its commitment to commence the authorised development described within paragraph 1 of Schedule 1, Part 1 and the Secretary of State has confirmed that the grid connection works may commence.

Control of development during operational phase

44

  • (1) During the operation of and within operational land related to Work No. 30 and Work No. 41, any development in addition to that authorised in this Order that is permitted under Schedule 2 Part 15 Class B (d), (e) or (f) of the General Permitted Development Order 2015 (“electricity undertakings permitted development”) or any equivalent successor provision is subject to the following conditions—
  • (2) In respect of operational drainage—
  • (a) No electricity undertakings permitted development may commence until an amendment to the operational drainage management plan approved pursuant to requirement 41 that includes provision for the replacement of any existing drainage measures to be removed and maintenance of any new drainage measures to be provided as part of the permitted development, has been submitted to and approved by the relevant lead local flood authority, in consultation with the relevant planning authority and the Environment Agency; and
  • (b) The measures in the amendment to the operational drainage management plan in respect of the permitted development must be implemented as approved.
  • (3) In respect of the provision, implementation and maintenance of landscaping—
  • (a) No electricity undertakings permitted development may commence until an amendment to the written landscape management plan and associated work programme approved pursuant to requirement 14 that includes provision for the replacement of any existing landscape measures to be removed and maintenance of any new landscape measures to be provided as part of the permitted development, has been submitted to and approved by the relevant planning authority; and
  • (b) The measures in the amendment to the written landscape management plan and associated work programme plan in respect of the permitted development must be implemented as approved.

SCHEDULE 2 — Streets subject to street works

(1) (2)
Area Street subject to street works
District of East Suffolk Public right of way footpath E-106/020/0 between reference points 1a and 1b on sheet 1 of 12 of the works plans.
District of East Suffolk Private track / public right of way footpath E-106/025/0 between reference points 2a and 2b on sheet 2 of 12 of the works plans.
District of East Suffolk SIZEWELL GAP between reference points 3a and 3b on sheet 3 of 12 of the works plans.
District of East Suffolk SIZEWELL GAP between reference points 3c and 3d on sheet 3 of 12 of the works plans.
District of East Suffolk Public right of way bridleway E-363/026/0 between reference points 3e and 3f and between points 3g and 3h on sheet 3 of 12 of the works plans.
District of East Suffolk Public right of way footpath E-363/029/0 between reference points 3i and 3j on sheet 3 of 12 of the works plans.
District of East Suffolk Public right of way footpath E-363/024/0 between reference points 3k and 3l on sheet 3 of 12 of the works plans.
District of East Suffolk Public right of way footpath E-363/023/0 between reference points 3m and 3n on sheet 3 of 12 of the works plans.
District of East Suffolk Public right of way footpath E-363/022/0 between reference points 3o and 3p on sheet 3 of 12 of the works plans.
District of East Suffolk Public right of way bridleway E-363/027/0 between reference points 3q and 3r on sheet 3 of 12 of the works plans.
District of East Suffolk Public right of way bridleway E-363/015/0 between reference points 4a and 4b on sheet 4 of 12 of the works plans.
District of East Suffolk Public rights of way footpath E-363/014/0 between reference points 4a and 4c on sheet 4 of 12 of the works plans.
District of East Suffolk Public rights of way footpath E-363/014/A between reference points 4d and 4e on sheet 4 of 12 of the works plans.
District of East Suffolk THORPE ROAD between reference points 5a and 5b on sheet 5 of 12 of the works plans.
District of East Suffolk Public right of way footpath E-106/065/0 between reference points 5c and 5d on sheet 5 of 12 of the works plans.
District of East Suffolk ALDEBURGH ROAD between reference points 5e and 5f on sheet 5 of 12 of the works plans.
District of East Suffolk Public right of way footpath E-260/030/0 between reference points 5g and 5h on sheet 5 of 12 of the works plans.
District of East Suffolk Public right of way footpath E-260/007/0 between reference points 5i and 5j on sheet 5 of 12 of the works plans.
District of East Suffolk Public right of way footpath E-260/009/0 between reference points 5k and 5l on sheet 5 of 12 of the works plans.
District of East Suffolk SLOE LANE between reference points 6a and 6b on sheet 6 of 12 of the works plans.
District of East Suffolk B1069 (SNAPE ROAD) between reference points 6c and 6d on sheet 6 of 12 on the works plans.
District of East Suffolk Public right of way bridleway E-354/020/0 between reference points 6e and 6f on sheet 6 of 12 of the works plans.
District of East Suffolk Public right of way bridleway E-354/036/0 between reference points 6g and 6h on sheet 6 of 12 of the works plans.
District of East Suffolk Public right of way bridleway E-354/001/0 between reference points 6i and 6j on sheet 6 of 12 of the works plans; and between reference points 8g and 8h on sheet 8 of 12 of the works plans.
District of East Suffolk Public right of way footpath E-354/003/0 between reference points 6k and 6l on sheet 6 of 12 of the works plans.
District of East Suffolk GROVE ROAD between reference points 7a and 7b on sheet 7 of 12 on the works plans.
District of East Suffolk CHURCH ROAD between reference points 7f and 7j on sheet 7 of 12 on the works plans.
District of East Suffolk Public right of way footpath E-354/007/0 between reference points 7c and 7d on sheet 7 of 12 on the works plans.
District of East Suffolk Public right of way footpath E-354/006/0 between reference points 7e and 8a on sheet 7 of 12 on the works plans.
District of East Suffolk Public right of way footpath E-260/017/0 between reference points 7f and 7g on sheet 7 of 12 on the works plans.
District of East Suffolk Public right of way footpath E-260/017/0 between reference points 7h and 7i on sheet 7 of 12 on the works plans.
District of East Suffolk Public right of way footpath E-354/008/0 between reference points 8a and 8b on sheet 8 of 12 on the works plans.
District of East Suffolk GROVE ROAD between reference points 8c and 8d on sheet 8 of 12 on the works plans.
District of East Suffolk Public right of way footpath E-354/007/A between reference points 8e and 8f on sheet 8 of 12 on the works plans.
District of East Suffolk B1121 (SAXMUNDHAM ROAD) between reference points 9a and 9b on sheet 9 of 12 on the works plans.
District of East Suffolk B1121 (SAXMUNDHAM ROAD) between reference points 9b and 9c on sheet 9 of 12 on the works plans.
District of East Suffolk Public right of way footpath E-260/016/0 between reference points 9d and 9e on sheet 9 of 12 on the works plans.
District of East Suffolk A1094 (FARNHAM ROAD) between reference points 10a and 10d on sheet 10 of 12 on the works plans.
District of East Suffolk A1094 (ALDEBURGH ROAD) between reference points 10b and 10d on sheet 10 of 12 on the works plans.
District of East Suffolk B1121 (ALDEBURGH ROAD) between reference points 10c and 10d on sheet 10 of 12 on the works plans.
District of East Suffolk B1069 (SNAPE ROAD) between reference points 10e and 10f on sheet 10 of 12 on the works plans.
District of East Suffolk A12 (MAIN ROAD) between reference points 11a and 11b on sheet 11 of 12 on the works plans.
District of East Suffolk A1094 (FRIDAY STREET) between reference points 11c and 11d on sheet 11 of 12 on the works plans.
District of East Suffolk A12 (MAIN ROAD) between reference points 12a and 12b on sheet 12 of 12 on the works plans.
District of East Suffolk Public right of way footpath E-387/009/0 between reference points 12c and 12d on sheet 12 of 12 on the works plans.

SCHEDULE 3 — Public rights of way to be temporarily stopped up

(1) (2) (3) (4)
Area Public right of way to be temporarily stopped up Extent of temporary stopping up Temporary public right of way to be substituted
District of East Suffolk Byway open to all traffic reference 1 (E-106/020/0) Approximately 120m of the existing byway open to all traffic reference 1 (E-106/020/0) between the points marked L-1 and L-2 on sheet 1 of 12 of the temporary stopping up of public rights of way plan shown with a dashed pink line. Approximately 646m of proposed byway open to all traffic reference TEMP1 between the points marked L-1 and L-2 on sheet 1 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Byway open to all traffic reference 2 (E-106/025/0) Approximately 66m of the existing byway open to all traffic reference 2 (E-106/025/0) between the points marked CS1-1 and CS1-2 on sheet 2 of 12 of the temporary stopping up of public rights of way plan shown with a dashed pink line. Approximately 236m of proposed byway open to all traffic reference TEMP2a, or approximately 360m of proposed byway open to all traffic reference TEMP2b between the points CS1-1 and CS1-2 on sheet 2 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Bridleway reference 3 (E-363/026/0) Approximately 73m of the existing bridleway reference 3 (E-363/026/0) between the points marked CS1-3 and CS1-4 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a dashed green line. Approximately 339m of proposed bridleway reference TEMP3 between the points marked CS1-3 and CS1-4 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Bridleway reference 4 (E-363/026/0) Approximately 345m of the existing bridleway reference 4 (E-363/026/0) between the points marked CS2-1 and CS2-2 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a dashed blue line. Approximately 578m of proposed bridleway reference TEMP4a between the points marked CS2-1 and CS2-2 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority. Approximately 780m of proposed bridleway reference TEMP4b between the points marked CS2-1 to CS2-7 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 5 (E-363/024/0) Approximately 739m of the existing footpath reference 5 (E-363/024/0) between the points marked CS2-3 and CS2-4 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 806m of proposed footpath reference TEMP5 between the points marked CS2-3 and CS2-4 or approximately 1146m of proposed footpath reference TEMP6b, TEMP6a, TEMP8 and TEMP7 between the points marked CS2-3 and CS2-4 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 6 (E-363/029/0) Approximately 88m of the existing footpath reference 6 (E-363/029/0) between the points marked CS2-5 and CS2-6 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 531m of proposed footpath reference TEMP4b and TEMP6b between the points marked CS2-5 and CS2-6 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 7 (E-363/023/0) Approximately 298m of the existing footpath reference 7 (E-363/023/0) between the points marked CS2-7 and CS2-8 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 497m of proposed footpath reference TEMP7 between the points marked CS2-7 and CS2-8 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 8 (E-363/022/0) Approximately 684m of the existing footpath reference 8 (E-363/022/0) between the points marked CS2-9 and CS2-12 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 537m of proposed footpath reference TEMP8 and TEMP7 between the points marked CS2-9 and CS2-12 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Bridleway reference 9 (E-363/027/0) Approximately 31m of the existing bridleway reference 9 (E-363/027/0) between the points marked CS2-10 and CS2-11 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a dashed green line. Approximately 98m of proposed footpath reference TEMP9 between the points marked CS2-10 and CS2-11 on sheet 3 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Bridleway reference 10 (E-363/015/0) Approximately 199m of the existing bridleway reference 10 (E-363/015/0) between the points marked CS2-13 and CS2-14 on sheet 4 of 12 of the temporary stopping up of public rights of way plan shown with a dashed green line. Approximately 216m of proposed bridleway reference TEMP10a or approximately 359m of proposed bridleway reference TEMP10b between the points marked CS2-13 and CS2-14 on sheet 4 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 11 (E-363/014/0) Approximately 66m of the existing footpath reference 11 (E-363/014/0) between the points marked CS2-15 and CS2-16 on sheet 4 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 288m of proposed footpath reference TEMP11 between the points marked CS2-15 and CS2-16 on sheet 4 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 12 (E-363/014/A) Approximately 106m of the existing footpath reference 12 (E-363/014/A) between the points marked CS2-17 and CS2-18 on sheet 4 of 12 of the temporary stopping up of public rights of way plan. shown with a dashed yellow line. Approximately 347m of proposed footpath reference TEMP12a or approximately 409m of proposed footpath reference TEMP12b between the points marked CS2-17 and CS2-18 on sheet 4 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 13 (E-106/065/0) Approximately 70m of the existing footpath reference 13 (E-106/065/0) between the points marked CS2-19 and CS2-20 on sheet 5 of 12 of the temporary stopping up of public rights of way plan. shown with a dashed yellow line. Approximately 270m of proposed footpath reference TEMP13a or approximately 266m of proposed footpath reference TEMP13b between the points marked CS2-19 and CS2-20 on sheet 5 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 14 (E-260/030/0) Approximately 61m of the existing footpath reference 14 (E-260/030/0) between the points marked CS3-1 and CS3-2 on sheet 5 of 12 of the temporary stopping up of public rights of way plan. shown with a dashed yellow line. Approximately 321m of proposed footpath reference TEMP14 between the points marked CS3-1 and CS3-2 on sheet 5 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 15 (E-260/007/0) Approximately 239m of the existing footpath reference 15 (E-260/007/0) between the points marked CS3-3 and CS3-4 on sheet 5 of 12 of the temporary stopping up of public rights of way plan. shown with a dashed yellow line. Approximately 654m of proposed footpath reference TEMP15 between the points marked CS3-3 and CS3-4 on sheet 5 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 16 (E-260/009/0) Approximately 156m of the existing footpath reference 16 (E-260/009/0) between the points marked CS3-5 and CS3-6 on sheet 5 of 12 of the temporary stopping up of public rights of way plan. shown with a dashed yellow line. Approximately 577m of proposed footpath reference TEMP16a or approximately 418m of proposed footpath reference TEMP16b between the points marked CS3-5 and CS3-6 on sheet 5 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Bridleway reference 17 (E-354/020/0) Approximately 220m of the existing bridleway reference 17 (E-354/020/0) between the points marked CS4-1 and CS4-2 on sheet 6 of 12 of the temporary stopping up of public rights of way plan. shown with a dashed green line. Approximately 637m of proposed bridleway reference TEMP17/18 between the points marked CS4-5 and CS4-2 on sheet 6 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Bridleway reference 18 (E-354/036/0) Approximately 225m of the existing bridleway reference 18 (E-354/036/0) between the points marked CS4-3 and CS4-4 on sheet 6 of 12 of the temporary stopping up of public rights of way plan. shown with a dashed green line. Approximately 637m of proposed bridleway reference TEMP17/18 between the points marked CS4-5 and CS4-4 on sheet 6 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Bridleway reference 19 (E-354/001/0) Approximately 270m of the existing bridleway reference 19 (E-354/001/0) between the points marked CS4-6 and CS4-7 on sheet 6 of 12 of the temporary stopping up of public rights of way plan. shown with a dashed green line. Approximately 538m of proposed bridleway reference TEMP19a between the points marked CS4-6 and CS4-3 or approximately 337m of proposed bridleway reference TEMP19b between the points marked CS4-7 and CS4-10 on sheet 6 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 20 (E-354/003/0) Approximately 96m of the existing footpath reference 20 (E-354/003/0) between the points marked CS4-8 and CS4-9 on sheet 6 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 363m of proposed footpath reference TEMP20a or approximately 347m of proposed footpath reference TEMP20b between the points marked CS4-8 and CS4-9 on sheet 6 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 21 (E-354/007/0) Approximately 316m of the existing footpath reference 21 (E-354/007/0) between the points marked S-1 and S-2 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 395m of proposed footpath reference TEMP21 between the points marked S-1 and S-2 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 22 (E-354/006/0) Approximately 283m of the existing footpath reference 22 (E-354/006/0) between the points marked S-4 and S-22 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 337m of proposed footpath reference TEMP22 between the points marked S-22 and S-14 and approximately 559m of proposed footpath reference TEMP22 between the points marked S-15 and S-5 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 23 (E-354/006/0) Approximately 206m of the existing footpath reference 23 (E-354/006/0) between the points marked S-4 and S-5 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 421m of proposed footpath reference TEMP23a or approximately 691m of proposed footpath reference TEMP23b between points marked S-4 and S-5 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 24 (E-354/006/0) Approximately 208m of the existing footpath reference 24 (E-354/006/0) between the points marked S-22 and S-24 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 324m of proposed footpath reference TEMP22 between the points marked S-22 and S-14 and approximately 157m of proposed footpath reference TEMP24 between points marked S-24 and S-25 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 25 (E-354/006/0) Approximately 294m of the existing footpath reference 25 (E-354/006/0) between the points marked S-24 and S-3 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 442m of proposed footpath reference TEMP25 and TEMP21 between the points S-24 and S-3 on sheet 7 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 26 (E-354/007/A) Approximately 465m of the existing footpath reference 26 (E-354/007/A) between the points marked S-10 and S-11 on sheet 8 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 571m of proposed footpath reference TEMP26 between the points marked S-10 and S-11 on sheet 8 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Bridleway reference 27 (E-354/001/0) Approximately 207m of the existing bridleway reference 27 (E-354/001/0) between the points marked S-12 and S-13 on sheet 8 of 12 of the temporary stopping up of public rights of way plan shown with a dashed green line. Approximately 491m of proposed bridleway reference TEMP27 between the points marked S-12 and S-13 on sheet 8 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 28 (E-260/017/0) Approximately 169m of the existing footpath reference 28 (E-260/017/0) between the points marked S-20 and S-21 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 524m of proposed footpath reference TEMP28a between the points S-20 and S-21 or approximately 413m of proposed footpath reference TEMP28b between points S-20 and S-21 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 29 (E-260/017/0) Approximately 769m of the existing footpath reference 29 (E-260/017/0) between the points marked S-14 and S-15 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 1136m of proposed footpath reference TEMP22, TEMP28b and TEMP22/34 between the points marked S-14 and S-15 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 30 (E-354/008/0) Approximately 429m of the existing footpath reference 30 (E-354/008/0) between the points marked S-6 and S-7 on sheet 8 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 393m of proposed footpath reference TEMP30 between the points marked S-6 and S-7 on sheet 8 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 31 (E-260/016/0) Approximately 53m of the existing footpath reference 31 (E-260/016/0) between the points marked S-16 and S-17 on sheet 9 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 265m of proposed footpath reference TEMP31a or approximately 273m of proposed footpath reference TEMP31b between the points marked S-16 and S-17 on sheet 9 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 32 (E-260/017/0) Approximately 548m of the existing footpath reference 32 (E-260/017/0) between the points marked S-8 and S-14 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 937m of proposed footpath reference TEMP35 and TEMP22 between the points marked S-8 and S-14 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 33 (E-387/009/0) Approximately 45m of the existing footpath reference 33 (E-387/009/0) between the points marked HW-1 and HW-2 on sheet 12 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Approximately 56m of proposed footpath reference TEMP33 between the points marked HW-1 and HW-2 on sheet 12 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 34 (E/260/017/0) Approximately 294m of the existing footpath reference 34 (E-260/017/0) between the points marked S-15 and S-21 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a dashed yellow line. Temporary diversion of approximately 295m of proposed footpath reference TEMP22/34 between the points marked S-15 and S-21 on sheet 7 of 12 of the temporary stopping up of public rights of way plan shown with a black and white dashed line or as otherwise agreed with the relevant highway authority.

SCHEDULE 4 — Footpaths to be stopped up

(1) (2) (3) (4)
Area Footpath to be stopped up Extent of stopping up New footpath to be substituted
District of East Suffolk Footpath reference 35 (E-354/007/0) Approximately 87m of the existing footpath reference 35 (E-354/007/0) between the points marked S-1 and S-3; and approximately 38m of the existing footpath reference 35 (E-354/007/0) between the points marked S-4 and S-5 on sheet 7 of 12 of the permanent stopping up of public rights of way plan shown with a dashed yellow line. Approximately 89m of proposed footpath reference PERM35a between the points marked S-1 and S-3 on sheet 7 of 12 of the permanent stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority. Approximately 24m of proposed footpath reference PERM35b between the points marked S-4 and S-5 on sheet 7 of 12 of the permanent stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.
District of East Suffolk Footpath reference 36 (E-354/006/0) Approximately 693m of the existing footpath reference 36 (E-354/006/0) between points marked S-6 and S-8 on sheet 7 of 12 of the permanent stopping up of public rights of way plan shown with a dashed yellow line. Approximately 584m of proposed footpath reference PERM36a between the points marked S-1 and S-13 on sheet 7 of 12 of the permanent stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority. Approximately 761m of proposed footpath reference PERM36b between the points marked S-13 and S-8 on sheet 7 of 12 of the permanent stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority. Approximately 569m of proposed footpath reference PERM36c between the points marked S-8 and S-2 on sheet 7 of 12 of the permanent stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority. Approximately 157m of proposed footpath reference PERM36d between the points marked S-6 and S-7 on sheet 7 of 12 of the permanent stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority. Approximately 188m of proposed footpath reference PERM36e between the points marked S-9 and S-10 on sheet 7 of 12 of the permanent stopping up of public rights of way plan shown with a black and white dashed line or as otherwise agreed with the relevant highway authority.
District of East Suffolk Footpath reference 37 (E-260/017/0) Approximately 194m of the existing footpath reference 37 (E-260/017/0) between points marked S-11 and S-2 on sheet 7 of 12 of the permanent stopping up of public rights of way plan shown with a dashed yellow line. Approximately 198m of proposed footpath reference PERM37 between the points marked S-11 and S-12 on sheet 7 of 12 of the permanent stopping up of public rights of way plan shown with a black and white dashed line or as otherwise approved by the relevant highway authority.

SCHEDULE 5 — Streets to be temporarily stopped up

(1) (2) (3)
Area Street to be temporarily stopped up Extent of temporary stopping up, alteration or diversion
District of East Suffolk Private track Approximately 66m of private track as is within Work No.9 as shown between reference points 2a and 2b on sheet 2 of 12 of the works plans.
District of East Suffolk SIZEWELL GAP Approximately 480m of Sizewell Gap as is within Work No.10 as shown between reference points 3a and 3b on sheet 3 of 12 of the works plans.
District of East Suffolk SIZEWELL GAP Approximately 307m of Sizewell Gap as is within Work No.15 as shown between reference points 3c and 3d on sheet 3 of 12 of the works plans.
District of East Suffolk THORPE ROAD Approximately 164m of Thorpe Road as is within Work No.17 as shown between reference points 5a and 5b on sheet 5 of 12 of the works plans.
District of East Suffolk ALDEBURGH ROAD Approximately 93m of Aldeburgh Road as is within Work No.19 as shown between reference points 5e and 5f on sheet 5 of 12 of the works plans.
District of East Suffolk SLOE LANE Approximately 73m of Sloe Lane as is within Work No.23 as shown between reference points 6a and 6b on sheet 6 of 12 of the works plans.
District of East Suffolk B1069 (SNAPE ROAD) Approximately 88m of the B1069 (Snape Road) as is within Work No.26 as shown between reference points 6c and 6d on sheet 6 of 12 of the works plans.
District of East Suffolk GROVE ROAD Approximately 88m of Grove Road as is within Work No.26 as shown between reference points 7a and 7b on sheet 7 of 12 of the works plans.
District of East Suffolk CHURCH ROAD Approximately 105m of Church Road as is within Work No.33 as shown between reference points 7f and 7j on sheet 7 of 12 of the works plans.
District of East Suffolk GROVE ROAD Approximately 573m of Grove Road as is within Work No.43 as shown between reference points 8c and 8d on sheet 8 of 12 of the works plans.
District of East Suffolk B1121 (SAXMUNDHAM ROAD) Approximately 269m of the B1121 (Saxmundham Road) as is within Work No.43 as shown between reference points 9a and 9b on sheet 9 of 12 of the works plans.
District of East Suffolk B1121 (SAXMUNDHAM ROAD) Approximately 621m of the B1121 (Saxmundham Road) as is within Work No.34 as shown between reference points 9b and 9c on sheet 9 of 12 of the works plans.
District of East Suffolk A1094 (FARNHAM ROAD) Approximately 226m of the A1094 (Farnham Road) as is within Work No.35 as shown between reference points 10a and 10d on sheet 10 of 12 of the works plans.
District of East Suffolk A1094 (ALDEBURGH ROAD) Approximately 525m of the A1094 (Aldeburgh Road) as is within Work No.35 as shown between reference points 10b and 10d on sheet 10 of 12 of the works plans.
District of East Suffolk B1121 (ALDEBURGH ROAD) Approximately 84m of the B1121 (Aldeburgh Road) as is within Work No.35 as shown between reference points 10c and 10d on sheet 10 of 12 of the works plans.
District of East Suffolk B1069 (SNAPE ROAD) Approximately 197m of the B1069 (Snape Road) as is within Work No.35 as shown between reference points 10e and 10f on sheet 10 of 12 of the works plans.
District of East Suffolk A12 (MAIN ROAD) Approximately 680m of the A12 (Main Road) as is within Work No.36 as shown between reference points 11a and 11b on sheet 11 of 12 of the works plans.
District of East Suffolk A1094 (FRIDAY STREET) Approximately 469m of the A1094 (Friday Street) as is within Work No.36 as shown between reference points 11c and 11d on sheet 11 of 12 of the works plans.
District of East Suffolk A12 (MAIN ROAD) Approximately 84m of the A12 (Main Road) as is within Work No.37 as shown between reference points 12a and 12b on sheet 12 of 12 of the works plans.

SCHEDULE 6 — Access to works

(1) (2)
Area Description of Access
District of East Suffolk Vehicular access to the south from Sizewell Gap and marked at point AC1 on sheet 3 of 12 of the access to works plan.
District of East Suffolk Vehicular access to the south from Sizewell Gap and marked at point AC2 on sheet 3 of 12 of the access to works plan.
District of East Suffolk Vehicular access to the east and west from Aldeburgh Road and marked at point AC3 on sheet 5 of 12 of the access to works plan.
District of East Suffolk Vehicular access to the west from Snape Road and marked at point AC4 on sheet 6 of 12 of the access to works plan.
District of East Suffolk Vehicular access to the northeast from Saxmundham Road and marked at point AC5 on sheet 9 of 12 of the access to works plan.

SCHEDULE 7 — Land in which only new rights etc. may be acquired

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.