The East Anglia TWO Offshore Wind Farm Order 2022

Type Statutory-Instrument
Publication 2022-03-31
Last updated 2022-12-22
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API

2

  • (1) In relation to any application to which this Schedule applies, the discharging authority has the right to request such further information from the undertaker as is reasonably necessary to enable it to consider the application.
  • (2) If the discharging authority considers such further information to be necessary it must, as soon as reasonably practicable and within 20 business days of receipt of the application notify the undertaker in writing specifying the further information required.
  • (3) If the discharging authority does not give such notification as specified in sub-paragraph (2) it is to be deemed to have sufficient information to consider the application and is not subsequently entitled to request further information without the prior agreement of the undertaker.
  • (4) A discharging authority may request further information under sub-paragraph (1) on more than one occasion provided that all such requests are made within the period specified by sub-paragraph (2).

Appeals

3

  • (1) The undertaker may appeal to the Secretary of State in the event that—
  • (a) the discharging authority refuses an application for any consent, agreement or approval required or contemplated by a requirement contained within Part 3 of Schedule 1 (requirements) to this Order or grants it subject to conditions to which the undertaker objects;
  • (b) the discharging authority does not give notice of its decision to the undertaker within the decision period specified in paragraph 1 (applications made for certain approvals);
  • (c) on receipt of a request for further information under paragraph 2 (further information) the undertaker considers that either the whole or part of the specified information requested by the discharging authority is not necessary for consideration of the application; or
  • (d) on receipt of any further information requested, the discharging authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application.
  • (2) The appeal process is as follows—
  • (a) the undertaker must submit the appeal documentation to the Secretary of State, which must include a copy of the application submitted to the discharging authority and any supporting documentation which the undertaker may wish to provide;
  • (b) the undertaker must on the same day provide copies of the appeal documentation to the discharging authority and the relevant consultees (if applicable);
  • (c) as soon as is practicable after receiving the appeal documentation, but in any event within 28 business days of receiving the appeal documentation, the Secretary of State must appoint a person to determine the appeal (“the appointed person”) and must notify the appeal parties of the identity of the appointed person and the address to which all correspondence for that person’s attention should be sent;
  • (d) the discharging authority and the relevant consultees must submit written representations to the appointed person in respect of the appeal within 20 business days of the date on which the appeal parties are notified of the appointment of a person under sub-paragraph (c) and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;
  • (e) the appeal parties shall make any counter-submissions to the appointed person within 20 business days of receipt of written representations pursuant to sub-paragraph (d) above.
  • (3) The appointed person must make a decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable and within 40 business days of—
  • (a) the deadline within sub-paragraph (2)(e); or
  • (b) the deadline for written submissions in respect of further information submitted in accordance with sub-paragraph (5),

whichever is later.

  • (4) If the appointed person considers that further information is necessary to enable consideration of the appeal the appointed person must, as soon as practicable, and within 10 business days of the deadline for submissions in accordance with sub-paragraph (2)(e), or where further information has already been requested, within 10 business days of the deadline for written submissions in accordance sub-paragraph (5), notify the appeal parties in writing specifying the further information required, the appeal party from whom the information is sought, and the date by which the information is to be submitted.
  • (5) Any further information required under sub-paragraph (4) is to be provided by the party from whom the information is sought to the appointed person and to other appeal parties by the date specified by the appointed person. Any written representations concerning matters contained in the further information must be submitted to the appointed person, and made available to all appeal parties within 10 business days of that date.
  • (6) On an appeal under this paragraph, the appointed person may—
  • (a) allow or dismiss the appeal; or
  • (b) reverse or vary any part of the decision of the discharging authority (whether the appeal relates to that part of it or not), and may deal with the application as if it had been made to the appointed person in the first instance.
  • (7) The appointed person may proceed to a decision even though no written representations have been made within those time limits if it appears to the appointed person that there is sufficient material to enable a decision to be made.
  • (8) The decision of the appointed person on an appeal is to be final and binding on the appeal parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review.
  • (9) If an approval is given by the appointed person under this Schedule, it is deemed to be an approval for the purpose of any consent, agreement or approval required under Part 3 of Schedule 1 (requirements) as if it had been given by the discharging authority.
  • (10) Except where a direction is given under sub-paragraph (11) requiring the costs of the appointed person to be paid by the discharging authority, the reasonable costs of the appointed person are to be met by the undertaker.
  • (11) On application by the discharging authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction and the terms on which it is to be made, the appointed person must have regard to Planning Practice Guidance on the award of costs or any circular or guidance which may from time to time replace it.

Interpretation of Schedule 16

4

In this Schedule—

  • the appeal parties” means the discharging authority, the undertaker and any relevant consultees.
  • business day” means a day other than Saturday or Sunday which is not Christmas Day, Good Friday or a bank holiday under section 1 of the Banking and Financial Dealings Act 1971;
  • discharging authority” means the body responsible for giving consent, agreement or approval pursuant to a requirement within Part 3 of Schedule 1 (requirements) to this Order;
  • relevant consultee” means any body named in a requirement which is required to be consulted by the discharging authority in discharging that requirement.

SCHEDULE 17 — Documents to be certified

PART 1 — Documents forming the environmental statement to be certified

(1) (2) (3) (4) (5)
Document Reference(and relevant ES Chapters) Examination Library Reference(and relevant ES Chapter reference) Document Name Version Date
6.1 APP-049 to APP-079 Environmental Statement 1 25th October 2019
6.2 APP-080 to APP-441 Figures 1 25th October 2019
6.3 APP-442 to APP-571 Technical Appendices 1 25th October 2019
ExA.WQ-1.A10.D1.V1(Chapter 6) REP1-099(APP-054) Applicants’ Responses to WQ1 Appendix 10 Landfall Indicative HDD Working Area 1 Deadline 12nd November 2020
ExA.WQ-1.A11.D1.V1(Chapter 6) REP1-100(APP-054) Applicants’ Responses to WQ1 Appendix 11 Landfall HDD Cross Sections 1 Deadline 12nd November 2020
ExA.AS-13.D6.V1(Chapter 6) REP6-024(APP-054) HDD Verification Clarification Note 1 Deadline 624th February 2021
ExA.WQ-1.A6.D1.V1(Chapter 6) REP1-090(APP-054) Applicants’ Responses to WQ1 Appendix 6 Illustrative Open Trench and Trenchless Onshore Cable Route 1 Deadline 12nd November 2020
ExA.WQ-1.A7.D1.V1(Chapter 6) REP1-091(APP-054) Applicants’ Responses to WQ1 Appendix 7 Onshore Crossing Schedule 1 Deadline 12nd November 2020
ExA.AS-10.D3.V1(Chapter 6) REP3-056(APP-054) Onshore Cable Route Works Programme Clarification Note 1 Deadline 315th December 2020
ExA.AS-11.D3.V1(Chapter 6)(Chapter 29) REP3-057(APP-054)(APP-077) Onshore Substations Update Clarification Note 1 Deadline 315th December 2020
ExA.AS-12.D3.V1(Chapter 6) REP3-058(APP-054) Construction in Proximity to Properties 1 Deadline 315th December 2020
6.3.6.2(Chapter 6) REP8-015(APP-054) EA2 Environmental Statement Appendix 6.2 Relationship of Onshore Plans Secured by the DCO 5 Deadline 825th March 2021
6.3.6.3(Chapter 6) REP8-016(APP-054) EA2 Environmental Statement Appendix 6.3 Relationship of Offshore Plans Secured by the DCO 5 Deadline 825th March 2021
6.3.6.4(Chapter 6) REP3-020(APP-054) EA2 Environmental Statement Appendix 6.4 Cumulative Project Description 2 Deadline 315th December 2020
ExA.RRA6.D0.V1(Chapters 7 to 17) AS-043(APP-055 to APP-065) Applicant’s Comments on Relevant Representations ... Appendix 6 Disposal Site Locations (Windfarm Site) 1 11th June 2020
ExA.RRA2.D0.V1(Chapter 7) AS-039(APP-055) Applicant’s Comments on Relevant Representations ... Appendix 2 Wave Climatology Clarification Note 1 11th June 2020
ExA.AS-13.D3.V1(Chapter 7)(Chapter 9)(Chapter 10)(Chapter 12) REP3-059(APP-055)(APP-057)(APP-058)(APP-060) Effects on Supporting Habitats of Outer Thames Estuary SPA Clarification Note 1 Deadline 315th December 2020
ExA.RRA3.D0.V1(Chapter 10) AS-040(APP-058) Applicant’s Comments on Relevant Representations ... Appendix 3 Fish and Shellfish Ecology Clarification Note 1 11th June 2020
ExA.AS-5.D11.V2(Chapter 11) REP11-045 (APP-059) Underwater Noise Modelling Report Update 2 Deadline 117th June 2021
ExA.AS-3.D2.V1(Chapter 12) REP2-006(APP-060) Cumulative Auk Displacement and Seabird Assemblage Assessment of FFC SPA and Gannet PVA 1 Deadline 217th November 2020
ExA.AS-2.D11.V5 (Chapter 12) REP11-026(APP-060) Displacement of red-throated divers in the Outer Thames Estuary SPA 5 Deadline 117th June 2021
ExA.AS-20.D1.V1(Chapter 19)(Chapter 26) REP1-040(APP-067)(APP-074) Deadline 1 Air Quality Clarification Note 1 Deadline 12nd November 2020
ExA.AS-16.D3.V1(Chapter 19) REP3-061(APP-067) Deadline 3 Air Quality Clarification Note 1 Deadline 315th December 2020
ExA.WQ-1.A8.D1.V1(Chapter 20) REP1-092(APP-068) Applicants’ Responses to WQ1 Appendix 8 Environment Agency Flood Zones 1 Deadline 12nd November 2020
ExA.AS-9.D4.V2(Chapter 20) REP4-044(APP-068) Clarification Note SuDS Infiltration Note 2 Deadline 413th January 2021
ExA.AS-12.D6.V1(Chapter 18)(Chapter 20) REP6-021(APP-066)(APP-068) Landfall Hydrogeological Risk Assessment 1 Deadline 624th February 2021
ExA.AS-13.D8.V1(Chapter 20) REP8-038(APP-068) Flood Risk and Drainage Clarification Note 1 Deadline 825th March 2021
ExA.AS-11.D1.V1(Chapter 21) REP1-022(APP-069) Land Use Clarification Note 1 Deadline 12nd November 2020
ExA.WQ-1.A4.D1.V1(Chapter 22) REP1-088(APP-070) Applicants’ Responses to WQ1 Appendix 4 Ecological Mitigation Works 1 Deadline 12nd November 2020
ExA.AS-12.D1.V1(Chapter 22) REP1-023(APP-070) Onshore Ecology Clarification Note 1 Deadline 12nd November 2020
ExA.AS-16.D1.V1(Chapter 22) REP1-035(APP-070) Ecological Enhancement Clarification Note 1 Deadline 12nd November 2020
ExA.AS-14.D3.V1(Chapter 22) REP3-060(APP-070) Deadline 3 Onshore Ecology Clarification Note 1 Deadline 315th December 2020
ExA.AS-10.D4.V1(Chapter 22) REP4-005(APP-070) Deadline 4 Onshore Ecology Clarification Note 1 Deadline 413th January 2021
ExA.AS-14.D6.V1(Chapter 22) REP6-025(APP-070) Deadline 6 Onshore Ecology Clarification Note 1 Deadline 624th February 2021
ExA.AS-28.D6.V1(Chapter 22) REP6-035(APP-070) Ecology Survey Results: February 2021 1 Deadline 624th February 2021
ExA.AS-16.D8.V1(Chapter 22) REP8-041(APP-070) Ecological Enhancement Clarification Note Addendum 1 Deadline 825th March 2021
ExA.AS-10.D1.V1(Chapter 24)(Chapter 29) REP1-021(APP-072)(APP-077) Archaeology and Cultural Heritage Clarification Note 1 Deadline 12nd November 2020
ExA.AS-13.D1.V1(Chapter 24) REP1-024(APP-072) Pre-Construction Trial Trenching Report 1 Deadline 12nd November 2020
ExA.AS-14.D1.V1(Chapter 24) REP1-025 to REP1-033(APP-072) Onshore Archaeology Geophysical Survey Report (Parts 1 to 9) 1 Deadline 12nd November 2020
ExA.AS-15.D1.V1(Chapter 24) REP1-034(APP-072) Onshore Archaeology Earthworks Report 1 Deadline 12nd November 2020
ExA.AS-29.D8.V1(Chapter 24) REP8-063(APP-072) Cultural heritage Viewpoint 5 Additional Visualisation 1 Deadline 825th March 2021
ExA.AS-16.D3.V1(Chapter 24) (Chapter 29) REP3-062 to REP3-068(APP-072)(APP-077) Updated Photomontages Clarification Note 1 Deadline 315th December 2020
ExA.AS-11.D4.V1(Chapter 24) REP4-006(APP-072) Heritage Assessment Addendum 1 Deadline 413th January 2021
ExA.AS-11.D4.V1_001(Chapter 24) REP4-007(APP-072) Heritage Assessment Addendum Appendix 1 CHVP2 –PRoW between Friston Hall and Friston (Appendix 24.7, Figure 7 Update) 1 Deadline 413th January 2021
ExA.AS-11.D4.V1_002(Chapter 24) REP4-008(APP-072) Heritage Assessment Addendum Appendix 2 CHVP3 – PRoW between Moor Farm and Little Moor Farm (Appendix 24.7, Figure 8 Update) 1 Deadline 413th January 2021
ExA.AS-11.D4.V1_003(Chapter 24) REP4-009(APP-072) Heritage Assessment Addendum Appendix 3 CHVP4 – PRoW to east of Little Moor Farm (Appendix 24.7, Figure 9 Update) 1 Deadline 413th January 2021
ExA.AS-11.D4.V1_004(Chapter 24) REP4-010(APP-072) Heritage Assessment Addendum Appendix 4 CHVP5 – PRoW at Woodside Farm (Appendix 24.7, Figure 10 Update) 1 Deadline 413th January 2021
ExA.AS-11.D4.V1_005(Chapter 24) REP4-011(APP-072) Heritage Assessment Addendum Appendix 5 CHVP7 – Friston House (b) (Appendix 24.7, Figure 12 Update) 1 Deadline 413th January 2021
ExA.AS-11.D4.V1_006(Chapter 24) REP4-012(APP-072) Heritage Assessment Addendum Appendix 6 CHVP8 – Friston War Memorial (Appendix 24.7, Figure 13 Update) 1 Deadline 413th January 2021
ExA.AS-30.D11.V1(Chapter 24) REP11-075 Heritage Assessment GIS Addendum 1 Deadline 117th June 2021
ExA.AS-30.D11.V1_01(Chapter 24) REP11-076 Heritage Assessment GIS Addendum App 1 CHVP2 App 24.7 Fig 7 Update 1 Deadline 117th June 2021
ExA.AS-30.D11.V1_02(Chapter 24) REP11-077 Heritage Assessment GIS Addendum App 2 CHVP3 App 24.7 Fig 8 Update 1 Deadline 117th June 2021
ExA.AS-30.D11.V1_03(Chapter 24) REP11-078 Heritage Assessment GIS Addendum App 3 CHVP4 App 24.7 Fig 9 Update 1 Deadline 117th June 2021
ExA.AS-30.D11.V1_04 (Chapter 24) REP11-054 Heritage Assessment GIS Addendum App 4 CHVP5 App 24.7 Fig 10 Update 1 Deadline 117th June 2021
ExA.AS-30.D11.V1_05(Chapter 24) REP11-079 Heritage Assessment GIS Addendum App 5 CHVP7 App 24.7 Fig 12 Update 1 Deadline 117th June 2021
ExA.AS-30.D11.V1_06(Chapter 24) REP11-080 Heritage Assessment GIS Addendum App 6 CHVP8 App 24.7 Fig 13 1 Deadline 117th June 2021
ExA.AS-14.D8.V1(Chapter 25) REP8-039(APP-073) Applicants’ Position Statement on Noise 1 Deadline 825th March 2021
ExA.AS-8.D2.V1(Chapter 25) REP2-011(APP-073) Noise and Vibration Assessment Clarification Note 1 Deadline 217th November 2020
ExA.AS-8.D4.V1(Chapter 25) REP4-043(APP-073) Noise Modelling Clarification Note 1 Deadline 413th January 2021
ExA.WQ-1.A14.D1.V1(Chapter 26) REP1-103(APP-074) Applicants’ Responses to WQ1 Appendix 14 Junction Locations 1 Deadline 12nd November 2020
ExA.AS-8.D1.V1 (Chapter 26) REP1-048(APP-074) Traffic and Transport Clarification Note for Deadline 1 1 Deadline 12nd November 2020
ExA.AS-6.D6.V2(Chapter 26) REP6-043(APP-074) Sizewell C Cumulative Impact Assessment Note (Traffic and Transport) 2 Deadline 624th February 2021
ExA.AS-9.D3.V1(Chapter 26) REP3-055(APP-074) Traffic and Transport Clarification Note for Deadline 3 1 Deadline 315th December 2020
ExA.AS-26.D4.V1(Chapter 26) REP4-027(APP-074) Traffic and Transport Deadline 4 Clarification Note 1 Deadline 413th January 2021
ExA.AS-9.D1.V1(Chapters 27 to 30) REP1-049(APP-075 to APP-078) Public Rights of Way Clarification Note 1 Deadline 12nd November 2020
ExA.AS-5.D2.V1(Chapter 28)(Chapter 29) REP2-008(APP-076)(APP-077) Effects with Regard to the Statutory Purposes of the Suffolk Coast and Heaths Area of Outstanding Natural Beauty and Accordance with NPS Policy 1 Deadline 217th November 2020
ExA.AS-33.D8.V1(Chapter 28) REP8-075(APP-076) Landscape and Visual: Sizewell C Cumulative Impact Assessment 1 Deadline 825th March 2021
ExA.WQ-1.A9.7.D1.V1(Chapter 29) REP1-093(APP-077) Applicants’ Responses to WQ1 Appendix 9.7 EA2 Annotated Viewpoint 1 1 Deadline 12nd November 2020
ExA.WQ-1.A9.8.D1.V1(Chapter 29) REP1-094(APP-077) Applicants’ Responses to WQ1 Appendix 9.8 EA2 Annotated Viewpoint 2 1 Deadline 12nd November 2020
ExA.WQ-1.A9.9.D1.V1(Chapter 29) REP1-095(APP-077) Applicants’ Responses to WQ1 Appendix 9.9 EA2 Annotated Viewpoint 3 1 Deadline 12nd November 2020
ExA.WQ-1.A9.10.D1.V1(Chapter 29) REP1-096(APP-077) Applicants’ Responses to WQ1 Appendix 9.10 EA2 Annotated Viewpoint 4 1 Deadline 12nd November 2020
ExA.WQ-1.A9.11.D1.V1(Chapter 29) REP1-097(APP-077) Applicants’ Responses to WQ1 Appendix 9.11 EA2 Annotated Viewpoint 5 1 Deadline 12nd November 2020
ExA.WQ-1.A9.12.D1.V1(Chapter 29) REP1-098(APP-077) Applicants’ Responses to WQ1 Appendix 9.12 EA2 Annotated Viewpoint 8 1 Deadline 12nd November 2020
ExA.AS-7.D2.V1(Chapter 29) REP2-010(APP-077) Sizewell C Cumulative Impact Assessment Note (Landscape and Visual) 1 Deadline 217th November 2020
ExA.AS-3.D4.V1(Chapter 29) REP4-031(APP-077) Landscape and Visual Impact Assessment Addendum 1 Deadline 413th January 2021
ExA.AS-3.D4.V1_001(Chapter 29) REP4-032(APP-077) Landscape and Visual Impact Assessment Addendum Appendix 1 Viewpoint 1 – Public Right of Way (PRoW) near Friston House (Figure 29.13 Update) 1 Deadline 413th January 2021
ExA.AS-3.D4.V1_002(Chapter 29) REP4-033(APP-077) Landscape and Visual Impact Assessment Addendum Appendix 2 Viewpoint 2 – Friston, Church Road (Figure 29.14 Update) 1 Deadline 413th January 2021
ExA.AS-3.D4.V1_003(Chapter 29) REP4-034(APP-077) Landscape and Visual Impact Assessment Addendum Appendix 3 Viewpoint 3 – Grove Road, near Pear Tree Farm (Figure 29.15 Update) 1 Deadline 413th January 2021
ExA.AS-3.D4.V1_004(Chapter 29) REP4-035(APP-077) Landscape and Visual Impact Assessment Addendum Appendix 4 Viewpoint 4 – Grove Road, near Church Road (Friston) (Figure 29.16 Update) 1 Deadline 413th January 2021
ExA.AS-3.D4.V1_005(Chapter 29) REP4-036(APP-077) Landscape and Visual Impact Assessment Addendum Appendix 5 Viewpoint 5 – PRoW near Moor Farm (Figure 29.17 Update) 1 Deadline 413th January 2021
ExA.AS-3.D4.V1_006(Chapter 29) REP4-037(APP-077) Landscape and Visual Impact Assessment Addendum Appendix 6 Viewpoint 6 – Friston, Village Green (Figure 29.18 Update) 1 Deadline 413th January 2021
ExA.AS-3.D4.V1_007(Chapter 29) REP4-038(APP-077) Landscape and Visual Impact Assessment Addendum Appendix 7 Viewpoint 8 – Saxmundham Road (North of Friston) (Figure 29.20 Update) 1 Deadline 413th January 2021
ExA.AS-3.D4.V1_008(Chapter 29) REP4-039(APP-077) Landscape and Visual Impact Assessment Addendum Appendix 8 Viewpoint 9 – B1121 Aldeburgh Road, south of Friston (Figure 29.21 Update) 1 Deadline 413th January 2021
ExA.AS-6.D7.V1(Chapter 29) REP7-062(APP-077) Updated Figure 29.37- Viewpoint 5 Public Rights of Way, near Moor Farm (with National Grid GIS Substation) 1 Deadline 74th March 2021
ExA.AS-28.D8.V1_01(Chapter 29) REP8-055(APP-077) National Grid GIS Substation Photomontages: Figure 29.13 Update Viewpoint 1 Public Rights of Way near Friston House 1 Deadline 825th March 2021
ExA.AS-28.D8.V1_02(Chapter 29) REP8-056(APP-077) National Grid GIS Substation Photomontages: Figure 29.14 Update Viewpoint 2 Friston, Church Road 1 Deadline 825th March 2021
ExA.AS-28.D8.V1_03(Chapter 29) REP8-057(APP-077) National Grid GIS Substation Photomontages: Figure 29.17 Update Viewpoint 5 Public Rights of Way, near Moor Farm 1 Deadline 825th March 2021
ExA.AS-28.D8.V1_04(Chapter 29) REP8-058(APP-077) National Grid GIS Substation Photomontages: Figure 29.20 UpdateViewpoint 8 Saxmundham Road (North of Friston) 1 Deadline 825th March 2021
ExA.AS-28.D8.V1_05(Chapter 29) REP8-059(APP-077) National Grid GIS Substation Photomontages: Figure 29.21 Update Viewpoint 9: B1121 Aldeburgh Road (south of Friston) 1 Deadline 825th March 2021
ExA.AS-28.D8.V1_06(Chapter 29) REP8-060(APP-077) National Grid GIS Substation Photomontages: CHVP3 – PRoW between Moor Farm and Little Moor Farm (Appendix 24.7, Figure 8-Update) 1 Deadline 825th March 2021
ExA.AS-28.D8.V1_07(Chapter 29) REP8-061(APP-077) National Grid GIS Substation Photomontages: CHVP4 – PRoW to east of Little Moor Farm (Appendix 24.7, Figure 9-Update) 1 Deadline 825th March 2021
ExA.AS-28.D8.V1_08(Chapter 29) REP8-062(APP-077) National Grid GIS Substation Photomontages: CHVP5 – PRoW at Woodside Farm (Appendix 24.7, Figure 10-Update) 1 Deadline 825th March 2021
ExA.AS-30.D8.V1_01(Chapter 29) REP8-066(APP-077) Different colour schemes for Substations Design Principles Statement : Viewpoint 1 Public Rights of Way near Friston House 1 Deadline 825th March 2021
ExA.AS-30.D8.V1_02(Chapter 29) REP8-067(APP-077) Different colour schemes for Substations Design Principles Statement: Viewpoint 2 Friston, Church Road 1 Deadline 825th March 2021
ExA.AS-30.D8.V1_03(Chapter 29) REP8-068(APP-077) Different colour schemes for Substations Design Principles Statement: Viewpoint 9 – B1121 Aldeburgh Road, south of Friston 1 Deadline 825th March 2021
ExA.AS-31.D8.V1_01(Chapter 29) REP8-071(APP-077) Viewpoint Photomontages with Potential National Grid Extension Bays: Figure 29.14 Update Viewpoint 2 Friston, Church Road 1 Deadline 825th March 2021
ExA.AS-31.D8.V1_02(Chapter 29) REP8-072(APP-077) Viewpoint Photomontages with Potential National Grid Extension Bays: Figure 29.17 Update Viewpoint 5 Public Rights of Way, near Moor Farm 1 Deadline 825th March 2021
ExA.AS-31.D8.V1_03(Chapter 29) REP8-073(APP-077) Viewpoint Photomontages with Potential National Grid Extension Bays: Figure 29.20 Update Viewpoint 8 Saxmundham Road (North of Friston) 1 Deadline 825th March 2021
ExA.AS-31.D8.V1_04(Chapter 29) REP8-069(APP-077) Viewpoint Photomontages with Potential National Grid Extension Bays: CHVP3 – PRoW between Moor Farm and Little Moor Farm (Appendix 24.7, Figure 8-Update) 1 Deadline 825th March 2021
ExA.AS-31.D8.V1_05(Chapter 29) REP8-070(APP-077) Viewpoint Photomontages with Potential National Grid Extension Bays: CHVP4 – PRoW to east of Little Moor Farm (Appendix 24.7, Figure 9-Update) 1 Deadline 825th March 2021
ExA.AS-32.D8.V1(Chapter 29) REP8-074(APP-077) Extension of National Grid Substation Appraisal 1 Deadline 825th March 2021
ExA.AS-4.D11.V1(Chapter 29) REP11-028 Landscape and Visual Impact Assessment GIS Addendum 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_01(Chapter 29) REP11-029 LVIA GIS Addendum Appendix 1 Viewpoint 1 Figure 29.13 GIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_02(Chapter 29) REP11-030 LVIA GIS Addendum Appendix 2 Viewpoint 2 Figure 29.14 GIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_03(Chapter 29) REP11-031 LVIA GIS Addendum Appendix 3 Viewpoint 3 Figure 29.15 GIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_04(Chapter 29) REP11-032 LVIA GIS Addendum Appendix 4 Viewpoint 4 Figure 29.16 GIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_05(Chapter 29) REP11-033 LVIA GIS Addendum Appendix 5 Viewpoint 5 Figure 29.17 GIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_06(Chapter 29) REP11-034 LVIA GIS Addendum Appendix 6 Viewpoint 6 Figure 29.18 GIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_07(Chapter 29) REP11-035 LVIA GIS Addendum Appendix 7 Viewpoint 8 Figure 29.20 GIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_08(Chapter 29) REP11-036 LVIA GIS Addendum Appendix 8 Viewpoint 9 Figure 29.21 GIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_09(Chapter 29) REP11-037 LVIA GIS Addendum Appendix 9 Viewpoint 1 Figure 29.13 AIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_10(Chapter 29) REP11-038 LVIA GIS Addendum Appendix 10 Viewpoint 2 Figure 29.14 AIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_11(Chapter 29) REP11-039 LVIA GIS Addendum Appendix 11 Viewpoint 3 Figure 29.15 AIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_12(Chapter 29) REP11-040 LVIA GIS Addendum Appendix 12 Viewpoint 4 Figure 29.16 AIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_13(Chapter 29) REP11-041 LVIA GIS Addendum Appendix 13 Viewpoint 5 Figure 29.17 AIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_14(Chapter 29) REP11-042 LVIA GIS Addendum Appendix 14 Viewpoint 6 Figure 29.18 AIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_15(Chapter 29) REP11-043 LVIA GIS Addendum Appendix 15 Viewpoint 8 Figure 29.20 AIS Update 1 Deadline 117th June 2021
ExA.AS-4.D11.V1_16(Chapter 29) REP11-044 LVIA GIS Addendum Appendix 16 Viewpoint 9 Figure 29.21 AIS Update 1 Deadline 117th June 2021
ExA.AS-17.D1.V1(Chapter 30) REP1-036(APP-078) Socio-Economics and Tourism Clarification Note (SZC CIA) 1 Deadline 12nd November 2020
ExA.WQ-1.A13.D1.V1(Chapter 30) REP1-102(APP-078) Applicants’ Responses to WQ1 Appendix 13 Tourism Impact Review 1 Deadline 12nd November 2020
5.3 APP-043 Habitat Regulations Assessment - Information to Support the Appropriate Assessment Report 1 25th October 2019
5.3.1 APP-044 Habitat Regulations Assessment - Appendix 1 - Information to Support AA Report - HRA Screening Report 1 25th October 2019
5.3.2 REP3-016 Habitat Regulations Assessment Appendix 2 – Information to Support AA Report – Screening Matrices 3 Deadline 315th December 2020
5.3.3 APP-046 Habitat Regulations Assessment - Appendix 3 - Information to Support AA Report - Integrity Matrices 1 25th October 2019
ExA.AS-19.D1.V1(Chapter 11) REP1-038(APP-059) Information to Support AA – Addendum for Marine Mammals 1 Deadline 12nd November 2020
ExA.AS-7.D1.V1 (Information to Support Appropriate Assessment Report) REP1-047(APP-043 to APP-047) Deadline 1 Offshore Ornithology Cumulative and In Combination Collision Risk Update 1 Deadline 12 November 2020
ExA.AS-7.D4.V1(Information to Support Appropriate Assessment Report) REP4-042(APP-043 to APP-047) Deadline 4 Offshore Ornithology Cumulative and In Combination Collision Risk Update 1 Deadline 413th January 2021
ExA.AS-11.D8.V1(Information to Support Appropriate Assessment Report) REP8-035(APP-043 to APP-047) Deadline 8 Offshore Ornithology Cumulative and In Combination Collision Risk Update 1 Deadline 825th March 2021
ExA.AS-3.D11.V1(Information to Support Appropriate Assessment Report) REP11-027(APP-043 to APP-047) Deadline 11 Offshore Ornithology Cumulative and In Combination Collision Risk and Displacement Update 1 Deadline 117th June 2021
ExA.AS-8.D12.V1 (Information to Support Appropriate Assessment Report) REP12-066 (APP-043 to APP-047) Deadline 12 Offshore Ornithology Cumulative and In Combination Collision Risk and Displacement Update 1 Deadline 1315 July 2021
ExA.AS-12.D13.V1(Information to Support Appropriate Assessment Report) REP13-019(APP-043 to APP-047) Deadline 13 Offshore Ornithology Cumulativeand In-Combination Collision Riskand Displacement Update 1 Deadline 135th July 2021
ExA.AS-3.SoSQ.V1 (Information to Support Appropriate Assessment Report) (APP-043 to APP-047) Updated Offshore OrnithologyCumulative and In-CombinationCollision Risk and DisplacementAssessment” 1 Column (5) “30 November 2021”

PART 2 — Other documents to be certified

(1) (2) (3) (4) (5)
Document Reference Examination Library Reference Document Name Version Date
2.2 REP11-003 Land Plans (onshore) 6 Deadline 117th June 2021
2.2.1 AS-002 Land Plans (offshore) (Rev 2) 1 20th December 2019
2.3.1 APP-010 Works Plans (offshore) (Rev 4) 1 25th October 2019
2.3.2 REP11-004 Works Plans (onshore) 7 Deadline 117th June 2021
2.4 REP12-004 Access to Works Plan (Rev 2) 2 Deadline 1228th June 2021
2.5 REP12-005 Temporary Stopping up of Public Rights of Way Plan (Rev 4) 4 Deadline 1228th June 2021
2.6 REP12-006 Permanent Stopping up of Public Rights of Way Plan (Rev 4) 3 Deadline 1228th June 2021
2.10 REP12-012 Important Hedgerows and Tree Preservation Order Plan (Rev 4) 4 Deadline 1228th June 2021
2.12 APP-022 Order limits boundary coordinates plan (offshore) 1 25th October 2019
4.3 REP12-019 Book of Reference (Version 10) 10 Deadline 1228th June 2021
8.1 . . . Outline Code of Construction Practice(Version 10) 10 31 January 2022
8.4 AS-116 Outline Public Rights of Way Strategy 3 22nd April 2021
8.5 REP6-005 Outline Written Scheme of Investigation (Onshore Archaeology) 3 Deadline 624th February 2021
8.6 REP3-028 Outline Written Scheme of Investigation (Offshore) 2 Deadline 315th December 2020
8.7 . . . Outline Landscape and Ecological Management Strategy (Version 08) 8 Deadline 13 31 January 2022
8.9 REP11-017 Outline Construction Traffic Management Plan 6 Deadline 117th June 2021
8.10 REP12-023 Outline Access Management Plan (Version 07) 7 Deadline 1228th June 2021
8.11 REP11-022 Outline Travel Plan 6 Deadline 117th June 2021
8.12 REP7-027 Outline Offshore Operations and Maintenance Plan 3 Deadline 74th March 2021
8.13 REP8-027 Offshore In Principle Monitoring Plan 4 Deadline 825th March 2021
8.14 REP8-029 Draft Marine Mammal Mitigation Protocol 4 Deadline 825th March 2021
8.17 REP8-031 In Principle East Anglia TWO Project Southern North Sea SAC Site Integrity Plan 4 Deadline 825th March 2021
8.18 APP-595 Outline Navigation Monitoring Strategy 1 25th October 2019
8.20 REP1-019 Outline pre-commencement archaeology execution plan (onshore) 2 Deadline 12nd November 2020
ExA.AS-1.D12.V4 REP12-025 Outline Landfall Construction Method Statement (Version 04) 4 Deadline 1228th June 2021
ExA.AS-2.D12.V3 REP12-027 Outline SPA Crossing Method Statement (Version 03) 3 Deadline 1228th June 2021
ExA.AS-6.D8.V2 REP8-086 Outline Sizewell Gap Construction Method Statement 2 Deadline 825th March 2021
ExA.AS-5.D3.V2 REP3-050 Outline Fisheries Liaison and Coexistence Plan 2 Deadline 315th December 2020
ExA.AS-4.D6.V3 REP6-039 Outline Sabellaria Reef Management Plan 3 Deadline 624th February 2021
ExA.AS-13.D13.V7 REP13-020 Outline Operational Drainage Management Plan (Version 07) 7 Deadline 135th July 2021
ExA.AS- 5.D12.V5 REP12-062 Outline Port Construction Traffic Management and Travel Plan 5 Deadline 1228th June 2021
ExA.AS- 29.D11.V4 REP11-074 Outline Watercourse Crossing Method Statement 4 Deadline 117th June 2021
ExA.AS-12.D8.V3 REP8-036 Best Practice Protocol for Minimising Disturbance to Red-Throated Diver 3 Deadline 825th March 2021
ExA.AS-6.D11.V4 AS-133 Substations Design Principles Statement (Rev 04) 4 ...21st June 2021
ExA.AS-6.SoSQ2.V5 . . . Offshore Ornithology Without Prejudice Compensation Measures 5 31 January 2022
ExA.AS-35.D8.V2 REP8-077 Activity Exclusion Zones Plan 2 Deadline 825th March 2021
ExA.AS-15.D7.V1 REP7-037 Sizewell C Order Limits Interaction – Offshore Plan 1 Deadline 74th March 2021
ExA.AS-34. D9.V2 REP9-031 Layout Principles Statement 2 Deadline 915th April 2021

SCHEDULE 18 — Offshore Ornithology Compensation Measures

PART 1 — Flamborough and Filey Coast Special Protection Area: Kittiwake Compensation Measures

1

In this Part—

  • the kittiwake compensation plan” means Appendix 1 of the Offshore Ornithology Without Prejudice Compensation Measures.

2

The authorised development may not be commenced until a plan for the work of the kittiwake compensation steering group (“KCSG”) has been submitted to and approved by the Secretary of State. Such plan to include—

  • (a) terms of Reference of the KCSG;
  • (b) details of the membership of the KCSG;
  • (c) details of the schedule of meetings, timetable for preparation of the kittiwake implementation and monitoring plan (the “KIMP”) and reporting and review periods; and
  • (d) the dispute resolution mechanism.

3

Following consultation with the KCSG, the KIMP must be submitted to and approved by the Secretary of State (in consultation with the MMO, the local planning authority for the land containing the artificial nest site, and the relevant statutory nature conservation body). The KCSG must be consulted further as required during the approval process. The KIMP must be based on the strategy for kittiwake compensation set out in the kittiwake compensation plan and include—

  • (a) details of the location where compensation measures will be deployed, why the location is appropriate ecologically and likely to support successful compensation, and details of agreements demonstrating how the land and/or rights will or have been secured to deliver the ecology objectives of the KIMP;
  • (b) details of designs of the artificial nest site including the type of nesting structure; and how risks from avian or mammalian predation and unauthorised human access will be mitigated;
  • (c) an implementation timetable for delivery of the artificial nest structure that ensures relevant compensation measures are in place to allow four full kittiwake breeding seasons prior to the operation of any wind turbine generator forming part of the authorised development;
  • (d) details of the proposed ongoing monitoring of the measures including: survey methods; survey programmes; success criteria; recording of KCSG consultations and project reviews; adaptive management measures and details of the factors used to trigger alternative compensation measures and/or adaptive management measures;
  • (e) details of the artificial nesting site maintenance schedule; and
  • (f) provision for annual reporting to the Secretary of State, to include details of the number of birds colonising the site including: evidence of birds prospecting; nesting attempts; egg laying; hatching; and fledging, to identify barriers to breeding success and target alternative or adaptive management measures.

4

The undertaker must not commence the authorised development unless it has first—

  • (a) provided a reasonable estimate of the cost of delivery of the compensation measures; and
  • (b) put in place either—
  • (i) a guarantee in respect of the reasonable estimate of costs associated with the delivery of the compensation measures; or
  • (ii) an alternative form of security for that purpose,

that has been approved by the Secretary of State.

5

The undertaker must implement the measures as set out in the KIMP approved by the Secretary of State, unless otherwise agreed in writing by the Secretary of State in consultation with the relevant statutory nature conservation body and the relevant local planning authority. In particular, no operation of any turbine forming part of the authorised development may begin until four full breeding seasons following the implementation of the measures set out in the KIMP have elapsed. For the purposes of this paragraph each breeding season is assumed to have commenced on 1st March in each year and ended on 30th September.

6

The undertaker shall notify the Secretary of State of completion of implementation of the measures set out in the KIMP.

7

Results from the monitoring scheme must be submitted at least annually to the Secretary of State and the relevant statutory nature conservation body. This must include details of any finding that the measures have been ineffective in securing an increase in the number of adult kittiwakes available to recruit to the SPA and, in such case, proposals to address this. Any proposals to address effectiveness must thereafter be implemented by the undertaker as approved in writing by the Secretary of State in consultation with the relevant statutory nature conservation body.

8

The artificial nest structure must not be decommissioned without written approval of the Secretary of State, in consultation with the relevant statutory nature conservation body. The artificial nest structures shall be maintained beyond the operational lifetime of the authorised development if they are colonised, and routine and adaptive management measures and monitoring must continue whilst the artificial nesting structures are in place.

9

The KIMP approved under this Schedule includes any amendments that may subsequently be approved in writing by the Secretary of State. Any amendments to or variations of the approved KIMP must be in accordance with the principles set out in the kittiwake compensation plan and may only be approved where it has been demonstrated to the satisfaction of the Secretary of State that it is unlikely to give rise to any materially new or materially different environmental effects from those considered in the kittiwake compensation plan.

10

In the event of any conflict or inconsistency between the terms of the kittwake compensation plan and the provisions of this Order, the provisions of this Order shall prevail.

PART 2 — Alde-Ore Estuary Special Protection Area: Lesser black-backed gull Compensation Measures

1

In this Part—

  • the lesser black-backed gull compensation plan” means Appendices 5 and 7 of the Offshore Ornithology Without Prejudice Compensation Measures.

2

The authorised development may not be commenced until a plan for the work of the lesser black-backed gull compensation steering group (“LBBCSG”) has been submitted to and approved by the Secretary of State. Such plan to include—

  • (a) terms of Reference of the LBBCSG;
  • (b) details of the membership of the LBBCSG;
  • (c) details of the schedule of meetings, timetable for preparation of the lesser black-backed gull implementation and monitoring plan (the “LBBIMP”) and reporting and review periods; and
  • (d) the dispute resolution mechanism.

3

Following consultation with the LBBCSG, the LBBIMP must be submitted to the Secretary of State for approval (in consultation with the MMO, the local planning authority for any land containing the predator control fencing, and the relevant statutory nature conservation body). The LBBCSG must be consulted further as required during the approval process. The LBBIMP must be based on the strategy for lesser black-backed gull compensation set out in the lesser black-backed gull compensation plan and include—

  • (a) details of the location where compensation measures will be deployed, why the location is appropriate ecologically and likely to support successful compensation, and details of agreements demonstrating how any land and/or rights will or have been secured to deliver the ecology objectives of the LBBIMP;
  • (b) details of designs of any predator control fencing including the type of fencing and area and location of enclosure, and details of any other habitats management measures;
  • (c) an implementation timetable for delivery of any predator control fencing and any other habitat management measures that ensures relevant compensation measures are in place to allow four full lesser black-backed gull breeding seasons prior to the operation of any wind turbine generator forming part of the authorised development;
  • (d) details of the proposed ongoing monitoring of the measures including: survey methods; survey programmes; success criteria; recording of LBBCSG consultations and project reviews; adaptive management measures and details of the factors used to trigger alternative compensation measures and/ or adaptive management measures;
  • (e) details of the maintenance schedule for any predator proof fencing; and
  • (f) details of the work in respect of ornithological by-catch measures as set out in Appendix 7 of the Offshore Ornithology Without Prejudice Compensation Measures, that could support practical management measures to reduce ornithological by-catch, and which would be undertaken alongside or in place of the predator control fencing.

4

The undertaker must not commence the authorised development unless it has first—

  • (a) provided a reasonable estimate of the cost of delivery of the compensation measures; and
  • (b) put in place either—
  • (i) a guarantee in respect of the reasonable estimate of costs associated with the delivery of the compensation measures; or
  • (ii) an alternative form of security for that purpose,

that has been approved by the Secretary of State.

5

The undertaker must implement the measures as set out in the LBBIMP approved by the Secretary of State, unless otherwise agreed in writing by the Secretary of State in consultation with the relevant statutory nature conservation body and the relevant local planning authority. In particular, no operation of any turbine forming part of the authorised development may begin until four full breeding seasons following the implementation of the measures set out in the LBBIMP have elapsed. For the purposes of this paragraph each breeding season is assumed to have commenced on 1st March in each year and ended on 30th September.

6

The undertaker shall notify the Secretary of State of completion of implementation of the measures set out in the LBBIMP.

7

Results from the monitoring scheme must be submitted at least annually to the Secretary of State and the relevant statutory nature conservation body. This must include details of any finding that the measures have been ineffective in securing an increase in the number of adult lesser black-backed gulls available to recruit to the SPA and, in such case, proposals to address this. Any proposals to address effectiveness must thereafter be implemented by the undertaker as approved in writing by the Secretary of State in consultation with the relevant statutory nature conservation body.

8

Any predator proof fencing installed must not be decommissioned without written approval of the Secretary of State, in consultation with the relevant statutory nature conservation body. The predator control fencing shall be maintained beyond the operational lifetime of the authorised development if the site is colonised. The routine and adaptive management measures and monitoring should continue whilst the fencing is in place.

9

The LBBIMP approved under this Schedule includes any amendments that may subsequently be approved in writing by the Secretary of State. Any amendments to or variations of the approved LBBIMP must be in accordance with the principles set out in the lesser black-backed gull compensation plan and may only be approved where it has been demonstrated to the satisfaction of the Secretary of State that it is unlikely to give rise to any materially new or materially different environmental effects from those considered in the lesser black-backed gull compensation plan.

10

In the event of any conflict or inconsistency between the terms of the lesser black-backed gull compensation plan and the provisions of this Order, the provisions of this Order shall prevail.

PART 3 — Outer Thames Estuary Special Protection Area: Red-throated diver Compensation Measures

1

In this Part—

  • the red-throated diver compensation plan” means Appendix 6 of the Offshore Ornithology Without Prejudice Compensation Measures.

2

The authorised development may not be commenced until a plan for the work of the red-throated diver compensation steering group (“RTDCSG”) has been submitted to and approved by the Secretary of State. Such plan to include—

  • (a) terms of Reference of the RTDCSG;
  • (b) details of the membership of the RTDCSG;
  • (c) details of the schedule of meetings, timetable for preparation of the red-throated diver implementation and monitoring plan (the “RTDIMP”) and reporting and review periods; and
  • (d) the dispute resolution mechanism.

3

Following consultation with the RTDCSG, the RTDIMP must be submitted to the Secretary of State for approval (in consultation with the MMO and the relevant statutory nature conservation body). The RTDCSG must be consulted further as required during the approval process. The RTDIMP must be based on the strategy for red-throated diver compensation set out in the red-throated diver compensation plan and include—

  • (a) details of the location where compensation measures will be deployed, why the location is appropriate ecologically and likely to support successful compensation, and details of agreements demonstrating how the vessel route diversions and/or exclusions will or have been secured to deliver the ecology objectives of the RTDIMP;
  • (b) an implementation timetable for delivery of the vessel route diversion and/or exclusion compensation measures that ensures that the measures are in place prior to the installation of any tower comprised within a wind turbine generator forming part of the authorised development;
  • (c) details in relation to the monitoring of red-throated diver abundance and distribution using aerial digital surveys in the Outer Thames Estuary SPA and a 10km buffer over two winters. Three surveys should take place each winter (between 1st November and 31st March) with one batch to take place before the installation of the turbines forming part of the authorised development and the other batch to take place after;
  • (d) details of the proposed ongoing monitoring of the measures including: survey methods; survey programmes; success criteria; recording of RTDCSG consultations and project reviews; details of the factors used to trigger alternative compensation measures and/or adaptive management measures;
  • (e) details in relation to the convening of a partnership with relevant authorities and user representation to—
  • (i) improve understanding of disturbance and displacement effects on red-throated diver within the Outer Thames Estuary SPA;
  • (ii) identify and implement opportunities to reduce these effects; and
  • (iii) ensure stakeholder engagement and liaison to raise awareness and communicate any proposed changes in usage; and
  • (f) details of the work in respect of ornithological by-catch measures as set out in Appendix 7 of the Offshore Ornithology Without Prejudice Compensation Measures, that could support practical management measures to reduce ornithological by-catch ... .

4

The undertaker must not commence the authorised development unless it has first—

  • (a) provided a reasonable estimate of the cost of delivery of the compensation measures; and
  • (b) put in place either—
  • (i) a guarantee in respect of the reasonable estimate of costs associated with the delivery of the compensation measures; or
  • (ii) an alternative form of security for that purpose,

that has been approved by the Secretary of State.

5

The undertaker must implement the measures as set out in the RTDIMP approved by the Secretary of State unless otherwise agreed in writing by the Secretary of State in consultation with the relevant statutory nature conservation body and the relevant local planning authority. No tower comprised within a wind turbine generator forming part of the authorised development may be installed until the implementation of relevant measures as set out in the RTDIMP.

6

The undertaker shall notify the Secretary of State of completion of implementation of the measures set out in the RTDIMP. Once implemented, the measures should remain in place throughout the operational lifetime of the authorised development.

7

Results from the monitoring scheme and aerial digital surveys must be submitted at least annually to the Secretary of State and the relevant statutory nature conservation body. This must include details of any finding that the measures have been ineffective in securing the maintenance of the SPA’s conservation objectives and, in such case, proposals to address this. Any proposals to address effectiveness must thereafter be implemented by the undertaker as approved in writing by the Secretary of State in consultation with the relevant statutory nature conservation body.

8

The RTDIMP approved under this Schedule includes any amendments that may subsequently be approved in writing by the Secretary of State. Any amendments to or variations of the approved RTDIMP must be in accordance with the principles set out in the red-throated diver compensation plan and may only be approved where it has been demonstrated to the satisfaction of the Secretary of State that it is unlikely to give rise to any materially new or materially different environmental effects from those considered in the red-throated diver compensation plan.

9

In the event of any conflict or inconsistency between the terms of the red-throated diver compensation plan and the provisions of this Order, the provisions of this Order shall prevail.

Signed

Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy

Gareth Leigh — Head of Energy Infrastructure Planning — Department for Business, Energy and Industrial Strategy — 2022-03-31

Explanatory note

(This note is not part of the Order)

EXPLANATORY NOTE

This Order grants development consent for, and authorises East Anglia TWO Limited to construct, operate and maintain a generating station located in the North Sea approximately 37.3km from the port of Lowestoft and 32.6km from Southwold together with all necessary and associated development. For the purposes of the development that it authorises East Anglia TWO Limited is authorised by the Order compulsorily or by agreement to purchase land and rights in land to use land, as well as to override easements and other rights. The Order also provides a defence in proceedings in respect of statutory nuisance and to discharge water. The Order imposes requirements in connection with the development for which it grants development consent.

The Order also grants deemed marine licences for the marine licensable activities, being the deposit of substances and articles and the carrying out of works, involved in the construction of the generating station and associated development. The deemed marine licences impose conditions in connection with the deposits and works for which they grant consent.

A copy of the plans and book of reference referred to in this Order and certified in accordance with article 36 (certification of plans etc.) of this Order may be inspected free of charge at East Suffolk Council Customer Services at Woodbridge Library, New Street, Woodbridge IP12 1DT.

Footnotes

[^f00001]: 2008 c. 29. Section 37 was amended by Chapter 6 of Part 6 of, and schedule 13 to, the Localism Act 2011 (c. 20) and by sections 22 to 27 of the Growth and Infrastructure Act 2013 (c. 27).

[^f00002]: Section 61 was amended by section 128(2) and Schedule 13, paragraph 18 to the Localism Act 2011 (c. 20) and by section 26 of the Infrastructure Act 2015 (c. 7).

[^f00003]: Section 65 was amended by Schedule 13, paragraph 22(2) and Schedule 25, paragraph 1 to the Localism Act 2011 (c. 20) and by section 27(1) of the Infrastructure Act 2015 (c. 7).

[^f00004]: S.I. 2010/103, amended by S.I. 2012/635.

[^f00005]: S.I. 2017/572.

[^f00006]: 1961 c. 33.

[^f00007]: 1965 c. 56.

[^f00008]: 1980 c. 66.

[^f00009]: 1981 c. 66.

[^f00010]: 1989 c. 29.

[^f00011]: 1990 c. 8.

[^f00012]: 1991 c. 22.

[^f00013]: 2003 c. 21.

[^f00014]: 2004 c. 20.

[^f00015]: 2009 c. 23.

[^f00016]: S.I. 2017/1012.

[^f00017]: “carriageway” is defined in section 329(1).

[^f00019]: Section 329(1) was amended by Schedule 1(1) para. 60(2)(a) to the Infrastructure Act 2015 c. 7.

[^f00020]: 1981 c. 67. Section 7 was amended by section 70 of, and paragraph 9 of Schedule 15 to, the Planning and Compensation Act 1991 (c. 34). There are other amendments to the 1981 Act which are not relevant to this Order.

[^f00021]: Section 48 was amended by section 124(2) of the Local Transport Act 2008 (c. 26).

[^f00022]: “street authority” is defined in section 49, which was amended by paragraph 117 of Schedule 1 to the Infrastructure Act 2015 (c. 7).

[^f00023]: S.I. 1997/1160.

[^f00024]: 2017 c. 20.

[^f00025]: 1990 c. 43. Section 82 was amended by section 107 and paragraph 6 of Schedule 17 to the Environment Act 1995 (c. 25), section 5 of the Noise and Statutory Nuisance Act 1993 (c. 40), and section 103 of the Clean Neighbourhoods and Environment Act 2005 (c. 16) and section 79 was amended by sections 101 and 102 of the Clean Neighbourhoods and Environment Act 2005 (c. 16), and by section 120 and paragraph 89 of Schedule 22 to the Environment Act 2005. There are other amendments to this Act which are not relevant to the Order.

[^f00026]: Section 79(1) was amended by sections 101 and 102 of the Clean Neighbourhoods and Environment Act 2005 (c. 16).

[^f00027]: 1974 c. 40. Section 61 was amended by Schedule 7 to the Building Act 1984 (c. 55), paragraph 15 of Schedule 15 to the Environmental Protection Act 1990 (c. 43) and Schedule 24 to the Environment Act 1995 (c. 25). There are other amendments to the 1974 Act which are not relevant to the Order.

[^f00028]: “apparatus” is defined in section 89(3) and section 105(1).

[^f00029]: Sections 55, 57, 60, 68 and 69 were amended by the Traffic Management Act 2004 (c. 18).

[^f00030]: Part 1 was amended by s.192(1) of the Housing and Planning Act 2016 (c. 22) and Schedule 1 to the Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009, S.I. 2009/1307.

[^f00032]: S.I. 2016/1154.

[^f00033]: Section 4 was amended by sections 184 and 185 of, and paragraph 2 of Schedule 18 to, the Housing and Planning Act 2016 (c. 22).

[^f00034]: Section 11(1) was amended by sections 186 to 188 of and Schedules 14 and 16 to, the Housing and Planning Act 2016 (c. 22), Schedule 4 to the Acquisition of Land Act 1981 (c. 67) and Schedule 5 to the Church of England (Miscellaneous Provision) Measure 2006 No 1 and Schedule 1 to the Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009/1307.

[^f00035]: Section 13 was amended by Tribunals Courts and Enforcement Act 2007 (c. 15).

[^f00036]: Section 105(2) was substituted by section 69(3) of the Energy Act 2008 (c. 32).

[^f00037]: 1978 c. 30.

[^f00038]: Section 105(2) was substituted by section 69(3) of the Energy Act 2008 (c. 32).

[^f00039]: S.I. 2016/765.

[^f00040]: S.I. 2019/703.

[^f00041]: 1973 c. 26.

[^f00042]: 1986 c. 44.

[^f00043]: 1991 c. 56.

[^f00044]: S.I. 2014/1599.

[^f00045]: S.I. 2017/826.

[^f00046]: S.I. 2017/1013.

[^f00047]: S.I. 2017/1012.

[^f00048]: S.I. 2017/1013.

[^f00049]: S.I. 2017/1012.

[^f00050]: 1996 c. 23.

Editorial notes

[^key-6c7e159cce120cec43b1321d742b0ca0]: Art. 1 in force at 22.4.2022, see art. 1(2)

[^key-77e9d9da08a2cf4ea4d691ede9ca3dd4]: Art. 2 in force at 22.4.2022, see art. 1(2)

[^key-79094a5d5baa97311e91db060a514156]: Art. 3 in force at 22.4.2022, see art. 1(2)

[^key-615b518e7d1aa1f3eb9a3d22b7eae557]: Art. 4 in force at 22.4.2022, see art. 1(2)

[^key-580f79f2468e2ac723bd0f8e35c967e7]: Art. 5 in force at 22.4.2022, see art. 1(2)

[^key-e829a82bcded21986d18038483f0a1d5]: Art. 6 in force at 22.4.2022, see art. 1(2)

[^key-0a1a6f0ef51fb0dd112295f9ab1805df]: Art. 7 in force at 22.4.2022, see art. 1(2)

[^key-5b8526ff3d369a080bd8018a5d1cf1a0]: Art. 8 in force at 22.4.2022, see art. 1(2)

[^key-9ba8f10acbe913604db0280fec9c0fbf]: Art. 9 in force at 22.4.2022, see art. 1(2)

[^key-fd2982377231305738a63e273f7bbb8f]: Art. 10 in force at 22.4.2022, see art. 1(2)

[^key-57cc5364df3c7876b7fb4d2eb45cc1bb]: Art. 11 in force at 22.4.2022, see art. 1(2)

[^key-e17fe04787ef9fbb06c63d54af7d6097]: Art. 12 in force at 22.4.2022, see art. 1(2)

[^key-f44d81b086255854d8d756d0c52dd05f]: Art. 13 in force at 22.4.2022, see art. 1(2)

[^key-ee958542a16c9a03d785ddc6e328791a]: Art. 14 in force at 22.4.2022, see art. 1(2)

[^key-dc1c98b8a57aeb8129088762055c8840]: Art. 15 in force at 22.4.2022, see art. 1(2)

[^key-f72d346ae768ece50cf83408218f4a21]: Art. 16 in force at 22.4.2022, see art. 1(2)

[^key-f2aed9b66c4d804b67ece29fe8c18749]: Art. 17 in force at 22.4.2022, see art. 1(2)

[^key-21b050ab43397f8df37b170b36288b87]: Art. 18 in force at 22.4.2022, see art. 1(2)

[^key-2d67840e0e150be6273c0abd341334e7]: Art. 19 in force at 22.4.2022, see art. 1(2)

[^key-93d4da37c3b7d955c4c73473ca4a9ca2]: Art. 20 in force at 22.4.2022, see art. 1(2)

[^key-7f2a7a61a6855d1a5f34a2eb269c49b6]: Art. 21 in force at 22.4.2022, see art. 1(2)

[^key-98f3115287c273a5fc2cb208c9349f89]: Art. 22 in force at 22.4.2022, see art. 1(2)

[^key-a0929fe9524ead2d4d9f044acc7dcc28]: Art. 23 in force at 22.4.2022, see art. 1(2)

[^key-7ebc5b12b0cc8b92420d925988cb6a4d]: Art. 24 in force at 22.4.2022, see art. 1(2)

[^key-915eb44dc7342d8f322e3db218ac687c]: Art. 25 in force at 22.4.2022, see art. 1(2)

[^key-f5bf0226343fdd80d5db956f25cb54c5]: Art. 26 in force at 22.4.2022, see art. 1(2)

[^key-e3df55a40b3fd9c5b38ec150a0da2723]: Art. 27 in force at 22.4.2022, see art. 1(2)

[^key-1bd3120e11b6e9f457d1b96b04be7fe2]: Art. 28 in force at 22.4.2022, see art. 1(2)

[^key-ceaa8cde32cd37ec8de44715e33935a8]: Art. 29 in force at 22.4.2022, see art. 1(2)

[^key-c05087d5f7b8394cb20fa295be603b6f]: Art. 30 in force at 22.4.2022, see art. 1(2)

[^key-e46defeabd73a37387e4b1e4aa3de852]: Art. 31 in force at 22.4.2022, see art. 1(2)

[^key-cc0b238e39db1eefa3975425b2c2b92c]: Art. 32 in force at 22.4.2022, see art. 1(2)

[^key-462b9ba58d6f548ce24d2d4c9deb8116]: Art. 33 in force at 22.4.2022, see art. 1(2)

[^key-c17d2ff8f519d03d2716a636c8ddda9a]: Art. 34 in force at 22.4.2022, see art. 1(2)

[^key-12546be2e20b4ee19bca0980ec85932c]: Art. 35 in force at 22.4.2022, see art. 1(2)

[^key-00c5e6921dbae4943310b087d6246777]: Art. 36 in force at 22.4.2022, see art. 1(2)

[^key-7f59e6413bdc49d9b6966c8c4cf66554]: Art. 37 in force at 22.4.2022, see art. 1(2)

[^key-f2de9734cfc460792221e08f72b776ba]: Art. 38 in force at 22.4.2022, see art. 1(2)

[^key-548cd975c8b1112ed28e805996c22369]: Art. 39 in force at 22.4.2022, see art. 1(2)

[^key-82db8335f9346c0390612ac6c3fbf8f7]: Art. 40 in force at 22.4.2022, see art. 1(2)

[^key-5b9287a32a82b6ba111b19792deeab77]: Art. 41 in force at 22.4.2022, see art. 1(2)

[^key-fbada5fba4924cc6066234d65ce765bb]: Art. 42 in force at 22.4.2022, see art. 1(2)

[^key-00992fd0528ac33f95da380043f42cc1]: Art. 43 in force at 22.4.2022, see art. 1(2)

[^key-ff53f557c1c9dd0c0a49217c4bc6b6f2]: Art. 44 in force at 22.4.2022, see art. 1(2)

[^key-44f40d5634d94c87d0080bc18891e040]: Art. 45 in force at 22.4.2022, see art. 1(2)

[^key-165c406501d733c91cbba0a858db577e]: Sch. 1 Pt. 1 para. 1 in force at 22.4.2022, see art. 1(2)

[^key-e0d4fe7d7eba39c7c1b0a69ea9a6943c]: Sch. 1 Pt. 1 para. 2 in force at 22.4.2022, see art. 1(2)

[^key-b2a9adb55efe70f32103febbee715a49]: Sch. 1 Pt. 1 para. 3 in force at 22.4.2022, see art. 1(2)

[^key-cc1654c45104e59541538de23618dd07]: Sch. 1 Pt. 2 para. 1 in force at 22.4.2022, see art. 1(2)

[^key-db532ec20f892f7e7ba4364c7d2327fa]: Sch. 1 Pt. 3 para. 1 in force at 22.4.2022, see art. 1(2)

[^key-a0f497a4cf97dfbaec48619613815c1f]: Sch. 1 Pt. 3 para. 2 in force at 22.4.2022, see art. 1(2)

[^key-01ea938a3ec88471f464005d3deff1cd]: Sch. 1 Pt. 3 para. 3 in force at 22.4.2022, see art. 1(2)

[^key-38888f64474902ce24120612802d4b6a]: Sch. 1 Pt. 3 para. 4 in force at 22.4.2022, see art. 1(2)

[^key-aff1afdc85baa0c489ad3f8b1ffb9ccd]: Sch. 1 Pt. 3 para. 5 in force at 22.4.2022, see art. 1(2)

[^key-571b9041a36ea9e3f0fdffcfdf6915f6]: Sch. 1 Pt. 3 para. 6 in force at 22.4.2022, see art. 1(2)

[^key-83304be6e126ef9c4d4d57533c4ca645]: Sch. 1 Pt. 3 para. 7 in force at 22.4.2022, see art. 1(2)

[^key-11943a006141bf8667e7bade6b93df37]: Sch. 1 Pt. 3 para. 8 in force at 22.4.2022, see art. 1(2)

[^key-49c5aed078f47e41b0d8e02a75a832d3]: Sch. 1 Pt. 3 para. 9 in force at 22.4.2022, see art. 1(2)

[^key-08399f8e813271967c5384398df4f2dd]: Sch. 1 Pt. 3 para. 10 in force at 22.4.2022, see art. 1(2)

[^key-994f892a86949aef74edff0e5bb6eb59]: Sch. 1 Pt. 3 para. 11 in force at 22.4.2022, see art. 1(2)

[^key-ef2a54febfb3218a001b747ff0f453ab]: Sch. 1 Pt. 3 para. 12 in force at 22.4.2022, see art. 1(2)

[^key-468a4361e183b5cf042771c23aef4b95]: Sch. 1 Pt. 3 para. 13 in force at 22.4.2022, see art. 1(2)

[^key-447f7d193d8898514753e74da285ecc4]: Sch. 1 Pt. 3 para. 14 in force at 22.4.2022, see art. 1(2)

[^key-243d9d11717e45f7daead7e5bb1e2cde]: Sch. 1 Pt. 3 para. 15 in force at 22.4.2022, see art. 1(2)

[^key-16a1466378ef80c2614b2f163854665e]: Sch. 1 Pt. 3 para. 16 in force at 22.4.2022, see art. 1(2)

[^key-84cc32e313c8be16121c96dd3ab54f40]: Sch. 1 Pt. 3 para. 17 in force at 22.4.2022, see art. 1(2)

[^key-1870d4a471293332decd8952145f01ac]: Sch. 1 Pt. 3 para. 18 in force at 22.4.2022, see art. 1(2)

[^key-027770ae93f73f86bdbf89c72693e60f]: Sch. 1 Pt. 3 para. 19 in force at 22.4.2022, see art. 1(2)

[^key-eaa58cf2a09d6741742ae265f346a8f7]: Sch. 1 Pt. 3 para. 20 in force at 22.4.2022, see art. 1(2)

[^key-061cbe72c10c1794521d479fb075510f]: Sch. 1 Pt. 3 para. 21 in force at 22.4.2022, see art. 1(2)

[^key-e33b64296674bee72fd07d3e18e8cd8c]: Sch. 1 Pt. 3 para. 22 in force at 22.4.2022, see art. 1(2)

[^key-efd0b205a8fddb32c820f751f2e832f8]: Sch. 1 Pt. 3 para. 23 in force at 22.4.2022, see art. 1(2)

[^key-dd0975209d01f3082184c86bb74ffa82]: Sch. 1 Pt. 3 para. 24 in force at 22.4.2022, see art. 1(2)

[^key-0f76e4d1b1c168e5cd478e96ec900523]: Sch. 1 Pt. 3 para. 25 in force at 22.4.2022, see art. 1(2)

[^key-463cb5631636650e15d1c29333f7e64a]: Sch. 1 Pt. 3 para. 26 in force at 22.4.2022, see art. 1(2)

[^key-4fc3d3db0f9ad3fe651c239723dc76a0]: Sch. 1 Pt. 3 para. 27 in force at 22.4.2022, see art. 1(2)

[^key-65b498656afd19e2cab69a6e333f2e10]: Sch. 1 Pt. 3 para. 28 in force at 22.4.2022, see art. 1(2)

[^key-dbe7679c6948b59f8e1c529de4ca8885]: Sch. 1 Pt. 3 para. 29 in force at 22.4.2022, see art. 1(2)

[^key-8ebfa5759522313be69e2cea7b018d1f]: Sch. 1 Pt. 3 para. 30 in force at 22.4.2022, see art. 1(2)

[^key-fb46df67eaba40f2d09551d64a864b36]: Sch. 1 Pt. 3 para. 31 in force at 22.4.2022, see art. 1(2)

[^key-dbf92e3f646c4f00a6aef511d7bc7911]: Sch. 1 Pt. 3 para. 32 in force at 22.4.2022, see art. 1(2)

[^key-1bc879f84a39d49dd97de801b15f897a]: Sch. 1 Pt. 3 para. 33 in force at 22.4.2022, see art. 1(2)

[^key-2d48acf37c76eb2c217a51a0ed2a0e8f]: Sch. 1 Pt. 3 para. 34 in force at 22.4.2022, see art. 1(2)

[^key-71bb9f0480c663b12347001fd9974ca7]: Sch. 1 Pt. 3 para. 35 in force at 22.4.2022, see art. 1(2)

[^key-4db4a4a358207b30693fb0e7fec70b98]: Sch. 1 Pt. 3 para. 36 in force at 22.4.2022, see art. 1(2)

[^key-3b1749b64b35b102f9f9abc3f6138039]: Sch. 1 Pt. 3 para. 37 in force at 22.4.2022, see art. 1(2)

[^key-84dbde7a69fcde466c7c7432cc64e8be]: Sch. 1 Pt. 3 para. 38 in force at 22.4.2022, see art. 1(2)

[^key-e61ac451d945a160eec295e619c12f88]: Sch. 1 Pt. 3 para. 39 in force at 22.4.2022, see art. 1(2)

[^key-a2cc55859b46edbdde5359c14423bb8f]: Sch. 1 Pt. 3 para. 40 in force at 22.4.2022, see art. 1(2)

[^key-c8c787718c9bc1cbc3e618fccfe1953f]: Sch. 1 Pt. 3 para. 41 in force at 22.4.2022, see art. 1(2)

[^key-80a6bf93a86dfeb4931bc25218ea4ef3]: Sch. 1 Pt. 3 para. 42 in force at 22.4.2022, see art. 1(2)

[^key-3fd0dbde737bf39219c24ba109c29431]: Sch. 1 Pt. 3 para. 43 in force at 22.4.2022, see art. 1(2)

[^key-7959796c72bfad8e1b3787506542038e]: Sch. 1 Pt. 3 para. 44 in force at 22.4.2022, see art. 1(2)

[^key-a9e0230ea3ed468798211944e15a9db9]: Sch. 8 para. 1 in force at 22.4.2022, see art. 1(2)

[^key-80a7e23a3a9ee5ef2c072bad93e451be]: Sch. 8 para. 2 in force at 22.4.2022, see art. 1(2)

[^key-68a9d3f0f8fb827595b3857bc9d49d58]: Sch. 8 para. 3 in force at 22.4.2022, see art. 1(2)

[^key-f01236b9b69eac79484c9fd8a59a4e4d]: Sch. 8 para. 4 in force at 22.4.2022, see art. 1(2)

[^key-64594b2c5e164a30c60a4f60209eb25f]: Sch. 8 para. 5 in force at 22.4.2022, see art. 1(2)

[^key-bc4562c3297b97a14937bd2434d3f19d]: Sch. 8 para. 6 in force at 22.4.2022, see art. 1(2)

[^key-2d150737b0a19babf1568d2e24567668]: Sch. 8 para. 7 in force at 22.4.2022, see art. 1(2)

[^key-c667768e3e02bd43d1b31a9ded2ed208]: Sch. 8 para. 8 in force at 22.4.2022, see art. 1(2)

[^key-493c7f8df41f037c97e953eceb4246f5]: Sch. 8 para. 9 in force at 22.4.2022, see art. 1(2)

[^key-4b9da039a772ad8c5df77c5cad5331c5]: Sch. 8 para. 10 in force at 22.4.2022, see art. 1(2)

[^key-f27a1fee5ce29915aace797d0a023368]: Sch. 10 Pt. 1 para. 1 in force at 22.4.2022, see art. 1(2)

[^key-cf8c218fdb215a5bde61d80da1a64c3f]: Sch. 10 Pt. 1 para. 2 in force at 22.4.2022, see art. 1(2)

[^key-e69a4eb300df7c01412d7834c50c1d5a]: Sch. 10 Pt. 1 para. 3 in force at 22.4.2022, see art. 1(2)

[^key-fcbc6301e5feb4666b45b3200ccac666]: Sch. 10 Pt. 1 para. 4 in force at 22.4.2022, see art. 1(2)

[^key-33849a4c309a46b863f94dfaf67ad181]: Sch. 10 Pt. 1 para. 5 in force at 22.4.2022, see art. 1(2)

[^key-744c76e8c14484cdbca1b4dd106d168d]: Sch. 10 Pt. 1 para. 6 in force at 22.4.2022, see art. 1(2)

[^key-737191d11752241aa2a403fdafcfdd27]: Sch. 10 Pt. 1 para. 7 in force at 22.4.2022, see art. 1(2)

[^key-f4e843d433d54f209537cc22bf414b8e]: Sch. 10 Pt. 1 para. 8 in force at 22.4.2022, see art. 1(2)

[^key-3458cf3ea18367b040f3f19b17102d56]: Sch. 10 Pt. 1 para. 9 in force at 22.4.2022, see art. 1(2)

[^key-c309fe0b9f8c08063b7f9b1ba3489d3d]: Sch. 10 Pt. 1 para. 10 in force at 22.4.2022, see art. 1(2)

[^key-352b2b5fe5afdd9ce2be60bf7536c272]: Sch. 10 Pt. 2 para. 1 in force at 22.4.2022, see art. 1(2)

[^key-d9bfe723b98097eee087ecb0438a5294]: Sch. 10 Pt. 2 para. 2 in force at 22.4.2022, see art. 1(2)

[^key-fa34fddd6fd432cb0d1bae96fdadef67]: Sch. 10 Pt. 2 para. 3 in force at 22.4.2022, see art. 1(2)

[^key-ad2dc64f14c2224051c6016736cb22ec]: Sch. 10 Pt. 2 para. 4 in force at 22.4.2022, see art. 1(2)

[^key-98dc8223dda423228b6740c6a700c4bd]: Sch. 10 Pt. 2 para. 5 in force at 22.4.2022, see art. 1(2)

[^key-352821c1bdea79766b1916b9849e91cd]: Sch. 10 Pt. 3 para. 1 in force at 22.4.2022, see art. 1(2)

[^key-9ff9871cc82fbc065a061014691502b1]: Sch. 10 Pt. 3 para. 2 in force at 22.4.2022, see art. 1(2)

[^key-51a68c021033040e48f3468a18ab292c]: Sch. 10 Pt. 3 para. 3 in force at 22.4.2022, see art. 1(2)

[^key-9c9a40003662675c746603d16f971118]: Sch. 10 Pt. 3 para. 4 in force at 22.4.2022, see art. 1(2)

[^key-1059e88d2376eb3cefacdc6a9264eab2]: Sch. 10 Pt. 3 para. 5 in force at 22.4.2022, see art. 1(2)

[^key-e6d00e41fe86bb972649f725785ecd3b]: Sch. 10 Pt. 3 para. 6 in force at 22.4.2022, see art. 1(2)

[^key-ad099bded9f20fe4c4d8d269336be7fd]: Sch. 10 Pt. 3 para. 7 in force at 22.4.2022, see art. 1(2)

[^key-2e7e0e30ed22594e46c81d30538e311a]: Sch. 10 Pt. 3 para. 8 in force at 22.4.2022, see art. 1(2)

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.