and such protective works must be constructed by the undertaker or by the Canal & River Trust at the undertaker’s request with all reasonable dispatch and the undertaker must not commence the construction of a specified work until the engineer has notified the undertaker that the protective works have been completed to the engineer’s reasonable satisfaction such consent not to be unreasonably withheld or delayed.

  • (5) The withholding of an approval of the engineer under this paragraph 31 will be deemed to be unreasonable if it would prevent the undertaker from complying with any condition contained in Schedule 2 (requirements).
  • (6) The undertaker must pay to the Canal & River Trust a capitalised sum representing any reasonably increased and additional cost of maintaining and, when necessary, renewing any works, including any permanent protective works provided under sub-paragraph (4), and of carrying out any additional dredging of the waterway reasonably necessitated by the exercise of any of the powers under this Order but if the cost of maintaining the waterway, or of works of renewal of the waterway, is reduced in consequence of any such works, a capitalised sum representing such reasonable saving is to be set off against any sum payable by the undertaker to the Canal & River Trust under this paragraph.
  • (7) In the event that the undertaker fails to complete the construction of, or part of, the specified works the Canal & River Trust may, if it is reasonably required in order to avoid detriment, serve on the undertaker a notice in writing requesting that construction be completed. Any notice served under this sub-paragraph must state the works that are to be completed by the undertaker and lay out a reasonable timetable for the works’ completion. If the undertaker fails to comply with this notice within 35 working days, the Canal & River Trust may construct any of the specified works, or part of such works, (together with any adjoining works) in order to complete the construction of, or part of, the specified works or make such works and the undertaker must reimburse the Canal & River Trust all costs, fees, charges and expenses it has reasonably incurred in carrying out such works.

Design of works

32

Without prejudice to its obligations under the foregoing provisions of this Part of this Schedule the undertaker must consult, collaborate and respond constructively to any reasonable approach, suggestion, proposal or initiative made by the Canal & River Trust on—

  • (a) the design of the specified works;
  • (b) the environmental effects of those works; and must have regard to such views as may be expressed by the Canal & River Trust in response to such consultation pursuant in particular to the requirements imposed on the Canal & River Trust by section 22 (general environmental and recreational duties) of the British Waterways Act 1995[^f00069] and to the interest of the Canal & River Trust in preserving and enhancing the environment of its waterways; and
  • (c) amendments or alterations to the construction environmental management plan, landscape and ecological management plan, operational environmental management plan, decommissioning environmental management plan (as may be approved pursuant to Schedule 2 (requirements)) in respect of a specified work or a protective work or otherwise in connection with the waterway.

Notice of works

33

The undertaker must give to the engineer 30 days’ notice of its intention to commence the construction of any of the specified works or protective works, or, in the case of repair carried out in an emergency, such notice as may be reasonably practicable so that, in particular, the Canal & River Trust may where appropriate arrange for the publication of notices bringing those works to the attention of users of the Canal & River Trust’s network.

Construction of specified works

34

  • (1) Any specified works or protective works must, when commenced, be constructed—
  • (a) with all reasonable dispatch in accordance with the plans approved or deemed to have been approved or settled as aforesaid and with any specifications made under paragraph 31 (approval of plans, protective works etc.) and paragraph 32 (design of works) of this Part;
  • (b) under the supervision (if given) and to the reasonable satisfaction of the engineer;
  • (c) in such manner as to cause as little detriment to the waterway as is reasonably practicable;
  • (d) in such manner as to cause as little inconvenience as is reasonably practicable to the Canal & River Trust, its officers and agents and all other persons lawfully using the waterways, except to the extent that temporary obstruction has otherwise been agreed by the Canal & River Trust;
  • (e) in such a manner as to ensure that no materials are discharged or deposited into the waterway otherwise than in accordance with article 18 (discharge of water); and
  • (f) in compliance with the Code of Practice (where appropriate and where consistent with the exercise of powers pursuant to this Order and for the timely, safe, economic and efficient delivery of the authorised works);
  • (2) Nothing in this Order authorises the undertaker to make or maintain any permanent works in or over the waterway so as to impede or prevent (whether by reducing the width of the waterway or otherwise) the passage of any vessel which is of a kind (as to its dimensions) for which the Canal & River Trust is required by section 105(1)(b) and (2) of the Transport Act 1968[^f00070] to maintain the waterway.
  • (3) Following the completion of the construction of the specified works the undertaker must restore the waterway to a condition no less satisfactory than its condition immediately prior to the commencement of those works unless otherwise agreed between the undertaker and the Canal & River Trust and save to the extent that any deterioration to the condition of the waterway is not caused by the construction of the specified works.
  • (4) In assessing whether the condition of the waterway is no less satisfactory than immediately prior to the works pursuant to sub-paragraph (3), the Canal & River Trust and the undertaker must take account of any survey issued pursuant to paragraph 30 (survey of waterway) and any other information agreed between them pursuant to this Part.

Prevention of pollution

35

The undertaker must not in the course of constructing a specified work or a protective work or otherwise in connection therewith do or permit anything which may result in the pollution of the waterway or the deposit of materials therein (unless otherwise permitted by the Order or the protective provisions in this Part of this Schedule) and must take such steps as the engineer may reasonably require to avoid or make good any breach of its obligations under this paragraph.

Access to work – provision of information

36

  • (1) The undertaker on being given reasonable notice must—
  • (a) at all reasonable times allow reasonable facilities to the engineer for access to a specified work during its construction; and
  • (b) supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing it.
  • (2) The Canal & River Trust on being given reasonable notice must—
  • (a) at all reasonable times afford reasonable facilities to the undertaker and its agents for access to any works carried out by the Canal & River Trust under this Part during their construction; and
  • (b) supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them and the undertaker must reimburse the Canal & River Trust’s reasonable costs in relation to the supply of such information.

Alterations to the waterway

37

  • (1) If during the construction of a specified work or a protective work or during a period of twenty four months after the completion of those works any alterations or additions, either permanent or temporary, to the waterway are reasonably necessary in consequence of the construction of the specified work or the protective work in order to avoid detriment, and the Canal & River Trust gives to the undertaker reasonable notice of its intention to carry out such alterations or additions (which must be specified in the notice), the undertaker must pay to the Canal & River Trust the reasonable costs of those alterations or additions including, in respect of any such alterations or additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by the Canal & River Trust in maintaining, working and, when necessary, renewing any such alterations or additions.
  • (2) If the cost of maintaining, working or renewing the waterway is reduced in consequence of any such alterations or additions a capitalised sum representing such saving is to be set off against any sum payable by the undertaker to the Canal & River Trust under this paragraph.

Repayment of the Canal & River Trust’s fees, etc.

38

  • (1) The undertaker must repay to the Canal & River Trust in accordance with the Code of Practice all fees, costs, charges and expenses reasonably incurred by the Canal & River Trust—
  • (a) in constructing any protective works under the provisions of paragraph 31 (approval of plans, protective works etc.);
  • (b) in respect of the approval by the engineer of plans submitted by the undertaker and the supervision by the engineer of the construction or repair of a specified work and any protective works;
  • (c) in respect of the employment during the construction of the specified works or any protective works of any inspectors, watchmen and other persons whom it is reasonably necessary to appoint for inspecting, watching and lighting any waterway and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of the specified works or any protective works;
  • (d) in bringing the specified works or any protective works to the notice of users of the Canal & River Trust’s network; and
  • (e) in constructing and/or carrying out any measures related to any specified works or protective works which are reasonably required by the Canal & River Trust to ensure the safe navigation of the waterway save that nothing is to require the Canal & River Trust to construct and/or carry out any measures.
  • (2) If the Canal & River Trust considers that a fee, charge, cost or expense will be payable by the undertaker pursuant to sub-paragraph (1), the Canal & River Trust will first provide an estimate of that fee, charge, cost or expense and supporting information in relation to the estimate to the undertaker along with a proposed timescale for payment for consideration and the undertaker may, within a period of 14 working days—
  • (a) provide confirmation to the Canal & River Trust that the estimate is agreed and pay to the Canal & River Trust, by the date stipulated, that fee, charge, cost or expense; or
  • (b) provide confirmation to the Canal & River Trust that the estimate is not accepted along with a revised estimate and a proposal as to how or why the undertaker considers that the estimate can be reduced and or paid at a later date.
  • (3) The Canal & River Trust must take in to account any representations made by the undertaker in accordance with this paragraph 38 and must, within 15 working days of receipt of the information pursuant to sub-paragraph (1), confirm the amount of the fee, charge, cost or expense to be paid by the undertaker (if any) and the date by which this is to be paid.
  • (4) The Canal & River Trust must, when estimating and incurring any charge, cost or expense pursuant this paragraph 38, do so with a view to being reasonably economic and acting as if the Canal & River Trust were itself to fund the relevant fee, charge, cost or expense.

Making good of detriment; compensation and indemnity, etc.

39

  • (1) If any detriment is caused by the construction or failure of the specified works or the protective works if carried out by the undertaker, the undertaker (if so required by the Canal & River Trust) must make good such detriment and must pay to the Canal & River Trust all reasonable expenses incurred by the Canal & River Trust, and compensation for any loss sustained by the Canal & River Trust in making good or otherwise by reason of the detriment.
  • (2) The undertaker must be responsible for and make good to the Canal & River Trust all costs, charges, damages, expenses and losses not otherwise provided for in this Part which may be occasioned to and reasonably incurred by the Canal & River Trust—
  • (a) by reason of the construction of a specified work or a protective work or the failure of such a work; or
  • (b) by reason of any act or omission of the undertaker or of any person in its employ or of its contractors or others whilst engaged upon the construction of a specified work or protective work, and subject to sub-paragraph (4), the undertaker must effectively indemnify and hold harmless the Canal & River Trust from and against all claims and demands arising out of or in connection with any of the matters referred to in paragraphs (a) and (b) (provided that the Canal & River Trust is not entitled to recover from the undertaker any consequential losses which are not reasonably foreseeable).
  • (3) The fact that any act or thing may have been done by the Canal & River Trust on behalf of the undertaker or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under the engineer’s supervision or in accordance with any directions or awards of an arbitrator is not to (if it was done without negligence on the part of the Canal & River Trust or of any person in its employ or of its contractors or agents) excuse the undertaker from any liability under the provisions of this paragraph.
  • (4) Nothing in sub-paragraph (2) imposes any liability on the undertaker with respect to any detriment, loss or interruption to the extent that it is attributable to the act, neglect or default of the Canal & River Trust, its officers, servants, contractors or agents.
  • (5) The Canal & River Trust must give the undertaker reasonable notice of any such claim or demand as aforesaid and no settlement or compromise of such a claim or demand is to be made without the prior consent of the undertaker.
  • (6) The Canal & River Trust must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph 39 applies. If requested to do so by the undertaker, the Canal & River Trust must provide an explanation of how the claim has been minimised.

Arbitration

40

Any difference arising between the undertaker and the Canal & River Trust under this Part (other than a difference as to the meaning or construction of this Part) must be referred to and settled by arbitration in accordance with article 43 (arbitration) of this Order.

Capitalised sums

41

  • (1) Any capitalised sum which is required to be paid under this Part must be calculated by multiplying the cost of the maintenance or renewal works to the waterway necessitated as a result of the operation of the authorised development by the number of times that the maintenance or renewal works will be required during the operation of the authorised development.
  • (2) The aggregate cap of the undertaker’s gross liability to pay capitalised sums and any other payments or liabilities under the terms of this Part of this Schedule shall be limited to £5,000,000 (five million pounds) for any one occurrence or all occurrences of a series arising out of the one original cause.

As built drawings

42

As soon as reasonably practicable following the completion of the construction of the authorised development, the undertaker must provide to the Canal & River Trust as built drawings of any specified works in a form and scale to be agreed between the undertaker and the Canal & River Trust to show the position of those works in relation to the waterway.

Decommissioning

43

Where the decommissioning environmental management plan identifies activities which may impact the waterway, the protective provisions in this Part 4 of Schedule 15 will, so far as appropriate, apply to those activities as if they were a specified work.

PART 5 — FOR THE PROTECTION OF COTTAM SOLAR PROJECT LIMITED

44

The provisions of this Part apply for the protection of Cottam unless otherwise agreed in writing between the undertaker and Cottam.

45

In this Part—

  • apparatus” means the cables, structures or other infrastructure owned, occupied or maintained by Cottam or its successor in title within the Cottam Work Area;
  • construction” includes execution, placing, altering, replacing, reconstruction, relaying, maintenance, extensions, enlargement and removal; and “construct” and “constructed” must be construed accordingly;
  • Cottam” means an undertaker with the benefit of all or part of the Cottam Solar Project Order for the time being;
  • Cottam Solar Project Order” means the Cottam Solar Project Order[^f00071] as granted by the Secretary of State following the examination of the project known as Cottam Solar Project and given reference number EN010133 by the Planning Inspectorate;
  • Cottam Work Area” means the area for Work Nos. 1A, 2(h), 3, 4A, 5, 6A, 6B, 7A, 8A, 9A, 9B, 10 authorised in the Cottam Solar Project Order;
  • plans” includes sections, drawings, specifications, designs, design data, software, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of the Cottam Work Area; and
  • specified works” means so much of any works or operations authorised by this Order (or authorised by any planning permission intended to operate in conjunction with this Order) as is— within Cottam Work Area; in, on, under, over or within 25 metres of the Cottam Work Area or any apparatus; or may in any way adversely affect any apparatus.

46

The consent of Cottam under this Part is not required where the Cottam Solar Project Order has expired without the authorised development having been commenced pursuant to the Cottam Solar Project Order.

47

Where conditions are included in any consent granted by Cottam pursuant to this Part, the undertaker must comply with the conditions if it chooses to implement or rely on the consent, unless the conditions are waived or varied in writing by Cottam.

48

The undertaker must not under the powers of this Order acquire, extinguish, suspend, override or interfere with any rights that Cottam has in respect of any apparatus or has in respect of the Cottam Work Area without the consent of Cottam, which must not be unreasonably withheld or delayed but which may be made subject to reasonable conditions.

49

  • (1) The undertaker must not under the powers of this Order carry out any specified works without the consent of Cottam, which must not be unreasonably withheld or delayed but which may be made subject to reasonable conditions and if Cottam does not respond within 28 days of the undertaker’s request for consent, then consent is deemed to be given.
  • (2) Subject to obtaining consent pursuant to sub-paragraph (1) and before beginning to construct any specified works, the undertaker must submit plans of the specified works to Cottam and must submit any such further particulars available to it that Cottam may reasonably require.
  • (3) Any specified works must be constructed without unreasonable delay in accordance with the plans approved in writing by Cottam.
  • (4) Any approval of Cottam required under this paragraph may be subject to such reasonable conditions as may be required for the protection or alteration of any apparatus (including proposed apparatus) in the Cottam Work Area or within 25m of the Cottam Work Area or for securing access to such apparatus or the Cottam Work Area.
  • (5) Where Cottam requires any protective works to be carried out either by themselves or by the undertaker (whether of a temporary or permanent nature) such protective works must be carried out to Cottam’s reasonable satisfaction.
  • (6) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of specified works, new plans instead of the plans previously submitted, and the provisions of this paragraph apply to and in respect of the new plans.

50

  • (1) The undertaker must give to Cottam not less than 28 days’ written notice of its intention to commence the construction of the specified works and, not more than 14 days after completion of the construction, must give to Cottam written notice of the completion.
  • (2) The undertaker is not required to comply with paragraph 49 or sub-paragraph (1) in a case of emergency, but in that case it must give to Cottam notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonably practicable subsequently and must comply with paragraph 49 in so far as is reasonably practicable in the circumstances.

51

The undertaker must at all reasonable times during construction of the specified works allow Cottam and its servants and agents access to the specified works and all reasonable facilities for inspection of the specified works.

52

  • (1) After the purpose of any temporary works has been accomplished, the undertaker must with all reasonable dispatch, or after a reasonable period of notice in writing from Cottam requiring the undertaker to do so, remove the temporary works in, on, under, over, or within the Cottam Work Area.
  • (2) If the undertaker fails to remove the temporary works within a reasonable period of receipt of a notice pursuant to sub-paragraph (1), Cottam may remove the temporary works and may recover the reasonable costs of doing so from the undertaker.

53

If in consequence of the exercise of the powers conferred by this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable Cottam to maintain or use the apparatus no less effectively than was possible before the obstruction.

54

The undertaker must not exercise the powers conferred by this Order to prevent or interfere with the access by Cottam to the Cottam Work Area or within 25m of the Cottam Work Area.

55

To ensure its compliance with this Part, the undertaker must before carrying out any works or operations pursuant to this Order within Cottam Work Area or within 25m of the Cottam Work Area request up-to-date written confirmation from Cottam of the location of any apparatus or proposed apparatus.

56

The undertaker and Cottam must each act in good faith and use reasonable endeavours to co-operate with, and provide assistance to, each other as may be required to give effect to the provisions of this Part.

57

The undertaker must pay to Cottam the reasonable expenses incurred by Cottam in connection with the approval of plans, inspection of any specified works or the alteration or protection of any apparatus or the Cottam Work Area or within 25m of the Cottam Work Area.

58

  • (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any specified works, any damage is caused to any apparatus or there is any interruption in any service provided, or in the supply of any goods, by Cottam, or Cottam becomes liable to pay any amount to any third party, the undertaker must—
  • (a) bear and pay the cost reasonably incurred by Cottam in making good such damage or restoring the service or supply; and
  • (b) compensate Cottam for any other expenses, loss, demands, proceedings, damages, claims, penalty, or costs incurred by or recovered from Cottam, by reason or in consequence of any such damage or interruption or Cottam becoming liable to any third party as aforesaid.
  • (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of Cottam, its officers, servants, contractors or agents.
  • (3) Cottam must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise shall be made, unless payment is required in connection with a statutory compensation scheme without first consulting the undertaker and considering its representations.
  • (4) Cottam must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph applies. If requested to do so by the undertaker, Cottam shall provide an explanation of how the claim has been minimised. The undertaker shall only be liable under this paragraph for claims reasonably incurred by Cottam.
  • (5) The fact that any work or thing has been executed or done with the consent of Cottam and in accordance with any conditions or restrictions prescribed by Cottam or in accordance with any plans approved by Cottam or to its satisfaction or in accordance with any directions or award of any arbitrator does not relieve the undertaker from any liability under this Part.

59

Any dispute arising between the undertaker and Cottam under this Part must be determined by arbitration under article 43 (arbitration).

PART 6 — FOR THE PROTECTION OF GATE BURTON ENERGY PARK LIMITED

60

The provisions of this Part apply for the protection of Gate Burton unless otherwise agreed in writing between the undertaker and Gate Burton.

61

In this Part—

  • apparatus” means the cables, structures or other infrastructure owned, occupied or maintained by Gate Burton or its successor in title within the Gate Burton Work No. 4B Area;
  • construction” includes execution, placing, altering, replacing, reconstruction, relaying, maintenance, extensions, enlargement and removal; and “construct” and “constructed” must be construed accordingly;
  • Gate Burton” means an undertaker with the benefit of all or part of the Gate Burton Energy Park Order[^f00072] for the time being;
  • Gate Burton Energy Park Order” means the Gate Burton Energy Park Order;
  • “Gate Burton Work No. 4B Area” means the area for Work No. 4B authorised in the Gate Burton Energy Park Order.
  • plans” includes sections, drawings, specifications, designs, design data, software, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of the Gate Burton Work No. 4B Area; and
  • specified works” means so much of any works or operations authorised by this Order (or authorised by any planning permission intended to operate in conjunction with this Order) as is— within the Gate Burton Work No. 4B Area; in, on, under, over or within 25 metres of the Gate Burton Work No. 4B Area or any apparatus; or may in any way adversely affect any apparatus.

62

The consent of Gate Burton under this Part is not required where the Gate Burton Energy Park Order has expired without the authorised development having been commenced pursuant to the Gate Burton Energy Park Order.

63

Where conditions are included in any consent granted by Gate Burton pursuant to this Part, the undertaker must comply with the conditions if it chooses to implement or rely on the consent, unless the conditions are waived or varied in writing by Gate Burton.

64

The undertaker must not under the powers of this Order acquire, extinguish, suspend, override or interfere with any rights that Gate Burton has in respect of any apparatus or has in respect of the Gate Burton Work No. 4B Area without the consent of Gate Burton, which must not be unreasonably withheld or delayed but which may be made subject to reasonable conditions.

65

  • (1) The undertaker must not under the powers of this Order carry out any specified works without the consent of Gate Burton, which must not be unreasonably withheld or delayed but which may be made subject to reasonable conditions and if Gate Burton does not respond within 28 days of the undertaker’s request for consent, then consent is deemed to be given.
  • (2) Subject to obtaining consent pursuant to sub-paragraph (1) and before beginning to construct any specified works, the undertaker must submit plans of the specified works to Gate Burton and must submit any such further particulars available to it that Gate Burton may reasonably require.
  • (3) Any specified works must be constructed without unreasonable delay in accordance with the plans approved in writing by Gate Burton.
  • (4) Any approval of Gate Burton required under this paragraph may be made subject to such reasonable conditions as may be required for the protection or alteration of any apparatus (including proposed apparatus) in the Gate Burton Work No. 4B Area or for securing access to such apparatus or the Gate Burton Work No. 4B Area.
  • (5) Where Gate Burton requires any protective works to be carried out either by themselves or by the undertaker (whether of a temporary or permanent nature) such protective works must be carried out to Gate Burton’s reasonable satisfaction.
  • (6) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any specified works, new plans instead of the plans previously submitted, and the provisions of this paragraph shall apply to and in respect of the new plans.

66

  • (1) The undertaker must give to Gate Burton not less than 28 days’ written notice of its intention to commence the construction of the specified works and, not more than 14 days after completion of their construction, must give Gate Burton written notice of the completion.
  • (2) The undertaker is not required to comply with paragraph 65 or sub-paragraph (1) in a case of emergency, but in that case it must give to Gate Burton notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonably practicable subsequently and must comply with paragraph 65 in so far as is reasonably practicable in the circumstances.

67

The undertaker must at all reasonable times during construction of the specified works allow Gate Burton and its servants and agents access to the specified works and all reasonable facilities for inspection of the specified works.

68

  • (1) After the purpose of any temporary works has been accomplished, the undertaker must with all reasonable dispatch, or after a reasonable period of notice in writing from Gate Burton requiring the undertaker to do so, remove the temporary works in, on, under, over, or within the Gate Burton Work No. 4B Area.
  • (2) If the undertaker fails to remove the temporary works within a reasonable period of receipt of a notice pursuant to sub-paragraph (1), Gate Burton may remove the temporary works and may recover the reasonable costs of doing so from the undertaker.

69

If in consequence of the exercise of the powers conferred by this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable Gate Burton to maintain or use the apparatus no less effectively than was possible before the obstruction.

70

The undertaker must not exercise the powers conferred by this Order to prevent or interfere with the access by Gate Burton to the Gate Burton Work No. 4B Area.

71

To ensure its compliance with this Part, the undertaker must before carrying out any works or operations pursuant to this Order within Gate Burton Work No. 4B Area request up-to-date written confirmation from Gate Burton of the location of any apparatus or proposed apparatus.

72

The undertaker and Gate Burton must each act in good faith and use reasonable endeavours to co-operate with, and provide assistance to, each other as may be required to give effect to the provisions of this Part.

73

The undertaker must pay to Gate Burton the reasonable expenses incurred by Gate Burton in connection with the approval of plans, inspection of any specified works or the alteration or protection of any apparatus or the Gate Burton Work No. 4B Area.

74

  • (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any specified works, any damage is caused to any apparatus or there is any interruption in any service provided, or in the supply of any goods, by Gate Burton, or Gate Burton becomes liable to pay any amount to any third party, the undertaker must—
  • (a) bear and pay the cost reasonably incurred by Gate Burton in making good such damage or restoring the service or supply; and
  • (b) compensate Gate Burton for any other expenses, loss, demands, proceedings, damages, claims, penalty, or costs incurred by or recovered from Gate Burton, by reason or in consequence of any such damage or interruption or Gate Burton becoming liable to any third party as aforesaid.
  • (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of Gate Burton, its officers, servants, contractors or agents.
  • (3) Gate Burton must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise shall be made, unless payment is required in connection with a statutory compensation scheme without first consulting the undertaker and considering its representations.
  • (4) Gate Burton must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph applies. If requested to do so by the undertaker, Gate Burton shall provide an explanation of how the claim has been minimised. The undertaker shall only be liable under this paragraph for claims reasonably incurred by Gate Burton.
  • (5) The fact that any work or thing has been executed or done with the consent of Gate Burton and in accordance with any conditions or restrictions prescribed by Gate Burton or in accordance with any plans approved by Gate Burton or to its satisfaction or in accordance with any directions or award of any arbitrator does not relieve the undertaker from any liability under this Part.

75

Any dispute arising between the undertaker and Gate Burton under this Part must be determined by arbitration under article 43 (arbitration).

PART 7 — FOR THE PROTECTION OF WEST BURTON SOLAR PROJECT LIMITED

76

The provisions of this Part apply for the protection of West Burton unless otherwise agreed in writing between the undertaker and West Burton.

77

In this Part—

  • apparatus” means the cables, structures or other infrastructure owned, occupied or maintained by West Burton or its successor in title within the West Burton Work No. 5B Area;
  • construction” includes execution, placing, altering, replacing, reconstruction, relaying, maintenance, extensions, enlargement and removal; and “construct” and “constructed” must be construed accordingly;
  • plans” includes sections, drawings, specifications, designs, design data, software, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of the West Burton Work No. 5B Area;
  • specified works” means so much of any works or operations authorised by this Order (or authorised by any planning permission intended to operate in conjunction with this Order) as is— within the West Burton Work No. 5B Area; in, on, under, over or within 25 metres of the West Burton Work No. 5B Area or any apparatus; or may in any way adversely affect any apparatus.
  • West Burton” means an undertaker with the benefit of all or part of the West Burton Solar Project Order for the time being;
  • West Burton Solar Project Order” means the West Burton Solar Project Order[^f00073]; and
  • “West Burton Work No. 5B Area” means the area for Work No. 5B authorised in the West Burton Solar Project Order.

78

The consent of West Burton under this Part is not required where the West Burton Solar Project Order has expired without the authorised development having been commenced pursuant to the West Burton Solar Project Order.

79

Where conditions are included in any consent granted by West Burton pursuant to this Part, the undertaker must comply with the conditions if it chooses to implement or rely on the consent, unless the conditions are waived or varied in writing by West Burton.

80

The undertaker must not under the powers of this Order acquire, extinguish, suspend, override or interfere with any rights that West Burton has in respect of any apparatus or has in respect of the West Burton Work No. 5B Area without the consent of West Burton, which must not be unreasonably withheld or delayed but which may be made subject to reasonable conditions.

81

  • (1) The undertaker must not under the powers of this Order carry out any specified works without the consent of West Burton, which must not be unreasonably withheld or delayed but which may be made subject to reasonable conditions and if West Burton does not respond within 28 days of the undertaker’s request for consent, then consent is deemed to be given.
  • (2) Subject to obtaining consent pursuant to sub-paragraph (1) and before beginning to construct any specified works, the undertaker must submit plans of the specified works to West Burton and must submit any such further particulars available to it that West Burton may reasonably require.
  • (3) Any specified works must be constructed without unreasonable delay in accordance with the plans approved in writing by West Burton.
  • (4) Any approval of West Burton required under this paragraph may be made subject to such reasonable conditions as may be required for the protection or alteration of any apparatus (including proposed apparatus) in the West Burton Work No. 5B Area or for securing access to such apparatus or the West Burton Work No. 5B Area.
  • (5) Where West Burton requires any protective works to be carried out either by themselves or by the undertaker (whether of a temporary or permanent nature) such protective works must be carried out to West Burton’s reasonable satisfaction.
  • (6) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any specified works, new plans instead of the plans previously submitted, and the provisions of this paragraph shall apply to and in respect of the new plans.

82

  • (1) The undertaker must give to West Burton not less than 28 days’ written notice of its intention to commence the construction of the specified works and, not more than 14 days after completion of the construction, must give West Burton written notice of the completion.
  • (2) The undertaker is not required to comply with paragraph 81 or sub-paragraph (1) in a case of emergency, but in that case it must give to West Burton notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonably practicable subsequently and must comply with paragraph 81 in so far as is reasonably practicable in the circumstances.

83

The undertaker must at all reasonable times during construction of the specified works allow West Burton and its servants and agents access to the specified works and all reasonable facilities for inspection of the specified works.

84

  • (1) After the purpose of any temporary works has been accomplished, the undertaker must with all reasonable dispatch, or after a reasonable period of notice in writing from West Burton requiring the undertaker to do so, remove the temporary works in, on, under, over, or within the West Burton Work No. 5B Area.
  • (2) If the undertaker fails to remove the temporary works within a reasonable period of receipt of a notice pursuant to sub-paragraph (1), West Burton may remove the temporary works and may recover the reasonable costs of doing so from the undertaker.

85

If in consequence of the exercise of the powers conferred by this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable West Burton to maintain or use the apparatus no less effectively than was possible before the obstruction.

86

The undertaker must not exercise the powers conferred by this Order to prevent or interfere with the access by West Burton to the West Burton Work No. 5B Area.

87

To ensure its compliance with this Part, the undertaker must before carrying out any works or operations pursuant to this Order within West Burton Work No. 5B Area request up-to-date written confirmation from West Burton of the location of any apparatus or proposed apparatus.

88

The undertaker and West Burton must each act in good faith and use reasonable endeavours to co-operate with, and provide assistance to, each other as may be required to give effect to the provisions of this Part.

89

The undertaker must pay to West Burton the reasonable expenses incurred by West Burton in connection with the approval of plans, inspection of any specified works or the alteration or protection of any apparatus or the West Burton Work No. 5B Area.

90

  • (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any specified works, any damage is caused to any apparatus or there is any interruption in any service provided, or in the supply of any goods, by West Burton, or West Burton becomes liable to pay any amount to any third party, the undertaker must—
  • (a) bear and pay the cost reasonably incurred by West Burton in making good such damage or restoring the service or supply; and
  • (b) compensate West Burton for any other expenses, loss, demands, proceedings, damages, claims, penalty, or costs incurred by or recovered from West Burton, by reason or in consequence of any such damage or interruption or West Burton becoming liable to any third party as aforesaid.
  • (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of West Burton, its officers, servants, contractors or agents.
  • (3) West Burton must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise shall be made, unless payment is required in connection with a statutory compensation scheme without first consulting the undertaker and considering its representations.
  • (4) West Burton must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph applies. If requested to do so by the undertaker, West Burton shall provide an explanation of how the claim has been minimised. The undertaker shall only be liable under this paragraph for claims reasonably incurred by West Burton.
  • (5) The fact that any work or thing has been executed or done with the consent of West Burton and in accordance with any conditions or restrictions prescribed by West Burton or in accordance with any plans approved by West Burton or to its satisfaction or in accordance with any directions or award of any arbitrator does not relieve the undertaker from any liability under this Part.

91

Any dispute arising between the undertaker and West Burton under this Part must be determined by arbitration under article 43 (arbitration).

PART 8 — FOR THE PROTECTION OF LINCOLNSHIRE FIRE AND RESCUE

Interpretation

92

  • (1) For the protection of Lincolnshire Fire and Rescue as referred to in this Part of this Schedule the following provisions have effect, unless otherwise agreed in writing between the undertaker and Lincolnshire Fire and Rescue.
  • (2) In this Part of this Schedule—
  • Index Linked” means an increase in the sums payable on an annual basis or pro rata per diem in accordance with the most recent published figure for the Consumer Price Index, or during any period when no such index exists the index which replaces it or is the nearest equivalent to it; and
  • Lincolnshire Fire and Rescue” means Lincolnshire County Council in its capacity as a fire and rescue authority pursuant to section 1(2)(a) of the Fire and Rescue Services Act 2004[^f00074].

93

  • (1) The undertaker must, prior to the date of final commissioning of Work No. 2, use reasonable endeavours to facilitate a site familiarisation exercise in connection with Work No. 2 of the authorised development for Lincolnshire Fire and Rescue for the purposes of providing the necessary assurance to Lincolnshire Fire and Rescue that all the required systems and measures are in place in accordance with the battery safety management plan.
  • (2) Following the first anniversary of the date of final commissioning of Work No. 2 of the authorised development, the undertaker must use reasonable endeavours to facilitate an annual review of Work No. 2 by Lincolnshire Fire and Rescue at the reasonable request of Lincolnshire Fire and Rescue, up until the year in which the undertaker commences decommissioning of Work No. 2.

Costs

94

  • (1) Pursuant to the provisions set out at paragraph 93, the undertaker must pay to Lincolnshire Fire and Rescue—
  • (a) £16,665 in the first year of operation of the authorised development for, or in connection with Lincolnshire Fire and Rescue’s attendance at the site familiarisation exercise facilitated by the undertaker pursuant to paragraph 93(1), such sum to be paid within 30 days following the date of the site familiarisation exercise; and
  • (b) £1,530 in each subsequent year of operation of the authorised development until the date of decommissioning of Work No. 2, such sums to be paid within 30 days of the date of the annual review for that year, if in that year an annual review has taken place pursuant to paragraph 93(2).
  • (2) The costs payable under paragraph (1)(a) are to be Index Linked.

PART 9 — FOR THE PROTECTION OF CADENT GAS LIMITED

Application

95

For the protection of Cadent the following provisions will, unless otherwise agreed in writing between the undertaker and Cadent, have effect.

Interpretation

96

In this Part of this Schedule—

  • alternative apparatus” means appropriate alternative apparatus to the reasonable satisfaction of Cadent to enable Cadent to fulfil its statutory functions in a manner no less efficient than previously;
  • apparatus” means any gas mains, pipelines, pipes, pressure governors, ventilators, cathodic protection (including transformed rectifiers and any associated groundbeds or cables), cables, marker posts, block valves, hydrogen above ground installations or other apparatus belonging to or maintained by Cadent for the purposes of Cadent’s undertaking together with any replacement apparatus and such other apparatus constructed pursuant to this Order that becomes operational apparatus of Cadent for the purposes of Cadent’s undertaking and includes any structure in which apparatus is or will be lodged or which gives or will give access to apparatus;
  • authorised development” has the same meaning as in article 2 (interpretation) of the Order and includes any associated development authorised by the Order and for the purposes of this Part of this Schedule includes the use and maintenance of the authorised development;
  • Cadent” means Cadent Gas Limited and includes its successors in title or any successor as a gas transporter within the meaning of Part 1 of the Gas Act 1986;
  • Cadent’s undertaking” means the rights, duties and obligations of Cadent Gas Limited as a public gas transporter within the meaning of Section 7 of the Gas Act 1986);
  • “commence” and “commencement” has the same meaning as in article 2 (interpretation) and for the purpose of this Part of this Schedule only includes any below ground surveys, monitoring, work operations, remedial work in respect of any contamination or other adverse ground condition, the receipt and erection of construction plant and equipment, and non-intrusive investigations for the purpose of assessing ground conditions;
  • deed of consent” means a deed of consent, crossing agreement, deed of variation or new deed of grant agreed between the parties acting reasonably in order to vary or replace existing easements, agreements, enactments and other such interests so as to secure land rights and interests as are necessary to carry out, maintain, operate and use the apparatus in a manner consistent with the terms of this Part of this Schedule;
  • “facilities and rights” for construction and for maintenance include any appropriate working areas required to reasonably and safely undertake that construction or maintenance, and any necessary rights of access;
  • functions” includes powers and duties;
  • ground mitigation scheme” means a scheme approved by Cadent (such approval not to be unreasonably withheld or delayed) setting out the necessary measures (if any) for a ground subsidence event;
  • ground monitoring scheme” means a scheme for monitoring ground subsidence which sets out the apparatus which is to be subject to such monitoring, the extent of land to be monitored, the manner in which ground levels are to be monitored, the timescales of any monitoring activities and the extent of ground subsidence which, if exceeded, requires the undertaker to submit for Cadent’s approval a ground mitigation scheme;
  • ground subsidence event” means any ground subsidence identified by the monitoring activities set out in the ground monitoring scheme that has exceeded the level described in the ground monitoring scheme as requiring a ground mitigation scheme;
  • “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;
  • “maintain” and “maintenance” will include the ability and right to do any of the following in relation to any apparatus or alternative apparatus of Cadent including retain, lay, construct, inspect, maintain, protect, use, access, enlarge, replace, renew, remove, decommission or render unusable or remove the apparatus;
  • “plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed;
  • rights” includes rights and restrictive covenants and, in relation to decommissioned apparatus, the surrender of rights, release of liabilities and transfer of decommissioned apparatus; and
  • specified works” means any part of the authorised development or activities (including maintenance) undertaken in association with the authorised development which— will or may be situated over, or within 15 metres measured in any direction of any apparatus the removal of which has not been required by the undertaker under sub-paragraph 101(2) or otherwise; or may in any way adversely affect any apparatus the removal of which has not been required by the undertaker under paragraph 101(2) or otherwise.

On street apparatus

97

  • (1) This Part of this Schedule does not apply to apparatus in respect of which the relations between the undertaker and Cadent are regulated by the provisions of Part 3 of the 1991 Act, except for—
  • (b) where sub-paragraph (2) applies, paragraphs 100 and 101.
  • (2) This sub-paragraph applies where any apparatus is diverted from an alignment within the existing adopted public highway but not wholly replaced within the existing public highway, notwithstanding that any diversion may be carried out under the provisions of Part 3 of the 1991 Act.
  • (3) The protective provisions in this Part of this Schedule apply and take precedence over article 33 (apparatus and rights of statutory undertakers in closed streets) of the Order which does not apply to Cadent.

Apparatus of Cadent where there is a temporary prohibition or restriction on the use of streets and public rights of way

98

  • (1) Where any street or public right of way is subject to temporary prohibition or restriction of use under article 12 (temporary prohibition or restriction of use of streets and public rights of way), if Cadent has any apparatus in the street or accessed via that street Cadent is entitled to the same rights in respect of such apparatus as it enjoyed immediately before the prohibition or restriction of use and the undertaker must grant to Cadent, or procure the granting to Cadent of, legal easements reasonably satisfactory to Cadent in respect of such apparatus and access to it prior to the prohibition or restriction of use of any such street or highway, but nothing in this paragraph affects any right of the undertaker or of Cadent to require the removal of that apparatus under paragraph 101.
  • (2) Notwithstanding the temporary alteration, diversion or restriction of use of any street under the powers of article 12 (temporary prohibition or restriction of use of streets and public rights of way), Cadent will be at liberty at all times to take all necessary access across any such street and to execute and do all such works and things in, upon or under any such street as it would have been entitled to do immediately before such temporary alteration, diversion or restriction in respect of any apparatus which at the time of the prohibition or restriction of use or diversion was in that street.

Protective works to buildings

99

The undertaker must exercise the powers conferred by article 19 (protective works to buildings) so as not to obstruct or render less convenient the access to any apparatus without the written consent of Cadent (such consent not to be unreasonably withheld or delayed).

Acquisition of land

100

  • (1) Regardless of any provision in this Order or anything shown on the land and Crown land plans or contained in the book of reference to the Order, the undertaker may not appropriate or acquire any interest in land or appropriate, acquire, extinguish, interfere with or override any easement or other interest in land of Cadent otherwise than by agreement.
  • (2) As a condition of agreement between the parties in sub-paragraph (1), prior to the construction or maintenance of any part of the authorised development (or in such other timeframe as may be agreed between Cadent and the undertaker) that is subject to the requirements of this Part of this Schedule that will cause any conflict with or breach the terms of any easement or other legal or land interest of Cadent or affect the provisions of any enactment or agreement regulating the relations between Cadent and the undertaker in respect of any apparatus laid or erected in land belonging to or secured by the undertaker, the undertaker must as Cadent reasonably requires enter into such deeds of consent upon such terms and conditions as may be agreed between Cadent and the undertaker acting reasonably and which must be no less favourable on the whole to Cadent unless otherwise agreed by Cadent, and the undertaker must use reasonable endeavours to procure and/or secure the consent to and entering into of such deeds and variations by all other third parties with an interest in the land at that time who are affected by such authorised works.
  • (3) The undertaker and Cadent agree that where there is any inconsistency or duplication between the provisions set out in this Part of this Schedule relating to the relocation or removal of apparatus, including but not limited to the payment of costs and expenses relating to such relocation or removal of apparatus and the provisions of any existing easement, rights, agreements and licences granted, used, enjoyed or exercised by Cadent and other enactments relied upon by Cadent as of right or other use in relation to the apparatus, then the provisions in this Schedule prevail.
  • (4) Any agreement or consent granted by Cadent under paragraph 102 or any other paragraph of this Part of this Schedule, is not to be taken to constitute agreement under sub-paragraph (1).
  • (5) As a condition of an agreement under sub-paragraph (1) that involves de-commissioned apparatus being left in situ on land owned by the undertaker, the undertaker must accept a surrender of any existing easement and/or other interest of Cadent in such decommissioned apparatus and consequently acquire title to such decommissioned apparatus and release Cadent from all liabilities in respect of such de-commissioned apparatus from the date of such surrender.
  • (6) Where an undertaker acquires the freehold of any land which is subject to any Cadent right or interest (including, without limitation, easements and agreements relating to rights or other interests) and the provisions of paragraph102 do not apply, the undertaker must—
  • (a) retain any notice of Cadent’s easement, right or other interest on the title to the relevant land when registering the undertaker’s title to such acquired land; and
  • (b) (where no such notice of Cadent’s easement, right or other interest exists in relation to such acquired land or any such notice is registered only on the Land Charges Register) include (with its application to register title to the undertaker’s interest in such acquired land at the Land Registry) a notice of Cadent’s easement, right or other interest in relation to such acquired land.

Removal of apparatus

101

  • (1) If, in the exercise of powers conferred by this Order, including pursuant to any agreement reached in accordance with paragraph 100, the undertaker acquires any interest in any land in which any apparatus is placed, that apparatus must not be decommissioned or removed and any right of Cadent to maintain that apparatus in that land must not be extinguished or interfered with until alternative apparatus has been constructed, is in operation, and the facilities and rights referred to in sub-paragraph (2) have been provided, to the reasonable satisfaction of Cadent and in accordance with sub-paragraphs (2) to (5) inclusive.
  • (2) If, for the purpose of executing any works in, on, under or over any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to Cadent advance written notice of that requirement, together with a plan and section of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order Cadent reasonably needs to move or remove any of its apparatus) the undertaker must afford to Cadent to its satisfaction (taking into account paragraph 102(1)) the necessary facilities and rights—
  • (a) for the construction of alternative apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by Cadent in respect of the apparatus);
  • (b) subsequently for the maintenance of that apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by Cadent in respect of the apparatus); and
  • (c) to allow access to that apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by Cadent in respect of the apparatus).
  • (3) If the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, Cadent may, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances in an endeavour to assist the undertaker in obtaining the necessary facilities and rights in the land in which the alternative apparatus is to be constructed save that this obligation does not extend to the requirement for Cadent to use its compulsory purchase powers to this end unless it (in its absolute discretion) elects to so do.
  • (4) Any alternative apparatus to be constructed in land of or land secured by the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between Cadent and the undertaker.
  • (5) Cadent must, after the alternative apparatus to be provided or constructed has been agreed, and subject to the prior grant to Cadent of such facilities and rights as are referred to in sub-paragraph (2) or (3), have been afforded to Cadent to its satisfaction, then proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to decommission or remove any apparatus required by the undertaker to be decommissioned or removed under the provisions of this Part of this Schedule.

Facilities and rights for alternative apparatus

102

  • (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to or secures for Cadent facilities and rights in land for the access to, construction and maintenance of alternative apparatus in substitution for apparatus to be decommissioned or removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between the undertaker and Cadent and must be no less favourable on the whole to Cadent than the facilities and rights enjoyed by it in respect of the apparatus to be decommissioned or removed unless otherwise agreed by Cadent.
  • (2) If the facilities and rights to be afforded by the undertaker and agreed with Cadent under sub-paragraph (1) in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are less favourable on the whole to Cadent (in Cadent’s opinion, acting reasonably) than the facilities and rights enjoyed by it in respect of the apparatus to be decommissioned or removed, then the terms and conditions to which those facilities and rights are subject may be referred to arbitration in accordance with paragraph 109 of this Part of this Schedule and the arbitrator must make such provision for the payment of compensation by the undertaker to Cadent as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.

Retained apparatus: protection of Cadent

103

  • (1) Not less than 56 days (or such time period as may be agreed in writing between Cadent and the undertaker) before the commencement of any specified works the undertaker must submit to Cadent a plan and, if reasonably required by Cadent, a ground monitoring scheme in respect of those works.
  • (2) The plan submitted to Cadent under sub-paragraph (1) must include a method statement which describes—
  • (a) the exact position of the works;
  • (b) the level at which these are proposed to be constructed or renewed;
  • (c) the manner of their construction or renewal including details of excavation, positioning of plant etc.;
  • (d) the position of all apparatus;
  • (e) by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus; and
  • (f) any intended maintenance regimes.
  • (3) The undertaker must not commence any specified works until Cadent has given written approval of the plan so submitted (and the ground monitoring scheme if required).
  • (4) Any approval of Cadent given under sub-paragraph (3)
  • (a) may be given subject to reasonably conditions for any purpose mentioned in sub-paragraph (5);
  • (b) must not be unreasonably withheld or delayed; and
  • (c) Cadent must meaningfully engage with the undertaker within 28 days of the date of submission of the plan under sub-paragraph (1).
  • (5) For the purposes of sub-paragraph (4)(b) it will be deemed to be reasonable for any approval to be refused if Cadent considers that the specified works would—
  • (a) cause interference with or risk of damage to its apparatus; or
  • (b) prevent access to its apparatus at any time.
  • (6) In relation to any specified works to which sub-paragraph (1) applies, Cadent may require such modifications to be made to the plan as may be reasonably necessary for the purpose of securing its apparatus against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus.
  • (7) Specified works must only be executed in accordance with—
  • (a) the plan submitted under sub-paragraph (1) (and ground monitoring scheme if required), as approved or as amended from time to time by agreement between the undertaker and Cadent; and
  • (b) all conditions imposed under sub-paragraph (4)(a), and Cadent is entitled to watch and inspect the execution of those works.
  • (8) Where Cadent requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to Cadent’s satisfaction prior to the commencement of any specified works (or any relevant part thereof) for which protective works are required.
  • (9) If Cadent, in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs (1) to (3) and (7) to (9) apply as if the removal of the apparatus has been required by the undertaker under paragraph 101(2).
  • (10) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days (unless otherwise agreed in writing by Cadent and the undertaker) before commencing the execution of the specified works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph will apply to and in respect of the new plan.
  • (11) As soon as reasonably practicable after any ground subsidence event attributable to the authorised development (including such an event attributable to its maintenance)—
  • (a) the undertaker must implement an appropriate ground mitigation scheme; and
  • (b) Cadent retains the right to carry out any further necessary protective works for the safeguarding of its apparatus and can recover any such costs in line with paragraph 104.
  • (12) The undertaker is not required to comply with sub-paragraph (1) where it needs to carry out emergency works but in that case it must give to Cadent notice as soon as is reasonably practicable and a plan of those works and must comply with the conditions imposed under sub-paragraph (4)(a) insofar as is reasonably practicable in the circumstances.
  • (13) In this paragraph, “emergency works” means works whose execution at the time when they are executed is required in order to put an end to, or to prevent the occurrence of, circumstances then existing or imminent (or which the person responsible for the works believes on reasonable grounds to be existing or imminent) which are likely to cause danger to persons or property.

Expenses

104

  • (1) Subject to the following provisions of this paragraph, the undertaker must pay to Cadent on demand, all charges, costs and expenses reasonably anticipated or incurred by Cadent in, or in connection with, the inspection, removal, relaying or replacing, alteration or protection of any apparatus or the construction of any new or alternative apparatus which may be required in consequence of the execution of any authorised development including without limitation—
  • (a) any costs reasonably incurred by or compensation properly paid by Cadent in connection with the acquisition of rights or the exercise of statutory powers for such apparatus including without limitation all costs (including professional fees) incurred by Cadent as a consequence of Cadent—
  • (i) using its own compulsory purchase powers to acquire any necessary rights under paragraph 101(3) if it elects to do so; or
  • (ii) exercising any compulsory purchase powers under this Order transferred to or benefitting Cadent;
  • (b) in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus;
  • (c) the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
  • (d) the approval of plans;
  • (e) the carrying out of protective works (including any protective works pursuant to article 19 (protective works to buildings), plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works if required;
  • (f) the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule; and
  • (g) any watching brief pursuant to paragraph 103(7)(b).
  • (2) There will be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule and which is not re-used as part of the alternative apparatus, that value being calculated after removal.
  • (3) If in accordance with the provisions of this Part of this Schedule—
  • (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
  • (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with paragraph 109 to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to Cadent by virtue of sub-paragraph (1) is to be reduced by the amount of that excess.

  • (4) For the purposes of sub-paragraph (3)
  • (a) an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
  • (b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
  • (5) An amount which apart from this sub-paragraph would be payable to Cadent in respect of works by virtue of sub-paragraph (1) will, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on Cadent any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
  • (6) Where anticipated charges, costs or expenses have been paid by the undertaker pursuant to sub-paragraph (1), if the actual charges, costs or expenses incurred by Cadent are less than the amount already paid by the undertaker, Cadent will repay the difference to the undertaker as soon as reasonable practicable.

Indemnity

105

  • (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works authorised by this Part of this Schedule (including without limitation relocation, diversion, decommissioning, construction and maintenance of apparatus or alternative apparatus) or in consequence of the construction, use, maintenance or failure of any of the authorised development (including works carried out under article 19 (protective works to buildings)) by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by the undertaker) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised development) or property of Cadent, or there is any interruption in any service provided, or in the supply of any goods, by Cadent, or Cadent becomes liable to pay any amount to any third party, the undertaker will—
  • (a) bear and pay on demand, accompanied by an invoice or claim from Cadent, the cost reasonably incurred by Cadent in making good such damage or restoring the supply; and
  • (b) indemnify Cadent for any other expenses, loss, demands, proceedings, damages, claims, penalty, compensation or costs properly incurred by, paid by or recovered from Cadent, by reason or in consequence of any such damage or interruption or Cadent becoming liable to any third party as aforesaid other than arising from any negligence, omission or default of Cadent.
  • (2) The fact that any act or thing may have been done by Cadent on behalf of the undertaker or in accordance with a plan approved by Cadent or in accordance with any requirement of Cadent or under its supervision including under any watching brief will not (unless sub-paragraph (3) applies) excuse the undertaker from liability under the provisions of this sub-paragraph (1) unless Cadent fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan or as otherwise agreed between the undertaker and Cadent.
  • (3) Nothing in sub-paragraph (1) imposes any liability on the undertaker in respect of—
  • (a) any damage or interruption to the extent that it is attributable to the neglect, omission or default of Cadent, its officers, servants, contractors or agents; and
  • (b) any part of the authorised development carried out by Cadent as an assignee, transferee or lessee of the undertaker with the benefit of the Order pursuant to section 156 (benefit of order granting development consent) of the 2008 Act or article 36 (consent to transfer the benefit of the Order) subject to the proviso that once such works become apparatus, any specified works yet to be executed and not falling within this paragraph are subject to the full terms of this Part of this Schedule, including this paragraph in respect of new apparatus.
  • (4) Cadent must give the undertaker reasonable notice of any such third party claim or demand and no settlement, admission of liability or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and considering its representations.
  • (5) Cadent must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph applies. If requested to do so by the undertaker, Cadent must provide an explanation of how the claim has been minimised. The undertaker is only liable under this paragraph for claims reasonably incurred by Cadent.

Enactment and agreements

106

Except where this Part of this Schedule provides otherwise, or by agreement in writing between Cadent and the undertaker, nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and Cadent in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.

Co-operation

107

  • (1) Where in consequence of the proposed construction of any part of the authorised development, the undertaker or Cadent requires the removal of apparatus under paragraph 101(2) or Cadent makes requirements for the protection or alteration of apparatus under paragraph 103, the undertaker must use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of Cadent’s undertaking and Cadent must use its best endeavours to co-operate with the undertaker for that purpose.
  • (2) For the avoidance of doubt whenever Cadent’s consent, agreement or approval is required in relation to plans, documents or other information submitted by the undertaker or the taking of action by Cadent, it must not be unreasonably withheld or delayed.

Access

108

If in consequence of any agreement reached in accordance with paragraph 100 or the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative rights and means of access to such apparatus as will enable Cadent to maintain or use the apparatus no less effectively than was possible before such obstruction.

Arbitration

109

Any difference or dispute arising between the undertaker and Cadent under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and Cadent, be determined by arbitration in accordance with article 43 (arbitration).

Notices

110

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.