The Tillbridge Solar Order 2025
PART 18 — FOR THE PROTECTION OF NATIONAL GRID ELECTRICITY DISTRIBUTION (EAST MIDLANDS) PLC AS ELECTRICITY UNDERTAKER
Application
278
For the protection of National Grid Electricity Distribution (East Midlands) plc the following provisions, unless otherwise agreed in writing between the undertaker and National Grid Electricity Distribution (East Midlands) plc, have effect.
Interpretation
279
In this Part of this Schedule—
- “alternative apparatus” means alternative apparatus adequate to enable NGED to fulfil its statutory functions in a manner not less efficient than previously and where the context requires includes any part of such alternative apparatus;
- “alternative rights” means all and any necessary legal easements, leases, consents, or permissions required by NGED in order to permit or authorise a diversion and to permit or authorise NGED to lay, keep, operate, maintain, adjust, repair, alter, relay, renew, supplement, inspect, examine, test and remove the alternative apparatus;
- “apparatus” means electric lines or electrical plant as defined in the 1989 Act[^f00082], belonging to or maintained by NGED;
- “diversion” means an alteration to the NGED Network in order to enable or facilitate the authorised development;
- “functions” includes powers and duties; “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over or upon land;
- “NGED” means National Grid Electricity Distribution (East Midlands) plc (company number 02366923) whose registered office is at Avonbank, Feeder Road, Bristol, BS2 0TB;
- “NGED Network” means NGED’s distribution network operated pursuant to its distribution licence issued pursuant to section 6 of the 1989 Act;
- “plan” or “plans” includes all designs, drawings, specifications, method statements, programmes, calculations, risk assessments and other documents that are reasonably necessary to properly and sufficiently describe and assess the works to be executed; and
- “specified work” means so much of any of the authorised development that is carried out within 6 metres of any apparatus.
Precedence of 1991 Act in respect of apparatus in streets
280
This Part of this Schedule does not apply to apparatus in respect of which the relations between the undertaker and NGED are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act. No acquisition except by agreement.
281
Regardless of any provision in this Order or anything shown on the land and crown land plans, the undertaker must not acquire any apparatus otherwise than by agreement.
Removal of apparatus
282
- (1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed or requires that apparatus is relocated or diverted, that apparatus must not be removed under this Part of this Schedule and any right of NGED to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed, alternative rights acquired or granted for the alternative apparatus and the alternative apparatus is in operation and access to it has been provided if necessary to the reasonable satisfaction of NGED in accordance with sub-paragraphs (2) to (10) or with such alternative or supplementary provisions as the undertaker and NGED may agree between them.
- (2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, the undertaker must give to NGED written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed.
- (3) If as a consequence of the exercise of any of the powers conferred by this Order NGED reasonably needs to remove or divert any of its apparatus and the removal of that apparatus has not been required by the undertaker under sub-paragraph (2) then NGED must give to the undertaker written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and this Part has effect as if the removal or diversion of such apparatus had been required by the undertaker under sub-paragraph (2).
- (4) If as a consequence of the removal or diversion of apparatus under sub-paragraph (2) or (3) alternative apparatus is to be constructed in land owned or controlled by the undertaker then the undertaker must afford to NGED the necessary facilities, alternative rights and any necessary third party consent or approvals for the construction of alternative apparatus in the other land owned or controlled by the undertaker as reasonably required by NGED.
- (5) If the undertaker or NGED requires to remove or divert any apparatus placed within the Order land and alternative apparatus is to be constructed in land not owned or controlled by the undertaker as a consequence of the removal or diversion of apparatus then NGED shall use its reasonable endeavours to obtain alternative rights in the land in which the alternative apparatus is to be constructed.
- (6) If alternative apparatus is to be constructed in land not owned or controlled by the undertaker and NGED is unable to obtain such alternative rights as are mentioned in sub-paragraph (5), the undertaker and NGED shall consider whether there is an alternative engineering solution that can achieve the diversion without the need for the use of compulsory powers. Should such an alternative engineering solution not be practicable and deliverable in a reasonable timescale and at a reasonable cost (which shall be determined by the undertaker acting reasonably), NGED may but shall not be compelled to use the powers of compulsory acquisition set out in this Order or the 1989 Act to obtain the necessary facilities and rights in the land outside the Order limits in which the alternative apparatus is to be constructed in accordance with a timetable agreed between NGED and the undertaker.
- (7) Any alternative apparatus required pursuant to sub-paragraphs (2) or (3) must be constructed in such manner and in such line or situation as may be agreed between NGED and the undertaker or in default of agreement settled in accordance with paragraph 287 (expert determination).
- (8) NGED must, after the alternative apparatus to be provided or constructed has been agreed or settled in accordance with paragraph 287(2) (expert determination) and, after the acquisition by or grant to NGED of any such facilities and alternative rights as are referred to in sub-paragraphs (2) to (6), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required to be removed by the undertaker under the provisions of this Part of this Schedule.
- (9) Regardless of anything in sub-paragraph (8), if the undertaker gives notice in writing to NGED that it desires itself to execute any work, or part of any work in connection with the construction or removal of apparatus in any land controlled by the undertaker, that work, instead of being executed by NGED, must be executed by the undertaker—
- (a) in accordance with plans and specifications and in such line or situation agreed between the undertaker and NGED, or, in default of agreement, determined in accordance with paragraph 287(2) (expert determination); and
- (b) without unnecessary delay under the superintendence, if given, and to the reasonable satisfaction of NGED.
- (10) Nothing in sub-paragraph (9) authorises the undertaker to execute the placing, installation, bedding, packing, removal, connection or disconnection of any apparatus or alternative apparatus, or execute any filling around the apparatus or alternative apparatus (where the apparatus or alternative apparatus is laid in a trench) within 600 millimetres of the point of connection or disconnection.
Facilities and rights for alternative apparatus
283
- (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to NGED facilities and alternative rights for the construction and maintenance in land of the undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities and alternative rights must be granted upon such terms and conditions as may be agreed between the undertaker and NGED or in default of agreement settled in accordance with paragraph 287(2) (expert determination).
- (2) In settling those terms and conditions in respect of alternative apparatus to be constructed in the land of the undertaker, the expert must—
- (a) give effect to all reasonable requirements of the undertaker for ensuring the safety and efficient operation of the authorised development and for securing any subsequent alterations or adaptations of the alternative apparatus which may be required to prevent interference with any proposed works of the undertaker;
- (b) have regard to the terms and conditions, if any, applicable to the apparatus for which the alternative apparatus is to be substituted;
- (c) have regard to NGED’s ability to fulfil its service obligations and comply with its licence conditions; and
- (d) have regard to the standard form rights NGED ordinarily secures for the type of alternative apparatus to be constructed in the circumstances similar to the authorised development.
- (3) If the facilities and alternative rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and alternative rights are to be granted, are in the opinion of the expert less favourable on the whole to NGED than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the expert must make such provision for the payment of compensation by the undertaker to NGED as appears to the expert to be reasonable having regard to all the circumstances of the particular case.
Retained apparatus
284
- (1) Not less than 60 days before the undertaker intends to start the execution of any specified work where the removal of the apparatus in question has not been required under paragraph 282 (removal of apparatus), the undertaker shall submit to NGED a plan of the works to be executed. Any submission must note the time limits imposed on NGED under sub-paragraph (3).
- (2) Subject to sub-paragraph (3) below the undertaker shall not commence any works to which sub-paragraph (1) applies until NGED has identified any reasonable requirements it has for the alteration or protection of the apparatus, or for securing access to it.
- (3) If by the expiry of 60 days beginning with the date on which a plan under sub-paragraph (1) is submitted NGED has not advised the undertaker in writing of any reasonable requirements for the alteration or protection of the apparatus, or for securing access to it, it shall be deemed not to have any such requirements and the undertaker shall be at liberty to proceed with the works.
- (4) The works referred to in sub-paragraph (1) must be executed only in accordance with the plan submitted under sub-paragraph (1) and in accordance with any reasonable requirements as may be notified in accordance with sub-paragraph (2) by NGED and NGED shall be entitled to watch and inspect the execution of those works.
- (5) At all times when carrying out the authorised development the undertaker must comply with NGED’s Avoidance of Danger from Electricity Overhead Lines and Underground Cables (2014), the Energy Network Association’s A Guide to the Safe Use of Mechanical Plant in the Vicinity of Electricity Overhead Lines (undated), the Health and Safety Executive’s GS6 Avoiding Danger from Overhead Power Lines, and the Health and Safety Executive’s HSG47 Avoiding Danger from Underground Services (Third Edition) (2014) as the same may be replaced from time to time.
- (6) If NGED, in accordance with sub-paragraph (2) and in consequence of the works proposed by the undertaker, reasonably requires the removal or diversion of any apparatus and gives written notice to the undertaker of that requirement, this Part of this Schedule applies as if the removal or diversion of the apparatus had been required by the undertaker under paragraph 282(3) (removal of apparatus).
- (7) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 60 days before commencing the execution of any works, a new plan instead of the plan previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.
- (8) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to NGED notice as soon as is reasonably practicable and a plan of those works as soon as reasonably practicable subsequently and must comply with any reasonable requirements stipulated by NGED under sub-paragraph (2) and with sub-paragraphs (4) and (5) in so far as is reasonably practicable in the circumstances. Nothing in this sub-paragraph prevents NGED from exercising its rights under sub-paragraph (6).
Expenses and costs
285
- (1) Subject to the following provisions of this paragraph, the undertaker must pay to NGED the proper and reasonable expenses incurred by NGED in, or in connection with, the inspection, removal, diversion, alteration or protection of any apparatus, the construction of any alternative apparatus and the acquisition or grant of alternative rights for the alternative apparatus, arising as a result of the powers conferred upon the undertaker pursuant to this Order.
- (2) The value of any apparatus removed under the provisions of this Part of this Schedule must be deducted from any sum payable under sub-paragraph (1), that value being calculated after removal.
- (3) If in accordance with the provisions of this Part of this Schedule NGED requires that alternative apparatus of better type, of greater capacity, of greater dimensions or at a greater depth is necessary in substitution for existing apparatus which for NGED’s network requirements is over and above what is necessary as a consequence of and for the purpose of the authorised development, NGED shall reduce the cost of such additional requirements from the amount payable by the undertaker pursuant to sub-paragraph (1).
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus where such extension is required in consequence of the authorised development; and
- (b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
- (5) An amount which apart from this sub-paragraph would be payable to a utility undertaker in respect of works by virtue of sub-paragraph (1), if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the utility undertaker any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, is to be reduced by the amount which represents that benefit.
286
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any specified work or any subsidence resulting from any of those works any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of NGED the undertaker is to—
- (a) bear and pay the cost reasonably incurred by NGED in making good such damage or restoring the supply; and
- (b) reimburse NGED for any other expenses, loss, damages, penalty or costs reasonably and properly incurred by NGED, by reason or in consequence of any such damage or interruption.
- (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of NGED, its officers, servants, contractors or agents.
- (3) NGED must give the undertaker reasonable notice of any third party claim or demand and no settlement, admission of liability or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and considering their representations.
- (4) NGED must act reasonably in relation to any claim or demand served under sub-paragraph (1) and use its reasonable endeavours to mitigate and to minimise any costs, expenses, loss, claims, demands, proceedings and penalties to which a claim or demand under sub-paragraph (1) applies.
- (5) NGED’s liability to the undertaker for negligence or breach of contract in respect of each diversion shall be limited to the value of that diversion and NGED shall not otherwise be liable to the undertaker for any losses or costs incurred by the undertaker resulting from delays to the authorised development as a result of its failure to undertake works to deliver any alternative apparatus.
Expert determination
287
- (1) Article 43 (arbitration) shall apply to any difference as to the legal interpretation of this Part of this Schedule and as provided for in sub-paragraph (7).
- (2) Save as provided for in sub-paragraph (1) or sub-paragraph (7) any difference under this Part of this Schedule must be referred to and settled by a single independent and suitable person who holds appropriate professional qualifications and is a member of a professional body relevant to the matter in dispute acting as an expert, such person to be agreed by the differing parties or, in the absence of agreement, identified by the President of the Institution of Civil Engineers or the President of the Institution of RICS or the President of the Institution of Engineering and Technology (as relevant and agreed between NGED and the undertaker, both acting reasonably and without delay).
- (3) All parties involved in settling any difference must use best endeavours to do so within 14 days from the date of a dispute first being notified in writing by one party to the other and in the absence of the difference being settled within that period the expert must be appointed within 21 days of the notification of the dispute.
- (4) The costs and fees of the expert and the costs of NGED and the undertaker are payable by the parties in such proportions as the expert may determine. In the absence of such determination the costs and fees of the expert are payable equally by the parties who shall each bear their own costs.
- (5) The expert must—
- (a) invite the parties to make submissions to the expert in writing and copied to the other party to be received by the expert within 14 days of the expert’s appointment;
- (b) permit a party to comment on the submissions made by the other party within 7 days of receipt of the submission;
- (c) issue a decision within 14 days of receipt of the submissions under sub-paragraph (b); and
- (d) give reasons for the decision.
- (6) The expert must consider where relevant—
- (a) the development outcome sought by the undertaker;
- (b) the ability of the undertaker to achieve its outcome in a timely and cost-effective manner;
- (c) the nature of the power sought to be exercised by the undertaker;
- (d) the effectiveness, cost and reasonableness of proposals for mitigation arising from any party;
- (e) NGED’s service obligations and licence conditions; and
- (f) any other important and relevant consideration.
- (7) Any determination by the expert is final and binding, except in the case of manifest error in which case the difference that has been subject to expert determination may be referred to and settled by arbitration under article 43.
PART 19 — FOR THE PROTECTION OF TRENT VALLEY INTERNAL DRAINAGE BOARD
288
The provisions of this Part of this Schedule have effect for the protection of Trent Valley Internal Drainage Board unless otherwise agreed in writing between the undertaker and Trent Valley Internal Drainage Board.
289
In this Part of this Schedule—
- “authorised development” has the same meaning as in article 2(1) (interpretation) of this Order and (unless otherwise specified) for the purposes of this Part of this Schedule includes the operation and maintenance of the authorised development and the construction of any works authorised by this Part of this Schedule;
- “construction” includes execution, placing, altering, replacing, relaying and removal, and “construct” and “constructed” is construed accordingly;
- “drainage work” means any ordinary watercourse and any bank, wall, embankment or other structure, or any appliance constructed or used for land drainage or flood defence which are within the geographical drainage district of Trent Valley Internal Drainage Board and subject to their general supervision;
- “ordinary watercourse” has the meaning given by section 72 (interpretation) of the Land Drainage Act 1991;
- “plans” includes plans, sections, elevations, drawings, specifications and method statements; and
- “specified work” means so much of the authorised development as is in, on, under, over or within 9 metres of a drainage work or is otherwise likely to— affect any drainage work or the total volume or volumetric rate of flow of water in or flowing to or from any drainage work; affect the flow of water in any ordinary watercourse or other surface waters; restrict access to ordinary watercourses; restrict the ability of Trent Valley Internal Drainage Board to spread spoils arising from ordinary watercourses within 9 metres of the landward toe of either side of the banks of the watercourse; or affect the conservation, distribution or use of water resources.
290
- (1) Before commencing construction of a specified work, the undertaker must submit to Trent Valley Internal Drainage Board for approval plans of the specified work and such further particulars available to it as the Trent Valley Internal Drainage Board may reasonably require within 28 days of the submission of the plans.
- (2) A specified work must not be constructed except in accordance with such plans as may be approved in writing by Trent Valley Internal Drainage Board or determined under paragraph 296.
- (3) Any approval of Trent Valley Internal Drainage Board required under this paragraph—
- (a) must not be unreasonably withheld or delayed;
- (b) is deemed to have been given if it is neither given nor refused within 42 days of the submission of the plans for approval, or submission of further particulars (where required by Trent Valley Internal Drainage Board under sub-paragraph (1)) whichever is the later; and
- (c) may be given subject to such reasonable requirements as Trent Valley Internal Drainage Board may make for the protection of any drainage work or for the prevention of flooding or pollution or discharge of its environmental functions.
- (4) Any refusal under this paragraph must be accompanied by a statement of the reasons for refusal.
291
Without limiting the scope of paragraph 290, the requirements which Trent Valley Internal Drainage Board may make under that paragraph include conditions requiring the undertaker at its own expense to construct such protective works, whether temporary or permanent, before or during the construction of the specified work (including the provision of flood banks, walls or embankments or other new works and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably necessary—
- (a) to safeguard any drainage work against damage by reason of any specified work; or
- (b) to secure that the efficiency of any drainage work for flood defence and land drainage purposes is not impaired, and that the risk of flooding is not otherwise increased beyond the level of flood risk that was assessed in the environmental statement, by reason of any specified work.
292
- (1) Subject to sub-paragraph (2), any specified work, and all protective works required by Trent Valley Internal Drainage Board under paragraph 291, must be constructed—
- (a) without unreasonable delay in accordance with the plans approved or deemed to have been approved or settled under this Part of this Schedule;
- (b) to the reasonable satisfaction of Trent Valley Internal Drainage Board; and
- (c) an officer of Trent Valley Internal Drainage Board is entitled to watch and inspect the construction of such works.
- (2) The undertaker must give to Trent Valley Internal Drainage Board—
- (a) not less than 14 days’ notice in writing of its intention to commence construction of any specified work and any protective work; and
- (b) notice in writing of its completion not later than seven days after the date on which it is brought into use.
- (3) If Trent Valley Internal Drainage Board reasonably requires, the undertaker must construct all or part of the protective works so that they are in place prior to the construction of the specified work to which the protective works relate.
- (4) If any part of a specified work or any protective work required by Trent Valley Internal Drainage Board is constructed other than in accordance with the requirements of this Part of this Schedule, Trent Valley Internal Drainage Board may by notice in writing require the undertaker at the undertaker’s expense to comply with the requirements of this Part of this Schedule or (if the undertaker so elects and Trent Valley Internal Drainage Board in writing consents, such consent not to be unreasonably withheld or delayed) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to the reasonable satisfaction of Trent Valley Internal Drainage Board.
- (5) Subject to sub-paragraph (6) and paragraph 296 if, within a reasonable period, being not less than 56 days beginning with the date when a notice under sub-paragraph (4) is served on the undertaker, the undertaker has failed to begin taking steps to comply with the requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, Trent Valley Internal Drainage Board may execute the works specified in the notice and any expenditure reasonably incurred by Trent Valley Internal Drainage Board in so doing is recoverable from the undertaker.
- (6) In the event of any dispute as to whether sub-paragraph (4) is properly applicable to any work in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, Trent Valley Internal Drainage Board must not except in the case of an emergency exercise the powers conferred by sub-paragraph (5) until the dispute has been finally determined in accordance with paragraph 297.
293
If by reason of the construction of a specified work and any protective work or of the failure of any of a specified work the efficiency of any drainage work for flood defence purposes or land drainage is impaired, or that drainage work is otherwise damaged, the impairment or damage must be made good by the undertaker as soon as reasonably practicable to the reasonable satisfaction of Trent Valley Internal Drainage Board and, if the undertaker fails to do so, Trent Valley Internal Drainage Board may make good the impairment or damage and recover from the undertaker the expense reasonably incurred by it in doing so.
294
If by reason of construction of the specified work Trent Valley Internal Drainage Board’s access to land drainage infrastructure, flood defences or equipment maintained for flood defence purposes is materially obstructed, the undertaker must provide such alternative means of access that will allow Trent Valley Internal Drainage Board to maintain the land drainage infrastructure, flood defence or use the equipment no less effectively than was possible before the obstruction within 24 hours of or as soon as reasonably practicable after the undertaker becoming aware of such obstruction.
295
The undertaker must indemnify Trent Valley Internal Drainage Board in respect of reasonable costs, charges and expenses which the relevant drainage authority may reasonably incur by reason of—
- (a) the review, examination or approval of plans under this Part of this Schedule;
- (b) the inspection of the proposed location of the specified work or any protective works and the construction of the specified work or any protective works required by Trent Valley Internal Drainage Board under this Part of this Schedule; and
- (c) the carrying out of any surveys or tests by Trent Valley Internal Drainage Board which are reasonably required in connection with the construction of the specified works and any protective work.
296
- (1) Without limiting the other provisions of this Part of this Schedule, the undertaker must indemnify Trent Valley Internal Drainage Board in respect of all costs and losses, liabilities, proceedings, damages, expenses, claims and demands not otherwise provided for in this Schedule which may be made or taken against, recovered from or incurred by Trent Valley Internal Drainage Board by reason of, or arising out of—
- (a) any damage to any drainage work so as to impair its efficiency for the purposes of flood defence;
- (b) any raising or lowering of the water table in land adjoining the authorised development or any sewers, drains and watercourse; or
- (c) any flooding or increased flooding of any such land
297
Any dispute arising between the undertaker and Trent Valley Internal Drainage Board under this Part of this Schedule, if the parties agree, is to be determined by arbitration under article 43 (arbitration).
SCHEDULE 16 — PROCEDURE FOR DISCHARGE OF REQUIREMENTS
Interpretation
1
In this Schedule—
- “discharge” means any consent, agreement or approval required by— a requirement; a document referred to by a requirement; or a document that has been approved pursuant to a requirement;
- “requirement consultee” means any body or authority named in a requirement as a body to be consulted by the relevant planning authority in discharging that requirement; and
- “start date” means the date of the notification given by the Secretary of State under paragraph 4(2)(c).
Applications made under requirement
2
- (1) Where an application has been made to the relevant planning authority for any consent, agreement or approval required by a requirement, the undertaker must also submit a copy of that application to any requirement consultee.
- (2) Where an application has been made to the relevant planning authority for any consent agreement or approval required by a requirement the relevant planning authority must give notice to the undertaker of its decision on the application within a period of ten weeks beginning with the later of—
- (a) the day immediately following that on which the application is received by the authority;
- (b) the day immediately following that on which further information has been supplied by the undertaker under paragraph 3; or
- (c) such longer period that is agreed in writing by the undertaker and the relevant planning authority.
- (3) Subject to paragraph 4, in the event that the relevant planning authority does not determine an application within the period set out in sub-paragraph (2), the relevant planning authority is to be taken to have granted all parts of the application (without any condition or qualification) at the end of that period.
- (4) Any application made to the relevant planning authority pursuant to sub-paragraph (2) must include a statement to confirm whether it is likely that the subject matter of the application will give rise to any materially new or materially different environmental effects compared to those in the environmental statement and if it will then it must be accompanied by information setting out what those effects are.
- (5) Where an application has been made to the relevant planning authority for any consent, agreement or approval required by a requirement included in this Order and the relevant planning authority does not determine the application within the period set out in sub-paragraph (2) and is accompanied by a report pursuant to sub-paragraph (4) which states that the subject matter of such application is likely to give rise to any materially new or materially different environmental effects compared to those in the environmental statement then the application is to be taken to have been refused by the relevant planning authority at the end of that period.
Further information and consultation
3
- (1) In relation to any application to which this Schedule applies, the relevant planning authority may request such reasonable further information from the undertaker as is necessary to enable it to consider the application.
- (2) In the event that the relevant planning authority considers such further information to be necessary and the provision governing or requiring the application does not specify that consultation with a requirement consultee is required, the relevant planning authority must, within 10 working days of receipt of the application, notify the undertaker in writing specifying the further information required.
- (3) If the provision governing or requiring the application specifies that consultation with a requirement consultee is required, the relevant planning authority must issue the consultation to the requirement consultee within five working days of receipt of the application, and must notify the undertaker in writing specifying any further information the relevant planning authority considers necessary or that is requested by the requirement consultee within five working days of receipt of such a request and in any event within 15 working days of receipt of the application (or such other period as is agreed in writing between the undertaker and the relevant planning authority).
- (4) In the event that the relevant planning authority does not give notification as specified in sub-paragraph (2) or (3) it is deemed to have sufficient information to consider the application and is not thereafter entitled to request further information without the prior agreement of the undertaker.
- (5) Where further information is requested under this paragraph in relation to part only of an application, that part is to be treated as separate from the remainder of the application for the purposes of calculating time periods in paragraph 2 and paragraph 3.
Appeals
4
- (1) The undertaker may appeal in the event that—
- (a) the relevant planning authority refuses an application for any consent, agreement or approval required by a requirement included in this Order or grants it subject to conditions;
- (b) the relevant planning authority is deemed to have refused an application pursuant to paragraph 2(5);
- (c) on receipt of a request for further information pursuant to paragraph 3 the undertaker considers that either the whole or part of the specified information requested by the relevant planning authority is not necessary for consideration of the application; or
- (d) on receipt of any further information requested, the relevant planning authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application.
- (2) The steps to be followed in the appeal process are as follows—
- (a) any appeal by the undertaker must be made within 42 days of the date of the notice of the decision or determination, or (where no determination has been made) the expiry of the time period set out in paragraph 2(2), giving rise to the appeal referred to in sub-paragraph (1);
- (b) the undertaker must submit the appeal documentation to the Secretary of State and must on the same day provide copies of the appeal documentation to the relevant planning authority and any requirement consultee;
- (c) the Secretary of State must appoint a person to determine the appeal as soon as reasonably practicable and must forthwith notify the appeal parties of the identity of the appointed person and the address to which all correspondence for the appointed person’s attention should be sent;
- (d) the relevant planning authority and any requirement consultee must submit written representations to the appointed person in respect of the appeal within 10 working days of the start date and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;
- (e) the undertaker may make any counter-submissions to the appointed person within 10 working days of receipt of written representations pursuant to sub-paragraph (d);
- (f) the appointed person must make their decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable and in any event within 30 working days of the deadline for the receipt of counter-submissions pursuant to sub-paragraph (e); and
- (g) the appointment of the person pursuant to sub-paragraph (c) may be undertaken by a person appointed by the Secretary of State for this purpose instead of by the Secretary of State.
- (3) In the event that the appointed person considers that further information is necessary to enable the appointed person to consider the appeal they must, within five working days of the appointed person’s appointment, notify the appeal parties in writing specifying the further information required.
- (4) Any further information required pursuant to sub-paragraph (3) must be provided by the relevant party to the appointed person and the other appeal parties on the date specified by the appointed person (the “specified date”), and the appointed person must notify the appeal parties of the revised timetable for the appeal on or before that day. The revised timetable for the appeal must require submission of written representations to the appointed person within 10 working days of the specified date, but otherwise the process and time limits set out in sub-paragraphs (d) to (f) of sub-paragraph (2) apply.
- (5) The appointed person may—
- (a) allow or dismiss the appeal; or
- (b) reverse or vary any part of the decision of the relevant planning authority (whether the appeal relates to that part of it or not),
and may deal with the application as if it had been made to them in the first instance.
- (6) The appointed person may proceed to a decision on an appeal taking into account only such written representations as have been sent within the relevant time limits and in the sole discretion of the appointed person such written representations as have been sent outside of the relevant time limits.
- (7) The appointed person may proceed to a decision even though no written representations have been made within the relevant time limits, if it appears to them that there is sufficient material to enable a decision to be made on the merits of the case.
- (8) The decision of the appointed person on an appeal is to be final and binding on the parties, unless proceedings are brought by a claim for judicial review.
- (9) If an approval is given by the appointed person pursuant to this Schedule, it is to be deemed to be an approval for the purpose of Schedule 2 (requirements) as if it had been given by the relevant planning authority. The relevant planning authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) is not to be taken to affect or invalidate the effect of the appointed person’s determination.
- (10) Save where a direction is given pursuant to sub-paragraph (11) requiring the costs of the appointed person to be paid by the relevant planning authority, the reasonable costs of the appointed person must be met by the undertaker.
- (11) On application by the relevant planning authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction and the terms on which it is to be made, the appointed person must have regard to advice on planning appeals and award costs published in Planning Practice Guidance: Appeals (March 2014) or any circular or guidance which may from time to time replace it.
Fees
5
- (1) Where an application is made to the relevant planning authority for a discharge, a fee is to apply and must be paid to the relevant planning authority for each application as follows—
| Application | Fee payable |
|---|---|
| First application for the discharge of each of the requirements 5 (Detailed design approval), 6 (Battery safety management), 7 (Landscape and ecological management plan), 8 (Biodiversity net gain), 10 (Surface and foul water drainage), 12 (Construction environmental management plan), 13 (Operational environmental management plan), 14 (Waste management plan) 15 (Construction traffic management plan), 17 (Public rights of way), 19 (Soils management), and 21 (Decommissioning and restoration). | £2,535 |
| Each subsequent application for the discharge of each of the requirements listed in Row 1. | £578 |
| Any application under requirement 5 (Detailed design approval) in respect of the requirements listed in Row 1. | £578 |
| Any application for the discharge of any other requirements not listed in Row 1. | £145 |
| Any application under requirement 3 (Approved details and amendments to them) in respect of requirements not listed in not listed in Row 1. | £145 |
| Any approval required by a document referred to by any requirement or a document approved pursuant to any requirement. | £145 |
- (2) Where an application under sub-paragraph (1) is made and a fee payable on or after 1 April 2025, then Regulation 18A of the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012[^f00083] (as amended by the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits (England) Amendment Regulations 2023) will apply as modified by this Order, so that “the relevant amount” means the fee payable under this sub paragraph (2)(a), 2(b) or 2(c) above.
- (3) Any fee paid under this Schedule must be refunded to the undertaker within four weeks of—
- (a) the application being rejected as invalidly made; or
- (b) the relevant planning authority failing to determine the application within the relevant period in paragraph 2(2) unless—
- (i) within that period the undertaker agrees, in writing, that the fee is to be retained by the relevant planning authority and credited in respect of a future application; or
- (ii) a longer period of time for determining the application has been agreed pursuant to paragraph 2(2) of this Schedule, as applicable.
Signed
Signed by authority of the Secretary of State for Energy Security and Net Zero
David Wagstaff — Head of Energy Infrastructure Development — Department for Energy Security and Net Zero — 14th October 2025
Explanatory note
(This note is not part of the Order)
EXPLANATORY NOTE
This Order authorises Tillbridge Solar Limited (referred to in this Order as the undertaker) to construct, operate, maintain and decommission a ground mounted solar photovoltaic generating station with a gross electrical output capacity of over 50 megawatts and associated development. The Order would permit the undertaker to acquire, compulsorily or by agreement, land and rights in land and to use land for this purpose.
A copy of the Order plans and the book of reference mentioned in the Order and certified in accordance with article 41 (certification of plans and documents, etc.) of this Order may be inspected free of charge during working hours at Lincolnshire County Council, County Offices, Newland, Lincoln, LN1 1YL.
Footnotes
[^f00001]: 2008 c. 29. Section 37 was amended by section 137(5) of, and paragraph 5 of Schedule 13 to, the Localism Act 2011 (c. 20).
[^f00002]: S.I. 2009/2264, amended by S.I. 2010/439, S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/755, S.I. 2014/469, S.I. 2014/2381, S.I. 2015/377, S.I. 2015/1682, S.I. 2017/524, S.I. 2017/572 and S.I. 2018/378.
[^f00003]: S.I. 2010/103.
[^f00004]: As amended by paragraph 29(1) and (3) of Part 1 of Schedule 13 to the Localism Act 2011 (c. 20).
[^f00005]: S.I. 2017/572.
[^f00006]: As amended by paragraph 55 of Part 1 of Schedule 13 to the Localism Act 2011.
[^f00007]: As amended by section 160 of the Housing and Planning Act 2016 (c. 22) and section 43 of the Wales Act 2017 (c. 4).
[^f00008]: As amended by section 140 of, and paragraph 60 of Part 1 of Schedule 13 to, the Localism Act 2011.
[^f00009]: As amended by paragraph 62 of Part 1 of Schedule 13 to the Localism Act 2011.
[^f00010]: As amended by paragraph 62 of Part 1 of Schedule 13 to the Localism Act 2011.
[^f00011]: 1961 c. 33.
[^f00012]: 1965 c. 56.
[^f00013]: 1980 c. 66.
[^f00014]: 1981 c. 66.
[^f00015]: 1984 c. 27.
[^f00016]: 1989 c. 29.
[^f00017]: 1990 c. 8.
[^f00018]: 1991 c. 22. Section 48(3A) was inserted by section 124 of the Local Transport Act 2008 (c. 26). Sections 78(4), 80(4) and 83(4) were amended by section 40 of, and Schedule 1 to, the Traffic Management Act 2004 (c. 18).
[^f00019]: 2008 c. 29.
[^f00020]: S.I. 2024/943.
[^f00021]: S.I. 2024/807.
[^f00022]: “highway” is defined in section 328(1). For “highway authority” see section 1.
[^f00023]: 1981 c. 67.
[^f00024]: 2003 c. 21.
[^f00025]: “street authority” is defined in section 49 which was amended by paragraph 117 of Schedule 1 to the Infrastructure Act 2015 (c.7).
[^f00026]: 2006 c. 46.
[^f00027]: Section 121A was inserted by paragraph 70 of Schedule 8 to the 1991 Act, and subsequently amended by section 271 of the Greater London Authority Act 1999 (c. 29); section 1(6) of, and paragraphs 70 and 95 of Schedule 1 to, the Infrastructure Act 2015; and S.I. 1999/1920 and S.I. 2001/1400.
[^f00028]: S.I. 2025/116.
[^f00029]: 1991 c. 59. Section 23 was amended by paragraph 192(2) of Schedule 22 to the Environment Act 1995 (c. 25), paragraphs 25 and 32 of Schedule 2 to the Flood and Water Management Act 2010 (c. 29) and S.I. 2013/755.
[^f00030]: Section 32 was amended by S.I. 2013/755.
[^f00031]: Section 66 was amended by paragraphs 25 and 38 of Schedule 2 to the Flood and Water Management Act 2010 and section 86 of the Water Act 2014 (c. 21).
[^f00032]: Paragraph 5 was amended by section 100 of the Natural Environment and Rural Communities Act 2006 (c. 16) and S.I. 2013/755. Paragraph 6 was amended by section 105 of, and paragraph 26 of Schedule 15 to, the Environment Act 1995 and S.I. 2013/755. Paragraph 6A was inserted by section 103(3) of the Environment Act 1995.
[^f00033]: S.I. 2016/1154. Regulation 12 was amended by S.I. 2018/110.
[^f00034]: 2017 c. 20.
[^f00035]: Section 9 was amended by section 4 of, and paragraph 141 of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11) and S.I. 2013/755. There are other amendments to section 9 that are not relevant to this Order.
[^f00036]: S.I. 1997/1160.
[^f00037]: S.I. 2012/605.
[^f00038]: S.I. 2010/948, amended by S.I. 2011/987. There are other amending instruments but none are relevant to this Order.
[^f00039]: 1990 c. 43.
[^f00040]: 1974 c. 40.
[^f00041]: S.I. 2016/362.
[^f00042]: S.I. 2011/935.
[^f00043]: 2004 c. 18.
[^f00044]: 1991 c. 56.
[^f00045]: S.I. 2016/1154.
[^f00046]: 1991 c. 57.
[^f00047]: 2003 c. 21.
[^f00048]: 1981 c. 67.
[^f00049]: 1803 c. xlii.
[^f00050]: 1845 c. 1.
[^f00051]: 1846 c. lxxi.
[^f00052]: 1846 c. ccciv.
[^f00053]: 1847 c. cxc.
[^f00054]: 1865 c. cx.
[^f00055]: 1865 c. cccxxi.
[^f00056]: 1971 c. xiii.
[^f00057]: 1887 c. cxv.
[^f00058]: 1906 c. lvii.
[^f00059]: 1907 c. lxxviii.
[^f00060]: 1928 c. lxvii.
[^f00061]: 1977 c. i.
[^f00062]: 1973 c. 26.
[^f00063]: Section 11 was amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67), section 3 of, and Part 1 of Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c. 71), section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (No. 1), sections 186(2), 187(2) and 188 of, and paragraph 6 of Schedule 14 and paragraph 3 of Schedule 16 to, the Housing and Planning Act 2016 (c. 22) and S.I. 2009/1307.
[^f00064]: Section 11A was inserted by section 186(3) of the Housing and Planning Act 2016.
[^f00065]: Section 11B was inserted by section 187(3) of the Housing and Planning Act 2016.
[^f00066]: Section 12 was amended by section 56(2) of, and Part 1 of Schedule 9 to, the Court Act 1971 (c. 23) and paragraphs (2) and (4) of Schedule 16 to the Housing and Planning Act 2016.
[^f00067]: Section 13 was amended by sections 62(3), 139(4) to (9) and 146 of, and paragraphs 27 and 28 of Schedule 13 and Part 3 of Schedule 23 to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).
[^f00068]: Section 20 was amended by paragraph 4 of Schedule 15 to the Planning and Compensation Act 1991 (c. 34) and S.I. 2009/1307.
[^f00069]: 1995 c. i.
[^f00070]: 1968 c. 73.
[^f00071]: S.I. 2024/943.
[^f00072]: S.I. 2024/807.
[^f00073]: S.I. 2025/116.
[^f00074]: 2004 c. 21.
[^f00075]: S.I. 2016/1154.
[^f00076]: 2016 c. 22. Section 203 was amended by section 147(3) of, and paragraph 5(2)(a) and (b), and paragraph 5(3)(a) and (b) of Schedule 20 to, the Environment Act 2021 (c. 30), and section 37(2)(a) to (d) and 46(1) of the Neighbourhood Planning Act 2017 (c. 20) and regulation 2(i) of S.I. 2017/767.
[^f00077]: Section 172 was amended by section 26(8)(b) and 46(1) of the Neighbourhood Planning Act 2017 (c. 20).
[^f00078]: 2017 c. 20.
[^f00079]: S.I. 2010/675.
[^f00080]: S.I. 1996/825.
[^f00081]: S.I. 1996/551.
[^f00082]: 1989 c. 29. The definition of “electrical plant” (in section 64) was amended by paragraphs 24 and 38(1) and (3) of Schedule 6 to the Utilities Act 2000 (c. 27).
[^f00083]: S.I. 2012/2920.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.