The A122 (Lower Thames Crossing) Development Consent Order 2025
- (2) If during the construction of a specified work or a protective work by the undertaker, the Company gives notice to the undertaker that the Company desires itself to construct that part of the specified work or protective work which in the reasonable opinion of the engineer is endangering the stability of railway property or the safe operation of traffic on the railways of the Company then, if the undertaker decides that part of the specified work or protective work is to be constructed, the Company must assume construction of that part of the specified work or protective work and the undertaker must, regardless of any such approval of a specified work or protective work under paragraph 32(3), pay to the Company all expenses properly and reasonably incurred by the Company and compensation for any direct loss which it may suffer by reason of the execution by the Company of that specified work or protective work.
- (3) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions a capitalised sum representing such saving is to be set off against any sum payable by the undertaker to the Company under this paragraph.
- (4) The engineer must, in respect of the capitalised sums referred to in this paragraph and paragraph 37(a) provide such details of the formula by which those sums have been calculated as the undertaker may reasonably require.
37
The undertaker must repay to the Company all reasonable fees, costs, charges and expenses properly and reasonably incurred by the Company—
- (a) in constructing any part of a specified work on behalf of the undertaker as provided by paragraph 32(3) or in constructing any protective works under the provisions of paragraph 32(4) including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;
- (b) in respect of the reasonable approval by the engineer of plans submitted by the undertaker and the supervision by the engineer of the construction of a specified work or a protective work;
- (c) in respect of the employment or procurement of the services of any inspectors, signallers, watchkeepers and other persons whom it is reasonably necessary to appoint for inspecting, signalling, watching and lighting railway property and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of a specified work or a protective work;
- (d) in respect of any special traffic working resulting from any speed restrictions which may in the reasonable opinion of the engineer, require to be imposed by reason or in consequence of the construction or failure of a specified work or a protective work or from the substitution of diversion of services which may be reasonably necessary for the same reason; and
- (e) in respect of any additional temporary lighting of railway property in the vicinity of the specified works, being lighting made reasonably necessary by reason or in consequence of the construction or failure of a specified work or a protective work.
38
- (1) In this paragraph—
- “EMI” means, subject to sub-paragraph (2), electromagnetic interference with the Company’s apparatus generated by the operation of the authorised development where such interference is of a level which adversely affects the safe operation of the Company’s apparatus;
- “the Company’s apparatus” means any lines, circuits, wires, apparatus or equipment (whether or not modified or installed as part of the authorised development) which are owned or used by the Company for the purpose of transmitting or receiving electrical energy or of radio, telegraphic, telephonic, electric, electronic or other like means of signalling or other communications.
- (2) This paragraph applies to EMI only to the extent that such EMI is not attributable to any change to the Company’s apparatus carried out after approval of plans under paragraph 32(1) for the relevant part of the authorised development giving rise to EMI.
- (3) Subject to sub-paragraph (5), the undertaker must in the design and construction of the authorised development take all measures necessary to prevent EMI and must establish with the Company (both parties acting reasonably) appropriate arrangements to verify their effectiveness.
- (4) In order to facilitate the undertaker’s compliance with sub-paragraph (3)—
- (a) the undertaker must consult with the Company as early as reasonably practicable to identify all of the Company’s apparatus which may be at risk of EMI, and must continue to consult with the Company (both before and after formal submission of plans under paragraph 32(1)) in order to identify all potential causes of EMI and the measures required to eliminate them;
- (b) the Company must make available to the undertaker all information in the possession of the Company reasonably requested by the undertaker in respect of the Company’s apparatus identified under sub-paragraph (a); and
- (c) the Company must allow the undertaker reasonable facilities for the inspection of the Company’s apparatus identified under sub-paragraph (a).
- (5) In any case where it is established that EMI can only reasonably be prevented by modifications to the Company’s apparatus, the Company must not withhold or delay its consent unreasonably to modifications of the Company’s apparatus, but the means of prevention and the method of their execution may be selected at the reasonable discretion of the Company, and in relation to such modifications paragraph 32(1) has effect subject to this sub-paragraph.
- (6) If at any time prior to the completion of the authorised development and regardless of any measures adopted under sub-paragraph (3), the testing or commissioning of the authorised development causes EMI then the undertaker must immediately upon receipt of notification by the Company of such EMI either in writing or communicated orally (such oral communication to be confirmed in writing as soon as reasonably practicable after it has been issued) cease to use (or procure the cessation of use of) the undertaker’s apparatus causing such EMI until all measures necessary have been taken to remedy such EMI by way of modification to the source of such EMI or (in the circumstances, and subject to the consent, specified in sub-paragraph (5)) to the Company’s apparatus.
- (7) In the event of EMI having occurred—
- (a) the undertaker must afford reasonable facilities to the Company for access to the undertaker’s apparatus in the investigation of such EMI;
- (b) the Company must afford reasonable facilities to the undertaker for access to the Company’s apparatus in the investigation of such EMI; and
- (c) the Company must make available to the undertaker any additional material information in its possession reasonably requested by the undertaker in respect of the Company’s apparatus or such EMI.
- (8) Where the Company approves modifications to the Company’s apparatus under sub-paragraphs (5) or (6)—
- (a) the Company must allow the undertaker reasonable facilities for the inspection of the relevant part of the Company’s apparatus; and
- (b) any modifications to the Company’s apparatus approved under those sub-paragraphs must be carried out and completed by the undertaker in accordance with paragraph 33.
- (9) For the purpose of paragraph 37(a) any modifications to the Company’s apparatus under this paragraph are deemed to be protective works referred to in that paragraph.
- (10) In relation to any dispute arising under this paragraph the reference in article 64 (arbitration) to a single arbitrator to be agreed between the parties is to be read as a reference to an arbitrator being a member of the Institution of Engineering and Technology to be agreed.
39
If at any time after the completion of a specified work or a protective work, not being a work vested in the Company, the Company gives notice to the undertaker informing it that the state of maintenance of any part of the specified work or protective work appears to be such as adversely affects the operation of railway property, the undertaker must, on receipt of such notice, take such steps as may be reasonably necessary to put that specified work or protective work in such state of maintenance as to not adversely affect railway property.
40
The undertaker must not provide any illumination or illuminated sign or signal on or in connection with a specified work or a protective work in the vicinity of any railway belonging to the Company unless the undertaker has first consulted the Company and the undertaker must comply with the Company’s reasonable requirements for preventing confusion between such illumination or illuminated sign or signal and any railway signal or other light used for controlling, directing or securing the safety of traffic on the railway.
41
Any additional expenses which the Company may properly and reasonably incur in altering, reconstructing or maintaining railway property under any powers existing at the making of this Order by reason of the existence of a specified work or a protective work must, provided that 56 days’ previous notice of the commencement of such alteration, reconstruction or maintenance has been given to the undertaker, be repaid by the undertaker to the Company.
42
- (1) The undertaker must pay to the Company all reasonable and properly incurred costs, charges, damages and expenses not otherwise provided for in this Part of this Schedule (but subject always to the remaining provisions of this paragraph and to article 67 (no double recovery) which may be occasioned to or reasonably incurred by the Company—
- (a) by reason of the construction or maintenance of a specified work or a protective work or the failure of it; or
- (b) by reason of any act or omission of the undertaker or of any person in the undertaker’s employ or of the undertaker’s contractors or others whilst engaged upon a specified work or a protective work,
and the undertaker must indemnify and keep indemnified the Company from and against all claims and demands arising out of or in connection with a specified work or a protective work or any such failure, act or omission; and the fact that any act or thing may have been done by the Company on behalf of the undertaker or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under the engineer’s supervision will not (if it was done without negligence on the part of the Company or of any person in its employ or of its contractors or agents) excuse the undertaker from any liability under the provisions of this sub-paragraph.
- (2) The Company must—
- (a) give the undertaker written notice of any such claims or demands as soon as reasonably possible after the Company became aware of any such claims or demands;
- (b) not admit liability or make any offer to settle or settle or compromise any such claim or demand without the prior consent of the undertaker (which, if it withholds such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand);
- (c) take all reasonable steps to mitigate any liabilities relating to such claims or demands; and
- (d) keep the undertaker informed in relation to the progress of any such claims and demands and pay due regard to the undertaker’s reasonable representations in relation to them.
- (3) In no circumstances is the undertaker liable to the Company under sub-paragraph (1) for any indirect or consequential loss or loss of profits, except that the sums payable by the undertaker under that sub-paragraph include a sum equivalent to the relevant costs in circumstances where—
- (a) the Company is liable to make payment of the relevant costs pursuant to the terms of an agreement between the Company and a train operator; and
- (b) the existence of that agreement and the extent of the Company’s liability to make payment of the relevant costs pursuant to its terms has previously been disclosed in writing to the undertaker, but not otherwise.
- (4) Subject to the terms of any agreement between the Company and a train operator regarding the timing or method of payment of the relevant costs in respect of that train operator, the Company must promptly pay to each train operator the amount of any sums which the Company receives under sub-paragraph (3) which relates to the relevant costs of that train operator.
- (5) The obligation under sub-paragraph (3) to pay the Company the relevant costs is, in the event of default, enforceable directly by any train operator concerned to the extent that such sums would be payable to that operator under sub-paragraph (4).
- (6) In this paragraph—
- “the relevant costs” means the costs, direct losses and expenses (including loss of revenue) properly and reasonably incurred by each train operator as a consequence of any restriction of the use of the Company’s railway network as a result of the construction, maintenance or failure of a specified work or a protective work or any such act or omission as mentioned in sub-paragraph (1); and
- “train operator” means any person who is authorised to act as the operator of a train by a licence under section 8 (licences) of the Railways Act 1993.
43
The Company must, on receipt of a request from the undertaker, from time to time, provide the undertaker free of charge with written estimates of the costs, charges, expenses, future cost forecasts and other liabilities for which the undertaker is or will become liable under this Part of this Schedule (including the amount of the relevant costs mentioned in paragraph 42 and with such information as may reasonably enable the undertaker to assess the reasonableness of any such estimate or claim made or to be made under this Part of this Schedule (including any claim relating to those relevant costs).
44
In the assessment of any sums payable to the Company under this Part of this Schedule there must not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by the Company if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by the undertaker under this Part of this Schedule or increasing the sums so payable.
45
The undertaker and the Company may, subject in the case of Network Rail to compliance with the terms of its network licence and in the case of HS1 to compliance with the terms of the concession agreement, enter into, and carry into effect, agreements for the transfer to the undertaker of—
- (a) any railway property shown on the works plans or land plans and described in the book of reference;
- (b) any lands, works or other property held in connection with any such railway property; and
- (c) any rights and obligations (whether or not statutory) of the Company relating to any railway property or any lands, works or other property referred to in this paragraph.
46
- (1) Nothing in this Order, or in any enactment incorporated with or applied by this Order, prejudices or affects the operation of Part 1 (the provision of railway services) of the Railways Act 1993.
- (2) Sub-paragraph (3) applies in respect of the land comprised in the plots listed in the second column of the table only.
- (3) In respect of the plots of land to which this sub-paragraph applies, the provisions of article 25 (compulsory acquisition of land) apply in respect of the specified airspace of the land only.
| (1) Location | (2) Plot Reference Number shown on Land Plan | (3) Height above the railhead |
|---|---|---|
| Franks Farm | 44-24, 44-45 and 44-53 | 7800 mm |
| FP252 | 42-123 | 7500 mm |
| Tilbury Viaduct | 23-77 | 6800 mm |
47
The undertaker must no later than 28 days from the date that the documents referred to in article 62 (certification of documents, etc.) are submitted to and certified by the Secretary of State in accordance with that article, provide a set of those documents to the Company in the form of a computer disc with read only memory.
PART 5 — FOR THE PROTECTION OF SPECIFIED GAS UNDERTAKERS
Application
48
For the protection of the gas undertakers referred to in this Part of this Schedule, the following provisions will, unless otherwise agreed in writing between the undertaker and the gas undertaker concerned, have effect.
Interpretation
49
In this Part of this Schedule—
- “alternative apparatus” means appropriate alternative apparatus to the reasonable satisfaction of the gas undertaker to enable the gas undertaker to fulfil its statutory functions in a manner no less efficient than previously;
- “apparatus” means any gas mains, pipes, pressure governors, ventilators, cathodic protections, cables or other apparatus belonging to or maintained by the gas undertaker for the purposes of its undertaking together with any replacement apparatus and such other apparatus constructed pursuant to this Order that becomes operational apparatus of the gas undertaker for the purposes of its undertaking and includes any structure in which apparatus is or will be lodged or which gives or will give access to apparatus;
- “Cadent Gas Limited” means Cadent Gas Limited (company number 10080864), whose registered office is at Pilot Way, Ansty, Coventry, England CV7 9JU;
- “commence” and “commencement” include any surveys, monitoring, work operations, remedial work in respect of any contamination or other adverse ground conditions, the receipt and erection of construction plant and equipment, and non-intrusive investigations for the purpose of assessing ground conditions;
- “deed of consent” means a deed of consent, crossing agreement, deed of variation or new deed of grant agreed between the parties acting reasonably in order to vary or replace existing easements, agreements, enactments and other such interests so as to secure land rights and interests as are necessary to carry out, maintain, operate and use the apparatus in a manner consistent with the terms of this Part of this Schedule;
- “facilities and rights” for construction and for maintenance include any appropriate working areas required to reasonably and safely undertake that construction or maintenance, and any necessary rights of access;
- “functions” includes powers and duties;
- “gas supply” means the transmission, transportation, supply or storage of gas;
- “gas undertaker” means Cadent Gas Limited or Southern Gas Networks plc as the case may be and includes any successor in title or any successor as a gas transporter within the meaning of Part 1 (gas supply) of the Gas Act 1986185;
- “ground mitigation scheme” means a scheme approved by the gas undertaker (such approval not to be unreasonably withheld or delayed) setting out the necessary measures (if any) for a ground subsidence event;
- “ground monitoring scheme” means a scheme for monitoring ground subsidence which sets out the apparatus which is to be subject to such monitoring, the extent of land to be monitored, the manner in which ground levels are to be monitored, the timescales of any monitoring activities and the extent of ground subsidence which, if exceeded, requires the undertaker to submit for the gas undertaker’s approval a ground mitigation scheme;
- “ground subsidence event” means any ground subsidence identified by the monitoring activities set out in the ground monitoring scheme that has exceeded the level described in the ground monitoring scheme as requiring a ground mitigation scheme;
- “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;
- “maintain” and “maintenance” have effect as if the gas undertaker’s existing apparatus was authorised development and as if the term maintain includes protect and use;
- “plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed;
- “rights” includes restrictive covenants and, in relation to decommissioned apparatus, the surrender of rights, release of liabilities and transfer of decommissioned apparatus;
- “Southern Gas Networks” means Southern Gas Networks Plc (company number 05167021, whose registered office is at St Lawrence House, Station Approach, Horley, Surrey, RH6 9HJ);
- “specified works” means any of the authorised development or activities (including maintenance) undertaken in association with the authorised development which—will or may be situated over, or within 15 metres measured in any direction of any apparatus the removal of which has not been required by the undertaker under sub-paragraph 54(2) or otherwise; ormay in any way adversely affect any apparatus the removal of which has not been required by the undertaker under sub-paragraph 54(2) (removal of apparatus) or otherwise; and
- “undertaking” means the rights, duties and obligations of the gas undertaker as a public gas transporter within the meaning of section 7186 of the Gas Act 1986.
On Street apparatus
50
- (1) This Part of this Schedule does not apply to apparatus in respect of which the relations between the undertaker and the gas undertaker are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act, except for—
- (a) paragraphs 51(on street apparatus), 56 (retained apparatus: protection of the gas undertaker), 57 (expenses) and 58 (indemnity); and
- (b) where sub-paragraph (2) applies, paragraphs 54 (removal of apparatus) and 55 (facilities and rights for alternative apparatus).
- (2) This sub-paragraph applies where any apparatus is diverted from an alignment within the existing adopted public highway but not wholly replaced within the existing adopted public highway, notwithstanding that any diversion may be carried out under the provisions of Part 3 of the 1991 Act.
- (3) Paragraph 57 (expenses) does not apply to any part of the authorised development that affects the gas undertaker’s apparatus in a street and which constitutes major highway works, major bridge works or major transport works for the purposes of Part 3 of the 1991 Act, but instead—
- (a) any allowable costs of the measures needing to be taken in relation to that apparatus in consequence of the authorised development, or in order to facilitate their execution, must be determined in accordance with Part 3 and section 85 (sharing of cost of necessary measures) of that Act, and any regulations for the time being having effect under that section; and
- (b) any allowable costs are to be borne by the undertaker and the gas undertaker in such proportions as may be prescribed by any such regulations.
Apparatus of the gas undertaker in stopped up streets
51
- (1) Where any street is stopped up under article 14 (permanent stopping up of streets and private means of access), if the gas undertaker has any apparatus in the street or accessed via that street the gas undertaker is entitled to the same rights in respect of such apparatus as it enjoyed immediately before the stopping up and the undertaker must grant to the gas undertaker, or procure the granting to the gas undertaker of, legal easements reasonably satisfactory to the gas undertaker in respect of such apparatus and access to it prior to the stopping up of any such street or highway, but nothing in this paragraph affects any right of the undertaker or of the gas undertaker to require the removal of that apparatus under paragraph 54 (removal of apparatus).
- (2) Notwithstanding the temporary closure, alteration, diversion or restriction of use of any street under the powers of article 12 (temporary closure, alteration, diversion and restriction of use of streets), the gas undertaker will be at liberty at all times to take all necessary access across any such closed, restricted, altered or diverted street and to execute and do all such works and things in, upon or under any such street as it would have been entitled to do immediately before such temporary closure, alteration, diversion or restriction of use in respect of any apparatus which at the time of the stopping up or diversion was in that street.
Protective works to buildings
52
The undertaker must exercise the powers conferred by article 20 (protective work to land and buildings) so as not to obstruct or render less convenient the access to any apparatus without the written consent of the gas undertaker (such consent not to be unreasonably withheld or delayed).
Acquisition of land
53
- (1) Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference to the Order, the undertaker may not appropriate or acquire any interest in land or appropriate, acquire, extinguish, interfere with or override any easement or other interest in land of the gas undertaker otherwise than by agreement.
- (2) As a condition of agreement between the parties in sub-paragraph (1), prior to the carrying out or maintenance of any part of the authorised development (or in such other timeframe as may be agreed between the gas undertaker and the undertaker) that is subject to the requirements of this Part of this Schedule that will cause any conflict with or breach the terms of any easement or other legal or land interest of the gas undertaker or affect the provisions of any enactment or agreement regulating the relations between the gas undertaker and the undertaker in respect of any apparatus laid or erected in land belonging to or secured by the undertaker, the undertaker must as the gas undertaker reasonably requires enter into such deeds of consent upon such terms and conditions as may be agreed between the gas undertaker and the undertaker acting reasonably and which must be no less favourable on the whole to the gas undertaker unless otherwise agreed by the gas undertaker, and it will be the responsibility of the undertaker to procure or secure the consent to and entering into of such deeds and variations by all other third parties with an interest in the land at that time who are affected by such authorised development or maintenance thereof.
- (3) Where there is any inconsistency or duplication between the provisions set out in this Part of this Schedule relating to the relocation or removal of apparatus, including but not limited to the payment of costs and expenses relating to such relocation or removal of apparatus and the provisions of any existing easement, rights, agreements and licences granted, used, enjoyed or exercised by the gas undertaker and other enactments relied upon by the gas undertaker as of right or other use in relation to the apparatus, then the provisions in this Schedule prevail.
- (4) Any agreement or consent granted by the gas undertaker under paragraph 56 (retained apparatus: protection of the gas undertaker) or any other paragraph of this Part of this Schedule, is not to be taken to constitute agreement under sub-paragraph (1).
- (5) As a condition of an agreement under sub-paragraph (1) that involves de-commissioned apparatus being left in situ the undertaker must accept a surrender of any existing easement or other interest of the gas undertaker in such decommissioned apparatus and release the gas undertaker from all liabilities in respect of such de-commissioned apparatus from the date of such surrender.
- (6) Where an undertaker acquires land which is subject to any right or interest of the gas undertaker (including, without limitation, easements and agreements relating to rights or other interests) and the provisions of paragraph 54 (removal of apparatus) do not apply, the undertaker must, unless the gas undertaker agrees otherwise—
- (a) retain any notice of the gas undertaker’s easement, right or other interest on the title to the relevant land when registering the undertaker’s title to such acquired land; and
- (b) (where no such notice of the gas undertaker’s easement, right or other interest exists in relation to such acquired land or any such notice is registered only on the Land Charges Register) include (with its application to register title to the undertaker’s interest in such acquired land at the Land Registry) a notice of the gas undertaker’s easement, right or other interest in relation to such acquired land.
Removal of apparatus
54
- (1) If, in the exercise of the powers conferred by this Order, including pursuant to any agreement reached in accordance with paragraph 53 (acquisition of land), the undertaker acquires any interest in any land in which any apparatus is placed, that apparatus must not be decommissioned or removed under this Part of this Schedule and any right of the gas undertaker to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed, is in operation, and the facilities and rights referred to in sub-paragraph (2) have been provided, to the reasonable satisfaction of the gas undertaker and in accordance with sub-paragraph (2) to (5) inclusive.
- (2) If, for the purpose of executing any works in, on, under or over any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to the gas undertaker advance written notice of that requirement, together with a plan and section of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order the gas undertaker reasonably needs to move or remove any of its apparatus) the undertaker must afford to the gas undertaker to its satisfaction (taking into account paragraph 55(1) (facilities and rights for alternative apparatus)) the necessary facilities and rights—
- (a) for the construction of alternative apparatus; and
- (b) subsequently for the maintenance of that apparatus.
- (3) If the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, the gas undertaker must, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances in an endeavour to assist the undertaker in obtaining the necessary facilities and rights in the land in which the alternative apparatus is to be constructed save that this obligation does not extend to the requirement for the gas undertaker to use its compulsory purchase powers to this end unless it (in its absolute discretion) elects to so do.
- (4) Any alternative apparatus to be constructed in land of or land secured by the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between the gas undertaker and the undertaker.
- (5) The gas undertaker must, after the alternative apparatus to be provided or constructed has been agreed, and subject to the prior grant to the gas undertaker of such facilities and rights as are referred to in sub-paragraph (2) or (3), then proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to decommission or remove any apparatus required by the undertaker to be decommissioned or removed under the provisions of this Part of this Schedule.
Facilities and rights for alternative apparatus
55
- (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to or secures for the gas undertaker facilities and rights in land for the access to construction and maintenance of alternative apparatus in substitution for apparatus to be decommissioned or removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between the undertaker and the gas undertaker and must be no less favourable on the whole to the gas undertaker than the facilities and rights enjoyed by it in respect of the apparatus to be decommissioned or removed unless otherwise agreed by the gas undertaker.
- (2) If the facilities and rights to be afforded by the undertaker and agreed with the gas undertaker under sub-paragraph (1) in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are less favourable on the whole to the gas undertaker than the facilities and rights enjoyed by it in respect of the apparatus to be decommissioned or removed then the terms and conditions to which those facilities and rights are subject may be referred to arbitration in accordance with paragraph 62 of this Part of this Schedule and the arbitrator must make such provision for the payment of compensation by the undertaker to the gas undertaker as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
Retained apparatus: protection of the gas undertaker
56
- (1) Not less than 56 days before the commencement of any specified works the undertaker must submit to the gas undertaker a plan and, if reasonably required by the gas undertaker, a ground monitoring scheme in respect of those works.
- (2) The plan to be submitted to the gas undertaker under sub-paragraph (1) must include a method statement and describe—
- (a) the exact position of the works;
- (b) the level at which these are proposed to be constructed or renewed;
- (c) the manner of their construction or renewal including details of excavation, positioning of plant etc.;
- (d) the position of all apparatus;
- (e) by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus; and
- (f) any intended maintenance regimes.
- (3) The undertaker must not commence any specified works until the gas undertaker has given written approval of the plan so submitted (and the ground monitoring scheme if required).
- (4) Any approval of the gas undertaker required under sub-paragraph (3)—
- (a) may be given subject to reasonable conditions for any purpose mentioned in sub-paragraph (5); and
- (b) must not be unreasonably withheld or delayed and the gas undertaker must meaningfully engage with the undertaker within 28 days of the date of submission of the plan under sub-paragraph (1).
- (5) The gas undertaker may require such modifications to be made to the plan as may be reasonably necessary for the purpose of securing its apparatus against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus.
- (6) Specified works must only be executed in accordance with—
- (a) the plan submitted under sub-paragraph (1) (and the ground monitoring scheme if required), as approved or as amended from time to time by agreement between the undertaker and the gas undertaker; and
- (b) all conditions imposed under sub-paragraph (4)(a), and the gas undertaker will be entitled to watch and inspect the execution of those works.
- (7) Where the gas undertaker requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to the gas undertaker’s satisfaction prior to the commencement of any specified works (or any relevant part thereof) for which protective works are required prior to commencement.
- (8) If the gas undertaker, in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 48 to 50 and 53 to 55 apply as if the removal of the apparatus had been required by the undertaker under sub-paragraph 54(2) (removal of apparatus).
- (9) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of the specified works, a new plan (and the ground monitoring scheme if required), instead of the plan previously submitted, and having done so the provisions of this paragraph will apply to and in respect of the new plan (and the ground monitoring scheme if required).
- (10) As soon as reasonably practicable after any ground subsidence event attributable to the authorised development (including such an event attributable to its maintenance)—
- (a) the undertaker must implement an appropriate ground mitigation scheme; and
- (b) the gas undertaker retains the right to carry out any further necessary protective works for the safeguarding of its apparatus and can recover any such costs in line with paragraph 57 (expenses).
- (11) The undertaker is not required to comply with sub-paragraph (1) where it needs to carry out emergency works but in that case it must give to the gas undertaker notice as soon as is reasonably practicable and a plan of those works and must comply with the conditions imposed under sub-paragraph (4)(a) insofar as is reasonably practicable in the circumstances.
- (12) In this paragraph, “emergency works” means works whose execution at the time when they are executed is required in order to put an end to, or to prevent the occurrence of, circumstances then existing or imminent (or which the person responsible for the works believes on reasonable grounds to be existing or imminent) which are likely to cause danger to persons or property.
Expenses
57
- (1) Subject to the following provisions of this paragraph, the undertaker must pay to the gas undertaker on demand, all charges, costs and expenses reasonably anticipated or reasonably incurred by the gas undertaker in, or in connection with, the inspection, removal, relaying or replacing, alteration or protection of any apparatus or the construction of any new or alternative apparatus which may be required in consequence of the execution of any authorised development including without limitation—
- (a) any costs reasonably incurred by or compensation properly paid by the gas undertaker in connection with the acquisition of rights or the exercise of statutory powers for such apparatus including without limitation all costs (including professional fees) incurred by the gas undertaker as a consequence of the gas undertaker—
- (i) using its own compulsory purchase powers to acquire any necessary rights under paragraph 54(3) (removal of apparatus) if it elects to do so; or
- (ii) exercising any compulsory purchase powers under this Order transferred to or benefitting the gas undertaker;
- (b) in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus;
- (c) the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
- (d) the approval of plans;
- (e) the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works;
- (f) the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule; and
- (g) any watching brief pursuant to sub-paragraph 56(6) (retained apparatus: protection of the gas undertaker).
- (2) There will be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule and which is not re-used as part of the alternative apparatus, that value being calculated after removal.
- (3) If in accordance with the provisions of this Part of this Schedule—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with paragraph 62 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to the gas undertaker by virtue of sub-paragraph (1) will be reduced by the amount of that excess save to the extent that it is not possible in the circumstances (or it would be unlawful due to a statutory or regulatory change) to obtain the existing type of apparatus at the same capacity and dimensions or place at the existing depth in which case full costs will be borne by the undertaker.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus will not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
- (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole will be treated as if it also had been agreed or had been so determined.
- (5) An amount which apart from this sub-paragraph would be payable to the gas undertaker in respect of works by virtue of sub-paragraph (1) will, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the gas undertaker any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
Indemnity
58
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works authorised by this Part of this Schedule (including without limitation relocation, diversion, decommissioning, construction and maintenance of apparatus or alternative apparatus) or in consequence of the construction, use, maintenance or failure of any of the authorised development (including works carried out under article 20 (protective work to land and buildings)) by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by the undertaker) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised development) or property of the gas undertaker, or there is any interruption in any service provided, or in the supply of any goods, by the gas undertaker, or the gas undertaker becomes liable to pay any amount to any third party, the undertaker will—
- (a) bear and pay on demand accompanied by an invoice or claim from the gas undertaker, the cost reasonably incurred by the gas undertaker in making good such damage or restoring the supply; and
- (b) indemnify the gas undertaker for any other expenses, loss, demands, proceedings, damages, claims, penalty, compensation or costs properly incurred or paid by or recovered from the gas undertaker, by reason or in consequence of any such damage or interruption or the gas undertaker becoming liable to any third party as aforesaid other than arising from any default of the gas undertaker.
- (2) The fact that any act or thing may have been done by the gas undertaker on behalf of the undertaker or in accordance with a plan approved by the gas undertaker or in accordance with any requirement of the gas undertaker or under its supervision including under any watching brief will not (unless sub-paragraph (3) applies) excuse the undertaker from liability under the provisions of this sub-paragraph (1) unless the gas undertaker fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan.
- (3) Nothing in sub-paragraph (1) imposes any liability on the undertaker in respect of—
- (a) any damage or interruption to the extent that it is attributable to the neglect or default of the gas undertaker, its officers, servants, contractors or agents;
- (b) any part of the authorised development carried out by the gas undertaker in the exercise of any functions conferred by this Order pursuant to a grant or transfer under article 8 (consent to transfer benefit of Order); and
- (c) any indirect or consequential loss of any third party (including but not limited to loss of use, revenue, profit, contract, production, increased cost of working or business interruption) arising from any such damage or interruption, which is not reasonably foreseeable.
- (4) The gas undertaker must give the undertaker reasonable notice of any such third party claim or demand and no settlement, admission of liability or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and considering their representations.
Enactments and agreements
59
Except where this Part of this Schedule provides otherwise, nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and the gas undertaker in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
Co-operation
60
- (1) Where in consequence of the proposed construction of any part of the authorised development, the undertaker or the gas undertaker requires the removal of apparatus under paragraph 54(2) (removal of apparatus) or the gas undertaker makes requirements for the protection or alteration of apparatus under paragraph 56 (retained apparatus: protection of the gas undertaker), the undertaker must use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of the gas undertaker’s undertaking and the gas undertaker must use its best endeavours to co-operate with the undertaker for that purpose.
- (2) For the avoidance of doubt whenever the gas undertaker’s consent, agreement or approval is required in relation to plans, documents or other information submitted by the undertaker or the taking of action by the undertaker, it must not be unreasonably withheld or delayed.
Access
61
If in consequence of any agreement reached in accordance with paragraph 53(1) (acquisition of land) or the powers conferred by this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative rights and means of access to such apparatus as will enable the gas undertaker to maintain or use the apparatus no less effectively than was possible before such obstruction.
Arbitration
62
Save for differences or disputes arising under paragraph 54(2) and (4) (removal of apparatus) any difference or dispute arising between the undertaker and the gas undertaker under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and the gas undertaker, be determined by arbitration in accordance with article 64 (arbitration).
Notices
63
Notwithstanding article 63 (service of notices) any plans submitted to the gas undertaker by the undertaker pursuant to paragraph 56(1) (retained apparatus: protection of the gas undertaker) must be sent via email and post to such email and postal addresses as the gas undertaker may from time to time appoint for that purpose and notify to the undertaker in writing.
PART 6 — FOR THE PROTECTION OF NATIONAL GAS TRANSMISSION PLC AS GAS UNDERTAKER
Application
64
- (1) For the protection of National Grid as referred to in this Part of this Schedule the following provisions have effect, unless otherwise agreed in writing between the undertaker and National Grid.
- (2) Subject to sub-paragraph (3) or to the extent otherwise agreed in writing between the undertaker and National Grid, where the benefit of this Order is transferred or granted to another person under article 8 (consent to transfer benefit of Order)—
- (a) any agreement of the type mentioned in sub-paragraph (1) has effect as if it had been made between National Grid and the transferee or grantee (as the case may be); and
- (b) written notice of the transfer or grant must be given to National Grid on or before the date of that transfer or grant.
- (3) Sub-paragraph (2) does not apply where the benefit of the Order is transferred or granted to National Grid (but see paragraph 74(3)(b) (indemnity)).
Interpretation
65
In this Part of this Schedule—
- “alternative apparatus” means appropriate alternative apparatus to the reasonable satisfaction of National Grid to enable National Grid to fulfil its statutory functions in a manner no less efficient than previously;
- “apparatus” means any gas mains, pipes, pressure governors, ventilators, cathodic protections, cables or other apparatus belonging to or maintained by National Grid for the purposes of gas supply together with any replacement apparatus and such other apparatus constructed pursuant to the Order that becomes operational apparatus of National Grid for the purposes of transmission, distribution or supply and includes any structure in which apparatus is or will be lodged or which gives or will give access to apparatus;
- “commence” and “commencement” in paragraph 72 (retained apparatus: protection of the gas undertaker) of this Part of this Schedule includes any below ground surveys, monitoring, ground work operations or the receipt and erection of construction plant and equipment;
- “deed of consent” means a deed of consent, crossing agreement, deed of variation or new deed of grant agreed between the parties acting reasonably in order to vary or replace existing easements, agreements, and other such interests so as to secure land rights and interests as are necessary to carry out, maintain, operate and use the apparatus in a manner consistent with the terms of this Part of this Schedule;
- “functions” includes powers and duties;
- “ground mitigation scheme” means a scheme approved by National Grid (such approval not to be unreasonably withheld or delayed) setting out the necessary measures (if any) for a ground subsidence event;
- “ground monitoring scheme” means a scheme for monitoring ground subsidence which sets out the apparatus which is to be subject to such monitoring, the extent of land to be monitored, the manner in which ground levels are to be monitored, the timescales of any monitoring activities and the extent of ground subsidence which, if exceeded, requires the undertaker to submit for National Grid’s approval a ground mitigation scheme;
- “ground subsidence event” means any ground subsidence identified by the monitoring activities set out in the ground monitoring scheme that has exceeded the level described in the ground monitoring scheme as requiring a ground mitigation scheme;
- “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;
- “maintain” and “maintenance” includes the ability and right to do any of the following in relation to any apparatus or alternative apparatus of National Grid including construct, use, repair, alter, inspect, renew or remove the apparatus;
- “National Grid” means National Gas Transmission Plc (company number 02006000, whose registered office is at National Grid House, Warwick Technology Park, Gallows Hill, Warwick, CV34 6DA) or any successor as a gas transporter within the meaning of Part 1 (gas supply) of the Gas Act 1986;
- “plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed; and
- “specified works” means any of the authorised development or activities undertaken in association with the authorised development (including maintenance) which—will or may be situated over, or within 15 metres measured in any direction of any apparatus the removal of which has not been required by the undertaker under paragraph 70(2) or otherwise; ormay in any way adversely affect any apparatus the removal of which has not been required by the undertaker under paragraph 70(2) (removal of apparatus) or otherwise.
66
Except for paragraphs 67 (apparatus of National Grid in stopped up streets), 72 (retained apparatus: protection of gas undertaker), 73 (expenses) and 74 (indemnity) of this Part of this Schedule which will apply in respect of the exercise of all or any powers under the Order affecting the rights and apparatus of National Grid, the other provisions of this Part of this Schedule do not apply to apparatus in respect of which the relations between the undertaker and National Grid are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act.
Apparatus of National Grid in stopped up streets
67
- (1) Where any street is stopped up under article 14 (permanent stopping up of streets and private means of access), if National Grid has any apparatus in the street or accessed via that street National Grid has the same rights in respect of that apparatus as it enjoyed immediately before the stopping up and the undertaker must grant to National Grid, or procure the granting to National Grid of, legal easements reasonably satisfactory to National Grid in respect of such apparatus and access to it prior to the stopping up of any such street but nothing in this paragraph affects any right of the undertaker or National Grid to require the removal of that apparatus under paragraph 70 or the power of the undertaker, subject to compliance with this sub-paragraph, to carry out works under paragraph 72 (retained apparatus: protection of the gas undertaker).
- (2) (Notwithstanding the temporary closure, alteration, diversion or restriction of use of any street under the powers of article 12 (temporary closure alteration, diversion and restriction of use of streets), National Grid is at liberty at all times to take all necessary access across any such street and to execute and do all such works and things in, upon or under any such street as may be reasonably necessary or desirable to enable it to maintain any apparatus which at the time of the closure, alteration, diversion or restriction of use was in that street.
Protective works to buildings
68
The undertaker must exercise the powers conferred by article 20 (protective work to land and buildings) so as not to obstruct or render less convenient the access to any apparatus without the written consent of National Grid (such consent not to be unreasonably withheld).
Acquisition of land
69
- (1) Regardless of any provision in this Order or anything shown on the land plans, the undertaker may not acquire any interest in land or apparatus or override any easement or other interest of National Grid otherwise than by agreement.
- (2) As a condition of an agreement between the parties in sub-paragraph (1), prior to the carrying out or maintenance of any part of the authorised development (or in such other timeframe as may be agreed between National Grid and the undertaker) that is subject to the requirements of this Part of this Schedule that will cause any conflict with or breach the terms of any easement or other legal or land interest of National Grid or affect the provisions of any enactment or agreement regulating the relations between National Grid and the undertaker in respect of any apparatus laid or erected in land belonging to or secured by the undertaker, the undertaker must as National Grid reasonably requires enter into such deeds of consent upon such terms and conditions as may be agreed between National Grid and the undertaker acting reasonably and which must be no less favourable on the whole to National Grid unless otherwise agreed by National Grid, and it will be the responsibility of the undertaker to procure and secure the consent and entering into of such deeds and variations by all other third parties with an interest in the land at that time who are affected by such authorised development or maintenance thereof.
- (3) Where there is any inconsistency or duplication between the provisions set out in this Part of this Schedule relating to the relocation or removal of apparatus (including but not limited to the payment of costs and expenses relating to such relocation or removal of apparatus) and the provisions of any existing easement, rights, agreements and licences granted, used, enjoyed or exercised by National Grid or other enactments relied upon by National Grid as of right or other use in relation to the apparatus, then the provisions in this Schedule prevail.
- (4) Any agreement or consent granted by National Grid under paragraph 72 (retained apparatus: protection of the gas undertaker) or any other paragraph of this Part of this Schedule, is not to be taken to constitute agreement under sub-paragraph (1).
Removal of apparatus
70
- (1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in or possesses temporarily any land in which any apparatus is placed, that apparatus must not be removed under this Part of this Schedule and any right of National Grid to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed, and is in operation to the reasonable satisfaction of National Grid in accordance with sub-paragraphs (2) to (5).
- (2) If, for the purpose of executing any works in, on, under or over any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to National Grid advance written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order National Grid reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to National Grid to its reasonable satisfaction (taking into account paragraph 71(1) (facilities and rights for alternative apparatus)) the necessary facilities and rights—
- (a) for the construction of alternative apparatus in other land of, or secured by, the undertaker; and
- (b) subsequently for the maintenance of that apparatus.
- (3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of or land secured by the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed, National Grid must, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances in an endeavour to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed save that this obligation does not extend to the requirement for National Grid to use its compulsory purchase powers to this end unless it elects to so do.
- (4) Any alternative apparatus to be constructed in land of or land secured by the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between National Grid and the undertaker.
- (5) National Grid must, after the alternative apparatus to be provided or constructed has been agreed, and subject to the grant to National Grid of any such facilities and rights as are referred to in sub-paragraph (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
Facilities and rights for alternative apparatus
71
- (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to or secures for National Grid facilities and rights in land for the construction, use, maintenance and protection of alternative apparatus in substitution for apparatus to be removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between the undertaker and National Grid and must be no less favourable on the whole to National Grid than the facilities and rights enjoyed by it in respect of the apparatus to be removed unless otherwise agreed by National Grid.
- (2) If the facilities and rights to be afforded by the undertaker under sub-paragraph (1) in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are less favourable on the whole to National Grid than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the matter may be referred to arbitration in accordance with paragraph 78 (arbitration) of this Part of this Schedule and the arbitrator must make such provision for the payment of compensation by the undertaker to National Grid as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
Retained apparatus: protection of gas undertaker
72
- (1) Not less than 56 days before the commencement of any specified works the undertaker must submit to National Grid a plan and, if reasonably required by National Grid, a ground monitoring scheme in respect of those works.
- (2) The plan to be submitted to National Grid under sub-paragraph (1) must include a method statement and describe—
- (a) the exact position of the works;
- (b) the level at which these are proposed to be constructed or renewed;
- (c) the manner of their construction or renewal including details of excavation, positioning of plant etc;
- (d) the position of all apparatus;
- (e) by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus; and
- (f) any intended maintenance regimes.
- (3) The undertaker must not commence any specified works until National Grid has given written approval of the plan so submitted.
- (4) Any approval of National Grid required under sub-paragraph (3)—
- (a) may be given subject to reasonable conditions for any purpose mentioned in sub-paragraphs (5) or (7); and
- (b) must not be unreasonably withheld or delayed.
- (5) National Grid may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its apparatus against interference or risk of damage for the provision of protective works or for the purpose of providing or securing proper and convenient means of access to any apparatus.
- (6) Specified works must only be executed in accordance with—
- (a) the plan, submitted under sub-paragraph (1), as approved or as amended from time to time by agreement between the undertaker and National Grid; and
- (b) such reasonable requirements as may be made in accordance with sub-paragraphs (5) or (7) by National Grid for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and National Grid will be entitled to watch and inspect the execution of those works.
- (7) Where under sub-paragraph (6) National Grid requires any protective works to be carried out by itself or by the undertaker such protective works (whether of a temporary or permanent nature) must be carried out to National Grid’s satisfaction prior to the commencement of any specified works for which protective works are required and National Grid must give notice of its requirement for such works within 42 days of the date of submission of a plan pursuant to this paragraph (except in an emergency).
- (8) If National Grid in accordance with sub-paragraphs (5) or (7) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 64 to 66 and 69 to 71 apply as if the removal of the apparatus had been required by the undertaker under paragraph 70(2) (removal of apparatus).
- (9) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of the specified works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph will apply to and in respect of the new plan.
- (10) As soon as reasonably practicable after any ground subsidence event attributable to the authorised development or its maintenance—
- (a) the undertaker must implement an appropriate ground mitigation scheme; and
- (b) National Grid retains the right to carry out any further necessary protective works for the safeguarding of its apparatus and can recover any such costs in line with paragraph 73 (expenses).
- (11) The undertaker will not be required to comply with sub-paragraph (1) where it needs to carry out emergency works but in that case it must give to National Grid notice as soon as is reasonably practicable and a plan of those works and must comply with sub-paragraphs (5) to (7) insofar as is reasonably practicable in the circumstances.
- (12) In sub-paragraph (11), “emergency works” means works whose execution at the time when they are executed is required in order to put an end to, or to prevent the occurrence of, circumstances then existing or imminent (or which the person responsible for the works believes on reasonable grounds to be existing or imminent) which are likely to cause danger to persons or property.
Expenses
73
- (1) Subject to the following provisions of this paragraph, the undertaker must pay to National Grid within 30 days of receipt of an itemised invoice or claim from National Grid all charges, costs and expenses reasonably anticipated within the following three months or reasonably and properly incurred by National Grid in, or in connection with, the inspection, removal, relaying or replacing, alteration or protection of any apparatus or the construction of any new or alternative apparatus which may be required in consequence of the execution of any authorised development or its maintenance including without limitation—
- (a) any costs reasonably incurred by or compensation properly paid by National Grid in connection with the acquisition of rights or the exercise of statutory powers for such apparatus including without limitation all costs incurred by National Grid as a consequence of National Grid—
- (i) using its own compulsory purchase powers to acquire any necessary rights under paragraph 70(3) (removal of apparatus); or
- (ii) exercising any compulsory purchase powers in the Order transferred to or benefitting National Grid;
- (b) in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus, where no written diversion agreement is otherwise in place;
- (c) the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
- (d) the approval of plans;
- (e) the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works;
- (f) the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule.
- (2) There will be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule and which is not re-used as part of the alternative apparatus, that value being calculated after removal.
- (3) If in accordance with the provisions of this Part of this Schedule—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.