The A122 (Lower Thames Crossing) Development Consent Order 2025
| (1) Road | (2) Extent |
|---|---|
| Diverted footway/cycle track along Park Pale | Between points 4/4 and 4/5 as shown on sheet 3 of the rights of way and access plans. |
| Diverted footway/cycle track NCN177 | Between points 11/1 and 11/7 as shown on sheet 3 of the rights of way and access plans. |
| Footway/cycle track in the verge of Park Pale | Between points 11/7 and 11/3 and between points 11/4 and 11/9 as shown on sheet 3 of the rights of way and access plans. |
| Public footpath NS179, re-designated to bridleway | Between points 11/8 on sheet 3 and 5/14 on sheet 4, as shown on sheets 3 and 4 of the rights of way and access plans. |
| New bridleway between NS179 and Brewers Road | Between points 5/14 and 5/3 as shown on sheet 4 of the rights of way and access plans. |
| New footway/cycle/horse-riding track across Brewers Road bridge to form part of NCN177 | Between points 5/13 and 5/20 as shown on sheet 4 of the rights of way and access plans. |
| New footway/cycle/horse-riding track in the verge of Brewers Road to form part of NCN177, from west of Brewers Road bridge to Cobham Hall access road | Between points 5/19 and 5/18 as shown on sheet 4 of the rights of way and access plans. |
| Footway/cycle track redesignated to footway/cycle/horse-riding track in the verge of Brewers Road to form part of NCN177, from Cobham Hall access road to Halfpence Lane roundabout | Between points 5/17, 5/9, 12/3 and 6/11 as shown on sheet 4 of the rights of way and access plans. |
| Horse-riding track in the verge of Thong Lane | Between points 6/51 and 6/52 as shown on sheet 4 of the rights of way and access plans. |
| Footway/cycle/horse-riding track in the verge of Thong Lane | Between points 6/8 and 6/48 as shown on sheet 4 of the rights of way and access plans. |
| New section of cycle track east of Thong Lane connecting to footway/cycle/horse-riding track in the verge of Thong Lane | Between points 6/47 and 6/3 as shown on sheet 4 of the rights of way and access plans. |
| New section of cycle track west of Thong Lane connecting to new bridleway to the west of Thong | Between points 6/45 and 6/50 as shown on sheet 4 of the rights of way and access plans. |
| New bridleway to the west of Thong | Between points 6/49 on sheet 4 and /12 on sheet 11, as shown on sheets 4, 6 and 11 of the rights of way and access plans. |
| Bridleway link from Thong Lane to Darnley Trail | Between points 6/9 and 6/41 as shown on sheet 4 of the rights of way and access plans. |
| Footway/cycle track in the highway verge from Halfpence Lane roundabout to Valley Drive, to form part of NCN177 | Between points 6/11 on sheet 4 and 9/1 on sheet 6 and between points 9/1, 9/2, 9/3, 9/4, 6/30, 10/6 and 10/18 on sheet 6, as shown on sheets 4 and 6 of the rights of way and access plans. |
| Darnley Trail (permissive path) between Halfpence Lane roundabout and road leading to Scalers Hill House | Between points 6/11 and A11 as shown on sheet 4 of the rights of way and access plans. |
| Byway NS195 | Between points 6/44 and 6/46 as shown on sheet 4 of the rights of way and access plans. |
| Byway NS311 | Between points 6/46 on sheet 4 and 6/53 on sheet 5 as shown on sheets 4 and 5 of the rights of way and access plans. |
| Permissive path between NS311 and Jeskyns Community Woodland (overlaps with a section of footpath NS177) | Between point 6/53 on sheet 5 and point 8/21 and 8/22 on sheet 6, as shown on sheets 5 and 6 of the rights of way and access plans. |
| Section of improved public footpath NS177 | Between points 6/54 on sheet 5 and 6/56 on sheet 6 as shown on sheets 5 and 6 of the rights of way and access plans. |
| New bridleway between Jeskyns Community Woodland and Church Road | Between points 6/35 and 8/25 as shown on sheet 6 of the rights of way and access plans. |
| Public footpath NS175A re-designated to cycle track | Between points 8/26, 8/27, 8/28 and 10/4 as shown on sheet 6 of the rights of way and access plans. |
| Permissive path leading to Jeskyns Community Woodland car park | Between points 8/20 and 8/21 as shown on sheet 6 of the rights of way and access plans. |
| Footway/cycle track in the highway verge from Hever Court Road to Valley Drive | Between points 10/21, 10/5, 10/6 and 10/18 as shown on sheet 6 of the rights of way and access plans. |
| Cycle track between Hever Court Road and Valley Drive re-designated to bridleway | Between points 10/5 and 10/22 as shown on sheet 6 of the rights of way and access plans. |
| Public footpath NG17 (western end) extended and re-designated to bridleway from Valley Drive to NS174 | Between points 10/7 and 10/9 as shown on sheet 6 of the rights of way and access plans. |
| Bridleway from NG17 to NS169 | Between points 10/9 on sheet 6 and 10/10 on sheet 11, as shown on sheets 6 and 11 of the rights of way and access plans. |
| Bridleway NS174 diverted and replaced by a public footpath | Between points 10/9 and 6/33 as shown on sheet 6 of the rights of way and access plans. |
| Diverted public footpath NS167 | Between points 10/8 and 6/32 as shown on sheets 6 and 11 of the rights of way and access plans. |
| Section of diverted public footpath NS167 re-designated to bridleway | Between points 10/12 and 6/10 as shown on sheet 11 of the rights of way and access plans. |
| Public footpath NS169 re-designated to cycle track | Between points 10/10 and 10/11 as shown on sheet 11 of the rights of way and access plans. |
| Bridleway from public right of way NS169 to diverted public right of way NS167 | Between points 10/10 and 10/12 as shown on sheet 11 of the rights of way and access plans. |
| Bridleway on Thong Lane over the A122 Lower Thames Crossing bridge | Between points 6/6 and 6/12 as shown on sheet 11 of the rights of way and access plans. |
| Bridleway from Thong Lane over the A122 Lower Thames Crossing bridge to NG9 | Between points 6/5 on sheet 11 and 6/16 on sheet 13, as shown on sheets 11 and 13 of the rights of way and access plans. |
| Bridleway | Between points 6/14 and 6/17 as shown on sheet 13 of the rights of way and access plans. |
| Public footpath | Between points 6/13 and 6/18 as shown on sheet 13 of the rights of way and access plans. |
| Public footpath | Between points 6/19 and 6/20 as shown on sheet 13 of the rights of way and access plans. |
| Public footpath NG7 (north-western section) | Between points 6/21 and 6/22 as shown on sheet 13 of the rights of way and access plans. |
| Public footpath NG7 (central section replaced by a bridleway) | Between points 6/22 and 6/31 as shown on sheet 13 of the rights of way and access plans. |
| Footpath NG8 (northern section) redesignated to bridleway | Between points 6/31 and 6/55 as shown on sheet 13 of the rights of way and access plans. |
| New bridleway from A226 Rochester Road | Between points 6/23 and 6/15 as shown on sheet 13 of the rights of way and access plans. |
| New bridleway from A226 Gravesend Road to Shorne Ifield Road | Between points 6/24 on sheet 13 and 6/25 on sheet 11, as shown on sheets 11 and 13 of the rights of way and access plans. |
| New footway/cycle/horse-riding track in the verge of the A226 Gravesend Road | Between points 6/29 on sheet 12 and 6/28 on sheet 13, as shown on sheets 12 and 13 of the rights of way and access plans. |
| New bridleway between bridleway from the A226 Gravesend Road to Shorne Ifield Road and Thong Lane over the A122 Lower Thames Crossing bridge | Between points 6/27 and 6/26 as shown on sheet 11 of the rights of way and access plans. |
| Public footpath FP146 (Two Forts Way) redesignated to cycle track | Between points 14/7 and 14/12 as shown on sheet 16 of the rights of way and access plans. |
| New public footpath linking FP146 (Two Forts Way) to FP200 | Between points 14/8 on sheet 16 and 14/23 on sheet 20, as shown on sheets 16 and 20 of the rights of way and access plans. |
| New permissive path linking FP146 (Two Forts Way) to FP200 (branch off main path) | Between points 14/20 and 14/21 as shown on sheet 20 of the rights of way and access plans. |
| New permissive path link through Tilbury Fields | Between points 14/9 on sheet 16 and 14/19 on sheet 20, as shown on sheets 16 and 20 of the rights of way and access plans. |
| New public footpath linking Tilbury Fields to FP200 | Between points 14/10 on sheet 16 and 14/23 on sheet 20, and between points 14/19 and 14/22 on sheet 20, as shown on sheets 16 and 20 of the rights of way and access plans. |
| New permissive path linking Tilbury Fields to FP200 (branch off main path) | Between points 14/18 and 14/11 as shown on sheet 16 of the rights of way and access plans. |
| New permissive path linking Tilbury Fields to FP200 (branch off main path) | Between points 14/16 and 14/17 as shown on sheet 16 of the rights of way and access plans. |
| New permissive path linking FP146 (Two Forts Way) to the Tilbury Field earthwork | Between points 14/13 and 14/15 as shown on sheet 16 of the rights of way and access plans. |
| Eastern section of FP200 redesignated to bridleway | Between points 13/2 and 13/3 as shown on sheet 19 of the rights of way and access plans. |
| New bridleway connecting to FP200 | Between points 13/3 on sheet 19 and 14/23 on sheet 20 and between points 14/23 and 14/25 on sheet 20 as shown on sheets 19 and 20 of the rights of way and access plans. |
| Section of FP200 near (south of) Station Road redesignated to bridleway | Between points 14/25 on sheet 20 and 14/24 on sheet 23, as shown on sheets 20 and 23 of the rights of way and access plans. |
| New permissive path adjacent East Tilbury Battery | Between points 13/4 on sheet 19 and 13/6 on sheet 22 as shown on sheets 19 and 22 of the rights of way and access plans. |
| New bridleway link from southern end of FP200 to Station Road | Between points 13/3 on sheet 19 and 13/10 on sheet 22 as shown on sheets 19 and 22 of the rights of way and access plans. |
| New permissive path connecting FP147 to Princess Margaret Road | Between points 13/5 and 13/7 as shown on sheet 22 of the rights of way and access plans. |
| New permissive path link to Princess Margaret Road | Between points 13/8 and 13/9 as shown on sheet 22 of the rights of way and access plans. |
| New footway/cycle/horse-riding track in the verge of Station Road | Between points 13/11 on sheet 22 and 13/12 on sheet 23 as shown on sheets 22 and 23 of the rights of way and access plans. |
| New bridleway from FP200 to Station Road | Between points 14/6 and 13/13 as shown on sheet 23 of the rights of way and access plans. |
| Public footpath FP200 – diverted section | Between points 14/6 and 14/5 as shown on sheets 20 and 23 of the rights of way and access plans. |
| Public footpath FP200 – improved northern section | Between points 14/5 and A9 as shown on sheet 23 of the rights of way and access plans. |
| Bridleway BR58 (Coal Road) – diverted section | Between points 16/1 and 16/2 as shown on sheet 23 of the rights of way and access plans. |
| Bridleway BR58 (Coal Road) – improved section | Between points 16/2 and 16/4 as shown on sheet 23 of the rights of way and access plans. |
| Improved public footpath FP61 | Between points 16/3 and 24/6 as shown on sheet 24 of the rights of way and access plans. |
| Diverted public footpath FP61 (diversion to reconnect to BR58) | Between points 16/4 on sheet 23 and 24/6 on sheet 24 as shown on sheets 23 and 24 of the rights of way and access plans. |
| New footway/cycle track in the verge of Muckingford Road between Beechcroft Avenue and Blue Anchor Lane | Between points 15/10 and 24/7 as shown on sheet 24 of the rights of way and access plans. |
| New footway/cycle/horse-riding track in the verge of Muckingford Road and Linford Road between Blue Anchor Lane and Turnpike Lane | Between points 24/7 on sheet 24 and 24/8 on sheet 25, as shown on sheets 24 and 25 of the rights of way and access plans. |
| New footway/cycle track in the verge of Linford Road between Turnpike Lane and Atherton Gardens | Between points 24/8 and 15/7 as shown on sheet 25 of the rights of way and access plans. |
| Realigned public footpath FP78 re-designated to bridleway along new alignment (in the verge) of High House Lane | Between points 19/1 and 19/2 as shown on sheet 28 of the rights of way and access plans. |
| Public footpath FP95 re-designated to bridleway | Between points 21/1 and F2 as shown on sheet 28 of the rights of way and access plans. |
| New bridleway between FP95 and FP79 | Between points F2 and 21/2 as shown on sheet 28 of the rights of way and access plans. |
| Public footpath FP79 diverted and redesignated to bridleway | Between points 21/2 and 21/4 as shown on sheet 28 of the rights of way and access plans. |
| Public footpath FP79 re-designated to bridleway north of A122 Lower Thames Crossing | Between points 21/4 on sheet 28 and 21/3 on sheet 32, as shown on sheets 28 and 32 of the rights of way and access plans. |
| Footway/cycle track in the verge of the A1013 Stanford Road | Between points 23/7 on sheet 26 and 23/8 on sheet 32, as shown on sheets 26, 29 and 32 of the rights of way and access plans. |
| Gammonfields Way bridleway | Between points 25/1 and 25/2 as shown on sheet 29 of the rights of way and access plans. |
| New bridleway through Blackshots | Between points 28/6 on sheet 29 and 28/7 on sheet 33, as shown on sheets 29 and 33 of the rights of way and access plans. |
| New horse-riding track in the verge of the A1013 Stanford Road, between FP79 and A1013/Rectory Road junction | Between points 21/3 and 23/10 as shown on sheet 32 of the rights of way and access plans. |
| Footway/cycle track in the verge of Rectory Road | Between points 32/14 and 32/15 as shown on sheet 32 of the rights of way and access plans. |
| Horse-riding track in the verge of Rectory Road | Between points 32/14 and 23/11 as shown on sheet 32 of the rights of way and access plans. |
| Footway/cycle track in the verge of Baker Street | Between points 27/1 and 27/2 as shown on sheet 29 of the rights of way and access plans. |
| Bridleway between Mill Lane (bridleway BR206) and Neville’s Field/Woolings Close | Between points 28/2 on sheet 29 and 31/2 on sheet 32, as shown on sheets 29 and 32 of the rights of way and access plans. |
| Bridleway between Mill Lane (bridleway BR206) and Rectory Road | Between points 31/2 and A13 as shown on sheet 32 of the rights of way and access plans. |
| Footway/cycle track in the verge of Stifford Clays Road | Between points 32/1 and 32/4 as shown on sheet 33 of the rights of way and access plans. |
| Cycle track from Stifford Clays Road to Green Lane | Between points 32/2 and 32/16 as shown on sheet 33 of the rights of way and access plans. |
| Green Lane bridleway | Between points 33/1 and 33/4 as shown on sheet 33 of the rights of way and access plans |
| Bridleway from Green Lane to bridleway BR219 | Between points 33/2 on sheet 33 and 33/7 on sheet 35, as shown on sheets 33 and 35 of the rights of way and access plans. |
| Bridleway BR219 | Between points 33/7 on sheet 35 and 41/7 on sheet 41, as shown on sheets 35 and 41 of the rights of way and access plans. |
| Public footpath from FP136 to BR219 | Between points 34/6 and 33/5 as shown on sheet 38 of the rights of way and access plans. |
| Improved public footpath FP136 | Between points 34/6 and 34/1 as shown on sheet 38 of the rights of way and access plans. |
| Diverted public footpath FP136 | Between points 34/1 and 34/4 as shown on sheet 38 of the rights of way and access plans. |
| Public footpath FP136 re-designated to bridleway | Between points 34/5 on sheet 38 and 41/7 on sheet 41, as shown on sheets 38 and 41 of the rights of way and access plans. |
| Bridleway from FP135 to FP136 | Between points 34/5 on sheet 38 and 34/3 on sheet 41, as shown on sheets 38 and 41 of the rights of way and access plans. |
| Public footpath FP135 re-designated to bridleway | Between points G3 on sheet 39 and s34/3 on sheet 41, as shown on sheets 38, 39 and 41 of the rights of way and access plans. |
| Bridleway adjacent to B186 North Road | Between points 35/5 and 35/8 as shown on sheet 39 of the rights of way and access plans. |
| Footway/cycle/horse-riding track in the verge of the B186 North Road | Between points 35/8 and 35/6 as shown on sheet 39 of the rights of way and access plans. |
| Public footpath FP151 re-designated to bridleway | Between points 36/2 and 36/3 as shown on sheet 39 of the rights of way and access plans. |
| Public footpath FP254 re-designated to bridleway | Between points 36/3 on sheet 39 and 41/8 on sheet 42 as shown on sheets 39 and 42 of the rights of way and access plans. |
| Public footpath FP252 re-designated to bridleway | Between points 36/3 on sheet 39 and 36/1 on sheet 42 as shown on sheets 39 and 42 of the rights of way and access plans. |
| Diverted public footpath FP251 | Between points 45/3 and 45/4 as shown on sheet 42 of the rights of way and access plans. |
| Bridleway adjacent to Dennis Road | Between points 36/5 and 40/4 as shown on sheet 40 of the rights of way and access plans. |
| Footway/cycle/horse-riding track in the verge of Dennis Road/Dennises Lane | Between points 40/4 on sheet 40 and 36/4 on sheet 42 and between points 36/6 and 36/7 on sheet 42 as shown on sheets 40 and 42 of the rights of way and access plans. |
| Permissive path to the west of diverted public footpath FP230 | Between points 39/1 and 39/2 as shown on sheet 43 of the rights of way and access plans. |
| Diverted public footpath FP230 | Between points 39/2, 39/3, 39/5 and 39/7 as shown on sheet 43 of the rights of way and access plans. |
| Permissive path in Thames Chase Forest overlapping with diverted public footpath FP230 | Between points 39/2, 39/3, 39/5 and 39/7 as shown on sheet 43 of the rights of way and access plans. |
| Section of diverted public footpath FP230 re-designated to bridleway | Between points 39/6 and 39/7 as shown on sheet 43 of the rights of way and access plans. |
| Permissive path between diverted public footpath FP230 and bridleway connecting Clay Tye Road to FP230 | Between points 39/5 and 43/5 as shown on sheet 43 of the rights of way and access plans. |
| Bridleway connecting Clay Tye Road to diverted public footpath FP230 | Between points 43/5 and 39/4 as shown on sheet 43 of the rights of way and access plans. |
| New permissive path linking Thames Chase Forest Centre to BR289 | Between points 40/1 on sheet 43 and 43/3 and 43/4 on sheet 44 as shown on sheets 43 and 44 of the rights of way and access plans. |
| New permissive path connection to culvert by M25 | Between points 43/3 and 40/2 as shown on sheet 44 of the rights of way and access plans. |
| Bridleway BR183 (southern section, south of the M25) | Between points 41/1 on sheet 44 and 37/28 on sheet 45 as shown on sheets 44 and 45 of the rights of way and access plans. |
| Bridleway BR183 (diverted section, south of the M25) | Between points 37/28 and 37/29 as shown on sheet 45 of the rights of way and access plans. |
| Bridleway BR183 (northern section, south of the M25) | Between points 37/29 and 37/30 as shown on sheet 45 of the rights of way and access plans. |
| New bridleway to the north of existing bridleway BR183 | Between points 37/30 and 37/24 as shown on sheet 45 of the rights of way and access plans. |
| Footway/cycle track in the highway verge of the A127 westbound off-slip at the M25 junction 29 and in the highway verge of the A127 westbound | Between points 37/24 and 42/3 as shown on sheet 45 of the rights of way and access plans. |
| Bridleway link and footbridge across the A127 to BR183, east of the M25 junction 29 | Between points 45/8 and 45/7 as shown on sheet 45 of the rights of way and access plans. |
| Stairs to southern side of footbridge across the A127 | Between points 45/12 and 45/13 as shown on sheet 45 of the rights of way and access plans. |
| Cycle track between the footway/cycle track in the highway verge of the A127 westbound and the footbridge across the A127 | Between points 41/6 and 45/10 as shown on sheet 45 of the rights of way and access plans. |
| Cycle track between the footway in the highway verge of the A127 eastbound and the footbridge across the A127 | Between points 42/4 and 45/11 as shown on sheet 45 of the rights of way and access plans. |
| Cycle track (ramp) connecting to the footbridge across the A127 | Between points 45/11 and 45/21 as shown on sheet 45 of the rights of way and access plans. |
| Stairs to northern side of footbridge across the A127 | Between points 45/14 and 45/15 as shown on sheet 45 of the rights of way and access plans. |
| Footway/cycle track in the highway verge of the M25 junction 29 roundabout and A127 eastbound off-slip | Between points 37/25 and 37/26 as shown on sheet 45 of the rights of way and access plans. |
| Bridleway link and footbridge across the A127, west of the M25 junction 29 | Between points 45/5 and 45/6 as shown on sheet 45 of the rights of way and access plans. |
| Stairs to southern side of footbridge across the A127 | Between points 45/16 and 45/17 as shown on sheet 45 of the rights of way and access plans. |
| Stairs to northern side of footbridge across the A127 | Between points 45/19 and 45/20 as shown on sheet 45 of the rights of way and access plans. |
| Cycle track between the footway/cycle track in the highway verge of the A127 eastbound and the footbridge across the A127 west of the M25 junction 29 | Between points 45/9 and 45/18 as shown on sheet 45 of the rights of way and access plans. |
SCHEDULE 6 — TRAFFIC REGULATION MEASURES
PART 1 — SPEED LIMITS
Note 1: Where roads are to become subject to the national speed limit as indicated in the column headed “speed limit” in this Part of this Schedule and as shown on the plans relating to this Schedule (the traffic regulation measures plans), speed limits are to apply in accordance with the applicable speed limit for such roads in accordance with the provisions of the 1984 Act and which are indicated in parenthesis for information only and such speed limits are not effected by article 16 (clearways, speed limits and prohibitions) of this Order.
Note 2: Where existing speed limits (to be retained) are shown in this Part of this Schedule or on the traffic regulation measures plans which relate to it, this is for information only and such speed limits are not subject to this Order.
| (1) Road name, number and length | (2) Speed limit |
|---|---|
| Existing northbound lanes of the M2 between points 2/2 and 2/8 shown as dot and dashed magenta line on sheet 3 of the traffic regulation measures plans. | Existing Variable Mandatory Speed Limit |
| Existing southbound lanes of the M2 between points 2/29 and 2/6 shown as solid magenta line on sheet 3 of the traffic regulation measures plans. | Existing National Speed Limit (70 miles per hour) |
| M2 northbound to A289 northbound between points 2/33 and 2/31 shown as solid magenta line on sheet 3 of the traffic regulation measures plans. | Existing National Speed Limit (70 miles per hour) |
| A289 southbound to M2 southbound between points 2/7 and 2/18 shown as solid magenta line on sheet 3 of the traffic regulation measures plans. | Existing National Speed Limit (70 miles per hour) |
| A289 southbound to A2 westbound link road between points 2/28 and 2/27 shown as solid magenta line on sheet 3 of the traffic regulation measures plans. | Existing National Speed Limit (70 miles per hour) |
| Brewers Road to A2 eastbound link Road between points 5/6 and 5/4 shown as dashed light blue line on sheet 4 of the traffic regulation measures plans. | 60 miles per hour |
| A2 eastbound link road to Brewers Road between points 5/5 and 5/13 and between 5/13 and 5/4 shown as dashed light blue line on sheet 4 of the traffic regulation measures plans. | 60 miles per hour |
| A2 eastbound between points 2/29 on sheet 3 and 13/1 on sheet 6 shown as dashed red line on sheets 3, 4 and 6 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| A2 eastbound between points 13/1 on sheet 6 and 2/36 on sheet 7 shown as dot and dashed red line on sheets 6 and 7 of the traffic regulation measures plans. | Variable Mandatory Speed Limit |
| A2 westbound between points 2/8 on sheet 3 and 2/24 on sheet 4 shown as dot and dashed red line on sheets 3 and 4 of the traffic regulation measures plans. | Variable Mandatory Speed Limit |
| A2 westbound between points 2/24 on sheet 4 and 2/21 on sheet 6 shown as dashed red line on sheet 4 and 6 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| A2 link road eastbound between points 2/11 on sheet 3 and 2/17 on sheet 6 shown as dashed light blue line on sheets 3, 4 and 6 of the traffic regulation measures plans. | 60 miles per hour |
| A2 link Road westbound between points 2/27 on sheet 3 and 2/19 on sheet 6 shown as dashed light blue line on sheets 3, 4 and 6 of the traffic regulation measures plans. | 60 miles per hour |
| Brewers Road between points 5/7 and 5/8 shown as dashed green line on sheet 4 of the traffic regulation measures plans. | 40 miles per hour |
| Brewers Road to Halfpence Lane roundabout between points 5/12 and 5/9 shown as dashed green line on sheet 4 of the traffic regulation measures plans. | 40 miles per hour |
| Halfpence Lane roundabout entire circulatory carriageway starting and ending at point 12/2 shown as dashed green line on sheet 4 of the traffic regulation measures plans. | 40 miles per hour |
| Thong Lane between points 6/2 and 6/43 shown as dashed orange line on sheet 4 of the traffic regulation measures plans. | 30 miles per hour |
| Thong Lane between points 6/5 and 6/6 shown as dashed orange line on sheet 11 of the traffic regulation measures plans. | 30 miles per hour |
| Cobham roundabout entire circulatory carriageway starting and ending at point 2/4 shown as dashed green line on sheet 6 of the traffic regulation measures plans. | 40 miles per hour |
| New local road between Cobham roundabout and Halfpence Lane roundabout between points 6/1 on sheet 4 and 2/37 on sheet 6 shown as dashed green line on sheets 4 and 6 of the traffic regulation measures plans. | 40 miles per hour |
| New local road between Cobham roundabout and Henhurst roundabout between points 2/38 and 7/1 shown as dashed green line on sheet 6 of the traffic regulation measures plans. | 40 miles per hour |
| A2 westbound to Cobham roundabout between points 2/3 and 2/39 shown as dashed red line on sheet 6 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| Gravesend East junction southern roundabout entire circulatory carriageway starting and ending at point 8/1 shown as dashed green line on sheet 6 of the traffic regulation measures plans. | 40 miles per hour |
| Gravesend East junction south to A2 westbound between points 2/30 and 2/32 shown as dashed red line on sheet 6 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| Eastbound and westbound lanes between Henhurst Road roundabout and Gravesend East junction south between points 8/6 and 8/8 shown as dashed green lines on sheet 6 of the traffic regulation measures plans. | 40 miles per hour |
| A2 westbound link Road to A122 Lower Thames Crossing northbound between points 2/22 on sheet 4 and 1/5 on sheet 6 shown as dot and dashed red line on sheets 4 and 6 of the traffic regulation measures plans. | Variable mandatory Speed limit |
| A2 westbound to A122 Lower Thames Crossing northbound between points 2/24 on sheet 4 and 1/2 on sheet 6 shown as dot and dashed red line on sheets 4 and 6 of the traffic regulation measures plans. | Variable mandatory Speed limit |
| A122 Lower Thames Crossing southbound to A2 eastbound between points 2/25 on sheet 4 and 1/4 on sheet 11 shown as dashed red line on sheets 4, 6 and 11 of the traffic regulation measures plans. | National Speed limit (70 miles per hour) |
| A122 Lower Thames Crossing southbound to A2 eastbound link road between points 11/2 on sheet 4 and 1/4 on sheet 11 shown as dashed red line on sheets 4, 6 and 11 of the traffic regulation measures plans. | National Speed limit (70 miles per hour) |
| A2 westbound link road to Cobham roundabout between points 2/20 and 2/40 shown as dashed light blue line on sheet 6 of the traffic regulation measures plans. | 60 miles per hour |
| Henhurst Road between points 7/3 and 7/2 shown as dashed magenta line on sheet 6 of the traffic regulation measures plans. | National Speed Limit (60 miles per hour) |
| Henhurst Road roundabout entire circulatory carriageway starting and ending at point 7/4 shown as dashed green line on sheet 6 of the traffic regulation measures plans. | 40 miles per hour |
| A122 Lower Thames Crossing southbound to Gravesend East junction south roundabout between points 2/16 and 8/4 shown as dashed magenta line on sheet 6 of the traffic regulation measures plans. | National Speed Limit (60 miles per hour) |
| Gravesend East junction northern roundabout entire circulatory carriageway starting and ending at point 10/1 shown as dashed green line on sheet 6 of the traffic regulation measures plans. | 40 miles per hour |
| A2 eastbound to Gravesend East junction north between points 2/35 and 10/15 shown as solid magenta line on sheet 6 of the traffic regulation measures plans. | Existing National Speed Limit (70 miles per hour) |
| Northbound and southbound Lanes between Gravesend East junction north and Gravesend East junction south between points 8/10 and 8/3 shown as dashed green line on sheet 6 of the traffic regulation measures plans. | 40 miles per hour |
| Hever Court Road roundabout entire circulatory carriageway starting and ending at point 10/6 shown as dashed green line on sheet 6 of the traffic regulation measures plans. | 40 miles per hour |
| Hever Court Road between points 10/3 and 10/13 shown as dashed green line on sheet 6 of the traffic regulation measures plans. | 40 miles per hour |
| Gravesend East junction north roundabout to Hever Court Road roundabout between points 10/14 and 10/16 shown as dashed green line on sheet 6 of the traffic regulation measures plans. | 40 miles per hour |
| Valley Drive between points 10/17 and 10/5 shown as dashed green line on sheet 6 of the traffic regulation measures plans. | 40 miles per hour |
| Hever Court Road roundabout to A2 eastbound between points 2/15 and 2/13 shown as dashed orange line on sheet 6 of the traffic regulation measures plans. | 30 miles per hour |
| Hever Court Road roundabout to A122 Lower Thames Crossing northbound between points 2/14 on sheet 6 and 1/3 on sheet 11 shown as dot and dashed red line on sheets 6 and 11 of the traffic regulation measures plans. | Variable mandatory Speed limit |
| A2 eastbound to A122 Lower Thames Crossing northbound between points 13/1 and 2/17 shown as dot and dashed red line on sheet 6 of the traffic regulation measures plans. | Variable mandatory Speed limit |
| A2 eastbound to A122 Lower Thames Crossing northbound between points 2/17 and 1/2 shown as dot and dashed red line on sheet 6 of the traffic regulation measures plans. | Variable mandatory Speed limit |
| A2 eastbound to A122 Lower Thames Crossing northbound between points 1/2 on sheet 6 and 1/3 on sheet 11 shown as dot and dashed red line on sheets 6 and 11 of the traffic regulation measures plans. | Variable mandatory Speed limit |
| A122 Lower Thames Crossing southbound to A2 westbound between points 1/1 and 2/16 shown as dashed red line on sheet 6 of the traffic regulation measures plans. | National Speed limit (70 miles per hour) |
| A122 Lower Thames Crossing southbound to A2 westbound between points 2/16 and 2/41 shown as dashed magenta line on sheet 6 of the traffic regulation measures plans. | National Speed Limit (60 miles per hour) |
| A122 Lower Thames Crossing northbound between points 1/3 on sheet 11 and 1/9 on sheet 43 shown as dot and dashed red line on sheets 11, 13, 14, 15, 16, 20, 23, 24, 27, 28, 29, 33, 35, 38, 39, 42 and 43 of the traffic regulation measures plans. | Variable mandatory Speed limit |
| A122 Lower Thames Crossing southbound between points 1/4 on sheet 11 and 1/10 on sheet 43 shown as dot and dashed red line on sheets 11, 13, 14, 15, 16, 20, 23, 24, 27, 28, 29, 33, 35, 38, 39, 42 and 43 of the traffic regulation measures plans. | Variable mandatory Speed limit |
| Muckingford Road between points 15/8 and 15/2 shown as dashed dark blue line on sheet 24 of the traffic regulation measures plans. | 50 miles per hour |
| Brentwood Road between points 20/5 and 20/3 shown as dashed dark blue line on sheet 28 of the traffic regulation measures plans. | 50 miles per hour |
| Brentwood Road between points 20/1 and 20/5 shown as dashed orange line on sheet 28 of the traffic regulation measures plans. | 30 miles per hour |
| Hornsby Lane between points 22/2 and 22/3 and between 22/1 and 22/4 and between 22/5 and 22/6 shown as dashed magenta line on sheet 28 of the traffic regulation measures plans. | National Speed Limit (60 miles per hour) |
| A1013 (Stanford Road) between points 23/4 on sheet 26 and 23/6 on sheet 29 shown as dashed green line on sheets 26 and 29 and of the traffic regulation measures plans. | 40 miles per hour |
| A1013 (Stanford Road) between points 23/6 on sheet 29 and 23/1 on sheet 32 shown as dashed dark blue line on sheets 29 and 32 of the traffic regulation measures plans. | 50 miles per hour |
| Gammonfields Way between points 25/1 and 25/3 shown as dashed dark green line on sheet 29 of the traffic regulation measures plans. | 20 miles per hour |
| Long Lane between points 25/2 and 25/3 shown as dashed dark green line on sheet 29 of the traffic regulation measures plans. | 20 miles per hour |
| Heath Road between points 24/1 and 24/2 shown as dashed orange line on sheet 29 of the traffic regulation measures plans. | 30 miles per hour |
| B188 Baker Street between points 27/3 and 27/2 shown as dashed green line on sheet 29 of the traffic regulation measures plans. | 40 miles per hour |
| B188 Baker Street between points 27/1 and 27/3 shown as dashed orange line on sheet 29 of the traffic regulation measures plans. | 30 miles per hour |
| Rectory Road between points 23/2 and 23/5 shown as solid green line on sheet 32 of the traffic regulation measures plans. | 40 miles per hour |
| Orsett Cock roundabout to A1089 southbound between points 39/3 on sheet 29 and 1/17 on sheet 32 shown as dashed red line on sheets 29and 32 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| A13 westbound to A122 Lower Thames Crossing southbound between points 1/16 on sheet 28 and 1/15 on sheet 32 shown as dot and dashed red line on sheets 28, 29 and 32 of the traffic regulation measures plans. | Variable Mandatory Speed limit |
| A1089 northbound to A122 Lower Thames Crossing northbound and southbound between points 1/12 on sheet 29 and 1/13 on sheet 33 shown as dot and dashed red line on sheets 29 and 33 of the traffic regulation measures plans. | Variable Mandatory Speed limit |
| A1089 northbound to A122 Lower Thames Crossing southbound between point 1/13 and 1/22 shown as dot and dashed red line on sheet 33 of the traffic regulation measures plans. | Variable Mandatory Speed limit |
| A1089 northbound to A122 Lower Thames Crossing northbound between point 1/13 and 1/14 shown as dot and dashed red line on sheet 33 of the traffic regulation measures plans. | Variable Mandatory Speed limit |
| A122 Lower Thames Crossing northbound to A13 eastbound between points 1/19 on sheet 32 and 1/18 on sheet 29 shown as dashed red line on sheets 29 and 32 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| A122 Lower Thames Crossing to Orsett Cock roundabout between points 29/5 and 1/20 shown as dashed red line on sheet 32 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| A13 eastbound to Orsett Cock roundabout between points 30/1 and 30/2 shown as dashed red lined on sheet 32 of traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| Orsett Cock roundabout to A13 westbound between points 29/6 on sheet 32 and 29/7 on sheet 29 shown as dashed red line on sheets 29 and 32 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| Orsett Cock roundabout to A1089 southbound between points 1/17 on sheet 32 and 39/3 on sheet 29 shown as dashed red line on sheets 29 and 32 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| A122 Lower Thames Crossing southbound to A13 eastbound/ Orsett Cock roundabout between points 1/24 on sheet 29 and 1/23 on sheet 33 and shown as dashed red line on sheets 29 and 33 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| Stifford Clays Road between points 32/1 and 32/3 shown as dashed dark blue line on sheet 33 of the traffic regulation measures plans. | 50 miles per hour |
| Stifford Clays Road between points 32/3 and 32/4 shown as dashed orange line on sheet 33 of the traffic regulation measures plans. | 30 miles per hour |
| B186 North Road between points 35/1 and 35/4 shown as dashed green line on sheet 39 of the traffic regulation measures plans. | 40 miles per hour |
| M25 northbound between points 37/1 on sheet 42 and 37/2 on sheet 46 shown as dash and dot red line on sheets 42, 43, 44, 45 and 46 of the traffic regulation measures plans. | Variable Mandatory Speed Limit |
| M25 southbound between points 1/11 on sheet 43 and 37/4 on sheet 46 shown as dash and dot red line on sheets 43, 44, 45 and 46 of the traffic regulation measures plans. | Variable Mandatory Speed Limit |
| A122 Lower Thames Crossing northbound to M25 northbound between points 1/9 on sheet 43 and 37/7 on sheet 44 shown as dot and dashed red line on sheets 43 and 44 of the traffic regulation measures plans. | Variable Mandatory Speed Limit |
| M25 southbound on-slip at M25 junction 29 between points 37/12 on sheet 44 and 37/23 on sheet 45 shown as dash and dot red line on sheets 44 and 45 of the traffic regulation measures plans. | Variable Mandatory Speed Limit |
| A122 Lower Thames Crossing northbound to M25 Junction 29 link road between points 1/9 and 37/6 shown as dashed red line on sheet 43 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| Connecting road (northbound exit slip) from M25 northbound to M25 junction 29 between points 37/5 on sheet 42 and 37/6 on sheet 43 point shown as dashed red line on sheets 42 and 43 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| Connecting road (northbound exit slip) from M25 northbound to M25 junction 29 between points 37/6 on sheet 43 and 37/20 on sheet 45 shown as dashed red line on sheet 43, 44 and 45 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| M25 northbound to A127 westbound dedicated off-slip between points 37/21 and 37/16 shown as dashed red line on sheet 45 of the traffic regulation measures plans. | National Speed Limit (70 miles per hour) |
| A127 westbound to M25 southbound dedicated on-slip between points 37/22 and 37/23 shown as dot and dash red line on sheet 45 of the traffic regulation measures plans. | Variable Mandatory Speed Limit |
PART 2 — CLEARWAYS AND OTHER RESTRICTIONS
| (1) Road name, number and length | (2) Measure |
|---|---|
| A2 westbound between points 2/8 on sheet 3 and 2/21 on sheet 6 as shown as black circle line on sheet 3, 4 and 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, hard shoulders, and slip roads) |
| A2 eastbound between points 2/29 on sheet 3 and 13/1 on sheet 6 shown as black circle line on sheet 3, 4 and 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, hard shoulders, and slip roads) |
| A289 southbound to A2 westbound link road between points 2/28 and 2/27 shown as black circle line on sheet 3 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A2 link road eastbound between points 2/11 on sheet 3 and 2/17 on sheet 6 shown as black circle line on sheet 3, 4 and 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A2 link road westbound between points 2/27 on sheet 3 and 2/19 on sheet 6 shown as black circle line on sheets 3, 4 and 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, hard shoulders, and slip roads) |
| Northbound lanes of A122 Lower Thames Crossing between points 1/3 on sheet 11 and 1/9 on sheet 43 shown as black circle line on sheets 11, 13, 14, 15, 16, 20, 23, 24, 27, 28, 29, 33, 35, 38, 39, 42 and 43 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| Southbound lanes of A122 Lower Thames Crossing between point 1/4 on sheet 11 and 1/10 on sheet 43 shown as black circle line on sheets 11, 13, 14, 15, 16, 20, 23, 24, 27, 28, 29, 33, 35, 38, 39, 42, and 43 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| Halfpence Lane roundabout to Thong Lane between points 6/1 and 6/2 shown as black circle line on sheet 4 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| New local road between Cobham roundabout and Halfpence Lane roundabout between points 6/1 on sheet 4 and 2/37 on sheet 6 shown as black circle line on sheet 4 and 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| New local road between Cobham roundabout and Henhurst roundabout between points 2/38 and 7/1 shown as black circle line on sheet 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A2 westbound to Cobham roundabout between points 2/3 and 2/39 shown as black circle line on sheet 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A122 Lower Thames Crossing southbound to Gravesend East junction south between points 2/16 and 8/4 shown as black circle line on sheet 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A122 Lower Thames Crossing southbound to A2 westbound between points 2/16 and 2/41 shown as black circle line on sheet 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A2 westbound link road to Cobham roundabout between points 2/20 and 2/40 shown as black circle line on sheet 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| Cobham roundabout at points 2/4 shown as black circle line on sheet 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| Eastbound and westbound Lanes between Henhurst road roundabout and Gravesend East junction south between points 8/6 and 8/8 shown as black circle line on sheet 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A2 westbound link road to A122 Lower Thames Crossing northbound between points 2/22 on sheet 4 and 1/5 on sheet 6 shown as black circle line on sheet 4 and 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A2 westbound to A122 Lower Thames Crossing northbound between points 2/24 on sheet 2 and 1/2 on sheet 4 shown as black circle line on sheet 2 and 4 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A122 Lower Thames Crossing southbound to A2 eastbound between points 2/25 on sheet 4 and 1/4 on sheet 11 shown as black circle line on sheet 4, 6 and 11 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A122 Lower Thames Crossing southbound to A2 eastbound link road between points 11/2 on sheet 4 and 1/4 on sheet 11 shown as black circle line on sheet 4, 6 and 11 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A122 Lower Thames Crossing southbound to A2 westbound between points 1/1 and 2/16 shown as black circle line on sheet 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A2 eastbound to A122 Lower Thames Crossing northbound between points 13/1 and 1/2 shown as black circle line on sheet 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A2 eastbound to A122 Lower Thames Crossing northbound between points 1/2 on sheet 6 and 1/3 on sheet 11 shown as dot and dashed red line on sheets 6 and 11 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| Hever Court Road roundabout to A122 Lower Thames Crossing northbound between points 2/14 on sheet 6 and 1/3 on sheet 11 shown as black circle line on sheets 6 and 11 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| Hever Court Road roundabout to A2 eastbound between points 2/15 and 2/13 shown as black circle line on sheet 6 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A13 westbound to A122 Lower Thames Crossing southbound between points 1/16 on sheet 28 and 29/8 on sheet 32 shown as black circle line on sheets 28, 29 and 32 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A1089 northbound to A122 Lower Thames Crossing northbound and southbound between points 1/12 on sheet 29 and 1/13 on sheet 33 shown as black circle line on sheets 29 and 33 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A1089 northbound to A122 Lower Thames Crossing southbound between points 1/13 and 1/22 shown as black circle line on sheet 33 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A1089 northbound to A122 Lower Thames Crossing northbound between points 1/13 and 1/14 shown on sheet 33 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads, and laybys) |
| A122 Lower Thames Crossing northbound to A13 eastbound between points 1/19 on sheet 32 and 1/18 on sheet 29 shown as black circle line on sheets 29 and 32 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A122 Lower Thames Crossing northbound to Orsett Cock roundabout between points 29/5 and 1/20 shown as black circle line on sheet 32 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A13 eastbound to Orsett cock roundabout between points 30/1 and 30/2 shown as black circle line on sheet 32 of Traffic Regulation Measures Plans. | Clearway (to include verges, hard strips, and slip roads) |
| Orsett Cock roundabout to A13 westbound between points 29/6 on sheet 32 and 29/7 on sheet 29 shown as black circle line on sheets 29 and 32 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| Orsett Cock roundabout to A1089 southbound between points 1/17 on sheet 32 and 39/3 on sheet 29 shown as dashed red line on sheets 29 and 32 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A122 Lower Thames Crossing southbound to A13 eastbound/ Orsett Cock roundabout between points 1/24 on sheet 29 and 1/23 on sheet 33 shown as black circle line on sheets 29 and 33 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A122 Lower Thames Crossing northbound to Junction 29 link road between points 1/9 and 37/6 shown as black circle line on sheet 43 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| Connecting road (northbound exit slip) from M25 northbound to M25 junction 29 between points 37/5 on sheet 42 and 37/6 on sheet 43 point shown as black circle line on sheets 42 and 43 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| Connecting road (northbound exit slip) from M25 northbound to M25 junction 29 between points 37/6 on sheet 43 and 37/20 on sheet 45 shown as black circle line on sheet 43, 44 and 45 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| M25 northbound to A127 westbound dedicated off-slip between points 37/21 and 37/16 shown as black circle line on sheet 45 of the traffic regulation measures plans. | Clearway (to include verges, hard strips, and slip roads) |
| A2 eastbound between points 2/29 on sheet 3 and 13/1 on sheet 6 shown on sheets 3, 4 and 6 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| Hever Court Road roundabout to A2 eastbound between points 2/15 and 2/13 shown on sheet 6 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A2 westbound between points 2/8 on sheet 3 and 2/19 on sheet 6 shown on sheets 3, 4 and 6 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A122 Lower Thames Crossing southbound to A2 eastbound between points 2/25 on sheet 4 and 1/4 on sheet 11 shown on sheets 4, 6 and 11 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A2 eastbound to A122 Lower Thames Crossing northbound between points 2/17 and 1/2 shown on sheet 6 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A2 eastbound to A122 Lower Thames Crossing northbound between points 1/2 on sheet 6 and 1/3 on sheet 11 shown on sheets 6 and 11 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| Hever Court Road roundabout to A122 Lower Thames Crossing northbound between points 2/14 on sheet 6 and 1/3 on sheet 11 shown on sheets 6 and 11 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A122 Lower Thames Crossing southbound to A2 eastbound link road between points 11/2 on sheet 4 and 1/4 on sheet 11 shown on sheet 2, 4 and 9 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A2 westbound to A122 Lower Thames Crossing northbound between points 2/24 on sheet 4 and 1/3 on sheet 11 shown on sheet 4, 6 and 11 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A2 westbound link road to A122 Lower Thames Crossing northbound between points 2/22 on sheet 4 and 1/5 on sheet 6 shown on sheet 4 and 6 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| Northbound lanes of A122 Lower Thames Crossing between points 1/3 on sheet 11 and 1/9 on sheet 43 shown on sheets 11, 13, 14, 15, 16, 20, 23, 24, 27, 28, 29, 33, 35, 38, 39, 42 and 43 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| Southbound lanes of A122 Lower Thames Crossing between points 1/4 on sheet 11 and 1/10 on sheet 43 shown on sheets 11, 13, 14, 15, 16, 20, 23, 24, 27, 28, 29, 33, 35, 38, 39, 42 and 43 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A13 westbound to A122 Lower Thames Crossing southbound between points 29/8 on sheet 32 and 1/16 on sheet 28 shown on sheets 28, 29 and 32 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A13 westbound to A122 Lower Thames Crossing northbound between points 1/15 on sheet 32 and 1/31 on sheet 35 shown on sheets 29, 32, 33 and 35 of the traffic regulation measures plans | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A1089 northbound to A122 Lower Thames Crossing northbound and southbound between points 1/12 on sheet 29 and 1/13 on sheet 33 shown on sheets 29 and 33 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A1089 northbound to A122 Lower Thames Crossing southbound between points 1/13 and 1/22 shown on sheet 33 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A1089 northbound to A122 Lower Thames Crossing northbound between points 1/13 and 1/14 shown on sheet 33 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A122 Lower Thames Crossing southbound to A13 eastbound/ Orsett Cock roundabout between points 1/24 on sheet 29 and 1/23 on sheet 33, as shown on sheets 29 and 33 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A122 Lower Thames Crossing northbound to A13 eastbound between points 1/19 on sheet 32 and 1/18 on sheet 29 shown on sheets 29 and 32 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A122 Lower Thames Crossing northbound to Orsett Cock roundabout between points 29/5 and 1/20 shown on sheet 32 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
| A122 Lower Thames Crossing northbound to M25 Junction 29 link road between points 1/9 and 37/6 shown on sheet 43 of the traffic regulation measures plans. | Prohibition of pedestrians, bicycles, motorcycles with engines less than 50 cubic centimetres, mopeds, invalid carriages, agricultural vehicles, horses ridden or accompanied, animals and vehicles drawn by animals |
PART 3 — VARIATIONS OF EXISTING TRAFFIC REGULATION ORDERS
| (1) Road name, number and length | (2) Title of Order | (3) Variations |
|---|---|---|
| Thong Lane at point 6/1 on sheet 4 of the traffic regulation measures plans | Gravesham Borough Council (Thong Lane) (Width Restriction) Order 1981 | Order to be varied to alter the southern termination point (point 6/1 on sheet 4 of the traffic regulation measures plans) of the existing width limit on Thong Lane. The southern termination point of the width limit will be moved to point 6/2 on sheet 4 of the traffic regulation measures plans. |
| Hornsby Lane between points 22/3 and 22/2 on sheet 28 of the traffic regulation measures plans. | The Borough of Thurrock (Brentwood Road, Chadwell St Mary) (7.5t Weight Restriction) Order 2012 | Order to be varied so that the restriction is disapplied between points 22/3 and 22/2 on sheet 28 of the traffic regulation measures plans. |
| Muckingford Road between points 15/8 and 15/2 on sheet 24 of the traffic regulation measures plans. | The Borough of Thurrock (Muckingford Road/ Linford Road, Linford & A1306 Arterial Road Purfleet) Order 2015 | Order to be varied to move 30m eastwards, to point 15/2 on sheet 24 of the traffic regulation measures plans, the eastern termination point of the 50 miles per hour speed limit restriction on Muckingford Road. |
SCHEDULE 7 — TREES SUBJECT TO TREE PRESERVATION ORDERS
| (1) Type of tree | (2) Work to be carried out | (3) Relevant part of the authorised development | (4) TPO reference |
|---|---|---|---|
| Woodland | Felling | Works Nos. 1E, E5, 1L | TPO No. 1960001(Gravesham) |
| Woodland | Felling | Works Nos. 1H, E4, E6, E10, MUT1, MU10, ULH13, OH2 | TPO No. 1972-001(Gravesham) |
| Woodland | Felling | Works Nos. 2I, 2Q, 2H, E9, G1b, G2, G3, OH1, ULH14 | TPO No. 1999-001 (Gravesham) |
| Woodland | Felling | Works Nos. E20, MU36, OH3, OH4, OHT2 | TPO No. 28/1991 (Thurrock) |
| Individual trees | Felling | Works Nos. E20, MUT6 | TPO No. 12/1999 (Thurrock) |
| Woodland | Felling | Works Nos. 6A, 6C, E23, E24, MU37 | TPO No. 07/1990 (Thurrock) |
| Area and individual trees | Felling | Works Nos. 7X, MU43 | TPO No. 01/1983 (Thurrock) |
| Individual trees | Felling | Works Nos. E44, MU72, MU75, MU76, MUT30 | TPO No. 4-88 (London Borough of Havering) |
| Area and individual trees | Felling | Works Nos. E48, FCA6, FCA7 | TPO No. 12-92 (London Borough of Havering) |
| Woodland, tree group and individual trees | Felling | Works Nos. 9A, 9D, 9E, 9N, MU73, MU75, MU76, MUT30 | TPO No. 1-06 (London Borough of Havering) |
| Tree group and individual trees | Felling | Works Nos. 9B, 9E, 9N, MU74, MU76 | TPO No. 13-72 (London Borough of Havering) |
| Individual tree | Felling | Works Nos. 9A, 9N, MU75, MU76, MUT30 | TPO No. 14-97 (London Borough of Havering) |
| Area | Felling | Works Nos. 9D, 9J, 9Y, MU91 | TPO No. 19-1991 (London Borough of Havering) |
| Area and individual tree | Felling | Works Nos. E51, ULH02 | TPO No. 20-81 (London Borough of Havering) |
| Area | Felling | Works No. 9J, 9Y, MU91 | TPO No. 16-07 (London Borough of Havering) |
SCHEDULE 8 — LAND OF WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.