The M5 Junction 10 Development Consent Order 2025
| (1) Plot reference number shown on land plans | (2) Purpose for which rights over land may be acquired | (3) Relevant part of the authorised development |
|---|---|---|
| Land Plans -Sheet 3 | Land Plans -Sheet 3 | Land Plans -Sheet 3 |
| 3/2b | New right for temporary access for the construction of motorway signage and associated cabling and ducting works | 1a |
| Land Plans -Sheet 4 | Land Plans -Sheet 4 | Land Plans -Sheet 4 |
| 4/1c | New right for the construction of motorway signage and associated cabling and ducting works New right for the construction of a new southbound exit slip from the M5 to the A4019 New right for the construction of a new northbound entry slip from the A4019 to the M5 New right for the construction of an environmental barrier adjacent to Barn Farm north of Junction 10 and west of the M5 | 1a, 1c, 1e, 1n |
| 4/1d | New right for the construction of a new southbound exit slip from the M5 to the A4019 New right for the construction of a new northbound entry slip from the A4019 to the M5 New right for an extension of the Leigh Brook culvert (also known as the Barn Farm culvert) New right for the construction of an environmental barrier adjacent to Barn Farm north of Junction 10 and west of the M5 New right for the construction of an environmental barrier adjacent to land housing a traveller site north of Junction 10 and east of the M5 New right for the diversion, use, protection, inspection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution PLC | 1c, 1e, 1m, 1n, 1o, 20 |
| 4/3a | New right for the construction of an environmental barrier adjacent to Barn Farm north of Junction 10 and west of the M5 New right for the diversion, use, maintenance and protection of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution PLC | 1n, 20 |
| 4/3b | New right for the construction, use, protection, inspection and maintenance of an environmental barrier adjacent to Barn Farm north of Junction 10 and west of the M5 New right for the diversion, use, protection, inspection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution PLC | 1n, 20 |
| 4/3d | New right for the temporary access for the construction of a new southbound exit slip from the M5 to the A4019 and new permanent right of access to provide, protect, inspect and maintain environmental and ecological mitigation | 1c |
| 4/3e | New right for the temporary access for the construction of a new southbound exit slip from the M5 to the A4019 and new permanent right of access to provide, protect, inspect and maintain environmental and ecological mitigation | 1c |
| 4/3h | New right for the use of land northwest of Junction 10 as a construction compound New right to provide, protect, inspect and maintain landscaping northwest of Junction 10 | 1j, 2b |
| 4/4b | New right for the temporary access for the construction of a new southbound exit slip from the M5 to the A4019 and new permanent right of access to provide, protect, inspect and maintain environmental and ecological mitigation | 1c |
| Land Plans -Sheets 5 and 5A | Land Plans -Sheets 5 and 5A | Land Plans -Sheets 5 and 5A |
| 5/1a(i) | New right for the construction of new or altered private means of access New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 3d, 27 |
| 5/2d | New right for the construction of motorway signage and associated cabling and ducting works New right for the construction of a new southbound exit slip from the M5 to the A4019 New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the construction of a new roundabout over the M5 comprising a circulatory carriageway and the Piffs Elm interchange bridges (north and south) New right for the demolition of the existing A4019 bridge over the M5 New right for the diversion, use, protection, inspection and maintenance of water pipeline for the benefit of Severn Trent Water Limited New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited New right for the diversion, use, protection, inspection and maintenance of telecommunication cable and associated apparatus and equipment New right for the demolition of the existing NRTS Transmission Station and associated infrastructure | 1a, 1c, 2, 2a, 2d, 15, 16, 27, 36a |
| 5/2h | New right for the realignment and widening of the A4019 (Tewkesbury Road) northwest of Junction 10 with associated footway, cycleway, shared use path, private access points, signage and ducting New right for the realignment of the unclassified road known as Stanboro Lane New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 3, 3a, 10 |
| 5/2h(i) | New right for the realignment and widening of the A4019 (Tewkesbury Road) northwest of Junction 10 with associated footway, cycleway, shared use path, private access points, signage and ducting New right for the realignment of the unclassified road known as Stanboro Lane New right for the diversion, use, protection, inspection and maintenance of telecommunication cable and associated apparatus and equipment | 3, 3a, 27 |
| 5/2i | New right for the realignment and widening of the A4019 (Tewkesbury Road) northwest of Junction 10 with associated footway, cycleway, shared use path, private access points, signage and ducting New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 3, 10 |
| 5/2j | New right for the realignment and widening of the A4019 (Tewkesbury Road) northwest of Junction 10 with associated footway, cycleway, shared use path, private access points, signage and ducting New right for the realignment of the unclassified road known as Stanboro Lane | 3, 3a |
| 5/2k | New right for the realignment of the unclassified road known as Stanboro Lane | 3a |
| 5/2l | New right for the realignment and widening of the A4019 (Tewkesbury Road) northwest of Junction 10 with associated footway, cycleway, shared use path, private access points, signage and ducting New right for the realignment of the unclassified road known as Stanboro Lane | 3, 3a |
| 5/2n | New right for the construction of a new northbound exit slip from the M5 to the A4019 New right for the construction of a new southbound entry slip from the A4019 to the M5 New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the construction of a new roundabout over the M5 comprising a circulatory carriageway and the Piffs Elm interchange bridges (north and south) New right for the extension of the Piffs Elm culvert New right for the demolition of the existing A4019 bridge over the M5 New right for the realignment and widening of the A4019 (Tewkesbury Road) northwest of Junction 10 with associated footway, cycleway, shared use path, private access points, signage and ducting New right for the diversion of telecommunication cable and associated apparatus and equipment New right for the diversion, use, protection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Distribution Limited PLC New right for the demolition of the existing NRTS Transmission Station and associated infrastructure | 1b, 1d, 2, 2a, 2c, 2d, 3, 10, 19, 36a |
| 5/2o | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the demolition of the existing A4019 bridge over the M5 New right for the realignment and widening of the A4019 (Tewkesbury Road) northwest of Junction 10 with associated footway, cycleway, shared use path, private access points, signage and ducting New right for the diversion, use, protection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Distribution Limited PLC | 2, 2d, 3, 19 |
| 5/2p | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the demolition of the existing A4019 bridge over the M5 New right for the diversion, use, protection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Distribution Limited PLC | 2, 2d, 19 |
| 5/2r | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the realignment of the unclassified road known as Stanboro Lane New right for the diversion, use, protection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Distribution Limited PLC | 2, 3a, 19 |
| 5/2y | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the demolition of the existing A4019 bridge over the M5 | 2, 2d |
| 5/2z | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the demolition of the existing A4019 bridge over the M5 | 2, 2d |
| 5/2aa | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the demolition of the existing A4019 bridge over the M5 | 2, 2d |
| 5/2cc | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the demolition of the existing A4019 bridge over the M5 | 2, 2d |
| 5/2ee | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the demolition of the existing A4019 bridge over the M5 New right for the realignment and dualling of the A4019 (Tewkesbury Road) southeast of Junction 10, M5 to east of Gallagher Junction with associated footway, cycleway, shared use paths, private means of access, signage and ducting New right for the construction of an underpass west of Withybridge Lane New right for the diversion and construction of bridleway BR AUC1 under the A4019 (Tewkesbury Road) New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 2, 2d, 4, 4b, 4c, 10 |
| 5/2gg | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the demolition of the existing A4019 bridge over the M5 New right for the realignment and dualling of the A4019 (Tewkesbury Road) southeast of Junction 10, M5 to east of Gallagher Junction with associated footway, cycleway, shared use paths, private means of access, signage and ducting New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 2, 2d, 4, 10 |
| 5/2jj | New right for the realignment and dualling of the A4019 (Tewkesbury Road) southeast of Junction 10, M5 to east of Gallagher Junction with associated footway, cycleway, shared use paths, private means of access, signage and ducting New right for the construction of an underpass west of Withybridge Lane New right for the diversion and construction of bridleway BR AUC1 under the A4019 (Tewkesbury Road) New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 4, 4b, 4c, 10 |
| 5/2kk | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the construction of a new roundabout over the M5 comprising a circulatory carriageway and the Piffs Elm interchange bridges (north and south) New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment New right for the demolition of the existing NRTS Transmission Station and associated infrastructure | 2, 2a, 10, 36a |
| 5/2mm | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 2, 10 |
| 5/2ss | New right for the realignment and dualling of the A4019 (Tewkesbury Road) southeast of Junction 10, M5 to east of Gallagher Junction with associated footway, cycleway, shared use paths, private means of access, signage and ducting New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 4, 10 |
| 5/2uu | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the construction of a new roundabout over the M5 comprising a circulatory carriageway and the Piffs Elm interchange bridges (north and south) New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 2, 2a, 10 |
| 5/3b | New right for the temporary access for the construction of a new southbound exit slip from the M5 to the A4019 and new permanent right of access to provide, protect, inspect and maintain environmental and ecological mitigation | 1c |
| 5/3c | New right for the temporary access for the construction of a new southbound exit slip from the M5 to the A4019 and new permanent right of access to provide, protect, inspect and maintain environmental and ecological mitigation | 1c |
| 5/4b | New right for the construction of new or altered private means of access New right for the diversion, use, protection, inspection and maintenance of water pipeline for the benefit of Severn Trent Water Limited New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited New right for the diversion, use, protection, inspection and maintenance of telecommunication cable and associated apparatus and equipment | 4g, 15, 16, 27 |
| 5/4b(i) | New right for the construction of new or altered private means of access New right for the diversion, use, protection, inspection and maintenance of water pipeline for the benefit of Severn Trent Water Limited New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited New right for the diversion, use, protection, inspection and maintenance of telecommunication cable and associated apparatus and equipment | 4g, 15, 16, 27 |
| 5/4b(ii) | New right for the diversion and construction of bridleway BR AUC1 under the A4019 (Tewkesbury Road) New right for the construction of new or altered private means of access New right for the diversion, use, protection, inspection and maintenance of water pipeline for the benefit of Severn Trent Water Limited New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited New right for the diversion, use, protection, inspection and maintenance of telecommunication cable and associated apparatus and equipment | 4c, 4g, 15, 16, 27 |
| 5/4b(iii) | New right for the construction of new or altered private means of access New right for the diversion, use, protection, inspection and maintenance of water pipeline for the benefit of Severn Trent Water Limited New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited New right for the diversion, use, protection, inspection and maintenance of telecommunication cable and associated apparatus and equipment | 4g, 15, 16, 27 |
| 5/4d(iv) | New right for construction compound no. 3 northeast of Junction 10 New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 1k, 4j |
| 5/4d(v) | New right for construction compound no. 3 northeast of Junction 10 New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 1k, 4j |
| 5/4d(vi) | New right for construction compound no. 3 northeast of Junction 10 New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 1k, 4j |
| 5/4d(vii) | New right for construction compound no. 3 northeast of Junction 10 New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 1k, 4j |
| 5/4d(viii) | New right for construction compound no. 3 northeast of Junction 10 New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 1k, 4j |
| 5/5a | New right for the demolition of Sheldon Nursery northwest of Junction 10 New right for the construction of new or altered private means of access New right for the diversion, use, protection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution PLC | 2f, 3d, 19 |
| 5/5b | New right for the construction compound no. 2 northwest of Junction 10 New right for the diversion, use, protection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution PLC | 1j, 19 |
| 5/5g | New right for the realignment of the unclassified road known as Stanboro Lane | 3a |
| 5/6f | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the demolition of the existing A4019 bridge over the M5 | 2, 2d |
| 5/6g | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the demolition of the existing A4019 bridge over the M5 New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 2, 2d, 10 |
| 5/6h | New right for the construction of a new grade separated roundabout junction and maintenance bays New right for the demolition of the existing A4019 bridge over the M5 | 2, 2d |
| 5/10d | New right for the provision, protection, inspection and maintenance of a flood compensation area at the location shown on sheets 5 and 11 of the works plans | 3e |
| 5/11b | New right for the diversion, construction, use and maintenance of bridleway BR AUC1 under the A4019 (Tewkesbury Road) New right for the construction of new or altered private means of access New right for the diversion, use, protection, inspection and maintenance of water pipeline for the benefit of Severn Trent Water Limited New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited New right for the diversion, use, protection, inspection and maintenance of telecommunication cable and associated apparatus and equipment | 4c, 4g, 15, 16, 27 |
| 5/31a(i) | New right for construction compound no. 3 northeast of Junction 10 New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 1k, 4j |
| 5/31b(i) | New right for construction compound no. 3 northeast of Junction 10 New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 1k, 4j |
| 5/31c(i) | New right for construction compound no. 3 northeast of Junction 10 New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 1k, 4j |
| 5/31d | New right for the diversion, construction, use and maintenance of bridleway BR AUC1 under the A4019 (Tewkesbury Road) New right for the construction of new or altered private means of access New right for the diversion, use, protection, inspection and maintenance of water pipeline for the benefit of Severn Trent Water Limited New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited New right for the diversion, use, protection, inspection and maintenance of telecommunication cable and associated apparatus and equipment | 4c, 4g, 15, 16, 27 |
| 5/33c | New right for the temporary access for the construction of a new southbound exit slip from the M5 to the A4019 and new permanent right of access to provide, protect, inspect and maintain environmental and ecological mitigation | 1c |
| Land Plans -Sheet 6 | Land Plans -Sheet 6 | Land Plans -Sheet 6 |
| 6/1e | New right for the use of land southwest of Junction 10 at the location shown on sheets 5 and 6 of the works plans as construction compound no. 1 | 1i |
| 6/1g | New right to construct, use, protect, inspect and maintain the environmental mitigation associated with the construction of a new northbound exit slip from the M5 to the A4019 | 1b |
| 6/3a | New right to construct, use, protect, inspect and maintain the environmental mitigation associated with the construction of a new northbound exit slip from the M5 to the A4019 | 1b |
| 6/3a(i) | New right to construct, use, protect, inspect and maintain the environmental mitigation associated with the construction of a new northbound exit slip from the M5 to the A4019 | 1b |
| 6/3a(ii) | New right to construct, use, protect, inspect and maintain the environmental mitigation associated with the construction of a new northbound exit slip from the M5 to the A4019 | 1b |
| 6/3a(iii) | New right to construct, use, protect, inspect and maintain the environmental mitigation associated with the construction of a new northbound exit slip from the M5 to the A4019 | 1b |
| 6/10a | New right to construct, use, protect, inspect and maintain a flood compensation area | 5n |
| 6/11a | New right to construct, use, protect, inspect and maintain a flood compensation area | 5n |
| Land Plans -Sheet 7 | Land Plans -Sheet 7 | Land Plans -Sheet 7 |
| 7/1e | New right to construct, use, protect, inspect and maintain the environmental mitigation associated with the construction of a new northbound exit slip from the M5 to the A4019 | 1b |
| 7/3b | New right to construct, use, protect, inspect and maintain the environmental mitigation associated with the construction of a new southbound entry slip from the A4019 to the M5 | 1d |
| 7/3b(i) | New right to construct, use, protect, inspect and maintain the environmental mitigation associated with the construction of a new southbound entry slip from the A4019 to the M5 | 1d |
| 7/3c | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 7/4a | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 7/4b | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 7/4b(i) | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 7/4c(i) | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 7/4d | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 7/5a | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 7/6a | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 7/6b | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 7/7a | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| Land Plans - Sheet 10 | Land Plans - Sheet 10 | Land Plans - Sheet 10 |
| 10/3b | New right for the construction of motorway signage and associated cabling and ducting works | 1a |
| 10/3b(i) | New right for the construction of motorway signage and associated cabling and ducting works | 1a |
| 10/3b(ii) | New right for the construction of motorway signage and associated cabling and ducting works | 1a |
| Land Plans – Sheet 11 | Land Plans – Sheet 11 | Land Plans – Sheet 11 |
| 11/1a | New right to construct, use, protect, inspect and maintain a flood compensation area | 3e |
| 11/1b | New right to construct, use, protect, inspect and maintain a flood compensation area | 3e |
| 11/1c | New right to construct, use, protect, inspect and maintain a flood compensation area New right for the diversion, use, protection, inspection and maintenance of telecommunication cable and associated apparatus and equipment | 3e, 28 |
| 11/3a | New right for the realignment and widening of the A4019 (Tewkesbury Road) northwest of Junction 10 with associated footway, cycleway, shared use path, private access points, signage and ducting New right for the diversion of a public right of way FP ABO14 to the south side of the A4019 (Tewkesbury Road) New right for the construction of new or altered private means of access New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 3, 3c, 3d, 10, 28 |
| 11/3b | New right for the realignment and widening of the A4019 (Tewkesbury Road) northwest of Junction 10 with associated footway, cycleway, shared use path, private access points, signage and ducting New right for the realignment of the unclassified road known as Stanboro Lane New right for the diversion of telecommunication cable and associated apparatus and equipment | 3, 3a, 10 |
| Land Plans - Sheets 12 and 12A | Land Plans - Sheets 12 and 12A | Land Plans - Sheets 12 and 12A |
| 12/1b | New right for the use of land north of the A4019 (Tewkesbury Road) as construction compound no. 4 New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4i, 4j |
| 12/1b(i) | New right for the use of land north of the A4019 (Tewkesbury Road) as construction compound no. 4 New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4i, 4j |
| 12/1b(ii) | New right for the use of land north of the A4019 (Tewkesbury Road) as construction compound no. 4 New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4i, 4j |
| 12/1b(iii) | New right for the use of land north of the A4019 (Tewkesbury Road) as construction compound no. 4 New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4i, 4j |
| 12/1e | New right for the diversion, construction, use and maintenance of bridleway BR AUC1 under the A4019 (Tewkesbury Road) New right for the construction of new or altered private means of access New right for the diversion, use, protection, inspection and maintenance of water pipeline for the benefit of Severn Trent Water Limited New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited New right for the diversion, use, protection, inspection and maintenance of telecommunication cable and associated apparatus and equipment | 4c, 4g, 15, 16, 27 |
| 12/2b | New right for the use of land north of the A4019 (Tewkesbury Road) as construction compound no. 4 | 4i |
| 12/2b(i) | New right for the use of land north of the A4019 (Tewkesbury Road) as construction compound no. 4 | 4i |
| 12/2c | New right for the diversion, construction, use and maintenance of bridleway BR AUC1 under the A4019 (Tewkesbury Road) New right for the construction of new or altered private means of access New right for the construction of a public right of way (footpath) to link to diverted bridleway BR AUC1 New right for the diversion, use, protection, inspection and maintenance of water pipeline for the benefit of Severn Trent Water Limited New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited New right for the diversion, use, protection, inspection and maintenance of telecommunication cable and associated apparatus and equipment | 4c, 4g, 4z, 15, 16, 27 |
| 12/2k | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the use of land east of Withybridge Lane and west of new West Cheltenham Link Road as construction compound no. 5 | 5, 5b |
| 12/2k(i) | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the use of land east of Withybridge Lane and west of the new West Cheltenham Link Road as construction compound no. 5 New right for the diversion, use, protection, inspection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution plc | 5, 5b, 21 |
| 12/2v | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the construction and use of a private means of access track to the east of the West Cheltenham Link Road New right to construct, use, protect, inspect and maintain a flood compensation area New right for the diversion, use, protection, inspection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution plc | 5, 5k, 5n, 21 |
| 12/2w | New right to construct, use, protect, inspect and maintain a flood compensation area New right to construct, use, protect, inspect and maintain a flood compensation area | 5n, 5o |
| 12/2x | New right to construct, use, protect, inspect and maintain a flood compensation area New right for the diversion, use, protection, inspection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution plc | 5n, 21 |
| 12/6a | New right for the realignment and dualling of the A4019 (Tewkesbury Road) southeast of Junction 10, M5 to east of Gallagher Junction with associated footway, cycleway, shared use paths, private means of access, signage and ducting New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 4, 10 |
| 12/7a | New right for the use of land north of the A4019 (Tewkesbury Road) as construction compound no. 4 | 4i |
| 12/7b | New right for the use of land north of the A4019 (Tewkesbury Road) as construction compound no, 4 New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4i, 4j |
| 12/7b(i) | New right for the use of land north of the A4019 (Tewkesbury Road) as construction compound no. 4 | 4i |
| 12/7b(ii) | New right for the use of land north of the A4019 (Tewkesbury Road) as construction compound no. 4 | 4i |
| 12/7g | New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4j |
| 12/8b | New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4j |
| 12/9a | New right to construct, use, protect, inspect and maintain a flood compensation area | 5n |
| 12/9b | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation | 5 |
| 12/10a | New right to construct, use, protect, inspect and maintain a flood compensation area | 5n |
| 12/16a | New right for the realignment and dualling of the A4019 (Tewkesbury Road) southeast of Junction 10, M5 to east of Gallagher Junction with associated footway, cycleway, shared use paths, private means of access, signage and ducting New right for the diversion, use, provision and maintenance of telecommunication cable and associated apparatus and equipment | 4, 29 |
| 12/16b | New right for the realignment and dualling of the A4019 (Tewkesbury Road) southeast of Junction 10, M5 to east of Gallagher Junction with associated footway, cycleway, shared use paths, private means of access, signage and ducting New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 4, 29 |
| Land Plans – Sheets 13 and 13A | Land Plans – Sheets 13 and 13A | Land Plans – Sheets 13 and 13A |
| 13/1a | New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4j |
| 13/1a(i) | New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4j |
| 13/1e | New right for temporary access for the realignment and dualling for the A4019 (Tewkesbury Road) southeast of Junction 10, M5 to east of Gallegher Junction with associated footway, cycleway, shared use paths, private means of access, signage and ducting New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4, 4j |
| 13/1e(i) | New right for temporary access for the realignment and dualling for the A4019 (Tewkesbury Road) southeast of Junction 10, M5 to east of Gallegher Junction with associated footway, cycleway, shared use paths, private means of access, signage and ducting New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4, 4j |
| 13/1h | New right for the construction of new or altered private means of access New right for the diversion, use, protection and maintenance of water pipeline for the benefit of Severn Trent Water Limited | 4g, 15 |
| 13/2b | New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4j |
| 13/2d | New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4j |
| 13/3o | New right for the diversion, use, protection, inspection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution plc | 23 |
| 13/3w | New right to construct, use, protect, inspect and maintain mitigation planting for dormice New right for the diversion, use, protection, inspection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution plc | 4j, 23 |
| 13/3w(i) | New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4j |
| 13/3z | New right to cleanse, widen, deepen and maintain the existing ditch outfall from the proposed attenuation pond | 4q |
| 13/6a | New right for the construction of service roads running east and west of The Green New right for the diversion, use, protection and maintenance of gas main for the benefit of Wales & West Utilities Limited New right for the diversion use, protection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution PLC | 4n, 17, 22 |
| 13/11a | New right for the construction of new or altered private means of access New right for the construction of service roads running east and west of The Green New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4g, 4n,4j |
| 13/11b | New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4j |
| 13/12a | New right to construct, use, protect, inspect and maintain mitigation planting for dormice | 4j |
| 13/14a | New right for the construction of a service road to the south of the A4019 (Tewkesbury Road) serving properties including the Cotswold Area Civil Service Sports Association; Homecroft Drive and the West Cheltenham Community Fire Station New right for the diversion, use, protection and maintenance of water pipeline for the benefit of Severn Trent Water Limited New right for the diversion, use, protection and maintenance of gas main for the benefit of Wales & West Utilities Limited New right for the diversion, use, protection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution PLC New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 4v, 15, 18, 24, 27, 32 |
| 13/15a | New right for the construction of a service road to the south of the A4019 (Tewkesbury Road) serving properties including the Cotswold Area Civil Service Sports Association; Homecroft Drive; and the West Cheltenham Community Fire Station | 4v |
| 13/16a | New right for the construction of a service road to the south of the A4019 (Tewkesbury Road) serving properties including the Cotswold Area Civil Service Sports Association; Homecroft Drive and the West Cheltenham Community Fire Station New right for the diversion, use, protection and maintenance of water pipeline for the benefit of Severn Trent Water Limited New right for the diversion, use, protection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution PLC New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 4v, 15, 24, 32 |
| 13/17a | New right for the construction of a service road to the south of the A4019 (Tewkesbury Road) serving properties including the Cotswold Area Civil Service Sports Association; Homecroft Drive and the West Cheltenham Community Fire Station New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 4v, 32 |
| 13A/1a | New right to cleanse, widen, deepen and maintain the existing ditch outfall from the proposed attenuation pond | 4q |
| 13A/2a | New right to cleanse, widen, deepen and maintain the existing ditch outfall from the proposed attenuation pond | 4q |
| Land Plans – Sheet 14 | Land Plans – Sheet 14 | Land Plans – Sheet 14 |
| 14/6a | New right for the alteration of the signalised junction serving Gallagher Retail Park and the B4634 to the south of the A4019 (Tewkesbury Road) with maintenance bay New right for the diversion, use, protection and maintenance of gas main for the benefit of Wales & West Utilities | 4x, 18 |
| Land Plans – Sheet 15 | Land Plans – Sheet 15 | Land Plans – Sheet 15 |
| 15/3c | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the construction of new or altered private means of access New right for the diversion, construction, use and maintenance of public right of way FP AUC11 to the north of the River Chelt under the new River Chelt Bridge | 5, 5k, 5e |
| 15/3d | New right to construct, use, protect, inspect and maintain a flood compensation area New right to construct, use, protect, inspect and maintain a flood compensation area | 5n, 5o |
| 15/4a | New right to construct, use, protect, inspect and maintain a flood compensation area | 5n |
| 15/4b | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the construction, use, protection and maintenance of a new bridge over the River Chelt and associated environmental mitigation New right for the diversion, construction, use and maintenance of public right of way FP AUC11 to the north of the River Chelt under the new River Chelt Bridge | 5, 5d, 5e |
| 15/4e | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the construction, use, protection and maintenance of a new bridge over the River Chelt and associated environmental mitigation New right for the diversion, construction, use and maintenance of public right of way FP AUC11 to the north of the River Chelt under the new River Chelt Bridge | 5, 5d, 5e |
| 15/4f | New right for the construction, use, protection and maintenance of a new bridge over the River Chelt and associated environmental mitigation New right for the diversion, construction, use and maintenance of public right of way FP AUC11 to the north of the River Chelt under the new River Chelt Bridge | 5d, 5e |
| 15/5b | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the construction, use, protection and maintenance of a new bridge over the River Chelt and associated environmental mitigation New right for the diversion, construction, use and maintenance of public right of way FP AUC11 to the north of the River Chelt under the new River Chelt Bridge | 5, 5d, 5e |
| 15/5b(i) | New right for the construction, use, protection and maintenance of a new bridge over the River Chelt and associated environmental mitigation | 5d |
| 15/6a | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 15/7a | New right for the construction, use, protection and maintenance of a new bridge over the River Chelt and associated environmental mitigation | 5d |
| 15/8a | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the construction, use, protection and maintenance of a new bridge over the River Chelt and associated environmental mitigation New right for the diversion, construction, use and maintenance of public right of way FP ABO24 to the south of the River Chelt under the new River Chelt Bridge | 5, 5d, 5f |
| 15/8a(i) | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited | 5, 35 |
| 15/8b | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the construction, use, protection and maintenance of a new bridge over the River Chelt and associated environmental mitigation New right for the diversion, construction, use and maintenance of public right of way FP ABO24 to the south of the River Chelt under the new River Chelt Bridge | 5, 5d, 5f |
| 15/8c | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the construction, use, protection and maintenance of a new bridge over the River Chelt and associated environment mitigation New right for the diversion, construction, use and maintenance of public right of way FP ABO24 to the south of the River Chelt under the new River Chelt Bridge | 5, 5d, 5f |
| 15/8c(i) | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the use of land east of the new West Cheltenham Link Road as construction compound no. 7 | 5, 5g |
| 15/8c(ii) | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the use of land east of the new West Cheltenham Link Road as construction compound no. 7 New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited | 5, 5g, 35 |
| 15/8c(iii) | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the use of land east of the new West Cheltenham Link Road as construction compound no. 7 | 5, 5g |
| 15/8c(iv) | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the use of land east of the new West Cheltenham Link Road as construction compound no. 7 | 5, 5g |
| 15/8c(v) | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for the construction of new or altered private means of access | 5, 5k |
| 15/8k | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 15/8k(i) | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 15/8l | New right for the diversion, use, protection, inspection and maintenance of 170 metres of gas main for the benefit of Wales & West Utilities Limited | 35 |
| 15/8m | New right for the use of land east of the new West Cheltenham Link Road as construction compound no. 7 New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited | 5g, 35 |
| 15/8n | New right for the use of land east of the new West Cheltenham Link Road as construction compound no. 7 New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited | 5g, 35 |
| 15/8p | New right for the use of land east of the new West Cheltenham Link Road as construction compound no. 7 New right for the diversion, use, protection, inspection and maintenance of gas main for the benefit of Wales & West Utilities Limited | 5g, 35 |
| 15/9a | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 15/10a | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 15/10d | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation | 5 |
| 15/10e | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation | 5 |
| 15/10e(i) | New right for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation. | 5 |
| 15/10e(ii) | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation | 5 |
| Land Plans – Sheets 16 and 16A | Land Plans – Sheets 16 and 16A | Land Plans – Sheets 16 and 16A |
| 16/1a(i) | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/2a | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/2b | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/2c | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/2d | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/2e | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/3a | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/3c | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation | 5 |
| 16/3c(i) | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation | 5 |
| 16/3e | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation | 5 |
| 16/3e(i) | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation | 5 |
| 16/3e(ii) | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation | 5 |
| 16/3e(iii) | New right of temporary access for the construction of a new West Cheltenham Link Road south of the A4019 (Tewkesbury Road) to join with the B4634 with footway and cycle track to the west and private access, signage and ducting, and new permanent rights to provide, protect, inspect, and maintain environmental and ecological mitigation New right for working space for the realignment of the B4634 connecting to the new West Cheltenham Link Road with shared use path, private access, signage and ducting | 5, 6 |
| 16/3i | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/3l | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/3o | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/4a | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/4b | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/4c | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/4d | New right to construct, use, protect, inspect and maintain a flood compensation area | 6d |
| 16/5d | New right for working space for the realignment of the B4634 connecting to the new West Cheltenham Link Road with shared use path, private access, signage and ducting | 6 |
| 16/6b | New right for the construction of new or altered private means of access New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment New right for the diversion, use, protection and maintenance of telecommunication cable and associated apparatus and equipment | 6c, 8, 34 |
| 16/6d | New right for the diversion, use, protection, inspection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution plc | 25 |
| 16/8a | New right for the diversion, use, protection, inspection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution plc | 25 |
| 16/10c | New right for the diversion, use, protection, inspection and maintenance of electric cable and associated apparatus and equipment for the benefit of National Grid Electricity Distribution plc | 26 |
SCHEDULE 6 — MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS AND IMPOSITION OF RESTRICTIVE COVENANTS
Compensation enactments
1
The enactments for the time being in force with respect to compensation for the compulsory purchase of land apply, with the necessary modifications as respects compensation, in the case of a compulsory acquisition under this Order of a right by the creation of a new right or imposition of a restrictive covenant as they apply as respects compensation for the compulsory purchase of land and interests in land.
2
- (1) Without limitation on the scope of paragraph 1, the 1961 Act has effect subject to the modification set out in sub-paragraph (2).
- (2) For section 5A(5A) (relevant valuation date) of the 1961 Act substitute—
(5A) If— (a) the acquiring authority enters on land for the purposes of exercising a right in pursuance of a notice of entry under section 11(1) of the Compulsory Purchase Act 1965 (as modified by paragraph 5(5) of Schedule 6 to the M5 Junction 10 Development Consent Order 2025 (the “M5 Junction 10 Order”)); (b) the acquiring authority is subsequently required by a determination under paragraph 12 of Schedule 2A to the Compulsory Purchase Act 1965 (as substituted by paragraph 5(8) of Schedule 6 to the M5 Junction 10 Order) to acquire an interest in the land; and (c) the acquiring authority enter on and take possession of that land, the authority is deemed for the purposes of subsection (3)(a) to have entered on that land when it entered on that land for the purpose of exercising that right.
3
- (1) Without limitation on the scope of paragraph 1, the Land Compensation Act 1973[^f00084] has effect subject to the modifications set out in sub-paragraph (2).
- (2) In section 44(1) (compensation for injurious affection), as it applies to compensation for injurious affection under section 7 (measure of compensation in case of severance) of the 1965 Act as substituted by paragraph 5(3)—
- (a) for “land is acquired or taken from” substitute “a right or restrictive covenant over land is purchased from or imposed on”; and
- (b) for “acquired or taken from him” substitute “over which the right is exercisable or the restrictive covenant enforceable”.
Application of Part 1 of the 1965 Act
4
Part 1 of the 1965 Act, as applied by section 125 (application of compulsory acquisition provisions) of the 2008 Act (and modified by article 27 (modification of Part 1 of the 1965 Act)) to the acquisition of land under article 21 (compulsory acquisition of land), applies to the compulsory acquisition of a right by the creation of a new right, or to the imposition of a restrictive covenant under article 24(1) (compulsory acquisition of rights and imposition of restrictive covenants)—
- (a) with the modifications specified in paragraph 5; and
- (b) with such other modifications as may be necessary.
5
- (1) The modifications referred to in paragraph 4(a) are as follows.
- (2) References in the 1965 Act to land are, in the appropriate contexts, to be read (according to the requirements of the particular context) as referring to, or as including references to—
- (a) the right acquired or to be acquired, or the restriction imposed or to be imposed; or
- (b) the land over which the right is or is to be exercisable, or the restriction is or is to be enforceable.
- (3) For section 7 (measure of compensation in case of severance) of the 1965 Act substitute—
(7) In assessing the compensation to be paid by the acquiring authority under this Act, regard must be had not only to the extent (if any) to which the value of the land over which the right is to be acquired or the restrictive covenant is to be imposed is depreciated by the acquisition of the right or the imposition of the restrictive covenant but also to the damage (if any) to be sustained by the owner of the land by reason of its severance from other land of the owner, or injuriously affecting that other land by the exercise of the powers conferred by this or the special Act.
- (4) The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say—
- (a) section 9(4) (failure by owners to convey);
- (b) paragraph 10(3) of Schedule 1 (owners under incapacity);
- (c) paragraph 2(3) of Schedule 2 (absent and untraced owners); and
- (d) paragraphs 2(3) and 7(2) of Schedule 4 (common land),
are modified so as to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be compulsorily acquired or the restrictive covenant which is to be imposed is vested absolutely in the acquiring authority.
- (5) Section 11[^f00085] (powers of entry) of the 1965 Act is modified so as to secure that, where the acquiring authority has served notice to treat in respect of any right or restriction, as well as the notice of entry required by subsection (1) of that section (as it applies to a compulsory acquisition under article 21), it has power, exercisable in equivalent circumstances and subject to equivalent conditions, to enter for the purpose of exercising that right or enforcing that restrictive covenant; and sections 11A[^f00086] (powers of entry: further notices of entry), 11B[^f00087] (counter-notice requiring possession to be taken on specified date), 12[^f00088] (unauthorised entry) and 13[^f00089] (refusal to give possession to acquiring authority) of the 1965 Act are modified correspondingly.
- (6) Section 20[^f00090] (tenants at will, etc.) of the 1965 Act applies with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right or the enforcement of the restrictive covenant in question.
- (7) Section 22 (interests omitted from purchase) of the 1965 Act as modified by article 27(4) is also modified so as to enable the acquiring authority in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired or enforce the restrictive covenant imposed, subject to compliance with that section as respects compensation.
- (8) For Schedule 2A of the 1965 Act substitute—
SCHEDULE2A (1) (1) This Schedule applies where an acquiring authority serves a notice to treat in respect of a right over, or a restrictive covenant affecting, the whole or part of a house, building or factory and have not executed a general vesting declaration under section 4 of the 1981 Act as applied by article 28 (application of the 1981 Act) of the M5 Junction 10 Development Consent Order 2025 in respect of the land to which the notice to treat relates. (2) But see article 29(3) (acquisition of subsoil or airspace only) of the M5 Junction 10 Development Consent Order 2025 which excludes the acquisition of subsoil or airspace only from this Schedule. (3) In this Schedule, “house” includes any park or garden belonging to a house. (3) A person who is able to sell the house, building or factory (“the owner”) may serve a counter-notice requiring the acquiring authority to purchase the owner’s interest in the house, building or factory. (4) A counter-notice under paragraph 3 must be served within the period of 28 days beginning with the day on which the notice to treat was served. (5) On receiving a counter-notice, the acquiring authority must decide whether to— (a) withdraw the notice to treat, (b) accept the counter-notice, or (c) refer the counter-notice to the Upper Tribunal. (6) The acquiring authority must serve notice of their decision on the owner within the period of 3 months beginning with the day on which the counter-notice is served (“the decision period”). (7) If the acquiring authority decide to refer the counter-notice to the Upper Tribunal they must do so within the decision period. (8) If the authority do not serve notice of a decision within the decision period it is to be treated as if it had served notice of a decision to withdraw the notice to treat at the end of that period. (9) If the acquiring authority serve notice of a decision to accept the counter-notice, the compulsory purchase order and the notice to treat are to have effect as if they included the owner’s interest in the house, building or factory. (10) On a referral under paragraph 7, the Upper Tribunal must determine whether the acquisition of the right of the imposition of the restrictive covenant would— (a) in the case of a house, building or factory, cause material detriment to the house, building or factory, or (b) in the case of a park or garden, seriously affect the amenity or convenience of the house to which the park or garden belongs. (11) In making the determination, the Upper Tribunal must take into account— (a) the effect of the acquisition of the right or the imposition of the covenant, (b) the use to be made of the right or covenant proposed to be acquired or imposed, and (c) if the right or covenant is proposed to be acquired or imposed for works or other purposes extending to other land, the effect of the whole of the works and the use of the other land. (12) If the Upper Tribunal determines that the acquisition of the right or the imposition of the covenant would have either of the consequences described in paragraph 10, it must determine how much of the house, building or factory the acquiring authority ought to be required to take. (13) If the Upper Tribunal determines that the acquiring authority ought to be required to take some or all of the house, building or factory, the compulsory purchase order and the notice to treat are to have effect as if they included the owner’s interest in that land. (14) (1) If the Upper Tribunal determines that the acquiring authority ought to be required to take some or all of the house, building or factory, the acquiring authority may at any time within the period of 6 weeks beginning with the day on which the Upper Tribunal makes its determination withdraw the notice to treat in relation to that land. (2) If the acquiring authority withdraws the notice to treat under this paragraph it must pay the person on whom the notice was served compensation for any loss or expense caused by the giving and withdrawing of the notice. (15) Any dispute as to the compensation is to be determined by the Upper Tribunal.
SCHEDULE 7 — LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.