The Mona Offshore Wind Farm Order 2025
- (c) the notice or document is legible in all material respects; and
- (d) the notice or document is in a form sufficiently permanent to be used for subsequent reference.
- (6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within seven days of receipt that the recipient requires a paper copy of all or part of that notice or other document the sender must provide such a copy as soon as reasonably practicable.
- (7) Any consent to the use of electronic transmission given by a person may be revoked by that person in accordance with paragraph (8).
- (8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—
- (a) that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and
- (b) such revocation is final and takes effect on a date specified by the person in the notice but that date must not be less than seven days after the date on which the notice is given.
- (9) This article does not exclude the employment of any method of service not expressly provided for by it.
- (10) In this article “legible in all material respects” means that the information contained in the notice or document is available to that person to no lesser extent than it would be if served, given or supplied by means of a notice or document in printed form.
No double recovery
43
Compensation is not payable in respect of the same matter both under this Order and under any other enactment, any contract or any rule of law, or under two or more different provisions of this Order.
Requirements, appeals, etc.
44
Schedule 12 (approval of matters specified in requirements) has effect in relation to all agreements or approvals granted, refused or withheld in relation to the requirements.
Arbitration
45
- (1) Subject to article 37 (saving provisions for Trinity House), any difference under any provision of this Order, unless otherwise provided for, is to be referred to and settled in arbitration in accordance with the rules at Schedule 13 (arbitration rules) of this Order, by a single arbitrator to be agreed upon by the parties, within 14 days of receipt of the notice of arbitration, or if the parties fail to agree within the time period stipulated, to be appointed on application of either party (after giving written notice to the other) by the Secretary of State.
- (2) For the avoidance of doubt, any matter for which the consent or approval of the Secretary of State or NRW is required under any provision of this Order is not subject to arbitration.
SCHEDULE 1 — Authorised Project
PART 1 — Authorised Development
1
A nationally significant infrastructure project as defined in sections 14 (nationally significant infrastructure projects: general) and 15 (generating stations) of the 2008 Act located in the Irish Sea approximately 28 kilometres from the coast of North Wales being an offshore wind generating station with an electrical output capacity of over 350 megawatts comprising—
Intertidal and in the County of Conwy
Work No. 3:
- (a) installation of up to four subsea cable circuits between Work No. 2 and Work No. 8 from MLWS to MHWS approximately 245 metres including cable ducts and cable crossings;
- (b) trenchless installation technique works; and
- (c) access during construction, operation, maintenance and decommissioning;
Work No. 4:access to Work No. 3 during construction;
Work No. 5:access to Work Nos. 7 and 8 during construction;
Work No. 6:access to Work No. 8 during construction;
Work No. 7:temporary laydown area of up to 800 square metres including fencing together with access to Work No. 4 during construction;
Work No. 8:
- (a) installation of up to four buried cable circuits between Work No. 3 and Work No. 9 from MHWS to the A547 approximately 142 metres including cable ducts; and
- (b) trenchless installation technique works;
Work No. 9:
- (a) installation of up to four buried cable circuits between Work No. 8 and Work No. 10 approximately 10 metres including cable ducts;
- (b) trenchless installation technique works; and
- (c) access to Work No. 10 during construction, operation, maintenance and decommissioning including works to the public highway and visibility splays;
Work No. 10:
- (a) installation of up to four buried cable circuits between Work No. 9 and Work No. 11 approximately 216 metres including cable ducts;
- (b) installation of up to four transition joint bays;
- (c) trenchless installation technique works including the creation of entry and exit pits for trenchless installation techniques and cable trenching works;
- (d) temporary construction compound of up to 30,000 square metres comprising a secondary temporary construction compound and a transition joint bay temporary construction compound;
- (e) access during construction, operation, maintenance and decommissioning;
Work No. 11:
- (a) installation of up to four buried cable circuits between Work No. 10 and Work No. 12 approximately 878 metres including cable ducts; and
- (b) trenchless installation technique works including the creation of entry and exit pits for trenchless installation techniques and cable trenching works;
Work No. 12:
- (a) installation of up to four buried cable circuits between Work No. 11 and Work No. 14 approximately 3,986 metres including cable ducts; and
- (b) trenchless installation technique works including the creation of entry and exit pits for trenchless installation techniques and cable trenching works;
Work No. 12a:access to Work No. 12 during construction;
Work No. 13:primary temporary construction compound and secondary temporary construction compound and access to Work Nos. 12 and 14 during construction including works to the public highway and visibility splays;
Work No. 14:
- (a) installation of up to four buried cable circuits between Work No. 12 and Work No. 15 approximately 2,700 metres including cable ducts; and
- (b) trenchless installation technique works including the creation of entry and exit pits for trenchless installation techniques and cable trenching works;
Work No. 15:
- (a) installation of up to four buried cable circuits between Work No. 14 and Work No. 17 approximately 2,179 metres including cable ducts; and
- (b) trenchless installation technique pit works including the creation of entry and exit pits for trenchless installation techniques and cable trenching works;
Work No. 16: primary temporary construction compound and laydown area or secondary temporary construction compound and access to Work No. 15 during construction including works to the public highway and visibility splays;
In the County of Denbighshire:
Work No. 17:
- (a) installation of up to four buried cable circuits between Work No. 15 and Work No. 20 approximately 1,594 metres including cable ducts; and
- (b) trenchless installation technique pit works including the creation of entrance and exit pits for trenchless installation techniques and cable trenching works;
Work No. 31: temporary landscaping, ecological and environmental works;
Work No. 32: permanent landscaping, ecological and environmental works;
Work No. 33: land reprofiling and permanent landscaping, ecological and environmental works;
Work No. 34: permanent landscaping, ecological and environmental works;
Work No. 35:landscaping maintenance works;
Work No. 36:permanent landscaping, ecological and environmental works;
In the Counties of Conwy and Denbighshire:
Work No. 37: hedgerow enhancement works; and
PART 2 — Ancillary Works
2
Works within the Order limits which fall within the scope of the work assessed by the environmental statement comprising –
- (a) intrusive ground investigations including the making of boreholes and trial pits;
- (b) temporary landing places, moorings or other means of accommodating vessels in the construction and/or maintenance of the authorised development;
- (c) marking buoys, beacons, fenders and other navigational warning or ship impact protection works; and
- (d) works to the benefit or protection of land, watercourses or structures affected by the authorised development.
SCHEDULE 2 — Requirements
Time limits
1
- (1) Subject to sub-paragraph (2) the authorised project must commence no later than the expiration of five years beginning with the date this Order comes into force.
- (2) If proceedings are begun to challenge the validity of this Order before the end of the period referred to in sub-paragraph (1) the period in sub-paragraph (1) must be taken to be extended by one year.
Offshore design parameters
2
- (1) The offshore works must be constructed in accordance with the parameters assessed in the environmental statement and set out in Table 2.
- (2) The undertaker may not undertake Work No. 1 in a manner which would give rise to any materially new or materially different environmental effects to those identified in the environmental statement and in particular may not exceed the maximum rotor swept area as identified in Table 2.
| Parameter | Value |
|---|---|
| Maximum number of wind turbine generators | 96 |
| Maximum height of wind turbine generators when measured from LAT to the tip of the vertical blade (metres) | 364 |
| Maximum rotor diameter of each wind turbine generator (metres) | 320 |
| Maximum rotor swept area (square metres) | 5,468,884 |
| Minimum distance from LAT to the lowest point of the rotating blade for each turbine (metres) | 34 |
| Minimum distance between wind turbine generators in a row of wind turbine generators (metres) | 1,400 |
| Minimum distance between rows of wind turbine generators (metres) | 1,400 |
| Maximum diameter of pin piles for wind turbine generators on jacket pin pile foundation (metres) | 5.5 |
| Maximum diameter of gravity base at the seabed for wind turbine generators on gravity base foundations (metres) | 49 |
| Maximum diameter of buckets for wind turbine generators on suction bucket jackets (metres) | 18 |
| Maximum diameter of pin piles for offshore substation platform on jacket pin pile foundations (metres) | 5.5 |
| Maximum diameter of gravity base at the seabed for offshore substation platforms on gravity base foundations (metres) | 80 |
| Maximum diameter of buckets for offshore substation platforms on suction bucket jackets (metres) | 18 |
| Maximum total seabed footprint for wind turbine generators (including scour protection) (square metres) | 735,488 |
| Maximum number of offshore substation platforms | 4 |
| Maximum dimensions of offshore substation platforms (excluding towers, helipads, masts, and cranes): | |
| Height of main structure when measured from LAT (metres) | 70 |
| Length (metres) | 80 |
| Width (metres) | 60 |
| Maximum total seabed footprint area for offshore substation foundations (including scour protection) (square metres) | 24,964 |
| Maximum total length of cables within Work No. 1 (inter-array and interconnector) (kilometres) | 325 |
| Maximum total length of interconnector cables (kilometres) | 50 |
| Maximum total length of cables within Work No. 2 (export cables) (kilometres) | 360 |
| Maximum number of cable crossings (inter-array) | 67 |
| Maximum number of cable crossings (interconnector) | 10 |
| Maximum number of cable crossings (export cables) | 14 |
Aviation safety
3
- (1) The undertaker must exhibit such lights, with such shape, colour and character and at such times as are required by Air Navigation Order 2016[^f00044] and/or determined necessary for aviation safety in consultation with the Defence Infrastructure Organisation Safeguarding and as directed by the Civil Aviation Authority. Lighting installed specifically to meet Ministry of Defence aviation safety requirements must remain operational for the life of the authorised project unless otherwise agreed with the Defence Infrastructure Organisation Safeguarding.
- (2) The undertaker must notify Defence Infrastructure Organisation Safeguarding and the Civil Aviation Authority, at least 14 days prior to the commencement of the offshore works, of the following—
- (a) the date of the commencement of construction of the offshore works;
- (b) the expected date any wind turbine generators are brought into use;
- (c) the maximum height of any construction equipment to be used;
- (d) the maximum heights of any wind turbine generator and offshore substation platform to be constructed; and
- (e) the latitude and longitude of each wind turbine generator and offshore substation platform to be constructed.
- (3) The Defence Infrastructure Organisation Safeguarding and the Civil Aviation Authority must be notified of any changes to the information supplied under sub-paragraph (2) and of the completion of the construction of the offshore works.
- (4) The lights installed in accordance with sub-paragraph (1) will be operated at the lowest permissible light intensity level.
Stages of authorised project
4
- (1) No stage of the onshore works may commence until notification has been submitted to the relevant planning authority detailing whether the onshore works will be constructed:
- (a) in a single stage; or
- (b) in two or more stages.
- (2) No stage of the onshore works may commence until details of the stages of the onshore works have been submitted to and approved in writing by the relevant planning authority.
- (3) The stages of the onshore works must be implemented as approved.
Onshore Substation works
5
- (1) Construction of Work No. 22a must not commence until details of—
- (a) the layout;
- (b) scale;
- (c) proposed finished ground levels;
- (d) hard surfacing materials;
- (e) the dimensions, colour and materials used for the buildings;
- (f) security fencing;
- (g) vehicular and pedestrian access, parking and circulation areas; and
- (h) proposed and existing functional services above and below ground, including drainage, power and communications cables and pipelines, manholes and supports,
have been submitted to and approved in writing by the relevant planning authority following consultation with NRW as appropriate.
- (2) The details submitted under sub-paragraph (1) of this requirement must be in accordance with requirement 6 (detailed design parameters onshore) and substantially in accordance with the design principles.
- (3) Work No. 22a must be implemented as approved.
Detailed design parameters onshore
6
- (1) The onshore works must not exceed the parameters assessed in the environmental statement and set out in sub-paragraphs (2) and (3).
- (2) The maximum number of transition joint bays must not exceed four.
- (3) In relation to Work No. 22a—
- (a) the highest part of any building, excluding lightning rods, must not exceed 15 metres above finished ground level;
- (b) the highest part of any external electrical equipment, excluding lightning rods, must not exceed 12.5 metres above finished ground level;
- (c) the total area of the fenced compound (excluding its accesses) must not exceed 65,000 square metres; and
- (d) the total number of lightning rods within the fenced compound area must not exceed 12 and the height of any lightning rod must not exceed 30 metres above finished ground level.
- (4) Trenchless installation techniques must be used to install the cable ducts and electrical circuits where identified in the onshore crossing schedule for the purpose of passing under a relevant obstruction unless otherwise agreed by the relevant planning authority, following consultation with the relevant highway authority.
- (5) For the purpose of this requirement, finished ground level must not exceed 61 metres above ordnance datum.
Provision of landscaping
7
- (1) Work No. 22a must not be commenced until a landscape plan for Work Nos. 23, 24 and 31 to 36 and associated work programme has been submitted to and approved in writing by the relevant planning authority following, where appropriate, consultation with NRW.
- (2) The landscape plan must accord with the outline landscape and ecology management plan and must include details of all proposed hard and soft landscaping works including—
- (a) location, number, species, size and planting density of any proposed planting including any trees;
- (b) implementation timetables for all landscaping works; and
- (c) proposed management for landscaping works.
- (3) The landscape plan must be implemented as approved and managed in accordance with the details in the landscape and ecology management plan approved under sub-paragraph (1).
Implementation and maintenance of landscaping
8
- (1) All landscaping works must be carried out in accordance with the landscaping plan(s) approved under requirement 7 (provision of landscaping).
- (2) Any tree or shrub planted as part of an approved landscaping plan that, within a period of five years after planting, is removed, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased must be replaced in the first available planting season with a specimen of the same species and size as that originally planted unless a different species is otherwise agreed in writing with the relevant planning authority.
Code of construction practice
9
- (1) No stage of the onshore works may commence until for that stage a code of construction practice has been submitted to and approved in writing by the relevant planning authority following consultation with NRW and the relevant highways authority as appropriate.
- (2) The code of construction practice must accord with the outline code of construction practice and greenhouse gas reduction strategy and include, as appropriate to the relevant stage—
- (a) spillage and emergency response plan (in accordance with the outline spillage and emergency response plan);
- (b) dust management plan (in accordance with the outline dust management plan);
- (c) construction noise and vibration management plan (in accordance with the outline construction noise and vibration management plan) which must include details of an action plan containing details of the measures that would be implemented in the event of exceedance and repeated exceedances of construction noise and vibration threshold levels;
- (d) construction traffic management plan (in accordance with the outline construction traffic management plan);
- (e) communications plan (in accordance with the outline communications plan);
- (f) construction fencing plan (in accordance with the outline construction fencing plan);
- (g) construction surface water and drainage management plan (in accordance with the outline construction surface water and drainage management plan);
- (h) flood management plan (in accordance with the outline flood management plan);
- (i) public rights of way management strategy (in accordance with the outline public rights of way management strategy);
- (j) soil management plan (in accordance with the outline soil management plan);
- (k) site waste management plan (in accordance with the outline site waste management plan);
- (l) artificial light emissions plan (in accordance with the outline artificial light emissions plan);
- (m) biosecurity protocol (in accordance with the outline biosecurity protocol);
- (n) discovery strategy for contaminated land (in accordance with the outline discovery strategy for contaminated land);
- (o) arboriculture method statement (in accordance with the outline arboriculture method statement);
- (p) onshore construction method statement (in accordance with the outline onshore construction method statement); and
- (q) landfall construction method statement (in accordance with the outline landfall construction method statement).
- (3) Each code of construction practice must be implemented as approved.
- (4) Onshore site preparation works must be carried out in accordance with the applicable details set out in the outline code of construction practice, the greenhouse gas reduction strategy and as appropriate the outline plans noted in sub-paragraphs (2)(a) – (q) inclusive.
Highway accesses
10
- (1) No new temporary or permanent means of access to a highway to be used by vehicular traffic, or any temporary or permanent alteration to an existing means of access to a highway used by vehicular traffic, may be formed until a highways access management plan for that access has been submitted to and approved in writing by the relevant planning authority in consultation with the relevant highway authority.
- (2) The highways access management plan must accord with the outline highways access management plan.
- (3) The highway accesses must be implemented as approved.
Onshore archaeology
11
- (1) No stage of the onshore works may commence until for that stage an onshore written scheme of investigation has been submitted to and approved in writing by the relevant planning authority.
- (2) The onshore written scheme of investigation must accord with the outline onshore written scheme of investigation as appropriate for the relevant stage.
- (3) The onshore written scheme of investigation must be implemented as approved.
- (4) Onshore site preparation works, including those necessary to allow production of any scheme required under sub-paragraph (1) must only take place in accordance the applicable details set out in the outline onshore written scheme of investigation.
Landscape and ecology management plan
12
- (1) No stage of the onshore works may commence until for that stage a landscape and ecology management plan has, following consultation with NRW, been submitted to and approved in writing by the relevant planning authority.
- (2) The landscape and ecology management plan must accord with the outline landscape and ecology management plan as appropriate for the relevant stage and must include details of an implementation timetable.
- (3) The landscape and ecology management plan must be implemented as approved for the relevant stage and managed in accordance with the details in the landscape and ecology management plan approved under sub-paragraph (1).
- (4) Onshore site preparation works must be carried out in accordance with the applicable details set out in the outline landscape and ecology management plan.
European protected species onshore
13
- (1) No stage of the onshore works other than surveying and investigation necessary to comply with this requirement may be undertaken until, for that stage, pre-construction survey work has been carried out to establish whether a European protected species or nationally protected species under the Wildlife and Countryside Act 1981 is present on any of the land affected, or likely to be affected, by any part of that stage of the onshore works.
- (2) Where a European protected species or nationally protected species under the Wildlife and Countryside Act 1981 is shown to be present, the stage of the onshore works likely to affect the species must not commence until, after consultation with NRW, a scheme of protection and mitigation measures for that stage has been submitted to and approved in writing by the relevant planning authority or a European Protected Species licence has been granted by NRW.
- (3) Each stage of the onshore works which requires a scheme of protection and mitigation measures must accord with the approved scheme as set out in sub-paragraph (2) of this requirement.
- (4) In this paragraph, “European protected species” has the same meaning as in regulations 42 (European protected species of animals) and 46 (European protected species of plants) of the Conservation of Habitats and Species Regulations 2017.
- (5) In this paragraph, “nationally protected species” means any species protected under the Wildlife and Countryside Act 1981.
Construction hours
14
- (1) Except as otherwise agreed in the code of construction practice and subject to sub-paragraphs (2) to (4), construction of the onshore works and heavy goods vehicle traffic movements arriving or departing from the site of the relevant work may take place only between the hours of 0700 and 1900 from Monday to Friday and 0700 to 1300 on Saturday, with no activity on Sundays or bank holidays.
- (2) Subject to paragraph (3), construction of the onshore works and heavy goods vehicle traffic movements arriving or departing from the site of the relevant work may take place outside the hours specified in sub-paragraph (1) for certain identified activities including—
- (a) where continuous periods of construction are required, for works such as concrete pouring and finishing, electrical circuit pulling and jointing and testing, trenchless installation techniques, and dewatering pumps;
- (b) for the delivery and unloading of abnormal loads;
- (c) for the landfall works;
- (d) for any other time-critical element of the onshore works;
- (e) emergency works; and
- (f) mobilisation activities, which may take place one hour immediately prior to and one hour immediately after the hours specified in sub-paragraph (1).
- (3) Except as provided in sub-paragraph (4) and in relation to emergency works, the undertaker must notify the relevant planning authority of all construction works and activities which are to be undertaken outside the hours specified in sub-paragraph (1) by giving at least 48 hours notice in advance of those works and activities and those works and activities must not be undertaken outside the hours specified in sub-paragraph (1) until the relevant planning authority has agreed.
- (4) In respect of trenchless installation techniques, where continuous 24-hour working is required and has been assessed in the environmental statement, the undertaker must notify the relevant planning authority in advance by giving at least 48 hours’ notice of such works.
- (5) In the event of an emergency, notification of that emergency must be given to the relevant planning authority and the relevant highway authority as soon as reasonably practicable.
- (6) For the purposes of this requirement “emergency” means a situation where, if the relevant action is not taken, there will be adverse health, safety, security or environmental consequences that in the reasonable opinion of the undertaker would outweigh the adverse effects to the public (whether individuals, classes or generally as the case may be) of taking that action.
- (7) For the purposes of this requirement “mobilisation activities” include personnel briefings, inspections, tool-box talks, inductions, health and safety works, deliveries excluding heavy goods vehicle movements, movement to place of work, general preparation and site maintenance work but does not include operation of heavy machinery or operation of generators or flood lights.
Restoration of land used temporarily for construction
15
Any land landward of MLW which is used temporarily for construction of the onshore works and not ultimately incorporated in permanent works or approved landscaping or ecological works must be reinstated within 12 months of completion of the relevant stage of the onshore works in accordance with such details as have been submitted to and approved pursuant to Requirements 7, 9, and 12 in respect of reinstatement, unless alternative details in relation to that land are agreed in writing by the relevant planning authority.
Control of operational artificial light emissions
16
- (1) Work No. 22a must not be brought into operation until a written scheme for the management and mitigation of internal and external artificial light emissions from Work No. 22a has been submitted to and approved in writing by the relevant planning authority.
- (2) The written scheme for the management and mitigation of artificial light emissions must be implemented as approved, and maintained during the lifetime of Work No. 22a.
Control of noise during operational stage
17
- (1) The noise rating level for the operational lifetime of Work No. 22a must not exceed 34db at Tan y Bryn Uchaf (301667, 372765) at a position representative of the façade, in free-field conditions, of any building authorised or lawfully occupied for residential or accommodation purposes at the date of the granting of this Order.
- (2) The noise levels set out in sub-paragraph (1) are to be measured—
- (a) in accordance with British Standard BS4142:2014+A1:2019, methods for rating and assessing industrial and commercial sound; and
- (b) with a microphone placed 1.5 metres above the ground in free-field conditions (being at least 3.5 metres from the nearest vertical reflecting surface).
Operational drainage
18
- (1) Work No. 22 must not commence until, for that work, an operation drainage management strategy has, following consultation with NRW, been submitted to and approved in writing by the relevant planning authority.
- (2) The operation drainage management strategy must accord with the outline operation drainage management strategy.
- (3) The written operation drainage management strategy must be implemented as approved, prior to final commissioning of Work No. 22a, and maintained during the operational lifetime of Work No. 22a.
Skills and Employment plan
19
- (1) No stage of the authorised project may commence until, after consultation with the relevant authorities, a skills and employment plan has been submitted to and approved in writing by Denbighshire County Council on behalf of the relevant authorities.
- (2) The skills and employment plan must accord with the outline skills and employment plan.
- (3) The skills and employment plan must be implemented as approved.
- (4) For the purposes of this requirement the “relevant authorities” are Denbighshire County Council, Conwy County Borough Council, Isle of Man Government, and the Isle of Anglesey County Council.
Offshore decommissioning
20
No offshore works may commence until a written decommissioning programme in compliance with any notice served upon the undertaker by the Secretary of State pursuant to section 105(2) (requirement to prepare decommissioning programmes) of the 2004 Act has been submitted to the Secretary of State for approval.
Onshore decommissioning
21
- (1) A written scheme of decommissioning for the onshore works must be submitted to and approved in writing by the relevant planning authority at least six months prior to any decommissioning works commencing.
- (2) The written scheme of decommissioning for the onshore works must include a code of construction practice.
- (3) The approved written scheme of decommissioning must be implemented as approved in the carrying out of any decommissioning works or relevant part of such works.
Great Dun Fell, Lowther Hill and St. Anne’s Primary Surveillance Radar
22
- (1) No part of any wind turbine generator (excluding foundations) shall be erected as part of the authorised development until a primary radar mitigation scheme agreed in advance with the operator has been submitted to and approved in writing by the Secretary of State in order to mitigate the impact of the authorised development on the primary radar of the operator located at Great Dun Fell, Lowther Hill and St. Anne’s and associated air traffic management operations.
- (2) No part of any wind turbine generator (excluding foundations) shall be erected until the approved primary radar mitigation scheme has been implemented and the authorised development shall thereafter be operated fully in accordance with the approved scheme.
- (3) In this requirement—
- “operator” means NATS (En Route) plc, incorporated under the Companies Act 2006 (Company Number 4129273) whose registered office is 4000 Parkway, Whiteley, Fareham, Hampshire PO15 7FL or such other organisation licensed from time to time under sections 5 and 6 of the Transport Act 2000 to provide air traffic services to the relevant managed area (within the meaning of section 40 of the Transport Act 2000); and
- “primary radar mitigation scheme” or “scheme” means a detailed scheme agreed with the operator which sets out the measures to be taken to mitigate the impact of the development on the primary radar located at Great Dun Fell, Lowther Hill and St Annes and air traffic management operations of the operator.
Warton Aerodrome Primary Surveillance Radar
23
- (1) No part of any wind turbine generator shall be erected as part of the authorised development until a radar mitigation scheme has been submitted to and approved in writing by the Secretary of State, in consultation with the Ministry of Defence and the operator.
- (2) No wind turbine generator erected as part of the authorised development shall be permitted to rotate its rotor blades about its horizontal axis other than for the purpose of testing the proposed mitigation solution identified in the approved radar mitigation scheme until the Secretary of State, following consultation with the Ministry of Defence and the operator, has confirmed in writing that he is satisfied that—
- (a) the proposed mitigation solution has been subject to technical and operational assessment and, in particular, has undergone ‘in-situ’ testing in line with the requirements of (and for the time period(s) specified in) the approved radar mitigation scheme;
- (b) the performance criteria required to be met by the proposed mitigation solution, as specified in the approved radar mitigation scheme, have been met; and
- (c) the approved radar mitigation scheme has been implemented by the operator (the costs of which shall be the sole responsibility of the undertaker in accordance with sub-paragraph (4)(a)).
- (3) The approved radar mitigation scheme must remain in place and be complied with for so long as any of the wind turbine generators erected as part of the authorised development are operational and provided that the PSR remains an operational requirement of the Ministry of Defence or the operator (or both).
- (4) The undertaker shall be solely responsible for the costs of—
- (a) implementing the approved radar mitigation scheme prior to any wind turbine generator erected as part of the authorised development being permitted to rotate its rotor blades about its horizonal axis;
- (b) thereafter maintaining, repairing and replacing, including without limitation resolving any failure (howsoever caused) of the approved radar mitigation scheme for so long as any of the wind turbine generators erected as part of the authorised development are operational and provided that the PSR remains an operational requirement of the Ministry of Defence or the operator (or both); and
- (c) in the event of any amendment being made to the authorised development which gives rise to new or different adverse impacts to those identified by the environmental statement on the operation of the PSR or the PSR air traffic control operations, working with the Ministry of Defence and the operator in good faith to agree any additional mitigation measures required to prevent or remove such adverse impacts for so long as any of the wind turbine generators erected as part of the authorised development are operational and provided that the PSR remains an operational requirement of the Ministry of Defence or the operator (or both), together with the costs of implementing and maintaining on an ongoing basis those additional mitigation measures.
- (5) For the purposes of this requirement—
- “approved radar mitigation scheme” means the radar mitigation scheme as approved by the Secretary of State in accordance with sub-paragraph (1);
- “Ministry of Defence” means the Ministry of Defence as represented by Defence Infrastructure Organisation – DIO Safeguarding, DIO Head Office, St George’s House, DMS Whittington, Litchfield, Staffordshire, WS14 9PY or any successor body;
- “operator” means BAE Systems (Operations) Limited (incorporated in England and Wales with company number 01996687 whose registered office is at Victory Point, Lyon Way, Frimley, Camberley, Surrey, GU16 7EX) or such other organisation as is licensed from time to time under sections 5 and 6 of the Transport Act 2000 to provide air traffic services at Warton Aerodrome or any other organisation employed by BAE Systems (Operations) Limited to provide an air traffic service at Warton Aerodrome;
- “PSR” means the primary surveillance radar at Warton Aerodrome or any upgrade thereto or replacement thereof;
- “PSR air traffic control operations” means the air traffic control operations, including both civil and military aircraft operations, of the Ministry of Defence or the operator (or both) which are reliant upon the PSR; and
- “radar mitigation scheme” means a scheme designed to prevent or remove any adverse impacts arising from the authorised development upon the operation of the PSR or the PSR air traffic control operations.
Air traffic services at Liverpool John Lennon Airport
24
- (1) No part of any wind turbine generator (excluding foundations) shall be erected as part of the authorised development until the Secretary of State, having consulted with the operator and the Civil Aviation Authority, confirms in writing that either—
- (a) no appropriate mitigation is required in respect of the authorised development; or
- (b) appropriate mitigation is required to be implemented and maintained for the life of the authorised development.
- (2) Where appropriate mitigation is required, no wind turbine generator forming part of the authorised development is permitted to rotate its blades on its horizontal axis until the appropriate mitigation has been approved by the Secretary of State, having consulted with the operator and the Civil Aviation Authority, and implemented.
- (3) The undertaker shall thereafter comply with all obligations contained within the approved mitigation for the life of the authorised development.
- (4) For the purposes of this requirement—
- “appropriate mitigation” means measures agreed with the Civil Aviation Authority and the operator to prevent or remove any adverse impacts which the operation of the authorised development will have on the operator’s ability to provide safe and efficient air traffic services for Liverpool John Lennon Airport during the life of the authorised development;
- “approved mitigation” means the appropriate mitigation approved by the Secretary of State in accordance with sub-paragraph (2); and
- “operator” means Liverpool Airport Limited incorporated under the Companies Act 2006 (Company Number 2116704) whose registered office is Venus Building, 1 Old Park Lane, Trafford City, Manchester, England, M41 7HA or such other organisation as is licensed from time to time under sections 5 and 6 of the Transport Act 2000 to provide air traffic services for Liverpool John Lennon Airport.
Operation of Blackpool Airport
25
- (1) No part of any wind turbine generator (excluding foundations) shall be erected as part of the authorised development until the Secretary of State, having consulted with the operator and the CAA, has confirmed in writing that he is satisfied that—
- (a) appropriate mitigation will be implemented and maintained throughout the lifetime of the authorised development; and
- (b) appropriate arrangements have been put in place with the operator to ensure that such appropriate mitigation is so implemented and maintained
- (2) The undertaker shall thereafter comply with all obligations contained within the approved mitigation throughout the lifetime of the authorised development.
- (3) For the purposes of this requirement—
- “appropriate mitigation” means appropriate mitigation measures to prevent or remove any adverse impacts which the authorised development will have on the ability of the operator to provide safe airport operational and air traffic services (including but not limited to any adverse impacts on instrument flight procedures, minimum sector altitudes, and very high frequency radio and direction finding communication systems) for Blackpool Airport;
- “approved mitigation” means the appropriate mitigation agreed with the CAA and the operator and approved by the Secretary of State in accordance with sub-paragraph (1);
- “CAA” means the Civil Aviation Authority constituted by the Civil Aviation Act 1982; and
- “operator” means Blackpool Airport Operations Limited (incorporated in England and Wales with company number 09307995 and whose registered office is Number One Bickerstaffe Square, Talbot Road, Blackpool FY1 3AH), or such other organisation as is licensed from time to time under sections 5 and 6 of the Transport Act 2000 to provide air traffic services for Blackpool Airport.
Air traffic services at Isle of Man Airport
26
- (1) No part of any wind turbine generator (excluding foundations) shall be erected as part of the authorised development until the Secretary of State, having consulted with the operator and the Isle of Man Civil Aviation Administration, confirms in writing that either—
- (a) no appropriate mitigation is required in respect of the authorised development; or
- (b) an appropriate mitigation scheme is required to be implemented and maintained for the life of the authorised development.
- (2) Where appropriate mitigation is required, no wind turbine generator forming part of the authorised development is permitted to rotate its blades on its horizontal axis until the appropriate mitigation has been approved by the Secretary of State, having consulted with the operator and the Isle of Man Civil Aviation Administration, and implemented.
- (3) The undertaker shall thereafter comply with all obligations contained within the approved mitigation for the life of the authorised development.
- (4) For the purposes of this requirement—
- “appropriate mitigation scheme” means a scheme agreed with the operator which sets out measures taken to prevent or remove any adverse impacts of the authorised development on the Isle of Man Primary Surveillance Radar and air traffic management operations and the operator’s ability to provide safe and efficient air traffic services for Isle of Man Airport during the life of the authorised development;
- “approved mitigation” means the appropriate mitigation approved by the Secretary of State in accordance with sub-paragraph (2); and
- “operator” means Isle of Man Airport or such other organisation as is licensed from time to time to provide air traffic services for Isle of Man Airport.
Operation of Walney Aerodrome (Air traffic services)
27
- (1) No part of any wind turbine generator shall be erected as part of the authorised development until—
- (a) the Secretary of State, having consulted with the operator and the CAA, confirms in writing that no mitigation is required in respect of the authorised development; or
- (b) the Secretary of State has, having consulted with the operator and the CAA—
- (i) approved in writing an ATS mitigation scheme; and
- (ii) confirmed in writing that he is satisfied that the approved ATS mitigation scheme has been implemented by the operator.
- (2) The approved ATS mitigation scheme must remain in place and be complied with for the lifetime of the authorised development (including the period during which the authorised development is being decommissioned in accordance with the decommissioning programme approved pursuant to requirement 20).
- (3) The undertaker shall be solely responsible for the costs of—
- (a) implementing the approved ATS mitigation scheme prior to the erection of any part of any wind turbine generator ... forming part of the authorised development;
- (b) thereafter maintaining, repairing and replacing, including without limitation resolving any failure (howsoever caused) of the approved ATS mitigation scheme throughout the lifetime of the authorised development (including the period during which the authorised development is being decommissioned in accordance with the decommissioning programme approved pursuant to requirement 20); and
- (c) in the event of any amendment being made to the authorised development which gives rise to adverse impacts on the operation of Walney Aerodrome which are new or different to those identified by the environmental statement, working with the CAA and the operator in good faith to agree any additional mitigation measures required to prevent or remove such adverse impacts throughout the lifetime of the authorised development (including the period during which the authorised development is being decommissioned in accordance with the decommissioning programme approved pursuant to requirement 20, together with the costs of implementing and maintaining on an ongoing basis those additional mitigation measures.
- (4) For the purposes of this requirement—
- “Approved ATS mitigation scheme” means the ATS mitigation scheme as approved by the Secretary of State in accordance with paragraph (1)(b)(i);
- “ATS mitigation scheme” means a scheme which is designed to prevent or remove any adverse impacts arising from the authorised development on the operation of Walney Aerodrome, including but not limited to:the Aerodrome’s ability to provide and deliver on an uninterrupted basis—national sovereign defence capabilities;safe airport operational and air traffic services that are fit for purpose for both civil and military aircraft operations; andany other operational requirements which are identified by the operator.the Aerodrome’s IFP, MSA and VHF communication systems;
- “CAA” means the Civil Aviation Authority constituted by the Civil Aviation Act 1982;
- “IFP” means instrument flight procedures;
- “MSA” means minimum sector altitude;
- “operator” means BAE Systems Marine Limited (incorporated in England and Wales with company number 00229770, whose registered office is at Victory Point, Lyon Way, Frimley, Camberley, Surrey, GU16 7EX) or such other organisation as is licensed from time to time under sections 5 and 6 of the Transport Act 2000 to provide air traffic services at Walney Aerodrome or any organisation employed by BAE Systems Marine Limited to provide an air traffic service at Walney Aerodrome; and
- “VHF” means very high frequency.
Operation of Warton Aerodrome (Air traffic services)
28
- (1) No part of any wind turbine generator shall be erected as part of the authorised development until—
- (a) the Secretary of State, having consulted with the operator and the CAA, confirms in writing that no mitigation is required in respect of the authorised development; or
- (b) the Secretary of State has, having consulted with the operator and the CAA,—
- (i) approved in writing an ATS mitigation scheme; and
- (ii) confirmed in writing that he is satisfied that the approved ATS mitigation scheme has been implemented by the operator.
- (2) The approved ATS mitigation scheme must remain in place and be complied with for the lifetime of the authorised development (including the period during which the authorised development is being decommissioned in accordance with the decommissioning programme approved pursuant to requirement 20).
- (3) The undertaker shall be solely responsible for the costs of—
- (a) implementing the approved ATS mitigation scheme prior to the erection of any part of any wind turbine generator ... forming part of the authorised development;
- (b) thereafter maintaining, repairing and replacing, including without limitation resolving any failure (howsoever caused) of the approved ATS mitigation scheme throughout the lifetime of the authorised development (including the period during which the authorised development is being decommissioned in accordance with the decommissioning programme approved pursuant to requirement 20); and
- (c) in the event of any amendment being made to the authorised development which gives rise to adverse impacts on the operation of Warton Aerodrome which are new or different to those identified by the environmental statement, working with the CAA and the operator in good faith to agree any additional mitigation measures required to prevent or remove such adverse impacts throughout the lifetime of the authorised development (including the period during which the authorised development is being decommissioned in accordance with the decommissioning programme approved pursuant to requirement 20), together with the costs of implementing and maintaining on an ongoing basis those additional mitigation measures.
- (4) For the purposes of this requirement—
- “approved ATS mitigation scheme” means the ATS mitigation scheme as approved by the Secretary of State in accordance with sub-paragraph (b)(i).
- “ATS mitigation scheme” means a scheme which is designed to prevent or remove any adverse impacts arising from the authorised development on the operation of Warton Aerodrome, including, but not limited to: the Aerodrome’s ability to provide and deliver on an uninterrupted basis— national sovereign defence capabilities; safe airport operational and air traffic services that are fit for purpose for both civil and military aircraft operations; and any other operational requirements which are identified by the operator. the Aerodrome’s IFP, MSA, DF, VHF and UHF communication systems;
- “CAA” means the Civil Aviation Authority constituted by the Civil Aviation Act 1982;
- “DF” means direction finding;
- “IFP” means instrument flight procedures;
- “MSA” means minimum sector altitude;
- “operator” means BAE Systems (Operations) Limited (incorporated in England and Wales with company number 01996687, whose registered office is at Victory Point, Lyon Way, Frimley, Camberley, Surrey, GU16 7EX) or such other organisation as is licensed from time to time under sections 5 and 6 of the Transport Act 2000 to provide air traffic services at Warton Aerodrome or any ... organisation employed by BAE Systems (Operations) Limited to provide an air traffic service at Warton Aerodrome; ...
- “UHF” means ultra high frequency; and
- “VHF” means very high frequency.
Wake effects
29
- (1) No part of any wind turbine generator may be erected as part of the authorised development until either—
- (a) A wake effects plan has been submitted to and approved by the Secretary of State; or
- (b) The undertaker has provided evidence to the Secretary of State that alternative mitigation for wake effects has been agreed with the existing Ørsted offshore wind farms.
- (2) The wake effects plan provided in accordance with paragraph (1)(a) must include details of reasonable steps that have been taken by the undertaker to minimise wake effects on the existing Ørsted offshore wind farms whilst maximising the capacity of the authorised development within the identified technical, environmental and other constraints of the authorised development.
- (3) Where paragraph (1)(a) applies the design plan submitted to the licencing authority under condition 17(1)(a) of schedule 14 of this Order must be in accordance with any approved wake effects plan.
- (4) For the purposes of this requirement—
- “existing Ørsted offshore wind farms” means Barrow offshore wind farm, Burbo Bank extension, Walney Extension, West of Duddon Sands, Walney offshore wind farm or Burbo bank.
Landscape enhancement scheme
30
- (1) Work No. 1 must not be commenced until a scheme for the provision of landscape enhancement in accordance with the landscape enhancement scheme principles has been submitted to and approved by the relevant planning authority following consultation with Natural Resources Wales, the Isle of Anglesey County Council and Eryri National Park Authority.
- (2) The landscape enhancement scheme shall set out appropriate measures to compensate for the impact of the authorised development on the protected landscapes of the Isle of Anglesey National Landscape and Eryri National Park.
- (3) The landscape enhancement scheme shall be implemented as approved.
Requirement for written approval
31
Where under any of the requirements the approval or agreement of the Secretary of State, the relevant planning authority or another person is required, that approval or agreement must be given in writing.
Amendments to approved details
32
With respect to any requirement which requires the authorised project to be carried out in accordance with the details approved under this Schedule, the approved details are taken to include any amendments that may subsequently be approved or agreed by the relevant discharging authority.
SCHEDULE 3 — Streets subject to street works
In the County of Conwy:
| (1) Street | (2) Extent as shown on the street works access plan |
|---|---|
| A547, Abergele Road | Between points 1 and 2, as shown on Sheet 2 of the street works and access to works plan |
| Public highway unclassified road off Rhyd-Y-Foel Road | Between points 3 and 4, as shown on Sheet 3 of the street works and access to works plan |
| Public highway unclassified road off Rhyd-Y-Foel Road | Between points 5 and 6, as shown on Sheet 4 of the street works and access to works plan |
| Public highway unclassified road connecting Rhyd-Y-Foel Road and Ffordd Abergele | Between points 7 and 8, as shown on Sheet 4 of the street works and access to works plan |
| Ffordd Abergele | Between points 9 and 10, as shown on Sheet 5 of the street works and access to works plan |
| A548 | Between points 11 and 12, as shown on Sheet 6 of the street works and access to works plan |
| B5381 Glascoed Road | Between points 13 and 14, as shown on Sheet 6 of the street works and access to works plan |
| Public highway unclassified road north of B5381 Glascoed Road | Between points 15 and 16, as shown on Sheet 6 of the street works and access to works plan |
| Public highway unclassified road connecting the B5381 Glascoed Road and A548 | Between points 17 and 18, as shown on Sheet 7 of the street works and access to works plan |
| Public highway unclassified road south of the B5381 Glascoed Road | Between points 19 and 20, as shown on Sheet 7 of the street works and access to works plan |
| Public highway unclassified road south of the B5381 Glascoed Road | Between points 21 and 22, as shown on Sheet 8 of the street works and access to works plan |
| B5381 Glascoed Road | Between points 23 and 24, as shown on Sheet 8 of the street works and access to works plan |
| Public highway unclassified road south of the B5381 Glascoed Road | Between points 25 and 26, as shown on Sheet 8 of the street works and access to works plan |
In the County of Denbighshire:
| (1) Street | (2) Extent as shown on the street works access plan |
|---|---|
| Public highway unclassified road south of the B5381 Glascoed Road | Between points 27 and 28, as shown on Sheet 9 of the street works and access to works plan |
| B5381 Glascoed Road | Between points 29 and 30, as shown on Sheet 9 of the street works and access to works plan |
| Public highway unclassified road west of Cae Onnen | Between points 31 and 32, as shown on Sheet 9 of the street works and access to works plan |
| B5381 Glascoed Road and Public highway unclassified road south | Between points 33 and 34, as shown on Sheet 9 of the street works and access to works plan |
| Public highway unclassified road south of the B5381 Glascoed Road towards Cae Onnen | Between points 34 and 35, as shown on Sheet 9 of the street works and access to works plan |
| B5381 / Glascoed Road | Between points 36 and 37, as shown on Sheet 9 of the street works and access to works plan |
| Public highway unclassified road south-east of Cae Onnen | Between points 38 and 39, as shown on Sheet 10 of the street works and access to works plan |
| Public highway unclassified road south of B5381 Glascoed Road, south-west of Bodelwyddan Substation | Between points 40 and 41, as shown on Sheet 11 of the street works and access to works plan |
| B5381 Glascoed Road | Between points 42 and 43, as shown on Sheet 11 of the street works and access to works plan |
SCHEDULE 4 — Streets to be temporarily closed or restricted
In the County of Conwy:
| (1) Street to be temporarily closed or restricted | (2) Extent of temporary closure or restriction as shown on the street works and access to works plan |
|---|---|
| A547, Abergele Road | Between points 1 and 2, as shown on Sheet 2 of the street works and access to works plan |
| Public highway unclassified road off Rhyd-Y-Foel Road | Between points 3 and 4, as shown on Sheet 3 of the street works and access to works plan |
| Public highway unclassified road off Rhyd-Y-Foel Road | Between points 5 and 6, as shown on Sheet 4 of the street works and access to works plan |
| Public highway unclassified road connecting Rhyd-Y-Foel Road and Ffordd Abergele | Between points 7 and 8, as shown on Sheet 4 of the street works and access to works plan |
| Ffordd Abergele | Between points 9 and 10, as shown on Sheet 5 of the street works and access to works plan |
| A548 | Between points 11 and 12, as shown on Sheet 6 of the street works and access to works plan |
| B5381 Glascoed Road | Between points 13 and 14, as shown on Sheet 6 of the street works and access to works plan |
| Public highway unclassified road north of B5381 Glascoed Road | Between points 15 and 16, as shown on Sheet 6 of the street works and access to works plan |
| Public highway unclassified road south of the B5381 Glascoed Road | Between points 19 and 20, as shown on Sheet 7 of the street works and access to works plan |
| Public highway unclassified road south of the B5381 Glascoed | Between points 21 and 22, as shown on Sheet 8 of the street works and access to works plan |
In the County of Denbighshire:
| (1) Street to be temporarily closed or restricted | (2) Extent of temporary closure or restriction as shown on the street works and access to works plan |
|---|---|
| Public highway unclassified road south of the B5381 Glascoed Road | Between points 27 and 28, as shown on Sheet 9 of the street works and access to works plan |
| B5381 Glascoed Road | Between points 29 and 30, as shown on Sheet 9 of the street works and access to works plan |
| Public highway unclassified road west of Cae Onnen | Between points 31 and 32, as shown on Sheet 9 of the street works and access to works plan |
| B5381 Glascoed Road and Public highway unclassified road south | Between points 33 and 34, as shown on Sheet 9 of the street works and access to works plan |
| Public highway unclassified road south of the B5381 Glascoed Road towards Cae Onnen | Between points 34 and 35, as shown on Sheet 9 of the street works and access to works plan |
| B5381 / Glascoed Road | Between points 36 and 37, as shown on Sheet 9 of the street works and access to works plan |
| Public highway unclassified road south-east of Cae Onnen | Between points 38 and 39, as shown on Sheet 10 of the street works and access to works plan |
| Public highway unclassified road south of B5381 Glascoed Road, south-west of Bodelwyddan Substation | Between points 40 and 41, as shown on Sheet 11 of the street works and access to works plan |
| B5381 Glascoed Road | Between points 42 and 43, as shown on Sheet 11 of the street works and access to works plan |
SCHEDULE 5 — Public rights of way to be temporarily closed or restricted
In the County of Conwy:
| (1) Public right of way to be temporarily closed or restricted | (2) Extent as shown on the public rights of way plan |
|---|---|
| Llanddulas & Rhyd y Foel 14 Footpath | Between points 1a and 1b as shown on sheet 3 and 4 of the temporary closure of public rights of way plan |
| Betws yn Rhos 43 Footpath | Between points 2a and 2b as shown on sheet 4 of the temporary closure of public rights of way plan |
| Betws yn Rhos 44 Footpath | Between points 3a and 3b as shown on sheet 4 and 5 of the temporary closure of public rights of way plan |
| Betws yn Rhos 48 Footpath | Between points 4a and 4b as shown on sheet 5 of the temporary closure of public rights of way plan |
| Llanfair TH 12 Footpath | Between points 5a and 5b as shown on sheet 6 of the temporary closure of public rights of way plan |
| Llanfair TH 15 Footpath | Between points 6a and 6b as shown on sheets 6 and 7 of the temporary closure of public rights of way plan |
| Llanfair TH 16 Bridleway | Between points 7a and 7b as shown on sheet 7 of the temporary closure of public rights of way plan |
| Llanfair TH 19 Bridleway | Between points 8a and 8b as shown on sheet 7 of the temporary closure of public rights of way plan |
In the County of Denbighshire:
| (1) Public right of way to be temporarily closed or restricted | (2) Extent as shown on the public rights of way plan |
|---|---|
| Footpath DE/105/99 | Between points 9a and 9b as shown on sheet 8 of the temporary closure of public rights of way plan |
| Footpath DE/105/5 | Between points 10a and 10b as shown on sheets 9 and 10 of the temporary closure of public rights of way plan |
| Footpath DE/105/6 | Between points 11a and 11b as shown on sheets 10 and 11 of the temporary closure of public rights of way plan |
| Bridleway DE 208/32 | Between points 12a and 12b as shown on sheet 11 of the temporary closure of public rights of way plan |
SCHEDULE 6 — Access to works
In the County of Conwy:
| (1) Reference as shown on the street works and access to works plan | (2) Description of new accesses and crossings |
|---|---|
| AC-A1 | From the public highway Sea Road as shown on sheet 1 of the street works and access to works plan |
| AC-B1 | From the public highway A457 Abergele Road as shown on sheet 2 of the street works and access to works plan |
| AC-C1 | Crossing point over and from public highway unclassified road as shown on sheet 3 of the street works and access to works plan |
| AC-C2 | Crossing point over and from public highway unclassified road shown on sheet 3 of the street works and access to works plan |
| AC-D1 | Crossing point over and from public highway unclassified road as shown on sheet 4 of the street works and access to works plan |
| AC-D2 | Crossing point over and from public highway unclassified road as shown on sheet 4 of the street works and access to works plan |
| AC-E1 | Crossing point over and from public highway unclassified road as shown on sheet 4 of the street works and access to works plan |
| AC-E2 | Crossing point over and from public highway unclassified road as shown on sheet 4 of the street works and access to works plan |
| AC-F1 | Crossing point over and from Ffordd Abergele as shown on sheet 5 of the street works and access to works plan |
| AC-F2 | Crossing point over and from Fford Abergele as shown on sheet 5 of the street works and access to works plan |
| AC-G1 | From the public highway B5381 Glascoed Road as shown on sheet 6 of the street works and access to works plan |
| AC-G2 | Crossing point over and from the public highway B5381 Glascoed Road as shown on sheet 6 of the street works and access to works plan |
| AC-H1 | From the public highway A548 as shown on sheet 6 of the street works and access to works plan. |
| AC-I1 | Crossing point over and from public highway unclassified road as shown on sheet 7 of the street works and access to works plan |
| AC-I2 | Crossing point over and from public highway unclassified road as shown on sheet 7 of the street works and access to works plan |
| AC-J1 | Crossing point over and from public highway unclassified road as shown on sheet 8 of the street works and access to works plan |
| AC-J2 | Crossing point over and from public highway unclassified road as shown on sheet 8 of the street works and access to works plan |
| AC-K1 | From the public highway B5381 Glascoed Road as shown on sheet 8 of the street works and access to works plan |
| AC-L1 | Crossing point over and from public highway unclassified road as shown on sheet 8 of the street works and access to works plan |
| AC-L2 | Crossing point over and from public highway unclassified road as shown on sheet 8 of the street works and access to works plan |
In the County of Denbighshire:
| (1) Reference as shown on the street works and access to works plan | (2) Description of new accesses and crossings |
|---|---|
| AC-M1 | Crossing point over and from public highway unclassified road as shown on sheet 9 of the street works and access to works plan |
| AC-M2 | Crossing point over and from public highway unclassified road as shown on sheet 9 of the street works and access to works plan |
| AC-N1 | From the public highway B5381 Glascoed Road as shown on sheet 9 of the street works and access to works plan |
| AC-O1 | Crossing point over and from public highway unclassified road as shown on sheet 9 of the street works and access to works plan |
| AC-O2 | Crossing point over and from public highway unclassified road as shown on sheet 9 of the street works and access to works plan |
| AC-P1 | Crossing point over and from public highway unclassified road as shown on sheet 10 of the street works and access to works plan |
| AC-P2 | Crossing point over and from public highway unclassified road as shown on sheet 10 of the street works and access to works plan |
| AC-Q1 | Crossing point over and from public highway unclassified road as shown on sheet 11 of the street works and access to works plan |
| AC-Q2 | Crossing point over and from public highway unclassified road as shown on sheet 11 of the street works and access to works plan |
| AC-R1 | From the public highway B5381 Glascoed Road as shown on sheet 11 of the street works and access to works plan |
| AC-S1 | From the public highway B5381 Glascoed Road as shown on sheet 11 of the street works and access to works plan |
| AC-T1 | From public highway unclassified road as shown on sheet 11 of the street works and access to works plan |
SCHEDULE 7 — Land of which only temporary possession may be taken
In the County of Conwy:
| (1) Number of plot shown onland plan (onshore) | (2) Purpose for which temporary possession may be taken | (3) Relevant part of authorised project |
|---|---|---|
| 01-001, 01-002 | Access to Work No. 3 during construction | Work Nos. 3 and 4 |
| 01-003, 01-004, | Temporary construction compound for vehicle parking, a circulation area and a laydown area of up to 800 square metres including fencing together with access to Work No. 4 during construction | Work Nos. 4 and 7 |
| 01-005, 01-006, 01-007, 01-008, 01-009, 01-010, 01-011 | Access during construction | Work Nos. 5, 7 and 8 |
| 02-013, 02-013a, 02-014, 02-015, 02-016, 02-017, 02-018, 02-019, 02-020 | Access to Work No. 8 during construction | Work Nos. 6 and 8 |
| 02-030 | Access to Work No. 10 during construction including works to the public highway and visibility splays | Work Nos. 9 and 10 |
| 03-052, 03-055, 03-057, 03-058, 04-068, 04-069, 04-071, 04-076 | Access to Work No. 12 during construction | Work Nos. 12 and 12a |
| 05-094, 05-095, 06-099, 06-102, 06-104 | Temporary construction compounds and laydown areas with a total maximum area of 37,500 square metres and access to Work Nos. 12 and 14 during construction including works to the public highway and visibility splays | Work Nos. 12, 13 and 14 |
In the County of Denbighshire:
| (1) Number of plot shown on land plan (onshore) | (2) Purpose for which temporary possession may be taken | (3) Relevant part of authorised project |
|---|---|---|
| 09-160, 09-162, 09-163, 09-164, 09-165 | Temporary construction compound and laydown area of up to 22,500 square metres and access to Work No. 17 during construction including works to the public highway and visibility splays | Work Nos. 17 and 18 |
| 09-166, 09-167 | Temporary works to the public highway including visibility splays | Work No. 19 |
| 11-197a, 11-223b, 11-228, 11-229a, 11-230, 11-230a, 11-233, 11-233a, 11-233b, 11-234, 1-234a, 11-234b, 11-236 | Access during construction including works to the public highway and visibility splays | Work Nos. 22, 22a, 27, 28, 29 and 30 |
| 11-197b | Onshore site preparation works | Work No. 27 |
| 11-228, 11-229 | Temporary construction compound and laydown area of up to 7,100 square metres | Work Nos. 22, 22a, 27, 28, 29 and 30 |
| 11-221a | Temporary construction area to facilitate the construction of permanent access | Work Nos. 27 and 29 |
| 11-215, 11-218, 11-218a | Temporary landscaping, ecological and environmental works in relation to the substation construction | Work Nos. 22, 22a and 31 |
SCHEDULE 8 — Land in which only new rights etc. may be acquired
In the County of Conwy:
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.