The Mona Offshore Wind Farm Order 2025

Type Statutory-Instrument
Publication 2025-07-04
Last updated 2025-10-24
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
Document Reference Number Planning Inspectorate Reference Document Name Revision Date
B1 REP6-004 Location plan F02 December 2024
B2 REP6-005 Offshore Order Limits and Grid Coordinates Plan F04 December 2024
B3 REP6-006 Works Plan - Onshore F03 December 2024
B4 AS-004 Works Plans - Offshore and Intertidal F02 April 2024
B5 REP7-004 Land Plan (Onshore) F05 January 2025
B6 REP7-005 Crown Land Plan (Onshore) F04 January 2025
B7 REP7-006 Special Category Land Plan F04 January 2025
B14 REP6-012 Tree and Hedgerow Plan F04 December 2024
B15 REP6-013 Street Works and Access to Works Plan F03 December 2024
B16 REP6-014 Temporary stopping up of Public Rights of Way Plan F03 December 2024
D4 REP7-014 Book of Reference F07 January 2025
Document Reference Number Planning Inspectorate Reference Document Name Revision Date
--- --- --- --- ---
F1 REP7-024 Non-Technical Summary - Welsh F02 January 2025
F1 REP7-025 Non-Technical Summary – English F02 January 2025
F1.1 REP7-026 Volume 1, Chapter 4: Introduction and overarching glossary F02 January 2025
F1.2 APP-049 Volume 1, Chapter 2: Policy and Legislative Context F01 February 2024
F1.3 REP7-027 Volume 1, Chapter 3: Project Description F02 January 2025
F1.4 REP7-029 Volume 1, Chapter 4: Site Selection and Consideration of Alternatives F03 January 2025
F1.5 APP-052 Volume 1, Chapter 5: Environmental Impact Assessment Methodology F01 February 2024
F2.1 APP-053 Volume 2, Chapter 1: Physical Processes F01 February 2024
F2.2 REP7-030 Volume 2, Chapter 2: Benthic Subtidal and Intertidal Ecology F02 January 2025
F2.3 REP7-031 Volume 2, Chapter 3: Fish and Shellfish Ecology F02 January 2025
F2.4 REP7-032 Volume 2, Chapter 4: Marine Mammals F02 January 2025
F2.5 REP7-033 Volume 2, Chapter 5: Offshore Ornithology F03 January 2025
F2.6 APP-058 Volume 2, Chapter 6: Commercial Fisheries F01 February 2024
F2.7 REP7-035 Volume 2, Chapter 7 Shipping and Navigation F02 January 2025
F2.8 REP7-036 Volume 2, Chapter 8: Seascape and Visual Resources F02 January 2025
F2.9 REP7-038 Volume 2, Chapter 9: Marine Archaeology F02 January 2025
F2.10 APP-062 Volume 2, Chapter 10: Other Sea Users F01 February 2024
F2.11 REP7-039 Volume 2, Chapter 11: Inter-related Effects - Offshore F02 January 2025
F3.1 REP7-040 Volume 3, Chapter 1: Geology, Hydrogeology and Ground Conditions F02 January 2025
F3.2 REP7-041 Volume 3, Chapter 2: Hydrology and Flood Risk F02 January 2025
F3.3 REP7-042 Volume 3, Chapter 3: Onshore Ecology F02 January 2025
F3.4 REP7-044 Volume 3, Chapter 3: Onshore and Intertidal Ornithology F02 January 2025
F3.5 REP7-045 Volume 3, Chapter 5: Historic Environment F02 January 2025
F3.6 REP7-046 Volume 3, Chapter 6: Landscape and Visual Resources F02 January 2025
F3.7 REP7-048 Volume 3, Chapter 7: Land Use and Recreation F02 January 2025
F3.8 REP7-049 Volume 3, Chapter 8: Traffic and Transport F02 January 2025
F3.9 REP7-050 Volume 3, Chapter 9: Noise and Vibration F03 January 2025
F3.10 REP7-051 Volume 3, Chapter 10: Air Quality F02 January 2025
F3.11 APP-074 Volume 3, Chapter 11: Inter-related Effects - Onshore F01 February 2024
F4.1 REP7-052 Volume 4, Chapter 1: Aviation and Radar F02 January 2025
F4.2 REP7-053 Volume 4, Chapter 2: Climate Change F02 January 2025
F4.3 APP-077 Volume 4, Chapter 3: Socio-economics F01 February 2024
F4.4 REP7-054 Volume 4, Chapter 4: Human Health Assessment F02 January 2025
F5.3.1 APP-079 Volume 5, Annex 3.1: Underwater Sound Technical Report F01 February 2024
F5.3.2 APP-080 Volume 5, Annex 3.2: Sulphur Hexafluoride Report F01 February 2024
F5.4.1 APP-081 Volume 5, Annex 4.1: Site Selection Area of Search Identification F01 February 2024
F5.4.2 APP-082 Volume 5, Annex 4.2: Site Selection BRAG Report F01 February 2024
F5.4.3 REP7-055 Volume 5, Annex 5.3: Onshore Crossing Schedule F04 January 2025
F5.5.1 REP7-056 Volume 5, Annex 5.1: Cumulative effects screening matrix F03 January 2025
F5.5.2 APP-085 Volume 5, Annex 5.2: Transboundary impacts screening F01 February 2024
F6.1.1 APP-086 Volume 6, Annex 1.1: Physical Processes Technical Report F01 February 2024
F6.2.1 APP-087 Volume 6, Annex 2.1: Benthic Subtidal and Intertidal Ecology Technical Report F01 February 2024
F6.2.2 REP7-057 Volume 6, Annex 2.2: Water Framework Directive Coastal Waters Assessment F02 January 2025
F6.3.1 APP-089 Volume 6, Annex 3.1: Fish and Shellfish Ecology Technical Report F01 February 2024
F6.4.1 APP-090 Volume 6, Annex 4.1: Marine Mammals Technical Report F01 February 2024
F6.5.1 APP-091 Volume 6, Annex 5.1: Offshore Ornithology Baseline Characterisation Technical Report F01 February 2024
F6.5.2 REP2-018 Volume 6, Annex 5.2: Offshore Ornithology Displacement Technical Report F02 August 2024
F6.5.3 REP2-020 Volume 6, Annex 5.3: Offshore Ornithology Collision Risk Modelling Technical Report F02 August 2024
F6.5.4 APP-094 Volume 6, Annex 5.4: Offshore Ornithology Migratory Bird Collision Risk Modelling Technical Report F01 February 2024
F6.5.5 REP7-058 Volume 6, Annex 5.5:Offshore Ornithology Apportioning Technical Report F03 January 2025
F6.5.6 REP2-024 Volume 6, Annex 5.6: Offshore Ornithology Population Viability Analysis Technical Report F02 August 2024
F6.6.1 APP-097 Volume 6, Annex 6.1: Commercial Fisheries Technical Report F01 February 2024
F6.7.1 REP7-061 Volume 6, Annex 7.1: Navigational Risk Assessment F02 January 2025
F6.8.1 APP-099 Volume 6, Annex 8.1: Seascape and Visual Resources Legislation and Planning Policy Context F01 February 2024
F6.8.2 APP-100 Volume 6, Annex 8.2: Seascape and Landscape Character Baseline Technical Report F01 February 2024
F6.8.3 APP-101 Volume 6, Annex 8.3: Visual Baseline Technical Report – Offshore Development F01 February 2024
F6.8.3 APP-102 Volume 6, Annex 8.3: Visual baseline technical report – Offshore Development Appendix – Part 1 F01 February 2024
F6.8.3 APP-103 Volume 6, Annex 8.3: Visual baseline technical report– Offshore Development Appendix – Part 2 F01 February 2024
F6.8.4 REP7-062 Volume 6, Annex 8.4: Seascape, Landscape and Visual Resources Impact Assessment Methodology F02 January 2025
F6.8.5 APP-105 Volume 6, Annex 8.6: International and Nationally Designated Landscape Study F01 February 2024
F6.8.6 APP-106 Volume 6, Annex 8.6: Seascape Visualisations Part 1 (Figures 1.1 – 9.3) F01 February 2024
F6.8.6 APP-107 Volume 6, Annex 8.6: Seascape Visualisations Part 2 (Figures 9.4 – 17.1) F01 February 2024
F6.8.6 APP-108 Volume 6, Annex 8.6: Seascape Visualisations Part 3 ( Figures 18.1 – 27.2) F01 February 2024
F6.8.6 APP-109 Volume 6, Annex 8.6: Seascape Visualisations Part 4 ( Figures 28.1 – 32.2) F01 February 2024
F6.8.6 APP-110 Volume 6, Annex 8.6: Seascape Visualisations Part 5 ( Figures 33.1 – 38.3) F01 February 2024
F6.8.6 APP-111 Volume 6, Annex 8.6: Seascape Visualisations Part 6 ( Figures 38.4 – 46.2) F01 February 2024
F6.8.6 APP-112 Volume 6, Annex 8.6: Seascape Visualisations Part 7 ( Figures 47 – 56) F01 February 2024
F6.9.1 APP-113 Volume 6, Annex 9.1: Marine Archaeology Technical Report F01 February 2024
F6.10.1 APP-114 Volume 6, Annex 10.1: Radar Early Warning Systems and Microwave Communication Links Technical Report F01 February 2024
F7.1.1 APP-115 Volume 7, Annex 1.1: Aquifers, Groundwater Abstractions and Ground Conditions F01 February 2024
F7.1.2 APP-116 Volume 7, Annex 1.2: Groundwater Sources of Supply – Hydrogeological Risk Assessment F01 February 2024
F7.2.1 REP7-063 Volume 7, Annex 2.1: Flood Consequences Assessment F02 January 2025
F7.2.2 APP-118 Volume 7, Annex 2.2: Surface Watercourses and NRW Flood Zones F01 February 2024
F7.2.3 APP-119 Volume 7, Annex 2.3: Surface Water Abstraction Licences, Discharge Consents and Pollution Incidents F01 February 2024
F7.2.4 REP7-064 Volume 7, Annex 2.4: Water Framework Directive Surface Water and Groundwater Assessment F02 January 2025
F7.3.1 APP-121 Volume 7, Annex 3.1: Onshore Ecology Desk Study F01 February 2024
F7.3.2 APP-122 Volume 7, Annex 3.2: Extended Phase 1 Habitat Survey Technical Report F01 February 2024
F7.3.3 APP-123 Volume 7, Annex 3.3: Great Crested Newt Survey Technical Report F01 February 2024
F7.3.4 APP-124 Volume 7, Annex 3.4: Hedgerow Survey Technical Report F01 February 2024
F7.3.5 APP-125 Volume 7, Annex 3.5: Terrestrial Invertebrates Survey F01 February 2024
F7.3.6 APP-126 Volume 7, Annex 3.6: Aquatic Invertebrates (inc White Clawed Crayfish) Survey F01 February 2024
F7.3.7 APP-127 Volume 7, Annex 3.7: Reptile Survey F01 February 2024
F7.3.8 APP-128 Volume 7, Annex 3.8: Water Vole Survey F01 February 2024
F7.3.9 APP-129 Volume 7, Annex 3.9: Bat Roost Survey (Part 1) F01 February 2024
F7.3.9 APP-130 Volume 7, Annex 3.9: Bat Roost Survey (Part 2) F01 February 2024
F7.3.9 APP-131 Volume 7, Annex 3.9: Bat Roost Survey (Part 3) F01 February 2024
F7.3.10 APP-132 Volume 7, Annex 3.10: Bat Activity Survey F01 February 2024
F7.3.11 APP-133 Volume 7, Annex 3.11: Otter Survey Technical Report F01 February 2024
F7.3.12 APP-135 Volume 7, Annex 3.12: Badger Survey Technical Report (Confidential) F01 February 2024
F7.3.12 APP-134 Volume 7, Annex 3.12: Badger Survey Technical Report (Public) F01 February 2024
F7.3.13 APP-136 Volume 7, Annex 3.13: Hazel Dormouse Survey Technical Report F01 February 2024
F7.3.14 APP-137 Volume 7, Annex 3.14: National Vegetation Classification and Invasive Non-Native Species Technical Report F01 February 2024
F7.3.15 APP-138 Volume 7, Annex 3.15: Fish and Eel Survey Technical Report F01 February 2024
F7.4.1 APP-139 Volume 7, Annex 4.1: Onshore Ornithology- Wintering and Migratory Birds Technical Report F01 February 2024
F7.4.2 APP-140 Volume 7, Annex 4.2: Intertidal Ornithology - Wintering and Migratory Birds F01 February 2024
F7.4.3 APP-142 Volume 7, Annex 4.3: Onshore Ornithology- Breeding Birds Technical Report (Confidential) F01 February 2024
F7.5.1 REP7-065 Volume 7, Annex 5.1: Desk-Based Assessment F02 January 2025
F7.5.2 APP-144 Volume 7, Annex 5.2: Historic Environment Policy and Guidance F01 February 2024
F7.5.3 APP-145 Volume 7, Annex 5.3: Onshore Geophysical Survey Report -Part 1 F01 February 2024
F7.5.3 APP-146 Volume 7, Annex 5.3: Onshore Geophysical Survey Report -Part 2 F01 February 2024
F7.5.4 APP-147 Volume 7, Annex 5.4: Intertidal Survey Report F01 February 2024
F7.5.5 APP-148 Volume 7, Annex 5.5: Trial Trenching Report – Part 1 F01 February 2024
F7.5.5 APP-149 Volume 7, Annex 5.5: Trial Trenching Report – Part 2 F01 February 2024
F7.5.6 APP-150 Volume 7, Annex 5.6: Settings Assessment (onshore infrastructure) F01 February 2024
F7.5.7 APP-151 Volume 7, Annex 5.7: Settings Assessment (offshore infrastructure) F01 February 2024
F7.6.1 APP-152 Volume 7, Annex 5.7: Landscape and Visual Resources Planning Policy Context F01 February 2024
F7.6.2 APP-153 Volume 7, Annex 6.2: Landscape and Seascape Character Baseline Technical Report – Part 1 F01 February 2024
F7.6.2 APP-154 Volume 7, Annex 6.2: Landscape and Seascape Character Baseline Technical Report – Part 2 F01 February 2024
F7.6.3 APP-155 Volume 7, Annex 6.3: Visual Baseline Technical Report - Onshore Development F01 February 2024
F7.6.4 APP-156 Volume 7, Annex 6.4: Landscape, Seascape and Visual Resources Impact Assessment Methodology F01 February 2024
F7.6.5 APP-157 Volume 7, Annex 6.5: Landscape Visualisations Part 1 (viewpoint 1 – viewpoint 8) F01 February 2024
F7.6.5 APP-158 Volume 7, Annex 6.5: Landscape Visualisations Part 2 (viewpoint 9 – viewpoint 15) F01 February 2024
F7.6.5 APP-159 Volume 7, Annex 6.5: Landscape Visualisations (viewpoint 16 – viewpoint 30) F01 February 2024
F7.6.6 APP-160 Volume 7, Annex 6.6: Tree Survey and Arboriculture Impact Assessment Part 1 F01 February 2024
F7.6.6 REP7-066 Volume 7, Annex 6.6: Tree Survey and Arboriculture Impact Assessment Part 2 – Appendix A F02 January 2025
F7.6.6 REP7-067 Volume 7, Annex 6.6: Tree Survey and Arboriculture Impact Assessment Part 3 – Appendix B F02 January 2025
F7.6.6 REP7-068 Volume 7, Annex 6.6: Tree Survey and Arboriculture Impact Assessment Part 4 – Appendix B F02 January 2025
F7.6.6 REP7-069 Volume 7, Annex 6.6: Tree Survey and Arboriculture Impact Assessment Part 5 – Appendix B F02 January 2025
F7.6.6 REP7-070 Volume 7, Annex 6.6: Tree Survey and Arboriculture Impact Assessment Part 6 – Appendix C F02 January 2025
F7.6.6 REP7-071 Volume 7, Annex 6.6: Tree Survey and Arboriculture Impact Assessment Part 7 – Appendix C F02 January 2025
F7.6.6 REP7-072 Volume 7, Annex 6.6: Tree Survey and Arboriculture Impact Assessment Part 8 – Appendix C F02 January 2025
F7.7.1 APP-168 Volume 7, Annex 7.1: Published Soil and Agricultural Land Classification Data Technical Report F01 February 2024
F7.7.2 REP5-014 Volume 7, Annex 7.2: Soil Survey Data Technical Report F02 December 2024
F7.7.3 APP-170 Volume 7, Annex 7.3: Published Recreational Resources Plan Technical Report F01 February 2024
F7.8.1 APP-171 Volume 7, Annex 7.3: Description of Network Links and Sensitivity F01 February 2024
F7.8.2 APP-172 Volume 7, Annex 8.2: Base Traffic Flows F01 February 2024
F7.8.3 APP-173 Volume 7, Annex 8.3: Personal Injury Accident Locations F01 February 2024
F7.8.4 APP-174 Volume 7, Annex 8.4: Public Transport Networks F01 February 2024
F7.8.5 APP-175 Volume 7, Annex 8.5: Construction Vehicle Trip Generation Assumptions F01 February 2024
F7.8.6 APP-176 Volume 7, Annex 8.6: Traffic Flows with Construction Traffic F01 February 2024
F7.8.7 APP-177 Volume 7, Annex 8.7: Traffic and Transport Figures F01 February 2024
F7.9.1 APP-178 Volume 7, Annex 9.1: Baseline Noise Survey F01 February 2024
F7.9.2 REP5-016 Volume 7, Annex 9.2: Construction Noise and Vibration Technical Report F02 December 2024
F7.9.3 APP-180 Volume 7, Annex 9.3: Operation Noise Assessment Technical Report F01 February 2024
F8.1.1 REP7-073 Volume 8, Annex 1.1: Aviation and Radar Technical Report F02 January 2025
F8.2.1 APP-182 Volume 8, Annex 2.1: Technical Greenhouse Gas Assessment Technical Report F01 February 2024
F8.2.2 APP-183 Volume 8, Annex 2.2: Climate Change Risk Assessment F01 February 2024
F8.3.1 APP-184 Volume 8, Annex 3.1: Socio-economics Technical Impact Report F01 February 2024
S_D3_15 REP3-046 Seascapes and Visual Resources: Cumulative Wirelines F01 September 2024
S_D3_16.1 REP3-047 Landscape and Visual Resources – Cumulative Visualisations Part 1 F01 September 2024
S_D3_16.2 REP3-048 Landscape and Visual Resources – Cumulative Visualisations Part 2 F01 September 2024
S_D4_6.2 REP4-038 Appendix to HAP ISH3_20: Updated Visualisations Part 1 F01 November 2024
S_D4_6.3 REP4-039 Appendix to HAP ISH3_20: Updated Visualisations Part 2 F01 November 2024
S_D4_15 REP4-046 Zone of Theoretical Visibility and representative viewpoint locations at 1:50,000 Scale F01 November 2024
Document Reference Number Planning Inspectorate Reference Document Name Revision Date
--- --- --- --- ---
S_RFI1_03 C1-008c Outline Code of Construction Practice F01 May 2025
J26.1 REP6-036 Outline Spillage and Emergency Response Plan F03 December 2024
J26.2 REP6-038 Outline Dust Management Plan F03 December 2024
S_RFI1_04 C1-008e Outline Construction Noise and Vibration Management Plan F01 May 2025
J26.4 REP6-042 Outline Communications Plan F03 December 2024
J26.5 REP6-044 Outline Construction Fencing Plan F03 December 2024
J26.6 REP6-046 Outline Construction Surface Water and Drainage Management Plan F03 December 2024
J26.7 REP6-048 Outline Flood Management Plan F03 December 2024
J26.8 REP6-050 Outline Soil Management Plan F03 December 2024
J26.9 REP6-052 Outline Site Waste Management Plan F03 December 2024
J26.10 REP6-054 Outline Artificial Light Emissions Plan F03 December 2024
J26.11 REP6-056 Outline Biosecurity Protocol F03 December 2024
J26.12 REP6-058 Outline Discovery Strategy for Contaminated Land F03 December 2024
S_RFI1_05 C1-008g Outline Construction Traffic Management Plan F01 May 2025
J26.14 REP7-089 Outline Landfall Construction Method Statement F05 January 2025
S_RFI1_06 C3-004, pdf pages 22 to 37 Outline Onshore Construction Method Statement F02 June 2025
S_RFI1_07 C1-008k Outline Highways Access Management Plan F01 May 2025
J26.17 REP6-064 Outline Public Rights of Way Management Strategy F03 December 2024
J26.18 REP6-066 Outline Arboriculture Method Statement F03 December 2024
Document Reference Number Planning Inspectorate Reference Document Name Revision Date
--- --- --- --- ---
J3 REP6-024 Design Principles F04 December 2024
J10 REP7-077 Mitigation and Monitoring Schedule F07 January 2025
J12 APP-198 Outline Offshore Operations and Maintenance Plan F01 February 2024
J13 REP7-079 Outline Fisheries Liaison and Co-existence Plan F03 January 2025
J14 REP6-028 Outline Vessel Traffic Management Plan F03 December 2024
J15 REP7-081 Offshore In-principle Monitoring Plan F03 January 2025
J16 REP5-028 Outline Underwater Sound Management Strategy F02 December 2024
J17 REP5-030 Measures to Minimise Disturbance to Marine Mammals and Rafting Birds from Transiting Vessels F03 December 2024
J18 REP7-083 Outline Offshore Written Scheme of Investigation and Protocol for Archaeological Discoveries F03 January 2025
J21 REP5-032 Outline Marine Mammal Mitigation Protocol F02 December 2024
J22 REP7-085 Outline Landscape and Ecology Management Plan F05 January 2025
J23 REP6-032 Outline Onshore Written Scheme of Investigation F03 December 2024
J24 REP4-015 Outline Skills and Employment Plan F02 November 2024
J27 REP6-068 Outline Operation Drainage Management Strategy F02 December 2024
S_D4_8 REP4-041 Greenhouse Gas Reduction Strategy F01 November 2024
S_D7_30 REP7-136 Landscape Enhancement Scheme Principles F01 January 2025

Signed

Signed by authority of the Secretary of State for Energy Security and Net Zero

David Wagstaff — Deputy Director for Energy Infrastructure Planning — Department for Energy Security and Net Zero — 4th July 2025

Explanatory note

(This note is not part of the Order)

EXPLANATORY NOTE

This Order grants development consent for, and authorises the construction, operation and maintenance of an offshore wind farm generating station located in the Irish Sea approximately 28 kilometres from the coast of North Wales, together with associated development. This Order imposes requirements in connection with the development and authorises the compulsory purchase of land (including rights in land) and the right to use land and to override easements and other rights.

A copy of the plans and book of reference referred to in this Order and certified in accordance with article 41 (certification of plans) together with a copy of any guarantee or alternative form of security approved by the Secretary of State pursuant to article 32 (funding), may be inspected free of charge at the offices of Mona Offshore Wind Limited, Chertsey Road, Sunbury On Thames, Middlesex, United Kingdom, TW16 7BP.

Footnotes

[^f00001]: 2008 c. 29. Section 37 was amended by section 128(2) and Schedule 13, Part 1, paragraphs 1 to 5 of the Localism Act 2011 (c. 20).

[^f00002]: S.I. 2010/103. This instrument was amended by S.I. 2012/635.

[^f00003]: S.I. 2017/572.

[^f00004]: 1961 c. 33.

[^f00005]: 1965 c. 56.

[^f00006]: 1980 c. 66.

[^f00007]: 1981 c. 66.

[^f00008]: 1989 c. 29.

[^f00009]: 1990 c. 8.

[^f00010]: 1991 c. 22.

[^f00011]: 2003 c. 21.

[^f00012]: 2004 c. 20. Section 105 was amended by section 69 of the Energy Act 2008 (c. 32).

[^f00013]: 2008 c. 29.

[^f00014]: 2009 c. 23.

[^f00015]: 1971 c. 80.

[^f00016]: “highway” is defined in section 328(1) for “highway authority” see section 1. Relevant amendments are as follows: section 1 was amended by sections 8 and 102 and Schedule 4, paragraph 1 and Schedule 17 of the Local Government Act 1985 (c. 51), by section 21 of the 1991 Act and by section 1(6) and Schedule 1, paragraph 2 of the Infrastructure Act 2015 (c. 7), by S.I. 2015/481, and by S.I. 1991/2288.

[^f00017]: Section 48 was amended by sections 124 and 134 of the Local Transport Act 2008 (c. 26).

[^f00018]: “Street authority” is defined in section 49, which was amended by section 57(1) and paragraph 117 of Schedule 1 to the Infrastructure Act 2015, and S.I. 2015/481.

[^f00019]: Section 6 was amended by sections 89, 136, 198, 143, and 145, Part 1 of Schedule 23 and paragraphs 3 and 5 of Schedule 19 to the Energy Act 2004 (c. 20), sections 72 and 121 and Schedule 1 to the Energy Act 2011 (c. 16), sections 166, 186, 334 and 205 to the Energy Act 2023 (c. 52), S.I. 2012/2400 and S.I. 2011/2704. There are other amendments to section 6 which are not relevant to the Order.

[^f00020]: 1991 c. 57. Paragraph 5 was amended by section 100(1) and (2) of the Natural Environment and Rural Communities Act 2006 (c. 16), section 84 of, and paragraph 3 of Schedule 11 to, the Marine and Coastal Access Act 2009 (c. 23), paragraph 49 of Schedule 2 to the Flood and Water Management Act 2010 (c. 29), paragraph 32 of Schedule 10 to the Fisheries Act 2020 and S.I. 2013/755. Paragraph 6 was amended by paragraph 26 of Schedule 15 to the Environment Act 1995 (c. 25), section 224 of, and paragraphs 20 and 24 of Schedule 16, and Part 5(B) of Schedule 22, to, the Marine and Coastal Access Act 2009 and S.I. 2013/755. Paragraph 6A was inserted by section 103(3) of the Environment Act 1995.

[^f00021]: 1991 c. 59. As substituted by section 49 of, and paragraph 38 of Schedule 2 to the Flood and Water Management Act 2010 (c. 29), section 22(2) and paragraph 14 of schedule 2 to the Local Government Byelaws (Wales) Act 2012 (2012 anaw 2) and section 86 (3) of the Water Act 2014 (c. 21).

[^f00022]: 1991 c. 59. Section 23 has been amended by paragraph 32 of Schedule 2 to the Flood and Water Management Act 2010, section 120 of and paragraph 192 of Schedule 22 to the Environment Act 1995 and paragraph 322 of Schedule 2 to the Natural Resources Body for Wales (Functions) Order 2013 (No.755); section 30 has been amended by S.I. 2013/1036.

[^f00023]: 2017 c. 20.

[^f00024]: 1990 c. 43. Relevant amendments are as follows: section 82 was amended by section 107 and Schedule 17 paragraph 6 of the Environment Act 1995 (c. 25) and section 5(2) of the Noise and Statutory Nuisance Act 1993 (c. 40), and section 79 was amended by sections 101 and 102 of the Clean Neighbourhoods and Environment Act 2005 (c. 16), by section 2 of the Noise and Statutory Nuisance Act 1993 and by section 120 and Schedule 22 paragraph 89 of the Environment Act 2005.

[^f00025]: 1974 c. 40. Section 61 was amended by Schedule 7 to the Building Act 1984 (c. 55), paragraph 15 of Schedule 15 to the Environmental Protection Act 1990 and Schedule 24 to the Environment Act 1995. There are other amendments to the 1974 Act which are not relevant to the Order.

[^f00026]: 1974 c. 40. Section 61 was amended by Schedule 7 to the Building Act 1984 (c. 55), paragraph 15 of Schedule 3 to the Environmental Protection Act 1990 and Schedule 24 to the Environment Act 1995.

[^f00027]: Section 48 is amended by sections 124 and 134 of the Local Transport Act 2008 (c. 26), and section 51 was amended by sections 40 and 99 and Schedule 1 to the Traffic Management Act 2004 (c. 18).

[^f00028]: Sections 55, 57, 60, 68 and 69 were amended by the Traffic Management Act 2004 (c. 18).

[^f00029]: 1991 c. 56. Section 106 was amended by sections 43(2) and 35(8)(a) and paragraph 1 of Schedule 2 to the Competition and Service (Utilities) Act 1992 (c. 43) and sections 99(2), (4), (5)(a), (5)(b) and (5)(c) of the Water Act 2003 (c. 37) and Schedule 3, paragraph 16(1) of the Flood and Water Management Act 2010 (c. 29).

[^f00030]: S.I. 2016/1154.

[^f00031]: Section 13 has been amended by section 139 and Schedules 13 and 23 to the Tribunals, Courts and Enforcement Act 2007 (c. 15).

[^f00032]: Section 125 is amended by section 216 and paragraph 17 of Schedule 16 to the Housing and Planning Act 2016.

[^f00033]: Section 4 was amended by sections 184 and 185 of, and paragraph 2 of Schedule 18 to, the Housing and Planning Act 2016 (c. 22).

[^f00034]: Section 8 was amended by section 216 of and paragraph 2 of Schedule 17 to the Housing and Planning Act 2016 and S.I. 2009/1307 and Schedule 2A was amended by section 216 of and paragraph 3 of Schedule 17 to the Housing and Planning Act 2016.

[^f00035]: 1981 c. 67.

[^f00036]: Section 11(1) was amended by section 186 of the Housing and Planning Act 2016, paragraph 14 of Schedule 4 to the Acquisition of Land Act 1981 and S.I. 2006/2.

[^f00037]: Section 152 was amended by S.I. 2009/1307.

[^f00038]: Section 138 was amended by section 23(4) of the Growth and Infrastructure Act 2013 (c. 27) and S.I. 2017/1285.

[^f00039]: Section 13 was amended by Tribunals Courts and Enforcement Act 2007 (c. 15).

[^f00040]: 2003 c. 21. There are amendments to this section which are not relevant to this Order.

[^f00041]: S.I. 1997/1160.

[^f00042]: Section 105(2) was substituted by section 69(3) of the Energy Act 2008 (c. 32).

[^f00043]: 1978 c. 30.

[^f00044]: S.I. 2016/765.

[^f00045]: 1973 c. 26.

[^f00046]: Section 11A was inserted by section 186(3) of the Housing and Planning Act 2016 (c. 22).

[^f00047]: Section 11B was inserted by section 187(2) of the above Act (c. 22).

[^f00048]: 1991 c. 56.

[^f00049]: 1993 c. 43.

[^f00050]: 2006 c. 46.

[^f00051]: S.I. 2015/1522 (W.179).

[^f00052]: 2004 c. 20. Section 105 was amended by section 69 of the Energy Act 2008 (c. 32).

[^f00053]: 2009 c. 23.

Editorial notes

[^key-dbed5d635d5594d8c000d67709dd7b40]: Art. 1 in force at 28.7.2025, see art. 1

[^key-e9462f2bc6aed9849023bf3ff732d2e8]: Art. 2 in force at 28.7.2025, see art. 1

[^key-5e4e32da5551a5be7961e0afbaf28e41]: Art. 3 in force at 28.7.2025, see art. 1

[^key-daf866585c50d9d407bc47987d05a9c1]: Art. 4 in force at 28.7.2025, see art. 1

[^key-e70a11b1d6cdc357bf7b242f98aa41a2]: Art. 5 in force at 28.7.2025, see art. 1

[^key-48f6412f47d929743de7aba67d11c520]: Art. 6 in force at 28.7.2025, see art. 1

[^key-8bc887b037ad6bd8c3fadd0e7eea3014]: Art. 7 in force at 28.7.2025, see art. 1

[^key-1623aeda1abeb61b2edd79835414fadc]: Art. 8 in force at 28.7.2025, see art. 1

[^key-0aef97a8dd021581b2e38dfb11ef22b8]: Art. 9 in force at 28.7.2025, see art. 1

[^key-03b74d4a86f942db0b72fdf16207016b]: Art. 10 in force at 28.7.2025, see art. 1

[^key-f2ea01d37da5f3775dff8eb2bb63ccfc]: Art. 11 in force at 28.7.2025, see art. 1

[^key-0123581582ae36a033832aadf95633ec]: Art. 12 in force at 28.7.2025, see art. 1

[^key-327d915ef23e4dac21da8d2ae7ec9a96]: Art. 13 in force at 28.7.2025, see art. 1

[^key-6fde6c9b6ac302c4cf2cdc24e080a39a]: Art. 14 in force at 28.7.2025, see art. 1

[^key-fff38aaf83ff0d3da317a25fa30f6932]: Art. 15 in force at 28.7.2025, see art. 1

[^key-8ae2cbfc3fc6ee0b88ee06d189ed40ac]: Art. 16 in force at 28.7.2025, see art. 1

[^key-731b29591de1089aae4d9ff0fdf8eeb3]: Art. 17 in force at 28.7.2025, see art. 1

[^key-4d1f5e79ce4a6ba307afb10d177ac077]: Art. 18 in force at 28.7.2025, see art. 1

[^key-4234e8891f01db3d50eed94c051865f2]: Art. 19 in force at 28.7.2025, see art. 1

[^key-e57307a6623325a6a649de64fbb87a3e]: Art. 20 in force at 28.7.2025, see art. 1

[^key-8b85841c3aa7acf81b4cb9835e531777]: Art. 21 in force at 28.7.2025, see art. 1

[^key-d0925f147106195b1892e29191e506e9]: Art. 22 in force at 28.7.2025, see art. 1

[^key-50ebf67cd7c16d8e54c330722c757f10]: Art. 23 in force at 28.7.2025, see art. 1

[^key-10070771339150e2a091c3f1a1b1d61d]: Art. 24 in force at 28.7.2025, see art. 1

[^key-46afb31be0875e5e6f1b36fa8a76e993]: Art. 25 in force at 28.7.2025, see art. 1

[^key-d2ceef1c38113b53037d2da030b0ca26]: Art. 26 in force at 28.7.2025, see art. 1

[^key-28ee2ab12b51d83f73b1b00dca0ec621]: Art. 27 in force at 28.7.2025, see art. 1

[^key-109f1e878bfd27632d4599324fc93587]: Art. 28 in force at 28.7.2025, see art. 1

[^key-f34658920ef11cd8c53d7e378dbe0ca5]: Art. 29 in force at 28.7.2025, see art. 1

[^key-d99b30ecd175d24489e7e4d97f7ad6e2]: Art. 30 in force at 28.7.2025, see art. 1

[^key-a29da0a0437c7ab200f830d81a599eb6]: Art. 31 in force at 28.7.2025, see art. 1

[^key-f2f12e61b774c6ecf7f96bf8474cd46a]: Art. 32 in force at 28.7.2025, see art. 1

[^key-11cd92a2c1b73bd9670cd3b546e0a195]: Art. 33 in force at 28.7.2025, see art. 1

[^key-4181f5df8b52506f3e9be8ad0b01bbe8]: Art. 34 in force at 28.7.2025, see art. 1

[^key-1cdee3b009a54be0ffc372388720c10d]: Art. 35 in force at 28.7.2025, see art. 1

[^key-8f9384e76068315e38587f41f177f2f9]: Art. 36 in force at 28.7.2025, see art. 1

[^key-3737febdf48c6218a9ec3c32046c9a99]: Art. 37 in force at 28.7.2025, see art. 1

[^key-25a2de94780fca31aaf38a851fc2b65c]: Art. 38 in force at 28.7.2025, see art. 1

[^key-78f06191d4b980868874fe6f1b9c9f8f]: Art. 39 in force at 28.7.2025, see art. 1

[^key-6b93c842a5a167869bf2987e449e62c0]: Art. 40 in force at 28.7.2025, see art. 1

[^key-f0ad6336ef05f4abb1e930b771eb765a]: Art. 41 in force at 28.7.2025, see art. 1

[^key-14b4be30a031cb11988630cd2541c8f2]: Art. 42 in force at 28.7.2025, see art. 1

[^key-1bed3d816f152dfb3dd1b5178a63d204]: Art. 43 in force at 28.7.2025, see art. 1

[^key-01ec94bc534bffc54352a89d0c5655c2]: Art. 44 in force at 28.7.2025, see art. 1

[^key-059a6ca718e24008730bcf86d4119e2c]: Art. 45 in force at 28.7.2025, see art. 1

[^key-96cfc76327cf807513c10da79548b0a3]: Sch. 1 para. 1 in force at 28.7.2025, see art. 1

[^key-902a883591e96a44cfef1821d43eff2f]: Sch. 1 para. 2 in force at 28.7.2025, see art. 1

[^key-2203a6061c265ecf854a1a2532ee8250]: Sch. 2 para. 1 in force at 28.7.2025, see art. 1

[^key-03c26e1e208fd738534e732c99cb8b76]: Sch. 2 para. 2 in force at 28.7.2025, see art. 1

[^key-ec69a39afdce3b0775ccca449e5c17e7]: Sch. 2 para. 3 in force at 28.7.2025, see art. 1

[^key-bd2e9be9b7436a6387d0fabc6f2874ae]: Sch. 2 para. 4 in force at 28.7.2025, see art. 1

[^key-fc87fa12fde00a005a1e68ade032ce9a]: Sch. 2 para. 5 in force at 28.7.2025, see art. 1

[^key-f2667a344709422121416a01cffece00]: Sch. 2 para. 6 in force at 28.7.2025, see art. 1

[^key-828e598135939dfdaaad50f3813d0fe1]: Sch. 2 para. 7 in force at 28.7.2025, see art. 1

[^key-5ba24529f1f779854d3cd4834f4458b5]: Sch. 2 para. 8 in force at 28.7.2025, see art. 1

[^key-fc26b67d7642bc0c0fdafee8d5a30896]: Sch. 2 para. 9 in force at 28.7.2025, see art. 1

[^key-03abe4a9781013adfbb0801cae4ba1ff]: Sch. 2 para. 10 in force at 28.7.2025, see art. 1

[^key-ad29ea0670a3cdc3ab7094c523db26e1]: Sch. 2 para. 11 in force at 28.7.2025, see art. 1

[^key-c79d87db53893467fffc6c757c3582cb]: Sch. 2 para. 12 in force at 28.7.2025, see art. 1

[^key-b1e49a40bdf03efe923db1e5936d4b2a]: Sch. 2 para. 13 in force at 28.7.2025, see art. 1

[^key-33088d46699ddb7632995f7c34906f5d]: Sch. 2 para. 14 in force at 28.7.2025, see art. 1

[^key-d88afe89c2d7058753b6c137f8339f02]: Sch. 2 para. 15 in force at 28.7.2025, see art. 1

[^key-07c64227eae55e3c3c5b3dc848be6bde]: Sch. 2 para. 16 in force at 28.7.2025, see art. 1

[^key-3b95d8ad1bf2cc409edb711bd64d7179]: Sch. 2 para. 17 in force at 28.7.2025, see art. 1

[^key-4bf55a33247c1cd0bcc05c258394301c]: Sch. 2 para. 18 in force at 28.7.2025, see art. 1

[^key-04f2c4e384c9f478d02c3f6b3e8f3b00]: Sch. 2 para. 19 in force at 28.7.2025, see art. 1

[^key-8d8c911b3162969dce8f79c686ec50ff]: Sch. 2 para. 20 in force at 28.7.2025, see art. 1

[^key-e16485ab7de8f6bae709285956afbf31]: Sch. 2 para. 21 in force at 28.7.2025, see art. 1

[^key-39fbd0cd6217eea482d52f8419f43179]: Sch. 2 para. 22 in force at 28.7.2025, see art. 1

[^key-bc69eb226596a1e82ec4d1b0735a7ca4]: Sch. 2 para. 23 in force at 28.7.2025, see art. 1

[^key-b8cf46a38608e2730a3759f0ae832a49]: Sch. 2 para. 24 in force at 28.7.2025, see art. 1

[^key-5c091aa5a1efbe41485ba2e4d88071c0]: Sch. 2 para. 25 in force at 28.7.2025, see art. 1

[^key-bfa55862503b4f3c8ed7120f75edc2d7]: Sch. 2 para. 26 in force at 28.7.2025, see art. 1

[^key-4063f69973c66fad30d4f9a1675ecb4e]: Sch. 2 para. 27 in force at 28.7.2025, see art. 1

[^key-5358d23c7250b5abb85cfee33a5067f2]: Sch. 2 para. 28 in force at 28.7.2025, see art. 1

[^key-8bd3a099f23d147b01f9d326f4757f8d]: Sch. 2 para. 29 in force at 28.7.2025, see art. 1

[^key-2d3255989770be30062454d88ac991ee]: Sch. 2 para. 30 in force at 28.7.2025, see art. 1

[^key-b99ae900de5176a5d05404a8f07b85b8]: Sch. 2 para. 31 in force at 28.7.2025, see art. 1

[^key-02c596ba7f2bee73b5667a7a82970698]: Sch. 2 para. 32 in force at 28.7.2025, see art. 1

[^key-89defbd4aa4965769e7febbaa9cb8ed7]: Sch. 9 para. 1 in force at 28.7.2025, see art. 1

[^key-5202c5a978c6a85ca0bf56cf3a659669]: Sch. 9 para. 2 in force at 28.7.2025, see art. 1

[^key-91b6adcc42e7f9e3db28c34c6603701b]: Sch. 9 para. 3 in force at 28.7.2025, see art. 1

[^key-4f91079ad75ec9433e05c422ca007c50]: Sch. 9 para. 4 in force at 28.7.2025, see art. 1

[^key-8c53df98773cc824d56121e91c9003ae]: Sch. 9 para. 5 in force at 28.7.2025, see art. 1

[^key-4d04da9aa9871a1edacd5d6315181721]: Sch. 10 para. 1 in force at 28.7.2025, see art. 1

[^key-2ff4d60c5bbe84b627d24c88764a358a]: Sch. 10 para. 2 in force at 28.7.2025, see art. 1

[^key-48675b19b6f34b9c006f9c1167ef0b16]: Sch. 10 para. 3 in force at 28.7.2025, see art. 1

[^key-503fa4b6e63bae5c4731a556df494c8f]: Sch. 10 para. 4 in force at 28.7.2025, see art. 1

[^key-605f222c6d97e9a7c151bc8885ac9f54]: Sch. 10 para. 5 in force at 28.7.2025, see art. 1

[^key-b395f65afddcebc45ae47a5018d8f36d]: Sch. 10 para. 6 in force at 28.7.2025, see art. 1

[^key-8d120828ddcc07b44be6de9982119608]: Sch. 10 para. 7 in force at 28.7.2025, see art. 1

[^key-1048a59704c89a46a61917a863174e7c]: Sch. 10 para. 8 in force at 28.7.2025, see art. 1

[^key-d33c6bdc13264871cd278b5848c8b4cd]: Sch. 10 para. 9 in force at 28.7.2025, see art. 1

[^key-fa90fec363fda6d1f632458805b173bf]: Sch. 10 para. 10 in force at 28.7.2025, see art. 1

[^key-799917670b1e931f5e1ea0d1ee2861a3]: Sch. 10 para. 11 in force at 28.7.2025, see art. 1

[^key-91bb314d143d549238453ae90734a528]: Sch. 10 para. 12 in force at 28.7.2025, see art. 1

[^key-72c0b915bfe69727558b600562d4665b]: Sch. 10 para. 13 in force at 28.7.2025, see art. 1

[^key-8e4d33cf993b3f8e06b353a02698ff81]: Sch. 10 para. 14 in force at 28.7.2025, see art. 1

[^key-1ee25ac0c141e0ac0a257d7944c9e715]: Sch. 10 para. 15 in force at 28.7.2025, see art. 1

[^key-58d838e1cad2349caf38d93761670c72]: Sch. 10 para. 16 in force at 28.7.2025, see art. 1

[^key-7bb7eae24beacd89a7aeafd58d0467e7]: Sch. 10 para. 17 in force at 28.7.2025, see art. 1

[^key-5a705ab3a0a81c36b1e07c7b5ee2b096]: Sch. 10 para. 18 in force at 28.7.2025, see art. 1

[^key-55196487e0a51f04011f9028bf3fa12f]: Sch. 10 para. 19 in force at 28.7.2025, see art. 1

[^key-121179a0c41f577e26705d6578b06a4e]: Sch. 10 para. 20 in force at 28.7.2025, see art. 1

[^key-66e26be0dd2bed3ef0bed98a2a562ca4]: Sch. 10 para. 21 in force at 28.7.2025, see art. 1

[^key-8123061ba0494dc79f0f83fff7a246f1]: Sch. 10 para. 22 in force at 28.7.2025, see art. 1

[^key-30a4ec0159d396ee7b600527e812c713]: Sch. 10 para. 23 in force at 28.7.2025, see art. 1

[^key-9f5d9dd9e2a2be446efbfcd1e10a8e7e]: Sch. 10 para. 24 in force at 28.7.2025, see art. 1

[^key-bb3414db258b14e94698f78f48b21a1c]: Sch. 10 para. 25 in force at 28.7.2025, see art. 1

[^key-c0b78af7fd2de186db723bc2c13e2852]: Sch. 10 para. 26 in force at 28.7.2025, see art. 1

[^key-6429ac9486bec6f5e536bb4d68ab7506]: Sch. 10 para. 27 in force at 28.7.2025, see art. 1

[^key-3c58044205c78f0a5120c62b9df0d110]: Sch. 10 para. 28 in force at 28.7.2025, see art. 1

[^key-6f7cbf4331e004f9ce299886a85552c4]: Sch. 10 para. 29 in force at 28.7.2025, see art. 1

[^key-71bb42be9da1c3ba16583244b697fa83]: Sch. 10 para. 30 in force at 28.7.2025, see art. 1

[^key-67cb57ed82a911450037c5922061d064]: Sch. 10 para. 31 in force at 28.7.2025, see art. 1

[^key-bf678f4b0fd15a9814de34d58b39a67e]: Sch. 10 para. 32 in force at 28.7.2025, see art. 1

[^key-22f501d0ea82bbff7e33c6d76d81f999]: Sch. 10 para. 33 in force at 28.7.2025, see art. 1

[^key-e0e092235281092c93cc73211da13485]: Sch. 10 para. 34 in force at 28.7.2025, see art. 1

[^key-a1cf25067b7b41536225c48ada1b1ed2]: Sch. 10 para. 35 in force at 28.7.2025, see art. 1

[^key-2f8f853c2e75e7e766f690e6d69bc652]: Sch. 10 para. 36 in force at 28.7.2025, see art. 1

[^key-13ff37a43df764976ec876f2bbc6dac1]: Sch. 10 para. 37 in force at 28.7.2025, see art. 1

[^key-7246f556360286029d36e7fc4b79834e]: Sch. 10 para. 38 in force at 28.7.2025, see art. 1

[^key-c2a4c41b20d472abfd3bcf7e6a34c179]: Sch. 10 para. 39 in force at 28.7.2025, see art. 1

[^key-1fdefe109f14a1d9bac24a8b90b8d58d]: Sch. 10 para. 40 in force at 28.7.2025, see art. 1

[^key-32e27888cf58eb2f45fa5af245c80e2b]: Sch. 10 para. 41 in force at 28.7.2025, see art. 1

[^key-d70b9f00e75174d7baeb1482b4cd940e]: Sch. 10 para. 42 in force at 28.7.2025, see art. 1

[^key-88918f0fd295ae2c90ec76abaca20200]: Sch. 10 para. 43 in force at 28.7.2025, see art. 1

[^key-7859401e2b3b7da11126f3754d5fd8a6]: Sch. 10 para. 44 in force at 28.7.2025, see art. 1

[^key-dc847d3ef214001b1b764ad810c34e08]: Sch. 10 para. 45 in force at 28.7.2025, see art. 1

[^key-584f633f2811ce5030ee0c6f2ae5ffe5]: Sch. 10 para. 46 in force at 28.7.2025, see art. 1

[^key-65169d406b33f6da1c8a140db89d4138]: Sch. 10 para. 47 in force at 28.7.2025, see art. 1

[^key-bc1bd49881916cb83243c66d1fe7c718]: Sch. 10 para. 48 in force at 28.7.2025, see art. 1

[^key-53ff0bab002330aa763b02ebdedf67b2]: Sch. 10 para. 49 in force at 28.7.2025, see art. 1

[^key-88c7249141cd14d6e0dbaadf2b60eb7b]: Sch. 10 para. 50 in force at 28.7.2025, see art. 1

[^key-35441088b911bb89c80c1b79b781c853]: Sch. 10 para. 51 in force at 28.7.2025, see art. 1

[^key-810333ab4f9d771b20b220937d3bb501]: Sch. 10 para. 52 in force at 28.7.2025, see art. 1

[^key-fe00611d80449e8709395ce2237be23e]: Sch. 10 para. 53 in force at 28.7.2025, see art. 1

[^key-d74a287a5582c8d06c645cc766c85820]: Sch. 10 para. 54 in force at 28.7.2025, see art. 1

[^key-6c8ddfb09822d04b484cc42ecbf8b1d3]: Sch. 10 para. 55 in force at 28.7.2025, see art. 1

[^key-832f8165643477a2762fb215b58e48f2]: Sch. 10 para. 56 in force at 28.7.2025, see art. 1

[^key-c7daf6566d85c9f617eb93f8839d54c3]: Sch. 10 para. 57 in force at 28.7.2025, see art. 1

[^key-81391e29ea15209f160b0a987895a4d6]: Sch. 10 para. 58 in force at 28.7.2025, see art. 1

[^key-63cf0f9d94ff896db367262027af81e5]: Sch. 10 para. 59 in force at 28.7.2025, see art. 1

[^key-b8fbb3dbf84ef6fae7a08a0d73991c52]: Sch. 10 para. 60 in force at 28.7.2025, see art. 1

[^key-4c7d2a352969d8dfcde6e6c0a3dadbfb]: Sch. 10 para. 61 in force at 28.7.2025, see art. 1

[^key-4a2f830f4bcce142adf9611f28d14c96]: Sch. 10 para. 62 in force at 28.7.2025, see art. 1

[^key-689159ef1e527a4a73743ee768634ea5]: Sch. 10 para. 63 in force at 28.7.2025, see art. 1

[^key-e9d11e8228b8411a6367bd2516fc0ed3]: Sch. 10 para. 64 in force at 28.7.2025, see art. 1

[^key-f7b877953826fe3498a03352affba2a5]: Sch. 10 para. 65 in force at 28.7.2025, see art. 1

[^key-28c7931019fcbcb35bdadce69bc02028]: Sch. 10 para. 66 in force at 28.7.2025, see art. 1

[^key-9e3ed14747200681e499f05bd3820b7e]: Sch. 10 para. 67 in force at 28.7.2025, see art. 1

[^key-518149c0ecc8538034b378b60677c9cd]: Sch. 10 para. 68 in force at 28.7.2025, see art. 1

[^key-375fc216e839d121be9fa3f7686096cb]: Sch. 10 para. 69 in force at 28.7.2025, see art. 1

[^key-bd6275fb538d4abe3b38264ae84acf99]: Sch. 10 para. 70 in force at 28.7.2025, see art. 1

[^key-88902f7f40a532281aea7c2b5f50e603]: Sch. 10 para. 71 in force at 28.7.2025, see art. 1

[^key-b1106fb23787d7e1568c2ed69a33cecf]: Sch. 10 para. 72 in force at 28.7.2025, see art. 1

[^key-0dcae1a3a470cbcadb230d8f9867987a]: Sch. 10 para. 73 in force at 28.7.2025, see art. 1

[^key-b821d6e07a08c5873deb6a3216dbcaa3]: Sch. 10 para. 74 in force at 28.7.2025, see art. 1

[^key-de5160c8bb62dc164780829ae65b5f07]: Sch. 10 para. 75 in force at 28.7.2025, see art. 1

[^key-4701ae0e40128014cb8312731c4aba59]: Sch. 10 para. 76 in force at 28.7.2025, see art. 1

[^key-1deeb5786c2b5a6012c0573ac5dec0de]: Sch. 10 para. 77 in force at 28.7.2025, see art. 1

[^key-019df6707946063805d97feb1ae4b424]: Sch. 10 para. 78 in force at 28.7.2025, see art. 1

[^key-08383510a7f541e469ae456a9c17c3f1]: Sch. 10 para. 79 in force at 28.7.2025, see art. 1

[^key-da2b86acad99ee2e867bd0c69a61abab]: Sch. 10 para. 80 in force at 28.7.2025, see art. 1

[^key-046c87c27f4424df4945696c3dbc0890]: Sch. 10 para. 81 in force at 28.7.2025, see art. 1

[^key-5e0b3c643131dbede3b8758b71a84caf]: Sch. 10 para. 82 in force at 28.7.2025, see art. 1

[^key-d5ed6aa7071fc4c5b39c11139203eafb]: Sch. 10 para. 83 in force at 28.7.2025, see art. 1

[^key-97fd1b0ea240426414f9846eb7464dc9]: Sch. 10 para. 84 in force at 28.7.2025, see art. 1

[^key-4d130247523426c6739bdccc9c3a4500]: Sch. 10 para. 85 in force at 28.7.2025, see art. 1

[^key-10e976dcaa1eeca486274e5e6d1de848]: Sch. 10 para. 86 in force at 28.7.2025, see art. 1

[^key-cba0b77737bba32d9311a82cffaacc0c]: Sch. 10 para. 87 in force at 28.7.2025, see art. 1

[^key-30eb775e206a96e71c84df804c9b47b7]: Sch. 10 para. 88 in force at 28.7.2025, see art. 1

[^key-a22659e7f1af7fbdff0833352061d3a3]: Sch. 10 para. 89 in force at 28.7.2025, see art. 1

[^key-346b2e9cd2aaebf86b8653a4dd8fd9d7]: Sch. 10 para. 90 in force at 28.7.2025, see art. 1

[^key-b62f09d7d66953be2d50f2c290c1dfff]: Sch. 10 para. 91 in force at 28.7.2025, see art. 1

[^key-9071bd90a2e5855975fdb2df493b8b90]: Sch. 10 para. 92 in force at 28.7.2025, see art. 1

[^key-4535e9e1d7a52dd126824824204616d5]: Sch. 10 para. 93 in force at 28.7.2025, see art. 1

[^key-44d901691ca528466c6e7c5d08a8bcc0]: Sch. 10 para. 94 in force at 28.7.2025, see art. 1

[^key-224ba76cdb17f1e4c48efe59f9036ecb]: Sch. 10 para. 95 in force at 28.7.2025, see art. 1

[^key-ae012ead5c7eb71668c222d2f344ac80]: Sch. 10 para. 96 in force at 28.7.2025, see art. 1

[^key-cbe959e92bef90c543a3c4306d1bec56]: Sch. 10 para. 97 in force at 28.7.2025, see art. 1

[^key-9940377d887fdea218b523194be0e134]: Sch. 10 para. 98 in force at 28.7.2025, see art. 1

[^key-30cf22b0e79b434c8c68a78cfbeb76f4]: Sch. 10 para. 99 in force at 28.7.2025, see art. 1

[^key-af683756b390256e994f1dfc2f6348dc]: Sch. 10 para. 100 in force at 28.7.2025, see art. 1

[^key-be0ea447cdcf668b27ef05d57475b353]: Sch. 10 para. 101 in force at 28.7.2025, see art. 1

[^key-903f5d1f4e6192612b08815a15bec073]: Sch. 10 para. 102 in force at 28.7.2025, see art. 1

[^key-c08f3d8dd6006c9c0b45f7f35db78777]: Sch. 10 para. 103 in force at 28.7.2025, see art. 1

[^key-1316fcacd74a900d68458e8373cc02be]: Sch. 10 para. 104 in force at 28.7.2025, see art. 1

[^key-7360dbcad734d399572964565d686636]: Sch. 10 para. 105 in force at 28.7.2025, see art. 1

[^key-8174bb7a278bcfa4ca4dc1b26371387f]: Sch. 10 para. 106 in force at 28.7.2025, see art. 1

[^key-fe045112823140d44563a63af27f79b8]: Sch. 10 para. 107 in force at 28.7.2025, see art. 1

[^key-5f0d66531de0bafc2e0f5cbe7bd355f3]: Sch. 10 para. 108 in force at 28.7.2025, see art. 1

[^key-d656bb95320a7f410c1ab01f65b9c430]: Sch. 10 para. 109 in force at 28.7.2025, see art. 1

[^key-994b869cb666b3dd021fb426850a9e68]: Sch. 10 para. 110 in force at 28.7.2025, see art. 1

[^key-3f1e243f16b2f7ad8ca6361fb04f58e5]: Sch. 10 para. 111 in force at 28.7.2025, see art. 1

[^key-352e99989c18468889e1e24bdd34a1dc]: Sch. 10 para. 112 in force at 28.7.2025, see art. 1

[^key-829574967ac87c7f06d439e23de6f40a]: Sch. 10 para. 113 in force at 28.7.2025, see art. 1

[^key-8896aabc14646bf9f61a934a281fc761]: Sch. 10 para. 114 in force at 28.7.2025, see art. 1

[^key-d482be17571bf317d234741b671e92e9]: Sch. 10 para. 115 in force at 28.7.2025, see art. 1

[^key-ab95129a87e2fed0d53c110b94009474]: Sch. 10 para. 116 in force at 28.7.2025, see art. 1

[^key-a7314fefb7eb10550738fd1139f02ebe]: Sch. 10 para. 117 in force at 28.7.2025, see art. 1

[^key-7d00f8a61960de3b4b37cd8df0e375b1]: Sch. 10 para. 118 in force at 28.7.2025, see art. 1

[^key-05252887fb023fcc7c8b81c0f084fd38]: Sch. 10 para. 119 in force at 28.7.2025, see art. 1

[^key-73cee274a6c343b696ec2b442e17dd21]: Sch. 10 para. 120 in force at 28.7.2025, see art. 1

[^key-2a54c09a4e22c829fc90892ac616b11c]: Sch. 10 para. 121 in force at 28.7.2025, see art. 1

[^key-10881426057997de91555c1037dbc6f4]: Sch. 10 para. 122 in force at 28.7.2025, see art. 1

[^key-536efc17b0bb77b3cd5cc7df7038caa3]: Sch. 10 para. 123 in force at 28.7.2025, see art. 1

[^key-1248d747d847465e68b719d8d5cbf3ee]: Sch. 10 para. 124 in force at 28.7.2025, see art. 1

[^key-35420ae58ad273e9bb87813a49c6b125]: Sch. 10 para. 125 in force at 28.7.2025, see art. 1

[^key-121afd908944ca7b78291b7e8e07d433]: Sch. 10 para. 126 in force at 28.7.2025, see art. 1

[^key-25867923be1db0ff2e0b99a14ef5b818]: Sch. 10 para. 127 in force at 28.7.2025, see art. 1

[^key-8c217ac84d74fe5fb29f7938e95ceff0]: Sch. 10 para. 128 in force at 28.7.2025, see art. 1

[^key-adefdee81f420e12192d46d818a07e22]: Sch. 10 para. 129 in force at 28.7.2025, see art. 1

[^key-1d35abf8d398c634f221f7ad18b415cf]: Sch. 10 para. 130 in force at 28.7.2025, see art. 1

[^key-26d287b81eb8d23ddd33c48bb27eca5f]: Sch. 10 para. 131 in force at 28.7.2025, see art. 1

[^key-511b9a1f83db971fea5fc7dc4efa7794]: Sch. 10 para. 132 in force at 28.7.2025, see art. 1

[^key-dc2c56efd2e069735eb1351a630c5abd]: Sch. 10 para. 133 in force at 28.7.2025, see art. 1

[^key-ef0d06b1eeb825c5dc9e485c06c21d6a]: Sch. 10 para. 134 in force at 28.7.2025, see art. 1

[^key-68d314597b9c1840f922d22c72948bf4]: Sch. 10 para. 135 in force at 28.7.2025, see art. 1

[^key-8c42f248e105164d4c3d85aabc1e6426]: Sch. 10 para. 136 in force at 28.7.2025, see art. 1

[^key-a45499d6c4f0373b5d84b1db0415fe83]: Sch. 12 para. 1 in force at 28.7.2025, see art. 1

[^key-d85fe165fc49b017844a080f4817f5f8]: Sch. 12 para. 2 in force at 28.7.2025, see art. 1

[^key-957042209dd1224851af7c843bd8a43c]: Sch. 12 para. 3 in force at 28.7.2025, see art. 1

[^key-f6deed3568567dfe1fc48fde8c6c727e]: Sch. 12 para. 4 in force at 28.7.2025, see art. 1

[^key-003e18bd100995bfe7dbb46454ec088c]: Sch. 12 para. 5 in force at 28.7.2025, see art. 1

[^key-ef3345d4942b30223972c360b44479fd]: Sch. 12 para. 6 in force at 28.7.2025, see art. 1

[^key-408365a92b072e9d3ab20ba870085004]: Sch. 12 para. 7 in force at 28.7.2025, see art. 1

[^key-e45f4bd099165073f2dc332170df152d]: Sch. 13 para. 1 in force at 28.7.2025, see art. 1

[^key-5e852ab220e3eaf76e3924e7707eb75d]: Sch. 13 para. 2 in force at 28.7.2025, see art. 1

[^key-6b24aaa4e5f8bb7e73210339e8a6e8ec]: Sch. 13 para. 3 in force at 28.7.2025, see art. 1

[^key-73531a85385f7f4b66243c11fe884e68]: Sch. 13 para. 4 in force at 28.7.2025, see art. 1

[^key-369795b40db6446a55f3be40d738dac4]: Sch. 13 para. 5 in force at 28.7.2025, see art. 1

[^key-492b09a411381e1ac5d07af7ace80164]: Sch. 13 para. 6 in force at 28.7.2025, see art. 1

[^key-33a09f731e01ab6e1b454b6b4d81beb7]: Sch. 13 para. 7 in force at 28.7.2025, see art. 1

[^key-06f2fb8a394d264f6ddf293345e1f7dd]: Sch. 14 para. 1 in force at 28.7.2025, see art. 1

[^key-246dd314d82b97359c8cabb20a492878]: Sch. 14 para. 2 in force at 28.7.2025, see art. 1

[^key-ef100cd7dd0ffb7c6f2e4d2d5ed3f609]: Sch. 14 para. 3 in force at 28.7.2025, see art. 1

[^key-16165cf69c4922b38f5c88629fa12d73]: Sch. 14 para. 4 in force at 28.7.2025, see art. 1

[^key-0df2ede7eccd835703664aff1d2c4a5e]: Sch. 14 para. 5 in force at 28.7.2025, see art. 1

[^key-3fa11b67dba1e57191921991231e8d58]: Sch. 14 para. 6 in force at 28.7.2025, see art. 1

[^key-ebab7081f34830d1ef427ca5286ad3d3]: Sch. 14 para. 7 in force at 28.7.2025, see art. 1

[^key-8c113c01943af2f15d6fb21b7aa1e7fc]: Sch. 14 para. 8 in force at 28.7.2025, see art. 1

[^key-974e094553e2217c166ff154daf6f843]: Sch. 14 para. 9 in force at 28.7.2025, see art. 1

[^key-9e307ca9058e46632db2c66949327cba]: Sch. 14 para. 10 in force at 28.7.2025, see art. 1

[^key-e74e4e3f6205032a93daf56bd37a9c5f]: Sch. 14 para. 11 in force at 28.7.2025, see art. 1

[^key-866a2c6c8d1729c2c40fa42c45985985]: Sch. 14 para. 12 in force at 28.7.2025, see art. 1

[^key-54e44d43d663987c6526383e22780b02]: Sch. 14 para. 13 in force at 28.7.2025, see art. 1

[^key-09a273e2de87bf4346b354811fda2d9f]: Sch. 14 para. 14 in force at 28.7.2025, see art. 1

[^key-b7a01d3c210ceac08c2a45a8bc9c88ee]: Sch. 14 para. 15 in force at 28.7.2025, see art. 1

[^key-c4f23ebda9d1ff0d737dfc82b5bc7395]: Sch. 14 para. 16 in force at 28.7.2025, see art. 1

[^key-61ddb7b38efce5bea8253ad56199c10d]: Sch. 14 para. 17 in force at 28.7.2025, see art. 1

[^key-1c5700cabb72bf0263f5c08ba166ea52]: Sch. 14 para. 18 in force at 28.7.2025, see art. 1

[^key-c12007fc2ce6b10246832444a6689ac8]: Sch. 14 para. 19 in force at 28.7.2025, see art. 1

[^key-a2e072e42ce0e7b283fad5ba9e78d6af]: Sch. 14 para. 20 in force at 28.7.2025, see art. 1

[^key-9dae4b5813475acc3a21f3970ab0afca]: Sch. 14 para. 21 in force at 28.7.2025, see art. 1

[^key-cd62ee9476a6f894a09d044098571da8]: Sch. 14 para. 22 in force at 28.7.2025, see art. 1

[^key-5a21c7e705d9252c2e497d91b23e5226]: Sch. 14 para. 23 in force at 28.7.2025, see art. 1

[^key-74eaa17e76c95affaa2a5383c1a2e8ef]: Sch. 14 para. 24 in force at 28.7.2025, see art. 1

[^key-247e18e5f6c029c14ccebe97237bbf10]: Sch. 14 para. 25 in force at 28.7.2025, see art. 1

[^key-650c5832a2b1112decf70c147e9f0ef8]: Sch. 14 para. 26 in force at 28.7.2025, see art. 1

[^key-fc1961f0f65870be4c207de326e79bc0]: Sch. 14 para. 27 in force at 28.7.2025, see art. 1

[^key-217ea976c30a707a63a845ee4f36e019]: Sch. 14 para. 28 in force at 28.7.2025, see art. 1

[^key-66307af52a9b82e3758ac8558c7fcee7]: Sch. 14 para. 29 in force at 28.7.2025, see art. 1

[^key-2ef50c56103ca83f78df32e24a1ef9f3]: Sch. 3 in force at 28.7.2025, see art. 1

[^key-04ddfb6aa42e91b635648a056a39a511]: Sch. 4 in force at 28.7.2025, see art. 1

[^key-9624d0acdab9d62ab827097fc68e937e]: Sch. 5 in force at 28.7.2025, see art. 1

[^key-f34d8da882d0d49a8a99939b55f20afc]: Sch. 6 in force at 28.7.2025, see art. 1

[^key-1b444f46dd99505f719eae5dfe812eaf]: Sch. 7 in force at 28.7.2025, see art. 1

[^key-7fa51b57b4ab5412cc46eb456b4133fc]: Sch. 8 in force at 28.7.2025, see art. 1

[^key-fa3409245058ec9a66f3ee1cd63afd16]: Sch. 11 Pt. 1 in force at 28.7.2025, see art. 1

[^key-e7fcc2d13be3c0a0126b19abf6057c0a]: Sch. 11 Pt. 2 in force at 28.7.2025, see art. 1

[^key-88a7e19684f4508d52fd269ee6780cab]: Sch. 11 Pt. 3 in force at 28.7.2025, see art. 1

[^key-5bba05c32b5bde7825f8cf4c4942ae9b]: Sch. 15 in force at 28.7.2025, see art. 1

[^key-95b11ff4a2bd6bd2b4791b59527e4fb0]: Word in Sch. 8 substituted (24.10.2025) by The Mona Offshore Wind Farm (Correction) Order 2025 (S.I. 2025/1123), art. 1, Sch.

[^key-0c76fade662f4a7b7b86b7ebabde4a9c]: Word in Sch. 15 Table 7 substituted (24.10.2025) by The Mona Offshore Wind Farm (Correction) Order 2025 (S.I. 2025/1123), art. 1, Sch.

[^key-1229ca20145d7d69a91d20311b6beeb5]: Words in Sch. 15 Table 7 substituted (24.10.2025) by The Mona Offshore Wind Farm (Correction) Order 2025 (S.I. 2025/1123), art. 1, Sch.

[^key-5cd0e780458b86b2f29874938e39efb6]: Words in art. 2(1) substituted (24.10.2025) by The Mona Offshore Wind Farm (Correction) Order 2025 (S.I. 2025/1123), art. 1, Sch.

[^key-f233f6795429da900793560bf221a206]: Word in art. 2(1) inserted (24.10.2025) by The Mona Offshore Wind Farm (Correction) Order 2025 (S.I. 2025/1123), art. 1, Sch.

[^key-6dc45b84e3d3657028adaeb02c7c985f]: Words in art. 7(3) inserted (24.10.2025) by The Mona Offshore Wind Farm (Correction) Order 2025 (S.I. 2025/1123), art. 1, Sch.

[^key-1041f3007f31ed505346571dc85448d5]: Words in art. 35(3) substituted (24.10.2025) by The Mona Offshore Wind Farm (Correction) Order 2025 (S.I. 2025/1123), art. 1, Sch.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.