The Mona Offshore Wind Farm Order 2025
- (1) If, in the exercise of the powers conferred by this Order the undertaker acquires any interest in or possesses temporarily any land in which any apparatus is placed, that apparatus must not be removed under this Part of this Schedule and any right of National Grid Electricity Transmission Plc to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed and is in operation to the reasonable satisfaction of National Grid Electricity Transmission Plc in accordance with sub-paragraph (2) to (5)
- (2) If, for the purpose of executing any works comprised in the authorised development in, on, under or over any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to National Grid Electricity Transmission Plc a minimum of 56 days’ advance written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order National Grid Electricity Transmission Plc reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), secure any necessary consents for the alternative apparatus and afford to National Grid Electricity Transmission Plc to its satisfaction (taking into account paragraph 91(1) below) the necessary facilities and rights—
- (a) for the construction of alternative apparatus in other land of or land secured by the undertaker; and
- (b) subsequently for the maintenance of that apparatus.
- (3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of or land secured by the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2) in the land in which the alternative apparatus or part of such apparatus is to be constructed, National Grid Electricity Transmission Plc may in its sole discretion, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances to assist the undertaker to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed save that this obligation shall not extend to the requirement for National Grid Electricity Transmission Plc to use its compulsory purchase powers to this end unless it elects to so do.
- (4) Any alternative apparatus to be constructed in land of or land secured by the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between National Grid Electricity Transmission Plc and the undertaker.
- (5) National Grid Electricity Transmission Plc must, after the alternative apparatus to be provided or constructed has been agreed, and subject to any necessary legal agreements having been entered into between the parties and the grant to National Grid Electricity Transmission Plc of any such facilities and rights as are referred to in sub-paragraph (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
Facilities and rights for alternative apparatus
91
- (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to or secures for National Grid Electricity Transmission Plc facilities and rights in land for the construction, use, maintenance and protection of alternative apparatus in substitution for apparatus to be removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between the undertaker and National Grid Electricity Transmission Plc and must be no less favourable on the whole to National Grid Electricity Transmission Plc than the facilities and rights enjoyed by it in respect of the apparatus to be removed unless otherwise agreed by National Grid Electricity Transmission Plc.
- (2) If the facilities and rights to be afforded by the undertaker and agreed with National Grid Electricity Transmission Plc under sub-paragraph (1) in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are less favourable on the whole to National Grid Electricity Transmission Plc than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject the matter may be referred to arbitration in accordance with paragraph 98 (Arbitration) of this Part of this Schedule and the arbitrator must make such provision for the payment of compensation by the undertaker to National Grid Electricity Transmission Plc as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case. In respect of the appointment of an arbitrator under this sub-paragraph, article 45 (arbitration) applies.
Retained apparatus: Protection of National Grid Electricity Transmission Plc as Electricity Undertaker
92
- (1) Not less than 56 days before the commencement of any specified works the undertaker must submit to National Grid Electricity Transmission Plc a plan of the works to be executed and seek from National Grid Electricity Transmission Plc details of the underground extent of their electricity assets.
- (2) In relation to specified works the plan to be submitted to National Grid Electricity Transmission Plc under sub-paragraph (1) must include a method statement and describe—
- (a) the exact position of the works;
- (b) the level at which these are proposed to be constructed or renewed;
- (c) the manner of their construction or renewal including details of excavation, positioning of plant;
- (d) the position of all apparatus;
- (e) by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus;
- (f) any intended maintenance regimes;
- (g) an assessment of risks of rise of earth issues; and
- (h) a ground monitoring scheme, where required.
- (3) In relation to any works which will or may be situated on, over, under or within 10 metres of any part of the foundations of an electricity tower or between any two or more electricity towers, the plan to be submitted under sub-paragraph (1) must in addition to the matters set out in sub-paragraph (2) include a method statement describing—
- (a) details of any cable trench design including route, dimensions, clearance to pylon foundations;
- (b) demonstration that pylon foundations will not be affected prior to, during and post construction;
- (c) details of load bearing capacities;
- (d) details of any cable installation methodology including access arrangements, jointing bays and backfill methodology;
- (e) a written management plan for high voltage hazard during construction and ongoing maintenance of any cable route;
- (f) written details of the operations and maintenance regime for any cable, including frequency and method of access;
- (g) assessment of earth rise potential if reasonably required by National Grid Electricity Transmission Plc’s engineers; and
- (h) evidence that trench bearing capacity is to be designed to support overhead line construction traffic of up to and including 26 tonnes in weight.
- (4) The undertaker must not commence any works to which sub-paragraphs (2) or (3) apply until National Grid Electricity Transmission Plc has given written approval of the plan so submitted.
- (5) Any approval of National Grid Electricity Transmission Plc required under sub-paragraphs (4)—
- (a) may be given subject to reasonable conditions for any purpose mentioned in sub-paragraphs (6) or (8); and
- (b) may be given subject to such reasonable requirements as National Grid may have in connection with the safe and efficient construction, commissioning, operation and maintenance of the Bodelwyddan Project and/or the Connah’s Quay Project; and
- (c) must not be unreasonably withheld.
- (6) In relation to any work to which sub-paragraphs (2) or (3) apply, National Grid Electricity Transmission Plc may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its apparatus against interference or risk of damage, for the provision of protective works or for the purpose of providing or securing proper and convenient means of access to any apparatus.
- (7) Works executed under sub-paragraphs (2) or (3) must be executed in accordance with the plan, submitted under sub-paragraph (1) or as relevant sub-paragraph (6), as approved or as amended from time to time by agreement between the undertaker and National Grid Electricity Transmission Plc and in accordance with such reasonable requirements as may be made in accordance with sub-paragraphs (6), or (8) by National Grid Electricity Transmission Plc for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and National Grid Electricity Transmission Plc will be entitled to watch and inspect the execution of those works.
- (8) Where National Grid Electricity Transmission Plc requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to National Grid Electricity Transmission Plc’s satisfaction prior to the commencement of any authorised development (or any relevant part thereof) for which protective works are required and National Grid Electricity Transmission Plc shall give 56 days’ notice of its requirement for such works from the date of submission of a plan pursuant to this paragraph (except in an emergency).
- (9) If National Grid Electricity Transmission Plc in accordance with sub-paragraphs (6) or (8) and in consequence of the works proposed by the undertaker reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 79 to 81 and 84 to 86 apply as if the removal of the apparatus had been required by the undertaker under paragraph 90 (2).
- (10) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of the authorised development, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph shall apply to and in respect of the new plan.
- (11) The undertaker will not be required to comply with sub-paragraph (1) where it needs to carry out emergency works as defined in the 1991 Act but in that case it must give to National Grid Electricity Transmission Plc notice as soon as is reasonably practicable and a plan of those works and must—
- (a) comply with sub-paragraphs (6), (7) and (8) in so far as is reasonably practicable in the circumstances and
- (b) comply with sub-paragraph (12) at all times.
- (12) At all times when carrying out any works authorised under the Order, the undertaker must comply with National Grid Electricity Transmission Plc’s policies for development near overhead lines EN43-8 and HSE’s guidance note 6 “Avoidance of Danger from Overhead Lines”.
Expenses
93
- (1) Save where otherwise agreed in writing between National Grid Electricity Transmission Plc and the undertaker and subject to the following provisions of this paragraph, the undertaker must pay to National Grid Electricity Transmission Plc within 30 days of receipt of an itemised invoice or claim from National Grid Electricity Transmission Plc all charges, costs and expenses reasonably anticipated within the following three months or reasonably and properly incurred by National Grid Electricity Transmission Plc in, or in connection with, the inspection, removal, relaying or replacing, alteration or protection of any apparatus or the construction of any new or alternative apparatus which may be required in consequence of the execution of any authorised works including without limitation—
- (a) any costs reasonably incurred by or compensation properly paid by National Grid Electricity Transmission Plc in connection with the acquisition of rights or the exercise of statutory powers for such apparatus including without limitation all costs incurred by National Grid Electricity Transmission Plc as a consequence of National Grid Electricity Transmission Plc—
- (i) using its own compulsory purchase powers to acquire any necessary rights under paragraph 85(3); or
- (ii) exercising any compulsory purchase powers in the Order transferred to or benefitting National Grid Electricity Transmission Plc.
- (b) in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus, where no legal agreement is otherwise in place;
- (c) the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
- (d) the approval of plans;
- (e) the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works;
- (f) the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule.
- (2) There will be deducted from any sum payable under sub-paragraph the value of any apparatus removed under the provisions of this Part of this Schedule and which is not re-used as part of the alternative apparatus, that value being calculated after removal.
- (3) If in accordance with the provisions of this Part of this Schedule—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 45 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to National Grid Electricity Transmission Plc by virtue of sub-paragraph (1) will be reduced by the amount of that excess save to the extent that it is not possible in the circumstances to obtain the existing type of apparatus at the same capacity and dimensions or place at the existing depth in which case full costs will be borne by the undertaker.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus will not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
- (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole will be treated as if it also had been agreed or had been so determined.
- (5) Any amount which apart from this sub-paragraph would be payable to National Grid Electricity Transmission Plc in respect of works by virtue of sub-paragraph (1) will, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on National Grid Electricity Transmission Plc any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
Indemnity
94
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any works authorised by this Part of this Schedule or in consequence of the construction, use, maintenance or failure of any of the authorised works by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by him) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised works) or property of National Grid Electricity Transmission Plc, or there is any interruption in any service provided, or in the supply of any goods, by National Grid Electricity Transmission Plc, or National Grid Electricity Transmission Plc becomes liable to pay any amount to any third party, the undertaker will—
- (a) bear and pay on demand accompanied by an invoice or claim from National Grid Electricity Transmission Plc the cost reasonably and properly incurred by National Grid Electricity Transmission Plc in making good such damage or restoring the supply; and
- (b) indemnify National Grid Electricity Transmission Plc for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from National Grid Electricity Transmission Plc, by reason or in consequence of any such damage or interruption or National Grid Electricity Transmission Plc becoming liable to any third party and including STC Claims or an Incentive Deduction other than arising from any default of National Grid Electricity Transmission Plc.
- (2) The fact that any act or thing may have been done by National Grid Electricity Transmission Plc on behalf of the undertaker or in accordance with a plan approved by National Grid Electricity Transmission Plc or in accordance with any requirement of National Grid Electricity Transmission Plc or under its supervision will not (unless sub-paragraph (3) applies), excuse the undertaker from liability under the provisions of this sub-paragraph (1) unless National Grid Electricity Transmission Plc fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan
- (3) Nothing in sub-paragraph (1) shall impose any liability on the undertaker in respect of—
- (a) any damage or interruption to the extent that it is attributable to the neglect or default of National Grid Electricity Transmission Plc, its officers, servants, contractors or agents;
- (b) any authorised works and/or any other works authorised by this Part of this Shcedule carried out by National Grid Electricity Transmission Plc as an assignee, transferee or lessee of the undertaker with the benefit of the Order pursuant to section 156 of the Planning Act 2008 or article 7 (benefit of the Order) subject to the proviso that once such works become apparatus (“new apparatus”) any authorised works yet to be executed and not falling within this sub-section 3(b) will be subject to the full terms of this Part of this Schedule including this paragraph 89; and/or
- (c) any indirect or consequential loss of any third party (including but not limited to loss of use, revenue, profit, contract, production, increased cost of working or business interruption) arising from any such damage or interruption, which is not reasonably foreseeable;
- (4) National Grid Electricity Transmission Plc must give the undertaker reasonable notice of any such third party claim or demand and no settlement, admission of liability or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and considering their representations.
- (5) National Grid must Electricity Transmission Plc, in respect of any matter covered by the indemnity given by the undertaker in this paragraph, at all times act reasonably and in the same manner as it would as if settling third party claims on its own behalf from its own funds.
- (6) National Grid Electricity Transmission Plc must use its reasonable endeavours to mitigate and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph applies where it is within National Grid Electricity Transmission Plc’s reasonable ability and control to do so and which expressly excludes any obligation to mitigate liability arising from third parties which is outside of National Grid Electricity Transmission Plc’s control and if reasonably requested to do so by the undertaker National Grid Electricity Transmission Plc must provide an explanation of how the claim has been minimised, where relevant.
- (7) Not to commence construction (and not to permit the commencement of such construction) of the authorised works on any land owned by National Grid Electricity Transmission Plc or in respect of which National Grid Electricity Transmission Plc has an easement or wayleave for its apparatus or any other interest or to carry out any works within 15 metres of National Grid Electricity Transmission Plc’s apparatus until the following conditions are satisfied—
- (a) unless and until National Grid Electricity Transmission Plc is satisfied acting reasonably (but subject to all necessary regulatory constraints) that the undertaker has first provided the acceptable security (and provided evidence that it shall maintain such acceptable security for the construction period of the authorised works from the proposed date of commencement of construction of the authorised works) and National Grid Electricity Transmission Plc has confirmed the same to the undertaker in writing; and
- (b) unless and until National Grid Electricity Transmission Plc is satisfied acting reasonably (but subject to all necessary regulatory constraints) that the undertaker has procured acceptable insurance (and provided evidence to National Grid Electricity Transmission Plc that it shall maintain such acceptable insurance for the construction period of the authorised works from the proposed date of commencement of construction of the authorised works) and National Grid Electricity Transmission Plc has confirmed the same in writing to the undertaker.
- (8) In the event that the undertaker fails to comply with 89(7) of this Part of this Schedule, nothing in this Part of this Schedule shall prevent National Grid Electricity Transmission Plc from seeking injunctive relief (or any other equitable remedy) in any court of competent jurisdiction.
Enactments and agreements
95
Save to the extent provided for to the contrary elsewhere in this Part of this Schedule or by agreement in writing between National Grid Electricity Transmission Plc and the undertaker, nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and National Grid Electricity Transmission Plc in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
Co-operation
96
- (1) Where in consequence of the proposed construction of any part of the authorised works the undertaker or National Grid Electricity Transmission Plc requires the removal of apparatus under paragraph 85(2) or National Grid Electricity Transmission Plc makes requirements for the protection or alteration of apparatus under paragraph9, the undertaker shall use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised works and taking into account the need to ensure the safe and efficient operation of National Grid Electricity Transmission Plc’s undertaking and National Grid Electricity Transmission Plc shall use its best endeavours to co-operate with the undertaker for that purpose.
- (2) For the avoidance of doubt whenever National Grid Electricity Transmission Plc’s consent, agreement or approval is required in relation to plans, documents or other information submitted by the undertaker or the taking of action by the undertaker, it must not be unreasonably withheld or delayed.
Access
97
If in consequence of the agreement reached in accordance with paragraph 84(1) or the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable National Grid Electricity Transmission Plc to maintain or use the apparatus no less effectively than was possible before such obstruction.
Arbitration
98
Save for differences or disputes arising under paragraphs 90(2), 90(4), 91(1) and 92 any difference or dispute arising between the undertaker and National Grid Electricity Transmission Plc under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and National Grid Electricity Transmission Plc, be determined by arbitration in accordance with article 45 (arbitration).
Notices
99
Notwithstanding article 42 (service of notices), any plans submitted to National Grid Electricity Transmission Plc by the undertaker pursuant to paragraph 92 must be submitted using the LSBUD system (https://lsbud.co.uk/) or to such other address as National Grid Electricity Transmission Plc may from time to time appoint instead for that purpose and notify to the undertaker in writing.
PART 8 — For the protection of Network Rail Limited
100
The provisions of this Part have effect unless otherwise agreed in writing between the undertaker and Network Rail and, where paragraph 113 applies, any other person on whom rights or obligations are conferred by that paragraph.
101
In this Part—
- “asset protection agreement” means an agreement to regulate the construction and maintenance of the specified work in a form prescribed from time to time by Network Rail;
- “construction” includes execution, placing, alteration and reconstruction and “construct” and “constructed” have corresponding meanings;
- “engineer” means an engineer appointed by Network Rail for the purposes of this Order;
- “network licence” means the network licence, as the same is amended from time to time, granted to Network Rail by the Secretary of State in exercise of powers under section 8 of the Railways Act 1993[^f00049];
- “Network Rail” means Network Rail Infrastructure Limited (company number 02904587, whose registered office is at 1 Eversholt Street, London NW1 2DN) and any associated company of Network Rail Infrastructure Limited which holds property for railway purposes, and for the purpose of this definition “associated company” means any company which is (within the meaning of section 1159 of the Companies Act 2006[^f00050]) the holding company of Network Rail Infrastructure Limited, a subsidiary of Network Rail Infrastructure Limited or another subsidiary of the holding company of Network Rail Infrastructure Limited; and any successor to Network Rail Infrastructure Limited’s railway undertaking:
- “plans” includes sections, designs, design data, software, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of railway property;
- “railway operational procedures” means procedures specified under any access agreement (as defined in the Railways Act 1993) or station lease;
- “railway property” means any railway belonging to Network Rail and—any station, land, works, apparatus and equipment belonging to Network Rail or connected with any such railway; andany easement or other property interest held or used by Network Rail for the purposes of such railway or works, apparatus or equipment;
- “regulatory consents” means any consent or approval required under:the Railways Act 1993;the network licence; and/orany other relevant statutory or regulatory provisions;by either the Office of Rail and Road or the Secretary of State for Transport or any other competent body including change procedures and any other consents, approvals of any access or beneficiary that may be required in relation to the authorised development;
- “specified work” means so much of any of the authorised development as is or is to be situated upon, across, under, over or within 15 metres of, or may in any way adversely affect, railway property and for the avoidance of doubt, includes the maintenance of such works under the powers conferred by article 6 (power to maintain the authorised project) in respect of such works.
102
- (1) Where under this Part Network Rail is required to give its consent, agreement or approval in respect of any matter, that consent, agreement or approval is subject to the condition that Network Rail complies with any relevant railway operational procedures and any obligations under its network licence or under statute.
- (2) In so far as any specified work or the acquisition or use of railway property is or may be subject to railway operational procedures, Network Rail must—
- (a) co-operate with the undertaker with a view to avoiding undue delay and securing conformity as between any plans approved by the engineer and requirements emanating from those procedures; and
- (b) use its reasonable endeavours to avoid any conflict arising between the application of those procedures and the proper implementation of the authorised project under this Order.
103
- (1) The undertaker must not exercise the powers conferred by—
- (a) article 3 (development consent etc. granted by the Order);
- (b) article 6 (power to maintain the authorised project);
- (c) article 16 (discharge of water);
- (d) article 17 (authority to survey and investigate the land);
- (e) article 19 (compulsory acquisition of land);
- (f) article 21 (compulsory acquisition of rights);
- (g) article 23 (private rights);
- (h) article 25 (acquisition of subsoil only);
- (i) article 27 (rights under or over streets);
- (j) article 28 (temporary use of land for carrying out the authorised project);
- (k) article 29 (temporary use of land for maintaining the authorised project);
- (l) article 30 (statutory undertakers);
- (m) article 34 (felling or lopping of trees and removal of hedgerows);
- (n) article 35 (trees subject to tree preservation orders);
- (o) the powers conferred by section 11(3) (power of entry) of the 1965 Act;
- (p) the powers conferred by section 203 (power to override easements and rights) of the Housing and Planning Act 2016( );
- (q) the powers conferred by section 172 (right to enter and survey land) of the Housing and Planning Act 2016;
- (r) any powers in respect of the temporary possession of land under the Neighbourhood Planning Act 2017;
in respect of any railway property unless the exercise of such powers is with the consent of Network Rail.
- (2) The undertaker must not in the exercise of the powers conferred by this Order prevent pedestrian or vehicular access to any railway property, unless preventing such access is with the consent of Network Rail.
- (3) The undertaker must not exercise the powers conferred sections 271 or 272 of the 1990 Act, article 30 (statutory undertakers) or article 23 (private rights), in relation to any right of access of Network Rail to railway property, but such right of access may be diverted with the consent of Network Rail.
- (4) The undertaker must not under the powers of this Order acquire or use or acquire new rights over, or seek to impose any restrictive covenants over, any railway property, or extinguish any existing rights of Network Rail in respect of any third party property, except with the consent of Network Rail.
- (5) The undertaker must not under the powers of this Order do anything which would result in railway property being incapable of being used or maintained or which would affect the safe running of trains on the railway.
- (6) Where Network Rail is asked to give its consent pursuant to this paragraph, such consent must not be unreasonably withheld but may be given subject to reasonable conditions but it shall never be unreasonable to withhold consent for reasons of operational or railway safety (such matters to be in Network Rail’s absolute discretion).
- (7) The undertaker must enter into an asset protection agreement prior to the commencement of any specified work.
104
- (1) The undertaker must before commencing construction of any specified work supply to Network Rail proper and sufficient plans of that work for the reasonable approval of the engineer and the specified work must not be commenced except in accordance with such plans as have been approved in writing by the engineer or settled by arbitration under article 45 (arbitration).
- (2) The approval of the engineer under sub-paragraph 5(1) must not be unreasonably withheld or delayed, and if after 28 days beginning with the date on which such plans have been supplied to Network Rail the engineer has not communicated disapproval of those plans and the grounds of disapproval—
- (a) the undertaker may serve on the engineer written notice requiring the engineer to communicate approval or disapproval within a further period of 28 days beginning with the date on which the engineer receives written notice from the undertaker; and
- (b) if by the expiry of the further 28 days the engineer has not communicated approval or disapproval, the engineer is deemed to have approved the plans as supplied.
- (3) If after the expiry of 28 days beginning with the date on which written notice was served on the engineer under sub-paragraph 5(2), Network Rail gives notice to the undertaker that Network Rail desires itself to construct any part of a specified work which in the opinion of the engineer will or may affect the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker desires such part of the specified work to be constructed, Network Rail must construct it without unreasonable delay on behalf of and to the reasonable satisfaction of the undertaker in accordance with the plans approved or deemed to be approved or settled under this paragraph, and under the supervision (where appropriate and if given) of the undertaker.
- (4) When signifying approval of the plans the engineer may specify any protective works (whether temporary or permanent) which in the engineer’s reasonable opinion should be carried out before the commencement of the construction of a specified work to ensure the safety or stability of railway property or the continuation of safe and efficient operation of the railways of Network Rail or the services of operators using the same (including any relocation, decommissioning and removal of works, apparatus and equipment necessitated by a specified work and the comfort and safety of passengers who may be affected by the specified works), and—
- (a) such protective works as may be reasonably necessary for those purposes must be constructed by Network Rail or by the undertaker, if Network Rail so desires, and such protective works must be carried out at the expense of the undertaker, in either case without unreasonable delay; and
- (b) the undertaker must not commence the construction of the specified works in question until the engineer has notified the undertaker that the protective works have been completed to the engineer’s reasonable satisfaction.
- (5) Any specified works and any protective works to be constructed by virtue of paragraph 104(4) must, when commenced, be constructed—
- (a) without unnecessary delay in accordance with the plans approved or deemed to have been approved or settled under paragraph 104;
- (b) under the supervision (where appropriate and if given) and to the reasonable satisfaction of the engineer;
- (c) in such manner as to cause as little damage as is possible to railway property; and
- (d) so far as is reasonably practicable, so as not to interfere with or obstruct the free, uninterrupted and safe use of any railway of Network Rail or the traffic on it and the use by passengers of railway property.
- (6) If any damage to railway property or any interference or obstruction referred to in sub-paragraph 5(5)(d) is caused by the carrying out of, or in consequence of, the construction of a specified work, the undertaker must, regardless of any approval, make good such damage and must pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may sustain by reason of any such damage, interference or obstruction.
- (7) Nothing in this Part imposes any liability on the undertaker with respect to any damage, costs, expenses or loss attributable to the negligence of Network Rail or its employees, contractors or agents or any liability on Network Rail with respect to any damage, costs, expenses or loss attributable to the negligence of the undertaker or its employees, contractors or agents.
105
The undertaker must—
- (a) at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and
- (b) supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing it.
106
Network Rail must at all times afford reasonable facilities to the undertaker and its employees, contractors or agents for access to any works carried out by Network Rail under this Part during their construction and must supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them.
107
- (1) If any permanent or temporary alterations or additions to railway property are reasonably necessary in consequence of the construction of a specified work or during a period of 24 months after the completion of that work in order to ensure the safety of railway property or the continued safe and efficient operation of the railway of Network Rail, such alterations or additions may be carried out by Network Rail.
- (2) If Network Rail gives to the undertaker reasonable notice of its intention to carry out such alterations or additions (which must be specified in the notice), the undertaker must pay to Network Rail the reasonable cost of those alterations or additions including, in respect of any such alterations or additions which have been reasonably incurred by Network Rail, including, in respect of any such alterations or additions as are to be permanent, a capitalised sum representing the increase.
- (3) If during the construction of a specified work by the undertaker, Network Rail gives notice to the undertaker that Network Rail desires itself to construct that part of the specified work that in the opinion of the engineer is endangering the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker decides that part of the specified work is to be constructed, Network Rail must assume construction of that part of the specified work and the undertaker must, regardless of any approval of the specified work under paragraph 104(3), pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may suffer by reason of the execution by Network Rail of that specified work.
- (4) The engineer must, in respect of the capitalised sums referred to in this paragraph and paragraph 108, provide such details of the formula or method of calculation by which those sums have been calculated as the undertaker may reasonably require.
- (5) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions, a capitalised sum representing such saving must be set off against any sum payable by the undertaker to Network Rail under this paragraph.
108
The undertaker must repay to Network Rail all reasonable fees, costs, charges and expenses agreed in advance with the undertaker and reasonably incurred by Network Rail—
- (a) in constructing any part of a specified work on behalf of the undertaker under paragraph 104(3) or in constructing any protective works under paragraph 104(4) including in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;
- (b) in respect of the approval by the engineer of plans submitted by the undertaker and the supervision by the engineer of the construction of a specified work or a protective work;
- (c) in respect of the employment or procurement of the services of any inspectors, signallers, guards and other persons whom it is reasonably necessary to appoint for inspecting, signalling, watching and lighting railway property and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of a specified work;
- (d) in respect of any special traffic working resulting from any speed restrictions which may in the reasonable opinion of the engineer, need to be imposed by reason or in consequence of the construction or failure of a specified work or a protective work from the substitution or diversion of services which may be reasonably necessary for the same reason; and
- (e) in respect of any additional temporary lighting of railway property in the vicinity of the specified works or protective works, being lighting made reasonably necessary by reason or in consequence of the construction or failure of a specified work or protective works.
109
- (1) In this paragraph—
- “EMI” means, subject to sub-paragraph 109(2), electromagnetic interference with Network Rail apparatus generated by the operation of the onshore works here such interference is of a level which adversely affects the safe operation of Network Rail’s apparatus
- “Network Rail’s apparatus” means any lines, circuits, wires, apparatus or equipment (whether or not modified or installed as part of the authorised development) which are owned or used by Network Rail for the purpose of transmitting or receiving electrical energy or of radio, telegraphic, telephonic, electric, electronic or other like means of signalling or other communications.
- (2) This paragraph applies to EMI only to the extent that such EMI is not attributable to any change to Network Rail’s apparatus carried out after approval of plans under paragraph 104(1) for the relevant part of the onshore works giving rise to EMI (unless the undertaker has been given notice in writing before the approval of those plans of the intention to make such change).
- (3) Subject to sub-paragraph 109(5), the undertaker must in the design and construct the onshore works and take all measures necessary to prevent EMI and must establish with Network Rail (both parties acting reasonably) appropriate arrangements to verify their effectiveness.
- (4) In order to facilitate the undertaker’s compliance with sub-paragraph 109(3)—
- (a) the undertaker must consult with Network Rail as early as reasonably practicable to identify all Network Rail’s apparatus which may be at risk of EMI, and thereafter must continue to consult with Network Rail (both before and after formal submission of plans under paragraph 104(1) in order to identify all potential causes of EMI and the measures required to eliminate them;
- (b) Network Rail must without unreasonable delay make available to the undertaker all information in the possession of Network Rail reasonably requested by the undertaker in respect of Network Rail’s apparatus identified pursuant to sub-paragraph 109(4)(a); and
- (c) Network Rail must allow the undertaker reasonable facilities for the inspection of Network Rail’s apparatus identified pursuant to sub-paragraph 109(4)(a).
- (5) In any case where it is established that EMI can only reasonably be prevented by modifications to Network Rail’s apparatus, Network Rail must not withhold its consent unreasonably to modifications of Network Rail’s apparatus, but the means of prevention and the method of their execution must be selected in the reasonable discretion of Network Rail, and in relation to such modifications paragraph 104(1) has effect subject to the sub-paragraph.
- (6) Prior to the commencement of operation of the authorised development the undertaker shall test the use of the authorised development in a manner that shall first have been agreed with Network Rail (such agreement not to be unreasonably withheld or delayed), and if, notwithstanding any measures adopted pursuant to sub-paragraph 109(3), the testing of the authorised development causes EMI then the undertaker must immediately upon receipt of notification by Network Rail of such EMI either in writing or communicated orally (such oral communication to be confirmed in writing as soon as reasonably practicable after it has been issued) forthwith cease to use (or procure the cessation of use of) the undertaker’s apparatus causing such EMI until all measures necessary have been taken to remedy such EMI by way of modification to the source of such EMI or (in the circumstances, and subject to the consent, specified in sub-paragraph 109(5) to Network Rail’s apparatus.
- (7) In the event of EMI having occurred—
- (a) the undertaker must afford reasonable facilities to Network Rail for access to the undertaker’s apparatus in the investigation of such EMI;
- (b) Network Rail must afford reasonable facilities to the undertaker for access to Network Rail’s apparatus in the investigation of such EMI;
- (c) Network Rail must without unreasonable delay make available to the undertaker any additional material information in its possession reasonably requested by the undertaker in respect of Network Rail’s apparatus or such EMI; and
- (d) the undertaker shall not allow regular revenue earning operations of the authorised development in a manner that has caused or will cause EMI until measures have been taken in accordance with this paragraph to prevent such levels of EMI occurring.
- (8) Where Network Rail approves modifications to Network Rail’s apparatus pursuant to sub- paragraphs 109(5) or 109(6)—
- (a) Network Rail must allow the undertaker reasonable facilities for the inspection of the relevant part of Network Rail’s apparatus; and
- (b) any modifications to Network Rail’s apparatus approved pursuant to those sub- paragraphs must be carried out and completed by the undertaker in accordance with paragraph 105.
- (9) To the extent that it would not otherwise do so, the indemnity in paragraph 113(1) applies to the costs and expenses reasonably incurred or losses suffered by Network Rail through the implementation of the provisions of this paragraph (including costs incurred in connection with the consideration of proposals, approval of plans, supervision and inspection of works and facilitating access to Network Rail’s apparatus) or in consequence of any EMI to which sub- paragraph 10(6) applies.
- (10) For the purpose of paragraph 108(a) any modifications to Network Rail’s apparatus under this paragraph shall be deemed to be protective works referred to in that paragraph.
- (11) In relation to any dispute arising under this paragraph the reference in article 45 (arbitration) to the Secretary of State shall be read as a reference to the Institution of Engineering and Technology.
110
If at any time after the completion of a specified work or a protective work, not being a work vested in Network Rail, Network Rail gives notice to the undertaker informing it that the state of maintenance of any part of the specified work or a protective work appears to be such as adversely affects the operation of railway property, the undertaker must, on receipt of such notice, take such steps as may be reasonably necessary to put that specified work or a protective work in such state of maintenance as to not adversely affect railway property.
111
The undertaker must not provide any illumination or illuminated sign or signal on or in connection with a specified work in the vicinity of any railway belonging to Network Rail unless it has first consulted Network Rail and it must comply with Network Rail’s reasonable requirements for preventing confusion between such illumination or illuminated sign or signal and any railway signal or other light used for controlling, directing or securing the safety of traffic on the railway.
112
Any additional expenses that Network Rail may reasonably incur in altering, reconstructing or maintaining railway property under any powers existing at the date on which this Order is made by reason of the existence of a specified work must, provided that 56 days’ previous notice of the commencement of such alteration, reconstruction or maintenance has been given to the undertaker, be paid by the undertaker to Network Rail.
113
- (1) The undertaker must:
- (a) pay to Network Rail all reasonable costs, charges, damages and expenses not otherwise provided for in this Part which may be occasioned to or reasonably incurred by Network Rail—
- (i) by reason of the construction or maintenance of a specified work or its failure; or
- (ii) by reason of any act or omission of the undertaker or of any person in its employ or of its contractors or others whilst engaged on a specified work;
- (iii) in respect of costs incurred by Network Rail in complying with any railway operational procedures or obtaining any regulatory consents which procedures are required to be followed or consents obtained to facilitate the carrying out or operation of the authorised development; and
- (iv) indemnify Network Rail and keep Network Rail indemnified from and against all claims and demands arising out of or in connection with a specified work or any such failure, act or omission.
- (2) The fact that any act or thing may have been done by Network Rail on behalf of the undertaker or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under the engineer’s supervision does not (if it was done without negligence on the part of Network Rail or its employees, contractors or agents) excuse the undertaker from any liability under this Part.
- (3) Network Rail must give the undertaker reasonable written notice of any claim or demand made against Network Rail that the undertaker may be liable to pay under this Part and no settlement or compromise of such a claim or demand is to be made without the prior written consent of the undertaker.
- (4) The sums payable by the undertaker under sub-paragraph 14(1) if relevant include a sum equivalent to the relevant costs.
- (5) Subject to the terms of any agreement between Network Rail and a train operator regarding the timing or method of payment of the relevant costs in respect of that train operator, Network Rail must promptly pay to each train operator the amount of any sums which Network Rail receives under sub-paragraph 14(4) which relates to the relevant costs of that train operator.
- (6) The obligation under sub-paragraph 14(4) to pay Network Rail the relevant costs is, in the event of default, enforceable directly by any train operator concerned to the extent that such sums would be payable to that train operator under sub-paragraph 14(5).
- (7) In this paragraph—
- “relevant costs” means the costs, direct losses and indirect losses expenses (including loss of revenue) reasonably incurred by each train operator as a consequence of any specified work including but not limited to any restriction of the use of Network Rail’s railway network as a result of the construction, maintenance or failure of a specified work or any such act or omission as mentioned in sub-paragraph 14(1)
- “train operator” means any person who is authorised to act as the operator of a train by a licence under section 8 of the Railways Act 1993.
114
Network Rail must, on receipt of a request from the undertaker, provide the undertaker free of charge with written estimates of the costs, charges, expenses and other liabilities for which the undertaker is or will become liable under this Part (including the amount of the relevant costs mentioned in paragraph 113) and with such information as may enable the undertaker to assess the reasonableness of any such estimate or claim made or to be made under this Part (including any claim relating to those relevant costs).
115
In the assessment of any sums payable to Network Rail under this Part there must not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Network Rail if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by the undertaker under this Part or increasing the sums so payable.
116
The undertaker and Network Rail may, subject in the case of Network Rail to compliance with the terms of its network licence, enter into, and carry into effect, agreements for the transfer to the undertaker of—
- (a) any railway property shown on the works plan or the land plans and described in the book of reference;
- (b) any lands, works or other property held in connection with any such railway property; and
- (c) any rights and obligations (whether or not statutory) of Network Rail relating to any railway property or any lands, works or other property referred to in this paragraph.
117
Nothing in this Order, or in any enactment incorporated with or applied by this Order, prejudices or affects the operation of Part 1 of the Railways Act 1993.
118
The undertaker must give written notice to Network Rail where any application is proposed to be made by the undertaker for the Secretary of State’s consent under article 7 (benefit of the order) and any such notice must be given no later than 28 days before any such application is made and must describe or give (as appropriate)—
- (a) the nature of the application to be made;
- (b) the extent of the geographical area to which the application relates; and
- (c) the name and address of the person acting for the Secretary of State to whom the application is to be made.
119
The undertaker must, no later than 28 days from the date that the documents referred to in article 41 (certification of plans and documents, etc.) are certified by the Secretary of State, provide a set of those documents to Network Rail in an electronic format.
PART 9 — For the protection of Awel y Môr
120
The provisions of this Part apply for the protection of Awel y Môr unless otherwise agreed in writing between the undertaker and Awel y Môr.
121
In this Part—
- “access plots” means those parts of the Order limits that includes such parts of the Awel y Môr Order land comprising the land within plots 11-221, 11-222, 11-223, 11-224, 11-225, 11-226, 11-227, 11-231, 11-232, 11-234 and 11-235 shown on the land plans and described in the book of reference, which covers private road, verges, agricultural land, private road off Glascoed road, B5381 and public bridleway (BR 208/32) and access splay;
- “apparatus” means the cables, switchgear, structures or other infrastructure owned, occupied or maintained by Awel y Môr or its successor in title within the Awel y Môr Order Land;
- “Awel y Môr” means an undertaker with the benefit of all or part of the Awel y Môr Order for the time being;
- “Awel y Môr Onshore Works” means the proposed location within the Awel y Môr Order land for any electrical circuit(s), electrical substation infrastructure, construction compound(s) and other onshore infrastructure and works (whether temporary or permanent in nature) authorised by the Awel y Môr Order or by any planning permission intended to operate in conjunction with the Awel y Môr Order
- “Awel y Môr Order” means the development consent order made by the Secretary of State in relation to the Awel y Môr Offshore Wind Farm on 19th September 2023;
- “Awel y Môr Order land” means Order land as defined in the Awel y Môr Order;
- “construction” includes execution, placing, altering, replacing, reconstruction, relaying, maintenance, extensions, enlargement and removal; and “construct” and “constructed” must be construed accordingly;
- “Overlap area” means those parts of the Order limits that includes such parts of the Awel y Môr Order land comprising the land within plots 11-200, 11-201, 11-202, 11-203, 11-204, 11-205, 11-206, 11-207 shown on the land plans and described in the book of reference;
- “plans” includes sections, drawings, specifications, designs, design data, software, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of the Awel y Môr Order land;
- “specified works” means so much of any works or operations authorised by this Order (or authorised by any planning permission intended to operate in conjunction with this Order) as is—within the Overlap area;in, on, under, over or within 15 metres of the Awel y Môr Onshore Works or any apparatus; ormay in any way adversely affect any apparatus;
- “temporary works” so much of the specified works which are temporary works as set out within the Order; and
- “undertaker’s temporary access track” means that part of Work No. 27 falling within part of plot 11-229 and the whole of plots 11-229a, 11-230, 11-230a, 11-233, 11-233a, 11-233b, 11-234, 11-234a, 11-234b.
122
The consent of Awel y Môr under this Part is not required where the Awel y Môr Order has expired without the authorised development having been commenced pursuant to any requirement of Schedule 2 to the Awel y Môr Order.
123
Where conditions are included in any consent granted by Awel y Môr pursuant to this Part, the undertaker must comply with the conditions if it chooses to implement or rely on the consent, unless the conditions are waived or varied in writing by Awel y Môr.
124
The undertaker must not under the powers of this Order—
- (a) acquire, extinguish, suspend, override or interfere with any rights that Awel y Môr has in respect of any apparatus or the Awel y Môr Onshore Works;
- (b) acquire, extinguish, suspend or override any rights that Awel y Môr has in respect of the access plots pursuant to the Awel y Môr Order;
- (c) acquire the Awel y Môr Order land or acquire any new rights or impose restrictive covenants or exercise any powers of temporary use over or in relation to the Awel y Môr Order land, without the consent of Awel y Môr, which must not be unreasonably withheld or delayed but which may be made subject to reasonable conditions.
125
- (1) During the construction of the authorised development the undertaker will not use Work No. 30 for the period starting with the date of completion of construction of the undertaker’s temporary access track until the date of commencement of demobilisation of the undertaker’s temporary access track unless otherwise agreed.
- (2) At all other times during the construction of the authorised project the undertaker must coordinate its use of Work No. 30, including traffic movements, with Awel y Môr so as to prevent against restricting or impeding Awel y Môr’s use of the same.
- (3) At least 28 days prior to the submission to the local highway authority of the design of temporary construction access AC-R1 (as identified on the street works and access plan) pursuant to requirement 10, the undertaker will share the proposed access designs and the details of any associated traffic management measures with Awel y Môr and take into account any reasonable representations made by Awel y Môr.
126
- (1) The undertaker must not under the powers of this Order carry out any specified works without the consent of Awel y Môr, which must not be unreasonably withheld or delayed but which may be made subject to reasonable conditions and if Awel y Môr does not respond within 56 days then consent is deemed to be given.
- (2) Subject to obtaining consent pursuant to sub-paragraph (1) and not less than 56 days before beginning to construct any specified works, the undertaker must submit plans of the specified works to Awel y Môr and must submit such further particulars available to it that Awel y Môr may reasonably require.
- (3) Any specified works must be constructed without unreasonable delay in accordance with the plans approved in writing by Awel y Môr.
- (4) Any approval of Awel y Môr required under this paragraph may be made subject to such reasonable conditions as may be required for the protection or alteration of any apparatus within the Overlap area or the Awel y Môr Onshore Works or for securing access to any apparatus within the Overlap area or the Awel y Môr Onshore Works.
- (5) Where Awel y Môr requires any protective works to be carried out either by themselves or by the undertaker (whether of a temporary or permanent nature) such protective works must be carried out to Awel y Môr’s reasonable satisfaction.
- (6) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of any specified works, new plans instead of the plans previously submitted, and the provisions of this paragraph shall apply to and in respect of the new plans.
127
- (1) The undertaker must give to Awel y Môr written notice of completion not more than 14 days after the completion of any specified works.
- (2) The undertaker is not required to comply with paragraph 126 or sub-paragraph (1) of this paragraph in a case of emergency, but in that case it must give to Awel y Môr notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonable practicable subsequently and must comply with paragraph 126 in so far as is reasonably practicable in the circumstances.
128
The undertaker must at all reasonable times during construction of the specified works allow Awel y Môr and its servants and agents access to the specified works and all reasonable facilities for inspection of the specified works.
129
- (1) After the purpose of any temporary works has been accomplished, the undertaker must with all reasonable dispatch, or after a reasonable period of notice in writing from Awel y Môr requiring the undertaker to do so, remove the temporary works, in, on, under, over, or within the Overlap area.
- (2) If the undertaker fails to remove the temporary works within a reasonable period of receipt of a notice pursuant to sub-paragraph (1), Awel y Môr may remove the temporary works and may recover the reasonable costs of doing so from the undertaker.
130
If in consequence of the exercise of the powers conferred by this Order the access to any apparatus or the Awel y Môr Onshore Works is materially obstructed, the undertaker must provide such alternative means of access to such apparatus or the Awel y Môr Onshore Works as will enable Awel y Môr to maintain or use the apparatus or access the Awel y Môr Onshore Works no less effectively than was possible before the obstruction.
131
Subject to paragraph 130, the undertaker must not exercise the powers conferred by this Order to prevent or interfere with the access by Awel y Môr to the Awel y Môr Onshore Works.
132
To ensure its compliance with this Part, the undertaker must before carrying out any works or operations pursuant to this Order within the Overlap area request up-to-date written confirmation from Awel y Môr of the location of any apparatus or the Awel y Môr Onshore Works.
133
The undertaker and Awel y Môr must each act in good faith and use reasonable endeavours to co-operate with, and provide assistance to, each other as may be required to give effect to the provisions of this Part.
134
The undertaker must pay to Awel y Môr the reasonable expenses incurred by Awel y Môr in connection with the approval of plans, inspection of any specified works or the alteration or protection of any apparatus or the Awel y Môr Onshore Works.
135
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction, use, maintenance or failure of any specified works, any damage is caused to any apparatus or there is any interruption in any service provided, or in the supply of any goods, by Awel y Môr, or Awel y Môr becomes liable to pay any amount to any third party, the undertaker must—
- (a) bear and pay the cost reasonably incurred by Awel y Môr in making good such damage or restoring the service or supply; and
- (b) indemnify Awel y Môr for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from Awel y Môr, by reason or in consequence of any such damage or interruption or Awel y Môr becoming liable to any third party as aforesaid.
- (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of Awel y Môr, its officers, servants, contractors or agents.
- (3) Awel y Môr must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise shall be made, unless payment is required in connection with a statutory compensation scheme without first consulting the undertaker and considering its representations.
- (4) Awel y Môr must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph 135 applies. If requested to do so by the undertaker, Awel y Môr shall provide an explanation of how the claim has been minimised. The undertaker shall only be liable under this paragraph 135 for claims reasonably incurred by Awel y Môr.
- (5) The fact that any work or thing has been executed or done with the consent of Awel y Môr and in accordance with any conditions or restrictions prescribed by Awel y Môr or in accordance with any plans approved by Awel y Môr or to its satisfaction or in accordance with any directions or award of any arbitrator does not relieve the undertaker from any liability under this Part.
136
Any dispute arising between the undertaker and Awel y Môr under this Part must be determined by arbitration under article 45 (arbitration).
SCHEDULE 11 — Removal of hedgerows
PART 1 — Removal of hedgerows
In the County of Conwy:
| (1) Grid coordinates | (1) Grid coordinates | (2) Identifier as shown on the tree and hedgerow plan | (3) Grid coordinates | (3) Grid coordinates | (4) Identifier as shown on the tree and hedgerow plan |
|---|---|---|---|---|---|
| Easting | Northing | Easting | Northing | ||
| 291991 | 376813 | 3a | 291993 | 376811 | 3b |
| 292001 | 376812 | 5a | 292100 | 376799 | 5b |
| 292082 | 376596 | 6a | 291983 | 376611 | 6b |
| 292125 | 376997 | 9a | 292172 | 376942 | 9b |
| 292266 | 377188 | 15a | 292180 | 377202 | 15b |
| 292268 | 377188 | 16a | 292237 | 377068 | 16b |
| 292312 | 377294 | 17a | 292355 | 377233 | 17b |
| 292301 | 378096 | 18a | 292443 | 378080 | 18b |
| 292320 | 376180 | 21a | 292290 | 376168 | 21b |
| 292381 | 377202 | 23a | 292415 | 376930 | 23b |
| 292396 | 376033 | 25a | 292403 | 376033 | 25b |
| 292408 | 376034 | 26a | 292453 | 375838 | 26b |
| 292421 | 376034 | 28a | 292491 | 376048 | 28b |
| 292442 | 378080 | 29a | 292305 | 378077 | 29b |
| 292502 | 376010 | 31a | 292418 | 376034 | 31b |
| 292535 | 375503 | 34a | 292545 | 375508 | 34b |
| 292545 | 375589 | 35a | 292535 | 375600 | 35b |
| 292575 | 375803 | 36a | 292467 | 375817 | 36b |
| 292620 | 375692 | 37a | 292509 | 375698 | 37b |
| 292668 | 375580 | 38a | 292631 | 375667 | 38b |
| 292685 | 375544 | 39a | 292583 | 375526 | 39b |
| 292763 | 375251 | 40a | 292830 | 375328 | 40b |
| 293067 | 374768 | 47a | 292997 | 374724 | 47b |
| 293124 | 374531 | 48a | 293124 | 374533 | 48b |
| 293308 | 374499 | 50a | 293287 | 374475 | 50b |
| 293312 | 373990 | 51a | 293387 | 373856 | 51b |
| 293454 | 373956 | 55a | 293497 | 373938 | 55b |
| 293493 | 374145 | 56a | 293343 | 374053 | 56b |
| 293497 | 373938 | 57a | 293518 | 374080 | 57b |
| 293497 | 373938 | 58a | 293638 | 374303 | 58b |
| 293637 | 374306 | 61a | 293635 | 374304 | 61b |
| 293640 | 374322 | 62a | 293637 | 374306 | 62b |
| 293991 | 373928 | 68a | 294087 | 373917 | 68b |
| 294087 | 373911 | 70a | 294118 | 373790 | 70b |
| 294265 | 373766 | 74a | 294316 | 373656 | 74b |
| 294441 | 373489 | 75a | 294464 | 373571 | 75b |
| 294462 | 373567 | 76a | 294487 | 373576 | 76b |
| 294672 | 373503 | 77a | 294690 | 373615 | 77b |
| 294826 | 373694 | 78a | 294901 | 373646 | 78b |
| 295002 | 373720 | 79a | 295005 | 373784 | 79b |
| 295351 | 373915 | 81a | 295210 | 373842 | 81b |
| 295639 | 373924 | 92a | 295607 | 373710 | 92b |
| 296112 | 373742 | 103a | 296091 | 373681 | 103b |
| 296323 | 373772 | 104a | 296363 | 373870 | 104b |
| 296406 | 373863 | 107a | 296433 | 373912 | 107b |
| 296523 | 373836 | 112a | 296558 | 373927 | 112b |
| 296558 | 373929 | 114a | 296570 | 373960 | 114b |
| 296580 | 374000 | 117a | 296585 | 373998 | 117b |
| 296648 | 373991 | 118a | 296710 | 373977 | 118b |
| 296623 | 374101 | 122a | 296628 | 374099 | 122b |
| 296570 | 373960 | 124a | 296559 | 373929 | 124b |
| 296720 | 373910 | 128a | 296726 | 374013 | 128b |
| 297028 | 374154 | 135a | 297061 | 374076 | 135b |
| 297194 | 374220 | 137a | 297177 | 374242 | 137b |
| 297369 | 374054 | 138a | 297351 | 373985 | 138b |
| 297369 | 374057 | 139a | 297192 | 374206 | 139b |
| 297380 | 374178 | 140a | 297199 | 374236 | 140b |
| 297464 | 374053 | 142a | 297369 | 374054 | 142b |
| 297463 | 374146 | 143a | 297403 | 374172 | 143b |
| 297513 | 373742 | 146a | 297506 | 373958 | 146b |
| 297513 | 373739 | 147a | 297513 | 373739 | 147b |
| 297536 | 374060 | 151a | 297496 | 373958 | 151b |
| 297547 | 374060 | 152a | 297506 | 373958 | 152b |
| 297766 | 373905 | 153a | 297795 | 374024 | 153b |
| 297833 | 373837 | 154a | 297945 | 373797 | 154b |
In the County of Denbighshire:
| (1) Grid coordinates | (1) Grid coordinates | (2) Identifier as shown on the tree and hedgerow plan | (3) Grid coordinates | (3) Grid coordinates | (4) Identifier as shown on the tree and hedgerow plan |
|---|---|---|---|---|---|
| Easting | Northing | Easting | Northing | ||
| 298416 | 373607 | 160a | 298409 | 373610 | 160b |
| 298420 | 373603 | 161a | 298638 | 373560 | 161b |
| 298421 | 373603 | 162a | 298383 | 373526 | 162b |
| 298465 | 373742 | 163a | 298469 | 373740 | 163b |
| 298468 | 373732 | 164a | 298419 | 373613 | 164b |
| 298469 | 373740 | 165a | 298469 | 373740 | 165b |
| 298638 | 373560 | 167a | 298684 | 373448 | 167b |
| 298638 | 373561 | 168a | 298683 | 373703 | 168b |
| 298684 | 373714 | 169a | 298698 | 373740 | 169b |
| 298859 | 373918 | 171a | 298936 | 373909 | 171b |
| 298912 | 373765 | 174a | 298891 | 373779 | 174b |
| 298918 | 373764 | 176a | 298918 | 373764 | 176b |
| 298996 | 373913 | 177a | 298912 | 373765 | 177b |
| 299207 | 373262 | 180a | 299308 | 373266 | 180b |
| 299230 | 373939 | 181a | 299278 | 373945 | 181b |
| 299246 | 373282 | 182a | 299239 | 373360 | 182b |
| 299302 | 373948 | 183a | 299302 | 373948 | 183b |
| 299308 | 373316 | 185a | 299314 | 373280 | 185b |
| 299332 | 374020 | 188a | 299314 | 374025 | 188b |
| 299426 | 373979 | 190a | 299407 | 373972 | 190b |
| 299592 | 373130 | 191a | 299468 | 373094 | 191b |
| 299712 | 372909 | 192a | 299756 | 372988 | 192b |
| 300273 | 372619 | 197a | 300251 | 372635 | 197b |
| 300312 | 372839 | 203a | 300504 | 372999 | 203b |
| 300334 | 372701 | 205a | 300279 | 372724 | 205b |
| 300419 | 372875 | 207a | 300432 | 372896 | 207b |
| 300422 | 372951 | 208a | 300413 | 372974 | 208b |
| 300528 | 372926 | 211a | 300504 | 372998 | 211b |
| 300736 | 373132 | 218a | 300690 | 373053 | 218b |
| 300837 | 372995 | 219a | 300915 | 373061 | 219b |
| 300919 | 373061 | 220a | 300954 | 373041 | 220b |
| 300954 | 373041 | 221a | 301021 | 372995 | 221b |
| 301044 | 373188 | 222a | 300922 | 373072 | 222b |
| 301182 | 373151 | 229a | 301148 | 373117 | 229b |
| 301182 | 373151 | 230a | 301127 | 373214 | 230b |
| 301268 | 373608 | 237a | 301197 | 373484 | 237b |
| 301276 | 373416 | 238a | 301309 | 373454 | 238b |
| 301323 | 373447 | 240a | 301463 | 373327 | 240b |
| 301392 | 372847 | 241a | 301341 | 372784 | 241b |
| 301434 | 372731 | 244a | 301407 | 372717 | 244b |
| 301447 | 373195 | 245a | 301407 | 373126 | 245b |
| 301460 | 372992 | 246a | 301547 | 373135 | 246b |
| 301461 | 373320 | 247a | 301423 | 373279 | 247b |
| 301471 | 372953 | 248a | 301392 | 372847 | 248b |
| 301480 | 372754 | 249a | 301440 | 372731 | 249b |
| 301522 | 372781 | 254a | 301579 | 372836 | 254b |
| 301564 | 373595 | 258a | 301394 | 373383 | 258b |
| 301578 | 372844 | 259a | 301561 | 372852 | 259b |
| 301579 | 372836 | 260a | 301601 | 372822 | 260b |
| 301608 | 372837 | 261a | 301878 | 373106 | 261b |
| 301666 | 373230 | 262a | 301571 | 373121 | 262b |
| 301690 | 373032 | 263a | 301551 | 372868 | 263b |
| 301731 | 372830 | 264a | 301631 | 372878 | 264b |
| 301854 | 372942 | 266a | 301756 | 372811 | 266b |
| 301860 | 372790 | 267a | 301859 | 372789 | 267b |
| 301860 | 372790 | 268a | 301783 | 372839 | 268b |
| 301880 | 372802 | 269a | 301860 | 372790 | 269b |
| 301884 | 372978 | 270a | 301964 | 372912 | 270b |
| 301945 | 372856 | 272a | 301916 | 372823 | 272b |
| 301956 | 372779 | 273a | 302045 | 372720 | 273b |
| 302003 | 373723 | 275a | 302011 | 373722 | 275b |
| 302009 | 373717 | 276a | 302002 | 373717 | 276b |
| 302045 | 373780 | 277a | 302052 | 373778 | 277b |
| 302074 | 373909 | 278a | 302032 | 373912 | 278b |
| 302107 | 373121 | 279a | 302230 | 373019 | 279b |
| 302144 | 373172 | 280a | 302269 | 373121 | 280b |
| 302170 | 373896 | 281a | 302115 | 373890 | 281b |
PART 2 — Removal of important hedgerows
In the County of Conwy:
| (1) Grid coordinates | (1) Grid coordinates | (2) Identifier as shown on the tree and hedgerow plan | (3) Grid coordinates | (3) Grid coordinates | (4) Identifier as shown on the tree and hedgerow plan |
|---|---|---|---|---|---|
| Easting | Northing | Easting | Easting | Northing | |
| 291968 | 376950 | 1a | 291965 | 376945 | 1b |
| 291975 | 376954 | 2a | 291959 | 376910 | 2b |
| 292104 | 376315 | 7a | 292181 | 376379 | 7b |
| 292160 | 376371 | 10a | 292100 | 376319 | 10b |
| 292160 | 376371 | 11a | 292128 | 376443 | 11b |
| 292179 | 376382 | 13a | 292163 | 376371 | 13b |
| 292308 | 378065 | 20a | 292468 | 378063 | 20b |
| 292452 | 377497 | 30a | 292494 | 377340 | 30b |
| 292511 | 375693 | 33a | 292628 | 375685 | 33b |
| 292883 | 374914 | 42a | 292929 | 374915 | 42b |
| 292910 | 374966 | 43a | 292970 | 375082 | 43b |
| 292930 | 374911 | 44a | 293010 | 374812 | 44b |
| 293006 | 374932 | 45a | 292930 | 374912 | 45b |
| 292899 | 374921 | 49a | 293008 | 374942 | 49b |
| 293434 | 373879 | 53a | 293586 | 373952 | 53b |
| 293588 | 373951 | 60a | 293606 | 373742 | 60b |
| 293882 | 373875 | 65a | 293942 | 373830 | 65b |
| 293944 | 373830 | 66a | 293959 | 373914 | 66b |
| 293944 | 373829 | 67a | 294191 | 373675 | 67b |
| 294020 | 373750 | 69a | 294190 | 373822 | 69b |
| 294219 | 373794 | 71a | 294192 | 373680 | 71b |
| 294262 | 373609 | 73a | 294347 | 373663 | 73b |
| 295117 | 373790 | 80a | 295236 | 373870 | 80b |
| 295372 | 373937 | 82a | 295431 | 373843 | 82b |
| 295380 | 373945 | 84a | 295436 | 373851 | 84b |
| 295590 | 373721 | 89a | 295650 | 373652 | 89b |
| 295612 | 374124 | 90a | 295475 | 374045 | 90b |
| 295702 | 373985 | 93a | 295636 | 373924 | 93b |
| 295786 | 374174 | 94a | 295612 | 374124 | 94b |
| 295817 | 373727 | 96a | 295909 | 373737 | 96b |
| 295921 | 374217 | 97a | 295788 | 374171 | 97b |
| 295993 | 373731 | 99a | 296092 | 373683 | 99b |
| 295995 | 373765 | 100a | 295991 | 373734 | 100b |
| 296001 | 373719 | 101a | 295984 | 373665 | 101b |
| 296091 | 374282 | 102a | 295922 | 374219 | 102b |
| 296359 | 373888 | 105a | 296362 | 373880 | 105b |
| 296472 | 373819 | 108a | 296373 | 373893 | 108b |
| 296453 | 373813 | 110a | 296362 | 373880 | 110b |
| 296558 | 373928 | 113a | 296663 | 373890 | 113b |
| 296608 | 374083 | 120a | 296613 | 374080 | 120b |
| 296665 | 374216 | 127a | 296655 | 374217 | 127b |
| 296838 | 373923 | 131a | 296825 | 374022 | 131b |
| 296831 | 374024 | 132a | 296842 | 373923 | 132b |
| 296986 | 374050 | 134a | 296850 | 374039 | 134b |
| 297095 | 374143 | 136a | 297126 | 374059 | 136b |
In the County of Denbighshire:
| (1) Grid coordinates | (1) Grid coordinates | (2) Identifier as shown on the tree and hedgerow plan | (3) Grid coordinates | (3) Grid coordinates | (4) Identifier as shown on the tree and hedgerow plan |
|---|---|---|---|---|---|
| Easting | Northing | Easting | Easting | Northing | |
| 298091 | 373653 | 158a | 298047 | 373576 | 158b |
| 298148 | 373545 | 159a | 298172 | 373643 | 159b |
| 298852 | 373413 | 170a | 298881 | 373508 | 170b |
| 298886 | 373507 | 173a | 298858 | 373411 | 173b |
| 299006 | 373917 | 178a | 299091 | 373914 | 178b |
| 299193 | 373271 | 179a | 299247 | 373275 | 179b |
| 299305 | 373275 | 184a | 299247 | 373275 | 184b |
| 299314 | 373260 | 186a | 299323 | 373194 | 186b |
| 299317 | 373277 | 187a | 299387 | 373278 | 187b |
| 299314 | 373267 | 189a | 299395 | 373275 | 189b |
| 300122 | 372712 | 195a | 300251 | 372636 | 195b |
| 300252 | 372636 | 196a | 300279 | 372724 | 196b |
| 300279 | 372847 | 198a | 300311 | 372829 | 198b |
| 300279 | 372724 | 199a | 300311 | 372829 | 199b |
| 300283 | 372854 | 200a | 300311 | 372837 | 200b |
| 300311 | 372837 | 201a | 300364 | 372794 | 201b |
| 300311 | 372829 | 202a | 300366 | 372784 | 202b |
| 300365 | 372794 | 206a | 300364 | 372794 | 206b |
| 300534 | 373171 | 212a | 300519 | 373161 | 212b |
| 300580 | 373211 | 214a | 300737 | 373132 | 214b |
| 300628 | 373324 | 215a | 300567 | 373211 | 215b |
| 300657 | 373359 | 217a | 300582 | 373221 | 217b |
| 301246 | 373196 | 235a | 301182 | 373151 | 235b |
| 301254 | 373193 | 236a | 301158 | 373117 | 236b |
| 301309 | 373454 | 239a | 301376 | 373609 | 239b |
| 301393 | 372850 | 242a | 301522 | 372781 | 242b |
| 301427 | 373217 | 243a | 301505 | 373360 | 243b |
| 301493 | 372641 | 251a | 301436 | 372728 | 251b |
| 301493 | 372640 | 252a | 301529 | 372686 | 252b |
| 301529 | 372691 | 255a | 301500 | 372763 | 255b |
| 301547 | 373135 | 257a | 301453 | 373187 | 257b |
| 301813 | 373121 | 265a | 301695 | 373040 | 265b |
| 301916 | 372823 | 271a | 301950 | 372787 | 271b |
| 301956 | 372779 | 274a | 302109 | 372982 | 274b |
| 302200 | 372940 | 282a | 302055 | 373021 | 282b |
PART 3 — Trees subject to tree preservation orders
| (1) Tree preservation order reference | (2) Type of tree | (3) Work to be carried out | (4) Relevant part of the authorised project |
|---|---|---|---|
| Conwy County Borough Council Tree preservation order No. 4 dated 4 November 1949 relating to Part of Gwrych Castle Estate and Adjoining Land | Trees within the area identified as W4 in the First Schedule of the tree preservation order and as shown on Sheet 2 of the tree and hedgerow plan | Removal, felling or lopping of trees to facilitate the construction of access AC-B1 identified on the street works and access to works plan and otherwise to facilitate the authorised project | Work No. 9 sub-section (c) and Work No. 10 sub-section (e) |
SCHEDULE 12 — Approval of matters specified in requirements
Interpretation
1
In this Schedule “application” means an application for any consent, agreement or approval required by a requirement whether or not the application seeks to discharge a requirement in whole or in part.
2
In this schedule “discharging authority” means—
- (a) any body responsible for giving any consent, agreement or approval required by a requirement included in Schedule 2, or for giving any consent, agreement or approval further to any document referred to in any such requirement; or
- (b) the local authority in the exercise of its functions set out in sections 60 (control of noise on construction sites) and 61 (prior consent for work on construction sites) of the Control of Pollution Act 1974 subsequently referred to as “the 1974 Act”(a).
Applications made under requirements
3
- (1) Where an application has been made to the relevant discharging authority for any agreement or approval required pursuant to a requirement included in this Order, the relevant discharging authority must give notice to the undertaker of their decision, including the reasons, on the application, within a period of 13 weeks beginning with—
- (a) the day immediately following that on which the application is received by the relevant discharging authority; or
- (b) where further information is requested under paragraph 4 the working day immediately following that on which the further information has been supplied by the undertaker, or such longer period as may be agreed in writing by the undertaker and the relevant planning discharging authority.
- (c) and where consent, agreement or approval is refused or granted subject to conditions the discharging authority must provide its reasons for that decision with the notice of the decision.
Further information
4
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.