The Mona Offshore Wind Farm Order 2025

Type Statutory-Instrument
Publication 2025-07-04
Last updated 2025-10-24
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API

With respect to any requirement which requires the authorised project to be carried out in accordance with the details approved under this Schedule, the approved details are taken to include any amendments that may subsequently be approved or agreed by the relevant discharging authority.

SCHEDULE 3 — Streets subject to street works

In the County of Conwy:

(1) Street (2) Extent as shown on the street works access plan
A547, Abergele Road Between points 1 and 2, as shown on Sheet 2 of the street works and access to works plan
Public highway unclassified road off Rhyd-Y-Foel Road Between points 3 and 4, as shown on Sheet 3 of the street works and access to works plan
Public highway unclassified road off Rhyd-Y-Foel Road Between points 5 and 6, as shown on Sheet 4 of the street works and access to works plan
Public highway unclassified road connecting Rhyd-Y-Foel Road and Ffordd Abergele Between points 7 and 8, as shown on Sheet 4 of the street works and access to works plan
Ffordd Abergele Between points 9 and 10, as shown on Sheet 5 of the street works and access to works plan
A548 Between points 11 and 12, as shown on Sheet 6 of the street works and access to works plan
B5381 Glascoed Road Between points 13 and 14, as shown on Sheet 6 of the street works and access to works plan
Public highway unclassified road north of B5381 Glascoed Road Between points 15 and 16, as shown on Sheet 6 of the street works and access to works plan
Public highway unclassified road connecting the B5381 Glascoed Road and A548 Between points 17 and 18, as shown on Sheet 7 of the street works and access to works plan
Public highway unclassified road south of the B5381 Glascoed Road Between points 19 and 20, as shown on Sheet 7 of the street works and access to works plan
Public highway unclassified road south of the B5381 Glascoed Road Between points 21 and 22, as shown on Sheet 8 of the street works and access to works plan
B5381 Glascoed Road Between points 23 and 24, as shown on Sheet 8 of the street works and access to works plan
Public highway unclassified road south of the B5381 Glascoed Road Between points 25 and 26, as shown on Sheet 8 of the street works and access to works plan

In the County of Denbighshire:

(1) Street (2) Extent as shown on the street works access plan
Public highway unclassified road south of the B5381 Glascoed Road Between points 27 and 28, as shown on Sheet 9 of the street works and access to works plan
B5381 Glascoed Road Between points 29 and 30, as shown on Sheet 9 of the street works and access to works plan
Public highway unclassified road west of Cae Onnen Between points 31 and 32, as shown on Sheet 9 of the street works and access to works plan
B5381 Glascoed Road and Public highway unclassified road south Between points 33 and 34, as shown on Sheet 9 of the street works and access to works plan
Public highway unclassified road south of the B5381 Glascoed Road towards Cae Onnen Between points 34 and 35, as shown on Sheet 9 of the street works and access to works plan
B5381 / Glascoed Road Between points 36 and 37, as shown on Sheet 9 of the street works and access to works plan
Public highway unclassified road south-east of Cae Onnen Between points 38 and 39, as shown on Sheet 10 of the street works and access to works plan
Public highway unclassified road south of B5381 Glascoed Road, south-west of Bodelwyddan Substation Between points 40 and 41, as shown on Sheet 11 of the street works and access to works plan
B5381 Glascoed Road Between points 42 and 43, as shown on Sheet 11 of the street works and access to works plan

SCHEDULE 4 — Streets to be temporarily closed or restricted

In the County of Conwy:

(1) Street to be temporarily closed or restricted (2) Extent of temporary closure or restriction as shown on the street works and access to works plan
A547, Abergele Road Between points 1 and 2, as shown on Sheet 2 of the street works and access to works plan
Public highway unclassified road off Rhyd-Y-Foel Road Between points 3 and 4, as shown on Sheet 3 of the street works and access to works plan
Public highway unclassified road off Rhyd-Y-Foel Road Between points 5 and 6, as shown on Sheet 4 of the street works and access to works plan
Public highway unclassified road connecting Rhyd-Y-Foel Road and Ffordd Abergele Between points 7 and 8, as shown on Sheet 4 of the street works and access to works plan
Ffordd Abergele Between points 9 and 10, as shown on Sheet 5 of the street works and access to works plan
A548 Between points 11 and 12, as shown on Sheet 6 of the street works and access to works plan
B5381 Glascoed Road Between points 13 and 14, as shown on Sheet 6 of the street works and access to works plan
Public highway unclassified road north of B5381 Glascoed Road Between points 15 and 16, as shown on Sheet 6 of the street works and access to works plan
Public highway unclassified road south of the B5381 Glascoed Road Between points 19 and 20, as shown on Sheet 7 of the street works and access to works plan
Public highway unclassified road south of the B5381 Glascoed Between points 21 and 22, as shown on Sheet 8 of the street works and access to works plan

In the County of Denbighshire:

(1) Street to be temporarily closed or restricted (2) Extent of temporary closure or restriction as shown on the street works and access to works plan
Public highway unclassified road south of the B5381 Glascoed Road Between points 27 and 28, as shown on Sheet 9 of the street works and access to works plan
B5381 Glascoed Road Between points 29 and 30, as shown on Sheet 9 of the street works and access to works plan
Public highway unclassified road west of Cae Onnen Between points 31 and 32, as shown on Sheet 9 of the street works and access to works plan
B5381 Glascoed Road and Public highway unclassified road south Between points 33 and 34, as shown on Sheet 9 of the street works and access to works plan
Public highway unclassified road south of the B5381 Glascoed Road towards Cae Onnen Between points 34 and 35, as shown on Sheet 9 of the street works and access to works plan
B5381 / Glascoed Road Between points 36 and 37, as shown on Sheet 9 of the street works and access to works plan
Public highway unclassified road south-east of Cae Onnen Between points 38 and 39, as shown on Sheet 10 of the street works and access to works plan
Public highway unclassified road south of B5381 Glascoed Road, south-west of Bodelwyddan Substation Between points 40 and 41, as shown on Sheet 11 of the street works and access to works plan
B5381 Glascoed Road Between points 42 and 43, as shown on Sheet 11 of the street works and access to works plan

SCHEDULE 5 — Public rights of way to be temporarily closed or restricted

In the County of Conwy:

(1) Public right of way to be temporarily closed or restricted (2) Extent as shown on the public rights of way plan
Llanddulas & Rhyd y Foel 14 Footpath Between points 1a and 1b as shown on sheet 3 and 4 of the temporary closure of public rights of way plan
Betws yn Rhos 43 Footpath Between points 2a and 2b as shown on sheet 4 of the temporary closure of public rights of way plan
Betws yn Rhos 44 Footpath Between points 3a and 3b as shown on sheet 4 and 5 of the temporary closure of public rights of way plan
Betws yn Rhos 48 Footpath Between points 4a and 4b as shown on sheet 5 of the temporary closure of public rights of way plan
Llanfair TH 12 Footpath Between points 5a and 5b as shown on sheet 6 of the temporary closure of public rights of way plan
Llanfair TH 15 Footpath Between points 6a and 6b as shown on sheets 6 and 7 of the temporary closure of public rights of way plan
Llanfair TH 16 Bridleway Between points 7a and 7b as shown on sheet 7 of the temporary closure of public rights of way plan
Llanfair TH 19 Bridleway Between points 8a and 8b as shown on sheet 7 of the temporary closure of public rights of way plan

In the County of Denbighshire:

(1) Public right of way to be temporarily closed or restricted (2) Extent as shown on the public rights of way plan
Footpath DE/105/99 Between points 9a and 9b as shown on sheet 8 of the temporary closure of public rights of way plan
Footpath DE/105/5 Between points 10a and 10b as shown on sheets 9 and 10 of the temporary closure of public rights of way plan
Footpath DE/105/6 Between points 11a and 11b as shown on sheets 10 and 11 of the temporary closure of public rights of way plan
Bridleway DE 208/32 Between points 12a and 12b as shown on sheet 11 of the temporary closure of public rights of way plan

SCHEDULE 6 — Access to works

In the County of Conwy:

(1) Reference as shown on the street works and access to works plan (2) Description of new accesses and crossings
AC-A1 From the public highway Sea Road as shown on sheet 1 of the street works and access to works plan
AC-B1 From the public highway A457 Abergele Road as shown on sheet 2 of the street works and access to works plan
AC-C1 Crossing point over and from public highway unclassified road as shown on sheet 3 of the street works and access to works plan
AC-C2 Crossing point over and from public highway unclassified road shown on sheet 3 of the street works and access to works plan
AC-D1 Crossing point over and from public highway unclassified road as shown on sheet 4 of the street works and access to works plan
AC-D2 Crossing point over and from public highway unclassified road as shown on sheet 4 of the street works and access to works plan
AC-E1 Crossing point over and from public highway unclassified road as shown on sheet 4 of the street works and access to works plan
AC-E2 Crossing point over and from public highway unclassified road as shown on sheet 4 of the street works and access to works plan
AC-F1 Crossing point over and from Ffordd Abergele as shown on sheet 5 of the street works and access to works plan
AC-F2 Crossing point over and from Fford Abergele as shown on sheet 5 of the street works and access to works plan
AC-G1 From the public highway B5381 Glascoed Road as shown on sheet 6 of the street works and access to works plan
AC-G2 Crossing point over and from the public highway B5381 Glascoed Road as shown on sheet 6 of the street works and access to works plan
AC-H1 From the public highway A548 as shown on sheet 6 of the street works and access to works plan.
AC-I1 Crossing point over and from public highway unclassified road as shown on sheet 7 of the street works and access to works plan
AC-I2 Crossing point over and from public highway unclassified road as shown on sheet 7 of the street works and access to works plan
AC-J1 Crossing point over and from public highway unclassified road as shown on sheet 8 of the street works and access to works plan
AC-J2 Crossing point over and from public highway unclassified road as shown on sheet 8 of the street works and access to works plan
AC-K1 From the public highway B5381 Glascoed Road as shown on sheet 8 of the street works and access to works plan
AC-L1 Crossing point over and from public highway unclassified road as shown on sheet 8 of the street works and access to works plan
AC-L2 Crossing point over and from public highway unclassified road as shown on sheet 8 of the street works and access to works plan

In the County of Denbighshire:

(1) Reference as shown on the street works and access to works plan (2) Description of new accesses and crossings
AC-M1 Crossing point over and from public highway unclassified road as shown on sheet 9 of the street works and access to works plan
AC-M2 Crossing point over and from public highway unclassified road as shown on sheet 9 of the street works and access to works plan
AC-N1 From the public highway B5381 Glascoed Road as shown on sheet 9 of the street works and access to works plan
AC-O1 Crossing point over and from public highway unclassified road as shown on sheet 9 of the street works and access to works plan
AC-O2 Crossing point over and from public highway unclassified road as shown on sheet 9 of the street works and access to works plan
AC-P1 Crossing point over and from public highway unclassified road as shown on sheet 10 of the street works and access to works plan
AC-P2 Crossing point over and from public highway unclassified road as shown on sheet 10 of the street works and access to works plan
AC-Q1 Crossing point over and from public highway unclassified road as shown on sheet 11 of the street works and access to works plan
AC-Q2 Crossing point over and from public highway unclassified road as shown on sheet 11 of the street works and access to works plan
AC-R1 From the public highway B5381 Glascoed Road as shown on sheet 11 of the street works and access to works plan
AC-S1 From the public highway B5381 Glascoed Road as shown on sheet 11 of the street works and access to works plan
AC-T1 From public highway unclassified road as shown on sheet 11 of the street works and access to works plan

SCHEDULE 7 — Land of which only temporary possession may be taken

In the County of Conwy:

(1) Number of plot shown onland plan (onshore) (2) Purpose for which temporary possession may be taken (3) Relevant part of authorised project
01-001, 01-002 Access to Work No. 3 during construction Work Nos. 3 and 4
01-003, 01-004, Temporary construction compound for vehicle parking, a circulation area and a laydown area of up to 800 square metres including fencing together with access to Work No. 4 during construction Work Nos. 4 and 7
01-005, 01-006, 01-007, 01-008, 01-009, 01-010, 01-011 Access during construction Work Nos. 5, 7 and 8
02-013, 02-013a, 02-014, 02-015, 02-016, 02-017, 02-018, 02-019, 02-020 Access to Work No. 8 during construction Work Nos. 6 and 8
02-030 Access to Work No. 10 during construction including works to the public highway and visibility splays Work Nos. 9 and 10
03-052, 03-055, 03-057, 03-058, 04-068, 04-069, 04-071, 04-076 Access to Work No. 12 during construction Work Nos. 12 and 12a
05-094, 05-095, 06-099, 06-102, 06-104 Temporary construction compounds and laydown areas with a total maximum area of 37,500 square metres and access to Work Nos. 12 and 14 during construction including works to the public highway and visibility splays Work Nos. 12, 13 and 14

In the County of Denbighshire:

(1) Number of plot shown on land plan (onshore) (2) Purpose for which temporary possession may be taken (3) Relevant part of authorised project
09-160, 09-162, 09-163, 09-164, 09-165 Temporary construction compound and laydown area of up to 22,500 square metres and access to Work No. 17 during construction including works to the public highway and visibility splays Work Nos. 17 and 18
09-166, 09-167 Temporary works to the public highway including visibility splays Work No. 19
11-197a, 11-223b, 11-228, 11-229a, 11-230, 11-230a, 11-233, 11-233a, 11-233b, 11-234, 1-234a, 11-234b, 11-236 Access during construction including works to the public highway and visibility splays Work Nos. 22, 22a, 27, 28, 29 and 30
11-197b Onshore site preparation works Work No. 27
11-228, 11-229 Temporary construction compound and laydown area of up to 7,100 square metres Work Nos. 22, 22a, 27, 28, 29 and 30
11-221a Temporary construction area to facilitate the construction of permanent access Work Nos. 27 and 29
11-215, 11-218, 11-218a Temporary landscaping, ecological and environmental works in relation to the substation construction Work Nos. 22, 22a and 31

SCHEDULE 8 — Land in which only new rights etc. may be acquired

In the County of Conwy:

(1)Number of plot shown onland plan (onshore) (2)Purpose for which rights may be acquired
02-033; 03-037; 03-045; 03-047; 03-049; 03-050; 03-060; 03-062; 03-063; 04-067; 04-070; 04-074; 04-078; 05-080; 05-083; 05-084; 05-087; 05-088; 05-091; 05-093; 06-097; 06-100; 06-106a; 06-103; 06-105; 06-106; 06-108; 07-109; 07-111; 07-117; 07-120; 07-125; 07-127; 07-129; 07-133; 08-136; 08-146 Cable rights and restrictive covenants1.Cable rightsRights for the purposes of the construction, installation, operation, maintenance and decommissioning of the authorised project to—lay down, install, test, retain, adjust, alter, construct, operate, erect, use, maintain, repair, renew, upgrade, inspect, remove and replace the electricity cables (including the removal of materials including spoil) in, under, over and/or on the land, together with such telemetry and fibre-optic lines, ducting, jointing bays and other apparatus, protection measures, cable marker posts, chambers and manholes, manhole covers, cable clamping and other equipment which is ancillary to the purposes of transmitting electricity along such electricity cables (the “cables”), and in doing so, to use or resort to open cut trenching or trenchless installation techniques including (but not limited to) directional drilling;enter, be on, and break open and break up the surface of the land, restore and remain with or without plant, vehicles, machinery, apparatus and equipment which is ancillary to the purposes of transmitting electricity along the cables;to benefit from continuous vertical and lateral support for the authorised project;pass and re-pass with or without vehicles, plant, machinery, apparatus, equipment and materials for the purposes of laying down, installing, adjusting, altering, constructing, using, maintaining, repairing, renewing, inspecting, removing, testing, upgrading and replacing the cables and connection into any adjacent cables and associated works, to take plant and equipment on to adjoining land;construct and install the cables and thereafter use the land for all necessary purposes for the construction, commissioning, testing, repair and maintenance of the cables in, on or under the land;place and use plant, machinery, structures and temporary structures within the land for the purposes of the installation, construction, maintenance, repairing, renewing, upgrading, inspecting, removal, testing and replacing of the cables and to erect temporary signage and provide measures for the benefit of public and personnel safety;erect fencing, gates, walls, barriers or other means of enclosure, and create secure working areas and compounds including trenchless installation technique compounds and working areas;construct, lay down, use and remove temporary access roads including any necessary hard standing and other surface materials including (but not limited to) matting, aggregate, trackway, stone, tarmacadam, terram, temporary bridging, culverting or diversion of water courses and drains during any period during which construction, maintenance, repair or renewal is being carried out;effect access to the highway including creation of temporary visibility splays;make such investigations in or on the land as are required;fell, lop, cut or remove or coppice wood, uproot trees or hedges or shrubs which now or hereafter may be standing on the land or other land which would if not felled, lopped, cut or removed would obstruct or interfere with the installation and operation of the cables;remove and discharge water from the land, and to install, retain, use, maintain, inspect, alter, remove, refurbish, reconstruct, replace, protect and improve sewers, drains, pipes, ducts, mains, conduits, flues and to drain into and manage waterflows in any drains, watercourses and culverts, install, use, inspect, maintain, adjust, alter, renew, repair, test or cleanse drainage schemes on the land or reinstate any existing drainage scheme on the land;install, alter, re-lay, maintain, protect, adjust or remove pipes, cables or conduits or apparatus including but not limited to electricity poles, electricity pylons, electricity masts, overhead electricity lines, telecommunications cables and any ancillary equipment and apparatus, public and private drains, watercourses, sewers, ponds or culverts, service media (including the pipes, cables or conduits or apparatus of statutory undertakers);remove fences and structures within the land during any period in which construction, maintenance, repair or renewal is being carried out (subject to erection of any temporary stock-proof fencing as is reasonably required and the re-instatement or suitable replacement of the fences or structures following the exercise of the rights);store and stockpile materials (including excavated material);create boreholes and trial excavation pits for the purposes of intrusively surveying the land and monitoring the use of any trenchless installation technique, to keep in place and monitor the same through construction, maintenance, repair, replacement or decommissioning and reinstatement of the land;to excavate materials below ground level, including soils, and to store and re-use or dispose of the same, and in so excavating to undertake any works, including works of protection or removal of archaeological remains as may be required by any written scheme of investigation approved under this Order;lay out temporary paths and bridleways for public use as temporary diversions for public rights of way which are interfered with during any period in which construction, maintenance, repair, renewal or decommissioning is being carried out;to install, execute, implement, retain, repair, improve, renew, relocate, maintain and carry out mitigation, maintenance, and remediation works for environmental or ecological mitigation or enhancement works, including temporary works for noise alleviation measures and the installation of temporary barriers for the protection of fauna;carry out such works (together with associated fencing) required by a planning permission and/or consent now or to be granted over the land and/or in accordance with any necessary licences relating to protected species and/or wildlife;(in an emergency only when the cables are temporarily unusable) to lay down, install, use, maintain and inspect replacement underground cables, telephone signalling and fibre-optic cables and ancillary equipment, associated works and other conducting media together with conduits or pipes for containing the same in and under the land;to construct, use, maintain and improve a permanent means of access including visibility splays, and retain, maintain, straighten, widen, repair, alter, upgrade and use existing access routes for the purposes of accessing the land, adjoining land and the highway; anderect temporary bridges and supporting or protective structures for the purposes of access to adjoining land.2. Restrictive covenantsA restrictive covenant over the land for the benefit of the remainder of the Order land to:aprevent anything being done in or upon the land or any part thereof for the purpose of the erection of any buildings or construction, erection or works of any kind (including the foundations or footings thereto);bprevent anything being done by way of hard surfacing of the land with concrete of any kind or with any other material or surface whatsoever without the consent in writing of the undertaker (such consent not to be unreasonably withheld or delayed if the proposed surfacing would not cause damage to relevant part of the authorised project nor make it materially more difficult or expensive to maintain the authorised project);cto prevent anything to be done by way of excavation of any kind in the land or any activities which would alter, increase or decrease ground cover or soil levels in any manner whatsoever save as are reasonably required for agricultural activities (being ploughing to no deeper than 0.6 metres for the purposes of arable farming) or are required to be carried out by any statutory undertaker in order to exercise their statutory functions or rights in relation to their apparatus (if any) within the land without the consent in writing of the undertaker;dto prevent the planting or growing within the land of any trees, shrubs or underwood without the consent in writing of the undertaker (such consent not to be unreasonably withheld or delayed provided that the proposed trees, shrubs or underwood would not cause damage to the relevant part of the authorised project nor make it materially more difficult or expensive to access and maintain the relevant part of the authorised project);eto prevent anything being done which may interfere with free flow and passage of electricity or telecommunications through the cables or support for the authorised project;fto prevent the carrying out of operations or actions (including but not limited to blasting and piling) which may obstruct, interrupt, or interfere with the exercise of the rights or damage the authorised project; andgto prevent any activity which would in the reasonable opinion of the undertaker result in the disturbance of ecological mitigation areas or areas of habitat creation or enhancement including any ploughing or grazing without the prior written consent of the undertaker.
02-012; 02-021; 02-021a; 02-022; 02-023; 02-024; 02-025; 02-026; 02-027; 02-028; 02-029; 02-031; 02-034; 02-035; 02-036; 03-061; 04-065; 04-073; 05-082; 06-096; 06-098; 06-101; 07-110; 07-126; 08-135; 08-140 Cable rights under existing infrastructure and restrictive covenants1. Cable rights under existing infrastructureRights for the purposes of the construction, installation, operation, maintenance and decommissioning of the authorised project to—lay down, install, retain, adjust, alter, construct, operate, erect, use, maintain, repair, renew, upgrade, inspect, remove and replace the electricity cables (including the removal of materials including spoil) in or under the land, together with such telemetry and fibre-optic lines, ducting, jointing bays and other apparatus, protection measures, cable marker posts, chambers and manholes, manhole covers, cable clamping and other equipment which is ancillary to the purposes of transmitting electricity along such electricity cables (the “cables”), and in doing so, to use or resort to trenchless installation techniques including (but not limited to) directional drilling;enter, be on, and remain on the land with or without plant, vehicles, machinery, apparatus and equipment which is ancillary to the purposes of transmitting electricity along the cables;to benefit from continuous vertical and lateral support for the authorised project;pass and re-pass with or without vehicles, plant, machinery, apparatus, equipment and materials for the purposes of laying down, installing, adjusting, altering, constructing, using, maintaining, repairing, renewing, inspecting, removing, testing, upgrading and replacing the cables and connection into any adjacent cables and associated works, to take plant and equipment on to adjoining land;construct and install the cables and thereafter use the land for all necessary purposes for the construction, commissioning, testing, repair and maintenance of the cables in or under the land;place and use plant, machinery, structures and temporary structures within the land for the purposes of the installation, construction, maintenance, repairing, renewing, upgrading, inspecting, removal and replacing of the cables and to erect temporary signage and provide measures for the benefit of public and personnel safety;erect fencing, gates, walls, barriers or other means of enclosure, and create secure working areas and compounds including trenchless installation technique compounds and working areas;construct, lay down, use and remove temporary access roads including any necessary hard standing and other surface materials including (but not limited to) matting, aggregate, trackway, stone, tarmacadam, terram, temporary bridging, culverting or diversion of water courses and drains during any period during which construction, maintenance, repair or renewal is being carried out;effect access to the highway including creation of temporary visibility splays;make such investigations in or on the land as are required;fell, lop, cut or remove or coppice wood, uproot trees or hedges or shrubs which now or hereafter may be standing on the land or other land which would if not felled, lopped, cut or removed would obstruct or interfere with the installation or operation of the cables;remove and discharge water from the land, and to install, retain, use, maintain, inspect, alter, remove, refurbish, reconstruct, replace, protect and improve sewers, drains, pipes, ducts, mains, conduits, flues and to drain into and manage waterflows in any drains, watercourses and culverts, install, use, inspect, maintain, adjust, alter, renew, repair, test or cleanse drainage schemes on the land or reinstate any existing drainage scheme on the land;install, alter, re-lay, maintain, protect, adjust or remove pipes, cables or conduits or apparatus including but not limited to electricity poles, electricity pylons, electricity masts, overhead electricity lines, telecommunications cables and any ancillary equipment and apparatus public and private drains, watercourses, sewers, ponds or culverts, service media (including the pipes, cables or conduits or apparatus of statutory undertakers);remove fences and structures within the land during any period during which construction, maintenance, repair or renewal is being carried out (subject to erection of any temporary stock-proof fencing as is reasonably required and the re-instatement or suitable replacement of the fences or structures following the exercise of the rights);store and stockpile materials (including excavated material);create boreholes and trial excavation pits for the purposes of intrusively surveying the land and monitoring the use of any trenchless installation technique, to keep in place and monitor the same through construction, maintenance repair, replacement or decommissioning and to reinstate the land;to excavate materials below ground level, including soils, and to store and re-use or dispose of the same, and in so excavating to undertake any works, including works of protection or removal of archaeological remains as may be required by any written scheme of investigation approved under this Order;lay out temporary paths and bridleways for public use as temporary diversions for public rights of way which are interfered with during any period in which construction, maintenance, repair or renewal or decommissioning is being carried out;to install, execute, implement, retain, repair, improve, renew, relocate, maintain and carry out mitigation, maintenance and remediation works for environmental or ecological mitigation or enhancement works, including temporary works for noise alleviation measures and the installation of temporary barriers for the protection of fauna;carry out such works (together with associated fencing) required by a planning permission and/or consent now or to be granted over the land and/or in accordance with any necessary licences relating to protected species and/or wildlife;(in an emergency only when the cables are temporarily unusable) to lay down, install, use, maintain and inspect replacement underground cables, telephone signalling and fibre-optic cables and ancillary equipment, associated works and other conducting media together with conduits or pipes for containing the same in and under the land;to construct, use, maintain and improve a permanent means of access including visibility splays, and retain, maintain, straighten, widen, repair, alter, upgrade and use existing access routes for the purposes of accessing the land, adjoining land and the highway; anderect temporary bridges and supporting or protective structures for the purposes of access to adjoining land.2. Restrictive covenantsA restrictive covenant over the land for the benefit of the remainder of the Order land to:aprevent anything being done in or upon the land or any part thereof for the purpose of the erection of any buildings or construction, erection or works of any kind (including the foundations or footings thereto) other than those related to works for the benefit of existing highway or railway infrastructure;bto prevent anything to be done by way of excavation of any kind in the land nor any activities which would alter, increase or decrease ground cover or soil levels by greater than one metre whatsoever without the consent in writing of the undertaker, save where such works are reasonably required for the exercise of statutory functions or rights in relation any public highway or railway on the land and will not damage, undermine or interfere with the cables;cto prevent the planting or growing within the land of any trees, shrubs or underwood without the consent in writing of the undertaker (such consent not to be unreasonably withheld or delayed provided that the proposed trees, shrubs or underwood would not cause damage to the relevant part of the authorised project nor make it materially more difficult or expensive to access and maintain the relevant part of the authorised project);dto prevent anything being done which may interfere with free flow and passage of electricity or telecommunications through the cables or support for the authorised project; andeto prevent the carrying out of operations or actions (including but not limited to blasting and piling) which may obstruct, interrupt, or interfere with the exercise of the rights or damage the authorised project.
02-032 Cable rights, transition joint bay rights and restrictive covenants1. Cable rightsRights for the purposes of the construction, installation, operation, maintenance and decommissioning of the authorised project to—lay down, install, retain, adjust, alter, construct, operate, erect, use, maintain, repair, renew, upgrade, inspect, remove and replace the electricity cables (including the removal of materials including spoil) in, under, over and/or on the land, together with such telemetry and fibre-optic lines, ducting, jointing bays and other apparatus, protection measures, cable marker posts, chambers and manholes, manhole covers, cable clamping and other equipment which is ancillary to the purposes of transmitting electricity along such electricity cables (the “cables”), and in doing so, to use or resort to trenchless installation techniques including (but not limited to) directional drilling;enter, be on, and break open and break up the surface of the land and remain with or without plant, vehicles, machinery, apparatus and equipment which is ancillary to the purposes of transmitting electricity along the cables;to benefit from continuous vertical and lateral support for the authorised project;pass and re-pass with or without vehicles, plant, machinery, apparatus, equipment and materials for the purposes of laying down, installing, adjusting, altering, constructing, using, maintaining, repairing, renewing, inspecting, removing and replacing the cables;construct and install the cables and thereafter use the land for all necessary purposes for the construction, commissioning, testing, repair and maintenance of the cables in, on or under the land;place and use plant, machinery, structures and temporary structures within the land for the purposes of the installation, construction, maintenance, repairing, renewing, upgrading, inspecting, removal and replacing of the cables and to erect temporary signage and provide measures for the benefit of public and personnel safety;erect fencing, gates, walls, barriers or other means of enclosure, and create secure working areas and compounds including trenchless installation technique compounds and working areas;construct, lay down, use and remove temporary access roads including any necessary hard standing and other surface materials including (but not limited to) matting, aggregate, trackway, stone, tarmacadam, terram, temporary bridging, culverting or diversion of water courses and drains during any period during which construction, maintenance, repair or renewal or decommissioning is being carried out;effect access to the highway including creation of temporary visibility splays;make such investigations in or on the land as are required;fell, lop, cut or remove or coppice wood, uproot trees or hedges or shrubs which now or hereafter may be standing on the land or other land which would if not felled, lopped, cut or removed would obstruct or interfere with the installation and operation of the cables;remove and discharge water from the land, and to install, retain, use, maintain, inspect, alter, remove, refurbish, reconstruct, replace, protect and improve sewers, drains, pipes, ducts, mains, conduits, flues and to drain into and manage waterflows in any drains, watercourses and culverts, install, use, inspect, maintain, adjust, alter, renew, repair, test or cleanse drainage schemes on the land or reinstate any existing drainage scheme on the land;install, alter, re-lay, maintain, protect, adjust or remove pipes, cables or conduits or apparatus including but not limited to electricity poles, electricity pylons, electricity masts, overhead electricity lines, telecommunications cables and any ancillary equipment and apparatus, public and private drains, watercourses, sewers, ponds or culverts, service media (including the pipes, cables or conduits or apparatus of statutory undertakers);remove fences and structures within the land during any period in which construction, maintenance, repair or renewal is being carried out (subject to erection of any temporary stock-proof fencing as is reasonably required and the re-instatement or suitable replacement of the fences or structures following the exercise of the rights);store and stockpile materials (including excavated material);create boreholes and trial excavation pits for the purposes of intrusively surveying the land and monitoring the use of any trenchless installation technique, to keep in place and monitor the same through construction, maintenance, repair, replacement or decommissioning and reinstatement of the land;to excavate materials below ground level, including soils, and to store and re-use or dispose of the same, and in so excavating to undertake any works, including works of protection or removal of archaeological remains as may be required by any written scheme of investigation approved under this Order;lay out temporary paths and bridleways for public use;to install, execute, implement, retain, repair, improve, renew, relocate, maintain and carry out mitigation, maintenance, and remediation works for environmental or ecological mitigation or enhancement works, including temporary works for noise alleviation measures and the installation of temporary barriers for the protection of fauna;carry out such works (together with associated fencing) required by a planning permission and/or consent now or to be granted over the land and/or in accordance with any necessary licences relating to protected species and/or wildlife; and(in an emergency only when the cables are temporarily unusable) to lay down, install, use, maintain and inspect replacement underground cables, telephone signalling and fibre-optic cables and ancillary equipment, associated works and other conducting media together with conduits or pipes for containing the same in and under the land.2.Transition joint bay rightsRights for the purposes of the construction, installation, operation, maintenance and decommissioning of the authorised project to lay down, install, adjust, alter, construct, create, use, maintain, repair, renew, upgrade, inspect, remove and replace transition joint bays.3. Restrictive covenantsA restrictive covenant over the land for the benefit of the remainder of the Order land to:aprevent anything being done in or upon the land or any part thereof for the purpose of the erection of any buildings or construction, erection or works of any kind (including the foundations or footings thereto);bprevent anything being done by way of hard surfacing of the land with concrete of any kind or with any other material or surface whatsoever without the consent in writing of the undertaker (such consent not to be unreasonably withheld or delayed if the proposed surfacing would not cause damage to relevant part of the authorised project nor make it materially more difficult or expensive to maintain the authorised project);cto prevent anything to be done by way of excavation of any kind in the land or any activities which would alter, increase or decrease ground cover or soil levels in any manner whatsoever save as are reasonably required for agricultural activities (being ploughing to no deeper than 0.6 metres for the purposes of arable farming) or are required to be carried out by any statutory undertaker in order to exercise their statutory functions or rights in relation to their apparatus (if any) within the land without the consent in writing of the undertaker;dto prevent the planting or growing within the land of any trees, shrubs or underwood without the consent in writing of the undertaker (such consent not to be unreasonably withheld or delayed provided that the proposed trees, shrubs or underwood would not cause damage to the relevant part of the authorised project nor make it materially more difficult or expensive to access and maintain the relevant part of the authorised project);eto prevent anything being done which may interfere with free flow and passage of electricity or telecommunications through the cables or support for the authorised project;fto prevent the carrying out of operations or actions (including but not limited to blasting and piling) which may obstruct, interrupt, or interfere with the exercise of the rights or damage the authorised project; andgto prevent any activity which would in the reasonable opinion of the undertaker result in the disturbance of ecological mitigation areas or areas of habitat creation or enhancement including any ploughing or grazing without the prior written consent of the undertaker.
03-038; 03-046; 03-048; 03-051; 03-053; 03-054; 03-056; 03-059; 03-064; 04-066; 04-072; 04-075; 04-077; 04-079; 05-081; 05-085; 05-086; 05-089; 05-090; 05-092; 06-107; 07-116; 07-128; 07-134; 08-147; 08-148 Cable corridor access rightsRights for the purposes of the construction, installation, operation, maintenance and decommissioning of the authorised project to—pass and re-pass with or without vehicles, plant, machinery, apparatus, equipment and materials for the purposes of the authorised project, the inspection, testing, maintenance, renewal, upgrading, replacement and removal of the cables and connection into any adjacent cables and associated works, to take plant and equipment on to adjoining land and make such investigations in or on the Land which is ancillary for the purposes of exercise of the rights;to construct, use, maintain and improve a permanent means of access including visibility splays, and retain, maintain, straighten, widen, repair, alter, upgrade and use existing access routes for the purposes of accessing the land, adjoining land and the highway;construct, lay down, use and remove temporary access roads including any necessary hard standing and other surface materials including (but not limited to) matting, aggregate, trackway, stone, tarmacadam, terram, temporary bridging, culverting or diversion of water courses and drains during any period during which construction, maintenance, repair, renewal or decommissioning is being carried out;erect temporary bridges and supporting or protective structures for the purposes of access to adjoining land;place and use plant, machinery, structures and temporary structures within the land, and to erect temporary signage and provide measures for the benefit of public and personnel safety;fell, lop, cut, coppice wood, uproot trees or hedges or shrubs which now or hereafter may be present on the land for the purpose of enabling the right to pass and re-pass to adjoining land;repair, improve, renew, remove, relocate and plant trees, woodland, shrubs, hedgerows, seeding and other ecological measures together with the right to maintain, inspect and replant such trees, shrubs and landscaping;erect and remove temporary fencing, gates, walls, barriers or other means of enclosure; andlay out temporary paths and bridleways for public use as temporary diversions for public rights of way which are interfered with during any period in which construction, maintenance, repair or renewal decommissioning is being carried out.
03-039; 03-040; 03-041; 03-042; 03-043; 03-044; 07-112; 07-113; 07-114; 07-115; 07-118; 07-119; 07-121; 07-122; 07-123; 07-124; 07-130; 07-131; 07-132; 08-141; 08-142; 08-143; 08-144; 08-145; 08-149 Hedgerow enhancement rights and restrictive covenants1. Hedgerow enhancement rightsRights for the purposes of the construction, installation, operation, maintenance and decommissioning of the authorised project to—pass and re-pass with or without vehicles, plant, machinery, apparatus, equipment and materials for the purposes of the authorised project;to use, maintain and improve a permanent means of access and retain, maintain, straighten, widen, repair, alter, upgrade and use existing access routes for the purposes of accessing the landscaping and mitigation land, adjoining land and highway;place and use plant, machinery, structures and temporary structures within the land and to erect temporary signage and provide measures for the benefit of the public and personnel safety;fell, lop, cut or remove or coppice wood, uproot trees or hedges or shrubs which now or hereafter may be standing on the land for the purpose of enabling the right to pass and re-pass to adjoining land;install, execute, implement, retain, repair, improve, renew, remove, relocate and plant trees, woodland, shrubs, hedgerows, seeding and other hedgerow enhancement works together with the right to maintain, inspect and replant such trees, shrubs and landscaping; andthe installation of temporary barriers for the protection of fauna.2. Restrictive covenantsA restrictive covenant over the land for the benefit of the remainder of the Order land to prevent any activity which would in the reasonable opinion of the undertaker result in the disturbance of the hedgerow enhancement works without the prior written consent of the undertaker or as authorised by a planning permission or consent granted over the land.

In the County of Denbighshire:

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.